                                    REPORT
                                        OF

      THE CHIEF OF ENGINEERS
                        UNITED STATES ARMY


                                         WAR D EPARTM ENT,
                            OFFICE OF THE CHIEF OF ENGINEERS,
                                Washington, D. C., October 81, 1944.
Subject: Annual Report.
To: The Secretary of War.
  I present for your information the following report on river and
harbor, flood control, and allied operations under the charge of the
Corps of Engineers for the fiscal year ending June 30, 1944. These
operations, which are in addition to the military construction, supply,
and training programs of the Corps, played a most significant role in-
the war effort.
                    APPROPRIATIONS AND EXPENDITURES

   During the fiscal year 1944 net funds made available to the De-
partment for river and harbor operations amounted to $62,465,129.82'
and for flood-control operations $59,791,854.49, a total of $122,256,--
984.31. The expenditures from the available funds, including then
balances on hand at the beginning of the fiscal year, amounted to
$168,841,838.14, of which $64,366,001.23 was for river and harbor
work and allied operations and $104,475,836.91 for flood-control and
related work. New work was completed on 23 river and harbor and
flood-control projects, materially advanced on 26 other projects, and
maintenance operations were in progress on 304 projects.
   Indicative of the scope of the year's operations is the following
tabulation setting forth the approximate quantities in the major work
classifications:
Dredging and excavation----------------_            cubic yards_ 273, 549, 400
Levee construction -----------------------------        do-------     41, 986, 800'
Rock removal-------- ---------                          do.....d          356, 600
Concrete placed      -------------------------------- do-------           683, 100-
Dikes and bulkheads------------------------linear              feet__      57, 50(
Revetment       ------------------------------------ do-- ------          209, 800
Stone placed in jetties and breakwaters_------         tons-- --          201, 300-
Embankment ------------------------------          cubic yards__       1, 800, 000.
   The policy of the Department to have work performed by contract,
except when the best interests of the United States require hired labor-
operations, has been followed during the year, 54 percent of all wrk
pg formedlhaving been done by contract and 46 percent by Govern-
ment plant and hired labor.                                 "
  The continuation of an adequate check on the cost of work per-
formed on river and harbor and flood-control projects has been main--
tained. Summary results of these efforts are reflected throughout this,
report.
4         REPORT OF 'CHIEF OF ENGINEERS, U. S. ARMY,       1944

   Comprehensive and continuous safety engineering supervision was
maintained over all operations, both those performed by contract and
hired labor. Accident frequency and severity rates showed a down-
ward trend through the year and substantial economic returns were
effected.
                         RIVERS AND HARBORS

   The present program for Federal improvement of rivers and harbors
for navigation and allied purposes as authorized by Congress includes
projects located throughout the continental United States, Puerto
Rico, Alaska, and the Hawaiian Islands, there being approximately
1,000 projects now actively in force. No general river and harbor
legislation was enacted during the year, the last general authorizing
act being that of 1938. A summary of authorizing legislation enacted
during the year follows:
   Public Law No. 168, Seventy-eighth Congress, approved October
23, 1943, adopted the report printed in House Document No. 711,
Seventy-seventh Congress, containing an estimate of cost for reim-
bursing drainage and levee districts along the Illinois River, Ill., for
damages caused by prosecution of the existing navigation project.
   Public Law No. 216, Seventy-eighth Congress, approved December
23, 1943, authorized the enlargement of the turning basin at the upper
end of Lorain Harbor, Ohio, in the- interest of national defense.
   Public Law No. 279, Seventy-eighth Congress, approved April 1,
1944, authorized the maintenance of a channel extension in the
Cuyahoga River at Cleveland Harbor, Ohio, the original dredging of
which was requested and financed by the Defense Plant Corporation
as an emergency measure.
   Improvement operations were carried out on 35 regular river and
harbor projects, of which 9 were fully completed. Maintenance
operations were performed on 259 projects, including the numerous
coastal ports, harbors and connecting channels on the Great Lakes,
and the extensive intracoastal and Mississippi River network together
with the operation and care of its canalized Ohio River system, Illinois
Waterway, and upper Mississippi-which met the heavy shipping
demands imposed by the war.
    In conformity with the national policy limiting wartime construc-
tion in order to conserve manpower, equipment, and materials the
new work program on river and harbor projects was restricted to
improvements having direct importance to the war effort. The fol-
lowing brief outline of new work operations includes typical examples
of the improvements accomplished:
    Dredging and rock removal to provide a 27-foot channel in the
Kennebec River, Maine, from the mouth to the shipbuilding facilities
at Bath were completed.
    New York Harbor.-Dredging to provide additional mooring space
was continued in the Liberty Island and Red Hook anchorage areas.
Deepening the center 800 feet of the Ambrose Channel to 45 feet was
completed. Enlargement of Buttermilk Channel was carried out
during the year, and dredging and rock removal in the Kill Van Kull
section of New York and New Jersey Channels were continued.
    In the Delaware River Channel leading to the Philadelphia Navy
    Yard rock removal operations in the westerly 400-foot half of the
                        RIVERS AND HARBORS                           5
channel, in the vicinity of Marcus Hook, were advanced from 57
percent to 90 percent completion.
   Bank stabilization under contract in the deep cut section of the
Chesapeake and Delaware Canal was advanced from 20 percent to
90 percent completion.
   Channel widening in the Sabine-Neches Waterway, Tex., to project
dimensions was finished except for a width of 50 feet between Port
Arthur and Taylors Bayou turning basin for which local interests
were unable to furnish the required rights-of-way.
   Construction of MacArthur Lock in St. Marys River at Sault Ste.
Marie, Mich., was completed during August 1943. Partial recon-
struction of the Southwest Pier and corrective dredging at the mouth
of the power canal were also completed. Deepening of lock ap-
proaches and other features essential to safe navigation through the
new lock were materially advanced.
   Enlargement of the turning basin in Lorain Harbor, Ohio, opposite
the National Tube Co's. dock, to facilitate turning of large lake
vessels, was accomplished.
   The Fort Peck power plant, having a present generating unit of
35,000 kilowatts, was placed in operation on July 1, 1943, the amount
of power generated during the year being 197,569,900 kilowatt-hours.
Water impounded by the completed Fort Peck Dam was released to
augment the natural stream flow during low water periods in order to
provide more adequate channel depths for navigation in the Missouri
River and the critical Chain of Rocks section of the Mississippi River
at St. Louis.
   Construction operations on the project for the development of
hydroelectric power at the Bonneville Dam on the Columbia River
were completed with the placing in operation of the last two units,
Nos. 9 and 10, during the fall and early winter of 1943, thus making
the present rated capacity of 518,400 kilowatts available. The com-
pleted dam, navigation lock and fishways were maintained and
operated during the year. The output of energy generated during
the fiscal year amounted to 3,502,610,000 kilowatt-hours.
   At San Diego Harbor, Calif., construction of a seaplane basin and
anchorage facilities was continued, involving the removal of more than
6,400,000 cubic yards of material, the present contemplated work
being advanced to 82 percent completion.
   Construction of the 8,000-foot breakwater extending from Waadah
Island to the westerly shore of Neah Bay, Wash., was finished.
   Extensiie dredging operations were carried out on the Intracoastal
Waterway system extending for more than 2,300 miles along the
Atlantic and Gulf coasts, providing a more adequate channel for
coastwise barge and other light-draft vessel traffic carrying petroleum
products and other essential commodities. A channel 12 feet or more
in depth was available throughout the Atlantic coast section of the
waterway from Trenton, N. J., to Jacksonville, Fla. Work was
actively continued on the provision of a 12-foot waterway extending
from Apalachee Bay, Fla., to the Mexican border, as authorized by
Public Law No. 675, Seventy-seventh Congress, approved July 23,
1942. The 12-foot channel was completed from Carrabelle, Fla., to
Galveston, Tex., and was 82 percent completed in the section between
Galveston and Corpus Christi, Tex. ' Enlargement of the Gulf County
Canal, Fla., connecting St. Josephs Bay with the Gulf Intracoastal
        REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,   1944

Waterway, to a depth of 9 feet and a width of 100 feet was completed.
The work carried out during the year on the Gulf Intracoastal Water-
way and tributary channels involved the removal of more than 81,-
500,000 cubic yards of material.
   Notable new work channel or harbor improvements were also
effected at other locations including those at Portland Harbor, Maine,
Weymouth Back River, Mass., Providence River and Harbor, R. I.,
Connecticut River below Hartford, Conn., Mississippi River between
the Ohio River and Minneapolis, Minn., Ohio River, Calumet Harbor
and River, Ill. and Ind., Indiana Harbor, Ind., Illinois Waterway,
Ill., Los Angeles Harbor, Calif., Keehi Lagoon, T. H., and Arecibo
Harbor, P. R.
   In accordance with the provisions contained in section 1 of the
River and Harbor Act, approved June 20, 1938, stating that Federal
improvement of rivers and harbors and other waterways shall be
prosecuted by the War Department, the Corps of Engineers performed
work during the year on 25 projects of a river and harbor nature not
previously authorized by Congress but required in connection with
the war effort by the Navy Department and other Government
agencies, with. funds transferred to the Chief of Engineers by those
agencies. Expenditures on such projects amoupted to $4,064,840.88.
   Examinations, surveys, and review studies authorized in the interest
of navigation and related purposes were prosecuted during the year
consistent with the primary requirements of war activities. A sum-
mary of this work is set forth under the heading of "Surveys" and in
the report of the Board of Engineers for Rivers and Harbors.
   Construction plans and specifications for a number of authorized
river and harbor projects were under preparation with funds provided
by Congress for advance planning. Such work was subject to the
availability of manpower and limited to projects included within the
small backlog of authorized river and harbor improvements yet to be
completed, the last general authorization legislation for rivers and
harbprs having been enacted in 1938. Upon the passage of an omni-
bus river and harbor bill, the Department will be in a position to pre-
pare construction plans and specifications for many proposed projects
of value to navigation and. related purposes throughout the country
and make ready for the prosecution of a construction program upon
appropriation of funds therefor.
   The water-borne commerce of the United States, Puerto Rico,
Alaska and the Hawaiian Islands, for the calendar year 1943,
aggregated 580,581,000 tons.

                    SPECIAL WARTIME PROJECTS

   Construction of a vessel fleet for and with funds furnished by the
Defense Plant Corporation to augment available floating equipment
for the barging of essential commodities over the Mississippi River
network and the Gulf and Atlantic Intracoastal Waterways was
continued during the year. The current program calls for the building
of 100 steel hull tugboats, 180 welded steel barges, 269 wooden and
composite barges, 21 twin-screw steel hull towboats, and 2 oil terminals
for water-rail transfer and vice versa.- At the end of the year the
entire project was 99 percent completed, with expenditures totaling
$84,462,000.
                       GENERAL FLOOD CONTROL                            7
SACRAMENTO    RIVER AND TRIBUTARIES, CALIFORNIA (DEBRIS CONTROL)

   Two of the four debris dams in the Sacramento River Valley author-
ized in 1935 have been completed; one on the North Fork of the
American River was completed during the fiscal year 1939 and one at
Upper Narrows on the Yuba River was completed in 1941. Both of
these dams are in use for the storage of mining debris, the North Fork
Dam having a storage capacity of 26,000,000 cubic yards and the
Upper Narrows Dam a storage capacity of 118,000,000 cubic yards.
Construction of the Ruck-a-Chucky Dam on the Middle Fork of the
American River and the Dog Bar Dam on the Bear River has been
postponed. A review report on the Sacramento River and tributaries,
requested by the Committee on Rivers and Harbors of the House of
Representatives, with a view to determining whether any change
should be made in the previously proposed location of the Dog Bar
Dam on Bear River is under preparation.

                       GENERAL FLOOD CONTROL

    This section describes the authorized general flood-control program
exclusive of that for the alluvial valley of the lower Mississippi River
and that for the Sacramento River. The.authorized programs for
those two rivers are discussed in the sections immediately following
this one.
    Congress in the Flood Control Act approved June 22, 1936, estab-
lished, and in the amendatory and supplemental general Flood
Control Acts approved August 28, 1937, June 28, 1938, August 11,
1939, and August 18, 1941, reaffirmed the general policy that flood
control throughout the United States is a proper activity of the Federal
Government, in cooperation with the States and local communities,
and that the Federal Government should improve or participate in the
improvement of navigable waters or their tributaries for flood-control
purposes, if such projects are economically justified and if the lives and
social security of people are otherwise adversely affected. Those acts
also specified the local cooperation required for the projects authorized
therein.
   Tse     requiremients of local cooperation, in brief, are as follows:
    (a) Dam and reservoir projects authorized in any of the afore-
mentioned flood-control acts are constructed entirely at the expense
of the United States and are maintained and operated with the use of
Federal funds. No local cooperation is required for dam and reservoir
projects unless specifically prescribed by special provisions of law.
    (b) For local flood-protection projects, except channel improvement
or channel rectification projects authorized by the acts of 1936, 1937,
and 1938, local interests must provide without cost to the United
States all lands, easements, and rights-of-way necessary for the
construction of the projects, hold and save the United States free from
damages due to the construction works, and maintain and operate
all the works after completion in accordance with regulations pre-
scribed by the Secretary of War. Channel improvement and channel
rectification projects authorized by the acts of 1936, 1937, and 1938
are built entirely at Federal expense, and no local cooperation is
required. Exceptions to these general rules are provided by law in
the case of certain specific projects.
8       REPORT OF CHIF OF ENGINEERS,-       U. S. ARMY,   1944

   Up to the end of the fiscal year 1944, authorizations totaling $930,-
400,000 had been provided by Congress for the construction of nearly
500 projects widely dispersed throughout the United States. To June
30, 1944, funds in the total amount of $565,285,000 have been provided
by Congress for the prosecution of the general flood-control program.
In addition to these authorizations Congress has approved general
comprehensive plans covering most of the important river basins of
the country and including many additional projects for flood control,
hydroelectric power, and allied water uses. All of these projects are
parts of comprehensive coordinated plans for the river basins of the
Nation to provide desirable and economic flood protection and allied
benefits for a large number of centers of industry and population and
for many thousands of acres of rich agricultural land. A number of
reservoirs in the authorized program also provide favorable possi-
bilities for the economic development of large quantities of hydro-
electric power. Several of the projects now authorized include power
generating machinery in the initial developments.
   The general flood-control program has been affected to a large
extent by the war. In accordance with present Federal policies,
those projects not directly connected with the war effort have been
suspended. This curtailment has been necessary to release for the
war effort critical materials, manpower, and construction equipment.
Since fiscal year 1942, all projects then under way and not vitilly
necessary to the war effort have been brought to a state of completion
where work could be safely suspended with due regard to protecting
lives and the work already accomplished. Some of these suspended
projects provide substantial flood-protection benefits, although the
projects will not be fully effective until construction is completed.
   The operation of reservoirs and maintenance work required by
existing law were carried on *during fiscal year 1944. Construction
work continued from the preceding year included the Berlin Reservoir,
Ohio, the Barker Dam in Buffalo Bayou Watershed, Tex., the Blue-
stone Reservoir, W. Va., the Youghiogheny Reservoir, Pa., and the
local protection works at Cincinnati, Ohio, and Johnstown, Pa.
Except for work suspended for the duration, the Denison. Reservoir,
Okla. and Tex.., the Norfork Reservoir, White-River Basin, Ark., and
the Franklin Falls Reservoir in the Merrimack River Basin, N. H.,
were completed during the year and the reservoirs placed in operation.
Although certain appurtenant features were not complete at the
end of the year, the Mosquito Creek Reservoir was placed in partial
operation. Work was suspended during the year on Bluestone and
Youghiogheny Reservoirs as soon as safe stopping points were reached.
To afford protection to certain critical areas essential to the war,
work was initiated during the year on local protection projects at
Tulsa and West Tulsa, Okla., and East Peoria, Ill. Construction
previously suspended was resumed on the Jeffersonville-Clarksville,
Ind., project. By the end of June 1944 a total of 47 reservoirs and
112 local protection projects had been placed in operation.
   In general, the United States suffered little from disastrous floods
in the early part of fiscal year 1944. In August 1943 minor floods
occurred on the streams of eastern Iowa and on the Vermilion and
Mackinaw Rivers in Illinois, and a flash flood of unusual magnitude
in a part of the Little Kanawha River Basin caused a loss of 23 lives
and considerable property damage.
    Heavy precipitation during February and March 1944 in the South-
                       GENERAL FLOOD CONTROL

eastern States culminated in floods in the Tombigbee Basin in Missis-
sippi exceeding records of 50 years standing. Flood stages prevailed
on many streams in North and South Carolina, Georgia, Alabama,
Mississippi, Louisiana, and Texas.
   Flood stages prevailed generally in the Missouri River Basin from
April to June 1944. Flood stages and discharges in April from Kansas
City to the mouth of the Missouri River exceeded those of May 1943
and at Booneville and Hermann, Mo., approached the level of the
historic flood of June 1844. Completed works at Kansas City
satisfactorily withstood the flood stages. Many private levees along
the Missouri failed, with consequent inundation of large areas of
farmland. At St. Louis the floodwaters of the Missouri, augmented
by' high flows from the Illinois River, produced a stage in the Missis-
sippi River at St. Louis on May 1 exceeding the level reached in
May 1943. During May, record floods occurred on many eastern
Iowa streams and along the upper Mississippi River. During the
entire period, levees along the streams of the Mississippi Basin con-
structed by the Federal Government to project grade and section
performed satisfactorily and prevented great losses, The flood crest
traveled down the Mississippi from Cairo to the Gulf during May.
Although emergency work was required throughout this period, all
main line levees held, satisfactorily protecting the bottom lands of the
lower Mississippi Basin. The Arkabutla and Sardis Reservoirs in
the Yazoo Basin and the Wappapello Reservoir in the St. Francis
Basin were operated during this period to reduce crests in the tributary
basins and along the lower Mississippi River.
    During the entire spring of 1944, record and near record floods were
experienced in Kansas and Oklahoma on western tributaries of the
Mississippi and in Texas and Louisiana on streams tributary to the
Gulf. All storm run-off into the Denison Reservoir was impounded
during this period, gradually bringing this reservoir to a level where
power generation could be initiated.
    During the early part of fiscal year 1944, emergency repairs were
underway on flood-control structures damaged or destroyed by the
widespread spring floods of 1943 in such areas as the Missouri, upper
and lowdr Mississippi, Arkansas, White, Ohio, Willamette, and Sac-
ramento River Valleys. These repairs were accomplished in accord-
ance with section 5 of the Flood Control Act of 1941, which granted
authority to the Department to expend $1,000,000 per year from
flood control appropriations in rescue work or in the repair or main-
tenance of flood control works threatened or destroyed by flood, and
in accordance with an act approved July 12, 1943, which authorized
the amount of $10,000,000 to be appropriated as an emergency fund
to be expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood control works which had been
damaged or destroyed by the recent floods. Those emergency re-
pairs were accomplished prior to the 1944 spring flood season.
    In view of the very extensive floods of the spring of 1944 and the
major losses experienced from these floods, Congress in an act approved
May 29, 1944, authorized the sum of $12,000,000 to be appropriated
for repair, restoration, and strengthening of levees or other flood con-
trol works threatened or destroyed by the recent floods; the provisions
of this act being additional and supplemental to existing general leg-
islation authorizing allocation of flood control funds for restoration
10      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,             1944

of flood control works threatened or destroyed by floods. Funds were
appropriated for this purpose in the Second Deficiency Appropria-
tion Act approved June 28, 1944, and repairs were undertaken just
subsequent to the close of the fiscal year throughout the country in
basins such as those of the upper Mississippi, Illinois, Missouri,
Arkansas, Trinity, Snake, Boise, and Sacramento Rivers.
   In the fiscal year 1944 limited progress was made in the prosecu-
tion of authorized examinations, surveys, and review investigations
for flood control and other purposes. A summary of the work ac-
complished is contained in the report of the Board of Engineers for
Rivers and Harbors. Those investigations are undertaken in close
cooperation with other Federal agencies, with the States and with
local interests, in order that the recommendations submitted to Con-
gress in the reports on those investigations may contain full consider-
ation of the views of all concerned. Those studies which are author-
ized primarily for flood control include also thorough studies of all
other feasible water uses of the streams under consideration. The
survey program of the Department was limited during the year' in
accordance with instructions from higher authority to only those
surveys necessary to the proper integration of basin plans.
   The need for advance planning of flood control projects in order to
have available a backlog of sound public works projects for post-war
construction was again recognized by Congress in authorizing funds
for this purpose for fiscal year 1944. Pursuant to this authority and
subject to the limitations of available manpower, planning studies
were continued during fiscal year 1944 at a slightly accelerated rate
made possible by the decline of military construction operations in
the continental United States. At the close of the year plans were
essentially complete on the large volume of work on uncompleted por-
tions of projects once initiated but on which construction operations
have been suspended for the duration of the war. In addition plans
were complete or in process on a large additional number of author-
ized projects. During fiscal year 1945 emphasis will be placed on
advancing such plans to completion subject to the primary military
activities of the Department. The availability of plans and speci-
fications for a large number of carefully selected projects will permit
the initiation of construction operations on a large scale when
desirable in the reconversion from war to peacetime economy.
                 SACRAMENTO RIVER FLOOD CONTROL

   The construction of the flood-control project for the Sacramento
River Valley, which was authorized by the Flood Control Acts ap-
proved March 1, 1917, May 15, 1928, August 26, 1937, and August 18,
1941, was continued during the year. This project provides for the
enlargement of river channels, the excavation of cut-offs, the construc-
tion of levees, weirs, bank protection and pumping facilities in the
lower Sacramento River Valley, and for channel clearing, rectification,
and snagging on the Sacramento River and tributaries in Tehama
County, and from Red Bluff southerly, all at an estimated Federal
cost of $30,750,000. Up to the present time, Federal funds in the total
amount of $28,645,000 have been appropriated by Congress for the
prosecution of this project, including $2,800,000 at the close of the fiscal
year 1944. In addition to that amount, local interests have contributed
a total of approximately $6,132,000 for the construction of protective
works related to the authorized project.
             FLOOD   CONTROL OF THE MISSISSIPPI RIVER                  11
    The project works of the Sacramento flood-control project, in addi-
tion to providing protection to cities and to thousands of acres of
farm land, are vital to adequate flood protection of strategic rail and
highway routes running eastward from the Pacific coast, and running
north and south through the valley, and to Army airports and other
installations in the area. These rail and highway routes will continue
to increase in strategic importance as links in the supply chain to
the Pacific theater as the tempo of the war increases in the far Pacific.
    Levees were constructed, including reinforcement of incomplete
levees, along Sacramento, Feather, Bear, and Yuba Rivers, and along
*Yolo and Sutter bypasses construction was continued during the year.
By the end of June 1944 the existing project was approximately 82
percent complete.
              FLOOD CONTROL     OF THE MISSISSIPPI    RIVER

   Progress was made during the fiscal year 1944 on the flood-control
project for the alluvial valley of the Mississippi River, adopted by the
Flood Control Act approved May 15, 1928, and amended by the acts
approved June 15, 1936, June 28, 1938, and August 18, 1941. The
1936 amendment retained the purpose of the 1928 Act and the features
completed under that authority, and authorized an additional $272,-
000,000 for extension of flood-control work on the lower Mississippi
River. The 1938 amendment removed legislative restrictions with
respect to certain features of the amended plan and authorized
$40,000,000 for work in addition to that contemplated for the project
as amended in 1936. The 1941 amendment provided for the aban-
donment of the Boeuf and Eudora floodways and extension, for rais-
ing main Mississippi River levees to confine within those levee lines
between the mouths of the Arkansas and Red Rivers the project flood
without a floodway west of the Mississippi River. That amendment
also authorized certain minor modifications and backwater protection
in the Yazoo and Red River backwater areas at an estimated ad-
ditional cost of $25,982,000. The total authorization for the project
as amended and supplemented is now $662,982,000. Of this amount
$517,107,424 has been appropriated (including $26,000,000 for fiscal
year 1945 made available by the War Department Civil Appropria-
tion Act approved June 26, 1944). In accordance with the provision
of the act approved August 18, 1941, "that funds hereafter expended
fore ma tenance shall not be considered as reducing present remain-
ing balances of authorizations" it is estimated that $40,880,000 ex-
pended for maintenance since August 18, 1941, or scheduled for
expenditure during fiscal year 1945, will not be deducted from the
total authorizations for the project.
   With the approval of the 1938 Flood Control Act, work in the
Atchafalaya Basin which had not been initiated because of legal re-
strictions was freed from such restrictions and placed under way.
Noteworthy progress has been made on these features, namely, the
Morganza Floodway, the Wax Lake Outlet, the Charenton Drainage
and Navigation Canal, and related works. At the same time urgent
main river work has been prosecuted and work on the tributary proj-
ects for headwater protection of the St. Francis and Yazoo Rivers,
including the construction of the Wappapello, Sardis, and Arkabutla
Reservoirs, and backwater protection for the White River, has been
pushed vigorously within the limits of funds available for such work.
12     REPORT OF CHIEF OF -ENGINEERS, U.       S. ARMY,   1944

  Under section 6 of the 1928 act, flood-control work was undertaken
on the Mississippi River between Rock Island, Ill., and Cape Girar-
deau, Mo., and on outlets and tributaries affected by backwaters of
the Mississippi River, wherever the local contributions of one-third
of the costs were provided as required by law.
   The Department was able to assist localities in the emergency repair
of flood-control works on tributaries of the Mississippi River threat-
ened or destroyed by flood, under the provisions of section 9 of the
act approved June 15, 1936.
   Work accomplished on the adopted project for the alluvial valley
of the Mississippi River has demonstrated its effectiveness by afford- *
ing unbroken protection for a period of 16 years to date. However,
because of the elimination of the Eudora floodway by the Flood Con-
trol Act of 1941, the levee system which constitutes the major part of
the project is not yet sufficiently complete to afford protection against
predicted floods. Even a partial overflow of the valley may interrupt
postal service, transcontinental and interstate commerce, and produce
widespread destruction and disorder, national in scope. As flood
control of this vast alluvial valley and navigation of the lower Mis-
sissippi River are most important to the orderly and efficient progress
of the war emergency, this project is being prosecuted at the maximum
rate consistent with the successful prosecution of the war.

                               SURVEYS

   During the year reports in response to 184 items of law enacted by
Congress and resolutions adopted by congressional committees
authorizing investigations of potential river and harbor and flood-
control improvements were completed and transmitted to Congress
with the recommendations of the Chief of Engineers. Of these
investigations 19 were preliminary examinations and 68 were surveys
prepared in response to authority contained in previously adopted
river and harbor and flood-control acts, whereas 97 were reexamina-
tions submitted in response to committee resolutions.
   The Beach Erosion and Shore Protection Boards carried out dur-
ing the year studies and investigations in cooperation with appro-
priate agencies of various States and municipalities and with the field
offices of the Department to develop efficient works for the protection
and stabilization of the shores and beaches of coastal and lake waters.
One cooperative study and one informal departmental study were
completed during the year. Ten cooperative studies and five depart-
mental studies were pending at the close of the year. Research on
the subject of wave action and related phenomena was continued in
the board's laboratory. In, addition to the cooperative studies
prosecuted during the year, the Beach Erosion Board has prepared
studies and reports of a special nature for the Army and for the
Navy. Three articles reporting the results of research were approved
for publication.
   The gathering of hydrological data in Nicaragua, under authority
contained in the River and Harbor Act approved June 20, 1938, was
continued.
   The cooperative programs with the United States Weather Bureau
and the Geological Survey for the purpose of more adequately meeting
the requirements of the Department in the planning and operation of
                    MISCELLANEOUS      CIVIL WORKS                    13
flood-control and river and harbor improvements were continued.
Projects included in the cooperation with the Weather Bureau were:
 (a) Operation of a Nation-wide network of recording rain gages; (b)
hydrometeorological investigations and review of the studies of major
storms of record and' the preparation of estimates of maximum pos-
sible precipitation for selected drainage basins; (c) organization of
cooperative networks of reporting rainfall and river stations; and (d)
development of the program for preparation of 48-hour quantitative
                                                             .-
forecasts of storm rainfall to facilitate the operation of reservoirs and
lo1al flood-protection projects. Cooperation with the Geological
Survey involved primarily the installation, operation, and mainte-
nance of stream-gaging stations for obtaining records of stream flow.
The development of certain equipment for general stream gaging was
continued.
                     MISCELLANEOUS     CIVIL WORKS
   Miscellaneous civil works have, as heretofore, been administered by
the Corps of Engineers. These works are varied in character and in-
clude the administration of the Federal laws enacted for the protection
and preservation of the navigable waters of the United States, which
govern the following: Granting of permits for structures or operations
in navigable waters; approval of the location and plans of bridges,
dams, dikes, or causeways; alteration of obstructive bridges; investiga-
tion and removal of sunken vessels or other obstructions endangering
navigation; establishment of regulations for the use, administration,
and navigation of navigable waters, including dhwbridge regulations;
establishment of anchorage grounds, special anchorage areas, danger
zones, dumping grounds, restricted areas, fishing areas, land harbor
lines; investigations of the discharge or deposit of refuse matter of any
kind in navigable waters; prevention of pollution of coastal navigable
waters by oil; determination of the heads of navigation and the extent
to which the laws shall apply to specific streams; supervision of the.
harbor of New York to prevent obstructive or injurious deposits in
the tidal waters thereof, including the waters of Long Island Sound;
establishment of reasonable rates of toll for transit across bridges over
navigable waters; granting of permits for the occupation and use of
Federal works under control of the Corps of Engineers; construction of
Anacostia Park and the reclamation and development of Anacostia,
River and Flats, D. C.; maintenance and repair of the Washington
Aqueduct, and increasing the water supply of the city of Washington;
surveys and charting of the northern and northwestern lakes, includ-
ing the Lake of the Woods; studies for the preservation of Niagara
Falls and the supervision of power companies diverting water there-
from; reports of international boards on operations affecting inter-
national boundary waters; issuance of instruments authorizing the
occupation of Government-owned land under the jurisdiction of the
Department; and legislation in connection with the foregoing.
PROJECTS    UNDER    THE   PUBLIC WORKS      AND    EMERGENCY     RELIEF
                               PROGRAMS

  As of June 30, 1944, allocation of funds to the following works and
in the amounts indicated have been made available to the Corps of
Engineers supplementing the allocations as published in detail in the
Annual Report for the fiscal year 1939. The grand total of these
amounts is $517,697,444.73.
                                                                                       RIVERS AND HARBORS




                                                                                                                                                                                                                      LJ
                                                                                                                                                                                                                      O


                                                                                                                                                                                                                      0
                                                                                           FLOOD CONTROL
                                                                                                                                                                                                                      M
Total allocations to flood-control projects to June 30, 1943-_     .-           -      -   -$72,      763, 886. 60    $3, 054, 196. 70   $20,074, 637. 79    $10,174,116. 53   $19, 911, 349.12    $2, 238, 822. 74

                                                                                 MISCELLANEOUS PROJECTS                                                                                                               o
                                                                                                                                                                                                                      0O
Total allocations to miscellaneous projects to June 30, 1943-- .-----...         .--
                                                                                  -                $1, 654, 489. 01     $109, 200. 00     $6, 384, 393. 74       $11, 395.17         $7, 592. 70   .                  Y
      Grand total to June 30, 1944 ._..............                 .........
                                                                          _-               . 257,922, 336.16          97, 361,193. 27    130, 070, 638. 74   10,185, 512. 00    19, 918, 941. 82   $2,238, 822. 74    z
                                                                                                                                                                                                                      M


                                                                                                                                                                                                                      1-+
                                                                                                                                                                                                                       cD
                                                                                                                                                                                                                      02



                                                                                                                                                                                                                      tP




                                                                                                                                                                                                                      FP
    Appropriations.-The funds with which the works for the maintenance And improvement of rivers and harbors
and flood control were prosecuted during the fiscal year were derived from uneipended balances of prior appropriations
and from the following appropriation acts:

                                                Appropriation title                                                             Date of act                     bors Har-
                                                                                                                                                           Riversand                               Flood Control                     Miscellaneous          Total byappro-
                                                                                                                                                                                                                                                             priation acts


Second Deficiency Appropriation Act, 1943:
    Maintenance and improvement of existing river and harbor works ........                                        ...     July           12,1943                 $7, 095,000.00                                                                                   $7, 095, 000. 00
    Flood control,'gneral              .   .-------------   _------                                                       ---        do     .---          - - -   - - -    - -   - - -   - -             $4, 385, 000. 00                                           4, 385, 000. 00
    Flood control, general (emergency fund)- ------------------
                                                ---                                _ _-    -                      -.- -   ___do            ...---.        ----------------                               10,000, 000.00         --------       _-                  10, 000,000.00
                                                                                                                                                                                               I                            I
      Total.........................                                                           . . .        ...............                 ....                    7, 095, 000. 00                      14, 385, 000. 00.---------------I                         21, 480, 000. 00
War Department Civil Appropriation Act, 1944:
   Flood control, general (transferred to flood control, Sacramento River, Calif.) .....--                                 June 2, 1943 .................                                                 -500, 000.00 .....-- _-.------                      --      500,000.00
   Flood control, Sacramento River, Calif. (transferred from flood control, general)---.....-                                -..do ..__---                                       _                          500,000.00 -------------------                            500,000.00
First Supplemental National Defense Appropriation Act, 1944:
    Maintenance and improvement of existing river and harbor works....--------                                             Dec. 23,1943                                   170, 000. 00 ----------------------------------                                             170, 000.00
    Flood control, Mississippi River and tributaries _-                                                                    _.. do .__----                                             _     5, 000, 000. 00 ------------------                                     5, 000, 000. 00
    Emergency fund for flood control on tributaries of Mississippi River . .  ..                                                 -   do.    __                                              3,000,000. 00 ------------------                                       3, 000, 000. 00
      Total_      ---------------------------------------
                                .. ...    _...                                  ------                   -------                                                          170, 000. 00                    8, 000, 000. 00           ____------------                8, 170, 000. 00
War Department Civil Appropriation Act, 1945:
   Maintenance and improvement of existing river and harbor works                           -           June 26,1944                                              51,344.000. 00                   ...            .    00.
                                                                                                                                                                                                                       ................        .      51, 344,000.00             O
   Maintenance and improvement of existing river and harbor works ........-..........                  ---   do .                                                 i--7000. 00                        .                ....------------------           -- 700, 000.00
   Flood control, General ......---------------.                                                       .. ..do                                                                                                    100. 00                                          00.00
                                                                                                                                                                                                                                                                  1------------------------
   Flood control, General --... ....     ....   .                     ------ ------- -------  -------- ..... do ..- --                                                                               1- 4, 0 00 , 0 00. 00 - - . -- . . ... ..           , 0 00 , 00 0 .00
                                                                                                                                                                                                                                                 . - - 4---
   Flood control, M ississippi River and tributaries ...................................                --- do_                                                                                        26, 000, 000. 00                                26, 000, 000. 00
   Emergency fund for flood control on tributaries of Mississippi River ...-                               - do _         --                                                                               500, 000. 00  ---------------------              500, 000.00
   Flood control, Sacramento River, Calif ...............-             " . ........._         ....       --- do __-                                                                                     2, 800, 000. 00 ------------------             12, 800, 000. 00
   Maintenance and operation, certain Federal water mains outside the District of Co-
      lumbia ..                         _--------------------------------                -              .....do . .--                                                                                                           0          $12, 000. 00                 12, 000. 00
      Total ------------.-------------------                                -             - --         --                                                         50, 644, 000. 00                       25, 300, 100. 00                   12, 000. 00            75, 956, 100. 00
Second Deficiency Appropriation Act, 1944:
    Maintenance and improvement of existing river and harbor works                        --         --.
                                                                                                  ----                     June 28,1944                             4, 250, 000. 00-                         --                                                     4, 250, 000.00
    Flood control, general (emergency fund) .-.............                                            ........           ----       do .          ----                     ......                       12, 000, 000. 00                                          12, 000, 000. 00
       Total_-------------                 _.....               ... -   .                                                                                           4,250,000. 00                        12,000,000.00 ---------- _                                16, 250,000.00
Special fund (credits to account from licenses under Federal Power Act, Aug. 26, 1935):
    Maintenance and operation of dams and other improvements of navigable waters ....-- - Aug. 26, 1935                                                                   306, 129. 82 .)-----------                                                -306,                  129. 82
    1 Transferred to surplus fund.
16                        REPORT OF CHIEF OF ENGINEERS, U.                                                                                                                                                                          S. ARMY,   1944
                                                                           8                    M                                   II                           82                    SIO                         i            a

                                              A QQ                                                                                                                        * og                                              C
                                                                       c0                      g            4           f..N.                    0 .               WC




                              .




                                                                      r1

                                                                                   f
                                                                                       1
                                                                                           *4Qeq c                          eq
                      0a                                                                        "                                                            -




                                                                                                                                                                                                                       t




                  ;                                                                                          1                                   1'                                        /                                                   "




     _       _~                                       _           _    II o                         _           _                            _           _            _            _           _                                i                  -




                                                                                                                                                 1I                                                                                                    -




                                                          1w,-I
                                                                                               1q                 C                                                                                    ,               1.
                          "                                                                             1C.                 1C7                                           f                        {




     f4
         0   COD
                                                                               oo
                1:
                                      ;   I       :
                                                                       f   l               l
                                                                                                                            Q; II


                                                                                                                                                                                                           I




                                                                                                                                                                                       ,                                             ,,




                                                                                   '0''.
                      "           !                                    .                                                                                                               i




                          r-1




                                                                                   *-                   '0
         3                                                                                                                                                                                                             t


                                                          tii




              o       I                               P                                                                                                                        0




                                                          /                                                                                                                        O
                                  u                                                                                                                                                                1_~

                                                                                               0                                                                          1z
                                              t                   "    1
                                                                           +d          t
                                                                                                'a1 '0              I




                                                  0.o                          *                                                                         1,                                                                                            ;
                                                                                                                                                 t                             ak




                                                  "                                                                                                                       z                                                                            1


                                                                  N0                                    NN                                       NN                                    NN0
                                      lw                      Y1               J                        ^




         o                                    V       °                                             '        '°                                                           I'




         Sa                                                                                                                                                                                    '




                                          aS                                                                                                         *


                                                                                               b
                                                                                                                  0n




                                                                                       a)~

                                                              v                                         D               O                                r(           w            w           w               w




                                                              45,              Z
                                                                                                    +.2                     8            t-wwwaIwi,
                                                                                                                                                 'CG                  b            W           b                            '
                                                                           b                                                    1        '
                                                  Oa




                                                                                                        k         a.B       C3                                                         ~
      The following amounts have been advanced by local interests for river and harbor improvements under the pro-
visions of section 11, River and Harbor Act, March 3, 1925, and for flood-control works under the provisions ofthe
Sact of October 15, 1940, and are returnable to the same interests when necessary Government funds are available.

                                                                                                                                                 Balance due           Amount                  Amount            Balance due
                                                                                                                                                                                              returned           from United
                                                                                                                           Districtfrom
                                                                                                                           District              States,United
                                                                                                                                                         June           received
                                                                                                                                                                      during fiscal          during fiscal       States, June
                                                                                                                                                   30, 1943               year                   year               30, 1944

SGreat Kills Harbor, Staten Island, N. Y...-------------------------New York, N. Y----------------------
                                                                                    .                                                                 $114,500- ............                         -       -         $114, 500
SBuffalo Bayou, Tex       ----------------------------------------- Galveston, Tex ...................----------------------.                       2,500,000 ..------------------------------                       2, 500, 000
. Sacramento River, Calif..--------------  -------------------------- Sacramento, Calif......---------------------                                      700,000 ----------------------------.                            700,000
    I    Total, flood control-----------------------.. .....       ------------------------------------------------.....                             3, 200, 000 -      -     -         --           -                3, 200, 000
         Grand total..............-.............................               .         -------.-.-.---.--                       .----------.       3, 314,500 .....................                        .        3, 314, 500

                                                                                                                                                                                                                                    z

                                                                                                                                                                                                                                    I11
    Expenditures.-The total actually expended under the direction of the Chief of Engineers in connection with the
maintenance and improvement of rivers and harbors, floodocontrol, and other miscellaneous works during the'fiscal
year ended June 30, 1944, is as follows:
                                                                                                                                                                             Expenditures                                   0
                                                                                                                   Appropriation                                             E___             ur
                                                                                                                                                                                it                                          O
                                                                                                                                                   New work                   Maintenance                  Total
                                                                                                                                                                                                                            O
                                                                                                                                                                                                                            4
Rivers and harbors:                                                                                                                                                                                                             TJ
    Maintenance and improvement of existing river and harbor works . ....................                            (1)                          $23, 461, 345. 85       2 $38, 258, 935. 49           $61,720, 281. 34
    National Indutrial Recovery, War, rivers and harbors, 1933-43 _...._-.._                                   June 16, 1933                           -9,205.72                                            -9, 205. 72     e

    Public Works Administration, allotment to War, rivers and harbors, 1935-43-                                June 19,1934                           -18,106. 10         .................                -18,106. 10
    Power plant, Fort Peck Dam, Mont., construction ..-...........................                                 (I)                                 406, 904. 73                                         406, 904.73
    Power plant, Bonneville Dam, Columbia River, Oreg., construction _-_                                            (1)                             2, 033, 929. 88       .................               2.033, 929. 88
    Emergency fund for the President, War (allotment to War, Corps of Engineers), 1940-42 (St. Lawrence
      W aterway) _ .     ..-.                 .       .   .   .     . .      .   .     . .         . . -       June 13,1940                               -24.79                                                -24.79      O
    Emergency fund for the President, national defense (allotment to War, Corps of Engineers), 1942 (construc-
      tion of submerged weir in the Niagara River)-... ..... _ ......................                          Apr. 5,1941                          -107, 245. 58                                         -107, 245.58
    Maintenance and operation of dams and other improvements to navigable waters --....    .     .........---  Aug. 26,1935                           326, 747.71                                           326, 747.71
    Improvement of Washington Channel, D. C. (transfer to War).................................... July 1,1941                                          12, 719.76                                           12,719.76
                 and harbors ..........-
     Total, rivers                   ....... . . . . . . . .           . . .. .. . . . . . . . . .
                                                                      ...                             .. . .       ...... _ ..........             26, 107, 065. 74              38, 258, 935. 49        64, 366, 001. 23
Flood control (projects authorized in act of June 22, 1936, as amended and supplemented):
   Flood control,general ---   - - - - - - - - -- - -- - - - - - - - - - - - - - - - - - - - - - - - -- - - -                (1)                   55, 807, 245. 57             s 8, 082, 917. 11        63, 890, 162. 68
   Flood control, general (emergency fund) ..... _.........                                                                  (1)                    3, 008, 723. 36               5, 522, 551. 44         8, 531, 274. 80
     Total, flood control, general ----...
                                         ...... . . .     . .    . .     . .   . .     . .   . .     . . .                       ).............    58, 815, 968. 93              13, 605, 468. 55        72, 421, 437. 48
Flood control, Mississippi River (act May 15, 1928, as amended):
    Flood control, M ississippi River and tributaries _ ......     ...............             ........                        (1)                 16, 421, 836. 43           4 10, 085, 909. 12         26, 507, 745. 55
    Emergency fund for flood control on tributaries of Mississippi River ......  -
                                                                                .-              - - -                                                  431, 182. 74                1, 891, 808. 70        2, 322, 991. 44       toj
      Total, flood control, Mississippi River.....................................                                             (1)                 16, 853, 019. 17              11,977, 717. 82         28, 830, 736. 99
Flood control, Sadcramento River, Calif_--       -    -     -     -      --.-...                               .               (1)                  3, 136, 167. 99                       86, 795. 05     3,222, 963. 04
                                                                                                                                                                                                                                CI).
Flood control, Missouri River at or near Niobrara, Nebr_...............               .................              May        +15.1936          _.-----             _                       699.40               699.40
      Total, allflood
                    control................... . . . .. .        . . .. . . . . . .
                                                                ...                    . . . . . . .. .   .. .                                     78, 805, 156. 09              25, 670, 680. 82       104, 475, 836. 91
Miscellaneous appropriations:
   National Industrial Recovery, Public Works Administration (allotment to War, Corps of Engineers),
     1933-44.....................................................--   .......... ..........................   June 16,1933                                                 39, 282. 80 .................                    39, 282. 80
   Development of landing areas for national defense, Office of Administrator of Civil Aeronautics (transfer
        to War), 1941-44- ..........- .......................       -         -................
                                                                                     ....................... 'Apr. 28,1942                                            47, 727, 922. 51 .................               47, 727, 922. 51
      Total miscellaneous appropriations.......................                     .     ... ...............                      .......                            47, 767, 205. 31---.... --..                     47, 767, 205. 31
Contributed and advaned funds:
   Funds contributed for improvement of rivers and harbors_ ............... __........................                                               (6)                   24, 103. 36       208, 20. 46                   232, 309.82
   Funds contributed for flood control, rivers and harbors.............................                                                              (8)                   98, 853.96        382, 521.$4                   481, 375.80
   Funds advanced for flood control, rivers and harbors..................................____...............                                  Oct.     5,1940             833, 411.74 --------...                      -833,    411.74
      Total, contributed and advanced funds_ ...............           _......                ... __        ....................                                          956, 369. 06              590, 728. 30         1,547, 097. 36
                                                                                                                                             ...............
      Total, Engineer Department and contributed funds......           ....-            _................                                                             153, 635, 796. 20      64, 520, 344. 61          218,156,140. 81
Working funds transfers from other departments):
   Working fund, War, Engineers, civil, no year (various projects).--.....................                                                                                      ...............                         3,583,832.58
   Working fund, War, Engineers, civil, 1942-43 (various projects) -.....................                                                                                                  _-__-     _- ____-
                                                                                                                                                                                                --___-_--    - __         366,377.12
   Working fund, War, Engineers, civil, 1943 (various projects) ----------------.........

                                                                                                                                              16,1933
                                                                                                                                             June                                 -- ------ -    --- - - -- - - -                 60
                                                                                                                                                                                                                           60, 100.
   Working fund, War, Engineers, civil, 1944 (various projects) ........................                                                                                                                                   54, 530.58
   Working fund, War, Engineers (National Industrial Recovery, Federal Emergency Administration
     of Public Works, allotment Civil Aeronautics Authority), 1933-43 (Gravelly Point National Airport) __--                                                                                                                    23.16
   Working fund, War, Engineers, civil (trust fund) no year (various projects) .....................-- ......                                --------------            .... -.....
                                                                                                                                                                                   ---
                                                                                                                                                                                  ----
                                                                                                                                                                                -... -..
                                                                                                                                                                                            -------
                                                                                                                                                                                           --- --- ---
                                                                                                                                                                                              .........-           .   69,886, 302. 95    x
      Total, working funds---------------------..
                                        .--. _.     ...   ...   ...              . ................                                                                     -.                     ._     ..   .   ._       73,951,120.67
                                                                                                                                               _-_---_----.----
      Grand total expenditures by Engineer Department ..          ..............................                                                                      153, 635, 796. 20      64, 520, 344              292, 107, 261.48
                                                                                                                                                                  i


                                                                                                                                                                                                                                          Ci
    I Annual or supplemental.
    2 Includes $147,7 $ transferred for cooperative work to other departments.
    8 Includes $371,309 transferred for cooperative work to other departments.
    SIncludes $2,200 transferred for cooperative work to other departments.
    SSixth Supplemental National Defense Appropriation Act, 1942, Apr. 28, 1942.
    6 Trust funds (various).                                19
                                                                             Consolidated cost and financial summary as of June                                                       80,     1944                 _



                                                         Cost of new                                           Value of                  Min                                                                                                                     Additional
                                                                                  Cost of main-             plant,stocks, Plus accounts counts pay-                              Total expendi-                    Balance un-                  Total tobe ac-   amount re
                                                            work                    terance                 and undistri-receivable able                                              tures                         expended                     ctinted for   quired for com-
                                                                                                             buted items                                                                                                                                           pletion

Seacoast harbors and channels-                $705, 568, 778.28 $333, 148, 683.91         $527,840.44 $91, 273.16 $14119, 971.02 $1,038,866, 604. 77 $9,224,747.24 $1, 048,091,352.01                      $84,000, 000                                                                       rO
Intracoastal canals and other water-                                                                                                                                                                                                                                                          0
  ways-----
         ......L .............------------------174, 016,289.94     88, 472,064.18 -218,556.99                  30, 811.36   679, 944.58    261, 620,663.91       4, 065, 288.84   265, 685, 952. 75         74, 400, 000                                                                     O
Mississippi River system-----...........        845,901, 682.85 297, 972, 723.45           768,094.37          123, 617.20   762, 948.89 1, 144,003,168.98        4, 502,694. 56 1, 148, 505, 863. 54        68,800, 000                                                                      0
Lake harbors and channels--------.........
Examinations, surveys, and contin-
                                                223, 865, 171.96    87,      996.84      052,
                                                                                           313, 932. 87         90,361.79   436, 613.86     310,885,849.60        1, 631,659. 63   312, 517,509. 23          14,800, 000
  gencies of rivers and harbors......             7, 613, 720.34    58, 992,111.00           11, 112.60        112,182.37    159, 490.21     66,569,636.10        1, 123,105.27      67,692, 741.37-...--.
Removing sunken vessels-------                                       8,606,  967.07              .---------
                                                                                                       .         -------..............        8,606,967.07           260,477.54       8,867, 444. 61o.trt..a
Power installation at Fort Peck and
  Bonneville-_- ---.------.-.                 -42, 953, 456.81          931,597.34           60,931.52               99.96   200,664.44      43, 745,421.19       3,690, 086.37      47,435, 507. 56 ..........                                                                               O
Dam No. 2, Tennessee River:
    Construction ----------------                46, 613,947.62         359, 592.52-------------
                                                                                     ..............-..-------                                46,973, 540.14------..                  46,973,540.14......                                                                                      In
    Operating and care of hydro-
       electric development--------......... ---------------         1, 711,656.48---------
                                                                                     ..............-------------...............---            1,711, 656. 48 ---------                1, 711, 656. 48                                                                                         0f
Passamaquoddy tidal power project,
  Maine------------------------6,384,160.89                       -     .:          --                   ---------------                      6,384,160.89-            -        -     6,384,160.89...........
Flood control-----------------               1,092,442.779.96     173, 640, 026.44 1,476, 394.19 1,299,126.26 7,348, 218.85 1,261, 510,108.00 64, 814,137.31 1, 326,324,245.31                             836,600,00
Plant:
    River and harbor--------------                               -----                34,705,071.93 5,145,208.18            94, 328.35       35, 865,951.76 14,047,869.51            49,913,821.27............
    Flood control....-------------------------------....                     --         9, 996, 677. 07 1, 687, 788. 20      173, 998. 67    10, 510, 466. 60     5, 509, 205. 09    16, 019, 671.69         .......
     Total---..-            --------- -----
Unallotted balances June 30, 1944:
                                                      3,145, 359, 988. 65 1,051, 538, 419.23 147,641, 498.00                        8, 580, 468.48 15,866,178.87                 4,237, 254, 195.49 108,869, 271. 36 4, 3486,
                                                                                                                                                                                                                           123, 466.85                                     1, 078,600,00
                                                                                                                                                                                                                                                                                              W
                                                                                                                                                                                                                                                                                              Co
                                                                                                                                                                                                                                                                                              mj
    Rivers and harbors--                            --- -----------...         -------------------------                           -----------                   ------------------------                              67,
                                                                                                                                                                                                                         857,106.90                        90 ............
                                                                                                                                                                                                                                                   67,857,106.
    Flood    control,     Mississippi
      River and tributaries            .------..-------                     --------.--------------                                       --- _--_.                ------------------                                  26,148, 928. 51            26, 148,
                                                                                                                                                                                                                                                         928.51............
    Flood control, Sacramento
      River, Calif.-------------..--------------..............-----------------------------------------------..............-.................                                                                                000.00
                                                                                                                                                                                                                        2,800,                         2,800,000.00............
    Emergencylunds for flood con-
      trol on tributaries of Missis-
      sippi River-___--- ---                       -------------------------------------------                                                          -----------------------------................                   1, 145, 809. 48            1,45, 809. 48....
    Flood control, general--------..........-------------------................---------------................-------.......--------------------------------.................                                          26,418, 95                 26,
                                                                                                                                                                                                                                                  541.418,
                                                                                                                                                                                                                                                         541. 95............
       Total unallotted balance.--.-.          ..
                                            ----..    .     --                                    _....-------------------------                                                                 124, 370, 386.84
                                                                                                                                                                                    -----------...........                         124, 370,386.84............
       Grand total----------------------...............-------
                                      ................        ...                              L.--------------------------------------------------------                                                          233,
                                                                                                                                                                                                                      239,658.20 4,470, 493,853. 69............

    S.Ofthis amount $42,463,210.48 represents                          the value of plant distributed as follows:

                                                                                                                                                                                 Construction                      Service plan                   Tools and        Total
                                                                                                                                                                                    a ntp                                   l n                  equipm ent -.
                                                                                                                                                                                                                                                             .. ...


       River and harbor------------ ----- .-- .----
                                                 - -. --- .                                                 .-..   _   ..-                                         _-_            $22, 949, 952. 75                    $8, 228, 020.05           $2, 356, 278.58          $33, 534, 251. 38
       Flood control. . . . .. . . .........
                                       .. .. . .      _ .. ..                                               . ..-_ . . . ..... .                      . . .. .     .  i.            4,355,354.60                        3, 261, 484. 84           1, 312,119.66             8,928,959. 10
                                                                                                                                                                                   27, 305, 307.35             I       11,489,504.89I1            3,6,382I                  243204
                Total............ . ...............................................-----------------------------------------------------------------------                                       27,    05,30735
                                                                                                                                                                                                              11          48,       54.89   I     3,   668,   398.   24    42, 463, 210. 48
              ~     0-IFI                                         ..    .          ~                                                            rr:                                                     ----                    6
           THE BOARD OF ENGINEERS FOR RIVERS AND HARBORS                                                   21
  The amounts that can be profitably expended during the fiscal year
ending June 30, 1946, are as follows:
Maintenance and improvement of existing river and harbor works:
    New work ------------------------------------------                                       $23, 643, 300
    Maintenance_----------.                           -   ____                                 61, 924, 686

         Total, rivers and'harbors-                        -85,                                       567, 986
Flood control:
    Mississippi River and tributaries ------------------------- 40, 000, 000
    Emergency work on tributaries of Mississippi River-------- -     500, 000
    Sacramento River, Calif --------------------------------      2, 050,000
    Flood control, general, act of June 22, 1936, as amended and
      supplemented --------------------------------------        22, 794, 000

           Total, flood control_          ----------------------                               65, 344, 000
           Grand total       -------------------------------------                            150, 911, 986

           THE BOARD         OF ENGINEERS             FOR RIVERS AND                 HARBORS

   The creation of the Board and the duties assigned to it under the
original and subsequent acts of Congress are described in the Annual
Report of the Chief of Engineers for the fiscal year 1922.
   On June 30, 1944, the Board was composed of the following mem-
bers: Brig. Gen. John J. Kingman, Brig. Gen. Roscoe C. Crawford,
Brig. Gen. John S. Bragdon, Col. Charles L. Hall, Col. Malcolm
Elliott, Col. Earl E. Gesler, and Col. Peter A. Feringa, United
States Army.
   In addition to the foregoing, the following-named officers have also
been detailed for various periods during the year to membership on
the Board: Brig. Gen. Beverly C. Dunn, Col. Roger G. Powell, and
Col. Clark Kittrell, United States Army.
   A summary of the reviews accomplished by the Board during the
year and the status of its operations from its organization up to the
close of the fiscal year are shown in the following table:

                                                      Number       Number         Total    Number
                                                      of investi- of investi- number completed Number
                                                        gtions      gations      number    during remainingber
                                                                                     completed
           Authority for investigations                 ordered
                                                        prior to
                                                                    ordered
                                                                     during
                                                                                 prior to  yearend-
                                                                                 Jay 1, ing June
                                                                                                  to be con-
                                                                                                    pleted
                                                        July 1,    fiscal year    1943     30, 1944
                                                          1943         1944

                                      ---------------
River and harbor and flood control acts..........          4,377            0      4,026         51        300
Concurrent resolutions of Congress......-... --.. -.. -- 1                 0            1 ..............
Congressional resolutions-------------------------1,741                   71       1, 525       57       230
     Total...-----------------------------------          6,119           71       5,552        108         530




   Number of hearings held by the Board during the year, nine.
   Studies prescribed by various river and harbor acts and by section
500 of the Transportation Act of 1920 were continued, and the results
published in two series of reports known as Port and Terminal Facili-
ties Reports and Transportation Series Reports. Since these reports
ciontain information affecting the national defense of the United
States, they are classified confidential and their distribution is limited
accordingly.
22         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                   1944

      The following reports were prepared during the year:
                        TRANSPORTATION     SERIES REPORTS

No. 3. Transportation Lines on the Great Lakes, 1944 (published).
No. 4. Transportation Lines on the Mississippi River System (in press).
                     PORT AND   TERMINAL FACILITIES REPORTS

San Francisco, Oakland, Alameda, Richmond, and Upper San Francisco Bay,
  Calif. (in press).
New Orleans and Lake Charles, La. (in press).
  Field work was completed and preparation of material was under
way on:
                    PORT AND    TERMINAL   FACILITIES REPORTS
Wilmington, N. C.
Charleston, S. C.
                        TRANSPORTATION     SERIES REPORTS

No. 5. Transportation Lines on the Atlantic, Gulf, and Pacific Coasts, 1944.
   The statistics of water-borne commerce as collected and compiled
by the Corps of Engineers as required by law, have continued to be
of service to numerous agencies including many connected with the
war effort.
   Miscellaneous special studies were made in connection with subjects
pending before the Board and in response to specific requests by the
Office of the Chief of Engineers and other governmental agencies; and
tables, graphs, and maps have been prepared as necessary in connec-
tion therewith.
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
                BOSTON, MASS., DISTRICT
  This district comprises all of Maine, the eastern two-thirds of New
Hampshire, and northeastern and eastern Massachusetts embraced
in the drainage basins tributary to the Atlantic Ocean north of
Nauset Harbor, inclusive, on the east coast of Cape Cod, and to the
head of Buzzards Bay, Mass., north of Butlers Point at the southern
extremity of Sippican Neck, and Scraggy Neck. It also includes
the Cape Cod Canal.
  District engineer: Lt. Col. Bruce D. Rindlaub, Corps of Engineers,
to November 26, 1943; and Lt. Col. Henry P. Dunbar, Corps of En-
gineers, since that date.
  Division engineer: Col. George W. Gillette, Corps of Engineers.
                                 IMPROVEMENTS
                Navigation                            Flood Control
                                    Page                                           Page
1.    Kennebec River, Maine .       23    11. Merrimack River Basin, N.
2.    Portland Harbor, Maine____    25          H. and Mass_-------                 46
3.                     ---------
       Mystic River, Mass            28    12. Franklin    Falls      Reservoir,
4.
5.
       Boston Harbor, Mass-------
       Weymouth Fore River, Mass.
                                     31
                                     35
                                                 Merrimack River Basin,
                                                 N. H_ --------------                48
6.    Weymouth Back R i v e r,            13. Blackwater Reservoir, Mer-
         Mass--------------------37              rimack River Basin, N. H_           50
7.    Cape Cod Canal, Mass          38    14. Lowell,    Merrimack        River
8.    Examinations, surveys and                 Basin, Mass ------------            53
         c)ntingencies (general) --- 42    15. Preliminary       examinations,
9.    Other navigation projects for             surveys and contingencies
         which no estimates are                  for flood control- ----.---.-       54
         submitted-.-------------    43
10.    Plant allotment --------      45
               RIVERS      AND      HARBORS-BOSTON,                   MASS.,      DISTRICT                  23
                                1. KENNEBEC RIVER, MAINE

   Location.-Kennebec River drains a large number of lakes and
minor streams, and flows from Moosehead Lake about 150 miles in a
southerly direction and discharges into the Atlantic Ocean about 25
miles east of Portland. (See U. S. Coast and Geodetic Survey Charts
Nos. 288, 289, and 314.)
   Previous projects.-The first project was adopted by the River and
Harbor Act of March 2, 1827. Modifications and additions were au-
thorized by River and Harbor Acts of August 30, 1852, June 23, 1866,
July 11, 1870, March 3, 1871, March 3, 1873, March 3, 1881, August 11,
1888. For further details of previous projects see page 1735 of Annual
Report for 1915, and page 52 of Annual Report for 1938.
   Existing project.--This provides for a channel 27 feet deep and not
less than 500 feet wide, extending from the mouth to a point about 0.6
mile above the bridge at Bath; thence to Gardiner a channel not less
than 150 feet wide, with a depth of 17 feet at Beef Rock Shoal, at
the foot of Swan Island, 18 feet deep through rock at Lovejoy Nar-
rows, near the head of Swan Island, decreasing to 16 feet deep at
Gardiner; a channel west of Swan Island 100 feet wide, 12 feet 'deep,
except at the upper shoal, where the depth was to be 15 feet; and a
channel 125 feet wide and 11 feet deep from Gardiner upstream to
Augusta, at the head of navigation. The section of river included in
the project is about 44 miles in length. The work includes dredging,
rock excavation, and two riprap training walls. The project depths
refer to mean low water. The mean tidal range is 8.3 feet at the mouth
of the river, 6.5 feet at Bath, 5.5 feet at the foot of Swan Island, 5 feet
at Gardiner, and 4.1 feet at Augusta. The spring tides are about 1 foot
greater at the mouth and about 0.5 foot greater at Augusta.
   The estimate of cost for new work, revised in 1941, was $1,186,500,
exclusive of amounts expended under previous projects. The latest
(1941) approved estimate for annual cost of maintenance is $5,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                    Documents 1


June 13,1902   Channel between Augusta and Gardiner; Maine_ H. Doc. No. 262, 56th Cong., 1st sess.
Mar. 2,1907    Channel below Gardiner, Maine_     -------------        H. Doc. No. 321, 59th Cong., 2d sess.
Mar. 4,1913    Channel west of Swan Island..           ...----------------
                                                                       H. Doc. No. 746, 62d Cong., 2d sess.
Oct. 17,1940   27-foot channel from mouth to Bath-..-------.---         S. Doc. No. 55, 77th Cong., 1st sess.


1 These documents contain the latest published maps.


  Recommended modification of p'roject.-In House Document No.
2107, Sixty-fourth Congress, second session, it was recommended that
the improvement and maintenance of the channel west of Swan Island,
near the town of Richmond, be abandoned.
  Terminal facilities.-Wharves capable of serving a useful purpose
are located at the towns of Bath, Richmond, Randolph, Gardiner,.
Hallowell, and Augusta.
   Of the 30 wharves at Bath, 4 are publicly and 26 privately owned,
but about one-third of the privately owned wharves are in poor repair
24      REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,    1944

and are little used. Rail connections are available at 19 of the wharves
at Bath. Depths alongside the wharves range from 12 to 25 feet.
   At the other above-named points there are 16 wharves in usable
condition. All but 1 are equipped with mechanism for handling pas-
sengers or freight. Those open to the public on equal terms are 9
at Hallowell and 1 each at Randolph and Augusta. None is publicly
owned. The facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-New work: Under a
contract for the removal of ledge rock and other material to provide
a channel 27 feet deep at mean low water and not less than 500 feet
wide from the mouth of the river to a point abreast of the Bath Iron
Works Corporation, in progress at the beginning of the fiscal year,
work was completed December 19, 1943. During the fiscal year there
were drilled and blasted 13 cubic yards place measurement, of ledge
rock, and there were dredged 16,202 cubic yards, place measurement
of material, Qf which 6,358 cubic yards were broken ledge and 9,844
cubic yards were material other than ledge rock, at a cost of $49,302.40
for new work. An adjustment pf minus 89 cubic yards was made in
the quantity of ledge rock drilled and blasted during the preyious
fiscal year. During the life of the contract, June 25, 1941, to Decem-
ber 19, 1943, there were drilled and blasted 25,005 cubic yards, place
measurement, of ledge rock, and there were dredged 63,079 cubic yards,
place measurement, of material, of which 35,883 cubic yards were
broken ledge and 27,196 cubic yards were material other than ledge
rock.
  Maintenance: Final cost adjustment was made in connection with
a maintenance survey from Gardiner to Augusta, at a cost of $42.21
for maintenance.
   The total costs during the fiscal year were $49,844.61, of which
$49,302.40 was for new work and $42.21 was for maintenance. The
expenditures were $228,081.27.
   Conditionat end of fiscal year.-The existing project was completed
December 19, 1943, with the exception of project dredging from the
Bath Iron Works Corporation to its upper limit 0.6 mile above the
Bath bridge, for which there appears to be no immediai i need. The
controlling depths at mean low water in the Kennebec River are:
27 feet in the channel from the mouth to the Bath Bridge (1944);
thence 14 feet to the Gardiner-Randolph Bridge (1937); thence 8 feet
to Augusta, at the head of navigation (1942).
  The costs under the existing project have been $1,222,935.53, of
which $1,090,529.30 was for new work and $139,406.23 was for main-
tenance. The expenditures have been $1,222,935.53.
  Proposed operations.-No funds are available and no work is pro-
posed during the fiscal years 1945 and 1946, as it is believed that the
channel is in a condition to meet the reasonable requirements of navi-
gation, and there appears to be no need, under present conditions, to
provide the 27-foot channel from the Bath Iron Works Corporation
to a point 0.6 mile above the Bath bridge, which feature of work
remains to be done to complete the authorized project.
                  RIVERS AND HARBORS-BOSTON,                                 MASS., DISTRICT                                  25
                                        Cost and fitnancial summary

Cost of new work to June 30, 1944        -------------------                                                $1, 599, 940. 83
Cost of maintenance to June 30, 1944.___.--       ----                                  __-                     132, 406.23
      Total cost of permanent work to June 30, 1944_____                                      ....           1, 732, 346. 56
Net total expenditures -- __-------      ----------------                                                    1, 732, 346. 56
Total amount appropriated to June 30, 1944-....           --                                         -       1, 732, 346.56


   Fiscal year ending June 30                1940            1941              1942                  1943              1944


Costof new work.......--.-----.-.-----------   $1,061.29  $271,093. 04                        $382, 634. 19          $49,302.40
Cost of maintenance-.-.---.----$4, 258. 55 --------------    3, 295. 66                          4, 024. 47               42.21
      Total cost...-------------4,             258. 55       1, 061. 29     274, 388. 70        386, 658. 66           49, 344.61

Total expended.------------------5,            501.30          980. 93      225, 743. 04        256, 648. 02         228, 081.27
Allotted.                                  -2, 744. 89
                                     .------------------   686, 000.00    ............------------------------............ 5,453.26


Balance unexpended July 1, 1943-   _               __      _-                                                  $222, 628. 01
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941--         -$27, 981. 91
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940 --        _ .---- 2, 715.30
Amount allotted from First Deficiency Appropriation
Act, April 1, 1941------------ ---------------         25, 000.00
                                                                                                                 55, 697. 21

      Amount to be accounted for--
                                 ___..      .-                                                                  278, 325.22
Deductions on account of revocation of allotment- -------                                                        50, 243.95
      Net amount to be accounted for--
                                     ....      --------                                                        228,081.27
Gross amount expended      ---------------------- $229, 247.57
Less reimbursements collected --------------------      1,166. 30
                                                                                                               228,081.27
Amount (estimated) required to be appropriated for completion
of existing project --------------------------------------                                                     $94, 000. 00
                                     2. PORTLAND HARBOR, MAINE
  Location.-This harbor is on the southwestern coast of Maine, about
100 miles northeast of Boston, Mass. (See U. S. Coast and Geodetic
Survey Chart No. 325.)
  Previous projects.-Adopted by joint resolution of June 5, 1868,
and River and Harbor Act of June 10, 1872. For further details see
page 1736 of Annual Report for 1915, and page 40 of Annual Report
for 1936.
  Existing project.-This provides for an anchorage off the eastern
end of the city, with a minimum depth of 30 feet; for dredging the
greater part of the inner harbor to a depth of 30 feet, except for the
lower part of the main harbor and its channel of approach, where the
depth is to be 35 feet; for a channel 30 feet deep and 300 feet wide
in Fore River up to the Boston & Maine Railroad bridge; for a chan-
nel 30 feet deep and 300 feet wide from the anchorage to the Grand
Trunk bridge at the mouth of Back Cove; for rock excavation to give
a depth of 14 feet between the Grand Trunk and Tukeys Bridges,
and a channel 12 feet deep and 300 feet wide thence to the head of Back
Cove; for the removal of two obstructing ledges in the main ship
26            REPORT OF CHIEF OF ENGINEERS,. U. S. ARMY,                                     1944

channel to a depth of 40 feet; and for a stone breakwater about 2,000
feet long on the southerly side of the mouth of the inner harbor.
   The project depths refer to mean low water. The mean tidal range
is 8.9 feet, extreme 10.2 feet, though variations as great as 16 feet have
been observed under storm conditions.
   The estimate of cost for new work, revised in 1942, is $1,970,000,
exclusive of amounts expended on previous projects. The latest (1928)
approved estimate for annual cost of maintenance is $20,000.
   The existing project was authorized by the following river and
harbor acts:


       Acts                       Work authorized                                    Documents


July    4,1836    Breakwater on southerly side of mouth of inner       H. Doc. No. 491, 23d Cong., 1st sess.
                   harbor.
June 23,1866      Extension of breakwater.
June 3,1896       Dredging to 30 feet over greater part of inner       S. Doc. No. 271, 54th Cong., 1st sess.
                    harbor.
Mar. 3, 1905 Extension of 30-foot depth up Fore River to Bos-
-(Sundrycivil) ton & Maine R. R. bridge and in channel of
               approach to Back Cove.
July 25,1912 30-foot anchorage; 14 feet at entrance to Back            H. Doc. No. 489, 62d Cong., 2d sess.
                    Cove; restoration of 12-foot depth in Back Cove
                    and 30-foot depth in the approach as well as in
                    lower part of harbor.
Aug.    8, 1917   35-foot depth in lower part of main harbor and the   H. Doc. No. 71, 65th Cong., 1st sess.
                    channel of approach, and removal of two ob-
                    structing ledges in main channel.

  Latest published map in H. Doc. No. 560, 76th Cong., 3d sess.


   Recommended modifications of project.-Under date of December
15, 1939, the Chief of Engineers recommended modification of the ex-
isting project so as to provide for dredging an anchorage area 35 feet
deep at mean low water, and approximately 170 acres in area, north-
west of House Island, at an estimated first cost of $780,000 for new
work, with annual maintenance of $10,000, in addition to that now
required (H. Doc, No. 560, 76th Cong., 3d sess.).
   Further modification of the existing project was recommended by
the Chief of Engineers in a report requested by Rivers and Harbors
Committee resolution adopted December 3, 1941, and March 12, 1942,
and transmitted to Congress by the Secretary of War May 4, 1943.
   Local cooperation.-Fully complied with.
   Terminal facilities.-The harbor has a water front of about 81/2
miles, rather more than one-half of which has been developed. There
are about 54 wharves and 4 shipyards in Portland Harbor. The large
modern pier owned by the State is on the Portland side. Fifteen of
the wharves and all of the 4 shipyards are on the South Portland side.
The facilities are considered adeqiuate for existing commerce.
   For further details see Port Series No. 1, Corps of Engineers,
revised, 1937.
   Operations and results during fiscal year.-New work: Under a
contract for dredging in the 35-foot channel in the vicinity of the
Portland Pipe Line Co.'s terminal in progress at the beginning of the
fiscal year, operations were completed August 11, 1943. During the
fiscal year there 'were dredged 20,133 cubic yards, place measurement,
               RIVERS AND       HARBORS-BOSTON,                  MASS.,        DISTRICT                 27
of material at a cost of $6,163.03 for new work. Upon resumption of
operations under this contract, this office designated an inside dis-
posal area, and by supplemental agreement reduced the unit price from
67 cents to 51 cents per cubic yard.
  An adjustment was made in the final costs under a contract for
removal of an additional ledge area (designated ledge 3A), completed
May 10, 1943, at a cost of $1,317.43 for new work.
  Maintenance: Under a contract for dredging to widen to project
width of 300 feet, the 30-foot channel in Fore River above the Vaughan
bridge, work was commenced June 8, 1944, and continued through June
30, 1944, operations still being in progress at the end of the fiscal year.
During the fiscal year, there were removed 7,359 cubic yards, place
measurement, of material at a cost of $1,399.26 for maintenance.
   The total costs during the fiscal year were $8,879.72, of which
$7,480.46 was for new work and $1,399.26 was for maintenance. The
expenditures were $84,238.07.
  Condition at end of fiscal year.-The existing project was about 95
percent completed, the remaining portion consisting of the removal to
a depth of 40 feet at mean low water of a ledge located about 0.5 mile
southeast of Portland Head Light, at the entrance to Portland Harbor.
The controlling depths at mean low water in the various improved
channels of Portland Harbor at the dates they were last surveyed
were: 32 feet in lower part of main harbor (1941); 29 feet in upper
part of main harbor (1935); 28 feet in Fore River (1942); 28 feet in
anchorage, thence 17 feet to Grand Trunk bridge, thence 14 feet to
Tukeys bridge, thence 9 feet to head of Back Cove (1941).
  The total costs under the existing project have been $2,346,524.13,
of which $1,827,710.29 was for new work and $518,813.84 was for main-
tenance. The expenditures have been $2,346,469.08.
  Proposed operations.-The funds unexpended at the end of the fiscal
year, including accounts receivable, amounting to $53,644.35, will be
applied as follows:
Accounts payable June 30, 1944_                      _---__________--           - -     $55.05
Maintenance:
    Complete by Aug. 1, 1944, under a contract in force, dredging to
      a depth of 30 feet at mean low water in the Fore River Channel
      at and above the Vauhan_              Irig---                  -----.-.---    17, 185. 17
    Coiplete by June 30, 1945, survy 'of 30-=and 35-foot channels to
      Portland bridge, and the 30-foot anchorage basin, by hired labor- 5, 500. 00
Balance remaining          __----------------------------------------30,904.                 13
       Total                   -------------------------                                        53, 644.35
  The sum of $99,550 can be profitably expended during the fiscal
year 1946 for maintenance dredging of the 30- and 35-foot channels
to Portland bridge and the 30-foot anchorage basin.
                               Cost and financial summary

Cost of new work to June 30, 1944--
                                 .-----------..                                            $2, 520, 145. 54
Cost of maintenance to June 30, 1944_--
                                      ............                     --...                   518, 813. 84
      Total cost of permanent work to June 30, 1944_ ....                      ---           3, 038,959.38
Minus accounts payable June 30, 1944_--
                                    .....        --------                                           55.05
     Net total expenditures -----                    ---------                       -3,      038, 904. 33
Unexpended balance June 30, 1944 -....                  __--                                   53,644.35
       Total 'imou nt'apropritat          tou       e 30, 1944- ----------                  3, 092, 548. 68
28            REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY, 1944


    Fiscal year ending June 30                1940           1941           1942          1943              1944

Cost of new work................                               ----
                                                               ----..............
                                           ---------------..............
                                                                      $92, 563. 10 $149,537.67              $7,480.46
Cost of maintenance.....---------........
                                 -----------------.... .-------------
                                                               ...         184.38    2,245.83                1,399.26
       Total cost--.................
                               --............ .
                                     --......-                          92, 747.48      151, 783.50          8, 879.72
Total expended. ..------.....-.......... -------............. 32,229.10                 136, 888.48         84, 238.07
                                     - -------------------
Allotted-------.....----........---...-.---..                 $92,000   65,000.00       150,000.00    ...

Balance unexpended July 1, 1943-- .----...-------            $137, 882.42
Gross amount expended ------------------------ $84, 736. 11
Less reimbursements collected-                    -   498.04
                                                    ....----
                                                                                                      84, 238.07
      Balance unexpended June 30, 1944 _.........53,644.35
Outstanding liabilities June 30, 1944_.- ---..        $55.05
Amount covered by uncompleted contracts---                                         17, 185.17
                                                                                                      17,240.22
          Balance available June 30, 1944------                         -          -   -36,404.13
Amount (estimated) required to be appropriated for completion
of existing project - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -      87, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance - - - - - - - - - - - - - - - - - - - - - - - - - - - -               99,550.00
    SExclusive of available funds.

                                         3. MYSTIC RIVER, MASS.
   Location.-Rises in Mystic Lakes, Mass., flows in a southeasterly
direction, and empties into Boston Harbor near the Charlestown Navy
Yard. It is 7 miles in length. (See U. S. Coast and Geodetic Survey
Chart No.248 and U. S. Geological Survey Chart, "Boston.")
   Previous projects.-Original project for the lower Mystic was
adopted by the River and Harbor Act of March 3, 1899, and curtailed
by the River and Harbor Act of June 25, 1910. For further details see
  age 1743 of Annual Report for 1915, and page 59 of Annual Report
for 1938.
   There has been no previous project for the upper Mystic.
   Existing project.-This provides for a channel 30 feet deep down-
stream from the mouth of Island End River, through the Chelsea
(north) bridge to the 35-foot channel of Boston Harbor about one-
half mile, 600 feet wide at the upper end, and gradually narrowing
to 300 feet wide at the lower end, and widening of the entrance channel
leading to Mystic wharf; a channel 30 feet deep and 500 feet wide
upstream from the mouth of Island End River to the city playground
at Charlestown; a channel 20 feet deep from the head of the existing
30-foot channel to a point 800 feet above the Malden bridge with widths
decreasing from 270 feet at the lower end to 75 feet through the draw-
span, thence increasing to approximately 340 feet to form a turning
basin above the bridge; a channel 6 feet deep and 100 feet wide from
the Boston & Maine Railroad (western division) bridge to about 2,500
feet above Wellington bridge, about 1 mile, and thence 4 feet deep,
gradually narrowing from 100 feet to 50 feet at the upper end for
about 2 miles to the head of commercial navigation at Cradock bridge
in Medford. The project depths refer to mean low water. The mean
range of tide is 9.6 feet. The extreme range is 13.7 feet.
   The estimate of cost for new work, revised in 1938, was $768,000,
exclusive of amounts expended on previous projects. The latest (1938)
approved estimate of cost for annual maintenance is $7,500.
                RIVERS AND HARBORS-BOSTON,                            MASS.,     DISTRICT                 29
  The existing project was authorized by the following river and
harbor acts:

      Acts                        Work authorized                                  Documents

July 13, 1892    Inrovement of the upper IVystic ......------------   Annual Report, 1891,   , A72.

June 25,1910     Improvement of channel downstream from               H. Doc. No. 1086, 60th Cong., 2d sess.
                   mouth of Island End River to the 35-foot chan-
                   nel of Boston Harbor.
Aug. 30,19351    Improvement of channel upstream from mouth           Rivers and Harbors Committee Doc.
                   of Island End River to city playground at            No. 33, 74th Cong., 1st sess.
                   Charlestown.
June 20, 1938    Improvement of channel upstream from city            H. Doc. No. 542, 75th Cong., 3d sess.
                   playground at Charlestown to a point 800 feet
                   above the Malden bridge.

  1 Also Emergency Relief Act of 1935.
  2   Contains latest published map.

   A map showing the entire river is published in House Document
No. 2108, Sixty-fourth Congres, second session.
   Terminal failities.--In the section of the river benefited by the
30-foot-channel project there are on the south bank of the river four
wharves aggregating over 4,000 feet of berthing space used for the
receipt, storage, and shipment of coal, lumber, and gypsum. These
wharves consist of substantial stone or wooden bulkheads filled solid,
and in some cases fronted by pile platforms. There is also on the
south bank a lumber terminal, the largest of its kind on the Atlantic
coast. It is equipped with the most modern mechanical appliances,
has railroad connection, and occupies 4,400 feet of water front. On
the north bank of the river within the scope of this improvement there
is a large wharf for receipt and shipment of oil on an extensive scale;
immediately adjacent to this wharf is an extensive terminal con-
structed in connection with an iron works; on the west bank of
Island End River which flows into Mystic River on the north about
midway of the 30-foot channel, are situated two large terminal wharves,
of 800 feet dockage, for receipt and shipment of coal, coke, tar, and oil.
These wharves are connected with the 30-foot channel by a channel 30
feet deep at mean low water, dredged by private interests. None of
the above wharves is publicly owned, and none is open to general
public use.
   Beyond the scope of the 30-foot-channel improvement, and within
the scope of the 20-foot channel and the improvement of the upper
Mystic, there are on the south bank in Charlestown and Somerville
about 1,850 feet, and on the north bank in Medford about 1,235 feet of
available dockage, of which 450 feet on the south bank and 435 feet on
the north bank are customarily in use. A large automobile assembly
plant is located on the south bank in Somerville.
   The existing wharves consist of stone and wooden bulkheads solid
filled. None is publicly owned, but two are open to the public on
payment of wharfage charges. The capacities of the lower Mystic are
being utilized to a gratifying extent.
   These facilities are considered adequate for existing commerce.
    Operations and results during fiscal year.-Maintenance: Under a
contract for maintenance dredging to restore project depth of 30
feet at mean low water in a reach of the Federal channel, work was
30        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                1944

started December 23, 1943, and completed. February 28, 1944. There
were removed 30,481 cubic yards, place measurement, of material at a
cost of $28,861.42 for maintenance.
   Work by hired labor consisting of completion of a preliminary
survey cost $649.92 for maintenance.
   The total costs during the fiscal year were $29,511.34, all for main-
tenance. The expenditures were $29.603.97.
   Conditionat end of fiscal year.-The existing project was completed
in 1940, with the. completion of the 20-foot chantiel in te vicinity of
Malden. bridge. The 30-foot channel extending from the 35-foot
channel in Boston Harbor to the mouth of Island End River was com-
pleted in 1914, and the extension of this channel upstream to the city
playground at Charlestown was completed in 1938. A channel in
the upper Mystic with project depths of 6 and 4 feet was completed
in 1906. The controlling depths at mean low water in Mystic River at
the time the various sections were last surveyed were: 29.5 feet for
full project width, or 30.2 feet for half of project width, from the up-
stream end of Chelsea North Bridge to a point abreast of center of
mouth of Island End River (1944); thence 27 feet for full project
width, or 29.6 feet for half of project width, from .apoint abreast of
center of mouth of Island End River to a point abreast of downstream
end of Colonial Beacon Oil Co. wharf (1944); thence 25 feet for full
project width, or 26.5 feet for three-quarters of project width, to the
upper linmit of the 30-foot chaniie'              (1941);
                                               thence    .,,feet to a point
800 feet above the Malden bridge (1940); thence 4.5 feet in the 6-foot
project channel and 4 feet in the 4-foot project channel (1916), the
width of the latter section having been contracted by caving of the
banks.
   The total costs under the existing project from regular funds have
been $341,385.69, of which $293,341.72 was for new work and $48,043.97
was for maintenance. The total expenditures have been $341,385.69.
The total costs and expenditures under Emergency Relief appropria-
tion funds have been $476,783.40, all for new work. The total costs
under all funds have been $818,169.09, of which $770,125.12 was for
new work and $48,043.97 was for maintenance. The total expenditures
have been $a18,1f9.09.
  Proposedoperations.-The funds unexpended at the end of the fiscal
year, including accounts receivable, amounting to $5,608.84 are avail-
able for revocation.
   No additional funds can be profitably expended during the fiscal
year 1946, as it is believed that the channel will be in a condition to
meet the reasonable requirements of navigation.
                               Cost and financial summary
Cost of new work to June 30, 1944 --------------------------        $895, 848. 32
Cost of maintenance to June 30, 1944 ---------------------------      58,325. 89
       Total cost of permanent work to June 30, 1944-------------$9       , 174.21
Net iotal ex  nditures ---------- _-_----------------954,174.21
       Unexpended balance Jurre 30, 1944..------------------------5,608.84
Total amount appropriated to June 80, 1944 .....-                    959, 783.05
                    RIVERS           AND HARBORS-BOSTON,                                    MASS.,                DISTRICT                        31

    Fiscal year ending June 30                          1940               1941                  1942                       1943           1944


Cost of new work....---------------$50, 714.81                            $1, 783.40 ..-------------------                         --------------
Cost of maintenance-------                 ----------------------------                      $3,123.73                       $156.09      $29, 511.34

Total expended -----------------...............       50, 714.81 -        -       ...            3,123. 73                    63.46        29,603. 97
Allotted....-------------------------714.81                               23.400.00     -               -----------------                  15, 000.00


Balance ute penie Jul ,1, 1943            --- --------   --------                                                                     $20,212. 81
Amount allotted from War Department CivilApprOYiriatl6n Act ap-
  proved May 23, 1941--------------------------$12,710.51
Amount allotted from War Department Civil Appropria-
  tion Act approved June 24, 1940--------              - 2,289.49
                                                                                                                                       15, 000. 0'
      Amount to be accounted for --------------------                                                                                  35, 212. 81
Gross amount expended ________---------$29,                                                                            604.87
Less reimbursements collected_---_------                                                                                 0. 90
                                                                                                                                       29,603.97
            Balance unexpended June 30, 1944_-                                              --                    ---                   5, 608. 84

                                             4. BOSTON HARBOR, MASS.
   Location.-This harbor includes all the expanse of tidewater lying
within a line from Point Allerton to Point Shirley and extending fron
that line westward tothe mainland. This co.prises an area of about.
47 square miles, exclusive of the islands. (See U. S. Coast and Geo-
detic Survey Charts Nos. 946 and 248.)
  Previous projects.-Adopted by the River and Harbor Acts of March
2, 1867, June 14, 1880, September 19, 1890, June 3, 1896, and July 25,
1912. For further details see page 1743 of Annual Report for 1915,.
page 81 of Annual Report for 1917, and page 63 of Annual Report for-
1938.
   Existing projeet.-This provides for the following:
   (a) A channel 40 feet deep in general, but 45 feet deep through rock,
from the sea to President Roads through Broad Sound, 2 miles, 900.
feet wide except at the outer end where it is widened to 1,100 feet.
   (b) Deepening the main ship channel from President Roads past
the United States.Navydrydock No. 3 at South Boston to Common-
wealth pier No. 1, East Boston, to 40 feet for a width of 600 feet with
suitable widening at the bend in the channel.
   (o) An anchorage area 2,000 feet wide, 5,500 feet long, and 40 feet
deep, on the north side of President Roads.
   (d) Deepening to 40 feet that part of the approach channel to the
United States Navy drydock No. 3 at South Boston between the main
ship channel and the United States harbor line.
   (e) A channel 35 feet deep from the sea (along the same line as the
40-foot channel) through Broad Sound to the navy yard at Charles-
town and the Chelsea North, Meridian Street, and Charles River
Bridges, 1.500 feet wide from the sea to President Roads, 1.5 miles, and
thence 1,200 feet wide for the remaining distance of 6 miles.
   (f) A channel 2 mi s long, 30 fet deep, and 1,200 feet wide from
the sea to President Roads through Broad Sound by a less direct router
than the 35- and 40-foot channels.
   (g) A channel 27 feet deep and 1,000 feet wide from Nantasket
Roads to President Roads, 3 miles.
32          REPORT OF CHIEF OF ENGINEERS,                       U.   S. ARMY,        1944


   (h) A channel 15 feet deep, 300 feet wide, and 550 feet long through
the bar which extends from the north head of Long Island to Nixes
Mate Shoal, known as "Nixes Mate" or "Nubble" Channel.
   (i) A channel in Chelsea Creek 30 feet deep and generally 200 feet
wide, from the mouth of the creek, at the head of the 35-foot channel
in Boston Harbor, to a point opposite the Hartol Oil Co. terminal.
   (j) Improvement of Reserved Channe east of L Street-Bridge by a
channel 30 feet deep and 300 feet wide.
   (k) The Fort Point Channel, 23 feet deep and 175 feet wide from
its entrance in Boston Harbor, about four-fifths of a mile to near the
Dorchester Avenue (old Federal Street) Bridge.
  (1) Sea walls of coursed stone .and riprap protecting the most ex-
posed headlands and islands.
   All depths are referred to mean low water. The mean range of
tide is 9 feet at Boston Light and 9.6 feet in the upper harbor, in
Chelsea Creek, and in Fort Point Channel. The extreme range is
about 4 feet greater.
   The estimate of cost for new work, revised in 1941, exclusive of
amount expended on previous projects and of sea walls for which no
estimate was given, is $20,043,700. The latest (1941) approved esti-
mate for annual cost of maintenance is $174,000.
   The existing project was authorized by the following river and
harbor acts:

     Acts                     Work authorized                                 Documents


Mar. 2, 1825  Preservation of islands by sea Walls.........
Aug. 5,1886                           ----------------------- H. Ex. Doc. No. 206, 48th Cong., 2d
              Fort Point Channel ........
                                                                 sess. Annual Report, 1885, p. 543.
              Channel 15 feet deep from Long Island to Nixes Annual Report, 1887, p. 517.
                Mate Shoal (Nixes Mate or Nubble Channel).
July 13, 1892 Channel 27 feet deep from Nantasket Roads to Annual Report, 1893, p. 766.
                President Roads.
Mar. 3,1899 For 30-foot channel from the sea to President H. Doc. No. 133, 55th Cong., 2d sess.
                Roads through Broad Sound by less direct         Annual Report, 1898, p. 886.
                route than the 35-and 40-foot channels.
June 13, 1902 For 35-foot chamnnel from the sea to navy yard at H. Doc. No. 119, 56th Cong., 2d sess.
                Charlestown.                                     Annual Report, 1901, p. 1096.
              Elimination from the project of the removal of Authorized by Chief of Engineers,
                Finns Ledge at the outer entrance.               Mar. 11, 1913.
                                                                                                     1
Aug. 8,1917 Depth of 40 feet (45 feet in rock) in Broad Sound H. Doc. No. 931, 63d Cong., 2d sess.
                Channel.
Aug. 30,19352 Present project dimensions of channel from Presi- H. Doc. No. 244, 72d Cong., 1st sess.I
                dent Roads to Commonwealth pier No. 1, East
                Boston, and anchorage area north side of Presi-
                dent Roads.
    Do-.......Present project dimensions of that part of ap- Rivers and Harbors Committee Doc.
                                                                                               1
                proach channel to U. S. Navy drydock No. 3,      No. 29, 74th Cong., 1st sess.
                at South Boston between Main Ship Channel
                and United States harbor line.
Aug. 26,1937 Chelsea Creek Channel, 30 feet deep ............   Rivers and Harbors Committee Dee.
                                                                                               1
                                                                 No. 24, 75th Cong., 1st sess.
                                                                                                  1
Oct. 17,1940 Reserved Channel, 30 feet deep--------------- H. Doc. No. 2?5, 76th Cong., 1st sees.
Sept. 7,1944 Abandons seaplane channel authorized in River Public Law 420, 78th Congress.
                and Harbor Act approved Oct. 17, 1940 (H.
                Doc. No. 362, 76th Cong., 1st sess.).

  I Contains latest published maps. See also Annual Report, 1911, p. 1178 (sea walls and Nixes Mate Chan*
nel) and Annual Report, 1903, p. 770 (Fort Point Channel).
  I Authorized in part by Public Works Administration, Sept. 6, 1933.
           RIVERS AND        HARBORS-BOSTON,   MASS.,   DISTRICT     33
   Recommended modifcation-e of project.-Under date of January 10,
1944, it was recommended that the dredging of a seaplane channel in
Boston Harbor, 12 feet deep and 1,500 feet wide, extending north-
westerly from President Roads 17,500 feet to the easterly margin of
Boston Airport (now officially designated the General Edward Law-
rence Logan Airport), which was authorized in the River and Harbor
Act approved October 17, 1940, be abandoned, and that in lieu thereof
authority be granted for the construction of a seaplane channel at such
alternate location as may be approved by the Chief of Engineers, at
a cost not exceeding $2,300,000, the estimated cost of the project now
authorized (H. Doc. No. 472, 78th Cong., 2d sess.).
  Local cooperation.--Fully complied with.
   Terminal facilities.-The wharf development of Boston Harbor lies
westerly of Governors and Castle Islands. Bordering on the 35- and
40-foot channel and below all bridges there are about 4 miles of water-
front, fully developed with wharves of various types devoted to com-
mercial purposes; and on the Charlestown shore is located the United
States navy yard, with a frontage of about five-eighths of a mile.
   The Boston Airport has been established easterly of the wharf
development on the East Boston front.
   There are numerous public and private wharves, piers, ferry slips,
and drydocks. The facilities are considered adequate for existing
commerce. For further details see Port Series No. 2, Corps of En-
gineers, revised, 1936.
   Operations and results during fiscal year.-Maintenance: Work by
hired labor consisting of a sounding survey of inside disposal areas
in Boston Harbor, carried on at intervals during the fiscal year, cost
$3,652.01 for maintenance.
  An adjustment was made in the cost of a maintenance survey of
the Broad Sound dumping ground made during a previous fiscal year
at a cost of $21.49 for maintenance.
  The total costs during the fiscal year were $3,673.50 for maintenance.
The expenditures were $5,969.55.
  Condition at end of fiscal year.-The existing project is substantially
completed. The work remaining to complete the project consists of
dredging to 30 feet a small area in Chelsea Creek in the vicinity of a
metropolitan district sewer siphon now under construction immedi-
ately below the Chelsea Street Bridge. Seawalls of a total length of
about 3.75 miles have been built and maintained on Great Brewster,
Lovells, Gallops, Long, Rainsford, Deer, and Georges Islands, and on
Point Allerton. The Nixes Mate or Nubble Channel was completed
in 1892; the 30-foot channel in 1905; the 27-foot channel in 1907; Fort
Point Channel in 1909; the 35-foot channel in 1915; the Broad Sound
40-foot channel in 1930; the 40-foot anchorage in 1937; the 30-foot
Chelsea Creek channel (except for the small area immediately below
the Chelsea Street Bridge) in 1940; the 40-foot inner harbor channel
in 1941; and the 30-foot Reserved Channel in 1941.
  The controlling depths at mean low water in the various improved
channels of Boston Harbor at the dates they were last surveyed were:
Nixes Mate Channel, 15 feet (1932); 35-foot channel, 35 feet (1934);
40-foot anchorage, 39 feet (1937); Broad Sound 40-foot channel, 40
feet (1939); 30-foot channel, 30 feet (1939); inner harbor 40-foot chan-
nel, 37.5 feet (1941); Reserved Channel, 30 feet (1941); Fort Point
Channel, 19 feet (1941); and Chelsea Creek Channel, 30 feet from the
     616634--45--pt. 1, vol. 1-8
34           REPORT OF CHIEF OF ENGINEERS,                                          U. S. ARMY,                 1944

mouth to a point about 170 feet downstream of the Chelsea Street
lBridge, thence 24 feet to the downstream end of the Grand Junction
Railroad bridge, thence 30 feet to a point abreast of the Hartol Oil Co.
(1940), thence 8 feet to the bend just below the head of navigation
(1936).
  The costs and expenditures under the existing project to June 30,
1944, have been as follows:

                                                New work                Maintenance                Total              Expenditures


Regular funds.--------------------             $13, 665,774.84           $1, 446, 812. 25    $15, 112, 587. 09        $15, 112, 459. 05
Public Works funds .....              ......     1, 030, 806. 26                               1,030, 806. 26            1,030,806. 26
Emergency Relief funds                              935, 303.03----------------03                 935, 303.03              935, 303.03

       Total-..........................         15, 631, 884. 13          1,446, 812. 25       17, 078, 696. 38        17, 078, 568. 34


   Proposed operations.-The funds unexpended at the end of the
fiscal year, including accounts receivable, amounting to $87,406.35,
will be applied as follows:
Accounts payable June 30, 1944                 ---------------------------------                                             $128.04

New work:
   Dredge to a depth of 30 feet in Chelsea Creek in the vicinity
     of a metropolitan district sewer siphon immediately below the
     Chelsea Street Bridge, by contract (Apr. 1-30, 1945)                                                                  4,710. 65

Maintenance:
   Dredge to a depth of 40 feet isolated shoal areas in the inner
      harbor 40-foot channel, by contract (May 1 to June 30, 1945)_                                                     71, 500. 00
   Complete by June 30, 1945, sounding survey of inside disposal
      areas in Boston Harbor, by hired labor-   - ------            -                                                      9, 450.93
   Complete by June 30, 1945, sounding survey of Broad Sound
      dumping ground, Boston Harbor, by hired labor                                      --------------                    1616.73
                                                                                                                           1,
              Total maintenance               ----------------------------------                                       82, 567. 66

              Total --          ----------          -------------------------------                                    87,406.35
  No additional funds can be profitably expended during the fiscal
year 1946, as it is not believed that maintenance work will be required
during that year.
                                      Cost and financial summary
                                   ------------------------- $17, 097, 007.09
Cost of new work to June 30, 1944___
Cost of maintenance to June 30, 1944- -----.........           1,464, 691. 51
     Total cost of permanent work to June 30, 1944_ .........  18, 561, 698.60
Minus accounts payable June 30, 1944 -------------------------          128.04
     Net total expenditures----- --     ----------                                                              18, 561, 570. 56
Unexpended balance June 30, 1944-----------------------------                                                        87, 406.35
          Total amount appropriated to June 30, 1944_ .........- 18,648, 976.91

     Fiscal year ending June 30              1940                1941                 1942               1943                1944

Cost of new work .-------------     $879, 562 81            $481,934. 58            $98,304.57      -$     281. 71
Cost of maintenance....-------------23, 009.83                 6, 108.91                511.53        1,838.65         ---   $3, 67.50
        Total cost---------------         902,572.64          488,043.49            98,816.10         14,556.94               3,673.50
  Iotal expended -       -..              939, 065. 67        593, 850. 27          105, 110. 38         3, 523. 27           5, 969. 55
Allotted--------       ----    --------   440,000. 00         138, 415.16 --------.-...               48, 500.00       -
               RIVERS AND HARBORS-BOSTON,                   MASS., DISTRICT                    35
Balance unexpended July 1, 1943    ------------------------                          $93, 375. 90
Gross amount expended _________----------$10,             309.33
Less reimbursements collected -------------            4, 339. 78
                                                                                        5, 969. 55

      Balance unexpended June 30, 1944_-                                          87,406.35
                                                                              ..........---
Outstanding liabilities June 30, 1944____---------_                         .128.        04

       Balance available June 30, 1944 -------                 ----------              87, 278. 31

                         5. WEYMOUTH FORE RIVER, MASS.
   Location.-Rises in Braintree, Mass., and flows in a northerly direc-
tion 7.5 miles, emptying into Hingham Bay, Boston Harbor. (See
U. S. Coast and Geodetic Survey Chart No. 246.)
   Previou.s projects.-Adopted by the River and Harbor Act of Sep-
tember 19, 1890, and extended by the River and Harbor Acts of March
3, 1905, February 27, 1911, and July 27, 1916. For further details see
page 1745 of Annual Report for 1915, page 64 of Annual Report for
1932, and page 67 of Annual Report for 1938.
   Existing project.-This provides for (a) a channel 27 feet deep
with a general width of 300 feet from a point in Hingham Bay be-
tween Nut and Peddocks Islands to the Weymouth Fore River bridge
at Quincy Point, about 3.0 miles; and (b) a channel in Nantasket Gut
27 feet deep and 400 feet wide, extending from deep water in Nan-
tasket Roads to Hingham Bay, a distance of about 2,000 feet; thence
through Hingham Bay 27 feet deep and 300 feet wid. for a distance of
about 1.4 miles to deep water in Weymouth Fore River west of Sheep
Island. The plane of reference is mean low water. The mean range
of tide is 9.5 feet. The extreme range is 13.6 feet.
   The estimate of cost for new work, revised in 1941, is $496,000, ex-
clusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $4,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                            Work authorized                            Documents


Aug. 30,1935   27-foot channel from Hingham Bay (between Nut and       H. Doc. No. 207, 72d Cong.,
                 Peddocks Islands) to Weymouth Fore River bridge.        1st sess.
Oct. 17,1940   27-foot channel through Nantasket Gut and Hingham Bay   H. Doc. No. 568, 76th Cong.,.
                                                                                 1
                 to deep water in Weymouth Fore River west of Sheep      3d sess.
                 Island.


I Contains latest published map.


  Recommended modifications8 of project.-Under date of March 20;
1941, the Chief of Engineers recommended modification of the existing
project so as to include the present 27-foot State-improved channeL
through and above the Weymouth Fore River bridge and to provide
in this section a combined channel and maneuvering basin of the same
depth; with a length of about 2,500feet and widths varying from 470
to 900 feet, at an estimated first cost of $225,000 with $1,500 annually
for maintenance in addition to the amounts now required (H. Dbe.
No. 291, 77th Cong., 1st sess.).
  Local cooperation.-Fully complied with.
   "TeVninalfacilities.--At the head of the Federal improvement at
36          REPORT OF CHIEF OF ENGINEERS,                            U.   S. ARMY,          1944

Weymouth Fore River bridge there is. on the westerly side below
the bridge, one wharf of masonry and concrete with pile platform
extension having aggregate dockage of 600 feet and depth in the
berth of 30 feet at mean low water. On the easterly side there is a
wharf abQut 600 feet in length, in front of which the owners have
dredged to 28 feet at mean low water. A large electric power plant
is located at this point.
   Above Weymouth Fore River bridge and served by the Common-
-wealth of Massachusetts improvements are eight wharves in use for
water-borne freight. There is also a terminal, with a depth of 32
feet, used for the receipt of petroleum. In this area is the Fore River
plant of the Bethlehem Shipbuilding Corporation, with depths up
to 38 feet, used for the building and equipping of large naval and
commercial vessels.
   These facilities are considered adequate for existing commerce.
   Operationsand results during fiscal year.--None.
   Condition at end of fiscal year.-The existing project was about 78
percent completed. The work remaining to complete the project con-
sists of dredging the 27-foot channel through Nantasket Gut and Hing-
ham Bay to deep water in Weymouth Fore River west of Sheep Island,
authorized by the River and Harbor Act of October 17, 1940. A sur-
vey of the river from Hingham Bay to Weymouth Fore River bridge,
made in 1941, showed a controlling depth in the channel of 26 feet at
mean low water for a width of 170 feet, and 25 feet for the project
width of 300 feet. The costs and expenditures under the existing proj-
ect have been $363,975.37, of which $355,227.34 was for new work and
$8,748.03 was for maintenance.
   Proposed operations.-No funds are available and no work is pro-
posed during the fiscal year 1945.
   The sum of $37,500 can be profitably expended during the fiscal year
1946 to be applied to maintenance dredging in the 27-foot channel.
                                    Cost and finamocial summary
Cost of new work to June 30, 1944_--- -           --------                                    $991, 127. 34
Cost of maintenance to June 30, 1944_-----
                                         __.-----
                                        ..                                                      13, 998. 03
      Total cost of permanent work to June 30, 1944                       -----------        1, 005, 125. 37
Net total expenditures---
                       .....     -___---                                            --       1,005, 125. 37
Total amount appropriated to June 30, 1944-......   --                               -1      1, 005,125. 37

     Fiscal year ending June 30           1940          1941          1942           1943           1944

                   -
Cost of new work- .....  -
                        ...... $1,352. 34             $65, 193. 11
Cost of maintenance--------------
                         .......        ---             5, 601. 58   $3, 146. 45.
       Total ,doSt-----------------.      1, 352.34    70, 794.69     3,146.45---------.
Total expended-..-------------1, 173.80                70, 864.07     3, 255. 61
Allotted-------------------------      -33,700.00       7,000.00      3,000.00------.----_----      -$719.14

Balance unexpended July 1, 1943-------------------------------                                     $719.14
Deductions on account of revocation of allotment--       .----..                                    719.14

Amount (estimated) required to be appropriated for completion
of existing project - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - -   141 000.00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance---- -.---------                                  --       ---        -  37, 500. 00
1In addition $100,000 was expended from contributed funds for new work.
 ' Exclusive of available funds.
          RIVERS   AND   HARBORS-BOSTON,      MASS.,   DISTRICT        37
               ,   6. WEYMOUTH BACK RIVER, MASS.

   Location.-Rises in East Weymouth, Mass., and flows in a northerly
direction 4.5 miles, emptying into Hingham Bay at the mouth of
Weymouth Fore River. (See U. S. Coast and Geodetic Survey Chart
No. 246.)
   Previous projects.-Adopted by the River and Harbor Act of Au-
gust 18, 1894, and completed in 1912. For further details of pre-
vious project see page 67 of Annual Report for 1932, and page 65 of
Annual Report for 1935.
   Existing project.-This provides for a channel 15 feet deep at mean
low water and 250 feet wide through the bar at the mouth of the
river, thence generally 200 feet wide to the downstream end of the
American Agricultural Chemical Co.'s wharf, with a turning basin
350 feet wide and 400 feet long at its inner end. The mean range of
tide is 9.4 feet. The extreme range is 13.5 feet. The estimate of
cost for new work, made in 1932, was $60,000 (including $20,000 con-
tributed by local interests). The latest (1932) approved estimate for
annual cost of maintenance is $700.
   The existing project was adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. No. 32, 72d
Cong., 1st sess.). The latest published map is in that document.
   Local cooperation.-Fullycomplied with. Approved by the Chief
of Engineers August 29, 1942.
   Terminal facilities.-There are one commercial wharf and one ship-
yard on this waterway. The commercial wharf has a frontage of
about 1,400 feet and is a stone wall, filled, with pile platform in front.
It is privately owned, not open to general public use, and is considered
adequate for existing commerce.
   Operations and results during fiscal year.-New work: Under a
contract for dredging the channel 15 feet deep at mean low water and
250 feet wide through the bar at the mouth of the river, thence gen-
erally 200 feet wide to the downstream end of the American Agricul-
tural Chemical Co.'s wharf, with a turning basin 350 feet wide and
400 feet long at its inner end, work was completed August 19, 1943.
During the fiscal year there were dredged 8,199 cubic yards, place
measurement, of material at a cost of $2,100.51 for new work.
   The total costs during the fiscal year were $2,100.51 for new work.
The expenditures were $24,026.61.
   Condition at end of fiscal year.-The existing project was completed
in 1943 with the completion of the dredging of the 15-foot channel and
turning basin. The controlling depths at mean low water in Wey-
mouth Back River at the dates the various sections were last surveyed
were: 15 feet from the mouth to the downstream end of the American
Agricultural Chemical Co.'s wharf (1943); thence, in the Navy proj-
ect beyond this point, 15 feet for a width of 200 feet to the Lincoln
Street Bridge, 14 feet in a further length of 2,000 feet for widths vary-
ing from 180 to 400 feet, and 14 feet in a turning basin approximately
500 by 830 feet in area at its inner end (1943).
   The total costs under the existing project have been $48,740.67
United States funds, and $20,000 contributed funds, a total of $68,-
740.67, all for new work. The expenditures have been $68,740.67,
including $20,000 contributed funds.
38                REPORT OF CHIEF OF ENGINEERS,                                                               U. S. ARMY,            1944

  Proposed operations.-No funds are available and no funds can be
profitably expended during the fiscal years 1945 and 1946, as it is
believed that the channel is in a condition to meet the reasonable re-
quirements of navigation.
                                                      Cost and financial summary

Cost of new work to June 30, 1944---
                                   ....                                                       ---------                                - $69, 219. 35
Cost of maintenance to June 30, 1944_-                                                     ---------                            ----       6, 521.32

      Total cost of permanent work to June 30, 1944_-   -----                                                                               75, 740. 67
Net total expenditures     ---------------------------------                                                                                75, 740. 67
Total amount appropriated to June 30, 1944                                                                                                 175,  740. 67
                                                                                                                                           1.......




     Fiscal year ending June 30                              1940                    1941                     1942            1943              1944

                                         ..--------------
Cost of new work...............----------------.........   --
                                                          -.....                                                            $46, 640.16         $2,100. 51
Cost ofmaintenance ..-----------.----------------------------------------------------
                             .....--------------
          Total cost-----------.........                                                      -------....--                  46, 640. 16              51
                                                                                                                                                 2,100.

Total expended .........                              ....................... _._ _.                                 ....    24, 714.06         24,026.61

Allotted----------------................----------............---.............---------------------------.............       59, 000.00       -10, 259. 33


Balance unexpended July 1, 1943---------------------------------$34,                                                                            285. 94
Deductions on account of revocation of allotment_-      -----                                                                               10, 259. 33

      Net amount to be accounted for                                                                                                        24, 026. 61
Gross amount expended ___________-                                                    -----------                                           24,026. 61
    1   $20,000 additional was spent from contributed funds on new work.

                                                   7. CAPE COD CANAL, MASS.

   Location.-This waterway is a sea-level canal, extending from the
head of Buzzards Bay, Mass., to a point on Cape Cod Bay about 15
miles southeast of Plymouth Harbor, Mass. In general direction the
canal trends from Buzzards Bay easterly to Cape Cod Bay. (See U. S.
Coast and Geodetic Survey Charts Nos. 251 and 1209.)
  Eaisting project.-This provides for the purchase of the Cape Cod
Canal at a cost to the United States of $11,500,000; for an open canal
32 feet deep at mean low water with a width of 540 feet in the land
cut, 500 feet in a,straight channel in Buzzards Bay to Wiigs Neck,
and 700 feet beyond Wings Neck; a harbor of refuge for small vessels,
by dredging a channel 15 feet deep and 100 feet wide into Onset Bay;
mooring basins; the construction of two fixed highway bridges having
a horizontal clearance of 500 feet with a vertical clearance at mean high
water of 135 feet; the construction of a railroad bridge with a vertical
lift of 500-foot span, and 135 feet vertical clearance when the span is
raised; an improved lighting system and other accessory and minor
features which may be deemed necessary, and to be in accordance
with plans approved by the Chief of Engineers.
   The land cut is 7.7 miles long, and with approach channels, the total
length of the canal is 171/2 miles.
  The mean range of tide in Cape Cod Bay is. 9.4 feet and in Buzzards
Bay 4.0 feet. The mean range of spring tides is about 13 feet in Cape
Cod Bay, and 6.5 feet in Buzzards Bay.
   The estimate of cost for new work, revised in 1935, is $27,145,000,
exclusive of $11,500,000, purchase price of the canal and properties
               RIVERS       AND HARBORS-BOSTON,                    MASS., DISTRIC ' '                      39
which were taken over by the United States on March 31, 1928. The
latest (1936) approved estimate for annual cost of maintenance is
$619,000, including $219,000 for operation and care.
   The existing project was authorized by the following river and
harbor acts:

              Acts                            Work authorized                             Documents


Jan. 21, 1927 (sec. 2) _...    ..   Purchase of canal from the Boston,         H. Doc. No. 139, 67th Cong.,
                                      Cape Cod & New York Canal Co.,            2d sess.
                                     in accordance with contract dated
                                     July 29, 1921, executed by that com-
                                     pany.
Included in Public Works Ad-        Construction of 3 bridges and widen-       H.     Doc. No. 795, 71st Cong.,
  ministration program, Sept. 6,     ing canal to 205 feet.                         3d sess.
  1933.
June 26, 1934 (Permanent Ap-        Operation and care of works of im-
  propriations Repeal Act).          provement provided for with funds
                                     from War Department appropria-
                                     tions for rivers and harbors.
Included in Public Works Ad-        Construction of a mooring basin- .-..      H. Doc. No. 795, 71st Cong.,
  ministration program, Apr.                                                    3d sess.
  29, 1935.
Included in Emergency Relief        Dredging and bank protection_-...
program, May 28, 1935.
                        -
Aug. 30, 1935- ---------. ------- Existing project adopted..                      Rivers and Harbors Commit-
                                                                        ..------------
                                                                                    tee Doe. No. 15, 74th Cong.,
                                                                                    1st sess. (Contains latest
                                                                                    published map.)



  Recommended mQdiflcations of project.-Under date of August 21,
1941, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for dredging a channel 150 feet wide and
15 feet deep at mean low water, extending from deep water in the
vicinity of Wickets Island to the town wharf at the village of Onset;
for enlargement of the 15-foot turning basin at the town wharf; and
for an anchorage basin of about 16 acres, contiguous to the proposed
channel and turning basin, havi-g a depth of 8 feet at mean low
wter; at an estimated cost of $ 000 with an annual maintenance of
$2,500; subject to certain conditions of local cooperation (IH. Doc. No.
481, 77th Cong., 1st sess.).
   Te nrinal facilities.-There are four terminals on the canal. Three
are privately owned, one being used for the receipt and freezing of fish
anid two for the receipt and storage of oil. The fourth terminal is the
State pier, owned by the Commonwealth of Massachusetts, and located
on the north bank of the canal at Bourne Neck. The terminals are
considered adequate for the purposes for which they are used.
   Operationsand results during fiscal year.-Maintenance: The U. S.
seagoing hopper dredge W. L. Marshall was engaged in maintenance
dredging to restore project depths in the canal, approaches and moor-
ing basins during the period July 23 to October 2, 1943, during which
period there were removed 506,343 cubic yards, bin measurement, of
material, at a cost of $136,402.17, for maintenance.
   The U. S. seagoing hopper dredge Atlantic was engaged in main-
tenance dredging to remove shoals in the Hog Island Channel and the
canal land cut during the period January 3 to 31, 1944, during which
40      REPORT OF CHIEF OF ENGINEERS,         U. S. ARMY,    1944

period there were removed 150,410 cubic yards, bin measurement, of
material, at a cost of $45,981.87 for maintenance.
   An adjustment was made in the final costs of maintenance dredging
by the U. S. seagoing hopper dredge Atlantio, performed during the
prior fiscal year, at a cost of minus $399.01 for maintenance.
   Drilling and blasting of submerged boulders was carried on at
intervals during the year, a total of 278 cubic yards of such boulders
having been drilled and blasted at a cost of $12,434.72 for maintenance.
   Under a contract for constructing a road and grading slopes and
placing revetment, on the easterly side of Stony Point Dike, stations
577 to 588, work was started September 25 and completed November
4, 1943, at a cost of $28,042.66, for maintenance.
   Preliminary surveys in connection with maintenance dredging on
the easterly side of Hog Island Channel were made during the year
at a cost of $139.29 for maintenance.
   An adjustment was made in the final costs of work in connection
with repairs to the north and south slopes, service roads, and revet-
ment, eroded as the result of a wreck in the canal, at a cost of $1,866.48
for maintenance.
   Operating and care of canal.-The canal was open to navigation
and the railroad bridge operated throughout the year. The costs
during the fiscal year for operating and care were $221,160.65 for
maintenance.
   The total costs during the fiscal year were $445,628.83, all of which
was for maintenance. The total expenditures were $441,945.79.
   Conditionat end of fiscal year.-The existing project is substantially
completed. The canal is crossed by two high-level highway bridges
and a vertical-lift railroad bridge. The canal in the land cut from
the easterly entrance to station 430 has a least bottom width of 480
feet, except opposite the State pier where the width is 450 feet. From
station 430 to Wings Neck (Hog Island Channel) the width is 500
feet, and beyond Wings Neck (Cleveland Ledge Channel), 700 feet.
On June 30, 1944, the controlling depths at mean low water for this
project were: Canal inthe land cut, 26.8 feet; mooring basin, north
side, easterly end, 13.7 feet; Hog Island Channel, 29.5 feet; Cleveland
Ledge Channel, 29.8 feet. On June 30, 1944, the mooring basin on
the south side, westerly end, had depths varying from 22 to 36.3
feet. At the time it was last surveyed (1943) the controlling depth
in the Onset Channel was 16.2 feet.
   The total costs from regular funds have been $26.275,186.34, of which
$20,437,653.42 (including the purchase price of $11,500,000) was for
new work and $5,837,532.92 was for maintenance, including $1,944,-
181.11 for operating and care of the canal. The total expenditures
have been $26,263,365.57.
   The total costs and expenditures from Public Works funds have been
$6,138,157.30 for new work.
   The total costs and expenditures from Emergency Relief appro-
priation funds have been $4,849,739.57 for new work.
   The total costs, all funds, have been $38,921,437.92, of which $31,-
425,550.29 (including the purchase price of $11,500,000) was for new
work and $7,495,887.63 was for maintenance. The total expenditures
have been $37,251,262.44. In addition, the sum of $1,658,354.71 was
expended between March 31, 1928, and June 30, 1935, on the operating
                  RIVERS AND HARBORS-BOSTON,                                       MASS., DISTRICT                                     41
and care of the works of improvement, under the piovision of the
permanent indefinite appropriation for such purposes.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, including accounts receivable, amounting to $105,157.31,
together with $388,000 allotted in July 1944, will be applied as follows:
Accounts payable June 30, 1944 ---------                                       -----------------                        $11, 820.77

Maintenance:
    Dredging by U. S. seagoing hopper dredge Atlantic (July 1-Aug.
      15, 1944; Jan. 1-Feb. 15, 1945; June 1-30, 1945)                                      ----------                  176, 015.16
    Dredging by contract in Hog Island Channel, stations 468 to 497_                                                     81,860. 71
   Removal of miscellaneous boulders, by hired labor (July 1, 1944
      to June 30, 1945)      ---          --------           -----                                                            6, 731.00

Operation and care of canal:
   Operation of canal, bridges, etc_---
                                     _-------111,                                                                                499. 83
    Ordinary maintenance and repair_.--           --------                                                                   78,092.38
   Channel work        ----------------------------------------                                                              27, 137. 46

           Total operation and care---       ---------              -216, 729. 67
           Total maintenance        ----------------------------------481, 336. 54

           Grand total_                 -              -           -           -              -          -               493, 157. 31
  The funds that can be profitably expended during the fiscal year
1946, $440,000, will be applied as follows:
Maintenance:
   Dredging by United States seagoing hopper dredge, 4 months___ $175, 000
    Removal of miscellaneous boulders, by hired labor (July 1, 1945,
      to June 30, 1946) ----------------------------------------     5,000
           Total maintenance                   -------------------------------------                                           180, 000

Operation and care of canal:
   Operation of canal, bridges, etc-               -     --         -                             -     -          -           125, 000
    Ordinary maintenance and repair---                       ----------                                                         90, 000
    Channel work     -------------------------------------------                                                                45,000
           Total operating and care-                    -    -     -------                                             __-260,000

           Grand total           ------------------------------------------                                                    440, 000
                                        Cost and financial summary
Cost of new work to June 30, 1944----____-
                                         -......  _ ......   $31,425,550.29
Cost of maintenance to June 30, 1944       --------------------7, 495, 887.63
      Total cost of permanent work to June 30, 1944 ----                                                 -         38, 921, 437.92
Minus accounts payable June 30, 1944---------------                                                                     11 820.77
     Net total expenditures....------------------38,                                                                    909, 617. 15
Unexpended balance June 30, 1944_         ..----------------------                                                      105, 157.31

           Total amount appropriated to June 30, 1944------------                                                  39, 014, 774.46

    Fiscal year endling June 30                 1940              1941               1942                   1943                1944

                    -
Cost of new work .....           .... $1, 046. 020.59        $151,817.00           $25,645.14         -$11,489.06        .       _
Cost of maintenance......------------         676,635.84      452, 022.49          338, 228.31         599, 016.20            $445,628.83
       Total cost.-................
                                1,722,656.43                  603, 839.49          363,873.45          587, 527.14             445,628.83
Total expended..........                    1,847, 844. 87    632, 576. 36         489, 461.34         477, 812. 26            441,945.79
Allotted                     655, 022.10
             ....................                                80, 000. 00       273, 850. 00        632, 000. 00            169, 460. 28
42          REPORT OF CHIEF OF ENGINEERS, U.                                S. ARMY,            1944

Balance unexpended July 1, 1943____.        ._  ___.___ .                                           $377, 642. 82
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941 ----------- $65, 198.24
Amount allotted from First Deficiency Appropria-
  tion Act approved Apr. 1, 1941-   - -----       104, 262.04
                                                                                                     169, 460. 28

      Amount to be accounted for__                 -    -                                            547, 103. 10
Gross amount expended ----------------------           $451, 082.82
    Less reimbursements collected. -.      $9, 128. 60
    Less receipts from sales --------------      8. 43
                                                          9, 137.03
                                                                                                     441.    945. 79
                                                                                                      - - -, . i .. . .


      Balance unexpended June 30, 1944_-.........                                    _               105, 157.31
Outstanding liabilities June 30, 1944-..... --                         -------                        11, 820. 77

     Balance available June 30, 1944                                                        -         93, 336. 54
Amount allotted in July 1944_                                                                   -    388, 000. 00
         Amount available during fiscal year 1945_                                                   481, 336. 54

Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance _---                                                                  440, 000. 00
     Exclusive of available funds.

      8. EXAMINATIONS, SURVEYS AND CONTINGENCIES                                          (GENERAL)

   The cost of work during the fiscal year amounted to $22,235.37, of
which $22,070.57 was for maintenance and $164.80 was undistributed
costs. The expenditures were '$16,624.04. The balance unexpended
June 30, 1944, amounting to $29,469.54, including accounts receivable,
minus accounts payable of $1,155.48, a balance of $28,314.06, plus
$28,000 allotted in July 1944, will be applied as needed during the
fiscal year 1945 to payment of expenses incurred under this heading.
The additional sum of $30,000 can be profitably expended during the
fiscal year 1946.
                                     Cost and financial summary
Cost of maintenance to June 30, 1944_____     ___
Cost of maintenance to June 30, 1944 _.....$854,                                                            825. 17

      Total cost of permanent work to June 30, 1944__ -------     854, 825.17
Undistributed costs June 30, 1944 -------------------------------      164.80
     Net total cost to June 30, 1944--------------------------854, 989.
Minus accounts payable June 30, 1944_---------------             1, 155. 48

      Net total expenditures --------------------------------                                        853, 834.49
Unexpended balance June 30, 1944___--    --     ---      --                                           29, 469.54
          Total amount appropriated to June 30, 1944_.---- .......-                                  883, 304.03


     Fiscal year ending June 30         1940              1941           1942            1943               1944
Cost of new work .....  . .- . . . .I                   .    .
Cost of maintenance-..-........ $139,175.72             $49, 356.87    $30, 463.66   $18, 781.23           $22,070.57
Total expended..._.___   .---   _-     143,520.05   :    49, 706. 63    32, 536.57    21,084.94.            16,424.04

Allotted..---------------------101,000.00                28,!544.36--46,000.00                            -20, 000.0
                        RIVERS            AND          HARBORS-BOSTON,                              MASS.,           DISTRICT                            43

Balance unexpended July 1, 1943                                   $66, 093.58
Deductions on account of revocation of allotment ---------------- 20, 000.00

      Net amount to be accounted for-      -- ---------                                                                                     46,093.58
Gross amount expended ------------------------- $20,438. 81
Less reimbursements collected--    ---------            3,814. 77
                                                                                                                                            16, 624. 04

      Balance unexpended June 30, 1944_-       ---     --   ----                                                                            29, 469.54
Outstanding liabilities June 30, 1944 ----------------------------                                                                           1,155.48
    Balance available June 30, 1944 ------------------------                                                                                28, 314. 06
Amount-allotted in July 1944---------------   -----------------                                                                             28,000.00
    Amount available during fiscal year 1945------------------                                                                              56, 314. 06

Amount that can be profitably expended in fiscal year ending June 30,
1946 for maintenance 1 _      - -- - -- - -- -- - - -- - -- - -- -- - - -- -
                                                                                                                                            30, 000.00
       2 Exclusive of available funds.


9. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                       SUBMITTED

                                                                                For last    Cost and expenditures
                                                                              full report       to June 30, 1944                              Estimated
                           Name of project                                    see Annual Reportquired                                                re-
                                                                                                                                              amount to
                                                                                  for-
                                                                                     ort
                                                                                  foRep-  New
                                                                                          New work           nac
                                                                                                           Mainte-                             complete
                                                                                                            nance


1.    Passamaquoddy tidal-power - -          project, Maine       - -      -             1935    $6, 384,160. 89 ------------                (1).
2.    St. Croix River, Maine 2 .........                                                 1924      3 180, 549. 81          $6, 450.19        Completed.
3.    Cobscook Bay, Maine 4-2 _ ___________.--1866                                                     4,173. 51--.-....                          Do.
4.    Lubec Channel, Maine            ......             .........                       1912        303, 365. 53            4,067.45             Do.
5.    Machias River, Maine 4 .- .-----.--------                                          1877         32, 000.00      ---.-.-....-                Do.
6.    Moosabec Bar, Maine 4--              .---.-.--...--.--                             1930        114,000.00            12, 600.00             Do.
7.    Pleasant River, Maine 46.              _..............                             1892          3, 500.00 ..............                   Do.
8.    Narraguagus River, Maine
                             2           4          ..............                        1907         71,643.81--..............                   Do.
9.    Corea Harbor, Maine         ____            __________
                                                           ..                             1939         31, 707.06 ..............                   Do.
10.    Sullivan Falls Harbor, Maine 45 ---------                                          1914         54, 870.64 ..............                   Do.
11.    Bar Harbor, Maine 2 .-                         -                -                  1932        406, 591.12 --         --          -$57,900.
12.    Bass Harbor Bar, Maine 4 -               -------  ____                      _.     1920          4, 076.13             3, 418. 20 Completed.
13.    Union Riter, Maine 2 6 -                    -                  -                   1912        176, 854.85           14, 095.15             Do.
14.    Deer Island Thoroughfare, Maine............                                        1916         40,000.00--.............                    Do.
15.    Bagaduce River, Maine 2 4 -._ ..----.                                    _         1912         28,000.00    -------------            $18,875.
16.    Penobscot River, Maine- .--...---.......                                           1942        501,020. 53           52,128.15         Completed.
17.    Bucksport Harbor, Maine -------------------                                        1907         18,420.99                   279.01          Do.
18..   Stockton Harbor, Maine 2 4 5-                __....                      .         1915         33,000.00----------
                                                                                                                         ............              Do.
19.
20.
       Carvers Harbor, Maine4__---- ...------.--
       Matinicus Harbor, Maine 4-................
                                                                                          1915
                                                                                          1935
                                                                                                       59,199.70 ...
                                                                                                       14, 000.00
                                                                                                                      -..........
                                                                                                                              7, 704.64
                                                                                                                                                   Do.
                                                                                                                                                   Do.
21.    Criehaven Harbor, Maine4- .......-........                                         1939         40, 775.99             7,956.28             Do.
22.    Belfast Harbor, Maine 2_.....................
                                     - - - - - - - - - - - - - - - - - - - 1897                                        ----
                                                                                                       61,561.46 ..............                    Do.
23.    Camden Harbor, Maine 2                                                             1931        102, 400.00           30,200.00              Do.
24.    Rockport Harbor, Maine 46 _._._.-                                 .-.              1915         47, 000.00 ..............                   Do.
25.    Rockland Harbor, Maine 2------                        --         --                1931        915,862. 73            24,637. 27            Do.
26.    OwlH         arbor, ,ie          2 4-                 -         -        -     -___1855         17,897.16-------------
                                                                                                                    .............-                 Do.
27.    Tenants Harbor, Maine  2 - 4_....................
                                         -                                                1920         18, 750.00    ..............                Do.
28.    Georges River, Maine       .................                                       1935         25, 787.91           39, 566. 38            Do.
29.    Medomak River, Maine2       4 6-             -                                     1914         17,000.00     ..............                Do.
30.    New Harbor, Maine ........................                                         1937         10, 500.00            12, 566. 27           Do.
31.    Damariscotta River, Maine 4 6-                       -         -        -      - 1906            5, 000. 00 .............                   Do.
32.    South Bristol Harbor, Maine 2 4 6 .1914                                                          3, 500.00- ..--..........                  Do.
33.    East Boothbay Harbor, Maine 4..............                                        1912          6, 500.00 .............                    Do.
34.    Boothbay Harbor, Maine 26 .................         -                 - -          1915                        .............-
                                                                                                       18,000.00-------------                      Do.
35.    Richmond Harbor, Maine 4                    _......         ....                   1883                      ..............
                                                                                                       20,000.00--------------            -        Do.
36.    Sasanoa River, Maine 5---------------------                                        1915         92,487.69-------------
                                                                                                                     .............-                Do.
87.    Cathance River, Maine            -...................                              1884         21,000.00                                   D.--------------
                                                                                                                                                   Do.
38.    Harraseeket River, Maine 46...............                                         1896         30, 963. 62 ..----------.--                 Do.
39.    Royal River, Maine 2 45           ............                             .       1884         21,919.03               8,080.97            Do.
40.    Richmond's Island Harbor, Maine 4 ..... _.                                         1882        119, 844.22 ........                         Do.
41.    Saco River, Maine 2 4 ...............                                     .        1942        531, 715.89          131,309.92          $22,500.
42.    Cape Porpoise Harbor, Maine 4 _                   5                    -_-...      1911        118,501.15     -------------..          Completed.
43.    Kennebunk River, Maine 2_ ............                                  ..         1942         83, 584.01            73, 039.05            Do.
44.    Wells Harbor, Maine 4 6d                                                              45, ---------------
                                                                                           871874                                  000.00          Do.
45.    York Harbor, Maine 2- ...................-
                                       s     -----                                        1936         57, 400.00              5, 660.83           Do.
46.    Portsmouth Harbor, N. H. -----------------................                         1892        130, 392.61            ..........            Do.
47.    Pepperells Cove, Maine 4.............                                ..            1920        158, 262. 28                 137. 72         Do.
                               4
48.    Cocheco River, N. H. 5..                         -.      ..                     -1913          289, 149.93              9, 642. 54          Do.
49.    Bellamy River, N. H.' 5 ..---.                                                     1897         34, 642. 98 ..............                  Do.
50.    Lamprey River, N. H.4 6.....................                                       1913         19, 980. 58             8, 267. 53          Do.
       See footnotes at end of table.
44            REPORT OF CHIEF OF ENGINEERS,                                        U.   S. ARMY,          1944

9.       OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                         SUBMITTED-Continued


                                                                   For last   Cost and expenditures
                                                                 full report      to June 30, 1944               Estimated
                     Name of project                             see Annual Reportquired                                 re-
                                                                                                                 amount to
                                                                    Report                    Mrk
                                                                                                ainte-            complete
                                                                     for-    New work          nanco


                              4
51. Exeter River, N. H. 46__...........                                1913        $62, 454. 42 --------------    Do.
52. Little Harbor, N. H. 8-                 -             -            1909        133, 227.33    $3,121.74       Do.
53. Isles of Shoals Harbor, Maine -and          N.   H......
                                          -- ---_ - -- -- -- -- - 1942 1930         80, 691.53    34, 261.68      Do.
54. Newburyport Harbor, Mass.                                                      463, 843. 62  290, 435.63   $10,000.
55. Merrimack River, Mass.......   -------------------
                                       4                               1940        369, 891.49   147, 860.42 Completed.
56. Lake Winnepesaukee,2 N. H. 8 .............                         1930          7, 500.00     5,000.00       Do.
57. Ipswich River, Mass.      5.___-
                        4- - - - - - - - - - - - - - - - - - - - - - - 1895
                                                -    ____.
                                                        -      --                    5, 617.91 ..............Do.
58. Essex River, Mass.                   4                       .     1912         21, 759. 21  108, 240. 79     Do.
59. Sandy Bay, Cape Ann, Mass.
60. Rockport Harbor, Mass.2-- --------
                                             11-    .1922
                                                      -       -     -.
                                                                       1905
                                                                                 1,925, 552.30    15, 925.70
                                                                                    91, 229.25 .- -.       -..
                                                                                                                  Do.
                                                                                                                  Do.
61. Gloucester
             1   Harbor and Annisquam River,                           1942        556,154. 73   108, 150.16      Do.
      Mass. '
62. Manchester Harbor, Mass.s-----                 ___              - 1908          23, 985. 57---.-             - (14).
63. Beverly Harbor, Mass..------------------1931
                               -- -- -- -- -- -- -- -- - -- -- 1931             15246,047. 76              642.65 Completed.
64. Salem Harbor, Mass.e                                                           100, 456.57          7, 500.00       Do.
65. Marblehead Harbor, Mass 17 -                       -__             1905-   - --     - --               584.00       Do.
66. Lynn Harbor, Mass.' 18-4 -. ..- - ..... - 1941                                 755, 042.91       100, 292. 70 $336,000.
67. Winthrop Harbor, Mass. 19     -5- - - - - - - - - - - - -          1895          8, 992.59 ---        .--      Completed.
68. Malden River, Mass. __                                             1922     20104,853.08          45,096.92         Do.
69. Dorchester Bay and Neponset River, Mass.'_                         1932         94, 584. 55       33, 591.89 $162,000.
70. Town River, Mass.'_   ................                             1941     " 285, 779. 76        12, 577.41 Completed.
71. Hingham Harbor, Mass ......-.......                      .... 1913              28, 316.58        10,000.00         Do.
72. Cohasset Harbor, Mass." ....-................                      1904         10,000.00 --....  --.          (14)
73. Scituate Harbor, Mass.' - _-_ ___- _- ___-_ ___ _                  1941        274, 886. 96       38, 930.98 Completed.
74. Duxbury Harbor, Mass.24..........
75. Kingston Harbor, Mass. (North Plymouth
                                                                       1908         37,000.00   -------------      $5,800.
                                                                       1895          8,940.09 -----                Completed.
                                                                                                                 -..
      Harbor).                    18
76. Plymouth Harbor, Mass. 4- - -- -- -- -- -- -- -- - 1942                     25377, 217. 75 28135, 664. 35    $190,000. 27
77. Wareham Harbor, Mass...                                            1896        95,997.30 -------------       $36,750.
                                8       - -
78. Wellfleet Harbor, Mass.s' ............. ..
79. Provincetown Harbor, Mass.'----------------...          ..... 1941
                                                                       1895        11,350.37 .
                                                                                  347, 453.72
                                                                                                        -
                                                                                                  42,128.73
                                                                                                                 $22,000.
                                                                                                                 $13,300.

     1Work discontinued 1937. Facilities transferred to the Works Progress Administration.
     Improvement adequate for commerce.
     2
     2 Exclusiveof $19,891.65 contributed by Canadian Government.
   4 No commerce reported.
   5 Abandonment recommended in H. Doc. No. 467, 69th Cong., 1st sess.
   eReported by the district engineer as unworthy of further improvement.
   7 Exclusive of $20,000 expended from contributed funds.
    SElimination of maintenance dredging recommended in H. Doc. No. 467, 69th Cong., 1st sess.
     Modification of existing project was recommended by the Chief of Engineers Apr. 10, 1940, in H. Doe.
No. 703, 76th Cong., 3d sess.
   90 Exclusive of $5,000 contributed by Commonwealth of Massachusetts in 1908.
    11Abandonment recommended in H. Doc. No. 411, 64th Cong., 1st sess. and in R. & H. Comm. Doe.
No. 3, 65th Cong., 1st sess.
   12 Modification of existing project was recommended by the Chief of Engineers Apr. 25, 1941, in H. Doe.
No. 329, 77th Cong., 1st sess.
   13Modification of existing project was recommended by the Chief of Engineers July 16, 1941, in H. Doe.
No. 447, 77th Cong., 1st sess.
   14Superseded by State project.
   15Exclusive of $100.000 expended from contributed funds.
   16 Modification of existing project was recommended by the Chief of Engineers Apr. 10, 1940, in H. Doe.
No. 701, 76th Cong., 3d sess.
   17Further improvement recommended by the Chief of Engineers Nov. 18, 1940, in H. Doc. No. 85, 77th
Cong., 1st sess.
      Awaiting local cooperation.
    s18
   10Under State maintenance.
   20 Exclusive of $62,000 expended from contributed funds.
   s31Modification of existing project was recommended by the Chief of Engineers June 19, 1941, in H. Doe.
No. 394, 77th Cong., 1st sess.
      In addition, $111,762.76 contributed funds expended for new work. Balance of $25,157.24 from con-
    s22
tributed funds, revoked fiscal year 1944.
   s2Modification of existing project was recommended by the Chief of Engineers July 5, 1939, in H. Doe.
No. 425, 76th Cong., 1st sess.
   24Modification of existing project was recommended by the Chief of Engineers June 20, 1941, in S. Doe.
No. 115, 77th Cong., 1st sess.
   28Exclusive of $108,000 expended from contributed funds.
   26 Exclusive of $400 expended from contributed funds.
   s7In addition, local interests are required to contribute $95,000.
   28 Modification of existing project was recommended by the Chief of Engineers Dec. 11, 1939, in H. Doe.
No. 557, 76th Cong., 3d sess.
                    RIVERS AND HARBORS-BOSTON,                                                    MASS., DISTRICT                         45
                     10. PLANT ALLOTMENT, BOSTON, MASS., DISTRICT
                                                           Cost and financial summary

Undistributed costs June 30, 1944----------                                                 ------------------ $279, 407.24

Net total cost to June 30, 1944    -------------------------------279, 407.24
Plus accounts receivable June 30, 1944 ------------------------ 120,153.35

      Gross total costs to June 30, 1944 ----------------------- 399, 560. 59
Minus accounts payable June 30, 1944--------------    ---------   30, 516.29

     Net total expenditures  ------------------------------- 369,044.30
Unexpended balance June 30, 1944 --------------------------- 249, 303.35
           Total amount appropriated to June 30, 1944------------- -618,                                                          347.65


    Fiscal year ending June 30                                    1940           1941              1942             1943          1944


Total expended ..... ----------------                        $90, 068.54     -$33, 865.07     $320, 569.80 -$546, 062.49        $183, 526.48

Allotted      ...................----------------------.   l.1             3..------------ 3, 355.96
                                                                 82, 977.90-------------
                                                                            .............    --              ...     ..     -         .


Balance unexpended July 1, 1943   .........                            $432, 829. 8&
Gross amount expended ------------------------ $1, 231, 208.52
Less:
    Reimbursements collected------ $1, 039, 787. 54
    Receipts from sales-------------        7, 894. 50
                                                       1, 047, 682. 04
                                                                        183, 526. 4&

      Balance unexpended June 30, 1944----------------------249,303.35
Outstanding liabilities June 30, 1944--------------- $30, 516. 29
Amount covered by uncompleted contracts ------------ 2, 701.96
                                                                  33, 218. 25

     Balance available June 30, 1944 ------------------------ 216, 085. 1a
Accounts receivable June 30, 1944 -------------------------- 120,153.35

           Unobligated balance available June 30, 1944 ..--------------                                                     336, 238.45

  Status of all investigationsfor navigation called for by river and harboracts and
                                 committee resolutions

                                                                                   Date trans-
            Locality                                 Authorization act              mitted to         Document No.          Recommenda-
                                                                                    Congress                                    tion

Belfast Harbor, Maine-......                     Commerce Commit-                 Nov. 30, 1943 ------.-                    Unfavorable.
                                                  tee resolution, Dec.
                                                    8, 1941.
Boston Harbor, Mass., to                         Rivers and Harbors               Oct. 11, 1943      (Restricted)-.......   Favorable.
modify the existing proj-                         Committee resolu-
  ect. -                                            tion, Dec. 10, 1941.
    Do ............---                           Rivers and Ijarbors Feb. 24,1944                    H. 472, 78th Cong.,        Do.
                                                   Committee resolu-                                  2d sess.
                                                  tion, Apr. 2 1943.
Boston Harbor, Mass., ex-                        Rivers and Harbors ....   .-....                           -....
pansion of the existing                           Committee resolu-
President Roads anchor-                          tion, Sept. 5, 1944.
age area.
Camden Harbor, Maine-.....                       Rivers and Harbors.........-....................
                                                   Committee resolu-
                                                  tion, June 15, 1943.
46           REPORT OF CHIEF OF ENGINEERS,                                           U.    S. ARMY,         1944

  Status of all investigations for navigation called for by river and harbor acts and
                           committee resolutions-Continued

                                                                        Date trans.,                             Reeommenda-
            Locality                  Authorization act                  mitted to          Document No.         Recommendn -
                                                                         Congress

Cape Cod, Mass., beach              River and Harbor Act, Aug. 14, 1943------. ------.                           Unfavorable.
erosion study.                       July 3, 1930; act of
                                      Congress, June 26,
                                      1936.
Cape Porpoise          Harbor,      Rivers and Harbors Nov. 19,1943        __        ..                               Do.
Maine.                               Committee resolu-
                                      tion, Mar. 11, 1941.
Danvers River, Mass ......          Rivers and Harbors     --
                                      Committee resolu-
                                      tion, Apr. 13, 1939.
Lynn Harbor, Mass-........          Rivers and Harbors-
                                      Committee resolu-
                                      tion, Feb. 8, 1944.
Merrimack River, Mass.,             River and Harbor Act,
and N. H., with view to              June 20, 1938.
improvement for naviga-
tion, flood control and
water power.
Portland Harbor, Maine,    Rivers and Harbors                                 ----
modify existing project.    Committee resolu-
                             tion, June 6, 1939.
Presumpscot River, Maine.. River and Harbor Act,-.
                             Aug. 26, 1937.



                     11. MERRIMACK RIVER BASIN, N. H. AND MASS.

  Location.-The works covered by the comprehensive plan are located
on the Merrimack River and its tributaries in New Hampshire and
Massachusetts.
  Existing project.-The Flood Control Act approved June 22, 1936,
authorized the construction of a system of flood-control reservoirs in
the Merrimack River Basin for the reduction of flood heights in the
Merrimack Valley generally at an estimated construction cost of $7,-
725,000; cost of lands and damages, $3,500,000. The Flood Control
Act approved June 28, 1938, approved the general comprehensive plan
for flood control and other purposes as set forth in House Document
No. 689, Seventy-fifth Congress, third session, wherein the estimated
cost of $13,000,000 for construction and $8,000,000 for lands and dam-
ages is given, and modifiqd the project authorized by the Flood Control
Act approved June 22, 1936, to provide, in addition to the construction
of a system of flood-control reservoirs, related flood-control works
which may be found justified by the Chief of Engineers.
   The following reservoirs and related flood-control works have been
considered for the comprehensive plan:
                                                         Reservoirs


                           Name                                                           State                            e sti-
                                                                                                                    mTotal cost
                                                                                                                    mated

Franklin Falls 2-                 ---------............                ..        New Hampshire...--------------------$7, 883, 000
Blackwater 2- -...- - - - - - - - - - - - - - - - - - - - - - - ----- -do-              - ---------               ----       193, 000
                                                                                                                          1, 750, 000
Beards Brook   ...................                                - - -  - - - -- - -- do-----------------------------
                                                                                       do.....---------------------------4, 205, 000
           3      - - - - - - - - - - - - -  -  -  - -  - - - - -
Bennington - ..................                                         ....
West Peterboro------ ----------------...........                        --------...- do...-----------------------------1,170,000
Mountain Brook......-----------------------...............       ---. ----....         do----------- -       ----            370,000

  1 Includes cost of lands and damages.
  S Details of this project are contained in an individual report.
  ' These projects have been substituted for the Hopkinton-Everett Reservoir.
                    FLOOD CONTROL--BOSTON,                      MASS.,        DISTRICT                         47
                                        Local protection projects
                                                                                  Estimated cost
                             Location
                                                                     Construc-     Lands and           Total
                                                                       tion         damages


Nashua, N. H-_..........------........__               _._......       $234,500          $2, 500        $237, 000
Jbwe4 ,MassI ............... .......... _....            ......         490,600          90,000          580,600
Wiorth Andover and Lawrence, Mass          ____        _-_    _         665,000          19, 000         684, 000

  I Details of this project are contained in an individual report.

   Local cooperation.-See page 7 for requirements.
   Operationsand results during fiscal year.-Investigations and stud-
ies were made in the further development of the comprehensive plan
for flood control. Planning for reservoir operation and the stream-
gaging program were continued.
   The costs from regular funds during the fiscal year were $38,500.77.
The expenditures were $35,316.02.
   Condition at end of fiscal year.-Work on the development of the
originally authorized comprehensive plan preliminary to construction
has been carried to an advanced stage and studies have been made for
related alternate flood-control works in the comprehensive plan. The
condition of projects for which construction has been undertaken
is given in individual reports, as noted in the preceding tabulations.
   The costs to date from regular funds have been $324,289.19. The
expenditures to date from regular funds have been $321,104.44.
   The total costs and expenditures to date from emergency relief
funds have been $23,716.07.
   The costs of all work, all funds, have been $348,005.26. The total
expenditures have been $344,820.51.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $152,348.06, including accounts receivable,
plus additional allotments totaling $99,740 during July and Septem-
ber 1944, will be applied to accounts payable, June 30, 1944, $3,205.45,
and to hydraulic and hydrology studies of the tributary watersheds
of the Merrimack River; storm studies for the development of the
flood-control program and reservoir operation planning; and to
foundation explorations, surveys, and design studies for reservoirs in
the comprehensive plan. Stream-gaging will be continued under the
cooperative program with the United States Geological Survey.
   The sum of $107,200 can be profitably expended during the fiscal
year 1946 for the continuation of the studies and surveys, reservoir
operation planning and the stream-gaging program.
                         Cost and financial summary
Cost of new work to June 30, 1944 __..........-                                              1 $348, 005. 26
Cost of maintenance to June 30, 1944 .....
       Total cost of permanent work to June 30, 1944---------- 1 348, 005. 26
Plus accounts receivable June 30, 1944----------------------------     20. 70
       Gross total costs to June 30, 1944----------------------                                    348, 025. 96
Mintus accounts payable June 30, 1944                   ___3,                                           205. 45
      Net total expenditures                                                                  1 344, 820. 51
Unexpended balance June 30, 1944_                                                                  152, 327. 36
         Total amount appropriated to June 30, 1944-------                                         497, 147. 87
  1Includes $23,716.07   emergency relief funds.
48               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                      1944


     Fiscal year ending June 30                        1940            1941           19-2               1943             1944

Cost of new work.....-..........                  $123, 145. 47 -$76,496. 57        $2, 006.97        $15, 306. 21    $38, 500. 77
Cost of maintenance., ..--                         ____         ---------.----. --------------.                      I ------
                                                                                          .....--- ---------------------

Total expended....----------------.............     75,897.44      -81, 682. 01         729. 53         16, 666. 26       35, 316.02
Allotted ...........              .........        223,131.80                             -
                                                                  -147, 500. 00 ..............         -6, 200. 00        -3,000. 00


Balance unexpended July 1, 1943__ _                                                                              $190,x&38
Deductions on account of revocation of allotment--                                           ------                 3, 000. 00

       Net amount to be accounted for_                    187, 643. 38
Gross amount expended------------------------------------35, 316. 02
      Balance unexpended June 30, 1944--- --                -                                                         152, 327. 36
Outstanding liabilities June 30, 1944             $3, 205. 45
Amount covered by uncompleted contracts---------- 29, 308. 45
                                                                                                                       32, 513. 90
      Balance available June 30, 1944------------------------119, 813. 46
Accounts receivable June 30, 1944_-   -                            20. 70

     Unobligated balance available June 30, 1944-------------119, 834. 16
Amount allotted in July and September 1944------------------   99, 740. 00

Amount available during fiscal year 1945                                                __                            219, 574. 16

Amount (estimated) required _to be appropriated for completion of
    existing project a___                          -            __--------                    ------            9, 394, 500. 00

Amount that can be profitably expended in fiscal year ending June
30, 1946, for new worka_s__
                          -        ___----__          -
                                                   ______-- --                                                        107, 200. 00
   $Exclusive of available funds.

12. FRANKLIN FALLS RESERVOIR, MERRIMACK RIVER BASIN, N. H.

Location.-The dam site of the reservoir is located on the Pemige-
wasset River, the main tributary of the Merrimack River, about 21
miles above Franklin, N. H., and 92 miles north of Boston, Mass.
  Existing project.-The dam is of rolled earth fill with dumped rock
shell and toe, 1,740 feetlong, with a maximum height of 136 feet. It
contains about 3,000,000 cubic yards of earth and rock fill. The spill-
way consists of a channel in an earth and rock cut in the right abutment
with a gravity-type concrete ogee section 550 feet long. Twin gate-
controlled outlet conduits are located in the right abutment. The
reservoir provides a storage capacity of 170,000 acre-feet and controls
a drainage area of 1,000 square miles.                                            The total estimated cost is
$7,883,000, which includes construction, lands, damages, and highway
relocations. The project is a unit of the comprehensive plan for flood
control and other purposes in the Merrimack River Basin which was
authorized by the Flood Control Act approved June 22, 1936, and
modified by the Flood Control Act approved June 28, 1938.
  Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
                FLOOD CONTROL-BOSTON,                       MASS.,   DISTRICT               49

   Operations and results during flscal year.-Construction of the dam
and appurtenant works was commenced by continuing contract on
November 14, 1939. Contract operations during the fiscal year con-
sisted of repairing graded slopes damaged by melting snow and rain
during the winter and spring; repairing slopes to be seeded and fer-
tilized; and dressing up the rock slopes on the upstream and down-
stream embankments. Final inspection and acceptance was made
October 2, 1943.
   Plans for highway relocations were in progress and plans and speci-
fications for the operator's quarters and plans for an observation point
were completed.
   A total of 3,036.27 acres of land has been acquired in the reservoir
area, of which 256.51 acres were acquired during the fiscal year.
   Maintenance: The structure was maintained and operated in a serv-
iceable condition throughout the fiscal year.
   Reservoir operation: Operation of the reservoir during the year
effected reductions in six minor floods on the Pemigewassett River,
although general flood conditions did not require operation of the gates
to control the reservoir discharge.                                 g
   The total costs during the fiscal year, including contract operations,
land acquisition and relocations, were $200,098.19, of which $192,241.54
was for new work, $16,806.60 for maintenance, and -$8,949.95 undis-
tributed costs. The expenditures were $365,821.31.
   Conditionat end of fiscal year.-The existing project for the Frank-
lin Falls Reservoir is about 95 percent complete. Final plans and
specifications and the contract for the construction of the dam and
appurtenant works are complete; the relocation of power lines is about
90 percent complete; and the acquisition of land for the reservoir is
about 95 percent complete. Relocation of cemeteries is complete; and
a highway relocation survey is approximately 50 percent complete.
   The costs to date from regular funds have been $7,546,430.41, of
which $7,529,442.49 was for new work, $18,422.06 for maintenance,
and -$1,434.14 undistributed costs. The expenditures from regular
funds have been $7,543,073.98.
   Proposedoperations.-The balance unexpended, including accounts
receivable, at the end of the fiscal year, amounting to $169,173.17 reg-
ular funds, plus an additional allotment of $1,000 in July 1944, will be
applied as follows:
Accounts payable, June 30, 1944 ----------------------------   - -                   $3, 603. 58
New work:
    Acquisition of lands, rights-of-way (hired labor)_- $41, 241. 56
    Relocation of power lines and acquisition of town
      roads, bridges, and water supply:
         Contract-----------------------          --      2, 194. 73
         Hired labor- -------------                                   95, 600. 00
    Completion of clearing and grubbing (hired labor)_                     77. 04
    Demobilization (hired labor)-- ---        -----                    2, 044. 53
    Contingencies_- --      - - - - - - - _' -
                          - --                      -                  9,687.82
      Total, new work___-----------------------------150,                                845. 68
Maintenance and operation-----------------------------                               15, 723. 91
       Total----- ---------------------------------------                           170, 173. 17



      616634---45--pt. 1, vol. 1-      4
50             REPORT OF CHIEF OF ENGINEERS,                                             U. S. ARMY,                   1944

  The sum of $15,000 can be profitably expended during the fiscal
year 1946 for maintenance of the dam and appurtenant structures.
                                               Cost and financial summary
Cost of new work to June 30, 1944 ---------------------------                                                          $7, 529, 442. 49
Cost of maintenance to June 30, 1944--------------------18,                                                                     422. 06
      Total cost of permanent work to June 30, 1944 ......                                                              7, 547, 864. 55
Undistributed costs June 30, 1944---------------------------                                                               -- 1,434. 14
       Net total cost to June 30, 1944                                                                     --           7, 546, 430. 41
Plus accounts receivable June 30, 1944                                                              -247.                            15
      Gross total costs to June 30, 1944                                                                                7, 546, 677. 56
Minus accounts payable June 30, 1944-- -                                           ---              --                       3, 603. 58
      Net total expenditures.                                                                                           7, 543, 073. 98
Unexpended balance June 30, 1944                                 --                                                        168, 926. 02
            Total amount appropriated to June 30, 1944------------7,                                                      712, 000. 00


    Fiscal year ending June 30                     1940               1941                 1942                 1943            1944


Cost of new work------------...  $1,068, 935. 23 $3,172, 411.78 $2,137, 860. 56    $797, 655.83                               $192,241.54
Cost
Cost of
     of maintenance_ _
        maintenance------------.             -------------- --------------
                                                                     ---     -----    1, 615.46
                                                                                      1654                                      16, 806. 60
                                                                                                                                1,8.0
      Total cost...........--------------      1, 068, 935. 23   3,172, 411. 78     2, 137, 860. 56        799, 271, 29       209,048. 14
Total expended................----------------    828, 061.81    2, 908, 124. 11    2, 267, 743. 65      1,017, 860. 72       365. 821.31
                                                                                                 00
Alloted____ __ ...--- ..-- ...-- .. 1,400, 000. 00                 575, 000.00           152,000.          300, 000.00


Balance unexpended July 1, 1943_--                                     -           -----------                          $534, 747. 33
Gross amount expended-_      ---------                                                     $397, 135. 60
Less:
     Reimbursements collected -----                                  $22, 380. 80
      Receipts from sales                                              8, 933. 49
                                                                                               31, 314. 29
                                                                                                                          365, 821. 31
      Balance unexpended June 30, 1944                                       -------------                                168, 926. 02
Outstanding liabilities June 30, 1944                                                         $3, 603. 58
Amount covered by uncompleted contracts--------                                              139, 204. 73
                                                                                                                          142, 808. 31

      Balance available June 30, 1944_----                                                     -    -_26,                      117. 71
Accounts receivable June 30, 1944_---------                                                                 ---                247. 15

     Unobligated balance available June 30, 1944-------------                                                              26, 364. 86
Amount allotted in July 1944 ---------------------------------                                                              1,000. 00
Amount available during fiscal year 1945_------         ---                                                               27, 364. 86
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1          ------------                                                                    15, 000. 00
  I Exclusive of available funds.
   13. BLACKWATER RESERVOIR, MERRIMACK RIVER BASIN, N. H.

  Location.-The dam site of the reservoir is located on the Black-
water River in New Hampshire, 8.2 miles above the confluence with
the Contoocook River and 118.8 miles above the mouth of the Merri-
             FLOOD CONTROL--BOSTON,        MASS.,   DISTRICT          51
mack. The reservoir lies within the towns of Webster and Salis-
bury in the county of Merrimack, the dam being situated just above
the village of Swetts Mills in Webster, 12.5 miles by highway north-
west of Concord, N. H.
    Existing project.-The dam is of the rolled-earth type, with a
dumped-rock toe and a dumped-rock blanket on the upstream face, 750
feet long at the top, with a m~ mum height of approximately 60
feet and a top width of about 39 feet containing about 239,000 cubic
yards of earth and rock fill. A gravity-type spillway, 240 feet long
55 square feet of gate-controlled and 22.5 square feet of ungated
outlet conduits, and a 16-foot diameter penstock intake, involving
24,300 cubic yards of concrete, have been constructed. The reservoir
will provide a storage capacity of 46,000 acre-feet and control a drain-
age area of 127.5 square miles. The estimated cost, revised in 1942,
is $1,193,000. The project is a unit of the comprehensive plan for
flood control and other purposes in the Merrimack River Basin which
was authorized by the Flood Control Act approved June 22, 1936,
and modified by the Flood Control Act approved June 28, 1938.
    Locat'cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operationsand results during fiscal year.-Construction of the dam,
dikes, and appurtenant works was commenced by contract on April 23,
1940, and all contract operations for construction of the dam were com-
pleted on November 22, 1941. The relocation of Smith's Corner Ceme-
tery and Steven's Yard Cemetery in the town of Salisbury, N. H., was
continued by contract.
    Maintenance: Maintenance operations consisted of constructing and
installing a log boom and subsequently removing the collected debris;
cutting brush and grass at the dam site; policing the reservoir area,
and periodic checking of the gates and gate-operating equipment.
    Reservoir operation: General flood conditions did not require opera-
tion of the gates to control the reservoir discharge, although reductions
were effected in several minor floods because of the comparatively small
outlet from the reservoir.
    A total of 2,724.60 acres of land has been acquired in the reservoir
area, of which 201.70 acres have been acquired during the fiscal year.
    The costs during the fiscal year have been $60,130.03, of which
 $57,325.43 was for new work and $2,804.60 was for maintenance. The
expenditures were $59,096.75.
    Condition at end of fiscal year.-Contract plans and specifications
are complete. The contract for the construction of the dam. dikes,
and appurtenant works is complete. The relocation of the cemetery
in the town of Webster is complete and in the town of Salisbury the
work on relocation of cemeteries is 78 percent complete. The acquisi-
tion of lands and rights-of-way for the dam site and reservoir area
is approximately 95 percent complete.
    The existing project is practically complete. The total costs for
new work have been $1,163,402.87 and $6,463.84 for maintenance.
The expenditures have been $1,167,414.56.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, including accounts receivable, amounting to $41,039.26
52           REPORT OF CHIEF OF ENGINEERS,                               U. S. ARMY,                       1944

regular funds, plus an additional allotment of $3,000 in July, will be
applied as follows:
Accounts payable, June 30, 1944------------ -------------                                                           $4, 405. 97
New work:
    Acquisition of lands and rights-of-way (hired labor)     $1, 400.                                      00
    Relocation of State highway (hired labor)-        -   .- 15, 385.                                      77
    Clearing of reservoir areas (hired labor) - - - -
    Relocation of cemeteries and power line (contract)....
                                                        -
                                                              6,000.
                                                             11, 471.
                                                                             --                            00
                                                                                                           25
      Total, new work -----------------               ---                      ------                               34, 257. 02
Msintenance and operation.......5------------------------5,                                                             376. 27
         Total....--------------------------------------------                                                      44, 039. 26
  The sum of $3,000 can be profitably expended during the fiscal year
1946 for maintenance of the dam and appurtenant structures.
                          Cost and financial summary
Cost of new work to June 30, 1944___--------------------                                              $1, 163, 402. 87
Cost of maintenance to June 30, 1944--.--.-----------.. __                                          --      6, 463. 84
       Total cost of permanent work to June 30, 1944--                                 --            -1,      169, 866. 71
Plus accounts receivable June 30, 1944_-                                                    --                        953. 82
                                                                                                             -1i, l-----------
      Gross total costs to June 30, 1944--                         ---------------                         1, 171, 820. 53
Minus accounts payable June 30, 1944-_ ---------------                                                          4, 405. 97
      Net total expenditures--- ---------------------------                                                1, 167,414. 56
Unexpended balance June 30, 1944    ---       -39,                                                                085. 44
         Total amount appropriated to June 30, 1944------------1,                                               206, 500. 00

   Fiscal year ending June 30          1940           1941                 1942                   1943                 1944

Cost of new work.-------------$151,444.44         $571, 670.08          $351,123.06              $31,839.86           $57,325. 43
Cost of maintenance------...........-....---.----.------                   1, 213. 10             2,446.14              2, 804. 6
     Total cost.---------------     151,444.44     571,
                                                      670.08             352,336.16              34,286.00                   03
                                                                                                                       60,130.
Total expended----------------116,914.82           547, 549.84           402, 322.04             41,531.11             59,096.75
Allotted..--------------------1,    300, 000.00   -175, 000.00            77,000.00               4,500.00-......


Balance unexpended July 1, 1943-      .---.----.----------..                                                  $98, 182. 19
Gross amount expended----- ----------------                                   $59, 190. 92
Less:
     Reimbursements collected- _------$88.                          17
     Receipts from sales_ ------------                           6. 00
                                                                                        94. 17
                                                                                                                59, 096. 75
       Balance unexpended June 30, 1944_-- -----.--                              ____--                         39, 085. 44
Outstanding liabilities June 30, 1944-------                                    4, 405. 97
Amount covered by uncompleted contracts-------                                 22, 594. 67
                                                                                                                27, 000. 64

      Balance available June 30, 1944 -----------------------                                                   12, 084. 80
Accounts receivable June 30, 1944 ---------------------------                                                    1, 953. 82
     Unobligated balance available June 30, 1944_-                                      -         ---           14, 038.62
Amount alloted in July 1944-----------------       -3,                                                              000. 00
Amount available during fiscal year 1945-_                       --.-                                           17, 038. 62
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1.-..--.---..---...-.............                                                       38, 000.   00
3Exclusive
         of available funds.
             FLOOD CONTROL---BOSTON,       MASS.,   DISTRICT         . 53

            14. LOWELL, MERRIMACK RIVER BASIN, MASS.

   Location.,-The project is located on the left (north) bank, 39 miles
above the mouth of the Merrimack River in the city of Lowell, Middle-
sex County, Mass. The site is 25 miles northwest of Boston, Mass.
  Existing project.-The project consists of about 5,100 linear feet of
earth dike, sheet piling, and concrete wall, which furnishes protection
to 930 acres of urban land in the Lakeview Avenue and Rosemont
sections of Lowell, Mass., and includes two pumping stations, on West
Street and Beaver Street, to carry the sanitary and storm-water flow
through the dikes during flood periods. The estimated cost of con-
struction is $490,600. The project is a unit of the comprehensive plan
for flood control and other purposes in the Merrimack River Basin
which was authorized by the Flood Control Act approved June 22,
1936, and modified by the Flood Control Act approved June 28, 1938.
Prior to the foregoing authorization, under provisions of the Emer-
gency Relief Appropriation Act, approved April 8, 1935, the sum of
$794,373.46 was expended for enlarging the available waterway at
various places to provide adequate channel capacity for flood dis-
charge. For further details, see page 77 of the Annual Report for
1940.
   Local oooperation--Section 3 of the Flood Control Act approved
June 22, 1936, applies. The city of Lowell; by resolution passed by
the city council and approved by the mayor on October 16, 1940, will
provide the necessary lands, rights-of-way, and sewer relocations in
accordance with the previously cited section 3 of the 1936 Flood Con-
trol Act.
   Operationsandresults during fisceal year.--Installation of the pump-
ing equipment and heating systems in West Street and Beaver Street
pumping stations was commenced by contract March 16,1943, and final
acceptance after satisfactory completion of tests was made on January
6, 1944.
   Construction of the 48-inch intercepting sewer along Lakeview
Avenue to the West Street pumping station, previously started as a
Work Projects Administration project sponsored by the city of
Lowell, in order to secure effective flood protection for the Lakeview
Avenue section of Lowell, was started by contract November 15, 1943,
and was completed February 1, 1944. The contract operations con-
sisted of installing 690 lineal feet of 48-inch concrete sewer pipe; con-
structing three brick manholes; plugging the Coburn and Fulton
Streets sewer outlets and connecting the sewers to the 48-inch inter-
ceptor.
   Minor repairs, adjustments and alterations were made to the pump-
ing stations and operating equipment by contract. Work was started
December 23, 1943, and was completed February 14,1944.
   The manual for the operation and maintenance of the local protection
work, being compiled by this office, is approximately 50 percent
complete.
   The costs from regular funds have been $20,425.96. The expendi-
tures were $112,105.
   Conditionat end of fisceal year.-Contract plans and specifications are
complete. The contracts for construction of the dikes and pumping
stations; for installation of the heating and pumping equipment; for
54            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                               1944

construction of the intercepting sewer; and for minor repairs are
complete.
   The costs to date from regular funds have been $489,427.83. The
expenditures were $489,411.35.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $1,188.65, will be applied as follows:
Accounts payable, June 30, 1944 -------------------------------- $16. 48
New work: Correction of minor deficiencies and stand-by costs prior to
transfer to city of Lowell (hired labor)----- .-----------        ..- 1, 172. 17

           Total ----------------------------------------------
                             _                            .                                                                  1, 188. 65
  No funds can be profitably expended during the fiscal year 1946 as
the project will be complete and maintenance of the project will be
the responsibility of local interests.
                                            Cost and financial summary
Cost of new work to June 30, 1944__-   _---------------                                                                $489, 427. 83
Cost of maintenance to June 30, 1944__
      Total cost of permanent work to June 30, 1944                                          ------------                 489, 427. 83
Minus accounts payable June 30, 1944_--.------.                                                   ---------.                 - 16. 48
      Net total expenditures_-------------------------------489, 411. 35
Unexpended balance June 30, 1944_ --- ________  -    _ _ --    1, 188. 65
           Total amount appropriated to June30, 1944                                      -----           ..-             490, 600. 00

    Fiscal year ending June 30                        1940            1941                 1942                1943            1944

Cost of new work  ---................    --                          $9, 234. 36     $349, 376.39       $110, 391.12          $20,425.96
Cost of maintenance-.....------------------
Total expended-......-.......              ........          ..       8,918.31        256, 913.40         111, 474.64         112,105.00
Allotted...........                                 $14, 000
                           .........-----------------------.        411, 000.00           40,000.00            6,200.00        19, 400.00

Balance unexpended July 1, 1943----------------------------                                                               $93, 893. 65
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942 -------------- $1,400.00
Amount allotted from War Department Civil Appro-
  priation Act approved July 19, 1937----------------     518. 20
Amount allotted from War Department Civil Appro-
  priation Act approved June 11, 1938---------        17, 481. 80
                                                                                                                           19, 400. 00

       Amount to be accounted for_--
Gross amount expended----------------_
                               ..-
                                                                                - --
                                                                          -----_--_    $112, 268. 35
                                                                                                       -----              113, 293. 65
Less reimbursements collected_         -                                      ----- -_       163. 35
                                                                                                                          112, 105. 00
       Balance unexpended June 30, 1944___                                    --------------                                 1188.
                                                                                                                             1,       65
Outstanding liabilities June 30, 1944                             ---------------                        $16. 48
Amount covered by uncompleted contracts-                                           ----               1, 172. 17
                                                                                                                             1, 188. 65
15. PRELIMINARY                    EXAMINATIONS, SURVEYS,                                         AND     CONTINGENCIES
                                       FOR FLOOD CONTROL
  The costs and expenditures from regular funds"for the fiscal year
were $5,064.63. The costs and expenditures to date from regular
funds were $155,023.98. The unexpended balance on June 30, 1944,
$27,576.02, minus a revocation of $23,500 in September 1944, will be
applied during the fiscal year 1945 to the payment of expenses to be
incurred under this heading.
                           FLOOD CONTROL--BOSTON,                                      MASS.,      DISTRICT                                55
  The sum of $5,000 can be profitably expended during the fiscal year
1946.
                                                Cost and          flnancial summary
Cost of new work to June 30, 1944_-
                                 ....                                  -      --
                                                                              __                                           -     ------
Cost of maintenance to June 30, 1944_                                   - ---------                                        $155, 023. 98
             Total cost of permanent work to June 30, 1944__                                                  -                155, 023. 98
Net total expenditures-_______--------------
                          -                                                                                                    155, 023. 98
Unexpended balance June 30, 1944_          -                                  -----------                                       27, 576. 02
        Total amount appropriated to June 30, 1944--------------                                                               182, 600. 00



     Fiscal year ending June 30                       1940             1941               1942                1943                  1944
C ost of new work---         -------------.-..                         . ..     ..-.     . .                              ----
                                                                                               ..---------------.--------------........--------------
Cost of maintenance_-----------_--------------_                        $147,500---------------$2,459.35                             $5,064.63
                                     ...
Total expended............----------------       --------------         147, 500                             2,459.35                5,064.63
Alloted.....................--------------------------... ----------    147, 500          .            --         500.00           -1,400.00


Balance unexpended July 1, 1943_   ---------               ---                                                              $34, 040. 65
Deductions on account of revocation of allotment ------------                                                                    1400.
                                                                                                                                 1,    00
       Net amount to be accounted for_           -----                                              -____                      32, 640. 65
Gross amount expended-     - -----              _-------                                           $5, 613. 07
Less reimbursements collected_     ------------                                                        548. 44
                                                                                                                                 5, 064. 63
     Balance unexpended June 30, 1944_ ..---------                                                                             27, 576. 02
Amount revoked in September 1944 ---------------------------                                                                   23, 500. 00

            Amount available during fiscal year 1945-----------------                                                            4, 076. 02

Amount that can be profitably expended in fiscal                                                 year ending
  June 30, 1946, for maintenance 1____.------------.___.                                                                   -5,      000. 00
 'Exclusive of available funds.

Status of all investigations for flood control called for by flood-control acts and com-
                                                           mittee resolutions

                                                                         Date trans-                                            Recom-
              Locality                       Authorization act            mitted to              Document No.                  mendation
                                                                          Congress

Androscoggin River, Maine__ Flood Control Corm- .................
                              mittee Resolution,
                              Mar. 27, 1936.
Androscoggin River, Maine.. Commerce Commit- _.................
                              tee Resolution,
                              Mar. 28, 1936.
Androscoggin River, Maine__ Flood Control Act, ...................
                              June 22, 1936.
Androscoggin River and Flood Control Act, .......................
tributaries, Maine and       June 25, 1936.
New Hampshire.
Kennebec River, Maine-..... Commerce Commit- ............................
                              tee Resolution,
                              Mar. 28, 1936.
Kennebec Riyver and tribu- Flood Control Act,.............
taries, Maine.               June 20, 1936.
Kennebec River, Maine..... Flood Control Act,-----------------
                              June 22, 1936.
Merrimack River, Mass., River and Harbor             ---------------------------
and N. H., with view to      Act, June 20, 1938.
improvement for navi-
gation, flood control and
water power.
56       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                            1944

   IMPROVEMENT OF RIVERS AND HARBORS IN THE
                 PROVIDENCE, R. I.,. DISTRICT
  This district comprises western New Hampshire, eastern Vermont,
western and southeastern Massachusetts, all of Rhode Island, all of
Connecticut except a small portion along its western boundary, and
small portions of southeastern New York embraced in the drainage
basins tributary to Long Island Sound and the Atlantic Ocean east
of the New York-Connecticut 'State line and south of Nauset Harbor
on the east coast of Cape Cod, exclusive 6f the watershed tributary
to the head of Buzzards Bay, Mass., north of Butlers Point and
Scraggy Neck. It also includes Fishers Island, N. Y.
   District engineer: Lt. Col. Edgar W. Garbisch, Corps of Engi-
neers, to January 13,1944; Lt. Col. Samuel G. Neff, Corps of Engineers,
from January 14, 1944, to May 22, 1944; Lt. Col. George L. Cook,
Corps of Engineers, acting district engineer from May 23, 1944, to
June 5, 1944; Col. Walter J. Truss, Corps of Engineers, from June 6,
1944.
  Division engineer: Col. George W. Gillette, Corps of Engineers.
                                        IMPROVEMENTS

                Navigation                                     Flood Control
                                         Page                                             Page
1. Pollock Rip Shoals, Nan-                    23. Clyde, Pawtuxet River Ba-
      tucket Sound, Mass     ---.          57         sin, R. I_                           101
2. Harbor of Refuge at Nan-                    24. Pontiac Diversion, Paw-
      tucket, Mass__--_                    59         tuxet River Basin, R. L_-            102
3. Cross Rip Shoals, Nantucket                 25. Thames River Basin, Conn.,
      Sound, Mass._       __               60    -    R.I., and Mass           .           104
4. New Bedford and Fairhaven                   26. Connecticut River Basin,
      Harbor, Mass._      _     .          62          Vt., N. H., Mass. and
5. Fall River Harbor, Mass _..            65          Conn....              -            106
6. Providence. River and Har-                  27. Claremont Reservoir, Con-
      bor, R. I-     -      -              67         necticut River Basin, N.
7. Pawtucket (Seekonk) River,                         H -        -        -               109
      R. I---          --                  69   28. Union      Village    Reservoir,
8. Harbor of Refuge at Block                          Connecticut River Basin,
      Island, R. I_-       _-              71         Vt_           _          _ . .       111
9. Great Salt Pond, Block Is-                  29. Sury Mountain Reservoir,
      land, R. I----------      -- -       73          Connecticut River Basin,
10. Pawcatuck River, R. I.                             N.H                                 112
      and Conn,                            75   30. Birch Hill Reservoir, Con-
11. New London Harbor, Conn_               77         necticut      River        Basin,
12. Thames River, Conn .....               78          Mass-----                     -    114
13. Connecticut River below                     31. Knightville Reservoir, Con-
      Hartford, Conn ......                80         necticut      River        Basin
14. Branford Harbor, Conn ..               84         Mass-          --                   116
15. New Haven Harbor, Conn _               85   32. Tully Reservoir, Connecticut
16. Housatonic River, Conn .               88         River Basin, Mass ...               118
17. Bridgeport Harbor, Conn         -      89   33. Hartford, Connecticut River
18. Southport Harbor, Conn...              93
19. Stamford Harbor, Conn. -                          Basin, Conn          .-----------   120
                                           94
20. Examinations, surveys and                   34. East Hartford, Connecticut
      contingencies (general) _--          98         River Basin, Conn .-.
                                                35. Winsted, Connecticut River
                                                                                          124
21. Other navigation projects
      for which no estimates                          Basin, Conn_.                       126
      are submitted------                  99   36. Springfield,        Connecticut
22. Plant allotment-----                  100         River,Basin, Mass .....             128
            RIVERS AND          HARBORS-PROVIDENCE,                 R.     I., DISTRICT            57
                                  IMPROVEMENTs-Continued

        Flood Control-Continued                              Flood Control-Continned
                                             Page                                           Page
37. West Springfield, Connect-                        41. Springdale (Holyoke), Con-
      icut River Basin, Mass-.                130           necticut    River       Basin,
38. Riverdale,    Connecticyt                               Mass.. ------------------       136
      River Basin, Mass                       132     42. Northampton, Connecticut
39. Chicopee, Connecticut River                             River Basin, Mass---    ....----138
      Basin, Conn_      ------------          133     43. Preliminary    examinations,
40. Holyoke, Connecticut River                              surveys, and contingencies
      Basin, Mass-------------                134           for flood control....---------- 139

            1. POLLOCK RIP SHOALS, NANTUCKET, SOUND, MASS.
  Location.--Pollock Rip Channel is the northerly passage through
the shoals off the eastern entrance to Nantucket Sound connecting the
deep water of the sound with that of the ocean. It is about 33 miles
east from the harbor of Vineyard Haven, on the island of Marthas
Vineyard, Mass., and 60 miles south from Provincetown Harbor at the
northern extremity of Cape Cod. (See U. S. Coast and Geodetic
Survey Chart No. 250.)
  Existing project.--This provides for dredging through the shoals
at the eastern entrance to Nantucket Sound with a Government dredge,
which is to assist the natural agencies in obtaining such depth and
width as may be found practicable, but not exceeding a depth of 30
feet at mean low water and a width of 1 mile. The mean tidal ranges
are about 3.7 feet at Monomoy Point, the nearest land, and 6.7 feet
at Chatham Light, about 9 miles to the north of this point. The
ranges of spring tides at these two points are 4.4 and 7.9 feet. The
ranges are largely affected by direction and force of storms. The orig-
inal expenditure authorized for experimental work was $250,000, and
later the operation of a dredge was authorized at an estimated annual
cost of $200,000.
   The estimated cost, revised in 1928, of providing a channel of suitable
dimensions was $1,100,000 for new work and $30,000 for annual
maintenance.
   The existing project was authorized by the following river and
harbor acts:
    Acts                            Work authorized                                Documents


July 25, 1912   Experimental dredging through the shoals to determine if    H. Doc. No. 536, 62d Cong.,
                 a channel could be secured and maintained not over 30       2d sess.
                 feet deep and not over 1 mile wide.
July 27, 1916   Continuation of work with a Government-owned hopper         Rivers and Harbors Cornm
                 dredge.                                                     mittee Doc. No. 3, 64th
                                                                             Cong., 1st sess.



  The latest published map is in the Annual Report for 1915, page
2056.
  Terminal facilities.-None.
  Operations and results during fiscal year.---U. S. hopper dredge
W. L. Marshall proceeded to Pollock Rip Shoals on October 4, 1943,
for maintenance dredging, but prior to its withdrawal from the proj-
ect no dredging was done due to bad weather. Costs of mobilization
amounted to $3,633.81 and preliminary costs were $148.17 during the
.58            'REPORT OF CHIEF OF ENGINEERS, ".S.                                                                     ARMY,               1944

year. Total costs were $3,781.98, all for maintenance. Expenditures
were $4,882.66.•
   Condition at end of fiscal year.-The existing project was com-
pleted in 1925. The depths previously secured over the northern
tongue of the Stone Horse Shoal have been maintained. A cut 2,000
feet wide has been dredged through Bearse and Pollock Rip Shoals.
In Jtme 1943 the controlling depth at mean low water was 30 feet for
a width of about 1,500 feet, and about 14 feet along the north edge
of the 2,000-foot channel. The costs and expenditures under the exist-
ing project have been $1,083,504.41 for new work and $664,894.81 for
maintenance, a total of $1,748,399.22.
   Proposedoperations.-Fundsunexpended on June 30,1944, amount-
ing to $39,680.24 and $25,000 allotted during July 1944, a total of
$64,680.24 will be applied to maintenance operations with a United
States hopper dredge, about 11/2 months, August to September 1944,
with necessary surveys.
   The sum of $75,000 can be profitably expended during the fiscal year
1946 for maintenance operations with a United States hopper dredge
for about 2 months in the spring of 1946. This sum exceeds the
average annual expenditure for the pist 5 years as the channel has
been permitted to deteriorate, no d'redging having been done since
1940.
                                                  Cost and financial summary
Cost of new work to June 30, 1944__ ---                                                    -       -$1,                                          083, 504. 41
Cost of maintenance to June 30, 1944_                                                -------------                                               664, 894. 81


                                                                    _------
              Total cost of permanent work to June 30, 1944----------
Net total expenditures----__                            --    1, 748, 399. 22
TUnexpended balance June 30, 1944 ---------------------------- 39, 680. 24
                                                                                                                                           1, 748, 399. 22



              Total amount appropriated to June 30, 1944-                                                             ----                  1, 788, 079. 46


      Fiscal year ending June 30                         1940                    1941                       1942                 1943                 1944

Cost o:new wor-.........                       ----    ........                ......              . ..       . ...              ..          .
Cost of maintenance--...........                      $55,079.59               $1, 409.87         -_--.       ...-              $1,100 68             $3, 781.98
Total expended--------------................--        60,2        .15                   '20,822
                                                                                            15     - -_--                             --     _         4,882.66
Allotted------------............-...........          50,000.00               -2,896.88              -11, 200 00                                    -22,000.00

Balance unexpended July 1, 1943_----------------------------                                                                                     $66, 562. 90
Deductions on account of revocation of allotment                                                                                                  22, 000. 00
      Net amount to be accounted for__-                                                     ---                      -__                          44, 562. 90
Gross amount expended-__   ---------                                                                               $4, 927. 32
Less reimbursements collected_                                         ----------                                           44. 66
                                                                                                                                                    4, 882. 66
      Balance unexpended 'June 30, 1944----------------------                                                                                     39, 680. 24
Amount allotted in July 1944,-----------               ----                                                                                      25, 000. 00
              Amount available during fiscal year 1945--                                                       ------                             64, 680. 24
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1__-_ __-                 --                                                                                      75, 000. 00
      1   Exclusive of available funds.
              RIVERS AND HARBORS-PROVIDENCE,                            R. I.,' DISTRICT            59
                 2. HARBOR OF REFUGE AT NANTUCKET, MASS.

   Location.-On the north shore of Nantucket Island about 28 miles
east-southeast from Vineyard Haven, Mass. (See U. S. Coast and
Geodetic Survey Chart No. 343.)
   Previous projects.-Adopted by the River and Harbor Act of March
2, 1829. For fnrther details see page 1747, Annual Report for 1915.
   Existing project.-This provides for a channel 15 feet deep at mean
low water, without prescribed width, through the bar at the entrance,
and for converging jetties, of riprap, 6,987 feet and 5,755 feet long, on
the east and west sides, respectively, of the entrance. The mean range
of the tide is 3.1 feet, and the maximum range due to the combined
effect of wind and other causes is 5 feet or more.
   The estimate of cost for new work, revised in 1931, is $522,500, ex-
clusive of amounts expended under previous project. The latest (1928)
approved estimate for annual cost of maintenance is $10,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                          .     Documents


June 14, 1880   West jetty------ _____.-------------H.            Doe. No. 18, 46th Cong., 2d sess., and
                                                                 Annual Report for 1880, p. 423.
Aug. 5,1886     East jetty and dredging when necessary    .--- Annual Report for 1885, p. 579.


  For latest published map see H. Doc. No. 115, 77th Cong., 1st sess.

   Recommended modifications of project.-Under date of November
14, 1940, the Chief of Engineers recommended modification of the
existing project, so as to provide an anchorage area of about 50 acres
on the east side of the harbor opposite the wharves, about 2,800 feet
long, 300 to 1,100 feet wide, and 15 feet deep at mean low water; a
fairway of the same depth extending southward through the harbor
along the west side of the anchorage to a point about 2,700 feet south
of Brant Point, at an estimated first cost of $63,000, with $1,500 an-
nually for maintenance in addition to that now required; subject to
certain conditions of local cooperation- (H. Doc. No. 115, 77th Cong.,
1st sess.).
   Local cooperation.-Nonerequired by law. The Commonwealth of
Massachusetts and local interests have expended for dredging and
boulder removal inside the harbor about $130,000.
   Terminal facilities.-These consist of four piers affording about
3,000 feet of berthing space. Facilities are considered adequate for
present commerce.
   Operations and results during fiscal year.-There were no opera-
tions. Costs in connection with a survey made in May 1943 amounted
to $5.40 for maintenance. Reimbursements of items due from other
projects were $246.67.
   Condition at end of fiscal year.-The existing project was about 87
percent completed. The east jetty was completed in 1907 and the
channel in 1930. The jetties have been built to varying heights and
cross sections with a view to controlling and regulating scour between
them. The west jetty is in need of repairs; the east jetty is in good
60             REPORT OF CHIEF OF ENGINEERS, U. S. AlIIY, 1944

condition. The controlling depth at mean low water in the channel
was 15 feet for widths generally in excess of 200 feet with shoals 12
feet along the western edge, as determined in May 1943. To com-
plete the project would require extension of the west jetty by about
800 feet and enlargement of 400 feet of the existing construction near
its outer end to full section. The costs and expenditures under the
existing project have been $456,482.25 for new work and $272,266.84
for maintenance, a total of $728,749.09.
   Proposedoperations.-Fundsunexpended on June 30,1944, amount-
ing to $41,381.69 will be transferred to other projects for more urgent
work.
   No additional funds are requested for fiscal year 1946 as maintenance
requirements are not sufficiently urgent to warrant the expenditure
under present conditions.

                                                Cost and financial summary
Cost of new work to June 30, 1944_ -------------------------                                                               $502, 317. 00
Cost of maintenance to June 30, 1944_ -----..---.--..-..--.-                                                                272, 266. 84
            Total cost of permanent work to June 30, 1944------------774, 583. 84
Net total expenditures- ------------------------------------- 774, 583. 84
Unexpended balance June 30, 1944 ---------------------------- 41, 381. 69

            Total amount appropriated to June30, 1944.                                          --------------                 815, 965. 53

    Fiscal year ending June 30                       1940                1941                     1942              1943            1944

Cost of new work_ . ..             .................                                                       ......              I..................
                                                                                                                                ....  .. .
Cost of maintenance........-------------.------............-----------...-...........   -------------...........     $612.91               $5.40
Total expended........-----------------------------------------------------864.98                                                    -246.67
Allotted ..........
         ------------------- --------------------------                                             $26, 000 ---------------
                                                                                                              ....  ........       1u6,
                                                                                                                                     000. 00


Balance unexpended July 1, 1943-_     .---.--------         .- $25, 135. 02
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940. ----------------------------------- 16, 000. 00
       Amount to be accounted for..................----------------------------.                                                41, 135. 02
Gross amount expended_ --------                       __--        -$27.     40
Less reimbursements collected_- -     ------             ___--274.          07
                                                                                                                                 -246.       67

            Balance unexpended June 30, 1944 -----------------------                                                            41, 381. 69
Amount (estimated) required to be appropriated for completion of
    existing project 1                    ------------------------------------------.- 66, 000. 00
  1Exclusive of available funds.

                    3. CROSS RIP SHOALS, NANTUCKET SOUND, MASS.

  Location.-Nantucket Sound lies south of Cape Cod and north of
Nantucket and the eastern part of Marthas Vineyard. Cross Rip
Shoals are a little southerly and easterly of the geographical center of
the sound. They are about 17 miles east from Vineyard Haven on the
island of Marthas Vineyard and about 15 miles northwest froI Nan-
tucket Harbor.                       (See U.. S. Coast and Geodetic Survey Chart No.
120)9.)
            RPTRS AND HARBORS-PROVIDENCE,                                      R. I.,       DISTRICT                61

  Existing project.-This provides for a channel 4,000 feet wide and
30 feet deep at mean low water between Half Moon Shoal and Cross
Rip Shoal, about 1.7 miles. The mean tidal range is about 2 feet and
the maximum range, due to the combined effect of wind and other
causes, is"3 feet or more.
   The estimate of cost for new work, made in 1928, was $27,000. The
latest (1928)        ,,approved
                           estimate for annual cost of maintenance is
$4,000. The existing project was authorized by the River and Harbor
Act of July 3, 1930 (H. Doc. No. 182, 70th Cong., 1st sess.). The
latest published map is in the project document.
   Terminal facilities.--None.
   Operations and results during fiscal year.-Maintenance dredging
by U. S. hopper dredge W. L. Marshall was in progress on October 4,
1943. During the period 2,294 cubic yards of material, bin measure-
ment, were removed from Cross Rip Shoals at a cost of $570.41 for
dredging and $47.08 for preliminary work. Total costs and expendi-
tures were $617.49, all for maintenance.
   Condition at end of fiscal year.-The existing project was completed
in 1931. In April 1941 the controlling depth was 30 feet at mean low
water except for minor shoals with a minimum depth of 26 feet along
the edges. The costs and expenditures under the existing project have
been $24,200.13 for new work and $41,354.56 for maintenance, a total of
$65,554. 69.
  Proposed operations.---Funds unexpended on June 30, 1944,
amounting to $6,882.51 will be applied to maintenance operations with
a United States hopper dredge for about 10 days in September 1944.
  No additional funds can be profitably expended during the fiscal
year 1946 as the completion of the above work will leave the channel
in satisfactory condition for use during that period.
                                  Cost and financial summary
                                 --------------------------
Cost of new work to June 30, 1944__                                                                 $24, 200. 13
Cost of maintenance to June 30, 1944-------------------------                                        41, 354. 56
         Total cost of permanent work to June 30, 1944 ------------- 65, 554. 69
Net total expencitures -------------------------------------                                        '65,  554. 69
Unexpended balance June 30, 1944_ ----------------                                                     6, 882. 51
        :Total amount appropriated to June 30, 1944                      ---------------              72, 437. 20


   Fiscal year, ending June 30        1040               1941             1942               1943            1944

Cost ofnew work ..... ... .. ..$ -               "                         -

Cost of maintenance....-------------... $12, 500-----------.....
                                                              ---------------------------                      $617. 49
Total expended: .--------------         12
                                        -, 00----------------------------------------                           617.49
                             ----------- $7,500 .. .. ..z_ ._...
Allotted-------------------------.........................
                          .........                                                                 ....      ....


Balance unexpended July 1, 1943-----------------------------                                          $7, 500. 00
Gross amount expended_-      -------------                $856. 78
Less reimbursements collected.             --------------  239. 29
                                     .                                                                       617. 49
         Balance unexpended June 30, 1944 .-------------------.-                                           6, 882. 51
62          REPORT OF CHIEF OF ENGINEERS, U.                               S. ARMY,         1944

                4. NEW BEDFORD AND FAIRHAVEN HARBOR, MASS.

  Location.-New Bedford Harbor is a tidal estuary on the western
side of Buzzards Bay, about 27 miles northwesterly from the harbor
at Vineyard Haven, Mass., and about 37 miles to the eastward of
Point Judith Harbor, R. I. (See U. S. Coast and Geodetic Survey
Chart  No. 252.)
   Previous projects.Adopted by River and Harbor Acts of July 4,
1836, March 3, 1875; and August 11, 188. For further details see
page 1748, Annual Report for 1915, and page 101, Annual Report
for 1938.
  Existing project.-This provides for a channel 30 feet deep and
350 feet wide from deep water in Buzzards Bay to a point just above
the New Bedford-Fairhaven. Bridge, nearly 5 miles, with increased
widths for anchorage and maneuvering purposes in the area north-
west of Palmer Island and above the bridge; a channel 25 feet deep
between harbor lines along the New Bedford wharf front near the
bridge, about 0.2 mile; a channel 100 feet wide and 18 feet deep
from the 30-foot area north of Fish Island to Belleville, a distance
of about 2 miles, with a turning basin at the upper end 300 feet
wide; dredging the area west of a line 50 feet channelward of the
Fairhaven Harbor line to a depth of 15. feet over widths of 150 to
400 feet from Peirce & Kilburn wharf to the Old South wharf, and
thence 10 feet deep and 150 feet wide ,to a point 1,000 feet south of
the old causeway pier, about 0.7 mile; and for the maintenance of
the 25-foot anchorage area east of the channel and north of Palmer
Island. The plane of reference is mean low water, the mean range
of the tide being 3.7 feet and the maximum range, due to the com-
bined effect of wind and other causes, 7 feet or more.
   The estimated cost for new work, revised in 1942, is $1,800,000,
including $20,385 contributed by local interests but exclusive of
amounts expended on previous projects. The latest (1937) approved
estimate for annual cost of maintenance is $23,250.
   The existing project was authorized by the following river and
harbor acts:

     Acts                        Work authorized                                      Documents

Mar. 2, 1907     The 25-foot anchorage area north of Palmer Island.    H. Doc. No. 271, 59th Cong., 2d sess.
Mar. 3. 1909     Extension of the 25-foot channel along the New        Specified in act.
                  Bedford wharf front near the bridge.
July 25, 1912    The 18-foot channel in Acushnet River to Belle-       H. Doc. No. 442, 62d Cong., 2d sess,
                   ville.
July 3, 1930     The 30-foot channel, anchorage, and maneuvering       H. Doc. No. 348, 71st Cong., 2d sess.1
                   areas (channel limited to width of 350 feet).
Aug. 30, 1935f   Present project dimensions of the anchorage area      Rivers and Harbors Committee Doe.
                  northwest of Palmer Island and maintenance of          No. 16, 74th Cong., 1st sess.'
                   the 25-foot anchorage.
                 Elimination from the project of the prior authori-
                  zation for enlarging and deepening the maneu-
                   vering area 30 feet deep east of theharbor ehai,-
                  nel.
Aug. 26, 1937    The 15-foot and 10-foot channel along the Fair-       Rivers and Harbors Committee Doe.
                  haven wharf front.                                    No. 25, 75th Cong., 1st seas.'


  I Contains latest published maps.
  'Also Emergency Relief Act, May 28, 1935.
        RIVERS AND    HARBORS-PROVIDENCE,        R. I., DISTRICT       63.
    Local cooperation.--The River and Harbor Act of July 25, 1912,.
imposed the condition that local interests construct a new bridge at
Coggeshall Street with a draw opening of at least 100 feet and build
a substantial wharf upon the city property at Belleville, the name
given to the northern part of the city. These conditions have not been
met, and there is no present prospect of their being complied with.
The condition imposed by the River and Harbor Act of August 26,
1937, was fully complied with.
    The Commonwealth of Massachusetts expended approximately
$120,000 in dredging a channel 25 feet deep and 100 feet wide fronm
Fish Island nearly to Coggeshall Street Bridge.
    Terminal facilities.---These consist of 28 wharves and piers with
a total of about 17,580' feet of docking space; 3 wharves are owned by
the city of New Bedford, 2 by the Commonwealth, and 1 by the town
of Fairhaven; 7 of the wharves are open to public use and 6 have rail
connections. These facilities are considered adequate for the existing
commerce. (For further details see Port Series No. 18, Corps of
Engineers.)
    Operations and results durinr g fiscal year.-Maintenance dredging,
by contract, of the inner portion of the entrance channel, the 30-foot
west maneuvering area and the 25-foot anchorage was commenced on
February 9 and was completed on June 14, 1944, except for clean-up
of the dispos. area, which was not completed at the end of the year.
During the period 221,023 cubic yards, place measure, ordinary mate-
rial were removed at a cost of $92,367.67. Preliminary expenses in
connection with the work amounted to $3,183.92. Preliminary ex-
penses in connection with proposed contract for removal of rocky shoals
in the entrance channel amounted to $34.95. Total costs were
$95,586.54, all for maintenance. Expenditures were $86,435.83."
    Condition at end of fiscal year.-The existing project was about 98
percent completed. The controlling depths at mean low water were
as follows: 29 feet in the entrance channel to the bridge except for edge-
shoals and small rocky shoals north of Palmer Island Light, which
have a minimum depth of about 27 feet in the midchannel section and
24 feet in the remainder of the channel (July 1943 and May 1942);
30 feet in the west maneuvering area except for minor shoals (Junp
1944) ; 30 feet for abouit one-third the area of the 30-foot turning basin
above the bridge, shoaling gradually to 18 feet along the east edge
  (July 1943); 25 feet in the 25-foot anchorage (June 1944); 15 feet
in 15-foot Fairhaven water-front channel, and 10 feet in 10-foot Fair-
haven water-front channel except minor edge shoals (March 1944);,
20 feet in 25-foot New Bedford water-front channel (February 1938);
in the Acushnet River, about 23 feet to a point about 1,200 feet below
Coggeshall Street Bridge (May 1928); and thence 7 feet to Belleville
  (1905). The head of navigation is about 7 miles north of the en-
trance, opposite Sconticut Point. To complete the project requires
the removal of a shoal of hard material along the east limit of the
turning basin above the bridge and the dredging of the 18-foot chan-
      ,Belleville.
nel to               The costs from regular funds hwVe beet $1,459,653:66.
for new work and $349,727.48 for maintenance, a total of $1,809,381.14.
The expenditures have been $1,800,140.08. The costs and expenditures
from Emergency Relief funds have been $227,264.49 for new work.
    The total costs, United States funds, were $1,686,918.15 for new
64            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

work and $349,727.48 for maintenance, a total of $2,036,645.63. The
total expenditures, United States funds, have been $2,027,404.57. In
addition, the sum of $20,400 was expended for new work from con-
tributed funds.
   Proposed operations.-Funds unexpended on June 30, 1944,
amounting to $85,064.17, will be applied as follows:
Accounts payable June 30, 1944 -----------------------------                                                   $9, 241. 06
Maintenance:
    Remaining obligations in connection with dredging entrance chan-
      nel, west maneuvering area and 25-foot anchorage, completed
      prior to June 30, 1944, except for a clean-up of disposal area _                                         24, 999. 33
    Removal of rocky shoals from the entrance channel and west
      maneuvering area, about 150 cubic yaids, by coptract, August
      to September 1944       __-                                                                              15, 000. 00
    Dredging about 52,000 cubic yards of mud and sand from the
      30-foot turning basin above the bridge, by contract, August
      to September 1944                       ---------                                                        35, 823. 78
                         Total_ --------------------------------------                                         85, 064. 17
  The sum of $30,000 can be profitably expended during fiscal year
1946 for maintenance dredging in the outer portion of the entrance
channel with a United States hopper dredge for about 3 weeks in the
fall of 1945.
                                           Cost and financial summary
Cost of new work to June 30, 1944 ----------------------      $1, 857, 618.15
Cost of maintenance to June 30, 1944_------------------------- 349,727.48
      Total cost of peirmanent work to June 30, 1944- -   -2,                                                 207, 345. 63
Minus accounts payable June 30, 1944 ------------------------                                                   9, 241. 06
      Net total expenditures                                                                           1-----------------------------
                                                                                                          198, 104. 57
Unexpended balance June 30, 1944_--                                        ---------                           85, 064. 17
           Total amount appropriated to June 30, 1944-----------                                    1   2, 283, 168. 74


    Fiscal year ending June 30                 1940              1941             1942          1943               1944

Cost of new work- ...... ....               $18, 867. 36    ------------          $1,431.64        $1.73
Cost of maintenance-----------............ -48,878.95       ---------------------------            90. 35                54
                                                                                                                  $95,586.

       Total cost_....----.-..---             67, 746. 31   --------------         1,431.64        92. 08          95, 586. 54

Total expended----------------83, 608.80                    --------------         1, 431.64           1.73        86, 435.83

Allotted-.---                   .238.46
                  _--.. ___------...                            $12, 000   --------------      79, 433.37          81,500. 00



Balance unexpended July 1, 1943         - -----------                                                         $90, 000. 00
Amount allctted from War Department Civil Ap-
  propriation Act approved May 23, 1941 -------- $35, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved June 2, 1943
Amount allotted from War Department Civil Ap-
                                                    31, 500. 00  -------
  propriation Act approved June 24, 1940-     -     15, 000. 00
                                                                                                               81, 500. 00
       Amount to be accounted for__ ___...------------171,                                                         500. 00
Gross amount expended_         ---------------------- $88, 429. 86
SIn addition $20,400 expended from contributed funds for new work.
             RIVERS AND HARBORS-PROVIDENCE,                  R. I.,    L~STRICT            65
Less reinbursements collected -------------------            $1, 994. 03
                                                                                   $86, 435. 83
      Balance unexpended June 30, 1944        ---------------------                 85, 064. 17
Outstanding liabilities June 30, 1944--------------
Amount covered by uncompleted contracts        -         -
                                                      $782. 75
                                                    32, 146. 03
                                                                                    32, 928. 78

          Balance available June 30, 1944--      -----             _52,                 135. 39
Amount (estimated) required to be appropriated
for completion of existing project 2- - - - - -         -     -   -   -   -   -
                                                                                    84, 000. 00
Amount that can be profitably expended in fiscal
year ending June 30, 1946, for maintenance 2- - - - -   - - - -- - -- - -
                                                                                    30, 000. 00
2   Exclusive of available funds.

                              5. FALL RIVER HARBOR, MASS.
   Location.-Situated at the mouth of Taunton River, on the east
side and at the head of Mount Hope Bay, which empties into the
ocean through Narragansett Bay and Sakonnet River. It is about
18 miles northerly from Newport Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 353.)
   Previous projects.-Adopted by River and Harbor Acts of June
23, 1874, March 3, 1899, June 13, 1902, and June 25, 1910. For fur-
ther details see page 1749 of Annual Report for 1915, and page 106
of Annual Report for 1938.
   Existing project.-This provides for a channel 30 feet deep at mean
low water and 400 feet wide through Mount Hope Bay and Fall River
Harbor, about 6.8 miles, with increased width opposite the wharves
below Slades Ferry Bridge; for the removal of the lower end of Hog
Island Shoal, and for the maintenance of the 25-foot anchorage, about
42 acres in area, west of the harbor channel. The mean tidal range
is 4.4 feet and the maximum range, due to the combined effect of wind
and other causes, is 8 feet or more.
   The estimate of cost for new work, revised in 1941, is $530,000, ex-
clusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $18,000.
   The existing project was authorized by the River and Harbor Act
of July 3, 1930 (H. Doc. No. 158, 71st Cong., 2d sess.). The latest
published map is in the project document.
   Terminal facilities.-These consist of 17 wharves and piers, afford-
ing about 10,100 feet of docking space.
   Three of the piers have direct railroad connection. Two of the
wharves are owned by the city. One wharf is open to public use
and two are available upon agreement. The facilities are considered
adequate for the commerce of the port. (For further details see Port
Series No. 18, Corps of Engineers.)
   Operations and results during fiscal year. A survey before main-
tenance dredging under contract in force was made in June 1944 at a
cost of $426.80. Preliminary costs on this contract amounted to $163.59
during the year. Total costs were $590.39 all for maintenance. Ex-
penditures were $252.54.
   Condition at end of fiscal year.-The existing project was about 98
percent completed. The controlling depths at mean low water were
as follows: Hog Island Shoal, 20 feet at west edge of channel (Decem-
ber 1940) ; 30-foot channel, 28 feet except at edges (June 1944) ; 25-foot
          616634-45-pt. 1, vol. 1-    5
66              REPORT %OF CHIEF OF ENGINEERS,                                       U. S. ARMY,                 1944

anchorage, 19 feet (June 1942). To complete the work requires re-
moval of ledge rock at Hog Island Shoal. The costs under the exist-
ing project have been $452,792.14 for new work, and $63,855.21 for
maintenance, a total of $516,647.35, including $2,859.87 for maintenance
dredging at the Firestone Wharf, under section 3 of the River and
Harbor Act of October 17, 1940. Expenditures have been $516,309.50.
  Proposedoperations.-Fundsunexpended on June 30, 1944, amount-
ing to $189,334.55 will be applied as follows:
Accounts payable, June 30, 1944_                           ---------------------
                                                                     $337. 85
Maintenance: Dredging channel from about 12 mile below Borden
  Flats Light to deep water south of Slades Ferry Bridge, by con-
  tract in force, July to October 1944, about 340,000 cubic yards 183, 573. 20
Balance reserved for contingencies on above work ----------------   5, 423. 50
       Total ---------------------------------------------        189, 334. 55
   The sum of $30,000 can be profitably expended during fiscal year
1946 for maintenance dredging in the outer portion of the entrance
chanel with a United States hopper dredge for about 3 weeks in the
fall of 1945.
                                                  Cost and financial summary
Cost of new work to June 30, 1944__                                                                               $782, 996. 30
Cost of maintenance to June 30, 1944                                        -145,                                       265. 52
      Total cost of permanent work to June 30, 1944-                                                                  928, 261. 82
Minus accounts payable June 30, 1944                                                                                       337. 85
      Net total expenditures _-_927,                                                                                       923. 97
Unexpended balance June 30, 1944 ---                                                                                  189, 334. 55
            Total amount appropriated to June 30, 1944                                        - - - -            1, 117, 258. 52

    Fiscal year ending June 30                      1940           1941               1942                1943             1944


Cost of new work___... -  ._ .                    $27, 235.86    $32,103. 49__-
Cost of maintenance_.........                      50, 554.96                        $6, 331.71            $650. 68          $590. 39

        Total cost_ __.             .    .   .'    77, 790. 82    32, 103. 49         6, 331.71             650. 68           590.39

Total expended ..----------------.............     79, 530. 64    32, 757. 41         6, 594. 93            387. 46           252. 54

Allotted-     ......    ..............             10, 000.00      2, 859.87        105, 083.48         -6, 800.00         91, 465.68


Balance unexpended July 1, 1943_                                                                                      $98, 121. 41
Amount allotted from War Department Civil Ap-
propriation Act approved May 23, 1941- "_ --  -    $465. 68
Amount allotted from War Department Civil Appro-
priation Act approved Apr. 28, 1942             91, 000. 00     ---------
                                                                                                                       91, 465. 68
       Amount to be accounted for                                                                                     189, 587. 09
Gross amount expended --------------------------                                                   $263. 96
                             --------------------
Less reimbursements collected_                                                                       11. 42
                                                                                                                           252. 54
      Balance unexpended June 30, 1944_______                                                                         189, 334. 55
Outstanding liabilities June 30, 1944---------------    $337. 85
Amount covered by uncompleted contracts       --..   168, 300. 00
                                                                                                                      168, 637. 85
            Balance available June 30, 1944                               _______                                      20, 696. 70

Amount (estimated) required to be appropriated for completion
  of existing project 1           ---                                                                                  70, 000. 00
Amount that can be profitably expended in fiscal year ending June
  30, 1946 for maintenance 1-         -_-                                                                              30, 000. 00
1Exclusive of available funds.
        RIVERS AND    HARBORS-PROVIDENCE,      R.   I., DISTRICT    67
             6. PROVIDENCE RIVER AND HARBOR, R. I.

   Location.-Providence River is formed at the city of Providence by
the junction of the Pawtucket (Seekonk) River and two small streams
which rise in northern Rhode Island. It is tidal and flows southerly
in a deep channel between broad flats about 8 miles, emptying into
Narragansett Bay. (See U. S. Coast and Geodetic Survey Chart No.
278.)
   Previous projects.-Adopted by River and Harbor Acts of August
30, 1852; March 2, 1867; March 3, 1873; June 18, 1878; August 2,
1882; August 5, 1886; June 3, 1896; June 13, 1902; March 3, 1905;
March 2, 1907; June 25, 1910; and March 4, 1913. For further details
see page 1750, Annual Report for 1915, page 96, Annual Report for
1936, and page 111, Annual Report for 1938.
   Existing project.-This provides for an approach channel 35 feet
deep at mean low water and generally 600 feet wide through the
river from the deep water of Narragansett Bay opposite North Point
on Popasquash Neck to the turn below Fields Point, 8.1 miles, and
thence with the same depth, and of width ranging up to 1,700 feet to
Fox Point, excluding a marginal strip 75 feet wide channelward of
the established harbor lines, about 2.6 miles. The mean tidal range
is about 4.6 feet and the.maximum range, due to the combined effect
of wind and other causes, is 8 feet or more.
   The estimate of cost for new work, made in 1937, is $1,580,000, ex-
clusive of amounts expended on previous projects. The latest (1937)
approved estimate for annual cost of maintenance is $42,000.
   The existing project was authorized by the River and Harbor Act
of August 26, 1937 (H. Doc. No. 173, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-Fullycomplied with. In addition to extensive
dredging prior to 1900 in the channel from Fox Point to the head of
navigation, the city of Providence has since spent about $216,000 in
maintaining a 20-foot depth in this channel.
   Terminal facilities.-There are 35 wharves (in use or usable condi-
tion), including 1 owned by the State and 5 by the city, adjacent
to the harbor area, Providence River below Crawford Street, and
Pawtucket (Seekonk) River below Red Bridge. The total available
berthing space is 19,170 feet. The municipal wharf at Fields Point
and the State pier are open to general public use for commercial
purposes. One wharf is open to the public upon agreement with the
owner. Thirteen of the wharves have rail connections. The facili-
ties are considered adequate for existing commerce. (For further
details see Port Series No. 18, Corps of Engineers.)
   Operations and results during fiscal year.-Improvement dredging,
by contract, for widening the channel opposite and below Fields Point,
suspended on July 5, 1941, was not resumed. The contract was ter-
minated due to the disposal area having been taken for shipyard use.
An adjustment for yardage previously removed was made in amount
of 15,839 cubic yards, place measure, ordinary material. The cost of
the work during the year amounted to $5,509.33.
   Rock removal below Conimicut Light and off Fields Point, by con-
tract, in progress at the beginning of the year, was completed on
68          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                           1944

January 14, 1944. During the period 98.9 cubic yards of rock and
1,397 cubic yards of overburden were removed below Conimicut Light,
and 408 cubic yards of rock and 613 cubic yards of overburden were
removed off Fields Point all at a cost of $29,662.67. These operations
completed the project except for the widening of the channel opposite
and below Fields Point. Total costs were              all for new work.  $35,172
Expenditures were $48,026.
   Condition at end of fiscal year.-The existing project was 97 per-
cent completed. Under the existing project a channel 600 feet wide
from the deep water of Narragansett Bay to the turn below Fields
Point, thence to Fox Point, with a width ranging up to 1,700 feet,
has been dredged to a general depth of 35 feet. The head of com-
mercial navigation is at Crawford Street Bridge, about 0.8 mile
above Fox Point. The controlling depths at mean low water were
as follows: In the channels, 35 feet to Sabin Point except for minor
shoals (February 1944); from Sabin to Fox Point, 28 feet except for
edge shoals (January 1944); in the widening below Fields Point, 5 to
35 feet (December 1942). To complete the project requires comple-
tion of the widening of the channel at the turn below Fields Point.
The costs and expenditures under the existing project have been
$2,112,233.67 for new work and $387.95 for maintenance, a total of
$2,112,621.62.
   Proposed operations.-Fundsunexpended on June 30, 1944, amount-
ing to $1,351.59, $90,000 allotted during July 1944, and $100,000 to
be requested, a total of $191,351.59, will be applied to maintenance,
dredging, by contract, from August 1944 to June 1945, about 400,000
cubic yards of mud and sand from the channel between Sabin and
Fox Points.
   The sum of $320,000 can be profitably expended during fiscal year
1946 in completion of the maintenance dredging, by contract, about
700,000 cubic yards of mud and sand from the channel between Sabin
and Fox Points. This amount is in excess of the average annual ex-
penditure of the past 5 years for maintenance, as the channel has been
permitted to deteriorate, no maintenance having been done since the
35-foot depth was obtained in 1941.
                                       Cost and financial summary
Cost of new work to June 30, 1944 ------------------------                                      $5, 873, 645. 23
Cost of maintenance to June 30, 1944   -------------------                                          650, 524. 22
           Total cost of permanent work to June 30, 1944----------                              6, 524, 169. 45

Net total expenditures_ __                       _--------------__-6,                                 524, 169. 45
                                     ---
Unexpended balance June 30, 1944_ _ _1,                                                                    351. 59
           Total amount appropriated to June 30, 1944                    ---------              6,525, 521. 04


     Fiscal year ending June 30           1940              1941          1942           1943              1944


Cost of new work-               -      $882, 650. 38    $679, 001. 21    $7, 817. 17   $23, 696. 32        $35, 172.00
Cost of maintenance         -      _                                                                   _..---
Total expended ----------------         899, 914. 39      737, 085. 89   13, 062. 42    16, 126. 74        48,026. 00
Allotted    ....----------------        592, 548. 55                                    1 632. 29
                                                                                        11,              -55, 107. 63
             RIVERS AND HARBORS-PROVIDENCE,                              R.      I., DISTRICT                 69
Balance unexpended July 1, 1943_ __                                                            $104, 485. 22
Deductions on account of revocation of allotment                                                 55, 107. 63

       Net amount to be accounted for_-_                                                         49. 377. 59
                                                                                                 -   "   _-   _   _




Gross amount expended __                 ----------                      $48, 323. 17
Less reimbursements collected__-                                                 297. 17
                                                         --                                      48, 026. 00

         Balance unexpended June 30, 1944-___----                                                 1, 351. 59
Amount alloted in July 1944_                    ----                                             90, 000. 00

         Amount available during fiscal year 1945_                                               91, 351. 59

Amount (estimated) required to be appropriated for completion
of existing project 1--_                                                                       150, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1--                                                             320, 000. 00
1 Exclusive of available funds.

                        7. PAWTUCKET (SEEKONK) RIVER, R. I.

   Location.-This river rises in the vicinity of Worcester, Mass., and
flows in a general southeasterly direction for about 52 miles, emptying
into Providence Harbor at Providence. (See U. S. Coast and Geo-
detic Survey Chart No. 278.)
   Previous projects.-Adopted by River and Harbor Acts of March
2, 1867, July 5, 1884, and March 3, 1899. For further details see page
1749 of Annual Report for 1915, and page 113 of Annual Report for
1938.
   Existing project.-This provides for a channel 16 feet deep at mean
low water and 150 to 230 feet wide from Red Bridge up to the ledge
rock between the wharves at Pawtucket, 3.2 miles; thence with same
depth 100 to 60 feet wide through the ledge to Division Street Bridge,
0.2 mile. The mean tidal range is about 4.6 feet at the mouth of the
river and about 5 feet at Pawtucket, and the maximum range due to
the combined effect of wind and other causes is 8 feet or more.
   The estimate of cost for new work, revised in 1922, was $423,035,
exclusive of amounts expended on previous projects but including the
expenditure of funds contributed by the State of Rhode Island to the
amount of $67,792. The latest (1928) approved estimate for annual
cost of maintenance is $10,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                               Work authorized                                     Documents


Mar. 3, 1905     The 16-foot channel from Red Bridge in Providence, to            H. Doc. No. 113, 56th Cong.,
                   Division St. Bridge in Pawtucket.                                1st sess.
Mar. 3, 1909     Provisional authorization to deepen the channel to 18 feet at    Specified in act.
                   mean low water and increasing the width at such places
                   as would best serve the interests of navigation.
Mar. 2, 1919     Widening the channel, except through the ledge at Paw-           H. Doc. No. 1283, 64th Cong.,
                   tucket, to 150 feet.                                            1st sess. (Contains latest
                                                                                   published map.)
Sept. 22, 1922   Present project width of channel through the ledge at Paw-       H. Doc. No. 654, 66th Cong.
                   tucket.                                                          2d sess.
70             REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,           1944

   Local cooperation.-Fully complied with.
   Terminal facilities.-Includingthe five terminals at and near Phil-
lipsdale, the facilities cover about 5,260 feet of docking space, of which
700 feet is owned by the State of Rhode Island and 4,560 feet owned
and used by private owners. At the State terminal 100 feet of docking
space is available for public use. The facilities are considered ade-
quate for the existing commerce.
   Operations and results during fiscal year.-Maintenance dredging,
by contract, in the channel from Phillipsdale to Pawtucket was com-
menced on April 10 and was completed on June 20, 1944. During the
period 199,102 cubic yards, place measure, ordinary material and 7.54
cubic yards boulders exceeding 2 cubic yards each in size were re-
moved at a cost of $100,180.80. Preliminary expenses in connection
with the work amounted to $565.32. Total costs were $100,746.12, all
for maintenance. Expenditures were $71,261.50. These operations
restored a depth of 17 feet except for minor edge shoals above Bass
Rock.
   Conditions at end of fiscal year.-The existing project was completed
in 1927. The controlling depths at mean low water are as follows:
17 feet to a point about 400 feet above State Pier, Pawtucket, except
for minor edge shoals just below and just above State Pier (May-
June 1944) ; thence about 12 feet to the head of the project (June 1943).
The head of navigation is at Pawtucket Falls, about 5.2 miles above
the mouth of the river. The costs under the existing project have
been $337,788.85 for new work, and $442,832.90 for maintenance, a total
of $780,621.75. The expenditures have been $750,868.22. In addition,
the sum of $67,792 has been expended for new work from contributed
funds.
   Proposedoperations.-Fundsunexpended on June 30, 1944, amount-
ing to $33,738.50 will be applied as follows:
Accounts payable June 30, 1944------------------------------                                  $29, 753. 53
Balance remaining                                                                             ,-------------------
                                                                                                 3, 984. 97
       Total-------------------------------------------      _____                              33, 738. 50
  No additional funds can be profitably expended during the fiscal
year 1946 as the project is in condition to meet the needs of existing
navigation.
                                      Cost and financial summary
Cost of new work to June 30, 1944__     ----- _--1                                             $672,   214. 17
Cost of maintenance to June 30, 1944_------------------------                                   442,   832. 90
       Total cost of permanent work to June 30, 1944-.....                                   1, 115,   047. 07
Minus accounts payable June 30, 1944---- -------------------                                     29,   753. 53
       Net total expenditures ----------------------------                                 1 1, 085,   293. 54
Unexpended balance June 30, 1944---------------------- --                                        33,   738. 50
       Total amount appropriated to June 30, 1944---------_ -_                             1 1, 119,   032. 04


    Fiscal year ending June 30           1940          1941            1942         1943               1944

Cost of new work---
                                --- $34, 481. 68
Cost of maintenance --- ----.......--..       .       $2, 098. 08- --------------   $268.91       $100, 746. i2

Tptal expended ----------------          28,903. 57
                                     fd-----71,        7, 717. 24                                         261. 50
Allotted----------------------10, 196. 16              _            $36, 000. 00--------------69, 000.00

     1 In   addition $67,792 expended from contributed funds for new work.
                RIVERS AND HARBORS-PROVIDENCE,                                     R.   I.,    DISTRICT             71
Balanice unexpended July 1, 1943_ --                                                                      $36,000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941- -------  $62, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved June 24, 1940- -------   7, 000. 00
                                                                                                           69, 000. 00
       Amount to be accounted for_ ____--                                             _-- __-             105, 000. 00
Gross amount expended_-------------------------                                   $72, 520. 49
Less reimbursements collected--- -----------------                                  1, 258. 99
                                                                                                           71, 261. 50
      Balance unexpended June 30, 1944----- --------------                                                 33, 738. 50
Outstanding liabilities June 30, 1944                     ---------------
                                                     $637. 06
Amount covered by uncompleted contracts -------- 29, 116. 47
                                                                                                           29, 753. 53

           Balance available June 30, 1944 ---------------------                                 _          3, 984. 97

                   8. HARBOR OF REFUGE AT BLOCK ISLAND, R. I.

    Location.-Located on the east side of Block Island, near the south
end of the inner curve of the shore line.                                      It is 13 miles south-south-
west from Point Judith Harbor and about 25 miles southeasterly
from Stonington Harbor, Conn. (See U. S. Coast and Geodetic Sur-
vey Chart No. 276.)
   Existing project.-This provides for a rubble-mound breakwater
extending northerly about 1,950 feet from the shore; a similar break-
water about 1,100 feet long, extending northerly and easterly, enclos-
ing, with the main breakwater, an area about 800 feet square desig-
nated as the inner harbor; masonry walls in the southeastern corner
of the inner harbor enclosing an area nearly 300 feet square desig-
nated as the basin; and for dredging to a depth of 15 feet at mean low
water the outer protected area and about 67 percent of the inner
harbor and of the basin. The mean tidal range is 2.9 feet, and the
maximum range, due to the combined effects of wind and other causes,
is 7 feet or more.
   The estimate of cost for new work, revised in 1928, is $615,300.
The latest (1928) approved estimate for annual cost of maintenance
is $3,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                             Work authorized                                          Documents


July 11, 1870    The main breakwater ..........
                                          -----------------------   ........   Annual Report 1868, p. 785, and S. Misc.
                                                                                 Doc. No. 81, 40th Cong., 2d sess.
Aug.   5,1886    Breakwater enclosing the inner harbor----------............   S. Doc. No. 27, 48th Cong., 2d sess., and
                                                                                 Annual Report, 1885, p. 610.
June   3,1896    Raising the crest of the main breakwater and mak-             i. Doe. No. 83, 54th Cong., 1st sess.
                  ing it sandtight.
July 25,1912     Rebuilding the basin walls and present project                H. Doc. No. 828, 60th Cong., 1st sess.
                  dimensions of the dredged areas.                               (Contains latest published map.)



   Recommended modiflcations of project.-On June 24, 1926, the
Chief of Engineers recommended that this project be modified by
eliminating the dredging of the outer harbor west of the entrance
channel (Ht. Doc. No. 467, 69th Cong., 1st sess.).
72             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                       1944

   Terminal facilities.-There is one wharf with a total of 265 feet of
docking space, 240 feet of which is owned by the town. All landing
space is used to capacity and is considered adequate for existing
commerce.
   Operations and results during fiscal year.-Maintenance dredging
of the entrance channel and inner harbor, by contract, was commenced
on November 2 and was completed on November 13, 1943. During the
period 27,891 cubic yards, place measure, ordinary material were
removed from the channel and basin, and 25,718 cubic yards from the
inner harbor at a cost of $26,099.10.. Preliminary expenses in connec-
tion with the work amounted to $247.62 during the year. These opera-
tions restored a depth of 15 feet in the entrance channel for a width
of 100 feet to the basin, and in the inner harbor except for minor edge
shoals and for a strip 100 to 200 feet wide at the west end of inner
harbor. Total costs were $26,346.72 all for maintenance. Expendi-
tures were $26,414.61.
   Condition at end of fiscal year.-The existing project was about
94 percent completed. The breakwater and harbor walls were com-
pleted in 1916. The inner harbor and basin have been dredged to
project dimensions, and a channel 60 to 130 feet wide and 15 feet deep
has been dredged from deep water outside the harbor up to the town
wharf. The controlling depths at mean low water are as follows:
Entrance channel to head of basin, 15 feet for width of 100 feet except
at entrance to the basin (November 1943) ; inner harbor, 15 feet except
for shoal extending 100 to 200 feet from the west end and other minor
shoals (November 1943) ; and outer protected area 6 to 14 feet (October
1941). The east breakwater and harbor walls are in good condition,
the west breakwater is in poor condition.
   To complete the project requires the deepening of the outer pro-
tected area adjacent to the dredged channel. The costs and expendi-
tures have been $576,856.47 for new work and $242,366.16 for main-
tenance, a total of $819,222.63.
   Proposed operations.-No funds are available and no operations
are contemplated during fiscal year 1945.
   The sum of $25,000 can be profitably expended during fiscal year
1946 in maintenance dredging, by contract, about 40,000 cubic yards
of sand from the entrance channel and basin.
                                                    Cost and financial summary
Cost of new work to June 30, 1944    __                                        __                                                  $576, 856. 47
Cost of maintenance to June 30, 1944                                -               -                -                  __          242, 366. 16

            Total cost of permanent work to June 30, 1944_
Net total expenditures                                                                                          ____
                                                                                                                    _          -819,                222. 63
                                                                                                                                          819, 222. 63
Total amount appropriated to June 30, 1944---------------                                                                                 819, 222. 63


     Fiscal year ending June 30                       1940              1941                  1942                      1943                        1944

Cost of new work..----------- -                     .---------- ------. .               .       .    .     .    .       .      .      .    .    .      .
Cost of maintenance............                     $16, 099. 54   $14, 908.68              $14, 735. 79                    $150.46             $26, 346.72

Total expended...--------------.............         27,164. 70     14, 694.87               14, 964. 24                      90.33                 26,414.61
Allotted---        ---------...                -.    15, 916. 59        8, 697. 34           22, 465. 21 ----           ..---...           --        8, 997. 18
            RIVERS      AND        HARBORS-PROVIDENCE,                 R.   I., DISTRICT                73
Balance unexpended July 1, 1943_ __$17,                                                           417. 43
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941                  ----------
                                                 $10, 500.00
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942                  114. 16
                                                    1,---------
Amount allotted from War Department Civil Appro-
priation Act approved June 24, 1940 ---------     2885.
                                                   2,         84
                                                                                               14, 500. 00

      Amount to be accounted for_ ---------------------                                        31, 917. 43
Deductions on account of revocation of allotment-- ------                                       5, 502. 82

       Net amount to be accounted for------------------------                                  26, 414. 61
Gross amount expended _______--------$29,                 029. 38
                             ---------------
Less reimbursements collected_                         2, 614. 77
                                                                                               26, 414. 61
Amount (estimated) required to be appropriated for
completion of existing project 1__     -      -    -__                        -       -       38, 400. 00
Amount that can be profitably expended in fiscal year
ending June 30, 1946, for maintenance 1------       _                        ____         _   25, 000. 00
1 Exclusive of available funds.                                                                    a
                   9. GREAT SALT POND, BLOCK ISLAND, R. I.

  Location.-On the west shore of Block Island, about 11 miles south-
west by south from Point Judith Harbor, R. I., and 18 miles south-
easterly from Stonington Harbor, Conn. (See U. S. Coast and
Geodetic Chart No. 276.)
   Existing project.-This provides for a channel from the ocean to the
pond 600 feet wide with a central depth of 25 feet for a width of 150
feet, sloping gradually up to a depth of 12 feet in a width of 504 feet;
thence up to low-water level with a 1 on 4 bottom slope; for two riprap
jetties at the entrance, the northerly one 1.200 feet long, and the
southerly one extending 350 feet beyond the 18-foot contour (actual
length, 1,691 feet, including 837 feet built by the State); and stone
revetment and sand fences to protect the banks through the original
beach. All depths refer to mean low water. Mean tidal range is 2.8
feet, and the maximum range, due to the combined effect of wind and
other causes, is 7 feet or more.
   Estimated cost for new work, revised in 1928, is $560,000. The
latest (1918) approved estimate for annual cost of maintenance is
$1,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                           Work authorized                                 Documents


June 3, 1896    Channel and jetties___ ....._     _
                                              ..----.      __
                                                      . .......  H. Doc. No. 57, 54th Cong., 1st sess.
June 13, 1902   Extending south jetty and dredging .------------ Specified in act. Annual Report for
                                                                      1900, p. 1276.


  For latest published map see H. Doc. No. 60, 58th Cong., 2d sess.

  Recommended modifications of project.-OnJune 24,1926, the Chief
of Engineers recommended curtailment of the existing project by
omitting construction of the proposed north jetty (H. Doc. No. 467,
69th Cong., 1st sess.)
74       REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,   1944

   Under date of April 29, 1941, the Chief of Engineers recommended
modification to provide for dredging an entrance channel 100 feet
wide and 12 feet deep at mean low water from Great Salt Pond into
the inner harbor and dredging a basin of about 1.4 acres in that harbor
to the same depth, at an estimated first cost of $16,000, with annual
maintenance of $500, subject to certain conditions of local cooperation
 (H. Doc. No. 330, 77th Cong., 1st sess.).
   Local cooperation.-None required by law. The State of Rhode Is-
land and the town of New Shoreham expended $124,975.90 in dredging
and protecting the channel.
   Terminal facilities.-These consist of a wharf with about 600 feet
of publicly available berthage and several privately owned and
operated small wharves and piers. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year.-Maintenance dredging
of the 25- by 150-foot portion of the entrance channel, by contract, was
commenced on September 16 and was completed on October 24, 1943.
Du ing the period 56,678 cubic yards, place measure,' ordinary mate-
riaT were removed at a cost of $29,914.76, including preliminary ex-
penses, all for maintenance.
   Maintenance dredging of the entrance channel into inner harbor
 (Trims Pond), by hired labor, authorized under section 3 of the River
and Harbor Act approved October 17, 1940, was commenced on October
25 and completed on October 28, 1943. During the period 29,431 cubic
yards, place measure, ordinary material were removed at a cost of
$3,000.
   Total costs and expenditures for the year were $32,914.76, all for
maintenance. These operations restored a depth of 25 feet with width
of 150 feet in the entrance channel into Great Salt Pond except for
minor shoals, and a depth of 10 feet in the entrance channel into inner
harbor except for minor edge shoals.
   Condition at end of fiscal year.-The existing project was.about 62
percent completed. The channel, 300 feet wide and 18 feet deep, with
a central depth of 25 feet over a width of 150 feet, has been dredged
into the pond. The south jetty was completed to its present length
of 1,691 feet in 1905. The controlling depths at mean low water were
as follows: 25 feet in the central portion of the 150-foot width with
minor shoals to about 23 feet at the edge thereof gradually shoaling
to 11 feet at the outer edge of the easterly 75-foot strip and to about 3
feet at the outer edge of the westerly 75-foot strip of channel (May-
June 1944); 10 feet in the entrance channel into inner harbor except
for minor edge shoals (October 1943). The jetty is in fair condition.
To complete the project would require the further widening and deep-
=ening of the channel and the construction of the north jetty. The costs
and expenditures have been $189,036.65 for new work and $86,087.79
for maintenance, a total of $275,124.44.
   Proposed operations.-Nofunds are available and no operations are
contemplated during fiscal year 1945.
   No additional funds can be profitably expended during fiscal year
1946, as this project is in condition to meet the needs of existing
navigation.
            RIVERS AND HARBORS-PROVIDENCE,                                      R.   I., DISTRICT            75
                                  Cost and financial summary
Cost of new work to June 30, 1944_                                                              $189, 036. 65
Cost of maintenance to June 30, 1944_-                         -----------                        86, 087. 79
       Total cost of permanent work to June 30, 1944------------ 275, 124. 44
Net total expenditures_ ------------------------------------     275, 124. 44
Total amount appropriated to June 30, 1944------------------- 275, 124. 44


   Fiscal year ending June 30        1940               1941                 1942        1943         1944

Cost of newwork---------------....--------------------------------------------
Cost of maintenance-- -------------------------------------------------------- $32, 914. 76
Total expended------       -------------- -----------------------------------------
                          .....                                                                       32,914.76
                           --------------
Allotted .........-----------....                 -----------------------------------------.. 3.2,914. 76


Amount allotted from War Department Civil Appropriation Act
approved May 23, 1941                     --                -                                   $17, 042. 10
Amount allotted from War Department Civil Appropriation Act
approved June 24, 1940                                                                             3, 000. 00
Amount allotted from First Deficiency Appropriation Act, Apr. 1,
1941                  __12,                                                                          872. 66
Amount to be accounted for                  ---                -32,                                   914. 76
Gross amount expended                        -         -32,                                           914. 76
Amount (estimated) required to be appropriated for completion of
existing project --                                                                             370, 900. 00

                       10. PAWCATUCK RIVER, R. I. AND CONN.

   Location.-Formedby the junction of the Wood and Charles Rivers
in southwestern Rhode Island, the river flows westerly and southerly
18 miles and enters Little Narragansett Bay about 13 miles east of New
London Harbor. (See U. S. Coast and Geodetic Survey Charts Nos.
358 and 1211).
   Previous projects.-Adopted by the River and Harbor Acts of
March 3, 1871, and August 5; 1886. For further details see page 1752 of
the Annual Report for 1915 and page 69 of the Annual Report for
1933.
   Existing project.-This provides for a channel in Little Narragan-
sett Bay and in the river 10 feet deep at mean low water and 200 feet
wide from Stonington to Avondale, about 4 miles; 100 feet wide from
Avondale to the lower wharves at Westerly, about 3 miles; and 40 feet
wide between the lower and upper wharves of Westerly, about one-half
mile; and for the removal of obstructions at Watch Hill, at the south-
eastern part of Little Narragansett Bay. The mean tidal range is
about 2.5 feet, and the maximum range, due to the combined effect of
wind and other causes, is 7 feet or more.
   The estimate of cost for new work, revised in 1928, is $150,000,
exclusive of amounts expended on previous projects. The latest
 (1928) approved estimate for annual cost of maintenance is $3,000.
   The existing project was authorized by the following river and
harbor acts: The act of June 3, 1896, provided for the present channel
dimensions (Ht. Doc. No. 62, 54th Cong., 1st sess.) ; the act of March 3,
1905, provided for the removal of obstructions at Watch Hill. The
76        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                  1944

latest published maps are in the project document and in the House
Document No. 839, Seventy-sixth Congress, third session.
   Recommended modifications of project.-Under date of May 13,
1940, the Chief of Engineers recommended modification to provide
for a channel 100 feet wide and 10 feet deep at mean low water from
the mouth of the river into Watch Hill Cove; an anchorage basin in
the cove 10 feet deep and about 16 acres in area; and a riprap jetty
200 feet long near the southwest cornerof the basin; at an estimated
first cost of $50,000 for new work with $1,000 annually for mainte-
nance; subject to certain conditions of local cooperation (H. Doc. No.
839, 76th Cong., 3d sess.).
   Ternminal facilities.-These consist of two wharves with a total of
680 feet of docking space, which is adequate for present needs.
   Operations and results during floal year.-None.
   Condition at end of fiscal year.-The existing project was about 57
percent completed. The channels have been dredged to project di-
mensions; except that the channel in the bay has a general width of
100 feet, the channel in the river at Pawcatuck Rocks a width of
80 feet, and there is a slight deficiency in depth at the channel edges
in the vicinity of Rhodes Folly Beacon, due to ledge rock or large
boulders deeply embedded in the bottom. The most obstructive boul-
ders in the vicinity of Watch Hill have been renmoved, the work being
completed in 1913. The controlling depths at mean low water were
as follows: 7 feet through Little Narragansett Bay (1941), thence
9 feet to 1,000 feet below the lower wharves in Westerly, and 5 feet
to the upper wharves (August 1942), 6 feet in natural channel through
Little Narragansett Bay to Watch Hill, and 3 to 7 feet in Watch
Hill Cove (1938 and 1939).
   To complete the project requires widening of the channel to 200
feet to Avondale and the removal of rock at Pawcatuck Rocks and
in the vicinity of Rhodes Folly Beacon. The costs and expenditures
under the existing project have been $85,335.10 for new work and
$119,553.93 for maintenance, a total of $204,889.03.
   Proposed operations.-The allotment of $35,000 made during July
1944 will be applied to maintenance dredging by contract, May to
June 1945, about 70,000 cubic yards of mud and sand from the river
channel to Westerly.
   No additional funds can be profitably expended during fiscal year
1946, as the completion of the above work will leave the project in
condition to meet the needs of existing navigation.
                                   Cost and financial summary
Cost of new work to June 30, 1944_ ___________$218,                            692. 07
Cost of maintenance to June 30, 1944_ ______ _ __ _ _ ___119,                  553. 93

      Total cost of permanent work to June 30, 1944-_-_                  338, 246. 00
Net total expenditures_ __338,                                                246. 00
Total amount appropriated to June 30, 1944         -------------------   338, 246.00

Amount allotted in July 1944_____ _ --------                              35, 000. 00
Amount available during fiscal year 1945_ __ ___                          35, 000. 00
Amount (estimated) required to be appropriated for completion of
existing project 1 _             -             -     -
                                                                            64, 600. 00
I Exclusive of available funds.
              RIVERS AND                  HARBORS-PROVIDENCE,                                 R.   I.,   DISTRICT           77
                                  11. NEW LONDON HARBOR, CONN.

  Location.-On the north shore of Long Island Sound, at its eastern
end and about 14 miles east of the mouth of the Connecticut River.
(See U. S. Coast and Geodetic Survey Chart No. 293.)
  Previous projects.-Adopted by River and Harbor Acts of June
14, 1880, March 3, 1881, and July 13, 1892. For further details see
Annual Reports for 1915 and 1938, pages 1753 and 116, respectively.
  Existing project.-This provides for an entrance channel generally
600 feet wide, widened at the approach to the State pier, 33 feet deep
and about 3.8 miles long from deep water in Long Island Sound to
the State pier; a channel 400 feet or more in width, 23 feet deep, and
about 6,000 feet long skirting the water front of the city; a maneuver-
ing area 0 to 450 feet wide, 23 feet deep, west of the main channel
and south of the State pier; and for dredging Shaws Cove to a depth
of 15 feet. The plane of reference is mean low water, the mean tidal
range being 2.5 feet. The maximum tidal range, due to the com-
bined effects of wind and other causes, is 7 feet or more. The esti-
mate of cost for new work, revised in 1937, was $568,400, exclusive
of amounts expended on previous projects. The latest (1937) ap-
proved estimate for annual cost of maintenance is $3,900.
  The existing project was authorized by the following river and
harbor acts:

       Acts                           Work authorized                                                    Documents


June   13, 1902   Water-front channel----------------------...........................   H. Doc. No. 392, 56th Cong., 1st sess.
June   25, 1910                                    -------------------
                  Dredging in Shaws Cove ............                                    H. Doc. No. 329, 60th Cong., 1st. sess.
                                                                                                                              1
July   27, 1916   Entrance channel---.......---------------------                        H. Doc. No. 613, 63d Cong., 2d sess.
Aug.   26,1.937   Maneuvering area and present project extent of                         Rivers and Harbors Committee Doc.
                                                                                                                        1
                   entrance channel.                                                       No. 82, 74th Cong., 2d sess.


1 Contains latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-These comprise 40 wharves and piers in a
developed frontage of about 3 miles. Five piers are owned and used
by the Federal Government, 1 owned by the city, and 1 by the State.
Nine of the wharves are entirely or in part open to general public use
and 2 by agreement with the owners. Three wharves have direct
rail connections. The total available berthage space is about 27,000
feet. Facilities are considered adequate for existing commerce. (For
further details see Port Series No. 18, Corps of Engineers.)
   Operations and results during fiscal year.-There were no operations
and no costs. Expenditures were $24,924.71 for accounts payable from
the preceding fiscal year.
   Condition at end of fiscal year.-The existing project was completed
in 1938. The controlling depths at mean low water are: Entrance
Channel from Long Island Sound to State Pier, about 32 feet (June
1942 and January 1943) ; water-front channel, 23 feet except for minor
shoal to 19 feet in south reach (May 1943); Winthrop Cove, 22 feet
 (1941); and Shaws Cove, 15 feet (1941). The costs and expenditures
under the existing project have been $567,974.19 for new work and
$219,029.37 for maintenance, a total of $787,003.56.
78            REPORT OF CHIEF OF ENGINEERS,                                U. S. ARMY,                      1944

   Proposed operations.-Nofunds are available and no operations are
contemplated during fiscal year 1945.
   No additional funds can be profitably expended during fiscal year
1946, as the project is in condition to meet the needs of existing naviga-
tion.
                                                  Cost and financial summary
Cost of new work to June 30, 1944_ "          -$608,                                                               774. 19
Cost of maintenance to June 30, 1944-------------------------                                                 219, 029. 37
       Total cost of permanent work to June 30, 1944--- --------                                              827, 803. 56
Net total expenditures -------------------------------------                                                  827, 803. 56
Total amount appropriated to June 30, 1944                                                                    827, 803. 56


    Fiscal year ending June 30                         1940    1941          1942                1943                 1944

Cost of new work ..-----------------------------------------------------
                  -------------------------------------
Cost of maintenance..                                                         $361.66       $168, 628. 10

Total expended-- -----------------------------                                   7. 50       144, 057. 55            $24, 924. 71

Allotted       --------------------------------------------                175,150.00 ---               .      -     -6,160.24



Balance unexpended July 1, 1943 -                                                                             $31, 084. 95
Deductions on account of revocation of allottment---------                                                      6, 160. 24

Net amount to be accounted for _                                                            __                     24, 924. 71
Gross amount expended_ ______$24,                                                           945. 23
Less reimbursements collected-----_                                   -    -_-20.                52
                                                                                              --                   24, 924. 71

                                               12. THAMES RIVER, CONN.

   Location.-This is a tidal estuary varying in width from about 400
feet to three-fourths of a mile, and extending from the junction of
the Yantic and Shetucket Rivers at Norwich, Conn., 15 miles south-
erly to Long Island Sound at New London. (See United States Coast
and Geodetic Survey Chart No. 359.)
   Previous projects.-Adopted by the River and Harbor Acts of July
4, 1836, and March 3, 1879. For further details see page 1754 of
Annual Report for 1915, and page 118 of Annual Report for 1938.
   Existing project.-This provides for a channel 25 feet deep and 250
feet wide to the upper end of Bartletts Crossover and thence to Nor-
wich generally 200 feet wide, with increased width in the bends,
through Long Reach, and at the head of navigation, a total distance
of about 8.6 miles; the construction of five training walls of pile
and stone or riprap, having their tops at mean high water and with an
aggregate length of about 13,800 feet, located, respectively, at Mo-
hegan, Trading Cove, Long Rock, Rolling Mill, and Norwich, and the
removal of obstructions in the Shetucket River at Norwich. The
plane of reference is mean low water, the mean tidal range being 2.5
feet at New London, and 3.1 feet at Norwich. The maximum range,
due to the combined effect of wind and other causes, is 7 feet or more.
   The estimate of cost for new work, revised in 1935, is $1,508,400,
exclusive of amounts expended on previous projects. The latest
 (1935) approved estimate for anntial cost of maintenance is $29,300.
              RIVERS AND HARBORS-PROVIDENCE,                          R. I., DISTRICT                  79
  The existing project was authorized by the following river and
harbor acts:
       Acts                        Work authorized                              Document


Aug. 2,1882       Training walls___--------------------------      Annual Report, 1882, p. 606.
June 25. 1910     Removal of obstructions in the Shetucket River   H. Doc. No. 397, 61st Cong., 2d sess.
Jan. 21,1927      Channel 18 feet deep above Allyns Point- .-.-    H. Doc. No. 107, 69th Cong., 1st sess.
July     3,1930   Present project dimensions of channel up to      Rivers and Harbors Committee Doc.
                                                                                                  1
                    Allyns Point.                                    No. 14, 71st Cong., 2d sess.
Aug. 30,1935      Present project dimensions of channel above      Rivers and Harbors Committee Doe.
                   Allyns Point.                                     No. 18, 74th Cong., 1st sess.A


  I Contains latest published maps.

   Recommended modifications of project.--Under date of June 13,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for increasing the width of channel oppo-
site the United States submarine base by an average of 350 feet,
at an estimated first cost of $120,000, with annual maintenance of
$1,700, in addition to that now required (H. Doc. No. 367, 76th Cong.,
1st sess). This improvement was accomplished by the United States
Navy Department in 1940 at a cost of about $125,000 from special
funds allotted the Navy for extension of the submarine base.
   Terminal facilities.-Wharves along the river and at Norwich are
mainly of the bulkhead type, both with and without pile aprons. The
facilities are considered adequate for the existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was prac-
tically completed. The training walls were completed in 1906, except
the upper end of the Rolling Mill dike, which is replaced by adjacent
shore improvements. The training walls are in fair condition. The
head of navigation is at Norwich about 15 miles above the mouth.
The controlling depth at mean low water (not full width) was 25 feet
to upper end Bartlett Crossover, except for minor shoals (August 1943),
thence 25 feet to Norwich except for minor shoals (1939 and 1941).
To complete the project requires slight widening of the channel at the
upper end of Long Reach. The costs and expenditures under the
existing project have been $1,323,571.87 for new work and $485,659.27
for maintenance, a total of $1,809,231.14.
   Proposed operations.-No funds are available and no operations are
contemplated during fiscal year 1945.
   The sum of $100,000 can be profitably expended during fiscal year
1946 in maintenance dredging, by contract, about 200,000 cubic yards
of mud and sand from the river channel between the submarine base
and Allyn Point.
                                      Cost and financial summary
Cost of new work to June 30, 1944                       _                              $1, 471, 919. 46
Cost of maintenance to June 30, 1944---------------------                                  522, 255. 14
       Total cost of permanent work to June 30, 1944---                                 1, 994, 174. 60
Net total expenditures___                                                               1, 994, 174. 60
Total amount appropriated to June 30, 1944     -----                                    1, 994, 174. 60
80            REPORT OF CHIEF OF ENGINEERS,                                                  U.    S. ARMY,             1944


    Fiscal year eiding June 30                              1940              1941             1942            1943                        1944


Cost of new work . .........------------            $367, 305. 60       $261, 584. 11         $2, 279. 60 .     -------................
Cost of maintenance.---                    --------------                   47, 697.33     ..----_---.--------------.--------------
       Total cost.......----------..        --.       367, 305. 60          309, 281. 44       2, 279. 60          _-                              -____________


Total expended..............--------------.           332, 960. 41          332, 716. 55      12, 890.61      $1, 000. 00                 ---

Allotted     .................------------------      125, 000.00    -18,                                         859. 64                  -$31,     500



Balance unexpended July 1, 1943_   ____________$31,                                                                                         500. 00
Amount allotted from War Department Civil Appropriation
  Act approved May 23, 1941--__- -    -----------                                                                                    20, 000. 00

      Amounttobeaccountedfor-----------------51,                                                                                         500. 00
Deductions on account of revocation of allotment--------------                                                                       51, 500. 00
Gross amount expended------------------------------------402.                                                                                        62
Less reimbursements collected                                                                                                                   402. 62
Amount (estimated) required to be appropriated for completion
  of existing project_ _____15,                                                                                                             000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946 for, maintenance-------------------------                                                                         100, 000. 00

                  13. CONNECTICUT RIVER BELOW HARTFORD, CONN.

    Location.-This river has its source in Connecticut Lake in northern
New Hampshire, flows southerly 380 miles, and empties into Long
Island Sound at Saybrook, Conn., 14 miles west of New London.
Hartford, now the head of commercial navigation, is 52 statute miles
by channel from the mouth. (See U. S. Coast and Geodetic Survey
charts Nos. 215, 254, 255, and 256.)
    Previous projects.-Adopted by the River and Harbor Acts of
July 4, 1836, and July 11, 1870. For further details see page 1754,
Annual Report for 1915, and page 120, Annual Report for 1938.
    Existing project.-This provides for a channel 15 feet deep at mean
low water, 300 feet wide from the mouth to the Lyme railroad bridge,
about 3.4 miles, and thence 150 feet wide to Hartford, the channel to
be obtained by dredging and the construction of dikes, training walls,
revetments, and accessory works; for two riprap jetties at the mouth
  of the river, the tops to be 5 feet above high water and 6 feet wide,
the easterly one about 2,300 feet and the westerly about 2,750 feet in
  length; and for a training dike about 3,700 feet long at Hartford.
The mean tidal range is 3.5 feet at the mouth and, at summer stage
about 1 foot at Hartford. The maximum tidal range at the mouth,
  due to wind or other causes, is 8 feet or more. At Hartford the usual
  rise due to spring freshets is between 16 and 24 feet above mean low
  water. The maximum recorded freshet at Hartford (March 1936)
  was 35.5 feet above mean low water. Below Middletown the height
  of the crest of the freshet decreases rapidly.
     The estimate of cost for new work, revised in 1935, is $918,000. The
  latest (1932) approved estimate for annual cost of maintenance is
  $53,000.
             RIVERS AND          HARBORS-PROVIDENCE,                    R. I.,   DISTRICT             81

  The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                  Documents

June 10, 1872   Jetties at the mouth_               _
                                                  __ _
                                          -----.------.    ..        Present project dimensions approved
                                                                       by the Chief of Engineers, Dec. 22,
                                                                   1887.
Mar. 3, 1881    The Hartford dike-            ____ _____       .Present
                                                                __       project dimensions authorized
                                                                   by the Chief of Engineers in 1889.
Feb. 27, 1911   Present project dimensions of the channel over H. Doc. No. 1294, 61st Cong., 3d sess.
                  Saybrook Bar.
Mar. 2, 1919    Dikes, training walls, and revetments -- -- . IH.Doc. No. 132, 65th Cong., 1st sess.
Aug. 30. 1935   Present project dimensions of channel and addi- H. Doc. No. 49, 73d Cong., 1st sess. 1
                  tional dikes, training walls, revetments, and
                  accessory works.


  1 Contains latest published maps.

   Recommended modifications of project.-Under date of June 14,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for an anchorage in North Cove in the
town of Old Saybrook, Conn., connected with deep water in the Con-
necticut River by a channel 100 feet wide and 11 feet deep, all at an
estimated cost of $140,400 for new work, with $3,000 annually for
maintenance, in addition to the amount now required, subject to certain
conditions of local cooperation (H. Doc. No. 368, 76th Cong., 1st sess.).
   Local cooperation.-The River and Harbor Act of August 30, 1935,
authorized the 15-foot channel up to Hartford and additional dikes,
training walls, and revetments, subject to the provision that local inter-
ests shall furnish, free of cost to the United States, suitable areas for the
disposal of dredged material during initial construction and for future
maintenance as and when needed. Areas have been furnished where
required, and it is understood that future requirements will be met.
   Terminal facilities.-There are two or three wharves at each of the
river towns, one or more in each town being open to public use. At
Hartford and at Middletown there is approximately one-half mile of
wharf frontage along the west bank of the river. The facilities are
considered adequate for existing commerce.
    Operations and results during fiscal year.-Tidal studies were con-
tinued at a cost of $2.10 for new work. Construction of training dikes
at Glastonbury Bend, by contract in force at the beginning of the
year, was resumed on July 12, 1943, and completed on August 6, 1943.
During the period 119 cords of brush were placed and an adjustment
of 1,047 feet was made in the quantity of piles previously driven,
all at a cost of $4,850.06 for new work. These operations completed a
series of 8 pile, timber and brush training dikes totaling 2,328 feet in
length at Glastonbury Bend.
    Maintenance dredging of bars above Middletown, by contract in
force at the beginning of the year, was resumed on July 26, 1943, and
completed on December 2, 1943. During the period 231,316 cubic
yards ordinary material were removed from Hartford, Clay Banks
Upper, Naubuc, Press Barn, Glastonbury Upper, Glastonbury Two-
Piers, Dividend, Pistol Point, Gildersleeve Island and Portland Bars
at a cost of $89,674.60. Maintenance dredging of Cobalt Shoal, below
           616634-45-pt. 1, vol. 1-       6
82      REPORT OF CHIEF OF ENGINEERS,         U.   S.   ARMY,   1944

Middletown, by contract, was commenced on December 3 and com-
pleted on December 10, 1943. During the period 14,036 cubic yards
ordinary material were removed at a cost of $5,477.17. Preliminary
costs on this work were $867.90. These operations restored project
dimensions on the above-mentioned bars.
   Maintenance dredging on the bars below Middletown with the U. S.
hopper dredge Absecon, commenced on June 16, 1944, was in progress
at the end of the year. During the period 90,420 cubic yards, bin
measurement, ordinary material, were removed from Calves Island,
Haddam Island, Rock Landing, and Higganum Creek bars at a cost
of $14,124.28. Preliminary expenses on the maintenance of these
and other bars below Middletown were $2,238.74. These operations
restored project dimensions on the four bars worked on. Preliminary
surveys for proposed dredging of river bars above Middletown cost
$788.18.
   Repairs to Press Barn dikes by hired labor were commenced on
August 19 and completed on September 14, 1943. During the period
57 cords of brush were placed at a cost of $2,697.45 to completely restore
the brush on the three piles and timber dikes. Repairs to revetments
by contract were commenced on September 15 and completed on No-
vember 30, 1943. During the period a total of 1,000 long tons of stone
were placed on revetments at Cys Hollow, Naubue, Crow Point, Press
Barn, Glastonbury Upper Bar and Gildersleeve revetments at a
cost of $3,950.66, thus restoring these structures to good condition.
Preliminary costs on repairs to dikes and revetments totalled $300.74.
Debris was removed on September 8, 1943, from the vicinity of Clay
Banks Upper Bar at a cost of $162.60 for maintenance.
   Total costs during the year were $4,852.16 for new work and $120,-
282.32 for maintenance, a total of $125,134.48. Expenditures were
$113,847.15.
   Condition at end of fiscal year.-The existing project was about 84
percent completed. The 15-foot channel from the mouth to Hartford
was completed iii 1937. The Saybrook jetties and training walls at
Hartford, Clay Banks, and Sears Shoal were completed in 1915. The
stone dikes and timber spurs at Pistol Point, Glastonbury, Press Barn,
Naubuc, Cys Hollow, and Clay Banks were completed in 1927. Tim-
be'r pile dikes at Press Barn were completed in 1940 and at Glastonbury
Bend in 1943. The Clay Banks, Cys Hollow, Naubuc, Press Barn,
Glastonbury (including Two Piers), and Gildersleeve Island Reaches
have been revetted. The jetties, training walls, dikes and revetments
are generally in good condition. The head of commercial navigation
is at Hartford 52 miles by channel from the mouth. A dam at Holy-
oke, Mass., 34 miles above Hartford, completely interrupts navigation.
   Due to the spring freshets of 1944 the channel dimensions are some-
what diminished. The controlling depths at mean low water were
12 feet on Saybrook Outer Bar except edge shoals (May 1944), thence
15 feet to Higganum except minor edge shoals (June 1944), and thence
12 feet to Hartford (May and June 1944). To complete the project
requires the construction of additional permanent works. The costs
under the existing project have been $768,882.73 for new work and
$1,200,300.46 for maintenance, a total of $1,969,183.19. Expenditures
have been $1,955,236.23.
           RIVERS AND HARBORS-PROVIDENCE,                               R. I., DISTRICT                       83
  Proposed operations.-Fundsunexpended on June 30, 1944, amount-
ing to $123,328.92, and $150,000 allotted during July 1944, a total of
$273,328.92, will be applied as follows:
Accounts payable June 30, 1944 _'__-_-_----_                                                  $16, 015. 72
New work: Tidal study, Hartford to Saybrook, and studies and
  designs for additional training works, in progress                                               4, 132. 47
Maintenance:
    Dredging on river bars below Middletown by United States
       hopper dredge, in progress, to be completed in August 1944--                               38, 136. 98
    Dredging on river bars above Middletown by a United States
       hopper dredge, August to September 1944-                                                    21, 711. 82
    Repairs to existing permanent works by hired labor, August to
       October 1944-------------------------------------                                            5,000 00
    Dredging on river bars below Middletown by a United States
       hopper dredge, for about 2 months in the spring of 1945                         _           45, 000. 00
    Dredging on river bars above Middletown, by contract, June to
       September 1945, about 200,000 cubic yards----------------                                   82, 500. 00
Unallocated balance------------------------------------------                                      60, 831. 93
        Total -------------------------------------------------                                   273, 328. 92
  The sum of $130,000 can be profitably expended during the fiscal
year 1946 as follows:
Maintenance:
    Dredging on river bars above Middletown, by contract, June to
      September 1946, removing about 200,000 cubic yards of sand _- $80, 000
    Dredging on river bars below Middletown, using a United States
      hopper dredge, about 2 months in the spring of 1946----------  45, 000
    Repairs to existing permanent works, by hired labor------------   5, 000

        Total for maintenance-----------------------------------                                     130, 000

                                    Cost and financial summary
Cost of new work to June 30, 1944_ ------------------------                              $1, 056, 257. 02
Cost of maintenance to June 30, 1944---- ---------------                                   1,566, 648. 93
      Total cost of permanent work to June 30, 1944 ------                                 2,622, 905. 95
Undistributed costs June 30, 1944---------------------------                                   2, 068. 76
      Net total cost to June 30, 1944--- ------------------                                2,624, 974. 71
Minus accounts payable June 30, 1944----- ----------------                                    16, 015. 72
     Net total expenditures_--- ---------                  _                               2,608, 958. 99
Unexpended balance June 30, 1944 --------------------------                                  123, 328. 92
        Total amount appropriated to June 30, 1944------------                             2, 732, 287. 91


   Fiscal year ending June 30          1940           1941           1942           1943               1944

Cost of new work ---------------     $45, 936. 76    $3, 571.50     $3, 197. 63   $23, 251.72          $4, 852.16
Cost of maintenance .... .. ..       152, 653. 78    73, 714. 60    91, 538. 78      7, 380. 57       120, 282. 32
     Total cost_ ----------------    198, 590. 54    77, 286. 10    94, 736. 41    30, 632. 29        125, 134. 48
Total expended   ----------------    197, 580. 13    91, 486. 40    96, 741.89     27, 739. 50        113, 847. 15
Allotted--.......-------    -----     90, 000. 00   135, 589. 28   105, 000. 00    95, 000. 00       -15,   000.00
 84           REPORT OF CHIEF OF ENGINEER,                           U. S. ARMY,         1944

Balance unexpended July 1, 1943_---------------------------                               $252, 176. 07
Deductions on account of revocation of allotment--------- -15,                                  000. 00

        Net amount to be accounted for_----           - -_                                   237, 176. 07
Gross amount expended_----------------------      $114, 022 04
Less reimbursements collected_--------------------      174. 89
                                                                                              113, 847. 15

       Balance unexpended June 30, 1944---------------------                                 123, 328. 92
Outstanding liabilities June 30, 1944--- ----------                                          17, 598. 13

      Balance available June 30, 1944 -------------------                                    105, 730. 79
Amount allotted in July 1944 ______     -    -__                                            150, 000. 00
             Amount available during fiscal year 1945              ------------              255, 730. 79
Amount (estimated) required to be appropriated for completion
  of existing project 1  ____     __ _-_        _--                                           131, 300. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1    ----------                                             130, 000. 00
  1 Exclusive of available funds.


                              14. BRANFORD HARBOR, CONN.

   Location.-On the north shore of Long Island Sound, 5 miles east
of New Haven Harbor. (See U. S. Coast and Geodetic Survey Chart
No. 217.)
   Existing project.-This provides for a channel 81/2 feet deep and
100 feet wide through the shoals at the mouth of the harbor, about one-
half mile and of the same depth, width, and length between the lower
and upper wharves in Branford River. The plane of reference is
mean lower water. The mean tidal range is 5.9 feet, and the maximum
range, due to the combined effect of wind and other causes, is 10 feet
or more.
   The estimate of cost for new work, revised in 1905, was $10,000. The
latest (1928) approved estimate for annual cost of maintenance is
$2,500.
   The existing project was authorized by the following river and
Sharbor       acts:

      Acts                     Work authorized                                    Documents

June 13, 1902    Channel between upper and lower wharves in the      H. Doc. No. 100, 56th Cong., 2d sess.,
                  river,                                               and Annual Report for 1901, p. 1188.
Mar. 2, 1907     Channel at the mouth of the harbor .      -..--      Specified in act.


  For latest published maps seeH. Doc. No. 1292, 64th Contig., 1st sess.


   Terminal facilities.-These facilities, comprising two wharves near
the head of the harbor and one at the mouth of the river are consid-
ered adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Conditionat end of fiscal year.-The project was completed in 1907.
The controlling depths at mean low water were as follows: 7 feet in
the outer harbor, thence 8.5 feet to head of navigation for widths of
50 to 100 feet, shoaling to 6 feet at channel edges (September 1942).
         RIVERS AND     HARBORS--PROVIDENCE,           R. I.,     DISTRICT        85
The cost and expenditures have been $9,537.45 for new work and
$73,559.49 for maintenance, a total of $83,096.94.
  Proposed operations.-An allotment of $30,000 to be requested will
be applied as follows:
Maintenance:
   Dredging about 40,000 cubic yards of mud and sand from the
      harbor channel, by contract, April to May 1945          $20, 000
   Dredging about 20,000 cubic yards of mud and sand from the
      river channel, by contract, May to June 1945   -         10, 000

        Total                                              -- -       --      30, 000
  No additional funds can be profitably expended during fiscal year
1946, as completion of the above work will leave the project in condi-
tion to meet the needs of existing navigation.
                          Cost and financial summary
Cost of new work to June 30, 1944__                                        $9, 537. 45
Cost of maintenance to June 30, 1944------------------                     73, 559. 49
       Total cost of permanent work to June 30, 1944-------                83, 096. 94
Net total expenditures __------------------------------                    83, 096. 94
Total amount appropriated to June 30, 1944-------------_                   83, 096. 94

                     15. NEW HAVEN HARBOR, CONN.

   Location.-On the north shore of Long Island Sound, about 67
miles to the east of New York City. (See U. S. Coast and Geodetic
Survey Chart No. 218.)
   Previous projects.-Adopted by River and Harbor Acts of August
30, 1852, March 3, 1871, June 10, 1872, and for West River, March 3,
1905. For further details, see page 1755 of Annual Report for 1915
and page 127 of Annual Report for 1938.
   Existing project. This provides for a channel 25 feet deep, 400
feet wide, and 31/2 miles long from Long Island Sound to opposite
Fort Hale; thence of same depth 500 feet wide (increased to 1,111
feet at the turn opposite Long wharf) 2 miles to Tomlinson Bridge;
two anchorage basins below Tomlinson Bridge of 16- and 15-foot
depths; a pile-and-riprap dike, total length about 4,200 feet, to con-
tract tidal flow at Fort Hale Bar; a channel 12 feet deep and 100 to
150 feet wide, from the southwest corner of the 16-foot anchorage
Basin via Oyster Point and the West Haven wharf front to Kimberly
Avenue Bridge; thence 12 feet deep and prevailing width of 75 feet
up West River approximately to the railroad bridge, and an anchor-
age basin 6 feet deep in West River opposite Mars wharf; a channel
100 feet wide and 12 feet deep from the 15-foot anchorage basin to-
ward Brewery Street, about 1,500 feet; a channel 200 feet wide and 18
feet deep up Quinnipiac River to Ferry Street Bridge, and thence 200
feet wide and 16 feet deep to Grand Avenue; a channel up Mill River
12 feet deep, 200 feet wide, to the junction of the two branches above
Chapel Street, thence to Grand Avenue, 100 feet wide in the East
Branch and gnerally 125 feet wide in the West Branch; and the re-
moval of certain obstructive rocks in Morris Cave. All depths refer
to mean low water, the mean tidal range being 6.2 feet. The maxi-
mu n tidal range, due to the combined effect of wind and other causes,
is 10 feet or more.
86            REPORT OF CHIEF OF ENGINEERS,                             U.    S.   ARMY,            1944

   The estimate of cost for new work, revised in 1941 is $975,000, ex-
clusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $57,000.
   The existing project was authorized by the following river and
harbor acts:
       Acts                          Work authorized                                     Documents

Aug.    2, 1882    Sandy Point dike _--------------.             .       Plans approved by a Board of Engi
                                                                             neers, Oct. 2, 1882.
Mar.    3, 1899    The 16-foot anchorage basin_                          H. Doc. No. 82, 55th Cong., 1st sess.
June 25, 1910      Brewery Street Channel, removal of rocks in           H. Doc. No. 1159, 60th Cong., 2d sess.
                    Morris Cove and present project dimensions of
                     the 15-foot basin.
July 25, 1912      Present project dimensions of the channels in Mill    H. Doc. No. 26, 62d Cong., 1st sess.
                  River.
     Do ___ .. Present project dimensions of the West River              H. Doc. No. 535, 62d Cong., 2d sess.
                  Channel and anchorage.
July     3, 1930   Present project dimensions of channel in Quinni-      H. Doc. No. 686, 69th Cong., 2d sess.
                     piac River.
Aug. 30, 19351     The 25-foot channel----_ -        ._-_-_.-------H.         Doc. No. 479, 72d Cong., 2d sess.


  1 Also Public Works Administration, Sept. 6, 1933.

  The latest published map is in H. Doc. No. 307, 76th Cong., 1st sess.

   Recommended modifcations of project.-Under date of May 25,
1939, the Chief of Engineers recommended modification of the exist-
ing project for New Haven Harbor, Conn., so as to provide a main
channel 30 feet deep at mean low water, 400 to 1,111 feet wide from
Long Island Sound to Tomlinson Bridge, two anchorage basins, one
30 feet deep, 1,100 feet wide, and 4,900 to 2,700 feet long, and one 16
feet deep, 600 feet wide, and 2,700 feet long, at the head of the harbor,
south of Long Wharf and west of the main channel, at an estimated
first cost of $1,673,000, with annual maintenance of $12,250 in ad-
dition to that now required; and a channel in Quinnipiac River 27
feet deep at mean low water, 350 to 170 feet wide from Tomlinson
Bridge to Ferry Street Bridge with a turning basin of the same
depth, about 31/-2 acres in area at the junction of Mill and Quinnipiac
Rivers, at an estimated first cost of $835,000, with annual maintenance
of $1,200 in addition to that now required; subject to certain condi-
tions of local cooperation (H. Doc. No. 307, 76th Cong., 1st sess.).
   Terminal facilities.-The wharves and piers served by this improve-
ment are grouped near the head of the main harbor; on both sides of
Mill River between Chapel Street and Grand Avenue; on both sides
of Quinnipiac River throughout the greater part of its improved por-
tion; at Oyster Point; and along the westerly side of West River. The
total length of berthing space available at 50 wharves or piers is about
16,920 feet. One of the wharves is open to public use, 6 are open to
public use upon agreement with the owners, and 9 have direct rail
connections.
   The facilities are not considered adequate, and various plans have
been prepared and considered by the municipality for extensive addi-
tions and improvements. (For further details see Port Series No. 18,
Corps of Engineers.)
   Operationsand results during fiscal year.-None.
   Conditionat end of fiscal year.-The existing project was practically
completed in 1935, the Sandy Point dike having been completed in
                 RIVERS            AND HARBORS-PROVIDENCE,                     R.     I.,      DISTRICT                        87

1890. The latter is in poor condition. The controlling depths at
mean low water are as follows: Main channel to within 1,000 feet of
Tomlinson Bridge, 22 feet, thence to within 300 feet of Tomlinson
Bridge, 18 feet (December 1943) ; 16-foot anchorage, 9 to 18 feet (1942);
15-foot anchorage, 16 feet except at edges (1940) ; Brewery Street Chan-
nel, 12 feet except at edges (1940); West Haven 6-foot anchorage, 0
to 6 feet (January 1944); West River, 9 feet to Kimberly Avenue
Bridge, thence 6 feet to head of navigation (January 1944) ; Mill River,
12 feet, (March 1943) ; Quinnipiac River 17 feet to Ferry Street Bridge,
thence 11 feet except at edges to Grand Avenue Bridge (December
1943).
   To complete the project requires the deepening of the main channel
for about 300 feet immediately below Tomlinson Bridge. The total
costs and expenditures, all funds, under the existing project have
been $2,078,717.33, of which $609,364.08 regular funds, and $350,083.75,
Public Works funds, a total of $959,447.83, was for new work, and
$1,119,269.50 for maintenance.
   Proposed operations.-An allotment of $200,000 to be requested will
be applied to maintenance dredging, by contract, from August 1944 to
June 1945, about 500,000 cubic yards of mud and sand from the main
channel north of Fort Hale.
  The sum of $150,000 can be profitably expended during fiscal year
1946 as follows:
Maintenance:
   Dredging about 200,000 cubic yards of mud and sand from
      the main channel south of Fort Hale by contract---------- --- $100, 000
   Dredging about 100,000 cubic yards of mud and sand from the
      West River channel by contract_               --------_         50, 000

                Total--------------------------------------------------                                            150, 000

                          Cost and financial summary
Cost of new work to June 30, 1944_-----------_          -    $1, 291, 073. 49
Cost of maintenance to June 30, 1944------------------ ------ 1, 151, 839. 50
       Total cost of permanent work to June 30, 1944-----------                                         2, 442, 912. 99
Net total expenditures----------------------------------                                                2,442, 912. 99
Total amount appropriated to June 30, 1944------------- -----                                           2, 442, 912. 99

     Fiscal year ending June 30                1940          1941          1942                  1943                1944

Cost of new work---- -----      --------                    $5, 145, 59   $6, 224. 95
Cost of maintenance...-----------        $31, 629.12        54, 582. 03       886. 91          $38, 651. 88    -          --

        Total cost------_             -----   31, 629. 12   59, 727. 62    7,111. 86            38, 651. 88
Total expended---------------44, 864. 50                    54, 990. 23   11, 845. 40           38, 651.88-

Allotted------------------------------35,                      764. 72    85, 769.36 -------                       -74,   830. 40


Balance unexpended July 1,1943 _                                                                              $74, 830. 40
Amount allotted from War Department Civil Appropriation Act
approved June 24, 1940-----------------------------------                                                           635. 28
      Amount to be accounted for-----------------------                                                       75, 465. 68
Deductions on account of revocation of allotment------ --------                                               75, 465. 68
Amount (estimated) required to be appropriated for completion
of existing project _---_---_---_---------_--------------_                                                    15, 000. 00
Amount that can be expended in fiscal year ending June 30, 1946,
for maintenance--_      ____-__-_-__-_-_-_150,                                                                      000. 00
88          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                     1944

                                    16. HOUSATONIC RIVER, OONN.

   Location.-Rises in Northwestern Massachusetts, flows southerly 130
miles through Massachusetts and Connecticut, and empties into Long
Island Sound at Stratford, 5 miles east of Bridgeport Harbor. (See
U. S. Coast and Geodetic Survey Chart No. 219.)
   Eoisting project.-This provides for a channel 18 feet deep at mean
low water and 200 feet wide from the mouth to the lower end of
Culvers Bar, about 5 miles, and thence 7 feet deep and 100 feet wide
to Derby and Shelton, about 8 miles; a riprap breakwater at the
mouth, consisting of an inner arm, 3,250 feet long, 3 feet high above
mean low water, top width 6 feet, side slopes 1 on 1, and an outer
arm 2,571 feet long, 6 feet high above mean high water, top width
12 feet, outer slope 1 on 2, inner slope 1 on 1; riprap dike in the river
below Stratford not to exceed 1,500 feet in length; and a riprap jetty
163 feet long at Sow and Pigs Rocks. The mean tidal range, exclu-
sive of the winter season and freshets, is 6.7 feet at the mouth, 5.5
feet at Stratford, and 5 feet at Shelton; the extreme range due to
combined effect of wind and other causes is about 11 feet at the mouth,
diminishing toward the head. The spring freshets occasionally rise
to a height of 18 feet or more above summer low water, but only
average about 12 feet above that datum.
    The estimate of cost' for new work, revised in 1928, is $810,000, of
which $150,000 is to be contributed by local interests. The latest
 (1930) approved estimate for annual cost of maintenance is $19,000.
    The existing project was authorized by the following river and har-
bor acts:

     Acts                                 Work authorized                                           Documents


IMar. 3, 1871    A jetty at Sow and Pigs Reef and the present                          H. Doc. Nb. 95, 41st Cong., 3d sess.,
                   project width of the channel across the outer                        and Annual Report, 1871, p. 781.
                   bar.
Aug. 11, 1888    Breakwater at the mouth and the present project                       S. Doc. No. 103, 50th Cong., 1st sess.,
                   dimensions of the river channel above the lower                       and Annual Report, 1888, p. 554.
                   end of Culvers Bar.
                 The Stratford dike -------------------....................------...   Authorized   by Department; project
                                                                                         submitted by the district engineer
                                                                                        July 15, 1892.
July   3, 1930   Present project dimensions of channel up to Cul-                      H. Doc. No. 449, 70th Cong., 2d sess.'
                   vers Bar.

  1Contains latest   published map.

   Local cooperation.-The River and Harbor Act of July 3, 1930, au-
thorized, the 18-foot channel up to Culvers Bar subject to the provision
that no work shall be started until local interests have contributed
$150,000 toward the cost of the work, and provided further that local
interests shall furnish, free of cost to the United States, suitable bulk-
headed areas for the deposit of dredged material, or in lieu thereof
an additional $50,000 in cash. These conditions have not been com-
plied with. Spoil areas were assured, but pledges of cash cooperation
were insufficient.
   Terminal facilities.-Thereare three wharves for mmercial use at
Stratford, one at Devon, and eight at Shelton and Derby. The facili-
ties are considered adequate for the existing commerce.
              RIVERS       AND          HARBORS-PROVIDENCE,                            R. I.,    DISTRICT              89

  Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was about 29
percent completed. The up-river channels were completed in 1893.
The breakwater at the mouth was completed in 1914, except that the
outer arm has a top width of 8 feet and outer slope of 1 on 11/2 instead
of project dimensions; the Stratford dike was completed to its present
length of 1,255 feet in 1916, and the jetty at Sow and Pigs Rocks was
completed in 1871. The breakwater is in good condition and the dike
and jetty in fair condition. The head of navigation is at Derby and
Shelton about 14 miles by channel above the mouth. The controlling
depths at mean low water in the channel were as follows: 7 feet to lower
end Culvers Bar (August 1943); thence 5 feet to Shelton (September
1943).
  To complete the project requires the enlargement of the outer arm
of the breakwater to provide a top width of 12 feet and an outer slope
of 1 on 2, which is not required at this time, the extension of the
Stratford dike not more than 245 feet, and deepening and widening
of the channel from the mouth up to the lower end of Culvers Bar.
The costs and expenditures have been $234,364.92 for new work and
$231,935.14 for maintenance, a total of $466,300.06.
  Proposed operations.-The allotment of $25,000 made during July
will be applied to maintenance dredging, by contract, May to June
1945, about 50,000 cubic yards of mud and sand from the river bars.
   No additional funds can be profitably expended during fiscal year
1946, as the completion of the above work will leave the project in
condition to meet the needs of existing navigation.
                         Cost and financial summary
Cost of new work to June 30, 1944_               .$234,                                                         364.      92
Cost of maintenance to June 30, 1944 ------------------------                                            231,   935.      14
      Total cost of permanent work to June 30, 1944------------                                          466,   300.      06
Net total expenditures----      -------------                                                            466,   300.      06
Total amount appropriated to June 30, 1944                               ------------------              466,   300.      06

     Fiscal year ending June 30                 1940              1941              1942          1943          1944

Cost of new work-.         .   .         ..        ..--------------
                                                          -----------------------------------------------
Cost of maintenance                           $10, 833. 85    $18, 184. 56 ...........
Total expended_-_ ..               --           8, 639. 01     20, 379. 40__________________                    ______
         -----------------------
Alloted....                                    12, 200. 00   --   3, 750.10         -$431.49--   --- ---    -    -__--_


Amount allotted in July 1944_---        ------------                                                     $25, 000.00
Amount available during fiscal year 1945 -----------------------                                          25, 000. 00
Amount (estimated) required to be appropriated for completion of
   existing project 1 2-         --                                       .------          --     _      425, 000. 00
  1Exclusive of available funds.
2   In addition $150,000 is to be contributed by local interests.

                               17. BRIDGEPORT HARBOR, CONN.

   Location.-On the north shore of Long Island Sound, about 51 miles
east of New York City. (See U. S. Coast and Geodetic Survey Chart
No. 220.)
   Previous projects.-Adopted by the River and Harbor Acts of July
4, 1836, March 3, 1871, and (for Black Rock Harbor) July 5, 1884. For
further details see page 1756 of Annual Report for 1915, and page
133 of Annual Report for 1938.
90           REPORT OF CHIEF OF ENGINEERS,                           U. S. ARMY,            1944

   Existing project.-This provides for-
    (1) Two riprap breakwaters, one 3,823 feet long on the easterly side,
and one 2,110 feet long on the westerly side of the entrance to the
main harbor.,
    (2) The construction and maintenance of shore protection on Fayer-
weather Island, including a. seawall connecting the northerly and
southerly portions of the island.
    (3) Main channel 25 feet deep and 300 feet wide, widened to within
75 feet of the harbor line opposite the City Lumber Co. terminal, from
Long Island Sound to Stratford Avenue Bridge across the Poquonock
River.
    (4) Three anchorage basins: One 25 feet deep and 29.4 acres in area,
opposite the inner breakwater; one 18 feet deep and 36 acres in area,
adjoining the main channel on the west above the inner breakwater;
and one 12 feet deep, in two areas, aggregating 14 acres to the east of
the main channel.
    (5) Poquonock River Channel, 18 feet deep and from 125 to 200
feet wide from the lower bridge to a point about 500 feet below the
dam at Berkshire Avenue, about 1.1 miles.
    (6) Yellow Mill Channel, 18 feet deep and 150 to 200 feet wide from
the 18-foot anchorage to a point.about 370 feet from Crescent Avenue,
about 1 mile.
    (7) Johnsons River Channel, 18 feet deep and 150 to 250 feet wide
from the 25-foot anchorage to a point 600 feet below Hollisters Dam,
about 1 mile.
    (8) Black Rock and Cedar Creek Channel, 18 feet deep and 100 to
200 feet wide from the 18-foot curve in Black Rock Harbor to the
heads of both branches of Cedar Creek, about 2.4 miles.
    (9) Burr Creek Channel, 7 feet deep and 100 feet wide from its
junction with Cedar Creek Channel to the south side of Yacht Street
extended, about one-quarter mile.
    All depths refer to mean low water, the mean tidal range being
'6.8 feet. The extreme tidal range, due to wind and other causes, is 11
feet or more.
    The estimate of cost for new work, revised in 1937, is $1,410,000, of
which $39,000 is to be contributed by local interests, exclusive of
amounts expended under previous projects. The latest (1937) ap-
proved estimate for annual cost of maintenance is $28,000.
    The existing project was authorized by the following river and
harbor acts:*
     Acts                             Work authorized                                     Documents
July 4, 1836     Fayerweather Island sea wall_.   ...   .....  .....
Mar. 3, 1899    Shore protection of Fayerweather Island_ ----------------       Annual Report, 1899, p. 1173.
Mar. 2, 1907     West breakwater and present project dimensions of east          H. Docs. Nos. 275 and 521,
                   breakwater.                                                     59th Cong., 2d sess.
Mar. 2, 1919     Present project depths of the 18- and 12-foot anchorage         H. Doc. No. 898, 63d Cong.,
                   basins and of Burr Creek Channel.                               2d sess.
July 3,   1930   Present project dimensions of the 25-foot entrance channel,     H. Doc. No. 281, 71st Cong.,
                   the 25-foot anchorage, the channels through the Poquo-          2d sess.
                   nock River, Yellow Mill Pond, Johnsons River, Black
                  Rock Harbor, and Cedar Creek.
Aug. 12, 19371                                         --------------
                 The present extent of Burr Creek Channel_                       Specified in act.
Aug. 26, 1937    The 25-foot channel through the main harbor, and present        H. Doe. No. 232, 75th Cong.
                  projct location and extent of the 18- and 12-foeot anchorage     1st sess
                   basins.
  1Public,  No. 276, 75th Cong.
  The latest published maps are in H. Doc. No. 819, 76th Cong., 3d sess.
        RIVERS AND    HARBORS-PROVIDENCE,       R. I.,   DISTRICT   91
  Recommended modificationsof project.-Underdate of May 13,1940,
the Chief of Engineers recommended modification of the existing
project so as to eliminate the present 12-foot anchorage area and
provide for a main channel 30 feet deep at mean low water and 400
feet wide from Long Island Sound to a point just beyond the south
end of East Main Street extended; thence decreasing in width to 250
feet at a point about 720 feet below Stratford Avenue Bridge across
the, Poquonook River, with widening at the bend opposite the Cilco
terminal to within 75 feet of the established harbor line, at an esti-
mated first cost of $529,000 with annual maintenance of $6,000 in
addition to that now required, subject to certain conditions of local
cooperation (H. Doc. No. 819, 76th Cong., 3d sess.).
  Local cooperation.-The River and Harbor Act of July 3, 1930,
required as a condition precedent to work on the Johnsons River
Channel that local interests contribute one-half ($39,000) of the esti-
mated cost of that work. This condition has not been met. Pre-
liminary surveys and studies for the development of the contiguous
territory have been made, but financial arrangements have not been
completed.
   Terminal facilities.-There are 45 wharves and piers in use or in
usable condition, including 1 modern deep-water public terminal on
the main harbor and 4 owned by the city, that are served by the im-
provement. The total available length for berthing is about 13,000
feet. Four of the wharves are open to general public use and 3 may
be used by the public upon agreement with the owners or operators.
Direct rail connections are available at 3 wharves. The existing
facilities are considered adequate for existing commerce. (For fur-
ther details see Port Series No. 18, Corps of Engineers.)
   Operations and results during fiscal year.-Maintenance dredging,
by contract, of the Black Rock Harbor and Cedar Creek channel, in
progress at the beginning of the year, was completed on October 14,
1943. During the period 210,523 cubic yards, ordinary material, were
removed at a cost of $90,046.79. Maintenance dredging, by contract,
of the 25-foot anchorage was begun on July 19, 1943, suspended July
31, resumed on October 11 and completed on November 27, 1943. Dur-
ing these periods 126,247 cubic yards, ordinary material, were removed
at a cost of $43,849.11. Maintenance dredging, by contract, of the
inner portion of the entrance channel was begun on November 18, 1943,
and completed on January 20, 1944. During the period 125,969 cubic
yards, ordinary material, were removed at a cost of $60,434.80. Pre-
liminary costs on this work amounted to $84.39 during the year. Main-
tenance dredging, by contract, of the Yellow Mill Pond channel was
in progress from March 22 to 25 and from June 1 to the end of the
year. During the period 19,400 cubic yards, place measure, ordinary
material, were removed at a cost of $1,193.30. Preliminary costs on
this work amounted to $259.76 during the year. Maintenance dredging,
by contract, of the Johnsons River channel, begun on June 22, was in
progress at the end of the year. During the period 1,500 cubic yards,
place measure, ordinary material, were removed at a cost of $285.73.
Preliminary costs on this work amounted to $172.67 during the year.
Preliminary expenses on contract in force for dredging Poquonock
River channel were $268.27 during the year, and Government costs
prior to commencement of dredging were $184.92.
92             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

   Total costs for the year were $196,779.74, all for maintenance. Ex-
penditures were $198,587.63.
   Condition at end of fiscal year.-The existing project was about 86
percent completed. The breakwaters were completed in 1908. The
east breakwater at the entrance is in good condition, the west break-
water and the shore protection works on Fayerweather Island are
in need of repairs. To complete the project requires the deepening
of the channel in Johnsons River, and rock removal in Yellow Mill
Channel. The controlling depths at mean low water are as follows:
Main channel to the breakwaters, 24 feet (May 1943); thence to
the lower bridge, 25 feet (January 1944); Poquonock River, about
15 feet to head of improved channel (June 1943) ; Yellow Mill Chan-
nel, 16 feet to Stratford Avenue, thence 15 feet nearly to head of
improved channel (June 1943); Johnsons River, 11 feet to first
bend at entrance to river, thence 6 feet (June 1944); Black Rock
Harbor and Cedar Creek, 18 feet except minor edge shoals (Septem-
ber-October 1943) ; Burr Creek, about 3 feet; 25-foot anchorage basin,
25 feet (November 1943) ; 18-foot anchorage basin, 18 feet (1942); 12-
foot anchorage basin, 2 to 12 feet (19:9). The costs under the exist-
ing project have been $1,217,008.93 for new work, and $615,435.84 for
maintenance, a total of $1,832,444.77. Expenditures have been $1,832,-
066.09.
   Proposed operations.-Fundsunexpended on June 30, 1944, amount-
ing to $86,534.24 will be applied as follows:
Accounts payable, June 30, 1944_                                         $378. 68
Maintenance:
    Dredging in Poquonock River channel by contract in force, August
      to October 1944, about 58,000 cubic yards------------------      25, 191.28
    Dredging in Yellow Mill Pond channel by contract in progress, July
      to August 1944, about 32,600 cubic yards-------------------- 21, 809. 50
    Dredging in Johnsons River channel by contract in progress, July
      to August 1944, about 16,500 cubic yards---------------------7,      604. 47
Balance remaining      __ ---------------------------------------- 31, 550.31

           Total-_ ---------------------------------------------                                                    86, 534. 24
  No additional funds are requested for fiscal year 1946 as mainte-
nance requirements are not sufficiently urgent to warrant the expendi-
ture under present conditions.
                                             Cost and financial summary
Cost of new work to June 30, 1944_-------                                                   ---             $1, 595, 458. 46
Cost of maintenance to June 30, 1944_-------                                                       ---          627, 384. 81
      Total cost of permanent work to June 30, 1944----------                                                2, 222, 843. 27
Minus accounts payable June 30, 1944-- ----------------                                                              378. 68
      Net total expenditures ----------------------------                                                    2, 222, 464. 59
Unexpended balance June 30, 1944_       -----------                                                              86, 534. 24
           Total amount appropriated to June 30, 1944                             ------------               2, 308, 998. 83

    Fiscal year ending June 30                    1940              1941           1942              1943                  1944

Cost of new work_ .............
                            _                         $743.90   .--.........        $974. 70 ..     .....
Cost of maintenance_- ........----------__...........               $13,889.97    22,380.82         $3,627.64            $196, 779.74
       Total cost.................                   743. 90       13, 889. 97    23, 355. 52        3, 627. 64           196, 779. 74
Total expended..................                  9, 289. 38       14, 147. 69    17, 770. 40        6, 768. 47           198, 587. 63

Allotted.........................                32, 323. 66      136, 000. 00   187, 010. 91     -- 40, 025. 30-    -       -    -
               RIVERS     AND HARBORS-PROVIDENCE,                                    R.   I.,   DISTRICT            93

Balance unexpended July 1, 1943 _____'_                                                                   $285, 121. 87
Gross amount expended-_                       --                                  $198,861.96
Less reimbursements collected-------------------                                          274. 33
                                                                                                           198, 587. 63

           Balance unexpended June 30, 1944                                   -       -         -           86, 534. 24
Outstanding liabilities June 30, 1944 __$378.                                                 68
Amount covered by uncompleted contracts---                                           48, 499. 20
                                                                                                            48, 877. 88

           Balance available June 30, 1944_-------                                                  ---     37, 656. 36

Amount (estimated) required to be appropriated
for completion of existing project 1 2__                                                                   79, 600. 00
1Exclusive   of available funds.
2 In addition, $39,000 is to be contributed by local interests.

                              18. SOUTHPORT HARBOR, CONN.
   Location.-On the north shore of Long Island Sound, about 50 miles
east of New York City. (See United States Coast and Geodetic Sur-
vey Chart No. 220.)
   Previous projects.-Adopted by the River and Harbor Act of March
2, 1829, and modified in 1876 and 1881. A second project was adopted
by the River and Harbor Act of June 13, 1902, and modified by the
River and Harbor Act of July 25, 1912. For further details see
Annual Reports for 1915 and 1936, pages 1758 and 121, respectively.
   Existing project.-This provides for a stone breakwater about 1,320
feet long at the harbor mouth; a 1,350-foot dike along the east side
of the harbor; a channel 9 feet deep to the upper end of the wharves,
100 feet wide from Long Island Sound to opposite East Main Street,
thence 400 to 175 feet wide; and for an anchorage basin 6 feet deep,
300 feet wide, and 500 feet long. The reference plane is mean low
water, the mean tidal range being 6.9 feet. The maximum range, due
to the combined effect of wind and other causes, is 11 feet or more.
   The estimate of cost for new work, made in 1935, was $90,400, includ-
ing $16,500 contributed by local interests but exclusive of amounts
expended on previous projects. The latest (1935) approved estimate
for annual cost of maintenance is $1,200.
   The existing project was authorized by the following river and
harbor acts:
       Acts                      Work authorized                                                Documents


Mar.    2,1829   Breakwater and dike .    -        -..   -.................   . Annual Report for 1871, p. 824.
Aug. 30,19351    Anchorage basin and present channel dimensions                   Rivers and Harbors Committee Doc.
                                                                                                          2
                                                                                   No. 36, 74th Cong., 1st sess.


  1 Also   Emergency Relief Appropriation Act of May 28, 1935.
  2 Contains latest published map.

  Local cooperation.-Fully complied with.
  Terminal facilities.-The several small wharves and private land-
ings for pleasure craft are ample for existing traffic.
  Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was com-
pleted in 1936. The dikes and breakwater are in fair condition. The
controlling depths were 9 feet in about one-half of the channel out-
94        REPORT OF CHIEF OF ENGINEERS,                     U.   S.   ARMY,     1944


side the breakwater with edges shoaled to about 6 feet, as deter-
mined in January 1941; 9 feet in remainder of channel to Golf Club
Wharf, and 6 feet in the anchorage basin, as determined in March
1940. The costs and expenditures under the existing project have
been $37,713.69 from Emergency Relief funds and $16,500 from con-
tributed funds; all for new work, a total of $54,213.69.
   Proposed operations.-No funds are available and no operations are
contemplated during the fiscal year 1945.
   The sum of $20,000 can be profitably expended during the fiscal year
1946 in maintenance dredging, by contract, about 25,000 cubic yards
of mud and sand from the channel and anchorage.
                              Cost and financial summary
Cost of new work to June 30, 1944-                                      _-_--     $96, 926. 72
Cost of maintenance to June 30, 1944 __--8,                                             931. 91

      Total cost of permanent work to June 30, 1944                                105,858. 63
Net total expenditures_ _ _                                                      1 105, 858. 63
Total amount appropriated to June 30, 1944                                       1--------
                                                                                   105, 858. 63
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_ _      --                     -20,                         000. 00
1In  addition $18,285 expended from contributed funds, of which $1,785 was for work outside the
approved project.

                          19. STAMFORD HARBOR, CONN.

   Location.-On the north shore of Long Island Sound, 32 miles east
of. New York City. (See U. S. Coast and Geodetic Survey Chart
No. 221.)
   Previous projects.-Adopted by the acts of August 5, 1886, and
July 13, 1892. For further details see page 1758 of Annual Report
for 1915, and page 139 of Annual Report for 1938.
   Existing project.-This provides for two detached breakwaters;
one 1,200 feet long on the easterly side, and one 2,900 feet long on the
westerly side of the channel at the entrance to the harbor; an entrance
channel 18 feet deep, 200 feet wide to the upper end of the 18-foot
anchorage, about 0.55 mile, and thence 15 feet deep to the junction of
the branches, about 0.5 mile; a channel in the west branch 15 feet deep,
125 feet wide, and about three-fourths mile long, and a basin of the
same depth at the head of the branch of such widths as to exclude
extensive rock excavation along the northeast side; a channel in the
east branch 12 feet deep and 100 feet wide, with increased width at the
turns, to a point 1,100 feet from the head of navigation, thence of the
same depth and from 85 to 125 feet wide to the head of navigation, a
total distance of about 1.5 miles; an anchorage basin 18 feet deep on
the west side of the 18-foot entrance channel, 600 feet wide, and 1,000
to 1,900 feet long, and an anchorage area 8 feet deep east of the en-
trance channel north of buoy No. 6, about 17 acres. The plane of ref-
erence is mean low water, the mean tidal range being about 7.2 feet.
The extreme tidal range, due to the combined effects of wind and other
causes, is 12 feet or more.
   The estimate of cost for new work, revised in 1937, is $907,000, in-
cluding a conditional contribution of $180,000, to be made by local
interests, but exclusive of amounts expended on previous projects.
The latest (1937) approved estimate for annual cost of maintenance
is $20,900.
             RIVERS       AND     HARBORS-PROVIDENCE,                    R.   I., DISTRICT             95
  The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                                   Documents


Mar.   2, 1919   The East Branch Channel and the present project      H. Doc. No. 1130, 63d Cong., 2d sess.
                  width of the entrance channel.
Aug. 30,1935     The 8-foot anchorage area, the present project       Rivers and Harbors Committee Doc.
                  depth of the upper portion of the entrance chan-      No. 8, 74th Cong., 1st sess.
                  nel, and the present project dimensions of the
                  West Branch Channel and Basin.
Aug. 26, 1937    The breakwaters, the 18-foot anchorage basin, and    Rivers and Harbors Committee Doc.
                  present project depth of the outer section of the    No. 29, 75th Cong., 1st sess. (Con-
                  entrance channel.                                    tains latest published map.)



   Local cooperation.-Theconditions of local cooperation imposed by
the River and Harbor Act of March 2, 1919, have been fully complied
with. The River and Harbor Act of August 30, 1935, contained the
provision that the 8-foot anchorage area shall be dredged only after
local interests contribute one-half ($8,000) of the estimated first cost
thereof. This requirement has not been met, and no assurance has
been received that it may be expected.
   The River and Harbor Act of August 26, 1937, authorized the break-
waters, the 18-foot anchorage basin, and the 18-foot channel to the
upper end of the basin, subject to the provisions that local interests
either contribute one-third the entire costs of the proposed improve-
ments or contribute one-third the cost less $50,000, and, in addition,
provide the proposed 18-foot anchorage basin west of the entrance
channel. These requirements have been met and approved by the
Chief of Engineers April 1, 1940.
   Terminal facilities.-There are 21 privately owned wharves and
piers in use and in usable condition adjacent to the channels in the
East and West Branches. The total available berthage is about 4,025
feet. None of the wharves is open to general public use. Two have
direct rail connections. The facilities are considered adequate for
existing commerce. (For further details see Port Series No. 18,
Corps of Engineers.)
   Operations and results during fiscal year.-Improvement dredging
of the 18-foot entrance channel and anchorage basin, by contract in
force at the beginning of the year, was resumed on September 20, 1943,
continued until November 15, on November 29, 1943, from January 22
to 29, 1944, and from March 6 to 10, 1944. During these periods, 55,463
cubic yards ordinary material, 548 cubic yards boulders exceeding 2
cubic yards each in size, and 45 cubic yards ledge rock were removed
at a cost for new work of $27,152.90, of which $17,190.23 were United
States funds and $9,962.67 contributed funds. Expenditures were
$23,851.95 United States funds and $9,962.67 contributed funds, a total
of $33,814.62. These operations substantially completed the 18-foot
entrance channel and anchorage except for minor rocky shoals near
the north end of the anchorage.
96            REPORT OF CHIEF OF ENGINEERS,                                         U. S. ARMY,                  1944

   Condition at end of fiscal year.-The existing project was about 98
percent completed. The East Branch Channel has been completed ex-
cept for a slight deficiency in width opposite Ludlow Street. The West
Branch Channel and entrance channel north of the 18-foot anchorage
have been dredged to 15 feet and all of the basin similarly deepened.
The 18-foot entrance channel and 18-foot anchorage basin have been
substantially completed except for minor rocky shoals near the north
end of the anchorage. The controlling depths at mean low water are
as follows: Entrance channel to north end 18-foot anchorage and
18-foot anchorage, 18 feet except for minor shoals, mostly near north
end of anchorage basin (February 1944); 15-foot entrance channel
to junction of branches 15 feet except edge shoals to 11 feet (September
1943); West Branch Channel and Basin, 13 feet except along edges
 (September 1943); East Branch Channel, 12 feet (not full width)
 (1941); 8-foot anchorage 3 to 8 feet (1942). To complete the project
requires a slight widening (not essential to navigation) in the East
Branch Channel opposite Ludlow Street, the removal of minor rocky
shoals near the north end of the 18-foot anchorage, and the dredging
of the 8-foot anchorage. Costs and expenditures under the existing
project have been $756,147.88 for new work and $136,356.38 for main-
tenance, a total of $892,504.26. In addition, costs and expenditures
have been $169,788.72 from contributed funds fot new work.
   Proposed operations.-Fundsunexpended on June 30, 1944, amount-
ing to $38,469.73 and $2,211.28 contributed funds, a total of $40,681.01,
will be applied as follows:
New work: Investigation of rocky shoal areas near the north end of
  the 18-foot anchorage    -----------------------------------     $7,092.44
Maintenance: Dredging about 90,000 cubic yards of mud and sand
  from the 15-foot portion of the entrance channel and the West
  Branch channel and basin, by contract in the spring of 1945-     33, 588. 57
           Total               --------------------------------------                                                  40, 681. 01
  No additional funds are requested for fiscal year 1946 as maintenance
requirements are not sufficiently urgent to warrant the expenditure
under present conditions.
                                            Cost and financial summary
                                                 UNITED STATES FUNDS

Cost of new work to June 30, 1944_--------                                                        ---              $891, 290. 73
Cost of maintenance to June 30, 1944--                                  -----                       _               195, 776. 37
           Total cost of permanent work to June 30, 1944 --                                               -      1, 087, 067. 10
Net total expenditures_                                                                                          1, 087, 067. 10
Unexpended balance June 30, 1944                           _        -           -         -         __               38, 469. 73

           Total amount appropriated to June 30, 1944--------                                                    1, 125, 536. 83

     Fiscal year ending June 30                 1940             1941                 1942                1943            1944

Cost of new work       .--------------
                                  $59, 911.83   $243, 892. 51                       $44, 912.85         $28, 458.66      $17,190. 23
Cost of maintenance---------           -------------- --
Total expended ----------.....-----           68. 792.80       217, 345. 15          68, 727.93          27, 235. 24      23,851. 95
Allotted-------.---.-------------------..------36,                                      000.00 .........                   ....
                   RIVERS AND HARBORS-PROVIDENCE, R. I., DISTRICT                                                                                       97
Balance unexpended July 1, 1943--- ------------------------                                                                                $62, 321. 68
Gross amount expended-----------------------                $34, 670. 60
Less reimbursements collected_
                            -------------------              10, 818. 65
                                                                                                                                            23, 851. 95

              Balance unexpended June 30, 1944- --------------------                                                                        38, 469. 73

Amount (estimated) required to be appropriated for completion
of existing project 1 ................................
                                _2                            .                                                                             24, 000. 00
   1 Exclusive of available funds.
   2In addition, $8,000 is to be contributed by local interests.

                                                          CONTRIBUTED                   FUNDS

Cost of new work to June 30, 1944_ --------------------------                                                                         $169, 788. 72
Cost of maintenance to June 30, 1944-
              Total cost of permanent work to June 30, 1944-- ---------                                                                    169, 788. 72

Net total expenditures--------------------------- ----                                                                                     169, 788. 72
Unexpended balance June 30, 1944------------- -----                                                                                          2, 211. 28

              Total amount contributed to June 30, 1944                                                       ---        -     _           172, 000. 00


     Fiscal year ending June 30                          1940                  1941                    1942                   1943              1944

Cost of new work ......-----------              --------------             $112,355.20            $32, 442.86            $15,027.99             $9, 962.67
C ost of m aintenance..              . . . .    . . . . . .        . . . . . . --
                                                                               . . ..            . .       . . .     . . .       . . . ..---   -.   .   .
Total expended.....-------------                  --------------            112, 355. 20           32, 442. 86               15, 027. 99         9,962.67

Contributed.--------------------$172,000-




Balance unexpended July 1, 1943 ---------------------------- $12,173.95
Gross amount expended      -----------------------------       9, 962. 67

Balance unexpended June 30, 1944                                                                                                             2, 211. 28

Amount (estimated) required to be appropriated for completion of
     existing project 1                           --------------------------------------------                                               8, 000. 00
IExclusive of available funds.
CONSOLIDATED                    COST        AND    FINANCIAL               SUMMARY               FOR STAMFORD                      HARBOR,       CONN.

Cost of new work to June 30, 1944__                                                                                                  $1, 061, 079. 45
Cost of maintenance to June 30, 1944                                                                   -            -195,                     776. 37

Total cost of permanent work to June 30, 1944---------                                                               -                1, 256, 855. 82

Net total expenditures - - _      ___1,                                                                                                    256, 855. 82
Unexpended balance June 30, 1944--                                                                                                          40, 681. 01

                                                                                                                                       -
                                                                                                              .-         -


              Total amount appropriated and contributed to June 30,
                1944         --------------------------                                                                               1, 297, 536. 83


     Fiscal year ending June 30                           1940                  1941                   1942                   1943              1944

Cost of new work--------------$59, 911. 83 $356, 247. 71                                          $77, 355. 71           $43, 486. 65          $27, 152. 90
Cost of maintenance------------------------------
Total expended------------------                        68, 792. 80          329, 700.35          101,170.79                 42, 263.23         33,814.62
Allotted and contributed--                     . -172,      000. 00n .              -                  6, 000. 00- -----.....

             616634--45--pt. 1, vol. 1-                        7
98            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                         1944

Balance unexpended July 1, 1943___-      -          -_________$74,                                                                            495. 63
Gross amount expended- __    ---------           $44, 633.27
Less reimbursements collected-------------------  10, 818. 65
                                                                                                                                       33, 814. 62

Balance unexpended June 30, 1944__                                -                    -                -_____           -             40,681.01

Amount (estimated) required to be appropriated for completion
      of existing project 12-              -          -               --                   - ____24,
                                                                                                   --                                         000. 00
  1 Exclusive of available funds.
  2   In addition, $8,000 is to be contributed by local interests.

20. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                                                    (GENERAL)

   The cost of the work during the year amounted to $34,992.67; the
expenditures were $34,176.56. The balance unexpended on June 30,
1944, amounting to $33,452.76 and $28,000 allotted during July, a total
of $61,452.76, will be applied as needed to payment of expenses
incurred under this heading throughout fiscal year 1945.
   The additional sum of $60,000 can be profitably expended during
fiscal year 1946. This amount exceeds the average annual expendi-
ture for the past 5 years, as it is expected that increased shipping ac-
tivity will necessitate more examinations, surveys and reports.
                                       Cost and finanecial summary
Cost of new work to June 30, 1944_     --

Cost of maintenance to June 30, 1944 __--                                                                                         $646, 204.24

      Total cost of permanent work to June 30, 1944 -                                                                                 646, 204. 24
Minus accounts payable June 30, 1944-                                                                                                      490. 80
      Net total expenditures__                                                                                                        645, 713. 44
Unexpended balance June 30, 1944-                                                                                                      33,452. 76
           Total amount appropriated to June 30, 1944_                                                                                679, 166. 20

      Fiscal year ending June 30               1940                   1941                          :1942                1943                 1944

Cost of new work -.....                  - -                  -        -.       .---                -       -     --        -          -         .. .
Cost of maintenance .-.      _           $67, 494. 77             $45, 857. 35                  29, 066. 28            $18, 405. 98          $34, 992.67

Total expended------          .----------71, 434. 19               46, 487. 26                  29, 396. 39             19, 097. 39           34, 176. 56

Allotted_ ------------------.             50, 000.00               40,000.00               ..                           66,000.00     /
Balance unexpended July 1, 1943_                              -$67,                                                                           629. 32
Gross amount expended      -     '                        -                -                    -           $36, 242. 17
Less:
     Reimbursements collected_                  -----------                    $1, 906. 61
     Receipts from sales _ - ------                                                159. 00
                                                                                                                 2, 065. 61
                                                                                                                                       324 176
                                                                                                                                       VT,   .....
                                                                                                                                                   56

      Balance unexpended June 30,1944_                                                                                                 33, 452. 76
Outstanding liabilities June 30, 1944_                                                                                                     490. 80

     Balance available June 30, 1944                                                                                                   32, 961.96
Amount allotted in July 1944_______                                                                                                    28, 000. 00

           Amount available during fiscal year 1945-                                                                                   60, 961. 96

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1---------                                                                                                   60, 000.00
  1 Exclusive of available funds.
                 RIVERS        AND       HARBORS-PROVIDENCE,                                R.   I.,   DISTRICT                   99

21. OTHER NAVIGATION                              PROJECTS FOR WHICH NO ESTIMATES
                                                 ARE SUBMITTED,

                                                                      For last    Cost and expenditures to
                                                                       full re-         June 30, 1944                   Estimated
                       Name of project                                port see    _                                     amount re-
                                                                      Annual                                             quired to
                                                                       Report     New work             Main e-           complete
                                                                         for-                          nance


1.   Chatham (Stage) Harbor, Mass. 12 2.-----                          1942           $7, 888. 95      $41, 745. 37    Completed.
2.   Hyannis Harbor, Mass. 1 2 4                                       1937         197, 382. 58        27, 067.78        Do.
3.   Edgartown Harbor, Mass.2                                          1943         545,614.42         -. .-              Do.
4.   Vineyard Haven Harbor, Mass. 2                  _1943                           82, 573.47      _       .            Do.
5.   Little Harbor, Woods Hole, Mass. 1 2......                        1906           18,000. 00 _Do.
6.   Woods Hole Channel, Mass.      1 2
                                                                        1940         338, 599.92         11, 660. 57            Do.
7.   Canapitsit Channel, Mass.2 26                                     1899            9,112. 54 .-                            Do.
8.   Cuttyhunk Harbor, Mass. _                    -         -          1940         727, 167. 86        17, 660. 50            Do.
9.   Westport River, Mass.'81 _ __                                     1942             3, 000.00                      9$28, 000.
10.   Sakonnet Harbor, R. 2I. 2                                         1940           62, 202. 50        9, 967. 97    Completed.
11.   Sakonnet River, R. I.1110(A)                               -_     1909           38, 426. 95                              Do.
12.   Taunton River, Mass.                                              1942         442,     894. 58    32, 916. 79    $508, 500.
13.   Newport Harbor, R. I.2 -1943                                                   733, 523.91         36, 962. 08    Completed.
14.   Harbor at Coasters Harbor Island, R.           1.1   (A)_          1911            5, 500.00       13, 052. 49            Do.
15.   Warren River, R. 1.2(A)                                            1890            5, 000.00             ..               Do.
16.
17.   Potowomut River, R.
                            1
      Greenwich Bay, R. I. 2 (A)
                                 1.1
                                  26
                                                                         1893
                                                                         1882
                                                                                         2,000.00
                                                                                        5,00.00
                                                                                                       -          .             Do.
                                                                                                                                Do.
18.   Wickford Harbor, R. I.212                        2                 1900          16, 300. 00                              Do.
19.   Harbor of Refuge at Point Judith, R. I.____                        1943     2, 371, 467. 55       739, 633. 93            Do.
20.   Entrance to Point Judith 2Pond, R. I.12 6 ....                    11917
                                                                          941        3 12,
                                                                                       3 7 , 4000.00
                                                                                               53. 83    45, 007 85     $ 2 , 50Do.
                                                                                                                                 0.
21.   Stonington Harbor, Conn.
                          2
                                                                                                                 .
22.   Mystic River, Conn. 13 14                   _ _ __                1942           48,125. 50        44, 264. 67    $2,500.
23.   Hay (West) Harbor, N. Y.2 ..... ......                            1931             8, 401.15                      Completed.
24.   Eightmile River, Conn.1     2 13  .1913                                            9, 000.00 --
                                                                                     116, 324. 81        14, 373. 54
                                                                                                                        $1, 500.
                                                                                                                        18$1,000,000.
25.   Connecticut River above Hartford,
                                      2           Conn." ..             1932
26.   Duck Island Harbor, Conn.
                              1         _. -                 -          1943         482, 165. 81       313, 116. 70    Completed.
27.   Clinton Harbor, Conn. 2 17                  __1894                                 6, 330. 02       1,917. 25          Do.
28.   Breakwater at New Haven,         Conn.1     2......               1943      1,242,      246.09     40, 253. 91         Do.
29.   Milford Harbor, Conn.
                              2
                                                                 2      1943          18
                                                                                       88, 716. 92       47, 873.06     $36,700.
30.   Westport Harbor and Saugatuck River, Conn.
        13 (B) _-1927                                                                  32, 104.55        3,360.44       $5,800.
                                2
31.   Norwalk Harbor, Conn. 19                  __                      1943          419, 206. 53     274, 888. 52     Completed.
32.   Harbor at Wilson Point, Conn.'      2 2 (A)- ---....              1895           54, 176.90                           Do.
33.   Fivemile River Harbor, Conn. 2        13 20              -        1938           35, 490.44          31, 311.43   $10,500.
34.   Greenwich Harbor, Conn. 21                          _      .      1943           54, 312. 64         75, 669.90   Completed.

   1 No commerce reported.
   2 Maintenance unnecessary or not urgent.
   3 Modification recommended Aug. 21, 1941, in H. Doc. No. 456, 77th Cong., 1st sess.
   4Modification recommended Nov. 15, 1940, in H. Doc. 98, 77th Cong., 1st sess.
   5 In addition, $10,000 was expended from contributed funds.
   8 Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess.
   7 In addition, $11,643.37 was expended from contributed funds.
   8 Awaiting local cooperation.
   9 In addition, $28,000 to be contributed by local interests.
   10Commerce included under Tiverton Harbor, R. I.
   11Revision of project under consideration.
   12Modification recommended Apr. 29, 1941, in S. Doc. No. 105, 77th Cong., 1st sess.
   13Completion unnecessary for existing commerce.
   14Modification recommended June 3, 1941, in H. Doc. No. 349, 77th Cong., 1st sess.
   15Awaiting local cooperation. Under date of Jan. 14, 1939, the Chief of Engineers recommended modi-
fication of the existing project to provide for construction of a lock, dam, and power plant at Enfield Rapids
(H. Doc.165, 76th Cong., 1st sess.).
   16 Estimated cost of project, $3,384,000; expenditures limited by 1lw to $1,000,000.
   17 Modification recommended Dec. 28, 1938, in H. Doc. 240, 76th Cong., 1st sess.
   18In addition, $11,379.58 was expended from contributed funds.
   1oModification recommended Mar. 4, 1939, in H. Doc. 220, 76th Cong., 1st sess.
  20 Curtailment recommended Dec.-15, 1914, in H. Doc. 1419, 63d Cong., 3d sess.
   21 Modification recommended Dec. 20, 1938, in H. Doc. 125, 76th Cong., 1st sess.

  (A) Classified as unworthy of furte r improvement.
  (B) Abandonment recommended ip H. Doc. No. 404, 64th Cong., 1st sess.
100          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

          22. PLANT ALLOTMENT, PROVIDENCE, R. I. DISTRICT
                        Cost and financial summary
Undistributed costs June 30, 1944- . - -----------                                                             $131, 511. 67

Net total cost to June 30, 1944__ -  -____-.------                                                       --          131, 511. 67
Plus accounts receivable June 30, 1944-    - - ---------                                                              38, 035. 61

      Gross total costs to June 30, 1944----------------------93,     476. 06
Minus accounts payable June 30, 1944- . - -------------           40, 195. 30
      Net total expenditures- -----------------                                                         --       133, 671. 36
Unexpended balance June 30, 1944_- ------                                     ___--------219,                         914. 26

          Total amount appropriated to June 30, 1944-------------                                                     86, 242. 90

   Fiscal year ending June 30               1940               1941               1942                  1943               1944

Total expended.--------------........... -$112, 157.86      $94, 032.97          $67,359.41         -$64, 738.67       -$116,839.60
Allotted.......................................                         _---.... ....
                                                                       -.                ...       ........    ...     .. ..... "..

Balance unexpended July 1, 1943__                                                                              $103, 074. 66
Gross amount expended_ -------                                 _-----$1,            084, 116. 94
Less:
      Reimbursements collected __ $1, 179, 738. 18
      Receipts from sales ....-------- - 21, 21& 36
                                                                                1, 200, 956. 54
                                                                                                              -116,       839.    60
      Balance unexpended June 30, 1944_----         ----------                                                  219,      914.    26
Outstanding liabilities June 30, 1944-------------------------                                                   49,      989.    81
      Balance available June 30, 1944_-     - --------                                                          169,      924.    45
Accounts receivable June 30, 1944_-_     ----------                                                              38,      035.    61
      Unobligated balance available June 30, 1944------------                                                   207,      960.    06
   Status of all investigationsfor navigation called for by river and harbor acts and
                                 committee resolutions

                                       Authorization             Date trans-              Document                   Recommen-
           LocalityA                         atin                mitted to                   No.                       dation
                                                 act              Congress

Bridgeport Harbor, Conn___         Rivers and Harbors_
                                     Committee resolu-
                                     tion, Aug. 30, 1944.
Fall River Harbor, Mass....        Rivers and Harbors ........
                                     Committee resolu-
                                     tion, Oct. 19,1943.
Mianus River, Conn-........        River and Harbor Apr. 22, 1944                   H. 549, 78th Cong.,          Favorable.
                                     Act, Aug. 26, 1937,                                2d sess.
New Haven Harbor, Conn.,           Rivers and Harbors
to modify the existing pro-         Committee resolu-                                                   __
ject, particularly on the           tion, Aug. 28,1944.
Quinnipiac River.
Niantic Harbor and River,          Commerce Commit----------------__
  Conn.                             tee resolution, June
                                    22, 1944.
Point Judith, R. I., harbor        Commerce Commit-
of refuge                          tee resolution, June
                                    15, 1944.
Point Judith, R. I., harbor        Commerce Commit-
  of refuge and pond, to             tee resolution, Aug.------------------
  modify existing project.           17, 1944.
Taunton River, Mass- ...     Rivers and Harbors
                               Committee resolu-.
                               tion, May 15, 1939.
Wickford Harbor, R. I-...... Commerce Commit-
                               tee resolution, Apr. ..                   _
                               14,1944.
Woods Hole and Little Rivers and Harbors
Woods Hole Harbor, Mass. Committee resol u-------------------------...-
                               tion, June 6, 1939.
                            FLOOD CONTROL---PROVIDENCE,                                                R. I.,   DISTRICT               101
                                 23. OLYDE, PAWTUXET RIVER BASIN, R. I.

   Location.-Clyde is a part of the town of West Warwick, in Kent
County, R. I., and is located on the north bank of the Pawtuxet River,
11.5 miles above the mouth.
   Existing project.-The plan of improvement provides for about
2,100 feet of earth levee and 950 feet of concrete wall, a pumping sta-
tion, and a 36-inch pressure conduit 550 feet long. The levee and wall
are designed to protect against a flood substantially greater than the
maximum flood of record. The existing project was authorized by
the Flood Control Act approved August 18, 1941 (H. Doc. 747, 76th
Cong., 3d sess.). The estimated cost of new work is $277,000 for con-
struction, and $22,000 for lands and damages.
   Local cooperation.-See page 7 for requirements. Assurances of
local cooperation have not been furnished.
   Operations and results during fiscal year.-Operations consisted of
surveys, geological explorations and engineering studies in connection
with design and preparation of plans and specifications. The cost was
$3,284.46 for new work. The expenditures were $2,975.39.
   Condition at end of fiscal year.-Plans and specifications were 20
percent complete. No construction work has been done under the
project. The total costs under the project have been $3,284.46 for new
work. The expenditures have been $2,975.39.
   Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, $12,024.61 and accounts receivable $77.14, a
total of $12,101.75 as follows:
Accounts payable -------------------------------------------             $386.21
New work: Continuation of surveys, foundation explorations, and
engineering studies necessary for the preparation of detailed plans
and design of the authorized project, including preparation of con-
tract plans and specifications, period July 1944 to June 1945-------- 11,715. 54

             Total             ---------------------------------------------                             _                      12, 101. 75
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                            Cost and financial summary
Cost of new work to June 30, 1944_ ---           -__       ---- __----$3,284.46
Cost of maintenance to June 30, 1944 ...........     .....................
       Total cost of permanent work to June 30, 1944-------------3, 284. 46
Plus accounts receivable June 30, 1944--------------------------     77. 14
      Gross total costs to June 30, 1944_ ___- ----------                                                                        3, 361. 60
Minus accounts payable June 30, 1944_ -     ----------------                                                                        386. 21
     Net total expenditures---------------_-----------------2, 975. 39
Unexpended balance June 30, 1944-       .---------- ___-----12, 024. 61
             Total amount appropriated to June 30, 1944_                                               ---------------          15, 000. 00

     Fiscal year ending June 30                        1940                        1941                 1942        1943           1944


Cost of new work---....--.........--..--------------.--------------.---------------------------             $3,284.46
Cost of maintenance..----------.........  -----    ---....----- -..........---------------- ----------------------
Total expended.......................                      ....................................                                     2, 975. 39
Allotted-.......................................-..                                               ..    ...... .      $6, 000       9, 000. 00
102      REPORT OF CHIEF OF ENGINEERS,                       U.   S. ARMY,        1944

Balance unexpended July 1, 1943_-----                 ------     _                       $6, 000. 00
Amount allotted from War Department             Civil Appropriation            Act
  approved Apr. 28, 1942-------------------                                          -    9, 000.00

       Amount to be accounted for_ ----                       ----         ____          15, 000. 00
Gross amount expended_--          ----------                           $3, 365. 33
Less reimbursements collected--
                             ........               ------                 389. 94
                                                                            -   -         2, 975. 39

       Balance unexpended June 30, 1944_             .--          ----------             12, 024. 61
Outstanding liabilities June 30, 1944 _-     ------
                                         _----------                                         386.21

      Balance available June 30, 1944 -------------------------                          11, 638. 40
Accounts receivable June 30, 1944_    ------------------------                                77. 14

       Unobligated balance available June 30, 1944           ---------------             11, 715. 54

Amount (estimated) required to be appropriated for completion of
  existing project 1__ __ - ____- -             __--------------------------262,             000. 00
1Exclusiveof available funds.

         24. PONTIAC DIVERSION, PAWTUXET RIVER BASIN, R. I.

   Location.-The Pontiac diversion extends from a point on Paw-
tuxet River 7.6 miles above the mouth, in the city of Warwick, Kent
County, R. I., to the head of Greenwich Bay, a part of Narragansett
Bay, R. I.
   Existing project.-The plan of improvement provides for the con-
struction of an earth diversion dam 600 feet long with top elevation
25 feet above the bed of the Pawtuxet River and with a supplementary
earth dike 1,300 feet long; and a diversion channel 5,500 feet long with
a control gate structure at the upper end and a concrete weir supple-
mented by 3,600 feet of earth dike near the lower end. The diversion
channel will be lined with concrete and have bottom widths of 100
feet in the upper 4,200 feet and 50 feet in the lower reach. The con-
crete weir and wing levees will be provided where the diversion channel
crosses a pond. The channel will have a capacity sufficient to accom-
modate flows greater than any observed in the Pawtuxet River and
will be crossed by three highway bridges.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. 747, 76th Cong., 3d sess.). The
estimated cost of new work is $1,311,000 for construction, and $79,000
for lands and damages.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to give assurances satisfactory to the Secretary
Qf War that they will participate in the expense of the project to the
extent of 25 percent of its first cost, but not to exceed the total sum
of $347,500.
 . Assurances of local cooperation have not been furnished.
   Operations and results during fiscaul year.-Operations consisted of
surveys, geological explorations, engineering studies in connection
with design, and preparation of plans and specifications. The cost
was $7,393.67 for new work. The expenditures were $7,125.46.
   Condition at end of fiseal year.-The preparation of contract plans
and specifications is in progress. No construction work has been done
under the project. The total costs under the project have been $7,-
393.67 for new work. The expenditures have been $7,125.46.
                    FLOOD CONTRO--PROVIDENCE,                                             R. I., DISTRICT                  103
  Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, $29,874.54 and accounts receivable $215.99,
a total of $30,090.53, as follows:
Accounts payable_-                                                                                                    $484. 20
New work: Continuation of surveys, foundation exploration, engineer-
  ing studies necessary for the preparation of detailed plans and
  design of the authorized project, including preparation of contract
  plans and specifications, period July 1944 to June 1945---_ _ _                                             -29,     606. 33

         Total---------------------------------------                                                              30,090. 53

  No additional funds can. be expended during the fiscal year 1946
in view of the existing Federal policies on wartime construction.
                                         Cost and financial summary
Cost of new work to June 30, 1944----------------------------                                                      $7, 393. 67
Cost of maintenance to June 30, 1944__
       Total cost of permanent work to June 30, 1944-----------                                                      7, 393. 67
Plus accounts receivable June 30, 1944_                                                                                 215. 99
      Gross total costs to June 30, 1944                                                                                609. 66
                                                                                                                     7-----------------,
Minus accounts payable June 30, 1944_--                                                  ---------                      484. 20
      Net total expenditures_             -__                                                                       7, 125. 46
Unexpended balance June 30, 1944---------------------------                                                        29, 874. 54
         Total amount appropriated to June 30, 1944-------------                                                   37, 000. 00

   Fiscal year ending June 30                 1940                  1941                   1942        1943            1944

Cost of new work ----         --------------------------------------------------------                                 $7, 393.67
Cost of maintenance-
Total expended-..       .                                                                            -7,125.46
Allotted .....---------------------------------------------------------                                 $10,000        27. 000.00



Balance unexpended July 1, 1943_                                                                                  $10, 000. 00
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942--------------------------------                                                           27, 000. 00
       Amount to be accounted for---------------------                                                             37, 000. 00
Gross amount expended ------------------------     $7, 432. 18
Less reimbursements collected----- ---------------     306. 72
                                                                                                                     7, 125. 46
      Balance unexpended June 30, 1944----------------------                                                       29, 874. 54
Outstanding liabilities June 30, 1944--------------------------                                                        484. 20
      Batance available June 30, 1944 ------------------------                                                     29, 390. 34
Accounts receivable June 30, 1944 ----------------------------                                                         215. 99

         Unobligated balance available June 30, 1944                                      --------------           29, 606. 33
Amount (estimated) required to be appropriated for completion of
existing project           ------------
                                  -------------------------      1, 005, 500. 00
  SExclusive of available funds.
104           REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,                     1944

              25. THAMES RIVER BASIN, CONN., R. I., AND MASS.
  Location.-The works covered by this project are a series of dams
and reservoirs on tributaries of the Thames River in Massachusetts
and Connecticut, within a radius of 45 miles from Norwich, Conn.,
and a channel enlargement on the Shetucket River where it discharges
into the Thames River at Norwich.
  Existing project.-The Flood Control Act approved August 18,
1941, approved the plan for a system of reservoirs and channel im-
provements in the Thames River Basin in accordance with House
Document 885, Seventy-sixth Congress, third session, and authorized
$6,000,000 for initiation and partial accoilplishment of the project:
The following individual projects comprise the approved plan:
                                                DAMS AND RESERVOIRS

                                                                                                           Estimated cost
                                                 Miles                                  Capac-
   Improvement                   River           aNo-          Nearestcity               acr-       Con-Lands
                                                 wich                                     feet      struc- dam-                Total
                                                                                                    tion          ages I


Hodges Village ...        French ...---------     56. 5   Oxford, Mass .--------.....   13, 000 $542, 000 $448, 000 $990, 000
Buffumville _......       Little..---------       57.0    Buffumville, Mass ..          11, 800 725,000      95,000 820, 000
East Brimfield ..         Quinebaug....           65. 7   East Brimfield, Mass-         20,800 625, 000     530, 000 1,155, 000
Westville               __-- .do   .....          58. 7   Westville, Mass-...           21,100 781,000      779,000 1, 560,000
Mansfield Hollow       - Natchaug ......-         23. 4   Mansfield    Hollow,          51, 200 2, 582, 000 508,000 3, 090, 000
                                                           Conn.
South Coventry --          Willimantie ..-        25.1    South Coventry,               36,900 1,557,000 1,758,0003,315,000
                                                            Conn.
Andover.....---------...   Hop-----------...      30.5    Andover, Conn......           16,800 1, 390, 000           240,000 1, 630,000

                                          CHANNEL IMPROVEMENT PROJECT

Norwich Channel            Shetucket__--                                                             $646, 000
                                                                                .-----------------------------   2   $24,000 $670,000
  improvement.

  1 Includes highway, railroad, and utilities relocation.
  2 To be borne by local interests.


  Local cooperation.-See page 7 for requirements. Assurances of
local cooperation have not been furnished for the channel work at
Norwich.
   Operations and results during fiscal year.-Operations consisted of
surveys, foundation, and geological explorations, and engineering
studies in connection with design and preparation of detailed plans
and specifications for the development of the comprehensive plan.
  The cost was $107,634.08 for new work. The expenditures were
$103,377.20.
   Conditionat end of fiscal                       year.-Surveys
                                            and plans for the develop-
ment of the comprehensive plan for flood control in the Thames River
Basin are in progress.
   The total costs under the existing project have been $107,634.08.
The expenditures have been $103,377.20.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $25,622.80, and accounts receivable,
$1,068.01 plus the amount of $115,000 allotted in July 1944, a total of
$141,~690.81, to accounts payable, June 30, 1944, $5,324.89, and to the
                      FLOOD CONTROL-PROVIDENCE, R. I., DISTRICT                                                                              105

continuation of surveys, hydraulic, geologic, and engineering studies
necessary for development of the comprehensive plan and for the
preparation of plans and specifications, period July 1944 to June 1945.
  The additional sum of $240,000 can be profitably expended during
the fiscal year 1946 for continuation of the development of the com-
prehensive plan for flood control in the Thames River Basin.
                                                Cost and financial summary
Cost of new work to June 30, 1944___ ___----------$107,                                                                                   634. 08
Cost of maintenance to June 30, 1944_--------
       Total cost of permanent work to June 30, 1944------------                                                                    107, 634. 08
Plus accounts receivable June 30, 1944_----                                                                                           1,___
                                                                                                                                         068. 01
      Gross total costs to June 30, 1944                      108, 702, 09  ----------------------
Minus accounts payable June 30, 1944-------------------------   5, 324. 89
      Net total expenditures_ ___----------                                                                                     -103,    377, 20
Unexpended balance June 30, 1944--  __                                             --------                                      -25,    622, 80
           Total amount appropriated to June 30, 1944                                                      -129,                         000. 00


      Fiscal year ending June 30                      1940                  1941                  1942                   1943             1944

Cost of new work ---...--------------.......----------------------------......--------------                                            $107,634.08
Cost of maintenance....--.---------------------------------------------------------------
Total expended                        .-------.----------------------------------------..--------------                                  103, 377.20
Allotted--------------------------------------------------.....................-------............                        $54,000         75,000.00


Balance unexpended July 1, 1943_---------                                                                          ---              $54, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941----------                                                          $25, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942                                                                    50, 000. 00
                                                                                                                                     75, 000. 00
       Amount to be accounted for_------                                                                   -_                       129, 000. 00
Gross amount expended-_     ---------                                                                     $105, 343. 78
                            ---------------------
Less reimbursements collected_                                                                                1, 966. 58
                                                                                                                                    103, 377. 20
      Balance unexpended June 30, 1944----------------------                                                                         25, 622. 80
Outstanding liabilities June 30, 1944_ ---------------                                                                                5, 324. 89
      Balance available June 30, 1944_                  ---                                                                          20, 297. 91
Accounts receivable June 30, 1944 -----------------------------                                                                       1, 068. 01
     Unobligated balance available June 30, 1944                                                 --------                            21, 365. 92
Amount allotted in July 1944--__    ------------                                                                                    115, 000. 00
Amount available during fiscal year 1945_------                                                                     ---             126, 365. 92
Amount (estimated) required to be appropriated for completion of
      existing project 1                 ________________                                            __________6,000,000. 00

Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 1    ___      __---------------                                                                             240, 000. 00
  I    Exclusive of available funds.
106     REPORT OF CHIEF OF ENGINEERS,        U.   S.   ARMY,   1944

      26. CONNECTICUT RIVER BASIN, VT., N. H., MASS., AND CONN.

   Location.-The works covered by this project are a series of dams
and reservoirs on tributaries of the Connecticut River in Vermont,
New Hampshire, and Massachusetts, within a radius of 230 miles from
Hartford, Conn., and local protection works at several cities in the
basin.
   Existing project.-The Flood Control Act, approved June 22, 1936,
as amended by the act approved May 25, 1937 (Public, No. 111, .75th
Cong.), authorized the construction of 10 reservoirs on tributaries of
the Connecticut River in accordance with plans in House Document
No. 412, Seventy-fourth Congress, second session, as the same may be
revised upon further investigation of the 1936 flood; estimated con-
struction cost, $10,028,900; estimated cost of land and damages
 $3,344,100.
    The Flood Control Act, approved June 28, 1938, approved a general
comprehensive plan for the control of floods and other purposes in the
Connecticut River Valley, as set forth in House Document No. 455,
Seventy-fifth Congress, second session, and authorized the sum of
 $11,524,000 for construction of local flood-protection projects in the
plan. The act of October 15, 1940, modified the act of June 28, 1938,
to provide additional protection at East Hartford, Conn., as set forth
in House Document No. 653, Seventy-sixth Congress, third session, at
an additional cost of $1,640,000. The act of August 18, 1941, modified
the comprehensive plan approved in 1938 to include the improvements
recommended in House Document 653, Seventy-sixth Congress, third
session, and House Document 724, Seventy-sixth Congress, third
session, with such further modifications as may be found justifiable in
the discretion of the Secretary of War and the Chief of Engineers.
The latter act also authorized to be appropriated the additional sums
of $6,000,000 for local protection works and $10,000,000 for reservoirs.
The act of October 26, 1942 (Public, No. 759, 77th Cong., 2d sess.),
further modified the plan by including the construction of Gully
Brook conduit at Hartford, Conn., at an estimated cost of $420,000.
.Following are lists of the reservoirs and local protection works con-
sidered in the modified comprehensive plans:
                                                                                                      DAMS AND RESERVOIRS

                                                                                                                            Distance                                                                              Estimated cost
                                                                                                                             above
                     Name                                                           Nearest city                            mouth o                                                Reservoir
                                                   Name                             Nearest city                             o   c-     Height             Type                    capacity      Construe-          Land and        Total
                                                                                                                                                                                                   tion             damages 1       Total
                                                                                                                              icut
                                                                                                                             River
                                                                                                                                                                                                                                                    t
                                                                                                                                                                                                                                                    o'
Massachusetts:                                                                                                               Miles       Feet                                      Acre-feet
   Knightville 2                                                  Knightville, Mass ..-- ....-..                              102. 8      160      Earth fill... ....                 39, 300    $2, 296,   000       $874, 000    $3,170,000
   West Brookfield_ ...........                                   West Brookfield, Mass. .-- -
                                                                                                       .-
                                                                                                                               99.1
                                                                                                                              130.2
                                                                                                                                           31
                                                                                                                                           63.5
                                                                                                                                                      ---do
                                                                                                                                                         ..-... .                     33, 900
                                                                                                                                                                                      24, 300
                                                                                                                                                                                                     635,
                                                                                                                                                                                                     876,
                                                                                                                                                                                                            000
                                                                                                                                                                                                            000
                                                                                                                                                                                                                     1, 682, 000
                                                                                                                                                                                                                         89, 000
                                                                                                                                                                                                                                    2,317, 000
                                                                                                                                                                                                                                      965, 000
                                                                                                                                                                                                                                                    d        4



   Barre Falls .. . .. . . .. . . .. .                            Barre, M ass - - ..     ....                  -                                         ..........
                                                                                                                                                  .....do -
    T ully 2 . . . . -. . ..            - - - -                   Fryville, M ass .....        -- ----                        148.7        62         ----
                                                                                                                                                         do......
                                                                                                                                                                                      22, 150        596,   000         163, 000      759, 000      0
    Birch Hill 2                                                  Sou th R oy alston , M ass -- . . . . .           .         153.3        56         - do......       . .
                                                                                                                                                                                      49, 900     1,215,000          2, 885, 000    4, 100, 000
New Hampshire:                                                                                                                                        - - do..... . .. .
   Honey Hill .. __. - ..............                             Keene, N. H   __-                                            168.9       65                                        .26, 200     1, 398, 000           537, 000    1,935, 000
                          - - - -                                                                                                                     --do -- - - - -
   Surry Mountain 2_                                                  do                       - --                            174.4       83                                         32, 500     1, 360, 000           355, 000    1, 715, 000     0
                                                                  Claremont, N. H          -     --                            202. 4     122.5          " do . - . .                 78, 400     3, 170, 000        1, 990, 000    5,160,000
   Claremont 2_ ....        .......                                                                                                                    --do ... . . . .
   West Canaan       -----------------                            West Canaan, N. H .         --                        .      233.8       79     -        do .                       34, 100       968, 000         1, 552, 000    2, 520, 000
   Sugar Hill            ..-------------------..                  Lisbon, N. H _    ---------------                            280.9      163           -- do ---- - - - -            91, 600     3, 500, 000        3, 385, 000    6, 885, 000
Vermont:
   Williamsville 3._-                                             Brattleboro, Vt_.                                            154.5      300     Concrete . ...                     445, 000    25, 028, 000        4, 072, 000   29,100,    000
                              .
   Cambridgeport..-------------.              --                  Cambridgeport, Vt.        -           -                      180.3      101     Earth fill-....                      21, 600    1, 355, 000          620, 000     1, 975,   000
   SBrockway ...-    --          - --       -             -       Brockway Mills, Vt      -         -                          182.0
                                                                                                                               191.3
                                                                                                                                          132
                                                                                                                                          106
                                                                                                                                                    -do
                                                                                                                                                   --         --   -   -   -   -       32, 300
                                                                                                                                                                                       33, 400
                                                                                                                                                                                                  1, 380, 000
                                                                                                                                                                                                  1, 693,   000
                                                                                                                                                                                                                     1, 564, 000
                                                                                                                                                                                                                       325, 000
                                                                                                                                                                                                                                    2, 944,
                                                                                                                                                                                                                                    2, 018,
                                                                                                                                                                                                                                              000
                                                                                                                                                                                                                                              000
    North Springfield_-                                           North Springfield, Vt_.                                                          --do --- -- --                                                                                   d

                           _..                  _ _-_..       .                                                                                                                        23, 900       925,   000      1, 275, 000    2, 200,   000
      udlow . . . . _                                             Ludlow, Vt ----     ----         ---.                        211.8      118      - do . ---      --                                                                               Z


       orth Hartland --------------..                             North Hartland, Vt ..                                        211. 7     176      -- do .. -------                    71, 100    3, 300,   000        330, 000     3, 630, 000
     South Tunbridge..-------------                               South Royalton, Vt                                           234.5      105         do     -.     ._                 32, 600    1, 305,   000        970, 000     2, 275, 000
     G aysville -- - - -- - - -- - - -- -                         Gaysville, Vt - _-                                           246.8      178     Concrete -_..-                      .84, 300    2, 665,   000      2, 120, 000    4, 785, 000
                                                                                                                                                                                                                                    2, 376, 000
                                                                                                                                                                                                                                                    M
     Union Village 2_........                                     Union Village, Vt -         .......               .          228.4      170     Earth fill......                     30, 200    2,108,    000        268, 000
    Victory... - - -- - - - - -                   - --            North Concord, Vt-      -           -     -       -          306.0       75          do ............
                                                                                                                                                   --....                              28, 200    1, 100,   000        315, 000     1, 415, 000

    1 Includes highway, railroad, and utilities relocation.
    2 Details of these project items are given in individual reports.
    3 Flood control and power, ultimate development.       Corresponding figures for initial project for flood control only are: Height, 184 feet; capacity, 152,000 acre-feet; construction,
14,000,000.                                                                                                                                                                                                                                            12
108          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

                                         LOCAL PROTECTION WORKS

                                    Distance                                                        Estimated cost
                                     above
                                     mouth
          Location                   of Con-         Type of structure
                                    necticut                                          Construe-       Land and           Total
                                      River                                             tion          damages
                                     (miles)

Hartford, Conn 1---.                     52    Wall and levee------------             $6, 052,000          $900, 000    $6, 952,000
East Hartford, Conn.'..                  52     .do ------           -------------     2, 350,000           270, 000     2, 620,000
Springfield, Mass.1'                     76 -      do ............           .....        925,000           272, 000     1, 197, 000
West Springfield,1- -Mass.1_
                      --- - -- --        76        do -------.                         1, 252, 000           30, 000     1, 282, 000
Chicopee, Mass.                          80 ...    do -------------------              1, 592,000           500, 000     2, 092, 000
Holyoke, Mass.'--...                     85 --     do ---------------------            2, 424,000           150,000      2, 574, 000
Northampton, Mass.' .-.                  94 --     do      ..    .-       --    ---       960,000           150, 000     1,110, 000
Springdale, Mass.' ......                84 ----- do ....----------------------           390, 000           57,000         447, 000
Riverdale, Mass.-------.                 80        do-- _------------------               490,000            50,000         540, 000
Winsted, Conn.1-_ __----                 115   Channel improvement--......               140,000              3,000        143,000

  1Details of these    project items are given in individual reports.

   Operationsand results during the fiscal year.-Operations consisted
of surveys, geological explorations, and engineering studies in connec-
tion with design and preparation of plans and specifications for the
development of the general comprehensive,plan.
   The cost was $123,649.04, and the expenditures were $113,051.46.
   Condition at end of fiscal year.-Surveys and plans for the develop-
ment of the comprehensive plan have been well advanced. The prog-
ress on projects selected for construction under this authorization is
given in individual reports. The total costs under the existing project
have been $800,952.30. The expenditures have been $809,509.16.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $73,490.84, plus accounts receivable,
$726.49, and $275,000 allotted in July 1944, a total of $349,217.33, as
follows:
Accounts payable June 30, 1944__-----
                                   ___------                                                                   -$9,      017. 26
New work: Continuing rainfall studies, stream flow studies,
  hydraulic and hydrologic studies, geologic explorations and
  design, period June 1944 to July 1945                        ---------------------                                340, 200. 07

          Total --------------------------------------------                                                        349,217.33
  SThe sum of $250,000 can be profitably expended during the fiscal
year 1946 in continuing engineering studies of flood control dams and
reservoirs, and local protection works included in the authorized plan.
                                          Cost and financial summary
Cost of new work to June 30, 1944                              ..-                    _-_                       $800, 952. 30
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944----------                                                       800, 952. 30
Undistributed costs June 30, 1944 ---------------------------                                                        16, 847. 63
       Net total cost to June 30, 1944 -------------------------                                                    817, 799. 93
Plus accounts receivable June 30, 1944------------                                                                       726. 49
      Gross total costs to June 30, 1944                       ---------------------                                818, 526. 42
Minus accounts payable June 30, 1944_-------                                                          -         -     9, 017. 26
      Net total expenditures-       -        ---                                                                    809, 509. 16
Unexpended balance June 30, 1944 --------------------------                                                          73, 490. 84
          Total amount appropriated to June 30, 1944- ----                                           .--            883, 000. 00
                           FLOOD CONTROL-PROVIDENCE,                                        R.-I., DISTRICT                              109

     Fiscal year ending June 30                           1940               1941             1942              1943                 1944

Cost of new work              ___                         $95, 252. 63
                                          ....--------------               $53, 656.17      $10, 652.04       $10, 504. 95         $123, 649. 04
Cost of maintenance....-------------------------------                                                                   --------------
Total exirended...............-----------------..        44, 205. 04        45, 687. 37       7, 489. 58        -846. 70            113, 051.46
Allotted--..........------.----                        125,000.00        -210,000.00      ............. 1-0, 000.00           __


Balance unexpended July 1, 1943_--       ------------ ______                                                           -$186, 542. 30
Gross amount expended-___--------                     $136, 570. 89
Less reimbursements collected_------------------- 23, 519. 43
                                                                                                                             113, 051. 46

       Balance unexpended June 30, 1944---------------------                                                                  73, 490. 84
Outstanding liabilities June 30, 1944-------------------------                                                                9, 569. 24
      Balance available June 30, 1944_-------            ---                                                                  63, 921. 60
Accounts receivable June 30, 1944---------------------------                                                                      726. 49
     Unobligated balance available June 30, 1944                                             ------------                     64, 648. 09
Amount allotted in July 1944_---------                                                                 ----                  275, 000.00
Amount available during fiscal year 1945                                     ---------------------                           339, 648. 09
Amount (estimated) required to be appropriated for completion of
existing project 1----           _____ --------                 10, 000,000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work' --
                              _--________ -        -____   -                                                                 250, 000. 00
    I Exclusive of available funds.


     27. CLAREMONT RESERVOIR, CONNECTICUT! RIVER BASIN, N. H.

   Location.-The site of the proposed Claremont Dam is on the Sugar
River, about 7 miles above its junction with the Connecticut River and
about 1 mile southeast of Claremont, N. H. The reservoir will extend
upstream approximately 4.5 miles.
   Existing project.-This project provides for the construction of a
rolled-fill earth dam 2,600 feet long at the crest line, rising 130 feet
above the stream bed and providing a total storage capacity of 78,400
acre-feet. The reservoir will be operated as a unit of a coordinated
reservoir system for the control of floods in the Connecticut River
Basin.
   The estimated cost, revised in 1940, is $3,170,000 for construction
and $1,990,000 for lands and damages, including highway, railroad,
and utilities relocation, a total of $5,160,000 for new work. The esti-
mated cost for annual maintenance is $18,500, of which $5,000 is for
operating and care.
   The existing project was adopted by the Flood Control Act ap-
proved June 22, 1936, as modified by the act of June 28, 1938 (H.Doc.
No. 455, 75th Cong., 2d sess.).
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.--Operations consisted of
dam site surveys, geological investigations, and engineering studies in
connection with design and preparation of plans and specifica-
tions. The cost was $32,854.65 for new work. The expenditures
were $32,190.15.
110          REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,                  1944

   Conditionat end of fiscal year. Geological investigations and dam-
site surveys were 90 percent complete. Preparation of plans and speci-
fications was 70 percent complete. The total costs under the project
have been $143,914.52 for new work. The expenditures have been
$143,250.02.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, $31,749.98 and accounts receivable $207.38, a total of
$31,957.36, as follows:
Accounts payable June 30, 1944_------                                   $871. 88
New work: Continuation of surveys, foundation explorations, engi-
  neering studies in connection with design and preparation of plans
  and specifications_                                     _    __    31, 085. 48
           Total      ---------------------------------------------                                                31, 957. 36
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                          Cost and financial summary
Cost of new work to June 30, 1944_--      ----------                                                             $143, 914. 52
Cost of maintenance to June 30, 1944

      Total cost of permanent work to June 30, 1944-
Plus accounts receivable June 30, 1944------------------------
                                                                                                    -             143, 914. 52
                                                                                                                       207. 38.
      Gross total costs to June 30, 1944                         --------------------                             144, 121. 90
Minus accounts payable June 30, 1944_--                                         ---------                              871. 88
      Net total expenditures -------------------------                                                            143, 250. 02
Unexpended balance June 30, 1944 ----------------------------                                                      31, 749. 98
           Total amount appropriated to June 30, 1944--------------                                               175, 000. 00

      Fiscal year ending June 30                 1940            1941                1942             1943                 1944


Cost of new work -----              -$33.04                    $91, 969. 71     $18, 042. 01         $1, 015 11           $32, 854.65
C ost of m aintenance    --   - -    - -  .- -   - - -   ..-    . .     -   .- .-.
                                                                                 . . .      -.     .. . .    .    . . .    .   . ..
Total expended-------------              --------------        89, 591.03           20, 480.06          988.78             32,190.15

Allotted       ...       ...
              -----------------              150, 000.00 .....------------------------.--------------                      25,000.00


Balance unexpended July 1, 1943 _-         -  -      -     -                                                      $38, 940. 13
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942___       ---------             ___                                                          25, 000. 00
       Amount to be accounted for---------------------------                                                        63, 940. 13
Gross amount expended--___---------                $33, 896. 09
Less reimbursements collected---------------------   1, 705. 94
                                                                                                                    32, 190. 15
      Balance unexpended June 30, 1944_------                                                        ---            31, 749. 98
Outstanding liabilities June 30, 1944_  -                                       -                ----- -_               871. 88
      Balance available June 30, 1944_---------                                                        ---          30, 878. 10
Accounts receivable June 30, 1944_ __-  -       ----------                                                              207. 38

            Unobligated balance available June 30, 1944-------------                                                31, 085. 48

Amount (estimated) required to be appropriated for completion of
existing project 1---_--        ---------                 -     4, 985, 000. 00
  1
      Exclusive of available funds.
            FLOOD CONTROL-PROVIDENCE,           R. I.,   DISTRICT         111
  28. UNION VILLAGE RESERVOIR, CONNECTICUT RIVER BASIN, VT.

   Location.-The site of the proposed Union Village Dam is on the
Ompompanoosue River, about 4 miles above its junction with the Con-
necticut River and one-quarter mile north of Union Village, Vt.
The reservoir will extend upstream approximately 31/2 miles.
   Existing project.-This project provides for the construction of a
rolled-fill earth dam, 1,100 feet long at the crest line, rising 170 feet
above the stream bed and providing a total storage capacity of 38,000
acre-feet. The spillway will have an ogee weir, 388 feet long,
built on rock, with a discharge capacity of 84,900 cubic feet per second.
The outlet will consist of a 13-foot diameter tunnel 1,200 feet long.
Control will be accomplished by gates mechanically operated from a
house over a shaft near the middle of the tunnel. The drainage area
controlled is approximately 126 square miles. Provision will be made
for future installation of penstocks for the development of hydro-
electric power. The reservoir will be operated as a unit of a coordi-
nated reservoir system for the control of floods in the Connecticut
River Basin.
   The estimated cost, revised in 1939, is $2,108,000 for construction
and $268,000 for lands and damages, including highway relocation, a
total of $2,376,000 for new work. The estimated cost for annual
maintenance is $16,300, of which $5,000 is for operating and care.
   The existing project was authorized by the 'Flood Control Acts
approved June 22, 1936, and June 28, 1938 (H. Doc. No. 455, 75th
Cong., 2d sess.).
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Revision of plans and
specifications was made in accordance with changes in design. The
cost and expenditures were $31,879.36 for new work.'
   Conditionat end of fiscal year.-Revision of plans and specifications
was 95 percent completed. The total costs and expenditures under
the project have been $53,197.17 for new work. In addition, $104,411.93
from funds allotted for development of the general comprehensive
plan for flood control in the Connecticut River Basin was applied to
preliminary exploration, surveys, and design of the Union Village
Reservoir.
   Proposed operations.-Itis proposed to apply the funds unexpended
on Juue 30, 1914, amounting to $1,802.83, to new work, completion of
plans and specifications, July 1944 to June 1945.
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                         Cost and financial summary
Cost of new work to June 30, 1944_ 1111 ---   --
                                              11-11-1$53,              197. 17
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-----------      53, 197. 17

Net total expenditures_ __53,                                           197. 17
Unexpended balance June 30, 1944_-             __                    1, 802. 83

      Total amount appropriated to June 30. 1944-                   55, 000. 00
112           REPORT OF CHIEF OF ENGINEERS,                                U.   S. ARMY,           1944


    Fiscal year ending June 30                 1940         1941             1942           1943            1944

Cost of new work .....----..                  $4, 353.08   $2, 883.05           $8.40 -     ------         $31,879.36
Cost of maintenance....-------........-----    --------    ---------    -------------- ------

                               5, 281. 69
Total expended ..................           2,883.05        -618. 58-----------                             31, 879. 3
Allotted-------------------
          ....................
                            ------------- 560,000. 00 ---------------------------.
                                                                                                            15,000.00


Balance unexpended July 1,1943 ----------------------------                                          $18, 682.19
Amount allotted from W. D. Civil Appropriation Act approved
  April 28, 1942-----------------------------------                                                   15, 000. 00
       Amount to be accounted for---------------------                                                33, 682. 19
Gross amount expended------------------------      $33, 364. 46
Less reimbursements collected --------------------- 1, 485. 10
                                                                                                      31, 879. 36

           Balance unexpended June 30, 1944                                                               1,802. 83
Amount (estimated) required to be appropriated for completion of
existing project 1- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ___ 2,321, 000. 00
  1Exclusive of available funds.

29. SURRY MOUNTAIN RESERVOIR, CONNECTICUT RIVER BASIN, N. H.

  Location.-The site of the Surry Mountain Dam is on the Ashuelot
River, about 34.6 miles above its junction with the Connecticut River
and 5 miles north of Keene, N. H. The reservoir will extend upstream
about 3 miles.
  Existing project.-This project provides for the construction of a
rolled-fill earth dam 1,670 feet long at its crest, rising 85 feet above
the stream bed, and providing a total storage capacity of 32,500 acre-
feet. The spillway consists of an open side channel with a low con-
crete weir 337.5 feet long, with a discharge capacity of 40,900 cubic
feet per second. The outlet consists of a 10-foot-diameter tunnel 383
feet long. Control is accomplished by gates mechanically operated,
through a shaft, from a house above. The drainage area controlled is
approximately 100 square miles. The reservoir is operated as a unit
of a coordinated reservoir system for the control of floods in the Con-
necticut River Basin.
  The estimated cost, revised in 1944 is $1,360,000 for construction
and $355,000 for lands and damages, including highway relocations, a
total of $1,715,000 for new work. The estimated cost for annual main-
tenance is $11,700, of which $5,000 is for operating and care.
  The existing project was authorized by the Flood Control Acts
approved June 22, 1936, and June 28, 1938 (H. Doc. No. 455, 75th
Cong., 2d sess.).
  Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Work was started on
the removal of fallen and unstable rock from the spillway channel
in August 1943 and was about 90 percent complete at the end of the
year. Work during the year included approximately 28,000 cubic
yards of rock excavation at a cost of $59,680.26. Partitions were
erected in the operating house to provide temporary office space, at a
              FLOOD CONTROI-PROVIDENCE,                  R. I.,   DISTRICT                  113;
cost of $235.19. Clearing reservoir area was continued at a cost of
$1,420.88. No additional work was done on utility relocation and
the work remains about 90 percent complete; costs of $5,722 were in-
curred through an adjustment between costs of land acquisition and
utility relocation. Work was continued practically to completion at
the end of the year on land acquisition in the dam site and reservoir
areas. There were 9.73 acres of land acquired; net costs for this
feature were minus $4,831.01. The total costs, including engineering,
amounting to $53.14, were $62,280.46 for new work. The expenditures
were $62,251.91. Maintenance and operation costs were $7,797.06;
expenditures were $7,336.39.
   Condition at end of fiscal year.-The existing project is approxi-
mately 95 percent complete. The work required to complete the
project consists of completion of the removal of rock slide from spill-
way, completion of utility relocation, and land acquisition, miscel-
laneous fencing, sodding and seeding, and the clearing of the reservoir
area of floating materials.
  The costs of the existing project for new work have been $1,636,-
593.92. The expenditures for new work have been $1,630,607.87. In
addition, $104,708.83 from funds allotted for the development of the
general comprehensive plan for flood control in the Connecticut River
Basin was applied to preliminary explorations, surveys, and designs.
of the Surry Mountain Reservoir project.
  The costs of maintenance and operation have been $18,361.78. The{
expenditures have been $18,009.30.
   Proposed operations.-It is proposed to apply funds unexpended
on June 30, 1944, amounting to $88,082.77, as follows:
                               ----------------------------- $6, 338. 47
Accounts payable, June 30, 1944_
New work: Acquisition of rights-of-way and lands, clearing of reservoir
  area, removal of fallen rock from spillway channel, and miscellaneous
  fencing, sodding and seeding, period July 1944 to June 1945 ...       61, 406. 08
Maintenance: Operation and maintenance of the flood-control reser-
  voir, period July 1944 to June 1945-------------------------          20, 338. 22

       Total --------------          ---------------------------
                                                _                          ----      88, 082. 77

  The sum of $11,700 can be profitably expended during the fiscal
year 1946 on maintenance, operation and maintenance of the flood con-
trol reservoir, period July 1945 to June 1946.
   No additional funds can be expended for new work during the fiscal
year 1946 in view of the existing Federal policies on wartime
construction.

                              Cost and financial summary
Cost of new work to June 30, 1944 ....                                        $1, 636, 593. 92
Cost of maintenance to June 30, 1944 ------------------------                      18, 361. 78
      Total cost of permanent work to June 30, 1944---_-- ----- I, 654, 955. 70
Minus accounts payable June 30, 1944-----------------------          6, 338. 47
     Net total expenditures-----------------------------1, 648, 617 23
Unexpended balance June 30, 1944--------------------------  88, 082. 77
       Total amount appropriated to June 30, 1944------_          ------          1, 736, 700. 00
       616634-45-pt. 1,vol. 1-       8
114         REPORT OF CHIEF OF ENGINEERS,                                    U. S. ARMY,                 1944


   Fiscal year ending June 30              1940            1941                1942               1943            1944

Cost of new work--------..          .-. $344,216. 39    $789, 448. 60      $407, 885. 05    $18, 120. 44         $62, 280. 46
Cost of maintenance -....  _         _-  - --            --       ----             255.39    10,309.33             7,797.06
      Total cost     ..      ......
                              _'_        344, 216. 39   789, 448. 60        408, 140. 44     28, 429. 77          70,077.52
Total expended   ----------------
                      _                  287, 726. 59   753, 086. 80        445, 560. 40     79, 786. 98          69, 588. 30
Allotted ______-          -.......... 275, 000. 00      260, 000. 00          67,000.00     -3,     300.00        68, 000. 00


Balance unexpended July 1, 1943_--       --------       _   -                                                $89, 671. 07
Amount allotted from War Department Civil Appropriation Act
  approved June 28, 1939_--     -------------                                                                100, 000. 00
      Amount to be accounted for ------------------------                                                    189, 671. 07
Deductions on account of revocation of allotment__    -----                                                   32, 000. 00
       Net amount to be accounted for-_-------                                              ---              157, 671. 07
Gross amount expended -----      ---------                                         $70, 346. 70
Less reimbursements collected--------------------                                       758. 40
                                                                                                              69, 588. 30
       Balance unexpended June 30, 1944-__       ----                                     -----               88, 082. 77
Outstanding liabilities June 30, 1944 -------------                                $24, 693. 22
Amount covered by uncompleted contracts                       --------              25, 691. 20
                                                                                                              50, 384. 42

         Balance available June 30, 1944_--                             --------                             37, 698. 35
Amount (estimated) required to be appropriated for completion
of existing project 1--_17,                      -                                                              000. 00
Amount that can be profitably 1expended
                                - -
                                        in -fiscal
                                      - -      - - -
                                                    year ending
June 30, 1946 for maintenance _                         _11,                                                    700. 00
1Exclusive of available funds.

    30. BIRCH HILL RESERVOIR, CONNECTICUT RIVER BASIN, MASS.

    Location.-The site of the Birch Hill Dam is on the Millers River,
about 27.3 miles above its junction with the Connecticut River, and 1.3
miles northeast of South Royalston, Mass. The reservoir extends
up the Millers River about 61/2 miles and up'the Otter River about 3
miles.
    Existing project.-This project provides for an earth dam of
rolled-fill construction, extending across the Millers River and over-
flow spillway sections closing natural saddles in the right bank.
The dam is 1,400 feet long and rises 56 feet above the river bed.
The spillway weir consists of two concrete overflow sections, sepa-
rated by a natural knoll and a short weir closing an abandoned rail-
road cut. The main spillway is approximately 810 feet long, the
adjacent spillway 350 feet, and the small one 23 feet. The total dis-
charge capacity is approximately 57,000 cubic feet per second at a
surcharge of 6 feet. The outlet works consist of an intake channel
1,500 feet long, with a bottom width of 70 feet; a gate structure with
operating gatehouse directly above; and an outlet channel 1,150 feet
long, with a bottom width of 70 feet. The intake and gate-operating
tower contain gates mechanically controlled from the operating house
above. The gross drainage area controlled is approximately 175
square miles. The reservoir provides a storage capacity of 49,400
acre-feet at spillway crest. The reservoir is operated as a unit of
             FLOOD CONTROI--PROVIDENCE,             R. I.,   DISTRICT          115

a coordinated reservoir system for the control of floods in the Con-
necticut River Basin.
   The estimated cost, revised in 1941, is $1,215,000 for construction
and $2,885,000 for lands and damages, including highway and rail-
road relocations, a total of $4,100,000 for new work. The estimated
cost for annual maintenance is $12,000, of which $5,000 is for operating
and care.
    The existing project was authorized by the Flood Control Acts
approved June 22, 1936, and June 28, 1938 (H. Doc. No. 455, 75th
Cong., 2d sess.).
    Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.                     *
    Operations and results during fiscal year.-Work was practically
completed during the fiscal year on the relocation of the Boston &
Maine Railroad at a cost of $82.29. Negotiations with officials of the
State of Massachusetts and Worcester County, providing for reloca-
tion of State highway and county roads, were continued. Costs of
surveys by Worcester County were $3,880.08. Work was continued
on land acquisition in the dam site and reservoir areas and at the end
of the year it was about 95 percent complete; 1,928 acres of land were
acquired, at a cost of $64,740.65. A temporary garage was erected at
a cost of $799.77. Partitions were constructed to provide temporary
office space in the operating house at a cost of $159.43. The total costs
for new work, including engineering costs of $2,032.27, were $71,-
694.49; expenditures were $87,795.50. Maintenance and operation
costs were $11,330.20; expenditures were $10,770.28.
    Condition at end of fiscal year.-The existing project is approxi-
mately 90 percent complete. The work remaining to be done to
complete the project consists of the completion of Boston & Maine
Railroad relocation, acquisition of lands, clearing of reservoir area,
construction of permanent operator's quarters, garage and utility
building, and miscellaneous fencing and sodding and seeding.
    The costs of the existing project for new work have been $3,316,-
353.77 and $26,458.12 for maintenance and operation, a total of $3,342,-
811.89. The expenditures have been $3,312,981.81 for new work and
 $25,668.20 for maintenance, a total of $3,338,650.01. In addition,
 $11,039.82 from funds allotted for development of the general com-
prehensive plan for flood control in the Connecticut River Basin was
applied to preliminary explorations, surveys, and designs of the Birch
Hill Reservoir project.
    Proposed operations.-It is proposed to apply funds unexpended
on June 30, 1944, amounting to $725,349.99, plus $7,000 allotted in
July 1944, a total of $732,349.99, as follows:
Accounts payable, June 30, 1944__-----------------------------           $4, 161. 88
New work: Completion of the railroad relocation, continuation of
  highway relocations, acquisition of rights-of-way and lands, clearing
  of reservoir area, and miscellaneous fencing, sodding and seeding,
  period July 1944 to June 1945-----------------------                  708, 646. 23
Maintenance: Operation and maintenance of the flood control reser-
  voir, period July 1944 to June 1945- -19,                                  541. 88
       Total------------------------------------------------            732, 349. 99
  The sum of $12,000 can be profitably expended during the fiscal
year 1946 on maintenance, operation and maintenance of the flood
control reservoir, period July 1945 to June 1946.
 116          REPORT OF CHIEF OF ENGINEERS,                                            U. S. ARMY,                 1944

   No additional funds can be expended during the fiscal year 1946 for
new work in view of the existing Federal policies on wartime con-
struction.
                                                 Cost and financial summary

Cost of new work to June 30, 1944                             $3, 316, 353. 77
Cost of maintenance to June 30, 1944 ------------------------      26, 458. 12
      Total cost of permanent work to June 30, 1944----------                                                      3, 342, 811. 89
Minus accounts payable June 30, 1944_--------              ---                                                             4, 161. 88
     Net total expenditures-- -----------------             3, 338, 650. 01
Unexpended balance June 30, 1944 --------------------------    725, 349. 99
            Total amount appropriated to June 30, 1944                                 ------------                4, 064, 000. 00


   Fiscal year ending June 30                        1940              1941             1942                1943              1944

Cost of new work            _ _....-.......        $227, 133. 04 $1, 657, 533. 56 $1, 258, 216. 70     $69, 936. 05          $71, 694.49
Cost of maintenance_--.
                     -                        ---------------------                     1,271.73           13, 856.19         11, 330. 20
      Total cost............---------------.      227, 133. 04    1, 657, 533. 56   1, 259, 488. 43        83, 792. 24        83, 024. 69

Total expended      ----------------              203, 644.49     1, 249, 824. 58   1, 575, 430. 29    181, 186. 59           98, 565. 78
Allotted-         .-.--   .--____----             813, 000.00     1, 510, 000.00      477, 000.00     -38, 000.00             ..


Balance unexpended July 1, 1943-                                                                                    $823, 915. 77
                      -
Gross amount expended___       --------           $99, 527. 48
Less reimbursements collected--------------------      961. 70
                                                                                                      --                  98, 565. 78

      Balance unexpended June 30, 1944 --------------- __--_                                                             725, 349. 99
Outstanding liabilities June 30, 1944_------------ $679, 196. 18
Amount covered by uncompleted contracts .......-     11, 544. 96
                                                                                                                         690, 741. 14
     Unobligated balance available June 30, 1944                                      ------------                       34, 608. 85
Amount allotted in July 1944_   ___------------                                                                           7, 000.00
            Amount available for fiscal year 1945                          ------------------                             41, 608. 85

Amount (estimated) required to be appropriated for completion
of existing project 1                                   __                                                               68, 000. 00

Amount that can be profitably  expended in fiscal year ending June
30, 1946 for maintenance 1 _ - - - - - - - - - - - - - -                                                      -
                                                                                                                          12, 000. 00
  1 Exclusive of available funds.

   31. KNIGHTVILLE RESERVOIR, CONNECTICUT RIVER BASIN, MASS.

   Location.-The site of the Knightville Dam is on the Westfield
River, about 27.5 miles above its junction with the Connecticut River
and 4 miles north of the town of Huntington, Mass. The reservoir
extends up the Westfield River about 6 miles and up the Little River
about 1 mile.
   Existing project.-This project provides for the construction of
a hydraulic-fill earth dam, 1,600 feet long at the crest line, including
400 feet of spillway, rising 160 feet above the stream bed and pro-
viding a total storage capacity of 39,300 acre-feet. The outlet con-
sists of a 16-foot diameter tunnel approximately 605 feet long. Con-
trol is accomplished by gates mechanically operated from a tower
             FLOOD CONTROL--PROVIDENCE,            R. I.,   DISTRICT         117
located at the intake end of the tunnel. The drainage area controlled
is approximately 164 square miles. Provision has been made for fu-
ture installation of penstocks for the development of hydroelectric
power. The reservoir is operated as a unit of a coordinated reservoir
system for the control of floods in the Connecticut River Basin.
   The estimated cost, revised in 1941, is $2,296,000 for construction
and $874,000 for lands and damages, including highway relocations,
a total of $3;170,00 for new work. The estimated cost for annual
maintenance is $18,700, of which $5,000 is for operating and care.
   The existing project was authorized by the Flood Control Acts ap-
proved June 22, 1936, and June 28, 1938 (H. Doc. No. 455, 75th Cong.,
2d sess.).
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Work was completed,
under a contract with the Commonwealth of Massachusetts, on the
relocation of 3.5 miles of highway. The costs were $21,465.80. Land
acquisition in the dam-site and reservoir areas was continued and was
about 95 percent completed at the end of the year. There were 327.04
acres acquired at a cost of $2,722.18. A temporary garage was con-
structed at a cost of $799.77, and partitions were erected in the operat-
ing house to provide temporary office space at a cost of $199.78.. The
total costs, including engineering, of $62.64, were $25,250.17 for new
work. The expenditures were $30,541.08. Maintenance and operation
costs were $8,136.45; expenditures were $7,804.36.
   Condition at end of fiscal year.-The existing project is approxi-
mately 95 percent complete. The work required to complete the project
consists of the completion of land acquisition, construction of perma-
nent operator's quarters, garage and utility building, and clearing of
reservoir area of floating materials. Total costs for new work have
been $3,093,323.66 and $25,622.94 for maintenance, a total of $3,118,-
946.60. The expenditures have been $3,093,311.19 for new work and
$25,358.10 for maintenance, a total of $3,118,669.29. In addition, $105,-
798.28 from funds allotted for the development of the general com-
prehensive plan for flood control in the Connecticut River Basin was
applied to preliminary explorations, surveys, and designs of the
Knightville Reservoir project.
   Proposed operations.--It is proposed to apply funds unexpended
on June 30, 1944, amounting to $90,030.71, as follows:
Accounts payable, June 30, 1944_-------------------------------         $277. 31
New work: Acquisition of rights-of-way and lands, relocation of high-
  ways, clearing of reservoir area and sodding and seeding, period
  July 1944 to June 1945----------------------------                  62, 676.34
Maintenance: Operation and maintenance of the flood control reser-
  voir, period July 1944 to June 1945-------------------------        27, 077. 06

       Total_
            -------------------            ----------------------      90, 030. 71

  The sum of $19,000 can be profitably expended during the fiscal year
1946 on maintenance and operation of the flood-control reservoir,
period July 1945 to June 1946.
 .No additional funds can be expended for new work during the fiscal
year in view of 'the existing Federal policies on wartime construction.
118         REPORT OF CHIEF OF ENGINEERS,                                           U. S. ARMY,                     1944

                                         Cost and financial summary
Cost of new work to June 30, 1944_-------                                                          ---           $3, 093, 323. 66
Cost of maintenance to June 30, 1944_                                 _                       __         _____25,         622. 94

      Total cost of permanent work to June 30, 1944----------                                                       3, 118, 946. 60
Minus accounts payable June 30, 1944----_ _-_-_-277. --                                                                          31

     Net total expenditures ____ _____----------3,                                                                       118, 669. 29
Unexpended balance June 30, 1944---------------------                                                                     90, 030. 71

         Total amount appropriated to June 30, 1944                                  ------------                   3, 208, 700. 00


   Fiscal year ending June 30                 1940                1941                1942                   1943             1944

                  .   .
Cost of new work------------          $1,069, 565. 63 $1, 555, 861.85              $304, 511.57          $116, 649.65        $25, 250.17
Cost of maintenance__                     -             --------------                5, 231.01            12, 255. 48         8,136.45
      Total cost---------------         1,069, 565.63        1, 555, 861. 85        309, 742. 58          128, 905. 13       33, 386.62
Total expended ..         ....----------------797, 757. 03   1, 681, 234. 06        407, 695. 18          173, 070. 92        38, 345. 44
Allotted ... --------------------
                 ..                     1,360, 000.00          400, 000.00          159, 000. 00             5,700.00       -16,000.00


Balance unexpended July 1, 1943_ __----          -------                                                             $144, 376. 15
Deductions on account of revocation of allotment_                                                                      16, 000. 00
      SNet amount to be accounted for_                               --                -       -     ___                 128, 376. 15
Gross amount expended __--            -                              -$39,                         019. 38
Less reimbursements collected----_ _-                                          -          -        673. 94
                                                                                                                          38, 345. 44
      Balance unexpended June 30, 1944---------------------                                                               90, 030. 71
Outstanding liabilities June 30, 1944_--   ---------                                                                      60, 284. 56
         Balance available June 30, 1944_--                                    --------                                   29, 746. 15
Amount (estimated) required to be appropriated for completion
of existing project 1 _   __--------------14,                                                                                000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1---------------------------                                                              19, 000. 00
  1Exclusive of available funds.

         32. TULLY RESERVOIR, OONNECTICUT RIVER BASIN, MASS.

  Location.-The site of the proposed Tully Dam is on the Tully
River, about 3.8 miles above its junction with the Millers River, and
1 mile north of Fryville, Mass. The reservoir will extend up the
Tully River about 21/2 miles.
   Existing project.-This project provides for the construction of a
rolled-fill earth dam, 1,500 feet long at its crest and rising 63. feet
above the stream bed, providing a total storage capacity of 22,150
acre-feet. A spillway will be constructed on rock in a saddle located
about 800 feet south of the left abutment of the dam. The outlet will
consist of a 6-foot diameter tunnel approximately 296 feet long.
Control will be accomplished by gates mechanically operated from a
tower located at the upper en4 of the tunnel. The drainage area
controlled is approximately 50 square miles. The design includes
provisions for future raising and adaption to the development of
hydroelectric power. The reservoir will be operated as a unit of a
coordinated reservoir system for the control of floods in the Con-
necticut River Basin.
                   FLOOD CONTROI--PROVIDENCE,                            R. I.,   DISTRICT.                 119

   The estimated cost, revised in 1940, is $596,000 for construction,
and $163,000 for lands and damages, including highway and utilities
relocation, a total of $759,000 for new work. The estimated cost of
annual maintenance is $7,700, of which $5,000 is for operating and care.
   The existing project was authorized by the Flood Control Acts ap-
proved June 22, 1936, and June 28, 1938 (H. Doc. No. 455, 75th Cong.,
2d sess.).
   Local cooperation--Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fscal year.-Engineering studies and
revision of plans and specifications were carried out. The cost was
$6,057.14. The expenditures were $5,867.91.
   Condition at end of fiscal year.-Geological investigations, reservoir
and dam-site surveys, plans and specifications were completed. Re-
vision of plans and specifications, in progress during the year, was
95 percent complete at the end of the year.
   The total costs under the project have been $78,877.35 for new work.
The expenditures were $78,688.12. In addition, $25,292.65 from funds
allotted for development of the general comprehensive plan for flood
control in the Connecticut River Basin was applied to preliminary
explorations, surveys, and design of the Tully Reservoir project.
   Proposed operations.--Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $21,311.88, plus accounts receivable
$95.73, a total of $21,407.61, as follows:
Accounts payable June 30, 1944_----------------------------------       $284. 96
New work: Completion of engineering studies and plans and specifica-
  tions_     -------------------------------------------             21, 122.65
         Total ---------------------------------------                                              21, 407.61
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                        Cost and financial summary
Cost of new work to June 30, 1944_ -------------------------- $78, 877. 35
Cost of maintenance to June 30, 1944---------------------------------
       Total cost of permanent work to June 30, 1944--------- --- 78, 877. 35
Plus accounts receivable June 30, 1944--------------------------       95. 73
      Gross total costs to June 30, 1944---- -------------     78, 973. 08
Minus accounts payable June 30, 1944--------------------------     284. 96
      Net total expenditures --------------------------------                                        78, 688. 12
Unexpended balance June 30, 1944 -----------------------------                                       21, 311.88
         Total amount appropriated to June 30, 1944- - - - - - - - -              -                 100, 000. 00

   Fiscal year ending June 30              1940           1941            1942          1943            1944


Cost of new work---------------          $70,804. 92     $2,015. 29--------------.--------------        $6,057. 14
Cost of maintenance --
Total expended...-----------------...    69,492.20        3,328.01                             ..        5,867.91
Allotted------------------------ -210,000.00-----                --------------.-------------------------
120      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                1944

Balance unexpended July 1, 1943_-         -----         -    --__   $27, 179. 79
Gross amount expended_ ____-----------$6,                   044. 31
Less reimbursements collected--- --------                   176. 40
                                                                      5, 867. 91

       Balance unexpended June 30, 1944_------            ---    21, 311. 88
                                    ----------------------------
Outstanding liabilities June 30, 1944_                               284. 96

      Balance available June 30, 1944_-------              ---          21, 026. 92
Aecounts receivable June 30, 1944------------------------------              95. 73

        Unobligated balance available June 30, 1944---------------      21, 122. 65

Amount (estimated) required to be appropriated for completion of
  existing project 1_- __________________---                 -       -659,   000. 00
1Exclusive of available funds.

           33.   HARTFORD, CONNECTICUT RIVER BASIN, CONN.
   Location.-Hartford, Conn., is located in Hartford County on the
west bank of the Connecticut River, 52 miles above the mouth.
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and flood walls approximately 38,000
feet long, along the Connecticut River from high ground immediately
north of town to high ground immediately south of town, with the
Park River, which discharges into the Connecticut River at about the
center of town, to be confined between concrete walls discharging
through a short conduit section through the Connecticut River dike,
including pumping stations for the disposal of interior drainage. The
improvement as planned involved the construction of approximately
4,000 linear feet of concrete flood wall, 22,000 feet of earth dike, and an
enlargement of 12,000 feet of existing dike along the Connecticut
River, the construction of 7,000 linear feet of concrete walls and 800
linear feet of concrete conduit on the Park River, construction of
four stoplog structures, three pumping stations, iand other appurte-
nant drainage structures and facilities. The project grade for levees
'and walls was designed to protect against a flood greater than any of
record, as modified by an approved plan of 20 reservoirs for flood
control in the Connecticut River Basin. The grades at all points were
:above the maximum stage of the record flood, that of March 1936.
At the request of the city of Hartford, the wall and dike grades were
increased 5 to 6 feet, the crown width for levees increased from 10
feet to 15 feet, and a conduit provided for the Park River in lieu of
the open channel improvement. Additional expense of approximately
 $2,220,500 involved in these changes is being borne by the city of
Hartford. The existing project was authorized by the Food Control
Act approved June 28, 1938 (H. Doc. No. 455, 75th Cong., 2d sess.),
and modified by the Flood Control Act of August 18, 1941 (H. Doe.
No. 653, 76th Cong., 3d sess.). The act of October 26, 1942 (Public,
No. 759, 77th Cong., 2d sess.) further modified the existing project
by including the construction of the Gully Brook conduit at an esti-
mated cost of $420,000. The estimated cost of new work for the
authorized project, revised in 1944, is $6,052,000 for construction and
 $900,000 for lands and damages, exclusive of the cost of the addi-
tional work desired by the city. In addition to the authorized exist-
ing project, supplementary work with relief labor has been undertaken
at a cost of $388,221.82 pursuant to the provisions of the Emergency
  Relief Act approved June 21, 1938.
            FLOOD CONTROI--PROVIDENCE,       R. I., DISTRICT        121
   Local cooperation.-See page 7 for requirements. Assurances of
local cooperation were approved by the Secretary of War on Decem-
ber 6, 1938, July 9, and August 26, 1940. Rights of entry have been
furnished for all construction undertaken to date. The sum of
$2,771,630 has been contributed by the city to cover the increased cost
of constructing the dikes to a higher grade, constructing a conduit
instead of walls for the Park River, and providing additional riprap
protection.
   Operations and results during fiscal year.-Construction was started
September 1940, under continuing contract, on the 5,600-foot double-
barreled pressure conduit for inclosing the Park River. The work
was practically completed during the year and included 30,000 cubic
yards of excavation, 54,600 cubic yaird's of earth fill, 13,900 cubic
yards of concrete, and 4,100 linear feet of drain pipe, at a total cost
of $396,972.78. Construction was started in September 1940, under
contract, on the section of earth dike and concrete flood wall, extend-
ing from Memorial Bridge 9,700 feet south to the existing dike. The
work was completed during the year at a cost of $22,684.69. The
reconstruction of the Masseek Street sewer and of the dike damaged
by slide which occurred July 1941 was completed at a cost of $71,-
197.93, of which $44,955 was reimbursed by the city of Hartford from
funds other than contributed funds. Construction was started Sep-
tember 1943, under contract, on temporary pumping stations at Bush-
nell Park and Keeney Lane. The work was practically completed
during the year at a cost of $49,485.41 for Bushnell Park and $98,-
542.15 for Keeney Lane. Preparation of engineering plans and
designs for the permanent pumping stations at Keeney Lane and
Bushnell Park was continued and the plans were practically com-
plete at the end of the year at a cost of $32,729. Construction was
started August 1943, under contract, on the 2,330-foot pressure conduit
inclosing Gully Brook. The work was practically completed during
the year and included 2,330 linear feet of excavation, 5,930 cubic
yards of backfill and 7,950 cubic yards of concrete, at a cost of
$413,089.47.
   The total costs were minus $308,170 from contributed funds, and
$1,347,916.43 from regular funds, a total cost of $1,039,746.43 for new
work. The expenditures were minus $308,170 from contributed funds,
and $1,531,573.60 from regular funds, a total of $1,223,403.60.
   Condition at end of fiscal year.-The existing project is approxi-
mately 95 percent complete. The work remaining to be done consists
of the completion of the Park River conduit, completion of the tempo-
rary Keeney Lane and Bushnell Park pumping stations, the construc-
tion of the permanent Keeney Lane and Bushnell Park pumping sta-
tions, and completion of the Gully Brook conduit.
   The costs of the existing project have been $835,000 from Public
Works Administration funds, and $4,884,484.41 from regular funds,.
a total of $5,719,484.41 for new work. In addition, costs of $2,214,-
139.72 apply to contributed funds. The expenditures have been
$835,000 from Public Works Administration funds, and $4,839,898.21
from regular funds, a total of $5,674,898.21. In addition, $2,214,139.72
was expended from contributed funds.
122        REPORT OF CHIEF OF ENGINEERS,                               U. S. ARMY,               1944

  Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, $634,592.07, plus $15,000 allotted in August 1944, as
follows:
Accounts payable June 30, 1944_---------------------                --- _      $44, 586. 20
New work: Completion of construction of the Park River conduit,
  the Gully Brook conduit, the temporary pumping stations at
  Bushnell Park and Keeney Lane, and completion of design of the
  permanent pumping stations at Bushnell Park and Keeney.Lane,
  period July 1944 to September 1944:
    From United States funds--------------------- $47, 515. 59
    From contributed funds                                          360. 28
                                                                 6,-----------------6
                                                                                  53, 875. 87
Overcontribution by the         city of Hartford,    to be returned    (esti-
  mated)----------------------.                   ------------------- _ 551, 130. 00

         Total----------------------------- ------                                                   649, 592.07
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                     Cost and financial summary
                                       UNITED       STATES      FUNDS

Cost of new work to June 30, 1944_-----------------------                                   1 $5, 719, 484. 41
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944_------                             --    15, 719, 484. 41
Minus accounts payable June 30, 1944--------------- ----                                              44, 586. 20
      Net total expenditures ----------------------------                                   1 5,674,898. 21
Unexpended balance June 30, 1944------ -------------------                                       77, 101. 79
         Total amount appropriated to June 30, 1944- ---------                               1 5, 752, 000. 00

   Fiscal year ending June 30          1940             1941             1942           1943               1944

Cost of new work-----------_-_    $998, 448.89 $1,285, 664.84 $1, 306, 979.36   $600, 989. 95         $1, 347,916. 43
Cost ofm aintenance . . . . . .-
                               --     . . .- - .. . . . . . . . . . ..---     - .-. --
                                                                                     .    .-              --.
                                                                                                          . . .
Total expended_..     ........       963, 588. 65     864,986.89     1,501, 007. 65   643, 433. 66      1, 531, 573. 60
Allotted.---------------------       600, 000.00    1, 776, 000.00    833, 000. 00    672, 000. 00      -143,000.00


Balance unexpended July 1, 1943--------------------------     $1,751, 675. 39
Deductions on account of revocation of allotment-------------    143, 000. 00
       Net amount to be accounted for----- ---------------                                       1, 608, 675. 39
Gross amount expended -------------------       $1, 754, 510. 83
Less reimbursements collected------ ----------       222, 937. 23
                                                                          --                     1, 531, 573. 60
      Balance unexpended June 30, 1944--------------------                                           77, 101. 79
Outstanding liabilities June 30, 1944-- ------- $3, 295. 15
Amount covered by uncompleted contracts..       70, 746. 48
                                                                                                      74, 041. 63
     Balance available June 30, 1944----------------------                                             3, 060. 16
Amount allotted in August 1944__
                             ----------------------------                                             15, 000. 00
        Amount available during fiscal year 1945--------------                                        18,060. 16
Amount (estimated) required to be appropriated for completion
of existing project2 - - -    -    -        - -- - - - - - - -                              -
                                                                                                     285000.00
   Includes $835,000 Public Works funds.
  2Exclusive   of available funds.
                   FLOOD CONTROL---PROVIDENCE,                                            R. I., DISTRICT                                123
                                                  CONTRIBUTED FUNDS

Cost of new work to June 30, 1944-                                                                                    $2, 214, 139. 72
Cost of maintenance to June 30, 1944--------------------------------
         Total cost of permanent work to June 30, 1944---------                                                             2, 214, 139. 72

Net total expenditures----------------------------------2, 214, 139. 72
Unexpended balance June 30, 1944-------------------------  557, 490. 28

         Total amount contributed to June 30, 1944--2,                                                                        771, 630. 00

    Fiscal year ending June 30                        1940                 1941             1942                 1948               1944


Cost of new work         ...---------------       $59, 049. 90         $649,701.17       $961,941.14           937. 41
                                                                                                           $340,                    -$308,170
Cost ofmaintenance           ...----------                    .------------------------------------------.--------........
Total expended ......-----------------             82, 887. 63          679, 431. 17      961, 941. 14         340, 937. 41          -308, 170

Contributed -------------------
            ........                                54, 230. 00       2,429,400. 00.-------------...--------------.-252, 000


Balance unexpended July 1, 1943            ----------                                                                        $501, 320. 28
Deductions on account of revocation of allotment---------                                                                     252, 000. 00

       Net amount to be accounted for------------------                                                                       249, 320. 28
Gross amount expended_----------------------    $144, 813. 50
Less reimbursements collected------------- ----  452, 983. 50
                                                                                                                            -308,    170. 00
         Balance unexpended June 30, 1944                                                                                     557, 490. 28
Amount (estimated) of over-contribution returnable to city of
  Hartford                                     --------------------                                                           551, 130.00

        CONSOLIDATED             COST          AND         FINANCIAL          SUMMARY         FOR        HARTFORD, CONN.

Cost of new work to June 30, 1944_ -----------------------  ' $7, 933, 624. 13
Cost of maintenance to June 30, 1944-----------------------
      Total cost of permanent work to June 30, 1944-- --------                                                              7, 933, 624. 13
Minus accounts payable June 30, 1944_------------------                                                                         44, 586. 20
      Net total expenditures----------------------------                                                              1 7,889, 037. 93
Unexpended balance June 30, 1944------------_ -------------                                                               634, 592. 07
         Total amount appropriated and contributed to June 30,
           1944 ----------------------------------------                                                              1 8,523, 630. 00

   Fiscal year ending June 30                         1940                 1941             1942                 1943               1944


Cost of new work.---.-_--------               $1,057, 498. 79 $1, 935, 366. 01 $2, 268,920. 50             $941, 927. 36        $1, 039, 746. 43
Cost of maintenance                                                                                        -            -
Total expended---------------1,046, 476. 28                           1,544,418. 06     2,462,948. 79          984, 371.07       1, 223, 403. 60
Allotted and contributed-------
                        ........ 654, 230. 00                         4, 205, 400. 00     833,000. 00          672,000. 00       -395,000.00


Balance unexpended July 1, 1943_-------------------------     $2, 252, 995. 67
Deductions on account of revocation of allotment-------------     395, 000. 00

       Net amount to be accounted for__                                                                                     1, 857, 995. 67
Gross amount expended-------------------       $1, 899, 324. 33
Less reimbursements collected_----------------     675, 920. 73
                                                                                                                            1, 223, 403. 60
         Balance unexpended June 30, 1944-----------------                                                                    634, 592. 07
  1Includes $835,000 Public Works funds.
124       REPORT OF CHIEF OF ENGINEERS,                            U. S. ARMY,         1944

Outstanding liabilities June 30, 1944 -------------                      $3, 295. 15
Amount covered by uncompleted contracts --------                         70, 746. 48
                                                                                            $74, 041. 63
     Balance available June 30, 1944---- ------------------                                 560, 550. 44
Amount allotted in August 1944_
                              ---------------------------                                    15, 000. 00
        Amount available during fiscal year 1945              ---------------           2   575, 550. 44
Amount (estimated) required to be appropriated (Federal funds)
for completion of existing project 3-------------------------                              285, 000. 00
2 Includes $551,130 over-contribution returnable to city of Hartford.
3 Exclusive of available funds.



         34. EAST HARTFORD, CONNECTICUT RIVER BASIN, CONN.

   Location.-East Hartford, Conn., is located in Hartford County
on the east bank of the Connecticut River, 52 miles above the mouth.
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and concrete flood walls consisting
of the following features: Approximately 19,000 feet of earth levee
and 750 feet of concrete flood wall along the Connecticut and Hocka-
num Rivers extending from the high ground near Greene Terrace in
the north, to high ground at Brewer Lane and Central Avenue in the
south; two stop-log structures; three pumping stations for the disposal
of interior drainage; and appurtenant drainage structures and facili-
ties. The levees and walls are designed to protect against a design
flood, greater than any of record, reduced by the approved plan of 20
reservoirs for flood control in the Connecticut River Basin. The levee
and wall grades are at all points above the maximum stage of the
greatest flood of record, that of March 1936. The existing project
was authorized by the Flood Control Act approved June 28, 1938 as
modified by Public, No. 859, Seventy-sixth Congress, approved October
15, 1940. The estimated cost of new work, revised in 1941, is $2,-
350,000 for construction and $270,000 for lands and damages. In addi-
tion to the authorized existing project, supplementary work with re-
lief-labor has been undertaken at a cost of $150,008.77 pursuant to the
provisions of the Emergency Relief Act approved June 21, 1938.
   Local cooperation.-See page 7 for requirements. Assurances
were approved by the Secretary of War January 5, 1939. Rights of
entry have been furnished, free of cost to the United States for all
construction undertaken to date. In addition to the above, the town
of East Hartford contributed $5,400 for the construction of inter-
connecting certain sewer lines. The sum of $2,237.48 also was con-
tributed for the installation of an additional 30-inch cast-iron pipe
through the dike at Meadow Hill with a view to its future use as an
outfall1 sewer line from a proposed sewage-treatment plant.
   Operations and results during fiscal year.-Construction was com-
pleted during the year, under contract, on two sections of earth dike
attaching to the completed section of dike and extending therefrom
6,800-feet and 7,100 feet respectively to high ground in the north
and south sections of the town. The work included 1,700 cubic yards
of earth fill and topsoil, 13 acres of sodding and seeding, and 200 cubic
yards of dike surfacing, at a cost of $57,328.61. Work was completed
during fiscal year 1943, under contract, on two pumping stations at
Cherry Street and Pitkin Street. Costs this fiscal year were $151.27.
   The total costs were $57,867.40 from regular funds, and minus $387.52
                      FLOOD CONTRO--PROVIDENCE,                                    R. I., DISTRICT                             125
from contributed funds. The expenditures, were $130,179.34 from
regular funds, and minus $387.52 from contributed funds.
  Condition at end of fiscal year.-The existing project is practically
complete. The work required to complete the project consists of the
design and construction of two storage structures for stop logs.
  The costs and expenditures of the existing project have been $380,000
from Public Works Administration funds, and $1,748,525.30 from
regular funds, a total of $2,128,525.30 all for new work. In addition,
costs and expenditures of $7,637.48 apply to contributed funds.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $90,324.26, minus the revocation of
$80,324.26 in September 1944, to new work, design and construction of
two stop-log storage structures, $10,000.
   No additional funds can be profitably expended during the fiscal
year 1946, as the above will complete the local protection work at East
Hartford, Conn.
                                               Cost and financial summary
                                                  UNITED STATES FUNDS

Cost of new work to June 30, 1944_                                                 -1                         $2, 128, 525. 30
Cost of maintenance to June 30, 1944
            Total cost of permanent work to June 30, 1944---------                                                2, 128, 525. 30
Net total expenditures_-----------                                                         --        -1           2, 128, 525. 30
Unexpended balance June 30, 194_------------_                                                                         90, 324. 26
            Total amount appropriated to June 30, 1944                              --------                  1   2, 218, 849. 56

   Fiscal year ending June 30                     1940              1941                1942          1943                1944


Cost of new work_- ---------                   $349, 980. 39    $284, 773. 01   $933, 386. 45      $445, 603. 48        $57, 867. 40
Cost of maintenance .---                                                                                                   -
Total expended ---------------                  286, 265. 92     313, 085. 48      844, 303. 57     507, 758. 95        130, 179. 34

Allotted_        ---------------------------
                         -_                                    1, 570,000. 00   -75, 000. 00 --           -             -56,150. 44


Balance unexpended July 1, 1943_--       ----------                                                                $276, 654. 04
Deductions on account of revocation of allotment-                                          -----   __                56, 150. 44
       Net amount to be accounted for----------------------                                                         220, 503. 60
Gross amount expended ------------------------   $130, 491. 56
Less reimbursements collected ------------------       312. 22
                                                                                                                    130, 179. 34
     Balance unexpended June 30, 1944--------------------                                                            90, 324. 26
Amount revoked in September 1944__-------- -----------------                                                         80, 324. 26
            Amount available during fiscal year 1945--- -----------                                                   10, 000. 00
                                                   CONTRIBUTED             FUNDS

Cost of new work to June 30, 1944-----------------                                                                   $7, 637. 48
Cost of maintenance to June 30, 1944
            Total cost of permanent work to June 30, 1944---------                                                     7, 637. 48

Net total expenditures_---              ---------------                                                                7, 637.48
Total amount contributed to June 30, 1944_                                                                             7, 637. 48
1Includes $380,000 Public Works funds.
126         REPORT OF CHIEF OF ENGINEERS,                                                      U. S. ARMY,                       1944


   Fiscal year ending June 30                    1940                    1941                       1942               1943                1944

Cost of new work - -        .-                      $5, 400       -       - -         -        --      -   -             $2, 625           -$387.   52
Cost of maintenance---                                                                                                  --                  -

Total expended------------------                      5,400 --                                                               2,625          -387. 52
Contributed                      ...---------------------------------------..---           -          $2, 625. --------------              -387.52

Reimbursements collected--
                       ________--------------$387.                                                                                              52
Deductions on account of revocation of allotment                                           ------------------                              387. 52

   CONSOLIDATED             COST AND FINANCIAL                          SUMMARY                FOR EAST HARTFORD,                         CONN.

Cost of new work to June 30, 1944 _______                                                                                 1$2, 136, 162. 78
Cost of maintenance to June 30. 1944

         Total cost of permanent work to June 30, 1944                                                ----------              1   2; 136, 162. 78

Net total expenditures_ _ ______                                                      -1                                          2, 136, 162. 78
Unexpended balance June 30, 1944 _90,                                                                                                     324. 26
         Total amount appropriated and contributed to June 30,
              1944--------------------------                                                   ---             -              1 2, 226, 487. 04

   Fiscal year ending June 30                    1940                    1941                       1942               1943                1944


Cost of new work .- ---        -            $355, 380. 39             $284, 773. 01        $933, 386. 45             $448, 228. 48        $57, 479. 88
C ost of m aintenance -- - - - -           .--- - - - -               .     - - -
                                                                           .--                . - __-              . . . _ __---.           .--
                                                                                                                                              --

Total expended- .---------------              291, 665. 92             313, 085. 48            844, 303. 57          510, 383. 95         129, 791.82

Allotted and contributed--              ---------------
                                     ..-...           1, 570, 000.00                       -72, 375.00 -----                 -       --   56, 537. 96


Balance unexpended July 1, 1943                                                                                                    $276,,654. 04
Deductions on account of revocation of allotment-                                                                                    56, 537. 96
       Net amount to be accounted for                                                                                                220, 116. 08
Gross amount expended                                                                      -$130,          491. 56
Less reimbursements collected------------------                                                            699. 74
                                                                                                                                     129, 791. 82
     Balance unexpended June 30, 1944                                                                                                 90, 324. 26
Amount revoked in September 1944 _                                                                                                    80, 324. 26
         Amount available during fiscal year 1945-                                                                                    10, 000. 00
  IIncludes $380,000 Public Works funds.
                  35. WINSTED, CONNECTICUT RIVER BASIN, CONN.
   Location.-Winsted is located in Litchfield County, on the Mad
River, a tributary of the Farmington River, which in turn is a
tributary of the Connecticut River, 115 miles from the mouth.
   Existing project.-The plan of improvement involves improve-
ment of the channel of Mad River to reduce flood heights. The
work consists of the removal of two dams and the excavation of a
trapezoidal channel from the Case Avenue Bridge to Lake Street,
with an average bottom width of 25 feet and 1-on-3 side slopes. The
existing project was authorized by the Flood Control Act approved
August 18, 1941 (H. Doc. No. 724, 76th Cong., 3d sess). The estimated
cost of the work is $140,000 for construction and $3,000 for lands and
damages.
   Local cooperation.-See page 7 for requirements. Informal assur-
ances of local cooperation have been furnished.
                    FLOOD CONTROL-PROVIDENCE,                                             R. I.,     DISTRICT                              127
  Operationsand results during fiscal year.-Operations consisted of
surveys, geological explorations, engineering studies in connection
with design, and preparation of plans and specifications. The cost
was $2,358.49 for new work.                              The expenditures were $1,252.88.
   Condition at end of fiscal year.-The plans and specifications were
70 percent complete. The total costs under the project have been
$2,358.49. The expenditures have been $1,252.88.
  Proposed operations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $2,747.12, plus accounts receivable of
$188 and additional allotment of $3,500 made in September 1944,.a
total of $6,435.12, as follows:
Accounts payable_-----------------------------------------$1,293.61
New work: Completion of surveys and engineering studies necessary
for preparation of plans and specifications, period July 1944 to
  June 1945---------------------------------------                5,                                                               5141.51
           Total                ---------------------------------------                                                            6,
                                                                                                                                   6435.     12
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                             Cost and financial summary
Cost of new work to June 30, 1944_                                           ----------                                           $2, 358. 49
Cost of maintenance to June 30, 1944---------
       Total cost of permanent work to June 30, 1944-------                                                                        2, 358. 49
Plus accounts receivable June 30, 1944------------------- ------                                                                      188. 00
      Gross total costs to June 30, 1944-----------------2,                                                                           546. 49
Minus accounts payable June 30, 1944                                                                                                  293. 61
                                                                                                                                   1-------------------1,
      Net total expenditures                                  ---------------------                                                1, 252. 88
Unexpended balance June 30, 1944_-                                                                                                 2, 747. 12
           Total amount appropriated to June 30, 1944---------- ----                                                               4, 000. 00

   Fiscal year ending June 30                    1940              1941                    1942                    1943               1944


Cost of new work----.....--------------------------.....--------------..........--------------.                                       $2, 358. 49
Cost of m aintenance ..   ..  . . .. . . ..  .......         .-

T otal expended       .......        . . . . . . . . . . . . . .-..       . . ..    . . . .                   ... . .    .....
                                                                                                                            -          1,252.88

Allotted           .....---------------------------------------------                      ...-------------             $4, 000-----------


Balance unexpended July 1, 1943 ----------------------------      $4, 000. 00
Gross amount expended     -------------------------    $1,256. 98
Less reimbursements collected------ ------------------      4. 10
                                                              -    1, 252. 88
      Balance unexpended June 30, 1944----------------                                                                             2, 747. 12
Outstanding liabilities June 30, 1944--------------------1,                                                                           293. 61
      Balance available June 30, 1944------------------1,                                                                             453. 51
Accounts receivable June 30, 1944 ------------------------------                                                                      188.00
     Unobligated balance available June 30, 1944-      --                                                                -         1, 641. 51
Amount allotted in September, 1944--------------------                                                                             3, 500. 00

Amount available during fiscal year 1945----------------                                                                           5, 141. 51

Amount (estimated)  required to be appropriated for completion of
                 - - - - - - - - - -
   existing project             1_                __      ______                                                                 132, 500.00
  I Exclusive of available funds.
128    REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,   1944

        36. SPRINGFIELD, CONNECTICUT RIVER BASIN, MASS.

    Location.-Springfield, Mass., is located in HIjampden County, on
the east bank of the Connecticut River, 76 miles above the mouth.
    Existing project.-The plan of improvement provides for the pro-
tection from flooding by the Connecticut River-of 2 large low areas
located in the northern and southern sections of the city. Protection
is provided for the northern area by earth levees and concrete walls
extending from high ground north of the Chicopee-Springfield town
line downstream to high ground near the Boston & Albany Railroad
bridge and for the southern area by concrete walls extending from high
ground below the Memorial Bridge to high ground at the South End
Bridge, and a pressure conduit, extending from the Connecticut River
up the Mill River, to provide protection against backwater and to
carry the flow of the Mill River. The improvement involves the
construction of approximately 700 feet of earth levee, 13,000 feet of
concrete flood wall, 1,700 feet of concrete conduit, wing walls along
the Mill River above 2 dams and above a highway bridge, 1 pumping
station and appurtenant drainage features to supplement the city
system of disposal of interior drainage. The levees and walls are
designed to protect against a flood, greater than any of record, re-
duced by the approved plan of 20 reservoirs. The levee and wall
grades are at all points above the maximum stage of the greatest flood
of record, that of March 1936. The existing project was authorized
by the Flood Control Act approved June 28, 1938 (H. Doc. No. 455,
75th Cong., 2d sess.) and modified by the Flood Control Act of
August 18, 1941 (H. Doc. 653 and 724, 76th Cong., 3d sess.).
    The estimated cost of new work, revised in 1941, is $925,000 for
construction and $272,000 for lands and damages. In addition to the
authorized existing project, supplementary work with relief labor
has been undertaken at a cost of $204,385.81 pursuant to the provi-
sions of the Emergency Relief Act approved June 21, 1938.
    Local cooperation.-See page 7 for requirements. The city has
furnished assurances of required cooperation for the entire plan of
improvement, and rights-of-way have been furnished free of cost to
the United States for all construction on the project. In addition to
the above, the city of Springfield has contributed $5,350 for the con-
struction of intercepting sewers and additional surface drains.
    Operationsand results during fiscal year.-Plans and designs were
substantially completed during the year for wing walls along the Mill
River above two dams and above a highway bridge at a cost of
$5,705.97. Expenditures were $5,194.32.
    Condition at end of fiscal year.-The existing project is approxi-
mately 95 percent complete. The work remaining to be done consists
of completion of plans and designs for, and construction of wing
walls along the Mill River above two dams and above a highway bridge.
The costs have been $355,000 from Public Works Administration funds,
and $513,710.07 from regular funds, a total of $868,710.07. In addi-
tion, costs of $5,350 apply to contributed funds. The expenditures
have been $355,000 from Public Works Administration funds, and
$513,198.42 from regular funds, a total of $868,198.42. In addition,
$5,350 has been expended from contributed funds.
                      FLOOD CONTROL-PROVIDENCE, R. I., DISTRICT                                                            129
  Proposed operation8s.-It is proposed to apply funds unexpended
on June 30, 1944, amounting to $14,801.58, and accounts receivable,
$101.80, a total of $14,903.38, as follows:
Accounts payable$-------------------------------------------             613. 45
New work:
    Completion of surveys and engineering studies necessary for the
      design of concrete wing walls along the Mill River, period July
      1944toSeptember 19442------------------------,                    300. 00
    Available for future commencement of construction of the above__ 11,989. 93

           Total----------                -----------------------------------                                      14, 903. 38
   No additional funds can be expended during fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                          Cost and financial summary
Cost of new work to June 30, 1944 -------------------------                                                  1 $868, 710. 07
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944------- --- 1868, 710. 07
Plus accounts receivable June 30, 1944------------------------        101. 80
      Gross total costs to June 30, 1944---------------- ----- 868, 811. 87
Minus accounts payable June 30, 1944-------------------------       613. 45
      Net total expenditures--------------------------                                                            868, 198. 42
Unexpended balance June 30, 1944--------------------                                                               14, 801. 58
           Total amount appropriated to June 30, 1944- -----                                             -        883, 000. 00

    Fiscal year ending June 30              1940                 1941          1942                   1943             1944

Cost of new work.--------------
                            $460, 092. 44   $274, 285. 96                  $3, 290. 71         -$5,                       705. 97
Cost of maintenance----
                   ...---------       . ...     ..    ...                 ..      ..------------             --

Total expended..--..          .--------   481, 503. 22     310, 468. 14        8,145. 73                                5, 194. 32
Allotted...........
            ---------------------------------               65, 000. 00                                 $3, 000         5, 000. 00.


Balance unexpended July 1, 1943          -----------                                                              $14, 995. 90
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942    -----------------------------                                                           5, 000. 00
       Amount to be accounted for---------------------                                                             19, 995. 90
Gross amount expended-------------------------     $5, 403. 44
Less reimbursements collected----- ---------------     209. 12
                                                                                                                    5, 194. 32
      Balance unexpended June 30, 1944------------- ---                                                            14, 801. 58
Outstanding liabilities June 30, 1944 -- ------------------------                                                      613. 45
      Balance available June 30, 1944------------------------                                                      14, 188. 13
Accounts receivable June 30, 1944----------------------------                                                          101. 80

           Unobligated balance available June 30, 1944                                                             14, 289. 93
Amount (estimated) required to be appropriated for completion
   of existing project 2------                           -----                        ------                       42, 000. 00
  I Includes $355,000 Public Works funds; in addition, the sum of $5,350 was expended from contributed
funds.
  2Exclusive of available funds.
        616634--45-pt. 1, vol. 1                9
130     REPORT OF CHIEF OF ENGINEERS,       U.   S.   ARMY,   1944

      37. WEST SPRINGFIELD, CONNECTICUT RIVER BASIN, MASS.

   Location.-West Springfield, Mass., is located in Hampden County
on the west bank of the Connecticut River, 76 miles above the mouth.
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and flood walls, approximately 24,500
feet in length, extending along the Connecticut and Westfield Rivers
for the protection of the section of town located on the point of land
above the junction of and between the two rivers. Three pumping
stations are provided for the disposal of the interior drainage. The
protection system extends from high ground in the vicinity of Harri-
son Place downstream along the Connecticut River and thence up-
stream along the Westfield River to high ground at the Boston &
Albany Railroad and involves the construction of approximately
2,300 feet of concrete flood wall, enlargement of 13,700 feet of exist-
ing levee, 2,400 feet of bank improvement, 6,100 feet of foundation
treatment and three pumping stations. The levees and walls are de-
signed to protect against a flood, greater than any of record, reduced
by the approved plan of 20 reservoirs. 'The levee and wall grades are
at all points above the maximum stage of the greatest flood of record,
that of March 1936. The existing project was authorized by the
Flood Control Act approved June 28, 1938 (H. Doc. No. 455, 75th
Cong., 2d sess.), and modified by the Flood Control Act of August
18, 1941 (H. Doc. No. 653, 76th Cong., 3d sess.). The estimated cost
of new work, revised in 1941, is $1,252,000 for construction and $30,000
for lands and damages. In addition to the authorized existing proj-
ect, supplementary work with relief labor has been undertaken at a
cost of $223,947.21 pursuant to the provisions of the Emergency Re-
lief Act approved June 21, 1938.
   Local cooperation.-See page 7 for requirements. The town has
provided the required assurances of cooperation for the entire plan
of improvement. Assurances covering work north of the North End
Bridge; between North End Bridge and Memorial Bridge; south of
Memorial Bridge to point near Circuit Avenue; from point near Cir-
cuit Avenue to Agawam Bridge; and north of Agawam Bridge, were
approved by the Secretary of War on February 28, 1939, January 31,
1940, May 23, 1939, March 31, 1941, and February 20, 1939, respec-
tively. Rights-of-way have been furnished free of cost to the United
States for all construction undertaken to date.
    Operations and results during fiscal year.-Work was completed
during the year on the construction of the Warren Street pumping
station at a cost of $12,676.99. Plans and designs were substantially
completed during the year for the foundation treatment for the sec-
tion of the dike along the Westfield River south of Agawam Bridge
at a cost of $4,156.71.
    The total costs were $16,833.70 from regular funds for neiv work.
The expenditures were $32,340.02 from regular funds.
    Condition at end of fiscal year.-The existing project is approxi-
mately 90 percent complete. The work remaining to be done to
complete the project consists of the completion of plans and designs
for, and construction of the foundation treatment for the section of
dike along the Westfield River south of Agawam Bridge. The costs
of the existing project have been $245,000 from Public Works Ad-
                      FLOOD       CONTRO---PROVIDENCE,                         R. I.,    DISTRICT                       131
    ministration funds, and $705,657.07 from regular funds, a total of
    $950,657.07 for new work. The expenditures have been $245,000
    from Public Works Administration funds, and $705,418.45 from reg-
    ular funds, a total of $950,418.45.
       Proposed operations.--It is proposed to apply funds unexpended
    on June 30, 1944, amounting to $4,581.55, plus accounts receivable of
    $39.13, a total of $4,620.68, as follows:
    Accounts payable              -------------------------------------------              $277. 75
    New work: Completion of surveys, foundation explorations, and engi-
      neering studies necessary for the preparation of plans and specifica-
      tions covering foundation treatment of a section of dike along the
      Westfield River south of Agawam Bridge, period July to September
      1944_----------------------                            ---------------------------- 4,342. 93

             Total---------------------------------------                                                         4, 620. 68
       No additional funds can be expended during fiscal year 1946 in
    view of the existing Federal policies on wartime construction.
                                          Cost and financial summary
    Cost of new work to June 30, 1944___ _                                   ___1                          $950, 657. 07
    Cost of maintenance to June 30, 1944
           Total cost of permanent work to June 30, 1944--- -------                                        1950, 657. T07
    Plus accounts receivable June 30, 1944------------------------                                                    39. 13:
          Gross total costs to June 30, 1944---- -----------------                                              950, 696. 20
    Minus accounts payable June 30, 1944                                                                             277. 75
          Net total expenditures -------------------------------                                           1 950, 41& 45
    Unexpended balance June 30, 1944---------------------------                                                   4, 581. 55
             Total amount appropriated to June 30, 1944- -------                                                955, 000. 00


       Fiscal year ending June 30             1940              1941             1942              1943              1944

                                  .
    Cost of new work--- ------ -----       $277, 701. 25    $176, 202. 72 $247, 998. 92          $52, 732. 29       $16, 833.7(
    Cost of maintenance ----        ........ .     ...             .....
                                                         ... --------------
    Total expended   ----------------       287, 326. 66      194, 798. 41     235, 426. 91       62, 200.63         32, 340. 02

    Allotted ----------------------
             .....                          402,000 00       -33,000.00 -8,00000.                     000.00.__


    Balance unexpended July 1, 1943__-_____                                                                     $36, 921. 57
    Gross amount expended_-------                 ---                                 $32, 935. 43
    Less reimbursements collected---------------------                                     595. 41
                                                                                                                 32, 340. 02
          Balance unexpended June 30, 1944_----_                                                                  4, 581. 55
    Outstanding liabilities June 30, 1944                  ---------------                    $133. 38
I
    Amount covered by uncompleted contracts                        ----------                   144. 37
                                                                                                   --                277. 75

          Balance available June 30, 1944_   -----------------                                                    4, 303. 80,
    Accounts receivable June 30, 1944----------------------------                                                     39. 13
             Unobligated balance available June 30, 1944--------                                                  4, 342. 93

    Amount (estimated)         required   to be appropriated for completion of
                                    -- - - - - -- - - - - - -- - - - -- - - - -- - -
      existing project 2- - - - - -                                                                             297, 000. 00
     1Includes $245,000 Public Works funds.
      2 Exclusive of available funds.
 132      REPORT OF CHIEF OF ENGINEERS,                            U. S. ARMY,                  1944

            38. RIVERDALE, CONNECTICUT RIVER BASIN, MASS.

    Location.-Riverdale is in the northern portion of the town of West
Springfield, Mass., in Hampden County, on the west bank of the
.Connecticut River. It is located 76 miles from the mouth.
    Existing project.-The plan of improvement involves the construc-
tion of approximately 12,700 feet of earth levee, and 2 pumping sta-
tions. The levee will provide protection against a flood greater than
any of record, reduced by the approved plan of 20 reservoirs. The
grades are at all points above the maximum stage of the greatest
flood of record, that of March 1936. The existing project was au-
thorized by the Flood Control Act approved August 18, 1941 (H. Doc.
724, 76th Cong., 3d sess.). The estimated cost of the work is $490,000
for construction, and $50,000 for lands and damages.
    Local cooperation.-See page 7 for requirements. Assurances of
local cooperation have not been furnished.
    Operations and results during fiscal year.-Operations consisted of
surveys, foundation explorations, engineering studies in connection
with design, and preparation of plans and specifications. The cost was
 $14,286.79 for new work. The expenditures were $12,592.75.
    Condition at end of fiscal year.-Surveys and foundation studies
were completed. Engineering studies and preparation of plans and
specifications were 40 percent complete. The total costs under the
project have been $14,286.79 for new work. The expenditures have
been $12,592.75.
    Proposedoperations.-Itis proposed to apply the funds unexpended
June 30, 1944, amounting to $24,407.25, plus accounts receivable of
 $291.99, a total of $24,699.24, as follows:
Accounts payable___---- -------------                          $1,986.03
New work: Completion of engineering studies in connection with
   design andpreparation of plans and specifications-------     22, 713. 21

        Total      ---------------------------------------------                                      24, 699. 24
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                    Cost and financial summary
Cost of new work to June 30, 1944_                                                                  $14, 286. 79
Cost of maintenance to June 30, 1944
        Total cost of permanent work to June 30, 1944-------------                                    14, 286. 79
Plus accounts receivable June 30, 1944_--     ----------                                                 291. 99
       Gross total costs to June 30, 1944_-------                                    ---              14, 578. 78
Minus accounts payable June 30, 1944-----                                        -_____               1,986. 03
       Net total expenditures-____------                                       -_____                 12, 592. 75
Uneipended balance June 30, 1944_-                        -----                -_____                24, 407. 25
        Total amount appropriatedto June 30, 1944                  ---------------                    37, 000. 00

   Fiscal year ending June 30           1940             1941       1942                 1943             1944

Cost of new work------.--.--------------------------.---------------------------- $14,286.79
Cost of maintenance-----------------------------------------------------------------
Total expended-................. -....
                                    ......                                 -12,6592.75           .--.-
                                        .-.--- ..- .. .-
Allotted ......................----.-.-...-.--.--                               I        $12, 000        25,000.00
                 FLOOD CONTROLr-PROVIDENCE,            R. I., DISTRICT         133
Balance unexpended July 1, 1943 ----------------------------  $12, 000. 00
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942__-----------------------------------  25, 000. 00

       Amount to be accounted for--------------------                    37, 000. 00
Gross amount expended_-------------------------     $13, 705. 39
Less reimbursements collected-_-------_-------_        1, 112. 64
                                                                    -    12, 592. 75

       Balance unexpended June 30, 1944---------------                   24, 407. 25
Outstanding liabilities June 30, 1944---------------------------          1, 986. 03
      Balance available June 30, 1944-----------------                   22, 421. 22
Accounts receivable June 30, 1944_
                                 ------------------------------              291. 99

        Unobligated balance available June 30, 1944--- -----             22, 713. 21
Amount (estimated) required to be appropriated for completion
of existing project 1 -------------------------------------  453, 000.00
1 Exclusive of available funds.

              39. CHICOPEE, CONNECTICUT RIVER BASIN, MASS.

   Location.-Chicopee, Mass., is located in Hampden County on the
east bank of the Connecticut River, 80 miles above the mouth.
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and floodwalls, approximately 25,700
feet in length, extending along the Connecticut River and north and
south banks of the Chicopee River, which flows into the Connecticut
River in the southern section of town, and pumping stations for the
disposal of interior drainage. The protection system consists of two
short sections of dike in the Willimansett section in the extreme
northern portion of the city; 20,200 feet of levee extending from high
ground about 2 miles below the Willimansett Bridge dpwnstream
along the Connecticut River and up the north bank of the Chicopee
River to high ground above the Boston and Maine Railroad Bridge;
3,200 feet of floodwalls and 1,500 feet of levee along the south bank of
the Chicopee River and Connecticut River from high ground above
the highway bridge over the Chicopee River to high ground north of
the highway bridge over the Connecticut River; three stop-log struc-
tures; six pumping stations, and appurtenant drainage structures.
The levees and walls are, designed to protect against a flood, greater
than any of record, that of March 1936. The existing project was
authorized by the Flood Control Act approved June 28, 1938. The
estimated cost of the new work, revised in 1941, is $1,592,000 for con-
struction and $500,000 for lands and damages. In addition to the
authorized existing project, supplementary work with relief labor has
been undertaken at a cost of $168,677.26 pursuant to the provisions
of the Emergency Relief Act approved June 21, 1938.
   Local cooperation.-See page 7 for requirements. The city has
provided the required assurances of cooperation for the entire plan
of improvement. Assurances were approved by the Secretary of War
November 10, 1938. Rights of entry have been furnished, free of
cost to the United States, for all construction undertaken to date.
   Operations and results during fiscal year.-None. There were no
costs or expenditures.
   Condition at end of fiscal year.-The existing project is approxi-
mately 85 percent complete. Work remaining to be done consists of
134         REPORT OF CHIEF OF ENGINEERS,                           U.   S. ARMY,           1944

the completion of design and construction of the dike in the Williman-
sett section and the Charbonneau terrace pumping station.
   The costs and expenditures of the existing project have been $295,000
from Public Works Administration funds, and $1,112,182.42 from
regular funds, a total of $1,407,182.42, for new work. In addition,
costs and expenditures of $385 apply to contributed funds.
   Proposed operations.-It is proposed to apply funds unexpended
on June 30, 1944, $14,817.58, to new work, completion of design of
Willimansett section dike work and pumping station, period July
1944 to June 1945.
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                   Cost and financial summary
Cost of new work to June 30, 1944--- --------                                           1 $1, 407, 182. 42
Cost of maintenance to June 30, 1944

           Total cost of permanent work to June 30, 1944                 ---------          11, 407, 182. 42
Net total expenditures---- -----------                    -1 1, 407, 182. 42
Unexpended balance June 30, 1944-------------------------        14, 817. 58

           Total amount appropriated to June 30, 1944                -----------         1 1, 422, 000. 00

   Fiscal year ending June 30          1940           1941            1942           1943                1944

Cost of new work -------------
                      .             $372,821. 31   $735, 735. 44   $135,404. 95     $2, 375. 95    -.    ..
                                    ..... . . ........ - .... . . . ...
Cost ofm aintenance .................-..                                                                 -.........

Total expended.-----------------426, 353.02         618, 314.31     213, 889.26     53, 338.89          -.
Allotted                           474,000.00 -575, 000. 00-
                        .---------------------                      .......       .... ....       ..     .........



Balance unexpended July 1, 1943                                                                   $14, 817. 58
Gross amount expended_--        --------          $2,452.71
Less reimbursements collected ------------------- 2, 452. 71-

Balance unexpended June 30, 1944              --------------------------                           14, 817. 58
Amount (estimated) required to be appropriated for completion
                                             -    - - - - - -
of existing projects 2 - - - - _ -- - - - -
                                                                                                  170, 000. 00
  1Includes $295,000 Public Works funds; in addition, the sum of $385 was expended from contributed
funds.
  sExclusive of available funds.

               40. HOLYOKE, CONNECTICUT RIVER BASIN, MASS.

   Location.-Holyoke, Mass., is located in Hampden County on the
west bank of the Connecticut River, 85 miles above the mouth.
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and concrete flood walls, consisting of
the following features: Approximately 400 feet of earth levee and
approximately 5,600 feet of concrete flood wall along the Connecticut
River, extending from the Holyoke Water Power Co. dam southerly
to high ground near Mosher Street; about 10,000 feet of concrete
flood wall along the Connecticut River, from high ground near Ap-
pleton Street southerly to the existing Springdale levee, including a
               FLOOD CONTRO---PROVIDENCE,              R. I.,   DISTRICT        135
concrete flood wall along both banks of a power canal, the level of
which is below flood grade; 7 pumping plants for the disposal of
interior drainage; 14 stop-log structures; 28 gate structures for inlet
and outlet works of existing power developments; and appurtenant
drainage structures. The levees and walls are designed to protect
against a flood, greater than any of record, reduced by the approved
plan of 20 reservoirs. The levee and wall grades are at all points
above the maximum stage of the greatest flood of record, that of
March 1936. The existing project was authorized by the Flood Control
Act approved June 28, 1938, and modified by the Flood Control Act
of August 18, 1941.
   The estimated cost of new work, revised in 1941, is $2,424,000 for
construction and $150,000 for lands and damages. In addition to the
authorized existing project, supplementary work with relief labor
has been undertaken at a cost of $344,236.87 pursuant to the pro-
visions of the Emergency Relief Act approved June 21, 1938.                        4


  Local cooperation.- See page 7 for requirements. The city has
furnished the required assurances of cooperation for the entire plan
of improvement. The assurances were approved by the Secretary of
War, January 19, 1939. Rights of entry have been furnished, free
of cost to the United States, for all construction undertaken to date.
In addition to the above, $3,355.70 was contributed by the city of
Holyoke to cover cost of relocation of poles of the Holyoke Water
Power Co. and connecting certain intersecting city sewers with the
project drainage system.
   Operations and results during fiscal near.-Engineering    studies and
design of the protection works south ofMosher Street were continued
at a cost of $540.27. Expenditures were $422.75.
   Conditions at end of fiscal year.-The construction work authorized
under the existing project is about 45 percent complete. Work remain-
ing to be done consists of completion of stop-log structures and of
design and construction of the dike and pumping stations south of
Mosher Street. The costs of the existing project have been $610,000
from Public Works Administration funds, and $469,679.47 from regu-
lar funds, a total of $1,079,679.47. In addition, costs of $3,355.70
apply to contributed funds. The expenditures have been $610,000
from Public Works Administration funds, and $469,561.95 from regu-
lar funds, a total of $1,079,561.95. In addition $3,355.70 was expended
from contributed funds.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $53,438.05, and accounts receivable,
$10.80, a total of $53,448.85, as follows:
Accounts payable-------------------------------------------            $128. 32
New work: Completion of the surveys, engineering studies, and design
  of the local protective work south of Mosher Street, and completion
  of stop-log structures, period July 1944 to June 1945 ------------ 53, 320. 53

      Total-----------------------------------------                       53,448.85
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
136          REPORT OF CHIEF OF ENGINEERS, U.' S. ARMY,                                                 1944

                                        Cost and financial summary
Cost of new work to June 30, 1944___---                                      __-__-1                    $1, 079, 679. 47
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944---------                                          1   1, 079, 679. 47
Plus accounts receivable June 30, 1944 -----------------------                                                     10. 80

      Gross total costs to June 30, 1944                  ---------------------                           1, 079, 690. 27
Minus accounts payable June 30, 1944_--                                      --------                             128. 32

      Net total expenditures -----------------------------
                                      _                                                                 11, 079, 561. 95
Unexpended balance June 30, 1944_--       ----------                                                             53, 438. 05

           Total amount appropriated to June 30, 1944-----------
                                                         _       11, 133, 000. 00

    Fiscal year ending June 30             1940            1941               1942               1943               1944

Cost of new work -------------          $633, 591. 13   $318,148. 03         $7, 409. 05   --------------
                                                                                                   ...                $540. 27
Cost of maintenance------------------
Total expended_----------------          524, 872. 64   418, 917. 61         15, 684. 73                               422. 75
Allotted        _          __    _       466, 000.00    -15,000.00     ...           .......                        22,000.00

Balance unexpended July 1, 1943-                                                                              $31, 860. 80
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942                                                                                         22, 000. 00
       Amount to be accounted for                         --                                                     53, 860. 80
Gross amount expended-------------------------       $426. 31
Less reimbursements collected---------------- ------    3. 56
                                                         - -422.                                                           75
      Balance unexpended June 30, 1944 --------------------                                                      53, 438. 05
Outstanding liabilities June 30, 1944 -   -     -    -    -                                                  -       136. 32
      Balance available June 30, 1944_------                                                    ---              53, 301. 73
Accounts receivable June 30, 1944_--------                                                            ---             10. 80

           Unobligated balance available June 30, 1944                       -----------                         53, 312. 53

Amount (estimated) required to be appropriated for completion
of existing project 2- -       -      -      ..---                                                         1, 291, 000. 00
  1 Includes $610,000 Public Works funds; in addition $3,355.70 was expended from contributed funds.
  2 Exclusive of available funds.

              41. SPRINGDALE, CONNECTICUT RIVER BASIN, MASS.
   Location.-Springdale is in the southern portion of the city of
Holyoke, Mass., in Hampden County, on the west bank of the Connecti-
cut River, 85 miles from the mouth.
   Existing project.-The plan of improvement involves the recon-
structing of approximately 4,200 feet of earth levee, and the con-
struction of a pumping station, a discharge gate for an existing outfall
sewer, and a short length of concrete wall between gate structure and
pumping station. The levee will provide protection against a flood
greater than any of record, reduced by the approved plan of 20 res-,
ervoirs. The grades are at all points above the maximum stage of the
greatest flood of record, that of March 1936. The existing project was
authorized by the Flood Control Act approved August 18, 1941 (H.
Doc. 724, 76th Cong., 3d sess.). The estimated cost of the work is
$390,000 for construction, and $57,000 for lands and damages.
  Local cooperation.-See page 7 for requirements. Assurances of
local cooperation have not been furnished.
                     FLOOD CONTROL-PROVIDENCE, R. I., DISTRICT                                                                   137

   Operations and results during fiscal year.-Operations consisted of
surveys, exploration of foundation conditions and engineering studies
in connection with design. The preparation of plans and specifications
was initiated. The cost was $7,207.11 for new work. The expenditures
were $6,735.89.
   Condition at end of fiscal year.--Surveys, exploration of foundation
conditions and engineering studies in connection with design of the
authorized project were 25 percent complete. The total costs under the
project have been $7,207.11 for new work. The expenditures have been
$6,735.89.
  Proposedoperations.-Itis proposed to apply the funds unexpended
June 30, 1944, amounting to $16,264.11, plus accounts receivable of
$188.09, a total of $16,452.20, as follows:
Accounts payable___-------------------------------------------           $659. 31
New work: Completion of surveys, foundation explorations, engineer-
  ing studies in connection with design, and plans and specifications- 15, 792. 89
       Total_ ---------------------------------------------            16, 452. 20
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                          Cost and financial summary
Cost of new work to June 30, 1944__                                 -------.-----                                     $7, 207. 11
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944-------------                                                      7, 207. 11
Plus accounts receivable June 30, 1944---      ----------                                                                 188. 09
      Gross total costs to June 30, 1944------------------------                                                       7, 395. 20
Minus accounts payable June 30, 1944,.-     -------           ---                                                         659. 31
      Net total expenditures ---------------------------------                                                         6, 735. 89
Unexpended balance June 30, 1944_--      ----------                                                                   16, 264. 11
          Total amount appropriated to June 30, 1944                                        ---------------           23, 000. 00
    Fiscal year ending June 30                1940                  1941                    1942          1943               1944

Cost of new work --
C ost of m aintenance ..-                            -   -
                                                             -
                                                             --   - - - -        --
                                                                                          ----------
                                                                                       - - - - - - -   ------. . .       .
                                                                                                                             $7, 207.11
                                                                                                                                    ---..

Total expended -.......        -----                                        --                           ------               6, 735.89
Allotted ................-----------------..........----------------------------------------                $10,000          13,000.00


Balance unexpended July 1, 1943_------------                 -  $10, 000. 00
Amount allotted from War Department Civil Appropriation Act ap-
  proved Apr. 28, 1942-----    --------------------------------  13, 000. 00
       Amount to be accounted for -                                        -------                                    23, 000. 00
Gross amount expended_--------                                                        ---          $6, 978. 52
Less reimbursements collected-___   -------                                                            242. 63
                                                                                                                       6, 735. 89
      Balance unexpended June 30, 1944--....     -------          16, 264. 11
Outstanding liabilities June 30, 1944----------------------------     659. 31
      Balance available June 30, 1944---                                         --------                             15, 604: 80
Accounts receivable June 30, 1944_--                                                   -
                                                                                 - _- -_                                  188. 09
          Unobligated balance available June 30, 1944 --------                                                        15, 792. 89
Amount (estimated) required to be appropriated for completion of
existing project '___    ----------- __ _367,                                                                               000. 00
  1 Exclusive of available funds.
138     REPORT OF CHIEF OF ENGINEERS,                    U.   S. ARMY,   1944

       42. NORTHAMPTON, CONNECTICUT RIVER BASIN, MASS.

   Location.-Northampton, Mass., is located in Hampshire County,
on the yvest bank of the Connecticut River, 94 miles above the mouth.
   Existing,project.-The plan of improvement provides for closing
off the valley of the Mill River within the town limits and the diver-
sion of Mill River through a canal to the Connecticut River via Ox
Bow Lake south of town; and a pumping station for the disposal of
interior drainage. The improvement involved the construction of two
closing dikes consisting of approximately 5,000 feet of levee in the
eastern portion of town along the Connecticut River extending from
high ground at Pomeroy Terrace across the bed of the Mill River to
high ground west of United States Highway No. 5, and 1,900 feet of
levee and 500 feet of flobd wall along the eastern bank of the Mill River
in the western portion of town; a diversion canal approximately 10,500
feet along, of which 2,700 feet is riprapped, to carry the flow of Mill
River and a combined concrete bridge and drop structure and a smaller
concrete bridge; a pumping plant; three stop-log structures, and ap-
purtenant drainage structures. The levees and walls are designed to
protect against a flood, greater than any of record, reduced by the
approved plan of 20 reservoirs. The levee and wall grades are at all
points above the maximum stage of the greatest flood of record, that
of March 1936. The existing project was authorized by the Flood
Control Act approved June 28, 1938. The estimated cost of new work,
revised in 1941, is $960,000 for construction and $150,000 for lands
and damages. In addition to the authorized existing project, sup-
plementary work with relief labor has been undertaken at a cost of
 $259,658.36 pursuant to the provisions of the Emergency Relief Act
approved June 21, 1938.
   Local cooperation.-See page 7 for requirements. The town has
furnished the required assurances of cooperation for the entire plan of
improvement. The assurances were approved by the Secretary of
War January 17, 1939. Because of changes in plan of construction,
new assurances were obtained for levee work along the east bank of
the Mill River and for the storage pond for the pumping station. The
assurances for these two sections were approved by the Secretary of
War on November 9, 1939, and April 17, 1940, respectively. Rights
of entry have been furnished, free of cost to the United States, for
the construction of the project.
   Operations and results during fiscal year.-None. There were no
costs or expenditures.
   Conditionat end of fiscal year.-The existing project was practically
complete. The work remaining to be done consists of the construction
of a stop-log storage shelter.
   The costs and expenditures of the existing project have been $280,000
from Public Works Administration funds, and $674,307.55 from regu-
lar funds, a total of $954,307.55, all for new work.
   Proposed operations.-It is proposed to apply funds unexpended
on June 30, 1944, $5,692.45, as follows:
New work:
    Construction by hired labor of storage shelter for stop logs -          $1, 692. 45
    Balance-----                                                             4, 000. 00

       Total-_       ___-_-_------------__----5,692.45
                      FLOOD CONTROIr-L-PROVIDENCE,                                R. I., DISTRICT                                 139

  No additional funds can be profitably expended during the fiscal
year 1946, as the above operations will complete the local protection
work at Northampton, Mass.
                                           Cost and financial summary
Cost of new cr] to June 30, 1944_-----------_                                                                      1$954, 307. 55
Cost of rraintenance to June 30, 1944-  -   -.-.
            Total cost of permanent work to June 30, 1944                              -----------                   1.   954, 307. 55
Net total expenditures-      -                                                                   .      _           1954, 307 55
Unexpended balance June 30, 1944_ --------                                                           ----              5, 692. 45
            Total amount appropriated to June 30, 1944-------------                                                  1    960, 000. 00

    Fiscal year ending June 30                 1940             1941               1942                      1943             1944

Cost of new work .....
                    ___ ...                $585,865.98       $224, 061.02         $4,042.06           ..... .......-              .-.
Cost of maintenance ...................---------------....................---------------------------------------------------
Total expended _------....                  554, 234. 27      241, 518. 68        27, 589.37--               ----"-
Allotted.       ..        .      "   .-     200,000. 00      -96,000.   00------
                                                                              ..... -                              ...........
                                                                                                -------------........--------------



Balance unexpended July 1, 1943_-----                            _----___--$5,                                                692. 45
Balance unexpended June 30, 1944.---                                        ---                 -___                        5,692. 45
  1 Includes $280,000 Public Works funds.

43.     PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGEN-
                    CIES FOR FLOOD CONTROL

  The cost of work and expenditures during the year amounted to
$13,943.22. The total costs and expenditures have been $235,678.51.
The balance unexpended on June 30, 1944, amounting to $9,871.49,
plus an additional allotment of $40,000 made in July 1944, will be
applied during the fiscal year 1945 to payment of expenses incurred
under this heading.
  The sum of $40,000 can be profitably expended during the fiscal year
1946.
                                          Cost and financial summary
Cost of new work to June 30, 1944 ...                          .   . .
                                                    . . ._ .. .-.....      ..
Cost of maintenance to June 30, 1944-- ---------------------      $235, 678. 51
            Total cost of permanent work to June 30, 1944------------235,                                                     678. 51
Net total expenditures------------------------------------235, 678. 51
Unexpended balance June 30, 1944 -----------     ----------   9, 871. 49
            Total amount appropriated to June 30, 1944 --------------                                                   245, 550. 00

    Fiscal year ending June 30                1940              1941               1942                  1943                 1944

C ost of new w ork -- - - - - - - . .-       -- -
                                               -.--.-
                                              .-      -43-  -               ---68 ..
                                                                      .. ..--
Cost of maintenance---- -------- $157, 749.20  $21,385.72 $17, 643.90      $128.68   $13, 943. 22
rotal expepded    ----------------          158, 762. 35       20, 325.43         17, 676. 12                 143. 60         13, 943. 22

Allotted_ _---------____---90,                   700. 00    -10, 000. 00 --------------                 20,000. 00
140           REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,               1944

Balance unexpended July 1, 1943--------------------------- $23, 814. 71
Gross amount expended-------------------------------------13, 943. 22
     Balance unexpended June 30, 1944-----------------------                                                     9, 871. 49
Amount allotted in July 1944 .....------------------                                                            40, 000. 00

        SAmount available during fiscal year 1945-----------------                                              49, 871. 49
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1---------------------------------40,                                                     000. 00
  1Exclusive of available funds.

Status of all investigations for flood control called for by flood control acts and
                                committee resolutions

                                                                        Date trans-Recommen-
            Locality                      Authorization act              mitted to     Document No.                 Rnen-
                                                                         Congress                                  dation

Blackstone       River,     Mass.       Flood Control           Act,   May 26, 1944       H. 624, 78th Cong.,   Favorable.
  and R. I.                               June 22, 1936.                                   2d zess.
Connecticut and Chicopee                Flood        Control Act,_..........
  Rivers.                                 Aug. 28, 1937.
Connecticut River and trib-             Flood Control Com- _- ------.                     .........
utaries, including West-                 mittee resolution,
  field River.                            June 16, 1938.
Connecticut River and trib-             Flood Control Corn-_.........                          ........
utaries, for substitute                  mittee resolution,
  flood-control project in                May 28, 1941.
  place of Sugar Hill Dam
  and Reservoir on Anmmo-
  noosuc River, N. H.
Connecticut River, Mass.,               Flood        Control Act,                         ..........
  between        Hatfield     and         Aug. 11, 1939.
Mount Tom.
Green River, Mass ..         ...    _    _...   -do .........      .....       ... ....        ..
Seekonk River, R. I. (trib-             Flood Control           Act,   May 26, 1944       H. 624, 78th Cong.,      Do.
  utary of Pawtucket River).              June 22, 1936.                                    2d sess.



IMPROVEMENT OF RIVERS AND HARBORS IN THE NEW
             YORK, N. Y., DISTRICT
   This district comprises western Vermont, small portions of western
Massachusetts and Connecticut, eastern New York, including Long
Island, and northeastern New Jersey, embraced in the drainage basins
tributary to Lake Champlain and the St. Lawrence River system east
thereof and to the Atlantic Ocean from the New York-Connecticut
State line to the head of Barnegat Bay at Bayhead, N. J., exclusive of
the drainage basin of the Mohawk River above Crescent, N. Y.
    It exercises jurisdiction, however, over all matters pertaining to
navigation on the Great Lakes to Hudson River waterway; and, for
the purposes of study, investigation, and survey for the St. Lawrence
River seaway and power project, over the International Rapids section
of the St. Lawrence River, extending from Chimney Point to the foot
of Cornwall Island.
   District engineer: Col. A. B. Jones, Corps of Engineers, to August
3, 1943, Lt. Col. Joseph J. Shoemaker, Corps of Engineers, acting dis-
trict engineer to August 7, 1943, Col. A. B. Jones, Corps of Engineers,
to January 13,1944, and Col. E. W. Garbisch, Corps of Engineers, since
that date.
    Division engineer: Brig. Gen. B. C. Dunn, Corps of Engineers, to
January 8, 1944, and Col. A. H. Burton, Corps of Engineers, since that
date.
            RIVERS AND HARBORS---NEW                   YORK,   N.   Y., DISTRICT       141
                                            IMPROVEMENTS

                  Navigation                               Navigation-Continued
                                              Page
1.
2.
      Port Chester Harbor, N. Y_
      Mamaroneck Harbor, N. Y.
                                        --     141 24. Newark Bay, Hackensack
                                               143       and Passaic Rivers, N. J -
                                                                                       Page

                                                                                       194
3.   East Chester Creek, N. Y         --      144 25. New York and New Jersey
4.   Westchester Creek, N. Y --               146       Channels-                     197
5.   Bronx River, N. Y--------                147 26. Raritan River to Arthur Kill
6.   Harbor at Flushing Bay,                            Cut-off Channel, N. J  --
                                               149 27. Great Kills Harbor, Staten
                                                                                       202
        N. Y-----------------
7.   Glen Cove Creek, N. Y       -- -         151       Island, N. Y-_-         __    203
8.   Long Island          Intracoastal            28. Raritan River, N. J _...-..     206
        Waterway, N. Y                         152 29. Shrewsbury River, N. J___       210
9.   East Rockaway (Debs) Inlet,                  30. Manasquan River, N. J  ---
                                               154 31. Examinations, surveys, and
                                                                                       212
        N.Y-----------------
10.   Jamaica Bay, N. Y        -----           155                             ---
                                                         contingencies (general)       214
11.   New York Harbor: Entrance                    32. Preliminary investigations of
        Channels and Anchorage                           St. Lawrence River ...        215
        Areas----------------                  158 33. Other navigation projects for
12.   Bay Ridge and Red Hook                             which no estimates are sub-
        Channels, N. Y                         162       mitted--------------          219
13.   Buttermilk Channel, N. Y. _              165 34. Plant allotment-                220
14.   East River, N. Y_              -         167
                                                                  Flood control
15.   Newtown Creek, N. Y        ---           171
16.   Hudson River Channel, New                    35. Rutland, Otter Creek, Vt_ -     221
        York Harbor-__             -           174 36. North Adams, Hoosic River
17.   New York Harbor: Collec-                           Basin, Mass_----              223
        tion and removal of drift              177 37. Adams, Hoosic River Basin,
18.   Peekskill Harbor, N. Y                   179       Mass-                         224
19.   Rondout Harbor, N. Y                     180 38. Hoosick   Falls, Hoosic River
                                                         Basin, N. Y_                  226
20.   Hudson River, N. Y------                 182 39. Preliminary examinations,
21.   Great Lakes to Hudson River                        surveys, and contingencies
        Waterway----------                     188       for flood control--------     227
22.   Narrows of Lake Champlain,                   40. Other flood-control projects
        N. Y. & Vt_-----------                 190       for which no estimates are
23.   Burlington Harbor, Vt .....              192       submitted-       -----        228
                         1. PORT CHESTER HARBOR, N. Y.

  Location.-This harbor is located at the boundary between the
States of New York and Connecticut and comprises the tidal mouth,
about 1.7 miles in length, of the Byram River whose source is in
Byram Lake about 12 miles north of Port Chester. The river empties
into Long Island Sound about 32 miles by water east of the Battery,
New York City. (See U. S. Coast and Geodetic Survey Chart
No. 222.)
  Previous projects.-Adopted by River and Harbor Act of June
10, 1872, modified in 1884 and 1888, and by the River and Harbor
Acts of March 3, 1899, and March 2, 1907. For further details see
Annual Report for 1915, page 1758, and Annual Report for 1938,
page 157.
  Existing project.-This provides for an anchorage basin near the
breakwater, 12 feet deep, for fenders on the east bank opposite the
southern end of Fox Island, and for a channel 12 feet deep at mean
low water and 150 feet wide from Long Island Sound to the mouth
of the river at the southerly point of Fox Island; thence 10 feet
deep and 100 feet wide to 900 feet below the fixed bridge at Mill
Street in Port Chester, including a turning basin opposite the steam-
boat landing; and thence 3 feet deep and 175 to 100 feet wide to 100
feet below the fixed bridge. The length of the section included in
142           REPORT OF CHIEF OF ENGINEERS,                            U.    S. ARMY,         1944

the project is about 1.7 miles. Mean tidal range, 7.1 feet; mean
range of spring tides, 8.5 feet; irregular fluctuations due to wind
and barometric pressure vary from 4 feet below mean low water up
to 4.5 feet above mean high water.
   The estimate of cost for new work, revised in 1938, is $380,000,
exclusive of amounts expended on previous projects, of which $5,500
is to be contributed by local interests. The latest (1927) approved
estimate for annual cost of maintenance after completion is $3,000.
   The existing project was authorized by the following river and
harbor acts:
       Acts                       Work authorized                                      Documents


June 25, 1910     Entrance channel 12 feet deep, thence 10 feet deep   H. Doc. No. 1165, 60th Cong., 2d sess.
                   to and including turning basin, thence 3 feet
                   deep to head of improvement:
July     3,1930   Widening turning basin, dredging anchorage            Rivers and Harbors Committee Doc.
                    basin, and constructing fenders on east bank.           No. 23, 70th Cong., 2d sess.   (Con.
                                                                            tains latest published map.)


   Local cooperation.-The River and Harbor Act of July 3, 1930,
,provides that local interests shall contribute $5,500 in cash toward
widening the channel at the turning basin. This condition has not
been complied with.
   Terminal facilities.-There is a pier at Fox Island and 5,100 feet
of bulkheaded shore on Byram River between Fox Island and the Mill
Street Bridge, of which 1,900 feet are available for dockage. The
village of Port Chester owns several bulkheads which are used as
public landings for small pleasure craft. The facilities appear to be
adequate for existing commerce. (For latest full description of ter-
minal facilities see Port and Terminal Facilities at the Port of New
York, 1942, Corps of Engineers.)
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project, was about
94 percent completed. When examined in May 1941 the controlling
mean low water depth was 12 feet for a width varying from 150 to
60 feet from Long Island Sound to Fox Island; 10 feet in the anchor-
age basin; thence 10 feet for a width of 30 to 100 feet to the turning
basin; 10 feet in the turning basin; thence 3 feet for a width of 60
feet to within 400 feet of the head of the improvement; thence de-
creasing to 1 foot at the head of the improvement. The work remain-
ing to be done under the existing project consists of widening the
turning basin and constructing fenders on the bank opposite the
southern end of Fox Island.
    The total cost and expenditures of the existing project to June 30,
1944, were $440,080.10-$358,475.33 for new work and $81,604.77 for
maintenance.
    Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
    Completion of the existing project will not be necessary during
the fiscal year 1946. Maintenance dredging will be necessary during
the fiscal year 1946. The sum of $20,000 can be profitably expended
  during the fiscal year ending June 30, 1946, in maintenance dredging,
under contract, to restore the entrance channel to project dimensions.
             RIVERS      AND      HARBORS-NEW                   YORK,    N.    Y., DISTRICT            143
                                      Cost and financial summary
Cost of new work to June 30, 1944         -   -      --       $433,470.43
Cost of maintenance to June 30, 1944-------------------------   97, 973. 89

       Total cost of permanent work to June 30, 1944------------ 531,444. 32
Net total expenditures -----------------     ------------------ 531,444.32
Total amount appropriated to June 30, 1944--------- ---------    531, 444. 32

Amount (estimated) required to be appropriated for completion of
  existing project 1                                ---------------                   -         16, 000. 00

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance-- -------------------------------                                    20,000.00
1In addition, $5,500 is to be contributed by local interests.

                              2. MAMARONECK HARBOR, N. Y.

   Location.-On the north shore of Long Island Sound, 5 miles west
of the Connecticut State line, and 27 miles by water east of the Bat-
tery, New York City. (See U. S. Coast and Geodetic Survey Chart
No. 222.)
   Previous projects.-Adopted by River and Harbor Act of August
2, 1882, modified in 1899, and by River and Harbor Act of July 25,
1912. For further details see Annual Reports for 1915, 1924, and
1938, pages 1759, 141, and 160, respectively.
   Existing project.-This provides for a channel 10 feet deep at
mean low water and 100 feet wide from deep water in Long Island
Sound to Orienta Point, and thence 80 feet wide to a point about
150 feet below the Boston Post Road, including an extension to the
northeast, 300 feet long and 80 feet wide, all with widening at bends;
for an anchorage in the East Basin of same depth; and for an anchor-
age in the West Basin 6 feet deep at mean low water with a channel
of like depth and 80 feet wide connecting this anchorage with the main
channel. Length of section included in project, 1.8 miles. Mean tidal
range, 6.9 feet; mean range of spring tides, 8.3 feet; irregular fluctua-
tions due to wind and barometric pressure vary from 4 feet below mean
low water up to 4.5 feet above mean high water.
   The estimated cost for new work, revised in 1935, was $161,000, ex-
clusive of amounts expended on previous projects but including an
estimated local contribution of $26,500. The latest (1935) approved
estimate of annual cost of maintenance is $1,500.
   The existing project was authorized by the following river and
harbor acts:
    Acts                         Work authorized                                    Documents


Sept. 22, 1922   Dredging 10-foot channel and anchorage -.... .._-.     H. Doc. No. 651, 66th Cong., 2d sess.
Aug. 30,1935     Dredging 6-foot anchorage in West Basin and its        Rivers and Harbors Committee Doe.
                  approach channel.                                       No. 4, 74th Cong., 1st sess. (Con-
                                                                         tains latest published map.)


  Local cooperation.-Fullycomplied with except that local interests
are required to provide adequate and suitable spoil-disposal areas
suitably diked or bulkheaded as needed.
  Terminal facilities.-There are 785 feet of bulkheads and wharves
available for dockage, a private boat landing, and a boat yard located
on the East Basin. Two small-boat repair yards, with about 650
144            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

feet of dockage for small boats and two boat landings open to the
public are situated on the west branch of the harbor. Four of the
terminals have mechanical handling devices and one is publicly
owned. The facilities are adequate for present requirements of
commerce. (For latest full description see Port and Terminal Facil-
ities at the Port of New York, 1942, Corps of Engineers.)
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in July 1939. When examined in May 1940, the controlling mean
low-water depth in the main channel was 10 feet for a width varying
from 100 to 30 feet from Long Island Sound to the East Basin anchor-
age area, where the depth was 9 feet. The controlling depth in the
West Basin and connecting channel, when examined in March-July
1939, was 6 feet below mean low water.
   The total cost and expenditures of the existing project to June 30,
1944, were $184,737.43-$145,407.89 for new work, of which $126,
679.83 were United States funds and $18,728.06 contributed funds,
and $39,329.54 for maintenance.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $20,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore the main channel and East Basin anchorage to project
dimensions.
                                           Cost and financial summary
Cost of new work to June 30, 1944-______-_______-     _   _ _-$207, 404. 26
Cost of maintenance to June 30, 1944_-------------------------52, 744. 40
       Total cost of permanent work to June 30, 1944-----------                                                  260, 148. 66
Net total expenditures_____----___________         -1260, _                                                           148. 66
Total amount appropriated to June 30, 1944 -----------                                        --------           260, 148. 66


    Fiscal year ending June 30                1940              1941                1942                1943            1944

                ---------- ------
Cost of new work_                            $1,064.90 ..-                           _----_                     ::--:----------------------
Cost ofmaintenance        . .                                      $417. 73
                                                    ..--------------...
                                              ..------------
                                                 ....
T ota l ex p end ed _______....   ......      2,8 70. 51          417. 73-0-                  --

Allotted- ....................                7, 728. 05      -9, 582. 27      ..    ....          ..            ..



Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance_ ------        -----------------                                                      $20, 000.00
  1 Exclusive of $18,728.06 contributed funds expended for new work.

                                    3. EAST CHESTER CREEK, N. Y.

   Location.-This creek, also known as Hutchinson River, is a small
tidal stream emptying into East Chester Bay, an indentation in the
north shore of Long Island Sound immediately north of Throgs Neck,
12 miles southwest of the Connecticut State line and 21 miles by water
northeast of the Battery, New York City. (See U. S. Coast and Geo-
detic Survey Chart No. 223.)
   Previous projects.-Adopted by the River and Harbor Acts of
March 3, 1873, and June 25, 1910. For further details see Annual
          RIVERS      AND HARBORS-NEW                    YORK,        N.   Y.,   DISTRICT       145
Report for 1915, page 1761, Annual Report for 1929, page 167, and
Annual Report for 1938, page 163.
   Existing project.-This provides for a channel 8 feet deep at mean
low water and generally 150 feet wide from Long Island Sound
through East Chester Bay to a point 700 feet below the Boston Post
Road Bridge, and thence 70 feet wide to the northern terminus of the
project, about 300 feet above the Fulton Avenue Bridge, and for a
passing basin in the vicinity of the Boston Post Road Bridge. Length
of section included in project, 4.7 miles. Mean tidal range, 7.3 feet in
the estuary; mean range of spring tides, 8.6 feet; irregular fluctuations
due to wind and barometric pressure vary from 4 feet below mean low
water up to 4.5 feet above mean high water.
   The estimate of cost for new work, made in 1930, was $283,000, exclu-
sive of amounts expended on previous projects. The latest (1930)
approved estimate for annual cost of maintenance is $15,000 for the
first 3 years and $12,000 annually thereafter.
   The existing project was adopted by the River and Harbor Act of
July 3, 1930 (Rivers and Harbors Committee Doc. No. 37, 71st Cong.,
2d sess.). The latest published map is in the project document.
   Local cooperation.-Fully complied with.
   Terminal facilities.-There is one pier with a berthage of 200 feet
and 7,179 feet of bulkheads available for dockage located along the
upper end of the waterway. Eleven of the terminals are equipped
with mechanical handling devices. The terminals are adequate to
meet the present requirements of commerce. (For latest full descrip-
tion of terminal facilities see Port and Terminal Facilities at the Port
of New York, 1942, Corps of Engineers.)
   Operations and results duling fiscal year.-None.
   Conditionat end of fiscal year.-The existing project was completed
in August 1941. When examined in June and July 1936, April to
August 1939, and November 1940 to August 1941, the controlling depth
at mean low water was 8 feet for a width of 150 feet from East Chester
Bay to 700 feet below the Boston Post Road Bridge, thence 8 feet deep
and 70 feet wide to 300 feet above the Fulton Avenue Bridge. The
minimum width through bridge draws is 59.6 feet.
   The total cost and expenditures of the existing project to June 30,
1944, exclusive of $14,402.80 contributed funds, were $392,436.86-
$183,507.10 from Emergency Relief funds and $208,929.76 from regu-
lar funds, all for new work.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging in the upper reach of the channel will be
necessary during the fiscal year 1946. The sum of $30,000 can be
profitably expended during the fiscal year ending June 30, 1946, in
maintenance dredging, under contract, to restore the channel extend-
ing from about 2,000 feet below the Boston Post Road Bridge to the
head of the project to authorized dimensions.
                           Cost and financial summary
Cost of new work to June 30, 1944 ____.        __  _                            _    1 $592, 056.    65
Cost of maintenance to June 30, 1944                                       _165,              023.   65
       Total cost of permanent work to June 30, 1944-
Net total expenditures _  -1
                                                                                 -       757, 080.
                                                                                         757, 080.
                                                                                                     30
                                                                                                     30
Total amount appropriated to June 30, 1944 -      - -                            -     1 757, 080.   30
1 Exclusive of $14,402.80 contributed funds expended for new work.
       616634     45--pt. 1, vol. 1      10
146           REPORT OF CHIEF OF ENGINEERS,                                   U.       S. ARMY,                1944


    Fiscal year ending June 30                   1940            1941           1942                    1943               1944

Cost of new work ...   .         -             $20, 695.17    $174, 537. 63   $14, 204. 06   ........                    .......
Cost of maintenance _-                                                -            -                -    -

Total expended ----------------
                 .  ...                         20, 144. 51    158, 310. 25    30, 882. 10                     $100   ---- _...--    .
Allotted .-----......      -- --............   195, 000.00      12,000.GO     10,000.00                  -4,000         -$4,070.24



Balance unexpended July 1, 1943                                                                                       $4, 070. 24
Deductions on account of revocation of allotment                                                                       4, 070. 24
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance ----      -        -     -     -$30,                                                           000. 00

                                     4. WESTCHESTER CREEK, N. Y.

   Location.-This creek is a tidal stream flowing into the East River
from the north at a point 14 miles by water northeast of the Battery,
New York City. (See U. S. Coast and Geodetic Survey Chart No.
226.)
   Previous projects.-Adopted by the River and Harbor Act of June
25, 1910. For further details see page 238 of Annual Report for 1921,
and page 164 of Annual Report for 1938.
   Existing project.-This provides for a channel 12 feet deep at mean
low water, 100 feet wide for a length of 2,000 feet through the estuary;
thence 80 feet wide for 3,000 feet; and thence 60 feet wide to the head
of navigation at East Tremont Avenue (Fort Schuyler Road), a dis-
tance of 8,800 feet, with widening at bends, and with two turning
basins, one near the upper end of the channel and another near the
Eastern Boulevard (Unionport) Bridge, a total length of about 2.6
miles. Mean tidal range, 7 feet; mean range of spring tides, 8.4 feet;
irregular fluctuations due to wind and barometric pressure vary from
4 feet below mean low water up to 3.5 feet above mean high water.
   The estimate of cost for new work, revised in 1932, was $117,000,
exclusive of amounts expended on previous projects. The latest (1928)
approved estimate for annual cost of maintenance is $5,000.
   The existing project was adopted by the River and Harbor Act
approved September 22, 1922 (Rivers and Harbors Committee Doc.
No. 8, 67th Cong., 2d sess.). The latest published map is printed in
House Document No. 370, Sixty-fourth Congress, first session.
   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 2,865 feet of bulkheads and wharves
available for dockage. One of the terminals is publicly owned. Eight
of the terminals are equipped with mechanical handling devices. The
facilities appear to be adequate. (For latest full description of ter-
minal facilities see Port and Terminal Facilities at the Port of New
York, 1942, Corps of Engineers.)
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1933. When examined in March to May 1941, the controlling mean
low-water depth of the channel was 10 feet for a width varying from
100 to 30 feet from the entrance in East River to the head of the project
at East Tremont Avenue.
   The total cost and expenditures of the existing project to June 30,
1944, were $158,699.09--$98,666.88 for new work and $60,032.21 for
maintenance.
         RIVERS AND HARBORS-NEW              YORK,   N.   Y., DISTRICT       147
  Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
  Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $60,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore the channel to project dimensions.
                           Cost and financial summary
                                 -----------------------------
Cost of new work to June 30, 1944__                                 $175, 848. 52
Cost of maintenance to June 30, 1944     -----------------            126, 632. 35
      Total cost of permanent work to June 30, 1944_                 302, 480. 87
Net total expenditures-    -------          -----------              302, 480.87
Total amount appropriated to June 30, 1944   --                      302, 480. 87
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_ ----------------------------              60, 000. 00

                            5. BRONX RIVER, N. Y.

   Location.-This stream empties into a shallow bay in the north
shore of East River, 11 miles by water northeast of the Battery, New
York City. (See U. S. Coast and Geodetic Survey Chart No. 226.)
   Previous project.-Adopted by the River and Harbor Act of June
3, 1896. For further details see Annual Report for 1915, page 1762,
and Annual Report for 1938, page 166.
   Existing project.-This provides for a channel 10 feet deep at mean
low water and 100 feet wide, to ektend from deep water in East River
to the head of navigation at the dam at East One Hundred and Seventy-
seventh Street, involving the first dredging from East River at Randall
Avenue to a width of 200 feet; thence to Spofford Avenue, 150 feet;
thence to Watson Avenue, 125 feet; thence to the railroad bridge near
Westchester Avenue, 100 feet except in the southern approach to the
bridge, where it is to be 140 feet; and above the bridge 100 feet, with
increase at bends where permissible, including a turning basin at the
head of the improvement. The length of the section included in the
project is about 3.3 miles. Mean tidal range, 6.9 feet in the estuary;
mean range of spring tides, 8.2 feet; irregular fluctuations due to wind
and barometric pressure vary from 4 feet below mean low water up to
3.5 feet above mean high water.
   The estimate of cost for new work, revised in 1942, is $2,237,000,
exclusive of amounts expended under previous projects. The latest
 (1928) approved estimate for annual cost of maintenance is $7,500.
   The existing project was adopted by the River and Harbor Act of
March 4, 1913 (H. Doc. No. 897, 62d Cong., 2d sess.). For latest pub-
lished map see Annual Report for 1912, page 1470.
   Local cooperation.-The River and Harbor Act of March 4, 1913,
provides that any right-of-way that may be necessary for the execu-
tion of the project shall be furnished free of cost to the United States.
Right-of-way within the bulkhead lines below the Westchester Ave-
nue Bridge was accepted by the Chief of Engineers under date of
June 9, 1920, and above the Westchester Avenue Bridge under date
of October 4, 1928. Under date of September 10,' 1940, the Chief of
Engineers approved releases from damages furnished by adjoining
property owners in, the reach of the river between Westchester Avenue
148     REPORT OF CHIEF OF ENGINEERS, U.        S. ARMY,   1944

and East One Hundred and Seventy-fourth Street. Under date of
November' 12, 1940, the Chief of Engineers approved an agreement
under which the city of New York would reimburse the United States
for the cost of a retaining wall to protect adjoining property in the
reach of the river between Westchester Avenue and New York, New
Haven & Hartford Railroad bridge in lieu of furnishing additional
right-of-way. On October 28, 1940, the Secretary of War authorized
the acceptance of $10,000 from the city of New York to defray the
cost of the retaining wall. The $10,000 was deposited to the credit
of the United States on December 7, 1940. Additional right-of-way
required in the section above East One Hundred and Seventy-fourth
Street has not been furnished. The city of New York has indicated
that it does not feel justified in acquiring any additional land along
the river.
    Terminal facilities.-There are 3,430 feet of bulkheads and wharves
available for dockage, located along the east and west banks from
Randall Avenue to East One Hundred and Seventy-third Street. One
of  the terminals is publicly owned. Eight of the terminals are
equipped   with mechanical handling devices. Additional terminals
with modern facilities will be needed when the existing project is de-
veloped. (For latest full description of terminal facilities, see Port
and Terminal Facilities at the Port of New York, 1942, Corps of
Engineers.)
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was about
49 percent completed. A channel to project dimensions was com-
pleted from deep water in East River up to the Westchester Avenue
Bridge in 1926. A channel 10 feet deep and 65 to 123 feet wide from
Westchester Avenue Bridge to East One Hundred and Seventy-fourth
Street was completed in 1941. When examined in June and August
1943 the controlling mean low water depth was 7 feet for a width vary-
ing from 100 to 40 feet from East River to a point 1,200 feet above
Eastern Boulevard Bridge; thence 5 feet for a width varying from 80
to 45 feet to Westchester Avenue Bridge; thence 8 feet for a width
varying from 123 to 60 feet to East One Hundred and Seventy-fourth
Street. As shown by an examination made in May 1934, the depth
in the section above East One Hundred and Seventy-fourth Street
varied from 1 foot below mean low water to an extreme height of 4.5
feet above mean low water just below the dam at the head of the
improvement. The work remaining to be done under the existing
project consists of completing the channel above the Westchester Ave-
nue Bridge to project dimensions.
   The total cost and expenditures of the existing project to June 30,
1944, exclusive of $10,000 contributed funds for new work, were
$1,264,956.99-$1,080,910.37 for new work and $184,046.62 for main-
tenance.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $60,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore the channel from East River to the Westchester Avenue Bridge
to project dimensions.
              RIVERS AND                       HARBORS-NEW                          YORK,      N.     Y.,       DISTRICT                     149
                                                  Cost and financial summary
Cost of new work to June 30, 1944_             -1                                                                       $1, 149, 946. 09
Cost of maintenance to June 30, 1944-----------------------                                                                 210, 967. 95
       Total cost of permanent work to June 30, 1944
Net total expenditures ---------------------------------
                                                                                               -                -         1, 360, 914. 04
                                                                                                                          1, 360, 914. 04
Total amount appropriated to June 30, 1944------------ -                                                                1 1, 360, 914. 04

   Fiscal year ending June 30                            1940                1941           1942                 1943                   1944

Cost of new work ---------------                    $16, 730. 35         $169, 296. 07    $97, 080. 30---------------
Cost of maintenance --------                        .                                       2, 814. 47-
                                                                      .--------------..--------------.
      Total cost- --------.----                         16, 730. 35        169, 296. 07    99, 894. 77
Total expended- ..          -             . -..         16, 380. 96        104, 869. 65   164, 670. 58      .       .    .        .      .     .
Allotted-   --------------------------------                              610, 000.00      11,000.00            -            -        -$65, 07& 81


Balance unexpended July 1, 1943             -----------                                                                          $65, 078. 81
Deductions on account of revocation of allotment--------------                                                                    65, 078. 81
Amount (estimated) required to be appropriated for comple-
tion of existing project - -_    _______1,                                                                                      148, 000. 00
Amount that can be profitably expended in fiscal year ending
                               ---------------------------
June 30, 1946, for maintenance_                                                                                                  60, 000. 00
  1Exclusive of $10,000         contributed funds expended for new work.

                                  6. HARBOR AT FLUSHING BAY, N. Y.

   Location.-On the north shore of Long Island, 12 miles by water
northeast of the Battery, New York City, and consists of Flushing
Bay, 2.0 miles long and Flushing Creek, 1.0 mile long. (See U. S.
Coast and Geodetic Survey Chart No. 226.)
   Previous projects.-Adopted by River and Harbors Acts of March
3, 1879, and March 4, 1913. For further details see Annual Reports
for 1915, 1932, and 1938, pages 1772, 169, and 168, respectively.
   Existing project.-This provides for a channel 12 feet deep at mean
low water from that depth in East River through Flushing Bay and
in Flushing Creek to the Main Street Bridge, with widths of 200 feet
through the bay and in the creek to the Northern Boulevard Bridge,
thence decreasing uniformly to 160 feet at the Main Street Bridge;
a branch channel 12 feet deep and 200 feet wide from the main channel
to a maneuvering area of the same depth outside the municipal boat
basin at the south end of the bay, with an anchorage basin of 8-foot
depth and approximately 700-foot width west of the branch channel;
and for the repair and reconstruction of 3,739 linear feet of dike.
   The length of the section included in the project is about 3.7 miles.
Mean tidal range, 6.8 feet; mean range of spring tides, 8.1 feet; ir-
regular fluctuations due to wind and barometric pressure vary from
4 feet below mean low water up to 3.5 feet above mean high water.
   The estimate of cost for new work, revised in 1942, is $662,000, ex-
clusive of amounts expended on previous projects. The latest (1937)
approved estimate for annual cost of maintenance is $20,000.
150         REPORT OF CHIEF OF ENGINEERS,                            U.     S. ARMY,          1944

  The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                        Documents


Mar. 4,1913     Construction of new dike; repair of old dike  --IH. Doc. No. 1333,      61st Cong., 3d sess.
Mar. 3, 1925    Dredging 12-foot channel _ _.. _... ..... _H.  ..        Doc. No. 124, 68th Cong., 1st sess.
Aug. 26, 1937   Branch channel, maneuvering area, and anchor-         Rivers and Harbors Committee Doc.
                 age basin. Modified conditions of local cooper-        No. 35, 75th Cong., 1st sess.'
                 ation.
June 20, 1938   Providing 6-foot channel along west side of harbor    Senate committee print, 75th Cong.
                                                                                     2
                    during period of the world's fair.1                   3d sess.


  1 No   work was done.
 ?2Contain latest  published maps.

   Local cooperation.-The River and Harbor Act of August 26, 1937,
provides that the branch channel and anchorage shall not be con-
structed until local interests give assurances satisfactory to the Sec-
retary of War that they will construct a suitable landing for excursion
boats and a boat basin of appropriate capacity; provide and maintain
a public landing of permanent construction for small boats, with
necessary service and supply facilities; provide adequate parking
spaces for automobiles in the immediate vicinity suitably connected
to the public-highway system and open to the public on equal terms,
and that no dredging shall be done in the Flushing Creek Channel
closer than 100 feet to the established harbor line at any wharf struc-
ture without previous consent of the owner and release of the United
States from any resultant claims for damages. Assurances providing
compliance with the local cooperation required for all improvements
authorized under this act, except for dredging in the creek channel,
were accepted by the Secretary of War on October 18, 1937.
   Terminal facilities.-There are 5,995 feet of bulkheads available
for dockage. Two of the terminals and an excursion-boat landing
and boat basin at the south end of the bay are owned by the city of
New York, the latter being open to the public. Twelve of the terminals
are equipped with mechanical handling devices. The facilities are
considered adequate for existing commerce. (For latest full descrip-
tion of terminal facilities see Port and Terminal Facilities at the Port
of New York, 1942, Corps of Engineers.)
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was about 59
percent completed. The 12-foot channel in the bay, branch channel,
and maneuvering area and the 8-foot anchorage area were completed
in November 1938. When examined in October 1938, April 1940, and
April 1942 the controlling mean low-water depth was 11 feet for a
width varying from 150 to 200 feet in the main channel through the bay
to the mouth of Flushing Creek, and thence 70 to 130 feet wide to the
Broadway Bridge; thence 8 feet for a width of 60 feet to the Roosevelt
Avenue Bridge; thence 5 feet for a width varying from 50 to 160 feet
to the Main Street Bridge. When examined in April 1942 the depth
in the branch channel and maneuvering area was 11 feet and in the
anchorage area the depth was 7 feet. The work remaining to be done
under the existing project consists of the construction of the channel
        RIVERS AND HARBORS-NEW             YORK,   N.   Y., DISTRICT        151
in the creek to a depth of 12 feet and the repair and reconstruction
of dike.
  The total cost and expenditures of the existing project to June 30,
1944, were $389,629.46, all for new work.
  Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
  It is expected that the remaining conditions of local cooperation
affecting the 12-foot channel will not be met during the next 2 years.
The reconstruction of dikes is hot considered necessary at this time.
Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $40,000 can be profitably expended during the fiscal year
ending June 30, 1946. in maintenance dredging, under contract, to
restore the channel from East River to the mouth of the creek to
project dimensions.
                          Cost and financial summary
Cost of new work to June 30, 1944 -------------------------         $628, 502. 37
Cost of maintenance to June 30, 1944 ------------------------        206, 411. 47
       Total cost of permanent work to June 30, 1944------------     834, 913. 84
Net total expenditures---
                       __      -------------                         834, 913. 84
Total amount appropriated to June 30, 1944-------------------        834, 913. 84
Amount (estimated) required to be appropriated for completion of
existing project_-------------                        -----         272, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance ---------------------------------          40, 000. 00

                        7. GLEN COVE CREEK, N. Y.

   Location.-This is a narrow tidal inlet extending eastwardly about
1 mile from the east side of Hempstead Harbor on the north shore
of Long Island, 26 miles northeast of the Battery, New York City.
(See U. S..Coast and Geodetic Survey Chart No. 223.)
   Existing project.-This provides for a channel 100 feet wide and 8
feet deep at mean low water from deep water in Hempstead Harbor
to the head of navigation at the city of Glen Cove, a total length of
about 1 mile, to be protected by a sand fence along its north side where
it crosses the beach. Mean tidal range, 7.4 feet; mean range of spring
tides, 8.7 feet; irregular fluctuations due to wind and barometric
pressure vary from 4 feet below mean low water up to 4.5 feet above
mean high water.
   The estimate of cost for new work (of which one-half is to be borne
by local interests), revised in 1934, is $109,000, with $6,000 the first year
and $4,000 annually thereafter for maintenance.
   The existing project was adopted by the River and Harbor Act of
March 3, 1925 (H. Doc. No. 207, 68th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-The River and Harbor Act of March 3, 1925,
provides that local interests shall pay one-half of the first cost of the
work, provide without cost to the United States all rights-of-way,
spoil-disposal areas, and bulkheads, anl give assurances satisfactory
to the Secretary of War that adequate terminals will be built. Com-
plied with as to contribution of one-half of first cost of work done
to date, cession of rights-of-way, provision of disposal areas, and the
construction of terminals. Pending construction of bulkheads by
152          REPORT OF CHIEF OF ENGINEERS,                         U.   S.   ARMY,   1944

local interests along the southerly side of the channel in the upper
1,600 feet of the improvement, a channel of less than project width
has been excavated.
   Terminal facilities.-There are 1,875 feet of bulkheads located along
the northerly side of the waterway. The terminals are adequate for
present needs and there is ample water front, both public and private,
for, additional terminals as needs arise.
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was about 55
percent completed. The work done provided a channel 100 feet in
width from deep water in Hempstead Harbor for a distance of 3,470
feet, thence gradually decreasing to 50 feet in width for a distance
of 180 feet, and 50 feet in width for a distance of about 1,450 feet
to the head of the improvement. When examined in March 1942 the
controlling mean low water depth was 8 feet for a width varying
from 100 to 55 feet from the mouth to within 1,600 feet of the head of
the improvement; thence 7 feet for a width of 35 feet for a distance
of 900 feet; thence 6 feet for a width of 35 feet to the head of the
project. The work remaining to be done to complete the existing
project consists in widening to 100 feet the upper 1,630 feet of chan-
nel and building a sand fence along the north side of channel where
it crosses the beach.
   The total cost and expenditures of the existing project to June 30,
1944, were $59,534.17, all for new work, of which $29,760.06 were United
States funds and $29,774.11 contributed funds.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Completion of the existing project is not considered necessary during
the fiscal year 1946. Shoaling is occurring near the entrance and in
the upper section of the improvement. The sum of $25,000 can be
profitably expended during the fiscal year ending June 30, 1946, in
maintenance dredging, under contract, to restore the channel to dimen-
sions previously obtained.
                                       Cost and financial summary
Cost of new work to June 30, 1944                                 ___                1 $29, 760. 06
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944------------      29, 760. 06
Net total expenditures_--- ------------                          _1   29, 760. 06
Total amount appropriated to June 30, 1944------------ -------      1 29, 760. 06
Amount (estimated)   required to be appropriated for completion of
existing project 2- - - - - - - - - - - - - - -         - - - -
                                                                                        25, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance ----------------------------------                            25, 000.00
1 Exclusive of $29,774.11 contributed funds expended for new work.
2 In   addition, $25,000 to be contributed by local interests.

                8. LONG ISLAND INTRACOASTAL WATERWAY, N. Y.

  Location.-This waterway *extends from East Rockaway Inlet, on
the south side of Long Island, to Great Peconic Bay at the eastern
end of Long Island. The section included under this project ex-
tends from Great South Bay opposite Patchogue to the south end
of Shinnecock Canal. (See U. S. Coast and Geodetic Survey Chart
No. 578.)
                 RIVERS              AND HARBORS                     NEW YORK, N.            Y., DISTRICT                            153
  Existing project.-This provides for a channel 100 feet wide and
6 feet deep at mean low water from the federally improved channel
in Great South Bay opposite Patchogue to the south end of Shinne-
cock Canal. The length of the section included in the project is 34
miles. The mean tidal range varies from 0.3 foot in Shinnecock Bay
to 0.7 foot in Moriches Bay, the rise and fall depending largely upon
meteorological conditions. Irregular fluctuations due to wind or
other causes are seldom of sufficient extent to affect navigation.
  The estimated cost for new work, made in 1937, is $286,000. The
approved estimate for annual cost of maintenance made in 1937 is
$15,000.
  The existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. No. 181, 75th Cong., 1st sess.). The latest
published map is in the project document.
  Local cooperation.-Fully complied with except that local inter-
ests are required to furnish suitable spoil disposal areas for subse-
quent maintenance as required.
   Terminal facilities.-There are 17 boat repair and storage yards
within the area immediately adjacent to the Federal improvement.
There is ample room for expansion and development of terminals
when future commerce warrants.
  Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was completed
in 1940. When examined in July 1936, July 1943, and May 1944, the
controlling mean low-water depth in the channel was 6 feet for a
width varying from 50 feet to 100 feet, except opposite Moriches Inlet
where shoals of least depth of 3.5 feet exist.
  The total cost and expenditure of the existing project to June 30,
1944, were $276,787.64-$235,964.25 for new work and $40,823.39 for
maintenance.
  Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
  Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $30,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore project dimensions in the portions of the channel subject to
rapid shoaling.
                                                     Cost and financial summary
Cost of new work to June 30, 1944_                            $235, 964. 25
Cost of maintenance to June 30, 1944-------------------------   40, 823. 39
       Total cost of permanent work to June 30, 1944------------ 276, 787. 64
Net total expenditures ---------------------------------------   276, 787. 64
Total amount appropliated to June 30, 1944--------------------276, 787. 64

    Fiscal year ending June 30                          1940           1941          1942                   1943                1944

Cost of new work .-------------- $173, 568. 59                       $60, 661.24    $1, 734.42 .              .
                                                                                                             -..   .        .    .     .
Cost of maintenance _...-------------------------------1,                               526. 01       $39, 297. 38
       Total cost----------------.................    173, 568. 59    60, 661.24     3, 260. 43        39, 297.38
Total expended....----------------                    155, 982. 06    78,147. 77     3, 221.15         39, 436. 66      -
Allotted ......---------------------                 -42, 000. 00     30, 000. 00   2, 787. 64    ..-----          -   ..-...


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance -------------------------------                                                             $30, 000. 00
154    REPORT OF CHIEF OF ENGINEERS,        U.   S.   ARMY,   1944

              9. EAST ROCKAWAY (DEBS)      INLET, N. Y.

   Location.-The inlet is situated on the south shore of Long Island
between the main body of the island and the western end of Long
Beach. It is 10 miles east of Rockaway Inlet and about 27 miles by
water south and east from the Battery, New York City. (See U. S.
Coast and Geodetic Survey Charts Nos. 579 and 1215.)
   Existing project.-This provides for a channel 12 feet deep at mean
low water and 250 feet wide from the 12-foot contour in the Atlantic
Ocean to the 12-foot contour in Long Beach Channel, a distance of
about 0.6 mile, protected by jetties. Mean tidal range, 4.1 feet; mean
range of spring tides, 4.9 feet; irregular fluctuations due to wind and
barometric pressure vary from about 31/ feet below mean low water
up to about 31/ feet above mean high water.
   The estimate of cost for new work -made in 1929 is $710,000 (in-
cluding $100,000, local contribution). The latest (1929) approved
estimate for annual cost of maintenance is $20,000.
   The existing project was adopted by the River and Harbor Act of
July 3, 1930 (H. Doc. No. 19, 71st Cong., 1st sess.). The latest pub-
lished map is in the project document.
   Local cooperation.-Tle River and Harbor Act of July 3, 1930,
provides that local interests shall contribute $100,000 to the cost of
the work; give assurances satisfactory to the Secretary of War and
the Chief of Engineers that they will provide and maintain at their
own expense interior channels suitable for navigation, not less than 12
feet deep; from East Rockaway Inlet to the Hempstead-Oyster Bay
line, a distance of about 15 miles, to Hewlett Harbor and to Freeport
Harbor; furnish, without expense to the United States, necessary
land, easements, and rights-of-way for construction and maintenance
of the jetties, and agree to hold and save the United States free of
claims for damages to public and private property resulting from the
improvement.
   Assurances of compliance with the conditions of local cooperation
precedent to construction of entrance channel and east jetty were
approved by the Chief of Engineers and Secretary of War on July
14 and 15, 1932, respectively. Local contribution of $100,000 was de-
posited to the credit of the United States on August 23, 1932. Since
the construction of the west jetty is not considered necessary at this
time, easements, rights-of-way and release of claims for damages
necessary for construction are not being secured.
   Terminal facilities.-No terminals are within the area immediately
adjacent to the Federal improvement. The water front on the north
side of Long Beach has been bulkheaded. There are five water termi-
nals at Oceanside with an available wharfage of 2,000 feet. Three
are oil terminals, of which one has a spur railroad connection; the
other two are unused at present. There are two terminals at Island
Park having a wharfage of 400 feet. There are public wharves at
East Rockaway and Woodmere. The facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was about 85
percent completed. The east jetty, 4,250 feet long, was completed in
1934. The project channel was completed in 1935. When examined
in May 1944 the controlling mean low-water depth through the best
              RIVERS AND               HARBORS-NEW                    YORK, N.             Y., DISTRICT                     155

available channel was 12 feet for a width varying from 100 to 250
feet. The work remaining to be done under the existing project
consists of building a west jetty, if necessary, to protect the channel.
   The total cost and expenditures of the existing project to June 30,
1944, were $595,388.61-$421,368.68 from regular funds and $82,600
from Public Works funds, a total of $503,968.68 for new work, and
$91,419.93 from regular funds for maintenance. In addition, the
costs and expenditures from contributed funds were $100,000 for new
work.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Neither completion of the project nor maintenance dredging will
be necessary during the next 2 years. Repairs to the jetty will be
necessary. The sum of $75,000 can be profitably expended during the
fiscal year ending June 30, 1946, in repairs, under contract, to restore
the jetty to a satisfactory condition.
                                       Cost and financial summary
Cost of new work to June 30, 1944 -------------------------                                                1 $503, 968. 68
Cost of maintenance to June 30, 1944_-----         --   __                                                         91, 419. 93
       Total cost of permanent work to June 30, 1944--------                                                  595, 388. 61
Net total expenditures_-----------_           -1                                                              595, 388. 61
Total amount appropriated to June 30, 1944                                                                  1 595,388. 61

    Fiscal year ending June 30                1940           1941               1942                1943               1944

Cost of new work---------------.---------.
                             .---..                         . . . . . . . . .                      . .     .. ..--------------
Cost of maintenance ---  -  ---------------                 $17, 676. 80 $8, 009.07               -$38. 73 ........

Total expended ____-      ....-..--.      $1,084. 85        17, 654. 37         7,902. 41              90. 36           -


Allotted__----...       -
                       ....- ....-.-      21, 482. 60        15, 000. 00       25, 000. 00   -17,     000. 00       -$26, 647. 87


Balance unexpended July 1, 1943                         -         -        -           -      -            -$26,       647. 87
Deductions on account of revocation of allotment                                                                   26, 647. 87
Amount (estimated) required to be appropriated for completion of
existing project_ __--_106,                                                                                           000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance ---------------------------------                                                       75, 000. 00
  1 Exclusive of $100,000 contributed funds expended for new work.

                                        10.     JAMAICA BAY, N. Y.

  Location.-Inside the south shore of Long Island, the entrance be-
ing about 17 miles by water south and east of the Battery, New York
City. (See U. S. Coast and Geodetic Survey Chart No. 542.)
  Previous projects.-Adopted by River and Harbor acts of June 14,
1880, and July 13, 1892. For further details see page 1770 of Annual
Report for 1915, and page 185 of Annual Report for 1938.
  Existing project.-This provides for an entrance channel 30 feet
deep at mean low water and 1,500 feet wide, with widening at bends;
a main channel extending from the entrance channel up to the mouth
of Cornells Creek, to be 30 feet deep at mean low water and 1,000
feet wide, with widening at bends; and for the protection of the
entrance channel by one or two riprap jetties, as may be necessary.
Length of section included in the project, 14.8 miles; mean tidal
range, 4.9 feet at Barren Island to 5.1 feet at Canarsie and Hammels;
156        REPORT OF CHIEF OF ENGINEERS,                                      U.    S. ARMY,        1944

mean range of spring tides, 5.9 and 6.1 feet, respectively; irregular
fluctuations due to wind and barometric pressure vary from 4 feet
below mean low water up to 3.5 feet above mean high water.
   Estimated cost to the United States for new work, made in 1919, is
$11,806,000, exclusive of amounts expended on previous projects. The
approved estimate of annual cost of maintenance made in 1919 is
$160,000 in entrance channel and $100,000 in main channel, a total of
$260,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                            Documents

June 25, 1910   Dredging 30-foot channel and construction of 1 or              H. Doc. No. 1488, 60th Cong., 2d sess.
                 2 riprap jetties as may be necessary.                             (Contains latest published map.)
Sept. 22,1922   Modified conditions of local cooperation---------..........    Specified in act.



   Recommended modifications of project.-Under date of April 11,
1940, the Chief of Engineers recommended that in lieu of the existing
project there be provided: (a) An interior channel extending from
the vicinity of the Marine Parkway Bridge along the west and north
shores of the bay, 18 feet deep and 300 feet wide to Mill Basin, with
a swinging basin 1,000 feet wide and 1,000 feet long at that point,
thence 12 feet deep and 200 feet wide to Fresh Creek Basin; (b) an
interior channel extending from the same locality along the south
shore to head of bay, 15 feet deep and 200 feet wide; and- (c) an en-
trance channel connecting the two interior channels with deep water
in the Atlantic Ocean, of suitable hydraulic dimensions to maintain
the present tidal prism in the bay but not less than 18 feet deep and
500 feet wide from opposite Barren Island to Rockaway Point, thence
enlarging to not less than 20 feet deep and 1,000 feet wide, protected
by one existing riprap jetty, at an estimated additional cost of $270,000
for new work with $9,000 annually for maintenance, in addition to
that required for existing channels and jetty, subject to certain condi-
tions of local cooperation (H. Doc. No. 700, 76th Cong., 3d sess.).
   Local cooperation.--The River and Harbor Act of September 22,
1922, provided that any funds heretofore or hereafter appropriated
for this improvement may be applied to providing the channels speci-
fied in House Document No. 1488, Sixtieth Congress, second session,
with a depth of 30 feet at mean low water whenever and to such extent
as the city of New York shall construct or provide for the construction
of terminals with facilities suitable to channels of that depth. It also
provided that the city of New York may be reimbursed for dredging
and disposing of the material dredged in the main interior channel
at actual cost, which shall not exceed a rate of 10 cents per cubic yard,
including any cost of inspection borne by the United States, such
reimbursement to include overdepth allowance not exceeding 1 foot.
    The city of New York has, at its expense, met in part the conditions
prescribed by Congress in adopting the project. The terminal at
        RIVERS AND HARBORS-NEW           YORK, N. Y., DISTRICT        157
Canarsie has been partly completed; highway and railroad connec-
tions with this terminal have yet to be made; and facilities for han-
dling cargoes, suited to the kind of freight to be handled by lessees,
are to be installed at the time of leasing. For further details on
work done by local interests see page 126 of Annual Report for 1934
The city of New York has indicated that it is not prepared to construct.
further terminal facilities.
    Terminal facilities.-There are 8. piers with a total berthage of
2,511 feet and 17,123 feet of bulkheads and wharves available for
dockage. Of the terminals,. 11 are municipally owned, 6 are open
to public use, and 20 are equipped with mechanical handling devices.
Yacht clubs, boat yards, and privately owned pleasure-boat landings
are located within the bay. The facilities are adequate for existing
commerce, but are wholly inadequate for the commerce for which
the project was adopted. (For latest full description of terminal
facilities see Port and Terminal Facilities at the Port of New York,
1942, Corps of Engineers.)
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was about 36
percent completed. The main interior channel has been dredged to a
depth of 30 feet at mean low water and width of 1,000 feet from Barren
Island up to Canarsie, a length of about 18,100 feet; thence up to a
point 500 feet east of Fresh Creek Basin, a stretch of about 3,400 feet, it
has been dredged to a depth of 18 feet at mean low water and width of
500 feet. The east jetty was completed August 4, 1933, for a total
length of about 8,400 feet. The controlling mean low-water depth was
22 feet for a width varying from 600 to 1,800 feet from the entrance to
Barren Island, when examined in April 1943; thence 30 feet for a width
varying from 400 to 1,000 feet to Canarsie, when examined July 1932;
thence 18 feet for a width of 500 feet to Fresh Creek Basin, when ex-
amined in July 1932. The work remaining to be done at the ex-
pense of the United States to complete the existing project consists
in dredging the entrance channel to a depth of 30 feet and width of
1,500 feet, and in building a west jetty, if necessary to maintain a
channel of project dimensions, and in dredging the main interior
channel to a depth of 30 feet at mean low water and width of 1,000
feet from Canarsie up to the head of the projected improvement at
the mouth of Cornell Creek.
    The total cost and expenditures of the existing project to June 30,
1944, were $4,314,689.60-$4,228,439.36 for new work and $86,250.24
for maintenance.
    Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
    It is expected that the conditions of local cooperation 'under this
project will not be complied with during the next 2 years. The
repair of the jetty will be necessary during the fiscal year 1946. The
sum of $50,000 can be profitably expended during the fiscal year ending
June 30, 1946, for maintenance repairs, under contract, to restore the
  jetty to a satisfactory condition.
158     REPORT OF CHIEF OF ENGINEERS,             U.   S. ARMY,     1944

                          Cost and financial summary

Cost of new work to June 30, 1944                                   307, 771. 72
                                                                $-----------------------
Cost of maintenance to June 30, 1944_--------                 -      89, 211.69
       Total cost of permanent work to June 30, 1944---------- 4, 396, 983. 41
Net total expenditures_-----------------------------------       4, 396, 983.41
Total amount appropriated to June 30, 1944-------------          4, 396, 983. 41
Amount (estimated) required to be appropriated for completion
of existing project -------------------------------------          7, 578, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_ ---         ------- ____       -----       50, 000.00

11. NEW YORK      HARBOR:      ENTRANCE      CHANNELS       AND ANCHORAGE
                                  AREAS

   Location.-The works included under the above title are in the
upper and lower bays, New York Harbor. The harbor is 330 miles
southwest by water of Boston Harbor, Mass., and 165 miles northeast
of the entrance to Delaware Bay, N. J. and Del.
   The upper bay extends southerly from the junction of Hudson and
East Rivers opposite the Battery, New York City, a distance of about
51/2 miles to the Narrows. The )ower bay extends from the Narrows
to the sea, a distance of about 9 miles. (See U. S. Coast and Geodetic
Survey Charts Nos. 369 and 541.)
   Existing project.-This provides for the Ambrose Channel 45 feet
deep and 2,000 feet wide, extending from the sea to deep water in the
lower bay, length about 10.2 miles; for the Anchorage Channel, an
extension of Ambrose Channel, with the same depth and width, in the
upper bay, opposite the anchorage grounds, length about 5.7 miles;
for Bayside-Gedney Channel 35 feet deep and 800 feet wide, extend-
ing from the sea to the junction with Main Ship Channel, length
about 6.2 miles; for the Main Ship Channel, 30 feet deep and 1,000
feet wide, extending from Bayside-Gedney Channel to deep water
in the lower bay, length about 5.3 miles; for the removal of Craven
Shoal to a depth of 30 feet; for a channel 16 feet deep, 200 feet wide,
and about 2.3 miles long, extending from bell buoy 23 to Hoffman
and Swinburne Islands, for an irregularly triangular-shaped anchor-
age area in the southerly half of Red Hook Flats (approximately 442
acres in extent), 40 and 30 feet deep; an anchorage in the vicinity of
Liberty (Bedloe) Island (about 160 acres in extent) 20 feet deep,
and for a channel along the New Jersey pierhead line connecting Kill
Van Kull with deep water in Anchorage Channel, south of the Liberty
Island anchorage, 20 feet deep for a width of 500 feet and a length of
about 3 miles. The project depths refer to mean low water. Mean
tidal range, 4.7 feet; mean range of spring tides, 5.6 feet; irregular
fluctuations due to wind and barometric pressure vary from 4 feet
below mean low water up to 4 feet above mean high water.
   The estimate of cost for new work, revised in 1942, is $15,200,000.
The latest (1937) approved estimate for annual cost of mainbenance
is $315,000.
               RIVERS      AND HARBORS-NEW                   YORK,      N.    Y.,   DISTRICT             159
  The existing project was authorized by the following river and
harbor acts:
       Acts                       Work authorized                                   Documents


July     5,1884    Main Ship-Bayside-Gedney to 30 feet for width      Annual Reports, 1887, p. 62; and 1888,
                    of 1,000 feet (dimensions fixed by Secretary of    p. 63.
                     War, Dec. 27, 1886, by authority of the act of
                    Aug. 5, 1886).
Mar.     3, 1899   Ambrose Channel (East Channel) to 40 feet---       H. Doc. No. 159, 55th Cong., 3d      se's.
                                                                        (Annual Report 1899, p. 1279).
June 25,1910       Maintenance of entrance channel under one head
Aug.     8,1917    Anchorage Channel, the extension of Ambrose        H. Doc. No. 518, 63d Cong., 2d sess.
                    Channel into Upper Bay.
   Do ----         Removal of Craven Shoal               _ _          H. Doc. No. 557, 64th Cong., 1st sess.
   Do-..-          Channel between Staten Island and Hoffman and      H. Doc. No. 625, 64th Cong., 1st sess.
                    Swinburne Islands.
July     3,1930    Relocation of southerly section of Anchorage       Rivers and Harbors Committee Doe.
                    Channel.                                           No. 18, 71st Cong., 2d sess.
                                                                                                           1
Aug. 30,1935       Dredging south end of Red Hook Flats, Liberty      H. Doc. No. 183, 73d Cong., 2d sess.
                    Island Anchorage, and channel along New
                    Jersey pierhead line.
   Do-.......      Deepening Bayside-Gedney Channel to 35 feet        H. Doc. No. 133, 74th Cong., 1st sess.'
                    for a width of 800 feet.
Aug. 26,1937       Deepening Ambrose and Anchorage Channels to        Senate committee print, 75th Cong.,
                    45 feet for a width of 2,000 feet.                  1st sess.'


  I Contain latest published maps.


   Terminal facilities.-The harbor consists of Upper Bay and Lower
Bay. In the Upper Bay there are 45 piers with a total berthage of
70,723 feet and 11,171 feet of bulkheads and wharves available for
dockage. In addition there are 5 car-float (railroad) bridges and
3 ferry terminals. These terminals are located along the westerly
shore of the bay, from St. George, Staten Island, to the Narrows and
from Constable Hook, Bayonne, to Ellis Island. The terminals along
the Brooklyn water front are reported under Bay Ridge and Red
Hook Channels. The Lower Bay is largely undeveloped, the terminals
being confined to Gravesend Bay. There are 7 piers with a total
berthage of 9,808 feet and 1 bulkhead providing dockage of 1,675 feet.
Of the terminals in the harbor, 27 are publicly owned, 4 are open to
public use, 27 are equipped with mechanical handling devices and
24 have railroad connections. The facilities are considered adequate
for present commerce. (For latest full description of terminal facil-
ities see Port and Terminal Facilities at the Port of New York, 1942,
Corps of Engineers.)
   Operations and results during fiscal year.-Under a contract for
dredging Liberty Island Anchorage to a depth of 20 feet, work was
commenced January 27, 1942, discontinued December 27, 1942, re-
sumed September 1, 1943, and was in progress at the end of the fiscal
year. During the fiscal year 1,942,076 cubic yards, place measure-
ment, of material were removed at a cost of $931,625.96 for new work.
   Under a contract for dredging sections 8 and 9 of Red Hook Flats
Anchorage to a depth of 30 feet, work was commenced April 1, 1943,
and was completed October 29, 1943. During the fiscal year there
were removed 1,543,437 cubic yards, place measurement, of material at
a cost of $581,435.47 for new work.
160     REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,   1944

    Under a contract for dredging sections 1-4 and 10 of Red Hook Flats
Anchorage to 40 and 30 feet, respectively, work was commenced June
9, 1944, and was in progress at the end of the fiscal year. During the
fiscal year there were removed 178,600 cubic yards, place measure-
ment, of material at a cost of $84,123.82 for new work.
    The U. S. seagoing hopper dredge Goethals was employed inter-
mittently from July 1-31, 1943, the U. S. seagoing hopper dredge
Navesink was employed intermittently from August 16, 1943, to
January 29, 1944, and the U. S. seagoing hopper dredge Atlantic was
employed intermittently from July 1-31, 1943, in dredging sections
1-7, Red Hook Flats Anchorage, to depths of 30 and 40 feet. Dur-
ing the fiscal year there was removed a total of 386,772 cubic yards,
place measurement, of material at a cost of $100,834.01 for new work.
    The U. S. seagoing hopper dredge Goethals was employed intermit-
tently from August 1, 1943, to May 28, 1944, the U. S. seagoing
hopper dredge Navesink was employed intermittently from August
16,1943, to January 29, 1944, and the U. S. seagoing hopper dredge At-
lantic was employed intermittently from February 2, 1944, to June
29, 1944, in dredging section 1-15 of Ambrose Channel to a depth of
45 feet. During the fiscal year there was removed a total of 2,417,335
cubic yards, place measurement, of material at a cost of $640,761.27
for new work.
    Under a contract for the removal of shoals in Anchorage Channel
to 40 feet, work was performed intermittently from November 2-20,
1943. During this period there were removed 9,800 cubic yards, place
measurement, of material at a cost of $15,651.76 for maintenance.
    The U. S. seagoing hopper dredge Goethals was employed on Sep-
tember 17 and 18, 1943, in the removal of a shoal in Anchorage Chan-
nel to a depth of 40 feet. There were removed 4,470 cubic yards, place
measurement, of material at a cost of $3,473.60 for maintenance.
    The cost of surveys and engineering preliminary to dredging Red
Hook Flats Anchorage, Ambrose Channel, and Liberty Island An-
chorage, was $5,332.85 for new work. The cost of surveys to deter-
mine the condition of the channel along the New Jersey Pierhead Line
and the channel between Staten Island and Hoffman and Swinburne
Islands was $459.28 for maintenance.
    The total cost of work was $2,363,698.02-$2,344,113.38 for new
work and $19,584.64 for maintenance. The total expenditure was
$2,468,666.34.
    Condition at end of fiscal year.-The existing project was about 76
percent completed.
    Main Ship-Bayside-Gedney Channels were completed to a depth of
30 feet in 1891. The deepening of Bayside-Gedney Channel to 35
feet for a width of 800 feet was completed in 1939.
    Ambrose Channel was completed to a depth of 40 feet for a width
of 2,000 feet in 1914. The center 800 feet was dredged to 45 feet
in 1944.
    Relocation of Anchorage Channel was completed to a depth of 40
feet in 1932.
    The channel between Staten Island and Hoffman and Swinburne
Islands was completed in 1920 up to within 300 feet of the southerly
limits of the project. The dredged channel meets all the needs of
navigation and no further work of improvement is contemplated for
the present.
               RIVERS        AND        HARBORS-NEW                          YORK,          N.         Y.,     DISTRICT           161

  The channel along the New Jersey pierhead line from Kill Van
Kull to Anchorage Channel was completed in 1939.
  The controlling mean low water depths of the channels included in
this project are as follows:
                       Section                                     Depth               Width                             Date
                                                                   (feet)              (feet)


Ambrose Channel _--_                -------         _ __            -   45   800 to 1,500 (through               June-August 1942, Feb-
                                                                               the center).                        ruary-December
                                                                                                                   1943, January-June
                                                                                                                   1944.
                                                                                                                 August 1943.
M ain Ship Channel _._.........-
Bayside-Gedney Channel _35
Anchorage Channel __42
                                          .......          -   _        30   850 to 1,000 ..........
                                                                             300 to 800 ........
                                                                             900 to 2,000   -...
                                                                                                               -June
                                                                                                             .January
                                                                                                                       1944.
                                                                                                                             to March,
                                                                                                                   and June, 1943.
Craven Shoal          ___1                                       30 -------.----------                           July 1931.
Channel between Staten Island and Hoffman
  and Swinburne Islands:
    Buoy 23 to Hoffman Island__                          _        13 100 to 200 .                      -         November1943.
                                                                                                                 November 1943.
    Hoffman Island to Swinburne Island ...                        10 120 to 200 ...----------
Red Hook Flats Anchorage:
    40-foot area:
         Westerly half-------------------------40-February-November
         Easterly half-------------------------                  30------
    30-foot area --      -------------------------       ---      30 ..........----------------                   .
Liberty (Bedloe) Island Anchorage........                       3 20 _July                                           1943 and January-
                                                                                                                  June 1944.
Along New Jersey Pierhead line........-.....                            20            .........--...
                                                                             170 to 500---------                 August-September
                                                                                                                  1943.

  1 Except for a shoal 100 by 600 with least depth of 27 feet located along westerly channel line.
  2 16 feet in the most easterly section.
  3 Except area off northeasterly corner of Ellis Island where rock shoals exist with least depth of 14 feet.

   The work remaining to be done under the existing project consists
of completing the dredging of the south end of Red Hook Flats to 40
feet and 30 feet, and Liberty (Bedloe) Island anchorage to 20 feet,
all as authorized in 1935; and deepening Ambrose and Anchorage
Channels to 45 feet for a width of 2,000 feet as authorized in 1937.
   The total cost of the existing project to June 30, 1944, was $15,173,-
368.41-$12,577,049.74 for new work, including $116,530 applied to
removing wrecks authorized by acts prior to the adoption of the
existing project, and $2,596,318.67 for maintenance. The total ex-
penditure was $14,967,140.85.
   Proposed operations.-The balance unexpended at the end of the
year amounting to $867,270.74, plus $211,000 allotted in July 1944 a
total of $1,078,270.74, will be applied as follows:
Accounts payable June 30, 1944         ________                                                   ..       _           $206, 227. 56
New work:
    Complete by Aug. 19 1944, under contract in
      force, dredging of Liberty Island Anchorage
      to 20 feet_   _______---------$113,                                                                  529. 00
    Complete by Dec. 1, 1944, under contract in
      force, dredging of sections 1-4 and 10, Red
      Hook Flats Anchorage to 40 and 30 feet ..---                                            428, 514. 18
                                                                                                                        542, 043. 18
Maintenance:
    Complete by Apr. 30, 1945, under contract to
      be entered into, dredging to restore the chan-
      nel along the New Jersey pierhead line to
      project dimensions ___        __      ____                                                 150, 000. 00
    Dredge by use of 1 United States seagoing hop-
      per dredge for about 4 months (Mar. 1 to
      June 30, 1945) in the removal of shoals from
      the entrance channels_      -      -     -                                                 180, 000. 00
                                                                                                                        330, 000. 00
              Total                   .................-----------------------------------------.. 1, 078, 270. 74
         616634--45---pt. 1, vol. 1-                   11
162              REPORT OF CHIEF OF ENGINEERS,                                        U. S. ARMY,                     1944

  Further new work is not considered necessary during the fiscal
year 1946. The existing channels should be maintained. The sum
of $200,000 can be profitably expended for dredging by use of one
United States seagoing hopper dredge for about 4 months during
the fiscal year ending June 30, 1946, in the removal of shoals from the
existing channels.
                                                   Cost and financial summary
Cost of new work to June 30, 1944-_       __ __     __ _                                                          $12, 577, 049. 74
Cost of maintenance to June 30, 1944_--------------------                                                            2, 596, 318. 67
      Total cost of permanent work to June 30, 1944                                              ----                 15, 173, 368. 41
Minus accounts payable June 30, 1944----------------------                                                                206, 227. 56

      Net total expenditures_-------               - -   _                                                            14, 967, 140. 85
Unexpended balance June 30, 1944 ---------------------------                                                              867, 270. 74
           Total amount appropriated to June 30, 1944-----------                                                      15, 834, 411. 59

    Fiscal year ending June 30                       1940              1941                1942                1943               1944


Cost of new work ...............                      $325. 60      $96, 076. 38     $295, 419. 24 $1, 150, 385. 13          $2, 344, 113. 38
Cost of maintenance .........
                            --                     274, 008. 58      65, 799. 36      -- -3,                585. 38               19, 584. 64
        Total cost_.       .__            ..----   274, 334.18      161, 875. 74      295, 419. 24        1, 153. 970. 51     2, 363, 698.02

Total expended............----------------.        280, 096. 86     163, 634.97       190, 438. 36          947, 755. 51      2, 468, 666. 34
Allotted     .         __..................        743,000.00     1, 246, 598. 33-    940. 360.41         1. 400. 000.00        483, 973.40


Balance unexpended July 1, 1943 _-          -     -    -    $2, 851, 963. 68
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942    --------------------------------  1, 100, 000. 00
      Amount to be accounted for----__       -------                                                                   3, 951, 963. 68
Deductions on account of revocation of allotment----------                                                                616, 026. 60
       Net amount to be accounted for_                                                                          -3,         335, 937. 08
Gross amount expended--------------------                                            $2, 486, 985.75
Less reimbursements collected-----------------                                            18, 319. 41
                                                                                                                       2, 468, 666. 34

      Balance unexpended June 30, 1944----------------                                                                      867, 270. 74
Outstanding liabilities June 30, 1944 ------------- $35, 950. 26
Amount covered by uncompleted contracts             711, 965. 61          --------
                                                                                                                            747, 915. 87
     Balance available June 30, 1944_ _                                        ---------                                    119, 354. 87
Amount allotted in July 1944_---
                             ...-----                                                               ___                     211, 000. 00
           Amount available during fiscal year 1945------------                                                             330, 354. 87
Amount (estimated) required to be appropriated for completion
of existing project 1                  -_-___-_3,                                                                          359, 000. 00
Amount that can be profitably expended in fiscal year ending
   June 30, 1946, for maintenance 1--                                                        -            __                200, 000. 00
  1 Exclusive of available funds.


                    12. BAY RIDGE AND RED HOOK CHANNELS, N. Y.

  Location.--These channels lie along th east shore of the Upper
Bay, New York Harbor, and, with Buttermilk Channel, form an
easterly channel along the Brooklyn water front from the Narrows
to Exst River.                      (See U. S. Coast and Geodetic Survey Charts Nos.
369 and 541.)
               RIVERS       AND HARBORS-NEW                     YORK,    N.   Y.,   DISTRICT            163
   Previous projects.-Adopted by River and Harbor Acts of March
3, 1881, August 11, 1888, September 19, 1890, August 18, 1894, and June
3, 1896. For further details see page 1768 of Annual Report for 1915,
and page 195 of the Annual Report for 1938.
   Existing project.-This provides for a channel 1,200 feet wide and
40 feet deep at mean low water from the Narrows to Bay Ridge
Avenue, Brooklyn, thence 1,750 feet wide to the junction of Bay
Ridge and Red Hook Channels, thence 1,200 feet wide through Red
Hook Channel to the junction with Buttermilk Channel, and a chan-
nel of the same depth extending into Gowanus Bay from the junc-
tion of Bay Ridge Channel with Red Hook Channel, narrowing uni-
formly in width to about 500 feet at Twenty-eighth Street, Brooklyn.
Length of section included in the project, 4.5 miles. Mean tidal range,
4.7 feet; mean range of spring tides, 5.6 feet; irregular fluctuations
due to wind and barometric pressure vary from 4 feet below mean
low water up to 4 feet above mean high water.
   The estimate of cost for new work, revised in 1930, was $4,609,000,
exclusive of amounts expended on previous projects. The latest (1930)
approved estimate for annual cost of maintenance is $150,000.
   The existing project was authorized by the following river and
harbor acts:
       Acts                        Work authorized                                  Documents


Mar.     3, 1899   Channel 40 feet deep and 1,200 feet wide .      ____ H. Doc. No 337, 54th Cong., 2d sess.;
                                                                          Annual Report, 1897, p. 1177.
Mar.     2, 1907   Dredging to obtain, first, a depth of 35 feet, sub-
                    sequently increasing depth to 40 feet for full
                    width.
July     3,1930    Widening of Bay Ridge Channel to 1,750 feet--..... Rivers and Harbors Committee Doc.
                                                                          No. 44, 71st Cong., 2d sess. (Con.
                                                                         tains latest published map.)


   Terminal facilities.-There are 52 piers with a total berthage of
84,366 feet and 8,096 feet of bulkheads and wharves available for
dockage. Twenty-two of the terminals have mechanical handling de-
vices and 19 have railroad connections. In addition, there are 6
railroad float bridges and 2 ferry slips. Of the terminals, 4 are Gov-
ernment owned, 15 are owned by the city of New York and 7 are open
to public use. The terminal facilities are considered adequate for
existing commerce. (For latest full description of terminal facilities,
see Port and Terminal Facilities at the Port of New York, 1942, Corps
of Engineers.)
   Operations and results during fiscal year.-The U. S. seagoing
hopper dredge Goethals was employed intermittently on July" 22-23,
1943, and January 4, 5, 6, 1944; the U. S. seagoing hopper dredge
Navesine was employed intermittently on October 1, 22, 25, 26, 1943;
and the U. S. seagoing hopper dredge Atlantic was employed inter-
mittently on December 18 to 20, 24 to 29, 1943, and June 2-3, 1944,
in the removal of shoals from Red Hook Channel to a depth of 40 feet.
During the fiscal year there was removed a total of 64,310 cubic yards,
place measurement, of material at a cost of $21,888.90 for maintenance.
  The cost of surveys and engineering preliminary to dredging Bay
Ridge and Red Hook Channels was $710.77 for maintenance.
 164         REPORT OF CHIEF OF ENGINEERS,                               U. S. ARMY,                 1944

   The total cost of work was $22,599.67 for maintenance. The total
expenditure was $17,483.81.
   Condition at end of fiscal year.-The existing project was completed
in 1940. Bay Ridge Channel was completed in 1939 and Red Hook
Channel in 1940. The controlling mean-low water depths when ex-
amined in June and October 1943 and February 1944 were as follows:
In Bay Ridge Channel 39 feet for full project width from deep water
in the Narrows to Sixty-fourth Street, Brooklyn, thence 37 feet for a
width varying from 400 to 750 feet to Forty-third Street, and thence
32 feet for a width varying from 1700 to 400 feet to Twenty-eighth
Street; in Red Hook Channel, 37 feet for a width of 500 feet.
   The total cost of the existing project to June 30, 1944, was $7,-
291,162.76-$4,212,636.95 regular funds and $64,559.68 Public Works
funds, a total of $4,277,196.63 for new work and $3,013,966.13 for
maintenance.
   The total expenditure was $7,285,643.11.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $306,017.08 plus $180,000 allotted in" July
1944, a total of $486,017.08, will be applied as follows:
Accounts payable, June 30, 1944-------------------------------           $5, 519. 65
Maintenance: Dredge by use of 2 United States seagoing hopper
  dredges for a total of 9Y dredge months during the period July 1,
  1944, to Feb. 15, 1945, to restore the easterly 800 feet of Bay Ridge
  Channel frompthe Army base to the junction with Red Hook
  Channel to project depth of 40 feet -------------------------         480, 497. 43

           Total   ---------------------------------------------                                           486, 017.08
  The project channels should be maintained. The sum of $300,000
can be profitably expended in dredging by use of one United States
seagoing hopper dredge for about 5 months during the fiscal year
ending June 30, 1946, in the removal of shoals from the channels.
                                    Cost and financial summary
Cost of new work to June 30, 1944_     --                                              -            $5, 523, 296. 63
Cost of maintenance to June 30, 1944-----                        ------------------                  3, 013, 966. 13
      Total cost of permanent work to June 30, 1944 ----- ---                                        8, 537, 262. 76
Minus accounts payable June 30, 1944---------- -----------                                                5, 519. 65
                          -----------------------------
      Net total expenditures_                                                                       8, 531, 743. 11
Unexpended balance June 30, 1944--------------------------                                             306, 017. 08
           Total amount appropriated to June 30, 1944_-- -------                                     8, 837, 760. 19

   Fiscal year ending June 30           1940              1941            1942               1943                 1944


Cost of new work--------------       $47, 077.06    -
Cost of maintenance------------      436, 361.58        $10, 450.05    $168, 013.85        $22, 193.03       -   $22, 599. 67

      Total cost---------------      483, 438. 64        10, 450.05     168, 013. 85        22, 193.03            22, 599. 67

Total expended----------------       469, 614. 40        20, 493. 16    136, 555. 64        53, 247. 45           17, 483.81

Allotted   ---------------------     153, 000.00         55, 000. 00    222,000. 00        150, 000. 00-
             RIVERS       AND HARBORS-NEW                  YORK,         N.       Y., DISTRICT            165
Balance unexpended July 1, 1943_                                                             $323, 500. 89
Gross amount expended ------------------------------------                                     17, 483. 81

      Balance unexpended June 30, 1944___-                          -------                    306, 017. 08
Outstanding liabilities June 30, 1944 _5,                                                           519. 65

     Balance a',ailable June 30, 1944 _       --                        -------                300, 497. 43
Amount allotted in July 1944_---        -180,                                                       000. 00

           Amount available during fiscal year 1945              ---------------               480, 497. 43

Amount that can be profitably expended in fiscal year ending June
   30, 1946 for maintenance          1   ____         -      -          --   ____              300, 000. 00
  1 Exclusive of available funds.

                             13. BUTTERMILK CHANNEL, N. Y.
   Location.-This channel connects deep water in the Upper Bay,
New York Harbor, southwest of Governors Island, with deep water
in East River northeast of Governors Island, and, with Bay Ridge
and Red Hook Channels, forms an easterly channel along the Brook-
lyn water front from the Narrows to East River. It lies between
Governors Island and Brooklyn Borough, New York City. (See
U. S. Coast and Geodetic Survey Charts Nos. 541 and 745.)
   Previovs projects.-Adopted by River and Harbor Acts of June 14,
1880, July 13, 1892, and June 3, 1896. For further details see page
205, Annual Report for 1932.
   Existing project.-This provides for a channel 1,000 feet wide, 40
feet deep at mean low water for the width of the existing 500-foot
channel and 35 feet deep for the remaining 500-foot width west of
the existing channel, with suitable widening at the junctions with
East River and Red Hook and Anchorage Channels. Length of sec-
tion included in the project, 2.3 miles. Mean tidal range, 4.4 feet;
mean range of spring tides, 5.3 feet; irregular fluctuations due to
wind and barometric pressure vary from 4 feet below mean low water
up to 4 feet about mean high water.
   The estimated cost for new work, revised in 1944, is $2,138,000, ex-
clusive of amounts expended on previous projects. The latest (1935)
approved estimate for annual cost of maintenance is $20,000.
   The existing project was authorized by the following river and har-
bor acts:
    Acts                        Work authorized                                      Documents


June 13, 1902   Channel 1,200 feet wide and not less than 30 feet     H. Doc. No. 122, 56th Cong., 2d sess.
                  deep.                                                  (Annual Report 1901, p. 1299.)
Aug. 30,1935    Channel 1,000 feet wide to depths of 40 and 35 feet_Rivers and Harbors Committee Doc.
                                                                         No. 55, 74th Cong., 1st sess. (Con-
                                                                         tains latest published map.)


   Terminal facilities.-There are 20 piers with a total berthage of
27,324 feet, and 3,722 feet of bulkheads and wharves available for
dockage. Of the terminals, 13 are equipped with mechanical handling
devices and 14 have railroad connections. Two of the terminals are
owned by the city of New York of which 3 are open to public use.
In addition, there are 2 float bridges and 2 ferry slips. Practically
all of the available water front is occupied and the facilities are con-
sidered adequate for existing commerce. (For latest full description
166     REPORT OF CHIEF OF ENGINEERS,        U.   S. ARMY,   1944


of terminal facilities see Port and Terminal Facilities at the Port
of New York, 1942, Corps of Engineers.)
    Operations and results during fiscal year.-Under a contract for
dredging the southerly 2,000 feet of the westerly 500-foot channel to
a depth of 35 feet and the widenings at the junctions with Anchorage
Channel and Red Hook Channel to depths of 35 and 40 feet, respec-
tively, work was commenced April 30, 1944, and was in progress at
the end of the fiscal year. During the fiscal year there were removed
177,300 cubic yards, place measurement, of material at a cost of
 $85,495.81 for new work.
    The U. S. seagoing hopper dredge Atlantic was employed intermit-
tently from August 1 to December 23, 1943, and the U. S. seagoing
hopper dredge Navesink was employed intermittently from July 22
to August 13, 1943, in dredging the southerly 2,000 feet of the west-
erly 500-foot channel to a depth of 35 feet and the widenings at the
junctions at Anchorage Channel and Red Hook Channel to depths
of 35 feet and 40 feet. There were removed 442,142 cubic yards, place
measurement, of material at a cost of $139,560.53 for new work.
    The U. S. seagoing hopper dredge Atlantic was employed intermit-
tently from July 4 to September 4, 1943, in dredging the easterly
500-foot width between Anchorage and Red Hook Channels to a depth
of 40 feet. There were removed 245,453 cubic yards, place measure,
ment, of material at a cost of $38,995.46 for maintenance.
    The cost of surveys and engineering preliminary to dredging was
$544.69 for new work.
    The total cost of work was $264,596.49-$225,601.03 for new work
and $38,995.46 for maintenance.          The total expenditure was
$242,633.60.
    Condition at end of fiscal year.-The existing project was about 61
percent completed. The easterly 500-foot width of channel from
Anchorage Channel to East River was completed to a 40-foot depth in
1935. The westerly 500-foot channel, including the widening at the
junction with the East River, was completed to a 35-foot depth for the
northerly three-quarters of a mile of its length in 1939. The widen-
ing at the junction with Red Hook Channel was completed to a 40-foot
depth in 1944. The controlling mean low-water depth in the easterly
500-foot channel was 40 feet for a width varying from 350 to 500
feet from Anchorage Channel to the East River, including the widen-
ing at the junction with Red Hook Channel (May 1940, February
1942, June and September 1943, May and June 1944). The controlling
mean low-water depth in the westerly 500-foot channel was 33 feet
in the southerly 2,000 feet, including the widening at the junction
with Anchorage Channel (May and June 1944), thence 20 feet for
a distance of 1.1 miles except along the westerly channel line where
it was 16 feet and less (June 1937 and May 1942), thence 35 feet for
full project width for the remainder of its length, including the widen-
ing at the junction with East River (July to December 1939). The
work remaining to be done under the project consists of completing
the deepening to 35 feet of the westerly 500-foot channel and the
widening at the junctions with Red Hook and Anchorage Channels.
   The total costs and expenditures of the existing project to June 30,
1944, were $1,713,393.02-$122,051.24 Public Works funds and $1,313,-
081.54 regular funds, a total of $1,435,132.78 for new work, and
$278,260.24 for maintenance. The total expenditure was $1,691,430.13.
              RIVERS AND HARBORS-NEW                                    YORK,        N.    Y., DISTRICT                        167
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $51,360.74, will be applied as follows:
Accounts payable June 30, 1944 ..                 -$21,                                                                    962. 89
New work: Complete by Aug. 1, 1944, under contract in force, dredg-
  ing of sections 1 and 2 to 35 and 40 feet, respectively_  - -                                                      29, 397. 85

          Total    -                             --         -       -                      -----                     51, 360.74
   Completion of the 35-foot channel is not considered necessary dur-
ing the fiscal year 1946. Maintenance dredging of the existing 40-foot
channel will be necessary. The sum of $75,000 can be profitably ex-
pended for dredging by use of one United States seagoing hopper
dredge for about 2 months during the fiscal year ending J(une 30,
1946, in the removal of shoals from the 40-foot channel.
                           Cost and financial summary
Cost of new work to June 30, 1944 --                                                                          $1, 931,     382.    78
Cost of maintenance to June 30, 1944_                                                                             278,     260.    24
       Total cost of permanent work to June 30, 1944_                                                          2, 209,     643.    02
Minus accounts payable June 30, 1944                                                                               21,     962.    89
          Net total expenditures._                                                                             2, 187,     680.    13
Unexpended balance June 30, 1944 _ -                                                                               51,     360.    74
          Total amount appropriated to June 30, 1944-                                                          2, 239,     040.    87

   Fiscal year ending June 30             1940                  1941               1942               1943                  1944


Cost of new work --------------       $196, 989.14           ...             _      $530. 80         $1,106. 42        $225, 601.03
Cost of maintenance---.......          --------------...---...... .-----....                          6, 368. 44         38, 995. 46
      Total cost_---        -------    196, 989. 14                                  530.80           7,474. 86            264, 596. 49

Total expended__---------             336, 899. 15                                   521.14           7, 484. 52           242, 633. 60

Allotted-------------------------            384. 23      _-              -      270, 000.00       -80,000.    00          112, 000. 00


Balance unexpended July 1, 1943__                                                                               $181, 994. 34
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942 _-___                                                                                      112, 000. 00
       Amount to be accounted for_                                                                                  293, 994. 34
Gross amount expended -_                       $246, 173. 68
Less reimbursements collected_                    3, 540. 08
                                                                                                                    242,   633.    60
     Balance unexpended June 30, 1944_                                                                               51,   360.    74
Amount covered by uncompleted contracts-                                                                             43,   417.    75
     Balance available June 30, 1944.                                                                                 7,   942.    99
Amount (estimated) required to be appropriated for completion of
existing project  _ -                                                                                              665, 000. 00
Amount that can be profitably expended in fiscal year ending
   June 30, 1946, for maintenance                  1              ----------                                         75, 000. 00
  1 Exclusive of available funds.
                                      14. EAST RIVER, N. Y.
   Location.-This is a tidal strait about 16 miles long and 600 to 4,000
feet wide, connecting Hudson River and the Upper Bay at the Bat-
tery, New York City, with Long Island Sound at Throgs Neck, New
York City, and separating Long Island from Manhattan Island and
the mainland. (See U. S. Coast and Geodetic Survey Charts Nos.
223, 226, and 745.)
  Previous projects.-Adopted by River and Harbor Acts of August
30, 1852, July 25, 1868, March 3, 1899, and June 25, 1910. For further
details see page 210, Annual Report for 1932.
168            REPORT     OF CHIEF OF ENGINEERS,                       U.     S. ARMY,        1,944

   Existing project.-This provides for channels of the following
dimensions (depths refer to mean low water) From deep water in
the Upper New York Bay to Wallabout Channel, 40 feet deep and
1,000 feet wide; from Wallabout Channel to Throgs Neck, 35 feet deep,
with widths varying from about 550 to 1,000 feet, according to local-
ity; east of Welfare (Blackwells) Island up to English Place (43d
Drive), Long Island City, 30 feet deep and varying in width from 500
to 900 feet, with widening in the approach from the main channel;
between South Brother and Berrian Islands, 20 feet deep and 300 feet
wide, with widening in the approach from the main channel; for the
removal of Coenties Reef to a depth of 40 feet, also the removal of the
following rocks and reefs lying outside of the limiting lines of the
main channel to give access to wharves: Along the Brooklyn shore,
Brooklyn Bridge to Manhattan Bridge (Fulton Ferry Reef), to a
depth of 25 feet; Jay Street Reef, 25 feet; Corlears Reef, 35 feet;
Shell Reef, 25 feet; Horns Hook, 40 feet; Rhinelander Reef, 26 feet;
and reef off Oak Point, 30 feet; and for the construction of a dike in
Pot Cove in Hell Gate. The length of the section included in the
improvement is about 16 miles. The mean range of tides varies
according to locality from 4 feet at Wallabout Channel and 4.4 feet
at the Battery to 4.9 feet at Hallets Point, 6.3 feet at Port Morris, and
7.1 feet at the eastern entrance.at Throgs Neck; mean range of spring
tides, 4.8, 5.3, 5.9, 7.4, and 8.5 feet, respectively; irregular fluctuati'ons
due to wind and barometric pressure vary according to locality from
4 feet below mean low water at the Battery, 3.5 feet at Wallabout
Channel and 4 feet at Throgs Neck up to about 4 feet above mean high
water at the Battery and 4.5 feet above mean high water at Throgs
Neck; extreme fluctuations do not seriously affect navigation.
   The estimate of cost for new work, revised in 1933, exclusive of
amounts expended on previous projects, is $24,000,000. The latest
(1921) approved estimate for annual cost of maintenance is $25,000.
   The existing project was authorized by the following river and
harbor acts:
    Acts                         Work authorized                                       Documents


Mar. 3, 1915   1 Removal of Coenties   Reef to 35 feet, conditioned    H. Doc. No. 188, 63d Cong., 1st sess.
                  upon local interests increasing depth to 40 feet.
Jiqly27,1916     Channel across Diamond Reef 35 feet deep and                 Do.
                  1,000 feet wide.
Aug.   8, 1917   Channel east of Blackwells Island to 20 feet; chan-          Do.
                   nel between South Brother and Berrian Islands,
                   to 20 feet; channel between North and South
               Brother Islands to 26 feet.
    Do-.......Channel 40 feet deep through East River and              H. Doe. No. 140, 65th Cong., 1st sess.
               Hell Gate.
July 18,1918 Secure a depth of 40 feet in channel through East         Specified in act.
               River and Hell Gate as soon as practicable.
Sept. 22,1922 Depth limited to 35 feet in the through channel          Rivers and Harbors Committee Doe.
               between Wallabout Channel and Throgs Neck.               No. 3, 67th Cong., 2d sess. (Con-
                   Channel east of Blackwells Island, 30 feet to            tains latest published map.)
                   English Place and eliminated 20-foot channel
                   north of English Place. Eliminated channel
                   between North and South Brother Islands
                   except as authorized prior to existing project.
                   Removal of certain rocks and reefs and con-
                   struction of dike in Pot Cove, Hell Gate.

  1 Pub. les. No. 67, 63d Cong.. 3d sess.
          RIVERS AND   HARBORS-NEW       YORK,   N.   Y.,   DISTRICT   169
   Recommended modifications of project.-Under date of December
11, 1939, the Chief of Engineers recommended modification of the
existing project so as to provide a channel generally 40 feet deep at
mean low water, 550 to 1,000 feet wide, extending from the upper
limit of the existing 40-foot depth at Wallabout Channel to Throgs
Neck, with widening of the bend in the channel south of Belmont
Island to a depth of 40 feet, dredging a cross channel 20 feet deep
and   1,000 feet wide between Belmont and Welfare Islands, dredging
East Channel at Welfare Island 25 feet deep and 500 to 600 feet wide,
removal of certain portions of Hallets Point to depths of 25, 40, and 47
feet, removal of the southern arm of Mill Rock to a depth of 20 feet,
removal of ledges near Mill Rock and along the east bank of East
River in the vicinity of the Triborough Bridge to a depth of 40 feet,
filling an area in the vicinity of Hogs Back Light and constructing a
dike from this area to Wards Island, cutting back Negro Point on
Wards Island to a depth of 40 feet, and dredging a channel 40 feet
deep and 650 feet wide between North and South Brother Islands, all
at an estimated initial cost of $34,509,000 with no increase in the
present annual cost of maintenance (H. Doc. No. 554, 76th Cong., 3d
sess.).
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are 120 piers with a total berthage of
85,844 feet and 56,518 feet of bulkheads and wharves available for
dockage along both shores of the East River from the Battery to
Clason Point. In addition, there are 10 ferry slips and 20 car-float
bridges. Of the terminals, 141 are publicly owned, 5 are open to pub-
lic use, 93 are equipped with mechanical handling devices, and 41 have
railroad connections. The facilities are considered adequate for pres-
ent needs. (For latest full description of terminal facilities see Port
and Terminal Facilities at the Port of New York, 1942, Corps of
Engineers.)
   Operations and results during fiscal year.-The U. S. derrick boat
N. Y. 34 was employed intermittently from July 1, 1943, to April 25,
1944, in the examination and removal of isolated rock shoals between
Diamond Reef and the Brooklyn Navy Yard. A total of 729.5 cubic
yards of rock was removed at a cost of $42,200.04 for maintenance.
   The cost of surveys to determine the condition of the waterway in the
vicinity of the navy yard and of Diamond Reef Channel was $9,467.64
for maintenance.
   The total cost of work was $51,667.68 for maintenance. The total
expenditure was $51,668.05.
   Condition at end of fiscal year.-The existing project was about
99 percent completed.
   The controlling mean low-water depth from deep water in the Upper
Bay to Wallabout Channel is 39 feet for a width varying from 900 to
1,000 feet except opposite the Battery where the width is limited to
400 feet by a shoal area 200 feet by 750 feet with a least depth of 37.7
feet located in the center of the channel and in the vicinity of Corlears
Hook where a shoal with a least depth of 32.5 feet extends into the
channel for a distance of 130 feet. Corlears Reef has been removed
to 40 feet with the exception of shoals over the cable area extending into
the channel from the Manhattan side for a distance of 100 feet having
a least depth of 38.6 feet. From Wallabout Channel through the West
Channel at Welfare (Blackwells) Island and Hell Gate to Throgs Neck
170            REPORT OF CHIEF OF ENGINEERS,                                    U.     S. ARMY,               1944


at Long Island Sound, the controlling mean low-water depth is 35 feet
for widths varying from 550 to 1,000 feet. In the section of the East
Changel at Welfare (Blackwells) Island included in the existing
project it is28 feet from off Newtown Creek to English Place (43d
Drive), Long Island City, and continuing through the natural channel
of navigable width to deep water off the north end of Welfare (Black-
wells) Island it is 24 feet. The controlling depth in the channel be-
tween South Brother and Berrian Islands is 20 feet for a width of 300
feet. The controlling depths are those determined by intermittent
surveys made during the period 1910 to 1944.
   The work remaining to be done to complete the existing project con-
sists of the removal of a small shoal area along the east side of the 35-
foot channel between Grand Street and North Third Street, Brook-
lyn. The construction of the dike at Pot Cove in Hell Gate and a part
of the widening near the pierhead line in Jay Street Reef were omitted
as being unnecessary.
   The total cost of the existing project to June 30, 1944, was $24,376,-
398.60-$1,743,265.42 Public Works funds and $22,106,453.80 regular
funds, a total of $23,849,719.22, for new work and $526,679.47 for main-
tenance. The total expenditure was $24,376,267.54.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $26,163.37, will be applied as follows:
Accounts payable June 30, 1944--------------------------------                                                             $131. 15
Maintenance:
    Complete by July 17, 1944, by hired plant, dredging in Diamond
      Reef Channel to 40 feet for cable relocation--- --------                                                            8,000. 00
    Dredge by use of 1 United States seagoing hopper dredge for                                                 /3
      month (July 24 to Aug. 3, 1944) to remove shoals from Dia-
      mond Reef Channel to 40 feet -        --___15, --                                                                     000. 00
    Operate 1 United States derrick boat for about / month (July 14
      to 24, 1944) in the removal of shoals from the project channel                                                      3, 032. 22

                Total-------------------------------------                                     _26,                         163. 37
  Completion of the project is not considered necessary during the
next 2 years. Additional maintenance will be necessary. The sum of
$25,000 can be profitably expended for the removal of shoals in Dia-
mond Reef Channel by use of one United States seagoing. hopper
dredge for one-half month during the fiscal year ending June 30, 1946.
                                           Cost and financial summary
Cost of new work to June 30, 1944-----------------------$30, 037, 412. 72
Cost of maintenance to June 30, 1944-----------------------  564, 343. 42
      Total cost of permanent work to June 30, 1944- --------                                                 30, 601, 756. 14
Minus accounts payable June 30, 1944-                            ---------------------                                 131. 15
      Net total expenditures-----------------------------                                                     30, 601, 624. 99
Unexpended balance June 30, 1944-------------------------                                                          26, 163. 37
            Total amount appropriated to June 30, 1944------- ---                                             30, 627, 788. 36

    Fiscal year ending June 30                 1940              1941             1942                 1943                 1944

Cost of new work
Cost of maintenancew
               o    --------------------                                        $5, 309. 65        $16, 924. 28            $51,667. 68
Total expended         ..       -$6.                  52-    -   -       -        5, 237. 63          16, 864. 78           51, 668. 05

Allotted --------------------                 26, 709. 45            $22, 500   100, 000. 00------------            ---     22, 566. 17
         RIVERS    AND HARBORS-NEW           YORK,        N.   Y.,      DISTRICT     171
Balance unexpended July 1, 1943   _-------                                   $100, 397.59
Deductions on account of revocation of allotment-------------                  22, 566. 17
      Net amount to be accounted for- -77,                                         831. 42
Gross amount expended ___-                    -         $51, 850. 01
Less reimbursements collected_ ____          -__181.              96
                                                               ----      -     51, 668. 05

      Balance unexpended June 30, 1944--------------------                     26, 163. 37
Outstanding liabilities June 30, 1944_                                             131. 15
      Balance available June 30, 1944 __ -   -         -26,                        032. 22

Amount" (estimated) required to be appropriated for completion
   of existing project 1-   _ __-_   _  -                                     150, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946 for maintenance 1_________        -      -            -25,         000. 00
  1Exclusive of available funds.

                         15.   NEWTOWN CREEK, N. Y.

   Location.-This creek is a tidal waterway entering the East River,
N. Y., and 41/2 miles by water northeast of the Battery, New York
City, and forms a part of the boundary between the boroughs of
Brooklyn and Queens, New York City. (See U. S. Coast and Geodetic
Survey Chart No. 745.)
   Previous projects.-Adopted by River and Harbor Acts of June 14,
1880, July 5, 1884, and June 3, 1896. For further details see page 1769
of Annual Report for 1915, and page 207 of Annual Report for 1938.
   Existing project.-This provides for a channel 23 feet deep and
130 feet wide from the East River to a point about 150 feet north
of Maspeth Avenue; for a turning basin at the former location of
Mussel Island and a triangular area lying on the north side of the
entrance to the creek of the same depth; for a channel 20 feet deep
at mean low water elsewhere in Newtown Creek, including Dutch Kills,
Maspeth Creek, and English Kills, of the following widths: 150 feet
wide from Maspeth Avenue to Grand Street Bridge, thence 125 feet
wide to Metropolitan Avenue on the East Branch; 100 feet wide for
a distance of 2,000 feet up Maspeth Creek; 75 to 100 feet wide for a
distance of 2,800 feet up Dutch Kills with a turning basin at the
head; and 150 feet wide in English Kills, or West Branch, to the
Metropolitan Avenue Bridge, including the easing of bends, and for
a channel 12 feet deep and 100 feet wide in English Kills from the
Metropolitan Avenue Bridge, to within 80 feet of the Montrose Avenue
Bridge, suitably widened at bends and materially widened by excavat-
ing upland at the second bend above the Metropolitan Avenue Bridge.
The total length of channel included in the project is about 5.2 miles.
Mean tidal range, 4.2 feet; mean range of spring tides, 5 feet; irregular
fluctuations due to wind and barometric pressure vary from about 3.5
feet below mean low water up to about 4 feet above mean high water.
   The estimate of cost for new work, revised in 1937, is $1,196,500,
exclusive of amounts expended on previous projects. The latest
(1937) approved estimate for annual cost of maintenance is $22,000.
172           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                        1944

  The existing project was authorized by the following river and
harbor acts:

       Acts                           Work authorized                                   Documents


Mar.     2, 1919     20-foot channel___-    -----------         _-         H. Doc. No. 936, 64th Cong., 1st sess.
July     3,1930      23-foot channel- _-----.----          __        ---   Rivers and Harbors Committee Doc.
                                                                                                       1
                                                                             No. 42, 71st Cong., 2d sess.
Aug. 26,1937         12-foot channel in English Kills___        .__---     Rivers and Harbors Committee Doc.
                                                                                                          1
                                                                             No. 4, 75th Cong., 1st sess.
                     Minor modification of project in the vicinity of
                      Mussel Island, without change in cost, ap-
                      proved by the Secretary of War, Mar. 22, 1920.

  1 Contains       latest published maps.

   Local cooperation.-The River and Harbor Act of March 2, 1919,
requires that all land needed for right-of-way be furnished without
cost to the United States, and provides that no work shall be done
in Maspeth Creek, in the removal of Mussel Island, or in English
Kills until this has been done in each case and corresponding changes
made in existing harbor lines; also that no work shall be undertaken
under the existing project in Dutch Kills until the obstructive bridges
near its mouth have been suitably modified.
   The River and Harbor Act of August 26, 1937, requires that local
interests furnish, free of cost to the United States, necessary ease-
ments or rights-of-way for the enlargement of the channel in English
Kills above Metropolitan Avenue and give assurances satisfactory
to the Secretary of War that they will remove obstructive deposits
resulting from the discharge of sewage into the waterway. That act
also requires that before widening the second bend south of Metro-
politan Avenue local interests shall furnish necessary lands or rights-
of-way and construct a new bulkhead on the widened channel.
   The lands needed' in Maspeth Creek, Mussel Island, and the East
Branch have been ceded to the United States by the city of New York
by deed. The work of modifying the bridges near the mouth of
Dutch Kills was completed in 1923. No action has been taken by the
city authorities to comply with the requirements for dredging in
English Kills (West Branch).
   Terminal facilities.-The length of water front measured along
both sides of the improvement is 11.6 miles, of which 9.6 miles are
bulkheaded and about 2 miles of frontage, distributed over the entire
length of this waterway, is yet undeveloped. There are 5 piers with
a total berthage of 3,062 feet and 44,137 feet of bulkheads and wharves
available for dockage. Of the terminals, 8 are owned by the city of
New York, of which 5 are open to public use; 55 are equipped with
mechanical handling devices, and 23 have railroad connections. The
terminal facilities are considered adequate for present needs. (For
latest full description of terminal facilities see Port and Terminal
Facilities at the Port of New York, 1942, Corps of Engineers.)
   Operationsand results during fiscal year.-The U. S. steam lighter
Rockaway was engaged on December 27, 1943, in the removal of an
obstruction from the channel in Dutch Kills, Newtown Creek, at a cost
of $97.73 for maintenance. The cost of survey to locate the obstruc-
tion was $78.41 for maintenance.
        RIVERS   AND   HARBORS-NEW        YORK,   N.   Y., DISTRICT        173
     The total cost of work was $176.14 for maintenance. The total
expenditure was $499.51.
     Condition at end of fiscal year.-The existing project was about 64
.percent completed. The work of enlarging the main channel to 23-
foot depth and 130-foot width from the entrance to 150 feet north of
Maspeth Avenue, including the triangular area at the entrance, and
a turning basin at the former location of Mussel Island, is about 90
percent completed. Dutch Kills has been dredged to project depth,
20 feet, for a width of 75 to 100 feet except at a few places near the
head of improvement, where unstable bulkheads restricted dredging
  operations. Maspeth Creek has been dredged to project dimensions
  throughout. The controlling mean low water depth in the main
  channel of Newtown Creek, according to a survey made in May 1941,
  was 20 feet for a width of 100 to 130 feet from the entrance to 150
  feet north of Maspeth Avenue. In the turning basin at the former
  location on Mussel Island the depth was 21 feet. When examined in
June 1940, the controlling depth in Dutch Kills was about 14 feet
  except at Hunters Point Avenue Bridge, where it was 11 feet. As
  shown by an examination made in September 1938, the depth in
  Maspeth Creek was 15 feet to a point 400 feet west of the easterly
limit of the project, thence decreasing to zero depth at the easterly
  limit of the project. The controlling mean low water depth in
  East Branch, according to surveys made in October 1929, July 1933,
  and May 1937, was 16 feet from 150 feet north of Maspeth Avenue to
  opposite the entrance to English Kills; thence to Grand Street, 13
  feet; and thence to Metropolitan Avenue, 12 feet. When examined
  in May and August 1941, the depth in English Kills (West Branch)
  to within 1,400 feet of Metropolitan Avenue was 16 feet, 85 to 125
  feet wide, thence 10 feet, 60 to 120 feet wide to within 500 feet of
  Metropolitan Avenue, and thence to 80 feet north of Montrose Avenue
   (the head of the project) the depth was about 8 feet. The work re-
  maining to be done consists of completing to project dimensions: The
  23-foot main channel between Greenpoint and Meeker Avenues, and
  between 800 and 150 feet north of Maspeth Avenue; to 20-foot channel
  in the East Branch; and the 20- and 12-foot channels in English Kills.
     The total cost and expenditures of the existing project to June 30,
  1944 were $922,018.53-$767,093.96 for new work and $154,924.57 for
  maintenance.
     Proposed operations.-No funds are available and no work is con-
  templated during the fiscal year 1945.
     It is expected that the conditions of local cooperation under this
  project will not be complied with during the next 2 years. Mainte-
  nance dredging will be necessary during the fiscal year 1946. The sum
  of $25,000 can be profitably expended during the fiscal year ending
  June 30, 1946, in maintenance dredging, under contract, to restore the
  channel in English Kills to the Metropolitan Avenue Bridge to pre-
  vious project dimensions.
                          Cost and financial summary
Cost of new work to June 30, 1944- -----------------------       $1, 168, 354. 47
Cost of maintenance to June 30, 1944 - --      --       __           322, 794. 03
       Total cost of permanent work to June 30, 1944----------    1, 491, 148. 50
Net total expenditures -----------------------------------        1, 491, 148. 50
Total amount appropriated to June 30, 1944-_               -      1, 491, 14& 50
174             REPORT OF CHIEF OF ENGINEERS,                                         U. S. ARMY,                 1944


     Fiscal year ending June 30                      1940                1941          1942               1943             1944

Cost of new work............                                                                                          -           -...

Cost of maintenance-------------............   ...     ...    ....--------------..    $1,   209.90         $431.11           $176.14
Total expended----.-------------.-----..--------------1, 209. 90                                            107. 74           499. 51
Allotted----------------------.......................... -------------     $25,000----------            21, 664.56
                                                                                                     -----                -1, 518.29


Balance unexpended July 1, 1943__-_     -    -    -      -$2,                                                               017. 80
Deductions on account of revocation of allotment----------- ----                                                         1, 518. 29
      Net amount to be accounted for_-------                                                                ---            499. 51
Gross amount expended ------------------------------------                                                                 499. 51
Amount le ;timated) required to be appropriated for completion of
existing project_------------                         --- _429,                                                           400. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance -----------------------                                                                25, 000. 00

                    16. HUDSON RIVER CHANNEL, NEW YORK HARBOR

   Location.-Hudson River empties into the Upper Bay of New York
Harbor at the Battery, New York City. The section included under
this title extends from deep water, in upper New York Bay to just
north of Harlem River ($puyten Duyvil Creek), a distance of about
14.5 miles. (See U. S. Coast and Geodetic Survey Charts Nos. 274,
745, and 746.)
   Previous projects.-Adopted by River and Harbor Acts of March
3, 1875, June 6, 1900, March 3, 1905, and March 4, 1913. For further
details, see Annual Report for 1915, page 1765, and Annual Report for
1938, page 213.
   Existng project.-This provides for a channel 48 feet deep and
2,000 feet wide, suitably widened at the bends, from West Fifty-ninth
Street, Manhattan, to West Fortieth Street, thence 45 feet deep of the
same width to deep water in Upper Bay; for a channel 40 feet deep
for the full width of the river extending from the north line of
Fifty-ninth Street to the south side of Little Basin, and thence a chan-
nel of the same depth to deep water in the Upper New York Bay off
Ellis Island, substantially as shown on maps in House Document
No. 309, Seventy-second Congress, first session, subject to the pro-
vision that no dredging shall be done under the project within 50 feet
of the pierhead lines; a channel 750 feet wide and 30 feet deep along
the Weehawken-Edgewater water front; the removal of a shoal on
the New York side between West Fifty-ninth and West Sixty-first
Streets to a depth of 40 feet; and the removal of an obstruction
north of the mouth of Spuyten Duyvil Creek to the depth of the
surrounding river bottom. The length of channel included in the
project is about 11 miles. The plane of reference is mean low water.
Mean tidal range at the Battery, 4.4 feet, and at the mouth of Spuyten
Duyvil Creek, 3.7 feet; mean range of spring tides, 5.3 feet and
4.4 feet, respectively; irregular fluctuations due to wind and baro-
metric pressure vary from 4 feet below mean low water at the Battery
up to 4 feet above mean high water, and at the mouth of Spuyten
Duyvil Creek from 3.5 feet below mean low water up to 3.5 feet above
mean high water.
                   RIVERS AND            HARBORS-NEW                  YORK)       N.   Y., DISTRICT                175

  The estimate of cost for new work, revised in 1937, is $6,383,000,
exclusive of the amounts expended on previous projects. The latest
(1937) approved estimate for annual cost of maintenance is $169,000
  The existing project was authorized by the following river and
harbor acts:

       Acts                             Work authorized                                     Documents


Mar.     4, 1913       Channel 30 feet deep from Ellis Island to Newark        H. Doc. No. 719, 62d Cong., 2d sess.
                        St., 40 feet deep through the shoal from Newark
                        St. to Castle Point and channel 26 feet deep and
                        550 feet wide along Weehawken-Edgewater
                        water front. Removal of shoal east side of
                        river between West 19th and West 32d Sts.;
                        removal of rock near the Battery to 40 feet, and
                        removal of obstruction near Spuyten Duyvil
                        Creek.
Mar.     4, 1915       Additional dredging through shoal from Newark           Annual Report, 1914, pp. 234-235.
                        St. to Castle Point.
Aug.     8, 1917       Removal of shoal between West 32d and West              H. Doc. No. 1697, 64th Cong., 2d segs.
                        61st Sts. to 40 feet and widening the 40-foot
                        channel between the Battery and Canal St. to
                        2,000 feet.
Mar.     3, 1925       Channel 30 feet deep and 750 feet wide along            H. Doc. No. 313, 68th Cong., 1st sess.
                        Weehawken-Edgewater water front.
Jan.    21, 1927       Modification of conditions of local cdoperation
                        affecting channel along Weehawken-Edgewater
                         water front.
July     3, 1930       Channel 40 feet deep between pierhead lines from        H. Doc. No. 450, 70th Cong., 2d sess.2
                        20th St., Manhattan, to a point 1,300 feet below
                        Newark St., Hoboken, thence 2,800 feet wide
                        to deep water off Ellis Island. Channel 30 feet
                        deep between 40-foot channel and channel along
                        Jersey City waterfront.
                                                                                                                      2
Aug. 30, 1935      1   Widening the 40-foot channel to full width of           H. Doc. No. 309, 72d Cong., 1st sess.
                        river from north line of 59th St. to south side of
                        Little Basin, thence a channel of same depth to
                        deep water off Ellis Island.
       Do ---          Waiver of all conditions of local cooperation affect-   Rivers and Harbors Committee Docu-
                        ing the channel along the Weehawken-Edge-                ment No. 49, 72d Cong., 2d sess.
                        water water front.
Aug. 26, 1937          Channel 45 and 48 feet deep and 2,000 feet wide--       Senate Committee print, 75th Cong.,
                                                                                          2
                                                                                1st sess.


1 Also Public Works Administration Sept. 6, 1933, and Apr. 27, 1935.
2 Contain latest published maps.


  Terminal facilities.-The length of water front included in the
project for improvement, measured along both shores of the river, is
32 miles; of this length 7 miles of the Manhattan water front and 10
miles of the New Jersey water front have been developed for com-
mercial use. Along the Manhattan water front, there are 96 piers
with a total berthage of 134,947 feet, 4,465 feet of bulkheads and
wharves available for dockage, 12 ferry slips and 6 car-float bridges.
Along the Jersey water front, there are 135 piers having a total berth-
age of 167,760 feet, 23,948 feet of bulkheads and wharves available for
dockage and 7 ferry slips, 11 car-float bridges, 6 small boat repair yards
and 1 large shipyard. Of the terminals, 134 are publicly owned, 27
176     REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,   1944

are open for public use, 159 are equipped with mechanical handling
devices, and 135 have railroad connections. The facilities are ade-
quate for present requirements. (For latest full description of ter-
minal facilities see Port and Terminal Facilities at the Port of New
York, 1942, Corps of Engineers.)
   Operations and results during fiscal year.-Under a contract for
dredging to a depth of 35 feet along the easterly channel line from op-
posite pier 83 to opposite pier 98, Manhattan, N. Y., work was com-
menced December 3, 1943, and was completed December 10, 1943.
During this period 17,620 cubic yards, place measurement, of material
were removed at a cost of $15,717.67 for maintenance.
   The U. S. seagoing hopper dredge Goethals was employed inter-
mittently during the period October 18-27, 1943, in dredging to re-
store a section of the channel along the Weehawken-Edgewater
water front to a depth of 30 feet. During the fiscal year 243,510 cubic
yards, place measurement, of material were removed at a cost of
$21,430.85 for maintenance.
   The U. S. derrick boat N. Y. 34 removed an obstruction off the
Battery, N. Y., on April 15, 1944, at a cost of $891.23 for maintenance.
   The cost of surveys to determine the condition of the 40-foot chan-
nel and the channel along the Weehawken-Edgewater water front
was $2,607.58 for maintenance.
   The total cost of work was $40,647.33 for maintenance. The ex-
penditures were $40,156.46.
   Conditionat end of fiscal year.-About 91 percent of the work under
the existing project has been completed. The work of widening and
deepening Weehawken-Edgewater Channel to project dimensions was
completed in 1937. The work of widening the 40-foot channel for the
full width of the river from Ellis Island to West Fifty-ninth Street,
Manhattan, was completed in 1939. An area 1,400 feet wide extend-
ing along the Manhattan water front from West Fortieth to West
Fifty-fourth Street was deepened to 48 feet in 1939.
   When examined intermittently from 1935 to 1939 the controlling
mean low water depth was 40 feet for the full width of the river from
opposite Ellis Island to West Fifty-ninth Street, except for minor
scattered shoals along the east and west channel lines. From West
Fortieth to West Fifty-fourth Street along the Manhattan water
front, the controlling depth was 48 feet for an area 1,000 feet wide.
   When examined in January, April, and October 1943, and February
1944, the controlling mean low water depth in Weehawken-Edgewater
Channel was 27 feet for a width varying from 650 to 750 feet from
opposite West Fifty-ninth Street to opposite West One Hundred and
Twentieth Street, thence 22 feet for a width varying from 350 to 750
feet to the upper end of the channel.
   The work remaining to be done under the existing project consists
of completing the dredging of the 45- and 48-foot channels for a width
of 2,000 feet from Upper Bay to West Fifty-ninth Street, as author-
ized in 1937.
   The total cost of the existing project to June 30, 1944, was $7,839,-
266.39--$668,820.36 Public Works funds and $5,158.802.95 regular
funds, a total of $5,827,623.31 for new work and $2,011,643.08 for
maintenance. The total expenditure was $7,838.775 52.
              RIVERS AND HARBORS-NEW                                 YORK,       N.    Y., DISTRICT                     177
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $100,289.46, plus $250,000 allotted in July
1944, a total of $350,289.46, will be applied as follows:
Accounts payable June 30, 1944 _ _          ----------                                                             $490. 87
Maintenance: Dredging by use of one United States seagoing hopper
  dredge for 5 months (July 1 to Nov. 30, 1944) to restore the chan-
  nel along, the Weeha\ken-Edgewater waterfront to project di-
   mensions------------------------------------349,798.59
         Total-----------------------                          -             -         -        -- -           350, 289. 46
  Completion of the project is not considered necessary during the
next 2 years. Further maintenance dredging will be necessary dur-
ing the fiscal year 1946. The sum of $200,000 can be profitably
expended for dredging by use of one United States hopper dredge for
about 4 months during the fiscal year ending June 30, 1946, in the
removal of shoals from the existing channels.
                                        Cost and financial summary

Cost of new work to June 30, 1944 _--                                                       _             $5, 897, 252. 43
Cost of maintenance to June 30, 1944_                                                                      2, 011, 643. 0

      Total cost of permanent work to June 30, 1944                                                        7, 908, 895. 51
Minus accounts payable June 30, 1944 -......                                                                       490. 87
      Net total expenditures                            -........                                          7, 908, 404. 64
Unexpended balance June 30, 1944                        -                                                     100, 289. 46

          Total amount appropriated to June 30, 1944_                                                      8, 008, b94. 10

   Fiscal year ending June 30              1940               1941           1941
                                                                             1942                  1943             1944

Cost of new work______ ___                $4, 028. 57----------
Cost of maintenance______ --             121, 765.22     $1,413.56               $517. 88       $34,525.00         $40, 647. 33
      Total cost_...    .   ...     .    125, 793. 79         1, 413. 56          517.88         34, 525. 00        40, 647. 33.
Total expended................           138, 036.41          1, 582.64           517. 88        34, 525. 00        40,156.46

Allotted-__     -____.--.-__..--. 125, 000. 00              -1, 246. 96      31,000.00          -5,511.20      _


Balance unexpended July 1, 1943_ ______---------                                                            $140, 445. 92
Gross amount expended-_________-------------40,                                                                   156. 46
      Balance unexpended June 30, 1944---------------------                                                    100, 289. 46
Outstanding liabilities June 30, 1944_                                                                              490. 87
     Balance available June 30, 1944_                                                                           99, 798. 5%
Amount allotted in July 1944_ _250,                                                                                 000. 00,
          Amount available during fiscal year 1945---------------                                              349, 798. 59
Amount (estimated) required to be appropriated for completion
of existing project 1 -------------------------------------     555,000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance' 1---------------------------200,     000. 00
  1 Exclusive of available funds.

     17. NEW YORK HARBOR-COLLECTION AND REMOVAL OF DRIFT
  Location.-This project applies to the Lower and Upper Bays, New
York Harbor; East River, Harlem River, Hudson River Channel,
N. Y., New York and New Jersey Channels, Newark Bay, N. J., and
their tributaries.
         616634-45-pt. 1, vol. 1-                 12
178           REPORT OF CHIEF OF ENGINEERS,                          U.   S. ARMY,   1944


   Existing project.-This provides for the collection and removal of
drift from New York Harbor and its tributary waters, and authorizes
the Secretary of War to allot such amounts as may be necessary for
the work from appropriations for maintenance and improvement of
existing river and harbor works or other available appropriations, and
that this work shall be carried as a separate and distinct project. It
is wholly a work of maintenance. The purpose of the work is to affbrd
relief from variable conditions of obstruction, and no advance estimate
of the amount of work required and its proper cost can be made.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                               Documents

                  Allotment from appropriations ihade for New
Mar. 4,1915         York Harbor and its immediate tributaries may
Aug.     8,1917    be used for collection and removal of drift in
                   these waterways.
July     3,1930   Carrying on this work as a separate and distinct
                   project.



   Terminal facilities.-Describedin the separate reports covered.
   Operationsand results during fiscal year.-The U. S. steam lighters
Rockaway and N. Y. 20, U. S. motor tenders Astoria and Stanwix,
launches and auxiliary plant were assigned to the work of removing
and disposing of drift. There were removed and disposed of during
the fiscal year 910,617.6 cubic feet (7114.2 cords) of driftwood ranging
in size from small blocks up to timber of large dimensions, including
piles and pieces of wreckage.
   The cost of this work was $313,636.20 for maintenance. The ex-
penditures were $309,878.16.
   Conditionat end of fiscal year.-The existing project is one of con-
tinuous maintenance for which no percentage of completion exists.
Navigation has been made safer by the continued patrol of the harbor
and the removal of large quantities of drift material. The total cost
of operations to June 30, 1944, has been $1,923,697.60. The total ex-
penditures amounted to $1,903,810.52.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $62,140.01, plus $235,000 allotted in July
1944, a total of $297,140.01, will be applied as follows:
Accounts payable June 30, 1944                               ---  $19, 887. 08
Maintenance: Continue the work of drift removal by use of United
  States lighters, motor tenders, and launches (July 1944 to June
  1945) -     --    ----------------------------------------      277,252.93
          Total---------------------------------- -----                        _       297,140.01
  It is necessary for the safety of navigation that the removal of drift
material be carried on regularly. The sum of $250,000 can be profit-
ably expended on this work by the operation of United States light-
ers, motor tenders, and launches during the fiscal year ending June 30,
1946.
                   RIVERS           AND HARBORS-NEW                       YORK,            N.     Y., DISTRICT                179
                                                Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_                                                                          $1,923, 697. 60
      Total cost of permanent work to June 30, 1944---------- 1, 923, 697. 60
Minus accounts payable June 30, 1944-----------------------       19, 887. 08
     Net total expenditures_     _                                   ------------                                , 903, 8,10. 52
Unexpended balance June 30, 1944_ _62,                                                                                  140. 01
              Total amount appropriated to June 30, 1944                                ------------            1, 965, 950. 53

     Fiscal year ending June 30                    1940            1941                  1942           1943              1944

C ost of new w ork .. . . . . . . . . . . . . . ..                                 . . . . . . .. . . . . . . . . .. . . .
Cost of maintenance-                ......      $112, 20. 23    $103 056.97        $149, 305. 71  $201, 826. 80  $313, 636.20

Total expended           ----------------
                          ...       ......       118, 618. 71    102, 494. 53          143, 167. 73   194, 724. 93       309, 878. 16
Allotted _-......................                100, 000.0CO    125,000. 0CO          225, 000. CO   240, 000.00        120, C000.00


Balance unexpended July 1, 1943_                                                                                 $252, 018. 17
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941         --   $10, 973. 40
Amount allotted from War Department Civil Appro-
priation Act approved Apr. 28, 1942_---         109, 026. 60
                                                                                                                     120, 000. 00

       Amount to be accounted for__        _                                                                         372, 018. 17
Gross amount expended_ ___ --------              $311, 827. 98
Less reimbursements collected-------------------    1, 949. 82
                                                                                                                     309, 878. 16
       Balance unexpended June 30, 1944-
Outstfanding liabilities June 30, 1944_
                                                                                -62,                                      140. 01
                                                                                                                      19, 887. 08
      Balance available June 30, 1944                              --                                                 42, 252. 93
Amou nt allotted in July 1944_                                                                              -235,         000. 00
              Amount available during fiscal year 1945---------------                                                277, 252. 93
Amount that can be profitably expended in fiscal year ending
June 30. 1946, for maintenance 1_-____-         -    -______ -                                                      250. 000. 00
   1 Exclusive of available funds.

                                             18. PEEKSKILL HARBOR, N. Y.

   Location.-This harbor is an indentation about 5/ mile long and
11/4 miles wide in the eastern shore of Hudson River, 42 miles above
the Battery, New York City. (See U. S. Coast and Geodetic Survey
Chart No. 282.)
   Existing project.-This provides for a channel 10 feet deep at mean
low water, 100 feet wide, and about 1.8 miles long, extending from deep
water in Hudson River north of the village to deep water south of it,
following generally the contour of the shore, and two turning basins,
200 by 150 feet, of the same depth in front of the lower and center
wharves. Mean tidal range, 2.9 feet; mean range of spring tides, 3.4
feet; extreme range, 7.1 feet; irregular fluctuations are infrequent
and do not materially affect navigation.
   The estimate of cost for new work made in 1896 was $50,000. The
 180           REPORT OF CHIEF OF ENGINEERS, U.                                 S. ARMY,      1944

latest (1928) approved estimate for annual cost of maintenance is
 $4,000.
    The existing project was authorized by the following river and
harbor acts:

        Acts                       Work authorized                                     Documents


June     3,1896                                           ----------
                   Channel 10 feet deep and 100 feet wide....             H. Doc. No. 37, 53d Cong., 3d sess.;
                                                                            Annual Report, 1895, P. 999.
                   Chief of Engineers authorized construction of 2        Annual Report, 1896, p. 839.
                    turning basins.


  For latest published map see Annual Report for 1903, p. 885.

    Terminal facilities.-There are 2,240 feet of bulkheads and wharves
available for berthage at the inshore section of the improvement.
One of the terminals is open to the public; four are equipped with
mechanical handling devices. The existing terminals are considered
adequate for present and prospective needs of commerce.
    Operations and results during fiscal year.-None.
    Conditionat end of fiscal year.-The existing project was completed
in 1899. The controlling depth at mean low water, as shown by an
examination made in April 1942, was 10 feet for full project width in
the north entrance channel, 9 feet for full project width in the south
entrance channel, and 9 feet for a width varying from 60 to 100 feet
in the channel along the wharf fronts.
   The total cost and expenditures of the existing project to June 30,
1944, were $77,932.07-$19,400 for new work and $58,532.07 for main-
tenance.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $15,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore the channel to project dimensions.
                                      Cost and financial summary
Cost of new work to June 30, 1944---------------------------
Cost of maintenance to June 30, 1944_ -----------        _58,
                                                                                                $19, 400. 00
                                                                                                         532.   7OT
          Total cost of permanent work to June 30, 1944-------                                    77, 932. 07
Net total expenditures                           -        --_           -----           _         77, 932. 07
                                         --------------- _77,
Total amount appropriated to June 30, 1944_                                                           932. 07
Amount that can be profitably expended in fiscal year ending June 30,
1946, for maintenance_ _        ___----------                ___                                 15, 000. 00

                                  19. RONDOUT HARBOR, N. Y.

  Location.-This harbor comprises the tidal mouth, about 1.8 miles
in length, of Rondout Creek, whose source is about 18 miles west of
Rondout. The creek empties into the Hudson River from the west,
_bout 89 miles north of the Battery, New York City, and 55 miles
                RIVERS AND         HARBORS-NEW                 YORK, N.         Y.,   DISTRICT             181
south of Albany. (See U. S. Coast and Geodetic Survey Chart No.
283.)
   Existing project.-This provides for a channel 100 feet wide, widen-
ing at the bends, and 14 feet deep from deep water in Hudson River
to the highway bridge, 1.3 miles above the mouth, thence 12 feet deep
to the west end of Island dock, 1.8 miles above the mouth, two parallel
dikes 350 feet apart, to maintain the channel, and for a branch dike
to extend upstream from the outer end of the north dike to protect
that dike from running ice in Hudson River.
   Mean tidal range, 3.6 feet; mean range of spring tides, 4.1 feet;
extreme range, 8.2 feet; irregular fluctuations due to freshets are
infrequent and do not materially affect navigation.
   The estimate of cost for new work, revised in 1935, was $105,000.
The latest (1935) approved estimate for annual cost of maintenance
is $5,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                     Documents


June 10, 1872    Parallel dikes, branch dike, and entrance channel      S. Ex. Doc. No. 35, 42d Cong., 2d sess.;
                   14 feet deep.                                          Annual Reports, 1872, p. 810.
Aug. 30,1935     Extension of the 14-foot channel and for the 12-foot   Rivers and Harbors Committee Doc.
                  channel.                                                No. 17, 73d Cong., 2d sess. (Con-
                                                                          tains latest published map.)



   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are 17 timber wharves with a total avail-
able dockage of 10,930 feet located along the section of the waterway
under improvement. Of the terminals, 1 with available dockage of
550 feet is open to the public. Some of the terminals are equipped
with transfer facilities; all are privately owned. The existing termi-
nals appear to be adequate for present needs of commerce. (For latest
full description of terminal facilities, see Port Series No. 25, 1936,
Corps of Engineers.)
   Operations and results during fiscal year.-The cost and expendi-
tures for a survey to determine the condition of the channel and dikes
were $597.47 for maintenance.
   Condition at end of fiscal year.-The existing project was substan-
tially completed in 1938; part of the diking originally proposed was
not built because deemed of doubtful usefulness. Two parallel dikes
of an aggregate length of about 5,000 feet, generally 350 feet apart,
with a now obsolete spur from the old lighthouse south of the south
dike, have been built across the bar at the mouth of the creek. A
branch dike about 1,000 feet long extending northerly from the outer
end of the north dike was also constructed. The project channel was
completed in 1938. When examined in May 1944 the controlling
depth at mean low water, from the Hudson River to the west end of
Island dock, was 14 feet for a width of 100 feet, for a distance of 1.25
miles, thence 12 feet for a width of 100 feet to the head of the project,
except for shoals opposite the Texas Co. plant where the channel is
182            REPORT OF CHIEF OF ENGINEERS,                                                             U.    S. ARMY,                    1944

restricted to a width of 50 feet with an available depth of 14 feet,
and opposite the C. Hiltebrant Shipyard Drydock where the channel
is restricted to a width of 70 feet with an available depth of 12 feet.
   The total cost and expenditures of the existing project to June 30,
1944, were $307,392.31-$123,108.63 for new work and $184,283.68 for
maintenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $5,493.02, plus an allotment of $11,000 made
in July, a total of $16,493.02, will be applied to the repair of the
Branch, North and South Dikes by use of Government plant and
hired labor, July 1944 to June 1945.
   Further repairs to dikes will be necessary during the fiscal year
1946. Therefore, the sum of $5,000 can be profitably experided during
the fiscal year ending June 30, 1946, in the repair of dikes where
necessary.
                                                            Cost and financial summary
Cost of-new work to June 30, 1944 -----------------------------                                                                              $123, 108. 63
Cost of maintenance to June 30, 1944_-----            --     ___                                                                              184, 283. 68
           Total cost of permanent work to June 30, 1944_                                                                                         307, 392. 31

Net total expenditures_-------                                                                     -      -                 -____                 307, 392. 31
Unexpended balance June 30, 1944.--
                                 .                                                          --------                            -'                  5,493. 02
           Total amount appropriated to June 30, 1944                                                     --------                                312, 885. 33

   Fiscal year ending June 30                                     1940                     1941            1942                   1943                  1944

Cost of new work-            -   -   -   -   -   - -   --    -    -   - -   -. -   -   - - - - .       --. -. - . .         - -   -   -     ..     .. . . .. .
Cost of maintenance   ..........                                 $4, 726. 46           $7, 719. 06        $3, 272. 11                                   - $597. 47
Total expended -----------------                                  4,029.06                 5,636.47        6,003. 71                      $2.65            597.47

Allotted   -----------------------                                5, 000.00                8,000.00        3,500.00     I.-----------                 $        .

Balance unexpended July 1, 1943                                                                                                                    $6, 090. 49
Gross amount expended --------------------------------------                                                                                           597.47
     Balance unexpended June 30, 1944-----------------------
Amount allotted in July, 1944-                                                 -                                        -    _
                                                                                                                                                    5493.
                                                                                                                                                    5,      02
                                                                                                                                                   11, 000. 00

           Amount available during fiscal year 1945                                                    -----------                                 16, 493. 02
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1                                                                                                                         5,000. 00'
  1Exclusive of availablefunds.

                                                       20. HUDSON RIVER, N. Y.

   Location.-This river has its source in the Adirondack Mountains,
about 250 miles in a direct line and 315 miles along its course from
the Battery, New York City, and flows in a generally southerly direc-
tion into New York Bay. The section under improvement extends
from New York City to Waterford, a distance of about 156 miles.
 (See U. S. Coast and Geodetic Survey Charts Nos. 281 to 284,
inclusive.)
         RIVERS    AND HARBORS-NEW           YORK,         N.   Y.,   DISTRICT       183
   Previous projects.-The original project for improvement by the
United States was adopted by River and Harbor Act of June 30, 1834,
and modified in 1852 and 1866.
   A second project was adopted by River and Harbor Act of July 13,
1892, and modified in 1899. For further details see page 1764, Annual
Report for 1915, and page 226, Annual Report for 1938.
   Existi'ng project.-This provides for a channel 27 feet deep at mean
low water and 300 feet wide up to Hudson; thence of same depth and
400 feet wide through rock cuts and 300 feet wide elsewhere, from
Hudson to the site of the former Albany-Greenbush Bridge at Albany;
thence 14 feet deep at lowest low water and generally 400 feet wide to
the Federal lock at Troy; and thence of same depth and 200 feet wide
to the southern limit of the State barge canal at Waterford; with
widening at bends and in front of the cities of Troy and Albany to
form harbors 12 feet deep at lowest low water; and removal of State
dam at Troy and the construction of a lock and dam about 21/2 miles
below Waterford.
   The channel is to be formed by dredging and rock excavation, and
to be maintained by dredging and by constructing new, and raising
and repairing old, longitudinal dikes, built partly under previous proj-
ects and partly by the State of New York. The mean range of pool
elevation above the Federal dam at Troy, in seasons of moderate
rains is about 2.2 feet, as determined in 1934. The mean tidal range
as determined in 1936 is about 4.7 feet at the Federal dam at Troy
and about 4.6 feet at Albany. The mean range during the summer
months is about 4.7 feet.
   The normal pool level above the Federal dam from Troy to Water-
ford is 14.33 feet above meanr. sea level at Sandy Hook, N. J. In the
tidal section of the river below the dam the assumed lowest low-water
plane from Troy to Albany is 3 feet below mean sea level at Sandy
Hook, N. J.
   The following table contains information concerning the various
features of the lock and dam included in the existing project:
Location:
    Below Waterford     --------------------------------                  miles_      2. 2
    Above Battery, New York City                                          do        153.8
Lock:
    Clear width                                ---------                   feet     44.44
     Greatest lengtl available for full width----------------             do --- 492. .5
     Lift at lowest stages --------------------                           do    . 17. 3
     Depth on miter sills:
          Upper (at normal pool level) -------------                      do    .    16. 3
          Lower (at lowest low water) -----                               do --      13.0
Character of foundation: Rock.
Kind of dam: Fixed.
Type of construction: Concrete.
Completed: 1917.
Cost: $1,463,014.07.
   The estimated cost for new work, revised in 1938, is $17,168,000,
exclusive of amounts expended on previous projects. The latest
 (1930) approved estimate for annual cost of maintenance is $337,300,
including $21,300 for operation and care of the lock and dam.
184          REPORT OF CiIEF OF ENGINEERS,                              U. S. ARMY,          1944

  The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                    Documents 1


June 25,1910      Channel 12 feet deep from Hudson to Waterford,        H. Doc. No. 719, 61st Cong., 2d sess.
                   removal of State lock and dam at Troy and con-
                   struction of a new lock and dam.
Mar.    3,1925    Channel 27 feet deep from Hudson to Albany....        H. Doc. No. 350, 68th Cong., 1st sess.
July    3, 1930   Channel 27 feet deep b6low Hudson    - ------
                                                              _         H. Doc. No. 210, 70th Cong., 1st sess.
       (2)        Operation and care of lock and dam at Troy were
                   included in project July 1, 1935.
Aug. 30,19353     Relocation of the 12-foot channel between Troy        S. Doc. No. 155, 72d Cong., 2d sess.
                   and Waterford.
June 20,1938      Deepening channel between Albany and Water-           H. Doc.No. 572, 75th Cong., 3d sess.
                   ford to 14 feet, with no change in depths for har-
                   bors in fiont of Albany and Troy.


  1 These documents contain latest published maps.
  2 Permanent Appropriations Repeal Act approved June 26, 1934.
    P. W. A., Sept. 6, 1933.


   Local cooperation.-Fullycomplied with.
   Terminal facilities.-The piers and other terminal or transfer facil-
ities served by the improvement are as follows:
   Between Waterford and the Federal dam at Troy there are 14
wharves aggregating approximately 5,000 feet in length. The State
of New York has constructed a barge-canal terminal at Cohoes.
There is a dock 325 feet long on the west side of the river just north
of the Federal dam.
   At Troy there are 10 terminals with available dockage of 2,395 feet,
including the State barge-canal terminal with 960 feet. In addition,
11/4 miles of concrete bulkhead were constructed along the water front
by the city of Troy. At Watervliet there is a stone bulkhead 800 feet
long. Between this point and Albany there are 5 timber wharves
aggregating 4,275 feet in length.
   At Albany and Rensselaer, on the east side of the river, there are
28 terminals aggregating 18,037 feet of available berthage, including
a city-owned recreation pier of 900 feet and the State barge-canal
terminal with 1,550 feet located on the west side of the river. These
terminals are adequately served with railroad trackage. There are 4
transit sheds, 1 warehouse, a 13,500,000-bushel grain elevator, and a
molasses-storage plant, all provided by the Albany Port District
Commission.
   Between Albany and Hudson there are about 100 timber wharves
aggregating 36,700 feet in length; at Hudson there are 12 timber
wharves aggregating 5,000 feet in length; at Athens there are 9 tim-
ber wharves aggregating 4,000 feet in length.
   Between Hudson and the upper limits of New York City the entire
water fronts of Poughkeepsie, Newburgh, and Yonkers are equipped
with transfer facilities.     At Poughkeepsie there are 13 terminals
with available dockage of 3,153 feet, including a city-owned pier of
270 feet. At Newburgh there are 16 terminals with a total dockage
of 8,034 feet, of which 3 with 1,124 feet of dockage are open to the
public. At Yonkers there are 24 terminals with dockage of 8,378
feet, of which 816 feet are for public use.
        RIVERS   AND HARBORS-NEW       YORK,   N.   Y., DISTRICT   185
   The existing wharves are ample for Hudson River traffic. (For
latest full description of terminal facilities see Port Series No. 25,
1936, Corps of Engineers.)
   Operations and results during fiscal year.--Under a contract for
dredging to a depth of 27 feet south of Houghtailing Island, work
was commenced July 2, 1943, and was completed October 9, 1943.
During the fiscal year 65,842.9 cubic yards, place measurement, of
material were removed at a cost of $33,472.27 for maintenahce.
   Work of maintenance dredging and driving of piles by Govern-
ment plant and hired labor at the entrance to the Troy Lock was
commenced June 19, 1943, and was completed July 8, 1943. During
the fiscal year 340 linear feet of piles were driven. A minus adjust-
ment of 121 cubic yards, place measurement, of material was made
in the amount reported for the previous fiscal year. The cost of work
was $1,532.43 for maintenance.
   By use of Government plant and hired labor, repairs were made to
Bath Dike, Schodack Dike (New York State paved section), Ford-
ham Point Dike, Overslaugh No. 1 Dike, Overslaugh No. 2 Dike and
Hillhouse Island Revetment. The cost of this work was $33,725.55
for maintenance.
   Work of establishing a mooring system for two sunken scows at
New Baltimore, N. Y., was commenced November 29, 1943, and was
completed December 4, 1943. The cost of this work was $438.56 for
maintenance.
   By use of Government plant and hired labor, snags and stumps
which formed a potential menace to navigation were removed from
the shores of the river at a cost of $2,727.06 for maintenance.
   The lock and dam in the Hudson River at Troy, N. Y., was operated
and maintained during the fiscal year. Operations of the lock for
the 1943 navigation season were suspended December 11, 1943, and
resumed March 23, 1944, for the 1944 season.. The cost of work during
the fiscal year was as follows: Operations $39,691.85, ordinary main-
tenance and repairs $8,957.05, a total of $48,648.90.
   The cost of engineering, surveys, and contingencies was $29,564.04,
all for maintenance.
   The total cost of work was $150,108.81--$101,459.91 for maintenance,
and $48,648.90 for operation and care of the lock and dam. The total
expenditure was $149,740.46.
   Condition at end of fiscal. year.-About 91 percent of the existing
project has been completed. The construction of new lock and dam
at Troy, removal of old dam at Troy, and construction of 16,545
linear feet of new dikes have been completed. In the reconstruction
of old dikes, 39,672 linear feet have been raised to the adopted crest
height. The channel from Albany to Troy has been completed to
a depth of 12 feet, with the exception 6f a small part of the widening
to form harbors at Albany and Troy, which work is not deemed neces-
sary for the present. About 4.1 miles of the channel between Albany
and Troy remain to be deepened to 14 feet. The channel from
Troy to Waterford has been completed to a depth of 14 feet. The
work of deepening the channel south of Albany to 27 feet mean low
water has been completed with the exception of about 1,500 linear
feet at the northern end.
   The controlling mean low water depth from New York City to Al-
bany, N. Y., is 27 feet through a navigable channel 300 to 400 feet in
186             REPORT OF CHIEF OF ENGINEERS,                                            U.     S. ARMY,            1944

width, except in the vicinity of Coxsackie Island, where a shoal having
a least depth of 26.6 feet extends across the channel, and in the vicini-
ties of Priming Hook, Fordham Point, Bronks Island, where the
channel is restricted to a width of 200 feet. The controlling lowest
low water depth from Albany to the lock and dam at Troy is 11 feet
through a channel varying in width from 400 feet at Albany to 100
feet near the south entrance to the lock at Troy, except at Congress
Street Bridge where the channel is restricted to a width of 50 feet with
an available depth of 14 feet. At the lock entrance it is 14 feet deep
for a width of 45 feet. The controlling pool level depth in the channel
above the lock at Troy to Waterford, the head of the improvement, is
14 feet for a width of about 200 feet.
   The work remaining to be done under the existing project consists
of completing the deepening of the channel from Albany to Water-
ford to 14 feet, completing the widening of the harbors in front of
Troy and Albany to a depth of 12 feet, the construction and reconstruc-
tion of dikes, and completing the deepening of the 27-foot channel
from New York City to the site of the former Albany-Greenbush
Bridge.
   The total costs under the existing project to June 30, 1944, were as
follows:

                                                            New work           Maintenance              care and
                                                                                                    Operating                Total


Regular funds- _     ......              _ _ _ _ _ _ _.   $14, 706, 125. 64    $3, 800, 924. 56          $383, 688. 42   $18, 890, 738. 62
Public works funds        ...  -------------------             238, 350.00- .._.-   ......      ...-..-.....                  238, 350. 00
Emergency relief funds ........              ......            311, 461. 08                                                   311, 461. 08

      Total...............-........                   .    15, 255, 936. 72      3, 800, 924. 56         383, 688. 42     19, 440. 549. 70


   The total expenditure under the existing project to June 30, 1944,
was $19,427,855.25-$18,878,044.17 regular funds; $238,350 Public
Works funds; and $311,461.08 Emergency Relief funds. In addi-
tion the sum of $454,272.93 was expended between August 18, 1915,
and June 30, 1935, on the operation and care of the works of improve-
mant under the provisions of the permanent indefinite appropriation
for such purposes.
   Proposed oprations.-The balance unexpended at the end of the
fiscal year, amounting to $91,276.33, plus $150,000 allotted in July
1944, a total of $241,276.33, will be applied as follows:
Accounts payable June 30, 1944-----------------------------                        $12, 694. 45
Maintenance:
   Complete by Dec. 30, 1945, under a contract to be entered into,
      dredging to remove shoals from 27-foot channel between Hud-
      son and Albany_--------                               - -          -___       88, 000.00
   Operate U. S. derrick boat No. 1 with attendant plant for about
      6 months on the removal of isolated shoals in channel between
      Waterford and Hudson, and removing from the shores stumps
      and snags which are likely to be carried into the channel (July
      1944 to June 1945)_ __________________________________                        23,000. 00
   Operate Government-owned plant consisting of pile driver, der-
      rick boat, etc., in repairing dikes where found to be most
      urgently needed (July 1944 to June 1945)                  ____ _ __ _ _ __ _  40, 000. 00
    Miscellaneous surveys, sweepings, and current observations per-
      taining to maintenance operations (July 1944 to June 1945)--                  30, 000. 00
   Operate, maintain, and repair lock and dam at Troy, N. Y., dur-
      ing the fiscal year-                                                          47, 581. 88
                 Total---..---------------------------                                                                   241, 276. 33
                 RIVERS AND HARBORS-NEW YORK, N. Y., DISTRICT                                                                          187
   The new work remaining for deepening of the channel between
Albany and Waterford to 14 feet has been suspended for the dura-
tion of the war. Completion of the 27-foot channel and the widening
of the harbors in front of Troy and Albany to a depth of 12 feet are
not considered necessary at this time. It is important that full proj-
ect dimensions be maintained in the channel south of Albany and in
the completed portions of the channel between Albany and Water-
ford, that the dikes be kept in a proper state of repair and that the
operation and care of the lock and dam at Troy be continued. There-
fore, the sum of $200,000 can be profitably expended during the fiscal
year ending June 30, 1946, as follows:
Complete by Sept. 30, 1946, under a contract to be entered into, removal
  of shoals in 27-foot channel between Hudson and Albany                 $65, 000
Operate 1 United States derrick boat with attendant plant for about
  6 months during fiscal year in removing isolated shoals between Hudson
  and Waterford and removing from shores stumps and snags which are
  likely to be carried into the river                        ----         25, 000
Operate Government-owned plant consisting of pile driver, derrick boat,
  etc., during the fiscal year in repairing dikes where found to be most
    urgently needed -                  _                           -     -                                                         30, 000
Miscellaneous surveys, sweepings, and current observations pertaining to
maintenance operations during the fiscal year              - -                                                                   30, 000
Operate, maintain, and repair lock and dam at Troy, N. Y., during the
fiscal year-----------------------------------------------------                                                                 50, 000
       Total_---------------------------------------------------- 200, 000
                            Cost and financial summary
Cost of new work to June 30, 1944_                         - $20, 368, 530. 22
Cost of maintenance to June 30, 1944_------            -_      4, 985, 682. 99
      Total cost of permanent work to June 30, 1944                                           ---                        25, 354, 213. 21
Minus accounts payable June 30, 1944_--      ----------                                                                       12, 694.45
      Net total expenditures_--- -----------                                                                          25, 341, 518. 76
Unexpended balance June 30, 1944_-    - ----------                                                                         91, 276. 33
            Total amount appropriated to June 30, 1944                                    -----------                    25, 432, 795. 09
     Fiscal year ending June 20                           1940               1941           1942                  1943             1944


Cost of new work- ...__.....               .        .   $65, 255.16     $469, 758. 67    $985, 539. 71       $592, 594.12-.
Cost of maintenance ......
                        -                      ..       400, 794. 50     245, 821.86      197, 754. 40        155, 592. 40        150, 108. 81
        Total cost-         ...    -....                466, 049. 66     715, 580. 53   1,183, 294.11           748,186. 52       150,108.81

Total expended-----..--------...                        457, 8C6. 54     671, 351.86    1,149, 796.94           861,480. 09       149, 740. 46
Allotted------ -----.---.- _...945,                          672. 25     785, 000. 00     223, 000. 00       -170, 000. 00      -120, 000. 00

Balance unexpended July 1, 1943_---------                                                                ----                $361, 016. 79
Deductions on account of revocation of allotment                                        ---------------                       120, 000. 00
       Net amount to be accounted for_    -------        ___                                                                  241, 016. 79
Gross amount expended                              $155, 550. 46
Less reimbursements collected --------------------    5, 810. 00
                                                                                                                              149, 740. 46

      Balance unexpended June 30, 1944 ----------------------                                                                  91, 276. 33
Outstanding liabilities June 30, 1944_------        - -__                                                                      12, 694. 45
     Balance available June 30, 1944                                                                                           78, 581. 88
Amount allotted in July 1944_-------------                                                                               -    150, 000. 00
     Amount available during fiscal year -228, 1945--                                                    -                         581. 88
Amount (estimated) required to be appropriated for completion of
existing project 1                                               1, 458, 000. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance 1_                                        ___-----____                                           200, 000. 00
1 Exclusive of available funds.
188     REPORT OF CHIEF OF ENGINEERS,         U.   S.   ARMY,   1944

21. GREAT LAKES TO HUDSON RIVER WATERWAY-ENLARGEMENT                   OF
                NEW YORK STATE BARGE CANAL

    Location.-This waterway consists of that portion of the New York
State Barge Canal system extending from the Hudson River at Water-
ford to Oswego Harbor on Lake Ontario. (See U. S. Lake Survey
Charts Nos. 182, 183, 184, and 185:)
    Existing project.-This provides for the allotment of Federal funds
to the State of New York for expenditure under suitable Federal
control and supervision in the improvement of the canal connecting
Lake Ontario with the Hudson River. The improvement includes
deepening between locks to 14 feet below normal pool levels, widening
at bends and elsewhere, and increasing the overhead clearance to 20
feet at maximum navigable stage at bridges and other overhead struc-
tures. The widths of channel to be provided under the project are
104 feet in earth cuts, 120 feet in rock cuts, 200 feet in river sections,
with widening at bends and elsewhere as may be necessary.
    The length of the waterway included in the project is about 184
miles, of which 160 miles are in the Erie Canal from Waterford to
Three Rivers Point and 24 miles are in the Oswego Canal from three
Rivers Point to Oswego.
    The estimated cost for new work, made in 1933, is $27,000,000. The
project document provides that the total amount to be allotted shall
not exceed $27,000,000 and that not to exceed $3,285,000 shall be ex-
pended on bridges and other overhead structures. No estimate of
maintenance with Federal funds is included, as mainfenance of the
canal is not a part of the Federal project.
    The existing project was authorized May 28, 1935, under the Emer-
gency Relief Appropriation Act of 1935, and by the River and Har-
bor Act approved August 30, 1935 (Rivers and Harbors Committee
Doc. No. 20, 73d Cong., 2d sess.), which document contains the latest
published map.
  . Recommended modifications of project.-Modification of the exist-
ing project for Great Lakes-Hudson River Waterway was recom-
mended by the Chief of Engineers in a report requested by Rivers and
Harbors Committee resolution adopted May 1, 1940, and transmitted
to Congress by the Secretary of War June 15, 1942.
    Local cooperation.-Fullycomplied with.
    Terminal facilities.-The State of New York has provided termi-
nal and transfer facilities at all important points along the Erie and
Oswego Canals, and at Buffalo, Troy,. Albany, and New York Harbor.
The freight-handling equipment, as well as the storage and dock
facilities, are governed by the requirements of the particular locality.
The State-owned terminal at Oswego is equipped with a grain elevator
of 1,000,000 bushels capacity. The Albany Port District Commission
has erected a grain elevator of 13,500,000 bushels capacity at Albany.
The State grain elevator in New York Harbor on Gowanus Bay has a
capacity of 2,000,009 bushels.
    Terminals at Buffalo, Rochester, Syracuse, Schenectady, Troy, Al-
bany, and Oswego are provided with direct railroad connections. All
State-owned terminals are open to the public on equal terms. Lake-
port terminals are extensive in character. The available terminals
appear ample to meet all requirements.
             RIVERS      AND HARBORS-NEW                       YORK,     N.       Y., DISTRICT               189
   Operations and results during fiscal year.-The following new work
was done by contract:
  Raising bridge E-3 at Saratoga Avenue, Waterford, N. Y. Work
was commenced April 13, 1942, and was completed April 14, 1943. The
total cost of raising the bridge under the contract was $70,922.01. An
adjustment of minus $2,822.06 was made during the fiscal year in the
costs previously reported.
  Raising Delaware & Hudson Railroad bridge E-4 at Waterford.
Work was commenced June 17, 1941, and construction work was com-
pleted September 1, 1942. Maintenance of new embankment was com-
plted September 1, 1943. The total cost of raising the bridge under
the contract was $157,331.95. The cost during the fiscal year was
$8,618.30.
  Raising New York Central Railroad bridge E-56 west of Rome.
Work was commenced August 14, 1941, and was 12 percent completed,
at the end of the fiscal year. Work was suspended as of October 16,
1941, for the duration of the war by order of the War Production
Board. The total cost of raising the bridge at the close of the fiscal
year was $21,724.77. An adjustment of minus $1,176 was made during
the fiscal year in the costs previously reported.
  The total cost of work was $4,620.24 for new work. The expenditures
were $65,356.32.
  Condition at end of fiscal year.-The existing project was about
78 percent completed. The status of the channel deepening and wid-
ening is as follows:

                                                                                        Distance (miles)


                                                                                   Corn-      Work remaining to
                From-                                    To-                       pleted         be done
                                                                                     to
                                                                                  project     Work in      Future
                                                                                   depth      progress      work


                   -Guard                                                                                      0.2
Hudson River_
Guard gate 2 at Waterford - ---
Lock 10 at Cranesville . ........
                                           Lock 10 at Cranesville--
                                           Lock 16 at Mindenville ..--
                                                                       ---
                                                 gate 2 at Waterford .--              2.6
                                                                                     32. 2
                                                                                     36. 1
                                                                                              ----------
                                                                                              .....
                                                                                              ......
Lock 16 at Mindenville-                    Guard gate 5 at Herkimer....              15.5      ........         .7
Guard gate 5 at Herkimer ...------------   Oswego Harbor -----------------           96. 7-
      Total (184 miles) ..---------.........----------------------------------.     183.1 ........                  9



   Thirty-five Barge Canal bridges have been raised to project clear-
ance with Federal funds under this improvement. Three additional
bridges were raised, four were removed, and two were removed and
replaced by new structures at project clearance; all by other agencies.
   The present depth is 14 feet at normal pool levels for the follow-
ing widths: 75 feet in earth cuts, 94 feet in rock cuts, and 200 feet in
canalized rivers and lakes. The 29 locks, 22 in Erie Canal east of
Three Rivers Point, and 7 in Oswego Canal, north of Three Rivers
Point, have a clear width of 45 feet, usable length of 300 feet, and
depth over miter sills of 12 feet. Numerous fixed bridges, transmis-
sion lines, and other structures span the waterways. There are 67
bridges between Waterford and Three Rivers Point and 13 between
Three Rivers Point and Oswego. The minimum clearance under
existing bridges and other overhead structures is 14.66 feet above
maximum navigable stage.
190            REPORT OF CHIEF OF ENGINEERS,                                            TU.S. ARMY,                  1944

   The work remaining to be done to complete the project consists
of widening and deepening the channel by excavation, including the
removal of ledge rock and work incidental thereto, for a total distance
of 0.9 miles, as described in the above table, the raising of 23 Barge
Canal bridges, the lengthening of 1 bridge, and the raising of 7 guard
gates, and the revetment of banks with quarry stone where necessary.
   The total cost and expenditures of the existing project to June 30,
1944, were $20,979,507.46 for new work-$16,166,107.30 from regular
funds and $4,813,400.16 from Emergency Relief funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $5,792.70, will be applied to work preliminary
to future bridge and guard gates raising and bank revetment
contracts.
   Completion of the existing project is not considered necessary dur-
ing the next 2 years. Therefore, no funds can be profitably expended
during the fiscal year ending June 30, 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944_ _                                         -               _         _        $20, 979, 507. 46
Cost of maintenance to June 30, 1944
            Total cost of permanent work to June 30, 1944--------- 20, 979, 507. 46

Net total expenditures ---------------                                                                 -_            20,979, 507. 46
Unexpended balance June 30, 1944_--                                              ---------                                5, 792. 70

            Total amount appropriated to June 30, 1944-----------                                                    20, 985, 300. 16


    Fiscal year ending June 30                      1940              1941                1942                1943            1944

Cost of new work             ....      -   -   $3, 237,037.05 $1,426,014.44 $939, 306.98                   $183,893.61        $4, 620.24
Cost ofmaintenance__ ....--
Total expended........--------------....       3, 874, 750. 64   1, 477, 319. 20     1, 146, 818. 93       249, 861. 81       65, 356. 32
                                    468, 087.46 700, 000.00
Allotted-------... -----------...---...............                                    269, 000.00 -1,201,100.00             -96,000.00


Balance unexpended July 1, 1943_ -------       --------                                                                $167, 149.02
Deductions on account of revocation of allotment                                                   -                     96, 000. 00
      Net amount to be accounted for_-_ _---------71,                                                                          149. 02
Gross amount expended ------------------------------------                                                                65, 356. 32

            Balance unexpended June 30, 1944--------------------                                                            5, 792. 70

Amount (estimated) required to be appropriated for completion
of existing project 1        --------------             _                                                            6,014, 699. 84
  1 Exclusive of available funds.


                   22. NARROWS OF LAKE CHAMPLAIN, N. Y. AND VT.

  Location.-This waterway, 37 miles long, comprises the southern
end of Lake Champlain and extends from Whitehall to Crown Point,
N. Y. The portion included in the project extends from Whitehall,
N. Y., at the southern extremity of the lake, northerly to Benson
Landing, Vt., a distance of 13.5 miles. (See U. S. Lake Survey Chart
No. 174.)
             RIVERS        AND HARBORS-NEW                        YORK,       N.    Y.,   DISTRICT             191

   Previous projects.&-Adopted by River and Harbor Acts of July
4, 1836, March 3, 1837, July 7, 1838, August 5, 1886, July 13, 1892,
and March 3, 1899. For further details, see page 256, Annual Report
for 1932.
   Existing project.-This provides for a channel extending from
Whitehall, N. Y., at the head of Lake Champlain, to Benson Landing,
to be 12 feet deep at low lake level and generally 200 feet wide, and
the installation of fender booms at Putts Rock, Putts Leap, Narrows
near Dresden, Pulpit Point, and Cedar Mountain. The reference plane
of low lake level is 92.5 feet above mean sea level at Sandy Hook, N. J.
The length of the section included in the project for improvement is
about 13.5 miles. The usual annual variation of the lake level is from
4 to 5 feet, and the extreme variation varies from 0.6 feet below up to
8.8 feet above the low lake level.
   The estimate of cost for new work, revised in 1928, is $1,196,000,
exclusive of amounts expended on previous projects. The latest (1918)
approved estimate for annual cost of maintenance is $5,000.
   The existing project was adopted by the River and Harbor Act of
August 8, 1917 (H. Doc. No. 1387, 62d Cong., 3d sess.). The latest
published map is in the project document.
   Terminal facilities.-Terminal facilities are located in Whitehall
Harbor and consist of three timber wharves, aggregating 4,200 feet in
length. The State of New York has constructed a barge canal ter-
minal at Whitehall, just south of the terminus of the canal, which
has been equipped with a 15-ton hand-operated derrick and a store-
house. The facilities are considered adequate for present commerce,
   Operationsand results during fiscal year.-The fender booms at the
Elbow, opposite the Delaware & Hudson Railroad trestle, at Putts
Leap- and at Putts Rock were repaired at a cost of $119.26, and the
automatic recording gage at Fort Montgomery, Rouses Point, N. Y.,,
was maintained at a cost of $690.01, a total cost of $809.30, for main-
tenance. The total expenditure was $779.23.
   Condition at end of fiscal year.-The existing project was about 47
percent completed. A channel 12 feet deep at low lake level and
least width of 150 feet has been excavated throughout the length of
the improvement, except at the Elbow, where the width is 110 feet.
Fender booms have been placed at the Elbow (Putts Leap) and op-
posite the Delaware & Hudson Railroad Co.'s coal trestle. No fender
booms appear to be needed at the Narrows near Dresden, Pulpit Point,
and Cedar Mountain. The controlling depths at low lake level, as
disclosed by surveys made in September and October 1940, through the
reach included in the project, were as follows:

                                           Locality                                                 Depth    Width

                                                                                                     Feet     Feet
Whitehall to the Elbow---   -------------------------------------------------                           12    140-300
At the Elbow-                                                                                           12        110
From the Elbow to Maple Bend                           -----------------                      -
                                                                                       _.._._.---       12    100-150
From Maple Bend to Red Rock Bay .............                                 . ------        _         12        150
From Red Rock Bay to Benson Landing -..................                                   .__           12        140
192            REPORT OF CHIEF OF ENGINEERS,                                U. S. ARMY,                  1944

   The work remaining to be done to complete the project consists
in widening the channel throughout its length to the project width
of 200 feet.
   The total cost of the existing project to June 30, 1944, was $738,-
748.42-$566,811.14 for new work and $171,937.28 for maintenance.
The total expenditure was $738,690.66.
   Proposed operations. The balance unexpended at the end of the
fiscal year, amounting to $201.28, plus an allotment of $1,000 made
in July, a total of $1,201.28, will be applied as follows:
Accounts payable June 30, 1944____---
                                   _-                                 -$57. 76
Maintenance: Repair and care of fender booms at the Elbow, opposite
  the Delaware & Hudson Railroad trestle, at Putts Leap and at Putts
  Rock during the working season (July 1944-June 1945)               1, 143. 52
           Total----------------------------------------------1,                                                        201. 28
  Neither completion of the project nor maintenance work will be
necessary during the fiscal year 1946. Therefore, no funds can be
profitably expended during the fiscal year ending June 30, 1946.
                                              Cost and financial summary
Cost of new work to June 30, 1944_                                                                             $681, 811. 14
Cost of maintenance to June 30, 1944_-------                                                   ---              191, 077. 63
      Total cost of permanent work to June 30, 1944------------                                                 872, 888. 77
Minus accounts payable June 30, 1944_--        ---------                                                              57. 76
      Net total expenditures -------------------------------                                                    872, 831. 01
Unexpended balance June 30, 1944--_                -------                                                           201. 28
           Total amount appropriated to June 30, 1944--------------                                             873, 032. 29


    Fiscal year ending June 30                  1940           1941           1942               1943                   1944

C ost of new work .-                            - - - - - - - - - - - - - - - - - - -. .   .     .   .     .     . .    .    .   .
'Cost of maintenance---
                     ...-----.                 $7, 242. 80   $45, 686.07      $985. 55         $1, 545. 21                  $809. 30

Total expended............-----------------     7, 062. 50   45, 765. 17      1,006. 13          1, 517. 52                  779. 23
Allotted..----------------------               45, 000.00      1, 500.00      1, 500.00----------------------


Balance unexpended July 1, 1943_-_         ---------                                                                   $980. 51
Gross amount expended ---------------------------------------
                         _                                                                                              779. 23

       Balance unexpended June 30, 1944------------------------                                                         201. 28
Outstanding liabilities June 30, 1944---. -----------                                                                    57. 76

    Balance available June 30, 1944_--------                                                         ---                143. 52
Amount allotted in July 1944_---    ----------                                                                 -1,      000. 00

           Amount available during fiscal year 1945-----------------                                                 1, 143. 52
Amount (estimated) required to be -appropriated  for completion of
                                      - -      -   -             -
existing project 1_ - ________
                       -   - -
                                            _______                                                             629, 200.00
  1Exclusive     of available funds.

                                     23. BURLINGTON HARBOR, VT.
  Location.-This harbor, about 100 acres in extent, is located in a
half-moon-shaped indentation in the eastern shore of Lake Champlain,
about 40 statute miles south of the international boundary line, 70
           RIVERS       AND HARBORS-NEW                      YORK,     N.   Y., DISTRICT              193
statute miles north of the southern end or head of the lake, and 20
statute miles southeast of the harbor at Plattsburg, N. Y. (See U. S.
Lake Survey Chart No. 172.)
   Existing project.-This provides for a breakwater 6,000 feet long
located about 1,000 feet from the shore and practically parallel with
it, to be built of stone-filled timber cribs, capped wi h large stone or
concrete. The completed breakwater is to be i two sections, the
northerly 500 feet being separated from the southerly 5,500 feet by
a gap 200 feet wide for the purpose of safety in entering the harbor
during storms. The reference plane of low lake level is 92.5 feet above
mean sea level at Sandy Hook, N. J. The level of the lake has varied
from 0.6 foot below up to 8.8 feet above the low lake level. The usual
annual variation is 4 to 5 feet.
   The estimate of cost for new work, revised in 1928, was $1,095,000.
The latest (1928) approved estimate for annual cost of maintenance is
$8,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                   Documents


July 4, 1836    Construction of first 1,000 feet of breakwater   --- H. Doc. No. 131, 23d Cong., 1st sess.
June 23, 1866   Extension of 1,500 feet to breakwater                H. Ex. Doc. No. 56, 39th Cong., 2d
                                                                      sess., pp. 17 and 179, printed in pts.
                                                                       3 and 4, Annual Report, 1866.
Mar. 3,1875     Extension of 2,000 feet to breakwater   -.....       Annual Report, 1874, p. 274.
                Chief of Engineers authorized extension southerly    Annual Report, 1887, p. 2407.
                 ol 1,000 feet and northerly for 500 feet.


For latest published map, see Annual Report for 1897, p. 3298.


   Terminal facilities.-The terminals consist of bulkheaded shore
front and open pile and solid filled piers having a total dockage of
6.520 feet. Of the terminals, five wharves, two piers, and one ferry
slip are in use. Five of the terminals have railroad connections. The
facilities are considered adequate for present needs of commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was prac-
tically completed in 1890; part of the breakwater originally proposed
was not built, the work completed being considered sufficient for the
needs of navigation. The breakwater has been built in two sections,
364 and 3,793 feet in length, respectively, separated by a gap of 200
feet. Sections of the stone and concrete superstructure of the break-
water have been displaced by wave action and the failure of the tim-
bers in the tops of the wooden cribs. The controlling depth in June
1939 was about 8.5 feet at low lake level at the wharves, increasing
considerably toward the breakwater.
   The distinction between new work and maintenance was not made
in the early reports, hence it is impossible to separate the costs prior
to July 1, 1886.
   The total cost and expenditures of the existing project to June 30,
1944, were $982,491.57;. since June 30, 1886, the cost of maintenance
was $276 077.46, leaving $706,414.11 as the cost of new work, including
maintenance prior to June 1, 1886.
        616634-45-pt. 1, vol. 1             13
194       REPORT. OF CHIEF OF ENGINEERS,                                     U.    S. ARMY,             1944

  Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
  Maintenance of the breakwater will be necessary during the fiscal
year 1946. The sum of $40,000 can be profitably expended during
the fiscal year ending June 30, 1946, under contract for maintenance,
for the repair of the breakwater.
                                         Cost and financial summary
Cost of new work to June 30, 1944__--   ----------                                                         $706, 414. 11
Cost of maintenance to June 30, 1944--- ----                                                -____           276, 077. 46
        Total cost of permanent work to June 30, 1944-                                       _              982, 491. 57
Net total expenditures                                  ---------------                                     982, 491. 57
Total amount appropriated to June 30, 1944                             ---------------                      982, 491. 57

   Fiscal year ending June 30               1940                1941           1942              1943             1944


Cost of new work--
Cost of maintenance__----------$40, 170. 89                 -                $14,991.42      $14, 410. 29
Total expended--.-. -      .        --
                                    -     40, 186. 56   --------------        13, 818. 43               28_.-_________
                                                                                                 15, 5833.
Allotted...-.---- .-----        -        -16,601.86             $30, 000 --------------          -598.29      -


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_ _-----___---------$40,                                                                       000

       24. NEWARK BAY, HACKENSACK AND PASSAIC RIVERS, N. J.

   Location.-Newark Bay is an estuary about 11/4 miles wide and 6
miles long, extending southerly from the confluence of the Hackensack
and Passaic Rivers to New York and New Jersey Channels.
   The Hackensack River rises near Haverstraw, Rockland County,
N. Y., and flows into Newark Bay. It is about 45 miles long.
   The Passaic River rises in the highlands of northeastern New Jersey
and flows into Newark Bay. It is about 80 miles long. (See U. S.
Coast and Geodetic Survey Charts Nos. 287 and 369 and U. S. Geologi-
cal Survey chart of New York City and vicinity.)
   Previous projects.-Adopted by River and Harbor Acts of August
30, 1852, June 10, 1872, June 14, 1880, June 13, 1902, March 2, 1907,
July 25, 1912, March 2, 1919, and September 22, 1922. For further
details see pages 265 and 266 of Annual Report for 1926; page 301,
Annual Report for 1929; and page 244, Annual Report for 1938.
   Existing project.-This provides for the following:
    (a) Newark Bay: A channel 30 feet deep and about 1,800 feet wide
at the entrance, including the removal to a depth of 30 feet of part of
the rock area at Bergen Point, shown on project map as area A (H.
Doc. No. 206, 67th Cong., 2d sess.), narrowing to 400 feet in the vicinity
of the Central Railroad of New Jersey bridge across the bay, and
continuing with that width to the juqlction of the Passaic and Hacken-
sack River Channels, a distance of about 4.7 miles.
    (b) A branch channel in Newark Bay 30 feet deep and 400 feet wide,
widened at the turn, to the Port Newark terminal extending from the
main channel as far as the United States pierhead line, a distance of
0.2 mile.
   Xc) Hackensack River: A channel 30 feet deep and 400 feet wide
from the upper end of the Newark Bay Channel to the Central Rail-
                RIVERS AND HARBORS-NEW                           YORK,         N.   Y., DISTRICT           195
road of New Jersey bridge, about 1.1 miles, thence 30 feet deep and 300
feet wide to a point about 2,000 feet north of the Delaware, Lacka-
wanna & Western Railroad bridge, 2.8 miles, thence 12 feet deep and
200 feet wide to Little Ferry, 10.1 miles, and thence 12 feet deep and
150 feet wide to the New York, Susquehanna & Western Railroad
bridge, 2.5 miles, a total distance for the Hackensack River of about
16.5 miles.
   (d) Passaic River: A channel 30 feet deep and 300 feet wide, from
Newark Bay to a point 3,000 feet above the Lincoln Highway bridge,
2.6 miles; thence 20 feet deep and 300 feet wide to the Nairn Linoleum
Works, about 4.4 miles; thence 16 feet deep and 200 feet wide to the
Montclair & Greenwood Lake Railroad bridge, about 1.1 miles; thence
10 feet deep and 150 feet wide to the Eighth Street Bridge at Passaic,
7.3 miles, a total distance for the Passaic River of 15.4 miles.
   All depths refer to the plane of mean low water. The mean tidal
range in Newark Bay is 4.9 feet, in Hackensack River at Court Street
Bridge, 5.3 feet; in Passaic River at Pennsylvania Railroad Freight
bridge, 5.1 feet; and in Passaic River at the Gregory Avenue Bridge,
4.9 feet; mean range of spring tides, 5.8, 6.4, 6.1, and 5.9 feet, respec-
tively. High easterly or westerly winds cause a fluctuation of as much
as 2 feet above or below mean tidal range.
   The estimate of cost for new work, revised in 1936, is $5,604,000,
exclusive of amounts expended on previous projects. The latest (1930)
approved estimate for annual cost of maintenance is $152,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                          Work authorized                                   Documents


Mar. 2,1907         16-foot channel in Passaic River_              -      H. Doc. No. 441, 59th Cong., 2d sess.
Feb. 27,1911        Widening 16-foot channel in Passaic River....            Do.
July 25,1912        20-foot channel in Passaic River            _         H. Doc. No. 707, 62d Cong., 2d sess.
    Do    ---       12-foot channel in Hackensack River-------            H. Doc. No. 643, 61st Cong., 2d sess.
Sept. 22,1922       30-foot channel in Hackensack River below Cen-        H. Doc. No. 206, 67th Cong., 2d sess.1
                      tral R. R. of New Jersey bridge, 30-foot channel
                      in Newark Bay, and 30-foot Port Newark con-
                      necting channel.
Jan.    21,1927     10-foot channel in Passaic River -      - -           H. Doc. No. 284, 69th Cong., 1st sess.
       Do-.......   30-foot channel in Hackensack River above Cen-        H. Doc. No. 429, 69th Cong., 1st sess.y
                      tral R. R. of New Jersey bridge.
July      3,1930    30-foot channel in Passaic River                ...      Doc. No. 156, 71st Cong., 2d sess.1
                                                                          H-----
                                                                          H.



  1Contains latest published maps.

  Recommended modificatiogns of project.-Under date of July 5,
1939, the Chief of Engineers recommended modification of the exist-
ing project for the section of Passaic River, N. J., extending from the
Montclair & Greenwood Lake Railroad bridge to the Eighth Street
Bridge in Passaic to provide that when spoil-disposal areas are not
available or the placing of dredge spoil ashore is uneconomical as
compared with other methods of disposal, local interests shall not be
required, to furnish disposal areas for maintenance dredging (H. Doc.
No. 430, 76th Cong., 1st sess.).
  Modification of the existing project for Newark Bay, N. J., was
recommended by the Chief of Engineers in a report requested by
196         REPORT OF CHIEF OF ENGINEERS,                                                            U.     S. ARMY,                 1944

resolution of the Committee on Commerce adopted May 21, 1941,
and transmitted to Congress by the Secretary of War July 22, 1942.
   Local cooperation.-Fully complied with as required by the River
and Harbor Act approved January 21, 1927, except that local inter-
ests are required to provide suitable spoil-disposal areas for mainte-
nance dredging in the 30-foot channel in the Hackensack River above
Central Railroad of New Jersey bridge; in the 10-foot channel in the
Passaic River; and whenever required by the Secretary of War, for
dredging in the 30-foot channel in Newark Bay and the Hackensack
River below the Central Railroad of New Jersey bridge, as required
by the River and Harbor Act approved September 22, 1922.
   Terminal facilities.-There are 16 piers with a berthage of 8,525 feet,
55,300 feet of bulkheads available for dockage and a large shipyard
along the waterways included in the project. Twelve of the terminals
are publicly owned, the largest of which, Port Newark, owned and
operated by the city of Newark, provides about 11,000 feet of wharfage.
Eight of the terminals are open for public use, 56 are equipped with
mechanical handling devices and 66 have railroad connections. The
facilities are considered adequate for existing commerce. (For latest
full description of terminal facilities see Port and Terminal Facilities
at the Port of New York, 1942, Corps of Engineers.)
   Operations and resuldts during fiscal year.-The cost of surveys to
determine the condition of the 30-foot channels in Passaic and Hacken-
sack Rivers was $1,345.33 for maintenance. The expenditures were
$5,175.73.
   Condition at end of ;fiscal year.-The existing project was about 90
percent completed. The 30-foot channels in Newark Bay and Port
Newark entrance channel, the 30- and 12-foot channels in Hacken-
sack River, and the 30-, 16-, and 10-foot channels in Passaic River are
completed. The 20-foot channel in Passaic River is completed to
Jackson Street, Newark.
   The controlling mean low water depths of the various channels, as
shown by surveys made intermittently from September 1932 to May
1944, are as follows:

                                             Section                                                                            Depth             Width
                                                                                                                                (feet)            (feet)

Through Newark Bay --------
                         -____                        -----------                 .. .. _......               -------                       30        180-400
In Hackensack River from Newark Bay to about 2,000 feet above the Delaware,
  Lackawanna & Western R. R. bridge -29                                                                                                               150-400
From 2,000 feet above the Delaware, Lackawanna & Western R. R. bridge to 1,500
  feet above route 3 highway bridge-.                      .-.. ......................                                                      12              200
From 1,500 feet above route 3 highway bridge to head of project at the New York,
  Susquehanna & Western R. R. bridge - .--- -------------                        ---                                                        12         90-150
In Passaic River to 2,650 feet above the Lincoln Highway Bridge---------                                                                    28             100
From 2,650 feet above Lincoln Highway Bridge to Jackson St. Bridge -------                                                                  16        160-300
From Jackson St. Bridge to Erie R. R. bridge (Newark branch) -------------------                                                            15        150-300
From Erie R. R. bridge to Montclair & Greenwood Lake R. R. bridge-
From Montclair & Greenwood Lake R. R. bridge to 2d St. Bridge--------
                                                                                                                      _                     14        100-150
                                                                                                                                            10         70-150
From 2d St. Bridge to 500 feet below the 8th St. Bridge--                                                                                    8         70-150
From 500 feet below and to 8th St. Bridge --------------------------------------                                                             4         80-120
Port Newark Entrance Channel .....--------------------------------------------                                                              30              400

MAinimum widths through bridge draws:
    Hackensack River:                                                                                                                                      Feet
       30-foot project ...                                                                                         __---------------------------------------------------------------
                                                                                                                                                             93
       12-foot project .       ..-..                          ._.                        ---------------                                    _---------        56
    Passaic River:
        30-foot project        ......--                                                  _---_---_---_---_---_---_---_---_---_---_-------_-           -
                                                                                                                                                      _100
         20- and 16-foot projects      .     .....    ..            .....     .....        ....._.. .....       ..... ....          .....     .     -- -     75
         10-foot project . ..               ..
                                           -.......              ....                            _..._...
                                                                                                      _.._..._..._..
                                                                                                       ....            .
                                                                                                                       _.
                                                                                                                      _...       ......                      45
                   RIVERS AND HARBORS-NEW                                         YORK,     N.     Y.,   DISTRICT                 197
  The work remaining to be done under the existing project consists
of the completion of the 20-foot channel in Passaic River from Jackson
Street to the Nairn Linoleum Works. This work includes the removal
of a small quantity of rock on the west side of the channel above Cen-
ter Street Bridge. Adjacent property owners are opposed to the
removal of this rock.
  The total cost and expenditures of the existing project to June 30,
1944, were $6,980,317.97-$5,063,756.27 for new work and $1,916,561.70
for maintenance.
  Proposed operations.-Allotment of $50,000 made in July 1944 will
be applied to maintenance dredging, by contract, to restore the chan-
nel in Passaic River, opposite the Second River to project depth of
10 feet.
  Completion of the project is not considered necessary at this time.
The sum of $150,000 can be profitably expended during the fiscal
year ending June 30, 1946, under contract for maintenance, in the
removal of shoals from the existing channels.
                                                      Cost and financial summary
                                 ---------------------
Cost of new work to June 30, 1944_                                                                        -$6,       819, 077. 73
Cost of maintenance to June 30, 1944_ .....-----....                                                              2, 359, 047. 14
       Total cost of permanent work to Junie 30, 1944 ......                                                      9, 178, 124. 87
Net total expenditures_   __---.---------                    --                                                   9, 178, 124. 87
Total amount appropriated to June 30, 1944.       .......                                                         9, 178, 124. 87


      Fiscal year ending June 30                        1940           1941               1942             1948                1944

C ost   ofn ew     Work ----------------. -..                   .... . .. ... ..          . .. .. . .. .. . .. .. . .. ..-.... .
                   ------------.
Cost of maintenance.....                              $69,156.29            72
                                                                    $310,478.          $48,767 46        $59, 665. 94          $1,345.33

Total bxpended ....------------......             -    72,118. 50    310, 097. 56       48, 650 84        56, 116. 46           5,175. 73
Allotted ....................----------------------   275, 000.00     35, 000.00 - .---        _   -----------            --     ,4466.
                                                                                                                                     11


Balanoe unexpended July 1, 1943_          .___$14,                                                                           630, 84
Deductions on account of revocation of allotment--------------                                                            9, 455. 11
      Net amount to be accounted for__                                        -     --------                              5, 175. 73
Gross amount expended_--------------_                                                                                     5, 175. 73
Amount allotted in July 1944_---         -----------                                                                     50, 000. 00
Amount available during fiscal year 1945                               ---------------------                             50, 000. 00
Amoutit (estimated) required to be appropriated for completion
  of existing project-----   --      _...                 -.
Amount that can be profitably expended in fiscal year ending
                                                            -                                                           540, 000. 00
  June 30, 1946, for maintenance_ _------------------150,                                                                      000. 00

                            25. NEW YORK AND NEW JERSEY CHANNELS

  Location.-These channels extend from deep water northwest of
Sandy Hook, through lower New York Bay and Raritan Bay, to
Perth Amboy, and thence through Arthur Kill, lower Newark Bay,
and Kill Van Kull to deep water in upper New York Bay. This
route is located approximately along the boundary line between the
States of New York and New Jersey. (See U. S. Coast and Geo-
detic Survey Charts Nos. 285, 286, and 369.)
198          REPORT OF CHIEF OF ENGINEERS,                           U.    S. ARMY,       1944


   Previousprojects.-(a) RaritanBay.-Adopted by River and Har-
bor Acts of March 3, 1881, September 19, 1890, and June 3, 1896.
    (b) Staten Island Sound.-Adopted by River and Harbor Acts of
June 23, 1874, March 3, 1875, June 14, 1880, August 11, 1888, May 15,
1889, and October 20, 1890, June 3, 1896, June 13, 1902, June 25, 1910,
and March 4, 1913.
    (c) New York and New Jersey Channels.-Adopted by River and
Harbor Act of September 22, 1922. For further details, see page 284
of the annual report for 1923, and page 194 of the annual report
for 1934.
   Existing project.-This provides for a channel through lower New
York Bay, Raritan Bay, Arthur Kill, lower Newark Bay, and Kill
Van Kull to upper New York Bay, the depth to be 37 feet in rock
and 35 feet in soft material throughout, except in Arthur Kill be-
tween a point 1,000 feet north of the mouth of Smiths Creek and
a point 1,000 feet south of Buckwheat Island, where the depth will
be 30 feet; the width to be 600 feet across lower New York Bay
and Raritan Bay and in the Arthur Kill to a point 500 feet south
of Morse Creek, widened to 800 feet in the vicinities of Seguine Point
and Wards Point, respectively, thence 500 to 600 feet wide and passing
north of Shooters Island and protected by a dike on its northern side
to the junction of the channel into Newark Bay; and thence 800 feet
wide through Kill Van Kull to upper New York Bay; with two an-
chorages 38 feet deep to accommodate five vessels each, one in the
vicinity of Sandy Hook and one south of Perth Amboy, all with suit-
able easing at the bends and junctions. Length of section included
in project 30.6 miles. All depths refer to the plane of mean low water.
The mean range of tides varies between 4.9 and 5.1 feet; the mean
•range of spring tides, 5.8 to 6.1 feet. Extreme easterly or westerly
winds produce fluctuations of 1 to 3 feet above or below the mean
range.
   The estimate of cost for new work, revised in 1939, is $37,630,000,
exclusive of amounts expended on previous projects. The latest
 (1935) approved estimate for annual cost of maintenance is $195,000.
   The existing project was authorized by the following river and
harbor acts:

     Acts                        Work authorized                                   Documents


         -        Construction of dike. (Completed under pre-        H. Doc. No. 653, 66th Cong., 2d sess.
                   vious projects; River and Harbor Act, Sept. 22,
                   1922.)
Sept. 6, 19331   1                                                Rivers and Harbors Committee Doe.
Aug. 30,1935     JAnchorage off Perth Amboy to 33 feet------------ No. 17, 71st Cong., 2d sess.
May 28,19352     1Existing project as a whole-_ .-.---       - H. Doc. No. 133, 74th Cong., sletsess.
Aug. 30,1935     Ji[                                                 Contains latest published map.)


                 I Public Works Administration.               2Emergency     Relief Act of 1935.


  Local cooperation.-Work under the existing project is subject to
the following conditions of local cooperation:
   (a) That where the project channel encroaches upon upland prop-
erty and extends shoreward of harbor lines, the completion of the
        RIVERS   AND   HARBORS-NEW      YORK,   N. Y.,   DISTRICT   199
encroaching portions of the project shall be deferred until the neces-
sary rights-of-way for channel purposes shall have been granted free
of cost to the United States; and
   (b) That local interests provide areas of land adjacent to the water-
way, free of cost to the United States, for the disposal of dredged
materials, except where, in the judgment of the Chief of Engineers,
no suitable disposal areas exist.
   Under condition (a), a portion of Buckwheat Island necessary for
channel purposes has been ceded to the United States. An easement
dated August 4, 1942, approved by the Chief of Engineers on Septem-
ber 5, 1942, conveyed to the United States free of cost, rights-of-way
for channel purposes at Howland Hook, Staten Island, N. Y. Condi-
tion (b) is being complied with.
   Terminal facilities.-There are 138 piers with a total berthage of
84,105 feet, 34,632 feet of bulkheads and wharves available for dock-
age, 7 ferry landings and 2 car-float (railroad) bridges. Of the ter-
mninals 20 are puflicly owned, 10 are open to the public, 93 are equipped
with mechanical handling devices and 76 have railroad connections.
Included in the terminals are 5 large shipyards. The facilities are
considered adequate for existing commerce. (For latest full descrip-
tion of terminal facilities see Port and Terminal Facilities at the Port
of New York, 1942, Corps of Engineers.)
   Operations and results during fiscal year.-f-Under a contract for
dredging and rock removal to a depth of 37 feet in section 7, westerly
part of area 10, in the northerly half of the channel in Kill Van Kull
in the vicinity of Bergen Point, work was commenced on March 7,
1942, and was completed on October 13, 1943. During the fiscal year
8,451 cubic yards, place measurement, of rock were drilled and blasted
and 23,676 cubic yards, place measurement, of rock and 1,921 cubic
yards, place measurement, of material other than ledge rock were re-
moved at a total cost of $123,204.35 for new work.
   Under a contract for dredging and rock removal to a depth of 37
feet in section 7, Rock Area 11 in the northerly half of the channel
in Kill Van Kull, in the vicinity of Bergen Point, work was com-
menced July 8, 1942, and was completed on October 11, 1943. During
the fiscal year 48,395 cubic yards, place measurement, of rock were
drilled and blasted and 49,757 cubic yards, place measurement, of rock
and 2,632 cubic yards, place measurement, of material other than ledge
rock were removed at a total cost of $419,747.32 for new work.
   Government plant removed an obstruction in Arthur Kill in the
vicinity of Sewaren, N. J., on August 13, 1943, at a cost of $523.27
for maintenance.
   The cost of surveys and engineering preliminary to contract dredg-
ing was $13,994.31--$4,210.81 for new work and $9,783.50 for main-
tenance.
   The total cost of all work was $557,469.25-$547,162.48 for new
work and $10,306.77 for maintenance. The total expenditure was
$703,296.26.
   Condition at end of fiscal year.-The existing project was about 53
percent completed. Work completed thus far has consisted of pro-
viding project depth of 35 feet in soft material and 37 feet in rock in
a 2i-mile reach in Raritan Bay extending westward from Bayside-
200          REPORT OF CHIEF OF ENGINEERS,                                U. S. ARMY,             1944

Gedney Channel; the westerly half of the channel from Buckwheat
Island to Elizabethport; the channel in Newark Bay and north of
Shooters Island from Elizabethport to the easterly end of Shooters
Island; the northerly half of the channel in Kill Van Kull from
Shooters Island to Constable Point; the channel from Constable Point
to St. George; and of providing 33-foot depth in the northeasterly
portion of the Perth Amboy anchorage.
   The controlling mean low water depth when examined intermit-
tently from 1933 to 1944 was 33 feet for a 600-foot width for a dis-
tance of 3.3 miles westward from Bayside-Gedney Channel in Raritan
Bay; thence 28 feet and 600 to 200 feet wide to Buckwheat Island,
following the previous project channel at the westerly end of Raritan
Bay; thence 35 feet and 250 to 800 feet wide to the entrance of Kill Van
Kull in New York Harbor, except in the channel north of Shooters
Island where the depth is 33 feet and 200 to 600 feet wide.
  The work remaining to be done under the existing project consists
of completing the deepening and widening of the entire channel to
dimensions authorized by the River and Harbor Act of August 30,
1935, the completion of the deepening of the anchorage south of Perth
Amboy, and dredging the anchorage in the vicinity of Sandy Hook.
   The total costs and expenditures under the existing project to June
30, 1944, were as follows:
                                                                      Costs
                                                                                                       Expenditures
                                                New work          Maintenance            Total

Regularfunds                                    $17, 052, 070. 13
                                      ..--------------------          $232, 651.32 $17, 284, 730. 45   $17, 283, 125.32
Publi Wotks funds ------------------- 807, 000.00 ----------------                       o,  000.00                  0
                                                                                                            807, 0.00.
Emergency Relief funds--------------
                      ...............             2, 023, 308.41 ----------------    2, 023, 308.41      2,023, 308. 41

     Total United States funds-........      19,882, 387. 54          232, 651.32    20,115, 038.86     20,113, 433.73
Contributed funds......---------------------      7,711.82- .........                     7,711.82            7, 711.82

      Total, all funds....----------------     19, 890, 099. 36      232, 651.32     20, 122, 750.68    20, 121, 145.52



   Proposed operations.-The balance unexpended at the end of the
fi cal year, amounting to $830,056.47, will be applied as follows:
Accounts payable June 80, 1944 _$------------------------------$1, 610. 13
New work: Advance planning and prepa'ation of speci-
  fications for post-war dredging and rock removal un-
  der contract in the easterly half of Arthur Kill from
  Buckwheat Island to Elizabethport, section 5, areas
  7 and 8_ -----------------------------------------------.             26, 000. 00
Maintenance:
     Complete by Nov. 20, 1944, under contract to be
        entered into, dredging to restore the existing
        channel north of Shooters Island between Eliza-
        bethport and Bergen Point, to project dimensions $224, 446. 34
     Dredge by use of 1 United States seagoing hopper
        dredge for about 2 months in the removal of
        shoals in the Raritan Bay channel to previous
        project depth -----------------------------        78, 000. 00
                                                                       302, 446. 34

             Total------------------------------------                                  -------- 330,056.47
   The deepening of the channel to project dimensions should be.con-
tinued. The existing channels in Raritan Bay should be maintained.
               RIVERS AND HARBORS-NE W YORK, N. Y., DISTRICT                                                                     201

The sum of $5,100,000 can be profitably expended during the fiscal year
ending June 30, 1946, as follows:
New work:
    Complete by May 1, 1946, under contract to be entered into,
       dredging and rock removal in the easterly half of the channel
       in Arthur Kill from Piles Creek to Morse Creek, section 5,
       area 7      --------------------------------------------               $1,050, 000
    Complete by Apr. 1, 1946, under contract to be entered into,
       dredging and rock removal in the easterly half of the channel
       in Arthur Kill from Morse Creek to Elizabeth River, section
       5,area 8_ ------------------------------------------                     1, 100,000
    Complete by Mar. 1, 1946, under contract to be entered into,
       dredging and rock removal in the easterly half of the channel
       in Arthur Kill from Elizabeth River to Elizabethport, section
       5,area9-------------------------------------------1,100,000
    Dredge by use of 3 United States seagoing hopper dredges for a
       total of 33 dredge months the lower entrance channels in
       Raritan Bay to 35 feet--------------------------1,750,000
         Total                                                                     000, 000
                                                                               5------------------------------
Maintenance: Dredging by contract to restore the existing channels
  in Raritan Bay to previous project dimensions-----------------                   100, 000
      Total---------------------------------------------5,                         100, 000
                                   Cost and financial summary
Cost of new work to June 30, 1944_ _                     ---------     12$32, 692, 362. 26
Cost of maintenance to June 30, 1944_-                       ----- -_2     1, 073, 980. 58
      Total cost of permanent work to June 30, 1944----- -- 1 2 33, 766, 342. 84
Minus accounts payable June 30, 1944---------------------             1, 610. 13

      Net total expenditures --------------------------                                                       233,764,732. 71
Unexpended balance June 30, 1944_---------                                                             ----            330, 056. 47
          Total amount appropriated to June 30, 1944---------                                              1 2    34, 094, 789. 18

   Fiscal year ending June 30                    1940             1941                  1942               1943             1944

Cost of new work__                          $2, 758, 703. 37 $1, 274. 823. 94 $1, 904, 574. 24 $1, 638, 536. 92           $547, 162.48
Cost of maintenance ...-.....
                           -                 -. 1, 603. 55        43, 568.34       71, 220. 19          562. 94             10, 306. 77

      Total cost..........---------------    2, 760, 306. 92   1, 318, 392. 28       1, 975, 794.43   1, 639, 099. 86      557, 469. 25
Total expended..........---------------      2, 789, 283.98    1, 423, 687.44        1, 731,185. 12   1, 847, 567. 30      703, 296. 26
Allotted---.....................             1, 281, 000.00    2, 708, 000.00        3, 750, 000.00 -2, 145, 000.00      -135,   484.08


Balance unexpended July 1, 1943_ ___----------$1,                                                                      168, 836. 81
Deductions on account of revocation of allotment-                                                                      135, 484. 08
       Net amount to be accounted for---------------------                                                         1, 033, 352. 73
Gross amount expended_---        -------------                                                                        703, 296. 26
      Balance unexpended June 30, 1944--------------------                                                             330, 056. 47
Outstanding liabilities June 30, 1944_---------            ----                                                          1, 610. 13
          Balance available June 30, 1944----------------------                                                        328, 446. 34
Amount (estimated) required to be appropriated for completion
of existing project 3- - - - - - - -    - - -    - - -     -
                                                                                                                  17, 722, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946: 3                                   -      -
   For new work ________            ______        _ -_ - - -                                                       5, 000, 000. 00
   For maintenance 3 _ - - -  - - - -   - - -    -                                                            -    -
                                                                                                                      100, 000. 00
        Total -_              -                    -              -              -                     -
                                                                                                                   5, 100, 000. 00
  1Exclusive of $7,711.82 expended from           contributed funds for new work.
   Includes $6,621 for new work and $1,621 for maintenance of Lemon Creek.
 * Exclusive of available funds.
202          REPORT OF CHIEF OF ENGINEERS,                                       U.     S.   ARMY,         1944

      26. RARITAN RIVER TO ARTHUR KILL CUT-OFF CHANNEL, N. J.

   Location.-This channel is in the western portion of Raritan Bay,
off Perth Amboy, and about 23 miles by water southwest of the Bat-
tery, New York City. (See U. S. Coast and Geodetic Survey Chart
No. 286.)
   Existing project.-This provides for a channel about 1 mile long,
20 feet deep at mean low water and 800 feet wide, connecting the
Raritan River Channel with the southern end of the Arthur Kill
Channel, New York and New Jersey Channels project. The mean
range of tides is 5.1 feet; mean range of spring tides, 6.1 feet. High
easterly or westerly winds cause irregular tidal fluctuations from 1
to 2 feet above or below the mean range.
   The estimate of cost of new work made in 1933 was $600,000. The
latest (1935) approved estimate of annual cost of maintenance is
$21,000.
   The existing project was authorized by the Public Works Admin-
istration under date of September 6, 1933, and by River and Harbor
Act approved August 30, 1935 (H. Doc. No. 50, 73d Cong., 1st sess.),
which document contains latest published maps.
   Termnal facilities.-No terminal facilities are served by the im-
provement, which is a connecting channel.
   Conditionat end of fiscal year.-The existing project was completed
in 1935. When examined in September 1941 and February 1942 the
controlling mean-low-water depth through the channel was 17 feet
for a width varying from 350 to 800 feet.
   The total cost and expenditures of the existing project to June 30,
1944, were $996,417.47-$810,500 Public Works funds for new work
and $185,917.47 regular funds for maintenance.
   Proposed operations.-Nofunds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $200,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging, under contract, to
restore the channel to project dimensions.
                                            Cost and financial summary
Cost of new work to June 30, 1944__                           $810, 500. 00
Cost of maintenance to June 30, 1944-------------------------  185, 917. 47
       Total cost of permanent work to June 30, 1944-_- --------                                                996, 417. 47
Net total expenditures-------------------------------------                                                     996, 417. 47
Total amount appropriated to June 30, 1944------------- -----                                                   996, 417. 47

    Fiscal year ending June 30                  1940                1941              1942          1943              1944

                 ........-...
Cost of new work-------          --      ------.......--.. ---     ---------------.------------ --....---------
Cost of maintenance__.------------ ------.                   $696.40    $26,184.22    $20,085.00----.-.
Total expended-------...............---....------ --------------
                                                        ......        124.30      24, 735. 88     22, 105, 44-----------
Allotted-----------------------                   $55,000          72, 000. 00   135, 000. 00   -215, 034. 38     _------------

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance-                           -$200,                                                           000. 00
              RIVERS      AND HARBORS-NEW                   YORK,      N.    Y.,   DISTRICT             203
                  27. GREAT KILLS HARBOR, STATEN ISLAND, N. Y.

  Location.-Great Kills is a small harbor contiguous to lower New
York Bay. located on the southeasterly shore of Staten Island, N. Y.,
about 8 miles northwest of Sandy Hook, N. J., and 161/2 miles south-
west of the Battery, New York City. (See U. S. Coast and Geodetic
Survey Chart No. 369.)
   Existing project.-This provides for an entrance channel 10 feet
deep and 150 feet wide from deep water in lower New York Bay
through the entrance to the harbor in the vicinity of the present west-
erly end of Crooks Island, thence of same depth and width along the
west side of the harbor and for an anchorage area of 138 acres and
8-foot depth. The length of the section included in the project is
about 1.9 miles. The mean range of tide is 4.7 feet, mean range of
spring tides, 5.7 feet. Extreme easterly or westerly winds produce
fluctuations of from 3 feet below mean low water to 3 feet above mean
high water.
   The estimate of cost for new work, revised in 1938, is $265,000, in-
cluding $114,500 contributed by local interests. The latest (1938)
approved estimate for annual cost of maintenance is $15,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                   Documents


Jan.    21,1927   Entrance channel to Crooks Island                    H. Doc. No. 252, 69th Cong., 1st sess.
                                                              ..------------
June 20, 1938     Extension of entrance channel and for an anchor-   H. Doc. No. 559, 75th Cong.,. 3d sess.
                   age area.                                           (Contains latest published map.)



   Local cooperation.-Fullycomplied with except that local interests
are required to furnish suitable spoil-disposal areas for maintenance.
   Terminal facilities.-No terminals suitable for commercial purposes
have been established. There are eight small piers used for mooring
and landing purposes. Four commercial boat yards are located at
Great Kills. Upon completion of the two public terminals to be con-
structed in accordance with the requirements of local cooperation, the
terminals will be sufficient for present needs.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was about 59
percent completed. The entrance channel up to Crooks Island was
completed in 1935. When examined in March and April 1941, March
to May 1942, and May 1943, the controlling depth at mean low water
was 9 feet for a width varying from 125 to 150 feet in the entrance
channel to Crooks Island, thence 9 feet for full project width in the
channel along the west side of the harbor for a distance of 2,000 feet,
thence 0.9 foot for full project width to the head of the project, and
8 feet in the anchorage except in the northwest corner where the least
depth was 1 foot. The work remaining to be done under the project
consists of completing the dredging of the channel along the west side
of the harbor and the anchorage area.
204           REPORT (OF CHIEF OF ENGINEERS,                                                                 U.          S. ARMY,                             1944

    The total cost of the existing project to June 30, 1944, was $166,-
147.41-$36,000 Public Works funds, $67,272.49 contributed funds, and
$50,796.01 advanced funds, a total of $154,068.50 for new work and
$12,078.91 regular funds for maintenance. The total expenditures were
$153,002.17 of which $61,956.48 were contributed funds, $42,966.78
advanced funds, and $48,078.91 United States funds.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $124,076.74, of which $52,543.52 are con-
tributed funds and $71,533.22 are advanced funds, less accounts pay-
able of $13,145.24, a balance of $110,931.50 will be returned to local
interests.
    Completion of the existing project is not essential at this time and
maintenance dredging will not be necessary during the fiscal year
1946.
                                                  Cost and financial summary
                                                      UNITED STATES                            FUNDS

Cost of new work to June 30, 1944----... . --.                                                                   -------                                           $36, 000. 00
Cost of maintenance to June 30, 1944_---- ....                                                                       ---                                            12, 078. 91
       Total cost of permanent work to June 30, 1944 ------                                                                                                         48, 078. 91
Net total expenditures_-------               -    -         -_____                                                                                                  48, 078. 91
Total amount appropriated to June 30, 1944--------------------                                                                                                      48, 078. 91

    Fiscal year ending June 30                         1940                         1941                          1942                               1943                   1944


C ost of new w ork - - - - - -. .                 - - - - - - . - - - - - - . -- - - -                                             ..      -- - - .            .    .. . . . .
Cost of maintenance ....------------               $12, 035. 21 -------     ........                                                    .......                    .......

Total expended ...........----------------          12,078.91 .           .......                        ........                           ..         -----        -           ------

Allotted_ __ --------------------- -2, 921.09-                             .         .     .     .           .       .        .         .        .        .    .        .   .       .



Amount (estimated) required to be appropriated for completion of
existing project 1----------------------------------------      $51, 000. 00
  1For repayment of funds advaned                    by local interests.

                                                        CONTRIBUTED FUNDS

Cost of new work to June 30, 1944__                                                  --                  _                        _67,                                      272. 49
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944                                                                                               -                 67, 272. 49
Minus accounts payable June 30, 1944-    --------                                                                                                     _              5, 316.01
      Net total expenditures__ _                                                     -                       -            -                      -__                61, 956. 48
Unexpended balance June 30, 1944                                                                                                                  __                52, 543. 52
           Total amount contributed to June 30, 1944-----------                                                                                                    114, 500. 00


    Fiscal year ending June 30                        1940                          1941                          1942                               1943                   1944

Cost of new work_- ....... -           -.......   _ ._ . -            -$1,927.             59                $62, 800.13                         $2, 544. 77
Cost of maintenance ..-
Total expended- ------------- _ _                 -_----.     .                     1, 927. 59                   57, 238. 16                      2, 790. 73 _

Contributed-- .......      ...   ...     ......     ......        .            114, 500. 00          .
                     RIVERS AND HARBORS-NEW                                                          YORK, N. Y., DISTRICT                                                205
Balance unexpended July 1, 1943_                                                                                                                        $52, 543. 52

Balance unexpended June 30, 1944_---
                                  _-------                   52, 543. 52
Amount covered by uncompleted contracts----------------------5, 316. 01
               Balance available Jun 30, 1944_                                                                                                           47, 227. 51
                                                                        ADVANCED FUNDS

Cost of new work to June 30, 1944_ _50,                                                                                                                             796. 01
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-                                                                                                     50, 796. 01
Minus accounts payable June 30, 1944_-                                                                                                                  -7, 829. 23

      Net total expenditures_ _____                                                         ------                                                       42, 966. 78
Unexpended balance June 30, 1944_                                                                                                                        71, 533. 22
               Total amount advanced to June 30, 1944-----------                                                                                        114, 500. 00

     Fiscal year ending June 30                                     1940                    1941                    1942                  1943                          1944


Cost of newt work-----------------------------                                                  $44. 88           $44, 248. 77           $6, 502. 36
Cost of maintenace     --   - --    - - -    - --                                           -    - --.-

T otal expended- .....                   .   .......--                   - ..            ----------                38,903.82              4,062. 96

A d v an ce d- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -    114 , 500. 0 0     .     . . . . . . . . .             ..-
                                                                                                                                                 - - .    .         .     .        .   .


Balance unexpended, July 1, 1943                                                   ---------------------------                                          $71, 533. 22

Balance unexpended, June 30, 1944---------------------------71,                                                                                                     533. 22
Amount covered by uncompleted contracts----------------7,                                                                                                           829. 23

               Balance available, June 30, 1944------------------------63,                                                                                              703. 99
CONSOLIDATED                       COST          AND         FINANCIAL                   SUMMARY,                GREAT        KILLS,           STATEN               ISLAND,
                                                                                         N.Y.
Cost of new work to June 30, 1944_ _______________                                                                                                     $154, 068. 50
Cost of maintenance to June 30, 1944-_-                                                                                                                   12, 078. 91
      Total cost of permanent work to June 30, 1944----166,                                                                                                  147. 41
Minus accounts payable June 30. 1944_                                                                                                                    13. 145. 24

      Net total expnditues--------------------------                                                                                                    153, 002. 17
Unexpended balance, June 30, 1944___                                                                                                                    124, 076. 74
               Total amount appropriated to June                                                   0, 1944---------                                     277, 078. 91

     Fiscal year ending June 30                                     1940                    1941                    1942                  1943                          1944


Cost of new work                           .                                               $1, 972. 47           $107, 048. 90           $9, 047. 13     - --
Cost of maintenance------------$12, 035. 21                                                                          -.
Total expended -----------------                                  12, 078 91                1, 927. 59             96, 141.98             6,853.69-

Allotted, contributed, and ad-
vanced ------------------     --                               -2,921.09                 229, 000.00 .---                 ....           ..     ...          ...              .


Balance unexpended, July 1, 1943-_-                                                                  -----                        ----                 $124, 076. 74

Balance tunexpended, June 30, 1944--_   ---------                                                                                                       124, 076. 74
Amount covered by uncompleted contracts                                                          ---------------------                                   13, 145. 24

               Balance available, June 30, 1944_--                                                                    - --               ___            110, 931. 50

Amount (estimated) required to be appropriated for completion of
    existing project 12                                              -51,                                                                                           000. 00
   1Exclusive of available funds.
   2For repayment of funds advanced                                by local interests.
206           REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,         1944

                                  28. RARITAN RIVER, N. J.
   Location.-Rises in the north-central part of New Jersey and flows
in a general southeasterly direction into Raritan Bay, between Perth
Amboy and South Amboy, about 24 miles, by water, south of the
Battery, New York City. (See U. S. Coast and Geodetic Survey
Chart No. 375.)
  Previous projects.-A survey of Raritan River for the improvement
of New Brunswick Harbor was made in 1836. Subsequent projects
were adopted by acts of June 18, 1878, and March 3, 1881.
   For further details see page 1777 of Annual Report for 1915, page
359 of Annual Report for 1918, and page 259 of Annual Report for
1938.
   Existing project.-This provides for a channel 25 feet deep and 300
feet wide extending from the turn in New York and New Jersey Chan-
nels near Great Beds Ligrht to the Government wharf on the main
channel, a distance of 5.8 miles, widened to 600 feet for a length of 1,000
feet opposite the wharf to form a turning basin of same depth; thence
a channel 15 feet deep and 200 feet wide, to the Washington Canal,
a distance of 3.0 miles; thence 10 feet deep in soft material, 11 feet deep
in rock, and generally 100 feet wide with widening at bends to the
Delaware and Raritan Canal entrance at New Brunswick, a distance
of 5.0 miles; and for a south channel, 25 feet deep and 300 feet wide
from the junction with the main channel at Keasby to the upper limit
of the Titanium Pigment Co. property, a distance of 0.8 mile; thence
10 feet deep and 150 feet wide to the upper junction with the main
channel at Crab Island, a distance of 2.4 miles. The plane of reference
is mean low water. The mean range of tides is 5.1 feet at the mouth of
the river and 5.3 feet at New Brunswick; mean range of spring tides,
6.1 and 6.3 feet, respectively. High easterly or westerly winds cause
irregular tidal fluctuations from 1 to 2 feet above or below the mean
range.
   The estimate of cost for new work, revised in 1940, is $1,415,000,
exclusive of amounts expended on previous projects but including
$665000 contributed by local interests. The latest (1940) approved
estimate for annual cost of maintenance is $60,000.
   The existing project was authorized by the following river and
harbor acts:
       Acts                      Work authorized                                 Documents

Mar.     2,1919   Channel 15 feet deep and 200 feet wide to Wash-   H. Doc. No. 1341, 62d Cong., 3d sess.
                   ington Canal, thence 10 feet deep and 150 feet
                   wide to canal locks and 10 feet deep through
                   south channel.
July     3,1930   Channel 25 feet deep and 300 feet wide up to New H. Doc. No. 127, 70th Cong., 1st sess.
                   York & Long Branch R. R. bridge.
                                                                                                          1
    Do..          Channel 10 feet deep in earth and 11 feet in rock H. Doe. No. 454, 70th Cong., 2d sess.
                   to New Brunswick. Width reduced to 100 feet.
    Do    -- --   Relocation of lower reach of south channel ...... Rivers and Harbors Committee Doc.
                                                                                                   4
                                                                       No. 31, 71st Cong., 2d sess.1
Aug. 26,1937      Channel 25 feet deep and 300 feet wide to junction Rivers and Harbors Committee Doe.
                                                                                                    1
                   of main and south channels, thence of same          No. 74, 74th Cong., 2d sess.
                   depth in south channel to Titanium Pigment Co.
Oct. 17, 1940     Channel 25 feet deep and 300 feet wide from junc- Report on file in the Office, Chief of
                   tion of main and south channels to the Govern-      Engineers (report not printed).
                   ment wharf, including a turning basin.
  1 Contain latest published maps.
        RIVERS   AND   HARBORS-NEW      YORK,   N.   Y.,   DISTRICT   207

    Local cooperation.-Fully complied with except that local interests
are required to furnish spoil-disposal areas for the maintenance of the
25-foot channel from New York and Long Branch Railroad bridge to
junction of main and south channels, and in the south channel to the
Titanium Pigment Co. property.
    Terminal facilities.-There are 7 piers with a total berthage of
5,774 feet and 9,545 feet of bulkheads available for dockage. The
Government has established a large ammunition and storage depot
and arsenal on the river known as Raritan Arsenal. One of the ter-
minals is municipally owned and is open to the public. Twelve of
the terminals are equipped with mechanical handling devices and 14
have railroad connections. In addition, there are 2 boat basins for
accommodating small craft, 1 of which is municipally owned and
open to the public. The terminals are considered adequate for the
existing commerce. (For latest full description of terminal facilities
see Port and Terminal Facilities at the Port of New York, 1942, Corps
of Engineers.)
    Operations and results during fiscal year.-Final costs of $1,534.70
from regular funds- for new work and $1,751 for maintenance were
reported during the fiscal year for dredging, under contract discon-
tinued April 29, 1942, to a depth of 25 feet in the main channel
from 300 feet east of the New York and Long Branch Railroad
bridge to the junction of the main and south channels, thence in the
south channel to the upper limit of the Titanium Pigment Co. property
and for dredging to 10 feet in the south channel from the upper limit
of the Titanium Pigment Co. property to Crossmar's Dock.
    The cost of the construction, under contract, of drainage ditches in
the vicinity of the approaches to the Victory and Edison Bridges was
$488.43 for new work from regular funds.
    The cost of surveys and engineering preliminary to dredging the
south channel and condition surveys of the main channel was $1,367.48
for new work from contributed funds.
    The total cost of work was $5,141.61-$2,023.13 from regular funds
and $1,367.48 from contributed funds, a total of $3,390.61 for new
work and $1,751 for maintenance. The total expenditure was
 $4,995.78, of which $4,774.13 was from regular funds and $221.65 from
contributed funds.
     Condition at end of fiscal year.-Work under the existing project
was about 87 percent completed. The main channel has been dredged
25 feet deep and 300 feet wide from the junction with New York and
  New Jersey Channels to and including a turning basin of the same
  depth opposite the Government wharf, except for a shoal along the
northerly channel line in the vicinity of the Victory Bridge, thence
  15 feet deep and 200 feet wide to the mouth of the Washington Canal,
thence 10 and 11 feet deep and 100 feet wide to the Delaware and Rari-
tan Canal outlet locks at New Brunswick. The south channel has been
  dredged 25 feet deep and 300 feet wide for a distance of 3,200 feet,
  thence 10 feet deep and 150 feet wide for a distance of 12,400 feet to
  within 1,300 feet of the junction with the main channel at Crab Island.
208        REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,                  1944


   The controlling depths at mean low water are as follows:
                           Section                               Depth           Width                  Date
                                                                 (feet)           (feet)

In main channel from New York and New Jersey Channels to              24           170-300      January 1944.
  junction with the South Channel.
From South Channel junction to the Government wharf                   18           210-300June 1944.
Opposite Government wharf_          - _ - .10                                      260-300          Do.
Turning basin opposite Government wharf
   Westerly half - ---   ... .       . ..------------.........        15      - .........           Do.
   Easterly half
               --.-                                                    8         -                  Do.
From turning basin to the Washington Canal..                          15           100-200      1935.
From Washington Canal to the Delaware and Raritan Canal               10                100     1932 and 1935.
lock at New Brunswick.
In South Channel to upper limit of Titanium Pigment Co.               10           120-300      June 1944.
   Dock.
From upper limit of Titanium Pigment Co. dock to Cross-                  9         90-150      January 1944.
  man's dock.
From Crossman's dock to a point about 6,000 feet below --..              3    . _ .. . 1935.
From a point 6,000 feet below Crossman's dock to junction                1. 5 ....----------- 1935.
   with main channel opposite Crab Island.


   The work remaining to be done under the existing project is the
dredging of the south channel to a depth of 10 feet and 150 feet
wide for a length of 1,300 feet at the upper junction with the main
channel at Crab Island.
   The total cost of the existing project to June 30, 1943, was $1,572,-
651.29-$878,179.72 from regular funds, $292,685.07 from Ordnance
funds, and $57,265.05 from contributed funds, a total of $1,228,129.84
for new work, and $344,521.45 from United States funds for main-
tenance. The expenditures were $1,571,505.46-$1,222,701.17 from
regular funds, $292,685.07 from Ordnance funds, and $56,119.22 from
contributed funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $132,192.35, of which $9,880.78 are contributed
funds, plus $50,000 allotted in July 1944, a total of $182,192.35 will be
applied as follows:
Accounts payable to June 30, 1944_ ----------------------------     $1, 145. 83
Maintenance: Complete by Dec. 5, 1944, under contract in force,
  dredging the south channel from the junction with the main
  channel at Keasby to the upper limit of the Titanium Pigment Co.
  property to 25 feet -------------------------------              181, 046. 52

        Total --------------------------------------------                                        182, 192. 35
   Completion of the existing channel is not considered necessary at
this time. Maintenance dredging will be necessary during the fiscal
year 1946. The sum of $50,000 can be profitably expended during the
fiscal year ending June 30,1946, under contract for maintenance, in the
removal of shoals in the existing channel.
                                     Cost and financial summary
                                       UNITED    STATES      FUNDS

Cost of new work to June 30, 1944_ __1                                                        $1, 551, 335. 04
Cost of maintenance to June 30, 1944----- ------------------                                      455, 940. 88
        Total cost of permanent work to June 30, 1q44                 ---------                2, 007, 275. 92

Net total expenditures ----------------------------------                                     1 2, 007, 275. 92
Unexpended balance June 30, 1944-              -       -                  -     -122,                   311. 57

        Total amount appropriated to June 30, 1944-                                           1 2,129, 587. 49
  I Exclusive of $292,685.07 Ordnance funds expended for new work.
               RIVERS AND HARBORS-NEW                                  YORK, N. Y., DISTRICT                                                 209

    Fiscal year ending June 30                  1940            1941                 1942                   1943                     1944


Cost of new work___                                           $73, 974. 13         $95, 092. 31            -$948. 94                 $2, 023. 13
Cost of maintenance -------------                 $194. 15    212, 696. 64          17, 349. 74               941. 60                 1, 751. 00

       Total cost-----------------                 194. 15    286, 670. 77         112, 442. 05                  -7. 34                 3, 774. 13
Total expended.------------------                  173. 87    277, 847. 13         120, 363. 85                   17. 80                4,774. 13:

Allotted           ..         .... ..----------------------
                                       _      296, 000. 00     70, 000. 00 --------------------------                               114, 488. 35



Balance unexpended July 1, 1943_                                                                                             $12, 597. 35
Amount allotted from War Department Civil Appropriation Act
                        _______
approved June 2, 1943_-----       --                                                                                        122, 000. 00
      Amount to be accounted for---       ---------                                                                          134, 597. 35
Deductions on account of revocation of allotment                                              -                                7,511. 65
       Net amount to be accounted for------------------                                                                      127, 085. 70
Gross amount expended_                                                                                                         4,774. 13
     Balance unexpended June 30, 1944---------------122,                                                                             311. 57
Amount allotted in July 1944                                                                          _50,                           000. 00
           Amount available during fiscal year 1945                              -----------                                 172, 311. 57
Amount (estimated) required to be appropriated for completion
of existing project 2                                                                                                        54, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2                        -50,                                                                        000. 00
  2 Exclusive of available funds.

                                                  CONTRIBUTED          FUNDS

Cost of new work to June 30, 1944                                      -------                                                57, 265. 05
Cost of maintenance to June 30, 1944_-                                       -         -          -              -            --         _

           Total cost of permanent work to June 30, 1944----                                                                  57, 265. 05
Minus accounts payable June 30, 1944----------------------                                                                         1, 145. 83
      Net total expenditures ------------------------------                                                                   56, 119. 22
Unexpended balance June 30, 1944_------_                                                                                       9,880. 78
           Total amount contributed to June 30, 1944---------                                                                 66, 000. 00

    Fiscal year ending June 30                   1940           1941                 1942                 1943                          1944

Cost of new work _$6,185.              46    $16, 182.62                           $32, 486.09             $1, 093.40                $1, 367. 48
                                                         ---                                          _     _        _   _    _     _     _.
Cost of maintenance--------------...-------------

Total expended ------------------                6, 185.46     16, 132. 62          32, 486.09              1, 093.40                        221.65
Contributed-----------              -------    66,000.00........................


Balance unexpended July 1, 1943_--------                                                              _-_                    $10, 102. 43
Gross amount expended- __________----------221.                                                                                        65

      Balance unexpended June 30, 1944---------------                                                                              9,880. 78
Outstanding liabilities June 30, 1944 ------------------------                                                                     1, 145. 83
            Balance available June 30, 1944_-----_                                                                                 8,734. 95


           616634-45--pt. 1,vol. 1-                     14
210            REPORT OF CHIEF OF ENGINEERS,                                  U.      S. ARMY,         1944

           CONSOLIDATED COST AND FINANCIAL SUMMARY, RARITAN RIVER, N. J.

Cost of new work to June 30, 1944_                           -_-_1                                    $1, 608, 600. 09
Cost of maintenance to June 30, 1944_-------                                                 ---          455, 940. 88

      Total cost of permanent work to June 30, 1944                                   ---------        2, 064, 540. 97
Minus accounts payable June 30, 1944------------------                                                      1,145. 83

      Net total expenditures_ _____________-----1                                                      2, 063, 395. 14
Unexpended balance June 30, 1944_                                                                       -132, 192. 35

           Total amount appropriated to June 30, 1944-----------1                                      2, 195, 587. 49


    Fiscal year ending June 30               1940           1941                1942           1943               1944

Cost of new work .....
                    -      ....             $6, 185. 46   $90, 106. 75     $127, 578. 40           $144.46        $3, 390. 61
Cost of maintenance __.......                   194. 15   212, 696. 64       17, 349. 74            941.60         1,751.00
       Total cost-- -------------            6, 379. 61   302, 803.39        144, 928. 14      1,086.06             5,141.61
Total expended -----------------             6, 359. 33   293, 979. 75       152, 849. 94      1,111.20             4, 995. 78
Allotted and contributed--------........   362, 000. 00    70, 000. 00114,                                            488. 35


Balance unexpended July 1, 1943 _                      -$22,                                                      699. 78
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943- _--_-_-_____-___--_                 .                                               122, 000. 00

      Amount to be accounted for_ ______________ -   -    ___144,                                                 699. 78
Deductions on account of revocation of allotment-------------                                                  7, 511. 65

      Net amount to be accounted for_ _ ________-___137,                                                           188. 13
Gross amount expended_                                                                                         4,-----------------------------4
                                                                                                                   995. 78

       Balance unexpended June 30, 1944----_                        ---------------                          132, 192. 35
(Outstanding liabilities June 30, 1944                             _ _ _ _____ _ _ _ _ _                        1, 145. 83

           Balance available June 30, 1944_----------------------                                            131, 046. 52

Amount (estimated) required to be appropriated for completion
of existing project2______________________      _____                                                        54,000.00

Amount that can be profitably expended in fiscal year ending
   June 30, 1946, for maintenance 2_-            _______________  __ -                                        50, 000. 00
1 Exclusive of $292,685.07 Ordnance funds expended for new work.
 :2Exclusive of available funds.

                                     29. SHREWSBURY RIVER, N. J.

  Location.-This river is mainly a large tidal basin in the eastern
part of New Jersey, the outlet being at the southeast end of Sandy
Hook Bay, about 4 miles south from the point of Sandy Hook. (See
U. S. Coast and Geodetic Survey Chart No. 543.)
  Previous projects.-Adopted by River and Harbor Acts of August
30, 1852; March 3, 1871; March 3, 1879, modified in 1883 and 1887;
and by the River and Harbor Act of March 2, 1919. For further
details, see page 1778 of Annual Report for 1915, page 373 of Annual
Report of 1918, and page 267 of Annual Report for 1938.
  Existing project.-This provides for a channel 12 feet deep and
300 feet wide, following the westerly shore, from deep water in
Sandy Hook Bay to a point 600 feet south of the railroad bridge at
HIighlands, a distance of 2.2 miles; thence 9 feet deep and generally
           RIVERS      AND HARBORS-NEW                     YORK,    N.   Y., DISTRICT             211
150 feet wide, suitably widened at bends and turns, in the south branch
of the river to the Branchport Avenue Bridge in the city of Long
Branch, a distance of 6.8 miles; and for a channel in the north branch
6 feet deep and 150 feet wide from the junction to Red Bank, a distance
of 6.1 miles. All depths refer to the plane of local mean low water.
The mean range of tides at the mouth is 4.6 feet; at Highlands Bridge,
3.8 feet; at Seabright, 1.7 feet; at Branchport, 1.7 feet; and at Red
Bank, 3.0 feet. Mean range of spring tides are 5.6, 4.6, 2.1, 2.2, and 3.6
feet, respectively. High easterly or westerly winds cause irregular
tidal fluctuations from 1 to 2 feet above or below the mean range.
   The estimate of cost for new work, revised in 1935, was $539,000,
exclusive of amounts expended on previous projects and exclusive of
$50,000 contributed by local interests. The latest (1935) approved
estimate of annual cost of maintenance is $45,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                Documents I


Mar. 2,1919     Channel 6 feet deep in North Branch-..........     H. Doc. No. 1296, 62d Cong. 3d sess.
Aug. 30,1935    Channel 12 feet deep -------     ----------        H. Doc. No. 157, 71st Cong., 2d sess.
   Do....   -   Channel 9 feet deep -         -          ---       Rivers and Harbors Committee Doc.
                                                                     No. 31, 74th Cong., 1st sess.


  *These documents'contain latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 5 publicly owned and 18 privately
owned wharves used for commercial purposes with a total available
dockage of 5,132 feet. In addition, there are many pleasure-boat land-
ings; these are not open to the public. None of the terminals has
direct rail connections. The terminals are considered adequate for
existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1937. The controlling depth at mean low water when examined
in October 1938, March 1939, and December 1942 was 11 feet for a width
of 100 to 300 feet from Sandy Hook Bay to the highway bridge at High-
lands, thence 5 feet for full channel width in the main stem and South
Branch to the Branchport Avenue Bridge at Long Branch, N. J., and
6 feet for a width of 100 to 150 feet in the North Branch to the head of
the project opposite Maple Avenue, Red Bank, N. J.
   The total cost and expenditures of the existing project to June 30,
1944, were $683,668.22-$466,562.59 for new work and $217,105.63 for-
maintenance. In addition, the costs and expenditures from contrib-
uted funds were $36,311.03, for new work.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
   Maintenance dredging will be necessary during the fiscal year 1946.
The sum of $25,000 can be profitably expended during the fiscal year
ending June 30, 1946, in maintenance dredging to restore the channel
in the vicinity of the Highlands Bridge to project dimensions.
212            REPORT OF CHIEF OF ENGINEERS,                               U.    S. ARMY,                1944

                                        Cost and financial summary

Cost of new work to June 30, 1944__------------                                                      -   1$687, 456. 54
Cost of maintenance to June 30, 1944_---------_                                                              503, 711. 68
              Total cost of permanent work to June 30, 1944-----------                                   1, 191, 168. 22
Net total expenditures -1                                                                                1, 191, 168. 22
Total amount appropriated to June 30, 1944 _                           -                                 1, 191, 168. 22


       Fiscal year ending June 30          1940            1941              1942                1943             1944

C ost of new work .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .. . . . . .
Cost of maintenance.....-------------     $1, 780. 34   $26, 033. 09       $2, 794. 70           $207.19         ---
Total expended -----------------
                ..                         2, 627. 65     26,681. 15        2, 772. 11              229.78
          ----------------------
Allotted ..........                       10, 200. 00    -1, 235. 05       10, 000. 00      -16, 500. 00          -$154. 26


Balance unexpended July 1, 1943_ ________-                                 ---                ---               $154. 26
Deductions on account of revocation of allotment                            --               -                   154. 26
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance ------------------------                                                      25, 000. 00
  1 Exclusive of $36,311.03 contributed funds expended for new work.

                                  30. MANASQUAN RIVER, N. J.

   Location.-This is a small stream located in the eastern part of New
Jersey, rising near Freehold and flowing easterly to the Atlantic
Ocean, about 26 miles south of Sandy Hook. (See U. S. Coast and
Geodetic Survey Chart No. 1216.)
   Previous projects.-Adopted by River and Harbor Act of March 3,
1879. For further details, see Annual Report for 1909, page 186j and
Annual Report for 1938, page 269.\
   Existing project.-This provides for the opening of Manasquan
Inlet and the provision of works designed to secure a channel at least
8 feet deep at mean low water. It also provides for a widening of
the channel to same depth on its northerly side by dredging an area
approximately 200 feet wide by 3,150 feet long. The mean tidal
range in the inlet is 3.9 feet, and at Highway Bridge No. 35, 3,4 feet;
mean ranges of spring tides, 4.8 and 4.1 feet, respectively. The mean
tidal range in the easterly lagoon is about 2 feet.
   The estimate of cost for new work, revised in 1935, was $646,000,
exclusive of amount expended on previous projects, but including
$300,000 contributed by local interests. The latest (1935) approved
estimate for annual cost of maintenance is $20,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                         Documents 1


July     3,1930   Channel 8 feet deep and provision of works de-           H. Doc. No. 482, 70th Cong., 2d sess.
                   signed to secure the channel.
Aug. 30, 1935     Widening of channel on northerly side .--......          Senate        committee       document,       74th
                                                                           SCong.,       1st sess.


  I These documents contain the latest published maps.
        RIVERS AND    HARBORS-NEW        YORK, N.   Y.,   DISTRICT   213
   Recommended modifications of project.-Under date of January 3,
1939, the Chief of Engineers recommended the adoption of a project
entitled "New. Jersey Intracoastal Waterway" to provide a channel
12 feet deep at mean low water and generally 100 feet wide, extend-
ing from the Atlantic Ocean at Manasquan Inlet,'N. J., to Delaware
Bay above Cape May, N. J., by the further improvement of Manas-
quan River and Inlet, N. J., and the present New Jersey Intracoastal
Waterway, and by the construction of a canal of similar dimensions
from Cape May Harbor to Delaware Bay via the New England
Creek Basin, with adequate jetties at the Delaware Bay entrance; all
at an estimated first cost of $2,100,000, with annual maintenance of
$150,000, subject to certain conditions of local cooperation (H. Doc.
No. 133, 76th Cong., 1st sess.).
   Under date of June 21, 1941, the Chief of Engineers recommended
modification of the existing project so as to provide for deepening the
existing Federal channel, including a slight extension, to 12 feet, ex-
cept in the reach seaward of the inner end of the north jetty, where
the depth is to be 14 feet; dredging to a depth of 10 feet an anchorage
of 19 acres south of the existing project; and dredging to a depth of
12 feet an anchorage of 27.5 acres about 0.5 mile west of the Route 35
highway bridge; at an estimated cost of $143,000, with $6,000 annually
for maintenance, in addition to that now required, subject to certain
conditions of local cooperation (H. Doc. No. 356, 77th Cong., 1st sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-Fivesmall landings used by commercial fisher-
men and 7 landings and boat basins, 5 of which are equipped with
marine railways, are available for charter and party fishing boats.
All are located along the Manasquan River and its branches. Two
yacht clubs with a mooring capacity of 51 boats and numerous private
pleasure-boat landings are also located along the waterway. None of
the terminals has railroad connections. The terminal facilities avail-
able are considered sufficient for present requirements.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1938. A rubble-mound jetty 1,230 feet long north of the entrance
and one 1,030 feet long south of the entrance were completed in 1931.
Two steel bulkheads, each 950 feet long, at the inshore ends of the
jetties were completed in 1937. A steel bulkhead 698 feet long and
two steel groins of an aggregate length of 570 feet, constructed on the
northerly beach, were completed in 1938. A channel 10 feet deep and
250 feet wide from the 10-foot contour in the ocean to a point near
the inshore end of the jetties and thence 8 feet deep and 300 feet wide
to a point 700 feet below the New York & Long Branch Railroad
bridge was completed in 1933, and the 200-foot widening on the north-
erly side of the channel was completed in 1937. When examined in
August 1942 and November 1943 the controlling depth at mean low
water through the channel, including the widening on the north side,
was 6 feet for a width varying from 150 to 500 feet.
   The total cost and expenditures of the existing project to June 30,
1944, were $641,456.60-$335,342.16 for new work and $306,114.44 for
maintenance. In addition, the costs and expenditures from contrib-
uted funds were $300,000 for new work.
   Proposed operations.-No funds are available and no work is con-
templated during the fiscal year 1945.
214         REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,                     1944

  Repair of the north jetty will be necessary during the fiscal year
1946. The sum of $75,000 can be profitably expended during the fiscal
year ending June 30, 1946, in repairs, under contract,, to restore the
north jetty to a satisfactory condition.
                                   Cost and financial summary

Cost of new work to June 30, 1944_ _       ____-                                            -     -            1 $374, 342. 16
Cost of maintenance to June 30, 1944_-------                                                      ---             308, 168. 55

       Total cost of permanent work to June 30, 1944-----------   682, 510. 71
Net total expenditures                                          1 682, 510. 71
Total amount appropriated to June 30, 1944        ------        1 682, 510. 71


Fiscal    year ending June 30           1940                  1941                  1942              1943               1944

Cost of new work ... . . .         .        ---- .      - -.          - -    . .-
                                                                            ---..                 -.-..
                                                                                                  . .-                      ---
Cost of maintenance_ .. _--            $41,   167.02       $19, 118.52             $6, 479.86           $404. 24
            .....- _---38, 845. 91
Total expended------                                        22, 229. 68              6,483 86             404. 24
Allotted                                      0------------6,046.
                                                   79        10, 000. 00           25,000. 00     -5,900. 00           -$25, 600.49


Balance unexpended July 1, 1943 ----------------------------                                                         $25, 600. 49
Deductions on account of revocation of allotment_                                                                     25, 600. 49

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_---------------------------------                                                          75, 000. 00
  1Exclusive   of $300,000 contributed funds expended for new work.

    31. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                          (GENERAL)

   The cost of work during the fiscal year amounted to $207,242.99. The
expenditures were $187,498.09. The balance unexpended at the end of
the fiscal year, amounted to $115,895.66, plus $135,000 allotted in July,
a total of $250,895.66, will be applied as needed during the fiscal year
1945 to payment of expenses incurred under this heading. The addi-
tional sum of $150,000 can be profitably expended during the fiscal year
ending June 30, 1946.
                                    Cost and financial summary
Cost of new work to June 30, 1944_----
Cost of maintenance to June 30, 1944_                          --------                                        $2, 158, 004. 27
      Total cost of permanent work to June 30, 1944----------                                                   2, 158, 004. 27
Minus accounts payable June 30, 1944---    ---------                                                                22, 798. 36
      Net total expenditures _                                                                                  2, 135, 205. 91
Unexpended balance June 30, 1944_--                                   ----------                                   115, 895. 66
           Total amount appropriated to June 30, 1944                               ------------                2, 251, 101. 57


   Fiscal year ending June 30             1940                 1941                  1942               1943              1944

C ost of new work .. . . . . . . . . . . . . . . . . . . . . .-..                  . .   . . . . . . . ..
Cost of maintenance--.........      $123, 528.32          $166,442.06          $166,179.63        $119, 340.87          $207, 242.99
Total expended                      -133,     636. 97       170, 224.18            159, 104. 23       122, 060. 65       187, 498.09
Allotted---- ..........                154,000.00          100, 000.00              50, 000. 00    259, 200. 00          165, 000. 00
          RIVERS AND HARBORS-NEW                  YORK,    N.     Y., DISTRICT          215
Balance unexpended July 1, 1943 ___-___-----------                             $138, 393. 75
Amount allotted from War Department Civil Ap-
propriation Act approved April 28, 1942 ..-     $85, 000. 00
Amount allotted from War Department Civil Appro-
priation Act approved July 19, 1937 ----------   80, 000. 00
                                                                                165, 000. 00

       Amount to be accounted for_ ----                   _________             303, 393. 75
Gross amount expended_ ________------                      201, 250. 41
                             -----------------
Less reimbursements collected__                             13, 752. 32
                                                                                187, 498. 09
      Balance unexpended June 30, 1944---------------------                      115, 895. 66
Outstanding liabilities June 30, 1944------_        -     -                  -22,     798. 36
     Balance available June 30, 1944-_        -            --
                                                           ----     _93,             097. 30
Amount allotted in July 1944_-- ____-- -------                      __135,           000. 00
       Amount available during fiscal year 1945--          --       -__         228, 097. 30
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1-         -     -__-___-                        -150,   000. 00
1 Exclusive of available funds.

  32. PRELIMINARY INVESTIGATIONS OF THE ST. LAWRENCE RIVER

   Location.-The International Rapids Section of the St. Lawrence
lies between the State of New York in the United States and the Prov-
ince of Ontario in Canada, generally between the cities of Ogdens-
burg, N. Y., and Cornwall, Ontario. The international boundary
follows approximately the center of the river, leaving the islands
Galop, Ogden, Croil, Long Sault, and Barnhart in the United States,
and the Sheek and Cornwall Islands in Canada. These islands are the
principal ones in this section, although numerous smaller ones exist.
This area for river and harbor and flood-control work is under the
jurisdiction of the district engineer, Buffalo, N. Y.
   Existing project.-There is no existing project; however, an investi-
gation was authorized by Executive Order No. 8568, dated October
16, 1940. The work consists of preliminary investigations and sur-
veys of the International Rapids Section of the St. Lawrence RivPe
with respect to the development of navigation and hydroelectric
power. The proposed plan provides for the development of naviga-
tion by the construction of canals and channels 27 feet deep, with a
depth of 30 feet over the sills of the necessary locks, and also provides
for the development of power by utilizing the difference in head of
about 80 feet between the pool above Long Sault Dam and the river
below.
   The investigation proposes construction to include the following
major items: Canadian and American powerhouses at the foot of
Barnhart Island, Long Sault Canal; two locks extending from Rich-
ards Point, 4 miles northeast of Massena, N. Y., to the mouth of the
Grass River; Long Sault Dam from the New York mainland to the
head of Barnhart Island; Iroquois Point Dam near Iroquois, Canada;
Point Rockway Canal and lock around Iroquois Dam; and channels
and cuts in the St. Lawrence River. In addition some rehabilitation
of towns, relocation of railroads, highways, and transmission lines,
construction of dikes, and adjustments to existing canals are necessary.
   Local cooperation.-None required. However, the Dominion of
Canada, the Province of Ontario, Canada, and the Hydroelectric
216          REPORT        OF CHIEF OF ENGINEERS,                                           U.        S. ARMY,          1944

Power Commission of Ontario have, by furnishing engineering serv-
ices, fully cooperated.
   Operations and results during fiscal year.-The model study of the
Galop Rapids section of the St. Lawrence River was continued and
field surveys in connection therewith were conducted during the fiscal
year. Printing of the final report on the improvement of the interna-
tional section of the St. Lawrence River was completed. Designs and
quantity estimates for various channel arrangements were prepared
and analyzed. The total cost was $98,014.20 for new work, including
a plus adjustment of $67,218.56 in cost reported for previous fiscal
year. The expenditures were $49,293.19.
   Condition at end of fiscal year.-The contract plans, specifications,
design analyses, and cost estimates have been completed for the major
items of construction. Printing of the final report regarding the im-
provement of the international section of the St. Lawrence River has
been completed. A model study of the Galop Rapids section of the
waterway is in progress. The total cost of work to June 30, 1944, was
$1,306,575.38 for new work. The total expenditure was $1,358,435.05.
   Proposed operations.-The balance unexpended at the end of the
fiscal year amounting to $116,119.87, plus accounts receivable of $329.51,
a total of $116,449.38 will be applied as follows:
                              -------------------------------- $642. 36
Accounts payable June 30, 1944_
New work: Completion of model study at Galop Rapids section of
  St. Lawrence River and prosecution of surveys required in con-
  nection therewith     ---------------------------------        80, 000. 00
Available for revocation__---    ------------                    35, 807. 02
          Total--------------------------------- -----                                                                     116, 449. 38
  No funds can be profitably expended during the fiscal year ending
June 30, 1946.
                                       Cost and financial summary
                               EMERGENCY                FUND        FOR THE                PRESIDFNT

Cost of new work to June 30, 1944---                                      ---------                                      $923, 348. 88
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944 ------------ 923, 348. 88
Undistributed costs June 30, 1944_---------               ---      7, 129. 36
       Net total cost to June 30, 1944-------------------------                                                            930, 478. 24
Plus accounts receivable June 30, 1944_---------              ---                                                                41. 70
          Gross total costs to June 30, 1944_------                                                        ---             930, 519. 94
Net total expenditures  _ ----------------------------                                                                     930, 519. 94
Unexpended balance June 30, 1944_---------           ---                                                                    19,480. 06
          Total amiount appropriated to June 30, 1944--------------950, 000. 00

   Fiscal year ending June 30                1940                     1941                       1942            1943              1944

Cost of new work----------------
                  .                                              $570, 770. 61            $297, 580. 62     $78, 400. 88       -$23,    403. 23
Cost of maintenance ............     ..............................................................
Total expended5----           --------------        .     _       6.._ 861.94
                                                                  584,                      315, 647. 42     30, 035. 37               -24. 79
Allotted- -------------                                       -950,       000. 00            - ..
              RIVERS AND HARBORS-NEW                                  YORK,          N.     Y., DISTRICT                 217

Balance unexpended July 1, 1943                                                                                $19, 455. 27
Gross amount expended _                                                                         $3.80
Less reimbursements collected -                                                                 20.99
                                                                                                                  -24.     79

      Balance unexpended June 30, 1944__                                                                        19, 480. 06
Accounts receivable June 30, 1944_                                                                                   41. 70

           Unobligated balance available June 30, 1944-_                                                        19, 521. 76

                                              PUBLIC WORKS            FUNDS


Cost of new work to June 30, 1944-_                                                                            383, 226. 50
Cost of maintenance to June 30, 1944
           Total cost of permanent work to June 30, 1944_                                                      383, 226. 50
Undistributed      costs June 30, 1944-_ - -                                                                    45, 043. 16

       Net total cost to June 30, 1944 _                                                                       428, 269. 66
Plus accounts receivable June 30, 1944-                                                                             287. 81

      Gross total costs to June 30, 1944                                                                       428, 557. 47
Minus accounts payable June 30, 1944 -                                                                              642. 36
      Net total expenditures____.                                                                              427, 915. 11
Unexpended balance June 30, 1944                         ---                                                    96, 639. 81

           Total amount appropriated to June 30, 1944 _                                                        524, 554. 92


   Fiscal year ending June 30                 1940             1941              1942             1943              1944

Cost of new work ..----------------          .--. .-     .....                $311, 378. 55     $17, 649.08        $54, 198. 87
Cost of m aititenance--    - - - - --      - - - - - -- - - -         - - -
                                                                      --         -                  - - -
                                                                                          -----------            - -
'total expeihde 4------------         . --------------                         368, 699.54
                                                                               8------            9, 897. 59       49, 317. 98;
Allotted                              --------------------------               400,000.00                -        124, 554. 92



Balance unexpended July 1, 1943 ...-                                                                           $21, 402. 87
Amount allotted from War Department Civil Appropriation Act
approved June 16, 1933 --------------------------------                                                       124,554. 92
       Amount to be accounted for--------------------                                                          145, 957. 79
Gross amount expended-------------------------     $52, 928. 42
Less reimbursements collected----- --------          3, 610. 44
                                                                                                                49, 317. 98

      Balance unexpended June 30, 1944----------------------96, 639. 81
Outstanding liabilities June 30, 1944----- -------------------- 80, 349. 04

      Balance available June 30, 1944-----------------                                                          16, 290. 77
Accounts receivable June 30, 1944 -----------------------------                                                     287. 81

           Unobligated balance available June 30, 1944-- ------------                                           16, 57&8. 58
218          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                      1944

CONSOLIDATED COST AND FINANCIAL SUMMARY FOR PRELIMINARY INVESTIGATIONS,
                           ST. LAWRENCE RIVER

Cost of new work to June 30, 1944       -$1,                   306, 575. 38
Cost of maintenance to June 30, 1944---------------------------------
      Total cost of permient work to June 30, 1944 ----------                                               1, 306, 575. 38
Undistributed costs June 30 1944_--------------------------                                                     52, 172. 52
       Net total cost to June 30, 1944-----------------------                                               1, 358, 747. 90
Plus accounts receivable June 30, 1944-----------------------                                                       329. 51

      Gross total costs to June 30, 1944---- ---------------- 1,359,077.41
Minus accounts payable June 30, 1944-----------------------         642. 36
                            -----------------------------
      Net total expenditures_                              1, 358, 435. 05
Unexpended balance June 30, 1944--------------------------    116, 119. 87
         Total amount appropriated to June 30, 1944---- --------                                            1, 474, 554. 92


    Fiscal year ending June 30                       1940            1941            1942           1943               1944

Cost of new work                             -              - -   $570, 770. 61   $608. 959.17    $96, 049. 96        $30, 795. 64
Cost of maintenance ....           .--                                                                       - -

Total expended    _            -         -                        584, 861. 94     684, 346. 96    39, 932. 96         49, 293. 19
Allotted_.    -    -       -                     -          --    950; 000. 00     400,000. 00      _124,                  554.92



Balance unexpended July 1, 1943----------------------------                                                      $40, 858. 14
Amount allotted from War Department Civil Appropriation Act
  approved June 16,1933----------------------------------                                                          124,554.92
       Amount to be accounted for--------------------------                                                        165, 413. 06
Gross amount expended -----------------------     $52,924.62
Less reimbursements collected--------------------   3, 631. 43
                                                                                                                   49, 293. 19

      Balance unexpended June 30, 1944---------------- -----                                                     116, 119. 87
Outstanding liabilities June 30, 1944------ -------------------                                                   80, 349. 04
      Balance available June 30, 1944-----------------------                                                        35, 770. 83
Accounts receivable June 30, 1944---------------------------                                                            329. 51
         Unobligated balance available June 30, 1944------------                                                    36,100.34
                                   r
               RIVERS        AY         HARBORS-NEW                    YORK,       N.     Y.,     DISTRICT                 219

33. OTHER NAVIGATION                             PROJECTS FOR WHICH NO ESTIMATES
                                                ARE SUBMITTED

                                                                For last     Cost and expenditures to            Estimated
                                                              full report          June 30, 1944                 amount re-
                    Name of project                           see Annual                                          quired to
                                                                Report
                                                                 for-        New work
                                                                                                                 complete
                                                                                              Maintenance        complete


1. Larchmont Harbor, N. Y. -_     ..--                 ---         1916       $76, 064. 85          $211.42         (2)
2. Echo Bay Harbor, N. Y.3-.........                               1941        64, 583.89         6, 215. 72        (2)
3. New Rochelle Harbor, N. Y.3-        -......                     1941        73, 213.67        21, 223.39         (2)
4. Manhassett Bay, N. y.4 . ...                      ..            1941    .     .      .     . .        .          2 $63, 000
45.Hempstead Harbor, N. Y.3           ------------------           1941        39, 468. 11       65, 937. 23        (2)
6. Glencove Harbor, N. Y.38 ..           ---------                 1911        72, 000.00    -63.000
7. Huntington Harbor, N. Y.4.........                              1942       771, 534. 92       47, 527. 38         8 29,   500
8. Port Jefferson Harbor, N. Y. 34                      .----      1932       171, 426. 71       10, 125. 44        9152, 700
9. Mattituck Harbor, N. Y.3 10 . --....                            1943       133, 344.15       126, 971. 15        (2)
10. G reenport H arbor, N . Y .3 . . . .-. . ..                     1941        74, 680. 83       17, 537. 01        (2)
11. Peconic River, N. Y.3a a . - --......                           1943        25, 000. 00       53, 844.25               .7, 800
12. Sag  Harbor,  N. Y.3 .      .     .       .          .          1941       121, 805. 39                          (2)
13. Great South Bay, N. Y.- --------------------                    1941        99, 820.82       149, 573. 99            6,100
14. Browns Creek, N. y.3                                            1941        33, 976.03        71, 553.82            51, 000
15. Fire Island Inlet, N. Y.a3                                      1943     11594, 354. 69    .... _       --       (2)
16. Sumpawanus (Babylon Creek) Inlet, N. Y.                      _  1895         7,000.00             -      -          16,000
17. Sheepshead Bay, N. y.3                                          1931        33, 827. 59        3, 342. 81        (2)
18. Coney  Island  Channel,  N.   Y.-             -   -----         1941       111, 371.21       217, 265. 00        (2)
19. Coney Island Creek, N. Y.4 .         .                  --      1938        69, 488. 84 ....                        91,000
20. Gowanus Creek Channel, N. Y 3                         ---       1940       145, 000. 00       68, 821.88         (2)
21. Wallabout Channel, N. Y.----------                              1940        18,173.69         34, 845. 24        (2)
22. Harlem River, N. Y. 3 .12--._...                          _.....1943    3, 616, 119. 48      264, 709. 46        (2)
23. Irvington  Harbor,  N. y.4  .........
24. Tarrytown Harbor, N. Y.3 .... - - - - -                         1941                                                15, 000
                                                                    1941        69,836. 48       56,628. 41          (2)
25. Wappinger Creek, N. Y.- ----------                         -    1943        13, 000. 00      40, 832. 02         (2)
26. Saugerties Harbor, N.   Y.3   _..._    ...              _--     1936        81, 904. 91      85, 094.28          (2)
27. Otter Creek, Vt.3 .............................                 1932        60, 253. 50       5, 246. 50            13,500
28. Gordons Landing, Lake Champlain, Vt.3 6_ __                     1892        34, 750.00    ......- -              (2)
29. Channel between North and South Hero
      Islands, Lake Champlain, Vt. 3 6 _-.._._                      1909        31,000.00       -(2)
30. St. Albans Harbor, Lake Champlain, Vt. __                       1917         3, 125.45           384.55          (2)
31. Swanton Harbor, Vt.3 8                                          1888        70, 500. 00 ..-.                      169, 500
32. Rouses Point, Lake Champlain, N. y.3                            1895        98, 467. 55 ----          --         (2)
33. Great Chazy River, N. Y .38_                                    1895        18, 000.00           ....            (2)
34. Plattsburg Harbor, N. Y.3=-__--..----=                          1941       198,415. 13        38,424.75          (2)
35. Port Henry Harbor, N. Y.8 ---------                             1931        69, 406.46
                                                                              13s                  1,252.75                 2,000
36. Ticonderoga River, N. Y. 8                                      1895        16, 500.00                                 26,000
37. Elizabeth River, N. J.4.                                        1941        60, 481.15        58, 791. 21              74,000
38. Rahway River, N. J.4                                            1941       37, 000.00                               35,400
39. Woodbridge Creek, N. J.3                                        1942       49, 822. 70       175, 130. 50        (2)
40. Lemon Creek, Staten Island, N. y.4.........                     1937      146, 621.00        241, 621.00            43, 000
41. Washington Canal and South River, N. J.3 _                      1942    15206, 116. 23       207, 059. 75        (2)
42. Cheesequake Creek, N. J.3-----.--                       -       1928       40,000.  00        24,956.69             50,000
43. Keyport Harbor, N. J.3 ....              -------.               1940       40, 475.00        174, 427. 79        (2)
44. Matawan Creek, N. J.3-                                          1934       21,000. 00         73, 964.09            12,000
45. Shoal Harbor and Compton Creek, N. J.318__                      1941       47, 281.99        189, 708.83         (2)
46. Sandy Hook Bay, N. J.3--                -----                   1943    17508, 936. 40      .......              (2)


  1 Modification of existing project was recommended by the Chief of Engineers, Apr. 10, 1940 (H. Doc.
No. 697, 76th Cong., 3d sess.).
  2 Completed.
  1 Improvement adequate for commerce.
  4 Awaiting local cooperation.
  5 In  addition, $50,000 to be contributed by local interests.
  SNo commerce reported.
  7 Exclusive of $19,545.86 expended from contributed funds.
  8 In  addition, $16,500 to be contributed by local interests.
  * In addition, $57,000 to be contributed by local interests.
  10 $950.73 revoked during fiscal year 1944.
  11 Exclusive of $90,190.39 expended from contributed funds.
  12 $1,000 revoked during fiscal year 1944.
  13 Exclusive of $10,000 expended from contributed funds.
  14These amounts also included in report for New York and New Jersey Channels. No work has been
<lone on the existing project for Lemon Creek.
  15Exclusive of $364.73 contributed funds expended for new work.
  16Modification of existing project was recommended by the Chief of Engineers, Feb. 27, 1940 (H. Doe.
No. 673, 76th Cong., 3d sess.).
  17 Exclusive of $53,790.03 expended from contributed funds.

  * Modification of existing project was recommended by the Chief of Engineers, Mar. 15, 1939 (H. Doc.
No. 237, 76th Cong., 1st sess.).
220-             REPORT OF CHIEF OF ENGINEERS,                                               U. S. ARMY,                  1944

               34. PLANT ALLOTMENT, NEW YORK, N. Y., DISTRICT

                                                       Cost and financial summary
Undistributed costs June 30, 1944--_                                         ---------                                    $4, 582, 941. 99

Net total cost to June 30, 1944        -----------                                                                         4, 582, 941. 99
Plus accounts receivable June 30, 1944----------------------                                                               - 441, 398. 12
      Gross total costs to June 30, 1944                                                                                   5, 024, 340. 11
Minus accounts payable June 30, 1944 -----------------------                                                                  336, 182. 77

                             __-----------
      Net total expenditures---                                                                                            4, 688, 157.34
Unexpended balance June 30, 1944_--------------------------                                                                   752, 508. 71
             Total amount appropriated to June 30, 1944                                       -----------                 5, 440, 666. 05

     Fiscal year ending Sune 30                           1940              1941                  1942             1943              1944

Total expended__.               ____.-------$213,           427. 54 $2, 022, 033. 70     -$131,     423. 26   -$290, 461. 06 -$2,$48,591.19
Allotted --------------------                           230, 706. 31   1, 977, 311. 53 ---                      27, 781. 79      -2,406,927.03


Balance unexpended July 1, 1943_ _-----------                                                                               $315,838. 55
Deductions on account of revocation of allotment                                                                           2, 406, 927. 03
      Net amount to be accounted for_-----------------       -- 2,091 088. 48
Gross amount expended_                        $3,754, 232. 22
Less:
    Reimbursements collected $6, 589, 129. 36
    Receipts from sales            8, 700 05
                                               6 597, 829. 41
                                                            . - 2, 843, 597. 19
      Balance unexpended June 30, 1944                                                                                        752, 508. 71
                                     ----------
Outstanding liabilities June 30, 1944_                                                            336, 182. 77
Amount covered by uncompleted contracts                                                            27, 251. 28
                                                                                                                              363, 434. 05
      Balance available June 30, 1944- ___-                                                       --                          389, 074. 66
Accounts receivable June 30, 1944- _____----------441,                                                                             398. 12
             Unobligated balance available June 30, 1944_ ---.--                                                              830, 472. 78

  Status of all investigations for navigation called for by river and harbor acts and
                                   committee resolutions

                                                                               Date trans-
               Locality                             Authorization act           mitted to                Document No.         lteomenda-
                                                                                Congress                                          tion

Bay Shore Harbor, N. Y -                       River and Harbor Act,
                                                 June 20, 1938.
East River and Flushing                        Rivers and Harbors
Bay and Creek, N. Y.,                           Committee resolu-
seaplane channels and                           tion, Jan. 19, 1940.
anchorage basins in vi-
cinity of North Beach
Airport.
East River and Hell Gate,                      Rivers and Harbors
N. Y., between South                            Committee resolu-
Brother and Berrian Is-                         tion, Apr. 17, 1940.
lands.
Great Lakes-Atlantic Tide-                     Rivers and Harbors
waters Deep Waterway                            Committee resolu-
 (under special board).                          tion, Mar. 7, 1928.
Great Lakes-Hudson River                       Rivers and Harbors
Waterway.                                       Committee resolu-
                                                 tion, Apr. 28, 1942
               FLOOD CONTROL-NEW                            YORK,     N.     Y., DISTRICT             221
Status cf all investigations for navigation called for by river and harbor acts and
                                 committee resolutions-Continued

                                                Date trans-                                  Recommenda-
          Locality                               mitted to
                                   Authorization act                          Document No.       tion
                                                  Congress
                         Hudsn     Rier     canne        an
Hudson River Channel and  Rivers and Harbors
Hudson River, N. Y.               Committee resolu-
                                  tion, May 8, 1941.
Keyport Harbor, N. J -.          River and Harbor Act,
                                   Aug. 30, 1935.
Manhasset Bay, N. Y ...          Rivers and Harbors
                                   Committee resolu-
                                    tion, Mar. 25, 1938.
   Do -----------                Rivers and Harbors
                                   Committee resolu-
                                    tion, Dec. 30, 1938.
Maawan Creek, N. J .             Rivers and Harbors
                                   Committee resolu-
                                    tion, Jan. 24, 1936.
   Do          .                    Rivers
                          .----------------and Harbors
                                    Committee resolu-
                                    tion, Jan. 26, 1940.
New Jersey Intracoastal          Rivers and Harbors
  Waterway in the vicinity         Committee resolu-
of Shrewsbury River, N. J.        tion, Nov. 11, 1943.
New Jersey Intracoastal          Rivers and Harbors
  Waterway,    Manasquan            Committee resolu-
Inlet to Shrewsbury River,         tion, Mar. 23, 1943.
N.J.             "
New York Bay-Delaware            Rivers and Harbors
River section of Intra-            Committee     resolu-
coastal Waterway, water            tion, June 25, 1943.
supply.
Nissequogue River, Long          River and Harbor Act,
  Island, N. Y.                   Aug. 30, 1935.
Raritan River, N. J-- ...-       Rivers and Harbors          Apr. 17, 1944                   Unfavorable.
                                   Committee resolu-
                                    tion, Mar. 27, 1941.
Sandy Hook Bay, N. J      .-     Rivers and Harbors
                                   Committee resolu-
                                   tion, Aug. 21, 1944.
Woodbridge Creek, N. J _-        Rivers and Harbors          Apr. 17, 1944                      Do.
                                    Committee     resolu-
                                    tion, Mar. 24, 1942.



                               35. RUTLAND, OTTER CREEK, VT.

   Location.-Otter Creek rises in the Green Mountains at Dorset, Vt.,
flows generally north about 107 miles and enters Lake Champlain
19 miles south of Burlington, Vt. It has a drainage area of 936
square miles. The city of Rutland is located about 72 miles above the
river's mouth at the junction of East Creek and the main stream.
 (See U. S. Geological Survey map covering Rutland, Vt., quadrangle.)
   Existing project.-This provides for channel clearing and construc-
tion of earth levees and concrete walls along East Creek in the
vicinity of Rutland. The aggregate length of the levees and walls
is about 6,000 feet, of which 4,500 feet are earth embankment and
1,500 feet are concrete walls. The installation of a pumping plant
and the removal of two bridges are included in the project.
   The estimate of cost for new work, revised in 1939, is $308,000,
exclusive of land and other work to be provided by local interests.
   The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936, and modified by the Flood Control Act approved
August 18, 1941. (See S. Doc. No. 171, 76th Cong., 3d sess., which
contains the latest published map.)
   Local cooperation.-See page 7 for requirements. These require-
ments have not been fulfilled.
222          REPORT OF CHIEF OF ENGINEERS,                                                 U.        S. ARMY,      1944

  Operations and results during fiscal year.-The cost of surveys,
preparation of plans, and hydraulic studies was $5,033.64 for new
work. The expenditures were $4,770.15.
    Condition at end of fiscal year.-Preparation of plans has been par-
tially completed. Completion of plans and specifications and con-
struction of the protective works remain to be done. The total cost
was $5,033.64 for new work. The total expenditure was $4,770.15.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $15,229.85 together with accounts receivable
of $63.93 and an allotment of $5,000 made during July 1944, a total of
$20,293.78, will be applied as follows:
Accounts payable June 30, 1944               - - -     - --     $327.
                                                                $-     42
New work: Complete by June 30, 1945, preparation of plans and
  specifications for the authorized local protective works- - 19, 966. 36
          Total           ---------------------------------------------                                                  20, 293. 78
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                         Cost and financial summary
Cost of new work to June 30, 1944_                                                                                        5, 033. 64
                                                                                                                         $-----------
Cost of maintenance to June 30, 1944-
       Total cost of permanent work to June 30, 1944-------                                                                5,033.64
                                     --------------------------
Plus accounts receivable June 30, 1944_                                                                                      63. 93
      Gross total costs to June 30, 1944 -----------------                                                                5097. 57
                                                                                                                          5,
Minus accounts payable June 30, 1944------ --------------------                                                              327. 42
      Net total expenditures---------------------------------                                                             4, 770. 15
Unexpended balance June 30, 1944----------------------------                                                             15, 229. 85
          Total amount appropriated to June 30, 1944---------- ----                                                      20, 000. 00

   Fiscal year ending June 30                  1940                    1941                  1942           1943             1944


Cost of new work-         -..--
                            -   ---- -    --          .--- --    - -    -- ----       -     ----
                                                                                              -     --- -     - -----       $5,033.64
Cost of m aintenance- - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - -
                                 ... ...------
Total expended ......----.....----...                             --   --- --     .         - ---           -- _             4, 770.15
         .........-------------.....--------
Allotted----                                                    -----------               ----------         $20, 000


Balance unexpended July 1, 1943 ----------------------------                                                            $20, 000. 00
Gross amount expended_-------------------------------------                                                               4, 770. 15

       Balance unexpended June 30, 1944 ----------------------- 15, 229. 85
Outstanding liabilities June 30, 1944----------------------------   327. 42

     Balance available June 30, 1944----------------------      14, 902. 43
Accounts receivable June 30, 1944------------------------------      63. 93
     Unobligated balance available June 30, 1944--- -----------                                                          14, 966. 36
Amount allotted in July 1944    --------------------------                                                                5000.
                                                                                                                          5,      00

         Amount available during fiscal year 1945--- --------------                                                      19, 966. 36

Amount (estimated)1- required
                          -   - to be
                                    - appropriated
                                         -      -  for- completion
                                                          -     -  of
existing project                                                     283, 000. 00
1 Exclusive of available funds.
           FLOOD CONTROLr-NEW          YORK,   N.   Y.) DISTRICT            223
           36. NORTH ADAMS, HOOSIC RIVER BASIN, MASS.

   Location.-The Hoosic River rises in northwestern Massachusetts,
flows generally north and northwest, crossing the southwest corner of
Vermont to the vicinity of Eagle Bridge, N. Y., where it turns
west and joins the Hudson River about 16 miles above Troy, N. Y. It
is 66 miles long and has a drainage area of 713 square miles. North
Adams, Mass., is situated on the Hoosic River about 14 miles below the
source of the river. (See U. S. Geological Survey map covering
Greylock, Mass.-Vt., quadrangle.)
   Existing project.-This provides for channel paving of the Hoosic
River and the North Branch to form a flume 6,200 feet long; channel
clearing, earth levees, and concrete walls on the South Branch; and
channel clearing, earth levees, and concrete walls on the main stream at
Braytonville. The aggregate length of the levees and flood walls, in
addition to the concrete flume, is 14,340 feet of which 2,450 feet are
concrete wall and 11,890 feet are earth embankment. Removal of a
portion of the dam and installation of a vertical lift gate in the Phoe-
nix Dam, and the removal of an abandoned dam on the South Branch
are included in the project.
   The estimate of cost for new work, revised in 1938, is $1,471,000 ex-
clusive of land and other work to be provided by local interests.
   The existing project was authorized by tire Flood Control Act ap-
proved June 22,1936, and modified by the Flood Control Act approved
August 18, 1941. (See H. Doc. No. 182, 76th Cong., 1st sess., which
contains the latest published map.)
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to give assurances satisfactory to the Secretary
of War that they will insure against future encroachments upon the
flood channels to be provided by the improvements. These require-
ments have not been fulfilled. However, the Commonwealth of Massa-
chusetts and the city of North Adams have indicated that they are
favorably disposed toward assuming the requirements of local
cooperation in connection with the proposed project.
   Operationsand results during fiscal year.-The cost of surveys, prep-
aration of plans, and hydraulic studies was $11,909.63 for new work.
The expenditures were $11,737.46.
   Condition at end of fiscal year.-The preparation of plans has been
partially completed. Completion of preparation of plans and specifi-
cations and construction of protective works remain to be done. The
total cost was $11,909.63 for new work. The total expenditure was
$11,737.46.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $48,262.54, together with an allotment of
$20,000 made during July 1944, a total of $68,262.54, will be applied
as follows:
Accounts payable June 30, 1944---------------------------- ----          $172. 17
New work: Complete by June 30, 1945, preparation of about 85 per-
  cent of contract plans and specifications for the authorized local
  protective works-------------------------------------_68,               090. 37

      Total-------------------------------------------                 68, 262. 54
224         REPORT OF CHIEF OF ENGINEERS,                                    U.    S. ARMY,               1944

  Funds in the amount of $10,000 can be profitably expended during
the fiscal year ending June 30, 1946, for the completion of contract
plans and specifications.
                                     Cost and financial summary
Cost of new work to June 30, 1944_                                                                          $11, 909. 63
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-----------                                               11, 909. 63
Minus accounts payable June 30, 1944_--        ---------                                                         172. 17

      Net total expenditures_                                                                                11, 737. 46
Unexpended balance June 30, 1944_                                                                            48, 262. 54
         Total amount appropriated to June 30, 1944-------------                                             60, 000. 00

   Fiscal year ending June 30                1940             1941             1942            1943               1944

Cost of new work---------------              .---------------------------- ----------------------------          $11,909.63
Cost of maintenance--
                     -
Total expended- .............
                            ..__----                     -- -                _------ ----
                                                                       - - ---                        -             737. 46
                                                                                                                  11,
                                  ----------------------------- $60, 000...
Allotted-------------------------......................---.............................

Balance unexpended July 1, 1943                     __$60,                                                        000. 00
Gross amount expended                  ---                        __                                         11, 737. 46

      Balance unexpended June 30, 1944---------------                                                        48, 262. 54
Outstanding liabilities June 30 1944 --------------------------                                                  172. 17
     Balance available June 30, 1944_-           ----                                    -___                48,090. 37
Amount allotted in July 1944_ ______------------20,                                                             000. 00

         Amount available during fiscal year 1945-----------                                                 68,090. 37

Amount (estimated) required to be appropriated for completion
of existing project 1                              .
                         -------------------------------             _ _ 1,391, 000. 00

                                               _----
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work 1
  .1 Exclusive of available funds.
                                                         _---_______  -     10, 000.00


                       37. ADAMS, HOOSIC RIVER BASIN, MASS.
   Location.-The Hoosic River rises in northwestern Massachusetts,
flows generally north and northwest, crossing the southwest corner
of Vermont to the vicinity of Eagle Bridge, N. Y., where it
turns west and joins the Hudson River about 16 miles above Troy,
N. Y. It is 66 miles long and has a drainage area of 713 square
miles. Adams, Mass., is situated on the Hoosic River about 6 miles
below the source of the river. (See U. S. Geological Survey map
covering Greylock, Mass.-Vt., quadrangle.)
   Existing project.-This provides for earth levees and concrete walls
along both banks of the river, and channel clearing at Adams. The
aggregate length of the levees and flood walls is about 7,500 feet, of
which 4,400 feet are concrete wall and 3,100 feet are earth embank-
anent.
   The estimate of cost for new work, made in 1938, is $271,000,
exclusive of land and other work to be provided by local interests.
   The existing project was authorized by the Flood Control Act
tapproved August 18, 1941. (See H. Doc. No. 182, 76th Cong., 1st sess.,
which contains the latest published map.)
                 FLOOD CONTROL--NEW                                     YORK,           N.        Y., DISTRICT                               225
    Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to give assurances satisfactory to the Secretary
of War that they will insure against future encroachments upon the
flood channels to be provided by the improvements. These require-
ments have not been fulfilled.
    Operations and resultsduring fiscal year.-The cost of surveys, prep-
aration of plans, and hydraulic studies was $3,609.35 for new work.
The expenditures were $3,078.87.
   -Conditionat end of fiscal year.-The preparation of plans has been
partially completed. Completion of preparation of plans and specifi-
cations and construction of protective works remain to be done. The
total cost was $3,609.35 for new work.                                                  The total expenditure was
$3,078.87.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $6,921.13, together with an allotment of
$12,000 made during July 1944, a total of $18,921.13, will be applied as
follows:

Accounts payable June 30, 1944_ _                                 --------------                                                      $530.48
New work: Complete by June 30, 1945, the preparation of plans and
  specifications for the authorized local protective works                                                         - --             18, 390. 65

        Total--------------------------------------------                                                                           18, 921. 13
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                           Cost and financial summary
Cost of new work to June 30, 1944------------------------------                                                                     $3, 609. 35
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-------                                                                           3, 609. 35
Minus accounts payatle June 30, 1944                                                                                                    530. 48
      Net total expenditures -----------------------------                                                                           3078.
                                                                                                                                     3,    87
Unexpended balance June 30, 1944-------------------------                                                                            6, 921. 13
        Total amount appropriated to June 30, 1944----------                                                                        10, 000. 00

   Fiscal year ending June 30                    1940                   1941     _            1942                   1943                 1944


Cost of new work             ..........----------------.--.--------------...--------------.......--------------                           $3, 609. 35
Cost of maintenance .---------- --. ----.                          .     .   .   . . .        .    .       .   . ..--------------         .
                                                                                                                                          ----. .
Totalexpended ..       ........                  .      ..             .--------
                                                                            -------------              -       --- ---                     3,078.87

Allotted----------------                -------------             --------------------------------                           ----     -10,000.00

Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940-------------------------------------- $10, 000. 00
Gross amount expended            -   --------                       078.87                                                           3,
      Balance unexpended June 30, 1944------------------------                                                                       6, 921. 13
Outstanding liabilities June 30, 1944----------------------------                                                                       530. 48

     Balance available June 30, 1944--------------------------                                                                       6, 390. 65
Amount allotted in July 1944 ----------------------------------                                                                     12, 000. 00

        Amount available during fiscal year 1945--- ----------                                                           _          18, 390. 65

Amount (estimated) required to be appropriated for completion of
existing project 1     __---_-----_-_---_-_---_-_-_-_-_-_-_-_-249. 000. 00
1Exclusive   of available funds.
       616634-45--pt. 1, vol. 1                       15
226    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                 1944

           38. HOOSICK FALLS, HOOSIC RIVER BASIN, N. Y.

    Location.-The Hoosic River rises in northwestern Massachusetts,
flows generally north and northwest, crossing the southwest corner of
Vermont to the vicinity of Eagle Bridge, N. Y., where it turns west
and joins the Hudson River about 16 miles above Troy, N. Y. It is
66 miles long and has a drainage area of 713 square miles. Hoosick
Falls, N. Y., is situated on the Hoosic River about 26 miles above the
mouth. (See U. S. Geological Survey map covering Hoosick, N. Y.-
Vt. quadrangle.)
    Existing project.-This provides for channel widening and for the
construction of earth levees and concrete walls on the east bank of the
river. The aggregate length of levees and flood walls is2,900 feet, of
which 2,000 feet are earth embankment and 900 feet are concrete wall.
The construction of a double concrete box culvert and two stop-log
structures is included in the project.
     The estimate of cost for new work, revised in 1943, is $191,000
exclusive of land and other work to be provided by local interests.
     The existing project was authorized by the Flood Control Act ap-
proved June 22,1936, and modified by the Flood Control Act approved
August 18, 1941. (See H. Doc. No. 182, 76th Cong., 1st sess., which
contains the latest published map.)
     Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to give assurances satisfactory to the Secretary
of War that they will insure against future encroachments upon the
flood channels to be provided by the improvements. These require-
ments have not been fulfilled. The New York State Flood Control
Commission, designated as the local agency for flood-control projects
within the State, declared that it was in general agreement with the
engineering features of the proposed plan and that it was favorably
disposed toward recommending State assumption of local cooperation.
     Operations and results during fiscal year.-The cost of surveys,
preparation of plans, and hydraulic studies was $6,016.28 for new work.
The expenditures were $5,968.59.
     Condition at end of fiscal year.-About 15 percent of all work in
connection with the preparation of contract plans and specifications
has been completed. Completion of contract plans and specifications
and construction of the protective works remain to be done. The total
  cost of the existing project was $6,016.28. The total expenditure was
 $5,968.59.
     Proposed operations...-The balance unexpended at the end of the
  fiscal year, amounting to $4,031.41, together with an allotment of $5,000
  made during July 1944, a total of $9,031.41, will be applied as follows:
Accounts payable June 30, 1944---------------------------------           $47. 69
New work: Complete by June 30, 1945, preparation of contract plans
  and specifications for the authorized local protective works- ------ 8, 983. 72
       Total   ----------------------------------------------           9,031.41

   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                      FLOOD CONTROL-NEW                                  YORK,           N.      Y.,     DISTRICT                               227
                          Cost and financial summary
Cost of new work to June 30, 1944__                                                                                                   $6, 016. 28
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-                                                            -      -               6,016. 28
Minus-accounts payable June 30, 1944_-- --------                                                                            -             47. 69

      Net total expenditures    -----------------------                                                                                5, 968. 59
Unexpended balance June 30, 1944-----------_                                                                                    -      4, 031.41

            Total amount appropriated to June 30, 1944 _                                                                              10, 000. 00
    Fiscal year ending June 30,                       1940                1941                  1942                  1943                  1944


Cost of new work ----                  ----------------------------....--------------                                      ..--------------.. $6, 016. 28
Cost of maintenance -
Total expended-             ....
                            ...        ... -_-            ___- _- - -                - -          --_-                       ..
                                                                                                                           ._-               5,968.59
Allotted- ..--------------------------------------------------------                                                   $10,000

Balance unexpended July 1, 1943---                                               ----------                                          $10, 000. 00
Gross amount expended                                             ------------                                                          5, 968. 59

      Balance unexpended June 30, 1944---_-------                                                                                      4, 031. 41
Outstanding liabilities June 30, 1944 ----------------------------                                                                         47. 69
     Balance available June 30, 1944_                                            -         -             -_                             3, 983. 72
Amount allotted in July 1944----------                                                                         -___                     5,000. 00
            Amount available during fiscal year 1945------------------                                                                 8983.
                                                                                                                                       8,    72
Amount (estimated) required to be appropriated for completion of
    existing project            1              _ _ _ __                                                                      _       176, 000. 00
   l Exclusive of available funds.

39. PRELIMINARY                        EXAMINATIONS, SURVEYS,                                          AND          CONTINGENCIES
                                           FOR FLOOD CONTROL
  The cost of work during the fiscal year amounted to $11,301.07. The
expenditures were $11,573.25. The baance unexpended at the end of
the fiscal year, amounting to $3,436.13, together with an allotment of
$9,750 made in July 1944, a total of $13,186.13, will be applied as
needed during the fiscal year 1945 to payment of expenses incurred
under this heading. The additional sum of $18,000 can be profitably
expended during the fiscal year ending June 30, 1946.
                           Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                                                   ---                   $155, 325. 09
      Total cost of permanent work to June 30, 1944------------                                                                      155, 325. 09
Minus accounts payable June 30, 1944-_ ---------------                                                                                    211. 22
      Net total expenditures_--------                                                             -            -___                  155, 113. 87
Unexpended balance June 30, 1944-------------___                                                                                       3,436. 13
            Total amount appropriated to June 30, 1944--------------                                                                 158, 550. 00

    Fiscal year ending June 30                        1940                1941                  1942                  1943                  1944

Cost of new work ..
Cost of maintenance _....               -..... $21,750. 58              $8,915.20              $9,298.28            $6. 560.06            $11, 301.07

Total expended......-----------------.......        22,097.57            8,460.23               9, 887.63            6,552.97               11, 573.25
Allotted.----------------------......               12, 000. 00          8,250.00 ----------                        18,800.00 I--
228            REPORT           OF      CHIEF OF               ENGINEERS,                      U.       S.   ARMY,          1944


Balance unexpended July 1, 1943_---
                                  ___                                            ----------                                   $15, 009. 38
Gross amount expended_-- -____---------_                                                                                        11, 573. 25
       Balance unexpended June 30, 1944___                                                                                         3, 436. 13
Outstanding liabilities June 30, 1944_---------                                                                       ---             211. 22
     Balance available June 30, 1944_---                                            -----                      _3,                    224. 91
Amount allotted in July 1944------------------                                                                  _9,                   750. 00
            Amount available during fiscal year 1945                                  ------------                             12, 974. 91

Amount that can be profitably expended in fiscal year ending June
                           1
30, 1946, for maintenance                             -      __------18, 000. 00
     1 Exclusive of available funds.


40. OTHER FLOOD-OONTROL PROJECTS FOR WHICH NO ESTIMATES
                      ARE SUBMITTED

                                                                     For last full    Cost and expenditure to                      Estimated
                                                                     report, see           June 30, 1944                             amount
                      Name of project                                  Annual                                                      required to
                                                                       Reportrcompret
                                                                        for-        New work      Maintenance                      complete


1. Lamoille River, Vt.1                     -                             1939             2   $49, 837.43   --------------            3$26, 500
2. Waterbury, Winooski River Basin,
                                  4
                                         Vt.......                        1941                                                          880, 000
3. Proctor, Otter Creek Basin, Vt.            --                          1937         -            -                                   3 22, 500
4. Bennington, Hoosic River Basin, Vt.....                                1941     -------------------------------                      291, 000
5. Waterford, Hudson, and Mohawk Rivers,
               . . . . . ..
      N . Y .4 _.               - - ..--
                                       - - - - --                         1939        -           -           -         -315,000
6. Winooski River, Vt_    ---- _-__----1940                                               4, 897, 427. 37                              (5)


     1 1 unit of project completed; remaining unit awaiting local cooperation.
     2 Includes $23,507.43 emergency relief funds.
     3 Completion not desired by local interests.

     4 Awaiting local cooperation.
     e Completed.


       Status of all investigations for flood control called for by flood control acts and
                                     committee resolutions

                                                                            Date trans-Recommen-
              Locality                      Authorization act               mitted to       Document No.                       Recmen
                                                                             Congress                                             dation


Ausable River Basin, N. Y.,   Commerce Commit-_        .....                ....            .................
  at and in the vicinity of     tee resolution, Dec.
  Lake Placid, N. Y.            1, 1943.
Blind Brook and tribu- Flood Control Act, ...                     ...            ..      ..         ...         ......                   . ...
  taries, New York.             Aug. 18, 1941.
Bronx River and tribu- _. .do .. . . . . . . .. . . . . . . .. . .. . . . . . . .. . . . . .
  taries, New York.
Hutchinson River and trib-     .. do ..
  utaries, New York.
Kinderhook Creek, N. Y.       Commerce Commit-__        ....                . ...            . .....                      .....            ...
  and Mass.                     tee resolution, Oct.
                                28, 1941.
Mamaroneck and Sheldrake      Flood Control Act,
                                Aug. 18, 1941.
                                                                         -........   ...........                                 .......
  Rivers, and their tribu-
  taries, New York.
Passaic River, N.J .. ...     Flood Control Act, ....                 ....            ...........                                .......
                                May 6, 1936.
     Do___ ------_ ..      .. Flood Control Act, ..        .        . . . ..                    . ..          .        ..        . . . ..
                                June 22, 1936.
Saw Mill River and tribu- Flood Control Act,                 .........................................
  taries, New York.              Aug. 18, 1941.
Winooski River and tribu- Flood Control Com-
  taries, VermOnt, final re-    mittee    resolution,
  port.                         June 20, 1940.
Winooski River and tribu- ...-.do-  o-                May 25,1944 H. 629,78th Cong.,                                            Favorable.
  taries, Vermont, interim                                                               2d sess.
   report covering the exist-
  ing Waterbury, Wrights-
   viUle, and East Barre
   Dams.
                 FLOOD CONTROL--SYRACUSE,              N.   Y., DISTRICT           229
FLOOD CONTROL IMPROVEMENTS IN THE SYRACUSE,
                N. Y., DISTRICT

   This district comprises the watershed of the Mohawk River and its
tributaries in noirtheastern New York, the watershed of the Oswego
River and its tributaries in northern New York, and the watershed
of the Susquehanna River and its tributaries, above and including
Shamokin Creek, in south central New York and northern Pennsyl-
vania.
   District engineer: Lt. Col. J. H. Elleman, Corps of Engineers.
   Division engineer: Brig. Gen. B. C. Dunn, United States Army, to
January 8, 1944, and Col. A. H. Burton, Corps of Engineers, since that
date.
                                        IMPROVEMENTS

                                 Flood-control projects
                                         Page                                      Page
1.   Syracuse,    Oswego      River            11. Williamsport, Susquehanna
         Basin, N. Y_                     229         River, Pa_                    261
2.   Owasco Lake, Oswego River                 12. Wilkes-Barre-Hanover Town-
         Basin, N. Y                      231         ship, Susquehanna River,
3.   Canandaigua Lake, Oswego                        Pa_                           263
         River Basin, N. Y ...            233   13. Kingston-Edwardsville, Sus-
4.   Keuka Lake, Oswego River                        quehanna River, Pa ....       265
         Basin, N. Y_                     234   14. Plymouth, Susquehanna Riv-
5.   Hammondsport,         Oswego                    er, Pa                        267
         River Basin, N. Y ...            236   15. Sunbury, Susquehanna Riv-
6.   Ithaca, Oswego River Basin,                     er, Pa                        268
         N.Y                              237   16. Swoyersville and Forty Fort,
7.   Watkins Glen, Oswego River                      Pa_                           269
         Basin, N. Y__     _       --     238   17. Preliminary    examinations,
8.   Montour Falls, Oswego River                     surveys, and contingencies
         Basin, N. Y_                     240         for flood control----         271
9.   Southern New York flood                   18. Other flood-control projects
         control project                  242         for which no estimates are
10.   Stillwater Reservoir, Lacka-                    submitted------------         271
        wanna River, Pa      .   .        260

                  1. SYRACUSE, OSWEGO RIVER BASIN, N. Y.
  Location.-Syracuse, N. Y., is located in Onondaga Cohnty at the
southern end of Onondaga Lake. (See U. S. Geological Survey topo-
graphical map of New York State.)
  Existing project.-The plan of improvement provides for increas-
ing the capacity of Onondaga Creek Channel through the city between
Atlantic and Dorwin Avenues, 4.5 and 6.3 miles, respectively, above
the mouth of Onondaga Creek from 1,000 to 6,000 cubic feet per second
by widening and realining the channel and constructing a levee on
the right bank just south of Atlantic Avenue. Two new bridges will
be required over the new channel.
  It also provides for constructing a retention reservoir on the south
branch of Onondaga Creek about 121/2 miles above the mouth of
Onondaga Creek, with a capacity of 12,800 cre-feet at spillway crest,
consisting of an earth dam 66 feet high, a concrete spillway channel,
and an outlet tunnel with appurtenant structures; and for construct-
ing a retention reservoir on the west branch of Onondaga Creek about
13 miles above the mouth of Onondaga Creek, with a capacity of 7,400
acre-feet at spillway crest, consisting of an earth dam 45 feet high,
230       REPORT OF CHIEF OF ENGINEERS,                              U.     S. ARMY,        1944

a concrete spillway channel, and an outlet tunnel with appurtenant
structures. This will provide protection for the city of Syracuse
against a flood approximately 70 percent greater than the largest
of record.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $2,210,000 for construction, and the
estimated local cost is $475,000 for lands and damages.
   The principal features of the reservoirs are shown in the following
table:
                                           Dams and reservoirs

                            Distance                                                   Estimated cost
                             above                               Reservoir-
Name      Nearest city      mouth of       Height      Type      Reservoi
                           Onandaga                               capacity Constrtlc- Land and Total
                             Creek                                           tion     damagestl

                              Miles         Feet               Acre-feet
  4A Syracuse, N. Y___            12            66 Earth fill__ 12,800 $1, 062,000         $209, 000   $1, 271, 000
  5A .....-
         do- ........             13                  do------
                                                45 ....           7, 400   768, 000        136, 000        904, 000

             Total.................------------------------------- ---------- 1,830, 000    345,000     2,175, 000

1To be borne by local interests.

   Local cooperation.-The improvement is subject to the condition
that responsible local agencies furnish assurances satisfactory to the
Secretary of War that they will provide without cost to the United
States all lands, easements, and rights-of-way necessary for the con-
struction of the project including the reservoirs; hold and save the
United States free from claims for damages due to the construction
work; maintain and operate the works after completion in accordance
with regulations prescribed by the Secretary of War; take such
measures as may be necessary to prevent any encroachments upon
the flood channel capacities to be provided by the proposed improve-
ments; and bear the expense of all utility and bridge changes.
Assurances have been received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were continued by hired
labor. The cost of this work was $51,780.54 for new work. The
expenditures were $53,880.61.
   Condition at end of fiscal year.-Preparation of plans is under way.
Construction has not been initiated. The cost of this work was
$60,788.73 for new work. The expenditures, all for new work, were
$60,858.94.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $119,141.06, plus accounts receivable, $449.27, amounted to
$119,590.33. This amount will be applied as follows:
Accounts payable, June 30, 1944_------------------------------                                         $379. 06
New work: Completion of engineering studies, design, plans, and
  specifications for dam, reervoir, and channel improvement on
  Onondaga Creek; period July 1944 to December 1944:
    Design (hired labor) -----------------------------------                                     119,211. 27
        Total- -           -------------                                                   -119,        590. 33
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                           FLOOD CONTRO--SYRACUSE,                                 N.    Y., DISTRICT                           231
                                                    Cost and financial summary
Cost of new work to June 30, 1944_ ___--                                                                                 $60, 788. 73
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944-----------                                                           60, 788. 73
Plus accounts receivable June 30, 1944------------------------                                                                449. 27
      Gross total costs to June 30, 1944------------------61,                                                                238. 00
Minus accounts payable June 30, 1944_--_ _-                                                                                  379. 06
      Net total expenditures_                                                                                    -        60, b58. 94
Unexpended balance June 30, 1944                                                                 _119,                        141. 06
             Total amount appropriated to June 30, 1944-------------                                                     180, 000. 00


    Fiscal year ending June 30                          1940           1941             1942              1943               1944

Cost of new work__.-----__-______                           -____
                                                     _____________   - -----     ----     -$9,                008. 19        $51,780. 54
Cost of m aintenance ..      .                    .-------------            . . -. . -----------..
                                                                  ------ ------       . . . . . . . .     .     . . ..    . . . . .------
Total expended...              .____                               __________                             6, 978. 33         53,880. 61
Allotted ---------------------------------------.....--------                                           180, 000. 00



Balance unexpended July 1, 1943 ----------------------------- $173, 021.67
Gross amount expended ------------------------------------ 53, 880. 61

       Balance unexpended June 30, 1944______                                                                            119, 141. 06
Outstanding liabilities June 30, 1944_                                                                                        503. 80
      Balance available June 30, 1944-----------------118,637. 26
Accounts receivable June 30, 1944_                        449. 27
             Unobligated balance available June 30, 1944-------------119, 086. 53
Amount (estimated) required to be appropriated for completion
of existing project 1_-    -    -    -     -       --        2, 030, 000. 00
  1Exclusive of available funds.

                            2. OWASCO LAKE, OSWEGO RIVER BASIN, N. Y.

   Location.-Owasco Lake, N. Y., is located in the central portion of
the Oswego River watershed. The city of Auburn, N. Y., is situated
at the outlet at the northern end of the lake. The outlet flows north-
erly for 17 miles and empties into the Seneca River. (See U. S.
Geological Survey topographic maps of New York State.)
   Existing project.-There is an old masonry dam, known as the
State Dam, in the city of Auburn across the outlet channel about
9,600 feet downstream from the lake. The plan of improvement pro-
vides for the replacing of the old dam with a new dam about 9,400
feet downstream from the lake, consisting of a rolled earth section and
a concrete spillway section, sluice gates, head gates, a concrete wall
between the power inlet and sluiceway, and the improving and deepen-
ing of the channel through a length of about 9,600 feet. The improved
channel will be 15 feet wide at the bottom, with side slopes of 1 on 2
in earth and 4on 1 in rock.
   The project will afford a substantial reduction of flood heights at
Auburn and Owasco Lake in general.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (HI. Doc. No. 846, 76th Cong., 3d sess.).
232       REPORT OF CHIEF OF ENGINEERS,                                U.           S. ARMY,                1944

   The estimated cost is $113,000 for construction, including $7,000 to
be contributed by local interests. The estimated local cost for lands
and damages is $1,000.
   Recommended modifications of project.-Underdate of May 11, 1942,
the Chief of Engineers recommended improvement of Owasco Inlet,
Montville Creek, and Dry Creek at an estimated cost of $48,700, im-
provement of State Ditch and Owasco Outlet at an estimated cost of
$13,100, and improvement of Crane Brook at an estimated cost of
$2,400, subject to certain conditions of local cooperation (H. Doc. No.
815, 77th Cong., 2d sess.).
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
prevent any encroachments upon the flood channel capacities to be
provided by the proposed improvements; contribute $7,000 which is
the excess cost of providing new control gates for the raceway to the
pumping plant; secure the necessary agreements to permit regulation
of lake levels; remove the remaining portion of the old prison dam
and the abandoned masonry columns and wall near Genesee Street
Bridge; relocate the pipe under the Genesee Street Bridge; and re-
move that portion of the Goldman block on North Street which
obstructs the outlet channel. Assurances have not as yet been received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were continued by hired
labor. The cost of this work was $13,697.34 for new work. The ex-
penditures were $13,758.03.
   Condition at end of fiscal year.-Preparation of plans is underway.
Construction has not been initiated. The cost and expenditures, all for
new work, were $15,707.33.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $5,292.67, will be applied to new work, completion of en-
gineering studies, design, plans and specifications for improvement of
the Owasco Lake outlet channel by hired labor; period July 1944 to
June 1945.
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                    Cost and financial summary
Cost of new work to June 30, 1944___                                                                              $15, 707. 33
Cost of maintenance to June 30, 1944
        Total cost of permanent work to June 30, 1944-                                      _        -             15, 707. 33
Net total expenditures_-               --------                        ----                     ____               15, 707. 33
Unexpended balance June 30, 1944 __________                       -_____                                            5, 292. 67
        Total amount appropriated to June 30, 1944---------                                                        21, 000. 00


   Fiscal year ending June 30          1940            1941                 1942                     1943              1944

Cost of newwork----             ____-----------------     ----
                                                 _______________. __        .       .               $2,009.99         $13,697.34
Cost of maintenance._                        -     --...-                       -       -       -     ,    --            ,--- 0
Total expended-----_-_---__-----_-_-_--                  _---_-_---                                  1, 949. 30        13, 758. 03
Allotted------------------------------------------.-----21,000. 00
                  FLOOD CONTROL---SYRACUSE,             N.   Y., DISTRICT          233

Balance unexpended July 1, 1943 -------------------------------             $19, 050. 70
Gross amount expended--------------------------- $13, 758. 25
Less reimbursements collected----------------- -----         0. 22
                                                                             13, 758. 03

        Balance unexpended June 30, 1944 -----------------------              5, 292. 67

Amount (estimated) required to be appropriated for completion
of existing project 1----------------------------------------- _               85, 000
I Exclusive of available funds.

           3. CANANDAIGUA LAKE, OSWEGO RIVER BASIN, N. Y.

   Location.-CanandaiguaLake is the most westerly of the Finger
Lakes in the Oswego River watershed. The lake outlet flows north-
eastward and joins the Clyde River at Lyons, N. Y. The city of
Canandaigua is located at the north end of the lake near the outlet.
 (See U. S. Geological Survey topographic maps of New York State.)
   Existing project.-The flow from Canandaigua Lake is carried by
two bhannels at its northerly end, the outlet and a feeder canal which
join about 2 miles below the lake. The plan of improvement provides
for the improvement of the outlet channel from the outlet sill to a
point about 4 miles downstream, so as to secure a minimum bottom
width of 20 feet with side slopes of 1 on 2 feet; the improvement of
the feeder canal for its total length of about 1 miles from the lake
to its confluence with the outlet channel, so as to secure a bottom width
of 20 feet with side slope of 1 on 21/2 feet; and the lowering of the
outlet sill 11/4 feet.
   The project will afford a substantial reduction in flood stages on
Canandaigua Lake.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $29,000 for construction, and the esti-
mated local cost is $1,000 for lands and damages.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
prevent any encroachments upon the flood-channel capacities to be
provided by the proposed improvements and secure the necessary
agreements to permit regulation of lake levels. Assurances have been
received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were started by hired
labor. The cost and expenditures were $2,847.49 for new work.
   Condition at end of fiscal year.-Preparation of plans is underway.
Construction has not been initiated. The cost and expenditures were
$2,847.49 for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $152.51, plus the sum of $6,000 allotted in July 1944,
amounted to $6,152.51. This amount will be applied to new work,
completion of engineering studies, design, plans, and specifications for
improvement of the Canandaigua Lake outlet channel and lowering
of outlet sill by hired labor; period July 1944 to January 1945.
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
234            REPORT OF CHIEF OF ENGINEERS,                                                      U.   S. ARMY,                 1944

                                                Cost and financial summary
Cost of new work to June 30, 1944-_                                                                                               _$2, 847. 49
Cost of maintenance to June 30, 1944
            Total cost of permanent work to June 30, 1944---                                               ---------                   2, 847. 49
Net total expenditures--
                     ___      --------                                                                        ______                    2, 847. 49
Unexpended balance June 30, 1944                             _-                               -        -      -             -              152. 51

            Total amount appropriated to June 30, 1944--------                                                                          3, 000. 00


    Fiscal year ending June 30                    1940                   1941                      1942              1943                 1944

Cost of new work .                     .                  -------------------- .                                                          $2,847.49
Cost of maintenance ........                      -     . . .-...
                                                      -....                        ..    .-                             --       -4-
Total expended ...        -.-.......       L-                                                                                              2,847.49
Allotted- ...........                                                                   ------------.                  $3,000 -

                                                                                                                                           /
Balance unexpended July 1, 1943-----------------------------
Gross amount expended ---------------------------
                                                                    $3,      00                                                           00000.
                                                        $2, 886. 49
Less reimbursements collected_
                             --------------------------      39. 00
                                                                     2, 847. 49
     Balance unexpended June 30, 1944----------------------- -                                                                             152. 51
Amount allotted in July 1944-------------------------                                                                                   6, 000. 00
            Amount available during fiscal year 1945---- --------------                                                                 6, 152. 51
Amount (estimated) required to be appropriated for com-
pletion of existing project 1- - - - - - - - - - - - - - - - - - - - - - - - - -                                 - - - - --
                                                                                                                                       20, 000. 00
1Exclusive of available funds.

                        4. KEUKA LAKE, OSWEGO RIVER BASIN, N. Y.

   Location.-Keuka Lake, N. Y., is located in the southwestern portion
of the Oswego River watershed and is shaped in the form of a Y. The
outlet is at the northern end of the eastern branch of the lake. The
village of Penn Yan is situated at the northern end of the lake along
the outlet. (See U. S. Geological Survey topographic maps of New
York State.)
   Existing project.-There is adam across the oitlet channel about
1 mile downstream from the lake, with raceways at both ends. Two
streams enter the outlet channel between the lake and the dam. The
plan of improvement provides for removing shoals in the channel just
upstream from the dam and at the mouths of the two streams entering
the outlet channel, replacing the present small gate in the raceway at
•the southern end of the dam by a single modern structure and appur-
tenances, and lowering the sill 2 feet.
   The project will afford a substantial reduction in flood stages in
Keuka Lake.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d ssss.).
   The estimated Federal cost revised in 1944 is $37,700 for construc-
tion, and the estimated local cost is $1,800 for lands and damages.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
                   FLOOD CONTROIr--SYRACUSE,                          N.   Y., DISTRICT              235
prevent any encroachments upon the flood-channel capacities to be
provided by the proposed improvements, and secure the necessary
agreements to permit regulation of lake levels. Assurances have been
received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were started by hired
labor. The cost of this work was $3,000 for new work. The expendi-
tures were $2,621.42.
   Condition at end of fiscal year.-Preparation of plans is under way.
Construction has not been initiated. The cost was $3,000 for new work.
The expenditures, all for new work, were $2,621.42.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $378.58, plus the sum of $6,000 allotted in July 1944,
amounted to $6,378.58. This amount will be applied as follows:
Accounts payable, June 30, 1944 --------------------------------                                $378.58
New work: Completion of engineering studies, design, plans, and
  specifications for flood protection on Keuka Lake outlet; period
  July 1944 to March 1945:
       Design (hired labor)_--      ------             -______                                 6, 000. 00
           Total       --------------------------------------------                            6, 378. 58
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                      Cost and financial summary
Cost of new work to June 30, 1944 ___$3,                                                          000. 00
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-------------                               3, 000. 00
Minus accounts payable June 30, 1944_--------             ---                                     378. 58
     Net total expenditures --------------------------------                                   2, 621. 42
Unexpended balance June 30, 1944_---------             --                                     -378. 58
        Total amount appropriated to June 30, 1944---------------                              3, 000. 00

   Fiscal year ending June 30             1940             1941            1942     1943          1944

Cost of new work---..--.------------------------------------------------------                    $3, 000.00
Cost of maintenance ..-------------                  -           .   --..
                                        _--------------
                                 ____--------------           -_               .                   2, 621.4
Total expended       -
                      ....
Allotted -----------------          -----------------..--------------                      -3,000-----------


Balance unexpended July 1, 1943                                                               $3, 000. 00
Gross amount expended-- ____---------------2,                                                     621. 42
      Balance unexpended June 30, 1944------------------------ -378.     58
Outstanding liabilities June 30, 1944_-- -----------                 97. 00

     Balance available June 30, 1944_--------                                       ---           281. 58
Amount allotted in July 1944----       -----------                                             6, 000. 00

        Amount available during fiscal year 1945------------------                             6, 281. 58

Amount (estimated) 1 required      to be appropriated for completion
                       - - -- - - - -- - - -- - - - -- - - - -- - - - -- - - - -- - - -
of existing project                                                          _         -         28, 700
1Exclusive of   available funds.
236     REPORT OF CHIEF         OF ENGINEERS,     U.   S. ARMY,     1944

           5. HAMMONDSPORT, OSWEGO RIVER BASIN, N. Y.
   Location.-The village of Hammondsport, N. Y., is located in Steu-
ben County and is situated at the southern end of Keuka Lake. (See
U. S. Geological Survey topographic maps of New York State.)
   Existing project.-The lower portion of Glen Brook, from its mouth
at Keuka Lake to a point about 2,450 feet upstream, is carried by an
existing concrete flume, the safe carrying capacity of which is limited
by a 90 ° bend at its upper end to 1,800 cubic feet per second. The
plan of improvement provides for increasing the channel capacity to
5,000 cubic feet per second by widening, deepening, and straightening
the upper 700 feet of the present flume, constructing reinforced-con-
crete cascades at the bend, clearing the channel above the flume, and
constructing 4 timber check dams in the channel above the flume to
reduce debris deposited in the flume. This will provide a safe channel
capacity of 5,000 cubic feet per second for Glen Brook, or approxi-
mately 40 percent greater than the discharge of the largest flood of
record.
    The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d sess.).
   The estimated cost is $163,000 for construction, and the estimated
local cost is $2,000 for lands and damages.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
prevent any encroachments upon the flood channel capacities to be
provided by the proposed improvements. Assurances have been
received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were started by hired
labor. The cost of this work was $4,968.98 for new work. The
expenditures were $4,507.68.
   Condition at end of fiscal year.-Preparation of plans is under way.
Construction has not been initiated. The cost was $4,968.98 for new
work. The expenditures, all for new work, were $4,507.68.
   Proposed operations.-The unexpended balance at the end of the
fiscal year; $1,492.32, plus the sum of $15,000 allotted in July 1944,
amounted to $16,492.32. This amount will be applied as follows:
Accounts payable, June 30, 1944 _ _--         _   _       ___------------$461. 30
New work: Completion of engineerir g studies, design, plans, and
  specifications for the improvement of Glen Brook; period July 1944
  to April 1945:
    Design (hired labor) _--_________---     --         ________ -   16, 031. 02
      Total_     _- -_--16,492.32
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                             Cost and financial summary
Cost of new work to June 30, 1944      _        -  -     -    -   $4, 968. 98
Cost of maintenance to June 30, 1944___________
       Total cost of permanent work to June 30, 1944-------------  4, 968. 98
Minus accounts payable June 30, 1944 --------------------------       461. 30
       Net total expenditures                                      4, 507. 68
Unexpended balance June 30, 1944-           -      -       -       1, 492. 32
       Total amount appropriated to June 30, 1944_                 6, 000. 00
                     FLOOD CONTROL---SYRACUSE,                                N.    Y.,       DISTRICT                          237

   Fiscal year ending June 30                     1940             1941            1942              1943                   1944


C ost of new w ork .. -   .     ..           _.      ..- _-_..-           -   -    ....---                                  $4, 968. 98
Cost of m aintenance - - - - - - -- - - - - - - - - - - - - - - - - - - - -
Total expended-----------------------                                                               -4,                        507. 68
Allotted -.   ...                       --        -- -      -$6,                                            000   -     -




Balance unexpended July 1, 1943_-------------------------------                                                   $6,000.00
Gross amount expended                                                                                                    507. 68
                                                                                                                      4,---------------------------

       Balance unexpended June 30, 1944-----------------_                                                              1, 492. 32
Outstanding liabilities June 30, 1944_----------------------------                                                         97. 00

     Balance available June 30, 1944-----_---------------                                                              1, 395. 32
Amount allotted in Jury 1944----------------------------                                                              15, 000. 00

          Amount available during fiscal year 1945------------------                                              16, 395. 32

Amount (estimated)     required     to be appropriated for completion of
                             -- -- - -- -- -- - -- -- -- -- -- -- -- -- -- -- -- - -- -
existing project 1- - - - -                                                            142, 000.00
  1 Exclusive of available funds.

                          6. ITHACA, OSWEGO RIVER BASIN, N. Y.

    Location.-The city of Ithaca, N. Y., is located in Tompkins County
and is situated at the southern end of Cayuga Lake. (See U. S. Geo-
logical Survey topographical maps of New York State.)
    Existing project.-Fall Creek flows along the northern edge of the
city and discharges into Cayuga Lake, and Cascadilla Creek flows
through the center of the city and empties into Cayuga Inlet about
1/2 -mile above its mouth. The plan of improvement provides for
widening Fall Creek channel from the foot of the falls at Lake
Street to a point 2,900 feet downstream and for constructing levees
on both banks of the channel, the levee on the left bank to be 5 fed
higher than the levee on the right bank so as to protect the left bank
from flows of 20,000 cubic feet per second and the right bank from
flows of 14,000 cubic feet per second; protecting the Fall Creek
channel slopes upstream from the railroad bridge with a concrete
crib wall and protecting bridge piers and abutments with riprap;
increasing the capacity of Cascadilla Creek channel from 1,200 to
1,800 cubic feet per second by clearing the channel from the mouth
of the gorge to Lincoln Street, a distance of about 4,200 feet; pav-
ing the bottom of Cascadilla Creek channel at the bend near
Cayuga Street bridge; and constructing a timber check dam at the
mouth of the gorge to reduce debris deposits in the channel.
    The plan of improvement for Fall Creek will protect the area along
the left bank from floods about 30 percent greater than the largest
flood of record and along the right bank from floods approximately
equal to the largest flood of record. The plan for Cascadilla Creek
will provide protection against floods about 30 percent greater than
the largest flood of record.
    The existing project was authorized by the Flood Control Act
approved August 18, 1941. (H. Doc. No. 846,             Cong., 3d sess.).
    The estimated Federal cost is $108,500 for construction, and the
                                                                                             16th
estimated local cost is $1,500 for lands and damages.
238         REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,              1944

   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
prevent any encroachments upon the flood-channel capacities to be
provided by the proposed improvements. Assurances have been
received.
   Operations and results during fiscal year.-Surveys, foundation
investigations, engineering studies, and design were started by hired
labor. The cost of this work and the expenditures were $4,000 for
new work.
   Condition at end of fiscal year.-Preparation of plans is under way.
Construction has not been initiated. The cost and the expenditures
were $4,000 for new work.
   Proposed operations.-The sum of $12,000, allotted in July 1944,
will be applied to new work, completion of engineering studies, de-
sign, plans, and specifications for flood protection on Fall and Cas-
cadilla Creeks by hired labor; period July 1944 to June 1945.
   No additional funds can be expended during the fiscal year 1946
in view of the existing Federal policies on wartime construction.
                                     Cost and financial summary
Cost of new work to June 30, 1944_ ___                        _          _--            _        _..$4,                       000
Cost of maintenance to June 30, 1944
           Total cost of permanent work to June 30, 1944----------------                                                4, 000
Net total expenditures -----                                       ---                  --                         -    4, 000
Unexpended balance June 30, 1944___
           Total amount appropriated to June 30, 1944------------------4, 000

   Fiscal year ending June 30            1940               1941               1942              1943                  1944


                 ---------------- -
Cost of new work.........
Cost of maintenance-... . . - . . .--- -          --                                         -
                                                       ---------------------------------------
                                                         - - - - - --   - - - - - --       . ..             ----          $4,000

Total expended----....-------------- -------------------           ---------- --------------      -------      -              4,000
Allotted     ---------------------------        ------- - ----------- ------------                 $4,000

Balance unexpended July 1, 1943__                                                                                      $4, 000
Gross amount expended_-------------                                                            -----                    4,000

           Balance unexpended June 30, 19440__.----------                                                                 -0

Amount allotted in July 1944_-----------                   ----                                                        12, 000
Amount available during the fiscal year 1945-----------------------                                                    12, 000
Amount (estimated)   required to be appropriated for completion of exist-
               -- - - - -- - - -- - - - - -- - - - - - -- - - - - - -- - - - - - -- - - - -- - - - -
ing project 1                                                                                       92,500
  I Exclusive of available funds.


                 7. WATKINS GLEN, OSWEGO RIVER BASIN, N. Y.

  Location.---Watkins Glen. N. Y., is located in Schuyler County at
the southern end of Seneca Lake. (See U. S. Geological Survey topo-
graphical maps of New York State.)
                   FLOOD CONTROr--SYRACUSE,                            N.   Y.,   DISTRICT    239
  Existing project.-The plan of improvement provides for the im-
provement of the Glen Creek Channel through the village of Watkins
Glen from the mouth of the gorge to below the village by increasing
the capacity of the channel to 10,000 cubic feet per second by widening
and deepening the channel and for the construction of 150 feet of con-
crete wall on the right bank above Franklin Street, 50 feet of concrete
wall on each bank below the railroad, a levee on the left bank upstream
from the railroad, and a levee on the right bank downstream from
Decatur Street. It also provides for protecting the channel banks
between Franklin and Decatur Streets with concrete cribs and stone
riprap, and for replacing one highway bridge, and adding spans to
one highway and one railroad bridge. This will provide a safe chan-
nel capacity for flood discharges of Glen Creek equal to that of the
largest flood of record.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $104,000, of which $72,000 is for con-
struction and $32,000 is for reimbursement to local interests for one-
half the cost of bridge alterations, lands, easements, and rights-of-way
in excess of the cost of channel improvements, and the estimated local
cost is $104,000 for lands and damages.
  Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such ineasures as may be necessary to pre-
vent any encroachments upon the flood-channel capacities to be pro-
vided by the proposed improvements, and to replace one highway
bridge and add spans to one highway and one railway bridge, with the
division of costs for that work between local interests and the United
State;; as stated in the previous paragraph. Assurances have been
received.
   Operations and results during fiscal year.-Surveys, foundation
investigations, engineering studies, and design were started by hired
labor. The cost of this work and the expenditures were $4,000 for
new work.
   Condition at end of fiscal year.-Preparation of plans is underway.
Construction has not been initiated. The cost and the expenditures,
all for new work, were $4,000.
   Proposed operations.-The amount of $8,000 allotted in July 1944
will be applied to new work, completion of engineering studies, de-
sign, plans, and specifications for flood protection on Glen Creek by
hired labor; period July 1944 to May 1945.
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                      Cost and financial summary

Cost of new work to June 30, 1944_ _$4,                                                        000
Cost of maintenance to June 30, 1944
         Total cost of permanent work to June 30, 1944------------ ---                       4, 000

Net total expenditures ___----------------------------------------4,                           000
Unexpended balance June 30, 1944
         Total amount appropriated to June 30, 1944 ------------------                       4, 000
240         REPORT OF CHIEF OF ENGINEERS,                            U.        S. ARMY,              1944


   Fiscal year ending June 30         1940            1941               1942                 1943                  1944

Cost of new work .------- ----------------------------                          ....----------------------------.     $4,003
Cost of m aintenance ...-    .-        -.             . . .
                                                 - --.-..            .     .     . . . . . . .                  -   - - --
T otal expended ---- - -- -- - ---- - -- - - ..   .- . . .. . .. .        .. .. .. ... ..        .$4,                      000
Allotted              _----------------------------------------------------------                $4, 000-

Balance unexpended July 1, 1943                                                                                     $4, 000
Gross amount expended --------------------------------------------                                                   4, 000

           Balance unexpended June 30, 1944                                                                                 00----------------

Amount allotted in July 1944- ------------------------------------                                                   8, 000
Amount available during the fiscal year 1945--------- ----------------                                               8, 000

Amount (estimated) required to be appropriated for completion of exist-
             1
ing project   ----------------------------------------------           _ 92, 000
   Exclusive of available funds.

                8. MONTOUR FALLS, OSWEGO RIVER BASIN, N. Y.

   Location.-The village of Montour Falls, N. Y., is located in
Schuyler County and is situated 2.5 miles from the southern end of
Seneca Lake. (See U. S. Geological Survey topographic maps of New
York State.)
   Existing project.-CatherineCreek flows northerly through the cen-
ter of the village of Montour Falls and discharges into Seneca Lake.
Havana Glen Creek joins Catherine Creek just south of the village,
Catlin Mill Creek flows through a diversion channel to the east of the
village and joins Catherine Creek north of the village, and Shequaga
Creek flows through a diversion channel along the northwest edge of
the village and joins Catherine Creek north of the village. The plan
of improvement for Catherine and Havana Glen Creeks provides for
the diversion of Catherine Creek to the east of the village to join the
present diversion channel of Catlin Mill Creek, involving the excava-
tion of a channel about 5,000 feet long and the construction of a levee
along the left bank of the channel so as to secure a channel with a
capacity of 35,000 cubic feet per second; the diversion of the lower
part of Havana Glen Creek to enter the Catherine Creek diversion
channel; the construction of timber check dams on Havana Glen Creek
and on Catlin Mill Creek; bank protection where scour is likely to
occur; construction of a small gate in the levee where it crosses th\
present Catherine Creek channel to provide water for sewage disposal;
and construction of two new highway bridges across the Catherine
Creek diversion channel, one at Oswego Street and one at Broadway
Street.'
   The plan of improvement for Shequaga Creek provides for increas-
ing the capacity through the village to 11,000 cubic feet per second to bey
secured by widening and deepening the channel and construction of a
wall and levee along the right bank. The plan also includes construc-
tion of a stilling basin at the base of the falls and replacing one high-
way bridge at Steuben Street with a more adequate structure.
   The project will provide substantial flood protection for the village
of Montour Falls.
                    FLOOD CONTROL-SYRACUSE,                                     N.        Y., DISTRICT                  241
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. No. 846, 76th Cong., 3d sess.).
   The estimated Federal cost is $478,000 for construction, and the
estimated local cost is $173,000 for lands and damages.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to take such measures as may be necessary to
prevent any encroachments upon the flood-channel capacities to be pro-
vided by the proposed improvements, and replace the Broadway Street
Bridge and the Steuben Street Bridge, estimated to cost $86,000 and
$20,000, respectively. Assurances have been received.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were continued by hired
labor. The cost of this work was $22,407.17 for new work. The
expenditures were $21,857.04.
   Condition at end of fiscal year.-Preparation of plans is under way,
Construction has not been initiated. The cost was $26,041.55 for new
work. The expenditures, all for new work, were $25,283.66.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $9,716.34, plus accounts receivable, $26.58, amounted to
$9,742.92. This amount will be applied as follows:
Accounts payable, June 30, 1944 -------                                                                   _--------$784. 47
New work: Completion of engineering studies, design, plans, and
specifications for channel improvement and check dams on Catlin
  Mill, Shequaga, and Catherine Creeks; period July 1944 to December
  1944:
      Design (hired labor) ---------------------------------                                                     8, 958. 45

         Total_---------------------------------------------------                                               9, 742. 92
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                       1  Cost and financial summary

Cost of new work to June 30, 1944------------------------------                                                $26, 041. 55
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944-- ------                                                   26, 041. 55
Plus accounts receivable June 30, 1944--------------------------                                                     26. 58
      Gross total costs to June 30, 1944------------------                                                      26, 068. 13
Minus accounts payable June 30, 1944 -------------------------                                                     784. 47
      Net total expenditures_----------------------------                                                       25, 283. 66
Unexpended balanoe June 30, 1944-----------------------                                                          9,716. 34
         Total amount appropriated to June 30, 1944--- ------                                                   35, 000. 00

   Fiscal year ending June 30                   1940               1941                  1942      1943            1944

Cost of new work -.........              .$3,                                                        634. 38      $22, 407. 17
Cost of maintenance--.   .             . .        .        .   .     .      .               -6$                             1

Total expended -    - -     - - - --
                            --                      . . .-... . . .
                                                 ..-..                                            3, 426. 62       21,857.04
Allotted - - - - - - - -       --- -     -.
                                          . . . . . ---
                                                    . .              -..-            -      -              0
                                                                                                  35,000 .00        -




        616634-45-pt. 1, vol. 1                       16
242         REPORT OF CHIEF OF ENGINEERS,                             U.   S.   ARMY,   1944

Balance unexpended July 1, 1943_        -------------------------------                   $31, 573. 38
Gross amount expended_---------------------------------                                    21, 857. 04

       Balance unexpended June 30, 1944------------------                                      9, 716. 34
Outstanding liabilities June 30, 1944 ----------------------------                                 14. 25

      Balance available June 30, 1944 --------------------                                     9702.
                                                                                               9,    09
Accounts receivable June 30, 1944------------------------------                                   26. 58

         Unobligated balance available June 30, 1944---------                                  9, 728. 67

Amount (estimated) required to be appropriated for completion of
existing project 1--------------------------------------------  443, 000. 00
   Exclusive of available funds.

             9. SOUTHERN NEW YORK FLOOD CONTROL PROJECT
   Location.-The work covered by this project is in the upper water-
shed of the Susquehanna River to and including the Chemung River.
This includes about 6,050 square miles in south central New York, and
about 1,480 square miles in northern Pennsylvania. (See U. S. Geo-
logical Survey index maps of New York and Pennsylvania.)
   Existing project.-The Flood Control Act approved June 22, 1936,
authorized the construction of detention reservoirs and related flood-
control works for protection of Binghamton, Hornell, Corning, and
other towns in New York and Pennsylvania, in accordance with plans
approved by the Chief of Engineers on recommendation of Board of
Engineers for Rivers and Harbors. The individual units which con-
stitute the approved plan of improvement are described in the follow-
ing paragraphs:
   Davenport Center Reservoir: This reservoir will be located on
Charlotte Creek near Davenport Center, N. Y. The dam will be of
the earth-filled type, 1,770 feet long at the top of the embankment and
rising 95 feet above the stream bed, with a concrete spillway and out-
let conduit in the right abutment. The reservoir willprovide a storage
capacity of 52,600 acre-feet. The estimated cost of new work, revised
in 1941, is $1,771,000 for construction and $1,219,000 for lands and
damages.
   West Oneonta Reservoir: This reservoir will be located on Otego
Creek near West Oneonta, N. Y. The dam will be of the earth-filled
type, 1,300 feet long at the top of the embankment and rising 78 feet
above the stream bed, with a concrete spillway and outlet conduit in
the right abutment. The reservoir will provide a storage capacity
of 32,500 acre-feet. The estimated cost of new work, revised in 1941,
is $1,709,000 for construction and $1,072,000 for lands and damages.
   East Sidney Reservoir: This reservoir will be located on Ouleout
Creek near East Sidney, N. Y. The dam will be of the earth-filled
type, 1,890 feet long at the top of the embankment and rising 124 feet
above the stream bed, with a concrete spillway and outlet conduit in
the left abutment. The reservoir will provide a storage capacity of
,2,000 acre-feet. The estimated Federal cost of new work, revised in
1941, is $1,896,000 for construction and $300,000 for lands and damages.
   Copes Corner Reservoir: This reservoir will be located on Butter-
nut Creek near Copes Corner, N. Y. The dam will be of the earth-
filled type, 940 feet long at the top of the embankment and rising
63 feet above the stream bed, with a concrete spillway and outlet
conduit in the right abutment. The reservoir will provide a storage
           FLOOD CONTROL---SYRACUSE,      N.   Y., DISTRICT      243
capacity of 38,700 acre-feet. The estimated Federal cost of new
work, revised in 1941, is $1,906,000 for construction and $765,000 for
lands and damages.
   Whitney Point Reservoir: The reservoir is located on the Otselic
River near Whitney Point, N. Y. The dam is of the earth-filled
type, 4,300 feet long at the top of the embankment and rising 90
feet above the stream bed, with a concrete spillway and outlet con-
duit in the left abutment. The reservoir has a storage capacity of
87,600 acre-feet. The estimated Federal cost of new work, revised
in 1942, is $3,946,300 for construction and $889,300 for lands and
damages.
   Arkport Reservoir: The reservoir is located on the Canisteo River
near Hornell, N.. Y. The dam is of the earth-filled type, 1,200 feet
long at the top of the embankment and rising 100 feet above the
stream bed, with a concretespillway and outlet conduit in the right
abutment. The reservoir has a storage capacity of 8,000 acre-feet.
The Federal cost of new work is $1,753,000 for construction and an
estimated $127,000 for lands and damages.
   Almond Reservoir: This reservoir will be located on Canacadea
Creek near Hornell, N. Y. The dam will be of the earth-filled type,
1,350 feet long at the top of the embankment and rising 85 feet above
the bed of the stream, with a concrete spillway and outlet conduit in
the left abutment. The reservoir will provide a storage capacity of
14,800 acre-feet. The estimated Federal cost of new work, revised in
1941, is $2,154,000 for construction and $745,000 for lands and
damages.
    Oxford, N. Y.: The plan of improvement provides for the con-
struction of earth levees and the clearing of the Chenango River
channel, consisting of the following features: About 2,100 feet of
earth levee on the left bank of the Chenango River, extending from
high ground near Cemetery Drive and running mostly along the
railroad to high ground near Main Street; removal of the dam and
island below Main Street; raising of the Delaware, Lackawanna &
Western Railroad over the levee; and appurtenant drainage struc-
tures. The improvement provides protection for the village of Ox-
ford on the left bank against a flood of magnitude approximately 5
feet higher than the maximum flood of record, which occurred in
July 1935. The estimated Federal cost of new work, revised in 1940,
was $86,000 for construction. The estimated Federal cost of lands
revised in 1941, is $46,100. The estimated local cost- of lands and
damages is $37,500.
   Lisle, N. Y.: The plan of improvement provides for channel realine-
ment and the construction of earth levees and concrete flood walls,
consisting of the following features: Relocation of about 3,000 feet
of the Dudley Creek channel, extending from 1,200 feet west of
the intersection of Cortland and Main Streets to the confluence
with the Tioughnioga River; realinement of some 5,700 feet of the
Tioughnioga River channel east of the village; about 3,700 feet of
earth levee and 1,000 feet of concrete wall on the right bank of
Dudley Creek and the Tioughnioga River, extending from Main
Street just above Collier Street to the railroad crossing on River
Street; raising of about 1,700 feet of the Delaware, Lackawanna &
Western single-track railroad over the levee; relocation of about
1,500 feet of Cortland Street; a new bridge over the relocated Dud-
244     REPORT OF   CHIEF OF ENGINEERS,     U.   S. ARMY,   1944


ley Creek; and appurtenant drainage structures. The improvement
will provide protection for the village of Lisle against a flood of
magnitude approximately 3 feet higher than the maximum flood of
record, which occurred in July 1935. The estimated Federal cost
of work, revised in 1941, is $319,300 for construction and $50,000
for lands and damages. The estimated local cost of lands and dam-
ages is $112,000.
   Whitney Point, N. Y.: The plan of improvement provides for chan-
nel realinement and construction of earth levees, consisting of the
following features: Realinement of about 1,800 feet of the Tioughnioga
River channel, above the confluence with the Otselic River; about 7,100
feet of earth levee along the right bank of the Tioughnioga River, ex-
tending from high ground on Main Street above the village to Collins
Street just below the village; and appurtenant drainage structures.
The improvement, supplemented by the Whitney Point Reservoir
above the area, will provide protection for the village of Whitney
Point against a flood of magnitude approximately 4 feet higher than
the maximum flood of record, which occurred in July 193t.. The esti-
mated Federal cost of new work, revised in 1941, is $176,000 for con-
struction and $2,000 for lands and damages. The estimated local cost
of lands and damages is $38,000.
   Binghamton, N. Y.: The plan of improvement provides for the
construction of earth levees and concrete flood walls, consisting of
the following features: About 900 feet of channel excavation and
about 1,400 feet of earth levee along Phelps Creek, town of Port
Dickinson; new concrete wall on the right bank of the Chenango
River extending downstream from high ground near the city
limits to the existing flood wall, a distance of about 500 feet;
raising about 3 feet the existing earth levee on the right bank of
the Chenango River, extepding from the Cutler Dam downstream
for a distance of about 1,200 feet; about 2,900 feet of the earth levee
on the left bank of the Chenango River north of the city limits
in the village of Port Dickinson, extending from Church Street to
high ground just north of the city line; about 3,900 feet of earth levee
on- the left bank of the Chenango River from DeForest Street to
Noyes Island; new concrete flood walls and river bank revetment
for a distance of about 5,500 feet, extending on the left bank of the
Chenango River from Noyes Island to the junction with the Susque-
hanna River; about 700 feet of concrete flood wall and raising of
about 1,000 feet of existing concrete flood wall on the right bank of
the Susquehanna River, extending from the Delaware, Lackawanna &
Western Railroad downstream to the Tompkins Street Bridge; about
2,000 feet of earth levee, about 1,800 feet of concrete flood wall on
the right bank of the Susquehanna River, extending from Stuyvesant
Street to the mouth of the Chenango River; about 9,000 feet of earth
levee and about 2,000 feet of concrete flood wall on the left bank
of the Susquehanna River, extending from Pierce Creek to high
ground at State Highway Route No. 17 about one-half mile below
Pennsylvania Avenue; a concrete pressure conduit, 1,200 feet long,
to carry the flow of Park Creek from Vestal Avenue to the Susque-
hanna River; about 700 feet of levee extending from the Erie Rail-
road to high ground along the right bank of the Chamberlain Creek
near the mouth; a weir, drop structure, about 1,300 feet of earth levee,
and about 1,500 feet of channel excavation and raising of about 500
            FLOOD CONTROL--SYRACUSE,       N.   Y., DISTRICT    • 245
feet of existing concrete flood wall for the improvement of Pierce
Creek from its mouth to about 1,000 feet above Conklin Avenue; and
appurtenant drainage structures. The improvement, supplemented
by the authorized flood-control dams above the area, will provide
protection for the city of Binghamton against a flood of magnitude
approximately 4 feet higher- than the maximum of record, which
occurred in March 1936.* The estimated Federal cost of new work
revised in 1942, is $2,558,000 for construction and $77,800 for lands
and damages. The estimated local cost of lands and damages is
 $600,000. Local interests have contributed an additional amount of
$155,430.13 for the construction of improvements not included in the
authorized project.
    Elmira, N. Y.: The plan of improvement provides for the con-
struction of earth levees and concrete flood walls, consisting of the
following features: About 5,900 feet of earth levee, enlargement of
about 6,200 feet of existing earth levee, and about 4,100 feet of con-
crete flood wall on the right bank of Chemung River, extending from
South Hoffman Street to a point below the city near the upper end
of Big Island; about 13,700 feet of earth levee and about 6,800 feet
of concrete wall on the left bank of the Chemung River extending
from Evergreen Avenue to Sullivan Street; about 10,000 feet of
earth levee on the right bank of Newtown Creek, extending from
about the intersection of the Delaware, Lackawanna & Western
Railroad and East Church Street to high ground near the intersec-
tion of Sullivan and Warren Streets; about 4,300 feet of earth levee
on the right bank of Diven Creek; about 2,000 feet of concrete conduit
enclosing Hoffman Brook from West Second Street to the Chemung
River; about 15,300 feet of earth levee on the left bank of Seely
Creek, extending from the Erie Railroad to high ground approxi-
mately 3,500 feet northwest of the intersection of South Broadway
and Pennsylvania Avenue, a pumping plant for the disposal of in-
terior drainage; and appurtenant drainage structures. The improve-
ment will provide protection for the city of Elmira against a flood
of magnitude approximately 5 feet higher than the maximum flood
of record, which occurred in June 1889. The estimated Federal cost
of new work, revised in 1942, is $3,355,000 for construction and
$86,000 for lands and damages. The estimated local costs of lands
and damages is $621,000.
   Corning, N. Y.: The plan of improvement provides for the con-
struction of a pumping station, earth levees, and concrete flood walls,
consisting of the following features: About 4,300 feet of earth levee,
enlargement of about 8,610 feet of existing earth levee, and about
3,100 feet of concrete flood wall on the right bank of Chemung River,
extending from the Erie Railroad bridge to high ground at Park
Avenue below the city; about 200 feet of concrete flood walls; about
2,500 feet of earth levees, and enlargement of about 11,500 feet of
existing earth levee on the left bank of the Chemung and Cohocton
Rivers, extending from the Erie Railroad Bridge over the Cohocton
River to the mouth of Post Creek; about 2,500 feet of earth levee
and enlargement of about 4,700 feet of existing earth levee on the
right bank of Post Creek from its mouth to Watson Street; realine-
ment of about 3,000 feet of channel, aboutw8,800 feet of earth levee,
about 3,000 feet of channel excavation, a pressure conduit about 400
feet long, a drop structure and a weir for the improvement of Cutler
246    REPORT OF CHIEF OF ENGINEERS,        U.   S.   ARMY,   1944


Creek, extending from its mouth to high ground at Deckertown
Road and Hornby Road; and appurtenant drainage structures. The
improvement will provide protection for the city of Corning against
a flood of magnitude approximately 6 feet higher than the maximum
flood of record, which occurred in July 1935. The estimated Fed-
eral cost of new work, revised in 1942, is $2,064,500 for construction
and $114,500 for lands and damages. The estimated local cost of
lands and damages is $212,000.
   Painted Post, N. Y.: The plan of improvement provides for chan-
nel realinement and the construction of earth levees and concrete flood
walls, consisting of the following features: Realinement of about 6,000
feet of the Cohocton River channel, extending from about one-half
mile above State Highway Route No. 17 to the Chemung River; con-
struction of about 3,000 feet of earth levee and raising of about 1,200
feet of existing flood wall along the left bank of the Cohocton River,
extending from the mouth of Hodgman Creek to the Chemung River;
about 2,900 feet of earth levee, and about 2,100 feet of concrete flood
wall, extending on the left bank of Hodgman Creek, from its mouth
to high ground above State Highway No. 2; and appurtenant drain-
age structures. The improvement provides protection for the village
of Painted Post against a flood of magnitude approximately 7 feet
higher than the maximum flood of record, which occurred in July
1935. The estimated Federal cost of new work, revised in 1941, is
$411,000 for construction and $9,500 for lands and damages. The
estimated local cost of lands and damages is $51,000.
   Addison, N. Y.: The plan of improvement provides for the construc-
tion of earth levees and concrete flood walls, consisting of the follow-
ing features: About 1,500 feet of channel realinement on the Canisteo
River, extending from the Baltimore & Ohio Railroad Bridge to the
Main Street Bridge; construction of about 1,500 feet of earth levee
and about 500 feet of concrete flood wall on the right bank of the
Canisteo River, extending from high ground on Steuben Street near
the Baltimore & Ohio Railroad to the mouth of Tuscarora Creek;
removal of existing dam, mill, and raceway from the channel; con-
struction of about 600 feet of earth levee and raising of about 2,400
feet of existing levee on the left bank of Tuscarora Creek, extending
from Tuscarora Street to the Canisteo River; cutting of a new outlet
channel on Tuscarora Creek approximately 500 feet long at its mouth;
reshaping of about 2,100 feet of existing earth levee on the right bank
of Tuscarora Creek, extending from the Baltimore & Ohio Railroad
to South Street; and appurtenant drainage structures. The improve-
ment, supplemented by the Arkport and Almond Reservoirs above the
area, will provide protection for the village of Addison against a
flood of magnitude 1 foot above the maximum flood of record, which
occurred in July 1935. The estimated Federal cost of new work, re-
vised in 1941, is $164,500 for construction and $31,000 for lands and
damages. The estimated local cost of lands and damages is $58,000.
   Bath, N. Y.: The plan of improvement provides for the construction
of earth levees and concrete flood walls along the Cohocton River,
consisting of the following features: Raising of about 4,100 feet of
the Erie Railroad from Belfast Street to a point opposite Cruger
Street, the embankment to serve as a levee; construction of about 4,200
feet of earth levee and about 800 feet of concrete flood wall, extending
from Cameron Street to the turn-out of the Bath & Hammondsport
            FLOOD CONTROL---SYRACUSE,       N.   Y.,   DISTRICT      247
Railroad; about 2,000 feet of earth levee running to high ground near
the junction of Morris Street and State Highway Route No. 2; a
pumping plant in the vicinity of the sewage treatment plant for the
disposal of interior drainage effluent from the sewage treatment plant;
and appurtenant drainage structures. The improvement will pro-
vide protection for the village of Bath against a flood of magnitude
of approximately the maximum of record which occurred in July 1935.
The estimated Federal cost of new work, revised in 1941, is $331,000
for construction. The estimated local cost of lands and damages is
$20,000.
   Avoca, N. Y.: The plan of improvement provides for the construc-
tion of earth levees, channel improvement, and channel realinement,
consisting of the following features: Improvement and realinement,
of about 8,300 feet of the Cohocton River channel, extending from
above the Erie Railroad to below the junction of Main Street and
State Highway Route No. 2; construction of about 8,500 feet of earth
levee on the left bank of the Cohocton River, extending from high
ground above Alexander Avenue to about 1,300 feet below the junc-
tion of Main Street and State Highway Route No. 2; about 4,500 feet
of earth levee on the right bank of Salmon Creek, extending from high
ground above Alexander Avenue to the Erie Railroad; a new high-
way bridge for State Highway No. 2 over the Cohocton River; raising
of the Erie Railroad bridge 4 feet; and appurtenant drainage struc-
tures. The improvement provides protection for the village of Avoca
against a flood of magnitude approximately 5 feet higher than the
maximum flood of record which occurred in July 1935. The estimated
Federal cost of work, revised in 1941, is $415,000 for construction and
$39,000 for lands and damages. The estimated local cost of lands and
damages is $95,000.
   Canisteo, N. Y.: The plan of improvement provides for the con-
struction of earth levees, consisting of the following features: About
9,000 feet of earth levees on the right bank of the Canisteo River,
extending from high ground 1,350 feet west of State Highway Route
No. 17F above the village to the mouth of Bennett Creek; about 10,000
feet of earth levee and about 300 feet of concrete flood wall on the left
bank of Purdy and Bennett Creeks, extending from the mouth of
Bennett Creek to high ground above Greenwood Street; a timber crib
debris dam above Greenwood Street; a new highway bridge at Green-
wood Street; about 2,000 feet of new outlet channel for Bennett Creek;
and appurtenant drainage structures. The improvement, supple-
mented by the Arkport and Almond Reservoirs above the village, will
provide protection for the village of Canisteo against a flood of mag-
nitude of approximately the maximum flood of record, which occurred
in July 1935. The estimated Federal cost of new work, revised in
1941, is $263,500 for construction and $47,000 for lands and damages.
The estimated local cost of lands arid damages is $34,000.
   Hornell, N. Y.: The plan of improvement provides for channel
realinement and the construction of earth levees and concrete flood
walls, consisting of the following features: Realinement of about
4,600 feet of Canisteo River Channel, and 'about 5,800 feet of earth
levee on its right bank, extending from Seneca Street upstream to
the junction of the Pittsburg, Shawmut & Northern Railroad and
the Erie Railroad; construction of about 4,500 feet of earth levee,
extending on both sides of Seneca Street from the Canisteo River to
248         REPORT OF CHIEF OF ENGINEERS,                                                        U. S.     ARMY,          1944


Wightman Avenue and the junction of Cleveland Avenue and Be-
thesda Drive; construction of about 7,200 feet of earth levee, about
2,500 feet of concrete flood wall, and raising of about 1,500 feet of
existing concrete flood wall on the right bank of the Canisteo River,
and about 12,000 feet of channel improvement, extending from Seneca
Street to the Erie Railroad; construction of about 2,500 feet of earth
levee, about 2,100 feet of concrete flood wall on the left bank of
Canisteo River, extending from a point opposite Walnut Street to the
Erie Railroad; a ring-earth levee about 2,800 feet long around the
sewage-disposal plant on the left bank of the Canisteo River; about
4,500 feet of realinement and improvement of the Canisteo River chan-
nel, with about 4,500 feet of earth levee on its right bank, extending
from Cedar Street downstream to about 1,400 feet above East Avenue;
about 2,400 feet of channel paving, 1,400 feet of earth levee, and rais-
ing of about 1,900 feet of concrete flood wall on Canacadea Creek;
about 1,600 feet of channel paving on Chauncey Run with about 300
feet of new wall and about 300 feet of wall capping; removal of five
bridges, erection of three bridges, miscellaneous bridge structures, and
two drop structures; and appurtenant drainage structures and small
stream-control works.
   The improvement, supplemented by the Arkport and Almond Res-
ervoirs above the area, will provide protection for the city of Hornell
against a flood of magnitude approximately 4 feet higher than the
maximum flood of record which occurred in July 1935. The estimated
Federal cost of new work, revised in 1941, was $2,728,000 for construc-
tion and $460,000 for lands and damages.
   Almond, N. Y.: The plan of improvement provides for channel
realinement and the construction of earth levees, consisting of the
following features: About 4,300 feet of earth levee on the left bank
of Canacadea Creek, extending from high ground above the village
to high ground below the village; realinement of about 3,200 feet of
channel on Canacadea Creek, extending downstream from Angelica
Street; and appurtenant drainage structures. The improvement will
provide protection for the village of Almond against a flood of
magnitude of approximately the maximum flood of record, which
occurred in July 1935. The estimated Federal cost of new work,
revised in 1941, is $48,000 for construction and $2,400 for lands and
damages. The estimated local cost of lands and damages is $8,500.
                                                       Dams and reservoirs1

                                                                                          2           a         Estimated Federal cost

      Name                     Nearest city                   River                 8,        4*o-D   '
                                                                                                                             b            o

Davenport Cen-            Oneonta-.......             Charlotte Creek_...                5     95 52, 600 $1, 771, 000 $1, 219, 000 $2, 990, 000
ter.
West Oneonta . - .. do.....---------                  Otego Creek ..   _                 2  78 32, 500      1, 709, 000   1, 072, 000 2, 781, 000
                     do ...--------.....
East Sidney .-----------                              Ouleout Creek_ .                   2 124 32, 000      1, 896, 000      300, 000 2, 196, 000
Copes Corner...   Sidney ......                       Butternut Creek-_                  3 63 38, 700       1, 906, 000      765, 000 2, 671, 000
Whitney Point 2_ Binghamton .-.-                      Otselic River         .            1      90 87, 600 3,946, 300      889, 300 4, 835, 600
Arkport 2-......          Hornell ..-...              Canisteo River ..                  50 100 8, 000 1, 753, 000          127, 000 1, 880, 000
Almond ....               .   do..........            Canacadea Creek                     3 85 14, 800 2, 154, 000          745,000 2, 899, 000
                                                                                                           15, 135, 300 5,117, 30020, 252, 600
             I   All   dams,     located   in   New    York   State,   of   earth    fill     type.               2 Completed.
                               FLOOD CONTROI--SYRACUSE,                                   N.     Y., DISTRICT                    2491
                                                           Local flood-protection works

                                                                                                          Estimated Federal cost

     Location,
     New York                            River                5              Type of structure               .




Oxford    1       --             Chenango       ---------         40 Levee and channel improve-           $86, 000 $46,100     $132, 100
                                                                       ment.
Lisle      .......----------- Tioughnioga              -          12 Walls, levee, and channel re         319, 300   50, 000    369, 300
                                                                         alinement.
Whitney Point ..-....                 do---...---...              10 Levee      and channel realine-      176,000     2,000     178, 000
                                                                        ment.
Binghamton 1...                  Susquehanna -328                      Wall, levee, and conduit --     2, 558, 000 77, 800 2,635, 800
Elmira 2_ .......                Chemung- .......                 27   -- do                           3, 355, 000 86, 000 3, 441, 000
                                                                                            .-------------------
Corning _...-..                  . do_ _........                  44   -----.
                                                                           do-.. .      _   - - - -2, 064, 500 114, 500 2,179, 000
Painted Post 1 .                 Cohocton       ---------          0   Wall, levee, and channel re-       411,000   9, 500    420, 500
                                                                         alinement.
Addison-
Bath--........             .
                               -Canisteo- ---
                                 Cohocton---------
                                                                   8
                                                                  21
                                                                          do_-..._. ___-------
                                                                       Wall and levee ----. .     ...
                                                                                                          164, 500
                                                                                                          331, 000
                                                                                                                     31, 000
                                                                                                                           0
                                                                                                                                195, 500
                                                                                                                                331,000
Avoca 1-....           .        __.   do-..........               30   Levee and channel improve-         415,000    39, 000    454, 000
                                                                         ment and realinement.
Canisteo....--------- Canisteo----------                          36 Levee and wall__ _ _  ..   .          263, 500 47, 000   310, 500
Hornell 1       -_. _ _ __-- do-...........                       42 Wall, levee, and channel re-       2, 728, 000 460,000 3,188,000
                                                                         alinement.
Almond.......---------..         Canacadea Creek                   6   Levee and channel realine-           48,000    2,400      50, 400
                                                                         ment.
        Total....... -----------------------------------------------                                    12, 919, 800 965, 300 13, 885,10@

  1 Construction completed.             2 Part of project completed.
  a Does not include contributed funds of $160,095.63 by the city of Binghamton and $3,000 by the village
of Port Dickinson.

   Local cooperation.-See page 7 for requirements. The Secretary
of War accepted as satisfactory the assurances of the State of New
York to comply with conditions and cooperation for local improve-
ment projects or parts thereof, within the purview of section 3 of
the Flood Control Act, approved June 22, 1936, at Avoca, Lisle, Ox-
ford, and Painted Post, N. Y., on December 15, 1936; at Bingham-
ton, N. Y., on November 15, 1937; at Corning and Elmira, N. Y., on
May 8, 1940; at Whitney Point, N. Y., on June 22, 1940; at Bath,
N. Y., on June 24, 1943; and at Addison, Almond, and Canisteo,
N. Y., on December 9, 1943. Permission to enter those properties
on which surveys and foundation investigations are necessary is be-
ing obtained as need therefor arises, and lands, easements, and rights-
of-way required for construction activities are being acquired as oper-
ations progress. The city of Binghamton has contributed a total of
$160,095.63 and the village of Port Dickinson has contributed a total
of $3,000 to the United States to defray the cost of related features
of construction desired by the city but not required for the authorized
project.
   Operations and results during fiscal year.--East Sidney Reser-
voir.-Work preliminary to the construction of the reservoir on Oule-
out Creek was continued by hired labor. Cost of this work was
$55,844.02 for new work.
   Whitney Point Reservoir.--Work consisted of general mainte-
nance and operation of the completed structures. The work in-
cluded the removal of debris deposited at the intake structure and
acquisition of one stand-by power unit. Negotiations and investiga-
tions necessary to consummate purchase of land were continued by
hired labor. Reimbursement to the State of New York for lands
required for the reservoir was in progress. Cost of the work was
250     REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,   1944

 $214,621.11, of which $207,847.63 was for new work and $6,773.48
for maintenance.
    Arkport Reservoir.-Maintenance of the completed structures was
in progress. The work included the construction of a trash boom
and gage-recorder house. Reimbursement to the State of New York
for lands required for the project was continued by hired labor.
The cost of the work was $34,045.04, of which $29,600.43 was for new
work and $4,444.61 for maintenance.
    Lisle, N. Y.-Work preliminary to the construction of the Dud-
ley Creek portion of the project was continued by hired labor. Cost
of this work was $4,679.40 for new work.        f
    Whitney Point (village), N. Y.-Work preliminary to construc-
tion of the project was continued by hired labor. Investigations nec-
essary to consummate the purchase of land for the project were con-
tinued by hired labor. Cost of this work was $6,029.20 for new work.
    Binghamton section No. 1.-Reimbursement to the State of New
York for lands required for the project was continued by hired labor.
The cost of this work was $2,502.80 for new work.
    Binghamton section No. 2.-Reimbursement to the State of New
York for lands required for the 'project was continued by hired labor.
The cost of this work was $13,665.28 for new work.
    Binghamton section No. 4.-Construction of the local flood protec-
tion on the Chenango River was begun on July 23, 1941, and was
completed December 15, 1943, under contract. Work included the
construction of 2,260 linear feet of concrete floodwall and 1,308
linear feet of intercepting sewer, involving the excavation of 23,658
cubic yards of earth, the removal of 2,256 cubic yards of old wall, the
placement of 13,572 cubic yards of earth fill, the placement of 7,415
cubic yards of rock paving and riprap, 2,861 cubic yards of gravel and
sand backing, and 3,526 cubic yards of concrete, the installation of
438,790 pounds of reinforcing steel and other metals, and the driving
of 8,797 square feet of steel sheet piling. Engineering studies and
design in connection with the construction of the project were com-
pleted by hired labor. Acquisition of lands required for the project
was continued by the State of New York. Cost of the work was
$292.825.12 for new work.
   Binghamton (maintenance).-Cost of channel clean-up (all sec-
tions) and maintenance of the completed structures was $743.43, of
which $347.08 was for maintenance of completed channel work.
   Elmira section No. 1.-Construction of the local flood protection
on the Chemung River was completed December 11, 1942, except for
the placing of certain riprap, which was deferred. Engineering
studies and design in connection with the construction of the project
were continued by hired labor. Acquisition of lands required for the
project was continued by the State of New York. Cost of the work
was $2,459.54 for new work.
   Elmira section No. 2.-Construction     of the local flood protection
on the Chemung River, Diven Creek, Newton Creek, Seely Creek,
and Hoffman Brook was terminated December 31, 1943, in accordance
with the existing Federal policies on wartime construction. Engineer-
ing studies and design in connection with the construction of the
project were continued by hired labor. Investigations necessary to
consummate purchase of land for the project were continued by hired
            FLOOD CONTROL-SYRACUSE,        N.   Y.,   DISTRICT     251
labor. Acquisition of lands for the project was continued by the State
of New York. Cost of the work was $103,593.10 for new work.
   Corning section No. 1.-Reimbursement to the State of New York
for lands required for the project was continued. Maintenance of the
completed structures was in progress. The cost of this work was
$10,810.92, of which $10,713.83 was for new work and $97.09 for
maintenance.
   Corning section No. 2.-Construction of the local flood protection
on the Chemung River was completed July 31, 1943, under contract.
Work consisted of placing 2,509 cubic yards of earth fill and 206 cubic
yards of rock paving and dumped riprap. Engineering studies and
design in connection with the construction of the project were com-
pleted during the fiscal year by hired labor. Acquisition of lands
required for the project was continued by the State of New York.
Cost of the work was $104,143.96, of which $103,351.78 was for new
work and $792.18 for maintenance.
   Corning pumping station (maintenance).-- Maintenance of the
completed structures was in progress during the fiscal year by hired
labor. The cost of this work was $344.98 for maintenance.
  Painted Post, N. Y.-The completed channel improvement works
were maintained during the fiscal year by hired labor. The cost of
this work was $13.20 for maintenance.
   Bath, N. Y.-Engineering studies and design preparatory to con-
struction of the local flood protection on the Cohocton River were
continued by hired labor. The cost of this work was $14,052.24 for
new work.
  Avoca, N. Y.-The completed channel improvement work was
maintained during the fiscal year by hired labor. The cost of this
work was $3.19 for maintenance.
   Hornell (all sections).-Surveys, engineering studies, and design
for proposed check dams on Chauncey Run and Canacadea Creek
were initiated. Reimbursement to the State of New York for lands
required for the project was continued. The cost of this work was
$36,136.30 for new work.
  Hornell (maintenance).-The existing channel improvement work
was maintained during the fiscal year. The work included the re-
moval of material deposited in Canacadea Creek between the Erie
Railroad bridge and the weir just upstream from the Seneca Street
Bridge and at the mouth of Canacadea Creek. The cost of this work
was $24,646.72 for maintenance.
  Davenport Center Reservoir.-Surveys, foundation investigations,
engineering studies, design, and partial plans and specifications were
started by hired labor. The cost of this work was $13,585.16 for
new work.
   West Oneonta Reservoir.--Surveys, foundation investigations, en-
gineering studies, design, and partial plans and specifications were
started by hired labor. The cost of this work was $21,356.38 for new
work.
  Almond Reservoir.-Surveys, foundation investigations, engineer-
ing studies, design, and partial plans and specifications were started
by hired labor. The cost of this work was $5,316.85 for new work.
  Addison local improvement.-Surveys, foundation investigations,
engineering studies, design, and partial plans and specifications were
252              REPORT OF CHIEF OF ENGINEERS,                                           U.     S. ARMY,             1944


started by hired labor. The cost of this work was $5,869.51 for new
work.
   Canisteo local improvement.-Surveys, foundation investigations,
engineering studies, design, and partial plans and specifications were
started by hired labor. The cost of this work was $30,211.75 for new
work.
   Almond local improvement.-Surveys, foundation investigations,
engineering studies, design, and partial plans and specifications were
started by hired labor. The cost of this work was $7,417.76 for new
work.
   Summary of operations and results during the fiscal year: Stream
flow in the Susquehanna River Basin was comparatively low through-
out the year. At no time were there damaging flows in the Che-
mung River basin (western portion of the upper Susquehanna River
basin), to test the protection afforded by the completed local protec-
tion projects. However, on three occasions during the spring season
the gate works of the Whitney Point Reservoir were operated when
damaging flows appeared possible in the eastern portion of the upper
Susquehanna River basin. The highest of these occurred on the 17th
and 18th of March 1944 when flood stages were reached. The gates
of the Whitney Point Reservoir were closed during that period, ef-
fecting a total reduction of about 1.6 feet in stage at Whitney Point
 (village), N. Y., decreasing to a 1-foot reduction at Binghamton,
N. Y., and to about 0.8 foot at Waverly, N. Y. Only negligible dam-
ages were sustained by the communities without local flood protection.
Stream flows below the confluence of the Chemung and the Susque-
hanna Rivers were very low; no damage was sustained.
   Summary of costs and expenditures: The total cost of new work for
the fiscal year was $967,454.43 of which $827,858.80 was from regular
funds and $139,595.63 from contributed funds. The total cost of
maintenance work for the fiscal year was $37,462.53. The total ex-
penditures for new work for the fiscal year were $942,007.35, of
which $802,411.72 was from regular funds and $139,595.63 was con-
tributed funds. The total expenditures for maintenance for the fiscal
year were $34,867.60.
   Condition at end of fiscal year.-The entire project is approxi-
mately 52 percent complete. The Federal cost of new work to June
30, 1944, and the percentage of construction work completed for
each project unit are as follows:
                                                                   Percent                                                           Percent
                                           Cost of new             of con-                                       Cost of new         of con-
                     Unitwork                      to               struc-               Unit                      work to            struc-
                     Unit                 June 30, 1944              tion                                        June 30, 1944         tion
                                             (all funds)            com-                                          (all funds)         com-
                                                                   pleted                                                            pleted


Reservoirs:                                                                  Local flood protections-
  Davenport Center ....                      1 $81, 937.10               0       Continued.
                                                                                          ...       ...                    964. 77        20
  West Oneonta...
  East Sidney .
  Copes Corner ...
                           _
                             ._
                                      .
                                             1
                                               1 83, 552. 48
                                                131, 021.29
                                               1I 55, 942. 73
                                                                         0
                                                                         0
                                                                         0
                                                                              Elmira _ _$924,
                                                                              Corning-        -----
                                                                              Painted Post... ....
                                                                                                                  2, 064, 827. 41
                                                                                                                     401, 976. 26
                                                                                                                                         100
                                                                                                                                         100
  Whitney Point .- ..                        4, 238, 976.06            100    Addison .       . . . .                1 10,157. 55          0
  Arkport _.               .                 1,804,044. 24             100    Bath_                                  126, 985. 81          0
  Almond_                                     1 262, 775.02              0    Avoca                         _        405, 083. 31        100
Local flood protections:                                                      Canisteo ..           -                1 36, 351.55          0
  Oxford                                        86, 066.   78          100    Hornell_-                           2, 790, 097. 91        100
  Lisle-   .----------------                   165, 038.   80           45    Almond_        ------                     8, 490. 64         0
  Whitney Point -                              130, 922.   93            0
  Binghamton                              2...
                                           2, 638, 478.    16          100      Total-..--                      216, 247, 690. 80         52

             1   Costs   for   preliminary        work     only.             SIncludes   $163,095.63   contributed      funds.
             FLOOD CONTROLr--SYRACUSE,            N.    Y., DISTRICT            253
   The remaining work necessary for completion of the existing project
consists of completion of the project units on which construction was
terminated in accordance with the existing Federal policies on war-
time construction and engineering studies, foundation investigations,
design, acquisition of lands and easements, utility and highway re-
locations, and construction of remaining project units.
   The total cost of new work to June 30, 1944, was $16,247,690.80, of
which $15,349,323.53 was from regular funds, $735,271.64 from emer-
gency relief funds, and $163,095.63 from contributed funds. The
total expenditures for new work to June 30, 1944, were $16,278,317.41,
of which $15,379,950.14 was from regular funds, $735,271.64 from
emergency relief funds, and $163,095.63 from contributed funds.
   The total cost for maintenance to June 30, 1944, was $67,516.78, all
from regular funds. The total expenditures for maintenance to June
30, 1944, were $63,556.88, all from regular funds.
   Proposed operations.-The unexpended balance at the end of this
fiscal year, $1,700,992.98, plus accounts receivable, $106,507.67, plus the
estimated value of plant and materials available for use in operations,
$35,575.16, amounted to $1,843,075.81. This amount, plus the sum of
$116,000 allotted in July 1944, will be applied as follows:
Accounts payable on June 30, 1944_                                       $24, 226. 21
New work:
    East Sidney Reservoir: Completion of construc-
      tion plans and specifications for dam and equip-
      ment on Ouleout Creek; period July 1944 to
      June 1945:
         Design (hired labor) _______        __ _____     $19, 000. 00
    West Oneonta Reservoir: Completion of engineer-
     ing studies and design for dam and equipment
     on Otego Creek, and partial completion of
     construction plans and specifications; period
     July 1944 to June 1945:
         Design (hired labor) ---   -                      68, 600. 00
    Davenport Center Reservoir: Completion of
     engineering studies and design for the dam on
      Charlotte Creek and partial completion of
     construction plans and specifications for dam
     and mechanical equipment:
         Design (hired labor)__________________-__71,400. 00
    Whitney Point Reservoir: Installa-
     tion of stand-by equipment in gate
     house of the dam on Otselic River
     and completion of reimbursement
     to the State of New York for th6
     cost of lands, easements, rights-of-
     way, highway, and utility reloca-
      tions; period July 1944 to June
      1945:
         Construction (hired labor) -
         Lands (hired labor)  ---------
                                           -$3,175. 00
                                          560, 000. 00
                                                       563, 175. 00
    Arkport Reservoir: Completion of reimburse-
      ment to the State of New York for the costs
      of lands, easements, rights-of-way, and high-
      way relocations for the dam and reservoir on
      the Canisteo River; period July 1944 to June
      1945:
         Lands (hired labor) -            _- __---------76,    000. 00
254      REPORT OF CHIEF OF ENGINEERS,                  U. S. ARMY,         1944

New work-Continued.
    Almond Reservoir: Completion of reimbursement
       to the State of New York for the costs of lands,
       easements, and rights-of-way for the dam site
       on Canacadea Creek and adjacent work area;
      period July 1944 to June 1945:
         Lands (hired labor)                                    000. 00
                                                    _--------------------$228,
   •Oxford: Completion of reimbursement to the
       State of New York for the costs of lands, ease-
      ments, rights-of-way, and utility relocations
      for the channel improvement on the Chenango
      River; period July 1944 to June 1945:
         Lands (hired labor) -----------------             46, 000. 00
    Lisle: Completion of construction
      plans and specifications for con-
      struction of channel, walls and re-
      lated structures on Dudley Creek
      and Tioughnioga River; comple-
      tion of reimbursement to the State
      of New York for the costs of lands,
      easements, and rights-of-way for
      Tioughnioga River channel im-
      provement; period July 1944 to
      June 1945:
         Design (hired labor)- ---------   $5, 000. 00
         Lands (hired labor)- ----_---     10, 000. 00
                                                              15, 000. 00
    Binghamton:
        Section No. 1: Completion of
          reimbursement to the State
          of New York for the costs of
          lands, easements, utility re-
          locations, and rights-of-way
          for the Park Creek channel
          improvement;     period July
          1944 to June 1945:
             Lands (hired labor) ____-__       25, 075. 00
        Section No. 2: Completion of re-
          imbursement to the State of
          New York for the costs of
          lands, easements, utility re-
          locations, and rights-of-way
          for the Pierce Creek channel
          improvement;     period July
          1944 to June 1945:
             Lands (hired labor) .......       21, 560. 00
        Section No. 4: Completion of
          record drawings; period July
          1944 to June 1945:
             Construction (hired labor) -          600. 00
                                                             47, 235. 00
                                                                      __


    Elmira:
        Section No. -1: Settlement of
          accounts for construction of
          concrete flood walls and lev-
          ees on the Chemung River:
          period July 1944 to June
          1945:
             Construction (contract)__         65, 850. 00
             FLOOD CONTROL---SYRACUSE, N. Y., DISTRICT                            255
New work-Continued.
   Elmira-Continued.
      Section No. 2: Completion of
         construction plans and spec-
         ifications for construction of
         flood walls, levees, and re-
         lated structures on the Che-
         mung River, Seely, Newtown,
         and Diven Creeks, and Hoff-
        man Brook; completion of re-
         imbursement to the State of
         New York for the costs of
        lands, easements, and rights-
        of-way for the Hoffman
        Brook pressure conduit; pe-
        riod July 1944 to June 1945:
            Design (hired labor) -_----               $6,200. 00
             Lands (hired labor) _   -_  -            86, 000. 00
                                            --       $158, 050. 00
   Corning: Section No. 1: Completion of reim-
     bursement to the State of New York for the
     costs of lands, easements, utility relocations,
     and rights-of-way for Cutler Creek channel
     improvement; period July 1944 to June 1945:
        Lands (hired labor)_ _________________-- -     42,900. 00
   Painted Post: Completion of reimbursement to
     the State of New York for costs of lands, ease-
     ments, and rights-of-way for the channel im-
     provement on Cohocton River and Hodgman
     Creek; period July 1944 to June 1945:
        Lands (hired labor) ----------------------      9, 500. 00
   Bath: Completion of plans and specifications
     for walls and levees on the Cohocton River;
     period July 1944 to June 1945:
        Design (hire labor)          -       ------                 10, 000. 00
   Avoca: Completion of reimbursement to the
     State of New York for costs of lands, ease-
     ments, utility relocations, and rights-of-way
     for Cohocton River and Salmon Creek channel
    improvement; period July 1944 to June 1945:
       Lands (hired labor)_----------------------                   39, 000. 00
   Hornell:
       Upper and lower sections:
          Completion of reimburse-
          ment to the State of New
          York for costs of lands,
         easements,    utility reloca-
         tions, and rights-of-way for
         channel improvement           on
          Canfisteo River; period July
          1944 to June 1945:
            Lands (hired labor)- .----    $151,000. 00
       Middle section: Completion of
         reinbursement to the State
         of New York for costs of
         lands, easements, utility re-
         locations, and rights-of-way
         on Canisteo River, Cana-
         cadea Creek and Chauncey
         Run; period July 1944 to
         June 1945:
            Lands (hired labor) - -.       197, 406. 38
256      REPORT OF CHIEF OF ENGINEERS,                U.    S.    ARMY,          1944

New work-Continued.
   Hornell-Continued.
       Crosby Creek: Engineering
         studies and design for flood
         protection on Crosby Creek;
         period July 1944 to June
         1945:
            Design (hired labor) .           $35, 000. 00
      Chauncey Run: Construction
         of debris control works on
         Chauncey Run: period July
         1944 to December 1944:
            Construction (contract) -         45, 000. 00
      Canacadea Creek: Engineer-
         ing studies and design and
         preparation of plans and speci-
         fications for debris control
         works on Canacadea Creek;
         period July 1944 to June
         1945:
            Design (hired labor) . _          12, 000. 00
            Construction, partial (con-
              tract) ----------------         21,000. 00
                                                            $461, 406. 38
    Addison: Completion of engineering studies and
      design for flood protection on Canisteo River
      and Tuscarora Creek: preparation of plans and
      specifications for channel straightening, flood
      walls, and levees; period July 1944 to Septem-
      ber 1944:
         Design (hired labor)  ----------         __              9, 100. 00
    Almond (village) : Completion of plans and speci-
      fications for revised project for flood protec-
      tion on Canacadea and McHenry Valley
      Creeks; period July 1944 to November 1944:
         Design (hired labor) _______------5,000.                           00
    Canisteo: Completion of plans and specifications
      for flood protection works on Canisteo River,
      Bennett and Purdy Creeks, period July 1944 to
      December 1944:
         Design (hired labor)-__    --------                     10, 000. 00

            Total new work                         ---------------_---------------
                                                                       $1, 879, 366. 38
1Maintenance: The following listed units of the south-
  ern New York flood-control project will be main-
  tained by hired labor; period July 1944 to June
  1945:
     Whitney Point Reservoir__-     -------                 7, 834.27
     Arkport Reservoir_---------------------------          6, 016.86
     Hornell Channel improvement_        -     - -      --. 9, 058. 87
     Oxford Channel improvement -----------------           2, 999. 42
     Painted Post Channel improvement     ------------      3, 586. 74
     Avoca Channel improvement_                             3, 399. 98
     Binghamton Channel improvement (Park and
       Pierce Creeks) -       _-_         -___8,799.                13
     Corning Channel improvement (Cutler Creek)             8, 710. 14
     Lisle-Tioughnioga River Channel improvement_           5, 077. 81

       Total maintenance__      ------   _______-______--               -          55, 483. 22

       Total for all work and accounts payable   -----------------               1, 959, 075. 81
                 FLOOD CONTROLr--SYRACUSE, N. Y., DISTRICT                                                 257

   Additional funds that can be profitably expended for engineering
studies, design, preparation of construction plans and specifications,
and maintenance during the fiscal year ending June 1946, estimated to
be $333,000, will be used as follows:            *
New work:
   Copes Corner Reservoir: Engineering studies, design,
     plans, and specifications:
        Design (hired labor)                  ----------------- $195, 000
   Elmira-Pumping plant: Engineering studies, design,
     construction plans, and specifications:
        Design (hired labor)--  _          -----------            40, 000
   Davenport Center Dam and Reservoir: Construction
     plans and specifications (completion):
        Design (hired labor)--- -            -------          -   20, 000
   West Oneonta Dam and Reservoir: Construction plans
     and specifications (completion):
        Design (hired labor) --------------------------- 20,000
   Unallocated: Review reports and revisions of con-
     struction plans and specifications:
        (Hired labor)-- __     -------------                      25,000
          Total, new work__ --                      ---------------    ___$300,                             000
Maintenance: The project units at the following listed
locations will be maintained during the fiscal year July
1945 to June 1946:
    Whitney Point Reservoir_                     -    ----------                8, 000
    Arkport Reservoir_----------                                    ----        6, 000
    Oxford ------------------------------------------                           1,000
    Lisle_-------------------------------------------                           1,000
    Binghamton -------------------------------------                            5,000
    Corning -----------------------------------------                           4,000
    Painted Post__---                   -----------                       -     1, 000
    Avoca ------------------------------------------                            1,000
    Hornell -----------------------------------------                           6,000
        Total maintenance___---                   ------------                                          33, 000
        Total, new work and maintenance--                        ----------                           333, 000

                                  Cost and financial summary

                                         REGULAR FUNDS

Cost of new work to June 30, 1944                                                        1 $16, 084, 595. 17
Cost of maintenance to June 30, 1944_------                                        ---           67, 516. 78
       Total cost of permanent work to June 30, 1944 _---                                    1 16, 152, 111. 95
Undistributed costs June 30, 1944_--------                                                        -- 55, 614. 75
       Net total costs to June 30, 1944_------                                --              16, 096, 497. 20
Plus accounts receivable June 30, 1944              ---------------------                         106, 507. 67
      Gross total costs to June 30, 1944-------------------                                   16, 203, 004. 87
Minus accounts payable June'30, 1944_------                ---                                     24, 226. 21
     Net total expenditures ---------------------------                                   1 16, 178, 778. 66
Unexpended balance June 30, 1944-_-  .---------                                                1, 700, 992. 98
        Total amount appropriated to June 30, 1944                     ---------         1    17, 879, 771. 64
1 Includes $735,271.64 Emergency Relief funds.




       616634-45-pt. 1, vol. 1-          17
258             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                      1944


       Fiscal year ending June 30                     1940                   1941              1942                     1943                  1944

Cost of new work................ $2, 795,185.88 $4, 214, 756.97 $2, 933,038.98                                $1, 522,855.82              $724,684.78
Cost of maintenance........                   ------------                  6, 453.77        6, 86277                 16,737.71             37, 462. 53
         Total cost..--------------             2,795,185.88           4,221,210.74       2, 939, 901. 75       1, 539, 593. 53             762,147.31

Total expended.................2,464,534.40                           3,842, 764.02      3, 547,752. 41        1,726,743. 24               837, 279. 32

Allotted.......................--------------------. 2,062,221.72      3,438,000.00       2,347,100.00                 47, 000.00       -1,087, 000. 0()


Balance unexpended July 1, 1943      __________________                                                                       $3, 625, 272. 30
Deductions on account of revocation of allotment------------                                                                   1, 087, 000. 00
       Net amount to be accounted for                                                                                                , 538, 272. 30
                                                                                                                                    2---------------------
Gross amount expended_                          $1, 748, 279. 61
Less:
     Reimbursements collected.    $906, 685. 68
     Receipts from sales --------    4, 314. 61
                                                    911, 000. 29
                                                                                                                                      837, 279. 32
      Balance unexpended June 30, 1944--------------------                                                                      1, 700, 992. 98
Outstanding liabilities June 30, 1944---------- 1, 269, 989. 03
Amount covered by uncompleted contracts.-.          76, 021. 89
                                                                                                                                    1, 346, 010. 92

      Balance available June 30, 1944_                                                                                                354, 982. 06
Accounts receivable June 30, 1944_ - -                                         --------                                 -             106, 507. 67

            Unobligated balance available June 30, 1944-------------                                                                  461, 489. 73
            Amount allotted in July 1944 -----------------------                                                                      116, 000. 00
            Available for fiscal year 1945- ...----------
                                                      .                                                   -    -                      577, 489. 73
Amount (estimated) required to be appropriated for comple-
      tion of existing project 2_-
                                .-                           ----------------------                                            16, 010, 642. 80

Amount that can be profitably expended in fiscal year ending
June 30, 1946:
   For new work 2-- - -- - - - - - - - - - - - - - - - - - - - - -                                                      -     - -
                                                                                                                                      300, 000. 00
         For maintenance 2---                   --------------------                                  ------                           33, 000. 00

            Total 2---          -           ------------------------------------.                                                     333, 000. 00
  2   Exclusive of available funds.
                                                       CONTRIBUTED FUNDS

Cost of new work to June 30, 1944__--         --------                                                                                163, 095. 63
Cost of maintenance to June 30, 1944_--------
       Total cost of permanent work to June 30, 1944--------                                                                          163, 095. 63
Net total expenditures-_                 -    --                                                                                      163, 095. 63
Total amount appropriated to June 30, 1944----------------                                                                            163, 095. 63

      Fiscal year ending June 30                     1940                   1941              1942                     1943                  1944


Cost of new work....
                 --------                        .                .-_
                                                                 ____        $20, 500           $3, 000 --.        ,                $139,
                                                                                                                               --.....     6&
                                                                                                                                        595.
Cost of maintenance.....................
Total expended.......------------------------------20, 500                                           --
                                                                                                 3, 000                              139, 595. 63
                                                                                                                            -------------

Allotted_......................                       $53, 400                   3,000          50,000             $49, 030. 13               7, 665. 50




                                                      4
                             FLOOD CONTROL--SYRACUSE,                                 N. Y., DISTRICT                              259
Balance unexpended July 1, 1943------------------ --------                                                              $131, 930. 13
Amount contributed under the authorizing act of July 19, 1937-                                                             7, 665. 50
       Amount to be accounted for------------------------                                                                 139, 595. 63
Gross amount expended_---- --                _-_139,                                                                           595. 63


CONSOLIDATED                  COST         AND     FINANCIAL SUMMARY   FOR                          SOUTHERN              NEW     YORK
                                                   FLOOD-CONTROL PROJECT

Cost of new work to June 30, 1944_                                                                      .-      1$16, 247, 690. 80
Cost of maintenance to June 30, 1944_--                                         --           -67,                               516. 78
      Total cost of permanent work to June 30, 1944_--     - 1 16, 315, 207. 58
Undistributed costs June 30, 1944_------------------------      --- 55, 614. 75
       Net total cost to June 30, 1944__                                                                              16, 259, 592. 83
Plus accounts receivable June 30, 1944---------------------                                                               106, 507. 67
       Gross total costs to June 30, 1944-------------------16, 366, 100. 50
Minus accounts payable June 30, 1944-----------------24,            226. 21
     Net total expenditures----------                                                                     -      1 16, 341, 874. 29
Unexpended balance June 30, 1944_-                                           .---------                                1, 700, 992. 98
              Total amount appropriated to June 30, 1944----------                                                    18, 042, 867. 27

     Fiscal year ending June 30                      1940                1941              1942                1943             1944


Cost of new work ........
                   __                       . $2, 795, 185. 88 $4, 235, 256. 97 $2,936, 038. 98 $1, 522, 855. 82             $967, 454. 43
Cost of maintenance ..........                --       -___
                                                         -___....    6, 453. 77      6, 862. 77      16, 737. 71               37, 462. 53

         Total cost..............--------------. 2, 795, 185. 88    4, 241, 710. 74   2, 942, 901. 75   1, 539, 593. 53     1, 004, 916. 96

Total expended....---------------2, 464, 534. 40                    3, 863, 264. 02   3, 550, 752. 41   1, 726, 743. 24       976, 874. 95

Allotted_ ............-.--            ..         2,115, 621. 72     3, 441, 000. 00   2, 397, 100. 0T         96, 030. 13 -1,079, 334. 50


Balance unexpended July 1, 1943_-    ---------                                                                 -$3,       757, 202. 43
Amount contributed under authorizing act of July 19, 1937....                                                               7, 665. 50
      Amount to be accounted for_-    -_____                                                                           3, 764, 867. 93
Deductions on account of revocation of allotment                                          -----------                  1, 087, 000. 00
       Net amount to be accounted for---------------------                                                             2, 677, 867. 93
Gross amount expended ------------------      $1, 887, 875. 24
Less:
     Reimbursements collected - $906, 685. 68
     Receipts from sales --------- 4, 314, 61
                                                  911, 000. 29
                                                                                                                          976, 874. 95
       Balance unexpended June 30, 1944-------------------                                                             1, 700, 992. 98
Outstanding liabilities June 30, 1944       1, 269, 989. 03        ---------
Amount covered by uncompleted contracts-.       76, 021.89
                                                            1, 346,                                                             010. 92
      Balance available June 30, 1944---------------------     354,                                                             982. 06
Accounts receivable June 30, 1944_                             106,                                                             507. 67
      Unobligated balance available June 30, 1944_             461,                                                             489. 73
Amount allotted in July 1944-----------------------------      116,                                                             000. 00
      Available for fiscal year 1945_                      -577,                                                                489. 73
      Amount (estimated) required to be appropriated for
         completion of existing project 2-    --   -16,        010,                                                             642. 86
   SIncludes $735,271.64 Emergency Relief Funds.                             2 Exclusive    of available funds.
260        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,           1944

Amount that can be profitably expended in fiscal year ending
June 30, 1946:
      For new work     2              -----------------         $300, 000. 00
      For maintenance -----------------------------------         33, 000.00
               2
       Total                  _         -----------------           333,000.00
sExclusive of available funds.

          10. STILLWATER RESERVOIR, LACKAWANNA RIVER, PA.

   Location.-The Stillwater Dam site is on the Lackawanna River, 37
miles from the mouth of the stream and about 2 miles upstream from
Forest City, Susquehanna County, Pa. (See U. S. Geological Survey
quadrangle sheet "Pennsylvania-Honesdale.")
   Existing project.-This provides for the construction of the Still-
water Dam, of the concrete gravity type, with spillway crest 50 feet
above river level. The reservoir capacity will be 13,300 acre-feet, of
which 12,480 acre-feet will be for flood-control storage and 820 acre-
feet will be utilized to maintain the existing water-supply reservoir
for Forest City, Pa., at this site. The reservoir area will be 550
acres, and the pool will extend 3 miles upstream. The reservoir will
control 55 percent of the watershed above Carbondale, 28 percent
above Olyphant, and 17 percent above Scranton. The existing project
was authorized by the Flood Control Act approved August 18, 1941, as
a modification of the southern New York and eastern Pennsylvania
project authorized by the Flood Control Act approved June 22 1936.
The estimated construction cost is $866,000; the cost of lands and dam-
ages is $1,554,000.
   Local cooperation.-Section2 of the Flood Control Act approved
June 28,1938, applies.
    Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were continued by hired
labor. The cost of this work was $4,554.51 for new work. The
expenditures were $6,383.82.
    Condition at end of fiscal year.-Preparation of plans has been tem-
porarily suspended pending completion of a review report for the
Lackawanna River. Construction has not been initiated. The cost
was $49,594.22 for new work. The expenditures, all for new work,
were $49,530.10.
    Proposed operations.-The unexpended balance at the end of the
fiscal year amounted to $80,469.90. This amount will be applied as
follows:
Accounts payable, June 30, 1944 --------------------------------     $64. 12
New work: Completion of engineering studies, design, plans, and
specifications for the dam on the Lackawanna River; period July
  1944 to June 1945:
    Design (hired labor) ------------------------------------    80, 405. 78
         Total--------------------------------------            .     80,469.90
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                           FLOOD CONTROL---SYRACUSE,                         N.    Y., DISTRICT                  261
                                         Cost and financial summary
Cost ofnewworktoJune30, 1944                                                                              49,594.22
                                                                                                         $-----------
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-----------                                            49, 594. 22
Minus accounts payable June 30, 1944_                                                                          64. 12
     Net total expenditures_ ___----49,                                                                       530. 10
Unexpended balance June 30, 1944                                 -_80,                                        469. 90
             Total amount appropriated to June 30, 1944-------------                                     130, 000. 00


     Fiscal year ending June 30            1940              1941                  1942     1943              1944

Cost of new work ------------------------------------------------......                   $45, 039. 71        $4, 554. 51
Cost ofmaintenance                                                                                                     .
Total expended __._______________...____          _     _________-_
                                                        ...                                43,146. 28          6, 383.82

Allotted-------------...--------------                --------------------------          130,000.00      -----------.............



Balance unexpended July 1, 1943_                                                                         $86, 853. 72
Gross amount expended -------------------------------------                                                6383.
                                                                                                           6,      82
             Balance unQxpended June 30, 1944 ---------------------                                       80, 469. 90
Amount (estimated) required to be appropriated for completion of
  existing project 1__- - - - - - - - - - - - - - - - -        -
                                                                 2, 290, 000. 00
1Exclusive of available funds.

                          11. WILLIAMSPORT, SUSQUEHANNA RIVER, PA.

   Location.-Williamsport, the county seat of Lycoming County, Pa.,
is located on the left bank of the West Branch of the Susquehanna
River, 40 miles above its mouth and immediately below the mouth
of Lycoming Creek. (See U. S. Geological quadrangle sheets, "Penn-
sylvania-Trout Run and Williamsport.")
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and concrete flood walls, consisting of
the following features: About 25,120 feet of earth levee and 3,770
feet of concrete flood wall along the left bank of the West Branch
of the Susquehanna River, extending from high ground near Meade
Street and Lose Avenue generally parallel to and on the right bank of
Millers Run to the Susquehanna River, thence extending upstream
along the left bank of the river and Lycoming Creek; about 15,350
feet of earth levee and 4,450 feet of concrete flood wall along the left
bank of the West Branch of the Susquehanna River, extending from
high ground at Mill Lane generally parallel to and on the right bank
of Lycoming Creek to the Susquehanna River, thence extending up-
stream along the left bank of the river to Reighard Avenue, thence
to high ground at Dove Street and Wayne Avenue; about 10,150 feet
of earth levee and 1,550 feet of concrete flood wall along the right
bank of the West Branch of the Susquehanna River in South Wil-
liamsport, extending from high ground at Central Avenue and Charles
Street, along Charles Street to the river, thence upstream along the
river to high ground at Maynard Street; a reinforced concrete pres-
sure culvert about 2,250 feet long to provide for control of Hagerman
Run; 10 pumping stations for the disposal of interior drainage; and
262       REPORT OF CHIEF OF ENGINEERS,                           U. S. ARMY,       1944

appurtenant drainage structures. The project will provide protec-
tion for the city of Williamsport and the borough of South Williams-
port against floods 4 feet higher than the maximum flood of record,
which occurred in March 1936. The existing project was authorized
by the Flood Control Act approved June 22, 1936. The estimated cost
of the new work, revised in 1940, is $5,278,000 for construction, and
$571,700 for lands and damages.
   Local cooperation.-See page 7 for requirements. Local interests
have furnished assurances that all the requirements will be complied
with. Rights-of-way have been acquired for the first and second units
of construction work.
    Operationsand results during fiscal year.-Engineering studies, de-
sign, and the preparation of contract plans and specifications by hired
labor were in progress. The cost of this work was $72,664.13 for new
work. The expenditures were $67,777.89.
   Condition at end of fiscal year.-Construction of the project was
suspended in accordance with the existing Federal policies on wartime
construction. The project is about 18 percent complete. Preparation
of contract plans for section I is 90 percent complete, for section II is
44 percent complete, for section III is 35 percent complete. The total
costs, all for new work, were $1,064,119.58, of which $1,062,232.55 were
regular funds and $1,887.03 were emergency funds. The total expendi-
tures, all for new work, were $1,061,158.83, of which $1,059,271.80
were regular funds and $1,887.03 were-emergency funds.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $181,728.20, plus accounts receivable, $52.41, amounted to
 $181,780.61. This amount will be applied as follows:
Accounts payable June 30, 1944  ------------                    $4, 847. 11
New work: Engineering studies, design, and plans and specifications
  for levees, walls, and pumping plants on the West Branch of the
  Susquehanna River; completion of plans for sections I and II;
  partial completion of plans for section III and pumping plants;
  period July 1944 to June 1945:
     Design (hired labor)----     ------------                _-176,                         933. 50
        Total     ---------------------------------------------                         181, 780. 61
   An additional sum of $50,000 can be profitably expended during the
fiscal year 1946 for completion of design, plans, and specifications for
section III.
                                    Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                        $1, 064, 119. 58
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944                 ---------       1 1, 064, 119. 58
Undistributed costs June 30, 1944---     -----------                                       1, 833. 95
       Net total cost to June 30, 1944---   --------                                 1, 065, 953. 53
Plus accounts receivable June 30, 1944-----------------------                                 52. 41
      Gross total costs to June 30, 1944 --------------------     1, 066, 005. 94
Minus accounts payable June 30, 1944_------                   ---      4, 847. 11
      Net total expenditures -----------------------------                           1, 061, 158:83
Unexpended balance June 30, 1944--------------------------                              181, 728. 20
        Total amount appropriated to June 30, 1944--_                    --     _    1, 242, 887. 03
1Includes $1,887.03 emergency relief funds.
                      FLOOD CONTROL-SYRACUSE,                                         N.    Y., DISTRICT                              263*

   Fiscal year ending June 30                      1940              1941                  1942                 1943             1944


Cost of new work _.___... ......             $113,762.14          $288, 689.17        $511, 706.86        $11, 511.34          $72, 664.13
Cost ofmaintenance ..-------- .              .          .     .        ..---------------------------------------------------------
Total expended_.... ..-.......               -117, 226. 90         220, 986. 25        581, 544.25           4,209. 55           67, 777. 89
Allotted          ..----------------------       366,000.00        200,000.00          500, 000.00      -490, 000.00 ...             ....


Balance unexpended July 1, 1943__-- -----            ---                                                                $249, 506.09
Gross amount expended- _       ---    -----       $67, 793. 10
                             --------------------
Less reimbursements collected_.                          15. 21
                                                                                                                           67, 777. 89

      Balance unexpended June 30, 1944---------------------                                                              181, 728. 20
Outstanding liabilities June 30, 1944---
                                      .....  ---------                                                                        112. 83

      Balance available June 30, 1944.-_                                          --------                               181, 615. 37
Accounts receivable June 30, 1944_---------                                                                     ---            52. 41

           Unobligated balance available June 30, 1944--------------                                                     181, 667. 78

Amount (estimated) required to be appropriated for completion of
   existing project 2- ___                          -         -        -          -          --             -          4, 035, 100. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 2-      ---         ----           ---                                                             50, 000. 00
  2 Exclusive   of available funds.

12. WILKES-BARRE-HANOVER TOWNSHIP, SUSQUEHANNA RIVER, PA.

   Location.-The city of Wilkes-Barre, with Hanover Township ad-
joining, is located in the central part of Luzerne County, Pa., on the
left bank of the North Branch of the Susquehanna River approxi-
mately 62 miles above its mouth. (See U. S. Geological Survey quad-
rangle sheets "Pennsylvania-Pittston and Wilkes-Barre.")
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees and concrete flood walls, consisting
of the following features: About 25,350 feet of earth levee and 161.5
feet of concrete flood wall along the left bank of the North Branch
of the Susquehanna River, extending from high ground at the Le- -
high & West Virginia Railroad near Union Street in Wilkes-Barre
downstream along the left bank of the river to high ground near the
mouth of Solomon Creek in Hanover Township; eight pumping sta-
tions for the disposal of interior drainage; appurtenant drainage
structures; about 17,900 feet of electric transmission line; and two
transformer substations for furnishing power to the pumping sta-
tions. The project will provide protection for the city of Wilkes-
Barre and the borough of Hanover Township against floods 4 feet
higher than the maximum flood of record, which occurred in March
1936. The existing project was authorized by the Flood Control Act
approved June 22, 1936. The estimated cost for new work, revised
in 1942, is $3,409,700 for construction, and $210,000 for lands and
damages. The completed portions of the project were turned over to
local interests for maint enance and operation.
   Local cooperation.-See page 7 for requirements. All rights-of-
way requirements have been met.
   Operations and results during fiscal year.-Construction of the
Solomon Creek pumping station was suspended July 20, 1943, in ac-
264            REPORT OF CHIEF OF ENGINEERS, U.                                                 S. ARMY,             1944

cordance with existing Federal policies on wartime construction.
Work consisted of placing 739 cubic yards of gravel for access road,
60 cubic yards of riprap, and miscellaneous clean-up. Engineering
studies and design in connection with the construction of the proj-
ect were continued by hired labor. The costs, all for new work, were
$76,509.67. The expenditures were $111,206.58.
   Condition at end of fiscal year.-The project, as originally author-
ized, is 96 percent complete. The work remaining to be done is the
completion of the Solomon Creek pumping station and the installa-
tion of pumping equipment which was deferred in accordance with
the existing Federal policies on wartime construction. The total
costs, all for new work, were $3,298,503.44, of which $2,425,788.71 were
regular funds and $872,714.73 from emergency funds. The total ex-
  enditures, all for new work, were $3,296,470.20, of which $2,423,-
  55.47 were regular funds and $872,714.73 were from emergency funds.
   Proposed operations.--The unexpended balance at the end of the
fiscal year, $43,086.65, plus accounts receivable, $258.79, amounted to
$43,345.44. This amount will be applied as follows:
Accounts payable, June 30, 1944 _           -     -             $1, 405. 44
New work: Solomon Creek pumping station (exclusive of pumping
equipment which will be supplied at a future date). Completion
of construction of pumping station and appurtenant work (con-
tract); period July 1944 to June 1945:
    Construction: Settlement of pending accounts-----
    Solomon Creek pumping station. Completion of final drawings
                                                                37, 833. 00                                  -__
      and reports by hired labor; period July 1944 to December
      1944----------------------                                 4, 107. 00
             Total            -------------------------------------------                                                  43, 345. 44
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                                 Cost and financial summary
Cost of new work to June 30, 1944_-----------------------                                                     1 $3, 298, 503. 44
(otf.   of    m    intennce          to   June     30.9    1944IQL.


      Total cost of permanent work to June 30, 1944-.......                                                       1'3, 298, 503. 44
Undistributed costs June 30, 1944 __                                                                                        - 886. 59
       Net total cost to June 30, 1944_                                                                              3, 297, 616. 85
Plus accounts receivable June 30, 1944__                                                                                     258. 79
      Gross total costs to June 30, 1944 --                                                --                        3, 297, 875. 64
Minus accounts payable June 30, 1944_ __                                                                -1,                  405. 44
     Net total expenditures                                                           -            -    -        1   3, 296, 470. 20
Unexpended balance June 30, 1944 _43,                                                                                        086. 65
             Total amount appropriated to June 30, 1944                                   -----------            1 3, 339, 556. 85



    Fiscal year ending June 30                      1940                 1941             1942              1943               1944


Cost of new work__-------------                  $472, 321.75         $682. 698. 48   $335, 835. 41    $383, 254. 59          $76, 509. 67
Cost of maintenance ..........
                          -    .....................................                                          ..........       .......
Total expended ----------------...............    391, 286. 03         694, 853.59     300, 783.37      415, 787. 57          111, 206. 58

Allotted_..---------------- ----------------                           134,110.61     -40,000.00        175,000.00           -70,096. 80

  1Includes $872,714.73 emergency relief funds.
                 FLOOD CONTROL-             SYRACUSE,        N.    Y.,   DISTRICT           265

Balance unexpended July 1, 1943_--------                                 ---        $224, 390. 03
Deductions on account of revocation of allotment_-                       __70,            096. 80

       Net amount to be accounted for----------------------                          154, 293. 23
Gross amount expended--     -------            $113, 978.06
Less reimbursements collected-----------------    2, 771.48
                                                                                     111, 206. 58

       Balance unexpended June 30, 1944--------------                                 43, 086. 65
Outstanding liabilities June 30, 1944        -----------
                                                     249. 82
Amount covered by uncompleted contracts    .     37, 933. 00
                                                                                      38, 182. 82
      Balance available June 30, 1944_- ....                 -------                   4, 903. 83
Accounts receivable June 30, 1944_-____----------                                         258. 79

        Unobligated balance available June 30, 1944               -----------          5, 162. 62

Amount (estimated) required to be appropriated                  for completion
                             - - -_- - - - - - - - - - - - -    -
  of existing project 2_            ___ _ _                                          195, 900.00
2 Exclusive of available funds, required for completion of deferred work.

        13. KINGSTON-EDWARDSVILLE, SUSQUEHANNA RIVER, PA.

   Location.-The boroughs of Kingston and Edwardsville, Pa., are
located in Luzerne County, Pa., on the right bank of the North Branch
of the Susquehanna River approximately 62 miles above its mouth.
 (See U. S. Geological Survey quadrangle sheet, "Pennsylvania-
Pittston.")
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees consisting of the following features:
About 18,169 feet of earth levee along the right bank of the North
Branch of the Susquehanna River, extending from high ground, near
Rutter Avenue and Church Street in Kingston southeasterly to the
river, thence downstream along the right bank of the river to the
Kingston-Edwardsville borough line, thence northerly generally par-
allel to the Edwardsville borough line, to high ground near Toby
Creek and Plymouth Street; a concrete pressure culvert about 6,659
feet long to carry the flow of Toby Creek; three pumping stations for
the disposal of interior drainage; 3,080 feet of concrete intercepting
sewer; appurtenant drainage structures; and about 16,700 feet of elec-
tric transmission lines with 2 transformer substations for furnishing
power to the pumping stations. The project will provide protection
for the boroughs of Kingston and Edwardsville against floods 4 feet
higher than the maximum flood of record, which occurred in March
1936. The existing project was authorized by the Flood Control Act
approved June 22, 1936. The estimated cost of new work, revised in
1943, is $4,376,600 for construction, and $370,000 for lands and dam-
ages. The completed portions of the project were turned over to
local interests for maintenance and operation.
   Local cooperation.-See page 7 for requirements. All rights-of-
way requirements have been met.
   Operations and results during fiscal year.-Alterations to the inlet
structure and removal of debris from the Toby Creek pressure culvert
was completed August 10, 1943, under contract. The work involved
the excavation of 976 cubic yards of earth, the placement of 148 cubic
yards of earth fill, 82 cubic yards of rock paving, 147 cubic yards of
266          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                              1944

concrete, and 50 cubic yards of gravel and sand backing. Engineering
studies and design in connection with the construction of the project
were continued by hired labor. The costs, all for new work, were
$18,445.07. The expenditures were $23,262.25.
   Condition at end of fiscal year.--Construction of the project was
completed in August 1943. The total costs, all for new work, were
$4,338,190.24, of which $3,175,641.82 were regular funds and $1,162,-
548.42 were from emergency relief funds. The total expenditures, all
for new work, were $4,345,996.51 of which $3,183,448.09 were regular
funds and $1,162,548.42 were from emergency funds.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $1,972.78, plus accounts receivable, $606.31, amounted to
$2,579.09. This amount will be applied as follows:
Accounts payable, June 30 1944--------------------------------$330. 16
New work: Completion of final drawings and reports by hired labor,
  period July to December 1944-------------------------------      2, 248. 93

          Total----------------------------------------------2,                                                                  579.09
                                         Cost and financial summary
Cost of new work to June 30, 1944__________                                                                     1 $4, 338, 190. 24
Cost of maintenance to June 30, 1944 ...

      Total cost of permanent work to June 30, 1944 ....                                             __             1 4, 338, 190. 24
Undistributed costs June 30, 1944_____   ......                                                                                7, 530. 12
       Net total cost to June 30, 1944__----                                   -- ____                               4, 345, 720. 36
Plus accounts receivable June 30, 1944---                               - --                     .                           606. 31

      Gross total costs to June 30, 1944                              ...-       ..-...                              4, 346, 326. 67
Minus accounts payable June 30, 1944_                                  ..-   --           .-..                               330. 16
      Net total expenditures------------,_                                                                          1 4, 345, 996. 51
Unexpended balance June 30, 1944_    ....                                          .                 ...                       1, 972. 78

          Total amount appropriated to June 30, 1944                                                 __-_           1 4, 347, 969. 29

    Fiscal year ending June 30                1940             1941              1942                        1943                1944

Cost of new work- .............            $638, 236. 88 $1, 019, 152. 83     $224, 140. 98            $230, 728. 33            $18, 445. 07
Cost of maintenance ---------   ----------      -     -  -------------.   --------------             --------------.       -           .
                                                                                                                                -- - ---


Total expended- ----.--------..
                             _             466, 042. 92   1,097, 498. 38      237, 321. 73                 244, 088. 67          23, 262. 25
Allotted,------------------           --------------        -57, 376. 87       40, 000. 00                  45, 000. 00        -28, 579. 13

Balance unexpended July 1, 1943-__-- -----------                                                                          $53, 814. 16
Deductions on account of revocation of allotment_-                                 ---------                               28, 579. 13
       Net amount to be accounted for ----------------------                                                               25, 235. 03
Gross amount expended_-- -          -        -     -     $33, 728. 87
Less:
     Reimbursements collected.......-------- $8, 695. 39
     Receipts from sales--------------1, 771.23
                                                          10, 466. 62
                                                                                                                           23, 262. 25
      Balance unexpended June 30, 1944--------------------                                                                  1, 972. 78
Outstanding liabilities June 30, 1944_-     -      ----------                                                                  378. 85
      Balance available June 30, 1944_ -      -___---------1,                                                                  593. 93
Accounts receivable June 30, 1944_-_ _    ---                 _------606.                                                           31
      Unobligated balance available June 30, 1944                               -----------                                 2, 200. 24
1Includes $1,162.548.42 emergency relief funds.
                FLOOD CONTROL---SYRACUSE,                   N.   Y., DISTRICT        267
                   14. PLYMOUTH, SUSQUEHANNA RIVER, PA.

   Location.-The borough of Plymouth is located in Luzerne County,
Pa., on the right bank of the North Branch of the Susquehanna
River, 59.5 miles above its mouth. (See U. S. Geological Survey
quadrangle sheet "Pennsylvania-Wilkes-Barre.")
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees consisting of the following features:
About 8,680 feet of earth levee along the right bank of the North
Branch of the Susquehanna River, extending from high ground near
the Carey Avenue Bridge downstream along the right bank of the
river to Mras Street, thence northerly to high ground near Main
Street approximately paralleling Flat Road; a diversion channel
about 2,670 feet long on the outside of the levee system from Main
Street to the river paralleling Flat Road; two pumping stations for
the disposal of interior drainage; appurtenant drainage structures;
and about 4,100 feet of electric transmission lines, with one trans-
former substation for supplying power to the pumping stations. The
project will provide protection for the borough of Plymouth against
floods 4 feet higher than the maximum flood of record, which occurred
in March 1936. The existing project was authorized by the Flood
Control Act approved June 22, 1936. The estimated cost of new work,
revised in 1942, is $1,311,900 for construction and $150,000 for lands
and damages.
   Local cooperation.-See page 7 for requirements. Local interests
have furnished assurances that all the requirements will be complied
with. All rights-of-way requirements have been met.
   Operations and results during fiscal, year.-Construction of the
Plymouth pumping stations was continued under contract. Work was
terminated July 31, 1943, in accordance with the existing Federal poli-
cies on wartime construction. The major features of construction in-
cluded 5,060 cubic yards of excavation, 4,799 cubic yards of earth fill,
82 cubic yards of riprap and rock gutter, 54 cubic yards of crushed
stone backing, and 104 cubic yards of gravel road surfacing. Engi-
neering studies and design in connection with the construction of the
project were continued by hired labor. The costs, all for new work,
were $72,451.81. The expenditures were $111,468.93.
   Condition at end of fiscal year.-The project, as originally author-
ized, is 84 percent complete. The remaining work consists of comple-
tion of construction of the Plymouth pumping stations. This includes
the installation of pumping equipment and appurtenances which was
deferred in accordance with the existing Federal policies on wartime
construction. The total costs, all for new work, were $1,138,791.82, of
which $1,134,435.06 were regular funds and $4,356.76 were from emer-
gency funds. The total expenditures, all for new work, were $1,133,-
965.41, of which $1,129,608.65 were regular funds and $4,356.76 were
from emergency funds.
   Proposed operations.-The unexpended balance at the end of the
fiscal year amounted to $9,391.35. This amount will be applied as
follows:
Accounts payable, June 30, 1944-----------------------------       $4, 826. 41
New work: Completion of final drawings and reports by hired labor,
  period July to December 1944__------------------------------4,       564. 94
      Total--. ----------------------.-------------------                       9, 391. 35
268                 REPORT OF CHIEF OF ENGINEERS,                                        U. S. ARMY,                        1944

  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                                         Cost and financial summary
Cost of new work to June 30, 1944                                                                                      1 $1, 138, 791. 82
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944- --------                                                           111,138, 791. 82
Minus accounts payable June 30, 1944----- -----------------                                                                        4, 826. 41
     Net total expenditures_----------------------------- 1 1,133, 965. 41
Unexpended balance June 30, 1944-------------------------       9, 391. 35
               Total amount appropriated to June 30, 1944                                                                     1, 143, 356. 76
                                                                                                                            t-----------


      Fiscal year ending June 30                           1940            1941            1942                      1943                 1944

                ....----------..
Cost of new work----                                     $69, 824. 34   $204, 419. 02   $233, 589. 44         $538, 420. 46              $72, 451.81
Cost ofm aintenance..- - .-                                              - - --..--       - --.-.-     . ..
                                                                                            . . ... .-..
Total expended....----------------                        69, 923. 46    179, 917. 26    199, 590. 69          552, 396. 14              111, 468. 93
Allotted---------------------.........................   109, 000. 00     97, 000. 00    357, 000.00         -145,    000. 00---------


Balance unexpended July 1, 1943_-- ---------                                                                     -            $120, 860. 28
Gross amount expended_ _     ---------------                                                                                   111, 468. 93
               Balance unexpended June 30, 1944-------------                                            --                         9, 391.35

Amount (estimated) required to be appropriated for completion
of existing project 2___                                                                                                      582, 000. 00
   1 Includes $4,356.76 emergency relief funds.
    2Exclusive of available funds.

                                      15. SUNBURY, SUSQUEHANNA RIVER, PA.

   Location.-Sunbury, Pa., is situated on the Susquehanna River in
Northumberland County, Pa. (See U. S. Geological Survey quad-
rangle sheet "Pennsylvania-Sunbury.")
   Existing project.-This provides for protection of people and prop-
erty at Sunbury, Pa., against floods somewhat higher than the 1936
flood, by means of levees, flood walls, and related works along the
river front and at the northern and southern limits of the city. The
existing project was authorized by the Flood Control Act approved
June 22, 1936, as modified by the Flood Control Act approved August
18, 1941 (H.Doc. No. 366, 76th Cong., 1st sess.). The estimated conk
struction cost, revised in 1944, is $2,185,000; the cost of lands and
damages is $53,000.
   Local cooperation.-See page 7 for requirements. Assurances of
cooperation have been furnished by the city of Sunbury.
   Operations and results during fiscal year.-Surveys, foundation in-
vestigations, engineering studies, and design were continued by hired
labor. The cost of this work was $60,320.38 for new work. The expen-
ditures were $55,542.75.
   Condition at end of fiscal year.-Preparation of contract plans and
specifications for the Shamokin Creek portion of the project is complete,
for the Susquehanna River portion is 89 percent complete. Construc-
tion has not been initiated. The cost was $69,195.97 for new work.
The expenditures, all for new work, were $63,517.06.
                       FLOOD CONTROL---SYRACUSE,                                     N. Y,               DISTRICT                       269
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $16,482.94, plus the amount of $10,000, allotted in July 1944,
amounted to $26,482.94. This amount will be applied as follows:
Accounts payable, June 30, 1944_ _--------------$5,                                                                                 678. 91
New work: Completion of construction plans and specifications for
  levees, flood walls, pumping stations, and related works on the Sus-
  quehanna River and Shamokin Creek, period July 1944 to June 1945:
     Design (hired labor)-----------------------------20,                                                                           804. 03

           Total              ---------------------------------------                                                       26, 482. 94
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                                 Cost and financial summary
Cost of new work to June 30, 1944_--                                                                                       $69, 195. 97
Cost of maintenance to, une 30, 1944
      Total cost of permanent work to June 30, 1944--------------                                                           69, 195. 97
Minus accounts payable June 30, 1944--------------------------                                                               5, 678. 91
      Net total expenditures  --------------------------------- 63, 517. 06
Unexpended balance June 30, 1944    ---------------------       16, 482. 94
           Total amount appropriated to June 30, 1944--                                                                     80, 000. 00


    Fiscal year ending June 30                      1940             1941                    1942                1943               1944

Cost of new work -------...--------------                        .   .....--------------....--------------   $8,875. 59            $60,320.38
Cost of maintenance-
Total expended ..-..... . . . ..                           .. .. .     . ..-             -    ----       -    7, 974. 31            55, 542. 75

Allotted    .......         ..----------------    ..--------------...--------------------------              80,000.00      ....


Balance unexpended July 1, 1943                                             -----------                                    $72, 025. 69
Gross amount expended _-                                                             -               -       -              55, 542. 75
       Balance unexpended June 30, 1944 -16,                                                                                        482. 94
Outstanding liabilities June 30, 1944------------------- ------                                                                     127. 78
                                      -
     Balance available June 30, 1944_--    -----        _                                                                   16, 355. 16
Amount allotted in July 1944---------------------------------                                                               10, 000. 00
           Amount available during fiscal year 1945---- -----------                                                         26, 355. 16

Amount (estimated) required to be appropriated for completion
of existing project------------------_  ------------ -----                                                             2, 085, 000. 00
  1 Exclusive of available funds.


                           16. SWOYERSVILLE AND FORTY FORT, PA.

   Location.-Swoyersville and Forty Fort, Pa., are situated on the
Susquehanna River in Luzerne County, Pa. (See U. S. Geological
Survey quadrangle sheet, "Pennsylvania-Pittston.")
   Existing project.--The proposed improvement will provide pro-
tection for the communities of Swoyersville and Forty Fort against
a flood approximately 4 feet higher than the maximum flood of
record, which occurred in March 1936, by means of levees and related
works along the north bank of the Susquehanna River and along
Abraham Creek. The existing project was authorized by the Flood
270          REPORT OF CHIEF OF ENGINEERS,                                   U. S. ARMY,            1944

Control Act approved June 22, 1936. (See H. Doc. No. 702, 77th
Cong., 2d sess.) The estimated construction cost is $529,800; the cost
of lands and damages is $42,300.
   Local cooperation.-See page 7 for requirements. The Common-
wealth of Pennsylvania has established drainage district No. 23, to
cover the drainage area of the North Branch of the Susquehanna
River in the boroughs of Forty Fort, Swoyersville, Wyoming, and
West Wyoming, County of Luzerne. Assurances for local coopera-
tion have been furnished by Luzerne County and Forty Fort Borough.
   Operationsand results during fiscal year.-Surveys and engineering
studies were started by hired labor. The cost of this work was $11.97
for new work. No expenditures were incurred.
   Condition at end of fiscal year.-Preparation of plans was started.
Construction has not been initiated. The cost was $11.97 for new work.
No expenditures have been incurred to date.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, in the amount of $20,000, will be applied as follows:
Accounts payable, June 30, 1944-------------------------------_                                             $11.97
New work: Engineering studies and design of levees, pumping sta-
tion, and diversion channel on Abraham Creek and Susquehanna
River; partial completion; period July 1944 to December 1944:
                       ------------------------------------
    Design (hired labor)_                                                                              19, 988. 03

          Total      ---------------------------------------------                                     20,000.00
  Additional funds in the amount of $60,000 can be profitably expended
during the fiscal year 1946 for completion of design, plans, and
specifications.
                                              Cost and financial summary
Cost of new work to June 30, 1944----------- -------------------                                            $11. 97
Cost of maintenance to June 30, 1944-
      Total cost of permanent work to June 30, 1944-------------                                             11. 97
Minus accounts payable June 30, 1944--------------------------                                               11. 97

Net total expenditures--
Unexpended balance June 30, 1944----------------------------                                           20, 000. 00
          Total amount appropriated to June 30, 1944-- ------------                                    20, 000. 00


   Fiscal year ending June 30                   1940           1941           1942           1943           1944

Cost of new work---                    ----
                                       .....    ---------------------------------- - -------------- ------.... $11.97
Cost of maintenance------------..                      ---------------------------------------.--------------.
Total expended...........           ...----
Allotted---------------.-.--------------------------------------------------------20,000.00


Amount allotted from War Department Civil Appropriation Act
  approved June 11, 1938 ----------------------------------  $20, 000.00
Balance unexpended June 30, 1944---------------------------- 20, 000. 00
Amount (estimated) required to be appropriated for completion of
existing project 1 ---------------------------------------                          509,800. 00
Amount that can be profitably
                            1-         expended in        - fiscal
                                                                -  year ending -June
30, 1946, for new work           _      _                                   _            A60,
                                                                                          000. 00
I Exclusive of available funds.
                         FLOOD CONTROL-SYRACUSE,                                  N.     Y., DISTRICT                          271
    17. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTIN-
                 GENCIES FOR FLOOD CONTROL

   The cost of work during the fiscal year amounted to $18,640.34.
The expenditures were $8,142.64. The balance unexpended on June
30, 1944, amounting to $45,857.36, plus the sum of $5,000 allotted in
July 1944, a total of $50,857.36, will be applied as needed during the
fiscal year 1945 to payment of expenses to be incurred under this
heading.                Cost and financial summary

Cost of new work to June 30, 1944________                                                      __          .-     -.
Cost of maintenance to June 30, 1944_ -------                                                       ___-$298,               891. 72

      Total cost of permanent work to June 30, 1944                                        ------------                298, 891. 72
Minus accounts payable June 30, 1944------------------------                                                            10, 497. 70
      Net total expenditures_ ------------------------                                                                 288, 394. 02
Unexpended balance June 30, 1944_ -----------------------                                                               45, 857. 36
            Total amount appropriated to June 30, 1944--------------                                                   334, 251. 38

    Fiscal year ending June 30                     1940           1941                  1942               1943             1944


Cost of new work----------------------------------------------------
Cost of maintenance------------$83, 878.92                   $63,178. 30 --                                                $18,640.34
Total expended._
            -----------------                     98, 528. 71    64, 829. 74           -$591.86     --------------          8,142.64
Allotted.................----------------------   92, 640.00     45,627. 90          -7, 866. 52 --------------             54, 000.00

Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940_ ----------------               __--------                                                    $54, 000.00
Gross amount expended_ -_____-------.-------------------8,                                                                  142. 64

      llance unexpended June 30, 1944----------------------                                                             45, 857. 36
Outstanding liabilities June 30, 1944-- ------------------------                                                             74. 71

     Balance available June 30, 1944_ -----------      _-------45,                                                          782. 65
Amount allotted in July 1944----------------------------                                                                 5, 000. 00

            Amount available during fiscal year 1945                           -----------------                        50, 782. 65

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1_ ____         -_____--__   _______                                                         10, 000. 00
    Exclusive of available funds.

18. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED
                                                                 For last          Cost and expenditures to
                                                                full report        June 30, 1944-                        Estimated
                       Name of project                          see Annual _amount                                              re-
                                                                  Report
                                                                       2                                                 quired to
                                                                  for--           New work             Maintenance       complete

Milton, Pa. -----                              1937------------------------                                               - $26-3,900
Montgomery, Pa.l..---------------------------1937      ----------------------------                                          139, 100
Muncy, Pa. -- _-1937                                   -----------------------------                                         360,800
Jersey Shore, Pa. ----------------------------                     1937 ----------------------------                         395, 900
Lock Haven, Pa.1_ _------------
Blloomsburg, Pa.1'     ----------------------------
                                                          - r                 _2,
                                                                   1937 --------
                                                                   1937     ----------------------------
                                                                                                                             860, 000
                                                                                                                             131,300
                             - - .....
West P ittston , P a .1__.....       - - -..... ....               1937 ---- ---------- --------------          100, 000
Nanticoke, Pa.1-.....- -_-          ----                           1937    .....        -   -------             381, 700
Snagging and clearing -------------------------                    1942 -------------- $280, 251.38 ...........

   I No funds have been allotted and no work has been done on these projects.
  2Prior  to 1942 the projects were reported by the Baltimore district.
272        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                          1944

Status of all investigations for flood control called for by flood-control acts and com-
                                     mittee resolutions

                                                           Date trans-Recommen-
          Locality              Authorization act           mitted to     Document No.            Redtommen-
                                                            Congressan

Catatonk Creek Basin in Commerce Commit- --                         -.--....
the vicinity of Candor,   tee resolution, June
N. Y. (tributary of the   20, 1944.
Susquehanna River.
Lackawanna River, Pa ....-Commerce Commit--
                               tee resolution, July
                                                                --             -       --..


                              8, 1942.
Mohawk River, N. Y- ..... Flood Control Act, .-----                  -----------------------------------
                              Aug. 11,1939.
Newton Creek, N. Y.__-_ . Flood Control Com-_ ... .. .. ... . ...............                     ........
                              mittee resolution,
                              May 13, 1943.
Owego Creek, in the vicinity Commerce Commit-.
of Owego, N. Y. (tribu-      tee resolution, June ......................................
tary of the Susquehanna      20, 1944.
River).


   IMPROVEMENT OF RIVERS AND HARBORS IN THE
           PHILADELPHIA, PA., DISTRICT

  This district comprises a portion of southeastern New York, eastern
Pennsylvania, western and southern New Jersey, northern and south-
eastern Delaware, and a small part of northeastern Maryland em-
braced in the drainage basin of the Delaware Bay and River system
and those basins tributary to the Atlantic Ocean from the head of
Barnegat Bay, N. J., to the south boundary of Delaware. It also
includes the Chesapeake and Delaware Canal and the approach channel
thereto in Chesapeake Bay and Elk River, Md.
  District engineer: Col. Albert H. Burton, Corps of Engin ers, to
January 7, 1944; Col. Clarence Renshaw, Corps of Engineer, since
that date.
  Division engineer: Brig. Gen. B. C. Dunn, Corps of Engineers, to
January 7, 1944; Col. Albert H. Burton, Corps of Engineers, since
that date.
                                                  IMPROVEMENTS

                     Navigation                                   Navigation-Continued
                                                   Page                                                 Page
1. Delaware    River   between                           10. Big Timber Creek, N. J _                   299
      Philadelphia,   Pa.,  and                           11. Mantua Creek, N. J      .                  301
        Trenton, N. J             ---               273   12. Cold Spring Inlet, N. J _                  302
2. Delaware River, Pa., N. J.,                           13. Absecon Inlet, N. J _- --                  304
      and Del., Philadelphia,
                                                    276
                                                          14.
                                                          15.
                                                              Barnegat Inlet, N. J
                                                              Examinations, surveys, and
                                                                                        -     -          306
        Pa., to the sea                  --
3. Dealware River at Camden,                                   contingencies (general) -                308
      N. J-                                         280   16. Other navigation projects for
4. Schuylkill River, Pa           --.              282         which no estimates are
5. Wilmington Harbor, Del -                        285          submitted         -                     309
6. Inland Waterway from Dela-                            17. Plant allotment                            310
      ware River to Chesapeake
     Bay, Del. and Md .
7. Mispillion River, Del
                                        --.
                                         -    -
                                                    288
                                                    293
                                                                  SFlood Control
8. Inland Waterway between                             18. Mount      Holly, Rancocas
      Rehoboth Bay and Dela-                                  Creek, N. J _        ___                   311
      ware Bay, Del                                 295 19. Preliminary     examinations,
9. Indian River Inlet and Bay,                               surveys, and contingencies
      Del_...                ..                     297       for flood control        _....             312
        RIVERS AND      HARBORS-PHILADELPHIA,     PA.,   DISTRICT   273
      1. DELAWARE RIVER BETWEEN PHILADELPHIA, PA., AND
                        TRENTON, N. J.

   Location.-This river has its source in southeastern New York,
flows in a general southerly direction, forming the boundary line be-
tween the States of New York and New Jersey on the east and Penn-
sylvania and Delaware on the west, and empties into Delaware Bay.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1218, 280, 294, 295,
and 296.)
   Previous projects.--Adopted by River and Harbor Acts of June 10,
1872; March 3, 1875; June 14, 1880; July 5, 1884; August 18, 1891;
March 2, 1907; June 25, 1910; July 25, 1912; June 5, 1920; and March
3, 1925. For further details see page 1778 of the Annual Report for
1915; page 311 of the Annual Report for 1921; page 220 of the An-
nual Report for 1934; and page 296, Annual Report for 1938.
   Emisting project.-This provides for a channel 28 feet deep and 300
feet wide from Allegheny Avenue, Philadelphia, to the Pennsylvania
Railroad bridge at Delair; thence 25 feet deep and 300 feet wide to
the upper end of the municipal marine terminal at Trenton, including
a turning basin 500 feet wide and 1,700 feet long at the terminal,
widening the 25-foot channel at bends above Delair, and the main-
tenance of a channel 12 feet deep and 200 feet wide from the upper
end of the 25-foot channel to the Pennsylvania Railroad bridge at
Trenton, dredged under a previous project. The project also pro-
vides for an auxiliary channel 20 feet deep and 200 feet wide east of
Burlington Island extending easterly from the main channel to the
upper end of the United States Pipe & Foundry Co.'s property at
East Burlington, with a turning basin 450 feet wide at the upper end,
and for the initial excavation only, of a cross channel 8 feet deep and
200 feet wide through the artificial island opposite Delanco, N. J.
The total length of the section included in the project is about 301/2
miles, excluding the auxiliary channel east of Burlington Island
which is 1.4 miles long, and the cross channel opposite Delanco. The
lower end is about 55 miles above the mouth of the river at Liston
Point and about 105 miles above the harbor of refuge at the mouth
of Delaware Bay. All depths refer to the plane of mean low water.
The mean tidal range at Trenton is 6.2 feet, an increase of 0.8 foot
since the completion of the 25-foot channel. Freshets, which occur
usually during February and March, attain a height of 9 to 20 feet
above mean low water in the vicinity of Trenton. Navigation is
occasionally suspended during a portion of the winter months on
account of ice.
   The estimate of cost for new work, revised in 1937, was $5,189,000,
exclusive of amounts expended on previous projects but including
$15,000 contributed funds. The latest (1935) approved estimate for
annual cost of maintenance is $131,000,




     616634-45-pt. 1, vol. 1   18
274            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                            1944

  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                          Documents


July     3,1930   A channel 28 feet deep, 300 feet wide between           Rivers and Harbors Committee Doe.
                     Allegheny Ave., Philadelphia, Pa., and Delair          No. 3, 71st Cong., 1st sess.'
               Bridge.
Aug. 30,19352 Deepening the channel to 25 feet from Delair                Rivers and Harbors Committee Doe.
                     Bridge to Trenton, N. J., and for maintenance          No. 11, 73d Cong., 1st sess.
                     of the 12-foot channel from the upper end of the
                     25-foot project to Pennsylvania R. R. bridge at
                   Ferry St., Trenton.
      Do-......   Auxiliary channel, 20 feet deep, east of Burlington     Rivers and Harbors Committee Doe.
                                                                                                               1
                     Island.                                                No. 66, 74th Cong., 1st sess.
Aug. 26, 1937     A cross channel 8 feet deep, opposite Delanco,          Rivers and Harbors Committee Doe.
                     N. J.                                                  No. 90, 74th Cong., 2d sess.


  1   Contains latest published maps.
  2   Also Public Works Administration, Sept. 6, 1933, and Emergency Relief Administration, May 28, 1935.

  Local cooperation.-Fully complied with.
   Terminal facilities.-There are 21 piers, wharves, and docks within
the improvement, exclusive of those within limits of city of Phila-
delphia. The facilities are considered adequate for existing com-
merce. (For further details see Port and Terminal Facilities at Ports
on the Delaware River, 1941, Corps of Engineers.)
   Operations and results during fiscal year.-Under maintenance by
hired labor, tide gages were operated and maintained at a cost of
$515.87; and surveys and channel examinations were made at a cost
of $1,963.45.
  The total cost of all work was $2,479.32, for maintenance. The
expenditures were $4,144.89.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1939.
  The latest examinations show minimum depths, at mean low water,
as follows:
                                                                                              Minimum depth

        Date                            Section                         Project                     Mid-
                                                                        depth          Left        channel         Right
                                                                                    outside        for half    outside
                                                                                    quarter        project     quarter
                                                                                                   width

                                                                         Feet          Feet         Feet           Feet
June 1943-........    Allegheny Ave. to Delair Bridge ------------           28            26. 5       27. 0          25.0
July 1943- .. , ..    Delair Bridge to Trenton Marine TerminaL.              25            15. 0       18. 0          20.6
     Do...-_ .....    Trenton Marine Terminal to Pennsylvania                12- .........              9.3.
                        R. R. bridge.
December 1941..                                               ..........
                      Channel east of Burlington Island----.-----20                                  117. 7
  1 At or near center line.
                 RIVERS AND HARBORS-PHILADELPHIA,                                                            PA., DISTRICT                  275

  The total costs and expenditures under the existing project were as
follows:
                                                                  Public Works           Emergency           Regular funds            Total
                                                                     funds               relief funds        Regular funds            Total

New work    _.. ...............-------              $2, 189, 955. 51    $2, 636, 456. 26                       $363, 405. 46        $5, 189, 817. 23
           ..........------------..............--..--------------- __........_____....__.._
Maintenance-----                                                                                                904, 214. 22            904, 214. 22
     Total- ............-                          ..-.-.-..          2, 189, 955. 51     2, 636, 456. 26      1,267, 619. 68        6, 094, 031.45
Expenditures- ......                 ...---         .-.-.-.-          2, 189, 955. 51     2, 636, 456. 26      1,267, 569. 65        6, 093, 981. 42

  In addition, $15,000 contributed funds were expended for new work.
  Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, amounting to $60,077.51, together with
$100,000 allotted from the act of June 26, 1944, as follows:
Accounts payable June 30, 1944_-----------------------------                                                                         -$50.      03
Maintenance:
         Dredging in 25-foot channel from Delair Bridge to Bordentown
           with a United States hopper dredge and rehandling with a
           pipe-line dredge (April and May 1945)---- --------------                                                                 61, 027. 48
         Dredging in 25-foot channel from Bordentown to the Trenton
           Marine Terminal by contract (March to May 1945)........                                                                  99, 000. 00
                 Total_ -------------------------------------------                                                                160, 077. 51
   No maintenance is contemplated during the fiscal year 1946, as
it is believed that channel conditions will be adequate to meet the
needs of commerce.
                                                        Cost and financial summary
Cost of new work to June 30, 1944_                                                                          __          1 $7, 678, 990. 68
Cost of maintenance to June 30, 1944__---                                                          --       __ _           1, 456, 934. 68
      Total cost of permanent work to June 30, 1944
Minus accounts payable June 30, 1944----------------------50.
                                                                                                        ---------         1 9, 135, 925. 36
                                                                                                                                               03
     Net total expenditures__ _________---___      -___- 1 9, 135, 875. 33
Unexpended balance June 30, 1944_-----------------------       60, 077. 51
            Total amount appropriated to June 30, 1944-----------1                                                           9, 195, 952. 84

    Fiscal year ending June 30                                 1940               1941             1942               1943              1944

Cost of new work -       --.......
Cost of maintenance ---___-_-___
                                                        ----                   $16, 612. 19
                                               .           $9, 166.83          142, 920.89     $ 6, 525. 47         $2,807.71           $2, 479.32

        Total cost_.-.----...                 --.-.        9, 166.83           159, 533. 08        6, 525.47          2,807. 71          2, 479.32
Total expended..---------------...............          -94,     348. 95       142, 537. 67        6, 350.17          1, 933. 51         4,144. 89
Alloted_.---.----....-..-.-...                         -141, 973.34            148, 453.44        56, 300.00       -35,000.00        -109,500.00


Balance unexpended July 1, 1943- -------------.----.-----      $173, 722. 40
Deductions on account of revocation of allotment--------------109, 500. 00
      Net amount to be accounted for----------------------                                                                          64, 222. 40
Gross amount expended -----------------------------------                                                                            4, 144. 89
      Balance unexpended June 30, 1944- -------------------                                                                         60, 077. 51
Outstanding liabilities June 30, 1944_------------------.-----50.                                                                            03
     Balance available June 30, 1944_---.---.-.---------60,                                                                             027. 48
Amount allotted in July 1944-------------.----------                                                                               100, 000. 00
            Amount available during fiscal year 1945---------------160, 027. 48
  I In addition $15,000 contributed funds expended for new work.
276     REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,   1944

2. DELAWARE RIVER, PA., N. J., AND DEL., PHILADELPHIA, PA., TO
                           THE SEA

    Location.-See page 273, also United States Coast and Geodetic
Survey Charts Nos. 1218, 294, 295, and 280.
   Previous projects.-Adopted by River and Harbor Acts of July 4,
1836; March 3, 1873; March 3, 1875; June 18, 1878; March 3, 1879;
July 5, 1884; August 11, 1888; and March 3, 1899. For further de-
tails, see page 1779 of Annual Report for 1915 and page 299, Annual
Report for 1938.
   Existing project.-This provides for a channel 35 feet deep from
Allegheny Avenue, Philadelphia, Pa., to the Philadelphia-Camden
Bridge, thence 37 feet deep to the Philadelphia Navy Yard, thence 40
feet deep to deep water in Delaware Bay, 800 feet wide in the straight
reaches from the bridge to a point in Delaware Bay near Ship John
Light, thence 1,000 feet wide to deep water in Delaware Bay, with
1,200 feet width at Bulkhead Bar and 1,000 feet width at other bends
and in Philadelphia Harbor. The project includes the construction
of dikes and training works for the regulation and control of the
tidal flow and dredging to provide for an anchorage 35 feet deep and
about 6,400 feet long at Port Richmond; for an anchorage area 30
feet deep and about 3,500 feet long at Gloucester, N. J.; for an anchor-
age 35 feet deep and about 7,300 feet long in the vicinity of Mantua
Creek; and for an anchorage 35 feet deep, 1,200 feet wide, and aver-
aging 5,700 feet long at Marcus Hook, Pa.; for straightening the
channel and extending the 1,000-foot width from Philadelphia
Harbor to Horseshoe Bend; and for the maintenance of any areas
dredged by local interests to a depth of 35 feet between the channel
and a line 100 feet channelward of the pierhead line between Point
House Wharf and the Philadelphia Navy Yard, when in the opinion
of the Chief of Engineers such areas are so located as to be of benefit
to general navigation. The total length of the section included in
the project is about 96.5 miles. All depths refer to the plane of mean
low water.
   The mean tidal range at various points on the river and bay is
as follows: Philadelphia, Pa., 5.5 feet; Chester, Pa., 5.4 feet; New
Castle, Del., 5.3 feet; Liston Point, Del., 5.6 feet; and Lewes, Del.,
4.1 feet. Under the influence of heavy and long-continued winds the
extreme tidal range is about 14 feet. The normal maximum velocity
of tidal current in the dredged channel varies between 2 and 3Y2
miles per hour. Storm tides may increase the maximum to as much
as 4/2 miles per hour.
   The estimate of cost for new work, revised in 1944, is $27,600,000,
exclusive of amounts expended on previous projects. The latest
(1938) approved estimate for annual cost of maintenance is
$1,700,000.
              RIVERS      AND HARBORS-PHILADELPHIA,                            PA., DISTRICT              277

  The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                   Documents


June 25,1910      Channel 35 feet deep from Allegheny Ave., Phila-     H. Doc. No. 733, 61st Cong., 2d sess.
                    delphia, Pa., to Delaware Bay.
July     3,1930   For 35-foot anchorages at Port Richmond and          H. Doc. No. 304, 71st Cong., 2d sess.s
                   Mantua Creek, a 30-foot anchorage at Glou-
                   cester, N. J., and extending the 1,000-loot chan-
                   nel width in Philadelphia Harbor to Horse-
                   shoe Bend.
Aug. 30,19352     For a 35-foot anchorage at Marcus Hook, Pa ... Rivers and Harbors Committee Doe.
                                                                         No. 5, 73d Cong., 1st sess.
                                                                                                             t
June 20,1938      For channel 37 feet deep from Philadelphia-Cam-      S. Doc. No. 159, 75th Cong., 3d sess.
                    den Bridge to the navy yard, thence 40 feet
                    deep to deep water in Delaware Bay.


  1 Contain latest published maps.
  2 Also Public Works Administration, Sept. 6, 1933.


   Recommended modifications of project.-Underdate of January 11,
1940, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for a depth of 37 feet in the channel from
Allegheny Avenue to the Philadelphia-Camden Bridge and in Port
Richmond Anchorage, at an estimated cost of $1,036,000 for new work
and $25,000 annually for maintenance in addition to that now author-
ized (H. Doc. No. 580, 76th Cong., 3d sess.).
   Under date of June 4, 1941, the Chief of Engineers recommended
further modification of the existing project so as to provide for an
anchorage area at Mantua Creek 37 feet deep, 1,400 feet wide and hav-
ing a mean length of 11,600 feet, and for an anchorage area at Marcus
Hook, of the same depth and width and with mean length of 10,500
feet, both with suitable flared approaches, at an estimated first cost
for dredging of $3,380,000, with $75,000 annually for maintenance in
addition to the amount now required (H. Doc. No. 340, 77th Cong.,
1st sess.).
   Local cooperation.-The River and Harbor Act of June 20, 1938,
imposes the condition that the cities of Philadelphia and Camden shall
agree to dredge not less than 110,000 cubic yards annually in maintain-
ing the channel and anchorages in Philadelphia Harbor between Alle-
gheny Avenue and the mouth of Schuylkill River. This condition
will become effective after completion of initial dredging of the 40-
and 37-foot channels.
   Terminal facilities.-There are 291 wharves on the river between
Allegheny Avenue, Philadelphia, and the sea, 235 located on the water-
front of Philadelphia and Camden, and 56 below Philadelphia.
Twelve are owned by the United States, 3 by the State of New Jersey,
33 by municipalities, 75 by railroad companies, and 168 by private
interests. The public and railroad piers are open to public use, some
free and others on payment of charges. Most of the piers which are
equipped to handle general cargo have direct rail connections with
three railroad systems operating in the area. The facilities are con-
sidered adequate for existing commerce. (For further details see Port
278     REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,    1944

and Terminal Facilities at Ports on the Delaware River 1941, Corps
of Engineers.)
   Operations and results during fiscal year-New work.-Removing
ledge rock to 41 feet below mean low water in the west half of
the channel on Marcus Hook, Chester, Eddystone, and Tinicum ranges
by contract, in progress at the end of the previous fiscal year, was
continued. There were removed 249,555 cubic yards of material which
included 180,175 cubic yards of ledge rock. The cost was $1,365,376.91.
The work was about 90 percent completed at the end of the fiscal
year.
   Maintenanee-Contract.-The construction of a 5,200-foot train-
ing dike on the east side of the channel near Pennsville, N. J., by con-
tract, in progress at the end of the previous fiscal year was completed.
The cost was $5,721.54. Repairing Pennsville Dike by contract consist-
ing of placing riprap stone on the river arm of the dike commenced
May 18, 1944, was 92 percent completed at the end of the fiscal year.
A total of 2,240.55 tons of stone was placed. The cost was $14,886.80.
   Maintenance-Hired labor.-Dredging in Mantua Creek Anchor-
age, and in the 35- and 40-foot channels where required, was in progress
throughout the year. Plant operating on this work included the
U. S. hopper dredges Clatsop, Delaware, Manhattan, New Orleans,
Raritan,and Rossell. There were removed 14,420,095 cubic yards, bin
measurement, of material from the channel and 788,352 cubic yards
from the anchorage, a total of 15,208,447 cubic yards. The cost, in-
cluding rehandling by pipe-line dredges, was $2,668,482.47. In addi-
tion 234,800 cubic yards, place measurement, of material was removed
from the channel by the U. S. pipe-line dredge Gulfport at a cost of
$53,573.83.
   Other costs were: Stabilizing Pennsville Dike with sand and gravel
fill by the U. S. pipe-line dredge Huston, $87,515.03; removing 500 feet
of pile and timber crib in Pennsville Dike, $9,002.08; constructing
foundations for two light bases on the ends of Pennsville Dike, $7,-
269.49; constructing protective pile dolphins at Pennsville Dike,
$13,657.93; sweeping and removing boulders by U. S. derrickboat
Babcock, $32,824.05; operating tide gages, $619.77; surveys and chan-
nel examination, $44,135.21; and work on model studies of shoaling
in the channel on New Castle, Finns Point, and Liston ranges by the
United States Waterways Experiment Station, Vicksburg, Miss.,
$13,125.20; a total of $208,148.76.
    The total costs for all work were $1,365,376.91 for new work, and
$2,950,813.40 for maintenance, a total of $4,316,190.31.        The ex-
penditures were $4,202,124.67.
   Condition at end of fiscal year.-The existing project was about 95
percent completed. The 40-foot channel from the Philadelphia Navy
Yard to the sea, except ledge areas on the west half of Marcus Hook,
Chester, and Eddystone ranges, has been completed. The work re-
maining to be done is the completion of the removal of the ledge rock
on Marcus Hook, Chester and Eddystone ranges to a depth of 41 feet
and the dredging of the channel from the Philadelphia Navy Yard
to the Philadelphia-Camden Bridge to a depth of 37 feet.
              RIVERS AND HARBORS-PHILADELPHIA,                                       PA.,     DISTRICT               279
  The latest examinations show depths, at mean low water, available
to navigation as follows:

                                                                                          Minimum depth

     Date                               Section                    Project
                                                                   depth         Left        Left     Right         Right
                                                                                outside     inside   inside        outside
                                                                                quarter     quarter quarter        quarter

                                                                     Feet        Feet        Feet        Feet        Feet
January 1944.. Allegheny Ave. to Philadelphia-Camden                    35        11.0        30.0        28.5         23.2
                Bridge.
June 1944..... Philadelphia-Camden Bridge to navy                        37        25.0       32. 5        34.9        32.9
                yard.
                                        _----__--
    Do ..... .Navy yard to the sea- ...-..                               40        26.5       36.1         37.4        28.9



  The costs and expenditures under the existing project were as
follows:
                                                            Puhlic Works
                                                              Public Worknds      Regular funds              Total


New work---..     _...     -    -----   ____-$813,045.79                                  382.
                                                                                   $25,544,  68               357,428.
                                                                                                           $26,      47
Maintenance- .---.-----------........
                   ---                               . ... ............ 40,530, 071.86                      40, 530, 071.86
       Total_ __-------------------------                        813, 045. 79       66, 074, 454. 54        66, 887, 500.33
Expenditures--- ____.----------------------813,                      045. 79        65, 868, 971.91         66, 482, 017. 70



   Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, amounting to $504,192.64, together with
$2,300,000 allotted during July 1944, as follows:
Accounts payable June 30, 1944_ ---------------------------- $205, 482. 63
New work: Removing ledge rock on west half of Marcus Hook,
  Chester, and Eddystone ranges under contract in force to be
  completed December 1944___---          ------------                                                     533, 350. 00
Maintenance:
    Placing riprap stone on the river arm of Penns-
      ville Dike by contract in force to be com-
      pleted July 1944-------------------------           $1, 233. 00
    Dredging with 3 United States hopper dredges
      and relhandling with pipe-line dredges as re-
      quired throughout the year--------------        2, 064, 127. 01

             Total maintenance--                   ----     ___----------2,                               065, 360. 01

             Total for all work-----------                                         _-     .----         2, 804, 192. 64
  The sum of $4,343,700 can be profitably expended during the fiscal
year 1946 as follows:
New work: Dredging 37-foo.t channel from Philadelphia Navy Yard
  to the Philadelphia-Camden Bridge by contract ----------------                                              743, 700
Maintenance:
    Dredging in 35-, 37-, and 40-foot channels with 5
       United States hopper dredges and rehandling with
       3 pipe-line dredges as required throughout the year $3, 390, 000
     Maintenance dredging in Philadelphia Harbor and
       Port Richmond Anchorage, by contract                    210, 000
                                                       .---------
              Total maintenance_ ___---------------------                                    __----3,             600, 000
              Total for all work- -------------------------------                                           4, 343, 700
280           REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,                    1944

   The proposed nzew work will complete the project, except for
scattered areas of hard bottom on Chester and Marcus Hook ranges,
between the areas of ledge rock now being removed under an existing
contract, where the project depth of 40 feet has not yet been attained.
                                    Cost and financial summary
Cost of new work to June 30, 1944_ _                                          ----------                                $39, 333, 486. 08
Cost of maintenance to June 30, 1944----_                                   -----------------                                41, 555, 480. 88

      Total cost of permanent work to June 30, 1944                                                   ---                    80, 888, 966. 96
Minus accounts payable June 30, 1944------_                                                                                      205, 482. 63

      Net total expenditures       _80,                                                                                          683, 484. 33
Unexpended balance June 30, 1944 _      -_504,                                                                                        192. 64

         Total amount appropriated to June 30, 1944--                                                                       81, 187, 676. 97

   Fiscal year ending June 30                    1940                  1941                     1942                 1943              1944


Cost of new work               __ _ _     $245, 498. 84 $2, 312, 643. 26 $3, 891, 983. 98                       $707, 651. 49     $1, 365, 376. 91
Cost of maintenance ._                   1, 344, 955. 93 1, 230, 649. 43 2, 183, 383. 69                       4, 263, 070. 43     2, 950, 813. 40

      Total cost. -                      1, 590, 454. 77         3, 543, 292. 69           6, 075, 367. 67     4, 970, 721.92      4, 316, 190. 31

Total expended    -------     - -             -38, 459. 52       3, 299, 383. 44           6, 280, 654. 48     4, 970, 064.15      4, 202, 124. 67

Allotted_--   -       - - -     .   .         354, 255. 00       4, 973, 950. 00           7, 226, 000. 00     5, 415, 458. 84



Balance unexpended July 1, 1943_                          _-- $4, 706, 317. 31
Gross amount expended4-----------------------------------       , 202, 124. 67
      Balance unexpended June 30, 1944                                                                               _504,             192. 64
Outstanding liabilities, June 30, 1944-_ __                                                    $205, 482. 63
Amount covered by uncompleted contracts ...                                                     540, 159. 43
                                                                                                                                 745, 642. 06
     Balance available June 30, 1944---------------------                                                                    -241, 449. 42
Amount allotted in July 1944_---------------------------------                                                               2, 300, 000. 00
         Amount available during fiscal year 1945---------- ---                                                              2, 058, 550. 58
Amount (estimated) required to be appropriated for completion
  of existing project 1----------------                                                                                          743; 700. 00

Amount that can be profiably expended in fiscal year ending
June 30, 1946:
      For new work 1_ _                  --                  -          -             -           -          -743,                    700. 00
      For maintenance           1-----------------------------------                                                         3, 600, 000. 00
        Total '_-_-_-_--                                                                      ---_                           4, 343, 700. 00
1 Exclusive of available funds.


                         3. DELAWARE RIVER AT CAMDEN, N. J.

   Location.-Camden, N. J., is located on the east bank of the Dela-
ware River, directly opposite the city of Philadelphia, Pa. It is
about 55 miles above the mouth of the river and about 101 miles above
the harbor of refuge at the mouth of Delaware Bay. (See U. S. Coast
and Geodetic Survey Charts Nos. 295 and 280.)
  Previous projects.-Adopted by River and Harbor Act of June 25,
1910. No work was done on this project. For further details see
page 321, Annual Report for 1932.
              RIVERS AND HARBORS-PHILADELPHIA,                             PA., DISTRICT               281

  Existing project.-This provides for dredging in front of Camden
to a depth of 18 feet at mean low water from that depth north of
Cooper Point to Berkley Street and 30 feet from the latter point to
Newton Creek, these depths to extend from the 35-foot channel in the
Delaware River to a line paTallel with and 50 feet distant from the
established pierhead line. The distance from Cooper Point to Berkley
Street is about 1.5 miles, and from Berkeley Street to Newton Creek is
about 2.5 miles. The lower end of the project is about 49 miles above
the mouth of the river at Liston Point and about 99 miles above the
harbor of refuge at the mouth of Delaware Bay.
  The mean tidal range is 5.5 feet and the extreme tidal range under
the influence of prolonged heavy winds is about 14 feet.
  The estimate of cost for new work, revised in 1930, was $495,300
including $15,000 contributed funds. The latest (1930) estimate for
annual cost of maintenance is $25,000.
  The existing project was authorized by the following river and
harbor acts:


       Acts                      Work authorized                                 Documents


                                                                                                              1
Mar. 2,1919       For a depth of 30 feet from Newton Creek to       H. Doc. No. 1120, 63d Cong., 2d sess.
                   Kaighn Point, thence 18 feet to Cooper Point.
July     3,1930   Extending the 30-foot depth upstream to Berkley   H. Doc. No. 111, 70th Cong., 1st sess.'
                   St. Terminal.


1 Contain latest published maps.


    Recommended modifications of project.-Under date of June 3,
1941, the Chief of Engineers recommended modification of the exist-
ming project so as to provide for a depth of 37 feet between the deep
ship channel and a line 50 feet channelward from the established
pierhead line in front of the Camden Marine Terminals, extending
about 2,900 feet along the inshore side and about 5,100 feet along the
ship channel, at an estimated first cost of $373,000, with no increase
iin) the estimated annual cost for maintenance, subject to certain condi-
tions of local cooperation (H. Doc. No. 353, 77th Cong., 1st sess.).
    Local cooperation.-Fullycomplied with.
    Terminal facilities.-There are 60 piers, wharves, and docks along
the Delaware River water front at Camden, including 3 oil terminals
on Pettys Island. Two are modern terminals designed for overseas
and domestic general cargo, and are open to all carriers on equal terms.
They are the Beckett Street Terminal, owned by the South Jersey Port
District, and the Spruce Street Municipal Pier, owned by the city of
Camden. The piers have direct railroad connections. The facilities
are considered adequate for existing commerce. (For further details
see Port and Terminal Facilities at Ports on the Delaware River 1941,
Corps of Engineers.)
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was com-
pleted in 1931. The latest examination (June 1941) indicates that
project depths are well maintained except along the eastern border
of the project.
282           REPORT OF CHIEF OF ENGINEERS, U.                                               S. ARMY,          1944

   The costs and expenditures under the existing project, excluding
$15,000 contributed funds expended for new work, were $462,905.66
for new work and $68,715.77 for maintenance, a total of $531,621.43.
   Proposed operations.-It is proposed to apply the funds allotted
from the act of June 26, 1944, in July* 1944, amounting to $25,000,
to maintenance dredging in front of the Camden Marine Terminal by
contract (March and April 1945).
   No maintenance is contemplated during the fiscal year 1946, as it
is believed that channel conditions will be adequate to meet the needs
of commerce.
                                              Cost and financial summary
Cost of new work to June 30, 1944___--------                                                                   1$462, 905.66
Cost of maintenance to June 30, 1944                                                                                 68, 715. 77
       Total cost of permanent work to June 30, 1944                                         -----------           531, 621. 43
Net total expenditures_--------------_                                                                           1 531, 621.43
Total amount appropriated to June 30, 1944                                                                       1 531, 621. 43

    Fiscal year ending June 30                   1940             1941                  1942            1943                1944

Cost of new work___            ...-                     --.-                   -   -     -     -..                      - _- -     .
Cost of maintenance ........-------------..       $350. 21         $329.40T3-o5
Total expended---....            -......      -. -- 347. 00          332. 61
Allotted.........................               50, 000. 00    -22, 750. 00            17, 00. 00    -66, 070. 39 ...........

Amount allotted in July 1944-                                                                                       $25, 000. 00
Amount available during fiscal year 1945 ----------------------                                                       25, 000. 00
  1In addition $15,000 contributed funds expended for new work.

                                           4. SCHUYLKILL RIVER, PA.

   Location.-This river has its source in Schuylkill County, Pa.,
flows in a general southeasterly direction, and empties into the Dela-
ware River at Philadelphia, Pa. (See U. S. Coast and Geodetic
Survey Charts Nos. 295 and 280.)
   Previous projects.-Adopted by River and Harbor Act of July 11,
1870, and modified April 26, 1892. For further details see page 325,
Annual Report for 1932.
   Existing project.-This provides for a channel 30 feet deep and 400
feet wide in Delaware River to the mouth and within the river to
Twenty-ninth Street, 3/4 mile above the mouth; thence the same depth
and 300 feet wide to Passyunk Avenue Bridge, 31/2 miles above the
mouth; thence 26 feet deep and                                 200
                                      feet wide to Gibsons Point, 41/2
miles above the mouth; and thence 22 feet deep and 200 feet wide to
University Avenue Bridge, 6 miles above the mouth, including widen-
ing at bends. The total length of the section included in the project
is about 61/2 miles. All depths refer to thetplane of mean low water.
The mean tidal range at the mouth is 5.4 feet and at Grays Ferry
Bridge about 1/2 mile below University Avenue Bridge, 5.8 feet. The
extreme tidal range, due to freshets and prolonged heavy winds is
about 14 feet.
              RIVERS AND HARBORS-PHILADELPHIA,                                  PA., DISTRICT              283

   The estimated cost for new work, revised in 1930, is $1r,490,000,
exclusive of amounts expended on previous projects. The latest
 (1930) approved estimate for annual cost of maintenance is $200,000,
in addition to $1,300,000 required to restore the project depths be-
tween the mouth and Passyunk Avenue Bridge.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                   Documents


Aug.     8,1917   For depths of 35 feet from mouth to Girard Point,      H. Doe. No. 1270, 64th Cong., 1st sess.
                    thence 30 feet, 26 feet, and 22 feet to University
                    Ave. Bridge, Philadelphia.
July    3,1930    For a depth of 30 feet instead of 35 feet between      Rivers and Harbors Committee Doc.
                    the mouth and Girard Point, and for the con-           No. 40, 71st Cong., 2d sess.    (Con.
                    ditional resotoration and maintenance of the           tains latest published maps.)
                    channel below Passyunk Ave. by the United
                    States.



  Local cooperation.-The existing project, as originally adopted, im-
posed the condition that the city of Philadelphia or the State of
Pennsylvania should maintain the improved channel until the com-
pletion of the city's projected sewage-treatment works. The River
and Harbor Act of July 3, 1930, provides for restoration and main-
tenance of the project from the mouth to Passyunk Avenue Bridge by
the United States in advance of the completion of the municipal
sewage-treatment works, provided the city of Philadelphia shall give
assurances satisfactory to the Secretary of War and the Chief of
Engineers that it will dredge not less than 300,000 cubic yards an-
nually in maintaining the channel above Passyunk Avenue Bridge
and in cooperation with the United States in channel maintenance
below Passyunk Avenue. On December 23, 1930, the Secretary of
War approved an ordinance passed by the City Council of Philadel-
phia, and letter from the mayor giving assurance that.the required
annual dredging will be done, as satisfactory compliance with the
project requirements for local cooperation.
  Terminal facilities.-There are 39 wharves located within the limits
of the improvement. These terminals are considered adequate for
existing commerce.. (For further details see Port and Terminal
facilities at Ports on the Delaware River 1941, Corps of Engineers.)
  Operations and results during fiscal year.-Maintenance dredging
in the channel between Delaware River and Passyunk Avenue Bridge
by the U. S. hopper dredges Clatsop and Rossell was in progress at
intervals throughout the fiscal year. There were removed 1,767,747
cubic yards, bin measurement, of material. The cost was $534,426.54.
Surveys and channel examinations were made at a cost of $6,036.03.
The total cost was $540,462.57 for maintenance. The expenditures
were $548,264.39.
  In compliance with local cooperation requirements, the city of
Philadelphia dredged a total of 385,770 cubic yards of material from
the channel above Passyunk Avenue Bridge,
284            REPORT OF CHIEF OF ENGINEERS,                                           U. S. ARMY,                         1944

  Condition at end of fiscal year.-The existing project was about 98
percent completed. The work remaining to be done is the removal
of a few rock shoals in the channel above Passyunk Avenue Bridge.
This work will be deferred until the overlying mud shoals are re-
moved by the city of Philadelphia as required under the project.
  The latest examinations show controlling depths, at mean low
water, available to navigation as follows:

                                                                                                               Controlling depth

       Date                                  SectionProject                                                                 Mid-
                                                     Section                           depth               Left            channel       Right
                                                                                                          outside          for half     outside
                                                                                                          quarter          project      quarter
                                                                                                                           width

                                                                                           Feet            Feet             Feet          Feet
June 1944- .. _..     Delaware River to 29th St_ _ ----------------                           30             14. 3           25. 3          19.8
   Do      ....       29th St. to Passyunk Ave__------.-------.--                              30             8. 0            17. 2         16.3
February 1944         Passyunk Ave. to Gibson Point        --------------                      26            15. 6            10. 5           6.0
   Do     ....        Gibson Point to University Ave ... ______22  ....                                       7.1              7.7            2.0



  The costs under the existing project were $1,456,001.01 for new work
and $3,727,817.54 for maintenance, a total of $5,183,818.55. The ex-
penditures were $5,183,052.99.
  Proposed operations.-Itis proposed to apply the funds unexpended
on June 30, 1944, and accounts receivable, amounting to $4,296.13, to-
gether with $160,000 allotted from the act of June 26, 1944, in July
1944, to maintenance dredging from Delaware River to Passyunk
Avenue Bridge with United States hopper and pipe-line dredges, as
required during the year.
  The sum of 250,000 can be profitably expended during the fiscal
year 1946 for channel maintenance dredging from Delaware River
to Passyunk Avenue Bridge, with Government plant.
                                             Cost and financial summary
Cost of new work to June 30, 1944_ ________                                        -               -$1,                        981, 001. 01
Cost of maintenance to June 30, 1944_-----__                                                                                3, 727, 817. 54
       Total cost of permanent work to June 30, 1944 ----                                                                   5, 708, 818. 55
Plus accounts receivable June 30, 1944 _      -__                                                                                2, 234. 44
            Gross total costs to June 30, 1944----------------                                                              5, 711, 052. 99

Net total expenditures _________-- -                        -            -             -            -5,                        711, 052. 99
Unexpended balance June 30, 1944_-                                     _                   -__                 --                2, 061. C9

            Total amount appropriated to June 30, 1944                                                    --                5, 713, 114. 68


    Fiscal year ending June 30                 1940               1941                      1942                    1943                1944

C ost of new work -- . . . . . . . . . . . . . . . . . . . -.
                                                            . . . . . . . . . . . ..-    .
Cost of maintenance- ._......       $209, 285. 65  $171,286. 49     $96, 375. 78  $269, 679.03                                        $540, 462. 57
Total expended ...........----------------   195,180. 96        187, 625. 73   .           95, 065. 78         264, 812. 95            548, 264.39

Allotted_-------             _--------214,       000.00         198, 614. 68           167, 000. 00            190, 000.00             371,000.00
   *'     RIVERS AND HARBORS-PHILADELPHIA,                          PA.) DISTRICT     285
Balance unexpended July 1, 1943 _$179,326.                                               08
Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942-     $100, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved June 2, 1943        --           220, 000. 00
Amount allotted from. War Department Civil Ap-
propriation Act approved June 24, 1940 --------             51, 000. 00
                                                                              371, 000. 00
       Amount to be accounted for--------------------------                   550, 326. 08
Gross amount expended_-____ - --------------                                  548, 264. 39

      Balance unexpended June 30, 1944--------------------                       2, 061. 69
Accounts receivable June 30, 1944_                    -_
                                                 -------                         2,234. 44
        Unobligated balance available June 30, 1944        ------------          4, 296. 13
Amount allotted in July 1944    - -     _--------160,                               000. 00

        Amount available during fiscal year 1945        --------------         164, 296. 13
Amount (estimated) required to be appropriated for completion
of existing project 1 -34,                                                         000.00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance     1-    -        -       -____       -      250, 000. 00
1Exclusive of available funds.

                             5. WILMINGTON HARBOR, DEL.

   Location.-This harbor is formed by Christina River, which rises
in New Castle County, Del., flows northeasterly 16 miles, passing
through the city of Wilmington, Del., and empties into Delaware
River about 29 miles below Philadelphia, Pa. (See U. S. Coast and
Geodetic Survey Chart No. 294.)
   Previous projects.-Work was done on Christina River from 1836
to 1838. The original project was adopted by River and Harbor
Act of July 11, 1870, and modified by River and Harbor Acts of
March 3, 1881, and July 5, 1884. For further details see page 1785
of Annual Report for 1915 and page 308 of Annual Report for 1938.
   Existing project.-This provides for a channel 30 feet deep and
400 feet wide in Delaware River to the mouth of Christina River and
within the river to Lobdell Canal, 3/4 mile above the mouth; thence
21 feet deep and 250 feet wide to the mouth of Brandywine River,
1    miles above the mouth; thence the same depth and 200 feet
wide to the pulp works, 33/4 miles above the mouth; thence decreas-
ing to a depth of 10 feet in 750 feet to the Pennsylvania Railroad
bridge No. 4; and thence 7 feet deep and 100 feet wide to Newport,
9 miles above the mouth, including an inner basin 30 feet deep formed
by widening the channel to an average width of 600 feet and extend-
ing approximately 4,400 feet upstream from the mouth to Lobdell
Canal. It also provides for the removal of about 1,200 feet of the
outer end of a stone-filled, pile- and timber-crib jetty constructed
2,150 feet long on the north side of the entrance; for a steel-sheet
pile jetty 2,300 feet long, with 120=foot inshore wing, on the south
side of the entrance, and for a V-shaped stone-filled pile and timber
jetty at the mouth of Brandywine River, 430 feet long on the Brandy-
wine side and 260 feet long on the Christina side. The total length
of the section included in the project is about 91/2 miles. All depths
refer to the plane of mean low water. The mean tidal range at the
286           REPORT       OF CHIEF OF ENGINEERS,                         U.      S.   ARMY,       1944

mouth is 5.1 feet, and at Newport 3.9 feet. The extreme tidal range
due to prolonged heavy winds is about 13 feet.
  The estimate of cost for new work, revised in 1935 to include the
cost of the south entrance jetty, was $1,197,700, exclusive of amounts
expended on previous projects. The latest (1930). approved estimate
for annual cost of maintenance is $281,000, of which $152,000 is the
estimated cost for annual maintenance of the 30-foot channel.
  The existing project was authorized by the following river and
harbor acts:

       Acts                          Work authorized                                        Documents
                                --                                       -I.       -


Mar. 3,1899        1
Mar. 3, 18969 For depths of 21, 10, and 7feet, and for jetties-----            H. Doc. No. 66, 54th Cong., 1st sess.;
                                                                                Annual Report, 1896, p. 973; Annual
                                                                                Report. 1897, p. 1250.1
July 25,1912       Purchase or construction of a dredge and auxil-             H. Doc. No 359, 62d Cong., 2d sess.
                    iaries, including a wharf and depot, and for
                    maintenance of the project.
                   Entrance channel and basin with 25-foot depth               H. Doc. No. 114, 67th Cong., 1st sess.,
Sept. 22, 1922
                    and for construction by local interests of the               and Senate Committee Print, 68th
Mar. 3, 1925
                    new south jetty.                                             Cong., 1st sess.'
July     3, 1930   For 30-foot depth between Delaware River and                Rivers and Harbors Committee Doe.
                    the Lobdell Canal and modification or removal                No. 20, 71st Cong., 2d sess.'
                    of a portion of the north jetty.
Aug. 30,19352      Completion of the new south jetty by the United             Rivers and Harbors Committee Doe.
                     States; subject to the provision that the city of           No. 32, 73d Cong., 2d sess.
                     Wilmington shall reimburse the United States
                    for the cost, without interest, of any part of the
                    structure that may subsequently be occupied
                    and utilized for the city activities.    *
Oct. 17, 1940      Permit temporary occupancy by the city of Wil-              H. Doc. No. 658, 76th Cong., 3d sess.
                    mington of any part of the south jetty for city
                    activities under revocable license, provided the
                    occupied portion of the jetty is properly main-
                    tained without expense to the United States.


  I Contain latest published maps.
  2 Also May 28, 1935, under Emergency Relief Administration.


  Local cooperation.-Fully complied with.
   Terminal facilities.-A modern marine terminal is located just
inside the entrance to the harbor. This terminal is operated for the
city of Wilmington by a board of harbor commissioners, and is
open to all on equal terms. Railroad connection on the terminal
wharf provides for direct interchange of freight between car and
ship. There are 34 other wharves and landings within the Chris-
tina River which forms the harbor. The facilities are considered
adequate for existing commerce. (For further details see Port and
Terminal Facilities at Ports on the Delaware River 1941, Corps of
Engineers.)
   Operations and results during fiscal year.-Maintenance dredg-
ing in the channel between Delaware River and Lobdell Canal by the
U. S. hopper dredges Clatsop, Delaware, Hains, New Orleans, and
Raritan, and the pipe-line dredges Alabama and Huston was in prog-
ress at intervals during the year. There were removed 686,694 cubic
               RIVERS         AND HARBORS-PHILADELPHIA,                                      PA., DISTRICT                        287

yards, bin measurement, of material by the hopper dredges, and
824,957 cubic yards, place measurement, by the pipe-line dredges.
The cost was $206,289.77. Other costs were surveys and channel
examinations, $1,502.98, and work on a model study of the shoaling
problem in the harbor by the United States Waterways Experiment
Station, Vicksburg, Miss., $7.06. The cost of all work was $207,799.81
for maintenance. The expenditures were $217,399.60.
   Condition at end of fiscal year.-The existing project was about
99 percent completed. The work remaining to be done is the deepen-
ing of the inner basin to a depth of 30 feet. The latest examinations
showed controlling depths, at mean low water, as follows:

                                                                                                        Present depth


       Date
                                                                                Project                        Mid-
                                              Section                           depth          Left         channel           Right
                                                                                              outside       for half         outside
                                                                                              quarter          project       quarter
                                                                                                               width

                                                                                  Feet           Feet           Feet           Feet
May 1944       ..-        Delaware River to Lobdell Canal .......                    30            20.8           24. 4           21.8
October 1943 -...-- Lobdell Canal to Brandywine River --..                            21 -   -   ....               8. 9
    Do --------- Brandywine River to pulpworks       ~21                                         .-               1 7. 2-
June 1944 ...-..   Pulpworks to Pennsylvania R. R. bridge
                     No.4 - --                   -- -                                 10                          16. 6     - - --
    Do....--------.....   Pennsylvania R. R. bridge No. 4 to New-
                           port -----------------------------------                     7----------16.                41.

  1In 80 percent project width.

  The costs and expenditures under the existing project, excluding
$60,000 contributed funds expended for maintenance, were as follows:

                                                                EmergencysRe-
                                                                  lief funds          Regular funds                       Total


New work ------------------------------------                          $206,176. 75           $924, 356.12            $1, 130, 532.87
Maintenance ...................-----------------------------.------------------              4, 838, 587.04            4, 838, 587.04

     Total ------------------------------------                        206,176. 75           5, 762, 943.16              5, 969,119. 91
Expenditures ----------------------------------                        206,176. 75           5, 759, 249. 53             5, 965, 426. 28



  Proposed operations.--It is proposed to apply the funds unex-
pended on June 30, 1944, amounting to $45,667.64, together with
$130,000 alloted from the act of June 26, 1944, in July 1944, as follows:
Accounts payable June 30, 1944-------------------------------$3, 693. 63
Maintenance:
    Dredging from Delaware River to Lobdell Canal with a United
      States pipe-line dredge as required throughout the fiscal year_ 131, 974. 01
    Dredging from Lobdell Canal to the old pulp works with a
      United States hopper dredge, including rehandling with a pipe-
      line dredge as required throughout the fiscal year.---------_    40, 000. 00
                Total_ ------------------------------------------                                                  175, 667. 64
   The sum of $200,000 can be profitably expended during the fiscal
year 1946 for channel maintenance dredging from Delaware River
to the pulp works with Government plant.
   The completion of the project is not required by existing commerce.
288           REPORT OF CHIEF OF ENGINEERS,                                                     U. S. ARMY,                    1944

                                                             Cost and financial summary
Cost of new work to June 30, 1944__      -                                                  -             -$1,                      532, 654. 08
Cost of maintenance to June 30, 1944_----                                                             -          -__           1 4, 838, 587. 04
      Total cost of permanent work to June 30, 1944----------                                                                   6, 371, 241. 12
Minus accounts payable June 30, 1944---------------------_  --                                                                       3, 693. 63
      Net total expenditures ----------------------------     1 6, 367, 547. 49
Unexpended balance June 30, 1944-    -------           -__45,           667. 64

           Total amount appropriated to June 30, 1944-----------                                                           1 6, 413, 215. 13


     Fiscal year ending June 30                              1940           1941                  1942                 1943              1944

Cost of new work   - -$676.                                                         75 --     - - - --.           - --....       .....        ..
Cost of maintenance-----------                        $197, 714. 26       137, 857. 00      $155, 806. 77          $416, 023. 92       $207, 799. 81

      Total cost-----_ ----------                      197, 714. 26       138, 533. 75          155, 806. 77        416, 023. 92       207, 799. 81

Total expended ...---------------                   .196,114. 23          139, 775. 11          149, 722. 76        408, 861.88        217, 399. 60
Allotted   ................----------------------           77, 000. 00   180, 588. 38          140, 000. 00        411, 000. 00         85, 000. 00


Balance unexpended July 1, 1943-_                        '..                                                                     $178, 067. 24
Amount allotted from War Department Civil Appropriation Act
approved May 23, 1941 -----------------------------                                                                                85, 000. 00
       Amount to be accounted for ----------------------                                                                           263, 067. 24
Gross amount expended -------------------- $218, 454. 79
Less reimbursements collected----_---_ -------       1, 055. 19
                                                                                                                           -       217, 399. 60
      Balance unexpended June 30, 1944--------------------                                                                          45, 667. 64
Outstanding liabilities June 30, 1944-                                                                                               3, 693. 63
     Balance available June 30, 1944                   __                                                                           41, 974. 01
Amount allotted in July 1944 -------------------------------                                                                       130, 000. 00
           Amount available during fiscal year 1945                                      -----------                               171, 974. 01

Amount (estimated) required to be appropriated for completion
  of existing project                  2-----------------                                                                           67, 850. 00
Amount that can be profitably expended in fiscal year ending
                                                      _
June 30, 1946, for maintenance 2---      ---           _ --                                                                       200, 000. 00
1In addition $60,000 contributed funds expended for maintenance.
SExclusive of available funds.
6. INLAND WATERWAY FROM DELAWARE RIVER TO CHESAPEAKE
                   BAY, DEL. AND MD.

  Location.-This waterway begins at Reedy Point on Delaware
River, about 41 miles below Philadelphia, Pa., and passes through
the sea level Chesapeake & Delaware Canal, a distance of 14 miles,
to Back Creek, at Chesapeake City, Md. It then passes for 5 miles
down Back Creek, and thence 9 miles down Elk River to Chesapeake
Bay. A branch channel connects Delaware River at Delaware City,
Del., with the main channel at a point about 11/2 miles west of Reedy
Point. (See U. S. Coast and Geodetic Survey Charts Nos. 294, 1226,
570, and 572.)
  Previous projects.--The River and Harbor Act of August 8, 1917,
made appropriation for preliminary studies with a view to taking
over the Chesapeake & Delaware Canal. The River and Harbor Act
of March 2, 1919, provided for the purchase of the Chesapeake &
        RIVERS    AND HARBORS---PHILADELPHIA,     PA.,   DISTRICT   289

Delaware Canal. The River and Harbor Acts of January 21, 1927,
and July 3, 1930, provided for dredging in Back Creek, Md., and
the construction of bridges and roadways. For furthers details see
Annual Report for 1934, page 242, and Annual Report for 1938,
page 312.
    Existing project.-This provides for a sea-level channel to accom-
modate vessels drawing 25 feet and having a depth of 27 feet and a
width of 250 feet from Delaware River to Elk River and thence 400
feet wide down Elk River and Chesapeake Bay to deep water at or
near Pooles Island; alteration of existing bridges over the canal;
extension of the entrance jetties at Reedy Point; the enlargement
of the anchorage and mooring basin in Back Creek to afford an area
about 400 feet wide, 1,000 feet long, and 12 feet deep, including pro-
vision of sluice gates at the fixed highway bridge; dredging the
Delaware City Branch Channel to a depth bf 8 feet and a width
of 50 feet; deepening the existing basin to the same depth; revet-
ment of both banks east of Fifth Street Bridge; and construction
of bulkheads.
   The project also provides for the construction of a four-lane high-
level fixed highway bridge across the canal at or near St. Georges,
Del., of such type, design, and clearances for navigation as are ap-
proved by the Chief of Engineers.
   The total length of the section included in the project, excluding
the Delaware City Branch Channel, which is about 2 miles long, is
about 46 miles. All depths refer to the plane of mean low water
in Delaware River. The mean tidal range at the Delaware River
entrance is 5.2 feet and in Elk River at the mouth of Back Creek,
2.2 feet. The extreme tidal range is from 6.3 feet above mean high
water to 3.0 feet below mean low water.
   The estimate of cost for new work, revised in 1939, is $15,089,000.
The latest (1939) approved estimate of cost for annual maintenance
is $730,000, including $130,000 for operation and care of the
waterway.
   The existing project was adopted by the River and Harbor Act
of August 30, 1935 (H. Doc. No. 201, 72d Cong., 1st sess., and Rivers
and Harbors Committee Docs. Nos. 18 and 24, 73d Cong., 2d sess.).
   The act approved August 7, 1939 (Pub. No. 310, 76th Cong., 1st
sess.) authorized the construction of a four-lane high-level fixed high-
way bridge at or near St. Georges, Del.
   The latest published map of the canal is found in Rivers and Har-
bors Committee Document No. 24, Seventy-third Congress, second
session. Operation and care of the canal and appurtenant works
were included in the project July 1, 1935, under the provisions of the
Permanent Appropriations Repeal Act approved June 26, 1934.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-A freight station owned by the Baltimore &
Philadelphia Steamboat Co. is located at Chesapeake City, no charges
for wharfage being made. Ample mooring facilities at the eastern
and western ends of the canal and bulkheads at Delaware City and
St. Georges have been constructed by the United States. A harbor
for small boats has been provided and a wharf has been constructed
at Chesapeake City. The facilities are considered adequate for exist-
ing commerce.
     616634-45-pt. 1, vol. 1-19
290     REPORT OF CHIEF OF ENGINEERS,         U. S. ARMY,    1944

   Operations and results during fiscal year-New work.-Bank
stabilization on the north side of the canal, station 57+010 to
63 + 700, by contract, in progress at the end of the previous fiscal year,
was 94 percent completed. The costs under the contract were
$623,389.61. Hired labor costs in connection with the work were
$2,835.76. The total cost was $626,225.37.
   Maintenance-Contract.-Engineeringservices in connection with
a preliminary design of a proposed combined railroad and highway
bridge to replace the present Summit and Pennsylvania Railroad
bridges were procured at a cost of $2,084.52.
   Costs in connection with the design and preparation of plans and
specifications for a two-lane, high-level highway bridge across the
canal at Chesapeake City were $35,658.61.
   Obtaining borings at site of proposed highway bridge at Chesa-
peake City, in progress at the end of the previous fiscal year, was com-
pleted August 5, 1943. The cost was $5,504.37.
   Driving test piles at site of proposed highway bridge at Chesapeake
City, commenced February 28, 1944, was completed April 12, 1944.
The cost was $12,221.38.
  The construction of protective works at the Pennsylvania Railroad
bridge, in progress at the end of the previous fiscal year, was completed
September 3, 1943. The cost was $113,475.22.
  The construction of seven 37-pile dolphins and repairing existing
boardwalk piling at the Reedy Point and Chesapeake City mooring
basins, commenced February 22, 1944, was completed April 18, 1944.
The cost was $38,429.04.
  Maintenance-Hired labor.-Dredging of miscellaneous shoals be-
tween Delaware River and Elk River by the U. S. hopper dredges
Absecon and Hains, and derrickboat No. 37 was in progress at intervals
during the year. There were removed 564,211 cubic yards of material.
The cost was $185,986.04.
  Dredging in the approach channel in Chesapeake Bay by the U. S.
hopper dredge Absecon, commenced September 25, 1943, was com-
pleted October 15, 1943. There were removed 240,900 cubic yards of
material. The cost was $19,082.24.
  Other hired labor costs included maintenance and repairs to banks,
$30,238.03; drainage of banks, $30,663.77; seeding and planting wind-
breaks along banks, $1,866.83; maintenance and repair of auxiliary
works, $37,811.93; maintenance and operation of tide gages, $2,330.87;
removing miscellaneous obstructions and debris, $14,792.25; and sur-
veys, examinations and collecting miscellaneous engineering data,
$33,927.70; a total of $151,631.38. The total cost of all maintenance
was $564,072.80.
  Operating and care -      Hired labor.-    The waterway,      highway
bridges, and a ferry at Chesapeake City were operated and main-
tained throughout the fiscal year. The cost was $556,752.76.
   The total cost of all work was $626,225.37 for new work, $564,072.80
for maintenance, and $556,752.76 for operating and care, a total of
$1,747,050.93. The expenditures were $1,741,940.80.
   Condition at end of fiscal year.-The existing project was about
92 percent completed. The work remaining to be done is the com-
pletion of bank stabilization through the Deep Cut; dredging the
Delaware City branch channel from a point 400 feet east of Fifth
Street Bridge to its junction with the canal; stabilizing Summit
                RIVERS          AND HARBORS-PHILADELPHIA,                                             PA., DISTRICT                        291

Bridge; bank treatment at railroad bridge, north side; protecting
slopes with vegetal cover; widening Reedy Point entrance channel;
and constructing extensions to existing jetties at the Delaware River
entrance.
    The latest examinations show minimum depths at mean low water,
as follows:

                                                                                                                  Present depth

         Date                                      Section                              Project                          Mid-
                                                                                         depth           Left           channel       Right
                                                                                                        outside         for half     outside
                                                                                                        quarter         project      quarter
                                                                                                                         width

                                                                                            Feet            Feet         Feet          Feet
May 1944 ......           Delaware River to Elk River-.        -..........                      27             7.6         23. 5         19. 0
June 1944 -..             Elk River and Chesapeake Bay........------------.                     27            14.7         25.0          16.5
June 1943          ....   Delaware City Branch Channel-------------.......                       8 ----------
                                                                                                    .........              1 2.0.


   180 percent project width.


  The total costs and expenditures under the existing project were as
follows:
                                                                          Emergency re
                                                                            lief fundsre-       Regular funds                      Total


New work ____...         .-         ..-------------------                   $4,756,247.79            $9,059, 508.14          $13,815,755.93
Maintenance. __...-----------.---.--------------...---------6,                                           730, 694. 12          6, 730, 694. 12
Operating and care-.           ......                            -------------------
                                                       .-..............                               2, 351, 984. 48          2, 351, 984. 48
     Total ----------------------------------
                     .                                                      4, 756, 247. 79          18,142, 186. 74          22, 898, 434. 53
Expenditures- ......   ---  ...---.--.------....-                           4, 756, 247. 79          18, 050, 769.90          22,807, 017. 69



  In addition, the sum of $2,513,270.27 was expended between August
1918 and June 1935 on operating and care of the works of improve-
ment under provisions of the permanent indefinite appropriation for
such purposes.
  Proposedoperations.--It is proposed to apply the funds unexpended
and accounts receivable on June 30, 1944, amounting to $238,562.94,
together with $1,000,000 allotted from the act of June 26, 1944, in
July 1944, as follows:
Accounts payable June 30, 1944   ---------------------------- $102, 952. 23
New work:
   Stabilizing north bank of canal between stations
     57+010 and 63+700 under contract in force
     to be completed September 1944-                $130, 000. 00
   Topsoiling and seeding slopes between stations
     57+010 and 63± 700 and providing drainage
     along bank between stations 61+000 and
     63+000 on north bank of canal by hired
     labor ----------------------------------         28, 300. 00
               Total new work_-----------                                                            ----                  158, 300. 00
292      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                  1944

Maintenance:
   Dredging from Delaware River to Elk River
      with a United States hopper dredge and der-
      rick boat and rehandling with a pipe-line
      dredge as required throughout the year-
   Dredging in Elk River and Chesapeake Bay
                                                            ---..
                                                     $175, 000.                00
      with a United States hopper dredge and re-
      handling with a pipe-line dredge as required
      throughout the year---------------------- 111,447.                       71
   Maintaining canal banks and auxiliary works
      throughout the year----------------------        95, 000.                00
   Removing obstructions and debris throughout
      the year_ --------------------------------       10, 000.                00
   Designing and preparing plans for a 2-lane, high-
      level highway bridge to cross the canal at
      Chesapeake City under contract in force------    25, 863.                00

Maintenance (operating and care):                    417, 310. 71
   Operating canal, bridges, and ferry at Chesapeake
      City ----------------------------------        510, 000.00
   Ordinary maintenance and repairs to bridges
      and ferry slips ---------------------------     50, 000. 00
                                                                    560, 000. 00

          Total for maintenance -----------------------------                         $977, 310. 71

          Total for all work       -------------------------------                   1, 238, 562. 94

  The sum of $925,000 can be profitably expended during the fiscal
year 1946, as follows:
Maintenance:
   Dredging from Delaware River to Elk River with a
      United States hopper dredge and derrickboat, and
      rehandling with a pipe-line dredge, as required through-
      outtheyear ---------------------------------             $155,000
   Dredging in Elk River and Chesapeake Bay with a
      United States hopper dredge and rehandling with a
      pipe-line dredge, as required throughout the year-        100, 000
    Maintaining canal banks and auxiliary works throughout
      theyear -------------------------------------
                   _                                            100,000
    Removing obstructions and debris throughout the year__       10, 000
                                                                                         $365, 000
Maintenance (operating and care):
    Operating canal, bridges, and ferry at Chesapeake City- 530,000
    Ordinary maintenance and repairs to bridges and ferry -30,   000
                                                                                           560, 000

       Total for all work--------------------------------                                  925, 000
   The completion of the project is not required at this time.
                                Cost and financial summary
Cost of new work to June 30, 1944------------------------
                                      _                                         $24, 525, 510. 94
Cost of maintenance to June 30, 1944-------------------_                  --     15, 986, 426. 46
       Total cost of permanent work to June 30, 1944-------   40, 511, 937. 40
Plus accounts receivable June 30, 1944---------- ------------      11,535. 39

      Gross total costs to June 30, 1944------------- ----- 40, 523, 472. 79
Minus accounts payable June 30, 1944-----------------------     102, 952. 23
      Net total expenditures -- _- _-40,                    --                         420, 520. 56
Unexpended balance June 30, 1944                                                       227, 027. 55
       Total amount appropriated to June 30, 1944-........                          40, 647, 548. 11
                     RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                                          293

       Fiscal year ending June 30                   1940                     1941              1942                   1943               1944

    Cost of new work ....------------
                                 _.....         $362, 023.89           $555, 333.18        $262, 653.38            $66, 308. 61        $626, 225.37
    Cost of maintenance ....-----------
                                   _.            987, 322. 38         2, 375, 459. 61     1, 578, 007.06         1,192, 561. 92       1,120,825. 56

            Total cost            .------------ 1, 349, 346. 27       2, 930, 792. 79     1, 840, 660.44         1, 258, 870. 53      1, 747, 050. 93

    Total expended                   .-------------
                                               1,129, 653.17          2,   486, 390. 21   2,146, 269. 88         1, 226, 212. 21      1, 741, 940. 80

    Allotted.--------------_...               3, 053, 491.34               995, 700.00        267, 500.00        2, 469, 500.00----------




    Balance unexpended July 1, 1943_ - ------       ______ -$1,                                                                    968, 968. 35
    Gross amount expended ------------------ $1, 756, 028. 65
    Less reimbursements collected-_- - -     - - - 14, 087. 85
                                                                                                                                 1, 741, 940. 80
           Balance unexpended June 30, 1944--------------------                                                              -     227, 027. 55
    Outstanding liabilities June 30, 1944---------- $102, 952. 23
    Amount covered by uncompleted contracts. -.       165, 641. 70
                                                                                                                                   268, 593. 93
          Balance available June 30, 1944----------------                                                                         -41, 566. 38
    Accounts receivable June 30, 1944--------------------------                                                                      11, 535. 39
I
       Unobligated balance available June 30, 1944-------------                                                                   -30, 030. 99
    Amount allotted in July 1944_----------------------------                                                                    1, 000, 000. 00
                 Amount available during fiscal year 1945----_--- --                                                               969, 969. 01

    Amount (estimated) required to be appropriated for completion
         of existing project 1- __________                        -              -        -           -$1,115,                           000. 00
    Amount that can be profitably expended in fiscal .year ending
        June 30, 1946 for maintenance 1                                              -----------                                   925, 000. 00
         1 Exclusive of available funds.



                                           7. MISPILLION RIVER, DEL.

       Location.-This river rises in Kent and Sussex Counties, Del., flows
    northeasterly 15 miles along the boundary line between the two coun-
    ties, and empties into Delaware Bay about 16 miles above Cape Hefilo-
    pen. (See U. S. Coast and Geodetic Survey Chart No. 1218).
       Previous projects.-Adopted by River and Harbor Acts of March
    3, 1879, July 13, 1892, modified July 3, 1893, and by River and Harbor
    Act of March 2, 1907. For further details see page 1786, Annual
    Report for 1915, page 448 of Annual Report for 1918, and page 327
    of Annual Report for 1938.
       Existing project.-This provides for a channel 6 feet deep at mean
    low water, 80 feet wide in Delaware Bay to the mouth, and thence
    60 feet wide to Milford, 11 miles above the mouth, with additional
    width at sharp bends. It also provides for four cut-offs, 50 feet wide,
    and for two parallel stone-filled pile and timber jetties at the mouth,
    spaced 210 feet apart, the south jetty 5,850 feet long and the north
    jetty about 6,496 feet long extending to a point opposite the end
    of the south jetty. The total length of the section included in the
    project is about 12 miles. The mean tidal range at the mouth is
    4.3 feet and at Milford 3.4 feet. The extreme tidal range is from
    about 1 foot below mean low water to about 2 feet above mean high
    water.
       The estimate of cost for new work, revised in 1937, was $177,350,
    exclusive of amounts expended on previous projects. The latest
294        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

(1937) approved estimate for annual cost of maintenance is $7,400.
The existing project was authorized by the following river and harbor
acts:

    Acts                        Work authorized                                     Documents


Mar. 2,1919    For 6-foot depth and extension of south jetty    -...   H. Doc. No. 678, 62d Cong., 2d sess.
                                                                                                            1

Aug. 26,1937   Extension of north jetty----- --------.....-            Rivers and Harbors Committee Doe.
                                                                                                        1
                                                                         No. 83, 74th Cong., 2d sess.


  1Contains latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 2 wharves inside the mouth of the
river and 10 piers or wharves at Milford, 2 of which are owned by
the city of Milford. There is also a marine railway at Milford. The
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-A contract was awarded
for dredging in the entrance channel and in the upper end of the
river. The cost was $28.14 for maintenance. There were no expendi-
tures.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depths, at mean low water, in June 1944, were
as follows: From Delaware Bay to the mouth, 5 feet; thence to the
highway drawbridge, 5.2 feet; and thence to the fixed highway bridge
at Milford, 6.7 feet.
  T
    he costs under the existing project were $216,390.72 for new work
and $127,378.01 for maintenance, a total of $343,768.73. The expendi-
tures were $343,740.59
  Proposed operations.--Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $40,000, as follows:
Accounts payable June 30, 1944 --------------------------------- $28. 14
Maintenance:
    Dredging in entrance channel and in upper section of river, by
      contract (July to September 1944)--       ---           ____     39, 421. 86
    Coating tops of piling in jetties at mouth with tar by hired labor     550. 00
           Total      -------------------------------------------                               40, 000. 00
   No maintenance is contemplated during the fiscal year 1946, as it
is believed that channel conditions will be adequate to meet the needs
of commerce.
                                   Cost and financial summary
Cost of new work to June 30, 1944_ ___-----------                                            $365, 189. 13
Cost of maintenance to June 30, 1944-------_                                         -        188, 550. 43
      Total cost of permanent work to June 30, 1944                    --------------          553, 739. 56
Minus accounts payable June 30, 1944-----------------------                                          28. 14
      Net total expenditures_ --------------------------------                                 553, 711. 42
Unexpended balance June 30, 1944--------_                 -                                     40, 000.00
        Total amount appropriated to June 30, 1944 -----------                                 593, 711. 42
               RIVERS AND HARBORS-PHILADELPHIA, PA., DISTRICT                                                                           295

    Fiscal year ending June 30                         1940                  1941         1942                  1943                1944

Cost of new work --------------
                      .           $108,356.45    ...
Cost of maintenance---------------------      --- --------                               $9, 118. 07-                                      28. 14

Total expended......                          .      127, 118. 29 --------------
                                 ....----------------.                                    9, 118. 07      -......-----------        4

Allotted-- -------------------                       14, 700.00              3,200.00     5, 918. 07----.----                      40, 000. 00


Amount allotted from War Department Civil Appropriation Act
approved July 19, 1937-- ----------------------------------                                                                   $40, 000. 00
Balance unexpended June 30, 1944 _                                            --------                                          40, 000.00
Outstanding liabilities June 30, 1944_                                     -------                      $28. 14
Amount covered by uncompleted contracts-- ------                                                   39, 421. 86
                                                                                                                                39, 450. 00
           Balance available June 30, 1944 ---------------------------                                                              550.00

8. INLAND WATERWAY BETWEEN REHOBOTH BAY AND DELAWARE
                       BAY, DEL.
  Location.-This waterway, a tidal canal, is situated in the south-
easterly part of Sussex County, Del. It extends 12 miles northward
from Rehoboth Bay through the highland west of the town of Reho-
both to Gordon Lake; thence through the marshes back of Cape Hen-
lopen to Lewes River; thence down Lewes River to its junction with
Broadkill River near its mouth. An entrance to the waterway from
Delaware Bay is located about 4 miles above Cape Henlopen. (See
U. S. Coast and Geodetic Survey Charts Nos. 379, 1218, and 1219.)
  Previous projects.-A canal along a slightly different route formed
a part of the projected waterway from Chincoteague Bay, Va., to
Delaware Bay, begun in 1886 and abandoned in 1905.
  Existing project.-This provides for a waterway 6 feet deep and
100 feet wide from Broadkill River to South Street Bridge at Lewes
and a basin of the same depth 1,200 feet long and up to 375 feet in
width at the latter point; an entrance channel of the same depth and
200 feet wide from Delaware Bay near Lewes, protected by 2 parallel
steel-sheet pile jetties reinforced with riprap stone spaced 500 feet
apart and 1,700 feet long; a channel 6 feet deep and 50 feet wide (40
feet wide through Deep Cut near Lewes) from Lewes to Rehoboth
Bay, and for 2 parallel rubble-mound jetties 725 feet long at the
Rehoboth Bay entrance. The project also includes the construction
of one railroad bridge and one highway bridge at Rehoboth. The
total length of the section included in the project is about 12 miles.
All depths refer to the plane of mean low water. The mean tidal range
in the waterway opposite the Delaware Bay entrance is 3.9 feet, at
Lewes 3.7 feet, and at Rehoboth 0.6 foot. The extreme tidal range is
from about 1 foot below mean low water to about 3 feet above mean
high water.
    The estimate of cost for new work, revised in 1935, is $526,000, ex-
clusive of amount expended on previous projects, and exclusive of
$60,000, contributed funds, but including $14,275 for the purchase of
land since obtained free of cost to the United States, making the actual
estimated cost for the construction of the canal $571,725, which in-
eludes $60,000 contributed funds and $37,343.58 awarded the railroad
company in full for all damages to that company for the erection and
maintenance of a railroad bridge across the canal at Rehoboth. The
296        REPORT OF CHIEF OF ENGINEERS,                              U. S. ARMY,         1944

latest (1935) approved estimate for annual cost of maintenance                                              is
$19,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                                     Documents


July 25,1912   For a 6-foot-depth canal to connect Rehoboth Bay       H. Doc. No. 823, 60th Cong., 1st sess.,
                and Delaware Bay.                                       and Rivers and Harbors Committee
                                                                        Doe. No. 51, 61st Cong., 3d sess.
Aug. 30,1935   For a 6-foot-depth entrance near Lewes, for jetties,   Rivers and Harbors Committee Doc.
                for widening the canal from Broadkill River to          No. 56, 74th Cong., 1st sess.   (Con-
                Lewes, and basin.                                       tains latest published maps.)



   Recommended modification off project.--Underdate of May 29, 1941,
the Chief of Engineers recommended modification of the existing
project so as to provide for extending the jetties at the entrance from
Delaware Bay and for a depth of 10 feet in the channel from Delaware
Bay to and including the turning basin at Lewes at an estimated cost
of $224,000, with $9,000 annually for maintenance in addition to the
amount now required; subject to certain conditions of local coopera-
tion (H. Doc. No. 344, 77th Cong., 1st sess.).
   Local cooperation.--Fullycomplied with.
   Terminal facilities.-There are 3 wharves at Lewes, Del., 1 owned
by the town, 1 Government owned, and 1 privately owned, all open to
public use. There are a number of small landings for fishing parties
and private boats on the inland waterway. At Lewes on the north
bank of the waterway, the Lewes Anglers Association has constructed
a wharf about 600 feet long with 43 slips for fishing party boats. At
Rehoboth there are 2 private wharves of pile and timber construction.
At Henlopen Acres, adjoining Rehoboth, a private yacht basin, with
accommodations for more than 50 fishing party boats and pleasure
craft, connects with the canal.
   Operations and results during fiscal year.-Repairing jetties at the
Delaware Bay entrance, by contract, commenced May 23, 1944, was 70
percent completed at the end of the fiscal year. The work consists
of repairing the outer ends of both jetties, placing stone along the
channel side of the east jetty, and constructing a 400-foot shore end,
stone extension to the east jetty. The cost was $6,927.65 for mainte-
nance. The expenditures were $5,955.81.
   Condition at end of fiscal year.-The existing project was about 85
percent completed. The work remaining to be done is the reinforcing
of the jetties at the Rehoboth Bay entrance, built in 1903 under a
previous project. The controlling depths, at mean low water, in June
1944, were as follows: From Delaware Bay to the mouth, 8.7 feet;
thence to the highway bridge at Lewes, 3.7 feet; thence to Rehoboth,
3.4 feet; and thence to Rehoboth Bay, 2.5 feet.
   The costs under the existing project, excluding $60,000 contributed
funds expended for new work, were $435,383.05 for new work and
$34,965.62 for maintenance, a total of $470,348.69. The expenditures
were $469,376.85.
             RIVERS AND HARBORS-PHILADELPHIA,                                                               PA.,      DISTRICT           297
  Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, amounting to $9,447.19, as follows:
Accounts payable June 30, 1944$----------------------------------                                                                     971. 84
Repair jetties by contract in force to be completed August 1944                                                                    8, 475. 35
           Total               -----------------------------------------                                                           9, 447. 19
   No maintenance is contemplated during the fiscal year 1946, as it
is believed that channel conditions will be adequate to meet the needs
of commerce.
   The completion of the project is not required by existing com-
merce.
                                                  Cost and financial summary
Cost of new work to June 30, 1944-------------------------$435,383.07
Cost of maintenance to June 30, 1944                     -34,                965.                                                           62
      Total cost of permanent work to June 30, 1944 ....              470, 348.                                                             69
Minus accounts payable June 30, 1944-.                        -971.                                                                         84
       Net total expenditures -------------                         1469,    376.                                                           85
Unexpended balance June 30, 1944            --                            9, 447.                                                           19
       Total amount appropriated to June 30, 1944-             -      478, 824.                                                             04

   Fiscal year ending June 30                          1940                 1941                  1942                  1943         1944

Cost of new work-----------                              --------------                ------------------------------------
Cost of maintenance-------------                          $72. 50                                                                    $6, 927. 65
Total expended ....                  ...------------------....72.50   f-I                                                             5, 955.81

Allotted    ----------------------                  -4,927.50           -          -           $13, 500.00        -$13, 500.00i      15, 403.00


Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942_                          _$15,                                                                              403. 00
Gross amount expended_---            -------------                                                                                 5, 955. 81
      Balance unexpended June 30, 1944----------------------                                                                       9, 447. 19
Outstanding liabilities June 30, 1944 _       _    _     -$971.      84
Amount covered by uncompleted contracts----                  8, 072. 35
                                                                                                                                   9, 044. 19
           Balance available June 30, 1944-                                                                                           403. 00
Amount (estimated) required to be appropriated for completion of
existing project 2----------------------------------                                                                             76, 350. 00
  1In addition $60,000 contributed funds expended for new work.
  SExclusive of available funds.

                              9. INDIAN RIVER INLET AND BAY, DEL.
   Location.-This bay is a shallow lagoon 6 miles long and 2 miles
wide on the Delaware coast about midway between Cape Henlopen
and the Maryland State line. The inlet is an opening through the
barrier beach separating Indian River Bay and the Atlantic Ocean.
(See  U. S. Coast and Geodetic Survey Chart No. 1219.)
   Previous  projects.-Adopted by River and Harbor Act of August
2, 1882. For further details see page 744, Annual Report for 1888.
   Existing project.-This provides for an inlet channel 15 feet deep
and 200 feet wide from the ocean to a point in Indian River Bay
7,000 feet from the ocean shore line; and thence a channel of pro-
gressively decreasing depth, and width decreasing from 200 to 100
feet to the 6-foot depth curve in the bay. It also provides for two
parallel jetties spaced 500 feet apart, each 1,566 feet long with inshore
end sections of steel-sheet pile construction reinforced with stone, the
298         REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,   1944

north jetty 904 feet long and the south jetty 890 feet long, and with
outshore end sections of all stone construction., The project also pro-
vides that the interior channel dimensions may, in the discretion of the
Chief of Engineers, be modified as may be found desirable to increase
the hydraulic efficiency of the channel, without increasing the cost.
The total length of the section included in the project is about 21/
miles. All depths refer to the plane of mean low water. The mean
tidal range in the ocean at the inlet is 3.8 feet, and at the highway
bridge inside the inlet 2.4 feet. The extreme tidal range at the highway
bridge is about 6 feet.
   Th estimate of cost for new work made in 1937 was $443,000, ex-
clusive of amounts expended on previous projects, but including
$160,000 contributed funds. The latest (1937) approved estimate for
annual cost of maintenance is $10,000.
   The existing project was adopted by the River and Harbor Act
approved August 26, 1937 (Rivers and Harbors Committee Doc. No.
41, 75th Cong., 1st sess.). The latest published map is in the project
document.
   Recommended modifications of project.-Under date of May 25,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide a channel 9 feet deep, 100 feet wide in the
bay, and 80 feet wide in the river, from that depth in the existing
channel in Indian River Bay to and including a turning basin 9
feet deep, 175 feet wide, and 300 feet long at Old Landing; thence
about 8,200 feet to the highway bridge at Millsboro, 60 feet wide and
4 feet deep; at an estimated first cost of $201,000, with annual main-
tenance of $10,000 in addition to that now required, subject to certain
conditions of local cooperation. (H. Doc. No. 330, 76th Cong., 1st
sess.).
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-Thereare two wharves located at Oak Orchard,
on Indian River Bay.
   Operations and, results during fiscal year-Maintenance-Hired
labor.-Fill was placed back of the north and south bulkheads, west
of the highway bridge. The cost was $19,992. A sand fence was
erected south of the south dike, west of the highway bridge. The
cost was $1,096.41. Surveys and channel examinations were made at
a cost of $1,270.49. The total cost was $22,358.90 for maintenance.
The expenditures were $21,753.15.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1940. The controlling depths, at mean low water, in October
1943 were as follows: Through the inlet channel to a point in the bay
7,000 feet from the ocean shore line, 6.1 feet; and thence to deep water
in Indian River Bay, +0.5 feet.
   The costs under the existing project, exclusive of $160,000 con-
tributed funds expended for new work, were $270,119.19 for new
work and $167,988 for maintenance, a total of $438,107.19. The
expenditures were $437,446.47.
   Proposed operations.-It is proposed to apply the funds unex-
pended on June 30, 1944, amounting to $5,353.53, as follows:
Accounts payable June 30, 1944-                         ----                            $660. 72
Surveys and channel examinations_                     ---------                        4, 692. 81
          Total ---------------------------------------------                          5, 353. 53
           RIVERS AND HARBORS-PHILADELPHIA,                                         PA., DISTRICT                     299

   No maintenance is contemplated during the fiscal year 1946, as
it is believed that channel conditions will be adequate to meet the
needs of commerce.
                                Cost and financial summary
Cost of new work to June 30, 1944_.                          1 $280, 119. 19
Cost of maintenance to June 30, 1944------------------------    167, 988. 00
      Total cost of permanent work to June 30, 1944                           -----------                     448, 107. 19
Minus accounts payable June 30, 1944_--------                                                    ---              660. 72
      Net total expenditures---
                              -         --------                                          ---                 447, 446. 47
Unexpended balance June 30, 1944_----------------------------                                                   5, 353. 53
        Total amount appropriated to June 30, 1944------------                                          1 452, 800. 00

   Fiscal year ending June 30           1940           1941                1942                 1943               1944

Cost of new work ---------------    $35,663.47 --         --------------------------------------
Cost of maintenance ..------------------------      $26, 673. 74         $62,190. 91           $56, 764. 45       $22,358.90
Total expended..-----------------65,     003. 94     26, 043.13           57, 032.11            62, 933.36         21, 753.15
Allotted------------------------..88,    000. 00     86, 500.00                               40,200. 00
                                                                                             --------              25, 500.00

Balance unexpended July 1, 1943-                                                                               $1, 606. 68
Amount allotted from W. D. Civil Appropriation Act approved
  June 2, 1943-----------------------------------------                                                        25, 500. 00
      Amount to be accounted for---------------------------27,                                                     106. 68
Gross amount expended-----------------------------------                                                       21, 753. 15
       Balance unexpended June 30, 1944---5,                                                                       353. 53
Outstanding liabilities June 30, 1944-------------------------                                                     660. 72
        Balance available June 30, 1944---- --------------------                                                4, 692. 81
  1In addition $160,000 contributed funds expended for new work.

                                10. BIG TIMBER CREEK, N. J.

   Location.-This creek rises in Camden and Gloucester Counties,
N. J., and with its south branch flows northwestwardly 16 miles along
the boundary line between the two counties, emptying into IDelaware
River opposite the south portion of Philadelphia, Pa. (See U. S.
Coast and Geodetic Survey Chart No. 295.)
   Existing project.-This provides for a channel 10 feet deep at mean
low water, generally 75 feet wide from the 10-foot contour in Delaware
River to the mouth and within the creek to Marters sand plant, 31/2
miles above the mouth, and thence 60 feet wide to Clements Bridge, 5
miles above the mouth, including 4 cut-offs. The total length of the
section included in the project is about 5/2 miles. The mean tidal
range at Westville near the mouth is 5.4 feet and at Clements Bridge
4.3 feet. The extreme tidal range is from about 11/ feet below mean
low water to about 2 feet above mean high water.
   The estimate of cost for new work, revised in 1935, was $104,500,
including $50,000 contributed funds. The latest (1935) approved
estimate for annual cost of maintenance is $4,000.
   The existing project was authorized by the following river and
harbor acts:
300              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                              1944


       Acts                                      Work authorized                                         Documents 1


July 3,1930-__ For a 10-foot depth from Delaware River to                           H. Doc. No. 217, 70th Cong., 1st sess.
                 Marters sand plant.
Aug. 30, 1935_ Extension of project to Clements Bridge- .......-                    Rivers and Harbors Committee Doc.
                                                                                     No. 15, 73d Cong., 1st sess.


   I Contain latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are two wharves and one boat yard for
the repair and storage of small boats at Westville. The wharves are
privately owned, one being open to public use. The facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year.-Maintenance dredging
in the entrance channel, by contract, was commenced February 21,
1944, and completed March 8, 1944. There were removed 8,370 cubic
yards place measurement, of material. The costs and expenditures
were $6,500.
   Condition at end of fiscal year.-The existing project was completed
in 1941. The controlling depths at mean low water in March 1944
were as follows: Delaware River to the mouth, 9.2 feet; thence (May
1942) to Westville, 10.7 feet; thence to Marters sand plant, 8.8 feet;
and thence to Clements Bridge 9 feet.
   The costs and expenditures under the existing project, excluding
$50,000 contributed funds expended for new work, were $58,664.77
for new work and $11,251.59 for maintenance, a total of $69,916.36.
   Proposed operations.-No funds are available and no maintenance
is contemplated during the fiscal years 1945 and 1946, as it is believed
that channel conditions will be adequate to meet the needs of com-
merce.
                                                      Cost and financial summary
Cost of new work to June 30, 1944-----------------------------                                                             1 $58, 664. 77
Cost of maintenance to June 30, 1944--------------------------                                                                   11, 251. 59
      Total cost of permanent work to June 30, 1944--------- --                                                                  69, 916. 36
Net total expenditures_----------------------------------------                                                                I 69, 916. 36
      Total amount appropriated to June 30, 1944--------------_                                                                1 69, 916. 36

     Fiscal year ending June 30                         1940         1941               1942                  1943                  1944

Cost of new work         --------------      $35,109. 41            $6, 571.40           $486. 00     ....            ......         .
Cost of maintenance___ .-.--.-.----.----..--                         4, 615.14            136. 45   ---------------                      $6,500
         Total cost                 .--------------    35,109. 41   11, 186, 54           622. 45     ...........--------------            6, 500

Total expended--------------..................         31,922. 52    5, 643.91      9, 387. 29       ...........--------------             6, 500

Allotted       .....------------------------------                   7, 083. 75   -1,     786.13    --------------                         6, 500



Amount allotted from War Department Civil Appropriation Act
approved June 2, 1943--------------------------------------                                                                     $6, 500.00
      Gross amount expended --------------------------------                                                                      6, 500. 00
   1 In addition, $50,000 contributed funds expended for new work.
           RIVERS AND HARBORS                    PHILADELPHIA, PA., DISTRICT                         301
                                  11. MANTUA CREEK, N. J.

  Location.-This creek rises in Gloucester County, N. J., flows north-
westerly 161/2 miles and empties into Delaware River about 10 miles
below Philadelphia, Pa. (See U. S. Coast and Geodetic Survey Chart
No. 295.)
  Previous projects.-Adopted by River and Harbor Act of August
2, 1882, and modified in 1889. For further details see page 1784,
Annual Report for 1915, and page 342, Annual Report for 1938.
  Existing project.-This provides for a channel 20 feet deep and 110
feet wide from that depth in Delaware River to the Grasselli Chemi-
cal Plant of E. I. du Pont de Nemours & Co., a distance of 5,400 feet;
thence 12 feet deep and 100 feet wide to the plant of the Strathmann
Sand & Gravel Co., 5,900 feet; thence 10 feet deep and 60 feet wide to
Friars Landing, 2,000 feet; and thence 7 feet deep and 60 feet wide
to Parkers Landing near Mount Royal, 2 miles; a dredged cut-off 3
feet deep and 50 feet wide across a bend in the creek 9,000 feet above
Mount Royal; and twin jetties at the mouth of the creek. The sec-
tion of the creek included in the existing project extends from Dela-
ware River upstream 7 miles to 1 mile below the town of Mantua. All
depths refer to the plane of mean low water. The mean tidal range
at the mouth is 5.2 feet; at Paulsboro, 5 feet; at Mount Royal, 4.6
feet; and at Mantua, 3.5 feet. The extreme tidal range is about 10 feet.
   The estimate of cost for new work, revised in 1938, was $200,000,
exclusive of amounts expended on previous projects. The latest (1938)
approved estimate for annual cost of maintenance is $5,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                  Documents


Mar. 3,1899    For a 12-foot, 8-foot, and 7-foot depth to Parkers   H. Doc. No. 123, 55th Cong., 2d sess.;
                 Landing,   cut-off above Mount Royal,       and     Annual Report 1898, p. 1122.1
                jetties at mouth.
Mar. 2,1907    For dike across old mouth....------------------- Specified in act.
Aug. 30,1935   For a 12-foot and 10-foot depth to Friars Landing_   Rivers and Harbors Committee Doc.
                                                                                                  1
                                                                     No. 14, 73d Cong., 1st sess.
June 20,1938   For a 20-foot depth to the Grasselli chemical plant. H. Doc. No. 505, 75th Cong., 3d sess 1

  1These documents and H. Doc. No. 523, 61st Cong., 2d sess., contain the latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 10 wharves of pile and timber con-
struction on this stream. The facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year.-Maintenance dredging
between Delaware River and Grasselli chemical plant, by contract was
commenced January 14,1944, and completed March 5,1944. There were
removed 65,374 cubic yards, place measurement, of material. The
costs and expenditures were $31,747.40.
   Conditionat end of fiscal year.-The existing project was completed
in 1940. The controlling depths, at mean low water, in March 1944,
were as follows: Delaware River to Grasselli chemical plant, 20.4 feet;
302            REPORT OF CHIEF OF ENGINEERS,                                             U. S. ARMY,                 1944

thence (April 1942) to Strathmann Sand Plant, 11.7 feet; thence to
Friars Landing, 11.5 feet; thence to Parkers Landing, 6.5 feet; and
thence to Mantua, 0.5 foot.
   The costs and expenditures under the existing project were $166,-
687.08 for new work and $111,483.82 for manitenance, a total of
$278,170.90.
   Proposed operations.--It is proposed to transfer the funds unex-
pended on June 30, 1944, amounting to $9,252.60, to another project
within the district.
   No maintenance is contemplated during the fiscal years 1945 and 1946,
as it is believed that channel conditions will be adequate to meet the
needs of commerce.
                                               Cost and financial summary
Cost of new work to June 30, 1944-_                                                                                   $169, 687.08
Cost of maintenance to June 30, 1944_-------                                                            ---            111, 483.'82
            Total cost of permanent work to June 30, 1944-------                                                          281, 170. 90
Net total expenditures -------------------------------------                                                              281, 170. 90
Unexpended balance June 30, 1944 ------------------------                                                                   9, 252. 60
            Total amount appropriated to June 30, 1944---------                                                           290, 423. 50

    Fiscal year ending June 30                       1940                1941               1942              1943             1944


Cost of new work------------..............         $36,128.56 -.......                             -..-..___ ...                -.
Cost of maintenance - ----............. ----..............        -. -          --.-         .-- - -                 .-       $31, 747. 40
Total expended.....-..-.. ... 36, 1856       . __._.                                 .   .....   _ _    ____.. ..    31,747.40
Allotted..-------------------17, 871.44.--------
                                                                                             .--------------------------
                                                                                                                     41, 000.00


Amount allotted from War Department Appropriation Act ap-
    proved June 2, 1943_.                      -              -           -     --           -      -           -         $41,000.00
Gross amount expended_------------------------------                                                                       31, 747.40
             Balance unexpended June 30, 1944_                                                                                 252. 60
                                                                                                                            9,---------------9

                                             12. COLD SPRING INLET, N. J.

   Location.-This inlet is located in Cape May County, southern New
Jersey, about 3 miles east of Cape May City and about 16 miles north-
east of Delaware Breakwater. The inlet connects Cold Spring Harbor
with the Atlantic Ocean and is about 1 mile in length. (See U. S.
Coast and Geodetic Survey Charts Nos. 234, 827, and 1219.)
   Emisting project.-This provides for an inlet entrance channel 25
feet deep at mean low, water and 400 feet wide, pr ected by two
parallel jetties spaced 850 feet apart, the east jetty         feet long
and west jetty 4,410 feet long, with inshore end wings 750 feet and 297
                                                                                                              4,548
feet long, respectively, the wings and the 2,000-foot inshore end sec-
tion of west jetty of stone-filled pile and timber construction, and the
entire east jetty and the outshore end section of the west jetty of
rubble mound construction. The total length of the section included
        RIVERS AND HARBORS-PHILADELPHIA,           PA., DISTRICT     303
in the project is about 1 mile. The mean tidal range at the inner ends
of the jetties is 4.3 feet. The extreme tidal range, due to ocean storms,
is about 11 feet.
    The estimate of cost for new work, made in 1906, was $1,311,000,
including $100,000 contributed funds. The latest (1928) approved
estimated for annual cost of maintenance is $20,000.
    The existing project was adopted by the River and Harbor Act of
March 2, 1907 (H. Doc. No. 388, 59th Cong., 2d sess.). The latest pub-
lished map is in the Annual Report for 1911, page 1382.
    Recommended modifications of project.-Under date of May 20,
1941, the Chief of Engineers recommended modification of the existing
project for Cold Spring Inlet, N. J., to provide an entrance channel
25 feet deep and 400 feet wide, protected by parallel jetties, and extend-
ing from the 25-foot depth in the Atlantic Ocean to a line 500 feet
harborward of a line joining the inner ends of the jetties, thence, 20
feet deep and 300 feet wide to deep water in Cold Spring Harbor; at
an estimated cost of $71,000 to complete the project and $30,000
annually for maintenance of the entire project (H. Doc. No. 262, 77th
Cong., 1st sess.).
    Local cooperation.-All cooperation has been completed, except the
work of deepening and enlarging the inner harbor, which is 80 percent
completed.
    Terminal facilities.-Wharves with docking facilities for commer-
cial fishing vessels and fishing-party boats are located on the inner
end of the harbor at Cape May. There is also a well-equipped marine
railway adjoining the fish dock, a number of small wharves for pri-
vate craft and party boats and a yacht basin with accommodations for•
about 50 boats. North of the inlet entrance channel at Wildwood Crest
is another large well-equipped wharf for commercial fishing boats.
Both fish docks have direct railroad connections. The facilities are
considered adequate for existing commei'ce.
    Operations and results during fiscal year.-Maintenance dredging
in the inlet channel by the U S. hopper dredge Absecon was in progress
from November 27, 1943, to January 15, 1944. There were removed
179,300 cubic yards, bin measurement, of material. The cost was
$39,175. The expenditures were $39,337.73.
    Conditionat end of fiscal year.-The existing project was completed
in 1917. The controlling depth, at mean low water, in November
1943, from the Atlantic Ocean to the inner limit of the project, was
20.7 feet.
    The costs and expenditures under the existing project, excluding
$100,000 contributed funds expended for new work, were $879,274.62
for new work and $614,868.07 for maintenance, a total of $1,494,142.69.
    Proposed operations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $3,181.07 together with $30,000 allotted
from the act of June 26, 1944, in July 1944, to maintenance dredging
throughout the project with a United States hopper dredge (March
1945).
    The sum of $25,000 can be profitably expended during the fiscal year
1946 for channel maintenance dredging with Government plant, as
required.
 304              REPORT OF CHIEF OF ENGINEERS,                                          U.   S. ARMY,         1944

                                                          Cost and financial summary
Cost of new work to June 30, 1944                            1-------------------------
                                                               $879, 274. 62
Cost of maintenance to June 30, 1944------------------------- 614, 868. 07
              Total cost of permanent work to June 30, 1944------- --                                           1, 494, 142. 69

Net total expenditures ----------------------------------                                                  1 1, 494, 142. 69
Unexpended balance June 30, 1944_      ---------------------------                                                3, 181. 07
              Total amount appropriated to June 30, 1944-----------                                            1 1, 497, 323. 76

     Fiscal year ending June 30                              1940            1941         1942          1943              1944

Cost of new work
Cost of maintenance .                             $46, 032. 76
                                        .------------                      $27, 732.84   $31,851.39      $792. 54       $39, 715. 00

Total expended__               .......----------------     46, 032 76      27, 732.84   25, 427. 21    7, 053. 99       39, 337. 73
Allotted........................----------------------.     66, 032. 76   -11, 000. 00   58,732.84     25, 000. 00      -10, 000. 00


Balance unexpended July 1, 1943-                                                                                    $52, 518. 80
Amount allotted from First Deficiency Appropriation Act, 1941,
   Apr. 1, 1941 --------------------------------------------                                                          40, 000. 00

       Amount to be accounted for---------------------------                                                          92, 518. 80
Deductions on account of revocation of allotment---------------                                                      50, 000. 00

       Net amount to be accounted for------------------------                                                         42, 518. 80
Gross amount expended ------------------------------------                                                           39, 337. 73
      Balance unexpended June 30, 1944--------- -------------                                                          3, 181. 07
SAmount allotted in July 1944 --------------------------------                                                        30, 000. 00

              Amount available during fiscal year 1945------------ ----                                              33, 181. 07

Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 2------------                                                                         25, 000. 00
   1In addition $100,000 contributed funds expended for new work.
   3 Exclusive of available funds.

                                                          13. ABSECON INLET, N. J.

   Location.-This inlet is located on the coast of New Jersey about
65 miles north of Delaware Breakwater, between Brigantine Beach
on the north and Absecon Beach on the south. It forms the entrance
to the harbor at Atlantic City, N. J. (See U. S. Coast and Geodetic
Survey Charts Nos. 826 and 1217.)
   Previous project.-Adopted by River and Harbor Act of July 25,
1912. The project was completed in 1916. For further details see
Annual Report for 1936, page 319.
   Existing project.-This provides for an inlet entrance channel
20 feet deep at mean low water and 400 feet wide. It also provides
that should the channel at any time have a deleterious effect on the
Atlantic City beach, work upon the improvement may cease, it being
understood that the project is adopted on the basis that the interests
of the beach in front of the city are superior to those of the inlet.
The total length of the section included in the project is about 1 mile.
The mean tidal range in the ocean is 4.0 feet and at the inlet gorge
3.6 feet. The extreme tidal range, due to ocean storms, is about
11 feet.
         RIVERS AND HARBORS-PHILADELPHIA,                  PA., DISTRICT           305
    The estimate of cost for new work, revised in 1942, is $510,000.
The latest (1922) estimate for annual cost of maintenance is $50,000.
    The existing project was adopted by the River and Harbor Act
of September 22, 1922 (H. Doc. No. 375, 67th Cong., 2d sess.). The
latest published map is contained in the Annual Report for 1887,
page 818.
    Terminal facilities.-There are nine wharves served by this im-
provement; one is Government owned, six are privately owned and
open to the general public use upon payment of moderate wharfage,
and two are publicly owned. Three of the wharves have direct
railroad connection. There is also a continuous line of piers or land-
ing places for pleasure craft on both sides of the large basins which
indent the south shore of the inner channel. There are three shipyards
and three marine railways at this locality. The facilities are consid-
ered adequate for the existing commerce.
    Operations and results during fiscal year. Maintenance dredging
in the entrance channel by the U. S. hopper dredge Absecon was in
progress from July 1 to 23, 1943, from August 16, to September 24,
1943, and from January 15, to April 4, 1944. There were removed
512,110 cubic yards, place measurement, of material. The cost was
$129,959.61. Surveys and channel examinations were made at a cost
of $4,842.16. The total cost was $134,801.77 for maintenance. The
expenditures were $139,606.01.
    Condition at end of fiscal year.-The project was about 46 percent
completed. The work remaining to be done is the completion of the
dredging of the inlet channel to project dimensions. The controlling
depth, at mean low water, in May 1944, across the ocean bar, was 18.3
feet.
   The costs under the existing project were $208,647.66 for new work
and $1,039,652.83 for maintenance, a total of $1,248,300.49. The ex-
penditures were $1,247,937.01.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $30,075.28, together with $30,000
allotted from the act of June 26, 1944, in July 1944, as follows:
Accounts payable June 30, 1944-------------------------------$363. 48
Maintenance dredging throughout the project with a United States
  hopper dredge (April and May 1945) ---------------             59, 711. 80
      Total -------------------------------------            _       _      60, 075.28
  The sum of $25,000 can be profitably expended during the fiscal
year 1946 for maintenance dredging, with Government plant, as
required.
                              Cost and financial summary

Cost of new work to June 30, 1944--------------------------               $435, 144. 55
Cost of maintenance to June 30, 1944-----------------------              1, 275, 438. 44
      Total cost of permanent work to June 30, 1944-- -------- 1, 710, 582. 99
Minus accounts payable June 30, 1944------------------------           363. 48
      Net total expenditures-----------------------------1, 710, 219. 51
Unexpended balance June 30, 1944---------------------------  30, 075. 28
      Total amount appropriated to June 30, 1944                 -       1, 740, 294. 79
      616634   45-pt. 1, vol. 1--20
306            REPORT OF CHIEF OF ENGINEERS,                                  U.     S.     ARMY,      1944


    Fiscal year ending June 30                 1940           1941              1942            1943             1944

Cost of new work......         _         _
Cost of maintenance---------...........---   $58, 331.34    $63, 592. 82       $4, 240.12    $263,323.88       $134,801. 77

Total expended.....----------------           58, 084. 50    64, 465.39         4,255.66      258,288.00        139, 606.01

Allotted.----------------------40, 706.08                    70,104.99         39, 000.00     187, 070.39       138, 000. 00


Balance unexpended July 1, 1943 ----------------------------                                                $31, 681. 29
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941 ------------   $88, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943-------------50, 000. 00
                                                                                                            138, 000. 00

      Amount to be accounted for---------------------------                                                 169, 681. 29
Gross amount expended---__    -------------                                                                 139, 606. 01
      Balance unexpended June 30, 1944__                               -     --------                        30, 075. 28
Outstanding liabilities June 30, 1944                                -------------                               363. 48
     Balance available June 30, 1944_ - - ---------                                                          29, 711. 80
Amount allotted in July 1944- ____---------__                                                                30, 000. 00

           Amount available during fiscal year 1945----------------                                          59, 711. 80
Amount (estimated) required to be appropriated for completion of
existing project 1 ------------------                                                                      300, 000.00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_ ____---____          ___- -                                               25, 000. 00
  1Exclusive of available funds.

                                         14. BARNEGAT INLET, N. J.

  Location.-This inlet is located on the east coast of New Jersey,
about 50 miles south of Sandy Hook and 23 miles north of Little Egg
Harbor. It forms the main entrance to Barnegat Bay, the largest of
the bays on the New Jersey coast which are separated from the ocean
by narrow barrier beaches. The inlet lies between Island Beach on
the north and Long Beach on the south. (See U. S. Coast and Geo-
detic Survey Charts Nos. 825 and 1216.)
  Existing  project.-This provides for a channel 8 feet deep through
the inlet and 10 feet through the outer bar, the channel to be pro-
tected by two converging stone jetties extending to the 12-foot con-
tour in the ocean and spaced 1,000 feet apart at the outer ends. The
north jetty is 4,900 feet long and the south jetty 2,950 feet long, each
with pile and timber sheet pile inshore end sections 769 and 750 feet
long, respectively, and outshore end sections of all stone construction.
A channel of suitable hydraulic characteristics extends in a north-
westerly direction from the gorge in the inlet to Oyster Creek Channel
just northwest of Sunset Shoal, thence via Oyster Creek Channel to
deep water in the bay. The total length of the section included in
the project is about 4.5 miles. All depths refer to the plane of mean
low water. The mean tidal range at the inlet gorge is 2.7 feet and in
Barnegat Bay 0.5 foot. The extreme tidal range at the inlet is from
about 2 feet below mean low water to about 3 feet above mean high
water.
             RIVERS        AND HARBORS-PHILADELPHIA,                       PA., DISTRICT            307
   The estimate of cost for new work, revised in 1940, was $800,000,
including $300,000 contributed funds. The latest (1937) approved
estimate for annual cost of maintenance is $15,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                            Work authorized                               Documents


Aug. 30,1935      For 8-foot depth through the inlet to Oyster       Rivers and Harbors Committee Doe.
                   Creek Channel and across inner bar, 10-foot        No. 19, 73d Cong., 2d sess.1
                   depth through outer bar and for jetties.
Aug. 26,1937      For a channel of suitable hydraulic characteris-   Rivers and Harbors Committee Doe.
                   tics from the gorge to Oyster Creek Channel,        No. 85, 74th Cong., 2d sess.'
                   and thence to deep water in bay.


1 Contains latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are four docks or terminals located in
the inner harbor at Barnegat City which furnish adequate facilities
for the present commerce of the locality. All are private, three being
used for fishing interests.
   Operations and results during fiscal year.-Maintenance dredging
by contract in the inlet and disposing of the material in a dike on the
south side, in progress at the end of the previous fiscal year was com-
pleted September 14, 1943. There were removed 1,229,584 cubic yards
of material. The cost was $241,556.88. Stabilizing the sand dike by
contract was commenced October 20, 1943, and completed January 13,
1944. The work consisted of erecting 18,500 linear feet of sand fence
and spreading 123,700 square yards of salt hay. The cost was
$14,771.49.
   The lowering of 100 linear feet of the south jetty near its inshore
end, by contract, to facilitate the movement of sand to the beach at
Barnegat City, commenced January 10, 1944, was completed February
5, 1944. The cost was $2,440.40.
   Other costs were, surveys and channel examinations $15,614.78; and
the acquisition of easements for disposal areas, $1,929.69.
   The total cost of all work was $276,313.24 for maintenance. The
expenditures were $293,142.43.
   Condition at end of fiscal year.-The existing project was completed
in 1940. The controlling depths, at mean low water, in June 1944,
were as follows: From the Atlantic Ocean through the inlet, 10.5 feet;
thence through the main channel, 9.5 feet; and thence through Oyster
Creek Channel to Barnegat Bay, 6.4 feet.
   The costs under the existing project, excluding $300,000 contributed
funds expended for new work, were $448,849.09 for new work and
$477,006.14 for maintenance, a total of $925,855.23. The expenditures
were $923,419.85.
   Proposedoperations.-Itis proposed to apply the funds unexpended
on June 30, 1944, amounting to $5,880.15, as follows:
Accounts payable June 30, 1944_ ------------------                                            $2, 435. 38
Maintenance: Surveys and channel examination----------                     ....                3, 444. 77
           Total---------------------------------------------5,                                  880. 15
308           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

  No maintenance is contemplated during the fiscal year 1946 as it is
believed that channel conditions will be adequate to meet the needs
of commerce.
                                         Cost and financial summary
Cost of new work to June 30, 1944_ ________--------           1 $448, 849. 09
Cost of maintenance to June 30, 1944 ------------------------- 477, 006. 14
      Total cost of permanent work to June 30, 1944-----------925, 855. 23
Minus accounts payable June 30, 1944---    -------           -   2, 435. 38
      Net total expenditures_____----------_                                                                                1923, 419. 85
Unexpended balance June 30, 1944_5----------------                                                                  ----      -5,     880. 15
                                                      --------
            Total amount appropriated to June 30, 1944_                                                                     1 929, 300. 00

    Fi       year ending June 30            1940              1941                   1942                          1943               1944


Cost of new work- ..........
                     - -                 $348, 348. 66      $58, 094. 93   -......................
Cost of maintenance ..      ..     ...       .   ...          4, 276. 29          $6, 308. 95              $190, 107. 66            $276, 313. 24

               ---------------
         Total cost                       348, 348. 66       62, 371.22             6, 308. 95                 190, 107. 66          276, 313.24
Total expended ----------------           321, 042. 61      124, 205. 00             6, 618.05                 170, 843.09           293, 142. 43

Allotted__----        _------------140, 000.00               96, 800.00 -------                                135,000.00            257, 500.00


Balance unexpended July 1, 1943---    --------                                                                 _          -$41,522.          58
Amount allotted from War Department Civil
  Appropriation Act approved May 23, 1941                            ------               $230, 000. 00
Amount allotted from War Department Civil
  Appropriation Act approved Apr. 28, 1942 ......-                                               20, 000. 00
Amount allotted from War Department Civil
  Appropriation Act approved June 2, 1943-------                                                     7, 500. 00
                                                                                                                              257, 500. 00

       Amount to be accounted for                        ---------------------------                                          299, 022. 58
Gross amount expended_,.------
                           .----------                                                                                        293, 142. 43
       Balance unexpended June 30, 1944-----------------------
                                                 __5,                                                                                  880. 15
Outstanding liabilities June 30, 1944- ---------                                                                                    2, 435. 38
            Balance available June 30, 1944                  -------                          --
                                                                                              _.._------3,                            444. 77
1 In addition $300,000 expended from contributed funds for new work.

     15. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)
  The cost of work during the year was $39,700.23. The expenditures
were $40,417.33. The balance unexpended June 30, 1944, amounting
to $10,848.87, together with $45,000 allotted from the act of June 26,
1944, in July 1944, will be applied as needed during the fiscal-year
1945 to payment of expenses incurred under this heading.
   The sum of $60,000 can be profitably expended during the fiscal year
1946.
                                         Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                                          ---                  $1, 028, 251. 92
      Total cost of permanent work to June 30, 1944---------- 1, 028, 251. 92
Minus accounts payable June 30, 1944_---------               ---      921. 50
      Net total expenditures_ _-1,                                                                                            027, 330. 42
Unexpended balance June 30, 1944-                                                                                              10, 848. 87
            Total amount appropriated to June 30, 1944 -                                                   -               1, 038, 179. 29
                  RIVERS AND HARBORS-PHILADELPHIA,                                                                PA., DISTRICT                                   309
      Fiscal year ending June 30                           1940                   1941                 1942                      1943                      1944

Cost of new work ......................--------------...----------------------............                                                      ............----------------------------
Cost of maintenance___..........          $109, 950. 68     $71, 046. 67    $75, 588. 37                                       $55, 319. 88               $39, 700.   23
Total    expended....-----------------88, 596.19                                98, 025.09            70, 644. 08               62271.33                   40, 417. 3

Allotted _--------------......                            66, 360. 09           71, 246. 56           14, 645.19               111,014.87                     .......

Balance unexpended July 1, 1943_.....                              $51,266. 20
Gross amount expended_ __-_           ____---- --   --      --   -40,    417. 33
      Balance unexpended June 30, 1944 ---------------------        10, 848. 87
Outstanding liabilities June 30, 1944--------------- $921. 50
Amount covered by uncompleted contracts               4, 888. 90
                                                                      5, 810. 40
      Balance available June 30, 1944                                 5, 038. 47
Amount allotted in July, 1944- _______ ---     ----       ----      45, 000. 00
      Amount available during fiscal year 1945----------------      50, 038. 47

Amount that can be profitably expended in fiscal year.....
ending June 30, 1946, for maintenance 1                                                                                                           60, 000. 00
   1 Exclusive of available funds.

16. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES
                   ARE SUBMITTED
                                                                                  For last        Cost and expenditures to
                                                                                  full re-              June 30, 1944                               Estimated
                           Name of project                                       port,  see                                                           amount
                                                                                  Annual                                                            required to
                                                                                  Report          New work             Maintenance                   complete
                                                                                   for--


1. Delaware River, N. Y., N. J., and Pa., at or
      near mouth of Neversink River 1 2                                        1917                                                                       $61, 392. 50
2. Chester River, Pa.                          4 .......                       1931                  $6,    000.00               $650.26                   3, 600.00
3. Ice Harbor at Marcus Hook, Pa.           4 - - ..- - - - - - - - -__ - - - 1928                 208,     963.64             14, 336. 36                 (5)
4. Ice Harbor at New Castle, Del.                                              1898                224,     703.84        -                                (5)
5. Appoquinimink River, Del.3_                  ___-               -----      1931                   36,    973.35             40,   998.56                3, 000.00
6. Smyrna River, Del.3 -------------                               --          1943                198,     843.94            102,   277.01               20, 000.00
7. Murderkill River, Del--- ------------------                                1943                   37,    630.07            168,   140. 06              22, 400. 00
8. Leipsic River, Del. ...                                      __             1931                  36,    956.06             32.   167.94                (5)
9. Little River, Del.3    - - - -----------------......
                                   - - - - - - - - - -
                                                                       -       1942                   12,    015.86             46,   020.59                (5)
10. St. Jones River, Del.                                 .... ......          1940                 207,     102. 37            64,   537. 22             267, 500.00
11. Broadkill River, Del.3                                        ..--          1941                  68,    227.97            101,   723. 67               (5)
12. Harbor of Refuge, Delaware Bay, Del .......                                 1939            4, 987,      657.13            120,   455. 55              65, 000.00
13. Inland Waterway from Chincoteague Bay, Va.,
      to Delaware Bay, Del.2 7                                                 1939                 168,     411.88         842, 794. 40                    (5)
14. Rancocas River, N. J.3                      _______-                    -1942                     44,    500. 21          13, 090. 94                  36, 750.00
15. Cooper River, N. J.3................                       - .              1942                  33,    101.64          109, 997.17                    (5)
16. Woodbury Creek, N. J.3 -1940                                                                      27,    093.01           55, 405. 91                   (5)
17. Raccoon Creek, N. J.3 _1942                                                                       83,    664. 96         147, 548. 80                   (5)
18. Oldmans Creek, N. J.3                        _---_----_           --       1941                   31,    188.43           31, 676.20                   88, 800.00
19. Salem River, N. J.3-------                                    -             1943              0 107,     634.43           77, 278. 32              10 36, 000.00
20. Alloway Creek, N. J.3 ----------------------- 1931                                                21,    397. 73          33, 002. 27                  (5)
21. Cohansey River, N. J.3               -----------------------                1943                146,     755. 75         104, 691.66                   (5)
22. Maurice River, N. J.e-1941                                                                      143,     984.49          118, 558. 91                 120, 000.00
23. Dennis Creek, N. J.3                                                        1897                    4,   701.05-       -      -    -              -     (5)
24. Goshen Creek, N. J.2- 3          -------                              -    1905                   15,    358. 77               870.00                   (5)
25. Absecon Creek, N. J.3 ..........................---                        1941                   11,    934.96           67, 725. 34                   (1)
26. Little Egg Harbor, N. J.1 2------ _._..                                     (u1)                  15,    048.00                                         (5)
27. Tuckerton Creek, N.2 J.3 --------------------- 1941                                               60,    242. 16           127, 818. 96                 (5)
28. Double Creek, N. J. 3                                                    121912
                                                                             12..........................
                                                                                                        7,   800.00    .                   -                (5)
29. Toms River, N. J.313 ------------------------                              1940                   10,    050.00             19, 818.21                  (5)

   1 Abandonment recommended in H. Doc. No. 467, 69th Cong., 1st sess.
   2No commerce reported.
   3 Channel adequate for commerce.
   4 Harbor not now required by existing commerce.
   5 Completed.
   6 Awaiting local cooperation.

   7 Cost of maintaining bridges assumed by State of Delaware.
   8 In addition to $2,000 expended from contributed funds for maintenance.
   * Exclusive of $51,825.10 contributed by local interests.
   10In addition, local interests are required to contribute an equal amount.
   11Last appropriation for this project was in 1852. No information is at hand relative to work done.
   12 Maintenance assumed by local authorities as required by act authorizing the project.
   13 Modification of existing project recommended in H. Doc. No. 393, 77th Cong., 1st sess.
310            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                   1944

           17. PLANT ALLOTMENT, PHILADELPHIA, PA., DISTRICT
                                             Cost and financial summary
Undistributed costs June 30, 1944_-------                                                _                          _      $4, 250, 648. 71

Net total cost to June 30, 1944___                           4, 250, 648. 71
Plus accounts receivable June 30, 1944-----------------------339, 472. 59

      Gross total costs to June 30, 1944--------------------4,                                                                590, 121. 30
Minus accounts payable June 30, 1944_                                                                                         412, 643. 54
      Net total expenditures_ __---4,                                                                                         177, 477. 76
Unexpended balance June 30, 1944-------------------------1,                                                                   491, 477. 47
           Total amount appropriated to June 30, 1944-                                                                      5, 668, 955. 23

   Fiscal year ending June 30                   1940             1941                        1942                   1943               1944

Total expended-----------...........--..... $1,946,498. 70    $631, 529. 80 $2, 382, 319. 16                  $55,183. 44      -$3,   540, 955. 90
Allotted_----.---_.----                 -2, 173, 580. 02     3, 358, 929. 72- -_                       -      173, 719. 87        -3, 215, 730. 87



Balance unexpended July 1, 1943__                                                                                          $1, 166, 252. 44
Amount allotted from War Department Civil Appropriation
  Act approved Apr. 28, 1942___ - - ----------                                                                                660, 000.00

      Amount to be accounted for--      -                                                                                   1, 826, 252. 44
Deductions on account of revocation of allotment-------------                                                               3, 875, 730. 87
       Net amount to be accounted for__ -      -  -    -   -      -- 2, 049, 478. 43
Gross amount expended-     - -------             $9, 639, 976. 66
Less:
     Reimbursements collected $13, 165, 705. 93
     Receipts from sales             15, 226. 63
                                                 13, 180, 932. 56
                                                                  -- 3, 540, 955. 90
      Balance unexpended June 30, 1944_                                                                  _-                 1, 491, 477. 47
Outstanding liabilities June 30, 1944-_                        --------                       412, 643. 54
Amount covered by uncompleted contracts .-                                                    943, 591. 76
                                                                                                                            1, 356, 235. 30
      Balance available June 30, 1944-__                                                             _135,                         242. 17
Accounts receivable June 30, 1944_ ___ ---                                         ----                      ----             339, 472. 59
           Unobligated balance available June 30, 1944-----------                                                             474, 714. 76

lStatus of all investigations for navigation, called for by river and harbor acts and
                                   committee resolutions

                                                                        Date trans-
             Locality                    Authorization act               mitted to                   Document No.             R       ticommenda-
                                                                         Congress

Absecon Inlet, N. J'........ Rivers and Harbors                    ...............................
                               Committee resolu-
                               tion, Apr. 16, 1935.
Absecon Inlet, N. J., im- Commerce Committee                       ...................
provement and mainte-         resolution, May 12,
nance of Gardners Basin.      1941.
Absecon Inlet, N. J., im- Rivers and Harbors                       _................
provement of anchorage        Committee resolu-
area and small boat harbor    tion, Feb. 28,1941.
  on Clam Creek.
Barnegat Inlet, N. J........ Rivers and Harbors                     .
                               Committee resolu-
                               tion, Aug. 10, 1944.
                   FLOOD CONTROL----PHILADELPHIA,                              PA., DISTRICT               311
Status of all investigations for navigation, called for by river and harbor acts and
                          committee resolutions-Continued

                                                             Date trans-                           Recommenda-
          Locality                  Authorization act         mitted to            Document No.        tion
                                                              Congress

Delaware River, N. Y., Pa.,       Rivers and Harbors ...................
N. J., and Del., construe-         Committee resolu-
tion of dams in vicinity of        tion, Jan. 24,1939.
Tocks    Island, Belvedere
and Chestnut Hill, Pa.,
  (navigation and power).
Delaware River to Chesa-          Commerce Committee --------............
peake Bay, Del. and Md.,           resolution, Mar. 28,
Inland Waterway (with              1939.
particular   reference      to
bridges.)
Delaware River to Chesa-          Commerce Committee         Mar. 29, 1944_      (Restricted)-_.   Favorable.
peake Bay, Del. and Md.,          resolution, Mar. 28,
interim report.                    1939.
Schuylkill River, Pa., man-       Commerce Committee        .-------          .........
  ner and order of expendi-        resolution, May 20,
ture of $10,000,000 by Fed-        1944.
eral Government."
Townsend Inlet, N. J ..-..        Rivers and Harbors ...................
                                    Committee resolu-
                                    tion, May 18,1937.



                     18. MOUNT HOLLY, RANCOCAS CREEK, N. J.

   Location.-Mount Holly, the county seat of Burlington County,
N. J., is located on Rancocas Creek, 13 miles above its mouth. Ran-
cocas Creek empties into Delaware River opposite the upper limits of
Philadelphia, Pa. Its drainage area covers a large portion of Bur-
lington County. (See U. S. Geological Survey Chart, Mount Holly,
N. J., quadrangle.)
   Existing project.-This provides for the enlargement of sections
of the existing channel through the eastern and western sections of
Mount Holly; the construction of a controlled bypass channel to
divert floodwaters from that part of the existing channel which loops
through the center of the town; the construction of a new channel
extending upstream from the upper end of the bypass channel so as
to pass around the business section and rejoin the existing channel in
the eastern part of the town; 'and the construction of one highway
bridge and one railroad bridge across the new channel. The estimated
cost of the existing project is $350,000, exclusive of land and other
work to be provided by local interests.
   The existing project was authorized by the War Department Civil
Appropriation Act approved May 23, 1941, and by the Flood Control
Act approved August 18, 1941 (H. Doc. 128, 77th Cong., 1st sess.).
   Local cooperation.-Fully complied with.
   Operations and results during fiscal year.-The construction of a
reinforced concrete lined bypasschannel with a concrete weir; a rigid
frame reinforced concrete highway bridge and wing walls at Wash-
ington Street; reinforced concrete, closed-faced type crib walls and a
link chain fence, by contract, in progress at the end of the previous
fiscal year, was completed. The cost was $20,640.70.
   Other contract costs in connection with new work on the project
were $5,305.51 for the construction of a railroad bridge over the new
cut-off chahnel completed during the previous fiscal year; repairing
the side slope of the bypass channel damaged by flood during con-
struction, $14,891.56; constructing drainage facilities at Washington
312           REPORT OF CHIEF OF ENGINEERS,                                            U. S. ARMY,                       1944

Street Bridge, $15,942.26; and removing shoal in stream near the
downstream end of the bypass channel, $1,227.74. In addition, road
surfacing at the ends of Washington Street Bridge was accomplished
by hired labor at a cost of $91.80.
   The total cost of all work was $58,099.57 for new work. The ex-
penditures were $72,613.96.
   Condition at end of fiscal year.-The existing project is completed.
It was accepted by and turned over to the Township Committee of
Mount Holly Township for maintenance on June 22, 1944. The costs
and expenditures under the existing project were $282,655.05.
   Proposed operations.-None. The project is completed. The bal-
ance unexpended on June 30, 1944, amounting to $7,344.95, was re-
voked in August 1944.

                                           Cost and financial summary
Cost of new work to June 30, 1944-                                                                                         $282, 655. 05
Cost of maintenance 'to June 30, 1944
           Total cost of permanent work to June 30, 1944------------                                                           282, 655. 05
Net total expenditures_------------                                                                   ----                     282, 655. 05
Unexpended balance June 30, 1944_                                  ---------------                                               7, 344. 95

           Total amount appropriated to June 30, 1944                                   --------------                         290, 000. 00


    Fiscal year ending June 30                     1940                   1941           1942                    1943                 1944

Cost of new work-        .... ____----------                             $2, 485.12    $28, 858. 05          $193, 212.31            $58,099.57
Cost of maintenance...-----------------.. .           .      .      .       .    .----------------           -          ----     -   -------

Total expended ............                                                   748.07
                                               ....------------------------------       12, 993 90            196, 299.12             72, 613.96

Allotted      --------------------------------
             ........                                                   350, 000.00-    ..            ..            ..            -60, 000.00


Balance unexpended July 1, 1943---        ----------                                                                       $139, 958. 91
Deductions on account of revocation of allotment----                                                                         60, 000. 00
      Net amount to be accounted for__-- --------                                                                               79, 958. 91
Gross amount expended---
                       __     _--------------72,                                                                                    613. 96
     Balance unexpeided June 30, 1944__      -   --------                                                                        7, 344. 95
Amount revoked in August 1944__- -   -----------                                                                                 7, 344. 95

19. PRELIMINARY EXAMINATIONS, SURVEYS,                                                          AND              CONTINGENCIES
                    FOR FLOOD CONTROL

  The cost of work during the year was $89,046.37. The expenditures
were $83,595.33. The balance unexpended June 30, 1944, amounting
to $37,621.76, plus an additional allotment of $27,000 made in July
1944, will be applied'as needed during the fiscal year 1945 to payment
of expenses incurred under this heading.
  The sum of $20,000 can be profitably expended during the fiscal year
1946.
                   FLOOD CONTROI---PHILADELPHIA, PA., DISTRICT                                                                 313
                                            Cost and financial summary
Cost of new work to June 30, 1944      -----------------------------------
Cost of maintenance to June 30 1944_ -    -------- __         -$139,  429. 28

      Total cost of permanent work to June 30, 1944------------                                                        139, 429. 28
Minus accounts payable June 30, 1944_    _____----.-------5,                                                                451. 04

      Net total expenditures -------------------------------                                                           133, 978. 24
TUnexpended balance June 30, 1944--    -   ---------------                                                              37, 621. 76

          Total amount appropriated to June 30, 1944--------------                                                     171,600. 00

    Fiscal year ending June 30                  1940             1941              1942               1943                  1944

Cost of new work-
                    ....--------.....
Cost of maintenance----                       $16, 595. 99      $5, 219. 17       $8, 995. 78             -$6.    00       $89, 046.37

Total expended.......                            17, 517.06
                             ......-----------------             5, 272.84         9,885. 60 __                   "         83, 595. 33
Allotted-......    .------   -----             13,100.00        17, 000. 00   --------------         18, 000. 00           100, 000.00


Balance unexpended July 1, 1943_.                                                                                      $21, 217. 09
Amount allotted from War Department Civil
  Appropriation Act approved Apr. 28, 1942 $35, 000. 00
Amount allotted from War Department Civil
  Appropriation Act approved June 24. 1940_ 65. 000. 00
                                                                                                                       100, 000. 00

      Amount to be accounted for       --------------------------                                                      121, 217. 09
Gross amount expended-__ --    ---------------                                                                          83, 595. 33
       Balance unexpended June 30, 1944_                                - --------                                      37, 621. 76
Outstanding liabilities June 30, 1944_ -                                 ------                           -      --      5, 451. 04
     Balance available June 30, 1944-                               - --------                                          32, 170. 72
Amount allotted in July 1944_ ----------                                                           ----                 27, 000. 00

          Amount available during fiscal year 1945 -----------------                                                    59, 170. 72
Amount that can be profitably expended in fiscal year ending
       June 30, 1946, for maintenance 1___-           ---- __                                                           20, 000. 00
  1 Exclusive of available funds.

Status of all investigations for flood control called for by flood control acts and
                               committee resolutions

                                                                    Date trans-
            Locality                    Authorization act            mitted to             Document No.                Recommenda-
                                                                     Congress                                              tion

Delaware River and tribu-             Flood Control Act,           Aug. 10, 1943 ..-----------.......                  Unfavorable.
taries, in vicinity of                 Aug. 11, 1939.
  Morrisville,          Bucks
County, Pa.
Delaware River, N. Y., Pa.,           Rivers and Harbors ........                    ...........
N. J., and Del., construc-             Committee resolu-
tion of dams in vicinity               tion, Jan. 24, 1939.
  of Tocks Island, Belve-
dere and Chestnut Hill,
Pa. (navigation and
power).
Lackawaxen      River and             Flood Control Comn-_.................
tributaries, Pennsylvania,             mittee resolution,
  in vincity of Honesdale,              Oct. 8, 1942.
  Hawley, Prompton, and
  Seeleyville, Wayne
  County, Pa.
Lehigh River, Pa., in vicin-          Flood Control Comn- ..............................
  ity of Bethlehem, Allen-             mittee resolution,
  town. and Easton, Pa.                 Oct. 20, 1942.
314     REPORT OF CHIEF OF ENGINEERS,              U. S. ARMY,     1944

IMPROVEMENT OF RIVERS AND HARBORS                                      IN     THE
          BALTIMORE, MD., DISTRICT
  This district comprises central southern Pennsylvania, eastern
Maryland, southwestern Delaware, and eastern Virginia, embracing
Chesapeake Bay and its tributaries north of Cove Point, Md., on the
western shore of the bay, and Onancock River, Va., on the eastern
shore, and the watersheds tributary to the Atlantic Ocean between
the south boundary of Delaware and a point north of White Creek and
Gargathy Inlet on the Atlantic coast. It includes the drainage basin
of the Susquehanna River to the south side of the watershed of Shamo-
kin Creek, Pa.
  District engineer: Col. Oscar J. Pool, Corps of Engineers.
  Division engineer: Col. Clark Kittrell, Corps of Engineers, to Sep-
tember 30, 1943; Col. G. J. Zimmerman, Corps of Engineers, acting
division engineer, to October 25, 1943; Col. Earl E. Gesler, Corps of
Engineers, since that date.
                                  IMPROVEMENTS

             Navigation                           Navigation-Continued
                                   Page                                        Page
1. Baltimore Harbor and Chan-            11. Other navigation projects for
      nels, Md                      314         which no estimates are
2. Chester River, Md __..          318         submitted _.                   331
3. Pocomoke River, Md -.           320   12. Plant allotment------------      332
4. Twitch Cove and Big Thor-
      oughfare River, Md ...        322
5. Starlings Creek, Va --.-.       323                Flood control
6. Tangier Channel, Va..-          324
7. Waterway on the coast of            13. York, Codorus Creek, Pa            332
      Virginia -_                   325 14. Harrisburg, Pa                     335
8. Ocean City Harbor and In-           15. Preliminary    examinations,
      let and Sinepuxent Bay,                 surveys, and contingencies
      Md _ .-                       327       for flood control----            337
9. Fishing Creek, Md .   -         329 16. Other flood-control projects
10. Examinations, surveys, and                for which no estimates are
      contingencies (general) -     330       submitted---------------         338

             1. BALTIMORE HARBOR AND CHANNELS, MD.
   Location.-Baltimore Harbor is located along the lower 14 miles of
the Patapsco River. Patapsco River is formed by the junction of the
North and South Branches, both of which rise in central Maryland.
It is about 65 miles long and flows in a general southeasterly direction.
 (See U. S. Coast and Geodetic Survey Chart No. 549.)
   Previous projects.-PatapscoRiver: The original project was dated
July 4, 1836.   Modifications were contained in the River and Harbor
Acts of August 30, 1852; June 10, 1872; March 3, 1881; June 3, 1896;
March 3, 1905; March 3, 1909; February 27, 1911; and March 4, 1913.
   Middle Branch: The original project was dated June 3, 1896.
   Curtis Bay: The original project was dated July 15, 1892. It was
modified by the River and Harbor Act of June 13, 1902.
   York Spit: The original project was dated March 3,1905.
   For further details see pages 1787 and 1788 of the Annual Report
for 1915, and page 389 of the Annual Report for 1932.
   Eisting project.-This provides for: (a) A main channel between
Cape Charles, Va., and Fort McHenry, Baltimore, Md., with dimen-
sions as follows: 37 feet deep and 1,000 feet wide between the curves
of 37-foot depth in Chesapeake Bay opposite York Spit, a distance of
                  RIVERS     AND      HARBORS-BALTIMORE,                     MD.,    DISTRICT              315
about 4 miles (under jurisdiction of the Norfolk, Va., district); 37
feet deep and a general width of 600 feet from the 37-foot curve in
Chesapeake Bay at the entrance to the Craighill section to the west
side of the main private channel to Sparrows Point, a distance of
about 121/2 miles, and thence 35 feet deep and 600 feet wide to Fort
McHenry, a distance of about 71/2 miles; (b) for branch channels with
dimensions as follows: 35 feet deep and 400 feet wide from the main
channel to head of Curtis Bay, a distance of about 21/5 miles; 35 feet
deep and 400 feet wide from the main channel at Fort McHenry to
Ferry Bar, and thence 27 feet deep and 250 feet wide to the Western
Maryland Railway bridge, a total distance of about 31/8 miles; (c) for
widening the angle between the Fort McHenry and Ferry Bar sec-
tions; (d) for widening at the approaches and bends and for anchor-
ages and turning basins, as approximately shown on the maps accom-
panying Rivers and Harbors Committee Document No. 11, Seventieth
Congress, first session, and House Document No. 29, Seventy-first Con-
gress, first session; (e) it is further provided that as rapidly as the city
of Baltimore, at its own expense, extends the 35-foot depth into the
Northwest Branch (inner harbor) the United States shall take over
the maintenance of that depth; (f) and a channel 2 feet deep and
generally 200 feet wide from the 22-foot depth curve in Curtis Creek
immediately below the Pennington Avenue bridge; 18 feet over an
irregular area of about 3 acres at the head and adjacent to the 22-foot
channel; a depth of 15 feet for a general width of 450 feet from the
head of the 22-foot channel to the upper end of the marginal wharf
of the United States ordnance depot. All depths refer to mean low
water. The mean range of the tide in the upper sections of the harbor
is a little more than 1 foot under ordinary conditions, with an extreme
range of 12.8 feet. In the York Spit Channel these ranges are 2.5 and
3.3 feet, respectively.
   The estimate of cost for new work, revised in 1942, is $4,368,500,
exclusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $164,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                    Documents


Mar. 3,1905        Main channel 35 feet deep and 600 feet wide           H. Doc. No. 186, 57th Cong., 2d sess.
                     throughout.
Mar.     3,1909    Anchorage basin near intersection of Fort Mc-
                    Henry and Curtis Bay Channels (within origi-
                    nal limit of cost authorized by act of Mar. 2,
                    1907).
Feb. 27,1911       Width increased at entrances and bends (increase
                    to be made within the limit of original estimate).
Aug. 8, 1917       Branch channel 35 feet deep to head of Curtis Bay,    H. Doc. No. 799, 64th Cong., 1st sess.
                    and one 35 feet deep and 400 feet wide into the
                    Southwest Branch of the Patapsco River to a
                    point near Ferry Bar, and 27 feet deep and 250
                    feet wide to Western Maryland Ry. bridge,
                    widened at approaches and bends, and with
                    anchorage and turning basins. Inclusion of
                    Patapsco River and tributaries into 1 project
                   Sfor Baltimore Harbor.
Jan. 21,1927       Change in location of the anchorage near upper
                    end of the Fort McHenry Channel.
316           REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY,           1944


       Acts                        Work authorized                                     Documents

July     3, 1930   Increased anchorage facilities------------..... -----...............
                                                                                 Rivers and Harbors Committee Doc.
                                                                                                           1
                                                                           No. 11, 70th Cong., 1st sess.
    Do.            For 37-foot depth in that portion of channel to       H. Dec. No. 29, 71st Cong., 1st sess.'
                    Baltimore lying between the 37-foot curve near
                     Baltimore Light to the Sparrows Point entrance
                    channel; widening the angle between Fort
                    McHenry and Ferry Bar sections; and for width
                    of 400 feet in the Curtis Bay section.
Oct. 17,1940       For the 22-, 18-, and 15-foot channels in Curtis      Adopted as a national defense project
                     Creek from the 22-foot depth below Pennington        (no printed report).
                    Ave. Bridge to the upper end of the marginal
                    wharf of the United States ordnance depot.

  I Contain latest published maps.


   Recommended modifications of project.--Modification of the exist-
ing project was recommended by the Chief of Engineers in a report
requested by Rivers and Harbors Committee resolutions adopted Jan-
uary 11, 1932, and August 21, 1937, and River and Harbor Acts ap-
proved August 26, 1937, and June 20, 1938; and transmitted to Con-
gress by the Secretary of War March 11, 1943.
   Local cooperation.-The River and Harbor Act of August 8, 1917,
required that on all new work under the project approved by that act,
except the channel into Curtis Bay, improvement by the United States
is made conditional upon local interests providing, whenever required
by the Chief of Engineers, free of cost to the United 'States, suitable
areas behind bulkheads or other revetment, satisfactory to the district
engineer, in which the dredged material may be deposited. This con-
dition has been met as far as the channel has been completed.
   The River and Harbor Act of July 3, 1930, provided for increased
anchorage facilities subject to the provisions that no work shall be
started on the area therein recommended until local interests have
provided suitable disposal areas satisfactory to the district engineer
alongside of bulkheads behind which said interests will agree to pump
the material without delay to the Government work; or, in lieu of
the above requirement, agree to contribute the sum of 5 cents per
cubic yard, scow measure, to cover the additional cost to the United
States for disposal of the material on its oin dumping area. This
condition has been met.
   Terminal facilities.-The total length of developed water front in
Baltimore Harbor, measured along the established bulkhead line, is
about 27 miles. Extensive areas remain which are available for fur-
ther development. The existing terminal facilities include wharves,
piers, grain elevators, coal and ore piers, storage and bunkering facili-
ties for fuel oil, terminal warehouses, marine railways, drydocks, and
shipyards.
   The State legislature has authorized the city of Baltimore to incur
an indebtedness of $50,000,000 for the development of the port. The
Port Development Commission, which is charged with administration
under this authorization, has completed an $8,500,000 terminal pier at
Port Covington. For further details, see page 391, Annual Report
for 1932.
   Operations and results during fiscal year.-Maintenance dredging
for restoration of project depth for a width of 800 feet in the angle
                  RIVERS           AND            IHARBORS-BALTIMORE,                          MD.,       DISTRICT                  317
sections of the channel was effected by the U. S. hopper dredge
Navesink from February 1, 1944, to May 31, 1944, when operations
were completed and the dredge was returned to the New York dis-
trict. The yardage removed and deposited on the Government dump
in Chesapeake Bay was as follows: Brewerton-Fort McHenry angle,
177,897 cubic yards of material (place measure); Cutoff-Brewerton
angle, 299,232 cubic yards of material (place measure); and the
Craighill-Cutoff angle, 585,003 cubic yards of material (place mea-
sure); a total of 1,062,132 cubic yards (place measure). The total
costs, all for maintenance, were $189,061.67. The total expenditures
were $160,803.03.
   Condition at end of fiscal year.-The existing project, excluding
York Spit Channel, which is under the jurisdiction of the Norfolk
district, was 74 percent complete.
   The work remaining to be done, excluding the York Spit Channel,
is completion of the Ferry Bar section from Port Covington entrance
channel to Ferry Bar, and the Spring Garden section, including turn-
ing basin from Ferry Bar to Western Maryland Railway bridge.
   The controlling dimensions were as follows:

                                          Section                                          Depth      Width               Date
                                                                                           (feet)     (feet)           ascertained


Craighill Entrance       ---------------------------------------
                             .....                                                           37             600     November 1942.
Craighill-.   ..__-.-... ......-....-....-................                                   37             440     April 1942.
Craighill Cutoff angle--------------              -----------------------                    37             800     April 1944.
Cutoff--                                                                                     37             450     January 1943.
Cutoff Brewerton angle -------------------------------------                                 37             800     May 1944.
Brewerton, to Sparrows Point------------------------------37                                                600     May 1942.
Brewerton, above Sparrows Point---              -----------------------                      35             600     April 1942.
Brewerton-Fort McHenry angle------_               -----------------------                    35             800     May 1944.
Fort McHenry       ------------------------------------------                                35             600     September 1943.
Curtis Bay ..- .....       ......-...              ............. .....                       35             400     December 1939.
Ferry Bar, to Western Maryland Ry.piers---------------------35                                              400     May 1939.
Ferry Bar, to Ferry Bar-             --     .-        .-   ----   -   -       ..-    -       20.7           250     August 1938.
Ferry Bar, to Hanover Street Bridge                         ........                         24. 5
                                                                            ..-------------------------     250         Do.
Ferry Bar, to old Sou hwest Baltimore Channel ----------------                               17. 9          100     January 1928.
Quarantine anchorage    ------------------------------------                                 35             600     March 1939.
Fort McHenry anchorage                           ..   .....                                  35             400
                                                                            ...----------------------------------       Do.
Riverview anchorage ..............................-------------------------------------.     35           1,500     April 1942.
Curtis Creek:
     Approach channel       .------------------------------------                            22             200 July 1941.
     Southerly anchorage area -------------------------------                                15             450     Do.
     Easterly anchorage area--------------------------------                                 18             320     Do.


  The total cost under the existing project was $7,799,095.88, of which
$3,258,195.30 was for new work and $4,540,900.58 for maintenance.
The total expenditures were $7,768,385.70.
  Proposed operations.-The unexpended balance July 1,1944, $72,-
071.06, together with $140,000 allotted in July 1944, plus the accounts
receivable, $3,217.61, a total of $215,288.67, will be applied as follows:
Accounts payable, June 30, 1944----------------------------             $33, 927. 79
Maintenance:
    Dredging in the Craighill section to restore project depth of 37
      feet at mean low water for full project width of 600 feet,
      Jan. 1, 1945, to June 30, 1945------------                         60, 000. 00
    Dredging in the Cutoff section to restore project depth of 37
      feet at mean low water for full project width of 600 feet, Jan.
      1, 1945, to June 30, 1945_ _-----------                            77, 000. 00
    Dredging to remove small shoals that have formed in various
      other sections to restore project depth for 600-foot width in
      straight sections and 800-foot width in the angles, Jan. 1, 1945,
      to June 30, 1945 .                                                 27, 000. 00
    Condition surveys of various sections of the channel, Sept. 1,
      1944, to June 30, 1945- ------------------                          17, 360. 88
318           REPORT OF CHIEF OF ENGINEERS, U.                                    S. ARMY,              1944

  This maintenance will be done with United States Government
plant and hired labor.
  The additional sum of $30,000 can be profitably expended during
the fiscal year 1946 for making condition surveys and maps of the
entire Baltimore Harbor and Channels, Md., project.
                                         Cost and financial summary
Cost of new work to June 30, 1944 ....-                                                           $12, 022, 198. 70
Cost of maintenance to June 30, 1944 ----------------------                                             4, 940, 702. 35

       Total cost of permanent work to June 30, 1944----                                                16, 962, 901. 05
Plus accounts receivable June 30, 1944 -----------------------                                                3, 217. 61
      Gross total costs to June 30, 1944---- ---------------                                            16, 966, 118. 66
Minus accounts payable June 30, 1944----- ----------------                                                   33, 927. 79
     Net total expenditures_-----------------------------                                               16, 932, 190. 87
UnexpendedbalanceJune30, 1944-------------------------                                                       72, 071. 06
           Total amount appropriated to June 30, 1944---                                     -17,          004, 261. 93

    Fiscal year ending June 30                  1940            1941           1942           1943               1944

Cost of new work- ...............               .        ..   $13, 881.91    $29, 075.89   -- -     -
Cost of maintenance-----....----.. ---- --.....$164,931.32    169, 643.72     13, 669.53   $194, 281.60        $189, 061. 67
       Total cost------. ---------           164, 931. 32     183, 525.63     42, 745.42    194, 281.60         189, 061. 67
Total expended----------------167, 714. 64                    162, 838.16     50, 641.81    202, 030.30         160, 803.03
Allotted ---------------------               250, 000.00       89, 738. 64   100,000.00     129,957.80         -25,000.00


Balance unexpended July 1, 1943---------------------------                                                $257, 874. 09
Deductions on account of revocation of allotment------------                                                25, 000. 00
       Net amount to be accounted for----------------------                                                232, 874. 09
Gross amount expended ---------------------     $160, 833. 03
Less reimbursements collected------------------        30. 00
                                                                                                           160, 803. 03
       Balance unexpended June 30, 1944---72,                                                                   071. 06
Outstanding liabilities June 30, 1944------ -------------------                                             34, 262. 74
      Balance available June 30, 1944----------------- ------                                               37, 808. 32
Accounts receivable June 30, 1944-------------------------- -3,                                                 217. 61
Unobligated balance available June 30, 1944------------ ----                                                41, 025. 93
      Amount allotted in July 1944------------------------                                                 140, 000. 00
           Amount available during fiscal year 1945--- -----------                                         181, 025. 93
Amount (estimated) required to be appropriated for completion
of existing project 1 2-   -    -         -        -1,                                                     139, 400. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 12-------------------------                                                  30, 000. 00
  I Exclusive of available funds.
  2 Exclusive of York Spit section.

                                            2. CHESTER RIVER, MD.
  Location.-Rises in Kent County, Del., flows in a generally south-
westerly direction, and empties into Chesapeake Bay. Its total length
is less than 50 miles. (See U. S. Coast and Geodetic Survey Chart
No. 78.)
         RIVERS AND     HARBORS--BALTIMORE,           MD., DISTRICT      319
   Previous projects.-The original project for the main river was
adopted by the River and Harbor Act of March 3, 1881. For further
details see page 333 of Annual Report for 1935.
   Existing project.-This provides for a channel 6 feet deep at mean
low water and 60 feet wide from Crumpton to Jones Landing, a dis-
tance of 61/4 miles, the lower end of the improved section being about
33 miles from the mouth of the river; and for a channel 7 feet deep
at mean low water and 100 feet wide from Chester River to Eastern
Bay through Kent Island Narrows. The mean range of tide is 2.4 feet
and the extreme range is 4 feet under ordinary conditions.
   The estimate of cost for new work, revised in 1945, is $26,000, ex-
clusive of the amount expended on previous projects. The latest (1922)
approved estimate for annual cost of maintenance from Crumpton to
Jones Landing is $1,200. The existing project was adopted by the
River and Harbor Acts of March 3, 1873, and September 19, 1890
 (H. Ex. Doc. No. 65, 51st Cong., 1st sess.). Maps of the locality are
printed in House Documents No. 797 and 1587, Sixty-third Congress,
second and third sessions, respectively.
   Terminal facilities.-Thereare two bulkhead wharves on the Chester
River section, in poor condition, with dockage room of 100 and 120
feet, and available depths of 2 and 6'feet, respectively. In Kent Island
Narrows there are eight timber pile wharves adjacent to crab and
oyster houses, in fair condition, aggregating approximately 700 lineal
feet of dockage, with available depths of from 3 to 13 feet. All are
privately owned and open to general public use and considered ade-
quate for existing commerce.
   Operationsand results during fiscal year.-Dredging by contract for
restoration of the project depth of 7 feet at mean low water for a
width of 75 feet in the Kent Island Narrows section of the project, was
commenced and completed during the year. A total of 37,261. cubic
yards of material was removed and deposited on authorized dumping
areas ashore. The total costs, all for maintenance, were $18,848.20.
The total expenditures were $18,902.95.
   Condition at end of fiscal year.-The existing project was about
78 percent complete and is in good condition. The work remaining
to be done to complete the project is to widen the channel from the
75-foot dredged width to the 100-foot project width in the Kent Island
Narrows section. The controlling depth at mean low water in the river
proper, November 1929, was 6 feet; and in the Kent Island Narrows
section was 7 feet, ascertained in August 1943. The total costs and
expenditures under the existing project were $98,911.68, of which $18,-
060.84, was for new work and $80,850.84 was for maintenance.
  Proposed operations.--No funds are available and no work is pro-
posed during the fiscal years 1945 and 1946.
                         Cost and financial summary
Cost of new work to June 30, 1944_                                $56, 102. 30
Cost of maintenance to June 30, 1944-------------------------      80, 850. 84

      Total cost of permanent work to June 30, 1944-      -       136, 953. 14
Net total expenditures_ _ _______-                                136, 953. 14
Total amount appropriated to June 30, 1944_ ____136,                   953. 14
320             REPORT OF CHIEF OF ENGINEERS,                                               U. S. ARMY,            1944


    Fiscal year ending June 30                               1940           1941              1942          1943                1944

Cost of new work ----------------------------                                $401.36---------------.                   -.

Cost of maintenance ....... ....------------..--------------..                361. 30   --------------       $383.56           $18, 848. 20
       Total cost------------------.................       ------------       762. 66                         383. 56           18, 848. 20

Total expended.............----------------            --------------         762. 66   ------------          328. 81           18,902. 95

Allotted.-----------------------$10, 000                                  -9, 237. 34          $18, 000 --------------           1,231. 76



Balance unexpended July 1, 1943_       -----------                                                                      $17, 671. 19
Amount allotted from War Department Civil Appropriation                                                       Act
  approved June 24, 1940-----------------------------                                                                        1,231. 76
      Amount to be accounted for----------------------------                                                                18, 902. 95
Gross amount expended ------------------------------------                                                                  18, 902. 95
Amount (estimated) required to be appropriated for completion of
existing project_---------------.                          --                                                               8, 000. 00

                                                       3. POCOMOKE RIVER, MD.

   Location.-This river is a tributary of Pocomoke Sound, an estuary
of and on the easterly side of Chesapeake Bay about 40 miles north
of Cape Charles, Va.
   Previous project.-The original project for Pocomoke River was
adopted June 18, 1878, and modified by the River and Harbor Act of
August 5, 1886. For further details see page 1789, Annual Report
for 1915, and page 385, Annual Report for 1938.
   Existing project.-This provides for a channel 7 feet deep and 100
feet wide from that depth in Pocomoke Sound through "The Muds"
to deep water in the river, and for a channel 9 feet deep at mean low
water and 100 to 130 feet wide from Shad Ianding to Snow Hill, a dis-
tance of about 41/3 miles. The mean range of tide is 2.5 feet and the
extreme tidal range is 3.7 feet under ordinary conditions.
   The estimated cost of new work, revised in 1935, was $165,000, exclu-
sive of amounts expended under previous projects. The latest (1935)
approved estimate of cost for annual maintenance is $10,000.
   The existing project was authorized by the following river and
harbor acts:

      Acts                                         Work authorized                                        Documents


June 3,1896             A 9-foot channel from Shad Landing to Snow Hill_                     Annual Report for 1895, p. 1167.
Aug. 30,1935            For a channel 7 feet deep and 100 feet wide from                     H. Doc. No. 227, 74th Cong., 1st sess.
                           Pocomoke Sound to Pocomoke River.                                   (Contains latest published map.)



  Recommended modifications of project.-Under date of July 5,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for extension of the channel above the
bridge at Snow Hill, with a depth of 9 feet and width of 100 feet,
widened to 150 feet to form a turning basin at the upper end, at an
estimated first cost of $8,500, with annual maintenance of $1,000, in
addition to that now required, subject to certain conditions of local
cooperation (H. Doc. No. 429, 76th Cong., 1st sess.).
             RIVERS AND            HARBORS-BALTIMORE,                                    MD., DISTRICT                             321
   Local cooperation.-Fullycomplied with except that local interests
are required to furnish spoil disposal areas and releases from damage
to oyster beds as needed for future maintenance.
    Terminal faeilities.-The present water fronts at Pocomoke City
and at Snow Hill consist of pile and timber bulkheads with earth
fills. Some have warehouses and factories with mechanical handling
facilities and rail sidings. Practically all are privately owned; most
of them are in bad repair. Any appreciable increase in commerce
at Pocomoke City would necessitate the construction of a new ter-
minal and the repair of existing terminals. Considerable land areas
are available for the development of additional terminals if and
when needed.
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was com-
pleted in 1938. The controlling depths at mean low water were 5.3
feet through "The Muds" at the mouth of the river, ascertained in
February 1944, and 9.0 feet in the section from Shad Landing to Snow
Hill, ascertained in April 1939. The total costs of the existing project
were $188,862.01, of which $161,457.83 was for new work and $27,-
404.18 was for maintenance. The total expenditures were $188,862.01.
   Proposed operations.-The unexpended balance July 1, 1944, $60,-
000, will be applied to maintenance, restoration of the channel through
"The Muds" section of the project by contract dredging, July 1 to
Dec. 31, 1944.
   The additional sum of $10,000 can be profitably expended for main-
tenance of the existing project during the fiscal year 1946.
                                    Cost and financial summary
Cost of new work to June 30, 1944___-- --------                                                                        $181, 957. 83
Cost of maintenance to June 30, 1944_-----                                                   --        __                27, 404. 18

        Total cost of permanent work to June 30, 1944-                                            --                 -209,      362. 01

Net total expenditures ------------------------------------                                                             209, 362. 01
Unexpended balance June 30, 1944---------------------------                                                              60, 000. 00

        Total amount appropriated to June 30, 1944                                --------                              269, 362. 01


   Fiscal year ending June 30            1940                 1941                    1942                   1943               1944

Cost of new work_
Cost of maintenance-------------        $1, 688. 73 --        ------         -------..                      .....               - -------

Total expended ------------------        2,040. 48 --        ------          -------------

Allotted_   --------------------- -16,348.01        -----.            -...        -     --             --       --                $60,000



Amount allotted from War Department Civil Appropriation Act
approved June 2, 1943-       --------------------                                                                      $60, 000. 00
Balance unexpended June 30, 1944                                                                                         60, 000. 00
Outstanding liabilities June 30, 1944 --           $8, 520. 00
Amount covered by uncompleted contracts -          51, 480. 00
                                                                                                                             60, 000. 00

Amount that can be profitably expended in fiscal year ending June
                           1 - - - -                -
30, 1946, for maintenance -                                                                                                 10, 000. 00
I Exclusive of available funds.
       61 6634-45-pt.       1, vol. 1        21
322           REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY,          1944

              4. TWITCH COVE AND BIG THOROUGHFARE RIVER, MD.
   Location.-This is a tidal waterway about 4 miles long traversing
Smiths Island, Md., in a southeasterly direction from Chesapeake Bay
on the west to Tangier Sound on the east. (See U. S. Coast and
Geodetic Survey Chart No. 78.)
   Existing project.-This provides for a channel 7 feet deep at mean
low water and 60 feet wide from Twitch Cove on Tangier Sound
through Big Thoroughfare River, thence through the canal at Ewell,
Md., thence through Levering Creek and Big Thoroughfare River to
the vicinity of Swan Point, thence of the same depth and 100 feet
wide through the .offshore bar to deep water in Chesapeake Bay, with
twin jetties at the entrance; and for a channel 4 feet deep and 25 feet
wide around the point between Big Thoroughfare River and Tylers
River. The mean range of tide is 1.7 feet, and the extreme tidal
range is 3 feet under ordti ary conditions.
   The estimate of cost for new work, revised in 1938, was $159,400.
The latest (1937) approved estimate for annual cost of maintenance
is $3,700.
   The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                    Documents


July 25, 1912     A channel 4 feet deep and 25 feet wide from Tangier   H. Doc. No. 285, 62d Cong., 2d sess.
                    Sound into Big Thoroughfare River, and one
                    of the same dimensions around the point be-
                    tween said river and Tylers River.
July     3,1930   A channel 5 feet deep at mean low water and 25        H. Doc. No. 313, 71st Cong., 2d sess.
                    feet wide from Twitch Cove on Tangier Sound
                    through Big Thoroughfare River to a point on
                    Levering Creek about 800 feet north of the
                   canal at Ewell, Md.
Aug. 30,1935      A channel 7 feet deep and 60 feet wide from Twitch    Rivers and Harbors Committee Doc.
                    Cove through Big Thoroughfare River to a              No. 67, 74th Cong., 1st sess.
                    point on Levering Creek about 800 feet north
                    of the canal at Ewell, Md.
June 20,1938      Present project dimensions of the main channel        Rivers and Harbors Committee Doc.
                   with twin jetties at the entrance.                     No. 49, 75th Cong., 2d sess. (Con-
                                                                          tains latest published maps.)



  Local cooperation.-Fullycomplied with except that local interests
are to furnish spoil disposal areas as needed for future maintenafice.
  Terminal facilities.-There are nine small open-pile wharves pri-
vately owned open to the general public use, which are considered
adequate for existing commerce.
  Operationsand results duringfiscal year.-Operations were confined
to payment of outstanding liabilities and completion of after dredg-
ing survey maps. The total costs, all for maintenance, were $172.83.
The total expenditures were $13,992.37.
   Condition at end of fiscal year.-The project was completed in
November 1940. The controlling depths at mean low water were as
follows: 7 feet from Tangier Sound to the branch channel to Tyler-
ton, ascertained in February 1937, thence 7 feet to Ewell, Md., in June
1943, thence 7 feet to Swan Point, thence 9 feet to deep water in
               RIVERS AND HARBORS                    BALTIMORE,                   MD., DISTRICT                      323
Chesapeake Bay, in June 1940 and 4 feet around the point between
Big Thoroughfare River and Tylers River, in January 1941. The
total costs and expenditures were $193,086.21, of which $164,174.53
was for new work and $28,911.68 was for maintenance.
  Proposed operations.-No funds are available for work in 1945.
The sum of $5,000 can be profitably expended in the fiscal year 1946
for condition survey and minor repairs to jetties in Chesapeake Bay.
                                      Cost and financial summary
Cost of new work to June 30, 1944__ -------------------------- $164, 174. 53
Cost of maintenance to June 30, 1944_-          - --     ____    28, 911. 68

       Total cost of permanent work to June 30, 1944-
Net total expenditures -.    ---------------------------------
                                                                                              -              193, 086. 21
                                                                                                             193, 086. 21
Total amount appropriated to June 30, 1944                    --------------                       -         193, 086. 21

   Fiscal year ending June 30            1940          1941                    1942             1943             1944


Cost of new work__      -       --    $59, 972. 99   $75, 801. 54
Cost of maintenance ........               487.84                              $221.07        $14, 729.35          $172.83

      Total cost__         __          60, 460. 83    75, 801.54                221.07         14, 729. 35          172.83

Total expended.-                       30, 605. 61    99, 656. 76   -,-.                        1,130.88         13, 992. 37

Alotted ____. _      _5,                   533. 77     -271.40             10,000.00            5,000. 00           123.25


Balance unexpended July 1, 1943 _-                            -            -             --                  $13, 869. 12
Amount allotted from War Department Civil Appropriation
Act approved June 24, 1940--------------------------------                                                      123. 25

      Amount to be accounted for---------------------                                                         13, 992. 37
Gross amount expended_ _------------------------------------13,                                                   992. 37
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance_--   --                  *-----
                                                         --                                                    5, 000.00

                                     5. STARLINGS CREEK, VA.

  Location.-Starlings Creek, about 1,500 feet long, is an estuary of
Pocomoke Sound at the southerly end of Saxis Island, Accomac
County, Va., about 11 miles southeasterly of Crisfield, Md. (See U. S.
Coast and Geodetic Survey Charts Nos. 1223 and 1224.)
   Existing project.-This provides for a channel 7 feet deep at mean
low water and 60 feet wide from that depth in Pocomoke Sound to
the mouth of Starlings Creek,.with a turning basin of the same depth
and 1,000 feet long inside the entrance, all essentially as shown on the
project map. The mean range of tide is 2.4 feet. The estimate of cost
for new work, made in 1935, was $27,000. The latest (1935) approved
estimate of cost for annual maintenance is $1,000. The existing project
was adopted by the River and Harbor Act of August 30, 1935 (Rivers
and Harbors Committee Doc. No. 46, 74th Cong., 1st sess.). This
document contains the latest published map.
  Local cooperation.-Fullycomplied with except that local interests
are to furnish spoil disposal areas as needed for future maintenance.
   Terminal facilities:-Bulkheadas required under local cooperation.
   Operationsand results duringfiscal year.-Operations were confined
to payment of outstanding liabilities and completion of after dredg-
324             REPORT OF                  CHIEF OF ENGINEERS,                                      U.      S.    ARMY,               1944

ing survey maps. The total costs, all for maintenance, were $640.09.
The total expenditures were $20,873.95.
  Condition at end of fiscal year.-The existing project was com-
pleted in 1937. The controlling depth, ascertained in June 1943, was
7 feet at mean low water in the channel and turning basin. The total
costs and expenditures were $38,053.72, of which $16,537.47 was for
new work and $21,516.25 was for maintenance.
  Proposed operations.-No funds are available and no work is pro-
posed during the fiscal years 1945 and 1946.
                                                   Cost and financial summary
Cost of new work to June 30, 1944_ _----------_$16,                                                                                                  537. 47
Cost of maintenance to June 30, 1944_             _                                                                   -__21,                         516. 25

       Total cost of permanent work to June 30, 1944     -                                                                        -            38, 053. 72
Net total expenditures_-                                                                                                                       38, 053. 72
Total amount appropriated to June 30, 1944        --------                                                                                     38, 053. 72

    Fiscal year ending June 30                           1940                      1941                 1942                   1943                  1944

C ost of new work - -- - - - -                  .-- - -             - .- -.-- .- -.                               . .     . .      . .     .    ..    . . .
Cost of maintenance...               ...           _$4.81                                                                $20, 871.35                   $640.09

Total expended------                        ----                          .....
                                                                --..................-........   .                                642. 30             20, 873.95

Allotted------------------------...................................---------------------                17, 500. 00            4,0.16.25


Balance unexpended Jul 1, 1943            -$20,                                                                                                      857. 70
Amount allotted from War Department Civil Appropriation Act
approved June 24, 1940_----------              ----                                                                                                   16. 25
            Amount to be accounted for_--                                                  ----------                                          20, 873. 95
Gross amount expended                               --               -------------                                                             20, 873. 95

                                            6. TANGIER CHANNEL, VA.

   Location.-This is a tidal channel about 1 mile long, extending
from Tangier Island, Va., in a northeasterly direction to deep water
in Tangier Sound, Chesapeake Bay. (See U. S. Coast and Geodetic
Survey Chart No. 1223.)
   Existing project.-This provides for a straight channel 7 feet deep
at mean low water and 60 feet wide from the 7-foot contour in Tan-
gier Sound to the town of Tangier with an anchorage basin adjacent
to the town 400 feet square and 7 feet deep. The length of the section
included in the project is 1 mile, its loiver end extending into Tangier
Sound. The mean range of tide is 1.7 feet, and the extreme.tidal range
is 4.7 feet under ordinary conditions. The estimate of cost for new
work revised in 1935 was $53,434. The latest (1935) approved esti-
mate for annual cost of maintenance is $1,500.
   The existing project was adopted by the River and Harbor Act of
March 2, 1919 (H. Doc. No. 107, 63d Cong., 1st sess.) ; the present
dimensions of the channel and anchorage were authorized by the Pub-
lic Works Administration January 3, 1934, and by the River and
Harbor Act of August 30, 1935 (Rivers and Harbors Committee Doc.
No. 51, 72d Cong., 2d sess.). This document contains the latest pub-
lished map.
   Recommended modifications of project.-Under date of January 23,
1941, the Chief of Engineers recommended modification of the existing
             RIVERS       AND HARBORS-BALTIMORE,                            MD., DISTRICT                      325
project so as to provide for a channel 8 feet deep at mean low water
and 100 feet wide from the 8-foot contour in Tangier Sound to day-
mark No. 4, and thence 8 feet deep and 60 feet wide to the town of
Tangier, at an estimated cost of $10,100, with an increase in present
annual maintenance cost of $750; subject to certain conditions of local
cooperation (H. Doc., No. 141, 77th Cong., 1st sess.).
   Local cooperation.-Fully complied with except that local interests
are to furnish spoil disposal areas as needed for future maintenance.
   Terminal facilities.-There are three bulkhead wharves having an
aggregate frontage of approximately 250 feet. These wharves are
open to all free of charge. Any considerable increase in commerce
would create a demand for additional facilities.
   Operations and results during fiscal year.-Operations were con-
fined to payment of outstanding liabilities and completion of after
dredging survey maps. The total costs, all for maintenance, were
$83.69. The total expenditures were $9,669.03.
   Condition at end of fiscal year.-The existing project was completed
in 1934. The controlling depth at mean low water is 7 feet, ascertained
in June 1943. The total costs and expenditures were $15,627.98 regu-
lar funds and $42,000 Public Works funds, a total of $57,627.98 for
new work and $49,567.85 regular funds for maintenance, a total of
$107,195.83.
   Propos&ed operations.-No funds are available and no work is pro-
posed during the fiscal years 1945 and 1946.
                                Cost and financial summary
Cost of new work to June 30, 1944___                                                                  $57, 627. 98
Cost of maintenance to June 30, 1944--                   --                      -     _____           49,567. 85
       Total cost of permanent work to June 30, 1944--------- --                                      107, 195. 83
Net total expenditures   _ ______                                                                     107, 195. 83
Total amount appropriated to June 30, 1944                            -----------------               107, 195. 83

   Fiscal year ending June 30      1940           1941                   1942            1943               1944

Cost of new work ......                                           -    --...........        .           .
Cost of maintenance                              .......
                                          ................. ...                 ..     $24, 994. 59            $83.69

Total expended ...                                                                      15,409.25           $9, 669.03

Allotted ....--------------------------------------------------------                   25,000.00                  78.28


Balance unexpended July 1, 1943 _-                  -----                                              $9 590. 75
Amount allotted from War Department Civil Appropriation Act
approved June 24, 1940_- ---------------------                                                             200. 00
      Amount to be accounted for-_      -------------                                                   9, 790. 75
Deductions on account of revocation of allotment                                                           121. 72
      Net amount to be accounted for__-                       -                 -_____                  9,669. 03
Gross amount expended-_ _---------                                                 -_____               9,669. 03

                     7. WATERWAY     ON THE COAST OF VIRGINIA

  Location.-This tidal waterway, which includes Cat River and
Bogues Bay, is a series of inland thoroughfares in the northeastern
part of Accomac County, Va., extending from Chincoteague Inlet
on the north to Assawaman Inlet on the south. (See U. S. Coast and
Geodetic Survey Chart No. 1221.)
326              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                 1944

   Existing project.-This provides for a channel 4 feet deep at mean
low water and 25 feet wide in Cat River, a distance of 2 miles, and
thence northward across Bogues Bay 50 feet wide for a further dis-
tance of about one-half mile. The mean range of tide is 3 feet. The
extreme range of tide is about 6 feet, due to storms. The estimate of
cost for new work, made in 1908, was $12,100. The latest (1908)
approved estimate for annual cost of maintenance is $1,200.
   The existing projet was adopted by the River and Harbor Act of
June 25, 1910 (H. Doc. No. 957, 60th Cong., 1st sess). The latest
published map is in the project document.
   Recommended modifcations of project.-Under date of April 5,
1939, the Chief of Engineers recommended the adoption of a project
to provide, in lieu of the improvements heretofore authorized for the
Waterway on the Coast of Virginia, an inland waterway 6 feet deep
and 60 feet wide from Chesapeake Bay to Chincoteague Bay, Va., at
an estimated first cost of $263,000, with annual maintenance of
$15,000 subject to certain conditions of local cooperation (H. Doc.
No. 268, 76th Cong., 1st sess.).
   Terminal facilities.-This waterway is a connecting tidal canal,
having no terminals or wharves, as none are required.
   Operations and results during fiscal year.-Operations were con-
fined to payment of outstanding liabilities and completion of after
dredging survey maps. The total costs, all for maintenance, were
$160.62. The total expenditures were $2,308.95.
   Conditionat end of fiscal year.-The existing project was completed
in 1912. The controlling depth, ascertained in May 1943, was 5 feet
at mean low water. The total costs and expenditures were $37,551.79,
of which $9,404.45 was for new work and $28,147.34 was for
maintenance.
   Proposed operations.-No funds are available and no work is pro-
posed for the fiscal years 1945 and 1946.
                                                     Cost and financial summary
Cost of new work to June 30, 1944                                                                                                $9, 404. 45
Cost of maintenance to June 30, 1944---                                                 -------                      _           28, 147. 34
       Total cost of permanent work to June 30, 1944--------                                                                _37, 551. 79
Net total expenditures-.                                                                                                         37, 551. 79
Total amount appropriated to June 30, 1944--------------                                                                         37, 551. 79


     Fiscal year ending June 30                          1940                   1941                    1942        1943             1944
Cost of new work ........... .                           . . .. . . . . . . . .
                                                    ......                                                 . . .. . . . . . . . . . . .
Cost of maintenance_-                              -........
                                        -----.............
                                                      . ...                       ...----------------             $16,184. 26          $160. 62
Total expended- ....
                   ------.......                          ---       ---------..                                    14, 035.93        2,308.95
Allotted------------------................................----------. --------------.          --------------      19, 700. 00      -3, 355.12


Balance unexpended July 1, 1943-                                                                                                 $5, 664. 07
Deductions on account of revocation of allotment---------                                                                          3,355. 12
             Gross amount expended -------------------------                                                                      2, 308. 95
                  RIVERS AND         HARBORS-BALTIMORE,                   MD.,    DISTRICT              327
   8. OCEAN CITY HARBOR AND INLET AND SINEPUXENT BAY, MD.

  Location.-Ocean City is on a barrier island between Sinepuxent
Bay and the Atlantic Ocean about 35 miles south of the entrance to
Delaware Bay. (See U. S. Coast and Geodetic Survey Chart No.
1220.)
  Existing project.-This provides for the construction of an inlet
between the Atlantic Ocean and Sinepuxent Bay, with a depth of
10 feet and width of 200 feet, protected by.jetties; a channel 6 feet
deep and 150 feet wide from the inlet to Green Point, and thence
100 feet wide into Chincoteague Bay; a channel 10 feet deep at mean
low water, 100 feet wide, and 3,000 feet long from the inlet channel
into the marsh area south of the railroad on the west side of Sine-
puxent Bay, with two turning basins of the same depth; and for a
channel 6 feet deep and 125 feet wide from the inlet channel to a
point opposite North Eighth Street in Ocean City, thence 75 feet
wide into Isle of Wight Bay.
  The estimate of cost for new work, revised in 1935, was $870,000,
including $500,000 contributed by local interests. The latest (1935)
approved estimate for annual cost of maintenance is $32,000. The
mean range of ocean tide is 3.4 feet.
  The existing project was authorized by the following river and
harbor acts:

     Acts                         Work authorized                                  Document   1

Aug. 30, 19352    Construction of an inlet between the Atlantic        Rivers and Harbors Committee Doc.
                   Ocean and Sinepuxent Bay, 10 feet deep and           No. 38, 72d Cong., 1st sess.
                   200 feet wide, protected by jetties, a channel 8
                    feet deep and 100 feet wide from the inlet to
                    Ocean City, 6 feet deep and 150 feet wide to
                    Green Point, and 100 feet wide into Chinco-
                    teague Bay.
Aug. 30, 1935 3   Modification providing a 10- by 100-foot channel     Rivers and Harbors Committee Doc.
                   from the inlet to the west side of the bay with      No. 60, 74th Cong., 1st sess.
                    2 turning basins, a channel 6 feet deep 125 feet
                    wide from the inlet channel to opposite North
                    8th St., Ocean City, and 75 feet wide into Isle
                    of Wight Bay.


  I Contains latest published maps.
  2 Included in Public Works Administration program Sept. 16, 1933.    The site chosen for the inlet under
this authorization was that opened just south of Ocean City by natural forces during a severe storm in
August 1933. This eliminated the necessity for an 8-foot channel from the inlet to Ocean City.
  3 Included in. Emergency Relief Program 1935.


  Local cooperation.-Fullycomplied with.
  Terminal facilities.-Numerous wharves and landings of pile and
timber construction are located along the bay and the marsh channel
at Ocean City.
  Operations and results during fiscal year.-Operations consisted of
drafting of survey maps showing the condition of the channel in Sine-
puxent Bay and Isle of Wight Bay. Maps were made from survey of
November 1942 to April 1943. Office studies for future maintenance
were made. The total costs, all for maintenance, were $2,317.14. The
total expenditures were $1,529.47.
328          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                      1944

   Conditionat end of fiscal year.-The existing project was completed
in 1936. The controlling depths at mean low water were 10 feet in the
inlet, ascertained in September 1940, thence 1.6 feet to the end of the
channel in Chincoteague Bay, ascertained in April 1943, and 8.3 feet
in the fishing harbor ascertained in September 1940, and 5 feet in the
channel to Isle of Wight Bay to a point opposite North Ninth Street,
thence 1 foot above mean low water to the end of the project in the
bay, ascertained in December 1942. The costs under the existing
project to June 30, 1944, have been $283,007.93 Public Works funds,
and $67,185.09 Emergency Relief funds, a total of $350,193.02 for new
work, and $166,975.82 regular funds for maintenance, a total of
$517,168.84. The total expenditures have been $283,007.93 Public
Works funds, and $67,185.09 Emergency Relief funds, a total of
$350,193.02 for new work, and $165,832.37 regular funds for mainten-
ance, a total of $516,025.39. In addition, $500,000 was expended from
contributed funds for new work.
   Proposed operations.-The unexpended balance July 1, 1944, of
$4,090.46, plus the additional amount of $33,000 allotted in July 1944,
a total of $37,090.46, will be applied as follows:
Accounts payable, June 3,0, 1944------------------------------$1,       143.               45
Maintenance:
    Condition surveys, and mapping of stone jetties, inlet channel,
      channel to commercial fish harbor, channel to Sinepuxent Bay
      and channel to Isle of Wight Bay. Work to be done by '
      Government plant and hired labor, July 1 to Sept. 30, 1944 .. 10, 747.               01
    Placing small stone and concrete at the inner end of the north
      jetty by hired labor, July 1, 1944, to June 30, 1945           5, 000.               00
    Replace the outer end of the steel sheet pile bulkhead at the
      north side of the inlet. Work to be done by contract, Aug. 1,
      1944, to June 30, 1945       ------------------------------
    Dredging to restore project dimensions in channel to commercial
                                                                     9,             9000. 00
      fish harbor, work to be done by contract, Aug. 1, 1944, to
      June 30, 1945--------------------------------                 11, 200.               00
   The additional sum of $32,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Condition surveys of channels and jetties, by hired labor, July 1,
      1945, to June 30, 1946          -----------------------                -$12, 000
    Dredging by contract to restore project dimensions in channel to
      commercial fish harbor, Sept. 1, 1945, to Oct. 31, 1945......             10, 000
    Minor repairs to rock jetties by hired labor, Sept. 1, 1945, to Oct. 31,
      1945_----                           --                                     5,000
    Repairs to stone riprap and steel sheet pile bulkhead by hired labor,
      Sept. 1, 1945, to Dec. 31, 1945---                                         5, 000

                                    Cost and financial summary
Cost of new work to June 30, 1944--                  _                     _ 1$350, 193. 02
Cost of maintenance to June 30, 1944                        -166,                   975. 82
      Total cost of permanent work to June 30, 1944--- --------                   517, 168. 84
Minus accounts payable June 30, 1944           - --      - -                        1, 143. 45
      Net total expenditures-_                  -                --   --      1   516, 025. 39
Unexpended balance June 30, 1944                         -       --
                                                    ---------------                 4090. 46
                                                                                    4,
          Total amount appropriated to June 30, 1944------ ------ 1520, 115. 85
1 In   addition, $500,000 contributed funds expended for new work.
                     RIVERS AND                     HARBORS-BALTIMORE,                          MD., DISTRICT                              329

    Fiscal year ending June 30                            1940             1941          1942                    1943                  1944


Cost of new work-                                                                                                         ...     ..      ...
Cost of maintenance                 -------------        $5,142.37    $12, 775.60               $2. 66          $9, 059. 09            $2, 317.14

Total expended ------------------                         6, 461.71    12, 655. 75               2. 66           8, 703. 31             1, 529. 47

Allotted -----------------------
             .        .      .                           28,000.00         5,800.00    -7,000.00               -33,700.00-----------


Balance unexpended July 1, 1943_                                             -          -                ---                    $5, 619. 93
Gross amount expended-                                                                                                           1, 529. 47

      Balance unexpended June 30, 1944__                                                 - -                                     4, 090. 46
Outstanding liabilities June 30, 1944_                                                             --           __               1, 237. 94

     Balance available June 30, 1944                                                        -                                    2, 852. 52
Amount allotted in July 1944-_ - _33,                                                                                               000. 00

             Amount available during fiscal year 1945-                                  -                  - - --               35, 852. 52

Amount that can be profitably expended in fiscal year ending June
    30, 1946 for maintenance                         2                --          --                            _ __            32, 000. 00
  2 Exclusive of available funds.

                                                    9. FISHING CREEK, MD.

   Location.-This creek is a narrow winding tidal stream which enters
Chesapeake Bay from the west 56 miles south of Baltimore and about
26 miles south, of Annapolis, Md. (See U. S. Coast and Geodetic.
Survey Chart No. 1225.)
   Existing project.-This provides for a channel 7 feet deep with
widths of 100 feet and 60 feet from deep water in Chesapeake Bay
to an anchorage of the same depth, 120 feet wide and 400 feet long,
located in the marsh 500 feet above the mouth of the creek and for
twin stone jetties at the entrance. The mean tidal range is about
1 foot.
   The estimate of cost of new work made in 1937 was $97,000. The
latest (1937) approved estimate of cost for annual maintenance is
$2,500.
   The existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. No. 241, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-Fullycomplied with except that local interests
are to furnish spoil disposal areas as needed for future maintenance.
   Terminal facilities.-None.
   Operationsand resultsduring fiscal year.-Dredging by contract for
restoration of the project was commenced and completed during the
year. A total of 35,005 cubic yards of material was removed and
deposited on authorized dumping areas ashore. The total costs, all
for maintenance were $17,067.49.          The total expenditures were
$17,516.99.
   Condition at end of fiscal year.-The existing project was completed
in 1942. The controlling depth, ascertained in May 1943, was 6.5 feet
at mean low water in the channel and 7 feet at mean low water in the
anchorage basin. The total costs and expenditures were $128,788.20,
of which $111,242.07 was for new work and $17,546.13 for maintenance.
   Proposed operations.-No funds are available.
   The additional sum of $15,000 can be profitably expended during
the fiscal year 1946 in the restoration of the project.
330               REPORT OF CHIEF OF ENGINEERS,                                               U. S. ARMY, .1944

                                               Cost and financial summary
Cost of new work to June 30, 1944-__- -                                           -------                                   $111, 242. 07
Cost of maintenance to June 30, 1944_ __-                                             ----                    ____             17, 546. 13
      Total cost of permanent work to June 30, 1944                                                -128,                              788. 20
Net total expenditures_-----------------__-____                                                                                  128, 788. 20
Total amount appropriated to June 30, 1944-----------------..                                                                    128, 788. 20

     Fiscal year ending June 30                      1940                 1941                  1942                1943                    1944


Cost of new work               ...                        $2. 68         $17, 594. 39         $82, 719. 85        $10, 702. 59    -
Cost of maintenance__ .         -....
                                  __           -. --...    ....     ............                    .                  478. 64             $17, 067. 49
        Total cost ...                   .                  2.68        17, 594.39             82, 719.85          11, 181.23               17, 067.49

Total expended      ------------------                      2. 68         4, 254. 98           74, 795. 39         31, 995. 60              17, 516. 99
Allotted_----._       --------------------..                            58, 550. 00            53, 400. 00         15, 316. 07               -477. 87


Balance unexpended July 1, 1943_---------               ---      $17, 994. 86
Deductions on account of revocation of allotment----------------      477. 87

       Net amount to be accounted for-----------------                                                                            17, 516. 99
Gross amount expended_- --       ------                -_____                                                                     17, 516 99
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance__----               - ---         -____                                                                15, 000.00
      10. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)
   The cost of work during the year amounted to $30,673.62. The
expenditures were $29,791.34. The balance. unexpended July 1, 1944,
$19,000.72, plus an allotment of $24,000 made in July 1944, a total of
$43,000.72, will be applied as needed during the fiscal year 1945 to
payment of expenses incurred under this heading.
   The additional sum of $30,000 can be profitably expended during the
fiscal year 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_ -                                          ------                      __             $450, 752. 23
      Total cost of permanent work to June 30, 1944                                                -450,                                   752. 23
Undistributed costs June 30, 1944_---------                                                                           --               -     4. 61
      Net total cost to June 30, 1944_-----                                                               -____                  450, 756. 84
Minus accounts payable June 30, 1944_-----                                                               --  __                    4, 114. 92
                           ---------------------------
      Net total expenditures_                                                                                                    446, 641.92
Unexpended balance June 30, 1944 ---------------------                                                                            19, 000. 72
             Total amount appropriated to June 30, 1944                                       --------                           465, 642. 64

    Fiscal year ending June 30                       1940                 1941                  1942                1943                    1944

Cost of new work .-
Cost of maintenance------
                  .
                                                 --.-- . . - . - .-..
                          -- ---........- $45, 240. 38
                                                                  - --..
                                                          $25, 368. 11
                                                                                          .      . . . . . . . . . .
                                                                                              $27, 315.13  $23,968.68
                                                                                                                                   .        --. . .
                                                                                                                                           $30,673.62
Total expended .....----------------               48, 553. 66          24, 317. 53            27, 218. 66         23, 031.04               29, 791.34
Allotted----------------------                     47, 301.99           14, 000.00--. --.                              000.00
                                                                                                                     ,50,

Balance unexpended July 1, 1943 ----------------------------                                                                     $48, 792. 06
Gross amount expended----  --           -------      $30, 010. 72
Less reimbursements collected ----------------------      219. 38
                                                                                                                                  29, 791. 34
             Balance unexpended June 30, 1944 -----------------------                                                             19, 000. 72
                   RIVERS AND                 HARBORS-BALTIMORE,                           MD.,        DISTRICT                      331

Outstanding liabilities June 30, 1944----------------------------                                                       $4, 114. 92
      Balance available June 30, 1944_ - --            - --   ____                                                      14, 885.80
Amount allotted in July, 1944 ----------------------------------                                                        24, 000. 00
      Amount available during fiscal year 1945                                    ------------------                    38, 885. 80
Amount that can be profitably expended in fiscal year ending June
                                                 1
    30, 1946 for maintenance                     1--                                                   ___ _            30, 000. 00
  1 Exclusive of available funds.

11. OTHER                 NAVIGATION                    PROJECTS FOR WHICH                                NO ESTIMATES
                                                       ARE SUBMITTED

                                                                       For last   Cost and expenditures to
                                                                     full report         June 30, 1944                    Estimated
                      Name of project                                                   ________________
                                                                     see Annual Reportquired                             amount    re-
                                                                                                                         a    untreoto
                                                                         for-
                                                                        Report   New work            ainte-
                                                                                                   MNew
                                                                                                    nac                   complete
                                                                                                    nance


1. Middle River and Dark Head Creek, Md.'___                              1942    2 $38, 715. 25--------------               (4)
2. Susquehanna River above and below Havre
      de Grace, Md.-
3. Northeast River, Md.- _
                            - -.
                                                   ____
                                                         -  .-
                                                                   __
                                                                           1941
                                                                           1940
                                                                                     270, 664. 40
                                                                                       28, 488. 71
                                                                                                       5$77, 530.- 62         (4)
                                                                                                       .-                     (4)
4. Elk and Little Elk Rivers, Md.1 .-...          .                       1932      7 90,121.28          44, 342.35          (4)
5. Rock Hall Harbor, 1Md_------                                 -    -1940          139, 757.13           9, 762. 04         (4)
6. Corsica River, Md.              __                   __1932                        39, 070.85         17, 611.85          (4)
7. Queenstown Rarbor, Md. 9                       -----                  1931         44, 858.27         26, 314.84          (4)
8. Channel connecting Plain Dealing Creek and
       Oak Creek, Md.           ------------------------                  1940            111.57 .$74,                                  000
9. Claiborne Harbor. Md.1 _                          -1933                           42, 973. 65      48, 584. 27             (4)
10. Knapps Narrows, Md.1 ..........-                               _       1936       46,121.20 --------------                (4)
11. Tilghman Island Harbor, Md.' 9 o--            10                      1922             29. 73 -- -                             7, 790
12. Tred Avon River, lMd.' 11-...------                                   1923        12, 692.87        1,140. 93                 22, 000
13. Island Creek, Md.                                                     1940         6,229.93 --------------                (4)
14. La Trappe River, Md.i                      ------                     1922         8,063.87        15,967. 97              (4)
15. Choptank River, Md.'-                                                 1931        84, 296. 34      21, 649. 83            (4)
16. Tuckahoe River, Md.i 9                 -------                        1923         9, 727. 36       1,092.64               (4)
17. Warwick River, Md.1 -
18. Cambridge Harbor. Md.8 -...
                                             - -1922                                  22, 040. 82      24, 641.00              (4)
                                                                          1940        81,973.94         6,987.30                     33, 500
19. Waterway from Little Choptank River to
       Choptank River, Md.8            _              .       --          1939           305.45      ---------------           -58, 700
20. Slaughter Creek, Md.1 -                                               1922         4,140.00                500.00         (4)
21. Honga River and Tar Bay (Barren Island
       Gap), Md.' ----------------------------                            1939        27,667.94       14,169.78               (4)
22. Fishing Bay, Md.'------------------------.1940                                    33, 874.19 --------------               (4)
23. Nanticoke River, Md.' .                . ......                       1940        73, 243.18 ...                          ()
24. Nanticoke     River     (including Northwest
       Fork), Del. and Md.X i 2                                           1940        48,815. 31          33,312. 79          (4)
25. Broad Creek River, Del.' -------------------                          1935        64, 520. 00         43, 313. 59         (4)
26. Tyaskin Creek, Md.' 9_...................                             1923        16, 296. 63         18, 266. 39         (4)
27. Wicomico River, Md.                           - -                     1942     13457, 847.03          86, 741.08                  2,900
28. Upper Thoroughfare, Deals Island, Md. .                               1940        62,445.73            3, 975.31          (4)
29. Lower Thoroughfare, at or near Wenona,
      Deals Island, Md.i 14-                   -        -1922                         12,200.00                 700.00        (4)
                               0
30. Manokin River, Md. ' 19-------                                        1919      1534, 788. 05         31, 874. 44         (4)
31. Crisfield Harbor, Md. ---------------------                           1941       211,961.83             2,839.46                 32,750
32. Broad Creek, Md. _------------------------1939                                    28, 227.19          44, 603.63          (4)
33. Chincoteague Bay, Va.1                                                1940        25,125. 92- .............               (4)
34. Herring Bay and Rockhold Creek, Md. ......                            1941        50, 591.47 ..--------------             (4)
35. Parish Creek, Md. -------  ___'                   _..          .      1937        19,170. 27 ----------------             (4)
36. Back Creek, Anne Arundel County, Md.i..                               1941        23,061.22 ----------------              (4)
37. Annapolis Harbor, Md.'1
                                 --------------------                     1941        34, 249.61 ...........---------------   (4)
38. Cypress Creek, Md. _----------------------1940                                     3,057.27 .........-----------...       (4)

  1 Channels adequate for commerce.
  2 In addition $111,581.43 expended by U. S. Navy Department and $54,000 expended from contributed
funds, all for new work.
  3 Modifications of existing project recommended by the Chief of Engineers Apr. 5, 1939 (S. Doc. No. 67,
76th Cong., 1st sess.).
  4 Completed.
   2 Exclusive of $2,498.62 for dredging to 12-foot depth at Port Deposit, Md., fiscal year 1942, under sec. 3,

River and Harbor Act approved Oct. 17, 1940.
  6 Awaiting local cooperation for completion to full width for 1,500 feet at lower end of project.

    In addition $8,414.09 was expended from contributed funds.
  SAwaiting local cooperation.
    Abandonment recommended in 1926 (H. Doc. No. 467, 69th Cong., 1st sess.).
  10Insufficient potential commerce to justify the improvement.
  11Awaiting local cooperation for work in north fork.
  12Modifications recommended Mar. 20, 1941 (S. Doc. No. 69, 77th Cong., 1st sess.).
  13In addition $14,000 was expended from contributed funds.
  14Modification of existing project was recommended by the Chief of Engineers, Jan. 11, 1939 (H. Dec.
No. 238, 76th Cong., 1st sess.).
  15Includes $2,000 expended outside the project limits.
  1s Modification of existing project was recommended by the Chief of Engineers, July 24, 1939 (H. Doc.
No. 457, 76th Cong., 1st seas.).
332             REPORT OF CHIEF OF ENGINEERS,                                                  U. S. ARMY,                               1944

               12. PLANT ALLOTMENT, BALTIMORE, MD., DISTRICT
                                              Cost and financial summary
Undistributed costs June 30, 1944 ----------------------------                                                                                 $5, 787. 57
Plus accounts receivable June 30, 1944--   ---              ____                                                                               27, 258. 00
      Gross total costs to June 30, 1944__- ---       ___                                                                                      33, 045. 57
Minus accounts payable June 30, 1944--------------------------                                                                                  8, 664. 16
      Net total expenditures- ___---------___                                                                                                  24, 381. 41
Unexpended balance June 30, 1944---------------                                                                                                60, 16. 56
Total amount appropriated to June 30, 1944------------                                                                                         84, 997. 97


    Fiscal year ending June 30                   1940                1941                        1942                         1943                   1944


Total expended...........------------..       -$3, 285. 37   -$68, 989. 27                 $386, 473. 09 -$332,169. 53                          -$49, 889. 94

Allotted             .   .----------------------3,138.01-    -   -        -.                    3, 355. 96     _   ...         ....       ..   ...      ...



Balance unexpended July 1, 1943__                                                                                              _            $10, 726. 62
Gross amount expended_                                                                                  $178, 658. 54
Less fReimbursements collected-------                                    $227, 605. 32
      Receipts from saleas --------                                            943. 16
                                                                                                         228, 548. 48
                                                                                                                               --- -           49, 889. 94

      Balance unexpended June 30, 1944-                                                    -           --           _ _ _                      60, 616. 56
Outstanding liabilities June 30, 1944_---                                                            - --                     _ __             13, 195. 28

      Balance available June 30, 1944_-        ------                                                           ___                            47, 421. 28
Accounts receivable June 30, 1944---    ------                                                                 __                              27, 258. 00

            Unobligated balance available June 30, 1944                                        --------------                                  74, 679. 28

Status of all investigations for navigation, called for by river and harbor acts and
                                committee resolutions

                                                                          Date trans-                                                       Recommenda-
              Locality                     Authorization act               mitted to                    Document No.                        Recomenda
                                                                     S         Congress


Jefferson Islands, Chesa-                 Rivers and Harbors ...                  ................
  peake Bay, Md., chan-                    Act, Aug. 26, 1937.
  nels to, as aid to naviga-
  tion, and establishment of
  harbor of refuge.
Manokin River, Md- __     .               Rivers and Harbors .                 ........                 ....             ..        ...
                                            Committee resolu-
                                           tion, Apr. 4, 1939.


                                          13. YORK, CODORUS CREEK, PA.

   Location.-York, Pa., is on Codorus Creek, 10 miles above its con-
fluence with the main Susquehanna River. Codorus Creek with its
tributary branches is located in York County in the south and central
part of Pennsylvania. (See U. S. Geological Survey quadrangle
sheets "Pennsylvania-York and Hanover.")
   Existing project.-The plan of improvement provides for the con-
struction of Indian Rock Dam, an earth and rock fill dam about
1,200 feet longat the top, rising 82 feet above the stream bed, with
a reservoir providing for the controlled storage of 28,000 acre-feet
at the elevation of the spillway crest. The dam site is located on the
         FLOOD CONTROL--BALTIMORE,        MD.,   DISTRICT           333
main branch of Codorus Creek about 3 miles above York. The outlet
works are located in the right abutment and the uncontrolled spillway
is located on the right bank, discharging upstream from the tunnel
outlet. The reservoir will control the entire drainage area of the
main branch of Codorus Creek and 41 percent of the drainage area
above York. The plan also provides for improvements to Codorus
Creek channel in the vicinity of and through the city of York for a
distance of about 22,969 feet extending from 300 feet above Richland
Avenue to a point downstream from the Pennsylvania Railroad cross-
ing known as Black Bridge. The improvements, which will increase
the channel capacity to 24,000 cubic feet per second, include widening
and deepening the channel and constructing bank protection. The
existing project was authorized by the Flood Control Act approved
June 22, 1936. The estimated cost of new work, revised in 1944, is
$4,610,000. The latest (1941) 'approved estimate for annual cost of
maintenance is $12,100.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Operation of Indian
Rock Dam and protection thereof: Dead storage is not maintained in
the Indian Rock Reservoir. Storage in this reservoir is only re-
tained during periods of high rungoff to prevent the flow in Codorus
Creek from exceeding its channel capacity through York, Pa., and
causing flood damages. During the fiscal year, the peak discharge
through Indian Rock Dam was 3,200 cubic feet per second, which oc-
curred on November 9, 1943. At no time during the year was it neces-
sary to close any of the outlets. A section of underground power cable
1,200 feet long between the operating house and a pole at the opposite
end of the dam was replaced with an overhead power line.
   Codorus Creek channel was maintained during the year and silt
surveys were made periodically. Hydraulic studies were made to de-
termine the effect of the removal of the York Roller Mill Dam on this
silting. Plans and specifications for the construction of the bridge
over Indian Rock Dam were completed. Field surveys and examina-
tions were made for use in the preparation of plans and specifications
for completion of the project, including the removal of the York Roller
Mill Dam and the construction of an 80-foot wide low-water channel
extending from the dam upstream approximately 3,500 feet. Con-
tracts were awarded for well drilling and piping water from the well
to the operator's house and the public rest rooms. The well-drilling
operations were commenced. The acquisition of land is in progress.
The total costs were $34,323.62, of which $24,663.69 were for new work
and $9,659.93 were for maintenance. The total expenditures were
$32,674.89.
   Condition at end ot fiscal year.-The construction of Indian Rock
Dam is essentially complete and the construction of Codorus Creek
channel improvements is about 80 percent complete. The work re-
maining to be done is the completion of the acquisition of lands, con-
struction of the steel highway bridge over the spillway, completion
of the channel excavation above the George Street crossing, and above
Black Bridge, completion of stone riprap slope protection, completion
of concrete retaining walls and head walls, and the removal of the
York Roller Mill Dam. The total costs were $3,903,364.68, of which
$11,588.14 were Emergency Relief funds; $3,873,230.99 were regular
334       REPORT OF CHIEF OF ENGINEERS,                                     U. S. ARMY,                1944

funds for new work; $18,545.55 for maintenance. The total expendi-
tures were $3,905,736.43, of which $11,588.14 were Emergency Relief
funds, and $3,894,148.29 regular funds.
  Proposed operations.-The unexpended balance July 1, 1944, $47,-
551.71 and the allotments of July 1944 of $50,000, plus the accounts
receivable of $75.28, making a total of $97,626.99, will be applied as
follows:
Accounts payable, June 30, 1944_ - -     --    ___ -----            $3, 842. 96
New work:
    Acquisition of rights-of-way, easements, lands, and damages for
      Indian Rock Dam_-------                     - -    -__        11, 000. 00
    Acquisition of rights-of-way, easements, lands, and damages for
      Codorus Creek improvements_--         ----------              68, 228. 93
Maintenance:
    Operations--------------------------------------------5, 500. 00
    Maintenance and repair of mechanical equipment of dam and of
      flood gates on Codorus Creek channel                              000. 00
                                                                     5,--------------5
    Monthly surveys of silting in Codorus Creek ----------           2400.
                                                                     2,        00
    Emergencies-following floods__----____                           1 655. 10
       Total      ---------------------------------------------
                                 .                                                                       97, 626. 99
   The above work will be done by hired labor during the period July
1, 1944, to June 30, 1945.
   The additional sum of $462,000 gan be profitably expended during
the fiscal year 1946, as follows:
New work:
   Indian Rock Dam: Steel highway bridge over spillway channel _- $22, 000
   Codorus Creek Channel improvements: Removal of York Roller
     Mill Dam, channel excavation, riprap for slope protection, con-
     crete retainig 'walls and headwalls, and miscellancus items...  428, 000
          Total---- -----------------------------------------                                                 450, 000

Maintenance:
   Operations.        -----------------------                                                -                  5, 500
    Maintenance and repair of mechanical equipment.                                                             4, 100
    Monthly surveys of silting in Codorus Creek                                    -        - -                 2, 400

       Total--       ----------------------------------------------                                            12, 000   I




  New work will be done by contradt and maintenance will be done
by hired labor during the period July 1, 1945, to June 30, 1946.
                                   Cost and financial summary
( Cost of new work to June 30, 1944_-                                                       -_    1 $3, 884, 819. 13
  Cost of maintenance to June 30, 1944_                 --                             --                18, 545. 55
       Total cost of permanent work to June 30, 1944                                               1 3, 903, 364. 68
Undistributed costs June 30, 1944 ___    --                                                              6, 139. 43
        Net total cost to June 30, 1944 -_-3,                                                            909, 504. 11
Plus accounts receivable June 30, 1944 _                         --                                           75. 28
I
        Gross total costs to June 30, 1944                   -               -3,                         909, 579. 39
Minus accounts payable June 30, 1944_                                 --                                  3, 842. 96
      Net total expenditures__-    --   ----        -__                                                3, 905, 736. 43
1Unexpended balance June 30, 1944 -------------------                                                      47, 551.71
        Total amount appropriated to June 30, 1944                          ---------              1   3, 953, 288. 14
1 Includes $11,588.14 Emergency Relief funds.
                FLOOD CONTROL--BALTIMORE,                                         MD., DISTRICT                             335

   Fiscal year ending June 30                   1940                 1941               1942           1943              1944

Cost of new work.      ___.........._ $470, 455. 70 $1, 410, 259. 91 $1, 330, 080.86                $495, 702.85        $24, 663.69
Cost of maintenance_-.................................
                              - --       -                                          .
                                                                                 . ._                  8,885.62           9,659.93
      Total cost.   ----------------       470, 455. 70         1, 410, 259. 91    1,330, 080. 86    504, 588.47         34, 323.62
Total expended.....----------------341,            532. 50      1, 365, 844.66     1, 329, 308.68   692, 307.41          32, 674.89
Allotted-................              -.. -185, 000.00         1, 375, 000.00       880,100.00       12, 100.00      -185, 500.00


Balance unexpended July 1, 1943__                                                                              $265, 726. 60
'Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942-------- $15, 500. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved June 24, 1940           12, 000. 00         -           -                                27, 500. 00
      Amount to be accounted for_                                                                                  293, 226. 60
Deductions on account of revocation of allotment-                                                                  213, 000.00
       Net amount to be accounted for_                                                                              80, 226. 60
Gross amount expended_------                ---                                         $37, 584. 86
Less reimbursements collected ---------------                                             4, 909. 97
                                                                                                                    32, 674. 89
      Balance unexpended June 30, 1944-                                                                             47, 551. 71
Outstanding liabilities June 30, 1944------------- $1, 716. 00
Amount covered by uncompleted contracts -        - 45, 215. 94
                                                                                                                    46, 931. 94
      Balance available June 30, 1944_                                                                                  619. 77
Accounts receivable June 30, 1944_                                                                                        75. 28
     Unobligated balance available June 30, 1944                                               -                        695. 05
Amount allotted in July 1944                                                                                        50, 000. 00
         Amount available during fiscal year 1945--------                                                           50, 695. 05
Amount (estimated) required to be appropriated for completion
  of existing project 2                  ----------                                                           2    640, 411. 86

Amount that can be profitably expended in fiscal year ending
June 30, 1946:
   For new work 2   -      ----------                                                                              450, 000. 00
   For maintenance 2                                                                                                12, 000. 00

        Total 2                           -------------------                                                      462,000.00
2 Exclusive of availble' funds.


             14. HARRISBURG, SUSQUEHANNA RIVER BASIN, PA.

   Location.-The Susquehanna River rises in the southern part of
New York, and flowing in a general southerly direction for over 400
miles, empties into the head of Chesapeake Bay at Havre de Grace,
Md. Harrisburg is about 70 miles upstream from the mouth of the
river. Paxton Creek flows through the city of Harrisburg into the
Susquehanna River, with most of its watershed being diverted into
Wildwood Lake, a reservoir at the upstream end of the town.
   Existing project.-The plan of improvement provides for the con-
struction of an earth dike, containing approximately 11,000 cubic
yards; a concrete dam at the mouth of Paxton Creek equipped with
large gates which can be closed by stop logs; a shut-off valve in the
336      REPORT OF CHIEF OF ENGINEERS,                      U. S. ARMY,                     1944

outlet of the Paxton Reservoir to shut off, completely, flow down the
Paxton Creek; and a pumping plant at the mouth of Paxton Creek to
remove the local run-off, which enters the creek below the reservoir,
and water overflowing the dam when the gates are closed. The existing
project was authorized by the Flood Control Act approved June 22,
1936. The estimated cost of new work is $104,000 for construction and
$5,200 for lands and damages.
   Recommended modification of project.-Under date of October 21,
1941, the Chief of Engineers recommended modification of the existing
project to provide 1,100 linear feet of levee, 9,000 linear feet of concrete
wall, raising the earth dam at Wildwood Lake, 800 feet of diversion
channel for Spring Creek, pumping stations, stop-log structures, and
intercepting sewers at a total construction cost of $2,227,000, subject to
certain conditions of local cooperation (H. Doc. No. 702, 77th Cong..
2nd sess.).
   Local cooperation.-See page 7 for requirements.
   Operationsand results duringfiscal year.-Duringthe year meetings
were held between representatives of the Department and local interests
to discuss the fulfillment of the terms of local cooperation. Rights-of-
way for core-boring operations were obtained. Core-boring operations
were commenced and completed during the year by contract. Surveys
and investigations for hydrologic studies and for design studies of
levee, wall, and pumping station were made together with initial work
on the plans. The costs, all for new work, were $11,703.92. The ex-
penditures were $10,263.08.
   Condition at end of fiscal year.-Construction work is not in prog-
ress. The preparation of plans is in progress. The total costs, all for
new work, were $11,703.92. The total expenditures were $10,263.08.
   Proposed operations.-The unexpended balance June 30, 1944, $4,-
736.92, and the allotment of July 1944 of $4,000, plus the accounts
receivable of $26, a total of $49,762.92, will be applied as follows:
Accounts payable, June 30, 1944 __                 -
                                                   -                       -         - __- $1, 466. 84
New work: Preparation of plans and specifications-                                  _       _48, 296. 08
      Total_   _ ___    _   -     -     -    -_         -   -49,762.                                    92
  The work will be done by hired' labor during the period July 1,
1914, to June 30, 1945.
  The amount of $50 000 can be expended during fiscal year 1946
for the preparation of plans and specifications.
                                Cost and financial summary
Cost of new work to June 30, 1944 ___             ---                  __________             $11, 703. 92
nCostfof mainftenance to June         044
                                      .1O




       Total cost of permanent work to June 30, 1944_                                   _      11, 703. 92
Plus accounts receivable June 30, 1944       --                                                     26. 00

      Gross total costs to June 30, 1944_-   ----      -____                                   11, 729. 92
Minus accounts payable June 30, 1944 -------------------                                        1, 466. 84
      Net total expenditures- ---     ---------                                 __             10, 263. 08
Unexpended balance June 30, 1944 ----------------------                                         4736.92
                                                                                                4,
      Total amount appropriated to June 30, 1944                                               15, 000. 00
                                                                                               1----------
                 FLOOD CONTROL---BALTIMORE,                                       MD., DISTRICT                              337

   Fiscal year ending June 30                1940                     1941               1942         1943             1944


Cost of new work e           _   _ _ --        __..---------
                                                        ..--                                     -------------        $11, 703.92
Cost of maintenance---                                                                                            -     --    -

Total expended                     --------------------------------                                                    10, 263.08
        ------------------------- -
Allotted_                                                     ---                                                      15, 000. 00



Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941                                      $15, 000. 00
Gross amount expended ___                       $10, 276. 33
Less reimbursements collected_ -13.                       25
                                                              10, 263. 08
       Balance unexpended June 30, 1944                                  -                                        4, 736. 92
Outstanding liabilities June 30, 1944 -                                                                           1, 500. 00

      Balance available June 30, 1944                                                                             3, 236. 92
Accounts receivable June 30, 1944 _                                                                              _      26.00

     Unobligated balance available June 30, 1944-                                                                 3, 262. 92
Amount allotted in July 1944 ____                                                                                45, 000. 00
           Amount available during fiscal year 1945                                                              48, 262. 92

Amount that can be profitably expended in fiscal year en ding June
30, 1946, for new work 1_       _____                                                                           50, 000. 00
    I   Exclusive of available funds.


   15. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES
                      FOR FLOOD CONTROL

   The cost of work during the year amounted to $3,940.45.                                                        The ex-
penditures were $3,969.64. The balance unexpended June 30, 1944,
$30.36, plus an allotment of $11,800 made in July 1944, a total of
$11,830.36, will be applied as needed during the fiscal year 1945 to
payment of expenses incurred under this heading.
  The additional sum of $15,000 can be profitably expended during
the fiscal year 1946.

                                        Cost and financial summary
Cost of new work to June 30, 1944                                            .

Cost of maintenance to June 30, 1944                                                                             $3, 940. 45
       Total cost of permanent work to June 30, 1944----                                                          3, 940. 45
Undistributed costs June 30, 1944    -----------                                                                      29. 96
      Net total cost to June 30, 1944__                                                                           3, 970. 41
Minus accounts payable June 30, 1944_                                                                                   . 77
      Net total expenditures---                                     -------                     _3,                    969. 64
Unexpended balance June 30, 1944_---                                             -----------                            30. 36
           Total amount appropriated to June 30, 1944                                                                000. 00
                                                                                                                  4,---------4




          616634-45-pt. 1, vol. 1-                22
338         REPORT OF CHIEF OF ENGINEERS,                                   U. S. ARMY,                          1944


   Fiscal year ending June 30              1940              1941             1942                        1943              1944


Cost of new work ..  --------.....-.--------...--.--------...-.---------...-.------..................
Cost of maintenance------------- ---------.............--
                                                 ......        ...............----------------------------$3, 940. 4
Total expended.....     ..........-----------..........----------------------------------------------------                  3,969.64
Allotted ......--------------...........
                                    _..-------------- -------------- -          -----                            00-------
Balance unexpended July 1, 1943_---------                                                       ---                 $4, 000. 00
Gross amount expended___                                                                                              3, 969. 64

      Balance unexpended June 30, 1944--------------------------                                                             30. 36
Outstanding liabilities June 30, 1944.                                                                                           77
                                                                                                                               .--------------------
     Balance available June 30, 1944_--                                ----------                                        29. 59
                           ___-__-
Amount allotted in July 1944--          -                                       -                     -             11, 800. 00

         Amount available during fiscal year 1945                                                                        829. 59
                                                                                                                    1,-----------11
Amount that can be profitably expended     in fiscal year ending June 30, .
                          -   - - - - - - - - - - - - - - - - - -
1946, for maintenance 1.___                                      _____   15, 000. 00
  I Exclusive of available funds.

16. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                      ARE SUBMITTED

                                                           For last       Cost and expenditures to
                                                           full re-             June 30, 1944                           Estimated
                  Name of project                          port se                       ....         _____         amount re-
                                                           Annual                                                       quired to
                                                           Report         New work          Maintenance                 complete
                                                             for--


Federalsburg, Marshyhope Creek, Md__ .....                 -1941             $4, 061.08 -------------                   -$216,     000

1Awaiting local   cooperation.

   IMPROVEMENT OF RIVERS AND HARBORS IN THE
           WASHINGTON, D. C., DISTRICT
   This district comprises a portion of south central Pennsylvania,
western Maryland, eastern West Virginia, and northern Virginia
embracing the western part of Chesapeake Bay and its tributaries
from Cove Point, Md., to a line due west through Wolf Trap Light to
the watershed line between the northerly arm of Winter Harbor and
Garden Creek, Va.
   District engineer: Col. Clarence Renshaw, Corps of Engineers, to
January 7, 1944; Col. John M. Johnson, Corps of Engineers, since
that date.
   Division engineer: Col. Clark Kittrell, Corps of Engineers, to Sep-
tember 30, 1943; Col. G. J. Zimmerman, Corps of Engineers, acting
division engineer to October 25, 1943; and Col. Earl E. Gesler, Corps
of Engineers, since that date.
        RIVERS   AND    HARORS---WASHINGTON,               D. C.,    DISTRICT      339

                                     IMPROVEMENTS

               Navigation                                  Flood control
                                      Page                                         Page
1. Washington Harbor, D. C -          339 14. Washington,      D.     C.,   and
2. Potomac River, north side                      vicinity_                       358
       of Washington Channel,                15. Cumberland,       Md.,     and
       D.C----                         342         Ridgeley, W. Va ....            360
3. Pptomc River at Alexan-                  16. Emergency repairs and rescue
       dria, Va------                  345         work under authority of
4. Potomac River below Wash-                      section 5 of the Flood Con-
       ington, D. C                    346         trol Act, approved August
5. Potomac River at Mount                         18, 1941         _      --      361
       Vernon, Va.                     348   17. Preliminary     examinations,
6. Occoquan Creek, Va ...             350         surveys, and contingencies
7. Little Wicomico River, Va__        351         for flood control_         __   362
8. St. Jeromes Creek, Md    --        352   18. Other flood-control projects
9. Rappahannock River, Va             353         for which no estimates are
10. Totuskey Creek, Va_ -              355         submitted-_-       -_            363
11. Examinations, surveys, and
       cbntigncies (general) ___       356
12. Other navigation projects for
       which no estimates arp sub-
       mitted_                         357
13. Plant allotment_                   358

                       1. WASHINGTON HARBOR, D. C.

  Location.-Washington Harbor is located at the junction of the
Anacostia River with the Potomac River within the District of Co-
lumbia, 108 miles upstream of the mouth of the Potomac River,
southerly 202 miles by water from Baltimore, Md., and northerly 195
miles from Norfolk, Va. (See U. S. Coast and Geodetic Survey
Chart No. 560.)
  Previous projects.-The original project for the Potomac River was
adopted by the River and Harbor Acts of March 2, 1833, July 11,
1870, aid August 2, 1882. For further details, see page 1791 of An-
nual Report for 1915, and page 295 of Annual Report for 1934. The
River and Harbor Act of September 19, 1890, authorized an allot-
ment for work on the Anacostia River; joint resolution of Congress
of April 11, 1898, made appropriation for a survey; and a project
was adopted by the River and Harbor Act of June 13, 1902 (H. Doc.
No. 87, 55th Cong., 3d sess., and Annual Report for 1899, p. 1443).
For further details, see page 430 of Annual Report for 1932 and
page 421 of Annual Report for 1938.
  Existing project.-This project is a combination and extension of
the latest projects for the Potomac River at Washington, D. C., and
the Anacostia River, D. C. The project provides for: (1) Virginia
Channel, from Giesboro Point to Francis Scott Key Bridge, 24 feet
deep and 400 feet wide, with the width increased as necessary to afford
a low-water cross-section area of 25,000 square feet; (2) Washington
Channel, from Hains Point to the head of Washington Channel, 24
feet deep and 400 feet wide; (3) Anacostia River, from Giesboro
Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with
turning basin 800 feet wide and approximately 2,400 feet long of
same depth opposite the navy yard; (4) Anacostia River from Ana-
costia Bridge, 24 feet deep and 200 feet wide to turning basin 400
feet square of same depth at foot of Fifteenth Street SE. The chan-
nel lengths including turning basins are: Virginia Channel 25,000
340    REPORT OF CHIEF OF ENGINEERS,        U.   S.   ARMY,   1944

feet, Washington Channel 10,000 feet, and Anacostia River 15,000
feet. The plane of reference is low-water datum which is 0.35 foot
below mean low tide as observed from 1932 to 1942. Tidal ranges are:
Mean, 2.9 feet; irregular, 4.5 feet; and extreme, 10.7 feet.
   The estimate of cost for new work, made in 1935, is $325,000, ex-
clusive of expenditures on previous projects. The latest (1935) ap-
proved estimate for annual cost of maintenance is $83,000.
   The existing project was adopted by the River and Harbor Act of
August 30, 1935 (Rivers and Harbors Committee Doc. No. 22, 74th
Cong., 1st sess.). The latest published maps are in the project
document.
   Terminal facilities.-On the Virginia Channel (Georgetown water
front) there are 9 wharves generally of the bulkhead type, of timber,
stone, and concrete, privately owned. Railroad and crane service are
available at a number of the wharves. On the Washington Channel
are 2 yacht basins with a total capacity for 198 yachts, under jurisdic-
tion of the District of Columbia and 15 wharves of open pile and
bulkhead construction, all owned by the Federal Government, but most
of which are leased to private parties or serve governmental agencies.
On the Anacostia River are about 23/4 miles of commercial water front
on which are located 33 privately owned and 2 Government wharves,
and 3,500 linear feet of bulkhead with slips for governmental agencies.
Some of the wharves and slips have transfer and rail facilities. The
wharves of the Washington Harbor are only open to the public by
special arrangement, except for the District of Columbia fish wharves
on the Washington Channel.
    Terminal facilities, except for those in the Washington Channel,
are considered adequate for existing commerce.
    Operations and results during fiscal year.-The tidal gates were
repaired and operated throughout the year at a cost of $3,074.60,
and maintenance dredging at the entrance to the inlet gates wgs com-
pleted by the U. S. hydraulic dredge Dalecarliaon July 9, 1943. A
total of 11,525 cubic yards of dredged material was deposited on the
adjacent flats at a cost of $3,418.13. Hydrographic surveys to deter-
mine channel condition were made throughout the year at a cost
of $1,138.01.
   Water chestnut growth (Trapa natans) was removed from scat-
tered locations by hired labor and Government plant in July 1943
at a cost of $2,503.41. The work was accomplished by manual-removal
crews, and the entire Washington Harbor area was patrolled, and all
scattered plants were removed.
    Total costs for the year were $10,134.15, applied to maintenance.
Total expenditures were $10,605.91.
    Condition at end of fiscal year.-The existing project was about
50 percent completed. The channels and basins in the Anacostia River
are completed and those at the forks of the channel at Hains Point
are partially completed. No new work has been done downstream
of Key Bridge in the Virginia Channel. The controlling depths
throughout the harbor were as follows: Virginia Channel, Hains
Point to Key Bridge, 16.5 feet for a width of 400 feet, November
1942; Washington Channel, 18 feet for a width of 400 feet and 22.4
feet for a width of 300 feet, July 1942; Anacostia River, to Anacostia
Bridge, 22.8 feet for a width of 400 feet, August 1942 and upstream
of Anacostia Bridge to foot of Fifteenth Street SE, 22.9 feet, August
             RIVERS AND HARBORS-WASHINGTON,                                              D. C., DISTRICT                  341
1942, except under the drawspan of the bridge where a depth of 21.1
feet.exists for a width of 100 feet.
  The total cost of the existing project was $425,678.32, of which
$162,006.33 was for new work and $263,671.99 was for maintenance.
The total expenditures were $425,059.12.
  Proposed operations.-The balance unexpended June 30, 1944,
$3,046.15, and an allotment of $16,000 made during July 1944 will be
applied as follows:
Accounts payable, June 30, 1944---          -----------                $827. 62
Maintenance:
    Operation and repair of tidal gates, Tidal Basin, by hired labor
       (July 1, 1944, to June 30, 1945)                    -----------------
                                                           ___        5,000. 00
    Jradication of water chestnut growth with Government plant and
      hired labor (July 1, 1944, to June 30, 1945)__                  1,500. 00
    Preparation of disposal area by Government plant and hired
      labor in Oxen Run for disposal of material dredged from the
       Washington Harbor (Sept. 1, 1944 to Apr. 30, 1945)
       Total_--------------------------------------
                                                                         718. 53
                                                                     19, 046. 15
                                                                                                   -11,
   The additional sum of $6,000 can be expended profitably during the
fiscal year 1946 as follows:
Operation and repairs of tidal gates, Tidal Basin, by hired labor (July 1,
  1945, to June 30, 1946) ------------------------------------------- $5, 000
Eradication of water chestnut growth with Government plant and hired
  labor (July 1, 1945, to June 30, 1946) -----------------------------     1, 000
                                            Cost and finanr;al summary
Cost of new work to June 30, 1944           _ __ _ __ _                                                       $3, 191, 007. 11
Cost of maintenance to June 30, 1944_ ____--------2,                                                              095, 281. 61
      Total cost of permanent work to June 30, 1944---                                                         5, 286, 288. 72
Minus accounts payable June 30, 1944            -   ----                                                               827. 62

      Net total expenditures-------------------------------                                                    5, 285, 461. 10
Unexpended balance June 30, 1944_                ---------_                                                         3, 046. 15
           Total amount appropriated to June 30, 1944------------- 5, 288, 507. 25

      Fiscal year ending June 30              1940              1941              1942                1943             1944

Cost of new work
Cost of maintenance-- ---------.        -    $4,655.17     $56, 754 22           $6, 007. 26         $6,413. 26      $10,134. 15
Total expended ------------------             4, 420. 27       50, 726. 74        6, 92.:69           9, 509.03        10,4605. 91
Allotted...----------------------            23,000. 00        55,000.00          7, 000.00        -93,000.00         _



Balance unexpended July 1, 1943                            _                 -     -           -          -        13, 652. 06
Gross amount expended_--       ---------                                               $10,606. 16
Less reimbursements collected---                                                                 25
                                                                                               .---------.
                                                                                                         10, 605. 91

      Balance unexpended June 30, 1944---------------------                                                         3, 046. 15
Outstanding liabilities June 30, 1944----------------------                                                            827. 62
     Balance available June 30, 1944_-       ----                                              _                    2,218. 53
                            ----------------------
Amount allotted in July 1944_.                                                                     _16,               000. 00

           Amount available during fiscal year 1945                               _-_18,                               218. 53
Amount (estimated) required to be appropriated for completion
      of existing project          -_                                                                             160, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance' ---------
                                     _        -------
                                           _---_-----_6,                                                               000. 00
  I   Exclusive of available funds.
342     REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,    1944

2. POTOMAC RIVER, NORTH SIDE OF WASHINGTON CHANNEL, D. C.

   Location.-The area covered by the project is the north side of the
Washington Channel water front upstream of the War College, all
located min  the District of Columbia." (See U. S. Coast and Geodetic
Survey Chart No= 560.)
   Eaisting project.-This provides for development of the commer-
cial water front of Washington Channel by construction of (1) a
yacht harbor in four sections on the upstream half of the section,
with berthing space for about 286 boats; (2) two wharves for activi-
ties of the District of Columbia; (3) three wharves for existing trans-
portation lines and general service; (4) construction of bulkhead
walls; (5) removal of the old and dilapidated existing structures, etc.
   The estimate of cost of new work, revised in 1943, is $3,364,430, of
which the District of Columbia is to contribute $389,000, the cost of
the two wharves for District of Columbia activities.
   The existing project was adopted by the River and Harbor Act of
August 30, 1935 (Rivers and Harbors Committee Doc. No. 13, 73d
Cong., 1st sess.).
   Local cooperation.-Fullycomplied with.
    Terminal facilities.-The entire waterfront is Government owned
and facilities are leased to individuals or serve governmental agencies.
Two yacht basins to accommodate 198 yachts and small boats together
with a public sales and service pier, and a large commercial pier have
been completed under the existing project. Of the 17 commercial
piers only 5 can be classed as modern. The only wharves open to the
public are those owned by the District of Columbia at the municipal
fish market where daily rental rates are charged. The facilities are
considered inadequate for existing commerce.
    Operations and results during fiscal year.-No construction work
Was done on the project. Preparation of plans and specifications for
post-war construction was continued throughout the fiscal year.
   Additional foundation tests were made at the sites of piers Nos. 2, 3,
and 4, and yacht basin No. 3, at a cost of $11,096.14. Plans and specifi-
cations for post-war construction of additional units of the project
were 21 percent complete on June 30, 1944, at a cost of $17,710.86. Mis-
cellaneous surveys were made at a cost of $821.23 and general studies
and investigations were in progress at a cost of $6,363.69.
    Total cost for the year, all for new work, was $35,991.92, of which
$20,233.01 was United States funds and $15,758.91 contributed funds.
The expenditures were $25,505.90, United States funds, and $12,719.76,
contributed funds, a total of $38,225.66.
    Condition at end of fiscal year.-The existing project was about
40 percent completed. Construction of the first two yacht basins was
completed in November 1940, and the basins were leased for commercial
use and transferred to the District of Columbia for operation on De-
cember 3, 1940. Commercial pier No. 5 at the foot of N Street SW.,
was completed in December 1941 and jurisdiction of the structure
transferred to the District of Columbia for operation March 21, 1942.
Removal of existing structures and dredging for construction of ex-
cursion pier No. 4 (fourth unit of construction) was completed
November 6, 1941, and plans and specifications were 72 percent com-
plete. Plans and specifications for yacht basin No. 3 (fifth unit of
construction) were 9 percent complete.
               RIVERS AND HARBORS-WASHINGTON,                                               D. C., DISTRICT                      343

   The work remaining to be done to complete the project consists of
 (1) construction of two yacht basins; (2) two piers for activities of the
District of Columbia; (3) construction of an excursion pier (pier
No. 4), and construction of a pier for existing transportation lines and
general service; (4) completion of bulkhead walls; and (5) comple-
tion of removal of existing structures.
   Total costs, all for new work, were $1,207,122.08, of which $930,363.17
was United States funds and $276,758.91, contributed funds. Total
expenditures were $930,363.17, United States funds, and $273,719.76,
contributed funds, a total of $1,204,082.93.
   Proposed operations.-The balance unexpended June 30, 1944,
$99,280.24, will be applied as follows:
Accounts payable, June 30, 1944 -----------------------------                                                      $3, 039. 15
New work:
    Completion of plans and specifications for pier No. 4 (excursion
      pier) (July 1, 1944, to Sept. 30, 1944)                                                                              475. 00
                                                                                                                        3,-------------3
    Foundation tests, surveys, and plans and specifications for yacht
      basin No. 3 (July 1, 1944, to June 30, 1945)                                                                 24, 200. 00
    Foundation tests, surveys, and plans and specifications for pier
      No. 2 (July 1, 1944, to June 30, 1945) _         -    -        _                                             28, 950. 00
    Foundation tests, surveys, and plans and specifications for pier
      No. 3 (police and fire department) (July 1, 1944, to June 30,
      1945)------     ---------------------------------------                                                      24, 500.00
    Foundation tests, surveys, and plans and specifications for bulk-
      head walls from N Street to P Street (July 1, 1944, to June 30,
      1945)                 --------------------------------------                                                 14, 640.00
Maintenance of unleased property------------                 -    -476.                                                    09

            Total                 ------------------------------------                                             99, 280. 24
The additional sum of $480,000 can be profitably expended for new
work during the fiscal year 1946 as follows:
New work:
   Construction of pier No. 4, by contract (July 1, 1945, to Apr. 30,
     1946) --                                                         $402,000                                                           I



   Dredging at site of yacht basin No. 3 by contract (Apr. 1, 1946,
     to June 30, 1946)         -------------------------                58,000                                                           w



   Rearrange and provide temporary facilities for tenants operating
     on the waterfront (June 1, 1945, to Mar. 31, 1946)                 20, 000              ------------                                I




                Total_ ---------------------------------------------                                                     480,000

                                                   Cost and financial summary
                                                     UNITED       STATES FUNDS

Cost of new work to June 30, 1944 -------------------------- $930, 363. 17
Cost of maintenance to June 30, 1944-------
       Total cost of permanent work to June 30, 1944-          930, 363. 17                 ---
Net total expenditures------------------------------------930, 363. 17
Total amount appropriated to June 30, 1944-------------------930, 363.17

     Fiscal year ending June 30                       1940           1941            1942             1943                 1944

                     ___
Cost of new work--------                     .     $96, 724.19    $301, 215. 52   $126, 723. 35     $10, 095. 27          $20, 233.01
Cost of maintenance ......                              ...            ...-----------------                  --------------
Total expended.................----------------.    170, 671.98    263,128. 59     164, 280. 02       5,199.94             25, 505. 90
Allotted---------.......................            221,000.00      46, 000.00     276, 000. 00   -273, 466.83     ..     ....      .
344          REPORT OF .CHIEF OF ENGINEERS, U. S. ARMY,                                                               1944

Balance unexpended July 1, 1943_ _                                     --                                                $25, 505. 90
Gross amount expended_ ___                                                                                                25, 505. 90

Amount (estimated) required to be appropriated for completion of
   existing project_ _              _ _ _____                                                                 _        2, 161, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work----------------------------480,                                                                       000. 00
                                           DISTRICT OF COLUMBIA FUNDS

Cost of new work to June 30, 1944 _-$276,                                                                                      758. 91
Cost of maintenance to June 30, 1944_
      Total cost of permanent work to June 30, 1944-
Minus accounts payable June 30, 1944
                                                                                                   -
                                                                                                                  _
                                                                                                                      -276, 3, 758. 91
                                                                                                                               039. 15

     Net total exepnditures ---------------                                                                              273, 719. 76
Unexpended balance June 30, 1944 ____                                                                                     99, 280. 24
           Total amount appropriated to June 30, 1944                                 --                 -               373, 000. 00

    Fiscal year ending June 30                 1940             1941                 1942                     1943             1944

Cost of new work --------------              $63, 745. 57    $128, 254. 43                                                   $15, 758. 91
Cost of maintenance_
Total expended ----------------               64, 271.01      115, 428. 98         $19, 200. 01           --                   12, 719. 76

Allotted----------------------64,000.00                        64,;000.00           64,000.00          -$64, 000.00          112,000:00


Amount allotted            from District of Columbia Appropria-
tion Act, July            1, 1941 __$64,                                                               000. 00
Amount allotted            from District of Columbia Appropria-
tion Act, June            27, 1942 _       _-                -48,                                      000. 00
           Amount to be accounted for                                                                                   $112,000. 00
Gross amount expended                      _-_____.                 --                      ----                           12, 719. 76

      Balance unexpended June 30, 1944                                                                                     99, 280. 24
Outstanding liabilities June 30, 1944__                                                                                     3, 039. 15
           Balance available June 30, 1944 _                                 -_                    _     ___               96, 241. 09

Amount (estimated) required to be appropriated for completion of
existing project 1 ----------------------------------------                                                               16, 000.00
  1Exclusive of available funds.

CONSOLIDATED COST AND FINANCIAL SUMMARY, NORTH SIDE WASHINGTON CHANNEL

Cost of new work to June 30, 1944__                                                                                   $1, 207, 122. 08
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-------                                                             1, 207, 122. 08
Minus accounts payable June 30, 1944_------_                                                                                3, 039. 15
      Net total expenditures_ ______ ------                                                            __              1, 204, 082. 93
Unexpended balance June 30, 1944_ _,_-- ----                                                           _99,                    280. 24
           Total amount appropriated to June 30, 1944                                 ---------                        1, 303, 363. 17

    Fiscal year ending June 30                 1940             1941                 1942                     1943             1944


Cost of new work             ..-------------- $160,469. 76   $429, 469.95         $126, 723.35           $10, 095. 27         $35, 991.92
Cost of maintenance .......-


Allotted---------                 - - --     285. 000. 0      110, 000. 00         340,000. 00         -337. 466. 83          112, 000. 0
          RIVERS AND HARBORS-WASHINGTON,                              D.   C., DISTRICT          345
Balance unexpended July 1, 1943_ ___$25,                                                      505. 90
Amount allotted from District of Columbia Appro-
  priation Act, July 1, 1941___           _ _ __      --        $64, 000. 00
Amount allotted from District of Columbia Appro-
priation Act, June 27, 1942----------------                         48, 000. 00
                                                                                      112, 000. 00

      Amount to be accounted for_--------                                    ---      137, 505. 90
Gross amount expended_-    --   --------------                                         38, 225. 66
      Balance unexpended June 30, 1944             ------------------                     99, 280. 24
Outstanding liabilities June 30, 1944__                                                       039. 15
                                                                                           8----------3,
                                        -
        Balance available June 30, 1944_--                 -------                 -96,       241. 09

Amount (estimated) required to be appropriated for completion
  of existing project       1_ _______   _ ___       _____2,                          177, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for new work 1_ _________________--___                                 480, 000. 00
1 Exclusive of available funds.

                    3. POTOMAC RIVER AT ALEXANDRIA,                          VA.

   Location.-Alexandria, on the right bank of the Potomac River, is
5 miles below Washington, D. C., and 105 miles above the mouth of
the river. (See U. S. Coast and Geodetic Survey Chart No. 560.)
   Existing project.-This provides for a depth of 24 feet in front of
Alexandria between the through channel and a line drawn 20 feet
outside of the established pierhead line. This area is about 6,700
feet in length and averages 300 feet in width. The plane of reference
is mean low water. Tidal ranges are: Mean, 2.8 feet; irregular, 4.5
feet; and extreme, 10.6 feet.
   The estimate of cost for new work, made in 1908, was $116,000.
The latest (1928) approved estimate for annual cost of maintenance
is .$5,500.
   The existing project was adopted by the River and Harbor Act of
June 25, 1910 (H. Doc. No. 1253, 60th Cong., 2d sess.). The latest
published map is in the project document.
   Terminal facilities.-Alexandria has 19 regular shipping wharves
or landings; 15 of these are privately owned (of which 4 are open to
the public by special arrangement) and 4 owned by the United
States. The terminal and transfer facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year.-Water chestnut growth
 (Trapa natans) was removed by hired labor and Government plant
in July and August 1943 along the Alexandria waterfront at a cost
of $2,219.98. The work was accomplished by manually removing
scattered growth throughout the waterfront area. Total costs and
expenditures for the year were $2,219.98, for maintenance.
   Conditionat end of fiscal year.-The existing project was completed
in 1912. The controlling depth in January 1943 was 19.6 feet in the
lower section and 18.5 feet in the upper section. Total costs and
expenditures were $276,770.74, of which $95,214.52 was for new work
and $181,556.22 for maintenance.
   Proposed.operations.-An allotment of $1,000 made during July
1944 will be applied to maintenance for the eradication of water chest-
nut growth from the Alexandria waterfront with Government plant
and hired labor (July 1, 1944, to June 30, 1945).
346         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                             1944

  The additional sum of $36,000 can be expended profitably during
the fiscal year 1946 as follows:
Maintenance:
    Dredging approximately 100,000 cubic yards in front of the wharves
      along the waterfront by contract (Mar. 1, to June 31, 1946) -.. $35, 000
    Eradication of water chestnut growth by Government plant and
      hired labor (July 1, 1945 to June 30, 1946)----                   1, 000
            Total-     ---------------------------------------------                                              36, 000

                                     Cost and financial summary
Cost of new work to June 30, 1944___--       --------                                                    $95, 214. 52
Cost of maintenance to June 30, 1944_-------                                        ---                  181, 556. 22
      Total cost of permanent work to June 30, 1944-     -    276, 770. 74
Net total expenditures--_              -------          _____ 276, 770. 74
Total amount appropriated to June 30, 1944------------------- 276, 770. 74

   Fiscal year ending June 30            1940            1941          1942                1943                   1944

C ost of new work .... . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .           .. .            -
                    -------------
Cost of maintenance.....                   450. 00       4, 793.95     2, 422.53          8,113. 54                    2, 219. 98

Total expended  --------------
                 .......        ....
                               --------------            3, 710. 19    3, 760. 05         8, 309. 78                   2, 219. 98
        -----------------------
Allotted.......          .             4,000.00         37, 000.00     4,000.00     -27,000.00            ..........


Balance unexpended July 1, 1943_---------                                            ---                  $2, 219. 98
Gross amount expended__                                                                                    2,2219. 98
Amount allotted in July 1944---------------------------------                                                1, 000. 00
Amount available during fiscal year 1945_-------          ---                                                1, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1_-    ___- --                       -                                          36, 000. 00
  SExclusive of available funds.

                 4. POTOMAC RIVER BELOW WASHINGTON, D. C.

   Location.-The Potomac River is formed 21 miles below Cumber-
land, Md., and flows southeasterly about 285 miles and enters Chesa-
peake Bay, about 80 miles from the Atlantic Ocean. (See U. S. Coast
and Geodetic Survey Charts Nos. 557, 558, 559, and 560.)
   Existing project.-This provides for a channel 24 feet deep and
200 feet wide between the mouth of the river and Giesboro Point at
Washington, D. C., a distance of 108 miles. The plane of reference
is mean low water. Tidal ranges are: Mean, 1.3 feet at the mouth,
2.9 feet at Washington; irregular, 2 feet at the mouth, 4.5 feet at
Washington; extreme, approximately 6 feet at mouth, 10.7 feet at
Washington.
   The estimate of cost for new work made in 1891 was $158,400.
The latest (1928) approved estimate for annual cost of maintenance
is $20,000.
   The existing project was adopted by the River and Harbor Act
of March 3, 1899 (H. Doc. No. 33, 52d Cong., 1st sess.). The latest
published map is in the Annual Report for 1902, page 1038, and in
House Document No. 859, Sixtieth Congress, first session.
           RIVERS AND HARBORS-WASHINGTON,                                                       D.   C., DISTRICT               347
   Terminal facilities.-In general, the improvement is a main river
channel, and terminal facilities are only served where the channel
runs close to either bank of the river. In all, 23 wharves are thus
served. These wharves are of open and solid fill construction and
bulkhead type. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year.-Maintenance dredging
by the Government dredge Talcott was in progress at Mattawoman,
Upper Smith Point, Lower Smith Point, and Maryland Point Bars
from August 28, 1943, to December 11, 1943. A total of 1,385,588
cubic yards was deposited on adjacent flats at a cost of $112,952.93.
   Water chestnut growth (Trapa natans) was removed from areas
adjacent to the channel from Fort Washington, Md., to Mount Vernon,
Va., and tributaries within these limits by Government-owned under-
water cutting machines and hired labor. During July and August
1943, a total of 1,385 acres was removed at a cost of $21,262.99. Re-
moval operations during May and June 1944 were prosecuted with
funds furnished by another agency and during this period a total of
2,608 acres of heavily infested areas and 1,511 acres of scattered growth
was cut. A total of 4,119 acres was cleared of the plant growth.
   Total costs for the year were $134,215.92, all for maintenance. Total
expenditures were $135,730.59.
   Condition at end of fiscal year.-The existing project was completed
in 1905. Controlling depths for a width of 200 feet were as follows:

                                        Name of bar                                                      Controlling
                                                                                                           depth           Date

                                                                                                            Feet
Naval Magazine -.-     .-.................---------------                                                      23.7    June 1944.
Marshall Hall ....------------------------------------------------------                                       23. 7   May 1943.
Mattawoman                 --                                                                                  25. 0   April 1944.
Upper Smith Point .---------------------                                          -------                      26. 3   November 1943.
Lower Smith Point-Maryland Point                                                                               25. 4      Do.
Kettle Bottom -.. . . . . . .. . . . . . ..                  . . . ....   . . . . . ..      . . . .25.             3   August 1939.



  Total costs were $761,538.86, of which $153,836 was for new work and
$607,702.86 for maintenance, which includes $1,000 for each of the fol-
lowing tributaries: Little Wicomico River, Va.; Herring Creek, Md.;
Coan River, Va.; and $20,000 under allotments to tributaries for water
chestnut eradication. Total expenditures were $761,538.86.
  Proposed operations.-The balance unexpended June 30, 1944,
$9,084.74, and an allotment of $75,000 made during July 1944, a total
of $84,084.74, will be applied as follows:
Maintenance:
    Eradication of water chestnut growth by Government plant and
      hired labor downstream of the District of Columbia boundary
      line on the main river and tributaries (July 1, 1944, to June
      30, 1945)    -     -    ---                                   $59, 084. 74
    Dredging by contract approximately 80,000 cubic yards at
      Marshall Hall bar(June 1945)_--         -----           ___    20, 000.00
    Preparation of-disposal area with hired labor and Government
      plant in Oxen Run for disposal of material dredged from
      Marshall Hall bar (May 1, to June 30, 1945)-                    5, 000. 00
            Total                                           ------                                                      84, 084. 74
348         REPORT OF CHIEF OF ENGINEERS,                                   U.             S. ARMY,          1944

   The/additional sum of $41,000 can be expended profitably for mainte-
nance during the fiscal year 1946 for the eradication of water chestnut
growth by Government plant and hired labor (July 1, 1945, to June 30,
1946).
   The operations proposed for the fiscal year 1946 exceeds the average
expenditures for maintenance during the preceding 5 years as this
amount is required for follow-up cutting of scattered growth in the
extensive areas of heavily infested growth that were cut during the
1944 operations. This will hold the material progress made with
funds in the amount of $75,000 contributed by the United States Public
Health Service and will expedite eradication of the plant from this
river.
                                        Cost and financial summary
Cost of new work to June 30, 1944____                                                                            $153, 836. O0
Cost of maintenance to June 30, 1944                                                                               607, 702. 86

           Total cost of permanent work to June 30, 1944                                   -                       761, 538. 86

Net total expenditures _                                                                                           761, 538. 86
Unexpended balance June 30, 1944                               --                                                    9, 084. 74

           Total amount appropriated to June 30, 1944                                                              770, 623. 60


   Fiscal year ending June 30                1940            1941                1942                 1943               1944


Cost of new work .    . .     .   .    i              ..                              ..                     i      .............
Cost of maintenance      _-                $11, 011. 17    $5, 511. 76      $8, 529. 91             $12, 257, 67      $134, 215.92

Total expended---------------               10,000.00      '4, 690.86       10, 70. 81              10,743.00           135, 730.59
Allotted         .....                       4,000.00
                              ..-----------------------    140,000.00       10, 00.00                17, 000 00-


Balance unexpended July 1, 1943 ..                                                                               $144, 815. 33
Gross amount expended ____-                                                     ---                                135, 730. 59

           Balance unexpended June 30, 1944                                                 -                        9, 084. 74
Amount allotted in July 1944                                                                    _                   75, 000. 00

           Amount available during fiscal year 1945                      -84,                                            084. 74

Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1----------------------------------                                                     41, 000. 00
1Exclusive of available funds.


                     5. POTOMAC RIVER AT MOUNT VERNON, VA.

   Location.-Mount Vernon lies in Fairfax County, Va., on the right
bank of the Potomac River about 141/2 miles below Washington, D. C.
 (See U. S. Coast and Geodetic Survey Chart No. 560.)
   Existing project.-This provides for dredging a channel 200 feet
wide and 9 to 10 feet deep, at mean low water, between the main
channel of the Potomac River and the Mount Vernon Wharf, a dis-
tance of about 2,200 feet, with a turning basin of the same depth
and a radius of 200 feet at the wharf. Tidal ranges are: Mean, 2.2
feet; irregular, 3 feet; and extreme, 9.7 feet.
   The estimate of the total cost of the project made in 1888 was
$26,000. There is no approved estimate for annual cost of mainte-
nIance.
               RIVERS AND                  HARBORS-WASHINGTON,                                                        D.   C.,       DISTRICT              349

  The existing project was authorized by the following river and
harbor acts:

       Act                                Work authorized                                                                        Documents


Mar. 3, 1879         Channel 6 to 7 feet deep, 150 feet wide, from Po-                                        Annual Report, 1879, vol. 1, p. 83.
                      tomac River channel to Mount Vernon wharf,
                      with turning basin at wharf.
                     Channel increased to 9- to 10-foot depth, 200-foot                                       Annual Report, 1888, vol. 1, p. 814.
                      width, turning basin to have 200-foot radius.



   Terminal facilities.-There is one privately owned and operated
wharf on the Mount Vernon estate at the head of the channel.
   Operations and results during fiscal year.-Water chestnut growth
(Trapa natans) in and adjacent to the channel and turning basin
was removed during July and August 1943 by Government under-
water cutting machines which were operated by hired labor at a total
cost and expenditure for the year of $5,555.79 applied to mkintenance.
   Condition at end of fiscal year.-The existing project was partially
completed in 1891. The controlling depth in May 1944 for a chan-
nel width of 50 feet was 8.3 feet and 6 feet for a 90-foot channel.
Total costs and expenditures under the existing project were $37,950,
of which $17,000 was for new work and $20,950 for maintenance.
   Proposed. operations.-An allotment of $4,000 made during July
1944 will be applied to the eradication of the water chestnut growth
(maintenance) at Mount Vernon, Va., by Government plant and
hired labor (July 1, 1944, to June 30, 1945).
   The additional sum of $2,500 can be expended profitably fbr
maintenance during the fiscal year 1946 for the eradication of water
chestnut growth with Government plant and hired labor (July 1,
1945, to June 30, 1946).
                                              Cost and financial summary
Cost of new work to June 30, 1944 _--                                                                                            -                  $17, 000. 00
Cost of maintenance to June 30, 1944 -                                                                        ----                                   20, 950. 00

       Total cost of permanent work to June 30, 1944- -                                                                                     _        37, 950. 00
Net total expenditures __                                                                                                        ____                37, 950. 00
Total amount appropriated to June 30, 1944       --                                             -                            -                       37, 950. 00


    Fiscal year ending June 30                           1940                            1941             ,    1942                  1943               1944

Cost of new work --         ---     -     -    --         --.....         ..        .....-                           ..                -..
Cost of maintenance -------                    -------                                   $1,588. 06           $2,228. 79             $627. 36           $5, 555. 79
Total expended -----------......                                               .I        1,548. 53    1        2,268.32               627.36             5,555.79

Allotted_                -         -$4,                             000                  4,000.00             2,000.00                          -              -




Balance unexpended July 1, 1943
Gross amount expended
                                                                    __$5,      --               -5,
                                                                                                                                                        555. 79
                                                                                                                                                        555. 79

Amount allotted in July, 1944                                       ---                                                                               4, 000. 00
Amount available during fiscal year 1945                                                                                                              4, 000. 00
Amount that can be profitably expended in fiscal year ending June
    30, 1946, for maintenance                                                   -                                                                     2, 500. 00
   I Exclusive of available funds.
350     REPORT OF CHIEF OF ENGINEERS,         U. S. ARMY,   1944

                       6. OCCOQUAN CREEK, VA.

   Location.-Occoquan Creek is formed by the junction of Bull and
Broad Runs, about 5 miles southeast of Manassas, Va., and flows about
13 miles in a southeasterly direction, emptying into the Potomac River
about 26 miles below Washington, D. C. (See U. S. Coast and Geo-
detic Survey Chart No. 560.)
   Previous projects.-The original project was adopted by the River
and Harbor Act of March 3, 1873. For further details see page
1792, Annual Report for 1915, and page 363, Annual Report for 1936.
   Existing project.-This provides for a channel 6 feet deep and 150
feet wide from deep water in the Potomac River to Taylors Point, and
thence 100 feet wide to the town of Occoquan, 6 miles from the mouth,
and the protection of the channel above Taylors Point by riprap-stone
dikes 2,200 feet long.o   The plane of reference is mean low water.
Tidal ranges are: Mean, 2 feet; irregular, 3 feet; extreme, approxi-
mately 8 feet.
   The estimate of cost for new work, revised in 1907, is $64,000, exclu-
sive of expenditures on previous projects. The latest (1923) approved
estimate for annual cost of maintenance is $3,000.
   The existing project was adopted by the River and Harbor Act of
September 19, 1890 (H. Doc. No. 75, 51st Cong., 1st sess.); was modi-
fied December 5, 1890 (see Annual Report for 1890, p. 1089, and for
1891, p. 1254); and was extended by River and Harbor Act of March
2, 1907 (H. 'Doc. No. 190, 59th Cong., 1st sess.). The latest published
map is in House Document No. 661, Sixty-third Congress, second
session.
   Terminal facilities.-There are 10 landings or wharves in Occo-
quan Creek. The principal terminal is solid fill and open-pile struc-
ture; all the other wharves or landings are solid bulkhead structures.
The terminal facilities are considered sufficient for the present traffic.
   Operations and results during fiscal year.-Removal by hired labor
of scattered water chestnut growth (Trapanatans) was in progress in
Belmont Bay and Occoquan Bay and Creek during July 1943 at a
total cost of $2,000. Through these operations the infestation was
confined to one small area in Belmont Bay. Total costs and expendi-
tures for the year were $2,000, applied to maintenance.
   Conditionat end of fiscal year.-The existing project was 92 percent
completed; the only work remaining is the construction of the dike at
Upper Mud Bar,'which is not at present considered necessary. Stone
dikes aggregating 1,953 linear feet were built and channels aggregat-
ing 2.6 miles were dredged. The controlling depth was 6.4 feet over
Occoquan Bar in March 1938. Total costs and expenditures were
$132,704.97, of which $41,252.95 was for new work and $91,452.02 for
maintenance.
   Proposed operations.-The balance unexpended and an allotment
of $2,500 made during July 1944 will be applied for the eradication of
the water chestnut growth (maintenance) at Occoquan Creek, Va.
 (July 1, 1944 to June 30, 1945).
   The additional sum of $3,000 can be expended profitably for main-
tenance during the fiscal year 1946 by the eradication of water chestnut
growth with Government plant and hired labor (July 1, 19.45 to
June 30, 1946).
          RIVERS AND HARBORS-WASHINGTON,                                          D.     C.,       DISTRICT           351
                                    Cost and financial summary
Cost of new work to June 30, 1944                                                                             $66, 252. 95
Cost of maintenance to June 30, 1944-------------------------                                                  91, 452. 02
        Total cost of permanent work to June 30, 1944------------                                             157, 704. 97

Net total expenditures_ ------------------------------------  157, 704. 97
Unexpended balance June 30, 1944-----------------------------      781. 88
        Total amount appropriated to June,30, 1944-- -------                                                  158, 486. 85

   Fiscal year ending June 30         1940             1941                1942                    1943            1944

Cost of new work.... .. .....         . .. .....
Cost of maintenance_- ........            $150     $2,153.72           $2,072.92               $2, 841.48             $2,000

Total expended.------------------         1, 200       2,303. 72           2,072. 92               2,841.48               2,000

Allotted-------------------------         4,000        4, 000.00           2,000.00


Balance unexpended July 1, 1943_ _                   -                      -                  -               $2, 781. 88
Gross amount expended_---------------------------------                                                         2000.
                                                                                                                2,      00,
     Balance unexpended June 30, 1944------------------------                                                      781. 8&
Amount allotted in July 1944 ----------------------------                                                       2500.
                                                                                                                2,    00
        Amount available during fiscal year 1945----------                                                      3,281. 88

Amount (estimated) required to be appropriated for completion of
   existing project 1_-_-                          -           -       -               -___                    22, 700. 00
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance           1                  -----------                                            3, 000. 00
IExclusive of available funds.

                           7. LITTLE WICOMICO RIVER, VA.

   Location.-Little Wicomico River is a tidal estuary 6 miles in
length lying in Northumberland County, Va., flowing in a south-
easterly direction to the Potomac River, which it enters on the right
bank one-half mile upstream of its mouth. (See U. S. Coast and
Geodetic Survey Chart No. 557.)
   Existing project.-This provides for a channel 8 feet deep, 150
feet wide and 4,800 feet long, extending from deep water in Potomac
River to deep water in Little Wicomico River, for two stone jetties
extending to the 8-foot contour in Potomac River, and for bulkhead
walls from the inner ends thereof extending sufficiently into Little
Wicomico River to stabilize the dredged inner channel. The plane
of reference is mean low water. The mean tidal range is 1.2 feet in
the Potomac River at the entrance and about 1.0 foot within the
river, with winds causing variations of 2 to 3 feet.
   The estimate of cost for new work, made in 1935, was $75,000, in-
cluding $5,000 contributed by local interests. The latest (1935) ap-
proved estimate for annual cost of maintenance is $2,000.
   The existing project was adopted by the River and Harbor Act
of August 30, 1935 (Rivers and Harbors Committee Doc. No. 24, 74th
Cong., 1st sess.). The latest published map is in the project
document.
   Local cooperation.-Fully complied with.
352            REPORT OF CHIEF OF ENGINEERS,                               U.        S. ARMY,                     1944


   Terminal facilities.-There are two wharves open to the public and
numerous small wharves and stagings for private use, an oyster
-shucking and packing plant, and a marine railway and boatbuilding
yard. These facilities are considered adequate for present commerce.
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1937. The controlling depth was 2.3 feet at mean low water
for a 150-foot width and 4 feet for a width of 50 feet in July 1943
in the entrance channel between the jetties. Total cost and expendi-
tures under the existing project were $96,913.27, of which $81,885.43,
was for new work and $15,027.84 for maintenance. In addition,.
$5,000 contributed funds was expended for new work.
   Proposed operations.-None during the fiscal year 1945. The sum
of $18,800 can be expended profitably during the fiscal year 1946 as
follows:
Maintenance:
    Dredging by contract, approximately 35,000 cubic yards from the
      entrance channel between the jetties (July 1945)              $9, 800
    Repairs to jetties by contract (Aug. 1, to Oct. 31, 1945) - - -  9, 000

            Total-           -----                                     -18,                                                      800

   The operations proposed during the fiscal year 1946 exceed the
average expenditures for maintenance during the preceding 5 years
as no maintenance dredging has been performed since the completion
of the project in 1937 and it is necessary to raise the stone jetties in
order to prevent encroachment of sand on the entrance channel.
                                       Cost and financial summary
Cost of new work to June 30, 1944 __--                                 _                  -                 _-     1$81, 885. 43
C'ost of maintenance to June 30, 1944                                  --                             - __--       -15,   027. 84

            Total cost of permanent work to June 30, 1944                                        -          _         96, 913. 27
Net total expenditures  _     _- _ __ __ _                             - -                             _____        1 96, 913. 27
Total amount appropriated to June 30, 1944_                                     -     -       - - -   _-     _      196, 913. 27

    Fiscal year ending June 30           1940         1941                   1942                          1943           1944

Cost of new work_ -
Cost of maintenance------              $10,159. 63    $1,503.60                     $27. 84

Total expended           -    - -        4, 510. 38   7,152. 85                      27. 84-
Allotted .............                   2,500.00     5,000.00     -                              -$11,472.16               ----




Amount that can be profitably expended in fiscal year ending June 30,
                              -----------
    1946, for maintenance _____        ____-           -_         -$18,                                                   800. 00
  1In addition, $5,000, contributed funds expended for new work.


                                     8. ST. JEROMES CREEK, MD.

  Location.-St. Jeromes Creek is a tidal estuary in St. Marys County,
Id., on the western shore of the Chesapeake Bay, 6 miles north of
Point Lookout, at the mouth of the Potomac River. (See U. S. Coast
and Geodetic Survey Chart No. 557.)
  Previous project.-The original project for improvement was
adopted by the River and Harbor Act of March 3, 1881. For further
           RIVERS AND              HARBORS-WASHINGTON,                              D.    C., DISTRICT        353
details see Annual Report for 1890, page 114, and Annual Report for
1938, page 432.
   Existing project.-This provides for a channel 100 feet wide and 7
feet deep from Chesapeake Bay to the vicinity of Airedele, thence
60 feet wide to deep water in the creek, with a turning basin of the
same depth 200 feet wide and 300 feet long opposite Airedele. The
project is 4,900 feet long. The plane of reference is mean low water.
The mean range of tide is 1.3 feet, with variations due to winds
of 1 to 3 feet.
  The estimate of cost for new work made in 1937 was $19,500, exclusive
of amounts expended under previous projects. The latest (1937) ap-
proved estimate for annual cost of maintenance is $1,600.
  The existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. No. 174, 75th Cong., 1st sess.). The latest
published map is in the proper document.
  Local cooperation.-Fullycomplied with, except that local interests
are to furnish spoil-disposal areas for future maintenance as needed.
   Terminal faoslities.-There are 10 privately owned wharves, 2 of
which are open to the public. It is considered that the present terminal
facilities are adequate for present and prospective commerce.
   Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depth in May 1944 was 4.1 feet in the entrance
channel. Total costs and expenditures under the existing project were
$17,856.95, all for new work.
  Proposed operations.-None during fiscal year 1945.
  The sum of $11,750 can be expended profitably during the fiscal year
1946 for maintenance dredging by contract.
                                        Cost and financial summary
Cost of new work to June 30, 1944                                                                      $44, 356. 95
Cost of maintenance to June 30, 1944__
        Total cost of permanent work to June 30, 1944--------- ---                                      44, 356. 95
Net total expenditures_                                 ----------                                      44, 356. 95
Total amount appropriated to June 30, 1944                                -----                         44, 356. 95

   Fiscal year ending June 30             1940     *     1941                1942               1943       1944

Cost of new w ork- - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - -
C ost of m ainte  ee -.n- - - - - -- - - - - - - - - - - - - -- - - - - - - -.. .. .. . . . . . . .
Total expended . .    .   .   .    .-                                [-
Allotted___-                                      05
                                                 ------------------------

Amount that can be profitably expended in fiscal year
                                                      ending June
   30, 1946 for maintenance_----------                                                   ----          $11, 750.00

                                  9. RAPPAHANNOCK RIVER, VA.

  Location.-Rappahannock River rises in the Blue Ridge Mountains,
in Virginia, and flows southeasterly about 212 miles to enter Chesa-
peake Bay, about 40 miles north of Old Point Comfort. (See U. S.
Coast and Geodetic Survey Charts Nos. 534, 535, 536.)
  Previous projects.-The original project was adopted by the River
and Harbor Act of March 3, 1871, and modified in 1879. For further
        616634       45   pt. 1, vol. 1      23
354     REPORT OF CHIEF OF ENGINEERS,                          U. S. ARMY,   1944

details see page 1793 of Annual Report for 1915 and page 433 of An-
nual Report for 1938.
   Existing project.-This provides for a channel 12 feet deep and
200 feet wide between the mouth and Port Royal and 12 feet deep
and 100 feet wide between Port Royal and Fredericksburg by dredg-
ing and the construction of 20,401 feet of crib and pile dikes and
1,906 feet of riprap-stone dikes, the dikes being designed to retain
the excavated material deposited behind them. The length of sec-
tion included in the project is 107 miles. The plane of reference is
mean low water. Tidal ranges are: Mean, 2.8 feet at Fredericks-
burg, 1.6 feet at Tappahannock; irregular 3.5 feet at Fredericksburg,
2.5 feet at Tappahannock; extreme, 6 feet at Fredericksburg, 5 feet
at Tappahannock.
   The estimate of cost for new work, made in 1905, was $171,000, ex-
clusive of amount expended on previous project. The latest (1926)
approved estimate for annual cost of maintenance is $22,000.
   The existing project was adopted by the River and Harbor Act
of March 3, 1905 (Annual Report for 1906, pp. 1110-1113). The
latest published map is in the Annual Report for 1910, page 1364.
   Terminal facilities.-In the section under improvement extending
from Fredericksburg, Va., to Tappahannock, Va., a distance of 65
miles, there are 26 wharves, of which 9 are solid bulkhead type and
17 are open pile structures. From Tappahannock to the mouth there
are 15 open pile wharves. Most of the wharves are open to the public.
The terminals are considered adequate for existing commerce.
   Operations and results during fiscal year.-None. The cost was
$278.96 and the expenditure $8,397.35 for accounts payable from the
preceding fiscal year.
   Conditionat end of fiscal year. The existing project was completed
in 1910. Th'e controlling depth was 8.5 feet at Fredericksburg bar op-
posite the Standard Oil wharf and 9.4 feet at Upper Spottswood bar
in April 1944. The total cost and expenditures under the existing
project were $801,831.40, of which $217,487.20 was for new work and
$584,344.20 for maintenance, which includes $994.59 for Parrotts
Creek and $1,000 each for Greenvale, Mill, and Beach Creeks and
$1,600 for Queens Creek, of which $600 was contributed by local in-
terests.
   Proposed operations.-Thebalance unexpended June 30, 1944, of $3,-
579.71, will be applied to the removal of additional submerged ob-
structions, resulting from the record flood of October 16, 1942.
   The sum of $72,000 can be expended profitably during the fiscal
year 1916 as follows:
Maintenance:
    Dredging by contract, approximately 312,000 cubic yards at 8 bars
      upstream of Tappahannock, Va. (Sept. 1, to Oct. 31, 1945) -- - - $52, 000
    Repairing timber dikes near Fredericksburg, Va., by Government
      plant and hired labor (July 1, to Sept. 15, 1945) --------------- 20, 000
        Total ----------------------------------------------                        72,000
   The operations proposed for the fiscal year 1946 exceed the average
expenditures for maintenance during the preceding 5 years as repairs
to the timber dikes have been deferred during the war period. The
dikes are now in a dilapidated condition and dredging is required to
restore project dimensions for important navigation.
               RIVERS AND HARBORS-WASHINGTON,                                           D. C., DISTRICT               355
                                     Cost and financialsummary
Cost o f new work to June 30, 1944__                                                                       $414, 633. 03
Cost o f maintenance to June 30, 1944-                                                                     1 697, 244. 20

            Total cost of permanent work to June 30, 1944_ _-1,                                                111, 877. 23

Net to tal expenditures__----------------                                                                11, 111, 877. 23
Unexp )ended balance June 30, 1944 __                                                                          3, 579. 71

            Total amount appropriated to June 30, 1944                              --       -           11, 115, 456. 94'

    Fiscal year ending June 30           1940             1941                   1942             1943             1944


Cost of new work
Cost of maintenance-----.-----$25, 738. 26___                          _------               $18, 420. 29-..
Total expended -----------------
                     ........           24, 604. 72      $1, 133.54 --------------
                                                                          ...                    10, 0229.94       $8, 397. 35

Allotted_ .......       ....------ ___--...     -     --- 9, 261. 74             $25, 000    -3, 000. 00

Balance unexpended July 1, 1943__---                                                                           $11, 977. 06
Gross amount expended_                                                                                           8, 397. 35

            Balance unexpended June 30, 1944-                                                                    3, 579. 71

Amount that can be profitably expended in fiscal year ending
June 3C, 1946 for maintenance 2                                                                                72, 000. 00
  1 In addition, $600 contributed funds was expended for maintenance on Queens Creek.
  2 Exclusive of available funds.


                                   10. TOTUSKEY CREEK, VA.

   Location.-Totuskey Creek, located in Richmond County, Va.,.flows
in a southerly direction about 15 miles to the Rappahannock River,
which it enters on the left bank about 35 miles upstream of its mouth.
(See U. S. Coast and Geodetic Survey Chart No. 535.)
   Previous projects.-After a survey and examination authorized by
the River and Harbor Act of June 23, 1874, appropriations were made
by River and Harbor Acts of June 14, 1880, March 3, 1881, and August
2, 1882. For further details, see page 403 of Annual Report for 1937.
    Existing projet.-This provides for a channel 8 feet deep, 150 feet
wide through the bar at the mouth, and 80 feet wide upstream to
Totuskey Bridge, a distance of about 41/2 miles, and the repair of
dike at Booker Bar constructed under the previous project. The
plane of reference is mean low water. The mean tidal range is 1.6
feet at the mouth and 2 feet at Totuskey Bridge, with winds causing
variations of 2 to 3 feet.
   The estimate of cost for new work made in 1931 was $36,000, exclu-
sive of amount expended on previous projects, but including $1,000
contributed by local interests. The latest (1935) approved estimate
for annual cost of maintenance is $2,000.
   The existing project was adopted by the River and HIjarbor Act of
August 30, 1935 (H. Doc. No. 183, 72d Cong., 1st sess.). The latest
published maps are in the project document.
   Recommended modifcations of project.-Under date of March 21,
1940, the Chief of Engineers recommended modification of the exist-
ing project so as to provide a channel 10 feet deep from that depth
in Rappahannock River to and including a turning basin below
Totuskey Bridge, with a width of 150 feet through the bar at the
356            REPORT OF CHIEF OF ENGINEERS,                                                    U.      S.        ARMY,          1944

entrance and 100 feet thence upstream, suitably widened at bends,
at an estimated total first cost of $45,000, with annual maintenance
of $1,500 in addition to that now required, subject to certain condi-
tions of local cooperation (H. DQc. No. 686, 76th Cong., 3d sess.).
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are 2 county-owned wharves and 13 pri-
vately owned wharves or landings. Terminal facilities are considered
adequate for exising and future commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1937. The controlling depth in May 1944 was 7.1 feet on Mouth
bar at the entrance of the project. Total cost and expenditures under
the existing project were $54,148.46, of which $27,648.46, United States
funds, and $1,000, contributed funds, were for new work arid $25,500
for maintenance.
   Proposed operations.-None during fiscal year 1945. The sum of
$6,000 can be expended profitably during the fiscal year 1946 for
maintenance dredging by contract of 30,000 cubic yards from the en-
trance channel during September 1945.
                                              Cost and financial summary
Cost of new work to June 30, 1944 _                                                                                                  1 $37, 648. 46
Cost of maintenance to June 30, 1944_-----                                                                    -__                       25, 500. 00
       Total cost of permanent work to June 30, 1944                                                        --                        '63,  148. 46
Net total expenditures ___                                                                                                            1 63, 148. 46
Total amount appropriated to June 30, 1944                                                                    -                  -      63, 148. 46

   Fiscal year ending June 30                 1940                   1941                            1942               1943                 1944


C ost of new work ...    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cost of maintenance       ....-------------     $25, 500-----------------                             --------------------------
Total expended      .....------------------      25, 500     -------..............----------------

Allotted ------------------------.
          .......   .                            25, 500 -          -       -        -                $10, 000          -$10, 000      .


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance________---------                     _                                                                      $6, 000. 00
  1 In addition, $1,000 contributed funds was expended for new work.

       11.    EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                                     (GENERAL)
   The cost of work during the fiscal year amounted to $17,271.99 and
expenditures were $10,174. The balance unexpended June 30, 1944,
$17,356.49 together with an allotment of $20,000 made during July
1944, a total of $37,356.49, will be applied as needed during the fiscal
year 1945 to payment of expenses incurred under this heading.
  The additional sum of $25,000 can be expended profitably during
the fiscal year 1946.
                                              Cost and financial summary
Cost     of   new work     to     Tune 30       1944
Cost cf maintenance to June 30, 1944                                        -$764,                                                           78t. 35

              Total cost of permanent work to June 30, 1944--                                                                         764, 781. 35
Minus accounts payable June 30, 1944-                                                          -                    -      - -          3, 630. 08

      Net total expenditures -761,                                                                                                           151. 27
Unexp ended balance June 30, 1944_ '                                                                                                    17, 356.49

              Total amount appropriated to June 30, 1944---------- ---                                                                778, 507. 76
               RIVERS        AND HARBORS-WASHINGTON,                                             D.        C.,     DISTRICT                 357

      Fiscal year ending June 30               1940                 1941                  1942                      1943             1944


(ost of new work
Cost of maintenance------------$57, 539. 21                       $52, 016.23           $79, 195. 93             $22, 089. 89       $17, 271. 99
Total expended ........-----------------.    63, 579.32            51,101. 99            75, 037. 85               31, 941. 95       10,174. 00

Allotted- ._.-------...--------------68,000.                       71,000.00            17, 000.00                 40, 000. 00 --


Balance unexpended July 1, 1943__     -$27,                                                                                          530. 49
Gross amount expended.                      -   -   $13, 642. 41
Less reimbursements collected ---------------------   3, 468. 41
                                                                                                                                 10, 174. 00

      Balance unexpended June 30, 1944                                                                                           17, 356. 49
Outstanding liabilities June 30, 1944  -                                          --     -3,                                         630. 08

     Balance available June 30, 1944.                                       ---                                                  13, 726. 41
Amount allotted in July 1944_    ---                                                                         -20,                    000. 00

            Amount available during fiscal year 1945.                                  --                                        33, 726. 41

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance '__     - ----             -25,                                                                            000. 00
  1 Exclusive of available funds.

12. OTHER              NAVIGATION               PROJECTS FOR WHICH NO ESTIMATES
                                               ARE SUBMITTED

                                                                 For last full         Expenditures to June 30,                  Estimated
                     Name of project                              report see                    1944                             amount re-
                                                                 Annual Re-                                  ---                  quired to
                                                                  port for-            New work             Maintenance           complete


1. Accotink Creek, Va.1                                             1878                $5,000.00                                     $14,000
2. Neabsco Creek, Va.                                               1884                 5,000.00                                      20,000
3. Aquia Creek, Va.2                                                1928                52, 464.84              $11,750.00           (3)
4. Potomac River at Lower Cedar Point, Md.2__                       1920                10, 233.51                6, 216. 49         (3)
5. Upper Machodoc Creek, Va.2    -         -                        1916                20, 281.28                6,118. 72          (3)
6. Monroe Bay and Creek, Va.2                                       1940                12, 460.07               18, 793. 63         (3)
7. Neale Soumd, Md.2                                                1939              4 12, 600.00          8                        (3)
8.   Breton Bay, Md2                                                1936                47,923.55             11,879.00                  7,500
9.   Nomini Bay and Creek, Va.2             -           -           1935                78, 446. 21           30, 841.62                 9, 500
10.   Lower Machodoc Creek, Va.' -.--                                1904                 9,916.47                 600.00             (3)
11.   Coan River, Va.2 5                                             1937          -      -      ---..--     -----                       54, 000
12.   Smith Creek, Md2                                               1936                 5, 252. 22                                 (3)
13.   Patuxent River, Md.2 6 -1905                                                       14,000.00                                        6,000
14.   Cockrells Creek, Va.2                                          1932                      --      --                                59,000
15.   Dymers Creek, Va.2                                             1912                 5, 581.99                 3, 418.01        (3)
16.   Hoskins Creek, Va.2 7                                          1941              8 19, 362. 22                8, 400.00        (3)
17.   Mulberry Creek, Va.2                                           1940                 2, 392. 60                1,767.10         (3)
18.   Urbanna Creek, Va.2 9...........                               1938                38, 811.77               45, 563. 97        (3)
19.   Carters Creek, Va.2' 5                                         1937                28,397. 55              10 2, 190. 93          18,000
20.   Lockiies Creek, Va.2 _                                         1928                11, 581.22                    518. 78       (3)
21.   M ill Creek, Va.2 .............                        .       1937                 5,444.95           -                       (3)
22.   Jackson Creek, Va.2 _.... .              .- ....               1937                 8, 500.00 -.                   -           (3)
23.   Milford Haven, Va.2              - .1937                                           24, 568.25               13, 389. 73        (3)


  1 No commerce reported.
  2 Channels adequate for commerce.
  3 Completed.
  4Exclusive of $1,000 contributed.
  5 Awaiting local cooperation.
  6 Abandonment recommended in 1903. (Rivers and Harbors Committee Doc. No. 32, 61st Cong., 2d sess.).
  7 Modification recommended Nov. 22, 1940, in H. Doc. No. 129, 77th Cong., 1st sess.
  8 Exclusive of $500 contributed.
  o Modification recommended Apr. 20, 1939, in H. Doc. No. 285, 76th Cong., 1st sess.
  to Exclusive of $700 contributed.
  11Exclusive of $4,000 to be contributed.
358          REPORT OF CHIEF OF ENGINEERS,                                        U. S. ARMY,                            1944

             13. PLANT ALLOTMENT, WASHINGTON, D.                                                   C., DISTRICT
                                         Cost and financial summary
Undistributed costs June 30, 1944 ____--                                     -           -          -              -      $499, 727. 76
Plus accounts receivable June 30, 1944_-                                 -----                              ___            169, 495. 03
      Gross total costs to June 30,.1944 --------------                                                                    669, 222. 79
Minus accounts payable June 30, 1944        -_                                                                              41, 270. 31

      Net total expenditures ----------------------------                                                                  627, 952. 48
Unexpended balance June 30, 1944 _194,                                                                                          871. 03

          Total amount appropriated to June 30, 1944                                                                       822, 823. 51

   Fiscal year ending June 30               1940               1941                 1942                          1943           1944

Total expended.....    -        -        $123, 525.86     $100, 644.77           $247, 448. 57          -$456, 548. 40          $76, 755.04

Allotted---------------------
       .......................            245, 473.98        -5, 000.00            67, 300. 00          ----




Balance unexpended July 1, 1943_                     _             -_$271,                                                       626. 07
Gross amount expended _        __                             -_                  -$1,          437, 544. 22
Less reimbursements collected_                                                               1, 360, 789. 18
                                                                                                                            76, 755. 04
      Balance unexpended June 30, 1944                                                   -194,                                   871. 03
Outstanding liabilities June 30, 1944                                        -                    $49, 438. 92
Amount covered by uncompleted contracts_ ....                                                          340. 00
                                                                                                                            49, 778. 92
      Balance available June 30, 1944                                                                             __       145, 092. 11
Accounts receivable June 30, 1944_ _____                                                                                   169, 495. 03
          Unobligated balance available June 30, 1944_                                                                     314, 587. 14

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                                   Date trans-                                             Recommenda-
           Locality                   Authorization act             mitted to                    Document No.                  tion
                                                                    Congress

Anacostia River, D. C., and         Rivers and Harbors
Md.                                  Committee resolu-
                                      tion, Nov. 17, 1937.
Hoskins Creek, Va......---------.   Rivers and Harbors-                                                 -          -
                                      Committee resolu-
                                      tion, May 5, 1943.
Rappahannock River, Va.             Sec. 6, River and Har-      -                            -
 (Sup. 308).                          bor Act, Aug. 30,
                                      1935.
Windmill Point Creek, Va.,          Rivers and Harbors ..................
for improvement of Deep              Committee resolu-
  Hole Creek.                         tion, Mar. 24, 1942.



                            14. WASHINGTON, D. C., AND VICINITY

   Location.-Washington, D. C., is located at the junction of the
Anacostia River with the Potomac River, within the District of Co-
lumbia, 110 miles upstream from the mouth of the Potomac River.
 (See U. S. Coast and Geodetic Survey Chart 560.)
           FLOOD CONTROL--WASHINGTON,          D.   C.,   DISTRICT    359
    Previous project.-A project providing for levees and grade rais-
ing to protect Bolling Field was authorized by the Emergendy Re-
lief Appropriation Act approved June 22, 1936. Items of the project
upon which work remained to be done on June 30, 1937, were trahs-
ferred to the authorized project described in this report for completion.
    Existing project.-This provides for levees and grade raising to
protect the downtown portion of Washington, the Arlington Experi-
mental Farm, Bolling Field, and Anacostia Naval Air Station.
    The estimate of cost of new construction is $522,500 and the esti-
mated cost of land and damages is $16,000.
    The existing project was adopted by the Flood Control Act approved
June 22, 1936 (H. Doc. No. 101, 73d Cong., 1st sess.). The latest pub-
lished maps are in the project document.
    Local cooperation.-See page 7 for requirements. Local coopera-
tion is fully complied with except for the Arlington County area
where protection is no longer required.
    Operations and results during fiscal year.-Repairs to 1,620 feet of
seawall damaged by levee settlement at the Anacostia Naval Air Sta-
tion were commenced October 20, 1943, and completed December 16,
1943, at a cost of $6,219.58, applied to new work. Responsibility for
maintenance of this final section of the levee project was assumed by
the Navy Department, in charge of the property on which the levee
is located, on February 7, 1944.
    Total costs for the year were $6,219.58 and expenditures were
$10,697.03.
    Condition at end of fiscal year.-The project for flood protection
at Washington, D. C., and vicinity, exclusive of the Arlington Experi-
mental Farm levee, was substantially completed in 1939 and fully
completed in December 1943. The Potomac Park levees were com-
pleted in 1939 and levees for the protection of Bolling Field and the
Anacostia Naval Air Station were completed at the end of the fiscal
year 1940, except for retopping of a section of earth levee and repairs
to seawall damaged by levee settlement, which were completed in De-
cember 1943. Maintenance of all flood protective structures has been
assumed by the Government agencies in charge of the property on
which these structures are located. The protection work at the Ar-
lington area is no longer required since the facilities originally to be
safeguarded no longer exist. The construction work for the Penta-
gon involved raising land area, roads, and structures above flood stages.
One or two new local points subject to possible inundation are cov-
ered by an emergency flood operation program.
    The total costs and expenditures of all work were $311,231.42, of
which $204,731.42 was from regular funds and $106,500 from Emer-
gency Relief funds, applied to new work. In addition to the above
costs and expenditures, the sum of $161,995.39 was expended for work
included in the Bolling Field project authorized by the Emergency
Relief Appropriation Act, approved June 22, 1936, uncompleted items
of which were transferred to the authorized project for completion.
   Proposed operations.-None. The balance unexpended June 30,
1944, $4,467.67, was revoked in August 1944. No work is proposed
during the fiscal years 1945 and 1946.
360          REPORT OF CHIEF OF ENGINEERS, U.                                    S. ARMY,                  1944

                                  Cost and financial summary
Cost of new work to June 30, 1944 ____________                                                             1$311, 231. 42
Cost of maintenance to June 30, 1944
          Total cost of permanent work to June 30, 1944                                                     1 311, 231. 42
Net total expenditures _-                              -      -          -                                  1 311, 231: 42
Unexpended balance June 30, 1944 _                     -          ---            -                              4, 467. 67

          Total amount appropriated to June 30, 1944_                        -------------                  1   315, 699. 09

   Fiscal year ending June 30         1940            1941                   1942               1943                     1944


Cost of new work .........           $1, 954. 05    $12, 278. 84               $57. 31        $11, 262. 72               $6, 219.58
C ost of m aintenance...-- - - - - - - - -. -. -...
                                               . . . . . . . . . . . . .-
Total expended ------------------       361.69       13, 429.68                 57. 31          6, 785. 27               10, 697.03

Allotted- -------------------- 20, 000. 00 ..                                             .            -         .....

Balance unexpended July 1, 1943__ ___                                                                           $15, 164. 70
Gross amount expended_ ___       _____                                  __           $15, 736. 83
Less reimbursements collected                      _ __ __ __ _                          5, 039. 80
                                                                                                                 10; 697. 03

          Balance unexpended June 30, 1944___--                                      -           _ _               4, 467. 67
Amount revoked in August 1944.      .       --                                           --                        4, 467. 67
  1 Includes $106,500 Emergency Relief funds. In addition, $161,995.39 was expended for work included in
the Bolling Field project authorized by the Emergency Relief appoupriation Act Approved June 22, 1936.

                     15. CUMBERLAND, MD., AND RIDGELEY, WV. VA.

   Location.-Cumberland,Md., and Ridgeley, W. Va., are located on
the North Branch of the Potomac River, 21 miles upstream from its
junction with the South Branch of the Potomac River and 197 miles
upstream from Washington, D. C. (See U. S. Geological Survey
quiadrangles, Frostburg and Flint Stone, Md., W. Va., and Pa.)
   Existing project.-This provides for levees, retaining walls, a mov-
able dam and channel clearing along both banks of the North Branch
of the Potomac River and of Wills Creek at Cumberland, West Cum-
berland, and South Cumberland, Md., and Ridgeley, W. Va.
   The estimated cost of new construction made in 1932 is $743,400
and the estimated cost of lands and damages is $143,700.
   The existing project was adopted by the Flood Control Act ap-
proved June 22, 1936 (H. Doc. No. 101, 73d Cong., 1st sess.). The
latest published maps are in the project document.
   Local cooperation.-See page 7 for requirements. Local coopera-
tion is pending action by local authorities.
   Operations and results during fiscal year.-Surveys and investiga-
tions including model studies and collection of hydraulic data for
revision of plans and various studies were in progress throughout the
fiscal year. Total costs for the year were $37,086.42, all for new work.
Total expenditures were $33,968.88.
   Condition at end of fiscal year.-A comprehensive study of the
flood problem at Cumberland, Md., and Ridgeley, W. Va., including
field surveys, subsurface explorations, hydrologic and hydraulic in-
vestigations, designs and estimates, has been made. Studies and in-
vestigations for the revision of the plans were 25 percent complete
at the end of the year. The total cost has been $100,158.30, all for
new work. Total expenditures have been $97,040.76.
                     FLOOD CONTROL--WASHINGTON,                                               D.         C., DISTRICT                                 361
  Proposed operations.-The balance unexpended June 30, 1944,
$66,031.12, plus an allotment of $50,000 made in July 1944, a total of
$116,031.12, will be applied as follows:
New work:
       Accounts payable June 30, 1944_ ____                                          _ _ _ ___$3,                                                 129. 58
       Completion of model and other studies and preparation of
         revised plans and specifications by hired labor, July 1944 to
                   _______
           June 1945_                                                            _ _                               -                        112,901.54

             ,Total                                                                                                                    -    116, 031. 12

                                             Cost and financial summary
Cost of new work to June 30, 1944                            __________-_$100,                                                                    158. 30
Cost of maintepance to June 30, 1944_---                                                                                                      -   -      --

      Total cost of permanent work to June 30, 1944                                                           --              -             100, 158. 30
Undistributed costs June 30, 1944                         _ __12.                                                                                     04
      Net total cost to June 30, 1944_                                                                             ___                      100, 170. 34
Minus accounts payable June 30, 1944_                                                     "                                                   3, 129. 58
      Net total expenditures_ _                       ___ __-                                                                  -             97, 040. 76
Unexpended balance June 30, 1944                                                                         --            -                     66, 031. 12

           Total amount appropriated to June 30, 1944                                                    --            -                    163, 071. 88

    Fiscal year ending June 30                    1940                   1941                     1942                      1943                  1944


Cost of new work ...   --          .. .          $5,681.14       $6, 286. 21     .....                      $37, 086. 42
C os t of m a in t en a n c e .d- . . . .    -     .... . . . . . . . . . . . . . . . . . . . . . . . . .. . . .
Total expended ..                                 6, 974. 88             6, 253 25        -_33,                                                       968. 88
Allotted         _             .     -            8, 071. 88                                                           100, 000. 00

Balance unexpended July 1, 1943_                                                                                                           $100, 000. 00
Gross amount expended ___                                    --
                                                         _----_$33,996.08
Less reimbursements collected                                            -                 - -       -                 27. 20
                                                                                                                        -- -33,                   968. 88

           Balance unexpended June 30, 1944------------------------                                                                          66, 031. 12
Outstanding liabilities June 30, 1944 _                                                           ----                                        3, 187. 88

     Balance available June 30, 1944 __                                              -_                                 -          -         62. 843. 24
Amount allotted in July 1944_ ____-                                                                           -___                           50, 000. 00

           Amount available during fiscal year 1945 ------------ _                                                            _             112, 843. 24
Amount (estimated) required to be appropriated for completion of
   existing project 1                    -               -------------                                                                      530, 300. 00
  1 Exclusive of available funds.

16. EMERGENCY REPAIRS AND RESCUE WORK UNDER AUTHORITY OF
   SECTION 5 OF THE FLOOD CONTROL ACT APPROVED AUGUST 18, 1941
   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood.
   Expenditures for the year were $181.42, which were made in pay-
ment of outstanding liabilities for the fiscal year 1943. The balance
unexpended June 30, 1944, amounting to $5,271.92, was revoked in
August 1944.
362            REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,                 1944

                                                      Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944-                                                                                         $44, 728. 08
            Total cost of permanent work to June 30, 1944-                                                   -44,                   728. 08

Net total expenditures_----------------------------------                                                                      44, 728. 08
Unexpended balance June 30, 1944-----------------------------                                                                   5, 271. 92
            Total amount appropriated to June 30, 1944-                                                                        50, 000. 00

    Fiscal year ending June 30                                1940              1941             1942               1943            1944


Cost of new work...
Cost of maintenance .----                                                                  -        -          $44, 728. 08
Total expended ._                     ..                                                                .       44, 546.66            $181.42

Allotted..       .......---------------.-- -...           -                                                     50, 000. 00


Balance unexpended July 1, 1943--------------------------------$5, 453. 34
Gross amount expended----------------------------------------      181. 42
     Balance unexpended June 30, 1944-----------------                                                                            5, 271. 92
Amount revoked in August 1944                                                                                                     5, 271. 92

17. PRELIMINARY                            EXAMINATIONS, SURVEYS,                                       AND     CONTINGENCIES
                                              FOR FLOOD CONTROL

  The costs for the year were $379,714.65 and expenditures were
$400,225.71. The balance unexpended on June 30, 1944, $34,199.08,
plus $30,000 allotted in July 1944, a total of $64,199.08, will be applied
as needed during the fiscal year 1945 to payment of expenses to be
incurred under this heading. The additional sum of $10,000 can be
profitably expended during fiscal year 1946.
                                                      Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944----------------- -----                                                                 $610, 006. 66
       Total cost of permanent work to June 30, 1944 ------------                                                             610, 006. 66
Undistributed costs June 30, 1944-----------------------------                                                                     425. 09
       Net total cost to June 30, 1944--------------------------                                                              610, 431. 75
Plus accounts receivable June 30, 1944------------------ ------                                                                17, 100. 57

      Gross total costs to June 30, 1944---------------- -----                                                                627, 532. 32
Minus accounts payable June 30, 1944---- ---------------                                                                       14, 981. 40
      Net total expenditures_-------------------------                                                                        612, 550. 92
Unexpended balance June 30, 1944----- -----------------------                                                                  34, 199. 08
            Total amount appropriated to June 30, 1944---------                                                               646, 750. 00

    Fiscal year ending June 30                                1940              1941             1942               1943             1944

Cost of new work ....
Cost of maintenance---...----..--....--           -       $36, 286.89        $17, 577.92       $10,074. 65    $141,883. 36         $379, 714.65
Total expended..............----------------               39, 436.12         18, 319.60         9,956. 61     124,034. 60          400, 225.71
Allotted-----------------                             -                 -----------              9, 500.00     284, 250.00          203,100 00
                 FLOOD CONTROI---WASHINGTON,                                                D.   C., DISTRICT                  363
Balance unexpended July 1, 1943_ _________         ____$231,                                                                 424. 79
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941-             $100, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942-----------103, 000. 00
                                                                                                                      203, 000. 00

       Amount to be accounted for_                                                                     ___            434, 424. 79
Gross amount expended_-____-                                                                     $411, 849. 00
                              -----------------
Less reimbursements collected__                                                                    11, 623. 29
                                                                                                                      400, 225. 71

       Balance unexpended June 30, 19199.
                                       1944                                                                            34,          08
Outstanding liabilities June 30, 1944_---------------                                             $14, 911.53
Amount covered by uncompleted contracts- ----                                                       5, 693. 04
                                                                                                                       20, 604. 57

      Balance available June 30, 1944--------------------------                                                        13, 594. 51
Accounts receivable June 30, 1944_ _--17,                                                                                  100. 57

     Unobligated balance available June 30, 1944--                                                        -            30, 695. 08
Amount allotted in July 1944           _                                                         -30,                      000. 00

           Amount available during fiscal year 1945                                                                     0, 695. 08
                                                                                                                       6-----------------
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance                 1_ ____________----                        -               -10,                 000.00
  1 Exclusive of available funds.

18. OTHER             FLOOD-CONTROL PROJECTS FOR WHICH                                                                NO     ESTI-
                             MATES ARE SUBMITTED

                                                              For last full Cost and expenditures to                    Estimated
                          projectof of
                         Name                                  report see         June 30, 1944                          amount
                         project
                         Name                                 Annual Re- -required                                              to
                                                               port for-            New work            Maintenance      complete

1. Harpers Ferry, W. Va.
                     1     ---------------------                    1937      ---------------                                $164. 900
2. Moorefield, W. Va. ------------------------                      1940                $7,928.12       -----                 158,270

1 Awaiting local cooperation.

Status of all investigations for flood control called for by flood-control acts and
                                committee resolutions

                                                                      Date trans-
           Locality                 Authorization act                  mitted to                 Document No.         Recommenda-
                                                                        Congress                                          ti

Anacostia River and tribu- Flood             Control      Act, ..................
taries.                           June 22, 1936.
Garden Creek,     Mathews        Flood Control            Act,-- ........------------------
County, Va.                       Aug. 18, 1941.
Potomac River and tribu-         Flood Control            Act, ..............................
taries.                           May 5 1936.
Potomac River and tribu-         Flood Control            Act, ...                  -
taries.                            June 22, 1936.
Potomac River, North             Flood Control            Act,-...........................
Branch of, and tributa-           Aug. 28, 1937.
ries, in the vicinity of
Keyser, W. Va.
Rappahannock River, Va.          Sec.       6, River and._ ...............................
 (supplemental 308).                     arbor Act, Aug.
                                    3,     1935.
Rappabannock River, and          Flood Control Comn-..............................
tributaries, Virginia.            mittee resolution,
                                   Nov. 24, 1942.
364      REPORT OF CHIEF OF ENGINEERS,                U.   S.   ARMY,   1944

   IMPROVEMENT OF RIVERS AND HARBORS IN THE
             NORFOLK, VA., DISTRICT
     This district comprises a small portion of southeastern West Vir-
ginia, central and eastern Virginia, and a portion of northern North
Carolina embraced in the west shore drainage basins tributary to
the southern part of Chesapeake Bay south of the watershed line be-
tween the northerly arm of Winter Harbor and Garden Creek, Va.,
and the eastern shore drainage basins south of and including Onan-
cock River, Va.; the drainage tributary to the Atlantic Ocean from
White Creek and Gargathy Inlet, inclusive, to the Virginia-North
Carolina State line; the Roanoke River Basin above Weldon, N. C.;
the Meherrin River Basin above Murfreesboro, N. C.; and the Cho-
wan River Basin above the confluence of the Nottoway and Black-
water Rivers, Va. It also includes the Virginia portion of the Intra-
coastal Waterway between Norfolk, Va., and Beaufort Inlet, N. C.,
and the portion of the waterway from Norfolk to the sounds of North
Carolina north of Albemarle Sound.
  District engineer: Col. G. J. Zimmerman, Corps of Engineers, to
January 22,1944; Col. R. E. Cruse, Corps of Engineers, since that date.
  Division engineer: Col. Clark Kittrell, Corps of Engineers, to Sep-
tember 30, 1943; Col. G. J. Zimmerman, Corps of Engineers, acting
division engineer to October 25, 1943; Col. E. E. Gesler, Corps of En-
gineers, since that date.
                                    IMPROVEMENTS

                Navigation                           Navigation-Continued
                                       Page                                      Page
1. Norfolk Harbor, Va        -
                             --        364 11. Inland waterway from Nor-
2. Thimble Shoal Channel, Va          370       folk, Va., to Beaufort In-
3. Channel to Newport News,                     let, N. C__ _--          _ -_   388
      Va_ ______371                        12. Blackwater River, Va _            393
4. James River, Va            -       373 13. Knobbs Creek, N. C-. _ .          395
5. Hampton Creek, Va....              376 14. Examinations, surveys, and
6. Channel from Phoebus, Va.,                   contingencies (general)-        396
      to deep water in Hampton             15. Other navigation projects for
      Roads -- --      - ---           378       which no estimates are sub-
7. Appomattox River, Va- -----        379       mitted             ______       397
8. Portsmouth Harbor,          Va.,       16. Plant allotment ------------      397
      Channel to Nansemond
      Ordnance Depot    ---------      381                 Flood control
9. York Spit Channel, Va -....-       383
10. Waterway from Norfolk, Va.,            17. Preliminary examinations,
      to the Sounds of North                     surveys, and contingencies
      Carolina_----------------        385       for flood control  ---------    398

  The following improvement is divided into three subheads: (1)
Norfolk Harbor, (2) Thimble Shoal Channel in the southern end of
Chesapeake Bay, and (3) the channel leading to Newport News from
Hampton Roads.
                             1. NORFOLK HARBOR, VA.

  Location.-Norfolk, Va., is 187 miles south of Baltimore, Md., and
30 miles from the entrance to Chesapeake Bay at Cape Charles and
Cape Henry. The harbor extends from the 40-foot contour in Hamp-
ton Roads to a point 2,500 feet above the Norfolk & Western Railway
bridge over the Southern Branch of the Elizabeth River, a distance
of 16.03 miles. (See U. S. Coast and Geodetic Survey Charts Nos.
400 and 452. )
                RIVERS AND HARBORS-NORFOLK,                               VA.,   DISTRICT               365
   Previous projects.-Adopted by River and Harbor Acts of August
14, 1876; July 5, 1884; modified June 30, 1885; and by River and
Harbor Acts of September 19, 1890; June 3, 1896; July 7, 1898; June
13, 1902; March 3, 1905; and March 2, 1907. For further details see
page 1795 of Annual Report for 1915, and page 454 of Annual Report
for 1938.
   Existing project. This provides for a main channel 40 feet deep,
750 feet wide from Hampton Roads to the mouth of the Southern
Branch of Elizabeth River, and 450 feet wide up this branch to the
Belt Line Railroad bridge, a total distance of 11.88 miles, and dredged
areas in front of the navy yard on either side of the 40-foot channel,
immediately downstream from the Belt Line Railroad bridge, 35 feet
deep for a width varying from 600 feet to 800 feet; thence 30 feet
deep, 375 feet wide, and 1.05 miles long to the Virginian Railway
bridge; and thence 25 feet deep and generally 200 feet wide, and 3.10
miles long to a point 2,500 feet above the Norfolk & Western Railway
bridge, making a total distance of 16.03 miles; a channel in the
Eastern Branch, 25 feet deep, 500 feet wide, and 1.09 miles long, from
the 40-foot channel at the mouth to the Norfolk & Western Railway
bridge, including within its limits, for a distance about 1,000 feet
above the mouth, a channel 30 feet deep and 300 feet wide to a point
opposite the terminal of the Imperial Tobacco Co. in Berkeley; thence
25 feet deep, 2'0 feet wide, and 1.75 miles long to the Virginian Rail-
way bridge; a channel in the Western Branch, between the 40-foot
channel at the mouth and a point about 3,000 feet above the West
Norfolk Highway bridge, a distance of about 1.72 miles; 24 feet deep,
300 feet wide, 0.78 mile, and 200 feet wide, 0.37 mile to the bridge;
thence 18 feet deep, 150 feet wide, 0.57 mile; a channel in Scotts
Creek between the 40-foot channel at the mouth and a point 100 feet
above the Atlantic Coast Line Railroad bridge (about 0.73 mile up-
stream), 12 feet deep and 100 feet wide; and anchorage areas on the
west side of the 40-foot channel opposite Lambert Point and south of
Craney Island aggregating 171 acres, consisting of: One anchorage
space 1,200 by 2,400 by 30 feet deep; one anchorage divided into two
spaces, each 1,200 by 1,200 by 22 feet deep; one space 900 by 1,900 by 16
feet deep; and another anchorage of 45 acres, 12 feet deep near Pinner
Point. All depths are referred to mean low water.
   The mean tidal range is 2.7 feet and the extreme 3 feet. The ex-
tremes of irregular fluctuations, due to combined effect of tides and
wind, referred to mean low water, are -2 feet and + 9.62 feet.
   The estimate of cost for new work, revised in 1944, exclusive of
amounts expended on previous projects, is $6,800,000. The latest
(1944) approved estimate for annual cost of maintenance is $236,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                                    Documents


                    HAMPTON ROADS AND ELIZTABETH RIVER


Mar. 2, 1907    A channel 30 feet deep t. the navy yard---             H. Doc. No.381, 59th Cong., 1st sess.
                                                                       I_--
June 25, 1910   Depth of 35 feet to the navy yard        __ ______ _   H. Doc. No. 551, 61st Cong., 2d sess.
Aug. 8, 1917    Depth of 40 feet and width of 750 feet to the mouth    H. Doc. No. 140, 65th Cong., 1st sess.
                 of the Southern Branch.
366           REPORT OF CHIEF OF ENGINEERS,                               Uf.   S.   ARMY,      1944




       Acts                        Work authorized                                       Documents


                                SOUTHERN BRANCH


June 25,1910       For a channel with depths of 22 and 25 feet.....        H. ,Doc. No. 551, 61st Cong., 2d sess.
Aug. 8, 1917       Depth of 40 feet and width of 450 feet from the         H. Doc. No. 140, 65th Cong., 1st sess.
                    mouth to the Belt Line R. R. bridge.
Mar.     3,1925    Channel30 feet deep and 375 feet wide to the Vir-       H. Doc. No. 226, 68th Cong., 1st sess. 1
                    ginian Ry. bridge, thence 25 feet deep and gen-
                    erally 200 feet wide to the Norfolk & Western
                     Ry. bridge.
Aug. 30, 19352     Depth of 25 feet and width of 200 feet from the         H. Doc. No. 182, 73d Cong., 2d sess. 1
                    Norfolk & Western Ry. bridge to a point 2,500
                    feet above, with a turning basin 500 feet square.

                                   EASTERN BRANCH


July 5,    1884    Improvement of the Eastern Branch.-----                Annual Report, 1885, p. 1015.
Mar. 2,    1907    Width of 500 feet and depths of 25 feet and 22 feet-   H. Doc. No. 373, 59th Cong., 1st sess.
    'Do    ..--    Removal of shoals at the mouth_                        Specified in act.
Mar. 3,    1925    Depth of 25 feet and width of 200 feet from the        H. Doc. No. 226, 68th Cong., 1st sess.      1
                     Norfolk & Western Ry. bridge to the Virginian
                     Ry. bridge.
July     3,1930    The 30-foot channel to a point opposite the ter-        H. Doc. No. 37, 71st Cong., 1st sess.
                     minal of the Imperial Tobacco Co. in Berkley.

                                   WESTERN BRANCH


Mar.     4, 1913   Channel with depth of 24 feet and widths of 300         H. Doc. No. 566, 62d Cong., 2d sess.
                     and 200 feet to the West Norfolk highway
                     bridge.
July     3,1930    For the 18-foot channel to a point about 3,000 feet     H. Doc. No. 265, 70th Cong., 1st sess. 1
                     above the West Norfolk highway bridge.

                                     SCOTTS CREEK


     Do.......     For the present project dimensions        ...------------H. Doc. No. 189, 70th Cong., 1st sess.

                                     ANCHORAGES


June 25, 1910      A 30-foot anchorage at Lambert Point ......             H. Doe. No. 551, 61st Cong., 2d sess.
Aug. 8,1917        Present project dimensions of the anchorage at          H. Doc. No. 605, 63d Cong., 2d sess. 1
                     Pinner Point.
July     3,1930    Present project dimensions of anchorage opposite        H. Doc. No. 143, 70th Cong., 1st sess.
                     Lambert Point and elimination of the 35-foot
                     anchorage authorized by the act of Aug. 8, 1917.
Oct. 17,1940       Extension of present anchorage to afford 2 anchor-      H. Doc. No. 683, 76th Cong., 3d sess.
                     age spaces 22 feet deep and 1 anchorage space 16
                     feet deep.


I Contains latest published maps.
9   Included in the Emergency Relief program, May 28, 1935.


   Recommended modifications of project.-Under date of March 4,
1939, the Chief of Engineers recommended modification of the ex-
isting project so as to provide for a channel in the Eastern Branch
of Elizabeth River, between the Norfolk & Western Railway bridge
          RIVERS AND    HARBORS-NORFOLK,       VA.,   DISTRICT     367
and the Campostella Bridge, 25 feet deep and 300 feet wide, extend-
ing between a line 100 feet north of and parallel to the line connect-
ing the centers of the draw spans of the bridges and a line 200 feet
south of and parallel to the same line; and for maintenance at a
depth of 25 feet of the existing turning basin approximately 51/2
acres in extent at the head of the existing project just below the
Virginian Railway bridge; all at an estimated first cost of $35 ,000,.
with annual maintenance of $3,300, in addition to that now required
 (H. Doc. No. 224, 76th Cong., 1st sess.).
   Local cooperation.-The River and Harbor Act of July 3, 1930,
in adopting the project for a channel in the Eastern Branch, 30 feet
deep and 300 feet wide, extending from the 40-foot channel to a point
opposite the terminal of the Imperial Tobacco Co., imposed the con-
dition that local interests give assurance satisfactory to the Secretary
of War and the Chief of Engineers that they will provide and main-
tain, without cost to the United States, a branch channel of equal
depth to the tobacco terminal. This condition has not been complied
with.
   All prior requirements and conditions imposed by the River and
Harbor Acts of August 30, 1935, and October 17, 1940, have been com-
plied with. The River and Harbor Act of August 30, 1935, requires
local interests to furnish suitable areas for the disposal of dredged
material for futuremaintenance as and when needed for the 25-foot
channel of the Southern Branch of Elizabeth River above the Norfolk
and Western Railway bridge.
   Terminal facilities.-The terminal facilities within the limits of
this improvement include about 227 wharves, piers, etc., with an
aggregate length available for wharfage purposes of about 32 miles.
It is considered that the facilities are adequate for the present com-
merce of the port.
   Operation and results during fiscal year.-No new work was per-
formed during the fiscal year. Negotiated termination of contract, and
cancelation of liquidated damages in connection with partially com-
pleted new work, construction of 16- and 22-foot anchorages near
Craney Island, amounted to $31,315.06.
   Maintenance dredging with U. S. hopper dredge Chinook in the
40-foot channel was in progress at the beginning of the fiscal year
and continued intermittently until June 24, 1944, when the work was
completed. There were removed 3,856,198 cubic yards of material, bin
measurement. The cost of the work was $425,291.39.
   Maintenance dredging under contract in the 25-foot channel of the
Southern Branch of the Elizabeth River was commenced on July 27,
1943, and continued to October 7, 1943, when the work was completed.
There were removed 179,469 cubic yards of material. The cost of the
work was $70,322.70.
   Miscellaneous surveys, water level studies, and maintenance of tide
gages were carried on during the year at a cost of $18,144.68.
   The total cost was $545,073.83, of which $31,315.06 was for new work
and $513,758.77 for maintenance. The total expenditure was $564,239.95.
368        REPORT OF CHIEF OF ENGINEERS,                                    U.   S. ARMY,         1944


  Condition at end of fiscal year.-The existing project was about 96
percent completed at the end of the fiscal year.
  The controlling depths at mean low water are as follows:
                                                                         Controlling depth

                       Name of channel                             Left out- Midchan- r                 Daeder-
                                                                     side        nelforoutside
                                                                   quarter       width      quarter
                                                                    (feet)       (feet)      (feet)


40-foot Channel:
    Hampton Roads to junction of branches     --------------           29. 2        37. 8      27. 5   May 1944.
    Junction of branches to Belt Line Railroad bridge .                31.4         38. 3      30.1    May 1944.
Southern Branch:
   Belt Line Railroad bridge to Virginian Railway
      bridge .--   -    ,-.   ....   ... . .....        .              29. 0        29. 1      29.1    M ay 1943.
    Virginian Railway bridge to point 2,500 feet above
      Norfolk & Western Ry. bridge---         _---------25.                 0       25. 0      25. 0   October 1943.
Eastern Branch:
    40-foot Channel to Virginian Railway bridge .....                  21.9         21.2       19. 0   April 1943.
Scotts Creek-_ -------  _---------------------._                        9. 3        10. 7       9. 5   January 1941.
Western Branch:
    40-foot Channel to West Norfolk highway bridge            --       14. 3        15. 6      15. 7   May 1934.
    West Norfolk highway bridge to3,000 feet above1.                   18.1         19. 5      18.2    April 1934.


   The work remaining to be done consists of dredging a channel 30
feet deep and 300 feet wide in the Eastern Branch between the 40-
foot channel at the mouth and a point opposite the terminal of the
Imperial Tobacco Co., a distance of about 1,000 feet; dredging a
turning basin in the Southern Branch 500 feet square to a depth
of 25 feet at a point 2,500 feet above the Norfolk & Western Railway
bridge; and completion of dredging three additional anchorage areas,
south of the present Craney Island Anchorage (two areas, 1,200 feet
by 1,200 feet to a depth of 22 feet, and one area 900 feet by 1,900 feet
to a depth of 16 feet).
   The total cost under the existing project was $10,406,961.53, of
which $6,430,864.07 was regular funds and $49,978.50 Emergency Re-
lief funds, a total of $6,480,842.57 for new work; and $3,926,118.96
regular funds for maintenance. The expenditures were $10,380,785.98
regular funds and $49,978.50 Emergency Relief funds, a total of
$10,430,764.48. In addition, $23,935.71 was expended from contrib-
uted funds for new work.
   Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year, $129,941.30, plus an allotment of
$394,000 made in July 1944, a total of $523,941.30, will be applied
as follows:
Maintenance:
    Maintenance of the 40-foot channel between the Belt Line R. R.
      bridge across the Southern Branch of Elizabeth River and
      Hampton Roads, with U. S. hopper dredge Chinook, 6
      months, January to June 1945------      -                    $348,000. 00
   Maintenance dredging in critical areas in the 40-foot channel
      between the Belt Line R. R. bridge across the Southern
      Branch of Elizabeth River and the junction of the Eastern
      and Southern Branches of Elizabeth River, by contract,
      215,000 cubic yards, September 1944 to January 1945 ..        139, 000. 00
   Miscellaneous surveys, triangulation controls, etc., June 1944
      to July 1945 -...- - - - - - -  -.   .-   ... ...  .           31, 941. 30
   Construction and maintenance of tide gaging structure, June
      1944 to July 1945---                                            5, 000.00
            Total for all work__         --   -                                                        523, 941. 30
                     RIVERS AND HARBORS-NORFOLK,:VA., DISTRICT                                                           369
  The additional sum of $380,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
    Maintenance of the 40-foot channel between the Belt Line R. R.
      bridge across the Southern Branch of Elizabeth River and
      Hampton Roads, with U. S. hopper dredge Chinook, 6 months,
      January to June 1946-------------------------------------      $350, 000
    Miscellaneous surveys, triangulation controls, and tide gagings,
      July 1945 to July 1946_------------------------------------      30, 000

                Total for all work --------------------------------------
                                                                       ..                                           380, 000
  No funds are required for the completion of the 16- and 22-foot
anchorages near Craney Island or for the turning basin, Southern
Branch of the Elizabeth River, as this work is not considered neces-
sary at the present time, nor. for the 30-foot channel in the Eastern
Branch of the Elizabeth River, since compliance with the conditions
of local cooperation is not expected during the fiscal year.
                                    Cost and financial summary
Cost of new work to June 30, 1944 _ _____                           ____1
                                                                      --                                     89, 042, 546. 84
Cost of maintenance to June 30, 1944 _                                                      -               2 3, 998, 158. 23
       Total cost of permanent work to June 30, 1944                                  -.           .        13, 040, 705. 07
Plus accounts receivable June 30, 1944             - -                                                           23, 802. 95
            Gross total costs to June 30, 1944---- ----------------                                         13, 064, 508. 02

Net total expenditures- _-  _                       ------                                              113, 064, 508. 02
Unexpended balance June 30, 1944                                                       --          -            106, 138. 35
           Total amount appropriated to June 30, 1944                           ---                     113, 170, 646. 37

    Fiscal year ending June 30         1940                  1941             1942                 1943              1944


Cost of new work _......._.......                      $4, 620. 62          $78, 387.07         -$2, 098. 00        $31,315. 06
Cost of maintenance.......          $399, 294. 35     776, 127. 11          236, 946. 49         152, 754. 84       513, 758. 77

       Total cost                    399, 294. 35     780, 747. 73          315, 333. 56        150, 656. 84        545, 073. 83

Total expended      - -436,              459. 15      788, 595. 30          300, 758. 90         171, 133. 22       564, 239. 95
Allotted__-_--------------1,016, 470. 11              330, 000. 00          239, 300. 00        370, 000. 00        -9, 350. 00



Balance unexpended July 1, 1943______________                                                                 $679, 728. 30
Amount allotted from War Department Civil Appropriation Act
appsroved Apr. 28, 1942__ ______-----       -------                                                             55, 000. 00

       Amount to be accounted for-------------------------                                                      734, 728. 30
Deduc tions on account of revocation of allotments------------                                                   64, 350. 00
      Net amount to be accounted for_                                                                           670, 378. 30
Gross amount expended-       -                                                         -_              --       564, 239. 95
       Balance unexpended June 30, 1944--------------------                                                     106, 138. 35
Accou nts receivable June 30, 1944 _23,                                                                              802. 95

      Unobligated balance available June 30, 1944-                                                              129, 941. 30
Amoulnt allotted in July 1944_   __---394,                                                                           000. 00
           Amount available during fiscal year 1945--------------                                               523, 941. 30
Amount (estimated) required to be appropriated for completion
of existing project 3. . . _ -..- .
                               ____-                                                                            319, 200. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance                                                                                  380, 000. 00
1 In addition, $23,935.71 expended from contributed funds for new work.
2 Includes $2,400.81 for removal of shoals in Hampton Roads, mine wharf.
8Exclusive of available funds.
          616634-45-pt. 1, vol. 1-         24
370     REPORT OF CHIEF OF ENGINEERS,                  LU. S.   ARMY,   1944

                     2. THIMBLE SHOAL CHANNEL, VA.
    Location.-Thimble Shoal Channel lies between Hampton Roads
:and the ocean, and is 20 miles northeast of the center of Norfolk Har-
bor, extending southeasterly 11 miles from a point 11/4 miles east of
Thimble Shoal Lighthouse toward the entrance to Chesapeake Bay.
  (See U.. S. Coast and Geodetic Survey Chart No. 1222.)
    Previous projects.-Adopted by River and Harbor Act of June 25,
1910. For further details see page 470, Annual Report for 1932.
    Existing project.-This provides for dredging a channel 11 miles
long, 750 feet wide, and 40 feet deep at mean low water. Under
ordinary conditions the mean tidal range is 2.6 feet and the extremes
.2 and 3 feet. The extremes of irregular fluctuation, due to combined
,wind and tides, referred to mean low water, are -2 feet and + 9.5 feet.
    The estimate of cost for new work, revised in 1928, was $2,325,000,
exclusive of amounts expended on previous projects. The latest
  (1928) approved estimate of cost for annual maintenance is $50,000.
    The existing project was adopted by the River and Harbor Act of
August 8, 1917 (H. Doc. No. 140, 65th Cong., 1st sess.). The latest
published map is in House Document No. 551, Sixty-first Congress,
second session.
    Terminal facilities.-Fora description of the terminal facilities for
 ,these points see this heading under "Norfolk Harbor" and "Channel
to Newport News, Va."
    Operations and results during fiscal year.-Maintenance dredging
with U. S. hopper dredge Chinook was commenced on July 6, 1913, and
,continued intermittently until February 16, 1944, when the work was
.completed. There were removed 1,307,927 cubic yards of material,
bin measurement. The cost of the work was $139,703.84. Miscellane-
.ous condition surveys were made during the year at a cost of $1,419.62.
    The total cost was $141,123.46, all for maintenance. The total ex-
penditure was $143,916.86.
    Conditionat end of fiscal year.-The existing project was completed
in 1929. The controlling depth as ascertained between April 1943
,nd February 1944 was 39.8 feet in the midchannel and 39 feet along
the edges. Depths are referred to mean low water.
    The total cost under the existing project was $3,088,489.24, of which
52,283,772.56 was for new work and $804,716.68 for maintenance. The
total expenditure was $3,094,2i2.62.
    Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year, $11,648.96, plus an allotment of
$75,000 made in July 1944, a total of $86,648.96, will be applied as
follows:
Maintenance:
   Maintenance of the channel with U. S. hopper dredge Chinook,
      1J months, July to December 1944 (intermittently) -------- $80, 000. 00
   Miscellaneous condition surveys July 1944 to July 1945--------  6, 648. 96
      Total for all work_----        --------------                        86, 648. 96
  The additional sum of $181,000 can be profitably expended during
the fiscal year 1946 as follows:
VIaintenance:
M
    Maintenance of the channel with U. S. hopper dredge Chinook, 3
      months, September to November 1945 .                         $175, 000
    Miscellaneous condition surveys, July 1945 to July 1946           6, 000

      Total for all work-       --             -181,                              000
                  RIVERS AND HARBORS-NORFOLK,                                        VA., DISTRICT                         371
                                           Cost and financial summary
Cost of new work to June 30, 1944-_    __ ___                                                           $2, 617, 381. 44
Cost of maintenance to June 30, 1944__                                                                      804, 716. 68

       Total cost of permanent work to June 30, 1944__                                                    3, 422, 098. 12
Plus accounts receivable June 30, 1944-                                                                        5, 723. 38

         Gross total costs to June 30, 1944_                                                              3, 427, 821. 50

Net total expenditures_____                                                                               3, 427, 821. 50
Unexpended balance June 30, 1944-_-_-_-                                                                        5, 925. 58
         Total amount appropriated to June 30, 1944_                                                 S3, 433, 747. 08


   Fiscal year ending June 30                 1940                    1941         1942          1943                   1944


C ost of new work - - - - - - - -        -- - -       -- - - - - - - - - - . - - - - - - .- - - - - - - . . . . . . .
Cost of maintenance -$75,301.76                                $195, 669.98     $1,930. 38    $9,141.38     $141, 123. 46

Total expended           .....---.           74 932. 58         195, 523. 76       2, 869.95    12,657.           _143, 016. 86
Allotted_   -       -           -    -      362, 626. 51      -190,     730. 69   45, 000.00   117, 500. 00   .......


Balance unexpended July 1, 1943 -_                                                                         $149, 842. 44
Gross amount expended                                                                                       143, 916. 86
      Balance unexpended June 30, 1944                                                                            5, 925. 58
Accounts receivable June 30, 1944_ _5,                                                                               723. 38
     Unobligated balance available June 30, 1944- _11,                                                             648. 96
Amount allotted in July 1944 ----       ......         .....  -..                                              75, 000. 00
         Amount available during fiscal year 1945                                                              86, 648. 96
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance 1                    -                                                           181, 000. 00

  1 Exclusive of available funds.


                         3. CHANNEL TO NEWPORT NEWS, VA.

   Location.-This channel lies to the west of the north entrance to
Norfolk Harbor Channel and connect deep water in James River with
Hampton Roads. (See U. S. Coast and Geodetic Survey Chart No.
400.)
  Previous projeets.-Adopted June 13, 1902. For further details,
see page 1797 of Annual Report for 1915, and page 459 of Annual
Report for 1938.
   Existing project.-This provides for dredging a channel 40 feet
deep at mean low water, 600 feet wide, increased to 1,000 feet at the
ends, and 31/4 miles long through the shoal north of Middle Ground
Light. Under ordinary conditions the mean tidal range is 2.7 feet
and the extremes 2.1 and 3 feet.                                  The extremes of irregular fluctua-
tions due to combined wind and tides, referred to mean low water,
are -2          feet and +9.5 feet.
  The estimate of cost for new work, revised in 1927, was $1,521,515,
exclusive of amount expended on previous projects. The latest (1927)
approved estimate for annual cost of maintenance is $20,000.
 372             REPORT OF CHIEF OF ENGINEERS.                                     U.       S. ARMY,           1944

   The existing project was authorized by the following river and
harbor acts:

       Acts                                    Work authorized                                        Documents



June 25,1910         Channel 35 feet deep and 400 feet wide .....----------        H. Doc. No. 550, 61st Cong., 2d sess.
Aug. 8,1917          Channel 35 feet deep and 600 feet wide ..----------           H. Doc. No. 605, 63d Cong., 2d sess.'
Jan. 21, 1927        Present project dimensions------- ------------                H. Doc. No. 486, 67th Cong., 4th sess.


    1 Contains     latest published map.

    Terminal facilities.-There are four piers at Newport News, which
are the property of the city, and which are open to general public
use on equal terms. All of the other piers and wharves served by
this improvement are owned by private corporations or companies.
The principal terminal and transfer facilities are those of the Chesa-
peake & Ohio Railway Co. and the Newport News Shipbuilding &
Dry Dock Co. There are also at Newport News a wharf used by
steamers of the Eastern Steamship Co. and a small-boat harbor. The
facilities are considered adequate for present commerce.
    Operations and results during fiscaal year.-None.
    Condition at end of fiscal year.-The existing project was completed
in 1931. The controlling depth as ascertained in October 1943 was
37.8 feet in midchannel and 31.1 feet along the edges. Depths are
referred to mean low water.
    The total costs and expenditures under the existing project were
 $1,438,515.26, of which $1,252,261.99 was for new work and $186,253.27
for maintenance.
    Proposed operations.-The allotment of $33,000 made in July 1944
will be applied as follows:
Maintenance:
     Maintenance of the channel to restore project dimensions with U. S.
       hopper dredge Chinook, / month, December 1944------------- $29, 000
     Miscellaneous condition surveys July 1944 to July 1945-----------   4, 000

             Total for all work_ ______________----- -------------------                                                  33, 000
   No funds can be profitably expended during the fiscal year 1946 as
the proposed work will meet the needs of navigation until a later date.
                                                   Cost and financialsummary
Cost of new work to June 30, 1944 __ __---------$1,                                                                477, 261. 99
Cost of maintenance to June 30, 1944_----                                               -    -_198,                     753. 27
       Total cost of permanent work to June 30, 1944---------- 1, 676, 015. 26
Net total expenditures                              -        -1,    676, 015. 26
Total amount appropriated to June 30, 1944_                      1, 676, 015. 26

     Fiscal year ending June 30                        1940           1941          1942               1946               1944


C ost of new work .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cost of maintenance                .                $1,186. 58
                                           .-------------           $55, 132. 34   $2, 311.89        $15, 869.19-------

Total expended        -.     .......----      ..   -------    .-     56, 318. 92    1, 631.08         16, 500.00

Allotted .....----------------------..               40, 000. 00   -32, 000. 00    16, 500. 00   .


Amount allotted in July 1944                                                                                       $33, 000. 00
Amount available during fiscal year 1945 -33,                                                                           000. 00
                   RIVERS      AND      HARBORS-NORFOLK,                  VA.,    DISTRICT                373
                                         4. JAMES RIVER, VA.

   Location.-This river is formed by the junction of the Cowpasture
and Jackson Rivers in Botetourt County, Va., flows easterly 340
miles, and empties into Hampton Roads at Newport News, Va. (See
U. S. Coast and Geodetic Survey Charts Nos. 529, 530, and 531.)
   Previous projects.-Adopted by River and Harbor Act of July 11,
1870. For further details see page 1797 of Annual Report for 1915,
and page 461 of the Annual Report for 1938.
   Existing project.-This provides for a channel 25 feet deep and
300 feet wide from the mouth to Hopewell, 69.2 miles; thence 25
feet deep and 200 feet wide, following the cut-off route between Hope-
well and the Richmond deep-water terminal, 17.2 miles; thence a
channel 18 feet deep and 200 feet wide from the deep-water terminal to
the Richmond lock, 4.4 miles, and the removal of the obstruction in
Richmond Harbor known as Trigg Cofferdam.
   Depths of channels are referred to mean low water. The total
length of channel included in the project is 90.8 miles, which is the
navigable section.
   The mean tidal ranges under ordinary conditions for different
parts of the river are as follows: Mouth, 2.7 feet; Jamestown, 1.85
feet; City Point, 2.8 feet; Dutch Gap, 3.5 feet; Richmond, 3.9 feet.
Following are the extreme ranges under ordinary conditions at the
same localities: Mouth, 2.1 to 3 feet; Jamestown, 1.6 to 2.3 feet; City
Point, 2.3 to 3.2 feet; Dutch Gap, 2.9 to 3.9 feet; Richmond, 3.2 to 4.2
feet. The ordinary fluctuations of stage at Richmond, due to floods,
are 6 to 12 feet above mean low water. The extreme fluctuations are
16 to 32 feet. The flood heights below Richmond diminish rapidly,
the extreme, according to available information, being about 11 feet
lower at Dutch Gap,. 14 miles below, and 17 to 18 feet lower 20
miles below.
   The estimate of cost for new work, revised in 1941, exclusive of
the amount expended on previous projects, is $6,641,000. The latest
 (1930) approved estimate of cost for annual maintenance is $100,000.
   The existing project was authorized by the following river and
harbors acts:

       Acts                        Work authorized                                     Documents


July     5,1884    Channel 22 feet deep from mouth to Richmond          S. Ex. Doc. No. 147, 47th Cong., 1st
                     and construction of spur and training dikes.        sess.
June 13, 1902      Extension of improvement to Richmond lock gate
Mar. 3,1905        Forming a turning basin by widening channel at       H. Doc. No. 234, 56th Cong., 1st sess.
                     Richmond.
                                                                                                                   1
July     3, 1930   Present project dimensions ...    ...--...    __ _   H. Doc. No. 314, 71st Cong., 2d sess.
Aug. 26,1937       Removal of the Trigg cofferdam.__            _ _     Rivers   and     Harbors    Committee
                                                                                                               1
                                                                          Doe. No. 68, 74th Cong., 1st sess.


  1Contains latest published maps.

  Recommended modifications of project.-Under date of March 12,
1942, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for dredging and maintaining a turning
374     REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,   1944

basin 200 feet wide, 600 feet long, and 18 feet deep at mean low water,
to occupy the same area dredged by the city of Richmond as a turn-
ing basin, at an estimated initial cost of $27,000, with annual mainte-
nance of $1,500, subject to certain conditions of local cooperation (H.
Doc. No. 738, 77th Cong., 2d sess.).
   Local cooperation.-Fully complied with. Local interests are re-
quired to furnish suitable areas for the disposal of dredged material
for future maintenance.
    Terminal facilities.-The river's commerce at Richmond is handled
at the city-owned terminals, city wharf, and Richmond dock, and at
14 privately owned wharves located within or in the immediate vi-
cinity of Richmond Harbor. The Richmond deep-water terminal at
the head of the 25-foot depth serves ocean-going vessels and the larger
ships engaged in coastwise trade. Below the deep-water terminal the
improvement is served by 42 wharves. The Richmond terminals and
wharves, together with the wharves between Richmond and the river's
mouth, are adequate for the river's commerce.
    Operations and results during fiscal year.-Costs outstanding in
connection with maintenance dredging in Richmond Harbor, by con-
tract, completed during previous fiscal year amounted to $250.11.
   Maintenance dredging under contract in the channel between the
mouth and Hopewell, Va., was commenced on June 17, 1944, and con-
tinued to the close of the fiscal year. There were removed 108,989
cubic yards of material. The cost of the work was $12,495.19.
   Miscellaneous surveys, river flow studies, and tide gagings were
made during the fiscal year at a cost of $27,462.75.
   The total cost of the work was $40,208.05, all for maintenance. The
total expenditure was $41,671.89.
   Condition at end of fiscal year.-The existing project was about 90
percent completed at the end of the fiscal year. The controlling
depths for the full project widths are as follows: Between the mouth
and Hopewell, 19.9 fet; between Hopewell and Richmond deepwater
terminal, 19 feet; between Richmond deepwater terminal and the
Buxton Line dock in Richmond Harbor, 13.1 feet; and thence to the
Richmond lock 7.1 feet. This information is based upon surveys made
between 1940 and 1943.
   The work remaining to be done is the removal of about 118-, 900
cubic yards of rock and overburden at the mouth of Falling Creek and
between the Richmond deepwater terminal and Richmond lock for
the completion of the project.
   The total cost under the existing project was $7,787,660.04, of which
$5,988,912.61 was for new work, representing $5,405,076.08 from regu-
lar funds and $583,836.53 from Public Works funds, and $1,798,747.43
for maintenance, including $837.98 applied to the removal of shoals in
Bennetts Creek, Va., under the provisions of section 3 of the River and
Harbor Act approved October 17, 1940. The total expenditure was
$7,782,817.45.
   Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year $251,979.84, plus an allotment of
                   RIVERS AND                     HARBORS-NORFOLK,                                VA.,       DISTRICT                 375
$110,000 made in July 1944, a total of $361,979.84, will be applied as
follows:
Accounts payable, June 30, 1944              -----------                $5, 623. 83j
Maintenance:
    Completion of dredging between Hopewell and the mouth to
      restore project dimensions under an existing contract, 2,870,000
      cubic yards, July 1944 to April 1945- - ---        _ _           184, 300. 00
    Dredging between Richmond deep water terminal and Hopewell
      to restore project dimensions by contract, February to April
          1945_         _         _--        --                   -            ------------                                    80, 000.00
      Dredging shoals after freshets, in Richmond Harbor, by con-
        tract, September and October 1944, April and May 1945 ..                                                               60, 000. 00
      Condition surveys above and below Hopewell, continuance of
        river flow studies, and maintenance of tide gages, June 1944
        to July 1945 -        -      -       --                                                                                32, 056. 01
              Total for all work                         ---------------------------                                          361, 979. 84
   The additional sum of $150,000 can be profitably expended during
fiscal year 1946 as follows:
Maintenance:
       Dredging to ease bends at lower end of Rock Landing Shoal, by
         contract, September 1945 to February 1946      ---------------- $90, 000
       Dredging shoals, after freshets, in Richmond Harbor, by contract,
         March to May 1946 -____--              -_30,                         000
       Condition surveys above and below Hopewell, continuance of river
         flow studies and maintenance of tide gages, June 1945 to July
         1946     ------------------------------------------------        30,00@

              Total for all work                     -----------------------------------                                         150. 000'

                                                  Cost and financial summary
Cost of new work to June 30, 1944------                                                           -                 - $6,     751, 912. 61
Cost of maintenance to June 30, 1944.                                                                                   1, 798, 747. 43&

       Total cost of permanent work to June 30, 1944_                                                                   8, 550, 660. 04
Plus accounts receivable June 30, 1944  -                                                                                       781. 24

      Gross total costs to June 30, 1944                                                                                8, 551, 441. 28
Minus accounts payable June 30, 1944                                    -                                                    5,623. 83
      Net total expenditures _                                                                                          8, 545, 817. 45
Unexpended balance June 30, 1944                                                                                           251, 198. 60
          Total amount appropriated to June 30, 1944-                                                                   8, 797, 016. 05

    Fiscal year ending June 30                       1940               1941                    1942             1943              1944

Cost of new work_ .........
Cost of maintenance- .....
                                         -        $227, 712. 03       $11, 429. 55      .-           .          .         .
                                   _..             167, 285.86        179, 182. 94            $33, 969. 47     $64, 870. 71       $40, 208. 05

       Total cost   ----------------               394, 997. 89       190, 612. 49             33, 969. 47      64,870. 71         40, 208. 05
Total expended _--------------470,                     303. 35        187, 437.83              36, 842. 95      58, 865. 07        41, 671.89

Allotted_ _----------------176,                        300. 00        107, 500. 00            168, 592. 60     -8, 500. 00_
376          REPORT OF CHIEF OF ENGINEERS,                          U. S. ARMY,              1944

Balance unexpended July 1, 1943                                -    -           -              $292, 870. 49
Gross amount expended_ _                                                                             41, 671. 89

     Balance unexpended June 30, 1944_                                                          251, 198. 60
Amount covered by uncompleted contracts                   --                                    189, 935. 10

      Balance available June 30, 1944                                                                61, 263. 50
Accounts receivable June 30, 1944_ ___781.                                                                    24

      Unobligated balance available June 30, 1944                    -62,                               044. 74
bmount allotted in July 1944 - - _______110,                                                           000. 00

           Amount available during fiscal year 1945                         -       -               172, 044. 74

Amount (estimated) required to be appropriated for completion of
existing project 1                                                                             652, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 1 __150,                                                                 000. 00
  1 Exclusive of available funds.

                                    5. HAMPTON CREEK, VA.

   Location.-This creek is a tidal estuary of Hampton Roads, located
entirely within Elizabeth City County, Va. It is about 3 miles in
length, flows in a southerly direction, and empties into Hampton
Roads about 1.5 miles west of Fort Monroe. (See U. S. Coast and
Geodetic Survey Charts Nos. 400 and 1222.)
   Previous projects.-Adopted by River and Harbor Act of June 18,
1878. For further details see Annual Reports for 1878, 1879, and
1938, pages 72, 85, and 465, respectively.
   Existing project.-This provides for dredging a channel 12 feet
deep from the vicinity of Old Point Comfort across Hampton Flats
and up the creek to Hampton Highway Bridge at Queen Street about
2.8 miles, with a width of 200 feet in the outer portion of the channel
and a width of 150 feet in the creek, suitably widened at the bends.
Under ordinary conditions the mean tidal range is 2.6 feet and the
extremes -2 feet and + 9.5 feet.
   The estimate of cost for new work, revised in 1935, was $88,000.
The latest (1935) approved estimate for annual cost of maintenance
is $3,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                         Documents


Sept. 19,1890   Channel 9 feet deep, varying from 200 to 300 feet   Annual Report, 1889, p. 974.
                  wide on bar at mouth; and same depth and 200
                  feet wide from mouth to Hampton Highway
                  Bridge.
Aug. 30,1935    Present project dimensions _ _ ............         Rivers and Harbors Committee Doc.
                                                  /                   No. 34, 72d Cong., 1st sess. (Con-
                                                                        tains latest published map.)


   Recommended modiflcations of project.-Under date of December
11, 1939, the Chief of Engineers recommended modification of the ex-
isting project so as to provide for a channel in Herberts Creek having
widths of 100 feet and 80 feet and a depth of 12 feet at mean low
water, extending from the existing improved channel in Hampton
                  RIVERS AND HARBORS-NORFOLK,                                VA.,      DISTRICT                 377
Creek upstream to Jackson Street, at an estimated first cost of $15,-
000, with annual maintenance of $1,000, in addition to that now
required; subject to certain conditions of local cooperation. (H. Doc.
No. 559, 76th Cong., 3d sess.)
   Local cooperation.-Fully complied with. The River and Harbor
Act of August 30, 1935, requires local interests to furnish free of cost
to the United States suitable areas for the disposal of dredged mate-
rial for future maintenance, when and as needed.
   Terminal facilities.-There are about 30 wharves located on Hamp-
ton Creek, with a total frontage of about 3,000 feet. None of the
wharves has direct rail connection but is connected to the streets of
Hampton with the highways of the locality. Most of the wharves
are privately owned and are utilized in connection with local enter-
prises. One public wharf owned by the county of Elizabeth City,
open to the public without charge, and a wharf owned by the Hamp-
ton Yacht Club are utilized without charge by visiting yachts. The
facilities are considered adequate for existing commerce.
   Operationsand results during fiscal year.-Miscellaneous condition
surveys were made during the year at a cost and expenditure of
$1,008.33, all for maintenance.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1939. The controlling depth in September 1943 was 9.2
feet at mean low water. The total costs and expenditures under the
existing project were $130,399.19, of which $123,787.85 was for new
work and $6,611.34 for maintenance, including $2,979.04 applied to
Herberts Creek under the provisions of section 3 of the River and
Harbor Act of October 17, 1940. In addition, $40,000 was expended
from contributed funds for new work.
   Proposed operations.-No funds are available and no operations
are proposed during the fiscal year 1945.
   No funds can be profitably expended during the fiscal year 1946,
as the present condition of the channel will meet the needs of naviga-
tion until a later date.
                                      Cost and financial summary
Cost of new work to June 30, 1944 ____--1                                                           $135, '87. 85
Cost of maintenance to June 30, 1944_--                                                 -_              6,611. 34
       Total cost of permanent work to June 30, 1944     -_                                          142, 399. 19
Net total expenditures_--- ---------                  -__                                            142, 399. 19
Total amount appropriated to June 30, 1944--------------                                             142, 399. 19

   Fiscal year ending June 30            1940           1941              1942               1943           1944

Cost of new w ork - - -        - - - -.
                              ---     . . . . . . .. . . . . . . . . . . .. . . . . . .
Cost of maintenance -------           -----      -    $2, 979.04     $2, 623. 97                            $1, 008.33
Total expended                            $510.68       2, 979.04         2, 623. 97                         1, 008. 33

Allotted    ...
             .    ...     .. . .. .    ....     .      26, 979. 04   .-                 -     -      -      20, 367. 70



Balance unexpended July 1, 1943_                                                                         21, 376. 03
Deductions on account of revocation of allotment_                                                        20, 367. 70

    Net amount to be accounted for---                                                                     1, 008. 33
Gross amount expended                                                                                     1,008. 33
  I In addition, $40,000 expended from contributed funds for new work.
378     REPORT OF CHIEF OF ENGINEERS,        U. S. ARMY,    1944

6. CHANNEL FROM PHOEBUS, VA., TO DEEP WATER IN HAMPTON ROADS

   Location.-The channel parallels the west shore of the Fort Monroe
Military Reservation and leads from deep water in Hampton Roads
to the Phoebus water front at the mouth of Mill Creek. (See U. S.
Coast and Geodetic Survey Charts Nos. 400 and 1222.)
   Existing project.-This provides for a channel 12 feet deep and
150 feet wide from deep water in Hampton Roads to the Phoebus
water front, a distance of about three-fourths of a mile. Under
ordinary conditions the mean tidal range is 2.6 feet. The extremes
of irregular fluctuation referred to mean low water due to combined
effect of wind and tides are -2 feet and + 9.5 feet.
    The estimate of cost of new work made in 1935 was $9,800. The
latest (1935) approved estimate of cost for annual maintenance is
$1,200.
    The existing project was adopted by the River and Harbor Act of
August 30, 1935 (Rivers and Harbors Committee Doc. No. 33, 72d
Cong., 1st sess.). The latest published map is in the project document.
    Local cooperation.-Fully complied with. The River and Harbor
Act of August 30, 1935, requires local interests to furnish free of cost
to the United States suitable areas for the disposal of dredged material
for future maintenance when and as needed.
    Terminal facilities.-Two wharves, with a combined frontage of
about 1,000 feet, are located on the Phoebus water front. Three
Government-owned and maintained wharves are located on the Fort
Monroe Reservation along the east side of the channel and are used
solely by the military authorities. A ferry slip, utilized by the ferries
operating between Willoughby Spit and Old Point, is located on the
Government reservation just above the Government-owned wharves.
The facilities are considered adequate for existing commerce.
    Operations and results during fiscal year.-Maintenance dredging
-under contract to provide project depth in the realignment of the
southerly portion of the channel was commenced on February 26, 1944,
and continued until March 10, 1944, when the work was completed.
There were removed 8,001 cubic yards of material. The cost of the
work was $9,509.70.
    Maintenance dredging by Government plant and hired labor to
remove a shoal located in the channel opposite the terminal of the
Chesapeake Ferry Co. was performed between April 14 and 19, 1944.
There were removed approximately 480 cubic yards of material. The
cost of the work was $2,240.30.
    The total cost and expenditure of the work was $11,750, all for
maintenance.
    Condition at end of fiscal year.-The project was completed in 1937.
  The controlling depth in March 1944, was 12 feet at mean low water.
The total cost and expenditures were $23,250, of which $11,500 was for
new work and $11,750 for maintenance. In addition, $1,199.57 was
expended from contributed funds for new work.
    Proposed operations.-No funds are available and no operations are
proposed during fiscal year 1945.
    No funds can be profitably expended during fiscal year 1946 as the
  present condition of the channel will meet the needs of navigation
  until a later date.
                     RIVERS AND              HARBORS-NORFOLK,                        VA., DISTRICT                          379
                                             Cost and financial summary
Cost of new work to June 30, 1944__ --------    __--1                                                             $11, 500. 00
Cost of maintenance to June 30, 1944_--------------------                                                          11, 750. 00
         Total cost of permanent work to June 30, 1944                                -------         _               23, 250. 00
Net total expenditures -------------------------------                                                            123, 250.00
Total amount appropriated to June 30, 1944                               ---------------------                        23, 250. 00

   Fiscal year ending June.30                  1940               1941              1942            1943                 1944

C ost of new work ..      . . . . . . . .". . . . . .     . . . . . . .      . .-                 -- - -    -     -        -
Cost of maintenance - --         -----   -     --- --      - ---                               ------------- --......- $11,750.00

Total expended .---                                                         ---            _           -----             11,750.00

Allotted .   .   .    .    ..------------------- --------------               ------               ---      -..          11,750.00


Amount allotted from First Deficiency Appropriation Act 1941,
  approved Apr. 1, 1941 ______--------  -     _    _$11,750.00
Gross amount expended___    _____-________________-_____                                                              11, 750.00
  1 In addition, $1,199.57 expended from contributed funds for new work.


                                      7. APPOMATTOX RIVER, VA.

  Location.-This river rises in Appomattox County, Va., flows north-
easterly 137 miles, and empties into the James River at Hopewell,
Va. The portion under improvement extends from its mouth to
Petersburg, Va., a distance of 11 miles, which is the length of the
tidal and navigable reach. (See United States Coast and Geodetic
Survey Chart No. 531.)
   Previous projects.-None. A survey of the river was made prior
to the adoption of the existing project. For further details see page
469, Annual Report for 1938.
   Existing project.-This provides for a navigable channel 80 feet
wide and 10 feet deep at mean low water between the mouth of the
river and Petersburg, the head of navigation, a distance of 11 miles,
and a turning basin at Petersburg; for a dam at Petersburg and the
excavation for a width of from 200 to 300 feet of a diversion channel
connecting the river above the dam at Petersburg with the river at
a point 21/2 miles below; for about 1.7 miles of levees on the low
grounds between the navigable and diversion channels; for a high-
way bridge and a railway bridge across the diversion channel; and
for other work incidental to the diversion channel. Under ordinary
conditions the mean tidal range is 2.9 feet and the extremes 2.4 and
3.3 feet. There are no records available of the heights of stage due
to ordinary floods. These are estimated at 6 to 8 feet above mean
low water at Petersburg, where the extremes are from 15.6 to 17.1
feet.
   The estimated cost of the navigable channel, revised in 1927, was
$578,136 for new work, and the estimated cost (1909) of the diversion
channel and work incidental to its construction was $260,000. The
estimated cost of maintenance (1927) of the navigable channel is $6,500
annually.
380         REPORT OF         CHIEF OF ENGINEERS,                  U.   S. ARMY,        1944

  The existing project was authorized by the following river and
harbor acts:

     Acts                      Work authorized                                   Documents


Mar. 3, 1871    Channel 12 feet deep at mean high water and 60     Annual Report 1874, pt. II, p. 54.
                 feet wide.
June 13,1902 Diversion channel and work incidental thereto         H. Doe. No. 139, 56th Cong., 2d sess.,.
Mar. 3,1909                        w                                 and Annual Report, 1901, p. 1467.
June 25, 1910   Increasing channel to width of 80 feet and main-   H. Doc. No. 952, 60th Cong., 1st sess.
                  tenance of diversion works.                        (Contains latest published map.)
Jan. 21, 1927   Present project dinmensions--.----_   -   --       H. Doc. No. 215, 69th Cong., 1st sess.



   Recommended modifications of project.-Under date of March 7,
1939, the Chief of Engineers recommended modification of the ex-
isting project so as to provide for extending the existing turning
basin to a point 100 feet below the center line of Lieutenant Run;.
for widening this basin to 160 feet at the bend at the mouth of the
run and to 140 feet at the lower end; for removal of all rock lying
less than 18 feet below mean low water in the north half of the
lower 200 feet of the basin; for removal of soft material in the south
half of the lower 200 feet of this basin to rock; for dredging the
remainder of the turning basin to a depth of 12 feet; for dredging
a basin 20 feet deep, 150 feet wide, and 200 feet long at the mouth
of Poes Run; for dredging a channel 12 feet deep and 80 feet wide
from the mouth of the river to the lower end of the turning basin;
and for dredging a channel 80 feet wide and of such depth, not ex-
ceeding 12 feet; as can be obtained without rock excavation from
the upper end of the turning basin to the head of the existing project,
generally in accordance with the plan presented by the division en-
gineer, at an estimated first cost of $110,000, with annual maintenance
of $11,000, including that now required; subject to certain conditions
of local cooperation (H. Doc. No. 223, 76th Cong., 1st sess.).
   Local cooperation.-Fully complied with. Local interests are re-
quired to furnish suitable areas for the disposal of dredged material
for future maintenance.
   Terminal facilities.-Wharves and terminals served by the Ap-
pomattox are situated on the river front at Petersburg. The wharves
constitute a continuous timber bulkhead on piling and have an ag-
gregate length of about 2,313 feet. There is one mooring trestle used
for sand and gravel loading, located 2.5 miles downstream from Peters-
burg. The terminal facilities are considered adequate for the present
river commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1931. The controlling depth in September 1942 was 10 feet at mean
low water.
   The total costs and expenditures under the existing project were
$1,233,211.38, of which $830,151 was for new work and $403,060.38 for
maintenance. Of the total expenditure, $938,211.38 was applied to
the navigable channel and $295,000 to the diversion channel.
                RIVERS AND HARBORS-NORFOLK,                            VA.,       DISTRICT                  381
  Proposed operations.-An allotment of $16,000 made in July 1944,
will be applied as follows:
Maintenance:
    Maintenance of the channel between the mouth and Petersburg by
      contract, November 1944_               _____                     $12, 800
    Miscellaneous condition surveys, June 1944 to July 1945_----------   3, 200

             Total for allwork______________________________________16,000
   The additional sum of $46,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Maintenance of the channel between the mouth and Petersburg, by
      contract, May and June 1946-- _      ------------               $25, 000
    Repair of levee between the navigation and diversion channels, by
      contract, January and February 1946_                 __          18, 000
    Miscellaneous condition surveys, June 1945 to July 1946---------    3, 000

           Total for all work ------------------------------------------                                 46,000
  The proposed expenditure exceeds the average for the last 5 years,
as it is necessary to repair the levee between the navigation and the
diversion channels. This levee is in very poor conidition and a heavy
rain in this locality will probably result in a break in the levee, which
will form shoals in the navigation channel.
                                    Cost and financial summary
Cost of new work to June 30, 1944_ __     ___$852,                                                       651.00
Cost of maintenance to June 30, 1944-----------------                                               403, 060. 38

           Total cost of permanent work to June 30, 1944_--                                   -1,255,    711. 38
Net total explnditures -- -     -     -    --                                      - --           1,255, 711. 38
Total amount appropriated to June 30, 1944                                  ---           -       1, 255, 711. 38

   Fiscal year ending June 30          1940           1941           1942                 1943           1944


C ost of new w ork - - - - - - - - . - - - - - - -. - - - - - - . - - . . . . . . - - - - - - . . . . . . .
Cost of maintenance.                    $6, 620. 25  $29,320.45        $353.57     $35,088.78
Total expended_ -6,                      620. 25     29, 320.45        353.57         35, 088.78

Allotted        -     --              27, 500.00     17, 500.00     12, 500.00       -6,120. 99             -



Amount allotted in July 1944_ ____________-------$16,                                                    000. 00
Amount available during fiscal year 1945_------------------                                          16, 000. 00

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance --------------------------------                                           46, 000.00
  1Exclusive of available fund.s:

8. PORTSMOUTH HARBOR, VA., CHANNEL TO NANSEMOND ORDNANCE
                           DEPOT

   Location.-This channel is located at the westerly end of Hampton
Roads, at the mouth of Nansemond River. (See U. S. Coast and
Geodetic Survey Charts Nos. 400, 529, and 1222.)
   Existing project.'--This provides for dredging a channel 100 feet
wide from deep water in Hampton Roads shoreward approximately
2,400 feet to a turning basin varying in width from 100 to 300 feet,
approximately 300 feet long, all to a depth of 12 feet at mean low
water; and the construction of a timber wharf apprcximately 650
feet long connecting the turning basin with the shore.                                           Under ordi-
382      REPORT OF CHIEF OF ENGINEERS,                          U. S. ARMY,            1944.

nary conditions the mean tidal range is 2.7 feet and the extremes
minus 2 feet and plus 9.5 feet.
   Tke estimated cost of new work made in 1940 was $117,000. The
latest (1940) approved estimate for annual cost of maintenance is
$5, 000.
   The existing project was adopted by the River and Harbor Act of
October 17, 1940, in accordance with a report on file in the Office
of the Chief of Engineers.
   Termisal facilities.-There are no terminal facilities located in the
vicinity, except the wharf constructed under the project. The termi-
nal facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-Maintenance dredging
under contract was commenced on December 8, 1943, and continued
until January 16, 1944, when the work was completed. There were
removed 58,007 cubic yards of material. The cost of the work was
$22,431.19. Miscellaneous condition surveys were made during the
year at a cost of $818.14, all for maintenance.
   The total cost was $23,249.33, all for maintenance.         The total
expenditure was $26,548.25.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1942. The controlling depth in January 1944 was 11.5 feet
at mean low water.
  The total cost was $213,981.07, of which $165,565.50 was for new
work and $48,415.57 for maintenance. The total expenditure was
$216,979.99.
  Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year, $15,318.93, plus an allotment of
$15.000 made in July 1944, a total of $30,318.93, will be applied as
follows:
Maintenance:
   Dredging in the channel and turning basin to restore project
      dimensions, by contract, February and March 1945         - - $28, 800. 00
   Miscellaneous condition surveys, June 1944 to July 1945 .....     1, 518. 93
       Total for all work-_           ---------------------------                         30, 318.93
   The additional sum of $46,500 can be profitably expended during the
fiscal year 1946 as follows:
Maintenance:
   Dredging in the channel and turning basin to restore project dimen-
      sions, bWycontract, April and May 1946---------------------      $45, 000
    Miscellaneous condition surveys, June 1945 to July 1946-----------   1, 500
      Total for all work      _   ------------------                                           46, 500
                              Cost and financial summary
Cost of new work to June 30, 1944-------------------- ------                            $165, 565. 50
Cost of maintenance to June 30, 1944-------------------                                   48, 415. 57
       Total cost of permanent work to June 30, 1944                ------------         213, 981. 07
Plus accounts receivable June 30, 1944      -------                                        2, 99& 92
      Gross total costs to June 30, 1944---- -------------                               216, 979.99

Net total expenditures --------------------                                              216, 979. 99
Unexpended balance June 30, 1944...                                                -      12, 320. 01
      Total amount appropriated to June 30, 1944-                                        229, 300. 00
                    RIVERS         AND HARBORS-NORFOLK,                                    VA.,       DISTRICT                   383

    Fiscal year ending June 30                         1940         1941                 1942                 1943            1944

Cost of new work- .----------------------                    $29, 320. 10     $140, 433. 49             -$4, 188. 09
Cost of maintenance ----........... _ ___---------------....----     __... _ ____                            25, 166. 24     $23, 249. 33

       Total cost----------        __      ___-         --    --   29, 320. 10         140, 433. 49          20, 978.15       23, 249. 33
Total expended ....             ..------------------               17, 637.14          147, 606. 24          25, 188. 36      26, 548. 25
Allotted-.....__-       -...               _ __43,
                               -......--......                        000. 00          157, 300.00-    ...    .   ..   -      29, 000.00


Balance unexpended July 1, 1943--- ---------                                                                               $9, 868. 26
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942__-- -_------_29,                                                                                     000.00
      Amount to be accounted for_------                                                         -            _             38, 868. 26
Gross amount expended_--        -----                                            ---                                       26, 548. 25
      Balance unexpended June 30, 1944--                                         -----                  __                 12, 320. 01
Accounts receivable June 30, 1944_--------_                                                                                 2, 998. 92
     Unobligated balance available June 30, 1944                                         ---------                         15, 318. 93
Amount allotted in July 1944_-_            ------                                                     _15,                     000. 00
           Amount available during fiscal year 1945------------------                                                      30, 318. 93
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1-  ----                       ____                                                             46, 500. CO
   1ExclUsive of available funds.

                                          9. YORK SPIT CHANNEL, VA.
   Location.-York Spit Channel lies in the lower Chesapeake Bay
opposite the mouth of York River and about 20 miles northerly from
Atlantic Ocean at the entrance of Chesapeake Bay. (See U. S. Coast
and Geodetic Survey Chart No. 1222.)
   Previous projects.-The original project was adopted March 3, 1905.
For further details see page 389 of the Annual Report for 1932.
   Emisting project.-This provides for a channel 4 miles long, 1,000
feet wide, and 37 feet deep at mean low water between the contours
of that depth in Chesapeake Bay opposite York Spit. Under or-
dinary conditions the mean tidal range is.2.5 feet and the extreme 3.3
feet. The extremes of irregular fluctuation, due to combined wind and
tides, referred to mean low water, are minus 2 feet and plus 9.5 feet.
   The estimated cost of new work revised in 1930 was $590,400. The
latest (1930) approved estimate for annual cost of maintenance is
$24,000.
  ' The existing project was authorized by the following river and
harbor acts:

      Acts                                Work authorized                                                    Documents


Mar.     3, 1905    A channel 35 feet deep and 600 feet wide......                       H. Doc. No. 186, 57th Cong., 2d sess.
Mar.     4, 1913    Channel width increased to 1,000 feet                          -H.      Doc. No. 1190, 62d Cong., 3d sess.
July     3, 1930    Channel depth increased to 37 feet           _ ___                   H. Doc. No. 29, 71st Cong., 1st sess.
                                                                                            (Contains latest published map.)


   Recommended modifications of projeet.-See report on Baltimore
Harbor and Channels, Md., transmitted to Congress March 11, 1943.
   Terminal facilities.-Fora description of the terminal facilities for
this channel, see Baltimore Harbor and Channels, Maryland.
384               REPOT               OF CHIEF OF ENGINEERS,                                     U.      S. ARMY,                1944

  Operations and results during fiscal year.-Costs outstanding in
connection with maintenance dredging with U. S. hopper dredge
Chinook performed during previous fiscal year amounted to $197.30.
  Miscellaneous condition surveys were made during the year at a cost
of $1,877.41, all for maintenance.
   The total cost was $2,074.71, all for maintenance. The total expen-
diture was $935.82.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1943. The controlling depth as ascertained in May 1944 in
midchannel was 37.8 feet and 33.1 feet along the edges. Depths are
referred to mean low water.
  The total costs and expenditures prior to fiscal year 1942 were
included in the project for Baltimore Harbor and Channels, Mary-
land. Since that date the total cost has been $375,639.38, of which
$74,358.58 was for new work and $301,280.80 for maintenance. The
total expenditure has been $380,146.83.
  Proposedoperations.-Theunexpended balance and accounts receiv-
able at the end of the fiscal year, $62,860.62, plus allotment of $22,000
made in July 1944, a total of $84,860.62 will be applied as follows:
Maintenance:
    Dredging in the channel with U. S. hopper dredge Chinook, 13
      months, July and August 1944 ---------------------           $77, 000. 00
    Miscellaneous condition surveys June 1944 to July 1945--------   7, .860. 62

              Total for all work--_                                 ---------                                      -____                   84, 860. 62
   The additional sum of $127,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
    Dredging in the channel to restore project dimensions with U. S.
      hopper dredge Chinook, 2 months, July and August 1945
    Miscellaneous condition surveys June 1945 to July 1946---------
                                                                     $120, 000
                                                                        7, 000
                                                                                                                          --
              Total for all work --------------------------------------                                                                         127, 000

                                                       Cost and financial summary
Cost of new work to June 30, 144 ---------------------------                                                                             $74, 358. 58
Cost of maintenance to June 30, 1944-------------------                                                                                  301, 280. 80
       Total cost of permanent work to June 30, 1944-
Plus accounts receivable June 33, 1944 -------------------------
                                                                 1 375, 639. 38
                                                                     4, 507. 45
                                                                                                                         -
             Gross total costs to June 30, 1944----------------                                                                          380, 146. 83

Net total expenditures -----------------------------------                                                                        1380, 146. 83
Unexpended balance June 30, 1944_------------------ ---                                                                             58, 353. 17
             Total amount appropriated to June 30, 1944------ -------                                                                    438, 50e. 00


     Fiscal year ending June 30                            1940                  1941             1942                  1943                    1944

:Cost of new work                 ....----------- ----------------------------                        $694.60        $73, 663.98          ---
                                  .----
Cost of maintenance --------.......-----------..                                   -2,753.60                         296, 452.49                $2,074.71

         Total cost_ ........................------------                                         3, 448. 20         370,116. 47                 2, 074. 71

Total expended .....                  ._                                         __3,                  448. 20       375, 762. 81                  935. 82

A llo t t e d ... . . . . .   . . .. . . .     -   .     .. . . . . . .. . .     $2 70 , 0 0 0   4 5 , 00 0 . 00     12 3 , 5 0 0 . 00     -



     Costsand expenditures prior to fiscal year 1942, are included in Baltimore Harbor and channels project.
               RIVERS AND HARBORS-NORFOLK,                                      VA.,       DISTRICT                    385
Balance unexpended July 1, 1943 _--___                                    --           -          -        $59, 288. 99
                              -- _
Gross amount expended_ ________                               ___--
                                                              --           --          --             --            935. 82
      Balance unexpended June 30, 1944 -----------------                                                       58, 353. 17
Accounts receivable June 30, 1944 ___-      --                                               __                 4, 507. 45

     Unobligated balance available June 30, 1944                                ---               -            62, 860. 62
Amount alloted in July 1944_ _ _ ____________                                   --                             22, 000. 00

         Amount available during fiscal year 1945                      --------------                          84, 860. 62

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintepance 2                                __    127, 000. 00
2 Exclusive of available funds.


10. WATERWAY             FROM NORFOLK, VA., TO THE                                     SOUNDS OF NORTH
                                   CAROLINA

   Location.-This water route extends south from Norfolk, Va., to
Pamlico Sound, N. C. (See U. S. Coast and Geodetic Survey Charts
Nos. 1227, 1228, 1229, and 1231.) For description see page 492,
Annual Report for 1932.
   Existing project.-This provides for dredging channels to depths
of 10 feet at mean low water, over a least bottom width of 80 feet,
in Deep Creek, Va.; Turners Cut, Pasquotank River, and Croatan
Sound, N. C., and maintaining the Dismal Swamp Canal (which
connects Deep Creek and Turners Cut) to a depth of about 9 feet
over a bottom width of 50 feet. The limiting width of 80 feet applies
to Turners Cut; the channels in Deep Creek and Pasquotank River
have been dredged to depths of 10 feet over bottom widths of 100 feet,
while the Croatan Sound Channel has been dredged to a depth of 12
feet over a bottom width of 200 feet. The project further provides
for the protection of banks in Turners Cut with sheet piling, and cut-
ting certain sharp points in Pasquotank River, in order to shorten
its course. The component parts of the waterway and their lengths
are about as follows: Deep Creek, Va., 3 miles; Dismal Swamp Canal,
22 miles; Turners Cut, 4.5 miles; Pasquotank River, 30 miles; Albe-
marle Sound, 20 miles, and Croatan Sound, 12.5 miles, a total of 92
miles. The total length of the Dismal Swamp Canal is about 25
miles, of which a 22-mile portion, a lock canal extending between
Deep Creek, Va., and South Mills, N. C., alone is navigable.
                Data relative to the completed locks included in the project

                                         Dimensions             Depthsi
                                                                miter sills
MilesYear
from-         Location               Great-                                      Character of          opened       Actual
folk
folk,                           of length
                               Width                                             foundation           togatgth
                                                                                                          navi-      cost
Va.                           chm-          avail-    Lift    Upper Lower                             gation
                                          a-able
                                   ber      for full
                                            width


                                   Feet       Feet     Feet     Feet    Feet
10. 7   Dismal Swamp Ca-            52         300      12       12      12    Natural earth           1940      $348, 878. 83
          nal (Deep Creek,                                                       with cut-off
          Va.).                                                                  walls.
33. 1   Dismal Swamp Ca-            52         300      12       12      13       do ......            1941       372, 556. 40
          nal (South Mills,
           N. C.).
         616634-45-pt. 1, vol. 1-               25
386        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                       1944

   The waterway is nontidal except in Deep Creek, where the mean
tidal range under ordinary conditions is 3 feet and the extremes 2.3
and 3.2 feet. The extremes of irregular fluctuation in this stream,
due to combined effect of tides and wind., referred to mean low water,
are about -2 feet and +9.62 feet. The remaining sections of the
waterway are nontidal and not subject to floods. There are at times,
however, variations of 1 to 2 feet in level, due to wind.
   The estimate of cost for new work, made in 1899, was $274,310,
exclusive of the purchase price of the Dismal Swamp Canal. The
latest (1928) approved estimate of cost for annual maintenance is
$50,000, including $45,000 for operation and care of the waterway.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                                      Documents


Mar. 3,1899     Present project dimensions and original route   - .-   H. Doc. No. 317, 54th Cong., 1st sess.,
                                                                         and Annual Report, 1896, p. 1086;
                                                                         H. Doc. No. 131, 55th Cong., 3d sess.,
                                                                         and Annual Report, 1899, p. 1485.
Mar. 3,1925     Purchase of the Lake Drummond Canal (Dismal            Rivers and Harbors Committee Doc.
                 Swamp Canal).                                           No. 5, 67th Cong., 2d sess.
June 26,19341   Operating and care of the works of improvement
                 provided for with funds from War Department
                 appropriations for rivers and harbors.


  1 Permanent Appropriations Repeal Act.
  Latest published map is found in H. Doc. No. 391, 62d Cong., 2d sess.


   Terminal facilities.--The northern end of this waterway is in
Norfolk Harbor, Va., the terminal facilities of which are described
under this heading in the report on that improvement. There are
3 small wharves on the Dismal Swamp Canal. There are 3 landings
along the Pasquotank River between the south end of the canal and
Elizabeth City. At Elizabeth City, N. C., there are 18 wharves.
Below Elizabeth City there are 2 wharves on the east bank of the
Pasquotank River. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year.-Maintenance dredging
under contract in Turners Cut, Dismal Swamp Canal, and Deep Creek
was commenced on March 2, 1944, and continued until June 20, 1944,
when the work was completed. There were removed 127,543 cubic
yards of material. The cost of the work was $72,557.61.
   Maintenance snagging and bank trimming with U. S. derrick boat
Roanoke in the Dismal Swamp Canal and Turners Cut was commenced
December 22, 1943, and continued intermittently until the end of the
fiscal year. The cost of the work was $9,740.36.
   Miscellaneous surveys and triangulation controls were made during
the year at a cost of $14,642.45.
   Maintenance cost for work performed in connection with the opera-
tion and care of the Dismal Swamp Canal was as follows:
   Operation, $87,789.11; maintenance and repairs, $11,180.97; improv-
ment and reconstruction, $50.16.
             RIVERS AND       HARBORS-NORFOLK,                        VA., DISTRICT          387
  The total cost was $195,960.66, of which $96,940.42 was for mainte-
nance, and $99,020.24 was for operation and care of the Dismal Swamp
Canal. The total expenditure was $179,875.63.
   Conditionat end of fiscal year.-The existing project was completed
in 1903. The Dismal Swamp Canal was acquired by the United States
March 30, 1929, from the Lake Drummond Canal & Water Co. for
$500,000. Project depth exists for the full width in all sections except
Pasquotank River, where project depth exists only for the center half
of the channel.
   The total cost was $3,023,855.16, of which $751,196.46 (including
$500,000 for the purchase of the Dismal Swamp Canal) was for new
work; $611,665.03 for operating and care, and $1,660,993.67 for
maintenance.
   The total expenditure was $3,013,984.57. In addition, the sum of
$338,837.89 was expended between March 30, 1929, and June 30, 1936,
on the operation and care of the works of improvement under the pro-
visions of the permanent indefinite appropriation for such purposes.
  Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year, $38,425.41, plus an allotment of
$104,000 made in July 1944, a total of $142,425.41, will be applied as
follows:
Accounts payable_ ----------------------------------------                 $10, 740. 09)
Maintenance:
    Dredging, snagging, and bank trimming in the Dismal Swamp
      Canal, Turners Cut, and Pasquotank River, with U. S. derrick
      boat Roanoke, 4 months, July to October 1944                                600. 00
                                                                                ,--------
    Miscellaneous surveys, triangulation control, and water-level
      investigations, June 1944 to July 1945--------------                   12, 085. 32
    Replace approximately 320 linear feet of timber bulkhead with
      steel sheet piling adjacent to the lock at South Mills, N. C., by
      contract, July and August 1944_- _                  -------        -23,     500. 00
    Operation of Dismal Swamp Canal:
         Operation of locks, bridges, and other works            --------------
                                                                             68, 000. 00
         Maintenance and repairs_             -------             -_____      14, 500. 00

            Total for all work----        -----------                                 142, 425. 41
   The additional sum of $141,600 can be profitably expended during
fiscal year 1946 as follows:
Maintenance:
    Maintenance of the channels in Deep Creek and Dismal Swamp
      Canal, by contract, October to November 1945_ ----            _.- $15, 000
   Dredging, snagging, and bank trimming in the Dismal Swamp
      Canal, Turners Cut, and Pasquotank River, with U. S. derrick
      boat Roanoke, 4 months, July to October 1945.                   ----------------
                                                                         13, 600
    Miscellaneous surveys, triangulation control, and water-level in-
      vestigations, June 1945 to July 1946_--              --------      12, 000
   Operation of Dismal Swamp Canal:
        Operation of locks, bridges, and other works---------------- 70, 000
        Maintenance and repairs_--------------------------               31, 000,
           Total for all work -------------------------------           141, 600

                             Cost and financialsummary
Cost of new work to June 30, 1944                                                    $751, 196. 46
Cost of maintenance to June 30, 1944                    -----                      2, 611, 496. 59
       Total cost of permanent work to June 30, 1944                               3, 362, 693. 05
Plus accounts receivable June 30, 1944_-                                                   869. 50
       Gross total costs to June 30, 1944------                 ---        --      3, 363, 562. 55
388             REPORT OF CHIEF OF ENGINEERS,                                                 U.      S. ARMY,         1944

Minus accounts payable June 30, 1944---                                                 --------                             $10, 740. 09

      Net total expenditures_ -_                                                  -3,                                        352, 822. 46
Unexpended balance June 30, 1944-                                                                                             37, 555. 91
            Total amount appropriated to June 30, 1944------------                                                      3, 390, 378. 37


    Fiscal year ending June 30                             1940            1941                    1942         1943              1944

Cost of new work .............
                           .-
Cost of maintenance.......-----------.                  $475,026. 76    $390,005. 13         $110, 768. 59   $149, 584. 11      $195, 960. 66

Total expended...............----------------            426, 278. 95    441, 477. 90         110, 247. 71    158, 981. 68       179, 875. 63

Allotted........                          ..---------
                                  ...-------------        68, 400. 00    101, 000. 00         185, 600.00     130, 602.78         20, 367. 70


Balance unexpended July 1, 1943 -   --    -    -      -                                                                -$197,     063. 84
Amount allotted from War Department Civil Appropriation Act
approved May 23, 1941 -__20,                                                                                                     367. 70

      Amount to be accounted for-----------------------                                                                      217, 431. 54
Gross amount expended_ -179,                                                                                                      875. 63

     Balance unexpended June 30, 1944---37,                                                                                       555. 91
Amount covered by uncompleted contracts---------------11,                                                                         503. 48

     Balance available June 30, 1944_--26,                                                                                        052. 43
Accounts receivable June 30, 1944----------------------------                                                                     869. 50

     Unobligated balance available Jule 30, 1944_                                                                             26, 921. 93
Amount allotted in July 1944 - -104,                                                                                              000. 00

            Amount available during fiscal year 19454------------                                                             30, 921. 93
Amount that can be profitably expended in fiscal year ending June
[_30, 1946, for maintenance 1 _-     -            -___--                                                                     141,600. 00
   1Exclusive of available funds.

         11. INLAND WATERWAY FROM NORFOLK, VA., TO BEAUFORT
                             INLET, N. C.

   Location.-The improvement described consists of a sea-level inland
water route approximately paralleling the Atlantic coast between
Norfolk, Va., and Beaufort Inlet, N. C., a distance of 197.91 statute
miles. For description of the waterway see pages 495-497, Annual
Report for 1932. (See U. S. Coast and Geodetic Survey Charts Nos.
1227, 1228, 1231, and 1233.)
   Previous projects.-Partial projects were adopted by River and
Harbor Acts of March 3, 1873, June 18, 1878, March 3, 1879, June 14,
1880, March 3, 1881, and September 19, 1890. For further details see
page 497, Annual Report for 1932, and page 476, Annual Report for
1938.
   Existing project.-This provides for an inland waterway with a
depth of 12 feet at mean low water between Norfolk, Va., and Beau-
fort Inlet, N. C., a distance of 197.91 miles, with bottom widths varying
from 90 feet in land cuts to 300 feet in open waters, for the construction
of a tidal guard lock in the Albemarle and Chesapeake Canal at or near
Great Bridge, Va., and for the construction, operation and mainte-
nance of a suitable bridge across the waterway near Fairfield, N. C.
                  RIVERS AND HIARBORS-NORFOLK,                             VA., DISTRICT                389
                  Data relative to the completed lock included in the project

                                    Dimensions               Depth on
                                                             miter sills
MilesYear
from                                   Great-                                                 Ya
  oa-     Locati                           st-                              Character of    opened    Actual
folk,                            Width length                               foundation     to navi-    cost
Va.                             chm- avail-        Lift    Upper Lower                      gation
                                  V.chm able
                                  ber  for full
                                       width

                                  Feet      Feet    Feet     Feet   Feet
12.04    Albemarle and Ches-       75        600    2. 7    (1)     (1)   Piles in sand      1932 $499,913.09
            apeake Canal                                                     andshells.
            (Great Bridge,
           Va.).

116 feet at mean low water.

   The waterway is nontidal except in the Southern Branch of Eliza-
beth River and in Beaufort Inlet, N. C. In the Southern Branch the
mean tidal range under ordinary conditions is 2.7 feet, and the extremes
are 2.3 and 3.2 feet. The extremes of irregular fluctuation, due to the
combined effect of the tide and wind, referred to mean low water, are
 -2 and + 9.62 feet. In Beaufort Inlet, N. C., under ordinary condi-
tions, the mean tidal range is 2.6 feet and the extremes are 2.3 and 3.2
feet.
   The estimate of cost for new work, revised in 1933, was $7,870,600,
exclusive of amounts expended on previous projects, but including
the purchase price of the canal. The latest (1933) approved estimate
for annual cost of maintenance is $196,600, including $106,000 for
operation and care of the waterway.
   The existing project was authorized by the following river and
harbor acts:

      Acts                      Work authorized                                     Documents


July 25,1912   Original route of the Norfolk-Beaufort Inlet sec-       H. Doc. No. 391, 62d Cong., 2d sess.
                tion.
    Do-....... Purchase of canal --------------------------            H. Doc. No. 589, 62d Cong., 2d sess.
Aug. 8,1917 Change in route; following changes approved by             H. Docs. Nos. 1478, 63d Cong., 3d sess.
                Secretary of War Apr. 14, 1919:                         and 1136, 64th Cong., 1st sess.1
                   Albemarle Sound-Pamlico Sound section:
                      Changed from "Alligator River-Rose Bay
                      route" to "Alligator River-Pungo River
                      route."
                   Pamlico Sound-Neuse             River section:
                      Changed from "Pamlico Sound-Brant
                      Shoal-Neuse River route" to "Goose
                      Creek-Bay River route."
July 18, 1918 Alligator River-Pungo River route (proposed              Approved by Secretary of War May
                land cut connecting the rivers): Changed from           15, 1919.
                 i straight line to a bent line approaching nearer
                the town of Fairfield, N. C.
Mar. 4,1933 2 Construction of a suitable bridge near Fairfield,        Rivers and Harbors Committee Doc.
                N. C.                                                    No. 5, 7d Cong., 1st sess.
                                                                                                             1
July 3,1930 Construction of a tidal lock at Great Bridge at a          S. Doc. No. 23, 71st Cong., 1st sess.
                limit of cost of not to exceed $500,000.
June 26,1934 3 Operating and care of the works of improvement
                provided for with funds from War Department
                appropriations for rivers and harbors.

1Contain latest published maps.
2Public, No. 433, 72d Cong.
1   Permanent appropriations repeal act.
390      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,       1944

   Recomm.ended modifications of project.-Under date of December
28, 1938, the Chief of Engineers recommended modification of the
existing project so as to provide protection to the canal property in
the vicinity of the lock at Great Bridge against flooding by storm
tides, through construction of necessary dikes and appurtenant works,
at an estimated cost of $39,000, and an annual maintenance of $1,000,
in addition to that now required. (H. Doc. No. 117, 76th Cong., 1st
sess.)
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-The north end of this waterway is in Nor-
folk Harbor, the terminal facilities of which are described in the
report on that improvement. Between Norfolk and Albemarle Sound
there are 13 wharves or landings. Along the route between Albe-
marle Sound and Pamlico River are 10 wharves. Located upon
waters tributary to the Pamlico River-Neuse River section are 15
wharves, aggregating a frontage of about 600 feet. There are 8
wharves on the section of the waterway from Neuse River to Beaufort
Inlet, with a combined frontage of about 400 feet. At Morehead
City, N. C., there are 27 wharves, their total frontage being about 500
feet. Contiguous to the harbor at Beaufort, N. C., the southern ter-
minus of the waterway, there are 46 wharves, their total frontage
being about 1,200 feet. The facilities are considered adequate for
existing commerce.
   Operationsand results during fiscal year.-Maintenance work under
contract for the construction of a highway bridge at Great Bridge, Va.,
was in progress at the beginning of the fiscal year and continued to
August 15, 1943, when the work was completed. The cost of the work
was $18,386.58.
   Maintenance dredging under contract in the Southern Branch of
Elizabeth River, the Virginia land cut section and North Landing
River was in progress at the beginning of the fiscal year and continued
to August 22, 1943, when the work was completed. Therewere re-
moved 142,747 cubic yards of material. The cost of the work was
 $51,208.13.
   Maintenance snagging and bank trimming with U. S. derrick boat
Roanoke in the Virginia land cut section and North Landing River
was commenced on August 11, 1943, and continued intermittently to
May 6, 1944, when the work was completed. The cost of the work was
$20,055.79.
   Maintenance work under contract for construction of additional
mooring facilities and fenders at Great Bridge, Va., was commenced
on December 6, 1943, and continued to March 24, 1944, when the work
was completed. The cost of the work was $47,315.32.
   Maintenance work under contract for the construction of approxi-
mately 860 lineal feet of timber sheet pile bulkhead immediately east
of Great Bridge, Va., was commenced on April 10, 1944, and continued
to June 21, 1944, when the work was completed. The cost of the
work was $32,947.77.
   Preliminary investigations in connection with general repairs to
bridge and fenders at North Landing, Va., were made at a cost of
$14.25.
                RIVERS AND                HARBORS-NORFOLK,                        VA.,    DISTRICT                  391
   Maintenance snagging with U. S. derrick boat Northeast in the
Adams Creek-Core Creek land cut was commenced on February 16,
1944, and continued to March 18, 1944, when the work was completed.
The cost of the work was $3,348.89.
   Maintenance work under contract for the construction of one set of
tie-up dolphins, consisting of eleven 11-pile.clusters, 4,000 feet north of
Morehead City-Beaufort highway bridge at Morehead City was per-
formed during the year at a cost of $17,133.54.
   Miscellaneous surveys, water level studies, and maintenance of tide
gages were made during the year at a cost of $18,370.73.
   Maintenance cost for work done in connection with the operation
and care of the waterway were as follows: Operations $120,593.40;
maintenance and repairs, $72,038.67; improvement and reconstruction,
$153.43.
   The total cost of the work was $401,569.50, of which $208,781 was for
maintenance, and $192,788.50 for operation and care. All work was
for maintenance, of which $305,099.28 pertains to the Norfolk, Va.,
district, and $96,470.22 to the Wilmington, N. C., district.
   The total expenditure was $453,077 of which $354,055 was disbursed
by the Norfolk, Va., district and $99,022 was disbursed by the Wilming-
ton, N. C., district.
   Condition at end of fiscal year.-The existing project was completed
in 1935. The controlling depth at the end of the fiscal year was 12
feet, at mean low water.
   The Albemarle and Chesapeake Canal was acquired by the United
States from the Chesapeake & Albemarle Canal Co. on April 30, 1913,
for $500,000.
   The total costs and expenditures on the existing project to June 30,
1944, were as follows:

                                                     New work         Maintenance        Operating and          Total
                                                                                             care

Norfolk district:
   Regular funds------------------                  $8,123, 213.36 1$2, 067,447. 85        $901, 326. 57    $11, 091, 987. 78
   Public Works funds----------------                   80, 282.36 _                                              80, 282.36
Wilmington district____... ..       ...         -------------
                                                           ____         671, 085.66          298, 364. 97        969, 450. 63

      Total         .------------------------        8, 203, 495.72    2, 738, 533.51      1,199, 691. 54    12,141, 720. 77

  1Includes $904.95 for Bennetts Creek, N. C.

  The expenditures were $12,059,815.90 from regular funds and $80,-
282.36 from Public Works funds, a total of $12,140,098.26, of which
$11,168,207.76 was disbursed by the Norfolk district, and $971,890.50
was disbursed by the Wilmington district.
  In addition, the sum of $975,744.25 was expended between May 1
1913, and June 30, 1936, on the operation and care of the works of
improvement under the provision of the Permanent Indefinite Appro-
priation for such purposes.
  Proposed operations.-The unexpended balance and accounts re-
ceivable at the end of the fiscal year, $69,073.51, plus an allotment
392      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

of $227,000 made in July 1944, a total of $296,073.51, will be applied
as follows:
Accounts payable June 30, 1944----------_--_               _- __-     $7, 345, 34
Maintenance:
    Snagging and bank trimming in Virginia Land Cut and North
      Landing River, with U.. S. derrick boat Roanoke, 4 months,
      March to June 1945                                              13, 600. 00
    Completion, under an existing contract, general repairs to North
      Landing Bridge, and fender system, July and August 1944           -
                                                                      21, 700. 00
    Completion, under an existing contract, reinforcement of fender
      systems at Fairfield, Wilkerson Creek, Hobucken, and Core
      Creek Bridges, July and August 1944_____
    Dredging south of the Virginia-North Carolina State line, by
                                                                        -
                                                                      27, 736. 58

      contract, December 1944 and January 1945----__            _-    28, 000. 00
    Snagging and bank trimming south of the Virginia-North Caro-
      lina State line with United States derrick boat, January and
      February 1945_                                                   3, 200. 00
    Miscellaneous surveys and water level investigations, June 1944
      to July 1945_                                                   26, 691. 59
    Operation of the waterway:
         Operation of locks, bridges, and other works                112, 000. 00
         Ordinary maintenance and repairs---- ---------------         55, 800. 00
            Total for all work--    -------                                 296, 073. 51
   The additional sum of $374,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
    Snagging and bank trimming in Virginia Land Cut and North Land-
      ing River with U. S. derrick boat Roanoke, January to April 1946-        $12, 000
    Replace approximately 1,000 linear feet of timber bulkhead around
      boat basin at Great Bridge, Va., by contract, October and No-
      vember 1945 -              --------------------------------------         40, 000
    Replace approximately 1,200 linear feet of timber bulkhead on
      north bank of canal between the lock and bridge at Great Bridge,
      Va., by contract, January to March 1946------------- -----                50, 000
    Replace approximately 300 linear feet of timber bulkhead adjacent
      to Great Bridge Bridge on south side of canal, by contract, March
      1946-------------------                   ------------------------------  12, 000
    Repair approximately 600 linear feet of revetment on south side of
      canal between the lock and bridge at Great Bridge, Va., May 1946          10, 000
    Dredging between the Virginia-North Carolina State Line and
      Beaufort Inlet, N. C., by contract, as needed, June 1945 to July
      1946------------------------                                              67, 000
    Snagging with United States derrick boat, south of Virginia-North
      Carolina State line, 2 months, as needed, June 1945 to July 1946           3, 000
    Miscellaneous surveys and water level investigations, June 1945 to
      July 1946 ---------------------------------------------                   15, 000
    Operation of the waterway:
         Operation of locks, bridges, and other works------------ ---          119, 500
         Ordinary maintenance and repairs_-----------------------               45,500
            Total for all work     ----------------------------------           374, 000

                             Cost and financial summary

Cost of new work to June 30, 1944                                       $8, 495, 591. 37
Cost of maintenance to June 30, 1944---------------- ----                4, 966, 773. 65
      Total cost of permanent work to June 30, 1944- -------            13, 462, 365. 02
Undistributed costs June 30, 1944-------------------------                    2, 458. 25
       Net total cost to June 30, 1944------------------                13, 464, 823. 27
Plus accounts receivable June 30, 1944-                                       3, 264. 58
       Gross total costs to June 30, 1944---- ---------------           13, 468, 087. 85
                      RIVERS AND HARBORS-NORFOLK,                                       VA.,      DISTRICT                   393
Minus accounts payable June 30, 1944_                                                                                 $7, 345. 34
      Net total expenditures---                                    --------                       _            13, 460, 742. 51
Unexpended balance June 30, 1944_-                                                                                  65, 808. 93
             Total amount appropriated to June 30, 1944---------                                               13, 526, 551. 44


    Fiscal year ending June 30                     1940              1941            1942               1943              1944

C ost of new w ork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .
Cost of maintenance -........... -            $307, 954. 94       $191, 908. 37   $419, 725. 92    $585, 743.67         $401,569. 50
Total expended                                    299, 642. 25
                                 ...----------------               206, 515. 17    382, 963. 24       570, 656. 73       453, 077.00
Allotted--------------_        ------          269, 400.00         479, 700. 00   623, 625.00         350, 000. 00      -58, 650.00



Balance unexpended July 1, 1943$577,535.
                           1943_                                                                                 $577,           93
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942----------- $40, 912. 12
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943------------- 53, 437. 88
                                                                                                                      94, 350. 00
      Amount to be accounted for_--------                 ---                                                        671, 885. 93
Deductions on account of revocations of allotments---------                                                          153, 000. 00
       Net amount to beaccounted for-----------------------518,     885. 93
Gross amount expended_------             ---     $453, 493. 41
Less reimbursements collected-------------------       416. 41
                                                               453, 077. 00
       Balance unexpended June 30, 1944------------------                                                             65, 808. 93
Outstanding liabilities June 30, 1944_                $139. 23   ---------------
Amount covered by uncompleted corttracts           56, 031. 67           ------
                                                                                                                      56, 170. 90
      Balance available June 30, 1944                                                                                  9, 638. 03
Accounts receivable June 30, 1944                                                                 _3,                     264. 58
     Unobligated balance available June 30, 1944---------       12, 902. 61
Amount allotted in July 1944-------------------------------227,     000. 00
            Amount available during fiscal year 1945--239,                                                                902. 61
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_    _    __-_--_       --                                                          374, 000. 00
   1 Exclusive of available funds.


                                        12. BLACKWATER RIVER, VA.

  Location.-This river rises in Prince George County, near Peters-
burg, Va., and flows in a general southeasterly direction for 80 miles,
where it unites with the Nottoway River to form the Chowan River,
which empties into Albemarle Sound. The portion under improve-
ment extends from its mouth to Franklin, Va., a distance of 13 miles.
(See U. S. Geological Survey, Holland quadrangle, Virginia.)
  Previous project.-The original project was adopted by the River
and Harbor Act of June 18, 1878. For further details see page 1802
of Annual Report for 1915 and page 480 of Annual Report for 1938.
  Existing project.-This provides for clearing the 13 miles of river
below Franklin, Va., of obstructions, so as to afford a condition of
easy navigation for boats of 7-foot draft. The stream is nontidal.
The portion of the river under improvement is subject to freshets of
394         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                              1944

short duration, causing rises of 3 to 4 feet, but the general stage
of the river remains for the greater part of the time at the elevation
of Albemarle Sound, with which it connects.
   The estimate of cost for new work made in 1907, exclusive of amount
expended on previous projects, was $8,000. The latest (1928) approved
estimate of cost for annual maintenance is $2,000.
   The existing project was authorized by the River and Harbor Act
of March 2, 1907 (H. Doc. No. 177, 59th Cong., 1st sess.).
  Recommended modifications of project.-Under date of October 19,
1938, the Chief of Engineers recommended modification of the exist-
ing project, so as to provide for a channel 12 feet deep and generally
80 feet wide from the mouth to a point just downstream from the
Seaboard Air Line Railway bridge at Franklin, Va., a distance of
14.5 miles, including cut-off channels of like dimensions through two
bends at Cherry Grove and Georges Bend, and a turning basin of 3.2
acres at Franklin, Va., at an estimated first cost of $120,000, with
annual maintenance of $3,500; subject to certain conditions of local
cooperation (H. Doc. No. 101, 76th Cong., 1st sess.).
   Terminal facilities.-There is a wharf at Franklin, Va., and three
small wharves and a warehouse between this point and the mouth of
the river. All of these are privately owned but are open to the gen-
eral public on equal terms. The facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The .existing project was com-
pleted in 1908. The controlling depth at the end of the fiscal year
was about 7 feet to Franklin, Va., 13 miles above the mouth. The
head of navigation is at Burdette, Va., 25 miles above the mouth.
Navigation is practicable throughout the year.
   The total costs and expenditures under the existing project were
$58,200, of which $2,144.33 was for new work, and $56,055.67 for
maintenance.
  Proposed operations.-An allotment of $12,000 made in July 1944
will be applied to snagging and bank trimming between the mouth
and Franklin with U. S. derrick boat Roanoke, 3 /2 months, October
1944 to February 1945.
  No funds can be profitably expended during the fiscal year 1946
as the proposed work will meet the needs of navigation until a later
date.
                          Cost and financial summary
Cost of new work to June 30, 1944---------------------------$16, 144. 33
Cost of maintenance to June 30, 1944--------------------------56, 055. 67
       Total cost of permanent work to June 30, 1944_-- ---------                                            72, 200. 00
Net total expenditures --------------------------------------                                                72, 200.00
Total amount appropriated to June 30, 1944--------------- ----                                               72, 200. 00

   Fiscal year ending June 30             1940             1941          1942               1943                       1944

Cost of new work -ce--__ ---
                          __...   ....           ----.--                        ,-                 -   --    - --. -        - -
                                                                                                                        -....---
Cost of maintenance-------------         $3,663.09                        $16, 000    ---      ---                        .--- ..
Total expended-----------------          6,090. 11                         16,000--                                           --
Allotted_---------------------.500.00                       $3, 500         6, 000

Amount allotted in July 1944-                                            ------                             $12, 000. 00
Amount available during fiscal year 1945-                             -----                                  12, 000. 00
                    RIVERS AND HARBORS-NORFOLK,                                     VA., DISTRICT                                  395
                                            13. KNOBBS CREEK, N. C.

   Location.-This creek is a nontidal fresh-water stream emptying
into Pasquotank River from the west, about 18 miles above its mouth
in Albemarle Sound. (See U. S. Coast and Geodetic Survey Chart
No. 1228.)
   Existing project.-This provides for a channel 10 feet deep at mean
low water, from that depth in Pasquotank River to the Norfolk-
Southern Railroad bridge, 100 feet wide in Pasquotank River and gen-
erally 60 feet wide in the creek, with a turning basin in the sharp bend
opposite the plant ofthe Chesson Manufacturing Co. Being a branch
of Pasquotank River, Knobbs Creek is affected by the wind tides which
influence that stream and Albemarle Sound. In extreme cases the
water rises 4 to 5 feet above mean low water, but the average fluctuation
of the water surface is about 1 foot.
   The estimate of cost for new work, made in 1927, was $79,000.
The latest (1927) approved estimate for annual cost of maintenance
is $500.
   The existing project was adopted by the River and Harbor Act of
July 3, 1930 (H. Doc. No. 102, 70th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-Fully complied with.
   Terminal facilities.-There are eight wharves with an aggregate
available frontage of 1,200 or 1,400 linear feet located on Knobbs
Creek. The existing wharves are considered adequate for present
commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1931. The controlling depth in February 1933 was 10 feet. The
head of navigation is the upper Norfolk-Southern Railway bridge,
about 1.4 miles above the mouth. Navigation is practicable through-
out the year.
   The total costs and expenditures were $90,500, of which $80,500 was
for new work and $10,000 for maintenance.
   Proposed operations.-No funds are available and no operations are
proposed during fiscal year 1945.
   The sum of $6,000 can be profitably expended during the fiscal year
1946 and will be applied to maintenance dredging, snagging, and bank
trimming with U. S. derrick boat Roanoke, 2 months,.November and
December 1945.
                                                  Cost and financial summary
Cost of new work to June 30, 1944 ---------------                                                                          $80, 500
Cost of maintenance to June 30, 1944.                                                                                       10, 000
       Total cost of permanent work to June 30, 1944---------- ----                                                          90, 500
Net total expenditures    ----------------------------------------                                                           90, 500
Total amount appropriated to June 30, 1944_-----                   - -                                                    -90, 500

    Fiscal year ending June 30                      1940          1941             1942                    1943             1944

Cost of new work .-                                  - - - - -- - - - - - - - - -         - --      - - - - - -- - --             - - - -
Cost of maintenance ..-------------...                $6,000 -       -$4,000                     -------          -   -    ----

Total expended..............------------------.        6,000 -    -       -4,000
Alloted-_ _................----*          --------------              $10,000       -6, 000

Amount that can be profitably expended in fiscal year ending June 30,
1946, for maintenance --      -   -     -      --       -    -    -                                                         $6, 000
396        REPORT OF CHIEF OF ENGINEERS, U.                             S. ARMY,                 1944

    14. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

   The cost of the work during the fiscal year was $33,515.91 and the
expenditure was $39,399.42. The unexpended balance and accounts
receivable, June 30, 1944, $49,925.47 plus an allotment of $37,000
made in July 1944, a total of $86,925.47 will be applied as needed dur-
ing the fiscal year 1945 to payment 'of' expenses to be incurred under
this heading. The additional sum of $94,000 can be profitably ex-
pended during the fiscal year 1946.
                                   Cost and financial summary

Cost of new work to June 30, 1944-
Cost of maintenance to June 30, 1944-- ----                                                          $732, 478. 33
       Total cost of permanent work to June 30, 1944----------- 732, 478. 33
Plus accounts receivable June30, 1944--------------------------7, 629. 46

        Gross total costs to June 30, 1944----------------------740,                                        107. 79
      Net total expenditures_--         ----------                  _                                1 740, 107, 79
Unexpended balance June 30, 1944--_-.---                                                  -             42, 296. 01
        Total amount appropriated to June 30, 1944----_                            --                1 782, 403. 80

   Fiscal year ending June 30         1940          1941   *         1942                 1943                1944

Cost of new work--
C ost of maintenance------------   $52, 429. 97   $68, 216. 57     $76, 493.66          $32, 742. 75       $33, 515. 91
Total expended.----------------57,      851. 11    59, 681.81       84,963.95            32, 453.26         39, 399.42
Allotted ----------------------      45,000.00    104, 700.00 :-            .---- _-    95, 500.00      - -          -
Balance unexpended July 1, 1943_ ---------.---------.                                                  $81, 695. 43
Gross amount expended-- -------  _______-------39,                                                          399.42

      Balance unexpended June 30, 1944_--_-_--                                                   .----- 42, 296. 01
Outstanding liabilities June 30, 1944_ ------.----------                                                 3, 289. 97
      Balance available June 30, 1944_---- ---------                                          .---      39, 006. 04
Accounts receivable June 30, 1944_------     _-----------..---.--7,                                         629. 46
     Unobligated balance available June 30, 1944                    --------------                      46, 635. 50
Amount allotted in July, 1944---- ----------------------------                                          37, 000. 00
        Amount available during fiscal year 1945---- -------------                                      83, 635. 50

Amount that can be profitably expended in fiscal year ending June
   30, 1946 for mafntenance 2-_-_----_-__.__.___                           .____._._                    94, 000. 00
  SIn addition, $912.50 contributed funds expended on beach erosion study.
  SExclusive of available funds.
                         RIVERS AND                  HARBORS--NORFOLK,                       VA.) DISTRICT                                    397
15. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                        SUBMITTED

                                                                    For last full       Cost and expenditures to               Estimated
                                                                     report see               June 30, 1944                      amount
                            Name of project                         Annual Re--                                                required to
                                                                     port for-          New work         Maintenance             complete


1.   Willoughby Channel, Va.'-                                         1943             $8, 500. 00          $15, 600. 27              (2)
2.   Lafay ette R iv er, 1V a.1 - . -. . . . . . . . . .               1940             12, 048. 19    --------------              (2)
3.   Deep Creek, Va. --------------------------                        1941             25, 637.45                282.66                     $5,600
4.   Pagan River, Va.t -------------------------                       1942             51, 425.49           135,125.18                (2)
5.   Nansemond River, Va.1 --------------------                        1943            167, 477.11            54,143. 82               (2)
6.   Mattaponi River, Va.11 ---------------------                      1942             83, 835.87           113,497.45                (2)
7.   Pamunkey River, Va. 3-                -          -                1942             31,376.44            108, 248.53               (2)
8.   York River, Va. --------------------------                        1941            180,904. 20           173,354. 65                128, 000
9.   Channel connecting York River, Va., with
        Back Creek to Slaight's Wharf 1-----._._..                      1938              14, 854. 71 ---------------                   (2)
10.   Horn Harbor, Va.' ------------------------
                                5                                       1937              11,486.79 ..-..--                             (2)
11.   Onancock River, Va. 8 ......            ........                  1942             119, 608. 51      26, 983.55                         25, 500
12.   Nandua Creek, Va.1 .-----------------------                       1932               6,987.81 - - - -        -                    (2)
13.   Occohannock Creek, Va.'_                                          1943              13,859.14        33, 315. 20                  (2)
14.   Cape Charles City Harbor, Va.1 7 8             -----------        1943             120, 049. 27      60, 313.08                (2)
15.   Little Machipongo River, Va. ---------------                      1931              15,000.00 --------------                  (2)


  I Channels adequate for commerce.
  2 Completed.
  3Modification recommended Feb. 27, 1940, in H. Doc. No. 671, 76th Cong. 3d sess.
    TIn addition, $2,500 expended from contributed funds.
  2 Awaiting local cooperation.
  6 Modification recommended June 13, 1939, in H. Doc. No. 358, 76th Cong. 1st sess.

  7 Abandonment of the project adopted in 1890 was recommended in 1915 (HII.Doc. No. 524, 64th Cong,
1st sess).
  8 Modification recommended by the Chief of Engineers, in a report requested by Rivers and Harbors
Committee resolution adopted Aug. 1, 1941, and transmitted to Congress by the Secretary of War July 23,
1942.

                      16. PLANT ALLOTMENT, NORFOLK, VA., DISTRICT
                           Cost and financial summary
Undistributed costs June 30, 1944--------------                                                                          -$151, 555. 11
Plus accounts receivable June 30, 1944.-        - -----                                                 ------                78, 211. 48
      Gross total costs to June 30, 1944 ------------------                                                              --    73, 343. 63
Minus accounts payable June 30, 1944_ --------              ---                                                               139, 375. 68
      Net total expenditures-  -----                                                -                          __         ---
                                                                                                                          -212,    719. 31
Unexpended balance June 30, 1944o-__                                     -----                          -__                   834, 423.04
             Total amount appropriated to June 30, 1944                                                                       621, 703. 73

      Fiscal year ending June 30                       1940            1941                1942               * 1943               1944

Total expended._......__              .......   --   $11, 089. 42   $144,924. 75 -$338,407.18            -$573, 587.31         -$117,         385. 52
Allotted ................       _.-              .    45,944. 27     150,000.00           38, 070. 53    -.      .....          -350,000.         00


Balance unexpended July 1, 1943 ------------           -----                                                             $1, 067, 0r37. 52
Deductions on account of revocation of allotments_---------                                                      -           350, 000. 00
       Net amount to be accounted for__--_--------------                                                                      717, 037. 52
Gross amount expended_   -------------------- $1, 450, 764. 73
Less:
     Reimbursements collected - $1, 567, 990. 30
                          ......--
      Receipts from sales------            159. 95
                                   -- -  ---             1, 568, 150. 25
                                                                                                                          - 117, 385.52
       Balance unexpended June 30, 1944---------------------                                                                  834, 423. 04
Outstanding liabilities June 30, 1944-------------------------                                                                318, 109. 49
      Balance available June 30, 1944_--------- _                                        -         ---                        516, 313. 55
Accounts receivable June 30, 1944_-----------                                             -----                                78, 211. 48
              Unobligated balance available June 30, 1944------------                                                         594, 525. 03
398              REPORT OF CHIEF OF ENGINEERS,                                      U.    S.       ARMY,      1944

Status of all investigations for navigation called for by river and harbor acts and
                                                     committee resolutions

                                                                       Date trans-Recommenda-
               Locality                    Authorization act            mitted to     Document No.                      tiRecommenda-
                                                                        Congress.

Bennetts Creek, Va-.........             Rivers and Harbors Nov. 16, 1943 .................... Unfavorable.
                                           Committee resolu-
                                           tion, Mar. 24, 1942.
Deep Creek, Va-............ Rivers and Harbors----              .      .
                                           Committee resolu-
                                           tion, Mar. 26, 1940.
Lafa y e tte R iver, V a -.... . . . . . Riv ers a nd H arb ors . . . . . . . .. . . . . . . . . .
                                           Committee resolu-
                                          tion,  Mar. 2, 1939.
Mattaponi River, Va., im Rivers and Harbors Sept. 25, 1944- ...-----                               Favorable.
  provement at West Point,                 Committee resolu-
  Va.                                     tion, July 18, 1941.
Newport News Creek, Va___ Rivers and Harbors_
                                           Committee resolu-
                                          tion, Aug. 13, 1942.
Norfolk Harbor, Va., dis- Rivers and Harbors .........                           .........
posal area for dredged                    Committee resolu-
material.                                tion, June 16, 1944.
Pamunkey River (York Sec. 6 River and Har-_.................
  River system, Virginia)                 bor Act, Aug. 30,
  (supplemental 308).                      1935.
Pasquotank River, N. C., Rivers and Harbors ................
  waterway from Norfolk,                   Committee resolu-
  Va., to the Sounds of                   tion, Jan. 27, 1937.
  North Carolina.



17. PRELIMINARY                       EXAMINATIONS, SURVEYS,                                 AND     CONTINGENCIES
                                          FOR FLOOD CONTROL

  The cost of the work during the fiscal year was $43,051.23 and the
expenditures were $37,064.99.. The unexpended balance June 30,
1944, $85,292.93, plus $70,000 allotted in July 1944, less accounts pay-
able of $6,758.71, a net balance of $148,534.22, will be applied to pay-
ment of expenses incurred under this heading. The additional sum
of $26,500 can be profitably expended during the fiscal year 1946.
                                            SCost      and financialesummary

Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944_                                     _----------$818,                               915. 78

      Total cost of permanent work to June 30, 1944                                      ------------               818, 915. 78
Minus accounts payable June 30, 1944--------------------------                                                        6, 758. 71

      Net total expenditures----------------------------                                                  -         812, 157. 07
Unexpended balance June 30, 1944_----------------     -------                                                        85, 292. 93

             Total amount appropriated to June 30, 1944 --------------                                              897, 450. 00


     Fiscal year ending June 30                     1940           1941               1942             1943              1944

Cost of new work ..
Cost of maintenance .........-                  $154, 220. 02   $231, 203. 62      $193, 405. 94     $74, 854. 95       $43, 051.23
Total expended...............----------------    146,177. 55     231,110.09         193, 428. 94      86, 681.84         37, 064.99
Allotted__...-._-...............                 216, 500.00     232, 450.00    --------------        54,900.00         100,000.00
                      FLOOD CONTROL---NORFOLK,                       VA., DISTRICT                          399
Balance unexpended July 1, 1943_---------            ---                                           $22, 357. 92
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941---.        ---------------                                                 100, 000. 00
      Amount to be accounted for--------------------------                                         122, 357. 92
Gross amount expended_------------                  ----                                            37, 064. 99
      Balance unexpended June 30, 1944-                                                             85, 292. 93
Outstanding liabilities June 30, 1944 --------------------------                                    20, 003. 00
     Balance available June 30, 1944_-------                                               ---      65, 289. 93
Amount allotted in July 1944_---     -----------                                                    70, 000. 00

          Amount available during fiscal year 1945               -----------------                 135, 289. 93

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1-     -    -    __----26,
                                              --                                                         500. 00
1Exclusive of available funds.


Status of all investigations for flood control called for by flood control acts and com-
                                    mittee resolutions

                                                         Date trans-
          Locality                Authorization act       mitted to           Document No.         Recommenda-
                                                          Congress                                     tion

Buggs Island Reservoir, Va.,   Flood Control Com-        May 30, 1944       H. 650,78th Cong.,     Favorable.
  interim report on the Ro  mittee resoltion,                                  2d sess.
  anoke River, Va. and N. C  Aug. 28, 1940.
James River, Va .--------- Flood Control Act,_.................
                            June 22, 1936.
James River, Va. (supple- Sec. 6 River and Har-_.........                       ........
mental 308).                     bor   Act, Aug. 30,
                           1935.
Pamunkey River (York .- ... do ................                            ..........
River system, Virginia)
 (supplemental 308)
Roangke River Reservoirs,      Sec. 7 of Flood Con-      May 30, 1944       H. 650,78th Cong.,        Do.
N. U. (supplemental 308).      trol Act, June 22,                           2d sess.
                                 1936.
Roanoke    River, Va. and      Flood Control Cornm-. .... do ......... do............                 Do.
N. C.                          mittee resolution,
                                Aug. 28, 1940.
Roanoke River,       Va. and   Rivers and Harbors . .. do_........... do............                  Do.
N. C.                           Committee resolu-
                                  tion, Jan. 26, 1942.
Smith River and tributaries,   Flood Control Act, _..       do .........          do............      Do.
Virginia and North Caro-       June 28, 1938.
lina.


     IMPROVEMENT OF RIVERS AND HARBORS IN THE
             WILMINGTON, N. C., DISTRICT
  This district comprises central and eastern North Carolina em-
braced in the drainage basins tributary to the Atlantic Ocean from
the southern boundary of Virginia to Shallotte River, inclusive, with
the exception of the Roanoke River Basin above Weldon, N. C.; the
Meherrin River Basin above Murfreesboro, N. C.; and the Chowan
River Basin above the confluence of the Nottaway and Blackwater
Rivers. It includes the portions of the Intracoastal Waterway from
the northern boundary of North Carolina to Little River, S. C., and
the portion of the waterway from Norfolk, Va., to the sounds of
North Carolina, south of the north shore of Albemarle Sound.
  District engineer: Lt. Col. J. T. Knight, Jr., Corps of Engineers,
to April 29, 1944; Maj. P. E. Werner, Corps of Engineers, acting
district engineer to June 7, 1944; Lt. Col. N. W. Haner, Corps of
400       REPORT OF CHIEF OF ENGINEERS,                U. S. ARMY,    1944

Engineers, acting district engineer to June 23, 1944; Col. E. E. Har-
ing, Corps of Engineers since that date.
   Division engineer: Brig. Gen. J. S. Bragdon, United States Army,
to June 10, 1944; Brig. Gen. R. F. Fowler, United States Army,
since that date.
                                      IMPROVEMENTS

                Navigation                           Navigation-Continued
                                        Page                                    Page
  1. Inland waterway from Nor-               17. Morehead City Harbor, N.
       folk, Va., to Beaufort In-                  C-----                        426
        let, N. C-------------           388 18. Cape Fear River, N. C., at
  2. Meherrin River, N. C      ----      400       and below Wilmington -- _     429
  3. Cashie River, N. C                  402 19. Cape Fear River, N. C.,
  4. Roanoke River, N. C ......          403
  5. Manteo (Shallowbag) Bay,                      above Wilmington .......      432
        N. C    _     - -     -          405 20. Northeast (Cape Fear) Riv-
  6. Far Creek, N. C____                 406       er, N. C-                     435
  7. Pamlico and Tar Rivers,                 21. Examinations, surveys, and
        N. C------------------           407                             ---
                                                   contingencies (general)_      437
  8. RQllinson Channel, N. C    ---      409 22. Other navigation projects
  9. Silver Lake Harbor, N.   C___       410       for which no estimates are
.10. Channel connecting Thor-                      submitted_                    438
       oughfare Bay with Cedar               23. Plant allotment-                439
        Bay, N. C_         _---          412
11. Drum Inlet, N. C___--               413
12. Beaufort Harbor, N. C .....         414
13. Waterway connecting Pam-                              Flood control
       lico Sound and Beaufort
        Harbor, N. C_         -_ _       416 24. Snagging and clearing under
14. Channel from Back Sound                       authority of sec. 2 of the
       to Lookout Bight, N. C _                    Flood Control Act ap-
                                         419
15. Inland waterway, Beaufort                     proved August 28, 1937 __     439
       to Cape Fear River, N. C.,            25. Preliminary    examinations
       including    waterway       to              and surveys for flood con-
       Jacksonville, N. C ....           420       trol--------------------     * 440
16. Intracoastal waterway, Cape             26. Other flood-control projects
        Fear River, N. C., to Win-                 for which no estimates are
       yah Bay, S. C------               423       submitted                     441

1. INLAND WATERWAY FROM NORFOLK, VA., TO BEAUFORT INLET,
   N. C. (SECTION EXTENDING FROM THE NORTH CAROLINA-VIRGINIA
   STATE LINE TO BEAUFORT INLET, N. C.)

   For report on this improvement, see page 388.
                           2. MEHERRIN RIVER, N. C.

  Location.-Rises in Lunenberg County, Va., flows in a southeast-
erly direction a distance of about 126 miles, and empties into the
Chowan River, N. C., at a point about 39 miles above Albemarle
Sound, N. C. (See U. S. Geological Survey, Winton quadrangle,
N. C.)
  Previous projects.-Adopted by River and Harbor Act of August
2, 1882. For further details, see page 1802 of Annual Report for
1915, and page 483 of Annual Report for 1938.
   Existing project.-This provides for a channel 10 feet deep from
the mouth to the State highway bridge at Murfreesboro, a distance
of about 10.5 miles, with a cut-off channel through Devils Elbow,
4 miles above the mouth, 80 feet wide through the cut-off, and 100
              RIVERS AND HARBORS-WILMIINGTON,                                 N.        C., DISTRICT          401
feet wide elsewhere; and a turning basin of the same depth, 300
feet wide and 500 feet long at Murfreesboro. The entire stream is
nontidal and, except during freshets, its water surface rises and
falls as the winds raise or lower the water level of Albemarle Sound.
Freshets cause variations of water level of from 3 to 4 feet in the
navigable portion of the river.
  The estimate of cost for new work, revised in 1935, exclusive of
amount expended on previous projects, was $46,000. The latest
(1935) approved estimate of cost for annual maintenance is $3,500.
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                         Documents


Mar.     2,1907   Removal of shoals and obstructions to make river        H. Doc. No. 137, 59th Cong., 1st sess.
                   safely navigable for vessels of less than 7-foot
                   draft.
Aug. 30, 1935     Present project dimensions      __            ..        Rivers and Harbors Committee Doe.
                                                                            No. 43, 74th Cong., 1st sess. (Con-
                                                                           tains latest published maps.)



  Local cooperation.-Fullycomplied with.
  Terminal facilities.-There are seven private wharves on Meherrin
River, four of which are located at Murfreesboro. All are of timber
construction with pile foundation and plank decking. The total
berthing space at Murfreesboro is approximately 130 feet. Smith-
Douglas Co., fertilizer manufacturers, operate two of the wharves,
with large mixing plant, warehouse, office, and storage facilities. The
Standard Oil Co. has a wharf about 200 yards downstreaih from the
Smith-Douglas terminal. Storage tanks, with total capacity of 48,000
gallons, are supplied by pipe lines running from the wharf. The
wharfage facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1938. The controlling depth at the end of the fiscal year was 9 feet.
The total costs and expenditures under the existing project to June 30,
1944, were $43,149.81 for new work and $49,195.55 for maintenance, a
total of $92,345.36.
  Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
  The sum of $10,000 can be profitably expended during the fiscal year
1946 for maintenance dredging, under contract, between the mouth
and Murfreesboro, during March 1946. There has been no mainte-
nance dredging on this project since December 1938.
                                      Cost and financial summary
Cost of new work to June 30, 1944   -                      -          -        -          -     -$47,       734. 34
Cost of maintenance to June 30, 1944_                          ---------------                          49, 195. 55

      Total cost of permanent work to June 30, 1944                                -_                   96, 929. 89
Net total expenditures  -_ -_ _                                                                         96, 929. 89
Total amount appropriated to June 30, 1944-                                                             96, 929. 89
          616634-45-pt. 1, vol. 1-           26
402               REPORT OF CHIEF OF ENGINEERS, U.                                                 S. ARMY,                      1944


    Fiscal year ending June 30                  1940              1941                       1942                        1943                1944

Cost of new work....... ..............--               -.        -...............................................
Cost of maintenance-------------.............    $958. 46           $532. 54                     $90.87 ......                   ..    ...       .
Total expended....------------------              958.46              532.54                       90.87            ..    ....
                                                                                                                            ..        ...    .       ...
Allotted.........................               3, 500. 00   -10, 000. 00                 -6, 909.13 .......................

Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance ---------------------------------                                                                        $10, 000. 00

                                            3. CASHIE RIVER, N. C.

   Location.-This river, a nontidal stream, rises in Bertie County,
near Kelford, N. C., flows in a general southeasterly direction for
about 57 miles to a point where it intersects the thoroughfare (con-
necting Cashie and Roanoke Rivers), thence in a northeasterly direc-
tion for approximately 7 miles, and empties into the extreme westerly
end of Albemarle Sound.
   Existing project.-This provides for the removal of logs, snags,
and other obstructions between the mouth of the thoroughfare in
Roanoke River and Windsor, a distance of 20.5 miles; the construc-
tion of three cut-off channels 80 feet wide through sharp bends at
points 1, 4, and 5 miles below Windsor, and a turning basin about
1.1 acres in area at Windsor, all to a depth of 10 feet. The river is
not subject to floods or freshets, but its water surface rises and falls
as the winds raise or lower the water level in Albemarle Sound. The
maximum fluctuation of the water surface is about 4 or 5 feet.
   The estimate of cost for new work, revised in 1937, was $32,000.
The latest (1937) approved estimate for annual cost of maintenance
is $1,200.
   The existing project was authorized by the following river and
harbor acts:

       Acts                            Work authorized                                                              Documents


July     3,1930    Removal      of obstructions        between     mouth           of      H. Doc. No. 779, 69th Cong., 2d sess.
                    thoroughfare in Roanoke River and Windsor.
Aug. 26, 1937      Construction of 3 cut-off channels and a turning                        Rivers and Harbors Committee Doe.
                    basin at Windsor.                                                        No. 31, 75th Cong., 1st sess. (Con-
                                                                                             tains latest published maps.)



  Local cooperation.-Fully complied with.
  Terminal facilities.-There are 1 public wharf and 4 privately
owned wharves at Windsor, N. C., and 12 between this point and the
thoroughfare. The facilities are considered adequate for existing
commerce.
  Operations and results during fiscal year.-The work consisted of
maintenance dredging by contract and making miscellaneous surveys.
The contract dredge Northwood, between January 23 and 27, 1944,
removed 16,667 cubic yards of material from a shoal area near the
junction of the river with the thoroughfare to Roaneke River, re-
storing project dimensions. The total costs and expenditures for the
year were $7,990.22, all for maintenance.
             RIVERS AND               HARBORS-WILMINGTON,                                 N.      C., DISTRICT            403

  Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depth at the end of the fiscal year was 10
feet. The total costs and expenditures under the existing project to
June 30, 1944, were $40,402.73 for new work and $15,394.93 for mainte-
nance, a total of $55,797.66.
  Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
  The sum of $2,000 can be profitably expended during the fiscal year
1946 for maintenance snagging between the mouth and Windsor with
U. S. derrickboat Northeast, during February 1946.
                                          Cost and financial summary
Cost of new work to June 30, 1944_
                                 --------------------------                                                     $40, 402. 73
Cost of maintenance to June 30, 1944_  -------------------------                                                 15, 394. 93
      Total cost of permanent work to June 30, 1944--------- ---                                                    55, 797. 66
Net total expenditures -------------------------------------                                                        55, 797.66
Total amount appropriated to June 30, 1944--- -----------------                                                     55, 797. 66

    Fiscal year ending June 30                 1940           1941                   1942               1943            1944

Cost of new work -------.          -----..                   --.....       ----. -.     ---. .....                      ....
                  ........- -----------.-
Cost of maintenance--                                           $209.78 ---------------------------                    $7.990.22
Total expended...........------------------   ------------          209. 78 -------------------------                   7.990. 22
Allotted-------------------------               $1,200   .    ...                --------------
                                                                        ..--------------                 $7,000-.



Balance unexpended July 1, 1943-----------------------------                                                        $7, 990. 22
Gross amount expended --------------------------      $8, 787. 63
Less reimbursements collected------------------ -----     797. 41
                                                                                                                     7, 990. 22
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance ----------------------------------                                                         2, 000.00

                                         4. ROANOKE RIVER, N. C.

   Location.-This stream rises in the Blue Ridge Mountains, west of
Roanoke, Va., and flows southeasterly for about 200 miles to Clarks-
ville, Va., where it is joined by Dan River, its principal tributary; and
thence in the same general direction for about 198 miles and empties
into the westerly end of Albemarle Sound N. C. (See U. S. Coast
and Geodetic Survey Chart No. 1228 and Post Route Map of North
Carolina.)
   Existing project.-This provides for dredging a channel 12 feet
deep and 150 feet wide from the 12-foot contour in Albemarle Sound
into Roanoke River and thence upstream to a point about 1 mile above
the town of Plymouth, N. C., a distance of 10 miles; thence a channel
10 feet deep and 100 feet wide to Hamilton, a distance of 53 miles;
thence a channel 8 feet deep and 80 feet wide to Palmyra Landing, a
distance of 18 miles, with a cut-off channel of like dimensions about 2
miles above Hamilton; and thence a channel 5 feet deep and 50 feet
wide to Weldon, N. C., a distance of 50 miles, by dredging, snagging,
and regulation.. Depths of channels are referred to mean low water.
The rise and fall of the river, resulting from freshets, is from 18 to 33
feet for about 70 miles below Weldon, but this fluctuation diminishes
toward the mouth, the variations in water levels being from 1 to 2
404          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                  1944

feet in the lower 15 or 20 miles. The total length of channels in-
cluded in the project is 131 miles.
   The estimate of cost for new work, revised in 1938, is $638,500. The
latest (1938) approved estimate for annual cost of maintenance is
$6,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                                   Documents


Mar. 3, 1871    Improvement of the river between the mouth          S. Doc. No. 23, 42d Cong., 2d sess., and
                  and Weldon.                                         Annual Report, 1872, p. 726.
July 3, 1930    Entrance channel 10 feet deep and 150 feet wide-_   H. Doc. No. 211, 70th Cong., 1st sess.t
June 20, 1938   Present project dimensions__       ..--------
                                                   .--              H. Doc. No. 694, 75th Cong., 3d sess.L


  1 Contains latest published maps.

   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are 8 wharves at Plymouth. One mile
farther upstream there is a large wharf and bulkhead, a transit shed,
and crane runway for handling wood pulp and pulp materials. Be-
tween this point and Hamilton there are 10 wharves. Between Hamil-
ton and Halifax there are 13 log landings. These facilities appear to
be adequate for existing commerce.
   Operations and results during fiscal year.-The work consisted of
snagging with Government plant and hired labor. The U. S. der-
rick boat Northeast, supplemented by one tractor, commenced snag-
ging between the 78 and 102 mileboards on December 23, 1943,
and continued to February 15, 1944. There were removed from the
channel 241 snags, 83 stumps, 60 logs, and 133 trees, and from the
banks 30 trees, at a cost of $5,000. The total costs and expenditures,
were $5,000, all for maintenance.
   Conditionat end of fiscal year.-The existing project has been com-
pleted to the practicable limit. As it is impracticable to obtain and
maintain the project above Palmyra by dredging, snagging, and regu-
lation, the percentage of completion is uncertain. At the close of
the fiscal year the hlimiting depths at local mean low water were as
follows: Between Albemarle Sound and 1 mile above Plymouth, 11
feet; thence to Hamilton, 8 feet; thence to Palmyra, 4 feet; and
thence to Weldon, 1 foot. The work remaining to be done consists
of completing by dredging, snagging, and regulation, a channel be-
tween Palmyra and Weldon to a depth of 5 feet and a minimum
bottom width of 50 feet. The total costs and expenditures under the
existing project to June 30, 1944, were $40",584.34 for new work and-
$186,205.04 for maintenance, a total of $590,789.38.
   Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
   The sum of $40,000 can be profitably expended during the fiscal
year 1946, for maintenance as follows:
Dredging channel between mouth and Palmyra Landing, under contract,
  January and February 1946_ --------------                         $38, 000
Snagging between Williamston and Palmyra Landing with U. S. derrick
  boat Northeast, March 1946___-_-____-_-__--__-_--__-_-____ _-       2,000
           Total for all work___            ______-- ______-         -_____        -_      --
                                                                                          ___     40, 000
             RIVERS AND HARBORS                                       WILMINGTON,                            N.    C., DISTRICT               405

   There has been no maintenance dredging on this project since 1941.
Considerable shoaling has taken place and navigation is experiencing
difficulty throughout the improved portion of the river.
                          Cost and financial summary
Cost of new work to June 30, 1944_-------------_                                                                                      $404, 584. 34
Cost of maintenance to June 30, 1944_-------                                                                       __                  186, 205. 04
           Total cost of permanent work to June 30, 1944                                                                               590, 789. 38
Net total expenditures_                        ______                 --                     --                     __                 590, 789. 38
Total amount appropriated to June 30, 1944_                                             ----------------                               590, 789. 38

   Fiscal year ending June 30                          1940                      1941                  1942                  1943          1944


Cost of new work___                                  $4, 279. 04           $107,175. 81             $25, 765.46
Cost of maintenance -------------                     2, 577. 33             16, 103. 74              1,054. 36 -       --                    $5, 000
      Total cost -----------------                    6, 856. 37            123, 279. 55             26, 819. 82                                  5,000
Total
Alo  expended
           -5, ....              ...------------------...6, 847. 62         105, 479. 86             44, 628. 26                                    000
Allotted   .....--------------------------------                            156,000. 00                             -$19, 391. 50            -1,000


Balance unexpended July 1, 1943_                                             -          --                                              $6, 000. 00
Amount allotted from War Department Civil Appropriation Act
   approved June 2, 1943                     -------                                                                           _-3,        000. 00

           Amount to be accounted for                                                             --------                               9000.
                                                                                                                                         9,         00
Deductions on account of revocation of allotment-----------                                                                              4, 000. 00
      Net amount to be accounted for__                                                                                                   5, 000. 00
Gross amount expended____   ____--------                                                          -------                                5, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_-----------------------------    ___                                                                         40, 000. 00
                                5. MANTEO (SHALLOWBAG) BAY, N. C.
   Location.-Manteo Bay or Shallowbag Bay, formed by a natural
indentation of the shore line, is situated on the northeastern side of
Roianoke Island, N. C. (See U. S. Coast and Geodetic Survey Chart
No. 1229.)
   Existing project.-This provides for a channel 100 feet wide and
6 feet deep at mean low water from that depth in Roanoke Sound
to the town of Manteo, a distance of about 22/3 miles, and for a con-
necting channel of the same dimensions extending south through
Roanoke and Pamlico Sounds to Oregon Inlet, a distance of about
11 miles. The variations of the water surface are due to winds and
seldom exceed 2 feet above or below mean stage. The extreme range
of wind and tides, determined by 1 year's gage readings at Manteo,
is 5.1 feet. The estimate of cost for new work, revised in 1941, was
$55,503. The latest 1941 approved estimate of cost for annual main-
tenance is $5,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                                   Work authorized                                                              Documents


June 25,1910       Channel 6 feet deep and 100 feet wide from Roa-                                    T. Doc. No. 906, 60th Cong., 1st sess.
                    noke Sound to Manteo.
Oct. 17, 1940      Connecting channel of same dimensions to Ore-                                      H. Doc. No. 313, 76th Cong., 1st sess.1
                    gon Inlet.

I Contains latest pablished maps.
406            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

   Terminal facilities.-There are 17 wharves on the portion of this
harbor under improvement. They have a total frontage of 1,060 feet.
The existing facilities are considered adequate for present commerce.
   Operations and results during fiscal year.-None.
   Conditionat end of fiscal year.-The existing project was completed
in 1941. The controlling mean-low-water depth in channel to Manteo
was 5.5 feet and 3.3 feet in channel to Oregon Inlet. The total costs
and expenditures under the existing project to June 30, 1944, were
$63,383.84 for new work and $46,182.03 for maintenance, a total of
$109,565.87.
  Proposed operat ions.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
   The sum of $20,000 can be profitably expended during the fiscal year
1946 for maintenance dredging, under contract, during May 1946.
There has been no maintenance dredging in the channel leading to
Oregon Inlet since its completion in November 1941. Shoaling is
rapidly taking place and restoration of project dimensions will be
necessary to accommodate Coast Guard and commercial boats.
                                           Cost and financial summary
Cost of new work to June 30, 1944_ _-----------                                                                      $63, 383. 84
Cost of maintenance to June 30, 1944------------------ -46,                                                               182. 03
      Total cost of permanent work to June 30, 1944-------                                                           109, 565. 87
Net total expenditures-___________-------------109,                                                                       565. 87
Total amount appropriated to June 30, 1944--------------------                                                       109, 565. 87

   Fiscal year ending June 30                1940              1941        1942                     1943                  1944

                                 ...--------------
Cost ofnew work......---------............   . ....--------------
                                                             $52,880.66                     .
Cost of maintenance           ........      $1, 003. 43        $246. 13      441.23                      $156. 77     -
      Total cost -----------------           1, 003. 43         246.13    53, 321.89                      156. 77-
Total expended ....------------------          896. 80          352.76    53, 321.89                      156.77_ .......
Allotted--        ..---              .--          _--_37, --    000. 00   17, 000. 00   -       -.-...                  -$9,   271.78


Balance unexpended July 1, 1943_ ___-_-_    _$9,
                                              --------                                                                    271.78
Deductions on account of revocation of allotment-----------------                                                      9, 271. 78
Amount that can be profitably expended in fiscal year ending June
   30, 1946 for maintenance                     ------------------------------------                                  20, 000. 00

                                            6. FAR CREEK, N. C.

  Location.-FarCreek is located in Hyde County, N. C., and flows
inan easterly direction into Pamlico Sound at a point about 95 miles
south of Norfolk, Va. (See U. S. Coast and Geodetic Survey Chart
No. 1232.)
  Existing project.-This provides for a channel 7 feet deep at mean
low water and 60 feet wide from Pamlico sound to a point about 200
feet below the highway bridge at Englehard, with a turning basin at
the head. The total length of channels included in the project is above
2 miles. There is some lunar tide in Pamlico Sound, but the principal
variations in the level of the water surface are due to winds. Ordinary
winds cause a variation of about 1 foot, while severe storms will double
or triple this variation.
                 RIVERS AND HARBORS-WILMINGTON,                                                  N.         C., DISTRICT               407
   The estimate of cost for new work, made in 1929, was $30,000. The
latest (1929) approved estimate for annual cost of maintenance is
$2 000.
   The project was authorized by the River and Harbor Act, approved
July 3, 1930 (H. Doc. No. 112, 71st Cong., 1st sess.). The latest pub-
lished map is contained in this document.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are five wharves at Engelhard with a
total frontage of about 510 feet, all privately owned. The existing
facilities are considered adequate for present commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1931. At the close of the fiscal year the controlling depth to Engel-
hard was 5.4 feet. The total costs and expenditures under the existing
project to June 30, 1944, were $34,500 for new work and $41,633.93 for
maintenance, a total of $76,133.93.
   Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
   The sum of $16,000 can be profitably expended during the fiscal year
1946 for maintenance dredging, under contract, during April 1946.
There has been no maintenance dredging on this project since Feb-
ruary 1940. Shoaling in this channel is increasing and will have to be
removed in order to assure continuous movement of supplies to the
Coast Guard installations and civilian population at Hatteras.
                                                Cost and financial summary
Cost of new work to June 30, 1944_                                                                            _-----------     $34, 500. 00
Cost of maintenance to June 30, 1944_------                                                             --        _             41, 633. 93
         STotal cost of permanent work to June 30, 1944-                                                                 -      76, 133. 93

Net total expenditures----------_                                                                               _____           76, 133.93
Total amount appropriated to June 30, 1944---------------                                                                       76, 133. 93

     Fiscal year ending June 30                   1940                  1941              1942                     1943             1944

Cost of new work -----. -..                      -. -. --.          ------.           -------.                ------........
Cost of maintenance -------------..                    $9, 300   -.............
Total expended .....------------------                  9,300-
Allotted.-------------------................-   ----      700           -$2, 000   ......................


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance -------------------------------        $16, 000.00.00

                                         7. PAMLICO AND TAR RIVERS, N. C.

  Location.-The two names are applied to the same river, it being
known as the Pamlico below Washington, N. C., and as the Tar above
that point. This stream rises in Person County, flows in a general
southeasterly direction for 217 miles, and empties into Pamlico Sound.
The Pamlico River is 38 miles long. (See U. S. Coast and Geodetic
Survey Chart No. 537.)
  Previous projects.--Adopted lby River and Harbor Acts of July 4,
1836, and August 30, 1852. For further details see page 502 of Annual
Report for 1938.
408            REPORT OF CHIEF OF ENGINEERS, U.                            S. ARMY,        1944

  Existing project.-This provides for a channel 12 feet deep at mean
low water and 200 feet wide from the 12-foot contour in the river below
Washington to the Atlantic Coast Line Railroad bridge at Washing-
ton; 12 feet deep and 100 feet wide from Washington to a turning basin
of the same depth, 200 feet wide, and 300 feet long, in Hardee Creek,
1,500 feet above its mouth; 6 feet deep and 75 feet wide to Greenville;
20 inches deep and 60 feet wide to Tarboro; thence to clear the natural
channel above Tarboro to Little Falls. The length of section under
improvement is 97 miles, extending from a point 14 miles below Wash-
ington to Little Falls. The stream is nontidal; variations in the water
surface at Washington, due to prevailing winds, seldom exceed 2 feet.
The extreme range of the flood or freshet stage for the upper section is
34 feet at Tarboro. For the lower section, the extreme range due to
winds is 8.3 feet.
   The estimate of cost for new work, revised in 1937, was $754,000,
exclusive of amount expended on previous project. The latest (1937)
approved estimate for annual cost of maintenance is $66,000:
   The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                   Documents


Aug. 14, 1876      Channel 9 feet deep and 100 feet wide from the
                     mouth to Washington.
Mar. 3, 1879       Clearing the channel to Tarboro_-------__            H. Doc. No. 68, 45th Cong., 3d sess.,
                                                                         and Annual Report, 1879, p. 700.
Aug. 11, 1888      Clearing the channel between Tarboro and Little      Annual Report, 1889, p. 1130.
                     Falls (Rocky Mount).
Mar. 2, 1907       Channel 4 feet deep and 60 feet wide between         H. Doc. No. 342, 59th Cong., 2d sess.
                    Washington and Greenville.
                                                                                                               1
July 25, 1912      A 10-foot depth and 200-foot width from the mouth    H. Doc. No. 270, 62d Cong., 2d sess.
                     to Washington, thence 6-foot depth and 75-foot
                     width to Greenville.
July     3, 1930   Present 12-foot project to the Atlantic Coast Line   Rivers and Harbors Committee Doc.
                     R. R. bridge at Washington.                          No. 11, 71st Cong., 1st sess)
Aug. 26, 1937      Present 12-foot project from Washington to a turn-   Rivers and Harbors Committee Doc.
                    ing basin in Hardee Creek.                           No. 22, 75th Cong., 1st sess.l


  ' Contains latest published maps.

   Recommended modifcations of project.-The abandonment of this
improvement above Tarboro, N. C., is recommended in House Docu-
ment No. 467, Sixty-ninth Congress, first session.
   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 54 wharves on the portion of this
river under improvement, of.which 34 are along the water front at
Washington, 19 between Washington and the mouth, and only 1 in
usable condition above Washington. They have a total frontage of
3,570 feet. The existing facilities are considered adequate for exist-
ing commerce.
   Operationsand results duringfiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling mean low water depth at the close of the
fiscal year was 11 feet to Washington, 6 feet to and including the
turining basin in Hardee Creek, 3.5 feet to Greenville, and 1 foot to
            RIVERS AND HARBORS-WILMINGTON,                                           N.     C., DISTRICT                409

the mouth of Fishing Creek. The total costs and expenditures under
the existing project to June 30, 1944, were $674,651.38 for new work
and $429,943.43 for maintenance, a total of $1,104,594.81.
  Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
  The sum of $66,000 can be profitably expended during the fiscal
year 1946, for maintena as follows:
Dredging channel at and below Washington, under contract, June 1946_ $20, 000
Dredging channel between Washington and Hardee Creek, under con-
  tract, April and May 1946_-----------                   ----        41, 000
Snagging between Washington and Hardee Creek with U. S. derrickboat
  Northeast and/or tractors between Feb. 1 and Apr. 30, 1946           5, 000                    --------
          Total for all work                  --------------------------------------66, 000
                                       Cost and financial summary
Cost of new work to June 30, 1944__       .                            ..                  ._      .$689,     651.38
-Cost of maintenance to June 30, 1944 _-._.                                           _;_          --_    429, 943. 43
       Total cost of permanent work to June 30, 1944         1, 119, 594. 81    ----------
Net total expenditures ----------------------------------- 1, 119, 594. 81
Total amount appropriated to June 30, 1944 ----------------- 1, 119, 594. 81

   Fiscal year ending June 30                 1940         1941               1942                1943               1944

Cost ofnew work .. .......--------------.$241,401.08--........
                                                        -   -           ........ 7               . ... ..................--
Cost of maintenance.............            3, 372. 89    48,077. 66       62, 131.76             9,820.81.  ........

      Total cost.................           244, 773.97   48, 077.66         62, 131.76           9, 820. 81
Total expended .....----------------    244, 973. 02      48, 077. 66        43, 156.19          28, 866.38     ...........

Allotted----------------------
       ........................         -    19, 000.00   53,000.00          18,100.00    -----------          ---   $9, 610.12


Balance unexpended July 1, 1943_ .-      ____----------.----$9,                                                    610. 12
Deductions on account of revocation of allotment ---------------                                                9, 610. 12
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance ---------------------------------                                                   66, 000. 00

           S8.                         ROLLINSON CHANNEL, N. C.

   Location.-This channel extends from deep water in Pamlico Sound
to a natural inner basin lying north of the village of Hatteras, near
Hatteras Inlet, N. C. (See U. S. Coast and Geodetic Survey Chart
No. 1232.)
   Existing project.-This provides for dredging a channel about 4,300
feet long, 100 feet wide at the bottom, and 6 feet deep at mean low
water. Variation in the water surface due to winds seldom exceeds 1
or 2 feet above or below mean stage. Severe windstorms will double
or triple this variation. The estimate of cost for new work, made in
1932, is $27,000. The latest (1936) approved estimate for annual cost
of maintenance is $4,270.
   The existing project was adopted by the River and Harbor Act of
August 30, 1935 (H. Doc. No. 218, 72d Cong., 1st sess.) The latest
published map is contained in this document.
   Recommended modifications of project.--Under date of March 15,
1939, the Chief of Engineers recommended that the project be modi-
fied to provide for a channel 100 feet wide and 6 feet deep, extending
410         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                    1944

from that depth in Pamlico Sound to and including a basin of the same
depth in front of the wharves at Hatteras, at an estimated first cost
of $27,000, with no increase in annual maintenance, subject to certain
conditions of local cooperation (H. Doc. No. 236, 76th Cong., 1st sess.).
   Terminal facilities.-None required.
   Operations and results during fiscal year.-The work consisted of
maintenance dredging by contract and makig miscellaneous surveys.
The contract dredge Northwood, between November 27 and Decem-
ber 10, 1943, removed 48,511 cubic yards of material from the channel,
restoring project dimensions. The total costs and expenditures were
$22,500, all for maintenance.
   Condition at end of fiscal year.--The existing project was completed
in 1936. The controlling mean-low-water depth at the end of the
fiscal year was 6 feet. The total costs and expenditures under the
existing project to June 30, 1944, were $20,125.43 for new work and
$37,600 for maintenance, a total of $57,725.43.
   Proposed operations.-No funds are on hand and no work is
proposed during the fiscal year 1945.
   The sum of $20,000 can be profitably expended during the fiscal
year 1946 for maintenance dredging, under contract, during June
1946. The last work was done in 1943. Shoaling takes place rapidly
and will have to be removed to provide sufficient depth for Coast
Guard and commercial supply boats serving Hatteras.
                                   Cost and financial summary
Cost of new work to June 30, 1944__ ____----------                                            $20, 125. 43
Cost of maintenance to June 30, 1944_--------                                   ---            37, 600. 00
       Total cost of permanent work to June 30, 1944               -------------                57, 725. 43
Net total expenditures_ --------------------------------------                                  57, 725. 43-
Total amount appropriated to June 30, 1944_--------------------                                 57, 725. 43


   Fiscal year ending June 30        1940         1941           1942             1943                 1944

Cost of new work---------........---      ---------------------------------------------------
Cost.of maintenance........------------$14,400.10      $699.90 -----------------------      $                 500
Total expended....-----------------14, 400.10       699.90   ----------------------------                  22, 500
Allotted.-----------------------     6,900.00   -4,000.00    ----------------    ------------...........   22, 500


Amount allotted from War Department Civil Appropriation Act
                                _
  approved June 2,1943____------------.      •-                      $22, 500. 00
Gross amount expended ________------------------------- $22, 517. 07
Less reimbursements collected----------_-------_------_       17. 07
                                                                                                22, 500. 00
Amount that can be profitably expended in fiscal year ending June 30,
1946, for maintenance___------------------------------------                                   20, 000. 00
                            9. SILVER LAKE HARBOR, N. C.

  Location.-Silver Lake Harbor is located at the westerly end of
Ocracoke Island, which is a portion of the barrier separating Pamlico
Sound from the Atlantic Ocean. Beaufort Harbor lies about 50 miles
southwest; Belhaven is about 60 miles northwest. (See U. S. Coast
and Geodetic Survey Chart No. 1232.)
              RIVERS     AND HARBORS-WILMINGTON,                         N.   C., DISTRICT            411

   Eaistingproject.-This provides for a channel 10 feet deep from that
depth in Pamlico Sound to and including an anchorage basin of the
same depth in Silver Lake Harbor, with widths of 100 feet across Big
Foot Slough bar, and 60 feet in the entrance channel, together with a
training wall 300 feet long to protect the outer end of the entrance
channel from northeast storms. The ordinary range of tide is about 1
foot within the lake and about 21/2 feet at the outer end of the connect-
ing channel. Severe storm tides have been known to raise the water
surface of the lake as much as 5 feet.
   The estimate of cost for new work, revised in 1941, is $71,000. The
latest (1911) approved estimate for annual cost of maintenance is
$4,900.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                  Documents


July     3,1930   Entrance channel 5 feet deep and 50 feet wide      Rivers and Harbors Committee Doc.
                   from Pamlico Sound to the 3-foot contour in the     No. 3, 70th Cong., 1st sess.
                   lake and training wall at entrance.
                                                                                                              1
Oct. 17,1940      Channel 10 feet deep and anchorage basin of same   H. Doc. No. 325, 76th Cong., 1st sess.
                   depth, 100 feet wide across Big Foot Slough and           N
                   60 feet wide in entrance.


  I Contains latest published map.

  Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are 12 small wharves extending from
the shore to the deeper waters in the lake, and 1 at the outer entrance
of the channel. These facilities are considered adequate for the pres-
ent commerce..
   Operations and results during fiscal year.-The work consisted of
maintenance dredging by contract and making miscellaneous surveys.
The contract dredge Northwood, between October 23 and November 3,
1943, removed 36,764 cubic yards of material from Big Foot Slough
bar channel, restoring project dimensions in that channel. The cost
was $16,767.44.
   Between August 13 and 31, 1943, 350 linear yards of open drainage
ditch were constructed, 1,700 linear yards of open ditch were cleared
out, and 200 linear yards of wooden culvert were installed by Govern-
ment plant and hired labor, restoring to usefulness the drainage system
damaged by dredging operations. The cost was $3,574.55. Miscel-
laneous surveys were made at a cost of $744.45.
  The total costs and expenditures were $21,086.44, all for mainte-
nance.
   Conditionat end of fiscal year.-The existing project was completed
in 1942. At the end of the fiscal year the controlling mean-low-water
depth in the entrance channel and basin was 10 feet, and 5 feet in
Big Foot Slough bar channel. The total costs and expenditures under
existing project to June 30, 1944, were $67,241.30 for new work and
$24,560.01 for maintenance, a total of $91,801.31.
  Proposed operations.-An allotment of $20,000 made during July
1944 will be applied to maintenance dredging, under contract, in Big
412            REPORT OF CHIEF OF ENGINEERS, U.                                               S. ARMY,           1944

Foot Slough bar channel and entrance channel to Silver Lake, during
November 1944.
  As the channels forming a part of this project are subject to rapid
shoaling and their maintenance is necessary to assure uninterrupted
movement of vessels attached to the armed services stationed in this
vicinity, the additional sum of $20,000 can be profitably expended dur-
ing the fiscal year 1946 for maintenance dredging, under contract,
during May 1946.
                                                       Cost and financial summary
                                 ---------------------------
Cost of new work to June 30, 1944_                            $67, 241. 30
Cost of maintenance to June 30, 1944_--        - --      ____  24, 560. 01
       Total cost of permanent work to June 30, 1944-------                                                            91, 801. 31
Net total expenditures                                                                                                 91, 801. 31
Total amount appropriated to June 30, 1944                                         --------------------                91, 801. 31


      Fiscal year ending June 30                             1940           1941           1942           1943              1944

                       -----
Cost of new work-.....--------                                                           $13, 956.64    $42, 284.66    ........
Cost of maintenance_ ________--.--.---------$449. 72                                          239. 61        257. 35          $21,086.44

        Total cost---                        _ _ .....-...
                                         ----.......-.            __449.           72     14,196.25      42,542. 01         21,086. 44
Total expended.........                    -     ---------------              449. 72     14,196. 25     42, 542.01         21, 086.44
Allotted      --.......................-....                 ..   ....     57, 000. 00    17, 504. 27   -20, 229. 85        20,000.00



Balance unexpended July 1, 1943 ------------------------------                                                         $1,086.44
Amount allotted from War Department Civil Appro-
priation Act approved June 11, 1938--------------- $1, 500. 00
Amount allotted from War Department Civil Appropri-
ation Act approved June 2, 1943------------           18, 500. 00
                                                                                                                       20, 000. 00
       Amount to be accounted for ----------------------------                                                         21, 086.44
Gross amount expended -------------------------- $21, 764. 86
Less reimbursements collected___---------               678. 42
                                                                                                                       21, 086. 44

Amount allotted in July 1944--_       ------            -____                                                           20, 000. 00
Amount available during fiscal year 1945 -----------------                                                              20, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1 _ -   - - - - - - -         -
                                                           ____                                                         20, 000. 00
  i   Exclusive of available funds.

10. CHANNEL CONNECTING THOROUGHFARE                                                          BAY WITH CEDAR BAY,
                           N. C.

   Location.-Thoroughfare Bay is on the north side of Core Sound,
about 6 miles west of the end of the peninsula at the junctionl of Core
and Pamlico Sounds. It lies about 30 miles by the boat route through
Core Sound easterly from Beaufort, N. C. (See U. S. Coast and
Geodetic Survey Chart No. 1233.)
   Existing project.-This provides for a channel 5 feet deep and 50
feet wide on bottom to connect Thoroughfare Bay and Cedar Bay.
The length of this channel is about 1/ miles. There is no lunar tide
in the channel or waterway, variations in the level of the water sur-
face being due entirely to the action of the wind. Ordinary storms
will cause a variation of 1 foot above or below mean stage, while
severe storms may cause a variation of as much as 3 feet.
                RIVERS AND HARBORS-WILM9INGTON,                               N.      C., DISTRICT                      413
    The estimate of cost for new work, revised in 1919, was $9,000.
The latest (1928) approved estimate for annual cost of maintenance
is $1,000.
    The existing project was adopted by the River and Harbor Act
of March 2, 1919 (H. Doc. No. 1125, 63d Cong., 2d sess.). The latest
published map is in the project document.
    Recommended modifications of project.-Under date of June 14,
1939, the Chief of Engineers recommended that the project be modi-
fied to provide a depth of 7 feet and for increasing the width at the
bends, at an estimated first cost of $20,000, with no increase in
annual maintenance over that now required, subject to certain condi-
tions of local cooperation (S. Doc. No. 87, 76th Cong., 1st sess.).
    Terminal facilities.-None. Not required.
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was com-
pleted in 1921. At the close of the fiscal year the controlling mean-
low-water depth was 4.5 feet. The total costs and expenditures under
the existing project to June 30, 1944, were $9,000 for new work and
$15,549.01 for maintenance, a total of $24,549.01.
    Proposed operations.-No funds are on hand and no work is pro-
posed during the fiscal year 1945.
    The additional sum of $5,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging, under contract, during
March 1946. No work has been done since 1937. This project is the
connecting link for small boats between Core Sound and Neuse River
and the gradually increasing shoaling will require removing in order
to assure continuous passage.
                                      Cost and financial summary
Cost of new work to June 30, 1944 -_-                                -           -              -          -$9,       000. 00
Cost of maintenance to June 30, 1944---                      ---------                                            15, 549. 01
       Total cost of permanent work to June 30, 1944
Net total expenditures_-------------------------------
                                                                              ---               - -24,                549. 01
                                                                                                                  24, 549.01
Total amount appropriated to June 30, 1944                                                 --                     24, 549. 01

     Fiscal year ending June 30          1940         1941               1942                       1943             1944

C ost of new work.... . . . . . . . . . . . . .--. . . . . .       . . . . . . . . . . . .                 . . .. . . . . .
Cost of maintenance.......
Total expended.......------------   ---------         ------------------------------------
Allotted..---------------                -$6,   000   -$1,   000    ..-----------------------         I

Amount that can be profitably expended in fiscal year
                                                       ending June 30,
1946, for maintenance_ -------       --    -    ---------             $5, 000. 00

                                       11. DRUM INLET, N. C.

   Location.-Drum Inlet is an opening through the barrier beach
which separates Core Sound from the Atlantic Ocean. It is about
1,100 feet wide and is situated about 35 miles northeast of Beaufort
and opposite the village of Atlantic.
   Existing project.-This provides for a channel 12 feet deep at mean
low water and 200 feet wide from the gorge in the inlet to the federally
improved channel in Core Sound, a distance of about 1 mile. The mean
    414                 REPORT OF CHIEF OF E1tGINEERS, U. S. ARMY,                                                                      1944

    range of tide is 3.8 feet in the ocean and 0.3 foot in Core Sound at
    Atlantic.
       The estimate of cost for new work, made in 1937, was $507000. The
    latest (1937) approved estimate for annual cost of maintenance is
    $4,500.
       The existing project was adopted by the River and Harbor Act of
    June 20, 1938 (H. Doc. No. 414, 75th Cong., 2d sess.). The latest pub-
    lished map is contained in this document.
       Local cooperation.-Fullycomplied with.
       Terminal facilities.-None. Not required.
       Operationsand results during fiscal year.-None.
       Condition  at end of fiscal year.-The existing project was completed
    in 1940. At the close of the fiscal year the controlling mean low-water
    depth was 4.5 feet. The total costs and expenditures under the existing
    project to June 30, 1944, were $52,828.22 for new work and $23,851.82
    for maintenance, a total of $76,680.04.
       Proposed operations.-No funds are on hand and no work is pro-
    posed during the fiscal year 1945.
       The additional sum of $50,000 can be profitably expended during the
    fiscal year 1946 for maintenance dredging, under contract, during May
    and June 1946. There has been no maintenance dredging on this
    project since October 1941. Considerable shoaling has taken place,
    particularly at the inner end of the channel where the controlling
    depth limits the use of the improvement to the smaller type Coast
    Guard and commercial boats.
                                                              Cost and financial summary
    Cost of new work to June 30, 1944___---------------------------                                                                           $52, 828. 22
    Cost of maintenance to June 30, 1944 --------------------------                                                                            23, 851. 82

           Total cost of permanent work to June 30, 1944-------------                                                                           76, 680. 04
    Net total expenditures---- -     ----------------                                                                                           76, 680. 04
    Total amount appropriated to June 30, 1944_                                             --------------------                                76, 680. 04

         Fiscal year ending June 30                             1940                 1941             1942                      1943                   1944

    Cost of new work _.--------------                         $52,663.87 ........................                              ......     ...    ...       .....
    Cost of maintenance-------. _ _                             1,760.00         $4, 800.34         $17, 291.48      .......

              Total cost ----------------
                            ..                                 54, 423.87            4, 800. 34      17, 291.48      ..        ....       .

    Total expended .--..-...........                           54,423.87             4, 784.34       17, 307. 48.........                         ......
    Allotted ........................----------------------    11, 500.00           38, 000.00       10, 000. 00               -$24,    500       -$8,319.96


    Balance unexpended July 1, 1943 -----------------------------                                                                                8, 319. 96
    Deductions on account of revocation of allotment-----------------                                                                            8, 319. 96

    Amount that can be profitably expended in fiscal year ending June 30,
     1946, for maintenance---              ---____--- .*-------                                                                                 50, 000. 00

                                                         12. BEAUFORT HARBOR, N.O

       Location.-This harbor is located just inside Beaufort Inlet adja-
    cent to Morehead City Harbor. New Bern, N. C., the nearest city of
-   importance, is about 43 miles by inland waterway to the northwest.
     (See U. S. Coast and Geodetic Survey Chart No. 420.)
           - RIVERS AND               HARBORS-WILMINGTON,                                N.    C., DISTRICT           415
   Previous projects.-Adopted by River and Harbor Act of July 4,
1836. The total cost and expenditure was $5,000 for new work. For'
further details see page 1803 of Annual Report for 1915.
   Existing project.-This provides for the stopping of erosion at the
inlet by jetties and sand fences at Fort Macon and Shackelford Points
and other shore protection; for a channel 100 feet wide and 12 feet
deep at mean low water in Bulkhead Channel and Gallants Channel
and the same depth, with width varying from 200 to 400 feet, in front
of the town of Beaufort; and the construction of a stone bulkhead
extending from Town Marsh across Bird Shoal to the westerly end,
of Carrot Island. The distance from the inlet to the upper end of
Gallants Channel is about 5 miles. The average rise of tide is 21/,
feet at Beaufort and 31/2 feet at the inlet. The extreme range of tides
is 5 feet.
   The estimate of cost for new work, revised in 1930, exclusive of
amount expended on previous projects, was $262,800. The latest
 (1930) approved estimate for annual cost of maintenance is $17,500.
   The existing project was authorized by the following river and
harbor acts:

       Acts                            Work authorized                                             Documents


Mar. 3,1881        9-foot channel 200 feet wide through Bulkhead                     Annual Report, 1881, p. 1013.
                     Channel to Beaufort; a 6-foot channel 100 feet
                     wide to North River and Core Sound; and the
                    construction of jetties on Shackleford Point.
                   Reduced channel 100 feet wide and 7 feet deep                     Annual Report, 1890, p. 1134.
                    through Bulkhead Channel to Beaufort.
Mar. 2,1907        Repairs to Fort Macon jetties and additional                      Specified in act.
                    jetties and shore protection.
June 25,1910       10-foot channel 60 feet wide from Beaulort through                H. Doc. No. 511, 61st Cong., 2d sess.
                    Gallants Channel to the inland waterway.
Mar. 2,1919        Turning and anchorage basin 10 feet deep in front                 H. Doc. No. 1108, 63d Cong., 2d sess.
                    of Beaufort.
Mar. 3,1925        Bulkhead across Bird Shoal------------------...................   Rivers and Harbors Committee Doe.
                                                                                                                 1
                                                                                       No. 8, 68th Cong., 2d sess.
                                                                                                                         1
July     3, 1930   Increase in depth to 12 feet in Bulkhead Channel,                 H. Doc. No. 776, 69th Cong., 2d sess.
                     Gallants Channel, and in front of Beaufort.


  SContains latest published maps.

    Recommended modifcations of project.-Under date of May 25,,
1939, the Chief of Engineers recommended that the project be modi-
fied to provide for extension of the existing basin eastward to the
-easterly side of Marsh Street, and for increase in width of the entire
basin to 600 feet, all to a depth of 12 feet, at an estimated first cost
of $54,000, with annual maintenance of $2,700 in addition to that now
required, subject to certain conditions of local cooperation. (H. Doc.
No. 334, 76th Cong., 1st sess.)
    Local cooperation.---Fullycomplied with.
    Terminal facilities.-There are 40 wharves contiguous to this har-
bor. They have a total frontage of about 1,400 feet. The existing
facilities are considered adequate for present commerce.
    Operations and results during fiscal year.-None.
416          REPORT OF CHIEF OF ENGINEERS,                               U.   S. ARMY,          1944

   Conditionat end of fiscal year.-The existing project was completed
in 1931. At the close of the fiscal year the controlling mean-low-
water depth was 10 feet in the Bulkhead and Gallants Channels, and
12 feet in the harbor in front of Beaufort. The stone jetties and
training walls were in fair condition. The total costs and expendi-
tures under the existing project to June 30, 1944, were $269,667.38 for
new work and $260,631.86 for maintenance, a total of $530,299.24.
   Proposed operations.-An allotment of $20,000 made during July
1944 will be applied to maintenance dredging, under contract, in
Bulkhead and Gallants Channels during November 1944.
   The additional sum of $17,500 can be profitably expended during the
fiscal year 1946 for maintenance dredging, under contract, during June
1946.
                                            Cost and financial summary
Cost of new work to June 30, 1944_ ___________------$274,                                                  667. 38
Cost of maintenance to June 30, 1944_-------------------
                                          _                                                           260, 631. 86

       Total cost of permanent work to June 30, 1944------------                                      535, 299. 24
Net total expenditures __------------------------                                                     535, 299.24
Total amount appropriated to June 30, 1944_                        -------------------                535, 299. 24

    Fiscal year ending June 30                1940          1941          1942           1943              1944

Cost of new work....
Cost of maintenance-........          -..    $7, 160.16   $25, 238. 20   $1, 429. 11   $13, 729. 67

Total expended_...-.....-..-...               7,160.16     23, 242. 89    3, 424. 42    13, 729. 67

Allotted ....----------------------          10, 000.00    21, 500.00    10, 000. 00 ---------------      $12, 092. 71


Balance unexpended July 1, 1943_-______----------$12,                                                      092. 71
Deductions on account of revocation of allotment----------------                                       12, 092. 71
Amount allotted in July 1944_ _________---------.20,                                                       000. 00
Amount allotted during fiscal year 1945 ------------------------                                       20, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1     __    -      -       - -____     -                                     17, 500. 00
I Exclusive of available funds.

    13. WATERWAY CONNECTING PAMLICO SOUND AND BEAUFORT
                        HARBOR, N. C.

   Location.-This waterway begins at the southeast corner of Pam-
lico Sound, passing southwesterly through Wainwright Slough, Core
Sound, The Straits, and Taylors Creek to Beaufort Harbor, a total
length of 36.5 miles. (See U. S. Coast and Geodetic Survey Chart
No. 1233.)
   Previous projects.-No previous project exists for this waterway
as a whole. The River and Harbor Act of March 4, 1913, authorized
a channel 23/4 miles long connecting Core Sound and Beaufort Har-
bor. For further details see page 520 of the Annual Report for 1938.
   Existing project.-This provides for a channel 7 feet deep at mean
low water, with bottom width of 75 feet, extending from Pamlico
Sound by way of Wainwright Channel and Core Sound to Beaufort
Harbor, a distance of 36.5 miles, and for a channel 7 feet deep and
75 feet wide from the main channel in Core Sound to the town of
Atlantic. There are no lunar tides in the northern portion of Core
            RIVERS AND HARBORS-WILMINGTON,                                 N.   C., DISTRICT            417
Sound. Ordinary storms cause a variation of 1 foot above or below
mean stages, increasing to as much as 3 feet during severe storms.
The mean tidal range at Beaufort is 21/2 feet, gradually diminishing
toward the upper end of Core Sound.
  The estimate of cost for new work, revised in 1937, was $84,400,
exclusive of amounts expended on previous projects. The latest
(1937) approved estimate for annual cost of maintenance is $11,750.
  The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                                    Documents   1

Sept. 22,1922   A 7-foot channel 75 feet wide from Core Sound to      H. Doc. No. 88, 67th Cong., 1st sess.
                 Beaufort Harbor.
Aug. 30, 1935 2 A 7-foot channel 75 feet wide from Pamlico Sound      HI. Doc. No. 485, 72d Cong., 2d sess.
                  to Beaufort Harbor via Wainwright Channel.
Aug. 26, 1937   A 7-foot side channel 75 feet wide to Atlantic-----   Rivers and Harbors Committee Doc.
                                                                       No. 92, 74th Cong., 2d sess.


SThese documents contain the latest published maps.
SIncluded in the Public Works Administration program Jan. 3, 1934.


    Recommended modifications of project.-Under date of November
7, 1940, the Chief of Engineers recommended that the project be modi-
fied to provide for channels 7 feet deep and 75 feet wide, located near
the east and west ends of Harkers Island, respectively, and for a side
channel 75 feet wide and 5 feet deep to and including a basin of the
same depth 150 feet long and 130 feet in mean width at Davis, at an
estimated first cost of $35,000, with $1,500.'annually for maintenance
in addition to the amounts now required, subject to certain conditions
of local cooperation (H. Doc. No. 99, 77th Cong., 1st sess.).
    Under date of May 20, 1942, the Chief of Engineers recommended
modification of the existing project so as to provide for the dredging
of a side channel 75 feet wide and 7 feet deep at imean low water, from
that depth in Core Sound to and including a turning basin of the same
depth, 200 feet wide and 500 feet long at Sealevel, at an estimated
total initial cost of $8,000 with annual maintenance of $500 in addi-
tion to that now required; subject to certain conditions of local coop-
eration (S. Doc. No. 247, 77th Cong., 2d sess.).
    Local cooperation.-Fully complied with.
    Terminal facilities.-There are 5 wharves on the portion of the
waterway connecting Core Sound with Beaufort Harbor. Between
the eastern end of this portion of the waterway and Pamlico Sound
there are 12 small wharves. Additional wharves are needed at several
of the communities along Core Sound.
    Operations and results during fiscal year.-The work consisted of
maintenance dredging by leased dredge and making miscellaneous
surveys. Under authority of section 3, Riv er and Harbor Act ap-
proved October 17, 1910, the leased dredge Marion removed 22,714 cubic
yards of material from a side channel beyond the limits of the Federal
project, 60 feet wide, 800 feet long, and 6 feet deep, with a basin 150
by 500 feet, same depth, at Sealevel, N. C. The cost was $4,000, of
which $1,000 was contributed by local interests.
       616634     45-pt. 1, vol. 1-        27
418               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

    Condition at end of fiscal year.-The portion of the existing proj-
ect providing for a through waterway from Pamlico Sound to Beau-
fort was completed in 1934, and the side channel to Atlantic in 1937.
At the close of the fiscal year the controlling low-water depth was
5 feet. The total costs and expenditures for the through waterway to
June 30, 1944, including $40,000 of Public Works funds for new work,
and $1,000 contributed by local interests for maintenance, were $183,-
049.13, of which $67,655.04 was for new work, and $115;394.09 was for
maintenance. The total cost of the side channel to Atlantic, all for
new work, was $18,584.53, of which $13,171.72 was from Works Prog-
ress Administration funds, and $5,412.81 was from funds contributed
by local interests.
    Proposed operations.-An allotment of $20,000 made during July
1944 will be applied to maintenance dredging, under contract, during
October 1944.
    The additional sum of $30,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging, under contract, during
March and April 1946.
    The channels making up this project are subject to rapid shoaling
and their maintenance is required to afford safe and certain movement
of the mail boat from Atlantic to Ocracoke, the service boats attached
to Army and Navy units along Core Banks, and fishing boats engaged
in food and menhaden fishing.
                                            Cost and financial summary

Cost of new work to June 30, 1944_ ____1                                                                             $87, 655. 04
Cost of maintenance to June 30, 1944_-------                                                      ---                128, 247,90

      Total cost of permanent work to June 30, 1944-------                                                           215, 902. 94
Net total expenditures- --    __- -___-                                                             ____ 1 215,           902. 94
Total amount appropriated to June 30, 1944_ _                                                          _ 1 215,           902. 94


    Fiscal year ending June 30                1940            1941              1942                    1943             1944

C ost of new w ork -- - - - - - - . - - - - -            ..-- - - -        .-.-- - -         .-     .      . . . . . .    .     .. .
Cost of maintenance ------                     32, 000      $9, 486. 38      $20, 088. 42          $4, 362.18            $4, 000. 00

Total expended ..            ....---           32, 000        8, 228. 72       21, 346. 08              4, 362. 18            4, 000. 00

Allotted__.-- -        _
                  __ _----        --   --      21,000        24, 000. 00       11,000. 00         -7,     000. 00                63. 02



Balance unexpended July 1, 1943 -----------------------------                                                        $4, 063. 02
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942____.. _..----        --------- _ _                                                             3, 000. 00

      Amount to be accounted for--_         ---------                                                                -7, 063. 02
Deductions on account of revocation of allotment.                              - ---                                   3, 063. 02

      Net amount to be accounted for_----                                              -     _     _                   4, 000. 00
Gross amount expended.----------                                                  -              ___                   4, 000. 00

Amount allotted in July 1944 --------------------------                                                              20, 000.00
Amount available during fiscal year 1945--     -----            __                                                   20, 000. 00
Amount that can be profitably  expended in fiscal   year ending June
                          2           -    - -     - -    - -
30, 1946, formaintenance _______ ___30,__        _                                                                      000. 00
  1In addition, $10,000 contributed funds expended on new work under previous project.
  2 Exclusive of available funds.
         RIVERS AND HARBORS-WILMINGTON,                N.   C., DISTRICT    419
       14. CHANNEL FROM BACK SOUND TO LOOKOUT BIGHT, N. C.

   Location.-This channel extends from a point near the eastern end
of Harkers Island, about 8 miles east of Beaufort, through the shallow
waters of Back Sound and Lighthouse Bay, to and through Shackle-
ford Banks, and into the Atlantic Ocean at Lookout Bight, and is about
4 miles long. (See U. S. Coast and Geodetic Survey Chart No.*421.)
   Existing project.-The project provides for a channel 50 feet wide
and 5 feet deep at mean low water from deep water in Back Sound,
through Shackleford Banks to deep water in Lookout Bight. The
mean range of tide is 3.8 feet in Lookout Bight and 1.3 feet in Back
Sound, and the extreme range is 8.2 feet in Lookout Bight and 3.8
feet in Back Sound.
   The estimate of cost for new work, made in 1937, was $50,000. The
latest (1937) approved estimate for annual cost of maintenance is
$11,000.
   The existing project was authorized by the River and Harbor Act
of August 26, 1937 (H. Doc. No. 251, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Recommended modifications of project.-Under date of February
16, 1942, the Chief of Engineers recommerided modification. of the
existing project so as to provide for a dredged channel 7 feet deep and
100 feet wide from deep water in the sound to deep water in the
ocean at an estimated cost of $50,000, with $12,000 annually for main-
tenance of the modified project; subject to certain conditions of local
cooperation (H. Doc. No. 746, 77th Cong., 2d sess.).
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-None. Not required.
   Operations and results during fiscal year.-The work consisted of
making miscellaneous surveys. The cost and expenditures were $1,-
352.96 for maintenance.
   Condition at end of fiscal year.-The existing project was completed
in 1938. The controlling mean-low-water depth at the end of the fiscal
year was 2 feet. The total costs and expenditures under existing
project to June 30, 1944, were $24,676.08 for new work and $60,823.92
for maintenance, a total of $85,500.
   Proposed operations.-An allotment of $30,000 made during July
1944 will be applied to maintenance dredging, under contract, during
August and September 1944.
   The additional sum of $25,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging, under contract, during
August 1945. This channel serves the mail boat from Beaufort to
Cape Lookout and boats attached to the various Army and Navy units
stationed in the vicinity of Cape Lookout. A large number of com-
mercial boats engaged in food and menhaden fishing use this channel
to reach the fishing grounds at Cape Lookout.
                          Cost and financial summary

Cost of new work to June 30, 1944 _-------          --        -     $24, 676.08
Cost of maintenance to June 30, 1944-------------------------        60, 823. 92
       Total cost of permanent work to June 30, 1944-- -       -     85, 500. 00
Net total expenditures ---                                           85, 500. 00
Total amount appropriated to June 30, 1944---                        85, 500. 00
420         REPORT OF CHIEF OF ENGINEERS, U.                                         S.    ARMY,               1944


   Fiscal year ending June 30               1940                1941              1942              1943                 1944

Cost of new work---                                                                            -
Cost of maintenance ..              ..    $18, 417. 89        $12, 183. 07       $6, 963. 97       .$1,                    352. 96
Total expended   _       -     --        -18, 417. 89           2, 321. 22       16, 825.82                              1, 352. 96
Allotted-- --        -   ---               14, 000. 00         31,500. 00        10, 000.00        -$31,       000


Balance unexpended July 1, 1943                                                                -           -         $1,352. 96
Gross amount expended_________                                               _     _-              _____              1, 352. 96

Amount allotted in July 1944 -                 ______    --                         ______                           30, 000.00
Amount available during fiscal year 1945--                  --                  -_____                               30, 000. 00
Amount that can be profitably      expended in fiscal year ending                      June
  30, 1946, for maintenance 1- - - - - - - - - - - - - - - -- - - - - - - - - - - _25,
                                                                                   --
                                                                                                                        000. 00
1Exclusive of available funds.

15. INLAND WATERWAY, BEAUFORT TO CAPE FEAR RIVER, N. C., IN-
          CLUDING WATERWAY TO JACKSONVILLE, N. C.

   Location.-This waterway begins at Beaufort Harbor and follows
the general line of the coast, passing through Bogue Sound and the
sounds and marine marshes to the south, to a point in Myrtle Sound
just north of Carolina Beach, crossing the mainland at this point into
Cape Fear River, which it enters about 16 miles below Wilmington.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1234 and 1235.)
   Previous projects.-Adopted by River and Harbor Acts of July 4,
1836; March 3, 1837; July 7, 1838; August 2, 1882; August 5, 1886;
September 19, 1890; March 3, 1905; June 25, 1910; and August 8, 1917.
For further details, see page 1803 of Annual Report for 1915, and
page 585 (for New River), page 587, (for waterway between New
River and Swansboro), page 589 (for waterway between Beaufort
Harbor and New River; that is, portion between Beaufort and Swans-
boro), Annual Report for 1917; Annual Report for 1926, page 532, and
Annual Report for 1938, page 523.
   Existing pro]ect.-This provides for a waterway 12 feet deep at
mean low water with a bottom width of 90 feet, extending along the
coast from Beaufort, N. C., to the Cape Fear River, a distance of
93.5 miles, with such modifications in routing as the Chief of Engi-
neers may find desirable and economical, and including the provision
of a tidal lock near the Cape Fear end and a highway bridge in its
vicinity. The project also provides for a channel 10 feet deep at mean
low water and 90 feet wide in New River to the Atlantic Coast Line
Railroad bridge at Jacksonville, N. C., a distance of 21 miles; for a
side channel 12 feet deep and 90 feet wide to a turning basin of the
same depth, 200 feet wide and 350 feet long, opposite the principal
wharves at Swansboro; and for an entrance channel 6 feet deep and
90 feet wide at New River Inlet with connecting channel of the same
dimensions to the Inland Waterway near the mouth of New River.
   The tidal range varies from 31/2 feet at the inlets to 1 foot at points
between. The tidal range for New River varies from 31/2 feet at New
River Inlet to 1 foot at the head of the marshes, and nothing at Tar
Landing 31 miles above. At the Beaufort end of this waterway the
extreme range of tide is 5 feet. At the various inlets between Beau-
fort Inlet and New River Inlet the extreme range of tides is probably
              RIVERS AND HARBORS-WILMINGTON,                               N.    C., DISTRICT            421
from 4.5 to 5 feet. At the Cape Fear River end the mean range is 3.8
feet.
  The estimate of cost for new work, revised in 1938, was $2,402,000,
exclusive of amounts expended on previous projects. The latest
(1938) approved estimate for annual cost of maintenance is $161,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                  Documents



Aug.     8,1917    A 3-foot channel 100 feet wide from Beaufort to     H. Doc. No. 1775, 64th Cong., 2d sess.
                    Swansboro, thence 40 feet wide to Jacksonville.
                                                                                                                   1
Jan.    21, 1927   A 12-foot channel 90 feet wide from Beaufort to     H. Doc. No. 450, 69th Cong., 1st sess.
                     Cape Fear River, N. C.
                                                                                                               1
Aug. 30, 1935      A 10-foot channel 90 feet wide in New River from    H. Doc. No. 67, 74th Cong., 1st sess.
                     the Inland Waterway to Jacksonville.
Aug. 26,1937       A 12-foot side channel 90 feet wide to Swansboro_   Rivers and Harbors Committee Doe.
                                                                        No. 16, 75th Cong., 1st sess.'
                                                                                                             1
June 20, 1938      A 6-foot channel 90 feet wide from New River        H. Doc. No. 691, 75th Cong., 3d sess.
                    Inlet to the Inland Waterway.


  1   Contain latest published maps.


    Recommended modifications of project.-Under date of February
27, 1940, the Chief of Engineers recommended that the existing project
be modified to provide for the construction of six mooring basins at
various locations along the waterway, at an estimated cost of $24,000
for new work and $600 annually for maintenance in addition to that
now required (H. Doc. No. 660, 76th Cong., 3d sess.).
    Under date of June 3, 1941, the Chief of Engineers recommended
further modification of the existing project so as to provide a channel
8 feet deep and 90 feet wide, extending from the waterway via Motte
and Banks Channels to a point just within Masonboro Inlet at Wrights-
ville Beach, N. C., at an estimated cost of $9,000, with $500 annually
for maintenance in addition to that now required; subject to certain
conditions of local cooperation. (H. Doc. No. 346, 77th Cong., 1st
sess.)
   Local cooperration.-Fully complied with.
    Terminal facilities.-The north end of this waterway is in Beaufort
Harbor and harbor at Morehead City, the terminal facilities of which
are described in the reports for those improvements in this report.
There are 16 wharves between Morehead City and Swansboro, 10 at
or near Swansboro, 9 on New River, of which 5 are at or near Jack-
sonville, and 16 between New River and Cape Fear River. The facili-
ties are considered adequate fo~r existing commerce.
    Operations and results during fiscal year.-The work consisted of
maintenance dredging by Government plant and hired labor, by
leased plant, and by contract. The U. S. dredge Henry Bacon, be-
tween January 27, and May 12, 1944, removed 54,868 cubic yards of
material from sections IV and V. The leased dredge Charleston
between July 1, and December 2, 1943, removed 259,720 cubic yards of
material from section IV, and 313,311 cubic yards from section III,
a total" of 573,031 cubic yards. The leased dredge Marion, between
August 3, 1943, and March 24, 1944, removed 24,985 cubic yards of
422             REPORT OF CHIEF OF ENGINEERS,                                 TJ. S. ARMY,                    1944

material from section I, 170,640 cubic yards from section II, and
284,214 cubic yards from section III, a total of 479,839 cubic yards.
The leased dredge Hallandale, between May 12 and 19, 1944, removed
14,752 cubic yards of material from section I, 12,307 cubic yards from
section III, and 10,909 cubic yards from section IV, a total of 37,968
cubic yards. The contract dredge Hallandale, between January 12,
and May 12, 1944, removed 995,729 cubic yards of material from
section I. The total yardage removed by all dredging operations
was 2,141,435 cubic yards at a cost of $384,158.25.
  Five sets of tie-up dolphins, each set consisting of 11 eleven-pile
clusters, were constructed under contract at the following locations:
500 yards south of Morehead City-Beaufort highway bridge at More-
head City,      mile east and west of Atlantic Beach bridge at More-
head City, and 1/2 mile east and west of Carolina Beach bridge across
section V, at a cost of $73,391.37.
  The total costs were $457,549.62, all for maintenance. The total
expenditures were $464,138.22.
  Condition at end of fiscal year.-The existing project was com-
pleted in 1940. At the close of the fiscal year the controlling mean-
low-water depths were as follows: 12 feet between Beaufort and Cape
Fear River, 12 feet in side channel to Swansboro, 7 feet in New River
to Jacksonville, and 4 feet on the bar at New River Inlet. The total
costs of the existing project to June 30, 1944, were $2,361,331.39, for
new work, and $1,292,119.23 for maintenance, a total of $3,653,450.62.
  Proposed operations.-The balance unexpended July 1, 1944, $14,-
171.63, together with an allotment of $150,000 made in July 1944
will be applied to maintenance dredging to restore project dimensions
in waterway between Beaufort and Cape Fear River, including water-
way to Jacksonville, N. C., in side channel to Swansboro; and in
New River Inlet Channel, with- Government plant and hired labor,
or under contract, as needed.
  The additional sum of $161,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging with Government plant
and ired labor between July 1, 1945, and June 30, 1946.
                                        Cost and financial summary
Cost of new work to June 30, 1944__                                                                         $2, 560, 038. 31
Cost of maintenance to June 30, 1944_----                                            -         -_              1,399, 753.17
            Total cost of permanent work to June 30, 1944----------                                           3, 959, 791. 48
Net total expenditures__                          _-       -           _-    -           -_                    3, 959, 791. 48
Unexpended balance June 30, 1944_--------                                                             ---           14, 171. 63
            Total amount appropriated to June 30, 1944----                                                    3, 973, 963. 11


     Fiscal year ending June 30            1940        -        1941              1942                 1943             1944

Cost of new work___ :..---              $113,003.03
Cost of maintenance- -----.....           59, 347. 82      $71,932. 00       $115, 997. 92          $119,026. 72      $457, 549.62
       Total cost-_        -_-_--.---    172, 350. 85          71, 932. 00    115, 997. 92           119, 026. 72      457, 549. 62
Total expended..----------------..       161, 645. 52          82, 590. 56    116, 094. 93           112, 438. 12      464, 138. 22
Allotted ---------------------            64, 000. 00          84, 000. 00       95, 000. 00         275, 000. 00      204, 000. 00
          RIVERS AND HARBORS-WILMINGTON,                N.     C., DISTRICT       423
Balance unexpended July 1, 1943           __ __ __                        $274, 309. 85
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942              $73,.000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943 --------------181, 000. 00
                                                                           254, 000. 00

      Amount to be accounted for----------------------           -         528, 309. 85
Deductions on account of revocation of allotment   --          --           50, 000. 00

        Net amount to be accounted for-----------------------              478, 309. 85
Gross amount expended_ _ _______ _ _ __           --   465, 138. 22
Less reimbursements collected - - -   -     ---          1, 000. 00
                                                                           464, 138. 22

     Balance unexpended June 30, 1944                        -14,              171. 63
Amount allotted in July 1944_ __-                            -150,             000. 00

        Amount available during fiscal year 1945                     -_    164, 171. 63

Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance   1-     ---------                        161, 000. 00
1 Exclusive of available funds.


  16. INTRACOASTAL WATERWAY FROM CAPE FEAR RIVER, N. C., TO
                      WINYAH BAY, S. C.

   Location.-This waterway begins at Southport, N. C., and follows
in general a route from the Cape Fear River up Elizabeth River 6.7
miles to a point near its headwaters; thence through high ground 2.6
miles to the headwaters of Davis Creek; thence down Davis Creek to
the sounds and salt marshes and through the latter to Little River,
S. C., a distance of 24.2 miles; thence up Little River 5.7 miles to its
headwaters; thence through high ground 21.8 miles to the head of
Socastee Creek; thence down Socastee Creek 6.5 miles to the Wacca-
maw River, .and down the latter 27 miles to Winyah Bay; a total dis-
tance of 94.5 miles. (See U. S. Coast and Geodetic Survey Charts Nos.
1236 and 1237.)
   Existing project.-This provides for a waterway 12 feet deep at
mean low water with a bottom width of not less than 90 feet, between
Cape Fear River, N. C., and Winyah Bay, S. C., a distance of approxi-
mately 94.5 miles; for the construction of three bridges crossing the
waterway in Horry County, S. C.; and for a yacht basin 230 feet wide,
450 feet long, and 12 feet deep near the town of Southport, connected
with the Intracoastal Waterway by a suitable channel of the same
depth. The mean range of tide on Cape Fear bar is 4.7 feet; at inlets
4 feet, varying to 2 feet at points midway between inlets and in
Winyah Bay, at Georgetown, 3.3 feet.
   The estimate of cost for new work, revised in 1938, was $6,431,500.
The latest (1938) approved estimate for annual cost of maintenance
is $62,100.
424            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                  1944

  The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                    Documents


July     3,1930   A waterway 8 feet deep and 75 feet wide from Cape   H. Doc. No. 41, 71st Cong., 1st sess.
                    Fear River to Winyah Bay.
Aug. 30,19351     Construction of bridges across the waterway in      Rivers and Harbors Committee Doc.
                    Horry County, S. C.                                 No. 14, 72c Cong., 1st sess.
Aug. 26,1937      Increasing dimensions of waterway to 12 feet deep   Rivers and Harbors Committee Doc.
                                                                                                       2
                   and 90 feet wide.                                    No. 6, 75th Cong., 1st sess.
June 20,1938      To provide a yacht basin near Southport, 12 feet    H. Doc. No. 549, 75th Cong., 3d sess.'
                   deep, 230 leet wide, and 450 feet long, with
                   connecting channel.

  1 Included in Public Works Administration program Sept. 6, 1933.
  2Contain latest published maps.
   Recommended modifications of project.--Under date of May 25,
1939, the Chief of Engineers recommended modification of the existing
project so as to provide near Myrtle Beach, S. C., an anchorage basin
125 feet wide,-335 feet long, and 12 feet deep, at an estimated first cost
of $11,000, with annual maintenance of $200 in addition to that now
required; subject to certain conditions of local cooperation (H. Doc.
No. 327, 76th Cong., 1st sess.).
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are numerous wharves and landings
along the present waterways which are used mostly for shipping
agricultural and timber products. These wharves are of the open-pile
and timber type. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year.-The work consisted of
maintenance dredging, by contract and with Government plant and
hired labor, and miscellaneous surveys.
   The work under the Wilmington, N. C., district, covering the section
from Cape Fear River, N. C., to Little River, S. C., was as follows:
The leased dredge Marion, between July 1 and 21, 1943, removed
73,877 cubic yards of material at a cost of $11,446.52. The U. S. dredge
Henry Bacon, between April 13 and 28, 1944, removed 145,808 cubic
yards of material at a cost of $19,752.69. Miscellaneous surveys were
made at a cost of $4,377.02. The total costs were $35,576.23, all for
maintenance. The expenditures were $49,209.39.
   The work under the Charleston, S. C., district, covering the section
from Little River to Winyah Bay, S. C., was as follows: During
August 1943, the U. S. dredge Howoell removed 51,045 cubic yards of
material at a cost of $26,330.41, and the dredge Cherokee, under con-
tract, removed 6,850 cubic yards o'f material at a cost of $3,945.12. Re-
mains of damaged wooden spillways were removed by the U. S. snag-
boat Wateree at a cost of $1,726.90. During March 1944 the dredge
Hampton Roads, under contract, removed 30,531 cubic yards of ma-
terial at a cost of $9,281.33. The cost of surveys and supervision was
         RIVERS AND HARBORS            WILMINGTON,        N.      C.,    DISTRICT        425

$12,326.39 (including $1,323.49 applicable to work in fiscal year 1943).
The total costs were $53,610.15, all for maintenance. The expendi-
tures were $52,234.90.
   The total costs for the year for the Wilmington and Charleston dis-
tricts were $89,186.38, all for maintenance. The total expenditures
were $101,444.29.
   Condition at end of fiscal year.-The existing project was completed
in 1940; the 8-foot waterway, including construction of three bridges,
was completed in 1936. The enlargement of the previous 8-foot proj-
ect to the existing 12-foot project and dredging the yacht basin at
Southport were completed in 1940. At the close of the fiscal year
the controlling mean-low-water depths were 12 feet from Cape Fear
River, N. C., to Little River, S. C.; thence 12 feet to Socastee Bridge;
thence 12 feet to Winyah Bay, S. C. The total costs under the exist-
ing project to June 30, 1944, were $6,709,940.50, of which $4,644,503.56
was from regular funds and $2,085,436.94 from Public Works funds.
A total of $6,013,621.86 was for new work and $696,318.64 for main-
tenance. The total expenditures were $6,709,717.99, of which $4,-
644,281.05 was from regular funds and $2,065,436.94 from Public
Works funds.
   Proposed operations.-The balance unexpended June 30, 1944,
$9,198.71, plus accounts receivable, $321.51, together with an allot-
nent of $184,400 made in July 1944, a total of $193,920.22, will be
applied to maintenance as follows:
Accounts payable, June 30, 1944_ __ __ __ _ _----                                    $544. 02
Restoring project dimensions with Government plant and hired
  labor, as needed between July 1, 1944, and June 30, 1945:
    Section from dape Fear River, N. C., to Little River, S. C
    Section from Little River to Winyah Bay, S. C _        ---
                                                               _39,     ----
                                                                       753. 29
                                                                  153, 622. 91
       Total for all work_----------------------------
                               __   _193,                                              920. 22
  The additional sum of $62,100 can be profitably expended during
the fiscal year 1946 for maintenance, as follows:
Dredging the waterway to restore project dimensions, with Government plant
and hired labor, as needed, between July 1, 1945, and June 30, 1946:
    Section from Cape Fear River, N. C., to Little River, S. C- ------ $28, 600
    Section from Little River to Winyah Bay, S. C_----------------- 33, 500
       Total                                              _
               ------------------------------------------------                       62, 100

                             Cost and fjiancial summary
Cost of new work to June 30, 1944                                             $6, 013, 621. 86
Cost of maintenance to June 30, 1944_------                ---                    696, 318. 64
       Total cost of permanent work to June 30, 1944                           6, 709, 940. 50
Plus accounts receivable June 30, 1944            - -                                  321. 51
      Gross total costs to June 30, 1944---------------               -----    6, 710, 262. 01
Minus accounts payable June 30, 1944                             --                    544. 02
      Net total expenditures_                                                  6, 709, 717. 99
Unexpended balance June 30, 1944                                                    9, 198. 71

       Total amount appropriated to June 30, 1944   ---------                  6, 718, 916. 70
426         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                          1944


   Fiscal year ending June 30               1940           1941                   1942                  1943             1944

Cost of new work.                        $794, 532. 32   $60, 137. 48
Cost of maintenance- .---.. .              27, 575. 52    45, 478. 54        $22. 056. 35          $245, 384. 92       $89, 186. 38

      Total cost----_ _   _-----          822, 107.84    105, 616. 02            22, 056. 35        245, 384. 92        89, 186. 38

Total expended----------------909,            979. 58    153, 194. 66            24, 050. 56        231, 020.40         101, 444. 29

Allotted__.-.----...---.---         --    134, 162. 60    66, 400. 00            58, 000.00         178, 471.35         33,000.00



Balance unexpended July 1, 1943 __                                                                                 $77, 643. 00
Amount allotted from War Department Civil Appro-
priation Act approved Apr. 28, 1942_              $10, 000. 00
Amount   allotted from War Department Civil Appro-
  priation Act approved June 2, 1943                10, 000. 00
Amount allotted from War Department Civil Appro-
   priation Act approved June 2, 1943 _                                 --               13, 000. 00
                                                                                                                    33, 000. 00

         Amount to be accounted for                                                ------      -    -              110, 643. 00
Gross amount expended _-                                                           $128, 918. 15
Less reimbursements collected_                                                       27, 473. 86
                                                                                                                   101, 444. 29

         Balance unexpended June 30, 1944                                                                             9, 198. 71
Outstanding liabilities June 30, 1944 _-                                                                                544. 02

      Balance available June 30, 1944-                                                                                8, 654. 69
Accounts receivable June 30, 1944 _                                                                                      321. 51
         Unobligated balance available June 30, 1944                                                                  8, 976. 20
Amount allotted in July 1944_ __                                             _                                     184, 400. 00

         Amount available during fiscal year 1945                                                                  193, 376. 20

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_                                                                                  62, 100. 00
  1 Exclusive of available funds.

                            17. MOREHEAD CITY HARBOR, N. C.

   Location.--On the northern shore of Bogue Sound, adjacent to
Beaufort Harbor and Inlet. New Bern, N. C., the nearest city of im-
portance, is about 43 miles by inland waterway to the northwest. (See
U. S. Coast and Geodetic Survey Chart No. 420.)
   Previous project.-The channel across the ocean bar was formerly
improved under the title of Beaufort Inlet, N. C. The project was
adopted by the River and Harbor Act of March 3, 1905 (H. Doc. No.
563, 58th Cong., 2d sess.). For further details, see page 470 of Annual
Report for 1935.
  SExisting project.--This provides for a channel 30 feet deep and 400
feet wide across the ocean bar at Beaufort Inlet, thence same depth
and 300 feet wide to the marine terminals at Morehead City, enlarged
to 600 feet to form a turning basin at that point, and for construction
of jetties at the inlet; for a channel 12 feet deep and 100 feet wide from
the 30-foot channel to Sixth Street, Morehead City, thence same depth
and 200 to 400 feet wide to Tenth Street, thence 6 feet deep and 75
feet wide to deep water in Bogue Sound. The average rise of the tide
is about 21/2 feet at Morehead city and 31/2 feet at the inlet. Observa-
tions made in 1907 showed an extreme range of tide of 4.8 feet.
               RIVERS AND HARBORS-WILMINGTON,                              N.       C., DISTRICT        427
   The estimate of cost of new work, revised in 1936, is $1,610,000.
The latest (1936) approved estimate for annual cost of maintenance
is $89,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                    Documents


June 25, 1910      Channel 10 feet deep and 100 feet wide to the       H. Doc. No. 649, 61st Cong., 2d sess.
                    wharves at Morehead City, thence 200 feet wide
                    in front of the wharves.
                                                                                                                1
July     3, 1930   Channel 12 feet deep and 100 feet wide from the     H. Doc. No. 105, 70th Cong., 1st sess.
                    outer harbor to 6th St. in Morehead City, thence
                    200 to 400 feet wide to 10th St., and a channel
                    6 feet deep and 75 feet wide connecting with
                    Bogue Sound.
Aug.26,19372       Channel 30 feet deep and 400 feet wide across the   Senate committee print, 74th Cong.,
                    bar at Beaufort Inlet, thence 30 feet deep and      1st sess.      "
                    300 feet wide to the marine terminals at More-
                    head City.


  1Contains the latest published map.
  2 Included in Public Works Administration     program, July 5,1934, under the National Industrial Recovery
Act of 1933.


   Local cooperation.-The project provides that local interests fur-
nish, free of cost to the United States, spoil-disposal areas as required
for new work and for future maintenance and all other lands needed
for the improvement, and to the further condition that local interests
give assurances satisfactory to the Secretary of War that an adequate
terminal open to the public on uniform terms will be available by the
time the channel is completed. Terminals have been completed and
spoil-disposal areas for new work furnished. Lands needed in connec-
tion with the construction of jetties have not been furnished.
   Terminal facilities.-There are 37 wharves along the main water
front of the town, with a total frontage of about 1,182 feet. The
marine terminals provide 1,350 feet of berthing space with a depth
alongside of 27 feet at mean low water, and facilities for transfer of
cargoes between rail and water carriers. The existing facilities are
considered adequate for existing and prospective commerce.
   Operations and results during fiscal year.-The work consisted of
maintenance dredging by contract and by Government plant and
hired labor. The contract dredge Florida,between September 25 and
November 19, 1943, removed 159,759 cubic yards of material from the
turning basin. The contract dredge Hallandale, between November
15, 1943, and January 11, 1944, removed 334,704 cubic yards of mate-
rial from the 300-foot eastern approach channel. The contract dredge
Washington, between December 19, 1943, and January 30, 1944, re-
moved 231,101 cubic yards of material from the turning basin. The
U. S. hopper dredge San Pablo, between July 24 and October 31,
1943, removed 584,913 cubic yards of material from the ocean bar
channel. Dredging ranges were replaced and miscellaneous surveys
were made. The costs were $213,141.53 for maintenance. The ex-
penditures were $212,586.53.
428                REPORT OF CHIEF OF ENGINEERS,                                       U.         S. ARMY,               1944

   Condition at end of fiscal year.--The existing project was 40 percent
completed. The portion of the existing project providing for a 12-foot
channel to Morehead City, thence a 6-foot channel to the westward
to Bogue Sound, was completed in 1931; the portion providing for
the 30-foot channel to the terminals was completed in 1936. No work
has been done on the jetties proposed for Beaufort Inlet. At the close
of the fiscal year, a depth of 28.6 feet at mean low water was available
in ocean bar channel; 26.6 feet in the 30-foot channel (inside) to the
terminals at Morehead City; 12 feet from deep water in the outer har-
bor to the foot of Tenth Street, Morehead City; and thence 5 feet to
Bogue Sound to the westward. The total costs under the existing proj-
ect to June 30, 1944, were $1,090,581.60, includipg $59,630.54 regular
funds and $553,475.86 Public Works funds, a total of $613106.40 for
new work and $477,475.20 for maintenance. The total expenditures
amounted to $1,090,026.60, including $553,475.86 Public Works funds.
  Proposed operations.-The balance unexpended June 30, 1944,
$555, together with an allotment of $100,000 made during July 1944,
will be applied to maintenance, as follows:
Accounts payable, June 30, 1944_         .-  _____________$555
Dredging channel through inlet and channel just inside the inlet with
  Government plant and hired labor, March, April, May, and June 1945                                                                 96, 000
Miscellaneous surveys and contingencies---------------------------                                                                    4, 000
              Total for all work                    --------------------------------------                                        100, 555

  The additional sum of $89,000 can be profitably expended during
the fiscal year 1946 for maintenance, as follows:
Dredging harbor in front of Morehead City and approach channels,
  under contract, February 1946_----------                  ----       $16, 000
Dredging the 30-foot channel from a point just inside the inlet to the
  Morehead City terminals, and the turning basin in front of the
terminals, under contract, January 1946-----_         -         -      25, 000
Dredging the channel through the inlet and the channel just inside the
inlet, with Government plant and hired labor, May and June 1946 ....   48, 000

             Total for all work_ --------------------------------------                                                             89,000

                                                    Cost and financial summary
Cost of new work to June 30, 1944__-- --------                                                                            $657, 590. 64
Cost of maintenance to June 30, 1944_-------                                                               ---             762, 032. 64
      Total cost of permanent work to June 30, 1944-
Minus accounts payable June 30, 1944-- --------
                                                                                                                     -   1, 419, 623. 28
                                                                                                                                 555. 00
     Net total expenditures_---------                                                               ----                 1, 419, 068. 28
Unexpended balance June 30, 1944                                   ---                                                           555. 00
             Total amount appropriated to June 30, 1944---                                                               1, 419, 623. 28


     Fiscal year ending June 30                       1940                1941              1942                  1943              1944

Cost of new work-----------........-....                                                .     .             ......             ..-------------------
Cost of maintenance ............                    $96, 469. 26         $9, 216. 93   $36, 255. 83          $22, 237. 29         $213,141.53
Total expended.............----------------..        96, 469. 26          8, 572. 60    36, 900. 16              22, 237. 29       212, 586. 53

Allotted ..                   -............... ..    60,000.00           30, 500.00     55,000.00--------------                   144, 357. 59
          RIVERS AND HARBORS-WILMINGTON,                     N.      C., DISTRICT              429
Balance unexpended July 1, 1943_ __                                              $68, 783. 94
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941                $65, 100. 53
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942                82, 985. 28
Amount allotted from First Deficiency Appropriation
  Act, approved Apr. 1, 1941 ______       -9,            271. 78
                                                                                 157, 357. 59

      Amount to be accounted for__                                               226, 141. 53
Deduction on account of revocation of allotment                                     13, 000. 00

      Net amount to be accounted for _-                                          213, 141. 53
Gross amount expended                                                            212, 586. 53

       Balance unexpended June 30, 1944 .           --                                  555.00
Outstanding liabilities June 30, 1944           -                                       555.00

Amount allotted in July 1944 _ _                                                 100, 000.00
Amount available during fiscal year 1945    -                                    100, 000. 00

Amount (estimated) required to be appropriated for completion of
  existing project     1                                                   _1,   000,   000.    00
Amount that can be profitably expdnded in fiscal year ending June
  30, 1946, for maintenance 1____     -     -            -    ----    __           89, 000. 00
I Exclusive of available funds.


        18. CAPE FEAR RIVER, N. C., AT AND BELOW WILMINGTON

   Location.-This river is formed by the confluence at Moncure, N. C.,
in Chatham County, of the Deep and Haw Rivers. It flows in a south-
easterly direction and empties into the Atlantic Ocean, at Cape Fear,
near the sduthern extremity of the State. (See U. S. Coast and
Geodetic Survey Charts Nos. 424 and 425.)
   Previous proyeots.-Authorized by River and Harbor Acts of March
2, 1829; July 22, 1854; July 11, 1870; March 3, 1873; June 23, 1874;
September 19, 1890; June 13, 1902; and March 2, 1907. For further
details, see page 1804 of Annual Report for 1915 and page 533 of
Annual Report for 1938.
   Existing project.-This provides for a channel across the bar 30 feet
deep and 400 feet wide from Baldhead Point in a southwesterly direc-
tion; thence 30 feet deep and 300 feet wide in the river up to Wilming-
ton, with increased width at bends; and for an anchorage basin of the
same depth at Wilmington 2,000 feet long, 900 feet wide at the upper
end, and 1,100 feet at the lower end,with approaches 1,500 feet long at
both ends, and for a turning basin 30 feet deep at Wilmington, 1,000
feet long, and 600 feet wide, with approaches 500 feet long at both
ends, located opposite the principal terminals. The plane of reference
is mean low water. The length of the section under improvement is
about 30 miles, the upper limit being at Hilton Bridge (Atlantic Coast
Line and Seaboard Air Line Railroads) on Northeast Cape Fear
River, 11/4 miles above its mouth. The average rise of the tide is 4.7
feet at the ocean bar, 3.6 feet at Keg Island, and 3.4 feet at Wilming-
ton. The-extreme range of tides is about 8.5 feet at the ocean bar, 7.3
feet at Orton Cove, and 6.4 feet at Wilmington.
   The estimated cost for new work, revised in 1930, was $1,745,700,
exclusive of amounts expended on previous projects. The latest
(1930) approved estimate for annual cost of maintenance is $225,000.
430           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                    1944

  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                   Documents


July 25,1912      Channel 26 feet deep and 400 feet wide across the    H. Doc. No. 287, 62d Cong., 2d sess.
                   bar, thence same depth and 300 feet wide, in-
                   creased at bends, to Wilmington.
Mar.     2,1919   Channel 30 feet deep and 400 feet wide, across the   H. Doc. No. 746, 65th Cong., 2d sess.
                   ocean bar. (No work was done on this project.)
Sept. 22,1922     A new channel across the ocean bar 30 feet deep      H. Doc. No. 94, 67th Cong., .1st sess.
                   and 400 feet wide from Baldhead Point.
July     3,1930   Present 30-foot project to Hilton Bridge at Wil-     Rivers and Harbors Committee Doc.
                   mington, and a turning basin.                         No. 39, 71st Cong., 2d sess.


  Latest published maps are in Annual Report, 1914, p. 2018, and H. Doc. No. 615, 70th Cong., 2d sess.

   Recommended modifications of project.-Under date of December
28, 1938, the Chief of Engineers recommended that the project be
modified to provide for increasing the width of the authorized 30-foot
channel between the inner end of the ocean bar channel and Wil-
mington from 300 to 400 feet, with increased width at bends; for
increasing the width of the authorized 30-foot turning basin at Wil-
mington from 600 to 800 feet with suitably lengthened approaches at
both ends; and for a channel 12 feet deep and 100 feet wide in the
Cape Fear River, extending from a point near the eastern entrance of
the inland waterway to a connection with the main river channel, at
a point about 3 miles above; at a total estimated first cost of $675,000
with annual maintenance of $50,000 in addition to that now required;
subject to certain conditions of local cooperation. (H. Doc. No. 131,
76th Cong., 1st sess.)
   Under date of May 25, 1939, the Chief of Engineers recommended
that the project be further modified to provide for an increase in the
length of the southerly approach to the anchorage basin from 1,500
feet to 4,500 feet, and for a depth of 32 feet in the channel between the
outer end of the ocean bar channel and Wilmington, and in the turn-
ing basin, with widths as previously recommended, at an additional
estimated first cost of $790,000, with annual maintenance of $25,000 in
addition to the amounts now required and previously recommended;
subject to certain conditions of local cooperation. (S. Doc. No. 83,
76th Cong., 1st sess.)
   Under date of February 27, 1940, the Chief of Engineers recom-
mended that the project be further modified to provide for a chan-
nel 25 feet deep and 200 feet wide, with increased width at bends,
extending from Hilton Bridge to and including a turning basin of the
same depth and 600 feet wide, at a point 11/4 miles above, at an esti-
mated first cost of $73,000, with annual maintenance of $3,000 in addi-
tion to that now required, subject to certain conditions of local
cooperation. (S. Doc. No. 170, 76th Cong., 3d sess.)
   Terminal facilities.-There are 53 wharves of all classes at Wil-
mington, with a combined berthing space of 18,229 linear feet, and
depths of water alongside from 10 to 30 feet at mean low water. It
is believed that the terminals at Wilmington are adequate at the
         RIVERS AND HARBORS-WILMINGTON,                                           N. C., DISTRICT                     431
present time for the commerce through this port. Below Wilmington
there are 27 wharves, which are considered adequate for present needs.
For further details see Port Series No. 33, revised 1940, Corps of
Engineers.
   Operations and results during fiscal year.-The work consisted of
periodic project surveys, replacing dredging ranges and maintenance
dredging, all with Government plant and hired labor. Between
October 30, 1943, and March 26, 1944, the U. S. dredge Henry Bacon
removed 1,568,962 cubic yards of material from the river channel and
anchorage basin at a cost of $162,438.26.                                     Between November 1 and
December 4, 1943, the U. S. dredge San Pablo removed 263,550 cubic
yards of material from the ocean bar channel at a cost of $29,916.93.
Other costs during the year were $23,172.51 for project surveys,
$139.41 for replacing a dredging range, and $85.30 applicable to dredg-
ing done by Government plant and hired labor during the previous
fiscal year. The total costs were $215,752.41, all for maintenance.                                                   The
total expenditures were $215,673.37.
   Condition at end of fiscal year.-The existing project was completed
in 1932. At the close of the fiscal year the controlling mean low-water
depths were 30 feet in the ocean bar channel, 30 feet in the river channel
up to Wilmington and 28 to 30 feet in the anchorage basin at Wil-
mington. The total costs under the existing project to June 30, 1944,
were $2,033,982.47 for new work, and $4,685,083.41 for maintenance, a
total of $6,719,035.88. The total expenditures were $6,718,986.84.
  Proposed operactions.-The balance unexpended June 30, 1944,
$5,682.32, together with an allotment of $210)000 made during July
1944, will be applied to maintenance as follows:
Dredging ocean bar channel with Government plant and hired labor,
  January and February 1945 __-$50,                                                                              000. 00
Dredging river channels up to Wilmington, and anchorage and turn-
  ing basins at Wilmington, with Government plant and hired labor,
  between February and June 30, 1945__ _       -_--
                                                __165,                                                           682. 32

                          _-
       Total for all work --      ---            _     ---
                                                       _-          _215,                                         682. 32
  The additional sum of $225,000 can be profitably expended during
the fiscal year 1946 for maintenance as follows:
Dredging ocean bar channel with Government plant ad                                             hired labor,
  January and February 1946__                 -----                              ----------
                                                                                   --                          $60, 000
Dredging river channels up to Wilmington, and anchorage and turning
  basins at Wilmington, with Government plant and hired labor, be-
  tween Oct. 1, and Dec. 31, 1945, and Apr. 1, and June 30, 1946 ..... 155, 000
Repairing New Inlet and swash defense dams with hired labor, May and
  June 1946--------------------                                         10,000
      Total-                                                                                                            000
                                                                                                               2---------------

            Total----------Cost and financial summary--------------------                                      225, 000
                               Cost     and    financial            summary




Cost of new work to June 30, 1944_ _ _                       -_                             -           $6, 659, 597. 14
Cost of maintenance to June 30, 1944_ -                           ----                      __           5, 287, 697. 66

       Total cost of permanent work to June 30, 1944                                 -_--       -   _   11, 947, 294. 80
Undisttributed costs June 30, 1944 _    ---                                                         -          -79.      04

      Net total cost to June 30, 1944______________________                                             11, 947, 215. 76

Net to tal expenditures _ _ ___                                                                         11, 947, 215. 76
Unexp ended balance June 30, 1944 _-                                 -           -                  _         5, 682. 32

      Total amount appropriated to June 30, 1944_                             ------------              11, 952, 898. 08
 432             REPORT OF CHIEF OF ENGINEERS,                                         U.        S. ARMY,           1944


      Fiscal year ending June 30                       1940            1941              1942                1943                1944

C ost of new w ork ...-          . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . .
Cost of maintenance             -..........         $88, 885. 30   $237, 626. 60      $49, 520. 89    $225, 817.33          $215, 752. 41

Total expended---...-----..                   ...   88, 943. 07     236, 088. 18       51, 059.31      225, 817. 33            215, 673. 37
Allotted-   -        --------                       111,000.00      174, 000.00       175, 000.00      168, 775.00               2, 500. 00


Balance unexpended July 1, 1943--------------------------                                                            $218, 855. 69
Amount allotted from War Department Civil Ap-
   propriation Act approved June 2, 1943-- -------         $35, 000. 00
Amount allotted from First Deficiency Appropria-
   tion Act approved Apr. 1, 1941_---------------          100, 000. 00
                                                                                                                        135, 000. 00
       Amount to be accounted for.-----------------------                                                               353, 855. 69
Deductions on account of revocation of allotment----------                                                             132, 500. 00
       Net amount to be accounted for---_-- ---------------                                                     _       221, 355. 69
Gross amount expended---------------------------------                                                                 215, 673. 37
      Balance unexpended June 30, 1944-               -                                                                   5, 682. 32
Amount allotted in July 1944-----------------------------_                                                             210, 000. 00
             Amount afailable during fiscal year 1945----------- -                                                      215, 682. 32

Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance --       ----------------                                                              225, 000. 00
   1 Exclusive of available funds.


                     19. CAPE FEAR RIVER, N. C., ABOVE WILMINGTON

    Location.-Forlocation of river see preceding report on Cape Fear
River, N. C., at and below Wilmington.
    Previous projects.-Adopted by acts of March 3, 1881, and June 13,
1902. For further details see page 1805 of Annual Report for 1915
and page 535 of Annual Report for 1938.
    Existing project.-This provides for a navigable depth of 8 feet at
low water from Navassa to the head of navigation at Fayetteville,
115 miles above W'imington, by the construction of three locks and
dams and by dredgig of river shoals between Navassa and Fayette-
ville, and for a dredged channel from Wilmington to Navassa (4
'miles), 25 feet deep and generally 200 feet wide, with a cut-off across
Horseshoe Bend and a turning basin approximately 550 feet long and
400 feet in average width at its head. Data regarding locks and dams
are as follows:

                                                                                   Distance       Distance       Maximum
           Lock and dam                                  Location                  from Wil-       above         available          Lift
                                                                                    mington        mouth        dimensions

                                                                                    Miles          Miles              Feet          Feet
No. 1--------------------Kings                        Bluff-_         --                   39             69       200 by 40              11
No. 2--------------------Browns Landing ---.                                               71          101         200 by 40              9
No. 3---------------------Tolars Landing ......                                            95          125         300 by 40              9
              RIVERS         AND   HARBORS-WILMINGTON,                              N.   C.,    DISTRICT         433

                             Available
                             depth on Character            Kind of                                  Year of   Actual
       Lock and dam          miter sills of foun-           dam         Type of construction        comple-    cost
                              at low      dation            dam                                       tion     cost
                               water


                                Feet
No. 1..                  -             9    Sand--         Fixed--    Concrete lock, timber crib     1916     1$565, 856
                                                                       dam, rock filled.
No. 2 -       --------              12     ___do----...-    do ---    Concrete lock, dam rock        1917     2 909, 633
                                                                       filled.
No. 3         ---                      9 ___do .--          do.....   Concrete lock, concrete        1935       660,930
                                                                       dam.

  1 Includes $96,184 for increasing lift.
2 Includes $356,443 for reconstruction and repairs.


   The tide ranges from 3.4 feet at Wilmington to 1 foot at lock No. 1,
Kings Bluff, N. C., 39 miles above. The extreme range of lunar tides
is 6.4 feet at Wilmington and 1.5 feet at Kings Bluff. The maximum
variation due to floods ranges from 70 feet at Fayetteville to 5 feet at
Wilmington.
  The estimate of cost for new work, revised in 1937, is $2,700,700,
exclusive of amount expended on previous projects. The latest (1937)
approved estimate for annual cost of maintenance is $43,600, including
$14,000 for operation and care of locks and dains.
  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                             Documents


June 25,1910      The 8-foot channel and construction of 2 locks and           H. Doe. No. 890, 60th Cong., 1st sess.
                   dams.
July     3,1930 Channel 22 feet deep to Navassa. (No work was                  Rivers and Harbors Committee Doc.
                   done on this project.)"                                       No. 39, 71st Cong., 2d sess.
June   26,1934 1 Operation and care of locks and dams provided
                   for with funds from War Department appro-
                   priations for rivers and harbors.
                                                                                                                        3
Aug.   30, 1935 2 Construction of lock and dam No. 3, and repairs              H. Doe. No. 786, 71st Cong., 3d sess.
                   and alterations to locks and dams Nos. 1 and 2.
Aug.    26,1937 Present project dimensions from Wilmington to                  Rivers and Harbors Committee Doc.
                   Navassa with cut-off across Horseshoe Bend,                   No. 17, 75th Cong., 1st sess.3
                   and a turning basin.


  1Permanent    Appropriations Repeal Act.
  2 Included in Public Works Administration program Sept. 27, 1933.
  3 Contains latest published maps.


  Local cooperation.-Fully complied with.
  Terminal facilities.-There are six wharves between Wilmington
and Fayetteville, including the public terminal at that point. They
have a total frontage of about 700 feet. The terminals appear to be
adequate for existing commerce.
   Operations and results during fiscal year.-The work consisted of
repairs to dam No. 1 with Government plant and hired labor. Be-
tween October 22 and December 9, 1943, approximately 11,000 square
feet of wooden decking were removed from the downstream face
of the dam, the timber cribs were refilled with 1,585 tons of riprap
          616634-45-pt. 1, vol. 1-                  28
434       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                              1944


stone, and 505 cubic yards of concrete were placed as paving, replacing
the wooden decking removed, at a cost of $28,990.21. O'her costs
were $1,431.98 for flowage easements and $998.19 for miscellaneous
surveys.
   The three locks and dams were operated and maintained through-
out the fiscal year at a total cost of $32,659.11, of which $30,948.55
was for operation, and $1,710.56 for maintenance and repairs. The
total costs were $64,079.49, all for maintenance. The expenditures
were $64,146.18.
   Conditionat end of fiscal year.-The existing project was completed
in 1935 except the 25-foot project to Navassa, which was completed
in 1939. The controlling low-water depths are 25 feet from Wil-
mington to Navassa, 4 miles, thence 22 feet to a point 9 miles above
Wilmington, thence 5 feet to Fayetteville. The total costs under the
existing project to June 30, 1944, were $3,220,793.83, of which $2,-
339,797.63, including $1,104,390.72 from Public Works funds, was
for new work, $486,465.59 for maintenance, and $394,530.61 for op-
erating and care. The total expenditures to June 30, 1944, were
$3,220,860.52, of which $1,940,644.24 was from regular funds, $1,-
104,390.72 from Public Works funds, and $175,825.56 expended be-
tween November 1, 1916, and June 30, 1935, on the operating and
care of the works of improvement under the provisions of the in-
definite appropriation for such purposes.
   Proposed operations.--The balance unexpended June 30, 1914, $1,-
604.24, together with an allotment of $62,000 made in July 1944, will
be applied as follows:
Accounts payable June 30 , 1944_-       - -      -------------             $12. 35
Maintenance:
    Dredging river channel between Navassa and Fayetteville with
       leased plant, October 1944                                      21 091. 89
    Snagging between Wilmington and Fayetteville with U. S.
       derrick boat Northeast, Oct. 1, to Dec. 31, 1944----------- ---  7, 500. 00
Operating and care of locks and dams:
    Operating locks and dams Nos. 1, 2, and 3, July 1,
        1944 to June 30, 1945 -_-__---                              $32, 900. 00
      Maintenance and repairs, locks and dams Nos. 1, 2,
        and3 _   _   _ __   _   _ _-_-2,100.00
                                                                                         35, 000. 00
          Total for all work_--------------------------------                            63, 604. 24
   The additional sum of $70,000 can be profitably expended during the
fiscal year 1946 for maintenance as follows:
Dredging river channel between Navassa and Fayetteville, under con-
  tract, August and September 1945 _- ---   __   --------           $27, 500
Snagging between Wilmington and Fayetteville with U. S. derrickboat
  Northeast, between Aug. 1 and Oct. 31, 1945_ _-             _----------7,                      500
Operating and care of locks and dams:
    Operating locks and dams Nos. 1, 2, and 3, July 1, 1945,
        to June 30, 1946_                 ___---    -     -        _          $32, 900
      Maintenance and repairs, locks and dams, Nos. 1, 2, and 3_                2, 100
                                                                                             35, 000

          Total for all work          _ _    __-_       ___- -         _-       - -      -   '70, 000
  Oil operators have requested that project dimensions be restored, as
they expect to resume shipments of petroleum products by barge to
Fayetteville in 1945. It is expected that the shipment of veneer and saw
logs, and pulpwood, by barge, will increase during the fiscal years 1945
and 1946.
                 RIVERS AND HARBORS-WILMINGTON,                                                 N. C., DISTRICT                     435
                                          Cost and financial summary
Cost of new work to June 30, 1944_                                         ----------                               $2, 488, 916. 82
Cost of maintenance to June 30, 1944__                                                                                1 889, 173. 87
            Total cost of permanent work to June 30, 1944-----------3, 378, 090. 69
Undistributed costs, June 30, 1944 _                                 ---                                                           79. 04

      Net total cost to June 30, 1944_                                                                                   3, 378, 169. 73
Minus accounts payable, June 30, 1944_------                                                         ---                          12. 35
      Net total expenditures _____                                   -3,                                                   378, 157. 38
Unexpended balance, June 30, 1944___                                                                                         1, 604. 24
            Total amount appropriated to June 30, 1944                                           -         -3,             379, 761. 62

    Fiscal year ending June 30              1940                       1941                 1942                 1943            1944
            SI                                          I       -          -
Cost of new work....
Cost of maintenance------                  $70,361.44               $82, 223. 91          $46,002.53       $38, 685. 71         $64,079.49
Total expended..............               80,427.68                81,874.96              46, 361. 58       38, 685.71          64,146. 18
Allotted -- - - - - - -             - -    44, 006.35               94, 000.00             51,325.00         11, 000. 00         37. 000. 00


Balance unexpended, July 1 1943 --                 -- -                                                                    $28, 750. 42
Amount allotted from W. D. Civil Appropriation Act approved
June 2, 1943-   - ---
                 --      ---                  _37,000.00

      Amount to be accounted for                                -                                                            65,-, 750. 42
Gross amount expended_                                                                         $72, 688. 85
Less reimbursements collected                               -                         -          8. 542. 67
                                                                                                                             64, 146. 18
      Balance unexpended, June 30, 1944                                               -                                       1, 604.24
Outstanding liabilities, June 30, 1944 _ _                                                                          --             12. 35

            Balance available, June 30, 1944 _                                                                                1, 591. 89
Amount allotted in July 1944                                __                                                               62, 000. 00
            Amount available during fiscal year 1945                                                                         63, 591. 89

Amount that can be profitably expended in fiscal year ending June
    30, 1946, for maintenance 2___                                             __ -                                          70, 000. 00
   1 Does not include $12,732.73 working fund allotment.
   2 Exclusive of available funds.


                               20. NORTHEAST (CAPE FEAR) RIVER, N. C.
  Location.-Rises in the northern part of Duplin County and flows
130 miles in a general southerly direction, emptying into the Cape
Fear River at Wilmington, 30 miles above its mouth. (See U. S.
Coast and Geodetic Survey Chart No. 1235.)
  Existing project.-This provides for a channel 22 feet deep and
150 feet wide, increased at entrances and on curves, from Hilton rail-
way bridge to a point 23J/4 mil s above same, and for clearing the natural
channel for small steamers, thence to Hallsville and for pole boats to
Kornegays Bridge. Total length of section, 103 miles. The tide
ranges from about 3.4 feet at the mouth of this stream but decreases
to nothing a short distance above Bannermans Bridge. The upper
portion is subject to freshets of from 8 to 12 feet. The extreme
range of lunar tides is 6.4 feet at mouth, 2.5 feet at Castle Hayne, and
2 feet at Smiths Bridge. The maximum variation due to floods is 5
feet at mouth, 8 feet at Kornegays Bridge, and 13 feet at Bannermans
Bridge.
436           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

  The estimate of cost for new work, revised in 1930, is $61,400, of
which local interests are to contribute $25,375. The latest (1919) ap-
proved estimate for annual cost of maintenance is $5,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                   Documents


Sept    19,1890   Clearing the natural channel from Wilmington to     H. Ex. Doc. No. 35, 51st Cong., 1st sess.,
                    Hallsville, 88 miles, for small steamers and to    and Annual Report, 1890, p. 1181.1
                    Kornegays Bridge, 15 miles farther, for pole
                   boats.
Mar.     2,1919   Channel 22 feet deep and 150 feet wide, increased   H. Doe. No. 1356, 62d Cong., 3d sess.'
                   at bends, from Hilton Bridge to a point 2%
                   miles above same. (No work has been done on
                   this project.)


  1Contains latest published maps.

    Recommended modifications of pro_ject.-Under date of February
27, 1940, the Chief of Engineers recommended that the project be
modified by eliminating authorization for the 22-foot channel, on
which no work has been done, and by transferring the section of
the river between Hilton Bridge and a point 11/4 miles above to the
project for Cape Fear River, N. C., at and below Wilmington. (S.
Doc. No. 170, 76th Cong., 3d sess.)
   Local cooperation.--The River and Harbor Act of March 2, 1919,
requires that local or other interests contribute one-half the cost of
the 22-foot channel authorized by the act of March 2, 1919, viz, $25,375.
Local interests have not contributed these funds.
   Terminal facilities.-The wharves on the portion of the river under
improvement by the United States number eight, all of which are
just above Hilton Bridge. They have a total frontage of about 1,140
feet. The water terminals are considered adequate for existing
commerce.
   Operations and results during fiscal year.-The work consisted of
snagging with Government plant and hired labor. The U. S. derrick
boat Northeast, working between Smith's Bridge at the 52 mile board
and Wilmington during the period September 11 to October 9, 1943,
removed 227 snags, 60 stumps, 77 logs, and 117 trees from the channel
and 109 trees from the bank at a cost of $1,397.14. The total costs were
$1,936.70, all for maintenance. The expenditures were $1,936.70.
   Condition at end of fiscal year.-The entire project was about 22
percent completed. The clearing of the natural channel was com-
pleted in 1896. The river is in fair condition to a point 521/2 miles
above the mouth. The governing low-*ater depths are 15 feet to a
point 23/4 miles above the mouth; thench 6 feet to a point 48 miles
above the mouth; and thence 3 feet to Crooms Bridge, 56 miles above
the mouth. Above Crooms Bridge the river is navigable only during
freshets, which may occur any month in the year. The work remain-
ing to be done to complete the project is to dredge the channel 22 feet
deep and 150 feet wide, increased at entrances and on curves, from
                RIVERS AND HARBORS-WILMINGTON,                                                N.     C., DISTRICT                    437
Hilton Bridge to a point 23/4 miles above the mouth of the river. The
total cost and expenditures under the existing project to June 30, 1944,
were $10,687.96 for new work and $61,138.57 for maintenance, a total
of $71,826.53.
   Proposed operations.-The balance unexpended June 30, 1944,
$563.30, will be applied to mainteriance snagging between the mouth
and Crooms Bridge, 56 miles above, with U. S. derrick boat Northeast,
during January 1945.
   The additional sum of $3,000 can be profitably expended during the
fiscal year 1946 for maintenance snagging from the mouth to Crooms
Bridge, 56 miles above, with U. S. derrick boat Northeast, during
January and February 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944 ____--                                           -_                                      $10, 687. 96
Cost of maintenance to June 30, 1944  ---                                           ---                                    161, 138. 57

      Total cost of permanent work to June 30, 1944_                                                                  _     71, 826. 53
Net total expenditures __                                                                                                   71, 826. 53
Unexpended balance June 30, 1944                                                                                                563. 30

             Total amount appropriated to                       June 30, 1944 _                                             72, 389. 83


     Fiscal year ending June 30                  1940               1941              1942                     1943               1944


Cost of new work .-                                     -      --                                                          ----
Cost of maintenance ----               -   -       $1,000                                                                         $1,936.70
Total expended             -    - --                1,000..                         . . . . . ..         . . . . . .               1, 936. 70
Allotted-------------------------2,                     000         -$2, 500                       ---    .-          --          2, 500. 00



Amount allotted from War Depa
  approved Apr. 28, 1942 __
                                                            irtment    Civil Appropriation Act
                                                                                                                            $2,500. 00
Gross amount expended _-                                                       -          -        $2, 171.68
Less reimbursements collected--                                                                        234.98
                                                                                                                             1, 936. 70
             Balance unexpended June 3( 0, 1944-                                                    -563.                                30

Amount (estimated) required to b e appropriated for completion of
existing project            -     nde i - -                                                                               25,375.00
Amount that can be profitably expe nded in fiscal year ending June 30,
1946 for maintenance 2 _ _                                                                                                  3, 000. 00
  I Does not include $27,267.27 working fund allotment.
  2 Exclusive of available funds.


    21. EXAMINATIONS,                          SURVEYS, AND CONTINGENCIES                                         (GENERAL)

   The cost and expenditures during the fiscal year amounted to
$12,416.16. The balance unexpended June 30, 1944, $5,906, together
with an allotment of $10,000 made in July 1944, will be applied as
needed during the fiscal year 1945 to payment of expenses incurred
under this heading.
   The additional sum of $15,000 can be profitably expended during the
fiscal year 1946.
438             REPORT          OF CHIEF           OF ENGINEERS,                     U.     S.    ARMY,             1944


                                           Cost and financial summary
Cost of new work to June 30, 1944_
Cost of maintenance to June 30, 1944_-                                                                                   $298, 086. 21
            Total cost of permanent work to June 30, 1944------------298,                                                           086. 21

Net total expenditures-_                      --      -     ------------                                                       298, 086. 21
Unexpended balance June 30, 1944_                                                                                                5, 906. 00
            Total amount appropriated to June 30, 1944                                 --------------                          303, 992. 21


       Fiscal year ending June 30              1940                    1941               1942               1943                    1944

Co st of n ew w ork .. .. .. . .. .. . .. .. .. . ..            ..    . .. .. .. . .. .. . .. .. .. . _. ...    ...                ... ... ..
Cost of maintenance----  .  _-. ---     $24, 734. 38                 $27, 282.09    $13, 416. 17   $10, 007. 22                     $12, 416. 16
Total expended-- .-----                       20, 390.80              27. 778. 45      12, 930. 47          10, 007. 22              12, 416. 16
Allotted ...........        ..........        40, 000. 00              6, 000. 00     -5, 000. 00            5, 000. 00              10, 000. 00



Balance unexpended July 1, 1943                                                                                                 $8, 322. 16
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941_-     -- ---------            _                                                                         10, 000. 00
      Amount to be accounted for ----------------------------                                                                   18, 322. 16
Gross amount expended------------------------------12,                                                                              416. 16
     Balance unexpended June 30, 1944------------------5,                                                                           906. 00
Amount allotted in July 1944 --------------                                                                                     10, 000. 00
             Amount available during fiscal year 1945                                   -15,                                         906. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1   -              -_-          -    -                                                               15, 000. CO
   I Exclusive of available funds.


22. OTHER NAVIGATION                                PROJECTS FOR WHICH                                      NO ESTIMATES
                                                   ARE SUBMITTED

                                                                       For last     Cost and expenditures to                     Estimated
                                                                     full report          June 30, 1944                          amount re-
                       Name of project                               see Annual                                                   quired to
                                                                       Report
                                                                        for-        New work           Maintenance                complete


1.    Newbegun Creek, N. C.1                                           1928           $4, 802. 08              $246. 58              (2)
2.    Perquimaus River, N. C.1                                         1910           13, 750. 00     -   -(2)
3.    Edenton Harbor, N. C.1                                           1941           73, 750. 00           2, 970. 84               (2)
4.    Mackay Creek, N. C.1-..........                                  1938           13, 374. 60           4, 773.03                (2)
5.    Scuppernong River, N. C.'- ---------                             1941           81, 163.63           54, 865.81                (2)
6.    Waterway connecting Swan Quarter Bay
         with Deep Bay, N. C.1.             .........                   1940             8, 550. 98         10, 433.40                (2)
7.    Belhaven Harbor, N. C.' ..........                               1942           126,687.41             2,188. 81               (2)
8.    Fishing Creek, N. C.3.          ...........                      1931            22, 715. 10           8, 632. 85              (2)
9.    South River, N. C.1                                              1936            12, 452. 02         21,469. 88                (2)
10.    Bay River, N. C.1
11.
12.
       Smith Creek (Pamlico County), N. C.'
       Neuse River, N. C.'-..            ..........
                                                          -..           1941
                                                                        1941
                                                                        1942
                                                                                        44, 381.56
                                                                                        14, 471.80
                                                                                       403, 066.04
                                                                                                            49, 518. 44
                                                                                                              6, 957. 80
                                                                                                           288, 167.90
                                                                                                                                      (2)
                                                                                                                                      (2)
                                                                                                                                      (2)
13.    Swift Creek, N. C.1                                              1940             1,600. 00            5, 422. 00              (2)
14.    Contentnea Creek, N . C .1 _ . . . . . . . . .                   1941            64, 394. 56         32, 247. 15               (2)
15 .   T ren t R ive r, N . C .' 4 . . . . . . . . . . . .              19 42          115, 199. 4 5        6 9 , 7 86 . 7 7          (2)
16.    Harbor of Refuge at Cape Lookout, N. C.1                         1934        1, 368, 798. 72         32, 853. 75             $1, 160. 000
17.    Smiths Creek (Wilmington), N. C.1 .- -..                         1941             8, 507. 45                 17. 61            (2)
18.    Black River, N. C.1                  .. _ .......                1941            12, 358. 40         36, 071.85                (2)
19.    Lockwoods Folly River, N. C.1----                                1942            17, 818.50          11, 162.60                (2)
20.    Shallotte River, N. C.1 .          -......        .....          1933            18, 181.37            6, 467.81               (2)


   2 Channels adequate for commerce.
   2 Completed.
   3 No commerce reported.
   4 Modifications recommended in H. Doc. No. 623, 77th Cong., 2d sess.
                     FLOOD CONTROL-WILMINGTON,                                 N. C., DISTRICT                            439
           23. PLANT ALLOTMENT, WILMINGTON, N. C., DISTRICT

                                      Cost and financial summary
Undistributed costs June 30, 1944----------------------------                                              $606, 797. 77
Plus accounts receivable June 30, 1944-_   -----          __                                                 22, 706. 97

      Gross total costs to June 30, 1944--  -----                                              _               629, 504. 74
Minus accounts payable June 30, 1944 ------------------
                                         _                                                                      51, 120. 43

      Net total expenditures- ___   -------                                                -__                 578, 384. 31
Unexpended balance June 30, 1944--_                                -------                         _           219, 320. 12

           Total amount appropriated to June 30, 1944-------------                                             797, 704. 43


    Fiscal year ending June 30            1940              1941                1942               1943              1944


                ----------------
Total expended ...                     $57, 712. 06      $187, 475. 75 -$128, 925. 88          -$44, 043. 92     -$258,   689. 28

Allotted__ .--------.------             288, 755. 73       50,000.00         -98,100.00                           -176,000.   00



Balance unexpended July 1, 1943_--      -----------
Deductions on account of revocation of allotment_                                          -176,
                                                                                          _-
                                                                                                           $136,630.84
                                                                                                                000. 00
        Net amount to be accounted for                                                                     -39,      369. 16
Gross amount expended             -$901,                                                       067. 58
       Reimbursements collected--
Less ssReceipts                     $1, 157, 637. 79
                from sales                2, 119. 07
                                                                                1, 159, 756. 86
                                                                                                          -258,      689. 28

      Balance unexpended June 30, 1944_                                                                        219, 320. 12
Outstanding liabilities June 30, 1944                                        _ __                               61, 377. 97
      Balance available June 30, 1944_ ________------157,                                                            942. 15
Accounts receivable June 30, 1944_ ____ _ ____--22,                                                                  706. 97

           Unobligated balance available June 30, 1944                              ---                        180, 649. 12

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                              Date trans-                                      Recommenda-
            Locality               Authorization act           mitted to               Document No.            Recommenda-
                                                               Congress

Tar River, N. C., including      Rivers and Harbors .................----
Fishing, Otter, Swift, and       Committee resolu-
  Town Creeks, navigation          tion, Feb. 1, 1939.
  and flood control.


24. SNAGGING AND CLEARING UNDER AUTHORITY OF SECTION 2 OF
   THE FLOOD CONTROL ACT APPROVED AUGUST 28, 1937, AS AMENDED
  The Flood Control Act approved August 28, 1937, as amended by the
Flood Control Acts approved August 11, 1939, and August 18, 1941,
authorized the allotment of not to exceed $500 000 from the flood-
control appropriations for any one fiscal year for the removal of accu-
mulated snags and other debris from, and clearing and straightening
of channels in, navigable streams and tributaries thereof when such
work is advisable in the interest of flood control; provided that not
more than $25,000 shall be allotted for this purpose for any single trib-
utary froin the appropriations for any one fiscal year.
440               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

  No snagging or field operations were carried on during the fiscal
year on Contentnea Creek, N. C., or on Tar River and tributaries,
North Carolina.
  The balance unexpended at the end of the fiscal year, $465.65 on Con-
tentnea Creek, N. C., and $2,639.92 on Tar River and tributaries, a total
of $3,105.57, was revoked November 29, 1943.
             "            Cost and financial summary
Cost of new work to June 30, 1944                                                                                     $64, 960. 36
Cost of maintenance to June 30, 1944
             Total cost of permanent work to June 30, 1944-- ----------                                                64, 960. 36
Net total expenditures_                         _ _ _____________                                                      64, 960. 36
Total amount appropriated to June 30, 1944 -                                        -            -        -            64, 960. 36

    Fiscal year ending June 30                      1940               1941              1942             1943             1944

-Cost of new work             ........            $25, 000. 00        $1,583.18     $24, 344. 41         $1,032. 77
Cost of maintenance----
                    .-----------------------------------------------------------                                            -     ---
               .....
Total expended ----------------                   $24, 936.12            468. 09     22, 974. 36          3, 581.79
Allotted.....
         ----------------------                    25, 000. 00        16, 465. 93       13, 600. 00   --------------       $3, 105. 57

Balance unexpended July 1, 1943-------------------------------                                                         $3, 105. 57
Deductions on account of revocation of allotment------------ ----                                                       3, 105. 57

25. PRELIMINARY                               EXAMINATIONS, SURVEYS,                            AND      CONTINGENCIES
                                                  FOR FLOOD CONTROL

   The cost and expenditures during the fiscal year amounted to
$3,430.30. There were no funds on hand June 30, 1944. An allot-
ment of $7,000 made in July 1944 will be applied during the fiscal
year 1945 to the payment of expenses incurred under this heading.
   The additional sum of $5,000 can be profitably expended during
the fiscal year 1946.
                                                 Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944-------------------------                                                         $20, 781.29
       Total cost of permanent work to June 30, 1944-    -                                                    -        20, 781. 29
Net total expenditures                         -    -20,                                                                   781. 29
Total amount appropriated to June 30, 1944-------------                                                                20, 781. 29

     Fiscal year ending June 30                     1940               1941             1942              1943             1944

Cost of new work---------------.-------
Cost of maintenance-_ .                            $7, 647. 88          $252. 12     $1, 550. 59         $7,900.40         $3, 430.30
Total expended .....-..                  ..         7, 647.88            252. 12        1, 261.14         8,189. 85         3,430. 30
Allotted.-----------------------.....
                           ..         .....         4,900.00     --------------      20,000.00            2,000.00        -9,118.71


Balance unexpended July 1, 1943------------------------ ----                                                          $12, 549. 01
Deductions on account of revocation of allotment--- -------------                                                        9, 118. 71
        Net amount to be accounted for ------------------------                                                         3,430. 30
Gross amount expended-----------------------------                                                                      3, 430. 30
Amount allotted in July 1944---------------------------------
Amount available during fiscal year 1945
                                                                                                                        7000.
                                                                                                                         7,      00
                                                                                                                         7, 000. 00
Amount that can be profitably expended in fiscal year ending June 30,
                         -
1946, for maintenance 1                                                                                                5, 000. 00
   1Exclusive      of available funds.
           RIVERS AND HARBORS-CHARLESTON,                                    S. C., DISTRICT                 441
26. OTHER FLOOD-CONTROL PIROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                       For last       Cost and expenditures to        Estimated
                                                      full report            June 30, 1944              amount
                Name of project                       see Annual                                      required to
                                                        Report                                         cmplete
                                                         for-         New work        Maintenance      complete

1. Tar River, N . C ..... ..... .... ..... .....         1939          $81, 265. 61                        (1)
2. Goldsboro, Neuse River, N. C----------------          1941                                                     000
                                                                                                            $--------------40,

1 Completed.

Status of all investigations for flood control called for by flood-control acts and com-
                                   mittee resolutions

                                                              Date trans-                           Recommenda-
         Locality                 Authorization act            mitted to      Document No.              tion
                                                               Congress

Tar River, N. C., including   Rivers and     Harbors     ..
Fishing, Otter, Swift, and       Committee Resolu-
Town Creeks, navigation       tion, Feb. 1, 1939.
and flood control.


     IMPROVEMENT OF RIVERS AND HARBOJS IN THE
             CHARLESTON, S. C., DISTRICT
   This district comprises a very small portion of southwestern Vir-
ginia, western-central North Carolina, and all of South Carolina ex-
cept the western portion, embraced in the drainage basins tributary
to the Atlantic Ocean between Little River and the Beaufort-St.
Helena Bridge at Beaufort, S. C. It includes the Intracoastal Water-
way in the same reach.
   District engineer: Lt. Col. J. W. Patton, Jr., Corps of Engineers.
   Division engineer: Brig. Gen. J. S. Bragdon, United States Army,
to June 10, 1944, Brig. Gen. R. F. Fowler, United States Army,
since that date.
                                             IMPROVEMENTS

                      Navigation                                      Navigation-Continued
                                               Page I                                                        Page
1. Intracoastal Waterway, Cape                          11. Shipyard River, S. C ...                          463
      Fear River, N. C., to Win-                         12. Waterway from Charleston
      yah Bay, S. C., (Wilming-                                to Beaufort, S. C .--     _                     466
      ton, N. C. district) ..-                  423      13. Examinations, surveys, and
2. Winyah Bay, S. C-                           442            contingencies (general)               ---       468
3. Waccamaw River, N. C. and                            14. Other navigation projects for
        S. C . _         .                      445            which no estimates are sub-
4. Great Pee Dee River, S. C_                  446            mitted__                                        469
5. Mingo Creek, S. C                           448      15. Plant allotment     -_                            470
6. Waterway from Winyah Bay
      to Charleston, S. C ...                   449               Flood control
7. Santee River, S. C                          452
8. Congaree River, S. (__...                   454 16. Preliminary    examinations,
9. Charleston Harbor, S. C .-                  456       surveys, and contingencies
10. Ashley River, S. C ----                     461       for flood control --                                 471
442           REPORT OF CHIEF OF ENGINEERS,                          U.   S. ARMY,      1944

1. INTRACOASTAL WATERWAY FROM CAPE FEAR RIVER, N. C., TO
    WINYAH BAY, S. C.-SECTION SOUTH OF LITTLE RIVER, S. C.

   For report on this improvement, see page 423.
                                      2. WINYAH BAY, S. C.

    Location.-On the coast of South Carolina, 50 miles northeast of
Charleston Harbor and 90 miles southwest of the entrance to Cape
Fear River, N. C. (See U. S. Coast and Geodetic Survey Chart No.
787.)
    Previous projects.-Adopted by River and Harbor Acts of Au-
gust 2, 1882, and August 5, 1886. For further details see page 1806
of Annual Report for 1915, and page 549 of Annual Report for 1938.
    Existing project.-This provides for a channel 400 feet wide and
18 feet deep at mean low water from the entrance of Winyah Bay,
following the western shore as far as may be necessary, to a point on
the Sampit River 1 mile above the limits of the city of Georgetown,
to be secured and maintained (a) by the construction of two jetties
springing, respectively, from North and South Islands and converg-
ing to give an opening 4,800 feet wide at the 18-foot curve on the
seaward side of the bar, the jetties to be of stone on brush mattresses,
the north jetty having a length of 11,139 feet and the south jetty
21,051 feet; (b) by dredging across the bar to the 18-foot curve indi-
cated; (c) by construction of an earthen dike 14,300 feet long to pro-
tect the shore line of South Island at the southerly side of the bay;
 (d) by dredging in the bay proper, following the southwestern shore
for a distance of about 6 miles opposite Mud Bay; (e) by dredging
a channel between Eastern and Western Channels from Fraziers
Point to Mosquito Point; and (f) by dredging in Sampit River op-
posite the city of Georgetown and across the bar at the mouth of the
river. The mean range of the tide at Georgetown is 3.3 feet, while the
spring tides have a mean rise and fall of 3.9 feet.
    The estimate of cost for new work, revised in 1935, was $817,000,
exclusive of amounts expended on previous projects. The latest
  (1928) approved estimate for annual cost of maintenance is $46,000.
    The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                  Documents


Aug.    5,1886   Jetties and earthen dike to protect south jetty--    H. Ex. Doc. No. 258, 48th Cong., 2d
                                                                       sess., and Annual Report, 1885, pp.
                                                                       1154-1170, and H. Ex. Doc. No. 117,
                                                                       50th Cong., 2d sess., and Annual Re-
                                                                       pert, 1889, pp. 1110-1115.
June 25,1910     Present project channel dimensions and training      H. Doc.No. 398, 58th Cong., 2d sess.,
                  wall.                                                and Annual Report, 1904, pp. 1591-
                                                                       1609.


  For the latest published map see Annual Report for 1915, p. 2394.

  Recomimended modifications of project.-Under date of February
24, 1939, the Chief of Engineers recommended modification of the
existing project so as to provide for a channel 27 feet deep from that
        RIVERS   AND   HARBORS-CHARLESTON,       S.   C.,   DISTRICT   443
depth in the Atlantic Ocean to and including a turning basin in
Sampit River, with a width of 600 feet across the outer bar and in
the gorge and 400 feet thence to the turning basin, widened at the
bends, at an estimated cost of $1,260,000 for new work, with annual
maintenance of $6,000 in addition to the amounts now required, sub-
ject to certain conditions of local cooperation (H. Doc. No.. 211, 76th
Cong., 1st sess.).
   Terminal facilities.-The terminal facilities at the port of George-
town served by this improvement consist of four wharves of ordinary
timber construction, one of creosoted timber construction, suitable
for oceangoing vessels, and a number of smaller wharves and landing
places. These are considered adequate for the present commerce of
the port.
   Operations and results during fiscal year.-On the entrance bar to
Sampit River, 14 feet depth for 200 feet width was restored by U. S.
pipe-line dredge Colonel G. P. Howell, which removed 16,485 cubic
yards of material at a cost of $3,666.46. The cost of surveys and
supervision was $130.49. The total cost during the year was
$3,796.95, all for maintenance. The expenditures were $3,295.87.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1937 with the completion of Eastern Channel, the new
direct channel from Frazier Point to Mosquito Point. The jetties
were completed in 1903-4. The crest elevations range from 8 to -4
feet and are as much as 12 feet below their original heights. Dikes
of various forms have been built to protect the South Island beach
and the shore end of the south jetty. An earthen dike has been con-
structed approximately 3,010 feet long, east of the Eastern Channel,
largely from original channel excavation to assist in maintenance of
the channel. The Sampit River entrance is protected on the eastern
side by a timber and brush training wall 2,000 feet long.
   A reconnaissance examination during June 1944 showed that from
deep water in the ocean to the lower end of the Eastern Channel,
6 miles, full project dimensions obtained; thence to the upper end,
6 miles, not less than 17.5 feet depth on the center line, with estimated
depths of not less than 15 feet on the sides ~f the 400-foot channel,
based on random cross-sections; thence to the mouth of Sampit River,
3 miles, full project dimensions obtain through natural deep water.
In a 1,000-foot reach in the mouth of Sampit River, there is a con-
trolling depth of 14 feet, at mean low water, for 200 feet width along
the easterly side of the channel only; thence a controlling center-line
depth of 16 feet to the head of the project, a distance of 2.75 miles.
No vessels using Winyah Bay and Sampit River have required depths
greater than 12 feet since the commencement of the war.
   The Western Channel from the Estherville-Minim Creek Canal to
the upper end of the Eastern Channel is maintained as a link in the
Intracoastal Waterway, and at the end of the fiscal year had a con-
trolling center-line depth of 13 feet. The downstream portion of
this channel, below the Estherville-Minim Creek Canal, had a con-
trolling center-line depth of 13 feet at mean low water. This portion
of the Western Channel is rarely used by navigation.
   The costs of the existing project to the end of the fiscal year have
been $858,217.30 for new work and $1,346,897.49 for maintenance, a
total of $2,205,114.79. The expenditures have been $2,204,593.71.
444             REPORT OF CHIEF OF ENGINEERS,                      U. S. ARMY,                1944

   Proposed operations.-The balance unexpended June 30, 1944,
$6,712.68, together with $12,000 allotted July 3, 1944, a total of
$18,712.68, will be applied as follows:
Accounts payable June 30, 1944_$------------                                                           521. 08
Maintenance:
   Emergency dredging, as required, to restore 14-foot depth for
      200-foot width in the mouth of Sampit River, with U. S. pipe-
      line dredge Colonel G. P. Howell and hired labor, Feb. 1-6, 1945_ 4,200. 00
   Dredging by contract, as may be required, to remove shoals in
      Sampit River from the mouth to the head of the project, June
      1-17, 1945_----------------------------------                     13, 991. 60

               Totalforallwork----------------------------------18,                                     712. 68
   The additional sum of $20,000 can be profitably expended during
the fiscal year 1946, and will be applied to contract dredging to main-
tain sufficient depth and width for navigation, from the mouth of
Sampit River to the head of the project, September 1-30, 1945.
                                       Cost and financial summary
Cost of new work to June 30, 1944                                                             $3, 304, 069. 15
Cost of maintenance to June 30, 1944---------------- ------                                    1, 461, 453. 86
           Total cost of permanent work to June 30, 1944 -------                               4,765, 523. 01

Gross total costs to June 30, 1944----------------------                                       4,765, 523. 01
Minus accounts payable June 30, 1944------ -----------------                                         521. 08
      Net total expenditures----------------------                                             4, 765, 001. 93
Unexpended balance June 30, 1944---------------------                                               6,712. 68
           Total amount appropriated to June 30, 1944------- -                                 4, 771, 714. 61


   Fiscal year ending June 30            1940          1941         1942               1943             1944

C ost of new work -- - - - - -. - - - - --. -- - - - - -. -- - - - -.. - - - - -.. . . . . . . .
Cost of maintenance .........------------. $19,810. 16 $48, 962. 37 $7, 205.81 $2,258.49 $3, 796.95
Total expended ----------------         20, 365. 42   48, 961.75   7, 387. 82          2,057.10         3, 295.87

Allotted   ----------------------       40, 000.00                 15, 600.00      -27, 500.00         -9,000.00



Balance unexpended July 1, 1943----------------------------                                       $19, 008. 55
Deductions on account of revocation of allotment---------                                           9,000. 00
       Net amount to be accounted for----------------- -----                                       10, 008. 55
Gross amount expended _____-__--__$3,                 444. 60
Less reimbursements collected --- _     ---           148. 73
                                                                                                     3, 295. 87

      Balance unexpended June 30, 1944                         -                                     6, 712. 68
Outstanding liabilities June 30, 1944_                              - -                                 521. 08
     Balance available June 30, 1944-------------------                                              6,191. 60
Amount allotted in July 1944_ _- _-_12,- --                                                            000. 00

           Amount available during fiscal year 1945                             -18,                   191. 60

Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance 1                  _--                                    __          20, 000. 00
  1Exclusive     of available funds.
              RIVERS      AND    HARBORS-CHARLESTON,                       S.   C., DISTRICT              445
                           3. WACCAMAW RIVER, N. C. AND S. C.

   Location.-This river rises at Lake Waccamaw, N. C., and flows
southwest 139.9 miles into Winyah Bay, near Georgetown, S. C. (See
U. S. Geological Survey map of North and South Carolina, 1929.)
   Existing project.-This provides for a channel 12 feet deep at low
water, with 80 feet bottom width, from the mouth of the river to
Conway, 41.5 miles; thence a channel 4 feet deep at low water and
50 feet wide to Red Bluff, 25.5 miles above Conway; thence a cleared
channel to Lake Waccamaw. The usual seasonal variation in water
surface is about 7.5 feet at Conway and about 12 feet at Star Bluff,
80 miles above the mouth. The tidal variation in Winyah Bay is
3.3 feet and at Conway at low river stage it is 1.2 feet.
   The estimate of cost for new work, revised in 1930, was $262,800.
The latest (1930) approved estimate for annual cost of maintenance is
$4,500.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                    Documents


June 14,1880      Channel 12 feet deep to Conway and cleared      S. Ex. Doe. No. 117, 46th Cong., 2d sess.,
                   channel, Conway to Lake Waccamaw.                   and Annual Report, 1880, p. 848.
July     3,1930   Channel 4 feet deep from Conway to Red Bluff.   H.     Doc. No. 82, 70th Cong., 1st sess.
                                                                       (Contains latest published map.)



   Recommended modifications of p~oject.-Recornmendation was made
to Congress in 1926 that the project be curtailed by eliminating all
work between Star Bluff and Lake Waccamaw (H. Doc. No. 467, 69th
Cong., 1st sess.).
   Terminal facilities.-At Bucksport there is a wharf with an electri-
cally operated boat lift, where marine fuel may be obtained. At inter-
mediate landings there are privately owned wharves, a number of
which are used for loading pulpwood on barges. These facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year.-There were no opera-
tions during the fiscal year. The costs and expenditures were $127.71.
   Condition at end o fiscal year.-The 12-foot channel to Conway,
mile 41.5, was completed in 1924, and that depth obtains for most of
the distance. An investigation during May 1944, between Enterprise,
mile 27, and Conway, mile 41.5, showed that there were about 100 vis-
ible.obstructions consisting of logs, stumps, snags, and trees in the river,
and overhanging trees along the banks thereof, which may interfere
with navigation or which may enter the channel shortly and form
obstructions to navigation. There has been no commercial navigation
above Conway during the past several years.
   A survey during 1939, and an investigation during February 1942,
showed that shoals have formed at several places, limiting the con-
trolling depth at these points to 11.3 feet for a width of about 40 feet.
These surveys showed full project dimensions in the 4-foot channel
above Conway to Sessions Landing, mile 54; thence to Red Bluff, mile
67, sand bars limit the controlling depth to 2.8 feet at low water for a
446          REPORT OF CHIEF OF ENGINEERS,                                              U.   S. ARMY,           1944

width 'of 30 feet. Above Red Bluff, no work having been done for
several years, the channel is obstructed by logs and snags and cannot
be navigated safely.
   The costs and expenditures to the end of the fiscal year have been
$262,813.58 for new work and $154,600.34 for maintenance, a total of
$417,413.92.
   Proposed operations.-The balance unexpended June 30, 1944,
$1,412.95, together with $2,000 allotted July 3, 1944, a total of $3,412.95,
will be applied to maintenance snagging and possibly to the removal
of sandbars, as required, from Enterprise, mile 27, to Conway, S. C.,
mile 41.5, with the U. S. snagboat Wateree and hired labor, July 20,
to August 15, 1944.
   The additional sum of $4,500 can be profitably expended during the
fiscal year 1946, in maintenance snagging, as required, from Enter-
prise, mile 27, to Red Bluff, S. C., mile 67, with U. S. snagboat Wateree
and hired labor, December 15, 1945, to January 15, 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944_-     -------.-----                $262, 813. 58
Cost of maintenance to June 30, 1944_-                - -- _____154,       600. 34
       Total cost of permanent work to June 30, 1944------------ 417, 413. 92

Net total expenditures   -------------------------------                                                              417, 413. 92
Unexpended balance June 30, 1944_----                    -                                              -                1, 412. 95
       Total amount appropriated to June 30, 1944-- -----------                                                       418, 826. 87


   Fiscal year ending June 30                     1940                 J941              1942           1943               1944

Cost of new work                                           -------------
Cost of maintenance        .....-------------    $5, 979. 51           $1, 939. 21      $2, 417. 39                          $127.71

Total expended -----------------
                ...                               6, 032. 10               1, 998. 79    2, 485. 23     -$67.    79           127. 71

Allotted.         ..-----------------               500. 00                4, 500. 00    3, 000. 00   -4, 200. 00-.


Balance unexpended July 1, 1943-----------------------------                                                           $1, 540. 66
Gross amount expended     ------------------------- $131.40
Less reimbursements collected------------------------  3. 69
                                                                                                                  --       127. 71
     Balance unexpended June 30, 1944                                                                                   1412.     95
                                                                                                                        1,-------------------
Amount allotted in July 1944_                                                                                           2, 000. 00
     Amount available during fiscal year 1945-----------                                                                3, 412. 95
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance'----------------------                                                                           500. 00
                                                                                                                        4,-----
  1 Exclusive of available funds.


                                   4. GREAT PEE DEE RIVER, S. C.

  Loeation.-Great Peedee (Pee Dee) River rises in the mountains
of North Carolina and flows generally southeast for 435 miles into
Winyah Bay, near Georgetown, S. C. Above the Uharie River, 233
miles from the mouth, it is called the Yadkin. (See U. S. Geological
Survey map of South Carolina, 1929.)
  Emisting project.-This provides for a cleared 9-foot channel from
Waccamaw River, via Bull Creek, to Smiths Mills and thence a 31/-
foot channel to Cheraw at all stages of water. The tidal variation
            RIVERS AND HARBORS-CHARLESTON,                           S.   C., DISTRICT           447
at low-water stage is 2.3 feet at Waccamaw River and 3 inches 16
miles above. The ordinary flood stage is 18 feet above the low-water
stage at Smiths Mills, 17 feet at Atlantic Coast Line Railroad bridge,
and 30 feet at Cheraw Bridge, respectively 55, 105, and 172.5 miles
from the mouth.
   The estimated cost for new work, revised in 1900, was $235,345.
The latest (1900) approved estimate for annual cost of maintenance
is $5,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                                Documents


June 14, 1880   Removal of obstructions to secure a navigable     S. Ex. Doc. 1no. 117, 46th Cong., 2d
                 depth of 9 feet to Smiths Mills and 3i feet to     sess., and Annual Report, 1880, p.
                 Cheraw.                                            844.
June 13,1902    To secure a 3 -foot channel between Cheraw and    H. Doc. No. 124, 56th Cong., 2d sess.
                 Atlantic Coast Line R. R. bridge by dredging,
                 snagging, and constructing timber and pile
                 dams.


  For map see Annual Report for 1889, p. 1180.


   Recommended modifications of project.-Recommendation was
made to Congress in 1926 that the project be curtailed by elimination
of all work between Jeffreys Creek and Cheraw (H. Doc. No. 467, 69th
Cong., 1st Sess.).
   Terminal facilities.-Located at various places along the stream are
landings for the handling of pulpwood. There are practically no
other terminal facilities, except small sheds constructed at a few land-
ings as a protection to freight. They are privately owned.
   Operationsand results duringfiscal year.-There were no operations
during the fiscal year. The costs and.expenditures were $48.79.
   Condition at end of fiscal year.-The existing project was completed
in 1909. An investigation during May 1944, between the head of Bull
Creek, in Great Pee Dee River, mile 29.5, and Smiths Mills, mile 55,
showed that there were about 350 visible obstructions, consisting of
logs, stumps, snags, trees, and sand bars in the river, and overhanging
trees along the banks thereof, which may interfere with navigation
or which may enter the channel shortly and form obstructions to navi-
gation. There has been no commercial navigation above Smiths Mills
during the past several years.
   A survey during January 1939, and an investigation during January
1942, showed a cleared channel 9 feet deep from Waccamaw River via
Bull Creek to Smiths Mills, mile 55; thence 3 feet to Jeffreys Creek,
mile 91; thence 2 feet to Mars Bluff, mile 105; thence less than 1 foot
to Cheraw, mile 174.5.
   The costs and expenditures to the end of the fiscal year have been
$183,712.41 for new work and $219,184.06 for maintenance, a total of
$402,896.47.
  Proposed operations.-The balance unexpended June 30, 1944,
$1,489, together with $2,000 allotted July 3, 1944, a total of $3,489, will
be applied to maintenance snagging and possibly to the removal -of
448          REPORT OF CHIEF OF ENGINEERS,                              U.    S. ARMY,                     1944


sand bars, as required, from the head of Bull Creek at Great Pee Dee
River, mile 29.5, to Smiths Mills, mile 55, with U. S. snagboat Wateree
and hired labor, August 16, to September 13, 1944.
   The additional sum of $5,000 can be profitably expended during the
fiscal year 1946 in maintenance snagging, as required, from the head
of Bull Creek at Great Pee Dee River, mile 29.5, to Smiths Mills, mile
55, with U. S. snagboat Wateree and hired labor, November 11, to
DI)ecember 15, 1945.
                                     Cost and financial summary
Cost of new work to June 30, 1944_ __                                -$183,                                         712. 41
Cost of maintenance to June 30, 1944                   -       --                                              219, 184. 06

         Total cost of permanent work to June 30, 1944------------                                             402, 896. 47

Net total expenditures_ _._______                    -_-__                                                     402, 896. 47
Unexpended balance June 30, 1944_ ________--------1,489.                                                                 00

         Total amouint appropriated to June 30, 1944--------                                                   404, 385. 47

   Fiscal year ending June 30             1940          1941              1942                      1943             1944
Cost of new work    .....-....     ..-
Cost of maintenance ----------           $5, 222.98    $5,609. 94        $3, 716. 52 --------------                     $48. 79

Total expended ----------------           5, 222.98     5, 609. 94        3, 843.48                -$126.96              48. 79

         -----------------------
Allotted__                                4, 000. 00    5, 000. 00        5, 000. 00              -5,000. 00


Balance unexpended July 1, 1943                  _ _                             ---- --                        $1, 537.79
Gross amount expended_ _                                                                                        -48.79
     Balance unexpended June 30, 1944                                                  --                         1, 489. 00
Amount allotted in July 1944 _ __________                                                   -2,                      000.00

         Amount available during fiscal year 1945_                                                                   489. 00
                                                                                                                  3----------,

Amount that can be profitably expended in fiscal y ear ending June
30, 1946 for maintenance 1-__   __        _           -_ --
                                                           -5,                                                       000.00
  SExclusive of available funds.


                                    5. MINGO CREEK, S. C.

   Location.-This stream rises in the northern part of Williamsburg
County, S. C., about 12 miles east of Kingstree, flows in a south-
easterly direction about 45 miles in Williamsburg and Georgetown
Counties and enters Black River at a point approximately 25 miles
above the mouth of the latter and about 30 miles by water from
Georgetown, S. C. The head of navigation is regarded as being 11
miles above the mouth. (See U. S. Geological Survey Map of South
Carolina, 1929.)
   Previous projects.-The original project was adopted by the River
and Harbor Act of August 11, 1888. For scope of previous projects,
see page 1807, Annual Report for 1915.
   Eisting project.-This provides for a channel 60 feet wide and 8
feet deep at mean low water, from the mouth to Hemingway Bridge,
11 miles, by making four short cut-offs. The rise of tide is 2 feet and
freshet rise 41/2 feet.
   The estimate of cost for new work, made in 1910, was $22,000. The
latest (1928) approved estimate for annual cost of maintenance is $400.
             RIVERS        AND HARBORS-CHARLESTON,                                   S.       C., DISTRICT                  449
   The existing project was adopted by the River and Harbor Act of
July 25, 1912 (H: Doc. No. 782, 61st Cong., 2d sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-Several landings for loading pulpwood are
located along the creek. These facilities are considered sufficient for
present and prospective commerce.
   Operations and results dwring fiscal year.-There were no opera-
tions or expenditures during the fiscal year.
   Condition at end of fiscal year.-The existing project was completed
in 1913. The creek was cleared of obstructions during October and
November 1939, for the movement of pulpwood after long years of no
commercial navigation. No recent surveys have been made. Commer-
cial users report that the channel should be snagged at several
locations.
   The costs and expenditures of the existing project to the end of the
fiscal year have been $12,050 for new work and $3,750 for maintenance,
a total of $15,800.
   Proposed operations.-The balance unexpended June 30, 1944,
$1,000, will be applied to maintenance snagging, as required, from the
mouth to the Hemingway bridge, mile 11, with U. S. snagboat Wateree
and hired labor September 14-21, 1944.
   It is not expected that maintenance funds will be required during
the fiscal year 1946.
                                         Cost and financial summary
Cost of new work to June 30, 1944 -----------------------------                                                        $29, 050
Cost of maintenance to June 30, 1944_---------                ---                                                         4, 350
          Total cost of permanent work to June 30, 1944---------------                                                   33, 400

Net total expenditures_ ____----------------------------------------33,                                                       400
Unexpended balance June 30, 1944 _-     ---                                                                                1, 000
          Total amount appropriated to June 30, 1944-----------------                                                    34, 400

   Fiscal year ending June 30               1940               1941             1942                     1943            1944

C ost of new work .- . . . . . . . . . . . . . . . . . . . . . . . . . . .-                                 .- -.            -
Cost of m aintenance       - - -           $2, 856.96 -- - - - - - --       -   - - - - --         - -    - - - --   - - - - - - -

Total expended------------------            3,000.00 --                                        -

Allotted .............-------------------- -------------   -           --           $1, 500                -$500


Balance unexpended July 1, 1943                                                                                          $1, 000
Balance unexpended June 30, 1944__---                                 -----------                                         1,000

         6. WATERWAY FROM WINYAH BAY TO CHARLESTON, S. C.

  Location.-The route of the waterway follows creeks, sounds, rivers,
bays, and extensive marshland cuts beginning at a point 8 miles below
Georgetown in Winyah Bay to Charlestown Harbor. The route is tidal
throughout and is sheltered from the sea. The distances from
Charleston to McClellanville, Winyah Bay, and Georgetown are 37
miles, 57 miles, and 65 miles, respectively. (See U. S. Coast and Geo-
detic Survey Charts, Nos. 836 and 837.)
  Existing project.-This provides for a channel 12 feet deep at mean
low water and 90 feet wide at bottom between Charleston Harbor and
         616634---45----29
450           REPORT OF CHIEF OF ENGINEERS, U.                            S. ARMY,        1944

Winyah Bay, 54 miles, with a branch channel of the same dimen-
sions to McClellanville. The mean tidal range is 3.3 to 5.1 feet,
according to locality.
   The estimate of cost for new work, revised in 1937, was $2,326,000,
and the latest (1937) approved estimate for annual cost of main-
tenance is $57,500., f
   The existing project was authorized by the following river and
harbor acts:

      Acts                         Work authorized                                  Documents



Sept. 19,1890     Channel from Minim Creek to Winyah Bay ..- Annual Report, 1889, p. 1184.
June 13, 1902     Channel from Charleston to a point opposite          H. Doc. No. 84, 56th Cong., 1st sess.,
                   McClellanville.                                       and Annual Report, 1900, p. 1908.
Mar. 2,1907       Branch channel to McClellanville_    -------------   Annual Report, 1903, p. 1133.
Mar. 2,1919       Extending the channel to Minim Creek, thence         H. Doc. No. 178, 63d Cong., 1st sess.
                    through the Estherville-Minim Creek Canal to
                   Winyah Bay.
Mar. 3, 1925      Cut across the Santee Delta at Four Mile Creek__     H. Doe. No. 237, 68th Cong., 1st sess.
Aug. 30,19351     Enlarging the channel from Winyah Bay to             Rivers and Harbors Committee Doe.
                    Charleston, including the branch channel to          No. 11,72d Cong., 1st sess.
                   McClellanville, to depth of 10 feet and bottom
                    width of 90 feet.
Aug. 26, 1937     For present project dimensions----............       Rivers and Harbors Committee Doc.
                                                                                                      2
                                                                         No. 6, 75th Cong., 1st sess.


1Included      in Public Works Administration program Sept. 6, 1933.
2   Contains latest published maps.          .

   Local cooperation.-Fully complied with.
   Terminal facilities.-Onthe waterway approximately 5 and 10 miles,
respectively, south of McCle-llanville there are wharves used for the
receipt of oysters and shipments of oyster shells and for shipments
of pulpwood. At McClellanville, on the branch channel, there are
located three wharves used for the receipt of oysters, shipments of
pulpwood, and for the loading and unloading of supplies. On con-
necting tributaries there are located privately owned wharves. These
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-Project dimensions were
restored in Duck Creek and in the Estherville-Minim Creek Canal by
U. S. pipe-line dredge Colonel G. P. Howell and U. S. snagboat
Wateree, removing 180,003 cubic yards of material at a cost of
$34,497.37 for maintenance.
   The channel was widened along the southerly side in the east-ap-
proach to The Cove bridge and along the northerly side in the west
approach by U. S. pipe-line dredge Colonel 0. P. Howell, removing
39,824 cubic yards of material at a cost of $8,242.89, for maintenance.
   A mooring berth was dredged alongside the channel approximately
1/4 mile east of The Cove bridge by U. S. pipe-line dredge Colonel
G. P. Howell, removing 21,270 cubic yards of material at a cost of
$6,357.19 for maintenance. Six 12-pile tie-up dolphins were con-
structed by contract in this mooring berth at a cost of $3,297.77 for
maintenance.
         RIVERS AND HARBORS               CHARLESTON,              S. C.,   DISTRICT      451
   Damaged piles and dolphins were removed, new guide dolphins con-
structed, and existing guide dolphins strengthened along the channel
in the approaches to The Cove bridge; and three mooring buoys were
placed in Hog Island Channel on the Charleston side of the bridge by
U. S. snagboat WVateree at a total cost of $9,391.51 for maintenance.
   Project dimensions were restored in Bullyard Sound by the pipe-
line dredge Cherokee, under contract, removing 75,392 cubic yards of
material at a cost of $10,675.84 for maintenance.
   Costs of preliminary work in connection with dredging to be done
during fiscal year 1945 were $2,580.91 for maintenance.
   The cost of surveys and supervision was $12,639.06 for maintenance.
The total costs during the year were $88,353.95 for maintenance. The
expenditures were $79,105.45.
   Condition at end of fiscal year.-The project was completed in
1940. An examination during June 1944 showed that project dimen-
sions obtained, except that shoals are found along the edges of the
cut and very soft bottom is found at a depth of approximately 10
feet in a 2-mile reach at the Winyah Bay end of the Estherville-Minim
Creek Canal; a 1/-mile reach just south of Minim Creek; a short reach
in Four Mile Creek; and 1/2-mile reaches in Mathews Creek. Harbor
River, Graham and Clauson Creeks. This shoaling does not materially
interfere with navigation.
   A center line survey during June 1944, in the branch channel to
McClellanville, showed a controlling depth of 6.5 feet at mean low
water.
   The costs to the end of the fiscal year for new work have been
$806,047.12 from regular funds and $1,262,080.87 from Public Works
funds, a total of $2,068,127.99. The costs to the end of the fiscal year
for maintenance have been $1,615,214.63 from regular funds, $13,308.01
from Public Works funds, and $54,915.78 from Emergency Relief
funds, a total of $1,683,438.42. The total cost for all work has been
$3,751,566.41. The expenditures have been $2,489,276.37 from regular
funds, $1,207,165.09 from Public Works funds, and $54,915.78 from
Emergency Relief funds, a total of $3,751,357.24.
   Proposed operations.-The balance unexpended June 30, 1944, $51,-
882.30, together with $45,000 allotted July 3, 1944, a total of $96,882.30
will be applied as follows:
Accounts payable July 1, 1944----------------------------------                        $209. 17
Maintenance:
    Dredging by contract to restore project dimensions in a 23-mile
      reach from the Winyah Bay end of the Estherville-Minim
      Creek Canal to a point 2 miles south of McClellanville, July
      12, to Oct. 24, 1944_
                         ---------------------------         _ _      51, 673. 13
    Dredging by contract, as may be required, to restore project
      dimensions between McClellanville and Charleston, including
      the branch channel to McClellanville, Jan. 1, to Feb. 4, 1945_- 45, 000. 00

        Total for all work   .----------------------------------                  96, 882. 30

  The additional sum of $57,500 can be profitably expended during
the fiscal year 1946, in maintenance dredging by contract to restore
project dimension, as may be required, from Winyah Bay to Charles-
ton, S. C., including the branch channel to McClellanville, September
1-30, 1945, and March 1-31, 1946.
452           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                1944

                                    Cosy and financial summary

Cost of new work to June 30, 1944__-- ------------------      $2, 068, 127. 99
Cost of maintenance to June 30, 1944-----------------------1,     683, 43&8. 42
      Total cost of permanent work to June 30, 1944----------                                          3, 751, 566. 41
Minus accounts payable June 30, 1944--------------------------209.                                                  17
      Net total expenditures- -------------------------     3, 751, 357. 24
Unexpended balance June 30, 1944_--------------------------     51, 882. 30

           Total amount appropriated to June 30, 1944------------                                      3, 803, 239. 54


   Fiscal year ending June 30            1940            1941               1942                1943                     1944

Cost of new work                     $219,637. 70
                           .-------------             $212,849.69     ........              .......           .......
Cost of maintenance-- ---------... -   12, 900. 95      41,094.12          $33, 533. 59      $473, 924. 00              $88,353.95

                      ..
      Total cost--------------         232, 538. 65    253, 943.81        33, 533. 59        473, 924.00                 88, 353.95

Total expended----. ____.......        174, 091.08     320, 014. 36       29, 565. 83        488, 728. 86                79,105.45

Allotted    .... ---------   ----       35,600.00     -45,000.00          57, 500. 00        540, 970.00                 10,000.00


Balance unexpended July 1, 1943__ ----------------                                                       $120, 987. 75
Amount allotted from War Department Civil Appropriation Act
 , approved June 2, 1943        "-----------------------------10,                                                        000. 00

       Amount to be accounted for-- -------                                        -----                     130, 987. 75
Gross amount expended_ --------------                                         $99, 014. 18
Less reimbursements collected ------------------                               19, 908. 73
                                                                                                              79, 105. 45

      Balance unexpended June 30, 1944 ---------------------                                                  51, 882. 30
Outstanding liabilities June 30, 1944_ ---------   -------                                                    45, 850. 07

     Balance available June 30, 1944_                      ------               --------                       6,032.23
Amount allotted in July 1944__ ------------                                       -------                     45, 000. 00

           Amount available during fiscal year 1945                   ---------------                         51, 032. 23
                                                              year ending
                                - - - - - - - - -in- -fiscal
Amount that can be profitably expended
June 30, 1946, for maintenance
                                                       - - - - - - - - -- - - - --                           57, 500. 00
  1 Exclusive of available funds.

                                     7. SANTEE RIVER, S. C.

   Location.-This river is formed by the confluence of the Congaree
and Wateree Rivers, about 29 miles southeast of Columbia, S. C. It
flows generally southeast for 143 miles and enters the Atlantic Ocean
about 45 miles northeast of Charleston Harbor.       (See UI. S. Coast
and Geodetic Survey Chart No. 1238 and U. S. Geological Survey map
of South Carolina, 1929.)
   Previous projects.-Adopted by River and Harbor Act of March
3, 1881. For further details of previous projects see page 1808 of
Annual Report for 1915, and page 558 of Annual Report for 1938.
   Existing project.---This provides for snagging the entire river.
The plane of reference for the lower river is mean low water, the
        RIVERS   AND HARBORS-CHARLESTON,        S.   C.,   DISTRICT   453
mean tidal range at the mouth being 4.5 feet. Tidal action extends
to Lenuds Ferry, 38 miles above the mouth. During June 1941, the
river was closed to navigation at Wilsons Landing, 87 miles above the
mouth, by the construction of the Santee Dam by the South Carolina
Public Service Authority. There is no approved estimate of cost for
annual maintenance.
    The existing project was adopted by the River and Harbor Act
approved September 19, 1890 (Annual Report for 1889, p. 1184).
    Terminal facilities.-There are no terminal facilities along the
river; however there are two landings used for loading pulpwood on
Wadrnecon River, a tributary entering Santee River approximately 20
miles above its mouth. In the tidal reach there are several privately
owned landings which are used infrequently.
    Operations and results during fiscal year.-There were no opera-
tions or expenditures during the fiscal year.
    Condition at end of fiscal year.-During June 1941, the river was
coastal Waterway crossing at mile 7 is approximately 9 feet; thence
of the Santee Dam of the Santee-Cooper hydroelectric project. The
controlling depth in the 12 miles of the stream next above the Intra-
coastal Waterway crossing at mile 7 is approximately 9 feet; thence
4 feet to Lenuds Ferry, 31 miles above the waterway crossing. The
head of the tidal reach is at river mile 48, about 10 miles upstream
from Lenuds Ferry. The controlling depth from Lenuds Ferry to
Santee Dam, a distance of approximately 49 miles, has been reduced
to probably no more than 2 feet by the diversion of the waters to the
Pinopolis Reservoir and Cooper River. The flow passing the dam has
on occasions been reduced to 500 cubic feet per second, the minimum
flow permitted under the terms of the Federal Power Commission
license. Upon completion of the new bridge on U. S. Highway No.
52 crossing .the tail canal, and the removal of the present temporary
pile-trestle detour bridge across the canal, probably by January 1945,
navigation from Santee River above the dam to the seacoast will be
restored. Navigation from the seacoast at Charleston to points on
the Santee River above the dam will be possible via the Cooper River
and the Santee-Cooper project.
   The costs and expenditures of the existing project to the end of
the fiscal year have been $174,844.49 for maintenance.
   Proposed operations.-The balance unexpended June 30, 1944, $1,-
447.18, will be applied to maintenance snagging and possibly to the
removal of sandbars, as required, from the crossing of the Intracoastal
Waterway, mile 7, to the mouth of Wadmecon River, a tributary
entering Santee River approximately 20 miles above its mouth, with
U. S. snagboat Wateree and hired labor, September 22, to October 3,
1944.
   The additional sum of $2,000 can be profitably expended during the
fiscal year 1946 in maintenance snagging, as required, from the Intra-
coastal Waterway crossing, mile 7, to the mouth of Wadmecon River,
mile 20, with U. S. snagboat Wateree and hired labor, October 25, to
November 10, 1945.
454            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

                                                     Cost and financial summary
Cost of new work to June 30, 1944_---------                                                            ----            $99, 750. 00
Cost of maintenance to June 30, 1944 -------------------                                                               174, 844. 49
           Total cost of permanent work to June 30, 1944------------                                                   274, 594. 49
Net total expenditures _-----------------274,                                                                                 594.49
Unexpended balance June 30, 1944--                                  ___           -----------                               1,447. 18
          Total amount appropriated to June 30, 1944--------                                                           276, 041. 67

   Fiscal year ending June 30                          1940                1941                 1942      1943                   1944

C ost of new w ork .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cost of maintenance            .                 $3, 951.08
                                      .-----------                        $3, 642. 77                    $1,176. 84     -               --
Total expended ................                        3, 951. 08          3, 642. 77                     1, 176. 84        _
Allotted .      ...............------------------      3, 000. 00          4, 600. 00 --------------    -1, 400.00      ..       ....


Balance unexpended July 1, 1943_ ________                                                                               $1, 447. 18
Balance unexpended June 30, 1944_ __------                                                             -____             1, 447. 18
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance1 -  -  - - - - -    - - - - -  - - - -
                                                                                                                            2, 000.00
  1 Exclusive of available funds.

                                                    8. CONGAREE RIVER, S. C.

   Location.-This river is formed by the confluence of the Broad and
Saluda Rivers at Columbia, S. C., and flows southeasterly 50 miles,
there uniting with the Wateree River to form the Santee River. (See
U. S. Geological Survey map of South Carolina, 1929.)
   Existing project.-This provides for a 4-foot navigable channel
over the lower 49 miles of the river, to be secured by dredging and
bank protection, and for the construction of a lock and dam to ex-
tend deep water to Gervais Street Bridge, Columbia, S. C. The
variation in water surface due to freshets is about 24 feet at the mouth
of the river and about 39 feet at Columbia, the plane of reference
being ordinary low water.
   The estimate of cost of new work, revised in 1925, is $514,000. The
latest (1928) approved estimate of annual cost of maintenance is
$5,200, including $200 for operation and care of the lock and dam.
   Data concerning the lock and dam are as follows:
   Location 2 miles below Gervais Street, Columbia, S. C., 47 miles above mouth
of river.
                                                                                                                                        Feet
     Length between miter sills_--                  --------------                                                                      170
     Clear width ---------------------------------------------------                                                                     55
     Lift------------------------------------------------------                                                                          10
     Depth of miter sills at low water_---                     -------------                                                              -6
Character of foundation, ledge granite.
Kind of dam, movable. Chanoine wickets.
Original structure completed, 1904; alterations, 1914.
Cost to date:
     Original structure_ ---------------------------------------             $225,                                                      000
     Alterations ---------------------------------------------                 56,                                                      000
     Total----------------------------------                                                                                    281, 000
Completed, 1914.
               RIVERS      AND HARBORS-CHARLESTON,                       S.   C.,   DISTRICT           455
  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                  Documents



Aug.     5, 1886   Improvement of the lower 49 miles_     -- -H.         Ex. Doc. No. 254, 48th Cong., 2d
                                                                       sess., and Annual Report, 1885, p.
                                                                       1140.
Mar.     3,1899    Construction of lock and dam      -         -     H. Ex. Doc. No. 66, 53d Cong., 2d sess.
                                                                       and Annual Report, 1896, p. 1183.
June 25, 1910      Rebuilding the dam and raising the crest   ---    H. Doc. No. 608, 61st Cong., 2d sess.
Aug. 8, 1917      Bank protection_    _          -.               _H.   Doe. No. 702, 63d Cong., 2d sess.
June 26, 19341     Operating and care of lock and dam provided for
                    with funds from War Department appropria-
                    tions for rivers and harbors.


  1 Permanent Appropriations Repeal Act.

    Terminal facilities.-There are no public terminals on the river.
The Gulf Oil Corporation has leased the Government reservation at
the lock and dam site, near Columbia, and has constructed an oil
terminal thereon for their use, but the movement of petroleum prod-
ucts to this terminus has been temporarily discontinued. There are
several landings along the river which were formerly used for han-
dling logs and veneer timbers.
    Operations and results during fiscal year.-There were no opera-
tions during the fiscal year.
    Operating and care of lock and dam across Congaree River near
Columbia, S. C.-Ordinary repairs were made during the year by hired
labor for maintenance and preservation of property at a cost of
 $513.22. The costs and expenditures during the year were $513.22 for
maintenance and operating and care.
    Condition at end of fiscal year.-That portion of the existing proj-
ect which covers dredging and bank protection has been approximately
71 percent completed for many years, the work remaining consisting
of revetting approximately 20,000 feet of banks in the vicinity of
Congaree and Gill Creeks, beginning about 5 miles below Columbia.
A survey in 1936, the only survey in recent years (commerce since
1925 having been but a small amount in 1937 to 1939, inclusive), and
an examination in April 1940 showed that the controlling depth from
the mouth to the lock and dam at Columbia, S. C., is 5.5 feet, except
during the low-water stage resulting from the week-end shut-down
of upstream power plants, when the controlling depth is 1.5 feet.
    The portion of the project covering the lock and dam has been
completed, as described in paragraph "Existing project." The lock
and dam were placed out of commission in August 1920, and the build-
ings and grounds are being leased.
   SThe costs to the end of the fiscal year have been $364,823.87 for new
work, $2,325.82 for operating and care, and $390,559.51 for mainten-
nance, a total of $757,709.20. The expenditures have been $757,709.20.
In addition the sum of $109,833.10 was expended between August 7,
1906, and June 30, 1935, on the operation and care of the works of
improvement under the provision of the permanent and indefinite
appropriation for such purposes.
456         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

   Proposed operations.-The balance unexpeided June 30, 1944,
$41.44, together with $200 allotted July 3, 1944, a total of $241.44, will
be applied to maintenance and protection of property at the lock and
dam, July 1, 1944, to June 30, 1945.
   The additional sum of $200 can be profitably expended during the
fiscal year 1946 for maintenance and protection of property at the lock
and dam.
                                     Cost and financial summary
                                 --------------------------
Cost of new work to June 30, 1944_                                                                         $364, 823. 87
Cost of maintenance to June 30, 1944_-------             ---                                                502, 718.43

         Total cost of permanent work to June 30, 1944------------                                            867, 542. 30

Net total expenditures-________-------------                   867, 542. 30
Unexpended balance June 30, 1944 -----------------------------       41.44

         Total amount appropriated to June 30, 1944--------------                                             867, 583. 74

   Fiscal year ending June 30          1940             1941                1942                  1943             1944


Cost of new w ork .-                     -    --.--.- .--.
                                                    .-.  - --. .--..                 .   . .. .     . .. .
Cost of maintenance    ......   ..    $5, 877. 79        $107.90             $126.12                $26. 16         $513.22

                     ....
Total expended -----------------       5,874.11           111.58                140.40               11.88           513.22

Allotted_-----------------------       5,200.00           500.00   ---------------                5, 300.00           350,00

Balance unexpended July 1, 1943__                       -__                                                       $204. 66
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941..                                                                                          350. 00
       Amount to be accounted for                                                                                  554. 66
Gross amount expended ---------------------------                                          $518. 33
Less reimbursements collected_    - ---------                                                 5. 11
                                                                                                                   513. 22

     Balance unexpended June 30, 1944-----------------------                                                        41. 44
Amount allotted in July 1944.---------------------------------                                                     200. 00
         Amount available during fiscal year 1945--- -------                                                       241. 44
Amount (estimated) required to be appropriated for completion of
existing project 1 -------------------------------      --------.                                            149,000.00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance '---------------------------------                                                      200. 00
  1Exclusive of available funds.

                                9. CHARLESTON HARBOR, S. C.
   Location.-On the coast of South Carolina, about 15 miles southerly
of the middle point of the coast line, 50 miles southwest of Winyah
Bay, S. C., and 80 miles northeast of the mouth of the Savannah River.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1239 and 470.)
   Previous projects.-Adopted by River and Harbor Acts of August
30, 1852; June 18,1878; August 11, 1888; March 3,1899; June 25, 1910;
August 8, 1917; and July 18, 1918.
   For further details see page 1808, Annual Report for 1915; page 579,
Annual Report for 1926; page 562, Annual Report for 1938.
   Existing project.-Thisprovides for commercial purposes a channel
35 feet deep, 1,000 feet wide from the sea to the inner end of the jetties,
thence 600 feet wide to Town Creek, thence 500 feet wide through Town
Creek, thence 600 feet wide to the navy yard, and thence 400 feet wide
to Goose Creek, with a turning basin 700 feet wide at the Port Ter-
              RIVERS AND HARBORS-CHARLESTON,                                  S. C.,   DISTRICT           457
minals, together with a channel 30 feet deep, 600 feet wide in Cooper
River around the east and north sides of Drum Island; also a channel
in Shem Creek 10 feet deep and 110 feet wide from a flared entrance
from Hog Island channel to and including a turning basin 130 feet
wide and 400 feet long with the upper end 250 feet upstream of the
Mount Pleasant public wharf.
   The estimate of cost for new work, revised in 1912, is $1,212,000
exclusive of amounts expended under previous projects. The latest
 (1941) approved estimate of cost for annual maintenance is $85,000.
   The existing project includes the maintenance of two entrance
jetties completed in 1895 under previous projects. These jetties are
of stone on log mattress foundation, the north jetty 15,443 feet long
and the south jetty 19,104 feet long; the distance between their axes
at the outer end is 2,900 feet. The height as originally built, except
the submerged inner portions and the gap left in the south jetty,
was 12 feet above mean low water for the greater part of their length.
   The Chief of Engineers authorized 35 feet depth for 600 feet width
in Cooper River around the north and east side of Drum Island on
July 23, 1942.
   The project also provides for a 40-foot channel 1,000 feet wide
from the sea to the inner ends of the jetties, described above, thence
600 feet wide to the south pier at the navy yard, and thence 1,000 feet
wide to the commandant's wharf, at an estimated first cost of $3,603,000
and $250,000 annually for maintenance, both figures being additional
to the estimates for the commercial project given above, and that it
be considered as a national-defense rather than a commercial measure
and be prosecuted only as found necessary in the interest of national
defense.
   The mean tidal range is 5.2 feet, though this is increased to 7 or 8
feet under the influence of northeast winds or storms of long duration.
   The existing project was authorized by the following river and har-
bor acts:

       Acts                         Work authorized                                    Documents



June 18,1878      2 jetties 1_ ___ ____-_-_____.__
                                     _ _              ________   __   _   Annual Report, 1878, pp. 553-572.
Aug.     8,1917   Increase in depth to 30 feet with width of 500 feet     H. Doc. No. 288, 62d Cong., 2d sess.
                    between the jetties and 1,000 feet seaward there-
                    of.
July    18,1918   The 40-foot channel to the navy yard. (Act pro-         H. Doc. No. 1946, 64th Cong., 2d sess.,
                   vided that the 40-foot channel should not be            pt. I, pp. 21-29, 57, 58, and 64-68.
                    undertaken "until the proposed new drydocks
                    at this navy yard, carrying a depth of 40 feet of
                    water over the blocks, has been authorized."
                    This dock was authorized in the Naval Appro-
                    priation Act approved July 1, 1918 (40 Stat. L.
                    725).)
Jan. 21, 1927     Present project dimensions of the channels for          H. Doe. No. 249, 69th Cong., 1st sess.
                   commercial purposes, and for the present proj-           (Contains latest published maps.)
                   ect widths of the 40-foot channel which was au-
                   thorized as a national-defense measure.
Oct. 17, 1940     The 35-foot channel depth from the sea to the           H. Doe. No. 259, 76th Cong., 1st sess.
                   head of the project via Cooper River and Town
                    Creek, also a channel in Shem Creek to Mount
                    Pleasant, 110 feet wide and 10 feet deep, includ-
                    ing a turning basin at the upper end.

  1Completed      under previous projects.
458     REPORT OF CHIEF OF ENGINEERS, U. S.       ARMY,   1944

   Recommended modifications of project.-Under date of January 23,
1941, the Chief of Engineers recommended the modification of the
existing national defense project to provide an anchorage area 30 feet
deep in the water area between Castle Pinckney and Fort Moultrie,
at an estimated first cost of $1,820,000, with $12,500 annually for
maintenance in addition to the amounts now authorized. (H. Doc.
156, 77th Cong., 1st sess.)
   Local cooperation.-The project authorized in the River and Harbor
Act of October 17, 1940 (H. Doc. No. 259, 76th Cong., 1st sess.), is
subject to the requirements that local interests furnish, free of cost to
the United States, suitable spoil-disposal areas as and when required
for initial work and for subsequent maintenance. All prior require-
ments have been fully complied with.
   Terminal facilities.-Piersand slips extend for about 1 mile along
the eastern water front of the city of Charleston, and aft additional
mile is covered by marginal wharves. The Port Utilities Commission
of the city of Charleston owns the terminals at Columbus Street, a
large pier near Market Street, and two piers at Tradd Street. It also
owns and operates the belt-line railway serving all wharves and ware-
houses and connecting with trunk lines entering the city. Its wharves
are open to the public on a charge'basis. Modern facilities exist also at
the coal pier of the Southern Railway and at the wharves of the
Standard Oil Co., the Charleston Shipbuilding & Dry Dock Co., the
Clyde Steamship Co., the Seaboard Air Line Railway Co., the South-
ern Railway Co., and the Concentration Warehouse & Compress Co.
   On Cooper River above the navy yard a compress and warehouse
company has a marginal wharf 750 feet long; and the Texas Corpora-
tion, the Sinclair Refining Co., and the Davison Chemical Co. main-
tain piers at their property. The facilities are considered adequate
for existing commerce. For further details, see Port Series No. 9,
revised 1940, Corps of Engineers.
   Operations and results during fiscal year.-Maintenance.-Project
depth was restored at five shoaled reaches in Cooper River, between
the north end of Drum Island and the head of the project, by the pipe-
line dredge Washington, under contract, which removed 662,623 cubic
yards of material at a cost of $134,872.75.
   Substantially project depth for about 600 feet width was restored
in the outer 6.5 miles of the entrance channel early in the fiscal year
by the U. S. hopper dredge Culebra, which removed 736,327 cubic
yards of material at a cost of $105,016.44. On May 22, 1944, the
Culebra commenced dredging to restore project dimensions in the en-
trance channel at a short shoaled reach 4.2 miles seaward of the outer
ends of the jetties, and to the end of the fiscal year had removed 67,516
cubic yards of material at a cost of $14,604.68; during the same period
this dredge also removed, by agitation, 441,389 cubic yards of mate-
rial from four shoaled reaches in lower Cooper River, at a cost of
$38,673.74.
   In addition, cost of preliminary work for contract 'dredging pro-
posed during fiscal year 1945 was $257.93. The cost of surveys and
supervision was $9,472.08. The total cost during the year was $302,-
897.62 for maintenance. The expenditures were $300,994.48.
        RIVERS   AND   HARBORS-CHARLESTON,        S.   C.,   DISTRICT   459
   Condition at end of fiscal year.-The jetties protecting the entrance
channel across the bar were completed in 1895. These jetties are de-
scribed in the "Existing project" paragraph.
   That portion of the existing project comprising the entrance and
South Channels has been about 83 percent completed. Dredging in
this portion of the channel was terminated on September 4, 1942, for
the duration of the war, after project depth had been secured for ap-
proximately project width in the outer 4.2 miles of the project, and
project depth for 600 feet width only between the jetties. The new-
work dredging in South Channel was never performed. That portion
of the existing project comprising Cooper River and Town Creek
Channels was completed in 1942. The 35-foot channel around the
north and east sides of Drum Island was completed in 1942.
   Surveys at the end of the fiscal year in the entrance channel and
outer harbor, from the sea to the lower end of Cooper River opposite
Castle Pinckney, 12.1 miles, via the natural deep-water bypass channel
around the intersection of the Mount Pleasant and South Channel
ranges, authorized by the Chief of Engineers on March 27, 1942,
showed a controlling depth at mean low water of 33 feet for a central
width of not less than 550 feet, with 30.8 feet and 30.4 feet depth on
the left and right 1,000-foot channel ranges, respectively, in the outer
4.2 miles of the project.
   Surveys at the end of the fiscal year in Cooper River, from its lower
end opposite Castle Pinckney to the Bodne Oil Co. wharf, 9 miles,
showed a controlling depth at mean low water of 35 feet for a central
width of not less than 250 feet, with 24 feet and 31 feet depths on the
left and right channel ranges, respectively, for channel widths ranging
from 600 feet in the lower 8.4 miles to 400 feet in the upper 0.6 mile,
exclusive of widenings; thence to within 400 feet of the upper end of
the project, 2.4 miles, a controlling depth of 32 feet for 400 feet width;
and in the remainder of the channel, a controlling depth of 30 feet for a
central width of 200 feet; except for 3 shoals (removal commenced by
Culebra May 22, 1944) in a reach between the north enl of Drum
Island and 2.8 miles upstream from the mouth of Shipyard River, over
which the controlling depth was 33 feet for a central width of not less
than 250 feet.
   A survey at the end of the fiscal year in Town Creek showed a con-
trolling depth at mean low water of 30 feet for a central width of about
200 feet.
   An examination at the end of the fiscal year in Shem Creek showed
a navigable depth of not less than 6 feet for 75 feet width.
   The cost of the existing project has been $1,494,964.34 from regular
fuids and $57,813.37 from Public Works funds, a total of $1,552,777.71,
for new work, and $1,010,099.26 from regular funds and $56,086.63
from Public Works funds, a total of $1,066,185.89 for maintenance, a
grand total of $2,618,963.60.
   The expenditures have been $2,502,990.27 from regular funds and
$113,900 from Public Works funds, a total of $2,616,890.27. In addi-
tion, $600 from contributed funds was expended for maintenance.
460             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                               1944

  Proposed operations.-The balance unexpended June 30, 1944.
$32,417.82, and accounts receivable, $807.78, together with $571,100 al-
lotted July 3, 1944, a total of $604,325.60, will be applied as follows:
Accounts payable June 30, 1944 ------------------------------            $2, 881. 11
Maintenance:
    Completion of dredging to restore project depth for safe navi-
      gable widths at a shoal lying 4.2 miles seaward from the outer
      ends of the jetties, and at critical shoals in Cooper River, with
      U. S. hopper dredge Culebra and hired labor, July 1-31, 1944--     42, 000. 00
    Dredging to restore 35 feet depth for 1,000 feet width from the 35-
      foot contour in the ocean to the outer ends of the jetties,
      thence 800 feet width between the jetties, except a mile reach
      4,000 feet inside the outer ends of the jetties where the width
                                                                                           Y
      will be restricted to 600 feet, with U. S. hopper dredge Cu-
      lebra and hired labor, Aug. 1, 1944, to Jan. 20, 1945--- ----     238, 000. 00
    Dredging by contract to restore substantially project dimen-
      sions in Cooper River and Town Creek channels from their
      lower junction to the head of the project, Aug. 20, 1944, to
      Feb. 20, 1945_ --------------------------------------             242,400.00
    Dredging by contract in Shem Creek to restore 8 feet depth for
      a navigable width of 80 feet from the mouth to the public
      wharf, Oct. 1-6, 1944 ----------------------------------            5, 000.00
    Dredging by contract, as required, to maintain project dimen-
      sions in Cooper River and Town Creek, May 1 to June 30, 1945 74, 044. 49

                Total for all work---------------------------                                                    604, 325. 60
  The additional sum of $150,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
        Dredging by contract to restore project dimensions, as required,
          in Cooper River and Town Creek channels, Jan. 1, to Mar. 31,
          1946 -----------------------------------------------               $108, 000
        Dredging, as required, to restore project dimensions in the entrance
          channel with U. S. hopper dredge Culebra and hired labor, or other
          United States hopper dredge of similar capacity, May 1-31, 1946      42, 000
                Total of all work------------------------------------150,                                                    000
                                                 Cost and financial summary
Cost of new work to June 30, 1944------------------------                                               $8, 139, 232. 82
                                   ----------------------
Cost of maintenance to June 30, 1944_                                                                   1 1, 468, 175. 39
       Total cost of permanent work to June 30, 1944---- - - - -                                           9; 607 46& 21
Plus.accounts recei ahble Junie 30, 1944-----------------------                                            -      807. 78
      Gross total costs to June 30, 1944-- - - - - - - - - - - - - - - - 9, 608, 215. 99
Minus accounts payable June 30, 1944------------------------                  2, 881. 11
      Net total expenditures ----------------------------  1 9, 605, 334. 88
Unexpended balance June 30, 1944--------------------------       32, 417. 82
            Total amount appropriated to June 30, 1944----_-- - ---                                        9, 637, 752. 70


    Fiscal year ending June 30                      1940            1941            1942            1943              1944

Cost of new work ............................           _        $136, 280.72    $815, 494.03    $238, 742. 27   -...---- --
Cost of maintenance.............                  $26, 204.92        1, 554.62     13,639.67       30, 779.07       $302,897.62

       Total cost---------------
                 ................--                26,204.92      137, 835. 34    829,133.70     269, 521.34         302, 897.62
Total expended ....             ..........         49, 684. 62    123, 750. 67    861, 051. 99   246, 974. 20        300, 994. 48
Allotted.........................                  30, 400. 00    441, 000. C0    679, 300. 00    256, 000. 00       110, 000. 00
  1In addition $600 was expended                from contributed funds for maintenance.
            RIVERS     AND HARBORS-CHARLESTON,                          S.    C.,   DISTRICT           461
Balance unexpended July 1, 1943---------------------------                                 $223, 412. 30
Amount allotted from War Department Civil Ap-
  propriation Act approved May 15, 1936-------- $70, 000. 00
Amount allotted from First Deficiency Appropria-
  tion Act 1941, approved Apr. 1, 1941-  ----    40, 000. 00
                                                                                            110, 000. 00

       Amount to be accounted for_     -  ----------                                        333, 412. 30
Gross amount expended_------              ---        $326, 205. 44
                              ------------------- 25, 210. 96
Less reimbfirsements collected_
                                                                                            300, 994. 48
      Balance unexpended June 30, 1944---------------------                                     32, 417. 82
Outstanding liabilities June 30, 1944_ - - -----------                                           2, 881. 11
      Balance available June 30, 1944_-------                                       ---         29, 536. 71
Accounts receivable June 30, 1944_- -    --                     -----------                         807. 78
     Unobligated balance available June 30, 1944 - -30,                                          344. 49
Amount allotted in July 1944_- -------         ---------                                    571, 100. 00
           Balance available during fiscal year 1945----------------                        601, 444. 49

Amount (estimated) required to be appropriated for completion
  of existing project 2_- ______----------                      ---------                   185, 600. 00
Amount that can be profitably expended  in- fiscal- year ending
                                    - -                - -
June 30, 1946 for maintenance 2_ -                        __                                   150, 000. 0(
2 Exclusive of available funds.


                                     10. ASHLEY RIVER, S. C.

   Location.-Rises near Ridgeville, S. C., and flows southeasterly 40
miles, uniting with the Cooper River to form the harbor of Charles-
ton, S. C. (See U. S. Coast and Geodetic Survey Charts Nos. 1239
and 470.)
   Previous projects.-The original project was adopted by the River
and Harbor Act of June 14, 1880. For further details see page 1809,
Annual Report for 1915, and page 566, Annual Report for 1938.
   Existing project.-This provides for a channel 30 deep at mean
low water and 300 feet wide from the mouth to the Standard wharf,
a distance of 7.8 miles, suitably widened at bends and at the head
of the improvement; and for maintenance, to a depth of 12 feet and
a width of 100 feet, of the approach channel to the Municipal Yacht
Basin. The mean tidal variation is about 5.2 feet.
   The estimate of cost for new work, revised in 1937, was $391,150,
exclusive of the amount expended on previous projects. The latest
 (1937) approved estimate for annual cost of maintenance is $26,000<
   The existing project was authorized by the following river and
harbor acts:

    Acts                           Work authorized                                  Documents


July 25,1912   Channel 20 feet deep and 240 feet wide up to        Rivers and Harbors Committee Doc.
                Standard wharf.                                      No. 4, 62d Cong., 2d sess.
Aug. 26,1937   Enlarging channel to present projct dimensions      Rivers and Harbors Committee Doc.
                   d for maintesiance of entraSM channel to           No. 449, 74th Cong., 2d sess.    (Con.
                 Municipal Yacht Basin.                               tains latest published map.)
                I
462         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

   Local cooperation.-Fullycomplied with.
   Term nal facilities.-The facilities extend 51/2 miles above the
United States lighthouse wharf adjacent to Tradd Street and in-
clude the wharves of the American Agricultural Chemical Co.,
Planters Fertilizer & Phosphate Co., Wood Preserving Corporation,
and the Virginia-Carolina Chemical Co. The fertilizer company
wharves are equipped with mechanical unloading devices. These
terminals are considered adequate for existing commerce. There are
located at the Municipal Yacht Basin three docks of creosoted timber
construction for the accommodation of local and transit yachts. For
further details see Port Series No. 9, revised 1940, Corps of Engi-
neers.
   Operations and results during fiscal year.--There were no opera-
tions during the fiscal year. The cost for surveys and supervision
was $502.73 for maintenance. The expenditures were $446.20.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1940. A reconnaissance examination during June 1944
showed a controlling center-line depth of 26 feet at mean low water
from the mouth of the river to the Seaboard Air Line Railway bridge,
4 miles; thence in the 1 mile next upstream through the crossing shoal,
a controlling center-line depth of 17.5 feet (a cross-section at the
point of limiting depth showed 17 feet depth on the sides of the chan-
nel); thence to the head of the project, 2.8 miles, not less than project
depth. No vessels requiring more than 14 feet depth have used the
river since the commencement of the war.
   A survey of the entrance channel to the Municipal Yacht Basin
during June 1944 showed that there is a controlling depth of 5.5 feet
for a navigable width of 75 feet.
   The costs of the existing project to the end of the fiscal year have
been $255,496.41 for new work and $86,939.90 for maintenance, a total
of $342,436.31. The expenditures have been $342,379.78. In addi-
tion, $700 from contributed funds was expended for maintenance.
   Proposed operations.-The balance unexpended June 30, 1944, $11,-
589.47, together with $12,000 allotted July 3, 1944, a total of $23,589.47,
will be applied as follows:
Accounts payable June 30, 1944_---------------------------------     $56. 53
Maintenance:
   Dredging by contract to restore project dimensions in the entrance
      chaninel to the Municipal Yacht Basin, Sept. 15-30, 1944 _      7,000. 00
   Dredging by contract, if needed, to restore 20 feet depth at the
      crossing shoal immediately above the Seaboard Air Line
      Railway bridge, Mar. 1-15, 1945    ------------------------ 16, 532. 94
         Total for all work_ ---------------------------------- 23, 589.47
  The additional sum of $10,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging by contract to restore
project dimensions in the entrance channel to the Municipal Yacht
Basin, December 1-15, 1945.
                          Cost and financial summary
Cost of new work to June 30, 1944 --------------                              --   $260, 996. 41
Cost of maintenance to June 30, 1944       -                                         86, 939. 90

         Total cost of permanent work to June 30, 1944.                             347, 936. 31

Gross total costs to June 30, 1944_         _--          .--..         ----         347, 936. 31
I   In addition $700 was expended from contributed funds for maintenance.
               RIVERS           AND HARBORS-CHARLESTON,                                            S.    C.,     DISTRICT               463
Minus accounts payable June 30, 1944 ...                                                                                            $56. 53

           Net total expenditures                                             --------                                     1347, 879. ?8
Unexpended balance June 30, 1944_---------                                                                     ---               11, 589.47
           Total amount appropriated to June 30, 1944--------------                                                             359, 469. 25

    Fiscal year ending June 30                           1940             1941                 1942                1943              1944

Cost of new work----------                     . $132, 805.92 ...               .        .     .        .        ...        .....       ...
Cost of maintenance--            .--------.              8, 420.02     $14, 062. 63           $6, 399.95          $6, 204. 76          $502.73

       Total cost ----------------                    141, 225. 94       14, 062. 63           6, 399.95          6, 204. 76            502. 73

Total expended ...                   ....----------------171, 347.42     14, 031.29            6,515.98            6, 130.97            446. 20
Allotted -----------------..........---               111, 145.00         2, 000.00            8, 500.00         -7, 000.00         -4, 000.00


Balance unexpended July 1, 1943                                   _      -               -$16,                                       035. 67
Deductions on account of revocation of allotment                                                        -                         4, 000. 00

       Net amount to be accounted for                                                        ---                                 12, 035. 67
Gross amount expended               --                                                                      $463. 52
Less reimbursements collected                                                                                    17. 32
                                                                                                                      -              446. 20

           Balance unexpended June 30, 1944                                      ---                                             11, 589. 47
Outstanding liabilities June 30, 1944                                  -56.                                                                 53

     Balance available June 30, 1944                                          -11,                                                   532. 94
Amount. allotted in July 1944                                                                                                    12, 000. 00

           Amount available during fiscal year 1945-----------------                                                             23, 532. 94

Amount that can be profitably expended in fiscal year ending
   June 30, 1946 for maintenance 2 _                                                                  _ ___10,                       000. 00
  1 In addition $700 was expended from contributed funds for maintenance.
  2 Exclusive of available funds.

                                                11. SHIPYARD RIVER, S. C.

   Location.-This waterway is a salt-water tidal tributary of Charles-
ton Harbor, S. C. It has its source about one-half mile below the
United States navy yard, whence it flows in a southerly direction for
about 3 miles and empties into Cooper River about three-fourths of a
mile above Drum Island. (See U. S. Coast and Geodetic Survey
Chart No. 470.)
   Previous projects.-Adopted by River and Harbor Acts of July
25, 1912, and March 3, 1925.
   For further details of previous projects, see page 610, Annual Re-
port for 1932.
   Existing project.-This provides for a channel 30 feet deep at mean
low water and 200 feet wide, widened to 670 feet at the entrance
from deep water in Cooper River, to a point 100 feet above the Gulf
Oil Corporation's terminal, with a turning basin 30 feet deep at
the latter point, and for an extension of this channel 20 feet deep
and 100 feet wide, widened at bends, to a point 50 feet above the
remains of the former Tuxbury Lumber Co.'s wharf (now the prop-
erty of the Pittsburgh Metallurgical Co.). The mean tidal variation
is 5.2 feet.
464           REPORT OF CHIEF OF ENGINEERS, U.                                 S. ARMY,       1944


  The estimate of cost of new work, revised in 1937, exclusive of
tmounts expended on previous project, was $100,000. The latest
(1937) approved estimate of cost for annual maintenance is $25,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                       Documents


July     3,1930   Channel depths of 12 and 20 feet   ....---------------.   Rivers and HarborsACommittee Doe.
                                                                              No. 13, 71st Cong., 2d sess.
Aug. 30,1935      28-foot channel from Cooper River to the Gulf Oil         Rivers and Harbors Committee Doc.
                    Corporation's terminal, and the deepening of             No. 43, 73d Cong, 2d sess.
                   the channel above that point to 20 feet from the
               depth of 12 feet previously authorized without
               local cooperation.
Aug. 26,19371 Enlargement of the channel to a depth of 30 feet              Rivers and Harbors Committee Doe.
               and a width of 200 feet up to the Gulf Oil Cor-                No. 38, 75th Cong., 1st sess. (Con-
               poration's terminal with a turning basin 30 feet               tains latest published map.)
               deep at the latter point.


  SIncluded in Emergency Relief Administration program May 28, 1935.



   Recommended wmodification of project.-Modification of the exist-
ing project for Shipyard River, S. C., was recommentd by the Chief
of Engineers in a report requested by Rivers and Harbors Committee
Resolution adopted June 20, 1941, and transmitted to Congress by the
Secretary of War, June 15, 1942.
   Local cooperation.-Theproject authorized in the River and Harbor
Act of August 26, 1937, is subject to the requirement that local inter-
ests furnish, free of cost to the United States, necessary rights-of-way
and suitable spoil-disposal areas for new work and for subsequent
maintenance as required. All prior requirements have been fully
complied with.
   Ter ninalfacilities.-In the lower 3 4-mile, on the 30-foot channel, are
the large marginal wharves of the Gulf Oil Corporation and the Ship-
yard River Terminal Co., the latter handling chiefly fertilizer and
fertilizer materials. These wharves accommodate deep-draft, ocean-
going vessels. On the 20-foot channel are the North State Lumber
Co.'s wharf, one small privately owned wharf and the .ecently con-
structed Pittsburgh Metallurgical Co.'s wharf for the handling of
ores.
   Operations and results during fiscal year.-In the 20-foot channel
up to the Pittsburgh Metallurgical Co. wharf, 12 feet depth for proj.
ect width was restored by U. S. pipe-line dredge Colonel G. P. Howell..
which removed 194,588 cubic yards of material at a cost of $35,665.77.
In the 30-foot channel, project depth for approximately 150 feet
width was restored from the lower end of the channel in Cooper River
to the upstream end of and along the face of the Etiwan Fertilizer Co.
wharf by the pipe-line dredge Cherokee, under contract, which re-
moved 134,125 cubic yards of material at a cost of $1279.10. Diking,
under contract, in conjunction with the above maiitenance dredging
in the 30-foot channel costs $1,864.54. The Government cost of dredg-
ing and diking for the 30-foot channel and for preliminary work was
$4,553.49 for maintenance.
              RIVERS AND HARBORS-CHARLESTON,                                                                 S. C.,     DISTRICT                465

   The cost of surveys and supervision was $1,073.49 for maintenance.
The total cost during the year was $55,436.39 for maintenance. The
expenditures were $55,400.17.
   Condition at end of fiscal year.-The existing project was completed
in 1939. An examination with a depth finder during May 1944, along
the center line, showed controlling depths in the 30-foot channel as
follows: 30 feet extending 1,000 feet upstream from deep water in
Cooper River to within 200 feet of the upper end of the flared en-
trance; thence 19 feet to the lower end. of the Etiwan Wharf, with
15.5 feet at the lower end of turning basin and 14 feet thence to the
Gulf Corporation wharf; thence depths decreasing to 6 feet at the
upper end of the turning basin at the head of the 30-foot channel.
Depths along the center line in the 20-foot channel range from 6 feet
at the lower end to less than 1 foot at the upper end and head of the
project. Present commerce in the 20-foot channel does not warrant
an expenditure for maintenance at this time.
   The costs of the existing project to the end of the fiscal year have
been $81,260.39 from regular funds and $31,563.71 from Emergency
Relief funds, a total of $112,824.10 for new work; and $280,366.93
from regular funds for maintenance, a total of $393,191.03. The ex-
penditures have been $361,591.10 from regular funds and $31,563.71
from Emergency Relief funds, a total of $393,154.81.
   Proposed operations.-The balance unexpended June 30, 1944, $46,-
233.16, together with $15,00, allotted July 3, 1944, a total of $61,
233.16, will be applied as follows:
Accounts payable June 30, 1944                                                                -------------                                  $36. 22^
Maintenance: Dredging by contract to restore substantially project
dimensions in the 30-foot channel from the mouth at Cooper River
to the head of the Etiwan Fertilizer Co. wharf, thence dredging 16
feet depth in the westerly portion of the turning basin opposite the
Gulf Oil Corporation wharf, Oct. 1-31, 1944, and June 1-30, 1945     61, 196. 94

           Total for all work_-___-                                   ----                    ------                    _____           61, 233. 16
  The additional sum of $25,000 can be profitably expended during
the fiscal year 1946 in maintenance dredging by contract, February
1-28, 1946.
                                                            Cost and financial summary
Cost of new work to June 30, 1944___--                                                   -------                                  $116, 974. 10
Cost of maintenance to June 30, 1944_-                                                             ----                  --        280, 366. 9a
      Total cost of permanent work ,to June 30, 1944------------                                                                       397, 341. 03
Minus accounts payable June 30, 1944_ -- -    ---------                                                                                      36. 22
     Net total expenditures_ ----------------------                                                                                    397, 304. 81
Unexpended balance June 30, 1944---------------------                                                                                   46, 233. 16
           Total amount appropriated to June 30, 1944-------------- 443, 537. 97


    Fiscal year ending June 30                                   1940                  1941                1942           1943                1944
C o st of ne w w or k - -   - - - - - - - -   --   -   ..    .             .
                                                            - -.. - - - - - --.   ....
                                                                                   - - - ..-.-.-.--       ..._-..-    ...........
                                                                                                                ---......              -..
Cost of maintenance-----------$31,;632.                                    23       $24i;82. 67        $58, 59480       $32, 543.97          $55, 436.39

Total expended .....-----------------                         31, 133. 82            23, 721.98           58, 956.33     32, 141.54           55,400.17
Allotted-.-.....            ---.     ---.....                 22, 000. 00            50, 000. 00          31, 600. 00    67, 500. 00          45, 000. 00

          616634--45-pt. 1, vol. 1-                                   30
466            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                    1944

Balance unexpended July 1, 1943 __                                                               $56, 633. 33
Amount allotted from War Department Civil Appropriation Act
approved May 23, 1941--                                                                             45, 000. 00
                                                                                                         6q      93
       Amount to be accounted for----                                                            m0
                                                                                                 1
                                                                                                 -        0.
                                                                                                     ,LJ)uV      U0
Gross amount expended -                                              - --      $67, 855. 83
Less reimbursements collected -                                                  12, 455. 66
                                                                                                     55, 400. 17

      Balance unexpended June 30, 19444                               ---                            46,233.16
Outstanding liabilities June 30, 1944                                                                      36. 22

     Balance available June 30, 1944                                                                 46, 196. 94
Amount allotted in July 1944 -                                                                       15, 000. 00

        Amount available during fiscal yea r1945                               -61,                      196. 94

Amount that can be profitably expende d in fiscal year ending June
  30, 1946 for maintenance 1 - ---             _-_ -_--_-_-      -                                   25,000.00
1Exclusive of available funds.

              12. WATERWAY FROM CHARLESTON TO BEAUFORT, S. C.

   Location.-The waterway begins at the Ashley River entrance of
Wappoo Creek; passes through Wappoo Creek, Stono, Wadmalaw,
and Dawho Rivers, North Creek, Watts Cut, and South Edisto River,
Fenwicks Island Cut, Ashepoo River, Ashepoo-Coosaw Cut, Coosaw
River, Brickyard Creek, and Beaufort River to Beaufort, S. C. The
distances from Charleston to Yonges Island, Martins Point, and Beau-
fort are 23 miles, 25 miles, and 68.5 miles, respectively. (See U. S.
Coast and Geodetic Survey Charts Nos. 837 and 838.)
   Previous projects.-Adopted by River and Harbor Acts of March
3, 1881, and June 13, 1902. For further details see page 613, Annual
Report for 1932.
   Existing project.-This provides for a waterway 12 feet deep at
mean low water and not less than 90 feet wide from Charleston to
Beaufort, S. C., with cut-offs in Wappoo Creek, from Church Flats
in Stono River to Wadmalaw Sound, from Dawho to South Edisto
River and from Ashepoo to Coosaw River.
   The mean tidal range is 5.2 feet at Charleston and 7.4 feet at
Beaufort.
   The estimate of cost for new work, revised in 1937, was $653,000,
exclusive of amounts expended on previous projects. The latest
(1937) approved estimate for annual cost of maintenance is $17,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                      Documents


Mar.     3, 1925   Widening and deepening the waterway from           S. Doc. No. 178, 68th Cong., 2d sess.
                    Charleston to Beaufort.
Aug. 30, 19351     Cut-off between Ashepoo and Coosaw Rivers--....     . Doc. No. 129, 72d Cong., 1st sess.
Aug. 26, 1937      Enlarging the channel from Charleston to Beau-     Rivers and Harbors Committee Doc.
                    fort, including a cut-off between Church Flats          No. 6, 75th Cong., 1st sess.       (Con-
                    of Stono River and Wadmalaw Sound.                      tains latest published map.)

  1   Included in Emergency Relief Administration program May 28, 1935.
         RIVERS     AND     HARBORS-CHARLESTON,                 S. C.,   DISTRICT    467

   Local cooperation.-Fully complied with.
   Terminal facilities.-There is a rail-water terminal owned by the
Atlantic Coast Line Railroad Co. at Yonges Island, S. C., used for the
receipt of farm produce by water and reshipment by rail. At Beau-
fort, S. C., and along connecting tributaries of the waterway there
are numerous wharves used for the receipt of shrimp and oysters,
andshipment of oyster shells and farm produce. These facilities are
considered adequate for present commerce.
   Operations and results during fiscal year-Maintenance.-The
channel in an open-water reach of Wadmalaw Sound was widened and
straightehed by the pipe-line dredge Cherokee, under contract, which
removed 98,825 cubic yards of material at a cost of $25,448.40. Moor-
ing berths were dredged on each side of and near all drawbridges
over this section of the waterway except the Johns Island highway
bridge by the pipe-line dredge Boca Grande, under contract, aug-
mented by the Cherokee, under subcontract, which removed 168,418
cubic yards of material at a cost of $42,158; also, project dimensions
were restored at eight shoaled reaches by U. S. pipe-line dredge Colonel
G. P. Howell which removed 163,518 cubic yards of material at a cost
of $36,305.26.
   Damaged piles in guide dolphins at the first and second Seaboard
Air Line Railway bridges, and at the Johns Island and Dawho River
highway bridges were removed by U. S. snagboat TVateree at a cost
of $4,254.72; also, 48 twelve-pile tie-up dolphins and 2 nineteen-pile
guide dolphins were constructed at the Wappoo Creek and Johns Is-
land highway bridges, the second Seaboard Air Line Railway bridge,
and the Dawho River highway bridge, by contract, at a cost of $25,-
629.25.
   Six twelve-pile tie-up dolphins were constructed by contract in the
mooring berths on each side of and near all drawbridges on this
section of the waterway except the Johns Island highway bridge, at a
cost of $16,261.46.
   The cost of surveys and supervision was $4,266.43. The total cost
during the year was $154.323.52 all for maintenance. The expendi-
tures were $154,236.25.
   Condition at end of fiscal year.-The existing project was completed
in 1940. An examination during June 1944 showed that project
dimensions obtained except at a few intermittent shoals along the
sides of the channel throughout the waterway, which do not materially
obstruct navigation.
   The costs of the existing project to the end of the fiscal year have
been $669,785.80 from regular funds, and $74,642.87 from Emergency
Relief funds, a total of $744,428.67 for new work, and $743,7413.13 from
regular funds for maintenance, a total of $1,488,141.80. The expend-
itures have been $1,413,345.06 from regular funds and $74,642.87 from
Emergency Relief funds, a total of $1,487,987.93.
   Proposed operations.-The balance unexpended June 30, 1944,
$5,108.07, together with $32,000 allotted July 3, 1944, a total of $37,-
108.07, will be applied as follows:
Accounts payable June 30, 1944---------------------------------         $153. 87
Maintenance: Dredging by contract, as required, to maintain project
  dimensions throughout the project, Dec. 1, 1944, to Jan. 15, 1945__ 36, 954. 20

       Total for all work--------------------------- _----37,                       108. 07
468             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

  The additional sum of $35,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging by contract to restore
project dimensions, as may be required, from Charleston to Beaufort,
S. C., including maintenance dredging in mooring berths near draw-
bridges.
                                                  Cost and financial summary
Cost of new work to June 30, 1944_ -----       __-------.---$853,                                                            918. 31
Cost of maintenance to June 30, 1944_ -------------------------                                                         767, 462. 71

      Total cost of permanent work to June.30, 1944----------                                                      1, 621, 381 02
Minus accounts payable June 30, 1944 ------------------------                                                              153. 87
      Net total expenditures_ .-   .- -------                                                                      1, 621, 227. 15
Unexpended balance June 30, 1944---------------------------                                                             5, 108. 07
          Total amount appropriated to June 30, 1944 ------------                                                  1, 626, 335. 22

   Fiscal year ending June 30                        1940             1941                 1942            1943              1944


Cost of new work.-------------                    $450, 213.46      $78, 819.92
Cost of maintenance-.........- -- ..                 2, 506. 74      26,444.50          $22, 897. 55    $336, 509. 05      $154, 323.52

      Total cost---------------................    452, 720. 20     105, 264. 42         22, 897. 55            05
                                                                                                         336,509.           154, 323.52

Total expended..................                   366,162.05       193, 210.98          22, 185. 30    337,180.49          154, 236.25

                               15,000.00
Allotted.........................                                    37,000.00           62, 600.00     330, 150.00         108, 000.00


Balance unexpended July 1, 1943_     -                    ..-------
                                                         _--$51,                                                             344. 32
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941                 $25, 000. 00  -------------
Amount allotted from War Department Civil Appro-
priation Act approved June 2, 1943                  57, 000. 00  --------------
Amount allotted from First Deficiency Appropriation
  Act 1941, approved Apr. 1, 1941_                           ----------------
                                                     26, 000. 00
                                                                                                                        108, 000. 00

       Amount to be accounted for-------            ___--------                                                         159, 344. 3?
Gross amount expended----------..        ------..--          $157, 981. 75
Less reimbursements collected---------------------3,               745. 50
                                                                                                                        154, 236. 25

      Balance unexpended June 30, 1944----------------------_                                                             5, 108. 07
Outstanding liabilities June 30, 1944_ -    .-------------                                             ------                153. 87

     Balance available June 30, 1944_                                        _----------------4,                             94. 20
Amount allotted in July 1944-_----                                         ..------------.------                         32, 000. 00

         Amount available during fiscal year 1945                                  -----------------                     36, 954. 20

Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance                            i_--_._------------.----.---35.                                 000. 00
1Exclusive of available funds.
   13. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                                 (GENERAL)

    The cost of work during the year was $27,364.11 fromn regular funds.
The expenditures were $28,855.94. The balance unexpended on June
30, 1944, $21,990.03, and accounts receivable, $1,312.03, together with
$24,O8    allotted July 3, 1944, E total    $47,60fO6, will be applied
during the fiscal year to accounts payable $66.35, and to the payment of
expenses to be incurred under this heading.
   The additional sum of $30,000 can be profitably expended during the
fiscal year 1946.
                RIVERS AND HARBORS-CHARLESTON,                                            S. C., DISTRICT                      469
                                                   Cost and financial summary
Cost of new work to June 30, 1944-----------------------------------
Cost of maintenance to June 30, 1944----------------------1 $790, 869. 14
       Total cost of permanent work to June 30, 1944-----------                                                     790, 869. 14
Plus accounts receivable June 30, 1944_                       _                                                       1 312. 03

      Gross total costs to June 30, 1944----------------------792, 181. 17
Minus accounts payable June 30, 1944------------------------        66. 35

      Net total expenditures---      -----------             1 792, 114. 82
Unexpended balance June 30, 1944 ---------------------------    21, 990. 03

            Total amount appropriated to June 30, 1944 -------                                                 1 814, 104. 85


      Fiscal year ending June 30                     1940          1941               1942             1943              1944


Cost of new work..          .-----                                                                                        -
Cost of maintenance-------..         ----.......   $97, 34866   $29, 719.95        $148, 637. 16    $110, 814.95        $27, 364. 11
Total expended----------------106,086 68                         30, 650.40         169, 519. 63      90, 153. 31        28, 855.94
Allotted-.----------------------                    79,000.00    21,000.00          114, 525.00      147,900.00          19,000 00


Balance unexpended July 1, 1943_-----------                                                                         $31, 845. 97
Amount allotted from War Department Civil Appropriation Act,
  approved Apr. 28, 1942_--------------                                                                              19, 000. 00
       Amount to be accounted for_----------                                                                         50, 845. 97
Gross amount expended_-------                                                 ---         $29, 908. 85
Less reimbursements collected                                                               11,---------------
                                                                                                052. 91
                                                                                                                     28, 855. 94

      Balance unexpended June 30, 1944----------------                                                 __            21, 990. 03
Outstanding liabilities June 30, 1944-  -_81.                                                                                 55

     Balance available June 30, 1944_                                                              __                21, 908. 48
Amount allotted in July 1944-_ _-_*- -_- -                                    --                                     24, 300. 00

            Amount available during fiscal year 1945-----------                                                      46, 208. 48

Amount that can be profitably
                           2
                              expended in fiscal year ending June
                                                              - -
30, 1946, for maintenance __ ______________                   _ _                                                   30, 000. 00
     1In-adition,    $738 was&expended from conastilte44funds.
     2 Exclusive of available funds.

14. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                        SUBMITTED

                                                                  For last         Cost and expenditures to          Estimated
                                                                full report              June 30, 1944               amount re-
                     Name of project                            see Annuali                                            u d tou
                                                                                                                      quu-uu
                                                                  Report
                                                                 Report
                                                                                                                      complete
                                                                    for-           New work        Maintenance        co

1.   Yadkin River, N. C.t                                          1892
                                                      ..-----------------------.. $102,808.91 ........                  $4,191.00
2.   Salkahatchie River, S. C.'-. .. .............  -              1896             15, 840.73-      ----.               ()
3.   Lumber River, N. C. and S.C.t __-                        - 1897                19,000.00 - .             -         16,000.00
4.   Lynch River and Clark Creek, S. C. .........                  1910              9, 500.00           .(2)
6.   Little Pee Dee River, S. C. ..................                1919             19, 549. 99   $25,650.01            30, 450. 00
6. Edisto River, S. C.1        ------------------------            1938              33,102.65           900.00          (2)
7. Wateree River, S. C.t         -----------------------
                                           _                       1940              60,000.00      151, 783.83          (2)

     I No commerce reported.
     SCompleted.
470            REPORT OF CHIEF OF ENGINEERS,                                              U.       S.   ARMY,                1944


               15. PLANT ALLOTMENT, CHARLESTON, S. C., DISTRICT
                                             Cost and financial summary
Undistributed costs, June 30, 1944_                                  -            -            -              -                $299, 845. 30
Plus accounts receivable, June 30, 1944-----------------------                                                                    195, 415. 29
           Gross total costs to June 30, 1944--- ------------------                                                               495, 260. 59
Minus accounts payable, June 30, 1944-----------------------                                                                       90, 052. 37
           Net total expenditures-------------------------------405,                                                                    208. 22
Unexpended balance, June 30, 1944-----------------------                                                                      -108, 126. 21
      Total amount appropriated to June 30, 1944--- ---------                                                                   297, 082. 01

    Fiscal year ending June 30                   1940                    1941                  1942                   1943              1944

Total expended-          ....
                           -      -    -     -$38, 509. 01        -$11, 213.96           $329, 786.08               $39, 447.18     -$139, 403. 23
Allotted ----------------------
          _                                     47, 545. 00   -            -44,                    983. 92    .--


Balance unexpended, July 1, 1943_                                                                                            - $247, 529. 44
Gross amount expended ____--------$1,                                                         811, 303. 59
Less reimbursements collected----------------                                              1, 950, 706. 82
                                                                                                                               -139, 403.      23
      Balance unexpended, June 30, 1944_-----                                                                          -----      108, 126.    21
Outstanding liabilities, June 30, 1944----------                                                             --                    143, 125.   55
      Balance available, June 30, 1944__  -----                                                                                -- 251, 251.    76
Accounts receivable, June 30, 1944_                                                                                                195, 415.   29
      Unobligated balance available, June 30, 1944                                                           -----------         -55. 836.     47
Status of all investigations for navigation called for by river and harbor acts and
                                 committee resolutions
                                                                           Date trans-
             Locality                      Authorization act                mitted to                 Document No.                Recommenda-
                                                                            Congress

Cape Fear River, N. C., to            Rivers and Harbors
  Winyah Bay, S. C., Intra-             Committee resolu-
  coastal Waterway, im-                 tion, June 20, 1940.
  provement at and near
  Singleton Swash.
Cooper River between                  Commerce Commit-
  Charleston and Pinop-                tee resolution, Mar.
  olis Dam, S. C. (review of           27, 1944.
  waterway from Charles-
  ton to Columbia, S. C.).
Edisto River, S. C., for nav-         Commerce Commit-                    Mar.        3,1944       S. 182, 78th Cong.,            Favorable.
  igation, flood control and            tee resolution, Mar.                                         2d sess.
  power.                                28, 1939.
Little River, N. C. and S. C_         Rivers and Harbors
                                        Committee resolu-
                                        tion, Apr. 30, 1940.
Pee Dee (Great) River,                Rivers and Harbors                  May 31,1944              H. 652, 78th Cong.,               Do.
   S. C., improvement be-               Committee resolu-                                            2d sess.
   tween Georgetown and                 tion, Apr. 1, 1937.
   Cheraw, S. C.
Santee and Congaree Rivers,           Commerce Commit-                    Apr. 24,1944             S. 189, 78th Cong.,               Do.
   S. C., to provide naviga-           tee resolution, Oct.                                          2d sess.
   tion to Columbia, S. C.,            24, 1938.
   and development of hydro-
   electric power.
Santee River, N. C. and               Commerce Commit-
   S. C., salt water intrusion         tee resolution, Apr.,
   and diversion of water into         2, 1941.
   Cooper River.
Santee River (Lower), N. C.           Sec. 6 of River and
   and S. C. (navigation and            Harbor Act, Aug.
 . irrigation).                         30, 1935.
Wateree River, S. C., from            Commerce Commit-
  junction of Santee to Cam-            tee resolution, Nov.
   den, S. C. (navigation and           17, 1938.
   hydroelectric power).
Yadkin-Pee Dee River,                 Commerce Commit-                    May 31,1944              H. 652, 78th Cong.,                Do.
   N. C. and S. C., to provide         tee resolution, Nov.                                         2d sess.
   navigation to Cheraw,               1, 1938.
   S. C., and for hydroelec-
   tric power.
                   FLOOD CONTROL----CHARLESTON,                                  S.     C.,    DISTRICT                    471

   16. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES
                      FOR FLOOD CONTROL

   The cost of the work during the year was $6,388.50. The expendi-
tures were $5,076.47. The balance unexpended bn June 30, 1944.
$1,312.03, together with $5,330 allotted in July 1944, a total of $6,642.03,
will be applied durifng the fiscal year to accounts payable, $1,312.03,
and to the payment of expenses to be incurred under this heading.
   The additional sum of $4,500 can be profitably expended during the
fiscal year 1946.
                                        Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944-------------------------- $178, 6750
      Total cost of permanent work to June 30, 1944---                                        --------            178, 675. 00
Minus accounts payable June 30, 1944____                                                                             1312.  03
      Net total expenditures____                                                                                  177, 362. 97
Unexpended balance June 30, 1944                                                                                    1, 312.03
          Total amount appropriated to June 30, 1944--------------178, 675. 00

    Fiscal year ending June 30              1940              1941                   1942            1943              1944


Cost of new work .
Cost of maintenance---- .---             $32, 366. 71       $11, 084. 01        $69, 725. 86       $13, 241.67         $6, 388. 50
Total expended....-----------------.      33, 373. 51         10, 824. 42        43, 814. 71        39, 672. 56         5, 076. 47
Allotted.-----------------------18, 500. 00                   8, 700. 00         68, 475. 00        15, 700. 00-


Balance unexpended July 1, 1943------------------------------                                                      $6, 388. 50
Gross amount expended_-     _-----------                -___                                                        5, 076.47

      Balance unexpended June 30, 1944 ...                                                                           1, 312. 03
Outstanding liabilities June 30, 1944-                                                                               1,312. 03
     Amount allotted in July 1944 --------------------------                                                        5, 330. 00
Amount available during fiscal year 1945-----------------------                                                     5, 330. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance              1--------------                                                           4, 500. 00
  I Exclusive of available funds.


Status of all investigationsfor flood control calledfor by flood-control acts and committee
                                       resolutions

                                                                 Date trans                                       Recommenda-
           Locality                  Authorization act            mitted to                 Document No.              ton
                                                                  Congress

Edisto River, S. C., for navi-     Commerce Commit-              Mar.       3,1944     S. 182, 78th Cong.,        Favorable.
  gation, flood control and          tee resolution, Mar.                                 2d sess.
  power.                             28, 1939..
Reedy River, S. C-       .......   Flood Control Com-
                                     mittee     resolution,
                                     May 2, 1939.
Rocky River (Loves Ford            Sec. 7 of Flood Control       May 31, 1944          H.     652, 78th              Do.
  and Crumps Ford, N. C.)            Act, June 22, 1936.                                    Cong., 2d sess.
  (supplemental 308 report).
Santee River (Lower), N. C.        Sec. 6 of River and
  and S. C. (navigation              Harbor Act, Aug.
and irrigation).                    30, 1935.
Wilkesboro Dam, Yadkin             Sec. 7 of Flood Control       May 31, 1944          H. 652, 78th                  Do.
River, N. C.                        Act, June 22, 1936.                                 Glong., 2d sess.
472      REPORT OF CHIEF OF ENGINEERS,              U. S. ARMY,     1944

  IMPROVEMENT OF RIVERS AND HARBORS IN THE
           SAVANNAH, GA., DISTRICT
   This district comprises a very small portion of southwestern North
Carolina, western South Carolina, eastern Georgia, and a small portion
of northeastern Florida embraced in the drainage basins tributary to
the Atlantic Ocean between the Beaufort-St. Helena bridge at Beau-
fort, S. C., and the harbor at Fernandina, Fla., inclusive. It includes
the Intracoastal Waterway between these points (Beaufort to Cum-
berland Sound section).*
   District engineer: Col. P. A. Feringa, Corps of Engineers, to Sep-
tember 20, 1943; Lt. Col. E. L. Beriswill, Corps of Engineers, to June
6, 1944, and Lt. Col. Huguenin Thomas, Jr., Corps of Engineers, since
that date.
   Division engineer: Brig. Gen. J. S. Bragdon, United States Army,
to June 10, 1944, and Brig. Gen. R. F. Fowler, United States Army,
since that date.
                                     IMPROVEMENTS

              Navigation                            Navigation-Continued
                                      Page                                     Page
1. Savannah Harbor, Ga    --          472  9. Examinations, surveys, and
2. Savannah River below Au-                     contingencies (general)___    495
       gusta, Ga_                      477 10. Other navigation projects for
3. Waterway between Beaufort,                   which no estimates are
       S. C., and St. Johns River,               submitted_                    496
       Fla. (Beaufort, S. C., to           11. Plant allotment_------------    496
       Cumberland Sound sec-
       tion) -------------------       481               Flood control
4. Altamaha, Oconee, and Oc-
       mulgee Rivers, Ga-------        485 12. Preliminary examinations,
5. Brunswick Harbor, Ga _             487       surveys, and contingencies
6. Satilla River, Ga_ -490                      for flood control -           497
7. St. Marys River, Ga. and               13. Other flood-control projects
       Fla-                            492       for which no estimates are
8. Fernandina Harbor, Fla ....        493       submitted_ _-..----498

                         1. SAVANNAH         HARBOR, GA.

  Location.-The entrance is 75 statute miles south of Charleston
Harbor, S. C., and 70 statute miles north of Brunswick Harbor, Ga.
(See U. S. Coast and Geodetic Survey Chart No. 440.)
  Previous projects.--Adopted by specific acts of Congress May 18,
1826; March 3, 1855; August 7, 1856; and by River and Harbor Acts
of March 3, 1873; June 23, 1874; September 19, 1890; June 3, 1896; and
June 13, 1902. For further details, see page 1810 of Annual Report
for 1915, and page 578 of Annual Report for 1938.
  Existing project.-This consists of eliminating the regulating dam
across South Channel, the relocation of the inland waterway in the
vicinity, and the further extension of training walls and revetments
and jetties and providing for-
   (a) Channels of the following dimensions: 30 feet deep and gener-
ally 500 feet wide from the 30-foot contour in the ocean to the old
quarantine station, 10.2 miles; thence 30 feet deep and generally 400
feet wide to the Seaboard Air Line Railway bridge, 16 miles; thence
26 feet deep and 300 feet wide to the foot of Kings Island, 1.3 miles;
thence 26 feet deep and 200 feet wide to the vicinity of the terminal
               RIVERS AND         HARBORS-SAVANNAH,                   GA.,   DISTRICT             473
of the Atlantic Creosoting Co., 2.1 miles; a total length of 29.6 miles.
   (b) Enlargement of contracted portions of the channel and such
enlargements of the channel as may be necessary to smooth out abrupt
changes and for otherwise improving the hydraulic conditions with
a view to reducing shoaling.
   (c) A turning basin near the upper end of the harbor to be formed
by widening the 26-foot channel to 600 feet for a length of 600 feet
and providing proper approaches.
   (d) The maintenance of the channels, anchorage basins, enlarge-
ments at Drakies Cut, Kings Island, West Broad and Barnard Streets,
mooring dolphins near Fort Oglethorpe, and the existing training
walls and jetties.
   The plane of reference is mean low water, which varies for differ-
ent parts of the harbor. The mean range of tide is 7.6 feet at the
upper end of the harbor, and 7.1 feet at the lower end. Extreme
ranges are about 10.5 feet and 11.0 feet, respectively. Tides below
mean low water occur six or seven times a month and minus 2-foot
tides occur from six to eight times a year. The mean tidal range has
been increased by the improvement about 2.8 feet at the upper end.
   The estimate of cost for new work, revised in 1935, was $5,600,000,
exclusive of amounts expended on previous projects. The latest
 (1935) approved estimate for annual cost of maintenance is $500,000.
   The existing project was authorized by the following river and
harbor acts:

     Acts                      Work authorized                                Documents


June 23,1874  Regulating works.......--- - --    - - -- - - Annual report 1873, p. 747.
Mar. 2,1907   Tentative provision for a 26-foot channel from the H. Doc. No. 181, 59th Cong., 1st sess.
                quarantine station to the Seaboard Air Line Ry.
                bridge.
June 25, 1910 Definite provision for the 26-foot channel .....
July 25, 1912 A 21-foot channel from the Seaboard Air Line Ry. H. Doc. 563, 62d Cong., 2d sess.
                bridge to the foot of Kings Island.
Aug. 8,1917   A 30-foot depth from the sea to the quarantine H. Doc. No. 1471, 64th Cong., 2d sess.
                station.
Jan. 21,1927  A 21-foot channel above Kings Island-....-----     H. Doc. No. 261, 69th Cong., 1st less.
    Do....... Channel 30 feet deep, with general width 500 feet, H. Doc. No. 262, 69th Cong., 1s sess.
               from the ocean to the quarantine station, thence
               26 feet deep, general width 400 feet, to the Sea-
               board Air Line Ry. bridge; thence 21 feet deep
               and 300 feet wide to Kings Island.
              Widening at West Broad and Barnard Sts.;
               anchorage basin; mooring dolphins; regulating
               dam across South Channel; relocation of the
               inland waterway; dredging Drakies Cut to 13
               feet; widening to 525 feet at Kings Island;
               extension of training walls, revetments, and
               jetties. Consolidation of projects relating to
                Savannah Harbor.
July 3, 1930  Channel 26 feet deep and 300 feet wide from the S. Doc. No. 39, 71st Cong.,"lst sess.
               Seaboard Air Line Ry. bridge to the foot of
               Kings Island.
Aug. 30, 1935 Authorizes the present project and the elimina- H. Doc. No. 276, 73d Cong., 2d sess.
               tion from the project of (a) the regulating dam    (Contains the latest published
               across South Channel; (b) the relocation of the    maps.)
               inland waterway; and (c) the further extension
               of training walls, revetments, and jetties.
474     REPORT OF CHIEF OF ENGINEERS,       U. S. ARMY,   1944

   Recommended modifications of project.-Under date of April 20,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for widening the present channel in the
vicinity of the Atlantic Coast Line Railway terminals from 400 feet
to a maximum of 550 feet for a length of 5,000 feet, and for deepen-
ing the present authorized channels and turning basin above the
Seaboard Air Line Railway bridge from 26 to 30 feet at mean low
water, with no change in width, all at an estimated cost of $281,000
for new work and without increase in the annual cost of maintenance;
subject to certain conditions of local cooperation (H. Doc. No. 283, 76th
Cong., 1st sess.).
   Local cooperation.-The River and Harbor Act approved August
30, 1935, imposes the condition that local interests shall furnish, with-
out cost to the United States, suitable disposal areas for the dredged
material if and when needed both for new work and for mainte-
nance. By resolution adopted March 13, 1929, the city of Savannah
made available certain lands necessary for improvement and the future
maintenance of the harbor at Kings Island, and binds itself to furnish,
when required, such dumping ground as may be needed in the future
improvement and maintenance of Savannah Harbor. The city of
Savannah has secured for the United States practically all of the
dumping privileges required for improvement under the existing
project.
   Terminal facilities.-This improvement serves numerous wharves
and piers owned by individuals and corporations, a municipal wharf,
and the terminals of three trunk-line railways and two ocean steam-
ship companies. For further details see Port Series No. 10, Corps of
Engineers (revised 1940). In addition to these facilities, there were
constructed in 1942 a pile and timber fitting-out wharf 1,800 feet long
at the shipyard of the Southeastern Shipbuilding Corporation, 2.3
miles below the center of the city, and a similar wharf 450 feet long
at the shipyard of the Savannah Machine & Foundry Co., about 3,000
feet below the Seaboard Air Line Railway bridge. Neither of these
shipyard wharves is open to the public. At the latter shipyard, a
graving dock has been constructed and is now open to the public on
equal terms. This dock will accommodate vessels having a beam as
great as 62 feet and an over-all length of 450 feet.
   Operations and results during fiscal year-Maintenance.-Govern-
ment plant and hired labor operated on the harbor between the sea and
Onslow Island, removing 7,976,768 cubic yards of material at a cost
of $646,791.42. Engineering studies and surveys were made at a cost
of $18,341.03.
   The total cost was $665,132.45 for maintenance. The total expend-
iture was $665,623.03.
                  RIVERS          AND HARBORS-SAVANNAH,                                    GA.,     DISTRICT                   475
  The following tabulation shows the names of plant, sections of the
harbor over which work was performed, yardage, and methods by
which removed:

                                                                                                       Cubic yards removed

                                      Name of channel
                                                                                                      Regular           Agitation
                                                                                                      dredging          dredging


Dredge Culebra:
   Obstruction, station 140 to 146+500----------                         ----------------                                      392, 966
   The Bight, station 146+500 to 151+700------                  ------------                      -------                      377, 887
   Upper Flats, station 151+700 to 162A -----------                             ---- ----                   5, 593             825. 226
   Lower Flats, station 162A to 171 ..--------- -- - -----                                                  1,583              597, 804
   Long Island Crossing, station 171 to 190A - ---------------                                            329, 035              59, 292
   Quarantine station 190A to 195B ......................                                                  53, 667
   Tybee Knoll, station 195B to 216B ....................                                                 248, 396-
   Tybee Roads, station 216B to 234                                                                       197, 087
   Bar, station 234 to 244 ---- - - - - - - - - -
Dredge De Witt Clinton:
                                                             -- - -- - - -- - - - - -                      48, 528          ----
                                                                                                                             ---
   1V arsh Island, station107to 116B---        ---------- -------                                         347,374 -- -----
   City Front, station 116B to 127+500. - ---                ,. ------ .1,
                                                          -----                                           129, 312      -         -
   Wrecks, station 127+500 to 135B__                                                                   1, 907, 484      ---         -...
   Five Fathom Hole, station 135B to 140 --            ----- ---------------                              231, 871    ...         ---

   Obstruction, station 140 to 146+500 - -------------------------                                        251, 187 .------------
   The Bight, station 146+500 to 151+700 -          -- ---- ------------- --- -                            36, 680
   Upper Flats,station151+700 to 162A -               ...- ...--   -         - -          --.. .-         177, 139 ----
   Lower Flats, station 162A to 171 .........-...-.---..                            -        -.-          252, 423 -         .        .
Dredge Morgan:
   Whitehall, station 88B to 100 -_                    -------------------                                  8,088         --          -
   Kings Island, station 100 to 107 _--.---------- -----                                  ---             105, 393   -
   Oyster Bed Dump -.     -. ...
                         -...             --.......   ..                                                  392,753                 -

       Total number cubic yards removed------.............------------------------                     5, 723, 593         2, 253, 175



   Condition at end of fiscal year.--The existing project was completed
in 1937. The 30-foot channel from the sea to Old Quarantine Sta-
tion was completed in 1930, and the remaining part of the channel
in 1937. That part of the 26-foot channel from the Seaboard Air
Line Railway bridge to the foot of Kings Island was completed in
1931, and the remaining part from the foot of Kings Island to the
Atlantic Creosoting Co.'s wharf, including the turning basin near
the upper end of the harbor, in 1937. .Cross-tides channel was closed
with a hydraulic fill in 1937. The anchorage basin and mooring
dolphins near Fort Oglethorpe were completed in 1926. The enlarge-
ments at Drakies Cut, Kings Island, and at West Broad and Bar-
nard Streets were completed in 1931, 19~29, and 1924, respectively.
Whitehall Channel training wall was completed in 1929 and was
replaced by three spur dikes in 1937. Fig Island training wall was
raised and extended in 1940. Long Island training wall fill was
completed in 1931, and other training walls and jetties prior to 1929.
   Least depths in midchannel for half project width at mean low
water, as determined in May and June 1944, were 28 feet over the bar
channels from the sea to Jones Island; 27.5 feet from Jones Island to
Fort Jackson; 29 feet from Fort Jackson to the Seaboard Air Line
Railway bridge; 26 feet from the Seaboard Air Line Railway bridge
to the upper end of the harbor. The turning basin at the upper end
of the harbor had a controlling depth of 21.1 feet for a width of 450
feet. The least depths do not occur abreast of one another and there
is a practical navigation channel 28.5 feet deep and one-third project
width from the sea to 2 miles below the Seaboard Air Line Railway
bridge and 29 feet deep for one-half project width for the 2 miles to
the bridge. The shoals, where they occur, are soft mud.
   Due to war conditions, the use of the sea-dumping ground for
476               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                            1944

hopper dredges was curtailed. This required the provision of an
inside dumping ground for such dredges and rehandling the spoil to
shore with a pipe-line dredge.
  The costs under the existing project to June 30, 1944, have been
$5,177,678.13 for new work and $13,988,367.89 for maintenance, a total
of $19,166,046.02. The total expenditures have been $19,159,710.59.
  Proposed operations.--The balance unexpended June 30, 1944,
$48,419.44, plus allotment of $550,700 dated July 3, 1944, a total of
$599,119.44, will be applied as follows:
Accounts payable June 30, 1944_-----                     ---------           $6, 335. 43
Maintenance:
    Dredging with U. S. pipe-line dredge De Witt Clinton in 30-foot
      channel between quarantine station and Seaboard Air Line
      R. R. bridge, 11 months between July 1, 1944, and June 30,
      1945     -----------------------------------------                    330, 000. 00
    Dredging with U. S. pipe-line dredge Morgan in 26- and 30-foot
      channels between quarantine station and upper end of harbor,
      2% months between July 1, 1944, and Oct. 31, 1944-...              .   70, 000. 00
    Dredging with U. S. hopper dredge Culebra in 30-foot channel
      between South Channel and outer end of bar, 3/ months be-
      tween Dec. 1, 1944, and June 30, 1945- -----------           _--_ _--157,
                                                                        _        784. Q1
    Dredging of a disposal area for the U. S. hopper dredge Culebra
      with U. S. pipe-line dredge Morgan, 1% months, between
      Aug. 1, 1944, and Sept. 10, 1944_ ___---------                         35,000. 00
                  Total for all work_ ____________------                                                                           _---      599, 119. 44
  The additional sum of $880,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredging with United States pipe-line dredge in 26- and 30-foot
      channels between South Channel and upper end of harbor, 12
      months between July 1, 1945, and June 30, 1946- -----------       $370, 000
    Dredging with United States hopper dredge in 30-foot channel be-
      tween South Channel and outer end of bar, 10 months between
      July 1, 1945, and Dec. 31, 1945; Mar. 1, 1946, and June 30, 1946_ 450, 000
    Dredging a disposal area for United States hopper dredge with
      United States pipe-line dredge, 2 months between July 1, 1945,
      and Dec. 31, 1945----------------_                              -   60, 000
                  Total for all work_--                                    ----              __--------880,                                                   000

                                                      Cost and financial summary
Cost of new work to June 30, 1944-----------------------                                                                            $12, 438, 062. 11
Cost of maintenance to June 30, 1944                                        ----------------------                                   14, 287, 262. 15
      Total cost of permanent work to June 30, 1944 --------- 26, 725, 324. 26
Minus accounts payable June 30, 1944----------------------          6, 335. 43
      Net total expenditures_ _---------_                                                                                              26, 718, 988.83
Unexpended balance June 30, 1944_---------                                                                                   ---            48, 419. 44
             Total amount appropriated to June 30, 1944                                                  -----------                   26, 767, 408. 27


     Fiscal year ending June 30                             1940                   1941                   1942                  1943                   1944
C o st of new work . .. . . . . . . . . . . . . .. . . .-.
                             -.                          . . .-.
                                                               . . . .. . . . . -.
                                                                                . . . . . . . .. . . . . . . . . .   . .. . . . . -.
                                                                                                                     -.           . . . -.
                                                                                                                                        . -.
                                                                                                                                          .. . . . . . . . . . . . .
Cost of maintenance-.............-$625,971.33                                 $455, 437.35           $449,403.00           $531, 799.42             $665, 132. 45
Total expended..................                         679, 170. 32          476, 587. 38            447, 814. 02          529, 141. 03            665, 623. 03
Allotted.................595.                                  500. 00         450, 000. 00            425, 800. 00          641, 375. 00            100, 000. 00
             RIVERS       AND HARBORS-SAVANNAH,             GA.,   DISTRICT         477
Balance unexpended July 1, 1943_- -------                                  $614, 042. 47
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943--____-------------                                  100, 000.00
      Amount to be accounted for---          ---------                      714, 042.47
Gross amount expended---
                     _         -------------                                665, 623. 03
      Balance unexpended June 30, 1944 --------------------                   48, 419. 44
Outstanding liabilities June 30, 1944---   ----------                          6, 335. 43
     Balance available June 30, 1944_---           - -_42,                        084. 01
Amount allotted in July 1944 _ ___------------550,                                700. 00

        Amount available during fiscal year 1945     --------------         592, 784. 01

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance' 1_______________--   -     -               880, 000. 00
I Exclusive of available funds.,


                   2. SAVANNAH RIVER BELOW AUGUSTA, GA.

   Location.-This river is formed by the confluence of the Tugaloo
and Seneca Rivers on the northwestern part of the South Carolina-
Georgia boundary line. It flows southeast for 314 miles, forming the
boundary line, and empties into the Atlantic Ocean 16.6 miles below
Savannah, Ga. (See U. S. Geological Survey maps of South Carolina
and Georgia.)
   Previous project.-Adopted by the River and Harbor Act of March
3, 1881. A subdivision between new work and maintenance is not
possible. For further details see page 1813 of Annual Report for 1915
and page 581 of Annual Report for 1938.
   Existing project.-This provides for a channel 6 feet deep and 75
feet wide (at ordinary summer flow, which corresponds to a discharge
of 4,000 second-feet at Augusta, Ga.), from the upper end of Savan-
nah Harbor to the head of navigation at Augusta, 3.0 miles above
Fifth Street Bridge, a distance of approximately 199 miles. The
improvement is to be obtained by the construction of one lock and
dam at New Savannah Bluff, the use of contraction works, the closure
of cut-offs, bank protection, removal of snags, overhanging trees, and
wrecks, and the dredging of troublesome bars. The mean tidal varia-
tion at the mouth of the river is 7.1 feet. The freshet variation above
the normal pool level (elevation 114.5, mean sea level) of the New
Savannah Bluff lock and dam at the head of the improvement is
approximately 13 feet ordinarily, with an extreme of 34 feet. The
pertinent data for the lock and dam are given in the following table:
                            Lock and dam at New Savannah Bluff
    Nearest railroad station, Augusta, Ga., 13 miles.
    Distance above Bull Street, Savannah, Ga., 188 miles.
    Lock dimensions, 56 by 360 feet.
    Lift of lock, 15 feet.
    Depth on lower miter sill at low water, 10 feet.
    Depth on upper miter sill at normal pool level, 13.5 feet.
    Character of foundations-piles in sand, clay, and gravel.
    Kind of dam, fixed.
    Type of construction, concrete.
    Completed, 1937.
    Total cost, $1,473,812.10.
   Five steel vertical-lift crest-control gates, set between concrete piers and resting on
roncrete sill.
478           REPORT OF CHIEF OF ENGINEERS,                          U.     S. ARMY,        1944

  The estimate of cost for new orrk, revised in 1935, is $3,340,000,
exclusive of amounts expended on previous projects. The latest (1930)
approved estimate for annual cost of maintenance and operation is
$75,000 for the first 3 years and $50,000 annually thereafter, of which
$15,000 is for operating and care of lock and dam.
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                      Documents


Sept. 19,1890     For a 5-foot channel ..   - .......... ..
                                                --. _ _.__          . H.     Doc. No. 255, 51st Cong., 2d sess.,
                                                                           and Annual Report, 1890, p. 1328.
June 25, 1910     Special improvement by bank protection work of      H. Doc. No. 962, 60th Cong., 1st sess.
                    20 or 25 miles of the river immediately below
                   Augusta.
July    3, 1930   The present 6-foot channel project and the lock     H. Doc.No. 101, 70th Cong., 1st sess.
                   and dam.
Aug. 30,19351     Provision made for locatihg the lock and dam at     Senate committee print, 73d Cong., 2d
                                                                             2
                    New Savannah Bluff.                                 sess.
Aug. 26, 1937                                                  _.
                  Conditions of local cooperation modified _...._     Rivers and Harbors Committee Doc_
                                                                        No. 39, 75th Cong., 1st sess.


  1 Included in the Public Works Administration program, Sept. 27, 1933.
  2 Contains the latest published map.


   Recommended modifications of project.-Under date of February
21, 1939, the Chief of Engineers recommended modification of the
existing project so as to provide for construction of the Clark Hill
Reservoir for the regulation of stream flow in the interests of naviga-
tion and for the development of hydroelectric power, at an estimated
first cost of $28,000,000 (S. Doc. No. 66, 76th Cong., 1st sess.).
   Under date of May 27, 1944, the Chief of Engineers recommended
that a general plan of development be adopted as the basis for im-
provement, step by step, of Savannah River, and tributaries for power,
flood control, navigation, and other purposes, and that the Clark Hill
project be authorized for construction as the initial step, at an esti-
mated cost of $35,300,000 for construction and $223,000 annually for
operation and maintenance (H. Doc. No. 657, 78th Cong., 2d sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-The only water terminals served by this im-
provement are at Augusta and at or near Savannah. The city of
Augusta owns and operates, on equal terms to all, a wharf and ware-
house; a short distance below this terminal the Pure Oil Co. has a
terminal (storage capacity of 27,500 barrels) for berthing and- dis-
charging oil barges; and just outside of the eastern city limits is the
Merry Bros. Brick & Tile Co.'s terminal. At Savannah there is one
municipal wharf, suitable for berths for river steamers, open to the
public on equal terms. In addition, there are extensive facilities
at Savannah, privately owned, for ocean-going and smaller vessels.
Along the river there are numerous natural landings without wharves
or railway connections. The terminal facilities on this improvement
are considered ample for existing commerce.
   Operations and results during fiscal year---Maintenance.-Govern-
ment plant and hired labor removed the most troublesome obstructions
             RIVERS AND HARBORS-SAVANNAH,                                        GA.,   DISTRICT               479
between mile 18 and mile 188, consisting of 296 snags and sunken logs,
at a cost of $6,839.92. This work was performed by the snagboat
Macon. Surveys and engineering studies were made at a cost of
$2,302.84.
    The minimum daily flow of the river at the New Savannah Bluff
navigation dam during 1943 was 2,700 cubic feet per second on October
15, 1943. The minimum weekly flow was 3,000 cubic feet per second.
The minimum daily and weekly flows of record are 1,105 and 1,220
cubic feet per second, respectively.
    Power plants which have storage on the river are Stevens Creek
plant, 9 miles above Augusta, and the six plants of the Georgia Power
Co. on the headwaters. No regulation of flow is required from head-
water plants, but the Stevens Creek plant is required to pass the
natural flow of the river when this flow is at or below 6,550 cubic feet
per second. The Stevens Creek plant has operated in this manner
during the past year, but sufficient information is not available to
determine what effect the headwater plants have on the natural flow
of the river.
    Maintenance (operating and care). The lock and dam at New
Savannah Bluff was operated and ordinary repairs to the structure
and appurtenant works were made at a cost of $20,766.68.
    The total cost, all from regular funds, was $29,909.44 for mainte-
nance. The total expenditure was $30,062.16.
    Condition at end of fiscal year.-The existing project was com-
pleted in 1939. Construction of the lock and dam at New Savannah
   luff was completed in 1937 and the open-channel work in 1939. All
open-channel works are in good repair. The controlling depth at
ordinary summer water was 4 feet or greater for about 64 percent of
the fiscal year. This depth corresponds to a height of 5.5 feet on the
Butler Creek gage, and to a discharge of 4,000 second-feet at Augusta.
    The costs and expenditures on the existing project to June 30, 1944,
were as follows:

                                                        Regular funds            Public Works          Total
                                                                                                       Total
                                                                                    funds


New work- - -                            .      $1,117, 237. 02
                   - - ...........................                                      562.24
                                                                                  $1,634,             $2, 751, 799. 26

                      _-
M aintenance _ . ._ .. . . . ..
Operating and care_ ...........
                        -
                                      . . .
                                     . ...
                                _.........
                                                 1, 389, 184. 90
                                                    156, 729. 81
                                                                                       ._      _
                                                                                          . - 2156,
                                                                                                       1, 389, 184. 90
                                                                                                               729. 84
     Total                                                     2, 663, 151. 73
                                        ..----------------------------------       1, 634, 562. 24     4, 297, 713. 97
Expenditures .        ..               ..                      2, 662, 451. 81     1, 634, 562. 24     4, 297, 014. 05


  Proposed operations..-The balance unexpended June 30, 1944,
$1,953.49, plus allotment of $41,000 dated July 3, 1944, a total of $42,-
953.49, will be applied as follows:
Accounts payable June 30, 1944---------------------------------        $699. 92
Maintenance:
    Snaging and removal of sand shoals with U. S. snagboat Macon,
      4 months between Sept. 1, 1944, and June30, 1945        - -- - 20, 253. 57
    Operation and care, New Savannah Bluff Lock and Dam:
        Operations      ----------------------          $19,000.00
        Ordinary repairs          ---------------------   2, 500. 00
        Improvements and reconstruction---------- - -          0. 00
        Emergencies-------------------------------           500. 00
                                                                     22, 000. 00

                 Total for all work_------------------------                                          42, 953. 49
480              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

   The additional sum of $80,500 can be profitably expended during
fiscal year 1946, as follows:
Maintenance:
    Snagging and removal of sand shoals with U. S. snagboat Macon
      8Y months between July 1, 1945, and June 30, 1946-_      -  $42, 500
    Operation and care, New Savannah Bluff Lock and Dam:
        Operations     ---------------------------------- $19,000
                 Ordinary repairs                            ----------------------                                    2, 500
                 Improvements and reconstruction-----------------         0
                 Emergencies _---   -------------                      500
                                                                         ---                                                            22, 000
        Construction, by contract, open channel works (pile dikes and bank
          revetment) at mile 183 (zero mile at Bull St., Savannah Ga.)
          between July 1, 1945, and June 30, 1946...                                                                                    12, 000
        Repairs, by contract, to open channel works (bank revetment) at
         mile 193 between July 1, 1945, and June 30, 1946                                            ------------                        4, 000

                 Total for all work_              _-------------_------------80,                                                               500
                                             Cost and financial summary
Cost of new work to June 30, 1944_----                                              -------                            $2, 845, 279. 35
Cost of maintenance to June 30, 1944_----                                                     - -_                      1, 545, 914. 71
      Total cost of permanent work to June 30, 194.4    --                                                              4, 391, 194. 06
Minus accounts payable June 30, 1944-----------------------                                                                     699. 92
      Net total expenditures_--        ---------                                                                -4,             390, 494. 14
Unexpended balance June 30, 1944__----------                                                                                    - 1, 953.49
            Total amount appropriated to June 30, 1944--------                                                          4, 392, 447. 63


     Fiscal year ending June 30                 1940              1941                  1942                    1943                    1944

Cost of new work ...-                           - - - - - - - - - - - -         -------..              .    .     . .       .     .    . . . .
Cost of maintenance -----------.             $162, 539. 54      $81,874. 40           $66, 577. 77         $41,185. 65                 $29, 909. 44

Total expended ...........----------------    168,104. 59        80, 816. 75           69,406.92            41,166. 44                  30, 062.16

Allotted      ----------------------.........................
                                           75,006.00             66,000.00             61,800.00            36, 649. 23               -30,000.00



Balance unexpended July 1, 1943_-------------                                                                                   $62, 015. 65
Deductions on account of revocation of allotment                                         _                              -        30,000.00.

      Net amount to be accounted for_-  _                                                                               _        32,015. 65
Gross amount expended_----------------------                                                                     _               30, 062. 16
      Balance unexpended June 30, 1944---                                                                                             1, 953.49
Outstanding liabilities June 30, 1944 - -                                      --                                                        699. 92
     Balance available June 30, 1944-                                                                                   -         1,253. 57
Amount allotted in July 1944_                                                                                                    41,000. 00
            Amount available during fiscal year 1945                                                                             42, 253.57
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1  -___-      _____                                                                              80, 500.00
   'Exclusive of available funds.
          RIVERS    AND    HARBORS-SAVANNAH,      GA.,   DISTRICT     481
3. WATERWAY BETWEEN BEAUFORT, S. C., AND ST. JOHNS RIVER, FLA.
       (BEAUFORT, S. C., TO CUMBERLAND SOUND SECTION)

   Location.-This section of the waterway connects Beaufort, S. C.,
with Fernandina, Fla. (See U. S. Coast and Geodetic Survey Charts
Nos. 838-841, inclusive.) For Cumberland Sound to St. Johns River
section see page 499.
  Previous projects-Between Savannah, Ga., and Fernandina, Fla.-
Previous improvements in this section were authorized by River and
Harbor Acts of August 2, 1882, August 11, 1888, July 13, 1892, and
March 3, 1905.
   For further details see pages 1814, 1821-1823 of the Annual Report
for 1915, and page 585 of the Annual Report for 1938.
   Existing project.-This provides for a waterway 12 feet deep, at
mean low water, and not less than 90 feet wide, between Beaufort, S. C.,
and Savannah, Ga., via Beaufort River and Port Royal Sound; for
a Waterway 12Jfeet deep, at mean low water, with widths of 90 feet in
land cuts and narrow streams and 150 feet in open waters, between
Savannah, Ga., and Fernandina, Fla., to follow in general the aline-
ment of the existing waterway, except for such cut-offs or other
changes in the route as may be found desirable and justified by the
resultant benefits to navigation; and for a suitable anchorage basin at
Thunderbolt, Ga. The total distance from Beaufort, S. C., to Fer-
nandina, Fla., is 180.2 miles. The project also provides for the follow-
ing: (1) Removing logs and snags from Generals Cut, Ga.; (2) an
alternate and more protected route, 7 feet deep at mean low water
from Doboy Sound to Brunswick Harbor, via Darien River, Three
Mile Cut, Altamaha River, One Mile Cut, Buttermilk Sound, Mackay
River, Back River, Clubb Creek, and Plantation Creek; (3) a pro-
tected channel 7 feet deep at mean low water and 75 feet around St.
Andrew Sound extending from the main route of the waterway in
Jekyll Creek through Jekyll Sound, Little Satilla River, Umbrella
Cut, Umbrella Creek, and its south branch, through Dover Cut to
Dover Creek, thence up Dover Creek and through a narrow neck of
land to Satilla River, thence through a land cut south of Todd Creek
and through Floyd Creek to the main route of the waterway in Cum-
berland River; (4) a channel 5 feet deep at mean low water and 50
feet wide to connect Baileys Cut to Satilla River and Dover Creek,
Ga.; (5) a loop 8 feet deep at mean low water to reach the wharves
at the southern end of Cumberland Sound. In general, the work is
to be accomplished by dredging, supplemented by training walls, as
necessary.
   The mean tidal range between Beaufort, S. C., and Fernandina,
Fla., is from 6 to 8 feet, with fluctuations from 11/2 to 21/2 feet, due to
winds and lunar phases.-
   The estimated cost of new work, revised in 1938, is $961,600, exclusive
of amounts expended under previous projects. The latest (1938) ap-
proved estimate for annual cost of maintenance is $112,000.           .




      616634-45-pt. 1, vol. 1--31
482                 REPORT           OF CHIEF OF ENGINEERS,                       U.        S.     ARMY,      1944


  The .existing project was authorized by the following river and
harbor acts:

      Acts                                 Work authorized                                             Documents
C-              -    ---------             --                               - I         -




                         BEAUFORT, S. C., TO SAVANNAH,       GA., SECTION


June 3,1896           Route No. 2 adopted _     --                                 H. Doc. No. 295, 53d Cong., 3d sess.
Mar. 3,1899           Route No. 1 adopted _         -                                 Do.'
July 25,1912          Provided for Archer Creek _..                                H. Doc, No. 513, 62d Cong., 2d sess.
                        (This route now abandoned.)

                       SAVANNAH,        GA., TO FERNANDINA, FLA., SECTION

July 13,1892          Original 7-foot channel .        .-----------.... H. Doc. No. 41, 52d Cong., 1st sess.
Mar. 3,1905           Provided for Skidaway Narrows ........            H. Doc. No. 450, 58th Cong., 2d sess.t
July 25,1912          Incorporated alternate routes previously im-      H. Doc. No. 1236, 60th Cong., 2d sess.'
                        proved as separate projects and the auxiliary
                        channels.

                                 CUMBERLAND SOUND, GA., AND FLA., TO
                                    ST. JOHNS RIVER, FLA., SECTION

Mar.       4, 1913    For a channel 7 feet deep and 100 feet wide ...              H.       Doe.   No. 898, 62d Cong.,   2d sess.

Aug.       8, 1917    Consolidation of the three sections, shown above,
                        into "Waterway between Beaufort, S. C., and
                        St. Johns River, Fla."

                         BEAUFORT, S. C., TO CUMBERLAND SOUND, GA.,
                                      AND FLA., SECTION

Mar. 2, 1919          Removing logs and snags from Generals Cut                    H. Doc. No. 581, 63d Cong., 2d sess.'
      Do   .-----     Improving Back River to provide a channel 7 feet             H. Doc. No. 1391, 62d Cong., 3d sess.
                        deep and 150 feet wide.
Mar. 3, 1925          Channel 75 feet wide between Beaufort, S. C., and            S. Doc. No. 178, 68th Cong., 2d sess.
                        Savannah, Ga.
                                                                                                                       1
July 3,1930           Channel from Baileys Cut to Dover Creek ...                  S. Doc. No. 43, 71st Cong., 2d sess.
Aug. 26,1937          A 7-foot protected channel around St. Andrew                 Senate committee print, 74th Cong.,
                                                                                               1
                        Sound.                                                       1st sess.
           -
      Do ...-         A 12-foot channel between Beaufort, S. C., and               Rivers and. Harbors Committee Doc.
                        Savannah, Ga., via Beaufort River and Port                   No. 6, 75th Cong., 1st sess.
                        Royal Sound.
June 20,1938          A 12-foot channel between Savannah, Ga., and                 H. Doc. No. 618, 75th Cong., 3d sess.
                        Fernandina, Fla.; various cut-offs; and anchor-
                       age basin at Thunderbolt, Ga.


     SContain latest published maps.


     Recommended modifications of project.-Under date of December
16, 1940, the Chief of Engineers recommended modification of the
existing project so as to provide for an alternate route 9 feet deep
and 150 feet wide in that part of Frederica River, Ga., not now tra-
versed by the main route, at no additional cost to the United States
(H. I)oc. No. 114, 77th Cong., 1st sess.).
  Local cooperation.-Fully complied with.
   Terminal facilities.-Exclusive of terminal facilities at the ports
of entry, this improvement serves numerous wharves, some of which
are open to the public on equaliterms. These facilities are considered
ample for existing commerce.
                     RIVERS            AND HARBORS---SAVANNAH,                                           GA.,      DISTRICT                       483

   Operations and results during fiscal year.-Government plant and
hired labor operated on maintenance dredging in various localities
between Ramshorn Creek and Jekyll Creek; in the auxiliary route at
Brunswick; and in the protected route around St. Andrew Sound,
removing a total of 3,616,631 cubic yards of material at a cost of
$373,889.68. The cost of construction of guide dolphins and repairs
to mileage and direction signs was $8,816.29. Twenty-four tie-up
dolphins were constructed, by contract, at a cost of $24,238 37. Sur-
veys and engineering studies were made at a cost of $11,859.59.
   The total cost for maintenance was $418,803.93. The total expendi-
tuies were $424,515.37.
   The following tabulation shows the names of plant, sections of
waterway over which work was performed, and total yardage removed:

                                                                                                                                       Cubic yards
                                           Name of channel or waterway                                                              removed (regu--
                                                                                                                                     lar dredging.

Dredge Creighton:
    Fields Cut, mile 37 to 39-                                                                                                                244, 745
    Wilmington River, mile 44 to 47.5 -----                                                                                                     66,032
    Skidaway Narrows, mile 58                              ----------------------------                          --                             29, 990
    Hell Gate, mile 66      ----------            --       --------------------------                                                           58,341
    Front River, mile 102.5.------                                       ---       -----                                                        39,037
    Creighton Narrows, mile 106 to 107               ---------------------------------------------                                            298,694
    Shell Bluff Creek, mile 107                                                                                                                 13,485
    Rockdedundy River, mile 116.5                                                                                                             124, 955
    Little Mud River, mile 117.5                                                                                                                65,604
    Altamab-%Sound, mile 122                                                                 -144,66T
    Butteonilk Sound, mile 1 6 ---                                                                                                            462,074
    Back      Rtiver,
                 m ile 135- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -59,251
    Plantation Creek (south mouth), mile 147                                                                                                    31, 079
    Umbrella Creek, mile 150                                        ----                                                                        60,8753
Dredge Morgan:
    Beaufort River, mile 0                                                                                                                      1
                                                                  ..................------------------------------------------------------- 26, 629,
                                                                                                                                              184, 348
                                                                                       ..........-----------------------------------------------.............
    Ramshorn Creek, mile 32 to 33.5
    Elba Island Cut, mile 42                                     .................------------------------------------------------------        64,052
    St. Augustine Creek, mile 43 ..........---------------..................                                                                  194, 581
    Wilmington River, mile 43 to 46-----..................................                                                                 1,195,953
    Skidaway Narrows, mile 58 ......................................                                                     ...                  181,259
   Jekyll Creek, mile 146 to 147 ...........................................                                                                    50, 202
Dredge Cvlebra:
    Fields Cut, mile 38 to 40 ....------------------------------------------------------                                                       20,777

         Total number cubic yardg(m )ved.................------------------------------------------                                          3,616,631

  1 Work performed by U. S. dredge Cherokee of the Charleston, S. C., engineer district.



     Condition at end of fiscal year.-The existing project was completed
in 1941 by dredging to provide a 12-foot channel. The protected rcute
around St. Andrew Sound was completed in 1939. The-training walls
and closure dams were completed in 1912 and are in satisfactory con-
dit ion. All other improvements were completed in 1932.
  Since March 1943, the route of the Intracoastal Waterway has been
through the Elba-McQueens Island cut and the northwesterly end of
St. Augustine Creek. The previous route through the westerly end
of South Channel and the northerly end of Wilmington River has
been abandoned. The main route has a controlling depth at mean low
water of 12 feet or greater, as determined by surveys made in May 1944.
  The costs under the existing project to June 30, 1944, were $763,599.20
for new work and $2,753,103.47 for maintenance, a total of $3,516,-
702.67. Total expenditures were $3,513,783.69.
484                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                   1944

  Proposed operations.-The balance unexpended June 30, 1944,
$61,786.66, plus account receivable, $17,518.23, plus allotment of $174,-
000 dated July 3, 1944, a total of $253,304.89, will be applied as follows:
Accounts payable June 30, 1944_----------                          $20, 437. 21
Maintenance:
    Dredging with U. S. pipe-line dredge Creighton between Beau-
      fort, S. C., and Cumberland Sound, 11 months between July
      1, 1944, and June 30, 1945_                           ---    198; 867. 68                                -
    Dredging with U. S. pipe-line dredge Morgan or by contractors'
      plant between Beaufort, S. C., and Cumberlad-d Sound, 1
      month between Nov. 1, 1944, and June 30, 1945--_
    Repairs by contract to guide and tie-up dolphins-------------
                                                                    29, 000. 00
                                                                     3, 000. 00
                                                                                                         --
    Repairs by hired labor to speed and directional markers along
      the waterway ----------------------------------------          2, 000. 00
                   Total for all work ---                                                                             253,304.89
   The additional sum of $377,000 can be profitably expended during
fiscal year 1946 as follows:
Maintenance:
    Dredging with U. S. pipe-line dredge Creighton between Beaufort,
      S. C., and Cumberland Sound, 11 months between July 1, 1945,
      and June 30, 1946-- -------           -----------               $198, 000
    Dredging with U. S. pipe-line dredge Morgan or by contractors'
      plant between Beaufort, S. C., and Cumberland Sound section,
      6 months between July 1, 1945 and June 30, 1946                  174, 000                   ------------
    Repairs by contract to guide and tie-up dolphins -      --           2, 500
    Repairs by. hired labor to speed and directional markers---------    2, 500

              Total for all work                             ---             -----------                                 377, 000
                                                   Cost and financial summary
Cost of new work to June 30, 1944_ ----------------                                                      --         $958, 096. 16
Cost of maintenance to June 30, 1944_---------------                                                      -        2, 887, 901. 10
       Total cost of permanent work to June 30, 1944----------3, 845, 997. 26
Plus accounts receivable June 30, 1944_-      -----        ---    17, 518. 23
      Gross total costs to June 30, 1944---------------------                                                      3, 863, 515. 49
Minus accounts payable June 30, 1944--    --------                                                                     20, 437. 21
      Net total expenlitures--- ----------                                                                 -       3, 843, 078. 28
Unexpended balance June 30, 1944_ ---------------                                                                      61, 786. 66
              Total amount appropriated to June 30, 1944-------------3, 904, 864. 94


     Fiscal year ending June 30                       1940            1941                 1942          1943              1944

Cost of new work-....... .     .                   $113, 358. 53   $413,142. 62
Cost of maintenance-...-......                       48, 575.96      54, 827.08       $122, 031.09    $650,175.33        $418,803.93
         Total cost ...........---------------      161, 934. 49    467, 969. 70       122, 031.09     650,175. 33        418,'803.93
Total expended----------------..................    173, 610.92    450, 490. 51        141, 763.63     642, 977.60        424, 515.37
Allotted............._...........                  -97,548.20       40, 000.00         127, 000.00   1, 010, 050.00        26,000.00



Balance unexpended July 1, 1943_- ----               ------------------                                             $460, 302. 03
Amount allotted froim War Department Civil Appropriation Act
  approved Apr. 28, 1942 -----------------------------------                                                           26,000. 00
      Amount to be accounted for-                                   --------                                          486, 302. 03
Gross amount expended.-       ---                                                                                     424, 515. 37
              Balance unexpended June 30, 1944- -.---...-.---.---.-.                                                   61, 786. 66
              RIVERS AND HARBORS-SAVANNAH,              GA.,    DISTRICT         485
Outstanding liabilities June 30, 19~44 --------------       $105. 12
Amount covered by uncompleted contracts---_ -------       20, 366. 40
                                                                          $20, 471. 52

      Balance available June 30, 1944------------------------41, 315. 14
Accounts receivable June 30, 1944 ---------------------------- 17, 518..23
     Unobligated balance available June 30, 1944--------------58, 833. 37
Amount allotted in July 1944-------------------------------174, 000. 00
        Amount available during fiscal year 1945-__     -- -- --- - ---   232, 833. 37

Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 1---  _           __---------377,              000. 00
I Exclusive of available funds.


            4. ALTAMAHA, OCONEE, AND OCMULGEE RIVERS, GA.

   Location.-These rivers are located entirely within the State of
Georgia. (See U. S. Geological Survey map of Georgia.) For full
description of these rivers, see page 636, Annual Report for 1932.
   Previous projects.-Prior to the present one, projects had been
adopted and expenditures made under them for the Altamaha River
by River and Harbor Acts of March 3, 1881, and September 19, 1890;
for the Oconee River by River and Harbor Acts of June 18, 1878,
September 19, 1890,. and March 3, 1905, for the Ocmulgee River,
August 14, 1876, and September 19, 1890.
   For further details, see page 1815 of Annual Report for 1915, and
page 589 of Annual Report for 1938.
   Ewisting project.-This contemplates an appropriation of $40,000
annually for the Altamaha, Oconee, and Ocmulgee Rivers, to be ap-
plied, following in general the methods which had been carried on
under the previous projects, to maintenance of 3-foot depth during
ordinary summer low water and to the gradual increase of channel
depth, so far as practicable, without sacrificing the maintenance work.
These methods are the removal of rock shoals, snags, overhanging
trees, and other obstructions; the closing of incipient cut-offs; the
revetting of caving banks; and the use of spur dikes and training
walls. The width of channel was not specified, but it should vary
from 60 to 100 feet, according to locality. This project covers the
entire Altamaha River (including a channel between the river and
Darien, Ga.), a length of 137 miles, the lower 145 miles of the Oconee
River, and the lower 205 miles of the Ocmulgee River. The Altamaha
River has a mean tidal range of 6.4 feet at its mouth, which gradually
decreases to mile 33 above, where there is no perceptible tidal effect.
At Doctortown, mile 59, ordinary floods attain a height of about 10
feet above low water, and extreme floods a height of about 15 feet
above low water.
   On the Oconee River at Dublin the ordinary fluctuations attain a
height of 22 feet, and the extreme fluctuations a height of 32 feet
above low water. On the Ocmulgee River at Macon the ordinary
fluctuations attain a height of 15 feet, and the extreme fluctuations a
height of 25 feet above low water. There is no approved estimated
cost for improvement or for maintenance.
   The existing project was adopted by the River and Harbor Act of
July 25, 1912 (H. Doc. No. 443, 62d Cong., 2d sess.). The latest pub-
lished maps of these rivers are in the following documents: Alta-
486      REPORT OF CHIEF OF ENGINEERS,            U. S. ARMY,    1944

maha River, House Executive Document No. 283, Fifty-first Congress,
second session; Oconee River, House Executive Document No. 211,
Fifty-first Congress, first session; and Ocmulgee River, House Execu-
tive Document No. 215, Fifty-first Congress, first session.
   Terminal facilities.-Along these rivers there are numerous natu-
ral shore landings. These are considered ample for existing
connexrce.
   Operations and results during fiscal year.-U. S. snagboat No. 1
operated periodically on maintenance snagging, removing 2,365 ob-
structions from the Altamaha River between mile 13 and mile 117.
No work was done on the Oconee or Ocmulgee Rivers during the
fiscal year. The total cost of snagging operations was $12,452.30.
Surveys and inspections were made at a cost of $587.69.
   The total cost was $13,039.99, all for maintenance. The total ex-
penditure was $13,029.81.
   Condition at end of fiscal year.-The existing project is of such a
nature that the percentage of completion cannot be stated. Channel
depths have been increased by the excavation of rock shoals and sand
bars, by the construction of contraction and bank-protection works,
and by the closing of cut-offs. Navigation has been rendered safer
by removal of obstructions. Many of the closing dams and contrac-
tion and bank-protection works need repairs.
   For about 9 months of the fiscal year 1944, the controlling depths
were equal to or greater than the following:
Altamaha River:                                                              Feet
    Mouth to mile 75 -4.                                                        5
    M ile 75 to Forks (mile 137) ... . . . .  .. .. . . .       .  . .    . 3.0
Oconee River:
    Forks to Dublin (mile 78)-                    -                          2. 5
    Dublin to Milledgeville (mile 145) -1.0
Ocmulgee River:
    Forks to mile 73_ _2.0
    Mile 73 to Macon (mile 205) -1.                                             0
  The low-water period usually occurs between August and November, during
which time controlling depths are from / to 1% feet less than those given.above.
  To June 30, 1944, the costs under the existing project were $60,847.16
for new work and $844,105.13 for maintenance, a total of $904,952.29.
The total expenditures were $904,930.15.
  Proposed operations.-The balance unexpended June 30, 1944, $2,-
333.26, plus allotment of $8,500 dated July 3, 1944,,a total of $10,833.26,
will be applied as follows:
Accounts payable June 30, 1944               -$22.                          14
Maintenance: Snagging with U. S. snagboat No. 1 on the Altamaha
  River between mouth and forks and on the lower 20 miles of Ocmul-
  gee River, 3% months between Aug. 1, 1944, and June 30, 1945 _ - 10, 811. 12
       Total for all work--                                             10, 833. 26
   The additional sum of $25,200 can be profitably expended during the
fiscal year 1946 in snagging with the U. S. snagboat No. 1 on the Alta-
maha River between the mouth and forks, 3 months, July 1 to 30, 1945,
and May 1, 1946, to June 30, 1946; on the Ocmulgee River between the
forks and Macon, Ga., 4 months August 1, 1945, to November 31, 1945;
and on the Oconee River between forks and 12 miles above Dublin, Ga.,
2 months, December 1, 1945, to January 31, 1946.
                       RIVERS        AND HARBORS-SAVANNAH,                                      GA.,        DISTRICT                    487
                                         Cost and financial summary
Cost of new work to June 30, 1944_                                                                                          $821, 457. 42
Cost of maintenance to June 30, 1944                                   -     --                    --                         956, 055. 45

      Total cost of permanent work to June 30, 1944-                                                   -                   1, 777, 512. 87
Minus accounts payable June 30, 1944                                                                        - -                     22. 14
              Net total expenditures                                                                                       1, 777, 490. 73
Unexpended balance June 30, 1944                                                  --                                               2, 333. 26

             Total amount appropriated to June 30, 1944_                                                   - - --          1, 779, 823. 99


     Fiscal year ending June 30                    1940               1941               1942                       1943             1944

Cost of new work _....
Cost of maintenance _-                       $32, 583.57          $32, 663. 14         $23, 018. 57           $14, 359. 29          $13, 039.99
Total expended               - -..                32, 757.88       38,433. 40          23,029.13                14, 934. 46          13, 029.81
Allotted---------.........       -                35,000.00        21,000.00           15, 500.00               12,500.00 -- - - -- - -


Balance unexpended July 1, 1943 ......                                                                                        $15, 363. 07
Gross amount expended_                                                                                                     -13,      029. 81

      Balance unexpended June 30, 1944 _                                                                     ----                  2, 333.26
Outstanding liabilities June 30, 1944 -..                                                                                              22.14
     Balance available June 30, 1944                              -                                                                2, 311. 12
Amount allotted in July 1944__                                                                                                     8, 500. 00
             Amount available during fiscal year 1945-                                          -10,                                 811. 12
Amount that can be profitably expended in fiscal year ending June
                                         1
  . 30, 1946 for maintenance                 --    _      _-_-_                                                      _            25, 200.00
   1 Exclusive of available funds.



                                       5. BRUNSWICK HARBOR, GA.

  Location.-The harborentrance is 70 statute miles south of entrance
to Savannah Harbor, Ga., and 25 statute miles north of entrance to
Fernandina Harbor, Fla. (See U. S. Coast and Geodetic Survey Chart
No.447.)
     Previous projects.-Adopted by River and Harbor Acts of July 4,
1836; August 5, 1886; June 3, 1896; and June 13, 1902.                                                                     For further
details see page 1818 of Annual Report for 1915 and page 591 of
Annual Report for 1938.
  Existing project.-This provides for a stone jetty 4,350 feet long at
the entrance to East River and for the following channels:
         30 feet deep and 500 feet wide through the bar;
         27 feet deep and 400 feet wide at Brunswick Point;
         27 feet deep and 350 feet wide in East River;
         27 feet deep and 300 feet wide in Turtle River;
         24 feet deep and 150 feet wide in Academy Creek; and
         A cut from Academy Creek to Turtle River, if later decided advisable.
         A channel in Back River 20 feet deep and 150 feet wide from St. Simons
            Sound to the mouth of Mill Creek.
         A channel in Terry Creek 10 feet deep and 80 feet wide from its mouth to a
           point immediately above the wharf of the Glynn Canning Co.
488           REPORT OF CHIEF OF ENGINEERS,                              U. S. ARMY,          1944

   The channels provided for extend from the 30-foot contour in the
ocean across the bar through St. Simons Sound, Brunswick River and
Turtle River to the upper end of the Atlantic Refining Co.'s wharf,
20.4 miles; from Brunswick River through East River to the upper
end of the project in Academy Creek, 2.7 miles; from St. Simons Sound
through Back River to Mill Creek, the upper end of Back River im-
provement, 2.9 miles; from Back River through Terry Creek to the
upper end of the Glynn Canning Co.'s wharf, 1.8 miles; a total distance
of 27.8 miles.
   All depths refer to mean low water. The mean tidal range on the
bar is 6.5 feet, at the city of Brunswick 7.3 feet, and at the upper end of
the harbor 7.6 feet, with minor fluctuations due to wind and lunar
effects.
   The estimated cost of new work, revised in 1938 (exclusive of
amounts expended on previous projects), is $2,242,800, including $10,-
000 contributed by local interests. The latest (1938) apprpved estimate
for annual cost of maintenance is $156,700.
   The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                      Documents


Mar.     3,1879   Construction of East River jetty .....--------------   Annual Report, 1880, p. 959.
Mar.     2,1907   For channels in the inner and outer harbors of         H. Doe. No. 407, 59th Cong., 1st sess.
                    30-foot depth at mean high water, with widths
                    varying from 150 feet in Academy Creek to 400
                    feet across the outer bar, extension of training
                    wall in East River, and construction of two
                   spur dikes.
Mar.     2,1919   Channels 27 feet deep at mean low water over the        H. Doe. No. 393, 64th Cong., 1st sess.
                    bar and at Brunswick Point; and 24 feet deep at
                    mean low water in the inner harbor, and pro-
                    vides for a cut from Academy Creek to Turtle
                    River, if deemed advisable.
fuly     3,1930   A channel in Back River 20 feet deep and 150 feet      S. Doc. No. 57, 71st Cong., 2d sess.'
                    wide.
                                                                                                                   1
   Do--.......    Increased channel dimensions of the bar, Bruns-         S. Doc. No. 132, 71st Cong., 2d sess.
                    wick Point, East River, and Turtle River, as
                    given in the existing project.
June 20,1938      A 10-foot channel in Terry Creek--------. ------        I. Doc. No. 690, 75th Cong., 3d sess.'


  1Contain the latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-This improvement is served by 25 wharves
and piers (20 in East River, 2 in Turtle River and 3 in Terry Creek)
having a total berthing space of 9,191 feet. Four wharves are owned
by railroads and 1 is a small public wharf. The remainder are pri-
vately owned. In a majority of cases the structures are of a pile and
timber construction. These facilities are considered ample for exist-
ing commerce. (For further details see Port Series No. 10, Corps
of Engineers, revised 1940.)
  SOperations and results during fiscal year.-No work was done in
Brunswick Harbor during the fiscal year. Miscellaneous surveys were
made at a cost of $1,635.77, for maintenance. The total expenditure
was $1,811.38.
                RIVERS             AND HARBORS-SAVANNAH,                                                GA.,     DISTRICT                  489

   Condition at end of fiscal year.-The existing project was completed
in 1939. Academy Creek was completed in 1926. Upper and Lower
Turtle River and Back River were completed in 1931. Brunswick
Point and East River were completed in 1932. Brunswick Bar was
completed in 1936. Terry Creek was completed in 1939. East River
trainingwall and spur dike are in satisfactory condition.
   The controlling depths, at mean low water, were as follows:

                                                                                              Project         Controlling
                                   Locality                                                    depth
                                                                                             mean  low          centeron Date determined
                                                                                                               depth
                                                                                               water            range

                                                                                                 Feet             Feet
Bar .........        ....--------------------------------------------------                        30.0              28.0     March 1944.
Brunswick River:
    Cedar Hammock Range --------------------------------                                              27.0            28.0    January 1944.
    Brunswick Point Cut Range .----------------------------                                           27.0            29.0        Do.
East River__ ---------------------------------------------                                            27. 0           23. 0   March 1944.
Academy Creek -----------------------------------------                                               24.0            10. 3   May 1943.
Lower Turtle River --------------------------------------                                             27.0            26. 5   January 1944.
Upper Turtle River .--------------------------------------                                            27.0            26.0        Do.
Back River ..--------------------------------------------                                             20.0            10.9    May 1943.
Terry Creek      --------------------------------------------                                         10.0             3.3        Do.



  The costs and expenditures on the existing project to June 30, 1944,
were as follows:

                                                                              Regular funds             Public Works               Total


N ew wo rk . . . .   ... . . . .           ... . .    ..      .....            $2, 12 8, 6 0 0 . 29           $97 , 520. 95      $2, 22 1, 12 1. 24
Maintenance                  -----------                                        2, 100, 839.86                  4,995.08          2,105,834. 94

     Total_                                                                     4, 224, 440.15                102, 516.03         4, 326, 956.18
Expenditures _-                                                                 4, 224, 440. 15               102, 516.03         4, 326,956.18



   In addition, the total cost and expenditure from contributed funds
was $10,000 for new work.
  Proposed operations.-The balance unexpended June 30, 1944,
$1,473.30, plus allotment of $30,000 dated July 3, 1944, a total of
$31,473.30, will be applied as follows:
Maintenance:
      Dredging with United States hopper dredge on the inner and
       outer harbor, 2 month between Jan. 1, 1945, and June 30,
        1945     --------------------------------------------- $23, 973. 30
      Dredging with U. S. pipe-line dredge Creighton in Terry Creek
        2/5month between July 1, 1944, and June 30, 1945---_ ------- 7, 500. 0

             Total for all work                      ----------------------------------                                          31. 473. 30
  The additional sum of $188,500 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredging with United States hopper dredge in the inner and outer
      harbor, 4 months between Jan. 1, 1946, and June 30, 1946-. $180, 000
    Dredging with the U. S. pipe-line dredge Creighton in Terry Creek
       Smonth between July 1, 1945, and June 30, 1946 __-----         8, 500

              Total for all work                     -----------------------------------                                            188, 500
490              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                  1944

                                                      Cost and financial summary
Cost of new work to June 30, 1944_             -$2,                                                        1      864, 586. 42
Cost of maintenance to June 30, 1944_-----------                                                  _            2, 160, 249. 01

            Total cost of permanent work to June 30, 1944                               ---------              5, 024, 835. 43

      Net total expenditures-- __-__-_- --                               -     --                 __        1'5, 024, 835. 43
Unexpended balance June 30, 1944_                                                                                       , 473. 30
                                                                                                                       1----------
            Total amount appropriated to June 30, 1944---                                         -            5, 026, 308. 73

    Fiscal year ending June 30                          1940           1941          1942               1943             1944

Cost of new work........--------------                $23, 339.42
Cost of maintenance .        -...                      69, 253. 48   $55, 655. 50   $6, 428.44        $78, 712. 94       $1, 635.77

        Total cost................----------------.    92, 592. 90    55, 655. 50    6, 428.44         78, 712.94          1,635. 77
Total expended------ ----------                        92, 592. 90    55, 120.93     6, 262. 59        79, 237.75          1, 811.38
Allotted..----------------------........               49, 339.42     45, 000.00    52, 000. 00        10,000. 00       -60,000.00


Balanice unexpended July 1, 1943_ __                                                                                 $63, 284. 68
Dedu ctions on account of revocation of allotment---------                                                            60, 000. 00

       Net amount to be accounted for-                                                                                 3, 284. 68
Gross amount expended___                                                                                               1, 811. 38
      Balance unexpended June 30, 1944---------------                                                                  1,473. 30
Amou nt allotted in July 1944_                      _30,                                                                  000. 00

          Amount available during fiscal year 1945------------31,                                                         473. 30
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance2 _ _ _                                                                               188, 500. 00
  I In addition, $10,000 contributed funds expended for new work.
  2 Exclusive of available funds.


                                                      6. SATILLA RIVER, GA.

  Location.-This river has its headwaters in southern and south-
eastern Georgia, flows in a generally southeasterly direction, and
empties into the Atlantic Ocean through St. Andrew Sound. (See
U. S. Geological Survey map of Georgia.)
  Existing project.-This provides for the removal of snags and
similar obstructions from the mouth to Burnt Fort:,a distance of 52
miles, and the removal of obstructions and the closing of incipient
cujt-offs from Burnt Fort to Waycross, a distance of 114 miles. The
mean tidal range is 6.6 feet at the mouth and 3.2 feet at Burnt Fort,
with minor fluctuations due to wind and lunar effects. The freshet
variation at Waycross is about 12 feet.
   The original and latest approved estimate of cost, made in 1912, was
$20,000, divided equally between the two portions of the river. The
latest (1928) approved estimate for annual cost of maintenance is
$2,000.
                  RIVERS       AND       HARBORS--SAVANNAH,                      GA., DISTRICT                       491"
  The existing project was authorized by. the following river and
harbor acts:

       Acts                        Work authorized                                         Documents


July 25,1912       Improvement of river from the mouth to Burnt              H. Doc. No. 41, 62d Cong., 1st sess.
                     Fort.
Mar.     4,1913    Improvement of river from Burnt Fort to Way-              H. Doc. No. 1113, 62d Cong., 3d sess.'
                    cross.



  1 Contains the latest published map of the upper section of the river.             The latest published map of the
lower section of the river is the U. S. Coast and Geodetic Survey Chart No. 450.

    Terminalfacilities.-Small wharves are located at five main loading
points, and in addition there are numerous natural landings along
the river. These facilities are considered sufficient for existing com-
merce.
    Operations and results during fiscal year.-No work was done on
the Satilla River during the fiscal year.
    Condition at end of fscal year.--The existing project was com-
Spleted in 1914. The controlling depths, as determined by a survey
made in June 1939, were as follows: The mouth to Owens Ferry, 8.8
feet; Owens Ferry to Burnt Fort, 4.5 feet; thence to Waycross, the
head of navigation, about 1 foot. These depths are at ordinary sum-
mer low water except in the tidal section from the mouth to Owens
Ferry, where the depth refers to mean low water. These depths are
practicable throughout the year.
    The costs and expenditures under the existing project to June 30,
1944, were $9,451.59 for new work and $36,439.31 for maintenance, a
total of $45,890.90.
   Proposed operations.-No funds are available and no work is con-
templated during fiscal year 1945.
    The sum of $4,000 can be profitably expended during the fiscal
year 1946 in snagging with U. S. snagboat No. 1, 11/2 months.
                                         Cost and financial summary
Coat of new work to June 30, 1944---------------------------  $9, 451. 59
Cost of maintenance to June 30, 1944-------------------------36, 439. 31
       Total cost of permanent work to June 30, 1944-                                        -   -             45, 890. 90
Net total expenditures --------------------------------                                                        45, 890. 90
Total amount appropriatcd to June 30, 1944---- ----------------                                                45, 890. 90

   Fiscal year ending June 30               1940               1941           1942           1943                  1944
Cost of new   work-.--            -
Cost of maintenance ....----------- --     $3, 879.76
                                                     ----
                                                        _---
                                                          -.     -
                                                                      -.
                                                                      -
                                                                            ----------
                                                                           -.........
                                                                                            ---$2,-0  ---
                                                                                               $2,500 -
                                                                                                                   -- _....


Total expended         .....                  3, 879.76 ---
                                ..------------------                                                 2, 500-
                                                                                                     2-----
Allotted........             ........         -- 20. 24                         $2, 500------_--- ----
                                                                                                    __ -------

Amount that can be profitably expended in fiscal
                                                                year ending June 30,
1946, for maintenance     ------------------------------------                      $4, 000. 00
492      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                     1944

                     7. ST. MARYS RIVER, GA. AND FLA.
   Location.-This river has its source in the Okefenokee Swamp and
flows, first in a southeasterly direction and then due north, thence in
a southeasterly direction, and empties into Cumberland Sound about
3 miles north of Fernandina, Fla. (See U. S. Geological Survey map
of Georgia.)
   Ewisting project.-This provides for a channel 17 feet deep at mean
low water with a width of 200 feet from the mouth to Crandall, 12.5
miles, and for clearing the channel of snags to Kings Ferry, 37 miles
above the mouth, and as much farther as may be practicable, for a
sum of $5,000. The upper limit reached by this expenditure was
Traders Hill, 59 miles above the mouth. The mean tidal ranges are
as follows: At the mouth, 5.8 feet; at the Atlantic Coast Line Rail-
road bridge, 55 miles above the mouth, 1.4 feet, with minor fluctua-
tions due to wind and lunar effects. Freshet fluctuations on the upper
portions are about 10 feet.
   The original and latest approved estimate of cost of new work,
made in 1912, was $19,450. The latest (1915) approved estimate of
cost for annual maintenance is $2,500.
   The existing project was adopted by the River and Harbor Act of
July 25, 1912 (H. Doc. No. 697, 62d Cong., 2d sess.). The latest pub-
lished map is in the project document.
   Recommended modifications of project.-Reduction of project depth
from 17 to 14 feet from St. Marys to Crandall, is recommended in
House Document No. 467, Sixty-ninth Congress, first session.
   Terminal facilities.-At St. Marys, Ga., there is a 50-foot municipal
wharf and several privately owned wharves, together with 446 feet
of wharf frontage in North River. Above St. Marys there are a
number of privately owned wharves and shore landings. These facili-
ties are considered ample for existing commerce.
    Operationsand results during fiscal year.-No work was done on the
St. Marys River during the fiscal year.
   Condition at end of fiscal year.-The existing project was completed
in 1914. The controlling depths at mean low water, as determined by a
survey made in June 1939, were as follows: The mouth to St. Marys
 (determined in May 1943), 13.8 feet; St. Marys to Kings Ferry, 11.3
feet; Kings Ferry to the Atlantic Coast Line Railroad bridge, mile 55,
5.6 feet; and Atlantic Coast Line bridge to Traders Hill, mile 59
 (the head of navigation), 4 feet. These depths are practicable
throughout the year.
   The costs and expenditures under the existing project to June 30,
1944, were $15,688.36 for new work and $55,265.46 for maintenance, a
total of $70,953.82.
   Proposed operations.-No funds are available and nowork is con-
templated during fiscal year 1945.
   The sum of $4,000 can be profitably expended during the fiscal year
1946 in snagging with U. S. snagboat No. 1, 11/2 months.
                          Cost and financial summary
Cost of new work to June 30, 1944__ -----------------------               $15,688. 36
Cost of maintenance to June 30, 1944_--------                 ------       55, 265. 46
       Total cost of permanent work to June 30, 1944 -----------              70, 953. 82
Net total expenditures-------------------------------------                   70, 953.82
Total amount appropriated to June 30, 1944- -------------------               70, 953. 82
                  RIVERS AND            HARBORS-SAVANNAH,                          GA.,     DISTRICT                493

    Fiscal year ending June 30                1940            1941              1942          1943              1944

Cost &f new work... . . .           .    .       .    .   .     .    .     .      .    .     .- -.    .    .
Cost of maintenance ..-.                     $3,629.02                            ....-          $2,500 ..

Total expended      .        ..               3,629. 02                                              ,5 0.
Allotted--------. _                 -         -270. 98    -                       $2,500-            -          -
Amount that can be profitably expended in fiscal year ending
                                                             June 30,
    1946, for maintenance ----------------------------------------                                           $4, 000.00

                                  8. FERNANDINA HARBOR, FLA.

   Location.-The harbor entrance is 221/2 statute miles north of the
entrance to Jacksonville Harbor, Fla., and 95 statute miles south of
the entrance to Savannah Harbor, Ga. (See U. S. Coast and Geodetic
Survey Chart No. 453.)
   Existing project.-This provides for two stone jetties at the harbor
entrance, the north jetty 19,150 -feet long and the south jetty 11,200
feet long; for a channel 28 feet deep at mean low water from the
deep water in the Atlantic Ocean to deep water at the junction of
Lanceford Creek with Amelia River, with widths of 400 feet below
Calhoun Street in the city of Fernandina, and 300 feet above; and
for widening the channel at the first bend below Lanceford Creek to
1,000 feet to form a turning basin. The length of the section included
in the project is about 7 miles. The mean tidal range on the bar is
5.8 feet and in the inner harbor 6 feet, with minor fluctuations due to
wind and lunar effects.
   The estimated cost of new work, revised in 1938, is $3,326,900. The
latest (1938) approved estimate for annual cost of maintenance is
$31,000.
   The existing project was authorized by the following river and
harbor acts:

       Act                          Work authorized                                         Documents



June 14,1880      Entrance jetties_ _           -           -                  Annual Report, 1879, p. 792.
July 13,1892      Raising and extending jetties so as to provide for           Annual Report, 1891, pp. 1565-1598;
                    19-foot depth.                                              Annual eport, 1896, p. 1289.
Mar.    2, 1907   Improvement of inner harbor to obtain depths of              H. Doc. No. 388, 59th Cong., 1st sess.
                    20 to 24 feet and channel widths of 400 to 600 feet.
June 25, 1910     Combining improvement of Fernandina Harbor
                    and Cumberland Sound under the general head-
                    ing of "Fernandina Harbor."
Mar.    3, 1925   Provided for the 26-foot channel---- .---------          H. Doc. No. 227, 68th Cong., 1st sess.
June 20, 1938     Provided for the 28-foot channel and turning basin       H. Doc. No. 548, 75th Cong., 3d sess.
                                                                            (Contains the latest published maps.)


   Recommended modifications of project.--Under date of March 20,
1941, the Chief of Engineers recommended modification of the existing
project so as to provide for reducing the maximum width of the turn-
ing basin from 1,000 feet to 800 feet, shifting the southerly channel
line in this vicinity 50 feet northwesterly, and for including in the
authorized project at no additional cost the small area dredged by
Rayonier Inc. (H. Doc. 284, 77th Cong., 1st sess.).
494          REPORT OF CHIEF OF ENGINEERS,                                                 U. S. ARMY,                 1944

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are 16 wharves and piers (including a
municipal wharf) having a total berthing space of 4,973 feet located
along the 2 miles of water frontage. The present facilities are con-
sidered ample for existing commerce. (For further details, see Port
and Terminal Facilities at the Ports of Fernandina, Fort Pierce
Harbor, Palm Beach, Fort Everglades, Miami, Key West, and Tampa,
Fla., 1941 Edition, Corps of Engineers).
   Operations and results during fiscal year.-A survey of the harbor
was made at a cost and expenditure of $713.17.
   Condition at end of fiscal year.-The existing project was completed
in 1940. The two stone jetties were completed in 1905 and are in need
of repairs. The 28-foot channel in the outer harbor and in the inner
harbor and the turning basin were completed in 1940. Controlling
depths at mean low water, as determined in May and December 1943,
were 21.4 feet over the outer harbor, 26.5 feet over the inner harbor,
and 21.1 feet in the turning basin.
   The costs and expenditures under the existing project to June 30.
1944, were $3,286,818.06 for new work and $752,891.24 for maintenance,
a total of $4,039,709.30.
   Proposedope'rations.-Thebalance unexpended June 30,1944, $41.37,
plus allotment of $25,000 dated July 3, 1944, a total of $25,041.37, will
be applied to maintenance dredging with United States hopper dredge
in 28-foot channel on outer bar one-half month between January 1,
1945, and June 30, 1945.
   The additional sum of $75.000 can be profitably expended during
fiscal year 1946, as follows:
Maintenance:
    Dredging, by contract, the inner harbor with pipe-line dredge, 1
      month between July 1, 1945, and June 30, 1946                  $50, 000                 -----
    Dredging with United States hopper dredge in 28-foot channel on
      outer bar, % month between Jan. 1, 1946, and June 30, 1946      25, 000                                          --
           Totalforall work --------------------                                                                                 75,000
                                                Cost and financial summary
Cost of new work to June 30, 1944 -        --                                                               -           $3, 286, 818. 06
Cost of maintenance to June 30, 1944- ---------------                                                                       752, 891. 24
           Total cost of permanent work to June 30, 1944                                        -           -            4, 039, 709. 30

Net total expenditures ----- -- ---_-- ---                                       --      ---                           ,4,
                                                                                                                        ,- 039, 709. 30
Unexpended balance June 30, 1944_                                                     ----- -_                  _41.                 37

           Total amount appropriated to June 30, 1944_                                                                   4, 039, 750. 67

   Fiscal year ending June 30                     1940                    1941               1942                1943            1944

                   .............. $97, 925. 91
Cost of new work--------------                                 -------.                   --.....       .   --.. ....        ,....    ..
Cost of maintenance_-............      347. 33                        $2, 500.00      _       $653.83             $591. 63           $713. 17
                      -
      Total cost ......             .....        98, 273. 24              2, 500.00            653.83              591.63             713. 17

Total expended_                          _    98, 273. 24
                                       __-...........                     2, 500.00            653.83              591. 6:            713. 17

Allotted    ---------------------------------
            ....                                                                  .............-- 15,000.00
                                                                      20, 226. 76-------------
                RIVERS AND                 HARBORS--SAVANNAH,                            GA.,     DISTRICT                        495
Balance unexpended July 1, 1943_                                                                                 -        $754. 54
Gross amount expended_------------                                                                ----                     713. 17
     Balance unexpended June 30, 1944---------------------                                                                   41. 37
Amount allotted in July 1944_                                                                                           25, 000. 00

           Amount available during fiscal year 1945-----------25,                                                             041. 37

Amount that can be profitably expended in fiscal year ending June
  30, 1946 for maintenance 1       _     _____75,                                                                             000. 00
1Exclusive of available funds.

      9. EXAMINATIONS,                   SURVEYS, AND CONTINGENCIES (GENERAL)

  The cost of work during the year amounted to $41,470.49. The ex-
penditures were $39,828.72. The balance unexpended June 30, 1944,
$13,070.95, plus $27,000 allotted in July 1944, will be applied as needed
during the fiscal year 1945 to payment of expenses incurred under this
heading. The additional sum of $35,000 can be profitably expended
during the fiscal year ending June 30, 1946.
                                           Cost and financial summary
Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944--                                  --------                                 1 $495, 123. 92
      Total cost of permanent work to June 30, 1944-----------                                                         495, 123. 92
Minus accounts payable June 30, 1944___                                                                                  2, 871. 22
      Net total expenditures- ___                          --------                               ___             1 492, 252. 70
Unexpended balance June 30, 1944                                                                                     13, 070. 95
           Total amount appropriated to June 30, 1944 ------------- 1 505, 323. 65


      Fiscal year ending June 30              1940               1941                1942                 1943                 1944

Cost of new work -
Cost of maintenance                         $38, 218. 29      $71, 128.12          $34, 670. 56      $32, 726. 21             $41, 470. 49
                ...-----.
Total expended-----            -------       42, 052. 83       68, 871. 58          32, 827. 21          35, 227. 08           39, 828. 72

Allotted..........----------------------    169, 300. 00       17, 500. 00                               16, 000. 00    ___



Balance unexpended July 1, 1943__                                                                                      $52, 899. 67
Gross amount expended_---         -------------                                                                         39, 828. 72
      Balance unexpended June 30, 1944----------------------                                                            13, 070. 95
Outstanding liabilities June 30, 1944--- ---         ___2,                                                                  871.22
     Balance available June 30, 1944_--                                              - --         ___                   10, 199. 73
Amount allotted in July 1944_---   -----------                                                                          27, 000. 00

           Amount available during fiscal year 1945------- ---------                                                    37, 199. 73
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 2-      -     _-    -_-  _---                                                            35, 000. 00
  1 In addition there was expended $1,800 contributed funds.
  3 Exclusive of available funds.
496            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

   10. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES
                       ARE SUBMITTED

                                                                      For last        Expenditures to June 30,
                                                                      full re-                 1944                             Estimated
                      Name of project                                 port  see                                                 amount   re-
                                                                                                                                 quired to
                                                                      Annual
                                                                      Report          New work           Maintenance             complete
                                                                       for-

1. Savannah River at Augusta, Ga.
                                              1--------------           1929      2   $200, 556.30             $17, 443.70      Completed.
2. Savannah River above Augusta, Ga. 3--------                          1929            69, 599.99               5,870.01          (4).
3. Sapelo Harbor, Ga.' 3 .......... __ _                _-_--
                                                           - ..         1929           17, 905.73               17,094.27       Co ipleted.
4. Darien Harbor, Ga.         ..-...  .................                 1929      * 6 199, 722.65               42, 343. 28         Do.
5. Fancy Bluff Creek, Ga.....................---------------------.     1935             8,000.00                4,200.00          Do.

   1Project recommended for abandonment in H. Doc No. 467, 69th Cong., 1st sess.
  2 In addition, $185,000 was expended from contributed funds: $172,150.72 for new work and $12,849.28
for maintenance.
   2 No commerce reported.
   4 About 84 percent completed. Owing to construction of 2 power dams which have submerged much of
the work under the present and former projects, this improvement cannot be completed as originally
planned.
  3 Channel adequate for commerce.
   6 Includes $54,929.44 expended on Doboy Bar.


                11. PLANT ALLOTMENT, SAVANNAH, GA., DISTRICT
                                              Cost and financial summary
Undistributed costs June 30, 1944_-                                   - ----------                                           $766, 099. 72

Net total cost to June 30, 1944_  ---------             --     -766, 099.72
Plus accounts receivable June 30, 1944------------------------   106, 195. 58
      Gross total costs to June 30, 1944                              ----------------                                        872, 295. 30
Minus accounts payable June 30, 1944------------------                                                                        112, 338. 52
      Net total expenditures_  ---------                                                                ----                  759, 956.78
Unexpended balance June 30, 1944_-                                     - ----------                                           234, 399. 02
           Total amount appropriated to June 30, 1944--                                      ------------                     994, 355. 80


    Fiscal year ending June 30                    1940                 1941              1942                    1943              1944


Total expended....---------------$235, 296.00                     $167, 904.01        $124, 092.66       -$306, 228.99            $22, 985.65
Allotted_--------------------_157, 564. 47                         175, 369. 30         21, 874. 09..



Balance unexpended July 1, 1943 ---------------------------     $257, 384. 67
Gross amount expended_ -----.------------         $344, 619. 72
Less:
        Reimbursements collected.....-------- $320, 466. 84
        Receipts from sales --------------       1, 167. 23
                                                                       -_____            -      321, 634. 07
                                                                                                                        --     22, 985. 65
      Balance unexpended June 30, 1944__                                           -----                                --    234, 399. 02
Outstanding liabilities June 30, 1944_-------                                                           -   ___               194, 956. 44
     Balance available June 30, 1944_    -------        -___                                                                  '39, 442. 58
Accounts receivable June 30, 1944 ----------------------------                                                                 106, 195. 58
            Unobligated balance available June 30, 1944 -.                                                                    145, 638. 16
                         FLOOD CONTROL----SAVANNAH,                                    GA.,       DISTRICT                             497
Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                                    Date trans.-Re.ommenda-
             Locality                  Authorization act             mitted to      Document No.                            Reconend-
                                                                     Congress

St. Marys River, Ga. and              Sec. 1 of River and                                  ..
  Fla., for navigation,                 Harbor Act, Jan. 21,
  flood control, power and              1927.
  irrigation (supplemental
  308eport)...
Savantinh Harbor, Ga-.....            Rivers and Harbors .                       ...
                                       Committee resolu-
                                       tion, Nov. 4, 1939.
Savannah River, Ga, from              Rivers and Harbors_
  Kings Island to the                   Committee resolu-
  Coastal Highway Bridge.               tion, Oct. 28, 1937.
Savannah River, Ga. (sup-             Sec. 6 of River and __.. .. .__.....                                  ...       .
  plemental 308 report).                Harbor Act, Aug.
                                        30, 1935.
Savannah, Ga., to St. Johns           Rivers and Harbors .................
  River, Fla., Intracoastal             Committee resolu-
  Waterway-branch water-                tion, Feb. 8, 1944.
  way via Shell Bluff Creek
  to the vicinity of Valona,
  Ga.



12. PRELIMINARY                       EXAMINATIONS, SURVEYS,                                    AND        CONTINGENCIES
                                          FOR FLOOD CONTROL

   The cost of work during the fiscal year was $42,887.55. The ex-
penditures were $46,095.47. The balance unexpended June 30, 1944,
$15,609.44, plus an allotment of $50,000 in July 1944, will be applied
to payment of expenses incurred under this heading.
   The additional sum of $195,000 can be profitably expended during
the fiscal year ending June 30, 1946.
                                           Cost and financial summary
Cost of new work to June 30, 1944___
Cost of maintenance to June 30, 1944--                              ...-------                                            $285, 465. 31
       Total cost of permanent work to June 30, 1944------------285, 465. 31
Plus accounts receivable June 30, 1944_
                                     -------------------------       196. 52
      Gross total costs to June 30, 1944_                                 -    ------                             -         285, 661. 83
Minus accounts payable June 30, 1944_                                    -      --          ---                   -   ---        771. 27
      Net total expenditures -------------------------------                                                                284, 80. 56.
Unexpended balance June 30, 1944_-_ _-----                                                        -----                      15, 609. 44
            Total amount appropriated to June 30, 1944--------------300, 500. 00

     Fiscal year ending June 30                 1940              1941                   1942                 1943                  1944

C ost of new w ork ..   - - --.           --.    - - - -. -. - - - -.            -. ----.        .    ..    .. . . . .          -     - -- - -
Cost of maintenance-...-_.......            $22,387.10          $20,990.22             $79, 927.98         $98, 899. 61         $42,887. 56
Total expended_ _---------------19, 531.46                       20, 975. 56            43, 777. 33        134, 462. 74             46,095. 47
Allotted --------------------------                    ------    19,100.00             102,500.00           76, 700.00              20, 000. 00




           616634-45-pt. 1, vol. 1-                32
498             REPORT OF CHIEF OF ENGINEERS,                                          U.. S. ARMY,             1944

Balance unexpended July 1, 1943_ ------         -   --     --                                                         $41, 704. 91
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941-----------------------------------                                                             20, 000. 00
      Amount to be accounted for                                                                                       61, 704. 91
Gross amount expended-   ---     --                                 -----------                                        46, 095. 47
       Balance unexpended June 30, 1944-----------------                                                                15, 609. 44
Outstanding liabiliti-JJunia30, 1944_ ---  -----------                                                                       771. 27

      Balance available June 30, 1944                                        -------                                    14, 838. 17
Accounts receivable June 30, 1944                                                              ---                          196. 52
     Unobligated balance available June 30, 1944-- -----------                                                          15, 034. 69
Amount allotted in July 1944 -----------------------------                                                              50, 000. 00
           Amount available for fiscal year 1945                            --------------                              65, 034. 69

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1 --------------------------------                                                         195, 000.00
  1 Exclusive of available funds.

13. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                                   For last         Cost and expenditures to
                                                                   full re-               June 30, 1944                  Estimsated
                      Name of project                              port see                                              amount re-
                                                                   Annual                                                 quired to
                                                                    Report          New work          Maintenance         complete
                                                                     for-

1. Clark Hill project on the Savannah River, Ga.-
      S.-C.1------------------------.--------------                                                                       2$1,700,000
2. Augusta, Savannah River, Ga ----------------                       1941        3 $642, 902. 77    --------------            (4)

   1Under date of May 27, 1944, the Chief of Engineers recommended that a general plan of devdlopment be
adopted as the basis for improvement, step by step, of Savannah River and tributaries for power, flood con-
trol, navigation, and other purposes, and that the Clark Hill project be authorized for construction as the
initial step, at an estimated cost of $35,300,000 for construction and $223,000 annually for operation and main
tenance (H. Doc. No. 657, 78th Cong., 2d sess.).
   2 For reimbursement to local interests for lands and damages. Authorized by Flood Control Act ap
proved June 28, 1938. No requests for reimbursement have yet been made by local interests.
   3 Unexpended balance June 30, 1944, $740.
   4 Completed.

     Status of all investigations for flood control called for by flood-control acts and
                                   committee resolutions

                                                                        Date trans-            Document                Recommen-
             Locality                    Authorization act              mitted to                 No                     domen
                                                                         Congress


Altamaha River, Ga-........         Flood Control Act, ..............................
                                      June 22, 1936.
Ocmulgee River at Macon, .....- do..............                                 ..  ........                    .
  Ga. (interim report on
  Altamaha River, Ga.).
                      ........---..
Ogeechee River, Ga--------              do. .---------------------------------------
St. Marys River, Ga. and            See. 1 of River and ...---------------------.-
  Fla., for navigation, flood         Harbor Act, Jan. 21,
  control, power and irriga-          1927.
  tion (supplemental 308
  report).
Savannah River, Ga-........ Flood Control Act, June 6,1944                                  H. 657,78th Cong., Favorable.
                                  -   June 22, 1036.                                          2d sess.
Savannfahb RIIver, ~(*a.:(sup       Sec. 6 :of River and                                               "............................
  plemental 308 report).              Harbor Act, Aug. 30,
                                      1935.
       RIVERS    AND    HARBORS---JACKSONVILLE,           FLA.,   DISTRICT      499
  IMPROVEMENT OF RIVERS AND HARBORS IN THE
          JACKSONVILLE, FLA., DISTRICT

   This district comprises a portion of. central southern Georgia and
all of Florida except the northwestern part and a small northeastern
portion embracing the watersheds tributary to the Atlantic Ocean
and the Gulf of Mexico from the vhrhor at Fernandina, Fla., ex-
clusive, to and including the Aucilla River. It includes the sections
,of the Intracoastal Waterway from Fernandina (Cumberland Sound
to St. Johns River section) to Florida Bay, and the waterway across
southern Florida via St. Lucie River and Canal, Lake Okeechobee, and
the Caloosahatchee Canal and River.
   District engineer: Col. D. W. Griffiths, Corps of Engineers, to Jan-
uary 9, 1944; Lt. Col. L. E. Reed, Corps of Engineers, acting district
engineer, to February 11, 1944; and Col. A. B. Jones, Corps of Engi-
neers, district engineer, since that date.
   Division engineer: Brig. Gen. J. S. Bragdon, U. S. Army, to June
10, 1944; and Brig. Gen. R. F. Fowler, U. S. Army, since that date.
                                  IMPROVEMENTS

               Navigation                          Navigation-Continued
                                      Page                                      Page
  1. Waterway between        Beau-            Charloite Harbor, Fla
                                             12.                       -----     539
       fort, S. G, and St. Johns              Tampa Harbor, Fla--------
                                             13.                                 541
       River, Fla (Cumberland                 Withlacoochee River, Fla--.
                                             14.                                 546
       Sound to St. Johns River               Removing the water hya-
                                             15.
       section)                       499       cinth from navigable wa-
2. St. Johns River, Fla., Jack-                ters in the State of Florida.    549
       sonville to the ocean ..       503 16. Examinations, surveys, and
3. Cross-Florida barge canal ..-     507       contingencies (general) - -      551
4. Oklawaha River, Fla-              509 17. Other navigation projects for
  5. Intracoastal Waterway from                 which no estimates are sub-
       Jacksonville    to Miami,                mitted._.....                    552
       Fla           - -     --       513 18. Plant allotment-            .      553
6. St. Augustine Harbor, Fla -       518
  7. Fort Pierce Harbor, Fla _.       520
8. Lake Worth Inlet, Fla-            522                Flood control
9. Hollywood Harbor          (Port
       Everglades), Fla_              525 19. Preliminary     examinations,
10. Miami Harbor          (Biayne               surveys, and contingencies
       Bay), Fla-       -       -     527       for flood control                555
11. Caloosahatchee River and              20. Other flood-control projects
       Lake Okeechobee drainage                 for which no estimates are
       areas, Fla___                  530       submitted___-------              556

1. WATERWAY BETWEEN BEAUFORT, S. C., AND ST. JOHNS RIVER, FLA.
       (CUMBERLAND SOUND TO ST. JOHNS RIVER SECTION)

  Location.-This section includes that portion of the Intracoastal
Waterway between the southerly limit of Fernandina Harbor, Fla.,
at the junction of Lanceford Creek and Amelia River, and the St.
Johns River, Fla. (See U. S. Coast and Geodetic Survey Charts
Nos. 841, 842577, and 1243.) (For Beaufort, S. C., to Cumberland
Sound sectin, aee p. 481.)
500            REPORT OF CHIEF OF ENGINEERS, U. S.                           ARMY,       1944

   Previous projects.-The first project for the improvement of this
section of the waterway was authorized by the River and Harbor
Act of May 23, 1828, and modified by River and Harbor Act of June
23, 1874. For further details.see Annual Report for 1915, page 1823,.
and Annual Report for 1938, page 605.
   Existing project.-This provides for dredging and maintaining a.
channel 12 feet deep, with widths of 90 feet in land-cuts and narrow-
streams and 150 feet in open waters, following in general the aline-
ment of the existing waterway from Fernandina Harbor to St. Johns
River, a distanceofThabout 22.6 miles, and with a cut-off in Kingsley
Creek just north of the Seaboard Air Line Railway bridge, with.
such additional cut-offs or other changes in the adopted route as may
be found desirable and justified by the resultant benefits to naviga-
tion. The mean range of tide is 6 feet at Fernandina and 3.7 feet in.
the St. Johns River, with fluctuations from 1.5 to 3 feet, due to winds
and lunar phases.
   The estimate of cost of new work, revised in 1938, was $261,000,
exclusive of amounts expended under previous projects. The latest
(1938) approved estimate for annual cost of maintenance is$13,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                    Documents


Mar. 4,1913     For a channel 100 feet wide and 7 feet deep -- _ __ H. Doc. No. 898, 62d Cong., 2d sess.
June 20,1938    For a channel 12 feet deep with present authorized   H. Doc. No. 618, 75th Cong., 3d sess.'
                 widths and including a cut-off in Kingsley
                 Creek, subject to the provision of additional
                 cut-offs or changes in routing upon the approval
                 of the Secretary of War.


iContains the latest published maps.

   Local cooperation.-Fully complied with as to original construc-
tion. The River and Harbor Act approved June 20, 1938, included
the requirement that local interests furnish spoil-disposal areas for
subsequent maintenance as may be required. The Florida Inliand
Navigation District, a special taxing district empowered by Florida
State law to comply with features of local cooperation, has furnished
rights-of-way and spoil disposal easements for maintenance dredging:
to provide for the rectification of the channel alinement. Documents
for a number of parcels obtained by negotiation were approved by the-
Chief of Engineers April 25, 1943. The remaining easements were
subsequently acquired by condemnation proceedings. The Florida
Inland Navigation District was requested June 9,1944, to furnish addi-
tional rights-of-way and spoil disposal areas in perpetuity for mainte-
nance. Temporary spoil disposal areas have been furnished as and.
when needed.
   Terminal facilities.-Exclusive of terminal facilities reported for-
Fernandina Harbor, there are no terminals along this waterway.
        RIVERS AND    HARBORS-JACKSONVILLE,        FLA.,   DISTRICT   501

    Operations and results during fiscal year.-Dredging to a depth of
12 feet, under contract, to rectify the channel alinement of the water-
-way by making five cut-offs and widening at three bends was com-
2menced May 27, and completed October 26, 1913. There were removed
during the fiscal year 2,873,985 cubic yards of material at a cost of
$455,261.28 for maintenance ,including $1,020.10 for late costs of pre-
liminary surveys and plans, by hired labor. The U. S. pipe-line
}dredge Congaree, employed from October 18, to November 6, 1943, for
maintenance dredging to restore project dimensions throughout the
waterway, removed 74,153 cubic yards of material from seven shoals
between the Nassau and St. Johns Rivers, aggregating 5,760 linear
feet in length. The cost was $15,559.40.
   To safeguard navigation through bridge openings and to permit
tows to be broken when tidal conditions are adverse, 8 protective
dolphins and 10 tie-up dolphins were provided at the Sisters Creek
bridge, and 14 protective dolphins and 10 tie-up dolphins at the
Kingsley Creek bridges. Damaged. tie-up dolphins at the latter
bridges were redriven or repaired and original dolphins which were
found to be inadequate were enlarged. The work was performed
under contract from October 12, 1943, to April 14, 1944, at a cost of
$61,256.26, including $991.80 for preliminary surveys and plans.
Work under a contract for constructing six 19-pile replacement tie-up
dolphins, strengthening 2 existing tie-up dolphins, and removing 5
broken-off dolphin tops and 1 damaged dolphin, all near the Kingsley
C-reek bridges, was commenced June 30, 1944. There were no costs.
   A picket boat was operated by hired labor from November 19, 1943,
to the close of the fiscal year, at the two adjacent bridges over Kingsley
'Creek, about 4 miles south of Fernandina, to safeguard navigation
by supervising the passage of tows through the bridge openings. The
'cost was $18,928.03. Periodic surveys and inspections to determine
the condition of the improvements were made at a cost of $3,801.39.
   The total cost for the year was $554,806.36 for maintenance. The
expenditures were $546,968.75.
    Condition at end of fiscal year.-The existing project was completed
in 1941. Rectification of the channel alinement, reducing the length
,of  the waterway by 2.4 miles, was effected during 1943 by making
5 cut-offs and widening bends at 3 localities. To safeguard naviga-
tion through bridge openings and to permit the breaking of tows when
tidal conditions are adverse, 8 protective and 10 tie-up dolphins have
been constructed at the Sisters Creek bridge at the southerly entrance
to the waterway, and 14 protective and 10 tie-up dolphins have been
constructed at the Kingsley Creek bridges, about 4 miles south of
Fernandina. Six of the tie-up dolphins at the latter bridges have
been demolished. Project depth of 12 feet, with widths of 90 feet
in land cuts and narrow streams, and 15Q feet in open waters, existed
in November 1943. The costs of the existing project have been $234,-
283.45 for new work and $697,519.59 for maintenance, a total of
$961,803.04. The expenditures have been $957,000.42.
502             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                          1944

  Proposed operations.-The balance unexpended June 30, 1944,
$36,838.43, will be applied as follows:
Accounts payable June 30, 1944_ ------------------------------         $4, 802. 62
Maintenance:
    Complete, under existing contract, about Aug. 15,
      1944, construction of six 19-pile replacement tie-up
      dolphins, strengthening 2 existing tie-up dolphins,"
      and removing 5 broken-off dolphin tops and 1
      damaged dolphin, all near the Kingsley Creek
      bridges -----------------------------------          $9, 200. 00
    Operation of a picket boat to safeguard navigation by
      supervising the passage of tows through the Kings-
      ley Creek bridges near Fernandina, by hired labor,
      July 1, 1943, to June 30, 1944_11111                 20, 435. 81
    Periodic and miscellaneous surveys, inspections, and
      contingencies, by hired labor, July 1, 1944, to June
      30, 1945-----------------------------------2,            400. 00
                                                                       32, 035. 81
               Total for all work--- .                         --------------                                             36, 838. 43
   The additional sum of $30,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging to remove shoals through-
out the project, with U. S. pipe-line dredge Congaree,about 1.2 months,
January and February 1946.
                                               Cost and financial summary

Cost of new work to June 30, 1944--------------------------                                                           $361, 849. 00
Cost of maintenance to June 30, 1944_-------               ---                                                         697, 519. 59
      Total cost of permanent work to June 30, 1944                                       ----------                 1, 059, 368. 59
Minus accounts payable June 30, 1944_-------                                                                 ---          4, 802. 62

     Net total expenditures-------------.                                                                            1,054, 565. 97
Unexpended balance June 30, 1944_-------                                                      --        __              36, 838. 43
           Total amount appropriated to June 30, 1944------------                                                    1, 091, 404. 40,


    Fiscal year ending June 30                     1940             1941              1942                   1943            1944

Cost of new work _.          ......    -         $14,459. 85      $88, 541.27       $60, 501.. 25   -
Cost of maintenance               _-                                       -....         276. 67        $96,078.79     '-   $554,806.36
       Total cost ----------------
                   ..                             14, 459.85       88, 541.27        60, 777.92          96, 078. 79        554,806.36

Total expended ..........---------------...     - 14, 378.79       66, 252.33'.    '*88,077.40           99,184.30          546, 968. 75

           -----------------
Allotted.....   ................              ---- 75 000.00       60000.00.         19,000. 00         483, 700.00          199,000.00



Balance unexpended July 1, 1943_---------------------------                                                           $384, 807. 18
Amount allotted from War Department Civil Appropri-
  ation Act approved June 28, 1939_---          -     $3, 750.                                                00
Amount allotted from War Department Civil Appropri-
  ation Act approved May 23, 1941-      --   _    --  99, 186.                                                 19
Amount allotted from War Department Civil Appropri-
  ation Act approved June 24, 1940                     7, 763.                                                 81
Amount allotted from War Department Civil Appropri-
Sation Act approved June 2, 1943 ----------------    88, 300.                                                 00.
                                                                                                                       199, 000. 00
            Amount to be accounted for_                                                                                583, 807. 18
           RIVERS AND HARBORS-JACKSONVILLE,                               FLA., DISTRICT          503
Gross amount expended--- -----------------------                       $551, 802. 81
Less reimbursements collected_--------------------                        4, 834. 06
                                                                                          $546, 968. 75

       Balance unexpended June 30, 1944----------------------                               36, 838. 43
Outstanding liabilities June 30, 1944 -------------- 4, 802. 62
Amount covered by uncompleted contracts ....         7, 751.58
                                                                                            12, 554. 20
         Balance available June 30, 1944_---                           - -___               24, 284. 23

Amount that can be profitably  expended in fiscal year ending June
                           1- - - - - - - - - - - - - - - - - - - - - - - - - - - - -
30, 1946, for maintenance                                                         _30,         000. 00
1 Exclusive   of available funds.

         2. ST. JOHNS RIVER, FLA., JACKSONVILLE TO THE OCEAN

   Location.-This river rises in the marshes of Brevard County, Fla.,
near the east coast, and flows northwestwardly to Jacksonville, thence
eastwardly into the Atlantic Ocean, 122 miles south of Savannah
River. Its total length is about 285 miles. (See U. S. Coast and Geo-
detic Survey Charts Nos. 577 and 1243.)
   Previous projects.-Six appropriations for surveys and experi-
mental dredging on the bar were made from 1852 to 1878. The first
project for permanent improvement was adopted by the River and
Harbor Acts of June 14,1880, and June 3, 1896. For further details,
see page 1823, Annual Report for 1915, and page 607, Annual Report
for 1938.
   Existing project.-This provides for a channel 30 feet deep at local
mean low water from the ocean to Jacksonville, the width to be in
general 300 feet in the straight reaches, increasing to as much as 600
feet at the bends and through jetties, 1,200 feet at Dames Point, and
400 feet in Drummond Creek Cut, Trout Creek Cut, and Long Branch
 (formerly Six Mile Creek) Cut, with greater easing of the bends be-
tween these three cuts; for an anchorage basin at Mayport (33/4 miles
from the entrance) 800 feet in width beyond the channel limits; for
a channel 400 feet wide and 30 feet deep along the terminals on the
west bank of the river between Commodore Point and deep water
just above Long Branch Cut; for a depth of 24 feet at mean low
water between the 24-foot curve and the pierhead line at Jacksonville,
from the Florida East Coast Railway bridge to Hogan Creek; and
for the construction of training walls and revetments.
   Two converging rubblestone jetties built at the entrance under a
previous project, are maintained under the existing project.           The
north jetty is 14,300 feet long and the south jetty is 11,183 feet long.
The jetties are parallel and 1,600 feet apart for a distance of 4,022
feet from the sea ends. Stone training walls have been built at seven
localities, involving about 7 miles of this class of structure. Stone
revetments at five localities provide about 3.5 miles of shore protec-
tion. The training walls and revetments are located between Dames
Point and Wards Bank, near the inner ends of the jetties.
   The length of section included in the project is 28 miles. The mean
tidal range is 5.3 feet on the bar, 4.5 feet at Mayport, 2.6 feet at Dames
Point (14 miles above the entrance), and 1.1 feet at Jacksonville
 (Duval County highway bridge). The extreme range varies from
about 9 feet on the bar to about 1.5 feet at Jacksonville. Strong north-
504           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                         1944

easterly winds raise the water level about 2 feet at Mayport and Jack-
sonville. Strong southwesterly winds lover the water about 11/2 feet
at Mayport and 1 foot at Jacksonville.
  The estimate of cost for new work, revised in 1937, was $5,270,000,
exclusive of amounts expended on previouaprojects. The latest (1942)
approved estimate for annual cost of maintenance is $365,000.
  The existing project was authorized by the following -river and
harbor acts:

       Acts                        Work authorized                                        Documents


Mar. 2,1907     A depth of 24 feet at mean low water between the            H. Doc. No. 663, 59th Cong., 1st sess.
                  24-foot curve and the pierhead line at Jackson-
                  ville.
June   25, 1910 Main channel, 30 feet deep at mean low water,               H. Doc. No. 611, 61st Cong., 2d sess.
                  and in general 300 feet wide, the anchorage
                  basin opposite Mayport, and training walls and
                  revetments, all subject to modification in de-
                  tail by the Chief of Engineers.
June    5, 1920 Present project effected by the consolidation of            Specified in act.
             Sformer projects.
July    3,1930 Widening the bend at Dames Point------------..............   H. Doc. No. 483, 70th Cong., 2d sess.
Aug.   30,1935 Widening Drummond Creek, Trout Creek, and                    Senate committee print, 74th Cong.,
                  Six Mile Creek cuts to 400 feet, and a channel              1st sess. (Contains latest published
                  30 feet deep and 400 feet wide along the termi-             maps.)
                  nals at Jacksonville.



   Recommended modifcations of project.---Under date of April 25,
1941, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for maintenance of channel widths as
they now exist, and, subject to the revision of harbor lines proposed
by the division engineer, for further improvement as follows: (a)
Widen Terminal Channel between its present westerly edge and the
new pierhead-bulkhead line to a depth of 30 feet; (b) dredge to a
depth of 28 feet the area between the foot of Laura Street and the
Duval County highway bridge; (c) dredge a navigation and flood-
way channel 200 feet wide and 26 feet deep along the south side of
the Commodore Point Terminals, terminating in deep water at each
end; and (d) dredge an approach and mooring basin 20 feet deep,
1,300 feet long at the 20-foot-depth contour, and 600 feet long at the
pierhead line in front of the Naval Reserve Armory in South Jack-
sonville; all substantially in accordance with the plan contained in
the report of the division engineer, at an estimated first cost of
$725,000, with $8,000 annually for maintenance, in addition to the
amount now required, subject to certain conditions of local coopera-
tion (H. Doc. No. 322, 77th Cong., 1st sess.).
   Under date of May 23, 1944, the Chief of Engineers recommended
modification of the existing project to provide for a channel depth
of 34 feet from Commodore Point to the ocean via Terminal Channel,
widened to pierhead-bulkhead line as recommended in House Docu-
mient No. 322, Seventy-seventh Congress, first session, at an estimated
cost for construction of $3,200,000, with no increase in the estimated
annual cost of maintenance required for the project, subject to certain
       RIVERS AND    HARBORS-JACKSONVILLE,        FLA., DISTRICT    505

conditions of local cooperation. (S. Doc. No. 230, 78th Cong., 2d
sess.)
   Terminal facilities.-There are 56 piers and wharves to serve the
water-borne commerce of the port. These piers have, a combined
berthing space of approximately 41,700 feet, with depths varying
from 31 feet at the larger terminals to a few feet at the inner ends
of the slips and barge berths. The Jacksonville Municipal Terminals
at Talleyrand Avenue consist of 3 piers. There are 30 other piers
and wharves for handling general freight and private commodities,
7 of which are open to the public. All have railway and highway
connections except 17 of the privately owned piers, which have high-
way connections only. Of the remaining piers, 8 are used in con-
nection with shipyards and marine repair plants, 6 for moorings,
including 2 for recreational craft, and 11 for various commercial pur-
poses. The facilities are considered adequate for existing commerce.
 (See Port Series No. 8, pt. 1, revised 1936, Corps of Engineers.)
   Operations and resultsduring fiscal year.-The U. S. hopper dredge
San Pablo was employed for maintenance dredging in Bar Cut at the
entrance, from July 1 to 11, 1943, and from December 7, 1943, to
March 24, 1944, with dredging during rough weather in Mile Point
Cut during December and January, and in White Shells Cut during
February and March. A minimum depth of 31 feet was obtained in
Bar Cut by the removal of 247,947 cubic yards, place measurement,
of material from two shoals at a cost of $98,570.25. Project depth
was restored in Mile Point Cut and at two small but obstructive
shoals located near the center of the channel in White Shells Cut
by the removal of 42,560 cubic yards, place measurement, of mate-
rial at a cost of $10,224.33. Periodic examinations and surveys to
determine the condition of the improvement, and repairing and re-
painting permanent examination ranges and triangulation stations
cost $13,271.96.
   The total cost for the year was $122,066.54 for maintenance. The
expenditures were $141,431.26.
   Condition at end of fiscal year.-The existing project was completed
in 1937. The jetties, completed in 1904 under a previous project, have
been maintained under the existing project. All training walls and
revetments at present considered necessary were completed in 1927.
About 3,555 linear feet of the inner end of the north jetty has been
capped with concrete and the easterly end of the Wards Bank training
wall has been revetted with granite riprap. Material dredged in the
vicinity of the westerly end of Bar Cut and deposited adjacent to and
on the north side of the north jetty, in the vicinity of the Fort George
Inlet encroachmeht, has effectively protected this structure. The
jetties are in good condition, except that capstone has been displaced
by sea action at isolated locations and that erosion at the inner end of
the north jetty, shoreward of the existing monolithic concrete cap-
ping, has become so pronounced that extension of the capping shore-
ward about 800 feet is desirable in order to prevent the wave-washed
sand through the eroded section of the jetty from entering the ad-
jacent ship channel. Revetments and training walls are in good
condition except as follows: The Browns Creek revetment is in poor
condition; the Dames Point training wall is in fair condition; the
revetment at Wards Bank training wall is in fair condition, except
506       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

that the seaward end has been undermined and the inner end needs
to be extended about 800 feet upstream.
   During May-June 1944 the controlling depths at local mean low
water were as follows: Bar Cut, 30 feet for a width of 400 feet; and
thence to Jacksonville, 27.1 feet for a width of 200 feet located in
Terminal Channelowith a depth of only about 28 feet for a width of
200 feet available in White Shells Cut, less than project depth at a
number of other localities, and with reduced widths in all cuts. The
project depth of 24 feet between the 24-foot contour and pierhead line
between the Florida East Coast Railway bridge and Hogan Creek
existed in 1934 except for shoaling with a limiting depth of about 20
feet along the pierhead line between the two highway bridges.
  The total cost of the existing project, all funds, has been $14,873,-
347.86, of which $5,259,724.45, including $290,013.37 Public Works
funds, was for new work, and $9,613,623.41 for maintenance. The
expenditures have been $14,875,585.49, including $290,013.37 Public
Works funds.
   Proposed operations.-The balance unexpended and accounts re-
ceivable June 30,1944, $344.61, plus $60,000 allotted during July 1944, a
total of $60,344.61, will be applied as follows :
Accounts payable June 30, 1944_---       -----------                                    $344. 61
Maintenance:
    Dredging to remove obstructive shoals in Terminal
      Channel and in Bar Cut, with U. S. hopper dredge
      San Pablo, about 0.6 month, July 20 to Aug. 5,
      1944------------------ -$16,200.00
    Dredging to restore project dimensions in Bar Cut
      between jetties with U. S. hopper dredge San
      Pablo, about 11 months, Mar. 1, to Apr. 8, 1945-                33, 800. 00
    Miscellaneous surveys, inspections, and contingen-
      cies-------------------------------                             10, 000. 00
                                                                                      60, 000. 00
          Total for all work ----------------------------------                       60, 344. 61
  The additional sum of $160,000 can be profitably expended' during
the fiscal year 1946 for maintenance, as follows:
Dredging to remove shoaling in Bar Cut between,the jetties, with U. S.
  hopper dredge San Pablo, 3 months, April to June 1946               ------------
                                                                         $80, 000
Repair the inner end of north jetty by extending the monolithic concrete
  cap shoreward between stations 5030 and 4230, by contract, July to
  September 1945----  -        ----------------                           70, 000
Miscellaneous surveys, inspections, and contingencies---------------- 10, 000

        Total for maintenance_---                                --        --------     160, 000

                              Cost and financial summary
Cost of new work to June 30, 1944                                               $8, 779, 861. 84
Cost of maintenance to June 30, 1944_-----------------------                    10, 157, 021. 93
       Total cost of permanent work to June 30, 1944-                           18, 936, 883. 77
Plus accounts receivable June 30, 1944------------------                              2, 582. 24
      Gross total costs to June 30, 1944      --------------------              18, 939, 466. 01
Minus accounts payable June 30, 1944_-              ----------                           344. 61
      Net total expenditures----------_                               __        18, 939, 121. 40
IUnexpended balance June 30, 1944-                                               --   2, 237. 63
        Total amount appropriated to June 30, 1944_                             18, 936, 883. 77
                RIVERS AND HARBORS--JACKSONVILLE,                                 FLA., DISTRICT                   507


     Fiscal year ending June 30             1940            1941           1942            1943                 1944

C ost of new w ork .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . .
-Cost of maintenance   -----------       $130, 588. 77   $182, 302.41   $311,439.80     $360, 677. 74         $122, 066.54
               ----------------
Total expended....                        132, 640. 58    181,146. 52    290, 690. 84    363,106. 94           141,431.26
Alloted ...........           .      .    195, 55:41       68,000.00     455,000.00      210, 500.00 ........


Balance unexpended July 1, 1943 ----------------------------                                        $139, 193. 63
Gross amount expended_------------------------                              $184, 074. 56
Less reimbursements collected-----------------                                 42, 643. 30
                                                                                                        141, 431. 26
      Balance unexpended June 30, 1944---------------------                                             -2,     237. 63
Outstanding liabilities June 30, 1944_- -  ---------                                                            344. 61
             Balance available June 30, 1944----------------------                                --      2, 582. 24
             Accounts receivable June 30, 1944------------------                                          2582.
                                                                                                          2,      24
Amount allotted in July 1944 -------------------------------                                             60, 000.00
Amount available for fiscal year 1945-------------------                            --------             60, 000. 00
Amount that can be profitably 1expended          in fiscal year ending
  June 30, 1946 for maintenance - -- - - - - - - - - - - - - - - - - - - - - -                          160, 000. 00
  1 Exclusive of available funds.

                              3. CROSS-FLORIDA BARGE CANAL

   Location.-The proposed canal extends up the St. Johns River,
past Palatka, thence up the valley of the Oklawaha River; across the
divide, and down the valley of the Withlacoochee River to the Gulf
of Mexico, at a point about 95 miles north of Tampa, Fla.
   Existing project.-This provides for a lock canal with project depth
of 12 feet and minimum bottom width of 150 feet, with locks 75 feet
wide, 600 feet long, and 13 feet deep over the sills. The project pro-
vides for the construction of five locks. The estimated cost of new
work, revised in 1913, is $55,000,000, with $323,000 annually for main-
tenance and operation.
   The project was authorized in Public Law No. 675, Seventy-seventh
Congress, approved Jiuly 23, 1942.
   Local cooperation.-The project provides that local interests fur-
nish without cost to the United States all lands, easements, and
rights-of-way necessary for the construction of the canal; hold and
save the United States free from damages due to the construction
works and take over, maintain, and operate all highway bridges and
roadways built in connection with the project.
   Operations and results during fiscal year.-Operations consisted of
field and office studies and design incidental to the preparation of a
definite project report and plans and specifications. The field work
consisted of the following: Aerial photography and the preparation
of mosaics covering the canal route, by contract; subsurface explora-
tions to determine the proper location for the canal structures, and
the materials to be encountered throughout the length of the canal, by
contract and hired labor; control surveys for the aerial mapping and
subsurface work, topographic surveys of lock and dam sites, and mis-
cellaneous leveling, traversing, and surveying as required, by contract
and hired labor. Test piles were driven and loaded at the St. Johns
and Eureka lock sites; a test pit was dug at the Eureka lock site;
508        REPORT OF CHIEF OF ENGINEERS,                     U. S. ARMY,             1944

experimental sections of bank-protection works were constructed
along the Withlacoochee River; and investigations were made to find
local sources of suitable construction materials, all by hired labor.
At the Dunnellon lock site grouting and pumping tests were made
by contract and hired labor and a 36-inch inspection hole was drilled
by hired labor. Office studies included the preparation of a definite
project report, with preliminary plans, which was transmitted to the
Chief of Engineers December 23, 1943. The preparation of detailed
plans and specifications was commenced upon completion of the defi-
nite project report. Laboratory tests and experiments were. made of
materials to be used and encountered in construction. Preliminary
plans for bridges were prepared by contract. The costs were $147,-
449.66 for work performed by contract and $840,324.71 for that per-
formed by hired labor, a total of $987,774.37, all for new work. The
expenditures were $999,495.44.
   Condition at end of fiscal year.--Work on the project has been lim-
ited to the preparation of a definite project report which was com-
pleted, and detailed plans and specifications which are 80 percent com-
pleted. The total cost has been $996,111.65 for new work. The-
expenditures have been $999,599.69.
   Proposed operations.-The balance unexpended and accounts re.
ceivable June 30, 1944, $301,885.02, will be applied as follows:
Accounts payable June 30, 1944_                -
                                              .-----       __----.----$16,                        126. 99o
New work:
    Completion of detailed plans and specifications,
      including surveys, subsurface explorations, ex-
      periments, tests, design, and drafting, July 1, to
      Nov. 30, 1944---------------------------                     $244,758.03
    General camp maintenance, 5 months, July 1 to
      Nov. 30, 1944 -----------------------------                      16, 000. 00
    Demobilization, involving the return of rented
      equipment, the assembly, indexing and transfer
      of data, files, etc., to the district office, and dis-
      banding the resident office at Camp Roosevelt,
      November 1944_ -_                  ____--      -----            25, 000. 00
                                                                                            285, 758. 0
        Total for all work ---------------------------------  301, 885. 02
  No funds can be profitably expended during the fiscal year 1946
due to restrictions on critical materials during the present emergency.
                                Cost and financial summary
Cost of new work to June 30, 1944 ----------------------------                             $996, 111. 65
Cost of maintenance to June 30, 1944_.
      Total cost of permanent work to June 30, 1944----------                               996, 111. 65
Undistributed costs June 30, 1944_-----------------------                                    18, 130. 32
       Net total cost to June 30, 19441__-------                                    -1,     014, 241. 97
Plus accounts receivable June 30, 1944_--                --------                             1, 484. 71
      Gross total costs to June 30, 1944           ---------------------                  1, 015, 726. 69
Minus accounts payable June 30, 1944_-                                          -             !-------
                                                                                              16,  126. 99
      Net total expenditures_--              .--              -----                         0-- 599. 69
                                                                                            999,
Unexpended balance June 30, 1944-                  ---                                      300, 400. 31
        Total amount appropriated to June 30, 1944-                 .--.---.-             1,300, 000. 00
                    RIVERS AND HARBORS---JACKSONVILLE,                                                         FLA., DISTRICT               509


      Fiscal year ending June 30                                      1940                      1941       1942            1943            1944

Cost of new work--------                            -----------------------------------------                          $8,337. 28      $987,774.37
Cost                    .--------------------------------------------------
          of maintenance------------
Total expended ...----------........                  ------------------------------------------                           104.25       999, 495.44
Allotted.......-------------------------...............------------.............          ...-...
                                                                                           --- -.                      100,000.00
                                                                                                            ..---------------
                                                                                                       ......                         1,200,000.00


Balance unexpended July 1,                                      1943 --------------. -----------                                    $99, 895. 75
Amount allotted from War                                        Department Civil Ap-
  propriation Act approved                                      May 23, 1941-------    $900, 000. 00
Amount allotted from War                                        Department Civil Ap-
  propriation Act approved                                      Apr. 28, 1942 --------  300, 000. 00
                                                                                                                                  1, 200, 000. 00
       Amount to be accounted for------------------ ------                                                                     1, 299, 895. 75
Gross amount expended--------------------     $1, 137, 112. 41
Less reimbursements collected.                    137, 616. 97      -----------------
                                                                                                                                    999, 495. 44
     Balance unexpended June 30, 1944--------------- -----                                                                          300, 400. 31
Outstandingliabilities June 30, 1944--------- --- $16, 126. 99
Amount covered by uncompleted contracts --------   32, 726. 94
                                                                                                                                     48, 853. 93
      Balance available June 30, 1944-----------------------                                                                        251, 546. 38
Accounts receivable June 30, 1944----- ----------------------                                                                         1, 484. 71

                Unobligated balance available June 30, 1944 -----------                                                             253, 031. 09
Amount (estimated) required to be appropriated for completion
of existing project 1 --     ---------------                 53, 700, 000.00
   1 Exclusive of available funds.


                                                        4. OKLAWAHA RIVER, FLA.

   Location.-This river has its source in the system of large lakes in
the central part of the peninsula of Florida and flows in a general
northerly direction, then eastwardly, emptying into the St. Johns
-River, 22 miles above Palatka. The extreme head of the system may
be taken as Lake Apopka, 120 miles above the mouth of the river.
   Previous projects.-The first improvement was authorized by an
act of Congress approved February 24, 1835. For further details
see page 1825, Annual Report for 1915, and page 613, Annual Report
for 1938.
   Existing project.-This provides for deepening the channel to 6 feet
at mean low water from the mouth to the head of Silver Springs Run,
a.distance of 58 miles; for clearing the channel of obstructions from
Silver Springs Run to Lake Griffin, including the Kyle and Young
Canal and its extension to Morrisons Landing and the J. D. Young
C'anal from Morrisons Landing to Starkes Ferry (clear title to the
-canals and sufficient land adjacent thereto to provide for future widen-
ing has been conveyed to the United States) and maintaining the dikes
with a view to obtaining a navigable depth of about 4 feet to Leesburg,
X6.5 miles above the-mouth. The work embraces dredging, snagging,
cut-offs at sharp bends, removal of overhanging trees and obstructive
aquatic vegetation, and the construction of a lock and dam at Moss
IBluff to retain the watdi level in Lake Griffin.
510          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                    1944

                                    Lock and dam at Moss Bluff
       Distance to nearest town: 20 miles by canals.
       Name of nearest town: Leesburg, Fla.
       Distance above mouth of river : 66.3 miles by canals.
       Distance above mouth of Silver Springs Run: 13.7 miles.
       Width of lock chamber: 30 feet.
       Greatest available length for full width: 125 feet.
       Lift above low water: 11.5 feet.
       Depth on upper miter sill at normal pool level: 7 feet.
       Depth on lower miter sill at low water: 7 feet.
        Maracter of f tadationk: Piles in sand and clay.
       Character of costrution: Concrete, with timber gates.
       Kind of dam: Movable.
       Type of dam : Needle.
       Completed in 1925.
       Total cost: $161,000.
   The river is nontidal except for a short distance above the mouth at
the St. Johns River, where a mean range at low-water stage of about
0.5 foot is found. The mean fluctuation due to rainfall is about 2 feet
at the mouth, about 3 feet at the mouth of Silver Springs Run, and
about 21/2 feet at Lake Griffin. The extreme fluctuation is about 3 feet
at the mouth, 5 feet at Silver Springs Run, and about 41/2 feet at Lake
Griffin.
   The estimated cost of the work proposed, revised in 1929, is $351,000,
exclusive of amount expended on previous projects. The latest (1942)
approved estimate of cost for aninattl maintenance is $12,500, including
$5,000 for operation and care of lock and dam.
   The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                   Documents


Sept. 19,1890    Clearing the river of obstructions with a view to    Annual Report for 1889, pp. 1360-1364..
                   obtaining a navigable channel about 4 feet deep
                     from the mouth to Leesburg.
Mar.    2,1907   Deepening the channel to 6 feet at mean low water    H. Doc. No. 782, 59th Cong., 1st sess.
                  from the mouth of the river to the head of Silver
                  Springs Run.
June 25, 1910    Maintenance of levels in the lakes at the head-of    Specified in act.
July 25, 1912    J   the river.
July 27,1916     Acceptance of certain artifical waterways and            Do.
                   extensions thereof between Heather Islaid and
                   Lake Griffin as part of the waterway in lieu of
                   portions of the natural bed of the river.
       (1)       Operation and care of the lock and dam provided
                  for with funds from War Department appro-
                  priations for rivers and harbors.


  IPermanent Appropriation Repeal Act of June 26, 1934.
  The latest published maps may be found in House Document No.
514, Sixty-third Congress, second session, and Annual Report for
1891, page 1626.
  Local cooperation.-Fully complied with.
  Terminal facilities.-There are numerous privately owned landings
along this river, more or less out of repair, and a municipal wharf at
       RIVERS AND HARBORS-JACKSONVILLE,           FLA., DISTRICT     511

Leesburg; no charges for wharfage. The facilities are considered
adequate for existing commerce.
   Operations and results dwring fiscal year-Maintenance.-The U. S.
derrick boat D-2 was employed for maintenance snagging between the
mouth of the river and Oklawaha Farms, a distance of about 60 miles,
from November 18, 1943, to February 29, 1944. A number of minor
obstructions were removed by hired labor during April 1944 at several
localities between the St. Johns River and Sharpes Ferry. A total of
9,617 obstructions, consisting of logs, snags, overhanging trees, etc.,
was removed at a cost of $6,621.40. Frequent inspections of the upper
river and gages and periodic inspections of the lower river were made
at a cost of $1,307.34.
   Operating and care.-The lock and dam were operated and main-
tained, and the buildings and grounds cared for with United States
plant and hired labor. The costs were $8,310.50 for operation, $172.91
for ordinary repairs, and $9.67 for emergencies, a total of $8,493.08.
   The costs for the year were $7,928.74 for maintenance and $8,493.08
for operating and care, a total of $16,421.82. The expenditures were
$15,352.06.
   Condition at end of fiscal year.-The existing project was about 89
percent completed. By dredging, making cut-offs, and snagging, a
channel with a depth of about 5 feet at ordinary stages has been ob-
tained from the St. Johns River to the head of Silver Springs Run,
58 miles above the mouth. A channel 30 feet wide and 4 feet deep at
low-water stages, between Silver Springs Run and the lock at Moss
Bluff, was completed in 1929. The lock and dam were completed in
1925. For further details relative to this lock, see paragraph "Existing
project." The United States reservation comprises 13.14 acres of land,
two dwellings, and a storehouse. Much of the original dredging of
the canal between Moss Bluff lock and Starkes Ferry was done by
private interests; the widening and deepening of that canal to provide
for the control of Lake Griffin was completed in 1930; and the dike
on the east side was repaired and improved in 1936. At the close
of the firscal year the river below the Moss Bluff lock was in good condi-
tion; the lock and dam were in fair condition and some repairs may
be necessary; and the canals and dikes above the lock were in fair
condition. The controlling depths at ordinary low stages were ap-
proximately as follows: Mouth of the river to Silver Springs Run,
4.5 feet; Silver Springs Run, 4.5 feet; Silver Springs Run to Moss
Bluff lock, 1.5 to 3.5 feet, depending on the operation of the power
plant at the lock; thence to Leesburg, 4 feet. The work remaining
to be done to complete the project is the easing of several sharp bends
and obtaining project dimensions in the section between the mouth
of the river and the mouth of Silver Springs Run, which is not con-
sidered necessary at this time.
    The costs of the existing project have been $311,352.45 for new work,
 $308,334.63 for maintenance, and $64,515.89 for operating and care, a
total of $684,202.97. The total expenditures have been $683,022.45. In
addition, $11,414.41 was expended between August 1,1929, and June
30, 1935. on the operation and care of the works of improvement under
the provisions of the permanent indefinite appropriation for such pur-
poses.
512                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                   1944

   Proposed operations.-The balance unexpended June 30, 1944,
 $1,180.52, plus $4,000 allotted during July 1944 and $5,284.34 to be al-
lotted, a total of $10,464.86, will be applied as follows:
Accounts payable June 30, 1944_ ---...                ___----_-___ _____-                                            $1, 180. 52
Maintenance:
     Miscellaneous surveys, inspections, etc., including weekly inspec-
       tions of the upper river and gages, and periodic inspections of
       the lower river, July 1, 1944,4to0 June 30, 1945_          ..-.----.-   ..                                      1, 184. 34
Maintenance (operating and care):
     Operation of lock and dam at Moss Bluff--------- $7, 800. 00
     Ordinary repairs_            _ - _--           -_  ------          250. 00
     Emergencies -----------------------------------                      50. 00
                                                                                                                       8, 100. 00

              Total for all work--------                      -       ---------------                                 10, 464. 86
  The additional sum of $9,500 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance: Miscellaneous surveys, inspections, etc., including weekly
  inspections of the upper river and gages, and periodic inspections of
  the lower river_---                ------------------                   $1, 200
Maintenance (operating and care):
     Operation of lock and dam at Moss Bluff----------------      $8, 000
     Ordinary repairs_          -----------------                     250
     Emergencies -----------------------------------------             50
                                                                           8, 300

              Total for all work---                  -------------           _-                         ___-9,                     500
     No funds can be profitably expended for new work during the fiscal
year 1946, as the completion of the project is not considered essential
at this time.
                                                    Cost and financial summary
Cost of new work to June 30, 1944_-           ----------                                                         $315, 264. 40
Cost of maintenance to Juine 30, 1944_-------                                                         ---         384, 264. 93
       Total'cost of permanent work to June 30, 1944------------                                                     699, 529. 33
Minus accounts payable June 30, 1944_--     ---------                                                                 1, 180. 52
      Net total expenditures-- ___------------                                                                       698, 348. 81
Unexpended balance June 30, 1944_---------                                                            ---              1, 180. 52
             Total amount appropriated to June 30, 1944                                 ---------           -        699, 529. 33


     Fiscal year ending June 30                       1940            1941               1942           1943                1944

Cost of new w ork..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                         . . . . ..     .. .   .
Cost of maintenance---. ..........                  $18,075. 40      $5, 541.86    $11, 382. 49       $15, 523. 05       $16,421.82
Total expended----------------..................     19,105. 31       5, 300. 67        10, 756. 57    16, 234. 65          15, 352.06
Allotted ----------...............                    4, 500.00       6,000.00          18, 700.00      9,200.00            10, 300.00


Balance unexpended July 1, 1943 -----------------------                                                               $6, 232. 58
Amount allotted from War Department Civil Appro-
  priation Act approved July 19, 1937--------------$1, 500. 00
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941 ---------------     2, 800. 00
Amount allotted from First Deficiency Appropriation
  Act approved Apr. 1, 1941 ....                   AA----
                                                        6, 000. 00
                                                                                                -                     10, 300. 00
             Amount to be accounted for.-----------------------16,                                                          532. 58
          RIVERS AND HARBORS-JACKSONVILLE,                           FLA., DISTRICT             513
Gross amount expended ------------------------       $15, 980. 50
Less reimbursements collected-----------------------      628. 44
                                                                                     -   $15, 352. 06

      Balance unexpended June 30, 1944_------                 ---                          1,180. 52
Outstanding liabilities June 30, 1944 ---------------------------                          1, 180. 52
Amount allotted in July 1944-_ ..- ___4,                                                      000.00
Amount available during fiscal year 1945--               -------           -   -.-         4, 000. 00
Amount (estimated) required to be appropriated for completion
of existing project 1_ - - - -
                                _ - - - - ---- --- _ -------                              39, 600. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1- - - - - - - - - - - -
                                                         -- - - - - -- - - -- - - --       9, 500. 00
I Exclusive of available funds.


5. INTRACOASTAL WATERWAY FROM JACKSONVILLE TO MIAMI, FLA.

   Location.-The waterway extends from Jacksonville to Miami,
Fla., following the St. Johns River to the mouth of Pablo Creek,
23 miles, and thence following in general the line of a canal con-
structed by the Florida Coast Line Canal & Transportation Co. (See
U. S. Coast and Geodetic Survey Charts Nos. 842, 843, 844, 845, 846,
and 847.)
   Previous projects.-Adopted by River and Harbor Acts of June 15,
1844, July 13, 1892, August 18, 1894, and Deficiency Act of February
26, 1896. For further details, see page 1825, Annual Report for 1915;
page 655, Annual Report for 1926; and page 618, Annual Report for
1938.
   Existing project.-This provides for an inland waterway in gen-
eral 100 feet wide and 8 feet deep at local mean low water from
Jacksonville to Miami, Fla., a distance of 372 miles, following the
coastal route, and for a turning basin 8 feet deep, 400 feet wide, and
800 feet long in the vicinity of Jacksonville Beach, Fla. Depths in
excess of those called for under this project already existed in the
St. Johns River from Jacksonville to a point 23 miles east and also
for a total of about 74 miles between the St. Johns River and Miami,
or about 25 percent of the total length of the project. The project
also includes the operation and maintenance of the bridge near Palm
Valley, the title to which was passed to the United States, along
with all other property of the Florida Coast Line Canal & Transpor-
tation Co., under the conditions of local cooperation.
   The mean range of tide is 3.8 feet at the St. Johns River, 0.7 foot in
the Indian River at Fort Pierce, 1.8 feet in Lake Worth at the Port
of Palm Beach terminals, 2.3 feet at the Port Everglades terminals,
and 2 feet in Biscayne Bay. The extreme range is about 7 feet at the
St. Johns River, 1.5 feet at Fort Pierce, and 3 feet in Biscayne Bay.
Tidal effect is imperceptible at points along the waterway distant
from inlets.
   The estimate of cost for new work, revised in 1937, was $7,271,500,
exclusive of amounts expended on previous projects. The latest (1942)
approved estimate for annual cost of maintenance is $165,000, includ-
ing $5,000 for the operation and care of the bridge near Palm Valley.



       616634-45-pt. 1, vol. 1--       33
514           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

  The existing project was authorized by the following river and
harbor acts:

       Acts                           Work authorized                              Documents


Jan. 21,1927     For a channel 8 feet deep and 75 feet wide from     H. Doc. No. 586, 69th Cong., 2d sess.
                   Jacksonville to Miami.
July    3,1930   For a width of 100 feet ......-...........     .    S. Doc. No. 71, 71st Cong., 2d sess.
       (1)       Operation and care of the bridge near Palm Valley
                  provided for with funds from War Department
                  appropriations for rivers and harbors.
                                                                                                              2
Aug. 26,1937     Turning basin in the vicinity of Jacksonville       H. Doc. No. 180, 75th Cong., 1st sess.
                  Beach.


1Permanent  Appropriation Repeal Act of June 26, 1934.
SContains latest published maps.

   Recommiended modifications of project.-Under date of May 25,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide at Sebastian, Fla., an entrance channel
100 feet wide and 8 feet deep from the Intracoastal Waterway to and
including a turning basin of the same depth, 600 feet long and 300 feet
wide, in front of the town, at an estimated first cost of $19,000, with
annual maintenance of $500, subject to certain conditions of local co-
operation (H. Doc. No. 336, 76th Cong., 1st sess.).
   Further modification of the existing project was recommended by
the Chief of Engineers in a report requested by, Rivers and Harbors
Committee resolutions adopted June 8, 1938, and June 17, 1942, and
River and Harbor Act approved' June 20, 1938, and transmitted to
Congress by the Secretary of War June 9, 1943.
   Local cooperation.-The work authorized by the River and Harbor
Act of August 26, 1937, is subject to the condition that local interests
provide, free of cost to the United States, all lands and rights-of-way
necessary for the improvement and for its subsequent maintenance
when and as required, and to the further condition that local interests
provide, without cost to the United States, suitable highway connec-
tions and a bulkhead along the south side of the basin on plans ap-
proved by the Chief of Engineers, and agree to maintain said bulk-
head and the land approaches thereto as a public terminal open to all
on equal terms. The lands needed for rights-of-way and spoil disposal
have been furnished. The town of Jacksonville Beach was issued a
War Department permit December 13, 1940, authorizing the construc-
tion of the required bulkhead, and on December 29, 1943, the time for
the completion of this work was extended to December 31, 1946.
   All prior requirements of local cooperation have been complied with
except the provision of spoil areas in perpetuity for maintenance as
required by the River and Harbor Acts approved January 21, 1927,
and July 3, 1930. The Florida Inland Navigation District, a special
taxing district empowered by State law to comply with features of
local cooperation, has furnished a number of permanent spoil disposal
areas, but these have been found to be inadequate. The Florida Inland
Navigation District was requested to furnish additional spoil disposal
areas in perpetuity for approximately the southerly and northerly
halves of the waterway on May 15, and July 1, 1944, respectively.
       RIVERS AND HARBORS-JACKSONVILLE,          FLA., DISTRICT    515

Temporary spoil disposal areas for maintenance have been furnished
as and when required.
    Terminal facilities.-Extensive terminals with railway and street
connections are available in connection with the harbors at Jackson-
ville and Miami. Terminals, with railway and highway connections,
for coastwise vessels have been constructed at Fort Pierce (Indian
River), Riviera (Lake Worth), and Port Everglades (Hollywood
Harbor). Municipal piers or wharves have been constructed at Titus-
ville, Courtenay, Cocoa, Melbourne, and Vero Beach for handling gen-
eral freight and at St. Augustine, Daytona Beach, New Smyrna
Beach, Eau Gallie, West Palm Beach, and Miami for the use of recrea-
tional craft. At Daytona Beach, Titusville, Eau Gallie, and Fort
Pierce yacht basins open to the public have been provided, connected
with the Intracoastal Waterway by channels 6 to 8 feet deep and 80 to
100 feet wide. At Fort Pierce a channel 6 feet deep and 80 feet wide
has been dredged by the United States from the Intracoastal Water--
way to and up Taylor Creek to the United States Lighthouse Service
buoy depot. There are also a number of privately owned piers,
wharves, and landings at various points along the waterway. The
facilities are considered adequate in general for the existing com-
merce. (For further details on facilities at Jacksonville and Miami,
see Port Series No. 8, revised 1936, Corps of Engineers.)
    Qperationsand results during fiscal year-Maintenance.-The U. S.
pipe-line dredge Congaree was employed for maintenance dredging,
involving the removal of critical shoaling as follows: At Monet
Bridge, Bakers Haulover, and in the vicinity of Deerfield from July 2
to 6, and July 93 to August 3, 1943; between the St. Johns River and
the vicinity of Matanzas Inlet from November 6, 1943, to February
15, 1944; and 2 rock shoals, respectively, 1.4 miles north of Wabasso
Bridge and 1 mile north Vero Beach Bridge, both of which required
blasting, and 8 other shoals located between Vero Beach Bridge and
Bakers Haulover, from February 21 to May 25, 1944. There were
removed 513,204 cubic yards of material from 20 shoals, aggregating
30,617 linear feet in length, at a cost of $186,009.87. Periodic surveys
and inspections to determine the condition of the improvement were
made at a cost of $17,836.65.
    Operating and care.-The steel and concrete double-leaf bascule
highway bridge near Palm Valley was operated and maintained.
The cost was $9,118.22 for operation, and $133.62 for repairs, a total
of $9,251.84.
   The costs for the year were $203,846.52 for maintenance and $9,-
951.84 for operating and care, a total of $213,098.36. The expendi-
tures were $212,519.08.
    Condition at end of fiscal year.-The existing project was com-
pleted in 1935 except for the provision of a turning basin in the
vicinity of Jacksonville Beach. The construction of a steel and con-
crete double-leaf bascule highway bridge near Palm Valley, Fla., to
replace the temporary pontoon bridge at that locality, was completed
in 1937. The controlling depth at mean low water, as determined
from surveys made from September 1943 to May 1944, was 8 feet for
a width of 100 feet except in the following reaches which had control-
ling dimensions as follows: Matanzas Inlet to Ponce de Leon Inlet, S
feet for a width of 50 feet, October 1943; Ponce de Leon Inlet to Haul-
over Canal, 7.2 feet for a width of 50 feet, October 1943; and Haulover
516          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

Canal to Melbourne, 6.6 feet in the central 30 feet of channel, with
8 feet available in the easterly 50 feet, September 1944. Project
width of 100 feet is reduced at 53 localities by bridges with a limiting
horizontal clearance of 52 feet at the Deerfield Beach bridge.
    The total costs under the existing project have been as follows:

                                                      New work               Mainte-
                                                                             nance                    Operating
                                                                                                      and care           Total


Regular funds_ ....-------------------------         $5, 052,153. 72 $2,  281.61
                                                                       643,                           $50, 660. 52    $7, 746, 095.85
Public Works funds..........----------------------   2,199,841.72      ............--------------..                    2, 199, 841.72

     Total, United States funds- ----------- 7, 251, 995. 44 2, 643, 281.61                            50, 660.52      9, 945, 937. 57
Contributed funds....-------------------------------------5,500.00                                --------------.           5, 500. 00
      Total, all funds. ........................     7, 251, 995. 44     2, 648, 781.61                50, 660. 52     9, 951, 437. 57


  The expenditures have been $9,938,815.50 United States funds, in-
cluding $2,199,841.72 Public Works funds. In addition, $5,500 were
expended from contributed funds for maintenance, and $3,179.07 were
expended between July 1, 1934, and June 30, 1935, on the operating
and care of the works of improvement under the provision of the per-
mnanent indefinite appropriation for such purposes.
  Proposed operations.-Thebalance unexpended June 30, 1944, $25,-
590.78, plus $158,400 allotted during July 1944, a total of $183,990.78,
will be applied as follows:
Accounts payable June 30, 1944__------------------------------$7, 122.07
Maintenance:
    Emergency repairs to approximately 2,200 linear
      feet of the south dike on the Indian River side
     ,of the Haulover Canal by placing native stone,
      by contract, November 1944------------ ---       $15, 000. 00
    Dredging, with U. S. pipe-line dredge Congaree, to
      remove critical shoaling between St. Johns River
      and Melbourne, as required, about 4 months,
      July 1 to Oct. 31, 1944----------------           100, 000.00
    Dredging, with U. S. pipe-line dredge Congaree, to
      remiove critical shoaling between Melbourne and
      Miami, as required, about 1.5 months, May 1 to
      June 15, 1945-----------------------               36, 500. 00
    Miscellaneous surveys, inspections, and contin-
      gencies------------------- ----------              15, 968. 71
                                                                     167, 468. 71
                                                                     167, 468.71
Maintenance (operating and care):
    Operation of Palm Valley highway bridge..             9,000. 00
    Ordinary repairs---- .........-------                    300.00
    Emergencies_---------------------------------            100.00
                                                                       9, 400. 00

         Total for all work------------------------------                                                            183, 990. 78
  The additional sum of $165,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredging to remove critical shoaling throughout the
      project, as required, with U. S. pipe-line dredge Con-
      garee, about 5% months, July to September 1945, and
      February to April 1946_-------------------------       $143, 600
    Miscellaneous surveys, inspections, and contingencies- _   12, 000
                                                                                                                       $155, 600
              RIVERS AND HARBORS---JACKSONVILLE,                                  FLA., DISTRICT                    517
Maintenance (operating and care):
   Operation of Palm Valley highway bridge- ------------                                         $9, 000
    Ordinary repairs -----------------------------------                                             300
   Emergencies_--------------------------------------                                                100
                                                                                                       -        $9, 400
            Total for all work -------------------------------------                                          165, 000
  No funds can be profitably expended for new work during the fiscal
year 1946 as the requirements of local cooperation affecting the re-
maining work have not been complied with and the completion of the
project is not considered essential at this time.
                                       Cost and financial summary

Cost of new work to June 30, 1944                                                                  $7, 346, 770. 69
Cost of maintenance to June 30, 1944---------------------                                          1 2, 910, 343. 45
      Total cost of perma)nent work to June 30, 1944        10, 257, 114. 14  ---------
Minus accounts payable, June 30, 1944----------------------       7, 122. 07
      Net total expenditures ---------------------------  1 10, 249, 992. 07
Unexpended balance, June 30, 1944------------------------        25, 590. 78
            Total amount appropriated to June 30, 1944-                                      -1 10, 275, 582. 85

    Fiscal year ending June 30             1940             1941           1942              1943               1944


Cost of new work     -                      $547. 73.
Cost of maintenance------------          150, 980. 62    $81, 588.88    $214, 973. 91    $381,531.15          $213, 098. 36

      Total cost-------           -      151, 528. 35     81, 588.88     214, 973. 91     381, 531.15          213, 098. 36
Total expended_                          147, 497. 75     97, 918. 54    213, 260. 85     382, 624. 75         212, 519. 08
Allotted-       -           -            131, 947. 84     91, 700. 00    284, 300. 00     415,100. 00           35, 000.00


Balance unexpended, July 1, 1943----------------_           ----------                                 $203, 109. 86
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942 ----------------------------------                                                 35, 000. 00
       Amount to be accounted for-------------------------                                                 238, 109: 86
Gross amount expended---------------------     $229, 978. 76
Less reimbursements collected-----------------   17, 459. 68
                                                                                                           212, 519. 08
       Balance unexpended, June 30, 1944---- ---------------                                                25, 590. 78
Outstanding liabilities, June 30, 1944.------------------------                                              7, 122. 07
     Balance available, June 30, 1944----------------- ----                                                 18, 468. 71
Amount allotted in July 1944 ------------------------------                                                158, 400. 00
            Amount available during fiscal year 1945---- -                              -- - -             176, 868. 71
Amount (estimated) required to be appropriated for completion
of existing project 2- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -    -
                                                                                                            20, 000.00
Amount that can be profitably expended                     in fiscal year ending
June 30, 1946, for maintenance 2- - - - - - - - - - - - - - - - - - - - - - - - -                         165,000.00
  1 In addition, $5,500 contributed funds expended for maintenance under authority of act of Mar. 4, 1915.
  2 Exclusive of available funds.
518      REPORT OF CHIEF OF ENGINEERS, U.      S. ARMY,   1944

                  6. ST. AUGUSTINE HARBOR, FLA.

  Location.-On the east coast of Florida, about 33 miles south of the
entrance to St. Johns River and about 180 miles north of Fort Pierce
Harbor. (See U. S. Coast and Geodetic Survey Charts Nos. 842 and
1243.)
   Previous projects.-Appropriations were made by the acts approved
March 2, 1829, and June 27, 1834, for a survey of the harbor and the
bar at the entrance. The River and Harbor Act approved'August 11,
1888, authorized the improvement of the harbor subject to a subsequent
report of a board of engineers. For further details see page 284, An-
nual Report for 1904, and page 623, Annual Report for 1938.
   Existing project.-This provides for an entrance channel 200 feet
wide and 27 feet deep at mean low water to be dredged from the ocean
across North Point to deep water in Tolomato River opposite the
mouth of Matanzas River and protected at its outer end by a steel-
sheet-pile sand trap extending from the coast north of and parallel to
the cut. The length of the channel is approximately 4,500 feet from
the 27-foot contour in the ocean to North Point and thence 3,550 feet
through the cut across the land point to the 20-foot depth contour in
the Tolomato River. The mean range of tide at the inlet is about 4.5
feet, and the extreme range about 7 feet.
   The estimate of cost of new work, made in 1937, was $275,000, ex-
clusive of amount expended on previous projects but including $137,-
500 contributed by local interests. The latest (1937) approved esti-
mate for annual cost of maintenance is $25,000. The existing project
was adopted by the River and Harbor Act approved June 20, 1938
(H. Doc. No. 555, 75th CoQng., 3d sess.). The latest published map is
in the project document.
  Local cooperation.-Fully complied with.
   Terminal facilities.-There are four timber docks on the Matan-
zas water front of St. Augustine, one being the municipal yacht dock
south of the highway bridge, one a fish dock, and two private docks.
The principal terminals are the numerous shrimp docks located in
the San Sebastian River which flows southward through the city into
the Matanzas River below the bridge; these consist of timber wharves,
with frame and corrugated-iron warehouses erected on them. The
present terminals have highway connections, and several of the shrimp
docks have rail connections. They are considered adequate for existing
commerce and yacht traffic, but there are no terminals suitable for
an extensive general commerce.
   Operationsand results during fiscal year.-Work under a contract
for repairing approximately 350 feet of the inner end of the existing
sand-trap groin and constructing a shoreward extension approxi-
mately 300 feet long at an angle of 450 to the existing groin, was
Commenced September 28 and completed December 21, 1943. Ap-
proximately 5,500.20 tons of granite, including 1,695.65 tons of 20-
to 300-pound granite and 3,804.55 tons of 300- to 1,000-potund granite,
weie placed in the structure; and 2,641.3 cubic yards of material were
excavated. The cost was $55,631.21. An adjustment in the cost of
periodic surveys and inspections pertaining to the previous fiscal
year reduced the cost of this feature $1,068.76. The total cost for
the year was $54,562.45 for maintenance. The expenditures were
$55,274.18.
               RIVERS AND HARBORS-JACKSONVILLE,                                                 FLA., DISTRICT                 519

  Condition at end of fiscal year.-The existing project was com-
pleted in 1941. The dredging was completed in 1940 and the granite,
native rock, and creosoted-timber sand-trap groin, 1,580 feet long
and extending from the coast line into the ocean, was completed in
1941. The groin is 740 feet north of and parallel to the northerly
edge of the channel. An extension at an angle of 450 and 300 feet
long was constructed at the shore end in 1943 to stop the flanking
of that end of the structure by sea action. The groin is in good
condition. The controlling mean-low-water depth in November 1943
was 8.8 feet in the northerly half of the channel, reducing to 6.2 feet
along the southerly edge of the channel, and located about 1,000 feet
seaward. of the seaward end of the sand-trap groin. The costs and
expenditures under the existing project have been $392,787.72 for
new work and $135,212.19 for maintenance, a total of $597,999.91. In
addition, $137,500 were expended from contributed funds for new
work.
  Proposed operations.-The balance unexpended June 30, 1944,
$3,700.09, is available for revocation.
  No funds can be profitably expended during the fiscal year 1946,
as the condition of the project is expected to meet the needs of com-
merce during the next 2 years.
                                                Cost and financial summary

Cost of new work to June 30, 1944----------------------------                                                    1$464, 090. 56
Cost of maintenance to June 30, 1944--     ----------                                                                  135, 212. 19

          Total cost of permanent work to June 30, 1944-                                                 -             599, 302. 75

Net total expenditures                         -----------------------------------                                     599, 302. 75
Unexpended balance June 30, 1944_-                               __-------------3,                                          700,09

          Total amount appropriated to June 30, 1944 - -                                             -            1 603, 002 84

    Fiscal year ending June 30                     1940             1941                 1942             1943              1944

Cost of new work- _.........   ..   $109, 975. 88                $212, 573.35        $70, 238.49
Cost of maintenance ..... - __    .    2, 109. 42                  11,853. 58         60, 750. 00        $5, 936. 74       $54, 562. 45
       Total cost   ----------------             112, 085. 30     224, 426. 93       130, 988. 49         5, 936. 74        54, 562.45

Total expended        .....                        101, 179.39
                                 .....----------------            135, 847. 44       230,161.24           5, 537. 66        55, 274.18

Allotted.__-          .---------.-----------                      277, 000.00           59,000. 00       25, 000. 00        33, 200.00


Balance unexpended July 1, 1943---      ---------                                                                      $25, 774. 27
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940             $26, 500. 00    -----------
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941------------    6, 700. 00
                                                                                                                        33, 200. 00

       Amount to be accounted for_---------        ---- __ -                                                            58, 974. 27
Gross amount expended_------                ---   $56, 535. 73
Less reimbursements collected.-------------------- 1, 261. 55
                                                                                                     ------             55, 274. 18

          Balance unexuended June 30. 1944_-                                     ----                    ----            3, 700. 00
  1In addition,     $137,500 expended from contributed funds for new work.
520          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                     1944

                              7. FORT PIERCE HARBOR, FLA.
   Location.--On the east coast of Florida, about 213 miles south of
the entrance to St. Johns River and about 124 miles north of the
entrance to Miami Harbor. (See U. S. Coast and Geodetic Survey
Charts Nos. 1247, 582, and 845.)
   Existing project.-This provides for the maintenance and amplifi-
cation of the project developed by private interests to provide a chan-
nel 350 feet wide at the 27-foot contour in the ocean, tapering to 200
feet wide at station 100, near the westerly side of the inlet, thence 200
feet wide across Indian River to station 30, thence flaring to a turning
basin 750 feet wide, the depth to be 25 feet in the basin and in the
channel to station 130, and thence 27 feet to the 27-foot contour in the
ocean; and for the maintenance of the jetties at the ocean end of the
inlet, and shore revetments within the inlet in prolongation of the
jetties. The two parallel rubblestone jetties with revetment exten-
sions, which local interests constructed to protect the entrance, are
900 feet apart, the north jetty and revetment being about 3,500 feet
long, and the south jetty and revetment about 3,200 feet long. The
mean range of tide is about 2.6 feet at the entrance and 0.7 foot at
the terminal, with northeast storm tides as high as 5 feet above mean
low water.
   The estimate of cost for new work, revised in 1937, was $322,000.
The latest (1935) approved estimate of cost for annual maintenance
is $250,000 for initial restoration, $50,000 a year for a period of 4
years, and $30,000 a year thereafter.
   The existing project was authorized by the following river and
harbor acts:

              Acts                             Work authorized                            Documents


Deficiency Act of Mar. 4, 1931-_-   The expenditure of $20,000 for dredging     Specified in act.
                                      the channel, provided that local in-
                                      terests agree to maintain said channel.
War Department Appropria-           The expenditure of up to $30,000 for            Do.
tion Act, Mar. 4, 1933.              dredging the channel.
Aug. 30, 1935 (maintenance in-      For maintaining the channels, jetties,      H. Doc. No. 252, 72d Cong.,
eluded in Public Works Ad-          and revetments, and the enlargement          1st sess.
ministration program Sept. 6,       of the channels and turning basin to       Rivers and Harbors Com-
1933).                              the existing project dimensions.             mittee Doc. No. 21, 74th
                                                                                  Cong., 1st sess. (Contains
                                                                                 latest published maps.)


  Local cooperation.-Fullycomplied with as to original construction.
The River and Harbor Act approved August 30, 1935, imposed the
condition that local interests furnish suitable spoil-disposal areas for
subsequent maintenance. Adequate spoil-disposal areas have been
furnished in perpetuity.
  Terminal facilities.--These consist of two earth-filled piers retained
by steel sheet-piling and enclosing a slip 200 feet wide by 330 to 350
feet long with bulkhead wharf at inner end. These facilities afford
        RIVERS   AND HARBORS       JACKSONVILLE, FLA.,     DISTRICT      521
a berthing space of about 1,653 feet. The south pier and the bulkhead
wharf are municipally owned, the pier having a berthing space of 524
feet, with depths of 25.5 to 18 feet. The bulkhead is used for tie-up
of Government vessels. A warehouse 75 by 280 feet is on the mu-
nicipal pier, and a precooling plant 102 by 365 feet occupies the north
pier, just landward of which is another warehouse, 50 by 100 Teet. A
fruit-packing house 170 by 225 feet is located at the west end of the
slip. The north pier is served by railway and both piers by highway
connections. North of the turning basin there is a bulkhead wharf
with a depth of 15 to 12 feet and with tank storage in the rear for
petroleum products. The facilities are considered adequate for exist-
ing commerce.
   Operations and results during fiscal year.-The U. S. pipe-line
dredge Congaree was employed from May 30 to June 26, 1944, in
maintenance dredging to remove an obstructive shoal near the easterly
end of the channel across Indian River and shoaling in the turning
basin. There were removed 69,133 cubic yards of material, resulting
in the restoration of project dimensions in the cut across Indian River
and in the turning basin.
   The total cost was $20,000 for maintenance. The expenditureswere
$2,546.11.
   Condition at end of fiscal yea.-The existing project was completed
in 1938, and the rehabilitation of the jetties originally constructed by
local interests was completed in 1934. Both jetties and the south
revetment are in good condition and the north revetment is in fair
condition, numerous stones having fallen into the land cut, leaving
the structure ragged along the water side. The controlling mean-low-
water depths when last ascertained were as follows: Outer Bar Cut,
26.4 feet for a width of 150 feet located about opposite the seaward
end of the south jetty, December 1943; channel between the land revet-
ments, 25 feet for project widths except for a spot shoal with a limiting
depth of 22.9 feet located about 25 feet inside the north channel line,
December 1943; channel across Indian River, 25 feet for a width of
200 feet, June 1944; and turning basin, 25 feet throughout, June 1944.
   The total costs have been $887,839.96, of which $337,182.67 was for
new work, and $550,657.29, including $250,000 Public Works funds,
was for maintenance. The expenditures have been $870,386.07.
   Proposed operations.-The balance unexpended June 30, 1944, $17,-
453.89, plus $20,000 allotted during July 1944, a total of $37,453.89,
will be applied as follows:
Accounts payable June 30, 1944_ ----------------------------- $17, 453. 89
Maintenance: Dredging to restore project dimensions throughout
the entrance channel, with U. S. hopper dredge San Pablo, about
 % month, February 1945---------------------------- -----          20, 000.00

      Total for all work-----------------------------------        37, 453. 89
   The additional sum of $30,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging to remove shoaling
throughout the improvement as required, with U. S. hopper dredge
San Pablo, 1 month, March 1946.
522              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

                                                          Cost and financial summary
Cost of new work to June 30, 1944___---                                      ------                     _                  $337, 182. 67
Cost of maintenance to June 30, 1944_                                                  _------                   .---       550, 657. 29
      Total cost of permanent work to June 30, 1944------------                                                             887, 839. 96
Minus accounts payable June 30, 1944_-------             ---                                                                 17, 453. 89

      Net total expenditures-__-         -----------                                                                         870, 386. 07
Unexpended balance June 30, 1944-_ ----.------                                                                  ---        -17,   453. 89
             Total amount appropriated to June 30, 1944                                 --------------                       887, 839. 96


    Fiscal year ending June 30                              1940         1941            1942                   1943                1944
Cost of new work__ . . . . . .. . .                            . .. .. _ .       .      .        .          .          .       .        .
Cost of maintenance-.............-$46, 357.80                           $1,573.42     $20, 708.42           $38, 000.00            $20,000.00
Total expended...............----------------..            46, 255.19      970. 51      21, 413. 94          38,000 00               2, 546.11
Allotted                ........----------------------.    20, 000.00   20, 500.00    -24, 000.00            38, 000.00             20, 000.00


Amount allotted from War Department Civil Appropriation Act ap-
  proved July 19, 1937_--------             -------    _ __                                                                  $20, 000. 00
Gross amount expended_-         _ ------             -    ____                                                                 2,546. 11

      Balance unexpended June 30, 1944 ----------------------                                                                 17, 453. 89
Outstanding liabilities June 30, 1944_--  ----------                                                                          17, 453. 89
Amounted allotted in July 1944 -----------------------                                                                        20, 000. 00
Amount available for fiscal year 1945_-------                                                         ___                     20, 000.00
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance-1   -------        ___-____--30,                                                                          000.00
   1Exclusive of available funds.

                                                 8. LAKE WORTH INLET, FLA.

   Location.-On the east coast of Florida about 71 miles north of
the entrance to Miami Harbor and is the entrance channel to the Port
of Palm Beach. (See U. S. Coast and Geodetic Survey Charts Nos.
1248 and 846.)
   Existing project.-This provides for the maintenance and ampli-
fication of the improvements constructed by local interests to provide
a channel 20 feet deep and 300 feet wide from deep water in the ocean
to station 69+00, thence reducing to a width of 200 feet at station
65+00, near the westerly side of the inlet, thence 200 feet wide across
Lake Worth to station 33 + 23, thence flaring to a turning basin of the
same depth, 700 feet square; for the removal of the obstructive point
on the south side of the inlet; for the revetment of the banks of the
inlet; and for restoration of the existing jetties. The jetties con-
structed at the entrance by local interests consist of two parallel rub-
blestone structures 800 feet apart, the north jetty and revetment being
about 1,800 feet long and the south jetty 1,700 feet long. The mean
range of tide is 2.8 feet at the inlet and 1.8 feet at the Port of Palm
Beach terminals. The extreme range is about 41/2 feet at the inlet
and 3 feet at the terminals.
   The estimate of cost for new work, made in 1935, was $548,000.
The latest (1935) approved estimate of cost for annual maintenance
is $30,000.
            RIVERS AND HARBORS-JACKSONVILLE,                               FLA., DISTRICT             523

   The existing project was authorized as follows:

    Acts                        Work authorized                                    Documents


     (1)       Maintenance of improvement previously con-            H. Doc. No. 185, 73d Cong., 2d sess.
                structed by local interests.
    , (2)      Deepening of channels and turning hasin, as con-      Recommended by Chief of Engineers
                structed by local interests, to 20 feet.              to Public Works Administration
                                                                       Oct. 17, 1934.
Aug. 30,1935   Authorized the work previously approved by            H. Doc. No. 185, 73d Cong., 2d sess.,
                Public Works Administration, and for widening         and Rivers and Harbors Committee
                of the channels to existing project dimensions,       Doc. No. 42, 74th Cong., 1st sess.
                enlargement of turning basin, removal of ob-          (Contains latest published maps.)
                structive point on south side of the inlet, revet-
                ment of the banks of the inlet, and restoration of
                existing jetties.


2Public Works Administration program Mar. 13, 1934.
2 Public Works Administration program Dec. 10, 1934.


   Recommended modification of project.-Under date of March 3,
1944, the Chief of Engineers recommended modification of the exist-
ing project to provide for deepening the present channel and turning
basin to 25 feet at mean low water, plus 1 foot overdepth in the turn-
ing basin and channel to station 65 + 00 and 2 feet overdepth seaward
of that station, at an estimated cost of $711,000, with no increase in the
present authorized cost of maintenance, subject to certain conditions
of local cooperation (H. Doc. No. 530, 78th Cong., 2d sess.).
   Local cooperation.-The authorized work is subject to the condi-
tion that local interests furnish, free of cost to the United States,
all lands needed for the disposal of dredged material and for the
improvement, including title to the jetties and easements over strips
of land adjacent to the channel through the inlet, which lie channel-
ward of due east and west lines passing approximately 100 feet land-
ward of the shore ends of the jetties. It is also stipulated that they
shall provide a suitable site at the terminals for a Government depot
for use in the maintenance of the waterways in the locality. Spoil
areas have been provided as required. All other requirements have
been complied with except that perpetual easements of access to the
north and south easement areas have not been furnished.
   Terminal facilities.-These consist of a slip 690 feet long, 210 feet
wide, and 22.5 feet deep, with a wharf on either side and a bulkhead
at the inner end, and two additional shore wharves. These facilities
afford a total berthing space of 2,092 feet, with depths ranging fronm
26 to 17 feet. All except one are owned by the Port of Palm Beach
Commission. A steel warehouse, 70 by 620 feet, and a wooden frame
building, 70 by 140 feet, have been constructed on the north side of
the slip; and the former precooling plant, 36 by 124 feet, north of the
warehouse has been remodeled for use as a warehouse for express
traffic. Two nearby storage depots for petroleum products and one
for tank-storage of imported fountain syrup are connected with the
terminals by pipe lines. Rail and highway connections, water supply,
and other facilities have been provided to the warehouse and shipside.
The facilities are considered adequate for existing commerce.
524         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

    Operations and results during fiscal year.-The U. S. pipe-line
dredge Congaree was employed- from July 7 to 17, 1943, in maintenance
dredging in the channel across Lake Worth between the turning basin
and station 60+00. There were removed 15,625 cubic yards of ma-
terial, which resulted in the restoration of project depth of 20 feet,
except for a spot shoal with a depth of 18.5 feet in the vicinity of
Peanut Island and for shoaling along the southerly edge of the chan-
nel near the easterly side of Lake Worth. The cost was $10,066.86.
The cost of a survey made during May 1944 to determine the condition
of the improvement was $489.86. The total cost for the year was
$10,556.72 for maintenance. The expenditures were $10,221.95.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1938. The enlargement and deepening of the entrance chan-
nel and turning basin originally constructed by local interests was
completed in 1937, and the rehabilitation of the stone jetties and revet-
ments and the removal of the obstructive land point on the south
side of the inlet were completed in 1938. As reconstructed, the
north jetty and revetment are 950 feet and 1,500 feet long, respectively;
the jetty has been capped with concrete for 850 feet from the shore-
-ward end, and the voids in the granite enrockment forming the sea
end of the structure have been filled with asphaltic concrete. The
south jetty and revetment are 1,890 feet and 420 feet long, respectively;
the jetty has been capped with concrete for 1,790 feet from the shore-
ward end, but asphaltic concrete was not placed in the voids of the
granite enrockment at the sea end. The turning basin is 700 feet wide
for 700 feet and thence, in about 850 feet, coverges to a width of 200
feet at its junction with the channel. Both jetties and the south
revetment are in good condition; the north revetment extending west-
ward from the west end of the north jetty is in bad condition, having
been broken down by wave action. The controlling depths, mean
low water Atlantic Ocean, ascertained in May 1944, were as follows:
Outer Bar Cut, 20.7 feet for a width of 150 feet; cut between jetties
and land revetments, 20 feet for a width of 300 feet; channel across
Lake Worth, 18.4 feet for a width of 200 feet; and turning basin,
22 feet throughout except along the southerly edge near the southeast-
erly corner, where the limiting depth is 20.5 feet. The total costs and
expenditures have been as follows:

                                                       New work        Maintenance            Total        Expenditures

Regular funds---__ ........................   $573,664.91               $332, 541.56      $906,206.47        $905, 851.81
Public Works funds--...----------------------   80,000.00                 30,000.00        110,000.00         110,000.00
      Total, all funds   -----------------------..............
                                                        653, 664. 91     362, 541.56     1, 016, 206. 47    1, 015, 851.81


   Proposed operations.-The balance unexpended June 30, 1944,
$1,778.65, plus $23,100 allotted during July 1944, a total of $24,878.65,
will be applied as follows:
Accounts payable June 30, 1944_----------                  ----      $354. 66
Maintenance: Dredging to restore project dimensions throughout the
  entrance channel, with U. S. hopper dredge San Pablo, about 0.9
  month, Aug. 10 to Sept. 6, 1944             _                 _  24, 523. 99
         Total for all work--                            _---------_                   ____                24, 878. 65
                  RIVERS AND HARBORS-JACKSONVILLE,                                                        FLA., DISTRICT                          525

   The additional sum of $30,000 can be profitably expended during
the fiscal year 1946 in maintenance dredging to remove shoaling
throughout the entrance channel and turning basin, with U. S. hopper
dredge San Pablo, about 1 month, during February and March 1946.
                                                  Cost an! financial summary
Cost of new work to June 30, 1944------------_  --------------                                                                   $653, 664. 91
Cost of maintenance to June 30, 1944 ------------------------                                                                     362, 541.56

      Total cost of permanent work to June 30, 1944                                                                             1, 016, 206. 47
Minus accounts payable June 30, 1944_        -354.                                                                                           66,

      Net total expenditures_ _______-----__                                                                                    1, 015, 851.81
Unexpended balance June 30, 1944----1,-                                                       __                     _               1 778. 65-

               Total amount appropriated to June 30, 1944 _                                                                     1, 017, 630. 46)


     Fiscal year ending June 30                       1940                  1941                   1942                  1943                 1944

Cost of new work .-                                       . --..     .       .     .      .         .     .      .       .      .        .        .
Cost of maintenance                                $26, 247. 92          $100, 724. 62         $86, 650. 91          $3, 302. 73             $10, 556. 72'
Total expended ..        . ............              48, 662. 53           39, 549. 24         148, 338. 35              3, 284. 39           10, 221.95
Allotted..............              .....-----------------------
                                                        25, 000.00        182, 000. 00        -25, 200.00             12, 000. 00     --------

Balance unexpended July 1, 1943_                                                                                                      $12, 000. 600
Gross amount expended - - -                                                        --          -        $10, 225. 01
Less reimbursements collected --- -                                                                           -3.06
                                                                                                                                       10, 221. 95,
              Balance unexpended June 30, 1944                                     .___                                                 1, 778. 65
Outsta nding liabilities June 30, 1944_ -----
                                          -                                                                           -354.                     66
              Balance available June 30, 1944_                                                                                          1, 423. 99'
Amouint allotted in July 1944--------------------------------23, 100. 0(9
              Amount available for fiscal year 1945--------------------                                                                24, 523. 99
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1_-   _____----------                                                                                       30, 000. 00
  1Exclusive of available funds.

                   9. HOLLYWOOD HARBOR                                    (PORT EVERGLADES), FLA.

   Location.-On the east coast of Florida, about 23 miles north of
Miami and about 48 miles south of Lake Worth Inlet (Port of Palm
Beach). The site of the harbor is in Lake Mabel. (See U. S. Coast
and Geodetic Survey Charts Nos. 546, 847, and 1248.)
   Existing project.-This authorizes the maintenance and amplifica-
tion of the improvement constructed by local interests to provide: A
channel 500 feet wide at its seaward end, converging to 400 feet at the
jetty entrance, thence converging to 300 feet at a point 1,000 feet
within the jetty entrance, and thence 300 feet wide to a turning basin
1,200 feet long and 1,550 feet wide over the major portion of its length,
all to a depth of 35 feet at mean low water; and for the maintenance of
two converging rubblestone jetties constructed at the entrance to pro-
tect the channel, and of two parallel steel sheet-piling bulkheads 800
feet apart to protect the land points of the inlet from erosion. The
entrance channel is approximately 7,300 feet long. The jetties area
526           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                     1944

700 feet apart at the outer ends and 1,200 feet apart at the shore ends.
'The north jetty is angular and about 1,450 feet long, whereas the
south jetty is straight and about 1,250 feet long. Both jetties were
built to 6 feet above mean low water with top widths of 6 feet at the
shore ends and 12 feet at the sea ends, nd with side slopes 1 on 11/2.
The mean range of tide is 2.5 feet at the entrance and 2.3 feet at the
terminals; the extreme range is about 4.5 feet, with storm tides of
about 6.5 feet.
   The estimate of cost of new work, revised in 1938, was $1,769,000.
The latest (1938) approved estimate of cost of annual maintenance is
$37,500.
   The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                    Documents


July     3,1930   Maintenance of the harbor as constructed by local     H. Doc. No. 357, 71st Cong., 2d sess.
                    interests.
Aug. 30,1935      For enlarging the entrance channel to existing        Rivers and Harbors Committee Doc.
                    project dimensions and completing the turning        No. 25, 74th Cong., 1st sess.'
                    basin to 1,200 feet square.
June 20,1938      For enlarging the turning basin to provide existing
                    project dimensions by adding a trapezoidal area
                                                                        H. Doc. No. 545, 75th Cong:, 3d sess.l

                    350 feet wide on the north side.


  i Contain latest published maps.

   Local cooperation.-Theconditions imposed by the River and Har-
bor Act approved June 20, 1938, included the requirement that local
interests agree to provide the slips, piers, and other terminal facilities
necessary for the full utilization of the improvement. A resolution
adopted January 26, 1939, by the Broward County Port Authority,
agreeing to provide suitable and sufficient slips, piers, and other ter-
minal facilities necessary for the full utilization of the improvement,
was accepted by the Chief of Engineers February 20, 1939, as satis-
factory assurance of compliance with that part of the required local
cooperation. In partial compliance with the conditions the port au-
thority has provided, north of the original slip, the second slip
described below under "Terminal facilities." All other requirements
affecting original construction have been fully complied with.
   The River and Harbor Acts approved August 30, 1935, and June
20, 1938, imposed the condition that local interests furnish suitable
areas for the disposal of dredged material for maintenance. Sufficient
temporary spoil disposal areas have been furnished when required.
   Terminal facilities.-These consist of three piers, one bulkhead, and
one mooring constructed around two slips off the turning basin, all
owned by the Broward County Port Authority. The docking facili-
ties provide 5,270 feet of berthing, with depths from 35 to 25 feet.
Slip No. 1 is 1,200 feet long and 300 feet wide, with steel bulkheads at
the end and both sides and a depth of 35 feet. Slip No. 2 is 700 feet
long, 300 feet wide, and 25 feet deep, with steel sheet-pile bulkheads
along its sides, so constructed that it can later be extended to 1,200 feet
long and deepened to 35 feet. A steel warehouse 1,120 by 75 feet and
a precooling plant have been built, with railway and highway connec-
                RIVERS AND               HARBORS--JACKSONVILLE,                                  FLA., DISTRICT                                        527

tions. Equipment for the transfer of railroad freight cars to and
from car ferries has been installed. Three nearby tank storage depots
for petroleum products and a tank depot for molasses are connected
with the terminals by pipe lines. The facilities are considered inade-
quate for present needs.
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1940. Local interests dredged an entrance channel 210 feet wide, 35
feet deep, and about 6,900 feet long, leading from the ocean to a par-
tially completed turning basin 1,200 feet square; and constructed two
converging angular stone jetties to protect the entrance channel, and
two steel sheet-piling bulkheads to protect the land points. The United
States has enlarged the entrance channel and turning basin to project
dimensions and has rehabilitated the jetties, including the straighten-
ing of the south jetty. Both jetties are in good condition, but the steel
sheet-pile bulkhead at the inner end of the south jetty is in poor con-
dition. The controlling mean-low-water depth in April 1944 was 35
feet with limiting widths of 200 feet in the channel from the ocean to
the seaward end of the jetties, thence 150 feet to the turning basin, and
500 feet in the turning basin.
   The costs and expenditures under the existing project have been
$1,436,853.83 for new work and $239,848.93 for maintenance, a total of
$1,676,702.76.
  Proposed operations.-No funds are available and no operations are
proposed for the fiscal year 1945.
   The sum of $30,000 can be profitably expended during the fiscal year
1946 in maintenance dredging in the entrance channel and in the turn-
ing basin, with U. S. hopper dredge San Pablo, about 1 month, during
February 1946.
                                               Cost and financial summary
Cost of new work to June 30, 1944------------------------                                                                  $1, 436, 853. 83
Cost of maintenance to June 30, 1944_-------           ---                                                                     239, 848. 93

       Total cost of permanent work to June 30, 1944----------                                                                1, 676, 702. 76
Net total expenditures                           --- -  --                                                                    1,676, 702. 76
Total amount appropriated to June 30, 1944                                                                                    1, 676, 702. 76

    Fiscal year ending June 30                     1940              1941                1942                       1943                            1944

Cost of new work...--------------.....         $181, 429.16      --                              .--------------.------------.--------------
Cost of maintenance-- ----------                 33, 540. 75      $110,708. 82   .......................
      Total cost----------------
                 .............         ..       214, 969. 91      110,708.82_ .......

Total expended.....----------------             237, 837. 52      140,004.89     -------------------                               --------------

Allotted    .                                   -- 205, 000.00
                    ... _.....-------------------........        -10, 754.05 ....                 ..............................


Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance ----------------------------                                                                          $30, 000. 00

                          10. MIAMI HARBOR                        (BISCAYNE BAY), FLA.

  Location.-Biscayne Bay is a large, shallow, salt-water sound lying
between the Florida Keys and the mainland on the east coast of Florida
near the southern extremity of the peninsula. (See U. S. Coast and
Geodetic Survey Charts Nos. 547, 847, and 1248.)
528           REPORT- OF CHIEF OF ENGINEERS, U. S. ARMY,                                 1944

   Emisting project.-This provides for a channel 30 feet deep at mean
low water and 500 feet wide from the ocean to near the outer end of
the north jetty, thence 300 feet wide through the entrance and across
Biscayne Bay to and including a turning basin 1,400 feet long and
1,350 feet wide, located on the westerly side of Biscayne Bay in front
of the municipal terminals; and for two parallel rubblestone jetties,
1,000 feet apart and with lengths of 3,000 feet and 2,750 feet, respec-
tively, on the north and south sides of the entrance. The southerly
boundary of the turning basin is to be in prolongation of the south
edge of the 30-foot slip dredged by the city of Miami. The total length
of the waterway under improvement is about 6 miles.
   The mean tidal variation is 2.5 feet at the entrance and 2 feet in the
bay. The extreme variation is about 4.5 feet at the entrance and 3
feet in Biscayne Bay. Strong easterly winds raise the water level
about 1.5 feet at the entrance and 1 foot in the bay. Strong westerly
winds lower the water level about 1 foot at the entrance and about
0.5 foot in the bay.
   The estimate of cost for new work, revised in 1937, was $7,004,000.
The latest (1937) approved estimate for annual cost of maintenance
is $80,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts     .                Work authorized                                  Documents


June 13, 1902    An 18-foot channel in a land cut across the penin-   H. Doc. No. 662, 56th Cong., 1st sess.
                   sula and construction of the north jetty.            (Annual Report, 1900, p. 1987.)
Mar.    2,1907 Construction of the south jetty and for a channel      Specified in act.
                  width of 100 feet.
July   25, 1912  Enlarging the channel to 20-foot depth and 300-      H. Doc No. 554, 62d Cong., 2d sess.
                  foot width, and extending the jetties.
Mar.    3, 1925 Deepening the channels to 25 feet, mean low water,    H. Doc. No. 516, 67th Cong., 4th sess.
                  with present project widths at the entrance and
                  a width of 200 feet across Biscayne Bay.
July    3, 1930 A channel width of 300 feet across the bay and        Rivers and Harbors Committee Doe.
                  enlarging the municipal turning basin, with           No. 15, 71st Cong., 2d sess.
                  expenditures thereon limited to $200,000.
Aug.   30, 19351 A depth of 30 feet from the ocean to and in the      Senate Committee Print, 73d Cong.,
                                                                                2
                  turning basin, with the existing authorized           2d sess.
                  project widths, including the 300-foot width in
                  the channel across the bay.
Aug.   26,1937 Extending the turning basin 200 feet to the south-     Rivers and Harbors Committee Doc.
                  ward.                                                No. 86, 74th Cong., 2d sess.2


1 Included in the Public Works Administration program Jan. 3, 1934.
2 Contains latest published maps.

   Recommended modifications of project.-Under date of July 29,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide an approach channel and turning basin,
at an estimated first cost of $3,275,000, with annual maintenance of
$30,000, in addition to that now required; subject to certain condi-
tions of local cooperation (H. Doc. No. 470, 76th Cong., 1st sess.).
   Further modification of the existing project, in lieu of the recom-
mendation contained in House Document No. 470, Seventy-sixth Con-
gress, first session, was recommended by the Chief of Engineers in a
       RIVERS AND      HARBORS-JACKSONVILLE,          FLA., DISTRICT       529

report requested by the Senate Committee on Commerce resolution
adopted August 6, 1941 and transmitted to Congress by the Secretary
of War October 30, 1943.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-These consist of 14 piers and wharves located
in Bascayne Bay, with an aggregate berthing space of about 13,555
feet, with depths of 31 to 18 feet. Five of the facilities have railway
connections, and all have highway connections except 1 located on
Fisher Island, which can be reached only by water. A municipal
yacht anchorage with a depth of 16 feet, and a municipal yacht basin
have been constructed for the use of recreational craft. One of the
municipal piers, the municipal open wharf, 1 private pier, and the
municipal yacht facilities are open to the public. In addition, there
are 6 piers and wharves located on Miami River, which are used by
smaller vessels serving the port. There are also numerous bulkhead
wharves and slips on this river which are used for mooring recrea-
tional craft. The facilities are considered inadequate for present
needs. (See Port Series No. 8, pt. 2, revised 1936, Corps of Engineers.)
   Operations and results during fiscal year.-Miscellaneous and pe-
riodic surveys and inspections incidental to the supervision of the proj-
ect cost $1,855.62 for maintenance. The expenditures were minus
$8,173.84.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The two stone jetties were completed during the calendar
year 1929, and the dredging was completed during the calendar year
1939. The total length of the north jetty and revetment is 4,688 feet,
and that of the south jetty and revetment, 3,850 feet. The two jetties
and revetments are in fair condition. The controlling mean-low-
water depths, when last ascertained in July 1941, were as follows:
Entrance channel, 30 feet for full project widths, except for a spot
shoal along the southerly side of the 300-foot channel across Biscayne
Bay, having a least depth of 29.6 feet located about 25 feet inside
the channel line; and turning basin, 29.6 feet for a width of 1,300 feet.
   The total cost, all funds, has been $7,909,805.92, of which $6,570,-
769.47, including $2,202,126.04 Public Works funds, was for new work,
and $1,339,036.45 for maintenance. The total expenditures have been
$7,914,964.85, including $2,202,126.04 Public Works funds.
   Proposed operations.-The balance unexpended and accounts re-
ceivable June 30, 1944, $8,416.50, will be applied as follows:
Accounts payable June 30, 1944                  -$122.                         56
Maintenance: Miscellaneous surveys, inspections, and contingencies     8, 293. 94
      Total for all work        ------------------------------------   8, 416.50
  The additional sum of $75,000 can be profitably expended during
the fiscal year 1946 for maintenance, as follows:
Repair the damaged portions of the jetties by placing new stone on the
  structures, by contract, July and August 1945 --                     $40, 000
Dredging, with U. S. hopper dredge San Pablo, to remove shoaling
  throughout the entrance channel and turning basin as required, 1
  month, December 1945 -------------------------------------            30, 000
Miscellaneous surveys, inspections, and contingencies          -5,          000

      Total for all work-                                                75, 000
      616634-45-pt. 1, vol. 1    34
530           REPORT OF CHIEF OF ENGINEERS,                                       U. S. ARMY,                     1944

                                      Cost and financial summary
Cost of new work to June 30, 1944---------------------------                                                      $6, 570, 769. 47
Cost of maintenance to June 30, 1944_    -      -     ---- -_                                                      1, 339, 036. 45
       Total cost of permanent work to June 30, 1944-------                                                        7,909, 805. 92
Plus accounts receivable June 30, 1944_--     --------                                                                 5,281.49

      Gross total costs to June 30, 1944                       ---------------------                               7, 915, 087. 41
Minus accounts payable June 30, 1944--                                 --------                                            122. 56
      Net total expenditures---                               -----------                                          7, 914, 964. 85
Unexpended balance June 30, 1944                       _---                       -                -3,                     135. 01

          Total amount appropriated to June 30, 1944                                  ------------                 7, 918, 099. 86


   Fiscal year ending June 30                 1940              1941                   1942                1943             1944

Cost ofnew work ..-------------------------
Cost of maintenance---------
                    .....         --...$38, 034. 42           $11, 933.32         $17, 552. 00           $16, 869. 80       $1,855.62
Total expended-               __....
                      _ _......           11, 941.67           13, 419.98             19, 967.45          25,224.38        -8,173.84

Allotted--------------------- 20,804.36
       ........................-                                7,000.00              24,400.00            8,000.00-


Balance unexpended July 1, 1943 _____                                                                               - $5, 038. 83
Gross amount expendedc                                                                S$162,   947. 12
Less reimbursements collected_                                                            171. 120. 96
                                                                                                                        - 8, 173. 84

       Balance unexpended June 30, 1944----------------3,135. 01
Outsta mding liabilities June 30, 1944_                  122. 56

       Balance available June 30, 1944_                                                                                  3, 012. 45
Accour nts receivable June 30, 1944                                                                            -         5, 281. 49
          Unobligated balance available June 30, 1944---------8,                                                            293. 94

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1.-                                 -                                                          75, 000. 00
  1 Exclusive of available funds.

11. CALOOSAHATCHEE                      RIVER AND LAKE OKEECHOBEE                                                   DRAINAGE
                                           AREAS, FLORIDA

   Location.-The Caloosahatchee River has its source in Lake Okee-
chobee and flows in a general southwesterly direction, emptying into
the Gulf of Mexico through San Carlos Bay, about 30 miles south of
the entrance to Charlotte Harbor. (See U. S. Coast and Geodetic
Survey Charts Nos. 473, 1255, and 1289.)
   Lake Okeechobee is a large, fresh-water lake located in south-central
Florida. (See U. S. Coast and Geodetic Survey Charts Nos. 804, 805,
and 1289.)
   St. Lucie Canal was constructed by the Everglades Drainage Dis-
trict as a control canal for Lake Okeechobee. It begins at about the
middle of the east shore of Lake Okeechobee and empties into the
south branch of the St. Lucie River at St. Lucie lock. The length of
the canal is 23.9 miles. (See U. S. Coast and Geodetic Survey Chart
No. 1289.)
   St. Lucie River, south branch, flows north from the entrance of the
St. Lucie Canal for about 7.4 miles to Stuart, where it joins the north
branch forming the St. Lucie River; thence east, southeast, and east
       RIVERS AND HARBORS-JACKSONVILLE,              FLA., DISTRICT       531
about 7.7 miles, emptying into the Indian River opposite St. Lucie
Inlet. (See U. S. Coast and Geodetic Survey Charts Nos. 846, 1247,
and 1289.)
   Taylor Creek is formed by the junction of several small creeks that
have their headwaters in Allapattah Flats and flows generally in a
southeasterly direction, emptying into Lake Okeechobee at its most
northerly extremity. (See U. S. Obast and Geodetic Survey Charts
Nos. 804 and 1289.)
   (For description of above waterways see p. 705, Annual Report for
1932.)
   Previous projects.-Adopted by River and Harbor Acts of August
2, 1882, and August 11, 1888. For further details see page 707, Annual
Report for 1932.
   Existing project.-The project for lower Caloosahatchee River pro-
vides for a channel 200 feet wide and 12 feet deep at mean low water
from the Gulf of Mexico to Punta Rasa, a distance of about 3.8 miles,
thence 100 feet wide and 10 feet deep at mean low water to Fort Myers
 (Edison Memorial Bridge), a distance of about 16.2 miles, with a turn-
ing basin at that point. The project for Caloosahatchee River and
Lake Okeechobee drainage areas provides for improving the Caloosa-
hatchee River and Canal from Lake Okeechobee to the Gulf of Mexico
by straightening and by dredging a channel which will provide a dis-
charge outlet capacity of 2,500 cubic feet per second from Lake Okee-
chobee and a navigation channel at least 6 feet deep and 80 feet wide,
including necessary control works (Lake Okeechobee to Fort Myers,
56.5 miles) ; for improving Taylor Creek by providing a channel 6 feet
deep, when the lake is at elevation 14, and 60 feet wide from the town
of Okeechobee into Lake Okeechobee, about 4.8 miles; for a levee about
67.8 miles long and a navigation channel 80 feet wide and 6 feet deep
when the lake is at elevation 14, following in general the south shore
of the lake for about 58.3 miles; for a north shore levee about 153/4
miles long; for replacing existing locks Nos. 1 and 2, St. Lucie Canal,
with a single new lock with a usable width of 50 feet and a usable
length of 250 feet, a depth of not less than 8 feet over the sills and a
new weir structure; for the protection of the St. Lucie Canal from
erosion and silting; and for improving St. Lucie River to provide a
channel 6 feet deep at local mean low water and 80 feet wide from
St. Lucie Canal to Indian River, about 15.1 miles.
    The total length of the waterway from the Gulf of Mexico to the
Intracoastal Waterway is about 165.3 miles via the channel along the
south shore of Lake Okeechobee, or 152 miles via the Liberty Point
Floodway Channel and the nonproject channel across Lake Okee-
chobee.
  The following tables show the principal features of the locks and
dams and protective works included in the project based on the mini-
mum water elevations as follows:
                                                                        Elevation
St. Lucie River-Indian River (Intracoastal Waterway) to St. Lucie lock-_  0. 0
St. Lucie Canal and Lake Okeechobee-St. Lucie lock to Moore Haven
   lock___ ------------------------------------------------------        14.0
Caloosahatchee Canal-Moore Haven lock to Ortona lock-- -----------       11. 5
Caloosahatchee River-Ortona lock to the Gulf of Mexico            -0.         0
                                                                                                 Locks and dams
                                                                                                ST. LUCIE CANAL


                    Distance                                         chamberof
                                                                    Width         Lift with      Depth over                                                       Type of
                                                                                                                                                                  Tp   o construction
                                                                                                                                                                           nt      i
                      from                                  Dis-    and great-    the above             with
                                                                                                 sills above
                                                                                                 the              Character
                                                                                                                  CharacterDate                                                                         of
   number
   numer              Ok             Nearest town          tance    est length    minimum           .
                                                                                                 minimum u        of founda-
                                                                                                                      tooDpi    Kind of dam                                                        com- Actual cost            0
                     chobee                               (miles)    available    water ele-     water ele-           tion                                    Lock                Dam             pletion
                     (miles)                                          for full      vation         vation                                                                                                                      N
                                                                                                                                                                           Concret,(needl

1 1.         ...           0. 3   Port Mayaca, Fla.          0.5    130 by 30..         0                      }Rock .....- Movable-.....___               Concrete.1      Conrleneedle             1925      $127, 448. 98
St.Lucie 2....           23. 9   Stuart, Fla                8. 0   250 by 50-         14.0 o        er 1...      Pile .       ..------
                                                                                                                                     do .-------...........---- do....     Concrete, rTainter        (3)      ,901,000.0
                                                                                                                                                                                                                               0.
                                                                                                                                                                                                                               LJ
                                                                                       CALOOSAHATCHEE RIVER


Moore Haven                0      Moore Haven,
                                    Fla.
                                                             0.75   50 by 250__         2.5     Uper 10.0__None..........Concrete
                                                                                               ,)Uper 1
                                                                                                            Ple
                                                                                                              I
                                                                                                            P.0_
                                                                                                                                                                           None....-       -        1935       556, 849.92
                                                                                                                                                                                                                               0
Ortona..                  15. 5   La Belle, Fla ...          8. 0   50 by 250__        11. 5    Uper        _do ......     Movable---------....... do .......              Concrete, Tainter        1937       856. 904. 15
                                                                                                            oe             11gate                                                control.
                                                                                                                                                                                                                               0
                                                                                                 Hurricane gates
Hurri-                                         Dis-     Width of chamber and        Lift at lake Depth over
cane              Nearest town                     t    greatest length avail-                  sills at lake Character of            Type of Construction              Type of gate       Date com-        Actual cost
                                                                         width      elevation     elevation
gate
No.
                                              (miles)    (feet) for full
                                                         able                         14 feet       14 feet    foundation                                                                    pleted


                                                                                                       Feet                                                                                                                    02
       2   Clewiston, Fla....----------0              50 feet wide, length un-    None                    10. 0          -.-
                                                                                                                   Pile .--          Concrete_ _----             _--Steel sector ...      Feb. 26, 1935      $309, 748.18
                                                        limited.
       3   Lake Harbor, Fla ....                  . 5 do.                  -      None                     10. 0 Rock-----.... --..-....-
                                                                                                                                     do..........--------------.--..do.......----------...do.....---------- 316, 938. 28
       4   Belle Glade, Fla.......---------     4.0 do...---------------------None                         10.0 __do ..........----        ---------------- do.......----------...do----------
                                                                                                                                     do........                                                       .... 350,025.30
       5   Canal Point, Fla ...                 0    .do.---------------------    None                                               do
                                                                                                           10.0 _-do .... ..----------.----    ---------------
                                                                                                                                                  .                  do......--------------..do...              262,464.60
                                                                                                                                                                                                        ..--------
       6   Okeechobee, Fla_                     6.0 .- do.--------------------- ' None                      7. 0 Pile--........  Concrete, with auto- _-do.....----------......              Dec. 11, 1936      373, 273. 30
                                                                                                                                    matic culvert con-
                                                                                                                                    trolled spillway.

  1 Constructed by Everglades Drainage District. It is provided with a bypass 50 feet wide, of unlimited length, and having a minimum depth of 8.5 feet on the sill. This lock and
dam will be eliminated after installation of the Tainter gates in the St. Lucie dam.
  2 Old Lock No. 2, constructed'by Everglades Drainage District, is adjacent to the new lock and will serve as an auxiliary after installation of Tainter gates in the new dam and an
auxiliary lock gate on the upstream side of the old lock. This lock is 30 by 130 feet in the clear, with a limiting depth of 4.7 feet on the lower sill.
  3 Substantially completed in 1943 except for the installation of the Tainter gates in the dam. This is now controlled by temporary wooden needles.
  4 Cost estimated.
  a Combined hurricane gate and lock (no spillway).
              RIVERS AND           HARBORS-JACKSONVILLE,                      FLA.,     DISTRICT           533
  The mean range of tide is 1.7 feet at Punta Rasa and 0.7 foot at
Fort Myers. The extreme range is about 41/2feet at Punta Rasa and
about 2 feet at Fort Myers. Tidal influence is perceptible at the Ortona
lock, 57.3 miles above Punta Rasa, at low-river stage. The mean range
of tide at St. Lucie Inlet is 2.6 feet and the extreme range about 41/
feet. Tidal effect is perceptible to St. Lucie lock, 15.1 miles. Lake
Okeechobee is maintained, so far as possible, between 14 and 17 feet
above Lake Okeechobee datum.
   The estimate of cost for new work, revised in 1942, exclusive of
amounts expended on previous projects, is $18,636,450, of which $500,-
000 was contributed by local interests. The latest (1942) approved
estimate for annual cost of maintenance is $305,000, including $110,000
for operating and care of locks and dams and protective works.
  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                    Documents


Jane 25, 1910     For improving the Caloosahatchee River from           Rivers and Harbors Committee Doc.
                    Fort Myers to the Gulf of Mexico.                     No. 8, 61st Cong., 2d sess.
                                                                                                              1
July     3,1930   For the Caloosahatchee River and Lake Okeecho-        S. Doc. No. 115, 71st Cong., 2d sess.
                    bee drainage areas project (St. Lucie lock and
                    weir structure not included), subject to the con-
                    dition that local interests contribute $2,000,000
                    toward the cost and agree to maintain all works
                    and channels within the Everglades Drainage
                    District.
Aug. 30, 1935     For the United States to maintain all project         Specified in act.
                    works when completed and to bear the cost of all
                    drainage structures heretofore or hereafter
                    constructed in connection with the project, and
                    for the total cash contribution required of local
                    interests to be $500,000.
Aug 26, 1937      The construction of a new lock and weir structure     Rivers and Harbors Committee Doe.
                   in St. Lucie Canal.                                    No. 28, 75th Cong., 1st sess.


  1 Contains the latest published map of the lake. The latest published maps of the remainder of the
project are in H. Doc. No. 215, 70th Cong., 1st sess.


  Recommended modifications of project.--Under date of July 24,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for raising and enlarging sections of the
Lake Okeechobee levees in division No. 9, at an estimated cost of
$3,960,000, subject to certain conditions of local cooperation (H. Doc.
No. 469, 76th Cong., 1st sess.).
  Under date of April 10, 1940, the Chief of Engineers recommended
modification of the existing project so as to provide for a channel 8
feet deep from Fort Myers to the Intracoastal Waterway near Stuart,
with widths of 90 feet from Fort Myers to Moore Haven, 80 feet in the
existing channel along the southerly shore of the lake to the hurricane-
gate structure at Clewiston, 100 feet thence along a relocated channel
to deep water on the south side of the lake, 100 feet from deep water
on the east side of the lake to S. Lucie lock No. 2, and thence 80
feet to the Intracoastal Waterway; all at an estimated first cost of
$208,000, with annual maintenance of $1,500 in addition to that now
534     REPORT OF CBIEF OF ENGINEERS, U. S. ARMY,         1944

required, subject to certain conditions of local cooperation (H. Doc.
No. 696, 76th Cong., 3d sess.).
   Further modification of the existing projects was recommended by
the Chief of Engineers in a report requested by River and Harbor
Committee resolutions adopted February 20 and October 5, 1940, and
transmitted to Congress by the Secretary of War October 15, 1943.
   Local cooperation.-The requirements imposed by the River and
Harbor Act approved August 26, 1937, have been fully complied with.
Compliance with all prior requirements has been substantially com-
pleted.
   Terminal facilities.-In the vicinity of Fort Myers on the Caloosa-
hatchee River these consist of three freight piers, one railroad ter-
minal pier, one municipal recreation pier, four privately owned piers,
and a glunicipal yacht basin. A mooring basin has been provided at
La Belle. There are numerous small wooden-pile landings along the
upper Caloosahatchce River, along the lake shore, in St. Lucie Canal,
and on St. Lucie River, including one railroad terminal pier, a munici-
pal pier, and a pier for handling petroleum products at Stuart. A
marginal wharf 30 feet long and other limited facilities with highway
and railway connections are available on Taylor Creek at the town of
Okeechobee. The facilities are considered adequate for existing
commerce.
   Operations and results during fiscal year-New work.-The con-
struction of a new spillway with temporary wooden flashboards, and
of a protective dike at the new St. Lucie lock, which was in progress
by contract and substantially completed at the beginning of the fiscal
year, was completed. Faulty operation of the hydroturbine was cor-
rected and minor accessories delayed by war priorities were furnished
and installed. Final tests were completed and the work accepted
March 20, 1944. The cost during the fiscal year was $14,587.06.
   Maintenance.-Maintenance,by hired labor, of the completed levees,
including repair of ramp roads on levee, repair of ramp and cattle
fences, the removal of shoals in levee borrow pit along the south
shore, and the minimum care of trees previously set on the berm and
foreshore areas along approximately 45 miles of levee, cost $14,412.80.
United States plant and hired labor repaired the rock riprap and
concrete revetment along berm and channel slopes of exposed levee
in division 2." A total of 1,000 cubic yards of rock was salvaged from
the spoil banks along St. Lucie Canal, barged to the site of the work,
and placed on the levee berm during August and September 1943.
The cost was $10,447.84. Payment of contractor's claim for levee
work completed during the fiscal year 1940 cost $43,437.53. Drive
borings by hired labor, in connection with contractor's claim for
additional compensation for levee work completed in a prior fiscal
year, cost $449.77.
   The maintenance and operation of meteorological instruments and
the compilation of meteorological data cost $17,950.94. Periodic and
miscellaneous surveys and inspections cost $7,038.17.
   Operating and care.-The Moore Haven and Ortona locks on the
-Caloosahatchee Canal, lock No. 1 and the new St. Lucie lock, supple-
mented by old lock No. 2, on the St. Lucie Canal, 5 hurricane gates on
Lake Okeechobee, 16 drainage structures on the west, south, and east
                RIVERS AND HARBORS-JACKSONVILLE, FLA., DISTRICT                                                                      535
shores, and 4 on the north shore of Lake Okeechobee, 16 drainage
spillways on the St. Lucie waterway and an intercommunicating radio-
telephone network of 6 stations were operated and maintained to a
minimum extent consistent with wartime conditions. Routine main-
tenance of grounds at all structures was effected by hired labor. The
costs were $62,338.17 for operation, $18,973.42 for ordinary repairs,
and $1,447.56 for improvement and reconstruction, a total of
$82,759.15.
   Regulation.-The regulation of Lake Okeechobee consists of the
maintenance of lake stages as nearly as possible within elevations 14
and 17 feet, Okeechobee datum. No water was released from the
lake for purposes of regulation during the fiscal year. There was,
however, a continuous "local-use demand" discharge through the
local drainage canals owned and operated by the Everglades Drain-
age District. These discharges were as follows:

                                                                                                                                 Total
                                      Period                                              Lake  stage
                                                                                            (feet)             Discharge
                                                                                                              (second-feet)   discharge
                                                                                                                              (acre-feet)

July 1 to Sept. 18, 1943-------------...............------13.                                      29-14.60            101          15, 576
Sept. 19 to Dec. 31, 1943------------....                                     ---              14.60-15.12             287         103, 958
Jan. 1 to May 20, 1944---------------------------------....................................... 15.12-14.25             644         189,490
May 21 to June 30, 1944------------------------------...............................-.....     14. 25-13.76            398          33,418



   The total discharge during the year was 342,442 acre-feet, which
corresponds to a depth of 0.85 foot over the lake surface between lake
stages 13 and 15 feet.
   Summary.-The costs for the year were $14,587.06 for new work,
$93,737.05 for maintenance, and $82,759.15 for operating and care, a
total of $191,083.26. The expenditures were $175,900.
   Condition at end of fiscal year.--The existing project was about 99
percent completed. The project for Caloosahatchee River below Fort
Myers was completed in 1913. Essential features of the Caloosa-
hatchee River and Lake Okeechobee drainage areas project have been
accoiplished as follows: Dredging 56.1 miles of floodway and navi-
gation channel in the Caloosahatchee River and Canal from Moore
Haven to Fort Myers, having a minimum bottom width of 90 feet and
a depth of at least 7 feet, and the riprap protection of all drainage
openings and bridges between Moore Haven and Citrus Center; dredg-
ing 58.3 miles of navigation channel, having a depth of at least 6 feet
and a bottom width of at least 80 feet, in Lake Okeechobee along the
south-shore levee from the Fisheating Creek auxiliary floodway chan-
nel to St. Lucie Canal; dredging a channel at least 6 feet deep and
60 feet wide in Taylor Creek from the town of Okeechobee to Lake
Okeechobee, approximately 4.8 miles; dredging 5 auxiliary floodway
channels extending into Lake Okeechobee at the mouth of the Clewis-
ton industrial canal, in the vicinity of Liberty Point, near the mouth of
Fisheating Creek, at the mouth of Kissimmee River, and at the mouth
of Taylor Creek; dredging a channel 6 feet deep and 80 feet wide in
St. Lucie River, completed in 1931; constructing 67.8 miles of con-
tinuous levee on the west, south, and east shores of Lake Okeechobee,
536           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

and 15.74 miles of levee on the north shore; constructing a lock and
spillway near Ortona, a combined lock and hurricane gate at Moore
Haven, a new lock and a new spillway with temporary wooden flash
boards at the lower end of St. Lucie Canal near Stuart; construct-
ing 4 hurricane gates through the levee at the entrances to canals at
Clewiston, Lake Harbor, South Bay, and Canal Point, and a com-
bined hurricane gate and culvert spillway through the north-shore
levee at Taylor Creek; constructing 16 metal-pipe drainage culverts
with concrete headwalls through the west, south, and east shore levees,
and 4 similar culverts through the north-shore levee; constructing 16
drainage spillways at drainage openings in the banks of St. Lucie
Canal; levee enlargement and construction of a protective beach along
approximately 14.4 miles of the east-shore levee between Bacom Point
and Port Mayaca; and the extension of levee toe along 1.2 miles of
levee on the north shore between Nubbin Slough and Kissimmee River.
For information relative to locks and hurricane gates see table in the
paragraph "Existing project." The controlling depths at mean low
water, when last ascertained, were as follows, less than project depth
being due to isolated shoals: Gulf of Mexico to Punta Rasa, 12 feet
for a width of 150 feet, and thence to Fort Myers, 8.6 feet for a width
of 50 feet, in January 1943.; Fort Myers to Lake Okeechobee at Moore
Haven, 7 feet for a width of 90 feet, in October 1943; Lake Okeechobee
from Moore Haven to St. Lucie Canal via south shore channel, 7 feet
for a width of 50 feet, and via Liberty Point floodway channel, 6.5
feet for a width of 60 feet, in October 1943; St. Lucie Canal and River
to Intracoastal Waterway, 6 feet for a width of 80 feet, in October
1943; and Taylor Creek from the town of Okeechobee to Lake Okee-
chobee, 6 feet for a width of 60 feet, in October 1943. The work re-
maining to be done to complete the project is the completion of the
new spillway at the new St. Lucie lock, involving the installation of
7 steel Tainter gates and appurtenant features, and the removal of
old St. Lucie lock No. 1 at Port Mayaca.
   The costs of the existing project to June 30, 1944, have been as
follows:

                                                               New work           Maintenance             Operating
                                                                                                          and care            Total


Regular funds___ .......
                    ---- ..             ...----.--              8. 104, 788. 93   b5,  052, 578. 84      $746, 096. 86 $13, 903, 464. 63
Public Works funds._-- .              .--      .-.- ..--- .--- 7, 694, 360. 74    ..............                         7, 694, 360. 74
Emergency Relief funds             .........------------------- 2, 170, 253. 00                747. 00                   2,171,000.00
       Total, United States funds        -          -        17, 969, 402. 67      5, 053, 325. 84        746, 096. 86    23, 768, 825. 37
Contributed funds ....--------............              ..       500,000. 00             1,000.00            .       8     2501,000.   00
       Total, all funds.---. ---------.-..-                  18, 469, 402. 67      5, 054, 325. 84       - 746, 096. 86   24, 269, 825. 37



  The expenditures have been $13,862,040.01 regular funds, $7,694,-
360.74 Public Works funds, and $2,171,000 Emergency Relief funds,
a total of $23,727,400.75 from United States funds. In addition,
$501,000 was expended from contributed funds for new work and
maintenance as indicated above.
          RIVERS AND HARBORS-JACKSONVILLE,                          FLA., DISTRICT          537
  Proposed operation.-The balance unexpended and accounts re-
ceivable June 30, 1944, $42,054.23, plus $175,000 allotted during July
1944, a total of $217,054.23, will be applied as follows:
Accounts payable June 30, 1944                        -------------                $42, 054. 23
Maintenance:
    General inspection, patrol and maintenance of
       levees, levee fences, ramps, and protective tree
       plantings, in divisions 1, 2, 3, 4, and 9, July 1,
       1944, to June 30, 1945--------------------- $23, 500. 00
    Repair of the worst sections of deteriorated con-
       crete revetment along levee berm in division 1,
       near Liberty Point, by Government plant and
       hired labor, March and April, 1945                        -  _ 10, 000. 00
    Removal of shoals forming at side drainage openings
       along the Caloosahatchee channel in division 7,
       by Government plant and hired labor, Novem-
       ber and December, 1944_      ---------------------               8, 000. 00
     Compilation of meteorological data and mainte-
       nance and operation of weather instruments, July
       1, 1944, to June 30, 1945--------------__                       17, 500. 00
    Periodic and miscellaneous surveys, inspections, and
       contingencies, July 1, 1944, to June 30, 1945 -                 10, 000. 00
                                                                                    69, 000. 00
Maintenance (operating and care of locks, spillways,
  hurricane gates, drainage culverts, and a 6-station
  radio-telephone system):
    Operation                          -----------                    65,000. 00
    Ordinary repairs__-----------------------------                   38, 000. 00
    Improvements and reconstruction--- ------------                     3, 000. 00
                                                                                   106, 000. 00

       Total for all work      ----------------------------------                   217, 054. 23
  The additional sum of $390,000 can be profitably expended during
the fiscal year 1946, as follows:
New work:
   Begin, under contract, during March 1946, the com-
     pletion of new spillway for the St. Lucie lock, involv-
     ing the provision of 7 Tainter gates and other appurte-
     nant features_--------------------------------          $125, 000
   Begin removal, by contract, during June 1946, of old
     lock No. 1 and spillway at Port Mayaca, St. Lucie
     Canal ----------------------------------------            40,000
                                                                                        $165, 000
Maintenance:
    Maintenance of levee slopes, ramps, roads, protective
      growth, and fences in divisions 1, 2, 3, 4, and 9, by
      hired labor, between July 1, 1945, and June 30, 1946-                   22, 500
    Repairs of worst sections of deteriorated concrete revet-
      ment along berm of south shore levee in division 1,
      near Liberty Point, by replacing with rock riprap, by
      Gdvernment plant and hired labor, March to May
      1946_ -----------------------------------------                         20,000
    Dredging to remove shoaling in the St. Lucie River and
      Canal between Lake Okeechobee and the Intracoastal
      Waterway, with U. S. pipe-line dredge Congaree,
      about 1.4 months, May and June 1946- -----------                        35, 000
    Compilation of meteorological data, maintenance and
      operation of weather instruments, by hired labor,
      July 1, 1945 to June 30, 1946---------------------                      17, 500
    Periodic and miscellaneous surveys, inspections, and
      contingencies, July 1, 1945, to June 30, 1946----- --                   10, 030
                                                                         --              105, 000
538           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                   1944

Maintenance (operating and care of locks, spillways, hurri-
cane gates, drainage culverts, and a 6-station radio-
telephone system):
    Operation-------------------------------------$65,000
      Ordinary repairs__-                         -     -           --               -40,000

      Improvement and reconstruction--------------------                                            10, 000
      Emergencies -------------------------------------                                              5, 000
                                                                                                                  $120, 000
         Total for all work --------------------------------------                                                 390,000
                                             Cost and financial summary
Cost of new work to June 30, 1944- ---------------------                                                $17, 996, 852. 43
Cost of maintenance to June 30, 1944- ---------------------                                               5, 921, 558. 70

       Total cost of permanent work to June 30, 1944------    1 23, 918, 411. 13
Plus accounts receivable June 30, 1944 -------------------------         629. 61

      Gross total costs to June 30, 1944------------------                                                23, 919, 040. 74
Minus accounts payable June 30, 1944--42,                                                                          054. 23

      Nettotal expenditures-------------------------                                                    1 23, 876, 986. 51
Unexpended balance June 30, 1944--                                                                             41, 424. 62
         Total amount appropriated to June 30, 1944--------                                             1 23, 918, 411. 13

   Fiscal year ending June 30                    1940              1941            1942            1943              1944


Cost of new work-_.---.               -      -$654, 355. 98    $410, 063. 76    $251, 980. 10   $443, 374. 11       $14, 587. 06
Cost of maintenance- --..-.               .1,848, 984. 85     1, 181, 770.04     262, 941.66     264, 967. 93       176, 496. 20

      Total cost.-----------2,                 503,340. 83    1, 591, 833. 80    514, 921.76     708, 342.04        191, 083. 26

Total expended....--------------            2,367, 787.10     1, 557, 568. 25    541,645. 38     772, 673. 98       175, 900.00
Allotted--.          ...-.---    ..        -3, 302, 296. 17     523, 234. 75     553, 000. 00     87, 000. 00        33, 944. 80


Balance unexpended July 1, 1943---------------------------$183, 379. 82
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941
Amount allotted from War Department Civil Ap-
                                               $38, 944. 80          --------
  propriation Act approved Apr. 28, 1942        20, 000. 00         ---------
                                                             58, 944. 80
      Amount to be accounted for--- ------------------                                                          242, 324. 62
Deductions on account of revocation of allotment-------------                                                    25, 000. 00

       Net amount to be accounted for----------------------                                                     217, 324. 62
Gross amount expended-------------_  --------  $404, 090. 75
Less reimbursements collected-----------------  228, 190. 75
                                                                                                                175, 900. 00

      Balance unexpended June 30, 1944----- ---------------                                                      41, 424. 62
Outstanding liabilities June 30, 1944----------------------_                                       --            42, 054. 23

       Balance available June 30, 1944--------------------                                                        -629.      61
Accounts receivable June 30, 1944 __                -----------                                                      629.    61
Amount allotted in July 1944 -----------------------------                                                      175, 000.    00
Amount available for fiscal year 1945-                          -                                               175, 000.    00
Amount (estimated) required to-be appropriated for completion
  of existing project 2    --------------------------------------                                               165, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946:
      For new work 2165,                                                                                             000. 00
      For maintenance 2                                                                                         225, 000. 00
        Total 2                                                                                           -390,      000. 00
  1In addition, $500,000 expended for new work and $1,000                 for maintenance from contributed funds.
  2 Exclusive of available funds.
              RIVERS AND HARBORS-JACKSONVILLE,                                FLA., DISTRICT              539
                                  12. CHARLOTTE HARBOR, FLA.

   Location.-This harbor is a large bay on the west coast of Florida.
The entrance is 70 miles south of the entrance to Tampa Bay and 150
miles north of Key West. Pine Island Sound is an arm of Charlotte
Harbor extending southward to connect with San Carlos Bay at the
mouth of the Caloosahatchee River. (See U. S. Coast and Geodetic
Survey Charts Nos. 474 and 1255.)
   Previous projects.-Appropriations for removing obstructions were
made in 1881, 1882, and 1886. Improvement of Charlotte Harbor and
Peace Creek was authorized by acts of September 19,1890, and June 13,
1992. For further details see page 152, Annual Report for 1890; page
1828, Annual Report for 1915; page 291, Annual Report for 1904; and
page 658, Annual Report for 1938.
   Existing project.-Thisprovides for maintenance of a channel 7 feet
deep at mean low water and 100 feet wide in Pine Island Sound from
Punta Rasa to Charlotte Harbor, and for a channel 30 feet deep at mean
low water and 300 feet wide, increased to 700 feet wide at the bend, from
the Gulf of Mexico to South Boca Grande, just inside the entrance,
thence 10 feet deep and 100 feet wide from deep water at Boca Grande
to the end of the municipal terminal at Maud Street, Punta Gorda, with
a turning basin 200 feet square at the outer end of the terminal. The
mean range of tide is 1 foot at South Boca Grande and 1.4 feet at Punta
Gorda. The extreme range is about 3 feet at South Boca Grande and
33/4 feet at Punta Gorda. Strong southwesterly winds raise the water
level about 11/2 feet, and strong northly and easterly winds lower
it about 1 foot.
   The estimate of cost for new work, revised in 1937, exclusive of
amount expended on previous projects, and exclusive of $15,562 con-
tributed by local interests, was $151,600. The latest (1937) approved
estimate of cost for annual maintenance is $29,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                  Documents


June 13, 1902      Maintenance of a channel 7 feet deep and 100 feet    H. Doc. No. 286, 56th Cong., 1st sess.
                    wide in Pine Island Soundfrom Punta Rasa to
                     Charlotte Harbor. (New work completed
                    under previous projects.)
July 25,1912       A 24-foot channel 300 feet wide from the Gulf of     H. Doc. No. 699, 62d Cong., 2d sess.
                    Mexico through the Boca Grande entrance.
Mar.     3,1925    A depth of 27 feet at the entrance and a width of    H. Doe. No. 113, 66th Cong., 1st sess.
                     500 feet at the bend.
July     3, 1930   The 10-foot depth to Punta Gorda and the turning     Rivers and Harbors Committee Doc
                     basin at that point.                                 No. 1, 70th Cong., 1st sess.1
Aug. 26, 1937      The 30-foot depth at the entrance and the 700-foot   Rivers and Harbors Committee Doe.
                     width at the bend.                                   No. 95, 74th Cong., 2d sess.1


  1Contain latest published maps.

   Local cooperation.-Fullycomplied with.
   Terminal facilities.-These consist of a phosphate wharf at South
Boca Grande and a municipal earth-fill pier about 850 feet long, re-
tained by steel-sheet piling, at Punta Gorda. Both wharves are open
540               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                   1944

to the public. Railway connections are available at South Boca
Grande, and highway and railway connections are available at Punta
Gorda. The facilities are considered adequate for existing commerce.
 (For further details see Port Series No. 8, Corps of Engineers.)
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1939. The 7-foot-depth channel through Pine Island Sound
was completed in 1903, and the 10-foot-depth channel to Punta
Gorda and the turning basin at that point were completed in 1931.
When last ascertained the controlling depths were as follows: En-
trance channel to South Boca Grande, 27.8 feet for a width of about
175 feet, in November 1943; channel from South Boca Grande to
and including the turning basin at Punta Gorda, 9 feet for a width
of 100 feet, in October 1941; and channel through Pine Island Sound.
6 feet for a width of 100 feet, in February 1940. The costs and
expenditures under the existing project, including $6,000 for the
7-foot-depth channel in Pine Island Sound included in previous
projects prior to 1940, have been $199,964.76 for new work and
  387,052.73 for maintenance, a total of $587,017.49. In addition,
 $15,562.78 was expended from contributed funds for new work in the
Boca Grande entrance channel.
   Proposed operations.-No funds are available and no operations
araproposed for the fiscal year 1945.
   The sum of $60,000 can be profitably expended during the fiscal
year 1946 in maintenance dredging in the Boca Grande entrance
channel, with U. S. hopper dredge San Pablo 2 months, December
1945 and January 1946.
                                                 Cost and financial summary
Cost of new work to June 30, 1944__ _-_----_                                           _         ____           1 $312, 964. 76
Cost of maintenance to June 30, 1944                                              -------------                       387, 052. 73
       Total cost of permanent work to June 30, 1944-----------700, 017. 49
Net total expenditures_ -----------------                     -1   700, 017.49
Total amount appropriated to June 30, 1944_------------------    1 700. 017. 49


     Fiscal year ending June 30                    1940             1941             1942               1943               1944

Cost of new work--------------......             $25, 596. 75   -
Cost of maintenance............-------------      39,256.80          $244.   07----------------           $55.20-----------       -
          Total cost----------------
                      ....                        64,853. 55          244.07   ---------------                55. 20-        -

Total expended.............----------------...    79, 679.86          244.07   --------------                 55.20
Allotted-..........-----......57,                    000. 00         -66.17--------------
                                                                            ..............              1, 000.00          -$944.80


Balance unexpended July 1, 1943_---------                                                              ----               $944. 80
Deductions on account of revocation of allotment_-----                                                         --          944. 80
Amount that can be profitably expended in fiscal year ending June
     30, 1946 for maintenance_--------                              ---                          ___                    60, 000. 00
   1 Inaddition, $15,562.78 expended from contributed funds for new work.
       RIVERS AND HARBORS-JACKSONVILLE,            FLA., DISTRICT     541
                        13. TAMPA HARBOR, FLA.

   Location.-This harbor is a large natural indentation of the Gulf
of Mexico approximately midway of the western coast of the peninsula
of Florida. The entrance is about 220 miles north of Key West, about
330 miles from Pensacola, 360 miles from Mobile, and 512 miles from
New Orleans. (See U. S. Coast and Geodetic Survey Charts Nos. 586,
587, and 1257.)
   Previous projects.-Adopted by the following river and harbor
acts: For Tampa Bay, acts of June 14, 1880, and August 11, 1888; for
Tampa and Hillsboro Bays, acts of June 14, 1880, March 3, 1899, and
March 3, 1905; for Hillsboro River, act of June 14, 1880. For further
details see pages 1829, 1830, and 1831 of the Annual Report for 1915,
and page 665, Annual Report for 1938.
   Existing project.-This provides for a depth of 32 feet at mean low
water, and a width of 600 feet on Egmont Bar; for a depth of 30 feet
in all other project channels and basins, except in Hillsboro River, with
widths of 400 feet in Mullet Key Cut and in Ybor Channel and 300
feet in all other channels, and including the widening at the bend
between Sparkman Channel and Cut D of Hillsboro Bay Channel by
250 feet; for turning basins at the mouth of Hillsboro River (west
end of Garrison Channel), at the entrance to Ybor Channel and at
the entrance to the Port Tampa terminals, the latter to be 2,000 feet
long and 550 feet in maximum width; and for securing and main-
taining by dredging a channel 2,400 feet long, 200 feet wide, and 12
feet deep at mean low water in Hillsboro River from a point 100 feet
south of the Lafayette Street Bridge to the turning basin at the mouth
of the river. It also provides for the construction of a breakwater of
dredged material at Peter O. Knight Field, Davis Islands, maintenance
to be assumed by local interests. The approved plans for the turning
basin at the mouth of Hillsboro River provide for a basin of irregular
shape, roughly about 900 feet square, and involve a land cut of about
300 feet at the northwest corner of Seddon Island. The basin at the
entrance to Ybor Channel is to be obtained by widening the bend be-
tween Ybor and Garrison Channels by about 200 feet and by cutting
back the point at the junction between Garrison and Sparkman Chan-
nels by about 710 feet. The breakwater at the Peter O. Knight Field
will be roughly 2,000 feet long and will provide a partially enclosed
landing basin for seaplanes.
   The mean range of tide is 1.3 feet at the lower end of the bay, 1.6 feet
at Port Tampa, and 1.8 feet at Tampa. The extreme range is about
33/4 feet at the lower end of the bay and 43/4 feet at Tampa. Strong
southwesterly winds raise the water level about 1.5 feet. Strong
northerly winds, which usually occur in the winter months, lower the
water level about 2 feet.
   The estimate of cost of new work, revised in 1941, is $8,858,700, ex-
clusive of amounts expended on previous projects. The latest (1938)
approved estimate of cost of annual maintenance, exclusive of the
breakwater at Peter O. Knight Field, is $127,500.
542           REPORT OF CHIEF OF ENGINEERS,                              U.   S. ARMY,        1944


  The existing project was authorized by the following river and
harbor acts:

       Acts                          Work authorized                                   Documents


                                       TAMPA BAY


Mar.     3,1899   Improving Tampa Bay from its entrance into the H. Doc. No. 52, 55th Cong., 3d sess.,
                    Gulf of Mexico to Port Tampa.                         and Annual Report, 1899, p. 282.
Mar.     3,1905   For a channel depth of 26 feet with sufficient width- Specified in act.

                            TAMPA AND HILLSBORO BAYS


June 25,1910      For a depth of 24 feet in Hillsboro Bay..--...---...   H. Doc. No. 634, 61st Cong., 2d sess.'
                                                                                                                 1
Aug. 8,1917       For a 27-foot depth from Gulf of Mexico up to          H. Doc. No. 1345, 64th Cong., 1st sess.
                   and in the several channels of Hillsboro Bay,
                   the widths to be 500 feet on the bar, 300 feet in
                   Tampa Bay, Ybor and Garrison Channels, and
                   200 feet in Hillsboro Bay, Sparkman and Seddon
                   Channels, with turning basins at the mouth of
                   Hillsboro River and at Ybor Estuary.

                                     HILLSBORO RIVER


Mar.     3,1899   For a 12-foot project under the title "Improving       H. Doc. No. 545, 55th Cong., 2d sess.,
                   Hillsboro Bay, Fla."                                    and Annual Report for 1898, pp. 1357-
                                                                           1360.
Sept. 22,1922     Consolidation of the above projects to form a
                   single project for Tampa Harbor.
                        *        *         *           *      *



July    3,1930  Increasing the depth of Egmont Channel to 29             H.   Doc. No. 100, 70th Cong., 1st sess.
                  feet and the width of Sparkman Channel to
                  300 feet.
Aug. 830,1935 2 For a depth of 32 feet and a width of 600 feet on        S. Doc. No. 22, 72d Cong., 1st sess.
                  Egmont Bar; a depth of 30 feet and a width of
                  400 feet in Mullet Key Cut; and a depth of 30
                  feet and a width of 300 feet in all other project
                  channels in Tampa Harbor except in Hillsboro
                  River; a turning basin 2,000 feet long and 550
                  feet in maximum width at the entrance to the
                  Port Tampa terminals.
June 20, 1938   For widening the bend between Sparkman Chan-             S. Doc. No. 164, 75th Cong., 3d sess.
                  nel and Cut D of Hillsboro Bay Channel by
                  250 feet; widening Ybor Channel 50 feet on each
                  side to a total width of 400 feet; and extending
                  the turning basin at the west end of Garrison
                  Channel (mouth of Hillsboro River) for a dis-
                  tance of 300 feet in an easterly direction.
   Do....... For construction of a breakwater at Peter O.                Senate Committee Print, 76th Cong.,
                                                                                     1
                  Knight Field, Davis Islands, its maintenance             1st sess.
                  to be assumed by local interests.

  1 Contain latest published maps.
  2 Included in the Public Works Administration program, Sept. 6, 1933.


   Recommended modifications of project.-Under date of November
7,1940, the Chief of Engineers recommended modification of the exist-
ing project so as to provide in Hillsboro River a channel 9 feet deep
and 100 feet wide from the upper end of the existing project to a point
2,000 feet upstream from the Michigan Avenue Bridge, and for re-
       RIVERS   AND HARBORS-JACKSONVILLE,        FLA., DISTRICT     543
moval of snags, wrecks, and piling thence to the Florida Avenue
Bridge, at an estimated first cost of $60,000 with annual maintenance
of $1,000, in addition to that now required, subject to certain condi-
tions of local cooperation (H. Doc. No. 119, 77th Coig., 1st sess.).
   Under date of December 5, 1940, the Chief of Engineers recom-
mended modification of the existing project so as to provide for a chan-
nel 25 feet deep and 150 feet wide from the ship channel in Hillsboro
Bay to and including a turning basin in the Alafia River, 600 feet wide
and 1,025 feet long, at an estimated cost of $189,000 for new work and
$5,000 annually for maintenance, in addition to the amount now
required, subject to certain conditions of local cooperation (S. Doc.
No. 16, 77th Cong., 1st sess.).
   Under date of March 4, 1944, the Chief of Engineers recommended
modification of the existing project to provide for the widening of
Sparkman Channel from 300 to 400 feet, Ybor Channel from 400 to 500
feet, widening of the bend between Sparkman and Garrison Channels
by cutting back the northeast corner of Seddon Island by 250 feet
and cutting off the resulting corners, and reduction from 300 to 150
feet of the widening between Seddon and Garrison Channel authorized
under the existing project, all to a depth of 30 feet, at an estimated
first cost of $607,400 and $7,500 annually for maintenance in addition
to that now required, subject to certain conditions of local cooperation
(S. Doc. No. 183, 78th Cong., 2d sess.).
   Local cooperation.-The River and Harbor Act approved June 20,
1938, in authorizing certain channel improvements in upper Tampa
Harbor, imposed the condition that local interests furnish, free of
cost to the United States, necessary rights-of-way and suitable spoil-
disposal areas for new work and for subsequent maintenance as re-
quired, and move and reconstruct all bulkheads, wharves, buildings,
roads, railroad tracks, and all other structures as may be necessary.
Temporary spoil-disposal areas were furnished in the early spring of
1940, but have since expired. The requirements imposed by the same
river and harbor act in authorizing the construction of a breakwater at
the Peter O. Knight Municipal Airport have been fully complied with.
   All prior requirements have been complied with except that the
conditions imposed by the River and Harbor Act approved August 8,
1917, include the requirement that the city of Tampa provide a mu-
nicipal belt-line railway to serve the channel frontage on both sides
of Ybor estuary, and provide a sufficient number of paved streets
and highways to give proper access to all parts of the estuary. Paved
streets adequate for present needs have been provided, those along
the north and east sides of Ybor Channel having been financed in large
part with Work Projects Administration funds. The municipal belt-
line railroad has not been extended across the north end and along the
east side of Ybor Channel. Under date of February. 11, 1943, the
Secretary of War notified the mayor of the City of Tampa that the
completion of the belt-line railroad at Ybor Channel is not required
at the present time.
   Terminal facilities.-There are 51 piers and wharves at Tampa, in-
cluding 13 on Hillsboro River, and a like number at Port Tampa.
The municipal terminal consists of a slip 778 feet long, 250 feet wide,
and 29 to 30 feet deep. The city of Tampa also owns a shore wharf
544             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

located on Hillsboro River, and another on Garrison Channel.
Thirty-eight of the facilities, including the municipal slip, have rail-
way connections and all, excepting 4 located on Seddon Island, have
highway connections. The municipal terminals, 1 city wharf and 10
private terminals are open to the public.
   On the east shore of Hillsboro Bay there is a large phosphate plant
providing about 1,000 feet of berthing space with a privately dredged
channel 3 feet deep connecting with the Hillsboro Bay Channel of
the Tampa Harbor project. The facilities are considered adequate
for the existing commerce. (See Port Series No. 8, pt. 2, revised 1936,
Corps of Engineers.)
   Operations and results during fiscal year.-A general survey to de-
termine the condition of the improvement and routine surveys and in-
spections incidental to the supervision of the project cost $7,998.17
for maintenance. The expenditures were minus $2,559.92.
   Condition at end of fiscal year.-The existing project was about
98.6 percent completed. The Hillsboro River project was completed
in 1905. Egmont Relocation Channel to replace the old channel aline-
ment on Egmont Bar was completed in 1939. The breakwater of
dredged material at Peter O. Knight, Municipal Airport was com-
pleted in 1941, and the city of Tampa has formally assumed respon-
sibility for its care, preservation, and maintenance. Channels with
project dimensions have been completed from the entrance to and
including the several channels of upper Tampa Harbor, except in the
bend between Sparkman Channel and cut D, Hillsboro Bay Channel,
and in Ybor Channel, which is only 300 feet wide. Tampa Bay Chan-
nel cut A, was dredged 400 feet wide. The turning basin at the
entrance to Ybor Channel has been completed and that at the west
end of Garrison Channel (mouth of Hillsboro River), partially com-
pleted. The turning basin at Port Tampa has been extended to a total
length of 2,750 feet by a widening on the westerly side of the Port
Tampa Channel at its junction with the basin.
   The controlling mean-low-water depths, when last ascertained, were
as follows:

                                  Channel                                                    Depth      Width          ascened
                                                                                                                    ascertained

                                                                                             Feet        Feet
Egmont Relocation Channel ------------------------------                                        30. 8       300    January 1944.
Mullet Key cut . ---------------------------------------                                        30.3        400          Do.
Tampa Bay Channel:
   Cut A_ --------------------------------------------                                          29.2        350          Do.
     Cuts B to F       ---------------------------------------                                  30.0        225          Do.
Port Tampa Channel                               ......................                         30.0        275   Jan.-Feb.    1944.
Port Tampa turning basin ..--                                                                   30. 5       550   February 1944
Hillsboro Bay Channel .-      ----------                                    -----        -      28. 5       150        Do.
Upper Tampa Harbor:
     Seddon Channel-- -- --- --------......             ..                ...       ..          29.2        275          Do.
     Sparkman Channel ---     -------       -...--.....                             ..          28.5        150          Do.
     Garrison Channel------------------.......-----------------..        30.0                               150          Do.
     Ybor Channel---------............ ..........-----------------------------
                                                                         28.8                               150          Do
     Hillsboro River---------- ---------------------------..............  9.7                               100          Do.


  The work remaining to be done to complete the project is as follows:
Widening the bend at lower end of Sparkman Channel by 250 feet;
widening Ybor Channel 50 feet on each side to a total width of 400
feet; and enlarging the turning basin at the west end of Garrison
Channel by 300 feet in an easterly direction.
              RIVERS AND HARBORS-JACKSONVILLE,                                                     FLA., DISTRICT                        545

  The total costs and expenditures under the existing project have
been as follows:

                                                             New work            Maintenance                    Total           Expenditures

Regular funds ....----------------------                  $5, 942, 724. 66    $1,820, 304. 30         $7, 763, 028. 96           $7, 766, 509. 80
Public Works funds- ..... -     -- --                      1, 329, 300. 47- -      -_-     -           1, 329, 300. 47            1, 329, 300. 47
Emergency Relief funds .......  _..   .                    1,463,000. 00 --           -------          1, 463, 000. 00            1,463,000.00
      Total.....------------.--.--.                    -- 8, 735,025.13           1,820, 304.30       10, 555, 329.43            10, 558, 810.27


  Proposed operations.-The balance unexpended and accounts re-
ceivable June 30, 1944, $17,176.86, plus $115,500 allotted during July
1944, a total of $132,676.86, will be applied as follows:
Accounts payable June 30, 1944_-        ----  ____------                                                                           $108. 23
Maintenance:
    Dredging to restore project dimensions through-
      out the improvement, with U. S. hopper dredge
      San Pablo, about 4.6 months, Sept. 13, 1944, to
      Jan. 31, 1945          ----------                $125,000.00
      Miscellaneous                    surveys, inspections, and contin-
           gencies--------------------------------                                           --          7, 568. 63
                                                                                                                                132, 568. 63

           Total for all work_- __                           ----------                                   -___                  132, 676. 86
  The additional sum of $88,500 can be profitably expended during
the fiscal year 1946 for maintenance, as follows:
Dredging to remove shoaling in the channels of upper Tampa Harbor as
  required, with U. S. hopper dredge San Pablo, 3 months, July to
  September 1945      ------------------------------------------        $81,000
Miscellaneous surveys, inspections, and contingencies_ ----------------- 7, 500
           Total for all work_                    -          __---         -------------                                             88, 500
   No funds can be profitably expended for new work during the
fiscal year 1946, as the requirements of local cooperation affecting
the remaining work have not been complied with.
                                                 Cost and financial summary
Cost of new work to June 30, 1944-   -----------                                                                           $9, 588, 075. 59
Cost of maintenance to June 30, 1944--       --------                                                                       1, 837, 411. 54
       Total cost of permanent work to June 30, 1944_         11, 425, 487. 13
Plus accounts receivable June 30, 1944-----------------------       3, 589. 07
      Gross total costs to June 30, 1944 -------------------     11,429, 076. 20
Minus accounts payable June 30, 1944_-------                 ---         108. 23
      Net total expenditures--    _--------_                                                                               11, 428, 967. 97
Unexpended balance June 30, 1944-_ --------                                                        ------                       13, 587. 79
           Total amount appropriated to June 30, 1944                                      -----------                     11, 442, 555. 76

    Fiscal year ending June 30                        1940                1941              1942                    1943             1944

Cost of new work-_-_ ......
                         --                  .   $12, 633.03         $317,083.32           $1, 784. 80      .
Cost of maintenance ______.---                    91, 491.38              2, 885.03         7,655. 93           $129, 552. 71        $7, 998. 17

               ----------------
      Total cost_ _                              104,124.41           319, 968. 35          9,;440. 73           129, 552. 71         7, 998.17
Total expended ..            .............        95, 735. 56         321, 038.09          19, 359. 18           128, 886. 38       -2, 559. 92

Allotted......           ...............              2, 855. 92      126, 000. 00      140, 000. 00              68,300. 00       -75, 000. 00

          616634-45-pt. 1, vol. 1--35
546         REPORT OF CHIEF OF ENGINEERS, U.            S. ARMY,       1944

Balance unexpended July 1, 1943__--       ---------                         $86, 027. 87
Deductions on account of revocation of allotment_                            75, 000. 00

       Net amount to be accounted for_                                       11, 027. 87
Gross amount expended_ _________------$102,                  235. 59
                             ------------------
Less reimbursements collected__                         104, 795. 51
                                                                            -2, 559. 92
      Balance unexpended June 30, 1944                                       13, 587. 79
Outstanding liabilities June 30, 1944-------------           108. 23
Amount covered by uncompleted contracts....                  164. 00
                                                                   -   --       272. 23

      Balance available June 30, 1944 -----------------------                13, 315. 56
Accounts receivable June 30, 19441-     ------          __3,                     589. 07

     Unobligated balance available June 30, 1944------------                 16, 904. 63
Amount allotted in July 1944  --------------------------                    115, 500. 00
        Amount available for fiscal year 1945   ------------------          132, 404. 63

Amount (estimated) required to be appropriated for completion of
existing project 1__          ___---- _______---    -     __125,               500.00

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance I                                                  88, 500. 00
  'Exclusive of available funds.

                            14. WITHLACOOCHEE RIVER, FLA.

   Location,-This river rises in central part of the peninsula of
Florida and flows in a general northwesterly and westerly direction,
emptying into the Gulf of Mexico about 20 miles southeast of Cedar
Keys, Fla., and 95 miles north of the entrance to Tampa Bay. (See
U. S. Coast and Geodetic Survey Chart No. 1259.)
   Previous projects.-A project for the improvement of the entrance
was adopted by the River and Harbor Act of June 13, 1902. For
further details see page 1832 of the Annual Report for 1915, and page
523 of Annual Report for 1934.
   Existing project.-This provides for securing and maintaining a
channel 100 feet wide and 10 feet deep at mean low water from the
10-foot contour in the Gulf of Mexico to Port Inglis, just within the
river entrance, by dredging and rock excavation, and for removing
snags, overhanging trees, and loose rock, and cutting through shoals
in the upper river, with a view to making a draft of 2 feet available
for about half the year as far as Pembertons Ferry (Oroom), 85
miles above the mouth. The Second Deficiency Appropriation Act,
1944, approved June 28, 1944, authorized the use of appropriations
for rivers and harbors for the improvement, in the interest of na-
tional defense and subject to the approval of the Chief of Engineers,
of the channel between the mouth of the river and Inglis. This work
embraces the easing of five sharp bends. The lengths of the sections
included in the project are 4.1 miles from the Gulf to Port Inglis
and thence 85 miles to Pembertons Ferry (Croom). The mean tidal
range at the mouth is 2.8 feet and the spring range about 3.5 feet.
The effect of the tide is perceptible for about 11 miles above the mouth.
Strong southwesterly winds raise the water level at the mouth about
1 foo0t0 and strong northerly winds, which usually occur during the
winter, lower the water level about 11/2 feet. Freshets raise the water
           RIVERS AND HARBORS-JACKSONVILLE,                              FLA., DISTRICT             547

level in the upper river from 4 to 6 feet and at the mouth about 1
foot.
   The estimate of cost for new work, revised in 1944, is $410,000,
exclusive of amounts expended on previous projects, but including
$25,000 for the improvement of the channel between the mouth and
Inglis. The latest (1942) approved estimate for annual cost of
maintenance is $4,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Worfk authorized                                   Documents


Mar. 3,1881    For J~iproement       Hof river from mouth to Hays   Annual Report, 1880, pp. 1110-1119.
                 Ferry, 79 miles.,
Aug. 5,1886     ar etending impravement to Pembertons
               Fo                                                   Annual Report, 1885, pp. 1277-1278.2
                 erry, 6-milesabove Hays Ferry.
Mar. 2, :1907 Fer  a depth of 10 feat mean low water from the       H. Doc. No. 483, 59th Cong., 2d sess,0
                Grulf to Port Inglis.
June2S,1 4     oEr the use ofMappropriations for rivers and har-    Specified in act.
                  ohersfor the improvement of the channel
                between the mouth and Inglisa.


   1 Modified in oerdune with :recommendations in Annual Report for 1885. (See also Annual Report
for 1887, p. 1248.)
   2The latest publisheAd nap itheriver to ieatbertons Ferry is in H. Doc. No. 199, 55th Cong., 2d seses
S3 Contains .latestpublished zp of ithe entrance.
  4 Second Deficiency AppropriationAct, 1944.


    Terrinal faciliti&-These consist of one small timber dock at
Inglis with shore facilities for fuel-oil storage, and one dock at Yan-
keetown with shore facilities for gasoline storage; two small docks
for handling fish-one each at Yankeetown and Inglis; one small
dock at Panasoffkee open to public use; and privately owned landing
docks scattered along the river. The facilities are considered ample
for existing commerce.
   Operations and results during fiscal year.-Maintenance snagging
with U. S. pile driver No. 2 and hired labor, from a point about 11/2
miles above the mouth of the river to the turning basin of the steam
electric plant of the Florida Power Corporation at Inglis, which
was commenced June 29 of the previous fiscal year, was completed
October 29, 1943. There were removed 1,768 obstructions to naviga-
tion, consisting of logs, submerged snags, and overhanging trees and
debris, which were disposed of by burning. The cost was $14,580.76
for maintenance. The expenditures were $15,022.75.
   Condition at end of fiscal year.-The existing project as a whole
was about 70 percent completed. The project for the entrance was
about 85 percent completed. The channel from the 10-foot contour
in the Gulf to Port Inglis was completed in the fiscal year 1915 to a
depth of 10 feet at mean low water and a width of 85 feet. The re-
moval of snags, overhanging trees, sunken logs, loose rocks and
boulders, and some rock ledges from the upper river to enable light-,
draft boats to ascend the river to Croom, except at low stages, was
practically completed in 1892. Under permit granted by the Secre-
tary of War on April 16, 1904, a power dam and a lock 134 feet by 36
feet, now owned and operated by the Florida Power Corporation, were
548          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                 1944

built about 11.4 miles above the mouth of the river. The dam creates
a pool extending nearly to Dunnellon, 241/2 miles above the mouth.
The lock, which had been inoperative since the completion of the in-
stallation of the gates in 1916, except for about 7 months during 1926,
was restored to operating condition in January 1942. The river is
now fairly clear of obstructions. The controlling depth from the
Gulf to Port Inglis was 6.9 feet for a width of about 60 feet, with a
minimum depth of about 9 feet on the sailing range, in April 1942.
Above Port Inglis the controlling depths when last ascertained in
May 1940 were about as follows: From Port Inglis to Inglis, 6 feet;
thence to the Florida Power Corporation's dam, 4 feet; thence to
Stokes Ferry, 4 feet; thence to the head of navigation at Croom,
about 2 feet, which prevails during about half the year, with 1 foot
during low stages. The depths referred to are mean low water, Gulf
datum, from the entrance to the dam and to local low-water stage of
the river above that point. The work remaining to be done to complete
the project is the 15-foot widening of the entrance channel to Port
Inglis, and the improvement of the channel between the mouth and
Inglis which embraces the easing of five sharp bends. The costs and
expenditures under the existing project have been $285,085.29 for new
work and $89,985.98 for maintenance, a total of $375,071.27.
  Proposed operations.-The balance unexpended June 30, 1944,
$1,584.25, together with $25,000 allotted during July 1944, will be
applied to new work dredging, by contract, involving emergency re-
moval of rock and overburden to a depth of 10 feet at mean low watef',
to ease five sharp bends between the mouth of the river and Inglis,
about 7 miles, during the period September 15 to October 15, 1944.
   The sum of $12,000 can be profitably expended during the fiscal year
1946 for maintenance dredging in the entrance channel, by contract,
during December 1945. No funds can be profitably expended for new
work during the fiscal year 1946 for the reason that the commerce using
the entrance does not justify the cost of completing the 15-foot wid-
ening of this channel.
                                 Cost and financial summary
Cost of new work to June 30, 1944_                                                      $315, 085. 29
Cost of maintenance to June 30, 1944-------------------                                      89,   985985.
                                                                                                     98
         Total cost of permanent work to June 30, 1944-------                               405, 071. 27

Net total expenditures--------------------------------                                      405, 071. 27
Unexpended balance June 30, 1944---------------------                                         1, 584. 25
         Total amount appropriated to June 30, 1944            --------                     406, 655. 52


   Fiscal year ending June 30      1940           1941          1942            1943               1944


Cost of new work--
                         .
Cost of maintenance------------. $21,755.39       $879.02     $2, 749. 18   -    $451.40        $14, 580.76
Total expended.....     .
            ----------------      20, 085.22      2,375.60     2,868. 00           64. 17          15, 022.75
Allotted--                        13,000.00.---------------------------
               .--------------------                                            15,000.00I         -
            RIVERS AND HARBORS-JACKSONVILLE,                                          FLA.,     DISTRICT         549
Balance unexpended July 1, 1943 -----------------------------                                             $16, 607. 00
Gross amount expended_              --------_        $15, 736. 77
Less reimbursements collected-----------------------      714. 02
                                                                                                           15, 022. 75

     Balance unexpended June 30, 1944     -----------------                                                 1584. 25
                                                                                                            1,
Amount allotted in July 1944----------------------------                                                   25, 000. 00

           Amount available during fiscal year 1945                      ------------                      26, 584. 25
Amount (estimated) required to be appropriated for completion of
   existing project 1                    ---------------                                          _       100, 000. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946 for maintenance 1__                            ______-____                                     12, 000. 00
  1 Exclusive of available funds.


15. REMOVING THE WATER HYACINTH FROM NAVIGABLE WATERS IN
                  THE STATE OF FLORIDA

   Location..-The water hyacinth is found in the fresh-water streams
and lakes in various parts of the district.
   Ewisting project.-This provides for the destruction or removal of
the water hyacinth in the navigable waters of the State so far as they
constitute an obstruction to commerce, using any mechanical, chemical,
or other means not injurious to cattle. The use of log booms to close
sloughs and backwaters as an auxiliary means was contemplated. No
estimate of the final cost of the work has been made. The latest (1940)
approved estimate of annual cost of maintenance is $75,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                            Work authorized                                           Documents


Mar. 3,1899    For the construction and operation of a suitable             H. Doc. No. 91, 55th Cong., 3d sess.
                 vessel, and for the use of log booms as adjuncts            and Annual Report, 1899, pp. 1613-
                to the operation of the vessel, for the removal of            1623.
                water hyacinths in the naviagable waters of the
                State of Florida.
June 13,1902   For the extermination and removal of water hya-              Specified in act.
                cinths by any mechanical, chemical, or other
                 means.                                                         Do.
Mar. 3,1905    Prohibited the use of any chemical process in-                   Do.
                 jurious to cattle.




   Operations and results during fiscal year.-The Camp Rosa boom,
located about 9.7 miles below Palatka, was maintained throughout the
year. Floating booms, which can be opened for traffic on signal, were
maintained across the navigation passes at the Camp Rosa boom and
at the Black Creek bridge, when needed, from April 10, 1943, to the
close of the fiscal year. United States hyacinth destruction boats, op-
erating on the St. Johns River and tributaries from July to October
1943 and from April to the close of the fiscal year, destroyed about
4,115 acres of hyacinths. Fence-wire traps fastened to the piling of
bridges over the St. Johns River and tributaries, to aid in the control
of hyacinths, were repaired when destruction operations were not in
progress. The total cost of work on the St. Johns River system was
550      REPORT OF CHIEF OF ENGINEERS,                 U. S. ARMY,      1944

$33,624.10. Hyacinth destruction boats operating on the Caloosa-
hatchee River and Lake Okeechobee drainage areas destroyed inter-
mittently during July, August, October, and November 1943, about 19
acres of hyacinths in Caloosahatchee Canal and in Clewiston Channel,
at a cost of $260.55.
   The total cost for the year was $33,884.65 for maintenance. The
expenditures were $31,329.55.
   Condition at end of fiscal year.-The project is for maintenance.
The work accomplished prior to the fiscal year 1939 consisted princi-
pally of breaking up jams and drifting. Later operations have con-
sisted principally of the control of hyacinths by the construction of
temporary and permanent traps at strategic points, the shredding of
hyacinths, or their removal.
   At the close of the fiscal year all waterway channels were open to
navigation. The St. Johns River was virtually clear of hyacinths
from Jacksonville to the new Camp Rosa boom near Palatka, and
tributary creeks between Jacksonville and Camp Rosa boom were in
satisfactory condition.
   The total cost has been $804,236.14 for maintenance. The expendi-
tures have been $801,427.63.
   Proposed operations.-The balance unexpended June 30, 1944, $9,-
779.11, plus $32,500 allotted during July 1944, a total of $42,279.11, will
be applied as follows:
Accounts payable June 30, 1944 -------------------------------           $2, 808. 51
Maintenance:
    Maintenance of the Camp Rosa boom near Palatka,
      the operation of traps to aid in the control of hya-
      cinths, and the removal or destruction of water
      hyacinths in the St. Johns River and tributary
      streams, as required by hired labor, July 1, 1944, to
      June 30, 1945 __-             -          -    -       $35, 000. 00
    Removal or destruction of water hyacinths in the
      Caloosahatchee River and Lake Okeechobee drain-
      age areas system, as required, by hired labor, July
      1, 1944, to June 30, 1945 __-      _r_--        ..--    4, 470. 60
                                                                         39, 470. 60

         Total for all work_--        --------------                          42, 279. 11
  The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 for the control, removal, or destruction of water
hyacinths in the various navigable waterways in the district, as
required, by hired labor:
                            Cost and financial summary
Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944_-------                      ---       $804, 236. 14
      Total cost of permanent work to June 30, 1944-          -              804, 236. 14
Minus accounts payable June 30, 1944-------------------------                  2, 808. 51
      Net total expenditures   ---------------------                         801 427. 63
                                _-
Unexpended balance June 30, 1944--    --------                          -      9, 779. 11
       Total amount appropriated to June 30, 1944      --------              811, 206. 74
               RIVERS AND HARBORS-JACKSONVILLE,                                          FLA., DISTRICT                           551

    Fiscal year ending June 30                     1940            1941           1942                1943                     1944

Cost of new work ......
C6st of maintenance---------......        ---   $170,182.20      $57,467.69     $96,914.05          $75, 266.75               $33, 884.65
Total expended .....----------------             183, 273. 37     58, 330.40     95, 289.78          79,182.25                 31, 329. 55
Allotted        _-........----    .-.---.--      186, 400.00      66, 000.00     88, 500.00          40,200.00            -




Balance unexpended July 1, 1943- .---                        _----                                                    $41, 108. 66
Gross amount expended_------               ---      $33, 957. 82
Less reimbursements collected .--------------------   2, 628. 27
                                                                                                                       31, 329. 55
      Balance unexpended June 30, 1944 ---------------------                                                            9, 779. 11
Outstanding liabilities June 30, 1944_-------                                                                           2, 808. 51
     Balance available June 30, 1944--                                    --                  -____                     6, 970. 60
Amount allotted in July 1944_---------                                                         ----                    32, 500. 00
           Amount available during fiscal year 1945-----------------                                                   39, 470. 60
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1_    ___ __ __        _40,                                                                          000. 00
  1Exclusive of available funds.


     16. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                        (GENERAL)

  The cost of work during the year wis $85,941.08; the expenditures
were $66,434.51. The balance unexpended June 30, 1944, $14,945.11,
plus $65,000 allotted during July 1944, a total of $79,945.11, will be
applied as needed during the fiscal year 1945 to the payment of ex-
penses incurred under this heading. The additional sum of $80,000
can be profitably expended during the fiscal year 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                                   ---            $2, 080, 701. 76
      Total cost of permanent work to June 30, 1944----------                                                  2, 080, 701. 76
Minus accounts payable June 30, 1944_----          - __6,                                                              056. 72
      Net total expenditures---       -----------                                                              2, 074, 645. 04
Unexpended balance June 30, 1944_- _-         ----------                                                           14, 945. 11
           Total amount appropriated to June 30, 1944------------2, 089, 590. 15

    Fiscal year ending June 30                     1940            1941          1942                 1943                    1944
Cost of new work .-----------..
                     . . . . . ..               . . . . . ...    . . . . ..-
Cost of maintenance--...-.--.--. --             $196, 651.86    $195, 571.69 $189, 492. 24          $39, 164.64           $85,941.08
Total expended...    ----------------
                             ..                 185,986.82       206, 713. 55   169, 654.54          75, 603. 33              66, 434.51
Allotted-----------_             -----------     215, 000.00     165, 000.00    70, 000.00          194, 100.00          -38, 000.00

Balance unexpended July 1, 1943             -                                       -          -             -$119,       379. 62
Deductions on account of revocation of allotment                                                                      38, 000. 00
           Net amount to be accounted for---------                                                                    81, 379. 62
552             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

Gross amount expended_     ------                                             -     --         $77, 849. 93
Less reimbursements collected__                                   -------                       11, 415. 42
                                                                                                                              $66, 434. 51
      Balance unexpended June 30, 1944-                                                                                        14, 945. 11
Outstanding liabilities June 30, 1944 --------------                                             $6, 056.72
Amount covered by uncompleted contracts ....                                                         868.&87
                                                                                                                                6, 925. 59
     Balance available June 30, 1944_-              - ----                                               ----                   8, 019. 52
Amount allotted in July 1944------------------------65,                                                                            000. 00
Amount available for fiscal year 1945-------------------------                                                                73, 019. 52

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1____                                                                                                80, 000. 00
   1 Exclusive of available funds.

17. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                       SUBMITTED

                                                                    For last full        Cost and expenditures to               Estimated
                                                                     report see                June 30, 1944                    amount re-
                      Name of project                                  Annual                                                   required to
                                                                       Report                                                   required to
                                                                       for--             New work         Maintenance            complete


1. St. Johns River, Fla., Jacksonville to Pa-
      latka 1. .............                                 ..            1933          $205, 698. 47      $116,328.46                 $13, 300
2. St. Johns River, Fla., Palatka to Lake Har-
      ney 12                                                1              1942        210, 059.92         268, 095.89                      10, 000
3. Lake Crescent and Dunns Creek,            4     Fla.- 3... -           1931         10, 276. 25           5, 723. 75                    53, 800
4. Atlantic-Gulf Ship Canal, Fla. ........ ...                            1939     55,099, 152. 55
5. Courtenay Channel, Fla.i-.------...-.....
                                    1                                      1940         22, 845. 70--------.             ----          (6)
6. Eau Gallie Harbor, Fla. .....................                          1940          9, 626.78-------.----.                      - (8)
7. Melbourne Harbor, 7Fla.1_ _ ________-______1939                                     17, 696. 27-     .---.-----                   (6)
8. St. Lucie Inlet, Fla. ----------                                   -- 1932          26, 688. 51---------..                        1.410, 000
9. Palm Beach, Fla., side channel and basin 8___                          1941     ......-...-......                            -    o.114, 000
10. Miami River, Fla.' 10                                                  1935        646,915. 17            3,000.00                 (6)
11. Intracoastal Waterway from Miami to Florida
      Bay, Fla.' 11____          ___ - _________1939  --                                  201, 362.73                282.12           (6)
12. Key West Harbor, Fla.' _                             --------          1941      1, 040, 408. 75            238, 742.96             956, 300
13. Channel from Naples, Fla., to Big Marco Pass,
      Fla.       ---------------------------------
                            1                                              1940            37, 524. 85         2, 724. 76             (6)
14. Orange River, Fla.'                   ______               __
                                                                __         1937             2,000.00           8, 574. 27             (6)
15. Kissimmee River, Fla.' ---------------------1
                                                                           1931            23,479. 18         25, 202. 14             (6)
16. Caseys Pass (Venice Inlet), Fla. 13-.... -                             1941
                                                                        -...              153, 970. 19       187, 141.02              (6)
17. Sarasota Bay, Fla.' 13-    1        -      -1940                                      249, 632. 22       134, 165.66                    54,000
18. Manatee River, Fla.'-.             --------
                                          1                                1938           123, 349. 56       101, 214. 04                   14, 400
19. St. Petersburg Harbor, Fla.'                ---                ---     1943           221, 578. 31      1469, 696. 79             (6)
20. Channel from Clearwater Harbor through                 1
      Boca Ciega Bay to       1 Tampa Bay, Fla.'13....                     1940           105;.877.01         111, 963.72             (0)
21. Anclote River, Fla. 15_                          __
                                                     -________    ..       1939           178, 427. 04          75, 305. 37           (6)
22. Homosassa River, Fla.'   1 -- -----------------------
                                       -- -- -- -- -- -- -- -- -           1937            S16
                                                                                            3,-998. 64     ...-..                 -(6)
23. Crystal River, Fla.                                                    1941            25, 000. 00          19, 993. 12           (0)
24. Cedar Keys Harbor, Fla.'__                               _..           1932           147, 020.98           30, 000. 00               3, 500
25. Suwannee River, Fla.1 17-                _             _1940                           76, 417. 96          37, 394. 06             200, 000
26. Steinhatchee River, Fla.1--                 .- -....                   1940           135, 053. 37              395. 28           (6)

  1 Chamnnels adequate for commerce.
  2 Modification of existing project recommended Dec. 11, 1943, in H. Doc. No. 445, 78th Cong., 2d sess.
  ' Awaiting local cooperation.
  4 Project not formally adopted by Congress. Modified project is recommended in H. Doc. No. 194, 75th
Cong., 1st sess.
  6 Emergency Relief funds.
  6 Completed.
  7 Modification of existing project recommended July 1, 1941, in H. Doc. No. 391, 77th Cong., 1st sess.
   8No funds available.
   9In addition, $114,000 to be contributed by local interests.
  10Modification of existing project was recommended by the Chief of Engineers Mar. 19, 1942
  11 Extension of waterway to Key West, Fla., was recommended by the Chief of Engineers in a report
transmitted to Congress June 9, 1943. (No printed report.)
  12 No commerce reported.
   18Included in project for a section of Intracoastal Waterway, recommended June 14, 1939, in R. Dool
No. 371, 76th Cong., 1st sess.
  14 In addition, the costs and expenditures from contributed funds have been $6,353.43.
  15Modification of existing project recommended Mar. 15, 1939, in H. Doc. No. 243, 76th Cong., 1st ses.
  16 In addition, $1,000 expended from contributed funds.
  17 Curtailment of existing project recommended in H. Doc. No. 467, 69th Cong., 1st sess;
           RIVERS AND HARBORS-JACKSONVILLE,                                         FLA., DI TRICT                 553
        18. PLANT ALLOTMENT, JACKSONVILLE, FLA., DISTRICT

                                     Cost and financial summary
Undistributed costs June 30, 1944_--------                                              ---             $811, 937. 48

Net total cost to June 30, 1944-----------------------------                                             811, 937. -48
Plus accounts receivable June 30, 1944_                                                                  101, 791. 81

      Gross total costs to June 30, 1944---------------------                                            913, 729. 29
Minus accounts payable June 30, 1944 .-----------------------                                            205, 267. 24

      Net total expenditures_ _ ---------                                                               708, 462. 05
Unexpended balance June 30, 1944_                                                                    -- 150, 851. 97

         Total amount appropriated to June 30, 1944_---                                           --     557, 610. 08

  Fiscal year ending June 30             1940            1941                1942             1943             1944


Total expended---------------
             .....                   $177, 034. 59    $260, 990. 69   $347, 389. 12 -$740, 775. 32         -$479, 948. 73
              _......
Allotted--------_                     143, 988. 32     111, 765. 25       -79, 228.54    -459, 000. 00      -453, 909.38



Balance unexpended July 1, 1943------------------------                                              -$176, 891. 32
Deductions on account of revocation of allotment                                                        453, 909. 38

       Net amount to be accounted for_-      ---------                                                   630, 800. 70
Gross amount expended_------              --        $3, 998, 948. 19
Less:
     Reimbursements collected   $4, 011, 465. 53
     Receipts from sales       ---------
                                    467, 431. 39
                                                      4, 478, 896. 92
                                                                                                       - 479, 948. 73

      Balance unexpended June 30, 1944--------------------150,851. 97
Outstanding liabilities June 30, 1944                -----------
                                               205, 267. 24
Amount covered by uncompleted contracts        266, 631. 86
                                                            471, 899. 10

      Balance available June 30, 1944_-                           -----                                -- 622, 751. 07
Accounts receivable June 30, 1944 _--                                                         -           101, 791. 81
     Unobligated balance available June 30, 1944 -------------520, 959. 26
Amount allotted during July 1944_ __------------550,               000. 00

        Amount available for fiscal year 1945_------------------                                          29, 040. 74

Status of all investigations for navigation called for by River and Harbor Acts and
                                 committee resolutions

                                                            Date trans-Recommenda-
          Locality               Authorization act           mitted to     Document No.                  Recommenda
                                                             Congress                                        tion

Anclote River to St. Marks     Commerce Commit- ...............................
Fla., Intracoastal Water-      tee resolution, Feb.
way,    and     connection     6, 1940.
across Florida with St.
Johns River.
Atlantic Ocean to Gulf of      Commerce Commit-              _.................................
Mexico, waterway across         tee resolution, June
Florida, via the St. Lucie      17, 1942.
River and Canal, Lake
Okeechobee and Caloosa-
hatchee Canal and River
 (war emergency).
Caloosahatchee River, Fla.,    Rivers and Harbors .
from Fort Myers to Gulf        Committee resolu-
of Mexico.                     tion, Apr. 30, 1935.
554         REPORT OF OHIEF OF ENGINEERS,                            U.     S.   ARMY,        1944

Status of all investigations for navigation called for by river and harbor acts and
                          committee resolutions-Continued

                                                         Date trans-I
          Locality               Authorization act        mitted to          Document No.          Recommenda-
                                                          Congress

Caloosahatchee River and       Rivers and Harbors
Lake Okeechobee drain-          Committee resolu-
age areas, Florida, modify      tion, Jan. 24, 1939.
existing project (final re-
port).
Caloosahatchee River and
Lake Okeechobee drain-
                               Rivers and Harbors
                                 Committee resolu-
                                                         Oct. 15,1943     1(Restricted)- .....     Favorable,
age areas, Florida, con-        tion, Feb. 20, 1940.
struction of side channels.
    Do..-- - - - - - .-        Rivers and Harbors                           __do-.....__..            Do.
                                 Committee resolu-
                                 tion, Oct. 5, 1940.
Crescent Lake, Fla., to River and Harbor
  Flagler Beach, Fla., water-    Act, Aug. 26, 1937.
  way via Haw Creek to
  Bunnell, thence via land
  cut.
DeLeon Springs to St. Johns Rivers and Harbors
  River, Fla, waterway.          Committee resolu-
                                 tion, Apr. 13, 1939.
Eau Gallie Inlet, Fla_,_ ... Rivers and Harbors            --
                                                           --------
                                 Committee resolu-
                                 tion, Sept. 17, 1941.
Fort Pierce Harbor, Fla., Commerce Commit-                                 --------------------
  reimburse local interests      tee resolution, Mar.
  for dredging prior to Fed-     1, 1944.                                  --------------------
  eral project.
Hollywood Harbor (Port Commerce Commit-
  Everglades), Fla., reim-       tee resolution, Mar.
  burse localinterests    for 1, 1944.
  dredging prior to Federal
  project.
Hollywood Harbor (Port Commerce Commit-
  Everglades), Fla., reim-       tee resolution, Feb.
  bursement for dredging         14, 1938.
  and jetty work.
Hollywood Harbor (Port Rivers and Harbors
  Everglades), Fla.               Committee resolu-
                                 tion, Jan. 13, 1944.
Jupiter Inlet, Fla........     Commerce Commit-
                                 tee resolution, Nov.
                                 8, 1943.
Lake Worth Inlet, Fla.._   --  Rivers and Harbors        Apr.   1,1944     H.   530,    78th           Do.
                                 Committee resolu-                           Cong., 2d sess.
                                 tion, Apr. 20, 1937.
Miami Harbor, Fla......        Commerce Commit-          Oct. 30, 1943      (Restricted) - -_ -       Do.
                                 tee resolution, Aug.
                                 6, 1941.
     Do...... ..   . . .   ... Commerce Commit-
                                 tee resolution, Aug.
                                 18, 1944.                                                   ..-
                                                                                          .(Restricted)
Pahokee, Fla., on Lake River and Harbor                  Oct. 15, 1943      (Restricted) .......   Unfavorable,
  Okeechobee, Yacht basin.       Acts, Aug. 26, 1937,
                                 and June 20, 1938.
Pirates Cove Channel in Commerce Commit-
  SacarmaBay,PiratesCove         tee resolution, May
  and Johnsons Pass, Fla.        27, 1936.
Ponce de Leon Inlet, Fla ...-Rivers and Harbors
                                 Committee resolu-
                                 tion, Mar. 25, 1938.
Punta Rasa to-Fort Pierce Rivers and Harbors
  and Stuart, Fla.,    water-    Committee resolu-
  way of 12-foot depth and       tion, Oct. 13, 1943.
  suitable width.
St. Augustine Harbor, Fla-- Rivers and Harbors
                                 Committee resolu-
                                 tion, June 10, 1941.
St. Johns River to Kissim- River and Harbor
  mee River, Fla., and           Act, Aug. 30, 1935.
  thence to Okeechobee-
  Cross-Florida Canal.
St. Johns River to Indian Rivers and Harbors
  River, Fla., channel from      Committee resolu-
  Sanford to near Titus-         tion, Jan. 27, 1937.
  ville.
St. Johns River, Fla., Jack- Commerce Commit-            June   5, 1944     S. 230, 78th Cong.,    Favorable.
  sonville to the ocean.         tee resolution, Oct.                         2d sess.
                                 19, 1943.
                     FLOOD CONTROL---JACKSONVILLE,                                            FLA., DISTRICT                        555

Status of all investigations for navigation called for by river and harbor acts and
                          committee resolutions-Continued

                                                                          Date  trans-
             Locality                  ,     Authorization aet             mitted to             Document No.              Recomend-
                                                                           Congress                                            tion

St. Johns River, Fla., Jack-               Commerce Commit-_ ...............
  sonville to the ocean,                    tee resolution, Oct.
  straighten channel      at                19, 1943.
  Dames Point, Browns
  Creek, and St. Johns
  Bluff.
St. Johns River, Fla., 12                  Commerce Commit-..................
  foot channel from Palatka                 tee resolution, Aug.
  to Sanford, and from the                  25, 1944.
  side channel to Enter-
  prise, Fla.
St. Johns River, Fla., San-             Rivers and Harbors Feb. 14,1944                       H. 445,78th Cong.,           Favorable.
  ford to Lake Harney.                    Committee resolu-                                    2d sess.
                                          tion, May 20, 1941.
Sebastian Inlet, Fla- ..-...            Rivers and Harbors -.
                                          Committee resolu-
                                          tion, Aug. 8, 1941.
Suwannee River, Fla., and               Sec. 1 of River and-
  Ga., for navigation, flood              Harbor Act, Jan. 21,
  control, power, and irriga-             1927.
  tion (308 report).
Tampa Harbor, Fla-........                 Commerce Commit- Apr. 4,1944 S. 183, 78th Cong.,                                   Do.
                                             tee resolution, Nov.            2d sess.
                                             14, 1939.
Withlacoochee River, Fla.,                 Sec. 1 of River and------- --------------------
for navigation, flood con-                  Harbor Act, Jan. 21,
trol, power,and irrigation                  1927.
 (308 report).
Withlacoochee River, Fla.-                 Rivers and Harbors           .------------------
                                             Committee resolu-
                                             tion, May 20, 1942.


19. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES FOR
                                                     FLOOD CONTROL

  The cost of work during the year was $15,730.66; the expenditures
were $15,950.21. The balance unexpended and accounts receivable
June 30, 1944, $2,999.34, plus $17,105 allotted during July 1944, a total
of $20,104.34, will be applied during the fiscal year 1945 to the pay-
xnent of expenses incurred under this heading. The additional sum
of $25,000 can be profitably expended during the fiscal year 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944                  ...
Cost of maintenance to June 30, 1944 -----------------------                                                          $156, 530. 66
            Total cost of permanent work to June 30, 1944------------                                                      156, 530. 66
Plus accounts receivable June 30, 1944_                                   --------                            ---               219. 55
            Gross total costs to June 30, 1944-                               -    --------                                156, 750. 21
Net total expenditures_ -    -  --------------                                                                             156, 750. 21
Unexpended balance June 30, 1944_--          --------                                          -------                       2, 779. 79

            Total amount appropriated to June 30, 1944--------                                                             159, 530. 00

    Fiscal year ending June 30                      1940               1941               1942                1943              1944

Cost of new work----------------
                  ..............       ......---------...........---------------------------------------................
Cost of maintenance------------.... $10,984.33             $18,609.15              $69, 720.58          $39, 320. 27           $15,730.66
Total expended.................                   11, 513. 21         17, 709,44         63,249.06          46,691. 50           15, 950. 21
Allotted.....          .--------...---14, 150.00                      99,600. 00          4,500.00          36, 280. 00---.-...-.-.
556         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                   1944

Balance unexpended July 1, 1943__
                                ----------------------------                                                                   $18, 730. 00
Gross amount expended_ _                              -      _                                            $15, 966. 71
Less reimbursements collected_      -16.                                                                            50
                                                                                                                                   15, 950. 21
      Balance unexpended June 30, 1944----                                                        -             _--__    -          2, 779. 79
Accounts receivable June 30, 1944_ ------                                                 ---          -----------                     219. 55
      Unobligated balance available June 30, 1944                                                ----------------                  2, 999. 34
Amount allotted July 3, 1944, from War Department Civil Appro-
priation Act approved May 23, 1941                                                                                                17, 105. 00
      Amount available for fiscal year 1945--------------------20,                                                                        104. 34
Amount that can be profitably expended in'fiscal year ending June
   30, 1946 for maintenance 1-  -      -  ____-
                                              --                                                                             -__   25, 000. 00
I Exclusive of available funds
         20. OTHER FLOOD-CONTROL PROJECTS FOR WHICH                                                                                NO
                     ESTIMATES ARE SUBMITTED
                                                                          For last              Cost and expenditures to           Estimated
                                                                        full report                  June 30. 1944                   amount
                 Name of project                                        see Annual                                                 required to
                                                                          Rfort             New work           Maintenance          complete

1. Snagging and clearing under authority of sec. 2                             1943             $12,057.21--. .....                Completed.
  of the Flood Control Act approved Aug. 28, 1937,
  as amended.

Status of all investigations for flood control called for by flood control acts and
                                committee resolutions
                                                                                  Date trans-Recommenda-
           Locality                  Authorization act                             mitted to     Document No.                         tiRecommenda-
                                                                                    Congress                                          t

Broward County, Fla., In-        Flood Control Act,                             Mar. 15,1944          --------------------     Unfavorable.
tracoastal Waterway               Junie 22, 1936.
throughout.
   Do _-- - - - - - - - -        Flood Control Act, .....   do .....
                                                                   - --------------                                                  Do.
                                   June 26, 1936.
Caloosahatchee River and         Rivers and Harbors ..............
   Lake Okeechobee drain-          Committee resolu-
   age areas, Florida, protec-     tion, May 29, 1940.
  tion of Kreamer, Ritta,
   and Torry Islands in
   Lake Okeechobee.
Estero River, Imperial           Flood Control Act,
   River, Corkscrew River          Aug. 28, 1937.
   (Horse Creek), Gordon
  River, Rock Creek, Hen-
  dry Creek, Mulock Creek,
  and Six Mile Cypress
   Slough, Fla.
Indian River and tributar-
   ies, Florida.
                                 Flood Control Act,
                                   Aug. 18, 1941.                            I-----------------
Kissimmee River and its          ---------------
                                       do .
   tributaries, Florida.
Kissimmee River, Fla., in-       Flood Control Act,
   cluding regulation and          Aug. 11, 1939.
   stabilization of water
  levels.
Kissimmee River Valley           Flood         Control Act,
   and tributaries, Florida.       Aug.        28, 1937.
St. Johns River (upper)
   and Marsh, and tribu-
                                 Flood
                                   Aug.
                                               Control Act,
                                               18, 1941.
                                                                              -----------I
   taries, Florida.
St. Lucie River, North           --..do--
   Fork, and tributaries,
   Florida.
Suwannee River, Fla., from       Flood Control Act,
   Florida-Georgia State line      Apr. 10, 1936.
  to Gulf of Mexico.
Suwannee River, Fla. and         Sec. 1 of River and
   Ga., for navigation, flood      Harbor Act, Jan. 21,
  control, power, and irriga-      1927.
  tion (308 report).
Withlacoochee River, Fla.,        ...----do .........-----------......-------------....                     --------------
                                                                                                           1!
  for navigation, flood con-
  trol, power, and irriga-
   tion (308 report).
Withlacoochee River, Fla.._      Flood Control Act, .........                                         --------------------
                                  June 22, 1936.
                             -
            RIVERS AND      HARBORS-MOBILE,             ALA.,    DISTRICT            557
  IMPROVEMENT OF RIVERS AND HARBORS IN THE
            MOBILE, ALA., DISTRICT
  This district comprises a small portion of southeastern Tennessee,
western Georgia, western Florida, all of Alabama south of the Ten-
nessee River Basin, eastern Mississippi, and a small portion of south-
eastern Louisiana embraced in the drainage basins tributary to the
Gulf of Mexico, west of the Aucilla River Basin, to and including the
Pearl River Basin. It includes the sections of the Intracoastal Water-
way from St. Marks River, Fla., to Lake Borgne Light No. 41, La.
  District engineer: Lt. Col. H. I. Collins, Corps of Engineers.
   Division engineer: Brig. Gen. J. S. Bragdon, United States Army,
to June 1, 1944, and Brig. Gen. R. F. Fowler, United States Army,
since that date.
                                     IMPROVEMENTS

               Navigation                            Navigation-Continued
                                       Page                                          Page
1. Gulf Intracoastal Waterway
       between Apalachee Bay,
                                            20.
                                            21.
                                                  Bayou La Batre, Ala_
                                                  Pascagoula Harbor, Miss.
                                                                             - ---   605
                                                                                     606
       Fla., and the Mexican                22.   Biloxi Harbor, Miss ....           609
       border (Mobile district) _       557 23.   Gulfport Harbor and Ship
2. St. Marks River, Fla ...            563         Island Pass, Miss .....          611
3. Carrabelle Bar and Harbor,              24.   Wolf and Jordan Rivers,
       Fla------------------_           564         Miss-              ---           613
4. Apalachicola Bay, Fla ..            566 25. Pearl River, Miss. and La_.          614
5. Apalachicola River, Fla., the           26. Examinations, surveys, and
       Cut-off, Lee Slough, and                   contingencies (general)     ---    615
       Lower Chipola River -....        567 27. Other navigation projects for
6. Flint River, Ga__                   570       which no estimates are
7. Chattahoochee River, Ga.                        submitted_                       616
       and Ala                         572 28. Plant allotment--                     617
8. St. Josephs Bay, Fla ...           574                Flood control
9. St. Andrews Bay, Fla ...           576
10. La Grange Bayou, Fla ..            578 29. Allatoona Reservoir, Coosa
11. East Pass Channel from the                  . River Basin, Ga                    618
       Gulf of Mexico into Choc-           30. Prattville, Autauga Creek,
       tawhatchee Bay, Fla   ---       580        Ala--       -                      620
12. Pensacola Harbor, Fla ...          581 31. Snagging and clearing under
13. Blackwater River, Fla ...          583        authority of section 2 of
14. Mobile Harbor, Ala -       .-      584        the Flood Control Act ap-
15. Removing the water hya-                       proved August 28, 1937, as
       cinths, Mobile River, Ala.,                amended_                           623
      tributaries                      588 32. Preliminary      examinations,
16. Chickasaw Creek Ala-               590        surveys, and contingencies
17. Alabama River, Ala_                592        for flood control  ----
                                       594 33. Other flood-control projects
                                                                                     623
18. Coosa River, Ga. and Ala__
19. Black Warrior, Warrior and                    for which no estimates are
      Tombigbee Rivers, Ala-           599        submitted_-         _    _.        624

1. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FLA.,
         AND THE MEXICAN BORDER (MOBILE DISTRICT)

  Location.-This section of the Gulf Intracoastal Waterway extends
in a general westwardly direction from Apalachee Bay through Ocklo-
ckonee Bay, Ocklockonee, Crooked, and Carrabelle Rivers, and St.
George Sound to Apalachicola Bay; thence through Apalachicola
River, Jackson River, Lake Wimico, Searcy Creek, a land cut, and
Wetappo Creek to St. Andrews Bay, Fla.; thence through a land cut
to Choctawhatchee Bay, Fla.; thence through Santa Rosa Sound to
Pensacola Bay, Fla.; thence through Big Lagoon and Old River, Fla.,
558             REPORT OF CHIEF OF ENGINEERS,                       U.     S. ARMY,         1944

Perdido Bay, Fla., and Alabama, Bay La Lanche, Wolfe Bay, Portage
Creek, Oyster Bay, and Bon Secour Bay, Ala., to Mobile Bay, Ala.;
thence through Mississippi Sound, Miss., and Lake Borgne, La., to
the Rigolets.
   Previous projects.-Adopted by the River and Harbor Acts ap-
proved May 23, 1828, and July 25, 1912, for the section between Mobile
Bay and Mississippi Sound. For further details see page 906', Annual
Report for 1930.
   Enoisting project.-This provides for a waterway 12 feet deep and 125
feet wide at mean low water, except in the section between Mobile Bay,
Ala., and the Rigolets, La., where the width is to be 150 feet, from
the vicinity of Apalathee Bay, Fla., to the Rigolets, La., and for con-
ditional acquisition of the Gulf County Canal, Fla., connecting
St. Josephs Bay with the Intracoastal Waterway, and its right-of-way,
free of cost to the United States, and enlargement of the canal to a
depth of 9 feet and a width of 100 feet.
   The estimated cost of new work, revised in 1943, is $6,456,000. The
latest (1943) approved estimate for annual cost of maintenance is
$101,400.
   The existing project was authorized by the following river and
harbor acts:

     Acts                       Work authorized                                      Documents


                  APALACHICOLA BAY TO ST. MARKS RIVER, FLA.

                                                                                                                1
Aug. 26,1937     A channel 9 feet deep and 100 feet wide at mean    H. Doc. No. 291, 75th Cong., 1st sess.
                  low water from Apalachicola Bay, Fla., via
                  St. George Sound, Carrabelle, Crooked, and
                  Ochlockonee Rivers and Ochlockonee and
                  Apalachee Bays to St. Marks River, Fla.

                 APALACHICOLA RIVER TO ST. ANDREWS BAY, FLA.


June 25,1910     A channel 5 feet deep at mean low water and 65     H. Doc. No. 670, 61st Cong., 2d sess.
                  feet wide at the bottom.
E. R. A. Act,    A channel 9 feet deep at mean low water and 100    Rivers and Harbors Committee Doc.
  May28,1935      feet wide at the bottom.                               No. 52, 72d Cong., 2d sess.'
  and River
  and Harbor
  Act, Aug.
  30, 1935.
                   CHOCTAWHATCHEE BAY TO WEST BAY, FLA.

                                                                                                            1
Aug. 30, 1935    A channel 9 feet deep at mean low water and 100    H. Doc. No. 259, 72d Cong., 1st sess.
                   feet wide at the bottom.

                 CHOCTAWHATCHEE    BAY TO PENSACOLA BAY, FLA.


June 25,1910     A channel 6 feet deep at mean low water, with no   H. Doc. No. 565, 61st Cong., 2d sess.
                  reference to width.
Aug. 30, 1935    A channel 9 feet deep at mean low water and 100 'Rivers and Harbors Committee Doc.
                  feet wide at the bottom.                               No. 42, 73d Cong., 2d sess.'
  aContain the   latest published maps.
                RIVERS AND           HARBORS-MOBILE,                  ALA.,     DISTRICT                 559

    Acts                        Work authorized                                       Documents


                  PENSACOLA BAY, FLA., TO MOBILE BAY, ALA.

July   3,1930   A channel 9 feet deep at mean low water and 100       Ii. Doc. No. 42, 71st Cong., 1st sess.
                  feet wide at the bottom.

                   MOBILE BAY, ALA., TO NEW ORLEANS, LA.


July   3,1930   A channel 300 feet wide and 10 feet deep from the     Rivers and Harbors Committee Doe.
                  10-foot contour in Mobile Bay to the 10-foot con-     No. 4, 71st Cong., 1st sess.'
                  tour in Mississippi Sound.
    Do...._..   A channel 100 feet wide and 9 feet deep from Lake     H. Doc. No. 341, 71st Cong., 2d sess.
                  Pontchartrain to Mississippi Sound.

                 APALACHEE BAY, FLA., TO NEW ORLEANS, LA.


July 23,1942    A channel 12 feet deep and 125 feet wide at mean      Public Law 675, 77th Cong., and report
                  low water, except in the section between Mo-          of the Chief of Engineers, Apr. 27,
                  bile, Ala., and New Orleans, La., where the           1942. (Report not printed.)
                  width is to be 150 feet.
June 17, 1943   Conditional acquisition of Gulf County Canal,         H. Doc. No. 257, 76th Cong., 1st sess.,
                  Fla., and enlargement of the canal to 9 feet          and Public Law 75, 78th Cong.,
                  depth and 100 feet width.                             1st sess.


  1 Contain the latcst published maps.

   Recommended modifications of project.-Under date of July 12,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for the construction by the United States
of a movable span in the Georgia, Florida & Alabama Railroad bridge
crossing the Ochlockonee River near McIntyre, Fla., at an estimated
first cost of $32,500; subject to certain conditions of local cooperation
(H. Doc. No. 442, 76th Cong., 1st sess.).
   Local cooperation.-The requirements of local cooperation for this
project have been fully complied with except for the section from
Apalachee Bay to Carrabelle, Fla., and the Gulf County Canal.
   The requirements of local cooperation for the section from Apala-
chee Bay to Carrabelle, Fla., provide that local interests undertake
all necessary modifications to bridges over the waterway, furnish free
of cost to the United States necessary rights-of-way and suitable spoil-
disposal areas for new work and for subsequent maintenance as re-
quired, and release the United States from all claims for damages
incidental to the work of improvement.
   For information concerning the conditions affecting the Gulf County
Canal project, see House Document No. 257, Seventy-sixth Congress,
first session, and act approved June 17, 1943 (Public Law 75, 78th
Cong., 1st sess.).
   Terminal facilities.-Terminal facilities available for public use
are located at Carrabelle, Apalachicola, Panama City, and Pensacola,
Fla.; Mobile and Bayou LaBatre, Ala.; Pascagoula, Biloxi, Gulfport,
Pass Christian, and Bay St. Louis, Miss. These facilities are consid-
ered adequate for existing commerce.
   Operations and results during fiscal year.-The following work was
accomplished in various sections during the fiscal year:
 560              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                            1944

                                                                  NEW WORK

                               Plant-                                                   Date                   Quantity              Cost


                        RENTED PLANT

Pipe-line dredge:                                                                                             Cubic yards
                   - -
    Ventnor-.............................                                 July   1 to Aug. 19, 1943 --            735, 737          $97, 918. 41
    Manatee --------------------------- -                          - July        1 to Aug. 31, 1943             1 438,114            96,047.95
    Margate                   ...          ...
                                           -_          ...     ...   -... July   1 to Aug. 30, 1943 ...           512,673            88, 276.33
    Duplex - --- ------------- .- . July                                         1 to Aug. 3, 1943 __             552, 414           84, 679. 95
    Savannah_.................                                            July   1 to Aug. 20, 1943 -.            174, 302           36, 464. 71
    Hendry No. £-                                          __        _ July      1 to Sept. 24, 1943 -.         1 739, 695          179, 047.19
   Hendry No. 4-                          ---------------------          July    1 to Aug. 22, 1943 ..            278, 730           48,098.92
   Hendry No. 5_ .-----------                                  _-        July    1 to Aug. 31, 1943 --_           805,866           136, 940.52
   Pearl     ---------------                    --------------- -- July          1 to Aug. 26, 1943 ____          546, 707           54,972.16
   Diesel ----------------- ----------------                              Aug.   19 to 30, 1943 -...               58,945            23,152.10
    Tampa... .                             . ...
                             . ..------------                             July   1 to Aug. 30, 1943 -_            605,415           114, 442.39
Lima dragline--......-...                ......--------            .      July   1 to 31, 1943 -..- -20,105
                                                                                                       .                              4.948.14
                     GOVERNMENT PLANT

Pipe-line dredge:
    Blackwater--------------------------...                           July 1 to Aug. 17, 1943--.                   589, 541          41, 850.84
    Wahalak             --_--
                            - -.--        .-- .------                 July 1 to Aug. 29, 1943                   1,534,522            82,040.18
    Pascagoula_- ... _-.--------------.               -               July 1 to Aug. 30, 1943                   1, 272, 622          74, 152.68
Dragline excavator:
    No. 1_-----                 ---------                             July to Aug. 13, 1943- .-                   127, 701            9, 252. 27
   No. 2-------_ _...-.     -----------------------                   July 7 to Aug. 26, 1943....                 1 91,850            5,386.19

                                                                                                               9,084, 939

                                                                                                                Acres
Hired labor crew clearing for dragline excava-                        July 1 to Aug. 12, 1943 ----                  42.4              6,253.62
  tion.
Surveys, mapping, and establishment of oca-                           July 1, 1943, to June 30,- --------                     .      29, 456. 82
  tions for aids to navigation.                                         1944.

        Total new work---------                           ------------------------------------------                              1,213,381.37

  1 Includes 648,158 cubic yards removed from Gulf County Canal, Fla., at a cost of $142,335.21.


    Maintenance.-The U. S. hydraulic pipe-line dredge Blackwsater,
operating in the waterway from October 23 to November 1, 1943, and
January 5 to 14, March '23 to April 5, May 1 to 9 and 12 to 25, 1944,
removed 226,886 cubic yards of material at a cost of $40,810.66. The
U. S. snag boat Albany operating in the waterway from September
3 to October 3, 1943, removed 1,642 obstructions from the channel and
cut 76 overhanging trees from the bank, at a cost of $7,635.91. Repairs
to dams and dikes of the erosion protective works system were carried
on from April 21 to June 30, 1944, at a cost of $4,276.56. The cost of
miscellaneous investigations and work in connection with mooring
buoys was $3,840.15. Under section 3 of the River and Harbor Act of
October 17, 1940, the U. S. hydraulic pipe-line dredge Blackwater,
from November 10 to 14, 1943, removed 30,551 cubic yards of material
from the entrance channel to Bayou Coden, Ala., at a cost of $2,998.92,
and from April 19 to 21, 1943, removed 15,762 cubic yards of material
from Mitchell River Bar Channel, Fla., at a cost of $2,765.97.
   The total cost for the fiscal year was $1,275,709.54, of which $1,-
213,381.37 was for new work and $62,328.17 for maintenance. The
expenditures were $1,313,058.94.
   Condition at end of fiscal year.-The existing project was about 89
percent completed. The controlling depth at the end of the fiscal year
was 12 feet in the various sections of the waterway, and 8 feet in the
Gulf County Canal. The work remaining to be done to complete
the project consists of dredging to project dimensions the section
from Carrabelle, Fla., to Apalachee Bay, Fla., via Carrabelle, Crooked,
and Ochlockonee Rivers and Ochlockonee and Apalachee Bays, Fla.
Included in the total cost of maintenance are items of $1,000 for
                RIVERS        AND            HARBORS-MOBILE,                       ALA.,    DISTRICT                    561
dredging in Wolf Creek and $1,000 for dredging in Soldier Creek,
during the fiscal year 1935; $964.54 for dredging in Joes Bayou and
$977.06 for dredging in Indian Bayou, during the fiscal year 1939;
$969.62 for dredging in Perdido Pass Channel and $971.66 for dredg-
ing in Bayou Coden, during the fiscal year 1940, all under the pro-
visions of section 3 of the River and Harbor Act of July 3, 1930.
Also included are items of $2,998.92 for dredging in Bayou Coden,
Ala., and $2,765.97 for dredging Mitchell River Bar Channel, Fla.,
during the fiscal year 1944, under the provisions of section 3 of the
River and Harbor Act of October 17, 1940.
  The total costs and expenditures for the existing project to June 30,
1944, were as follows:

                                                                           Costs
                                                                                                               Expenditures
                                                New work             Maintenance              Total

Regular funds      .          .----.            $5, 478, 775. 03      $1,171, 037. 45      $6,649, 812. 48      $6, 653, 092. 74
Emergency Relief funds--_ -            ---           340, 000. 00-------                      340, 000. 00          340,000.00
      Total__ ---------------------              5, 818, 775. 03       1, 171, 037.45       6,989, 812. 48       6,993,092. 74



   Proposed operations.-The balance unexpended at the end of the
fiscal year, $101,200.15, including accounts receivable, plus an allot-
ment of $220,000 made in July will be applied as follows:
Accounts payable June 30, 1944 -                                                                                   $497. 61
New work:
    Complete control and hydrographic survey by hired
      labor of entire route of waterway between the
      Rigolets, La., and Carrabelle, Fla., establish loca-
      tions of new aids to navigation to be constructed
      by U. S. Coast Guard, and prepare completion
      m ap of project __ __ __    __  _    -__$10,                                                 535.82
                                                                                                                10, 535. 82
Maintenance:
    Dredging to restore project dimensions of the
      following sections, with U. S. hydraulic pipe-line
      dredges Blackwater, Pascagoula, and Wahalak,
      about 5% months during the fiscal year:
         Apalachicola Bay to Carrabelle, Fla_       . -_                                    31, 000.      00
         Apalachicola River to St. Andrews Bay, Fla--_                                      48, 000.      00
         West Bay to Choctawhatchee Bay, Fla ....                                           49, 738.      92
         Choctawhatchee Bay to Pensacola Bay, Fla__                                         21, 000.      00
         Pensacola Bay, Fla., to Mobile Bay, Ala_ ...                                       61, 000.      00
         Mobile Bay, Ala., to the Rigolets, La _....61,                                         000.      00
    Snagging in the Apalachicola River-St. Andrews
      Bay section with U. S. snag boat Albany, about
       1% months during October and November 1944 _-                                        11, 000. 00
    Construction of spillways at mouths of intersecting
      creeks and drainage gullies in the Apalachicola
      River-St. Andrews Bay section to serve as pro-
      tective works to prevent excessive embankment
      erosion and shoaling after heavy rains at such
      places as may be needed during the fiscal year .-                                       6, 000. 00
    Maintenance of dikes, ditches, and outlet control
      structures of erosion protective works in the
       West Bay-Choctawhatchee Bay section, by
      hired labor, as necessary during the fiscal year                               -      10, 000. 00
    Construct and install mooring buoys at bridges. --                                      11, 427. 80
                                                                                                               310. 166. 72

                          - --------
         Total all work_----                            ____--__-____--                        -      -        321, 200. 15
        616634-45--pt. 1, vol. 1-               36
562           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

  The additional sum of $290,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance dredging to restore project dimensions with United States
hydraulic pipe-line dredges, a total of about 10 dredge-months_ $265, 000
Maintenance snagging "withU. S. snag boat Albany about 2 months_      15, 000
Maintenance of dikes, ditches, and other protective works in the
Choctawhatchee-West Bay section and Apalachicola River-St.
Andrews Bay section by hired labor during the fiscal year -          10, 000
          Total -               --           _--290,                                                                              000
                                        Cost and financial summary
Cost of new work to June 30, 1944 ------------------------                                                     $5, 864, 379. 62
Cost of maintenance to June 30, 1944_----          -  -__                                                       1, 236, 174. 86
       Total cost of permanent work to June 30, 1944----------                                                  7, 100, 554. 48
Plus accounts receivable June 30, 1944_--        --------                                                               197. 75
      Gross total costs to June 30, 1944                        ---------------------                           7, 100, 752. 23
Minus accounts payable June 30, 1944_--                                            --------                             497. 61
      Net total expenditures_--   -------                                                         -__           7, 100, 254. 62
Unexpended balance June 30, 1944_--                                        ---------                               101, 002. 40
          Total amount appropriated to June 30, 1944------------                                                7, 201, 257. 02

   Fiscal year ending June 30               1940                 1941                 1942              1943               1944

Cost of new work------....-     -----------------------------------                       ----. $1, 710, 680. 48       $1, 213,381. 37
Cost of maintenance ...... __            $235, 851.91          $217, 328. 21       $64, 951.06       36, 931.31             62, 328. 17

      Total cost..---------------        235, 851.91         217, 328. 21           64, 951.06      1, 747, 611. 79     1, 275, 709. 54

Total expended....----------------236,130. 23                216, 435. 65           69, 484. 36    1, 706, 452. 54      1, 313, 058. 94

Allotted.........................        344, 421.04           89,889.70            90,000.00      2, 837, 500. 57        140, 998.92


Balance unexpended July 1, 1943_-     ------       _----       $1, 273, 062. 42
Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942         $138, 000. 00
Amount allotted from First Deficiency Appropria-
  tion Act approved Apr. 1, 1941----------------    3, 000. 00
                                                                   141, 000. 00
      Amount to be accounted for---       ---------                                                            1,414, 062. 42
Deductions on account of revocation of allotment_                                                                       1. 08
       Net amount to be accounted for___ - --         -   __                                                   1, 414, 061. 34
Gross amount expended--     -------            $1, 315, 767. 35
Less reimbursements collected-----------------       2, 708. 41
                                                                                                               1, 313, 058. 94

      Balance unexpended June 30, 1944---------------------                                                          101, 002. 40
Outstanding liabilities June 30, 1944_--  ---------                                                                       497. 61
      Balance available June 30, 1944_--                                       --------                              100, 504. 79
Accounts receivable June 30, 1944--
                                 _----------197.                                                                               75

     Unobligated balance available June 30, 1944                                    ------------                     100, 702. 54
Amount allotted in July 1944- _____-------------220,                                                                      000. 00

         Amount available during fiscal year 1945---------------                                                     320, 702. 54

Amount (estimated) required to be appropriated
                                       -
                                               for completion
of existing project 1   _                                  _                                                        705, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 1--                -      -                                                           290, 000. 00
1Exclusive of available funds.
                  RIVERS AND         HARBORS-MOBILE,                 ALA.,   DISTRICT                563
                                  2. ST. MARKS RIVER, FLA.

   Location.-This river, 17 miles in length, rises about 14 miles south-
east of Tallahassee, Fla., and flows in a southerly direction into the
Gulf of Mexico, 116 miles east from the new entrance to St. Andrews
Bay. (See U. S. Coast and Geodetic Survey Chart No. 182.)
   Previous'projects.-Provisionwas made for the removal of obstruc-
tions between 1824 and 1844, but apparently under no definite project.
For further details see page 686, Annual Report for 1938.
   Existing projeet. This provides for a channel 10 feet deep and
100 feet wide at mean low water on suitable alinement and with
greater width where necessary at bends, from the 10-foot contour in
Apalachee Bay to the town of St. Marks, with a turning basin of
the same depth and 200 feet square at the latter point, and for the
removal of snags and similar obstructions from the present channel
between St. Marks and Newport. The extreme tidal range, except
during storms, is between 3 and 4 feet. The mean range of tides is
2.4 feet.
   The estimated cost of new work, exclusive of amounts expended on
previous projects, revised in 1937, was $86,000. The latest (1937)
approved estimate of cost for annual maintenance is $1,500.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work authorized                                 Documents


July     3,1930   Channel 10 feet deep and a bottom width of 100     H. Doc. No. 453, 70th Cong., 2d seas.
                   feet at mean low water between the mouth of
                   the river and St. Marks, a distance of 6 miles,
                   by dredging.
Aug. 26,1937      Present project dimensions, straightening and      Rivers and Harbors Committee Doe.
                   widening the channel where necessary and re-       No. 77, 74th Cong., 2d sess.   (Cone
                   moval of snags and obstructions.                   tains latest published map.)


  Recommended modification of project.-Underdate of June 4, 1941,
the Chief of Engineers recommended modification of the existing
project so as to provide for straightening the channel in the vicinity
of Big Bayou, at an estimated first cost of $71,000, with no increase
in annual cost of maintenance, subject to certain conditions of local
cooperation (H. Doc. No. 345, 77th Cong., 1st sess.).
  Local cooperation.-Fully complied with.
  Terminal facilities.-The terminal facilities on this stream consist
of small wooden wharves and docks at the towns of St. Marks and
Newport. These wharves and docks are used for transferring fish
from small fishing craft to cold storage, for unloading petroleum
products, for refueling fishing and pleasure craft, and as berths for
the small boats located there. They are owned by local residents and
by petroleum companies. None is publicly owned, but a privately
owned dock with 200 feet of frontage at St. Marks is open to the
public. There are small marine ways at both St. Marks and Newport.
The facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1940. The controlling depth at the end of the fiscal year
was 10 feet. The total cost and expenditures under the existing project
564             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

were $103,686.97, of which $97,880.20 was for new work and $5,806.77
for maintenance.
  Proposed operations.-No funds are available and no operations
are contemplated during the fiscal year 1945.
  The sum of $7,500 can be profitably expended during the fiscal year
1946, for maintenance snagging with U. S. snag boat Albany, for about
1 month.
                          Cost and financial summary
Cost of new work to June 30, 1944--------------------------                                                        $133, 891. 06
Cost of maintenance to June 30, 1944_--------           ---                                                            5, 806. 77
      Total cost of permanent work to June 30, 1944------------                                                       139, 697. 83
Net total expenditures -------------------                                                                            139, 697. 83
Total amount appropriated to June 30, 1944-------------------                                                         139, 697. 83

   Fiscal year ending June 30              1940               1941                      1942              1943              1944


                 .............-
Cost of new work--------------            $4, 944.24..
Cost of maintenance-----------
                    ..........--           1,392. 87-    -     -         -            $4, 413. 90
      Total cost-     -.... ..-   .        6,337.11      ._        _.4,413.                    90 ....     . . . ..   ...   ..   .

Total expended.....----------------33,       035.44 --------------                     4, 413.90

Allotted.........--------------------6,      576. 23           $5, 000       ------------                  $586. 10

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance     ------------------------------                                                           $7, 500. 00
                       3. CARRABELLE BAR AND HARBOR, FLA.

  Location.-Carrabelle Bar and Harbor are located on the coast of
northwest Florida about 185 miles east of Pensacola Harbor. (See
U. S. Coast and Geodetic Survey Chart No. 182.)
  Previous projects.-Adopted by the act of June 3, 1896. For fur-
ther details see page 1833 of Annual Report for 1915, and page 687
of Annual Report for 1938.
  Existing project.-This provides for a channel 200 feet wide and
27 feet deep from the Gulf of Mexico to a point west of Dog Island,
thence 150 feet wide and 25 feet deep through St. George Sound and
Carrabelle River to a turning basin 590 feet square and 25 feet deep
at the town of Carrabelle.
   The estimated cost of new work, revised in 1937, was $346,000, in-
cluding $15,500 for aids to navigation. The latest (1937) approved
estimate of cost for annual maintenance is $24,000.
  The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                                        Documents


June 13, 1902    Channel at East Pass and the work at Dog Island                      H. Doc. No. 63, 56th Cong., 1st sess.
Mar. 2,1907      Channel 100 feet wide with a depth of 18 feet from
                   the outer harbor to a point about 2,500 feet out-
                   side the mouth of the river, with a turning basin,
                   thence 10 feet deep to the wharves at Carrabelle,
                   without any prior report having been made
                   thereon.
Aug. 26, 1937    Present project dimensions..----. ..--------                         H. Doc. No. 184, 75th Cong., 1st sess.
                                                                                        (Contains latest published map.)
                            RIVERS AND                   HARBORS-MOBILE,                      ALA.,         DISTRICT                      565
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-The landings, consisting of pile bulkheads and
Fills along the water front, are considered adequate for existing com-
mnerce. However, should the anticipated increase in traffic at this port
-occur, as a result of the recent deepening of the Carrabelle Ship Chan-
nel, the terminal facilities above referred to will not be adequate.
To meet this possible need assurances have been given by local interests
that adequate deep-sea terminal facilities will be provided.
   Operations and results dhring fiscal year.-The rented pipe-line
dredge Hendry No. 5, operating in the inner channel from September
1 to September 26, 1943, removed 220,491 cubic yards of material at a
-cost of $47,619.54. The cost of miscellaneous investigations and sur-
veys was $57.64. The total cost was $47,677.18, charged to mainte-
nance. The expenditures were $47,907.44.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depths at the end of the fiscal year were as
follows: Entrance channel, 27 feet; St. George Sound, 25 feet; Car-
rabelle River, 23.5 feet; and turning basin, 23.5 feet. The total cost
under the existing project was $598,880.04, of which $341,982.30 was
for new work and $256,897.74 for maintenance. The expenditures
were $598,942.60.%
   Proposed operations.-The balance unexpended at the end of the
fiscal year, including accounts receivable and an allotment of $18,000
made during July 1944, will be applied to maintenance dredging,
removing shoals in the sound, the river channels and anchorage basin
with a hydraulic pipe-line dredge for three-fourths month during
August 1944.
   The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging as follows:
Removing shoals in the sound, the river channels and anchorage basin,
  by a hydraulic pipe-line dredge for about 1 month_                  $25, 000
Removing shoals in the entrance channel by a United States seagoing
  hopper dredge for a period of about / month-------------- ----       15, 000

                Total_                      --------------------------------------------                                             40,000
                                                  Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                                                               $363, 686. 38
Cost of maintenance td June 30, 1944                                                                       ---              256, 897. 74
               Total cost of permanent work to June 30, 1944-_                                               ---               620, 584. 12
Plus accounts receivable June 30, 1944                                                                                                 62. 56
                Gross total costs to June 30, 1944----------------------                                                       620, 646. 68
Net total expenditures -----------------------------                                                                           620, 646. 68
Unexpended balance June 30, 1944 -----------------------------                                                                       27. 47
               Total amount appropraited to June 30, 1944--------                                                              620, 674. 15

     Fiscal year ending June 30                            1940                1941           1942                 1943              1944

Cost of new work .------...-.-.                                       .-..---.-...                          .
                                                                                                           -.     ---...        ... ....
Cost of maintenance-----------
                  ............- $15,918. 43 --------------                                  $15, 084. 60         $39,148.19         $47, 677. 18
Total expended...-----------------..............         15, 930.09   --------------         15, 084. 60          38,980. 49         47, 907. 44
Allotted.....................-----------------------..    2, 592.98        $28, 000.00   --------------          74, 000.00    ..-----------
566           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                     1944

Balance unexpended July 1, 1943---------------------------                                    $47, 934. 91
Gross amount expended-_-                           $47, 912. 44
Less reimbursements collected       -- - -                5. 00
                                                                                               47, 907. 44
      Balance unexpended June 30, 1944---- -----------------                                         27. 47
Accounts receivable June 30, 1944 ----------                                                         62. 56
     Unobligated balance available June 30, 1944                              -   - -   -           90. 03
Amount allotted in July 1944_     -     --   _                               --                18, 000. 00

          Amount available during fiscal year 1945                     ---          -          18, 090. 03

Amount that can be profitably expended in fiscal year ending June
                          1
                              -
30, 1946 for maintenance _____      _-- _-40, --                                                   000. 00
  1 Exclusive of available funds.

                                4. APALACHICOLA BAY, FLA.

   Location.-On the cost of northwest Florida, 160 miles east of Pen-
sacola Harbor. (See U. S. Coast and Geodetic Survey Chart No.
183.)
   Previous projects. Adopted in the River and Harbor Act of June
14, 1880, and modified by the River and Harbor Act of March 3, 1899.
For further details' see page- 1833, Annual Report for 1915, and page
689, Annual Report for 1938.
   Existing project.-This provides for channels from the Gulf of
Mexico 10 feet deep at mean low water, through West Pass in the Gulf
of Mexico, and Link and Inner Bar Channels in Apalachicola Bay,
with a width of 150 feet in West Pass and Link Channels, and a width
of 100 feet in the Inner Bar Channel. It also provides for a channel
through Bulkhead Shoals, 9 feet deep and 100 feet wide, which serves
as another entrance to Apalachicola Bay through East Pass, the en-
trance channel to Carrabelle Harbor.
   The mean range of tide throughout this harbor is 2 feet. The
extreme range, except during storms, is about 3 feet.
   The estimate of cost of new work, revised in 1927, was $82,144,
exclusive of amounts expended on previous projects. The latest
 (1927) approved estimate of annual cost of maintenance is $14,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                               Documents


Mar. 2,1907      Channel 18 feet deep through West Pass and Link     H. Doc. No. 422, 59th Cong., 1st sess.
                  Channel, 10 feet deep across the bar, and 9 feet
                   through Bulkhead Shoals.
Jan.   21,1927   Present project dimensions_ -----         _____ __- H. Doc. No. 106, 69th Cong., 1st sess.
                                                                       (Contains latest published map.)



   Terminal facilities.-Consist of several marginal pile and timber
wharves. The facilities are considered adequate for existing
commerce.
   Operations and results du/ring fiscal year.-None. The cost was
$303.36 for miscellaneous investigations and surveys, charged to main-
tenance. The expenditures were $309.63.
                        RIVERS AND          HARBORS-MOBILE,                         ALA.,        DISTRICT                      567
   Condition at end of fiscal year.-The existing project was completed
in 1925. The controlling depths at the end of the fiscal year were as
follows: Inner Bar Channel, 10 feet; St. George Channel, 10 feet;
Link' Channel, 10 feet; West Pass, 10 feet; and Bulkhead Shoals, 9
feet. The total cost under the existing project was $675,574.65, of
which $82,144.59 was for new work and $593,430.06 for maintenance.
The expenditures were $675,574.65.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $307.89, will be applied to investigating reports of shoals
or other obstructions in the channel and making routine examinations
to determine available channel depths.
   The additional sum of $15,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging to provide project di-
mensions in the West Pass Channel, with a small United States sea-
going hopper dredge for about two-thirds month.
                                        Cost and financial summary
Cost    'fnew work to June 30, 1944_-----------------------------   $216,758.09
Cost of maintenance to Junie 30, 1944--- _---              -    ___  762, 195: 82
             Total cost of permanent work to June 30, 1944_                                                           978, 953. 91

Net total expenditures                                                                             __                 978, 953. 91
Unexpended balance June 30, 1944                                                                                             307. 89
             Total amount appropriated to June 30, 1944--------------                                                 979, 261. 80

    Fiscal year ending June 30                1940               1941               1942                  1943              1944

Cost of new work _-_-_
Cost of maintenance------....-.----..       $17,033.57         $14, 984.24        $15, 763.80              $388.75            $303.36
             -----------------
Total expended....                           17, 154. 82        15, 263. 26        15, 563. 80              382. 48            309. 63
Allotted-_......_.....18,                       916. 39         20, 918. 93        18, 000. 00     -19,     351.96      .


Balance unexpended July 1, 1943_______________ ______________                                                               $617. 52
Gross amount expended                   -                  -       -          -         -         $310. 69
Less reimbursements collected_--                                ---------                                 1. 06
                                                                                                                            309. 63
             Balance unexpended June 30, 1944__                          -            --------                              307. 89
Amount' that can be profitably expended in fiscal year ending June
                                        -  -   - -   -  -   -
  30, 1946, for maintenance 1 ____     _____                  ___                                                      15, 000.0bo
1Exclusive of available funds.

5. APALACHICOLA                   RIVER, FLA., THE CUT-OFF,                                      LEE       SLOUGH,            AND
                                     LOWER CHIPOLA RIVER

   Location.-The Apalachicola River is formed at the southwest
corner of the State of Georgia by the junction of the Chattahoochee
and Flint Rivers and flows south a distance of 112 miles, emptying
into Apalachicola Bay. The Florida River enters the Apalachicola
River from the east, 45.4 miles above its mouth, and the River Styx
also enters from the east, 36.7 miles above its mouth. (See U. S.
Coast and Geodetic Survey Chart No. 183.)
   Previous projects.-Expenditures were made between 1828 and
1831, but apparently under no definite project. In the years 1835
568            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                   1944

and 1836 appropriations were made for the Chipola River. Work
under existing project was begun in 1875. For further details see
page 690, Annual Report for 1938.
  Existing project.-This provides for a channel in the Apalachicola
River 6 feet deep at low water and 100 feet wide, to be secured by
the removal of snags and overhanging trees and by widening and
straightening Moccasin Slough, and for a channel 5 feet deep and
60 feet wide through the Cut-off, Lee Slough, and lower Chipola
River. Snagging and dredging to a depth of 6 feet of the lower
2,500 feet of the Styx River, a tributary of the Apalachicola River, is
included in the existing project.
  The existing project also includes the improvement of the Florida
River by dredging a new outlet from Florida River, 6 feet deep and
80 feet wide, about 600 feet downstream of its present mouth.
   The mean range of the tide at the mouth of Apalachicola River is
2 feet, and the variation between low and high water is about 30 feet
at the point where the river is formed.
   The estimate of cost for new work, revised in 1938, was $127,800,
exclusive of amount expended on previous project, but including
$1,250 contributed by local interests to apply on the improvement at
the mouth of Florida River. The latest (1938) approved estimate of
annual cost of maintenance is $16,000.
  The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                                    Documents


June 23, 1874      The channel in the Apalachicola River   ----------
                                                              .         H. Doc. No. 241, 42d Cong., 2d sess.,
                                                                         and Annual Report, 1873, p. 698.
June 13, 1902      The work in the cut-off, Lee Slough and lower Annual Report, 1889, p. 1416.
                    Chipola River.
Jan. 6, 1934   1   Work of snagging and dredging in the Styx River__
                                                                                                            2
June 20,1938       Dredging in the Florida River----------------
                                                  ..                    H. Doc. No. 575, 75th Cong., 3d sess.


  I Public Works Administration.
  2 Contains the latest published map of Florida River.

Map of Apalachicola River has been published in H. Doc. No. 342, 76th Cong., 1st sess. A map of the
                         0      eo is
Cuntoff, Lee ISu andlow
                     c      Chip      Rier ill be found in Annual .Report,;18 1eilosite
                                                                               ,        p. 1696.

 *Recommended modifications of project.-Under date of April 20,
1939, the Chief of Engineers recommended that the general plan
presented in the report for the full development of the Apalachicola,
Chattahoochee, and Flint River system in the combined interest of
navigation and power be approved, and that for the initiation and
partial accomplishment of said plan the existing project for Apa-
lachicola River, Fla., Chattahoochee River, Ga. and Ala., and Flint
River, Ga., be modified to provide for the construction of two of the
locks and dams for the 9-foot project, one at Fort Benning and one at
the junction, supplemented by dredging and contraction works, to
provide a navigable depth of 6 feet to Columbus, Ga., and to Bain-
bridge, Ga.; at an estimated cost for new work of $6,500,000, with
annual maintenance of $200,000 in addition to that now required;
subject to certain conditions of local cooperation (H. Doc. No. 342,
76th Cong., 1stisess.).
                    RIVERS          AND       HARBORS-MOBILE,                         ALA., DISTRICT                  569
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-At Apalachicola, Fla., the facilities consist of
several marginal pile and timber wharves. The landing at Blounts-
town, Fla., is a natural one. The wharf at River Junction, Fla., is
a private one and is used for the handling and storage of sand and
gravel. These facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year.-The U. S. pipe-line
dredge Blackwater, operating in the Apalachicola River from Octo-
ber 2-19, 1943, removed 79,183 cubic yards of material, at a cost of
$12,352.76. The U. S. snag boat Albany, operating in the river from
October 4 to November 3, 1942, removed 1,114 obstructions and cut
190 overhanging trees from the bank at a cost of $6,840.13. The cost
of miscellaneous investigations and surveys was $180.51. The total
cost was $19,373.40, charged to maintenance. The expenditures were
$19,313.47.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1939. Work on the Styx River, a tributary of the Apalachi-
cola River, was completed in 1934. Work on the Florida River, also
a tributary of the Apalachicola River, was completed in 1939. At
the end of the fiscal year the contraction works were in fair condi-
tion. The controlling depths at the end of the fiscal year were as
follows: Apalachicola River, 6 feet; the Cut-off, 5 feet; Lee Slough,
5 feet; Lower Chipola River, 5 feet; Styx River, 3.5 feet; and the
mouth of Florida River, 6 feet. Ordinarily, boats drawing 5 feet
can operate throughout the year at a stage of zero on the river junc-
tion gage. Greater depths are usually available from January to
July of each year.
   The total cost and expenditures under the existing project to June
30, 1944, were as follows:
                                                                              Costs
                                                                                                            Expenditures
                                                      New work            Maintenance        Total

Regular funds....
              -----------------------                   $114, 234. 27       $380, 273, 32   $494, 507. 59      $494, 362.91
Public Works funds................--------------------.   14, 335.12    -----------------     14, 335.12         14, 335. 12
       Total.--------------------------                 128, 569. 39         380, 273. 32    508, 842. 71       508, 698.03


   In addition, $1,923.53 was expended on new work from contributed
funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $803.76, will be applied as follows:
Accounts payable -------------------------------------------             $144. 68
Investigating reports of shoals or other obstructions in the channel and
  making routine examinations to determine available channel depths.      659. 08

           Total       ------------------------------------------------                                          803. 76
  The additional sum of $31,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance dredging to meet the needs of navigation in the Apalachicola
River, with, a hydraulicapipe- ine dredge fQr s mouth ------------      $20, 000
Maintenance snagging in the Apalachicola River with U. S. snag boat
Albany about 2 months -------------------------------------              11,000
          Total ---------------                                                                              -31,000
-570               REPORT OF CHIEF OF ENGINEERS,                                              U.    S. ARMY,               1944

                                                  Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                                                               1 $141,569. 39
Cost of maintenance to June 30, 1944                                                                                       -      80, 273. 32
                                                                                                                                 3------------------
      Total cost of permanent work to June 30, 1944                                                -521,                                   842. 71
Minus accounts payable June 30, 1944-------------------------                                                                              144. 68
      Net total expenditures_ ______-------___                                                                                 1 521, 698. 03
Unexpended balance June 30, 1944------_                                                                            -803.                   76
              Total amount appropriated to June 30, 1944-------------                                                          1 522, 501. 79


     Fiscal year ending June 30                      1940                   1941                1942                1943                   1944

C.ost of new w ork---------------                   $5, 770. 58   -   -     -   - - - -   .    . . . .       . .     . . . . .        . .
Cost of maintenance .........-------------.         20, 216. 08           $25, 620. 34        $20, 395. 71         $7, 745.79         $19, 373.40
                   ----------------
         Total cost...........   .                  25, 986. 66            25,620. 34          20. 395. 71          7, 745. 79             19, 373. 40
Total expended---------------..............-...     25, 511.06             26, 068. 91         20, 443. 02         7, 661.04               19, 313. 47
Allotted        ....----------------------          22, 520. 59            25, 810. 81         22, 000. 00-................           ..      ....



Balance unexpended July 1, 1943                              __                                                                  $20, 117. 23
'Gross amount expended_ ____----------             $20, 231. 58
Less reimbursements collected---------------------      918. 11
                                                                                                                                  19, 313. 47

4
       Balance unexpended June 30, 1944----------------------                                                                              803. 76
Outstanding liabilities June 30, 1944_--------            ---                                                                              144. 68
              Balance available June 30, 1944_-------                                                                  ---                 659. 08
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 2 ___          _____________                                                                           31, 000. 00
    1 In addition, $1,923.53 expended for new work from contributed funds.
     Exclusive of available funds.

                                                    6. FLINT RIVER, GA,

   Location.-This river, 330 miles in length, rises in the west central
part of the State of Georgia, flows in a generally southeasterly direc-
tion to Albany, and thence southwest to the southwest corner of the
State, where it joins with the Chattahoochee River in forming the
Apalachicola River. (See U. S. Geological Survey charts for south-
west Georgia.)
   Existing project.-This provides for a channel 100 feet wide and 3
feet deep at extreme low water from the mouth of the river to Albany,
a distance of 103 miles, to be obtained by dredging, rock excavations,
building contraction works, and removal of snags; and a channel for
light-draft steamers at moderate stages from Albany to Montezuma,
a distance of 79 miles, to be obtained by the removal of loose rocks,
snags, and overhanging trees. The extreme. fluctuation of stage due
to floods was 33 feet, while the average variation between low and
high water is approximately 21.5 feet. The estimated cost of new
work between the mouth and Albany, revised in 1928, is $715,000, and
between Albany and Montezuma, made in 1879, $15,100.. The latest
 (1928) approved estimate of annual cost of maintenance is $20,000.
                RIVERS       AND     HARBORS--MOBILE,                ALA.,     DISTRICT                 571
  The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                    Documents


June 23, 1874   A channel 100 feet wide and 3 feet deep at extreme   H. Ex. Doc. No. 65, 43d Cong., 1st sess.,
                 low water from the mouth of the river to Albany.      and Annual Report, 1873, p. 707.
June 14, 1880   Extended the project to Montezuma....-----------     H. Ex. Doc. No. 95, 45th Cong., 3d sess.,
                                                                       and Annual Report, 1879, p. 818.


The latest published map of Flint River, Ga., may be found in H. Doe. No. 342, 76th Cong., 1st sess.


   Recommended modifications of project.-Under date of July 25,
1917, the Chief of Engineers recommended modification of the project
by eliminating improvement of that portion of the river above Albany
  (H. Doc. No. 302, 65th Cong., 1st sess.).
   Modification of the existing projects for Apalachicola River, Fla.,
Chattahoochee River, Ga. and Ala., and Flint River, Ga., in the com-
bined interest of navigation and power, was recommended by the
Chief of Engineers April 20, 1939. (See recommendations reported
under the project for Apalachicola River, p. 568.)
   Terminal facilities.-The facility at Bainbridge consists of a natural
landing. There is also a natural landing at Albany, Ga. These
facilities are considered adequate for existing commerce.
    Operations autd results during fiscal year.-None. The costs and
expenditures were $140.60 for miscellaneous investigations and sur-
veys, charged to maintenance.
   Condition at end of fiscal year.-The existing project was 98 percent
completed at the end of the fiscal year. Work of improvement has been
carried on from the mouth to Albany Shoals, a distance of 103 miles.
The controlling depths at the end of the fiscal year were: Albany to
Bainbridge, 1.5 feet; and Bainbridge to mouth, 2.6 feet; however,
greater depths are generally available between the months of Novem-
ber and June of each year. The head of navigation for boat traffic is
Albany, Ga. A zero gage reading at Newton, Ga., indicates that a
3-foot depth of water is available for navigation. The work remaining
to be done to complete the project to Albany, Ga., consists of widening
various dredged cuts from 70 to 100 feet. The total cost and expendi-
tures were $847,721.09, of which $640,819.77 was for new work and
$206,901.32 for maintenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $295.25, will be applied to investigating reports of shoals
or other obstructions in the channel and making routine examinations
to determine available channel depths.
   The additional sum of $10,000 can be profitably expended during the
fiscal year 1946 for maintenance snagging and rock removal, with
U. S. snag boat Albany, for about 11/2 months.
   No new work is contemplated on this project, as the small amount of
work remaining to complete the project is not needed in view of thle
recommended modification contained in House Document No. 342,
Seventy-sixth Congress, first session.
572              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                      1944

                                                Cost and financial summary
Cost of new work to June 30, 1944___--        ---------                                          $640, 819. 77
Cost of maintenance to June 30, 1944_--------                                          ---        206, 901. 32
            Total cost of permanent work to June 30, 1944------------                                847, 721. 09
Net total expenditures----      --------------                                                       847, 721.09
Unexpended balance June 30, 1944_- -           -----------                                                295. 25
            Total amount appropriated to June 30, 1944                     --------------            848, 016. 34

    Fiscal year ending June 30                    1940         1941        1942          1943                 1944

Cost of new work..... - - - -                         .    . . . . . . . . . -. . .. . . . . .- .
Cost of maintenance----------.............       $6, 333.66    $6, 127.48 $3, 571.29 $3, 213.11 $140.60
Total expended-----------------..............     6,416.26     6,147.73    3, 551.04     3,213. 11               140.60
Allotted-------------......-...                   6, 771. 07   3, 347.73   3,000.00-----------------------

Balance unexpended July 1, 1943_-----           -    -    ----                                               $435. 85
Gross amount expended ---------------------------------------                                                 140. 60
             Balance unexpended June 30, 1944-----------------------                                          295. 25
Amount (estimated) required to be appropriated for completion of
existing project 1- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -                    89, 200.00
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1-                            -        -         -       -                 -_10,    000. 00
  1 Exclusive of available funds.


                            T. CHATTAHOOCHEE RIVER, GA. AND ALA.

   Location.-This river, 418 miles in length, rises in the north central
part of the State of Georgia and flows in a southwesterly direction to
West Point; and thence in a southerly direction to join with the Flint
at the southwest corner of the State of Georgia, forming the Apa-
lachicola River. (See U. S. Geological Survey charts for northwest
Georgia.)
   Previous projects.--The River and Harbor Act of July 13, 1892,
made an appropriation for the section of river between West Point
and Franklin, Ga., and appropriations therefor were continued until
1899, when they were discontinued. For further details see page 1834
of Annual Report for 1915, and page 696 of Annual Report for 1938.
   Existing project.-This provides for.securing a channel 4 feet deep
at low water and 100 feet wide from the mouth to Columbus, Ga., a
distance of 164 miles, by the removal of timber obstructions, dredging,
contraction works, and shore protection. The variation between aver-
age low and high water is approximately 20 feet. The extreme fluctua-
tion is 54.7 feet at Columbus.
   The estimated cost of new work, from the mouth to Columbus, Ga.,
revised in 1924, is $1,156,000, exclusive of amounts expended on pre-
vious projects. The latest (1928) approved estimate of annual cost
of maintenance is $60,000.
   The existing project was adopted by the River and Harbor Act
June 23, 1874 (H. Doc. No. 241, 42d Cong., 2d sess., and Annal Report of

for 1873, p. 699).                       The latest published map of Chattahoochee River,
           RIVERS AND            HARBORS-MOBILE,       ALA., DISTRICT                573
Ga. and Ala., may be found in House Document No. 342, Seventy-sixth
Congress, first session.
   Reconvrnended modifcations of project.-See recommendations
reported under the project for Apalachicola River, page 568.
   Terminal facilities.-The terminals at Columbus and Eufaula, Ala.,
consist of natural landings, and a marginal landing of masonry con-
struction is located at Columbus, Ga. These facilities are considered
adequate for the existing commerce.
   Operations and results during fiscal year.-The U. S. pipe-line
dredge Blackwater, operating in the channel from September 1 to
October 1, 1943, removed 132,017 cubic yards of material at a cost of
$24,656.46. The U. S. snag boat Albany, operating in the Chatta-
hoochee River from November 22 to December 14, 1943, December 24,
1943, to February 12, 1944, and June 28 to 30, 1944, removed 2,280
cubic yards of material and 2,317 obstructions from the channel and
cut 968 overhanging trees from the bank at a cost of $22,771.09. The
cost of miscellaneous investigations and surveys was $115.92. The
total cost was $47,543.47, charged to maintenance. The expenditures
were $44,992.67.
   Condition at end of fiscal year.-The existing project was 94 per-
cent completed in 1931, and operations since that date have consisted
of maintenance. At the end of the fiscal year dredging, open-channel
work, and snagging operations had been carried on from the mouth
of the river to a point 164 miles above the mouth. The controlling
depth at the end of the fiscal year at low water was 3 feet. Vessels
drawing not more than this may operate on the river throughout the
year, and 5 feet can ordinarily be carried from December to Septem-
  er, inclusive. The head of navigation for boat traffic is Columbus,
Ga. The work remaining to be done to complete the project consists
of the construction of contraction works in the lower 25 miles of the
river. A gage reading of 2.5 feet at Columbus, Ga., normally indicates
that the depth of water is adequate for 4-foot navigation.
   The total cost under the existing project was $2,718,182.52, of which
$1,081,084.85 was for new work and $1,637,097.67 for maintenance.
The expenditures were $2,715,461.70.
   Proposed operations.-The balance unexpended at the end bf the
fiscal year, including an allotment of $25,000 made during July 1944.
will be applied as follows:
Accounts payable June 30, 1944                            -----------_         $2, 720. 82
Maintenanke dredging with U. S. snagboat Albany remov-
ing shoals at locations of bars between mile 150 and
Columbus, Ga., about / month, during July 1944         $4, 279. 18
Maintenance snagging with U. S. snagboat Albany as may
be necessary to meet the needs of navigation between
Columbus, Ga., and the mouth, about 2% months, dur-
ing July, August, September, and October 1944----- -18,    177. 35
                                                                               22, 456. 53

      Total----------              -----------------------------------         25, 177.35
   The additional sum of $86,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance dredging to meet the needs of navigation with a hydraulic
pipe-line dredge for 2% months- -$65,                                                 000
Maintenance snagging operations with U. S. snagboat Albany, for 3
months- --               -   -      -    -     -    -      -     -                 21, 000

      Total_   ..-------------------                         ....---     ...---.-   86, 000
574            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

  No new work is contemplated, as the small amount of work remain-
ing to complete the project is not needed in view of the recommended
modification of this project contained in House Document 342, Seventy-
sixth Congress, first session.
                                                 Cost and financial summary

Cost of new work to June 30, 1944-__      --------                                                   _          $1, 100, 804. 07
Cost of maintenance to June 30, 1944------                                                       -    _ _         1,637, 097. 67

      Total cost of permanent work to June 30, 1944----------                                                    2, 737, 901. 74
Minus accounts payable June 30, 1944_-----             __                                                             2,720. 82

      Net total expenditures_ ------------------------------ 2, 735, 180. 92
Unexpended balance June 30, 1944_---------------------------         177. 35

           Total amount appropriated to June 30, 1944--------                                                    2735,
                                                                                                                 2,    358. 27

   Fiscal year ending June 30                       1940            1941            1942                 1943             1944

Cost of new work ......... ... ...
Cost of maintenance----------- $153,
                                   338.70                        $136, 828.86    $140,887.62         $56, 825. 35       $47, 543. 47

Total expended ----------------                   172, 723. 04    155, 028. 32    118, 875. 53        60, 632.73         44, 992. 67

Allotted    ............---------------------     282,155.10      143, 054. 10     60,000.00         -26, 864. 57        45,000.00


Balance uriexpended July 1, 1943_-                                                                                      $170. 02
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940_                                                                                            45, 000. 00

       Amount to be accounted for_                                                                                   45, 170. 02
Gross anount expended_- __      -------                                               $45, 026.03
Less reimbursements collected_-    ---------                                                33. 36
                                                                                                                     44, 992. 67

      Balance unexpended June 30, 1944_                                                                                   177. 35
Outstanding liabilities June 30, 1944_                                                                                 2, 720. 82
     Balanice available June 30, 1944_                                                                              - 2, 543. 47
Amount allotted in July 1944                                                                                         25, 000. 00

       *Amount available during fiscal year 1945-                                                                   22, 456. 53
Amount (estimated) required to be appropriated for completion
of existing project 1-------------------------------      __                                                       75, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance1 __--_     -
                                          ___  -___-----                                                            86, 000. 00
1Exclusive    of available funds.

                                                8. ST. JOSEPHS BAY, FLA.

  Location.-On the northwest coast of Florida, 115 miles east of
Pensacola Harbor. (See U. S. Coast and Geodetic Survey Chart
No. 184.)
  Eoisting project.-This provides for a channel 300 feet wide and
29 feet deep at mean low water across the bar at the entrance to the
bay, and a channel 200 feet wide and 27 feet deep from deep water
in St. Josephs Bay to Port St. Joe, with a turning basin approxi-
mately 6 acres in area and 27 feet deep at the proposed municipal
pier at Port St. Joe. The average tidal variation is 1.4 feet. The
extreme range, except during storms, is about 4 feet.
                RIVERS AND           HARBORS--,MOBILE,               ALA.,    DISTRICT                 575
   The estimated cost of new work, revised in 1937, was $124,000, exclu-
sive of $20,000 contributed by' local interests. The latest (1937) ap-
proved estimate of cost for maintenance is $15,000 annually for the
first 3 years and $5,000 annually thereafter.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                   Documents


July 25,1912    Project document recommended a width of 350          H. Doc. No. 660, 62d Cong., 2d sess.
                 feet and the act limited the width to 300 feet
                 with a depth of 24 feet across the bar at the en-
                 trance to the bay.-
Aug. 26, 1937   The present project dimensions ----------.....---.
                                                               --    Rivers and Harbors Committee Doc.
                                                                       No. 10, 75th Cong., 1st sess.   (Con-
                                                                       tains latest published map.)



   Recommended modifications of project.-Under date of November-
19, 1940, the Chief of Engineers recommended modification of the
existing project for St. Josephs Bay, Fla., to include the existing south
channel at its present dimensions, 27 feet deep and 200 feet wide, from
the turning basin at Port St. Joe to the 27-foot contour in the bay,,
at an estimated cost of $5,000 annually for maintenance in addition
to that now required; subject to certain conditions of local cooperation
(S. Doc. No. 17, 77th Cong., 1st sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-Consistof a deep-sea terminal with a marginaL
wharf of bulkhead and fill construction, approximately 3,522 feet in
length, with adequate rail and highway connections. One thousand
feet of this wharf and the warehouse located thereon are controlled by
the city of Port St. Joe, approximately 600 feet by the Gulf Oil Cor-
poration, and the remaining 1,922 feet are owned and used exclusively
by the St. Joe Paper Co. In addition there are several small privately
owned vharves of pile and timber construction, used, principally by
boats engaged in the fishing industry. These facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year.-None. The cost and
expenditures were $1,324.58 for miscellaneous investigations and sur-
veys, charged to maintenance.
   Condition at end of fiscal year.-The existing project was completed
in 1938. The controlling depths at the end of the fiscal year were'
Entrance channel, 29 feet; bay channel, 26 feet; turning basin, 25.8
feet. The total cost was $206,963.87, of which $124,105.99 was for new
work and $82,857.88 for maintenance. The expenditures were $206,-
963.87. In addition, $20,000 was expended from contributed funds
for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $33,620.39, will be applied to maintenance dredging to.
restore project dimensions in the inner channel and turning basin with
a hydraulic pipe-line dredge, about 11/2 months during September and
October 1944.
576               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

  The additional sum of $37,500 can be profitably expended during
the fiscal year 1946 for maintenance dredging to restore project di-
mensions in the entrance channel, with a United States seagoing hopper
dredge, about 11/4 months.
                                                    Cost and financial summary
Cost of new work to June 30, 1944-------------------------                                                 1   $124, 105. 99
Cost of maintenance to June 30, 1944_--------              ---                                                   82, 857. 88

             Total cost of permanent work to June 30, 1944-----------                                           206, 963. 87

Net total expenditures----    -------------                                                                    1 206, 963. 87
Unexpended balance June 30, 1944---------------------------                                                       33, 620. 39
             Total amount appropriated to June 30, 1944                             ------------               1 240, 584. 26

     Fiscal year ending June 30                        1940          1941           1942            1943              1944
Cost of new work--------.........---------------                            -                   .


Cost of maintenance..--.........                     $15, 655.91   $33, 470. 76   $16, 044.41       $155.03          $1, 324.58

Total expended----------------..................      15, 712.88    33, 607. 50    16, 032.05        167. 39           1,324.58

Allotted_--                     ....
                          ---............             49, 253.33    29,000.00      18, 000.00   13, 822.06          -10,000.00



Balance unexpended July 1, 1943_----------------------------.                                                   $44, 944. 97
Deductions on account of revocation of allotment---------------                                                  10, 000. 00

       Net amount to be accounted for ------------------                                                          34, 944. 97
Gross amount expended-_..____---         -$1,          331.07
Less reimbursements collected--------------------        6. 49
                                                                                                                   1, 324. 58
             Balance unexpended June 30, 1944----------------------33, 620. 39
Amount that can be profitably expended in fiscal year ending June
   30, 1946 for maintenance 2- ________                  -       ----                                            37, 500. 00
  1In addition $20,000 expended from contributed funds for new work.
  3 Exclusive of available funds.

                                                   9. ST. ANDREWS BAY, FLA.

   Location.-On the northwest coast of the State of Florida, 102 miles
east of the entrance to Pensacola Harbor. (See U. S. Coast and
Geodetic Survey Chart No. 184.)
   Previous project.-Adopted by the River and Harbor Act of June
25, 1910. For further details see page 541 of Annual Report for 1934
and page 710 of Annual Report for 1938.
   Existing project.-This provides for a channel extending from deep
water in the bay across Lands End to the Gulf of Mexico, 300 feet
wide and 27 feet deep in the bay and across Lands End and 450 feet
wide and 29 feet deep in the approach channel in the Gulf, and pro-
tected by two jetties, each about 700 feet long. The mean tidal range
is 1.4 feet, and the extreme range, except during storms, is about 4
feet.
   The estimated cost for new work made in 1933 was $435,000. The
latest (1939) approved estimate for annual cost of maintenance is
$35,000.
   The existing project, including abandonment of the project adopted
by the act of June 25, 1910, was authorized by the River and Harbor
                 RIVERS AND           HARBORS-MOBILE,                         ALA.,    DISTRICT                  577

Act approved August 30, 1935 (H. Doc. No. 33, 73d Cong. 1st sess.).
The latest published map of this locality will be found in the project
document. The existing project was also authorized by the Public
Works Administration September 6, 1933.
  Recommended modifications of project.--Under date of December
15, 1939, the Chief of Engineers recommended modification of the
existing project for St. Andrews Bay, Fla., so as to provide a chan-
nel in Watson Bayou 100 feet wide and 10 feet deep from that depth
in St. Andrews Bay to the highway bridge, at an estimated cost of
$1,000 annually for maintenance, in addition to that now required;
subject to certain conditions of local cooperation (H. Doc. No. 555,
76th Cong., 3d sess.).
  Local cooperation.-Fullycomplied with.
   Terminal facilities.-Consist of two privately owned oil terminals,
one concrete and steel pier and warehouse owned by the Atlanta & St.
Andrews Bay Railway Co., at Panama City, Fla., and wharves of con-
crete and steel construction owned by the municipality of Panama
City, Fla. These wharves afford berthing spaces for five ships. There
are also a number of small privately owned pile and timber wharves
located at Panama City, Fla. These facilities are considered adequate
for existing commerce.
   Operations and results during fiscal year.-None. The cost was
$2222.47 for miscellaneous investigations and surveys, charged to
maintenance. The expenditures were $2,327.65.
   Condition at end of fiscal year.-The existing project was completed
in 1934. The controlling depths at the end of the fiscal year were 27
feet in the channel from the bay across Lands End, and 28.2 feet in
the approach channel in the Gulf.
   The total costs and expenditures on the existing project to June 30,
1944, were as follows:

                                                                      Costs
                                                                                                        Expenditures
                                             New work            Maintenance             Total

                 --
Regular funds-._...........------                                $1,060, 738. 81      $1,060, 738.81     $1,060,738.81
Public Works funds_----._         -              $581, 958.86    --     .- .    -        581, 958.86        581, 958.86
     Total ..-        _
                    _ __.-... __.....
                                    -..           581, 958. 86    1, 060,738.81        1, 642, 697.67     1, 642, 697.67


   Proposed operations.- he balance unexpended at the end of the
fiscal year, $47,555.94, will be applied as follows:
Maintenance dredging to restore project dimensions in the new
entrance channel, with U. S. seagoing hopper dredge Benyaurd,
for about 1 month during the fiscal year 1945, when available -- $35, 000. 00
Maintenance of jetties at new entrance channel by hired labor, Sep-
tember to November 1944, inclusive -----------------   .           12, 555. 94
        Total---------------------------------------------47,                                                555. 94
   The additional sum of $85,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance dredging to restore project dimensions in the new entrance
channel with a United States seagoing hopper dredge, for a period of 1
month                -         -        -           -                  $50, 000
Maintenance of jetties at new entrance channel by hired labor--------    35, 000
       Total -------------------                                                                             85, 000

       616634---45--pt. 1, vol. 1-          37
578          REPORT OF CHIEF OF ENGINEERS,                           U. S. ARMY,              1944

                                      Cost and financial summary
Cost of new work to June 30, 1944-_                                                             $785, 518. 86
Cost of maintenance to June 30, 1944_---                              -     --      ___        1, 574, 343. 48

           Total cost of permanent work to June 30, 1944----------                            2, 359, 862. 34
Net total expenditures_ -----------------------------------                                   2, 359, 862. 34
Unexpended balance, June 30, 1944-- ------                __                                      47, 555. 94
           Total amount appropriated to June 30, 1944                     -----------         2, 407, 418. 28


   Fiscal year ending June 30            1940           1941              1942         1943              1944

Cost of new work.....
Cost of maintenance ------------       $35, 054.43    $48, 878. 25   $82, 277. 14     $1, 280. 39       $2, 222. 47
Total expended----------------
               ....                     32, 288. 57    53, 961.41     80,162. 57       1, 478. 81        2, 327. 65
Allotted   ----------------------
           .                            88,154. 37     54, 482. 10    37, 600.00      30, 000. 00      -35,000. 00



Balance unexpended, July 1, 1943_--       ----------                                                $84, 883. 59
Deductions on account of revocation of allotment---------                                            35, 000. 00
       Net amount to be accounted for-----------------                                               49, 883. 59
Gross amount expended_                              $2, 329. 60
Less reimbursements collected___ -  -------               1. 95
                                                                                                      2, 327. 65
           Balance unexpended, June 30, 1944---------------------                                    47, 555. 94
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1__-----_-____               ______--85,                                     000. 00
  1 Exclusive of available funds.


                                    10. LA GRANGE BAYOU, FLA.

   Location.-This waterway is an arm of Choctawhatchee Bay, Fla.,
located about 70 miles east of Pensacola Harbor and about 46 miles
west of Panama City, Fla. The length of the waterway is 31/2 miles
from its mouth through La Grange Bayou and Four Mile Creek to
the town of Freeport, Fla., which is the head of navigation. (See
U. S. Coast and Geodetic Survey Chart No. 185.)
   Previous project.-Adopted by the River and Harbor Act of March
3, 1881. For further details see page 869 of the Annual Report for
1931 and page 671 of the Annual Report for 1937.
   Ewisting project.-This provides for a channel 9 feet deep and 100
feet wide from the 9-foot contour in Choctawhatchee Bay to Freeport,
Fla., a distance of approximately 41/2miles. The normal tidal range
is about 0.5 foot, and the extreme range, except during storms, is about
3 feet.
   The estimated cost for new work made in 1935 was $75,000 with
$2,000 for annual maintenance.
                RIVERS AND            HARBORS-MOBILE,                 ALA.,    DISTRICT               579

  The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                 Documents


Sept. 22,1922   Channel 6 feet deep, 100 feet wide, and approxi-      H. Doc. No. 111, 67th Cong., 1st sess.
                 mately 10,700 feet long, extending from near the
                 mouth of La Grange Bayou to the mouth of
                 Four Mile Creek; no work was done under
                 this authorization.
Aug. 30,1935    Modified the required local cooperation and pro-      Rivers and Rarbors Committee Doe.
                 vided for the present channel dimensions, and         No. 49, 74th Cong., 1st sess. (Con-
                 the extension of the project to Freeport, Fla.        tains the latest published map.)



   Local cooperation.-Fullycomplied with.
   Termninal facilities.-Consist of small wharves and landings for
small craft. There are also privately owned storage tanks for petro-
leum products and molasses at Freeport, Fla. These facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year.-The U. S. hydraulic
pipe-line dredge Blackwater, operating in the channel from April 6
to 18, 1944, removed 81,556 cubic yards of material. The cost was
$11,329.62 for maintenance. The expenditures were $11,269.62.
   Condition at end of fiscal year.-The existing project was completed
in 1937. The controlling depth at the end of the fiscal year was 9 feet.
The total cost under the existing project was $81,894.92, of which
$64,150.62 was for new work, and $17,744.30 for maintenance. The
expenditures were $81,834.92.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $730.38, will be applied as follows:
Accounts payable June 30, 1944 -------------------------------- $60. 00
Investigating reports of shoals and other obstructions and making routine
  examinations to determine available depths in the channel---- ------ 670. 38
        Total      ------------------------------------------------                               730. 38
  The sum of $25,000 can be profitably expended during the fiscal year
1946 for maintenance dredging, removing shoals with a United States
hydraulic pipe-line dredge for about 1 month.
                                    Cost and financial summary
Cost of new work to June 30, 1944------------------------------$64,                               150. 62
Cost of maintenance to June 30, 1944-------------------------19,                                  905. 10
      Total cost of permanent work to June 30, 1944-------------84, 055./72
Minus accounts payable June 30, 1944---------------------------60.       00
      Net total expenditures---------------------------------83, 995. 72
Unexpended balance June 30, 1944-----------------------------    730. 38
        Total amount appropriated to June 30, 1944---------                          -----    84, 726. 10
580            REPORT OF CHIEF OF ENGINEERS, U.                                  S.   ARMY,         1944


    Fiscal year ending June 30              1940          1941            1942               1943          1944
Cost of new work__.
Cost of maintenance--------------------                ----------        $6,414. 68-------------11,           329. 62
Total expended----------.--------------------------6,414.68                            -------------       11,269.62
Allotted.....-------------------------.
                             .                     .    $10,000     --------------- $3, 585.32             12, 000.00


Amount allotted from First Deficiency Act approved Apr. 1, 1941L                                       $12, 000. 00
Gross amount expended-------------                     -----                                            11, 269. 62
       Balance unexpended June 30, 1944------------------------                                            730. 38
Outstanding liabilities June 30, 1944_-- -----------                                                        60. 00
           Balance available June 30, 1944_--                       ----------                             670. 38

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance '--------------------.-------------25,                                           000. 00
  1 Exclusive of available funds.

         11. EAST PASS CHANNEL FROM THE GULF OF MEXICO INTO
                      CHOCTAWHATCHEE BAY, FLA.

  Location.-This is the entrance from the Gulf of Mexico into Choc-
tawhatchee Bay at the eastern end of Santa Rosa Island. It is 41
miles east from the west pass entrance into Pensacola Bay and 49
miles west from the new entrance to St. Andrews Bay. (See U. S.
Coast and Geodetic Survey Chart No. 185.)
   Existing project.-This provides for the maintenance of a channel
not less than 6 feet deep and 100 feet wide from Choctawhatchee Bay
into the Gulf of Mexico, at an estimated annual cost of $600. The
mean range of tide is 1.3 feet. The extreme range, except during
storms, is 2.5 feet. The project was adopted by the River and Harbor
Act approved July 3, 1930 (H. Doc. No. 209, 70th Cong., 1st sess.).
There is no published map of the locality.
   Terminal facilities.-The small privately owned pile and timber
wharves used in connection with the fishing industry in this locality
are considered adequate for existing commerce.
   Operationsand results during fiscal year.-None.
  Condition at end of fiscal year.-The new (natural) East Pass Chan-
nel to the Gulf is 100 feet wide, with a controlling depth of 6 feet.
The total cost and expenditures under the existing project were
$31,071.56 for maintenance.
  Proposed operations.-No funds are available.
   The sum of $12,000 can be profitably expended during the fiscal
year 1946, for maintenance dredging, removing shoals, with a hy-
draulic pipe-line dredge, for about one-half month.
                                          Cost and financial summary
Cost of new work to June 30, 1944_.._
Cost of maintenance to June 30, 1944------------------------                                          $31, 071. 56
       Total cost of permanent work to June 30, 1944-------------                                       31, 071. 56
Net total expenditures_ ____------            ---------                                                 31, 071. 56
Total amount appropriated to June 30, 1944-     -------                                                 31, 071. 56
                     RIVERS            AND HARBORS-MOBILE,                                         ALA., DISTRICT                            581

       Fiscal year ending June 30                      1940                1941                    1942                1943               1944

Cost of new work--------....----..........                         ......----........---..---.-----...
                                               ........---------.------                                     -....----------------------
Cost of maintenance-------.......            ....
                                           ----------------------------                        $7,358.49---------------------
Total expended......----------------------........... ----                                      7, 358.49---------------
                                                                              .....--------------.
Allotted-                   -      ...-----.-.
                  . . . ..------..---.                                - $13,500                -            . -$6,141.51 .
Amount that can be profitably expended in fiscal year ending June 30,
       1946, for maintenance__ -----------------------------------                                                                  $12, 000. 00
                                           12. PENSACOLA HARBOR, FLA.
  Location.-This harbor is a landlocked bay on the coast of north-
west Florida, about 91 miles by water east of Mobile Harbor. (See
U. S. Coast and Geodetic Survey Chart No. 186.)
   Previous projects.-Authorized by the River and Harbor Act ap-
proved June 18, 1878, amended and modified by acts of August 18,
1894, and March 3, 1899. Work under existing project was begun in
1903. For further details see page 1835, Annual Report for 1915, and
page 714, Annual Report for 1938.
  Existing project.-This provides for an entrance channel 32 feet
deep at mean low water and 500 feet wide from the Gulf of Mexico
to deep water in Pensacola Bay, and an inner harbor channel parallel
to the pierhead line and not less than 50 feet therefrom, 500 feet wide
and 30 feet deep, with approach channels 250 feet wide and 30 feet
deep at each end of the inner harbor channel and an approach chan-
nel 250 feet wide and 30 feet deep to the pierhead line south of the
Muscogee wharf; for a channel 100 feet wide and 15 feet deep from
that depth in Pensacola Bay to the mouth of Bayou Chico, thence
75 feet wide, 14 feet deep, and 5,800 feet long in the bayou, terminat-
ing in a basin 14 feet deep and 500 feet square; and also provides
that $150,000 may be used in constructing or purchasing a seagoing
suction dredge. The mean range of tide throughout the harbor is
approximately 1.4 feet near the entrance and about 2 feet at the head
of the bay. The extreme tidal range, except during storms, is about
3 feet.
  The estimated cost of new work, revised in 1937, was $511,900. The
latest (1937) approved estimate for annual cost of maintenance is
$48,500.
   The existing project was authorized by the following river and
harbor acts:

         Acts                                Work authorized                                                         Documents


June 13,1902  A channel 30 feet deep at mean low water and 500 Specified in act.
               feet wide from the Gulf of Mexico to the dock
               line at the east end of the city of Pensacola, and
               also provided that $150,000 may be used in con-
               structing or purchasing a seagoing suction
               dredge.
Aug. 30,19351 Modified the existing project to provide for the H. Doc. No. 253, 72d Cong., 1st sess.s
                present inner channels and the deepening of the
               entrance channel to 32 feet.
Aug. 26,1937 Improvement of Bayou Chico-------- ------- Rivers and Harbors Committee Doc.
                                                                                                    No. 96, 74th Cong., 2d sess.'


   I   Public   Worsks   Administration,       Sept.    6,    1933.                             2Contains      the   latest   published   maps.
582         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                            1944

  Recommended modifications ofproject.--Modification of the exist-
ing project was recommended by the Chief of Engineers in a report
requested by Rivers and Harbors Committee resolution adopted June
10, 1941, and transmitted to Congress by the Secretary of War July
31, 1943.
  Local cooperation.-Fullycomplied with.
   Terminal facilities.-The modern rail-connected terminal facilities
at Pensacola are considered adequate for existing commerce. (See
Port Series No. 3, pt. 2, revised 1937, Corps of Engineers.)
   Operations and results during fiscal year.-The U. S. hydraulic
pipe-line dredge Blackwater,operating in the Bayou Chico inner chan-
nel from March 1 to-16, 1944, removed 72,308 cubic yards of material
at a cost of $11,186.77. The cost for miscellaneous investigations and
surveys was $1,561.13. The total cost was $12,747.90, for mainte-
nance. The expenditures were $12,741.34.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depths at the end of the fiscal year were as
follows: Entrance channel, 31 feet; inner harbor and approach chan-
nels to Frisco Railroad pier No. 2, 30 feet; approach channels to
Tarragona St. pier of L. & N. Railroad and Muscogee wharf, 29 feet;
Bayou Chico inner channel, 13.5 feet and outer channel 15 feet.
   The total costs and expenditures to the existing project to June 30,
1944, were as follows:

                                                                    Costs
                                                                                                      Expenditures
                                              New work          Maintenance            Total

Regular funds_----.------..-..-.-.      --- $378, 361.21           $938, 428. 23   $1, 316, 789. 44    $1,316, 782. 88
Public Works funds -------------------       119, 672. 91-119,                              672. 91        119, 672.91
      Total-..---..             -. -...      498, 034. 12           938, 428. 23    1, 436, 462. 35     1, 436, 455.79



   Proposed operations.-The balance unexpended at the end of the
fiscal year, $18,575.92, will be applied as follows:
Accounts payable June 30, 1944---------------------------------            $6. 56
Maintenance dredging, removing shoals to restore project dimensions
in the entrance and inner channels with U. S. seagoing hopper dredge
Benyaurd, for about 1' month during the fiscal year--------- ---     18, 569. 36
         Total           ---------------------------------------------                                 18, 575. 92
   The additional sum of $85,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging, removing shoals, to
restore project dimensions in the entrance and inner channels, with a
United States hopper dredge, for about 21/ months.
                                     Cost and financial summary
Cost of new work to June 30, 1944 ------------------------ $1, 092, 722. 67
Cost of maintenance to June 30, 1944-----------------------1, 065, 077. 89
      Total cost of permanent work to June 30, 1944 ----------                                    2, 157, 800. 56
Minus accounts payable June 30, 1944-----------------------                                                 6. 56
      Net total expenditures    -2,                                                                  157, 794. 00
Unexpended balance June 30, 1944---                                                                    18, 575. 92
         Total amount appropriated to June 30, 1944- --------                                     2, 176, 369. 92
                         RIVERS AND         HARBORS-MOBILE,                       ALA.,        DISTRICT                 583

     Fiscal year ending June 30               1940              1941              1942               1943            1944

Cost of new work-----------------------------------------------------
Cost of maintenance-----------              $43, 765. 09     $15, 438. 50       $35,118.56             $88.87      $12, 747.90

Total expended...........---------------.    47, 655. 68       14, 645. 88       35, 892. 62           107. 43       12, 741.34

Allotted ..................                  43, 955.09        1, 303.48         25, 000.00         15,000.00      -10,000.00


Balance unexpended July 1, 1943_-      - ---------                                                          -$41,   317. 26
Deductions on account of revocation of allotment-----------                                      ---            10, 000. 00
       Net amount to be accounted for-                                                                           31, 317. 26
Gross amount expended_ __----------$12,                                                    889.35
Less reimbursements collected------------------                                            148. 01
                                                                                                                 12, 741. 34
       Balance unexpended June 30, 1944                             ----------------------                       18, 575. 92
Outstanding liabilities June 30, 1944-                                                                                 6. 56
              Balance available June 30, 1944_-                         -----                  __                18, 569. 36
Amount that can be profitably expended in fiscal year ending June
     30, 1946, for maintenance 1               -                                 -____-_                         85, 000. 00
   1 Exclusive of available funds.

                               -   13. BLACKWATER RIVER, FLA.

   Location.-This river rises in the south-central part of the State of
Alabama and flows in a southwesterly direction for a distance of 75
miles through the States of Alabama and Florida, emptying into
Blackwater Bay, an arm of Pensacola Bay. (See U. S. Coast and
Geodetic Survey Chart No. 186.)
   Previous projects.-Adopted by the River and Harbor Act of March
3, 1899. Work under existing project was begun in 1906. For further
details see page 1834, Annual Report for 1915, and page 717, Annual
Report for 1938.
   Existing project.-This provides for a channel 9 feet deep at mean
low water and 100 feet wide from the mouth to Milton, a distance of
10 miles, to be secured by dredging at necessary points. The river is
tidal throughout the portion under improvement. The mean range
of tide is 2 feet, and the extreme range, except during storms, is 3
feet.
   The estimated cost of new work made in 1902, exclusive of amount
expended on previous project, was $15,000. The latest (1928) ap-
proved estimate of annual cost of maintenance is $5,000. The exist-
ing project was authorized by the River and Harbor Act of March
3, 1905 (H. Doc. No. 193, 58th Cong., 2d sess.). There is no map of
the Blackwater River published in any congressional document or
annual report.
   Terminal facilities.-There is a privately owned pile and timber
wharf at Bagdad, extending to 16 feet of water. This facility is
considered adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1916. The controlling depth at the end of the fiscal year
was 9 feet. The total costs and expenditures were $142,732.68, of
which $36,649.90 was for new work, and $106,082.78 for maintenance.
584            REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,                 1944
  Proposed operations.-Nofunds are available and no operations are
contemplated during the fiscal year 1945.
  The sum of $4,000 can be profitably expended during the fiscal year
1946, for maintenance dredging to remove shell reefs by the operation
of a United States hydraulic pipe-line dredge for a period of about
one-fifth month.
                                            Cost and financial summary
Cost of new work to June 30, 1944-----------------------------                                                    $41, 649. 90
Cost of maintenance to June 30, 1944-------------------------                                                     106, 082. 78
      Total cost of permanent work to June 30, 1944-  _    -                                                      147, 732. 68
Net total expenditures_------------------------------                                                             147, 732. 68
Total amount appropriated to June 30, 1944------------- -----                                                     147, 732. 68

    Fiscal year ending June 30                 1940           1941                   1942                  1943              1944

Cost of new work.                  --...

                  ............--
Cost of maintenance-----------                $9, 310.90    $10, 658. 19-
Total expended__
               -----------------               9, 310.90     10, 658. 19

          ....
Allotted --------------- -------              14, 511. 24   -4, 542.15      ......          ..   .......           .......


Amount that can be profitably expended in fiscal year ending June
                                      ---------
30, 1946, for maintenance_ _____________--                                                                        $4, 000. 00

                                           14. MOBILE HARBOR,                        ALA.
  Location.-This harbor, located along the lower 5 miles of Mobile
River, is in the southwestern part of the State of Alabama, 91 miles
by water from Pensacola Harbor, Fla., on the east and 90 fiiles from
Gulfport Harbor, Miss., and 144 miles from the mouth of the Missis-
sippi River on the west. (See U. S. Coast and Geodetic Survey Charts
Nos. 1266 and 1267.)
  Previous projects.-The original project for the bar channel was
adopted by River and Harbor Act of June 13, 1902. The original
project for the bay and river channels was adopted by River and
Harbor Act of May 20, 1826, and subsequent projects adopted by River
and Harbor Acts of July 11, 1870, March 3, 1879, August 11, 1888,
March 3, 1899, June 25, 1910, and August 8, 1917. For further details
see page 1840 of Annual Report for 1915, pages 802 and 807 of Annual
Report for 1916, page 833 of Annual Report for 1929, and page 718
of Annual Report for 1938.
  Existing project.-This provides for a channel across Mobile Bar
36 feet deep and 450 feet wide, and about 1.5 miles long, connecting
the 36-foot contours south and north of the bar; for a channel 32 feet
deep and 300 feet wide from deep water in Mobile Bay to a point
at the north edge of the proposed quarantine anchorage basin; for
a channel 32 feet deep and 350 feet wide from the north edge of the
quarantine anchorage basin to the mouth of Mobile River; for an
anchorage basin 32 feet deep extending 1,000 feet south from the north
edge of the present pier of the Mobile quarantine station and 200 feet
west of the west edge of the dredged channel in Mobile Bay; and for a
channel 32 feet deep, with a width of 500 feet, from the mouth of
Mobile River to the highway bridge across Mobile River about 1,000
feet below the mouth of Chickasaw Creek, for easing the bends at the
mouth and about 3,000 feet above the mouth, for the removal of sunken
                   RIVERS AND HARBORS-MOBILE,                         ALA., DISTRICT                   585

obstructions and for snagging in Three Mile Creek from Mobile River
to the Industrial Canal, a distance of 0.8 mile; and a channel 125 feet
wide from the Mobile River channel at its mouth, through Garrows
Bend, to and including a turning basin 800 feet long and 250 feet wide,
and from this point a channel contineiing through Garrows Bend at a
width of 125 feet to and including a turning basin 800 feet long and 600
feet wide, all 27 feet deep. The plane of reference is mean low water.
Under ordinary conditions the mean tidal range at the lower end of
the improvement is 1.1 feet and at the upper end 1.4 feet, and the
extreme tidal range is 3.4 feet at the lower end and 3.6 feet at the
upper end.
  The estimate of cost for new work revised in 1941 was $730,000,
exclusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $399,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                  Documents 1


July     3, 1930   Present project dimensions across the bar and to   Rivers and Harbors Committee Doc.
                    the mouth of Mobile River, thence 32 feet deep      No. 26, 71st Cong., 2d sess.
                and 300 feet wide to the highway bridge; and for
                the anchorage basin.
Aug. 26, 1937 For improvement of Three Mile Creek by snag-            Rivers and Harbors      Committee Doc.
                ging from Mobile River to the industrial canal.         No. 69, 74th Cong.,   1st sess.
    Do..__._  To provide a 500-foot channel 32 feet deep from a       Rivers and Harbors      Committee Doc.
               point about 5,000 feet south of the mouth of             No. 44, 75th Cong.,   1st sess.
                Three Mile Creek to the highway bridge across
                Mobile River, subject to the provision that no
               dredging be performed within 50 feet of any pier-
               head line.
Oct. 17, 1940 To provide a channel 27 feet deep and 125 feet          H. Doc. No. 221, 76th Cong., 1st sess.
               wide from the Mobile River channel at its
               mouth through Garrows Bend, to and includ-
               ing a turning basin of the same depth, 800 feet
               long and 250 feet wide.
    Do ...-.. Further modified to provide for extension of the        H. Doc. No. 282, 76th Cong., 1st sess.
                    channel through Garrows Bend 27 feet deep
                    and 125 feet wide, to and including a turning
                    basin of the same depth, 800 feet long and 600
                    feet wide.


1 Contain latest published maps.


  Recommended                modifications
                                 of project.-Modification of the exist-
ing project was recommended by the Chief of Engineers in a report
requested by Rivers and Harbors Committee resolution adopted June
20, 1941, and transmitted to Congress by the Secretary of War June
12, 1943.
  Local cooperation.-Fully complied with.
  Terminal facilities.-The modern rail-connected terminal facilities
at this port are considered adequate for existing commerce. (See
Port Series No. 3, pt. 1, revised 1937, Corps of Engineers.)
  Since the revision of the Port Series No. 3, part 1, Report in 1937,
three additional berthing spaces for deep-sea vessels have been pro-
vided at the Alabama State Docks and Terminals by the dredging
of a slip and the construction of a concrete-pile wharf with adequate
586          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                          1944

trackage and transit sheds at the north side of pier C. There has also
been constructed and placed in operation as an addition to the bulk
material handling plant at the Alabama State Docks and Terminals,
a large fertilizer warehouse with bulk material conveying equipment
to shipside.
   Operations and results during fiscal year.-The contractor, oper-
ating in the Mobile Bay Channel with pipe-line dredge Diesel from
July 4 to August 19 and August 31 to October 31, 1943, removed
4,816,385 cubic yards of material at a cost of $184,086.99. The con-
tractor, operating in the Mobile River Channel with pipe-line dredge
Ventnor from June 22 to 25, 1944, removed 28,000 cubic yards of mate-
rial at a cost of $5,827.17.    The U. S. hydraulic pipe-line dredge
Wahalak, operating in the Mobile Bay Channel from April 7 to June
30, 1944 removed 2,662,241 cubic yards of material at a cost of
$86,834.78. The U. S. derrick boat J. M. Pratt,operating in Mobile
River from July 1 to October 12, 1943, and April 1 to 3 and 19 to 30,
and May 1 to 2 and 22 to 28, 1944, removed 1,918 snags; and in Three
Mile Creek from February 26 to March 31 and May 29 to 31, 1944,
removed 799 snaps, at a cost of $33.977.58. The cost of miscellaneous
investigations and surveys was $9,039.89. Under authority of sec-
tion 3 of the River and Harbor Act of October 17, 1940, the contrac-
tor's pipe-line dredge Frederick, from May 14 to June 30, 1944, com-
pleted 90 percent of the additional work of enlarging a small-boat
basin at Fort Gaines, Dauphin Island, Mobile Bay, Ala. The total
cost was $319,766.41 for maintenance. The expenditures were
$335,624.29.
   Condition at end of fiscal year.-The existing project was completed
in 1941. The controlling depths at the end of the fiscal year were as
follows: Outer Bar Channel, 35.5 feet; Mobile Bay Channel, 31.5 feet;
Mobile River Channel, 26.5 feet; Garrows Bend Channel, 26.5 feet.
Included in the total cost of maintenance are items of $997.20 used
in dredging in the channel extending from the east of Arlington pier
to the main ship channel in Mobile Bay, and $777.59 for removing
obstructions in Conway Creek, Ala., under section 3 of the River and
Harbor Act of July 3, 1930; and items of $1,053.58 for removing ob-
structions in Blakely River, Ala., $2,918.12 for dredging access channel
from Mobile Bay Channel into dumping ground south of Pinto Island,
Ala., and $3,000 for enlargement of a small-boat basin at Fort Gaines,
Dauphin Island, Mobile Bay, Ala., under section 3 of the River and
Harbor Act of October 17, 1940.
   The total cost and expenditures on the existing project to June 30,
1944, were as follows:

                                                                                  Costs
                                                                                                                      Expenditures
                                                          New work           Maintenance               Total


Regular funds ...............                                $723, 924. 72
                                             ....----------------------           $3,188,157. 38   $3, 912, u82. 10    $2, 960,436.11
Public Works funds-- .....---     _ _.                           14, 000.00 ----------------            14, 000.00          14,000.00

      Total--_         ,..----   .-----.-.          ---    737, 924. 72        3,188,157. 38        3, 926, 082.10      2, 974,436.11


   Proposed operations.-The balance unexpended at the end of the
fiscal year, including an allotment of $290,500 made during July 1944,
will be applied as follows:
                   RIVERS AND HARBORS-MOBILE,                                        ALA.,        DISTRICT                        587
Accounts payable June 30, 1944                   - -       -                                                            $2, 918. 75
Maintenance dredging to restore project dimensions in
  the Mobile Outer Bar Channel, with U. S. seagoing
  hopper dredge Benyaurd, for about 1/ months dur-
  ing May and June 1945------------------------        $45,      00                                     000.00.
Maintenance dredging, by contract, to restore project
  dimensions in the Mobile River Channel from the
  mouth of Mobile River to deep water in the lower
  end of Mobile Bay, and in Garrows Bend Channel
  and turning basins, about 9 months during the fiscal
  year 1945_ -----------------------------------       481, 697. 07
Maintenance dredging, by contract, to complete en-
  largement of a small-boat basin at Dauphin Island,
  Mobile Bay, Ala., about Y month during July 1944 _- 3, 000. 00
Maintenance snagging in Mobile River with U. S. der-
  rick boat J. M. Pratt, about July to September 1944,
  April to June 1945-----------------------------       38, 500. 00
Maintenance snagging in Three Mile Creek with U. S.
  derrick boat J. M. Pratt about 1' months during
  October and November 1944 ---------------------
                                           _             8, 000. 00
                                                                                                                       576, 197. '07
          Total        --------------------------------------------                                                    579, 115. 82
  The additional sum of $350,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance dredging to restore project dimensions in the Mobile
Outer Bar Channel, with a United States seagoing hopper dredge,
for about 1% months________                                           $45, 000
Maintenace dredging, by contract, to restore project dimensions in the
Mobile River Channel from the mouth of Mobile River to deep water
in the lower end of Mobile Bay, about 7 months- ....                  260, 000
Maintenance snagging in Mobile River with U. S. derrick boat J. M.
Pratt, about 6 months_-                 __ -_             -37,             000
Maintenance snagging in Three Mile Creek with U. S. derrick boat
J. M. Pratt, about 1% months---------------------------------           8, 000

          Total_ -----------------------------------------------                                                              350, 000

                                                Cost and financial summary
Cost of new work to June 30, 1944 ------------------------
Cost of maintenance to June 30, 1944-      -_
       Total cost of permanent work to June 30, 1944 --
                                                               $7,421,029.40
                                                                            ____________
                                                           _---7, 284, 838. 49
                                                                                                   --      -14,        705, 867. 89
Plus accounts receivable June 30, 1944_--     --------                                                                  10, 733. 56

      Gross total costs to June 30, 1944_- ----------------                                                       14, 716, 601. 45
Minus accounts payable June 30, 1944_-------                                                               ---          2, 918. 75
      Net total expenditures---        ----------                                                                 14, 713, 682. 70
Unexpended balance June 30, 1944_--------                                                         ---                 277, 882. 26
          Total amount appropriated to June 30, 1944-----------                                                   14, 991, 564. 96


    Fiscal year ending June 30                       1940            1941            1942                  1943                1944

Cost of new work ----- ..        ..               ...........      $62, 109. 68   $103, 374. 16         --.-              -        ..    .
Cost of maintenance ......------------          $222, 595. 45      381, 710.16     121,945. 85     $271,309.28            $319, 766.41

       Total cost....                                222, 595.45
                                  .....----------------            443, 819.84     225, 320.01          271, 309. 28          319, 766.41

Total expended--_         ------        _ -250,          544. 33   406, 563. 77    253, 559. 32         271, 880. 91          335, 624. 29

             ...
Allotted_ _ _...     -- ..-----            -      298, 597.94      439, 947. 52    274, 271. 70         325, 500. 00          108, 600. 00
588        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

Balance unexpended July 1, 1943_                           _            $504, 906. 55
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942------------  $3, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943 ------------ 177, 100. 00
                                                                         180, 100. 00
      Amount to be accounted for                            __ __        685, 006. 55
Deductions on account of revocation of allotment-----   ---------         71, 500. 00
       Net amount to be accounted for-   -              -___ _           613, 506. 55
Gross amount expended    ----------------------     $336, 400.48
Less reimbursements collected--------------------         776. 19
                                                                         335, 624. 29
       Balance unexpended June 30, 1944---277,                                882. 26
Outstanding liabilities June 30, 1944___2,                                    918. 75
      Balance available June 30, 1944_                      __           274, 963. 51
Accounts receivable June 30, 1944_                                        10, 733. 56
     Unobligated balance available June 30, 1944------------ 285, 697. 07
Amount allotted in July 1944-------------------------------290, 500. 00

Amount available during fiscal year 1945---------------------            576, 197. 07
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1- - - - - - - - - -          -   - - -
                                                            -       -
                                                                         350, 000. 00
1 Exclusive ofavailable funds.


      15. REMOVING THE WATER HYACINTH, MOBILE RIVER, ALA.,
                          TRIBUTARIES

   Location.-The water hyacinth is a floating aquatic plant which
infests numerous fresh-water streams tributary to the south Atlantic
and Gulf coasts. It propagates from the seeds and suckers, spreads
quickly in most localities, and may cause entire suspension of naviga-
tion if not removed.
   Existing project.-This provides for the extermination or removal
of plants from the navigable waters of the States of Florida, Alabama,
Mississippi, Louisiana, and Texas so far as they are or may become
an obstruction to navigation by any mechanical, chemical, or other
means whatsoever; for the construction and operation of boats equipped
with suitable machinery for such removal; and for the construction
and operation of log booms to prevent the drifting of plants from one
stream to another.
   The estimated cost made in 1899 was $25,000 each for two boats,
$10,000 for operation in each district, and $1,000 for the establishment
of booms. The latest (1939) approved estimate for annual cost of
maintenance is $25,000.
                RIVERS        AND HARBORS-MOBILE,                   ALA.,    DISTRICT             589
  The existing project was authorized by the following river and
harbor acts:

    Acts                          Work authorized                               Documents


Mar." 3,1899    Appropriations made for the States of Florida and   H. Doc. No. 91, 55th Cong., 3d sess.
                 Louisiana and provided for the extermination or
                 removal of pants, the building of boats, and
                 the establishment of hooms.
June 13,1902    Use of any mechanical, chemical, or other means
                 whatsoever.
Mar. 3,1905     Appropriation made available for the State of
                 Texas.
  Do-_.         Appropriations made for Florida, provided that
Mar. 2,1897      no chemical process inj.ious to cattle shall be
                Iused.
July 25,1912    Appropriation made available for the State of
                 Mississippi, 'and also made available for use in
                 that State the 'perating plant pertaining to the
                 work in Louisiana.
July 27, 1916   Appropriatianmade      availablefor the State of
                1,
                  Alabamna.   .




    Terminal facilities.-None.
    Operations and results during fiscal year.--Operationswith United
States plant and hired labor were carried on in Three Mile Creek,
Briar Creek, Bayou Canot, and Little Bayou Canot, Ala., 634,000
square yards of hyacinths being sprayed and removed from July 1,
1943, to May 6, 1944. The cost and expenditures were $22,299.70 for
maintenance.
    Condition at end of fiscal year.-The existing project is for mainte-
nance. The total cost and expenditures were $254,824.07.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, plus $22,000 allotted in July 1944, a total of $22,101.55, will
be applied to the operation of two United States spraying plants and
one United States hyacinth conveyor on the spraying and removal of
hyacinths and other aquatic growths, by mechanical methods, during
the fiscal year in the navigable waterways of the Mobile, Ala., district.
    The additional sum of $25,000 can be profitably expended during
the fiscal year 1946 for maintenance by the operation of two United
States spraying plants and one United States hyacinth conveyor on
the spraying and removal of hyacinths-and other aquatic growths, by
mechanical methods, in the navigable waterways of the Mobile, Ala.,
district.
                                     Cost and financial summary
Cost of new work to June 30, 1944.__..._
Cost of maintenance to June 30, 1944__-------------------                               $254, 824. 07
        Total cost of permanent work to June 30, 1944-------                             254, 824. 07
Net total expenditures _ _ -      - .... . ......                                        254, 824. 07
Unexpended balance June 30, 1944_ _---------                                  ------          101. 55.

        Total amount appropriated to June 30, 1944 --------------- 254, 925. 62:
590           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                      1944


   Fiscal year ending June 30            1940           1941           1942           1943             1944

Cost of new work---------------                  ----------------------------                  --------------
Cost of maintenance_-_..........       $23, 781.18    $20, 387.32    $22,165.09     $10,451.58        $22,299.70

Total expended----------------26, 643. 86              20, 029. 07    22, 906. 09    10, 135. 91       22, 299.70

Allotted----------------------20, 000. 00              19, 041.81     18, 000. 00 --------------       16, 000.00


Balance unexpended July 1, 1943_                                                                   $6, 401. 25
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940_                                                                          16, 000. 00
       Amount to be accounted for-----------------                                                 22, 401. 25
Gross amount expended__---      ------------                                                       22, 299. 70
     Balance unexpended June 30, 1944___                                                               101. 55
Amount allotted in July 1944                                                                       22, 000. 00
          Amount available during fiscal year 1945 -----------------                               22, 101. 55
Amount that can be profitably expended in fiscal year ending June
                            i
30, 1946, for maintenance 1-----   - __ _____
                                           -__-_     -_   --                                       25, 000. 00
  1 Exclusive of available funds.

                                   16. CHICKASAW CREEK, ALA.

  Location.-Chickasaw Creek is a small waterway, about 40 miles in
length, entering Mobile River about 5 miles above the mouth.
  Existing project.-This provides for improvement by snagging and
by dredging a channel 18 feet deep and 150 feet wide from the mouth
to Chickasaw slips, about 21/ miles above the mouth.
   The estimate of cost for new work, made in 1933, was $42,000, with
$3,000 annually for maintenance.
  The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                 Documents


May 28, 19351 Existing project authorized-
Aug. 30,1935 Project adopted by Congress...      -----------------    H. Doc. No. 47, 73d Cong., 1st sess.s

  1   Emergency Relief Act of 1935.
  2 Contains  latest published map.

    Recommended modifications of project.-Reported under the proj-
ect for Mobile Harbor, Ala.
    Local cooperation.-Fullycomplied with.
    Terminal facilities.-The terminal of the Warrior-and Gulf Navi-
gation Co. is located on Chickasaw Creek about 11/2 miles above its
mouth. The Southern Kraft Corporation owns a terminal on Hog
Bayou, which is used for unloading pulpwood from barges. There
are several other smaller privately owned wharves of pile and timber
construction used in connection with the lumber mills and other indus-
tries located on this stream. These terminals are considered adequate
for existing commerce.
                 RIVERS AND HARBORS-MOBILE,                                               ALA., DISTRICT                           591
   Operations and results during fiscal year.-None. The cost and
expenditures were $477 for miscellaneous investigations, charged to
maintenance.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1935. The controlling depth at the end of the fiscal year
was 18 feet.
   The total costs and expenditures on the existing project to June 30
1944, were $41,241.64 Emergency Relief funds for new work, and
$51,995.82 regular funds for maintenance, a total of $93,237.46.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, including an allotment of $10,000 made during July 1944,
will be applied as follows:
Maintenance dredging to restore project dimensions with the U. S.
derrick boat J. M. Pratt, for about / month during January 1945 $3, 000. 00
Maintenance snagging with the U. S. derrick boat J. M. Pratt, about
2 months during November and December 1944                     _   14, 308. 29        -----------
         Total_           --------------------------------------                                                            17, 308. 29
   The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance dredging to restore project dimensions with a hydraulic
pipe-line dredge, for about 1 month      .                         -  $28, 000
Maintenance snagging with U. S. derrick boat J. M. Pratt, for a period
   of about 2 months_                                    ------------------                                                     12,000

         Total    -        -            -        -            -              -        -         -       -              -        40, 000

                                             Cost and financial summary
Cost of new work to June 30, 1944---     ---------                                                                         $41, 241. 64
Cost of maintenance to June 30, 1944 ---                                                                                    51, 995. 82
         Total cost of permanent work to June 30, 1944-                                                 -                   93, 237. 46

Net total expenditures       ---------------------------                                                                    93, 237. 46
Unexpended balance June 30, 1944 _                                                                                           7,308.29

         Total amount appropriated to June 30, 1944--------                                                                100, 545. 75

   Fiscal year ending June 30                  1940                     1941               1942               1943              1944


Cost ofnew work ..-----------
Cost of maintenance    .....-------------.    $5,033.59            $19, 544.09            $5, 242. 21       $5, 256.79      _          $477

Total expended    .....                          5,033. 59
                               ..------------------                  19, 544.09            5, 306.09          5, 192. 91               477

Allotted ___     ...                            15, 000.00
                       ....-----------------------.                     9, 671.64         18, 000.00        -4, 843. 26     .............



Balance unexpended July 1, 1943- ---                                                                                        $7, 785. 29
Gross amount expended_--        ---                                          --------------                                     477. 00
     BaIa~e unexpended Jiune 30, 1944-_                                               --------                               7, 308. 29
Amount allotted in July 1944_-----------                                                                    ----            10,000. 00
         Amount available during fiscal year 1945                                   -----------------                       17, 308. 29

Amount that can be profitably expended in fiscal year ending June 30,
   1946 for maintenance 1_----                               -------------                                                  40, 000. 00
  1Exclusive of available funds.
592        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

                               17. ALABAMA RIVER, ALA.

   Location.-This river is formed 18 miles above Montgomery, Ala.,
by the junction of the Coosa and Tallapoosa Rivers. From this junc-
tion it flows in a southwesterly direction through the State of Ala-
bama for a distance of 318 miles, and unites about 45 miles north of
the city of Mobile, in the southwestern part of the State, with the
Tombigbee River to form the Mobile River. (See U. S. Geological
Survey charts for central and southwest Alabama.)
   Previous projects. Adopted by River and Harbor Acts of June
18, 1878, and July 13, 1892. Work under existing project was begun
in 1905 For further details, see page 1837, Annual Report for 1915,
and page 725, Annual Report for 1938.
   Existing project.-This provides for securing a channel by open-
channel work not less than 4 feet deep at low water from the mouth
to Wetumpka, Ala., a distance of 331 miles. Under this project,
dredging and construction works were required at various obstructing
shoals, usually consisting of gravel bars distributed over the entire
length of the river. The variation between average high and low
water is 40.4 feet. The extreme variation is 58 feet, at Montgomery.
   The estimate of cost for new work, revised in 1928, is $1,155,000,
exclusive of amount expended on previous projects. The latest (1928)
approved estimate of annual cost of maintenance is $75,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                     Work authorized                                 Documents


Mar. 3, 1905   A channel from the mouth to Montgomery-._....   H. Doc. No. 378, 59th Cong., 1st sess.
June 25,1910   A channel from Montgomery to Wetumpka- ...      H. Doc. No. 1089, 60th Cong., 2d sess.


The latest published map of Alabama River will be found in Annual Report, 1913, p. 2124.

   Recommended modifications of project.-Under date of October 15,
1941, the Chief of Engineers recommended a general comprehensive
project for the initial and ultimate development of the Alabama-
Coosa River and tributaries for navigation, flood control, power de-
velopment, and other purposes be authorized, and that for the initia-
tion and partial accomplishment of the ultimate plan an expenditure
of $60,000,000 be approved for the construction of navigation and
power dams on the Alabama and Coosa Rivers (H. Doc. No. 414, 77th
Cong., 1st sess.; interim report).
   Terminal facilities.-On the east bank at Montgomery there is a
natural landing connecting with the city streets. The Wofford Oil
Co. has a small wharf about 10 miles below Montgomery *equipped
for handling petroleum products.
   There are also various natural landings located along the river.
These facilities are cqnsidered adequate for existing commerce.
   Operations and results during fiscal year.-The U. S. snag boat
R. C. McCalla, operating in the Alabama River from July 1 to 17,
August 9 to September 15, and October 29 to November 13, 1943, and
                 RIVERS AND HARBORS-MOBILE,                                ALA.,     DISTRICT


February 14 to 16, 1944, removed 2,313 obstructions from the channel
at a cost of $21,016.62; and from September 16 to October 28, 1943,
placed 1,040 tons of rock on jetties at Silver Creek Bar, Mrs. Gray's
Bar, and Pigeon Creek Bar, at a cost of $13,874.20. The cost of
miscellaneous investigations and surveys was $110.62. The total cost
was $35,001.44 for maintenance. The expenditures were $41,484.62.
   Condition at end of fiscal year.-The existing project was 62 percent
completed. The channel depth has been improved at the shallowest
bars and shoals between the mouth of the river and Montgomery, Ala.,
by dredging and contraction works; between Montgomery, Ala., and
Wetumpka, Ala., the work has consisted of removing snags. The.
controlling depths at the end of the fiscal year were as follows: Mouth
to Selma, 4 feet; Selma to Montgomery, 3.5 feet; Montgomery to
Wetumpka, 3 feet. Boats drawing 3 feet or less can usually operate
throughout the year. Greater depths are usually available from
November to June each year. Zero readings on the gages at Selma
and Millers Ferry, Ala., indicate that a depth of 4 feet is available
for commerce at those locations. A zero reading on the gage at;
Montgomery, Ala., indicates that a depth of 31/2 feet is available
for navigation. The work remaining to be done to complete the
project from Montgomery, Ala., to mouth is the construction of
approximately 800 linear feet of spur dikes. No work has been done
or is contemplated on the portion of the project from Montgomery
to Wetumpka, Ala. At the end of the fiscal year the channel was in
fair condition only; numerous dikes were badly in need of repair.
   The total cost and expenditures for the existing project to June
30, 1944, were as follows:

                                                                     Costs
                                                                                                      Expenditures
                                                  New work        Maintenance          Total

Regular funds---      -----
                   _---_-_$577,160.68                             $2, 189, 846.12   $2, 767, 006.80    $2, 767, 006.80
Public Works funds _...     _-----139,989.87                                            139,989.87         139,989.87
      Total_-----        -_------------717,150.              55    2,189, 846.12     2, 906, 996.67     2, 906, 996.67



   Proposed operations.-The balance unexpended at the end of the
fiscal year, $7,037.42, will be applied to maintenance between Mont-
gomery, Ala., and the mouth, with U. S. snag boat R. C. McCalla,
about 1 month, August 1945.
   The additional sum of $70,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance (with United States plant and hired labor):-
    Repairs and renewal of contraction works between Montgomery and
      the mouth -------------------------------                     $45, 000
    Snagging between Montgomery, Ala., and the mouth.                20, 000
Dredging between mile 302 and the mouth----------------------5,          000
          Total--.... -----------------------------------------                                             70, 000
  The completion of that portion of the project from Montgomery
to Wetumka, Ala., is not contemplated at the present time as no
commerce exists on that section of the river.

         616634---45--pt. 1, vol. 1-              38
594              REPORT OF CHIEF OF ENGINEERS, U.                                       S. ARMY,             1944

                                                Cast and financial summary
Cost of new work to June 30, 1944___                                                                         $1, 117, 571. 12
Cost of maintenance to June 30, 1944--------------------                                           -           2, 208, 871. 24

            Total cost of permanent work to June 30, 1944-------                                              3, 326, 442. 36
Net total expenditures -----------------------------------                                                    3, 326, 442. 36
Unexpended balance June 30, 1944_ ----------            -                                                     -7,     037. 42
            Total amount appropriated to June 30, 1944                              ------------              3, 333, 479. 78

    Fiscal year ending June 30                         1940           1941           1942             1943            1944

Cost of new work--- .......                     -..     $555.41
Cost of maintenance._ _ _ _ _. ..                     53, 395. 56   $50,656. 66    $49,185. 24    $51, 619. 24       $35, 001.44

        Total cost-...............                    53, 950.97     50, 656. 66    49, 185. 24    51,619. 24         35,001.44

Total expended..----------------.............         56, 374.82     49, 753.71     48,827. 31     45, 532. 25        41,484. 62,
Allotted.-.--.---.------.-..                    -- 55, 354. 66       51, 474. 63    52, 000. 00    35, 000. 00 ..

Balance unexpended July 1, 1943 ----------------------------                                                     $48, 522. 04
Gross amount expended_ ----------------------- $41, 490. 74
Less reimbursements collected -------------------.      6. 12
                                                                                                                  41, 484. 62

            Balance unexpended June 30, 144                                                                         7, 037. 42

Amount (estimated) required to be appropriated for completion
of existing project 1 _-    --     __-_437,                                                                          800. 00
Amount that can be profitably expended in fiscal year ending
   June 30, 1946, for maintenance 1______-------_                                            _    .               70, 000. 00
  I Exclusive of available funds.
                                        18. COOSA RIVER, GA. AND ALA.
   Location.-The Coosa River is formed at Rome, Ga., in the north-
west part of the State of Georgia, by the junction of the Oostanaula
and Etowah Rivers, which have their sources in northern Georgia.
From Rome the Coosa River flows in a southwesterly direction
through Georgia and Alabama for a distance of 286 miles and unites
with the Tallapoosa River to form the Alabama River near Mont-
gomery, Ala., at about the center of the State. (See U. S. Geological
Survey charts for northeast Alabama and northwest Georgia.)
   Previous projects.-The River and Harbor Act of August 14, 1876,
adopted the original project, which was modified by the River and
Harbor Act of September 19, 1890. Work under the existing project
was begun in 1877. For further details of previous projects see page
1837 of Annual Report for 1915, and page 728 of Annual Report for
1938.
   Existing project.-This provides for securing from dam No. 5, Ala-
bama, to Rome, Ga., a channel 4 feet deep at extreme low water and
100 feet wide, to be obtained by open-channel work and the con-
struction of locks and dams-one dam without a lock and four locks
and dams located between a point 7 miles below Riverside, Ala., and
Greensport, Ala., and one lock and dam located at Mayos Bar, 7.5
miles below Rome, Ga. The length of the section included in the
project is 169 miles, the lower end being 117 miles above the mouth
of the river. The project also provides for operating and care of
all locks and dams. Certain data relative to the Coosa River dams
are given in the following table:
                                                                           Available depth
                                                   Dimensions of locks     over miter sills
                                                                             at low water
                                       Miles                                                                                                              Year   Year of
Locks and     Location with refer-    from                                                    Character of founda.   Kind of     Type of construct   opened
   dams        ence to nearest town   mouth       Great-                                                tion            lam       Type ofconstruction to nay- comple-          Cost
                                      of river      est  Clear                                                                                 .      igation tion
                                                  avail-width     Lift     Upper      Lower
                                                   able
                                                 length

                                               Feet  Feet         Feet     Feet   Feet
Lock 31 (15).. Wetumpka, Ala_.-_.         11     280    52        14. 70    8. 00  8.00 Oneiss- - --.........-....
                                                                                                               ---------- _______-_-_--........                    (1)     2$228, 511.00
Dam 5-.......  Gadsden, Ala., 58         117- .........                  .......--..- . Disintegrated chert Fixed_.-- Concrete and cribs --.--------
                                                                  10. 00-------                                                                                   1917         397, 834.00
                miles.                                                                    and limestone.
No. 4-....... Gadsden, Ala.,' 48         127       280       52    8.00     7.00   7.00 .....
                                                                                           do--                do.....Dry rubble masonry 1914
                                                                                                            ....                                                   (3)     2   456, 620. 00
                 miles.
No. 3-.........Gadsdep, Ala., 27         148       176       40   12.00       5.15     4. 00   Disintegrated chert--
                                                                                                                  ....do-..........do __........          1890    1890         110, 744. 47   1-)
                 miles.
No. 2-........ Gadsden, Ala., 2 51/
                                 2       149       176       40    5. 57      5.40     5.20                                                   1890  1890
                                                                                               Sandstone and slate ....do..........do........----....-                         159, 166. 00
                 miles.
No. 1___.... Gadsden, Ala., 22           1522      176       40    5. 33      3. 41    3.25    Sandstone ........-.... do.....Rock-filled cribs ...       1890    1890         106, 173. 96
                 miles.
Mayos Bar-.. Rome, Ga., 7% miles.        278%      176       40   12.00      6.00      5.00    Compact shale----.....-----... do-....Dry rubble masonry   1913    1915         279, 929. 29

1 50 percent complete.

8
2 Estimated cost; no exact record.
   Lock is 99 percent complete, and the dam is completed.



                                                                                                                                                                                              H




                                                                                                                                                                                              H
596            REPORT OF CHIEF OF ENGINEERS, U.                       S. ARMY,       1944

   The fluctuations of stage are as follows: Rome, Ga., ordinary, 30
feet; extreme, 40 feet. Gadsden, Ala., ordinary, 22 feet; extreme,
38 feet. Lock No. 4, about 4 miles above Riverside, Ala., ordinary, 17
feet; extreme, 24 feet. Wetumpka, Ala., ordinary, 45 feet; extreme,
62 feet.
   The estimate of cost of new work, revised in 1928, is $1,835,000,
exclusive of amounts expended on previous projects. The latest
 (1928) approved estimate of annual cost of maintenance is $10,000 for
the part of the river between Rome, Ga., and Gadsden, Ala. The
estimate of annual cost of operation and care of locks and dams, made
in 1937, is $3,600.
   The existing project was authorized by the following river and
harbor acts:

     Acts                      Work authorized                                 Documents


Aug. 14,1876  Open-channel work and locks and dams Nos. 1, 2, Annual Report, 1872, p. 536, and
                and 3 for that section of the river between the     Annual Report, 1875, pt. 2, p. 661.
                Selma, Rome, and Dalton Railroad bridge near
                Wilsonville, Ala., and Rome, Ga., at an esti-
               mated cost of $470,668 for work between said
               bridge and Greensport, Ala., and $180,000 for
               work between Gadsden and Rome, a distance of
               107.5 miles.
Sept. 19,1890 Present channel dimensions, viz, 4 feet deep and H. Doc. No. 94, 51st Cong., 1st sess.
     and       100 feet wide, the increase of lock dimensions to
July 13, 1892  52 feet width and 280 feet clear length, and for
               the improvement of the entire river from We-
               tumpka, Ala., a distance of 11 miles above the
               mouth to Rome, Ga.
    Do _-. Only the walls of lock No. 31 and dam No. 4 were
               constructed under.this enlarged project, which
               has been considered as definitely abandoned
               following report of Jan. 9, 1905 (H. Doe. No. 219,
               58th Cong., 3d sess.).
                                                                  H. Dec. No. 1421, 60th Cong., 2d sess.
June 25, 1910 Dam No. 5 and the lock in dam No. 4----------...........
    Do ..... Lock and dam at Mayos Bar__-- ------------ H. Doc. No. 1115, 60th Cong., 2d seas.
June 26,19341 Operation and care of locks and dams provided
               for with funds from War Department appro-
               priations for rivers and harbors.


1 Permanent Appropriations Repeal Act.

   The latest published maps of the Coosa River will be found in An-
nual Report, 1890, page 1644, for that portion of the river from lock
No. 4 to Greensport; Annual Report, 1891, page 1752, for that por-
tion between Wetumpka and lock No. 4; and Annual Report, 1913,
page 2125, for the upper Coosa.
   Recommended modification of project.-See recommendation for
the development of Alabama and Coosa Rivers reported under the
project for Alabama River.
           RIVERS AND HARBORS-MOBILE,         ALA.,   DISTRICT     597
    The abandonment for the present of the existing project, except
for the inexpensive care and maintenance of locks and dams, was
recommended under date of December 29, 1920 (H. Doc. No. 1018,
66th Cong., 3d sess.).
    Terminal facilities.-At Rome, Ga., there is one small private wharf
on the left bank of Oostanaula River, and a private wharf on the left
bank of Etowah River used exclusively by the owners. These facili-
ties and the natural landings on the Coosa River are considered
adequate for the existing commerce.
    Operations and results during fiscal year.-Only Mayos Bar lock
was kept in operation during the year. All Government property at
the other locks and dams was protected. The cost was $3,175.90 for
maintenance. The expenditures were $3,311.67.
    Condition at end of fiscal year.-The existing project was 83.5
percent completed. Locks and dams Nos. 1, 2, and 3, the lock and
dam at Mayos Bar, and dam No. 5 have been completed. Lock No. 4
was completed, except about 1 percent of work required on the lock,
which consists of the completion of the backfill and completion
of upper guard wall. (See tabulated statement under "Existing
project.") Open-channel work by dredging, rock removal, and con-
struction of contraction works had been carried on at various shoals
between Lock No. 4, Alabama, and Rome, Ga. A 4-foot depth at
mean low water obtains at such bars as had been worked over, but
no extensive and consecutive length of stream had been completed.
At the end of the fiscal year the controlling depth was 21/2 feet ol
several of the bars; from Gadsden, Ala., to Woods Ferry, 37 miles,
the controlling depth was 3 feet, certain shoals and the lower sill at
Lock No. 1 being the controlling points; from Woods Ferry to Lock
No. 4, 9 miles, the controlling depth was 4 feet. These depths are
obtainable throughout the year. Increased drafts are ordinarily ob-
tained between the months of January and June, inclusive. The work
remaining to be done to complete the project consists of a lock at
dam No. 5, lowering sills at lock No. 1, and completing open-channel
work from Mayos Bar to lock No. 4, 148 miles. All locks and dams
are in poor condition, and with the exception of Mayos Bar lock
cannot be operated. At lock No. 1 the miter sills are badly worn
and are in need of replacement and the wooden gates at locks Nos.
2 and 3 are decayed and leak badly. All the dwellings at the locks
are badly in need of repair. At dam No. 5 the timber section of
the dam has decayed and washed out. Repairs are not contem-
plated at any of these. Open-channel work which has been done
has, in general, been maintained by the action of the river.
   The total cost under the existing project was $2,354,720.65, of
which $1,608,105.59 was for new work and $746,615.06 for mainte-
nance. The total expenditures were $1,795,589.89. In addition, $559,-
145.99 was expended between June 30, 1890, and June 30, 1935,, on
the operation and care of the works of improvement under the pro-
vision of the permanent indefinite appropriation for such purposes.
   Proposed operations.-The balance unexpended at the end of the
598             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

fiscal year, including an allotment of $9,800 made during July 1944,
and accounts receivable, will be applied as follows:
Maintenance:
   Operation of locks and dams-----------------------------                                                                     $3, 254.04
   Ordinary repairs___      --   --------------                                                                                  6, 700. 00

            Total__ ----------------------------------------------                                                               9, 954. 04
   The additional sum of $8,200 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Operation of locks and dams_----------                                                                       --               -$3, 200
    Ordinary repairs_ ------------------------------------------                                                                     5, 000

            Total         -------------------------------------------------                                                             8,200

                                                Cost and financial summary
Cost of new work to June 30, 1944__                                                                                   $2, 574, 911. 97
Cost of maintenance to June 30, 1944_-------                                                           ---                746, 6015. 06
       Total cost of permanent work to June 30, 1944 .-----                                                               3, 321, 527. 03
Plus accounts receivable June 30, 1944 -----------------------                                                                     15. 23
            Gross total costs to June 30, 1944---------------------                                                       3, 321, 542. 26
Net total expenditures----      ------------                                                                              3, 321, 542. 26
Unexpended balance June 30, 1944_------------                                                                                     138. 81
            Total amount appropriated to June 30, 1944                                 ------------                       3, 321, 681. 07


    Fiscal year ending June 30                      1940             1941               1942                  1943                     1944

Cost of new work _               .........        ...      .        .....     .                                ....             ....      .
Cost of maintenance_ ---            ------         $3, 351.76       $2, 896. 22        $2, 668. 49           $3, 170. 06               $3,175.90
Total expended .............-----------------       3, 580. 29       2, 942. 61         2, 621.30             3,050. 46                 3, 311. 67
Allotted------------------3,600.                               00    3, 509.84          4,000.00                 414. 71.



Balance unexpended July 1, 1943_---------                                                              --             -         $3, 450. 48
Gross amount expended_------------                                                                   ----                        3,311. 67
      Balance unexpended June 30, 1944 --------------------                                                                            138. 81
Accounts receivable June 30, 1944_---------                 ---                                                                         15. 23
     Unobligated balance available June 30, 1944------------                                                                         154. 04
Amount allotted in July 1944_---     -----------                                                                                  9, 800. 00
            Amount available during fiscal year 1945 ---------------                                                             9, 954. 04
Amount (estimated) required to be appropriated for completion
    of existing project                1___        __-                      -___-___                  -___                   227, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_ _ _____-             ___                                                               -__     8, 200. 00
  1Exclusive of available funds.
          RIVERS AND    HARBORS-MOBILE,      ALA.,   DISTRICT     599
   19. BLACK WARRIOR, WARRIOR, AND TOMBIGBEE RIVERS, ALA.

   Location.-The above names apply to what is virtually a single
stream, about 472 miles in length, having its source in northern Ala-
bama, flowing in a general southwesterly direction, and uniting with
the Alabama River to form the Mobile. River, 45 miles above Mobile
Bay. (See U. S. Geological Survey map of Alabama.)
   Previous projects.-The original project for the improvement of
Warrior River, now combined with the Black Warrior and Tombig-
bee Rivers, was adopted by act of March 3, 1875. For further details,
see page 1841 of Annual Report for 1915, and page 732 of Annual
Report for 1938.
   Existing project.-This provides for the construction of 15 dams
and 16 locks, the extra lock being at dam No. 17, where the lift of
72 feet is equally divided between 2 locks in tandem, and for such
dredging and clearing of channels by snagging as may be necessary
to secure an all-year channel 9 feet in depth and 200 feet wide, where
practicable, from the mouth of the Tombigbee River 45 miles above
Mobile, to mile 447.6 on the Sipsey Fork, mile 444.6 on the Mulberry
Fork, and mile 420.6 on the Locust Fork, a total distance of 426.6
miles. The project also provides for dredging a cut-off channel 9
feet deep and 150 feet wide approximately 1.4 miles long in the
vicinity of Sunflower Bend, and installing temporary flashboards on
dams 1-9, raising existing dams 13-16 each 1 foot, the construction
of crest gates 12 feet high on dam 17, and the maintenance by snag-
ging operations of Mobile River from the mouth of Chickasaw Creek
to the junction of the Alabama and Tombigbee Rivers, a distance of
42 miles.
   The project also provided for the construction of the new'lock and
dam in the vicinity of Tuscaloosa to replace original locks Nos. 10,
11, and 12.
   The maintenance of the section of the Tombigbee River below lock
No. 1 to its mouth, a distance of 56.6 miles, formerly reported under
the title "Tombigbee River, Ala., from mouth to Demopolis (main-
tenance of channel)," authorized by the River and Harbor Acts ap-
proved September 19, 1890, and June 13, 1902, is included in this
project. The last separate report under the above-quoted title is
shown on page 781, Annual Report for 1926.
   The project also provides for operation and care of all locks and
dams.
   The following table contains information concerning various fea-
tures of the locks and dams included in the existing project:
                                                                                                                 Locks and dams

                                                                                Great-                                                                                     Type of construction                                                                      C)
                               Dis-                                               est                            Depth
                              tae                                        Dis-   length     Width                  over          Character of            KindDate                                                          of    Date opened       ockand
    Lock No.                 above          Nearest town                ts-      avail-                 Lift     sills at                   f              ndof                                                      comple-    to navigation      f lock a
                               Mo-                                       ance    able      cham-                   low          foundation               ,dami                                                                         gati           dam
                                                                                for full    berwater                                                                       Lock                   Dam                                                                M
                              bile 1
                                                                                width

                             Miles                                     Miles     Feet       Feet        Feet      Feet
1-----------..............   101.6      St. Stephens, Ala_                 3     281.9      52          12.00     2 8. 0     Soft rock -....               Fixed- Concrete--                 Concrete ....             1909     Sept.   6,1908     $560, 290. 02
2-----------_                172. 6     Pennington, Ala_                   6     286        52           9. 00      8. 5     Hard clay             .....     do .-... do-.                   Timber crib,              1915     Nov.    1, 1914     560,114. 09
                                                                                                                                                                                               stone filled.
3--------             -      194.6   Oakchia, Ala .....         5                286        52          10. 00      8.5     .....- do- ....              .. do ... _ do---.....-..__do .......                         1915     Sept. 21,1914        609, 622.80     O
4..........                  221. 6  Dem opolis, Ala .          1                285. 6     52          10. 00      8. 5    . ....-do ...... ..            . do ..-       . do ..... . .... do .......                 1908     Dec. 1, 1908         479, 000. 00
5-----------_                236. 6  Cedarville, Ala ...-       5                285.6      52          10. 00      8. 5    ___do....-.-...       -             do.....do-...__                    do _                1908     Sept. 1,1908         501, 000. 00
6-----_                      257.1   Sawyerville, Ala           5                285. 6     52          10.00       8. 5      Piles ...-       ---       .. do          _-_ do_ ........--        do _-...             1908     Oct.   1,1908        443, 000. 00    Q
7_-          __--.-          272. 6  Wedgeworth, Ala_           5                284. 7     52          10.00       8. 5          _-do- ....--                  do-_     _do...           _ _._ __do ..-...            1903     Nov. 7,1903          225, 600.00
8---- -             -        288. 6  Akron, Ala...        .     3                284. 7     51.65       10.00       8. 5    _       do--         ....-
                                                                                                                                                    -           do _        do. _ - __-.           do.                 1903     Jan. 1,1903          212, 400. 00
9----       ------           305. 6  Powers, Ala .              4                284. 7     52          11.00       8. 5     ._do                  .-- ... do ..            do....-..          __--do ..-        .     1902    _ ___ do ... -        202, 440. 00'
Tuscaloosa. ....             351.35 Tuscaloosa, Ala__-----.                      460        95          30. 00     10. 8      Hard blue shale .. do                         do.....
                                                                                                                                                                            __--             Concrete -- _             1940     Aug. 29,1939      4, 450, 873. 50
13_..._. ---                 360. 6  Tidewater, Ala__    .....  -.               285. 5     52          11.00      10. 6      Hard sandstone                . do___ Stone -- _               Stone-              _     1905     July 4,1905          203, 700. 00
14...-._-                    364.1   Searles, Ala...            8                282.1      52          14. 00      9. 5     _..do_--......_.                   do___ Concrete__ Concrete-....                         1910     Mar. 29,1910         414, 714. 89    0
15.. ..........              370. 6  Kellerman, Ala __          6                282. 1     52          14. 00      9. 5        .. do--.......           ... do      ..     do   -...-  .     ..   do  .    - ..       1910     M ay 2, 1910         430, 233. 87
16....... - -                377.1 .... do .........        .  14                285. 5     52          21.00       9. 5    .. .. do- ..........             ...do    . ' do .. . ... .. d o........                   1915     Jan . 1,1915         520, 853.68
17 3-...........
        -                    378. 6 .... do............        14                285.5      52          72.00       8.5       ..... do---..............do ...               do-......___ _- do-.......                 1915     May 13,1915       53,424,858.98
   Total lift----....---...--...--     -----------------------------------                             254. 00

  1 Mileage from foot of Government St., Mobile, Ala.                                                                                4Now 99 percent completed; the remaining 1 percent covers cost of submerged land.
   2River is tidal below this lock and daily gage readings show that on an average of only                                           5Does not include $1,435,635.76, estimated cost of land submerged, damage to structures,
2 days per year is the depth over the sill less than 8 feet, the minimum being 6.9 feet.                                           and cost o ti1earing                                                                                                              00
  3 Double lock.
                   RIVERS    AND     HARBORS--MOBILE,                ALA.,    DISTRICT                601
   The tidal influence extends from Mobile 101.6 miles to lock No. 1,
where the tidal effect is apparent only at low stages of river. At
Mobile the mean and extreme tidal ranges are 1.4 and 3.6 feet, re-
speetively. These are at times slightly increased by the effect of winds.
The greatest fluctuation of river stages is at Demopolis, Ala., the
maximum at this point being 59.7 feet. The maximum fluctuations
at other points are 40 feet at lock No. 1, 101.6 miles from Mobile;
57.8 feet at Tuscaloosa, Ala., 352.6 miles from Mobile; 13 feet at Port
Birmingham, 409.6 miles from Mobile; and 27 feet at Cordova, 429.6
miles from Mobile. The ordinary fluctuations at these points are at
lock No. 1, 20 feet; at Demopolis, 35 feet; at Tuscaloosa, 40 feet; at
Port Birmingham, 4 feet; and at Cordova, 7 feet. The works of
improvement have reduced the amount of fluctuations at different
points from 3 to 10 feet.
   The estimated cost of new work, revised in 1939, is $16,200,000, ex-
clusive of amounts expended on previous projects. The latest (1936)
approved estimate for annual cost of maintenance is $574,000.
   The existing project was authorized by the following river and
harbor acts:
       Acts                     Work authorized                                   Documents


July           Original appropriation for improving Black War-
         5, 1884
                rior River.
               Original project for slack-water improvement         Annual Report, 1887, pt. 2, p. 1302.
                authorized by Secretary of War Apr. 19, 1887.
Mar. 3,1899    Construction of the first locks between Tuscaloosa
                and Demopolis
               Maintenance of       ction of Tombigbee River
Sept. 19, 1890
                below lock No. 1 to its mouth (66 miles) included
June 13, 1902
               Sin the existing project.
    Do....... Construction uf locks and dams Nos. 1, 2, and 3.      HI. Doc. No. 178, 56th Cong., 2d sess.,
                Merging of the individual projects for the Black      and Annual Report, 1901, pt. 3, p.
                Warrior and Warrior Rivers and the Tombigbee          1858.
                River below Demopolis.                              H. Doc. No. 165, 57th Cong., 1st sess.,
                                                                      and Annual Report, 1902, p. 1293.
Mar.     2, 1907Construction of locks and dams Nos. 14, 15, 16,
                  and 17.
Aug. 22, 1911   Lift of lock No. 17, changed to 63 feet, and con- IE Doe. No. 72, 62d Cong., 1st sess.
                  struction of locks and dams Nos. 18 and 19 elimi-
                  nated from the project. Extension of slack-
                  water improvement to Sanders Ferry on Mul-
                  berry Fork and Nichols Shoal on Locust Fork.
Mar. 2, 1919    Raising of various dams 2 feet and raising the lock Annual Report, 1918, p. 876.
                  walls 2 feet at lock No. 1 to provide a minimum
                  depth of 8 feet at low water, widening the chan-
                  nel to 150 feet where practicable.
Aug. 30, 1935 For snagging Mobile River from the mouth of H. Doc. No. 728, 71st Cong., 3d sess.
                  Chickasaw Creek to the junction of the Ala-
                  bama and Tombigbee Rivers.
                                                                                                       1
    Do ..... Exfension of the project to its present limits and H. Doe. No. 56, 73d Cong., 1st sess.
                  channel   dimensions.
    Do ...... Construction of a lock and dam below Tuscaloosa Rivers and Harbors Committee Doe.
                  to replace existing locks and dams Nos. 10, 11,    No. 26, 74th Cong., 1st sess.
                  and 12.
June 26, 19342 Operating and care of locks and dams provided for
                  with funds from War Department appropria-
                  tions for rivers and harbors.
  1 Contains latest published maps of the Tombigbee River and tributaries.
  2Permanent Appropriations Repeal Act.
  For maps of the Warrior and Black Warrior Rivers, see Annual Reports for 1911, p. 1702 and 1918, p. 2144,
respectively.
602          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

  Recommended modifications of project.-Under date of February
28, 1939, the Chief of Engineers recommended the further improve-
ment of the Warrior and Tombigbee Rivers, Ala. and Miss., by the
construction, at this time, and with priority over other locks and
dams proposed for the system, of a dam with normal lift of approxi-
mately 40 feet and with a lock chamber approximately 77 feet wide
and 600 feet long, generally as described in the report of the district
engineer, near Demopolis, Ala., to replace existing dams Nos. 4, 5, 6,
and 7, at an estimated cost of $6,750,000 for construction and for
acquisition of necessary lands (H. Doc. No. 276, 76th Cong., 1st sess.).
  Under date of June 20, 1941, the Chief of Engineers recommended
modification of the existing project so as to provide for an inoreased
spillway capacity at dam No. 1 at an estimated first cost of $115,000,
with no increase in the annual cost of operation and maintenance
above the amount now required (H. Doc. No. 382, 77th Cong., 1st
sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-Facilities comprising loading and transfer
stations, wharves, etc., have been provided, where required along this
waterway. All are privately owned and operated except the termi-
nals at Tuscaloosa which are leased to a private company, but serve
the general public, and the terminals at miles 357.6 and 409.6 which
are owned and operated by the Inland Waterways Corporation, also
serve the general public. These terminals are considered adequate
for the existing commerce.
   Operationsand results during fiscal year.-The following work was
accomplished during the fiscal year :
                                                            NEW WORK
                                                                                                                                  Cost
Installation of flashboards on dams 2 to 9, inclusive                                  _        -             --                $32. 52

                                                      MAINTENANCE


                                                                                                          Cubic
           Plant                       Locality                                 Date                       yards                 Cost
                                                                                                         removed

U.    S. pipe-line dredge    Warrior and Tombig-                   July 1 to Sept. 23, 1943, and        1, 845, 917           $166, 469.66
     Win. L. Guthrie.         bee Rivers.                            Mar. 16 to 31, Apr. 6 to 19,
                                                                     and May 2 to June 30, 1944.
U. S. pipe-line dredge       Tombigbee River....                                              -
                                                                   May 29 to June 30, 1944 .---             244, 313            25, 736. 33
  Blackwater.
U. S. snag boat Denison      Warrior River            ..-          July 1 to Nov. 27, 1943, and              1 8, 330           62, 298. 83
                                                                     Jan. 3 to June 30, 1944.
U. S. snag boat Mont-        Tombigbee River                 -     July 1 to 13 and Aug. 16 to               2 6, 520           65, 907.67
  gomery.                                                            Nov. 27, 1943, and Jan. 3 to
                                                                     June 30, 1944.
U. S. snag boat R. C ...          do_-                            July 22 to Aug. 8, 1943 ..                 (3)               21,831.73
   McCalla.
U. S. derrick boat Pearl
Spraying      grass  and
                             Warrior River -
                             Dam No. 17 pool and
                                                                   Apr. 17 to 29, 1944 -  -- -
                                                                   July 1 to Sept. 30, 1943, and
                                                                                                               3, 565
                                                                                                        -.. -....-
                                                                                                                                   610.94
                                                                                                                                 9,843.01
   banks at edge of water     Tuscaloosa lock and                    June 16 to 30, 1944.
   to eliminate mosquito      dam pool.
   breeding.
'Surveys in connection       Warrior and Tombig-                   July 1, 1943-June 30, 1944       ..------.....----------     16, 576.95
   with dredging opera-       bee Rivers.
   tions.
U. S. towboat Fayette-      Entire system                  .---   Miscellaneous investigations               --                 4, 214.80
   ville,                                                           and dredging surveys during
                                                                    the entire year.
      Total maintenance-           -
                            .---------------.-.----                                                                 .--        373, 489. 92

  1Also 8,438 obstructions.
 '2Also 6,560 obstructions and 70 cords of drift.
   Removed 711 obstructions.
                   RIVERS AND HARBORS-MOBILE,                                    ALA.,     DISTRICT                   603
   All locks and dams, telephone lines 141 miles long, and other equip-
ment and plants were operated and maintained by United States
plant and hired labor. The total cost of operating and care of locks
and dams was $371,483.24, charged to maintenance.
   The total cost for the fiscal year was $745,005.68, of which $32.52 was
for new work and $744,973.16 for maintenance. The expenditures
were $683,663.60.
   Condition at end of jiscal year.-The existing project was about 99
percent completed. Eighteen locks and dams have been built. Three
of these (Nos. 10, 11, and 12) have been removed and replaced by the
Tuscaloosa Lock and Dam. (See table under "Existing project.")
The channel has been dredged, original snagging completed, and prin-
cipal lock houses built at all locks. A dredged channel through Sun-
flower Bend cut-off on the Tombigbee River was completed in 1938.
4 depth of 8 feet over a minimum width of 100 feet obtains throughout
the entire length of the improvement, and all-year navigation for
boats is possible to the extent of the channel dimensions. Construction
of crest gates on dam No. 17, Black Warrior River, was completed in
1938. Construction of Tuscaloosa Lock and Dam was completed in
1940. The work remaining to be done to complete the project consists
of payment for damages caused by backwater from crest gates on dam
No. 17, payment for lands submerged by backwater above original
dam No. 17, payment for lands for right-of-way, spoil area and cut-off
lands at Sunflower Bend.
   The total costs and expenditures for the existing project to June
30, 1944, were as follows:
                                                                         Costs
                                                                                         Operating and          Total
                                                  New work           Maintenance
                                                                                              care


Regular funds--......               .....        $15, 620, 505.69    $2, 731, 773.97    $11, 517, 517.16    $29, 869, 796.82
Public Works funds _--------------------79,                219.93 _                                    E79,           219.93
Emergency Relief funds          ..--------.           607, 307. 56  .     -...  .    . ...                       607, 307. 56

       Total       --.......--.
                           ,-----   .   -.-...    16, 307, 033.18     2, 731, 773.97      11,517, 517.16     30, 556, 324.31


   The total expenditures to June 30,1944, were $21,604,036.96, of which
$20,917,509.47 were regular funds, $79,219.93 Public Works funds, and
$607,307.56 Emergency Relief funds.
   In addition, the sum of $8,932,686.64 was expended between. July 1,
1896, and June 30, 1935, on the operation and care of works of improve-
ment under the provision of the permanent indefinite appropriation
for such purposes.
   Proposed operations.--The balance unexpended at the end of the
fiscal year, including accounts receivable, and an allotment of $661,500
made during July 1944, will be applied as follows:
Accounts payable June 30, 1944_ _                  ____---------                                 .-. .$19,        641. 76
New work:
    Complete installation of temporary flashboards on
      dams Nos. 2-8, inclusive, with Government plant
      and hired labor_----------------------------                                        $9, 618.05
    Complete payment for lands submerged above dam
      No. 17_----------------------------                                                   9, 376.49
    Complete payment for lands for rights-of-way, spoil
      disposal area and cut-off at Sunflower Bend ...                                       5, 887. 89
    Complete payment for damages caused by back-
      water from crest1 gates  -57, on dam No. 17       ---                                     623. 73
                                                                                                             82, 506. 16
604           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

Maintenance (with United States plant and hired labor):
    Dredging in river channel between mile 45 and head
      of navigation with U. S. hydraulic pipe-line dredge
      Guthrie and U. S. snag boats Montgomery and
      Denison, as necessary_-      ------             _- $133, 620. 50
    Snagging in river channel between Chickasaw
      Creek and head of navigation with U. S. snag-
      boats Denison and Montgomery, as necessary _ -115, 000. 00
    Miscellaneous work at lock No. 17 and Tuscaloosa
      lock and dam pools---       ---------                12, 000. 00
                                                                                                                $260, 620. 50
Maintenance (operating and care):
   Operation of 15 locks and dams                             ----------------            227, 000. 00
   Ordinary repairs_ _-------             ____                                             30, 900. 00
   Improvement and reconstruction---------------                                          105, 000. 00
                                                                                                                   362, 900. 00
           Total for all work_ -----                                            _ __--------             __-- 725, 668. 42

   The additional sum of $845,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance (with United States plant and hired labor):
    Dredging in river channel between mile 45 and head of
      navigation_ ---------------------------------       $250, 000
    Snagging in river channel between Chickasaw Creek
      and head of navigation                               115, 000
    Miscellaneous work at lock No. 17 and Tuscaloosa lock
      and dam pools_ ___-------------15,000
                                                                                                                     $380, 000
Maintenance (operating and care):
    Operation of 15 locks and dams-- -------          $320, 000
    Ordinary repairs__--- ----------                    30, 000
    Improvement and reconstruction------------------- 115, 000
                                                                                                                      465
                                                                                                                      zvv,
                                                                                                                           000
                                                                                                                           vvv


           Total for all work_---..--------------                                                                     845,000

                                               Cost and financial summary
Cost of new work to June 30, 1944 _$16,                                                                           913, 963. 96
Cost of maintenance to June 30, 1944_------                                                  ---              14, 299, 291. 13

       Total cost of permanent work to June 30, 1944--------- 31, 213, 255. 09
Plus accounts receivable June 30, 1944----------------------            41. 05
      Gross total costs to June 30, 1944                           --------------------                       31, 213, 296. 14
Minus accounts payable June 30, 1944----------------------                                                         19, 641. 76
      Net total expenditures_ _______------------31,                                                               193, 654. 38
Unexpended balance June 30, 1944-------------------------                                                           64, 127. 37
           Total amount appropriated to June 30, 1944-----------                                              31, 257, 781. 75


    Fiscal year ending June 30                   1940              1941            1942                1943             1944

Cost of new work- ...... _.. .                $421,716. 50       $84, 534, 60   $16, 681.33         $211, 705.12            $32. 52
Cost of maintenance-        _
                          _........            602, 963. 01      670, 828.32    612, 037.07          806, 614.97       744, 973.16
       Total cost   --------------           1,024, 679. 51      755, 362. 92   628, 718. 40       1,018, 320.09       745, 005. 68

Total expended-............_          ....   1, 312,153.87       765, 624.95    609,191.02         1,073, 320.61       683, 663.60

Allotted_ -------------.--.-..                 736,183.49        735, 000.00 .. 714,430.00           955,467.57        100,000.00
               RIVERS      AND       IARBORS-MOBILE,   ALA.,   DISTRICT          605
Balance unexpended July 1, 1943_                                       $647, 790. 97
Amount allotted from War Department Civil Appropriation
  Act approved Apr. 28, 1942___                                           100, 000. 00

       Amount to be accounted for_                                        747, 790. 97
Gross amount expended_------             --            $685, 0C7. 07
Less reimbursements collected------------------           1, 403. 47
                                                                          683, 663. 60
        Balance unexpended June 30, 1944--------------------               64, 127. 37
Outsta nding liabilities June 30, 1944_                                    19, 641. 76
        Balance available June 30, 1944_                                   44, 485. 61
Accou nts receivable June 30, 1944_                                             41. 05

      Unobligated balance available June 30, 1944-----------               44, 526. 66
Amou nt allotted in July 1944_                                            661, 500. 00

        Amount available during fiscal year 1945--------------            706, 026. 66

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1___   _     __                           845, 000. 00
1 Exclusive of available funds.

                                   20. BAYOU LA BATRE, ALA.

   Location.-This is a tidal stream about 10 miles long, located in the
southwestern part of the State of Alabama, and empties into Mis-
sissippi Sound. It is 45 miles by water from Mobile Harbor, Ala., on
the east, and 21 miles from Pascagoula Harbor, Miss., on the west.
 (See U. S. Coast and Geodetic Survey Chart No. 1267.)
   Existing project.-This provides for a channel 6 feet deep at mean
low water and 100 feet wide across the bar and 6 feet deep and 75 feet
wide between the mouth and the county highway bridge, except where
the existing depth is 6 feet or more for a width of at least 50 feet: The
length of the channel across the bar is 3,500 feet, and the section of the
bayou included in the project is 21/2 miles in length. The mean and
extreme tidal ranges are 1% and 3% feet, respectively.
   The estimated cost for new work, made in 1923, was $20,000, with
$5,000 for annual maintenance.
   The existing project was adopted by the River and Harbor Act of
March 3, 1925 (Rivers and Harbors Committee Doc. No. 4, 68th Cong.,
1st sess.). The latest published map is in the project document.
   Recommended modifications of project.-Under date of April 20,
1939, the Chief of Engineers recommended modification of the exist-
ing project for Bayou La Batre, Ala., so as to provide a channel 100
feet wide and 9 feet deep from that depth in Mississippi Sound to the
highway bridge at the town of Bayou La Batre at an estimated cost of
$27,500, with maintenance estimated at $2,000 annually in addition to
the present cost of maintenance; subject to certain conditions of local
cooperation (H. Doc. No. 281, 76th Cong., 1st sess.).
   Local cooperation.-Fullycomplied with.
   Terdmnal facilities.-Consist of numerous small wooden wharves,
most of which are used in connection with the canning factories located
on the bayou. All of these wharves are privately owned but available
for public use. These facilities are considered adequate for existing
commerce.
606             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

  Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was completed
in 1926. The controlling depths at the end of the fiscal year were as
follows: Mississippi Sound Channel, 6 feet, Bayou La Batre Chan-
nel, 6 feet. The total cost and expenditures were $79,837.67, of which
$18.631.29 was for new work and $61,206.38 for maintenance.
  Proposed operations.-No funds are available and no operations are
contemplated during the fiscal year 1945.
  The sum of $16,000 can be profitably expended during the fiscal year
1946 for maintenance dredging to restore project dimensions with a
hydraulic pipe-line dredge, for one-half month.
                                        Cost and financial summary
Cost of new work to June 30, 1944_ -----------                                                                           $18, 631. 29
Cost of maintenance to June 30, 1944----                                   -11111111                                      61, 206. 38
       Total cost of permanent work to June 30, 1944-------------                                                         79, 837. 67
Net total expenditures--------------------------------                                                                    79, 837. 67
Total amount appropriated to June 30, 1944                     --------------------                                       79, 837.67


     Fiscal year ending June 30           1940          1941                  1942                             1943                 1944

Cost of new work .-                      - - - - -- - - - -         ---                                   --      ----       - -----
Cost of maintenance.......------         $6, 473.68    $5,358.63            $7,141.37                 -    -----.         .......
Total expended _ __..............         6,473.68      5, 508.63            6,991.37             .

Allotted--.--.---....                    10,000.00    -1,026.32     ...................................



Amount that can be profitably expended in- fiscal year ending June   30,
1946, for maintenance 1 _ -   - - -
                                     ___
                                             - -
                                                  __
                                                     -   -
                                                        ___
                                                            -   -  -
                                                                         $16,000.00
   1Exclusive of available funds.

                                    21. PASCAGOULA HARBOR, MISS.

  Location.-This harbor, located along the lower 6.8 miles of Pas-
cagoula River and the lower 4 miles of Dog River, is in the south-
eastern part of the State of Mississippi about 61 miles by water from
Mobile Harbor, Ala., on the east, and about 44 miles from Gulfport
Harbor, Miss., on the west. (See U. S. Coast and Geodetic Survey
Chart No. 1267.)
  Previous projects.-Appropriations were made for Pascagoula
River by River and Harbor Acts of March 2, 1827, May 23, 1828, and
August 30, 1852. The first definite project was adopted by River and
Harbor Act of June 14, 1880. Other projects were adopted by the
River and Harbor Acts of August 5, 1886, August 18, 1894, June 3,
1896, March 3, 1899, June 13, 1902, and June 25, 1910. For further
details see page 1843 of Annual Report for 1915 and page 741 of
Annual Report for 1938.
  Existing project.-This provides for a through channel of the maxi-
mum dimensions that can be secured by the expenditure of $283,000,
but.not exceeding a depth of 25 feet and width of 300 feet across the
outer bar at Horn Island Pass, and thence a depth of 22 feet and
width of 225 feet to the railroad bridge at Pascagoula, and thence a
depth of 22 feet and width of 150 feet, increased at sharp bends to a
point on Dog River 4 miles above its mouth. Under ordinary condi-
              RIVERS      AND      HARBORS-MOBILE,               ALA.,    DISTRICT              G607
tions the mean tidal range here is 13 feet and the extreme tidal range-
is 33/4 feet.
   The estimate of cost for new work, revised in 1914, is $283,000, ex-
clusive of amount expended on previous projects. The latest (1928)
approved estimate for annual cost of maintenance is $5,000 for the-
outer bar channel at Horn Island Pass and $100,000 for the channels
in the river and through Mississippi Sound.
   The existing project was authorized by the following river and
harbor acts:

   Acts                       Work authorized                                Documents


Mar. 4,1913   Limiting the channel dimensions subject to local   H. Doc. No. 682, 62d Cong., 2d sess.
               cooperation.
Mar. 4,1915   Modified the required local cooperation and pro-   Rivers and Harbors Committee Doe._
                vided present project channel dimensions.         No. 12, 63d Cong., 2d sess.


The latest published map may be found in H. Doc. No. 211, 54th Cong., 2d sess.


   Local cooperation.-Fullycomplied with.
   Terminal facilities.-The municipal wharf on the east side of Pas-
cagoula River has an available dockage of 1,094 feet. The Louisville-
& Nashville Railroad Co.'s wharf in the Pascagoula River at Pasca-
goula, Miss., just north of their bridge, and the Mississippi Export
Railroad wharf on the Dog River at Moss Point, Miss., have an avail-
able dockage of 60 and 380 feet, respectively. The Farnsworth Coal
Co. has a wharf on the Pascagoula River, located just north of the
Louisville & Nashville Railroad Co.'s wharf. All private terminals,
together with the municipal wharf, are considered adequate for exist-
ing commerce.      (See Port Series, No. 19, revised 1934, Corps of
Engineers.)
   Operationsand results during fiscal year.-Miscellaneous investiga-
tions and surveys were carried on during the fiscal year at a cost of
$2,930.75. Under authority of section 3 of the River and Harbor Act
of October 17, 1940, the U. S. hydraulic pipe-line dredge Wahalak,.
operating in Charmier Bayou, Miss., from April 4 to 6, 1944, removed
12,542 cubic yards of material at a cost of $2,585.43. The total cost
was $5,516.18, charged to maintenance. The expenditures were
$5,531.89.
   Condition at end offiscal year.-The existing project was about
91 percent completed. The controlling depths at the end of the fiscal
year were as follows: Horn Island Pass, 25 feet; Mississippi Sound
Channel, 21 feet; Pascagoula River Channel, 17.5 feet. Included in,
the total cost of maintenance is an item of $2,585.43 used in dredging
in Charmier Bayou, Miss., under section 3 of the River and Harbor
Act of October 17, 1940. The work remaining to be done to complete
the project consists of obtaining a 2-foot additional depth in the Pas-
cagoula River Channel from the Louisville & Nashville Railroad
bridge to a point on Dog River 4 miles above its mouth. The total'
cost was $1,376,284, of which $258,040.11 was for new work and
$1,118,243.89 for maintenance. The expenditures were $1,376,294.71.
   Proposed operations.-The balance unexpended at the end of the
608            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

fiscal year, including accounts receivable and allotment of $35,500
made during July 1944, will be applied as follows:
Maintenance dredging with a hydraulic pipe-line dredge to provide
channel dimensions adequate to the needs of navigation in Missis-
sippi Sound and River Channels, about 3 months during August
and September 1944, and February and March 1945_                  $81, 961. 83          -------------
Maintenance dredging to restore project dimensions in Horn Island
Pass Channel, with the U. S. seagoing hopper dredge Benyaurd, for
about    month during 1944----        -----------                  18,000.00
            Total_ ---------------------------------------------                                                          99, 961.83
   The additional sum of $50,000 can be profitably expended during
the fiscal year 1946, for maintenance dredging to provide channel
dimensions adequate to the needs of navigation in the Mississippi
Sound and River Channels, with a hydraulic pipe-line dredge about
11/2 months.
                                                 Cost and financial summary
Cost of new work to June 30, 1944- -.                                                                              $1, 162, 481. 72
Cost of maintenance to June 30, 1944_------                                                          ---            1, 530, 868. 04
       Total cost of permanent work to June 30, 1944---------- 2, 693, 349. 76
Plus accounts receivable June 30, 1944--------                ---       10. 71
            Gross total costs to June 30, 1944---------------------                                                 2, 693, 360. 47
Net total expenditures -----------------------------------   2, 693, 360. 47
Unexpended balance June 30, 1944----------------------------     64, 451. 12
            Total amount appropriated to June 30, 1944                                 ------------                 2, 757, 811. 59
                                                   e
     Fiscal year ending June 30                        1940            1941             1942                1943              1944

Cost of new work_    -               ----          $46, 295. 69 --                   $108, 706. 55.
                                                                                     $10,706.55--
Cost of maintenance.............                    99,190.99        $49, 737.72      151, 739. 57       $46,868:95           $5, 516.18

        Total cost       .---------------          145, 486. 68       49, 737. 72     260, 446. 12         46, 868.95              5, 516.18
Total expended ...........----------------          77, 223.38       118, 015.80      260, 416.98          46, 878. 31             5, 531.89
Allotted            .                                 197, 282. 16
                                  ......---------------------         25, 282. 05     304,650.00           25, 000. 00      -12,     414. 57


Balance unexpended July 1, 1943_                                                                                         $82, 397. 58
Amount allotted from First Deficiency Appropriation Act ap-
  proved Apr. 1, 1941-      -    -    -    -      -   -                                                                    3, 000. 00
      Amount to be accounted for_                                                                                         85, 397. 58
Deductions on account of revocation of allotment_                                                                         15, 414. 57
       Net amount to be accounted for_                                                                                    69, 983.01
Gross amount expended_-     - --------                                                    $11, 569. 15
Less reimbursements collected--------------------                                            6, 037. 26
                                                                                                                           5, 531. 89
      Balance unexpended June 30, 1944---------------------                                                               64, 451. 12
Accounts receivable June 30, 1944_ --  --     ---      --   ---                                                                10. 71
            Unobligated balance available June 30, 1944                                ------------                       64, 461. 83
            Amount allotted in July 1944_ - ------------                                                                  35, 500. 00
            Amount available during fiscal year 1945                                ---------------                       99, 961. 83

Amount (estimated) required to be appropriated for completion
of existing project 1__                                                                                                  25, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1-__-                                                                -                    50, 000. 00
  1 Exclusive of available funds.
               RIVERS AND              HARBORS-MOBILE,                   ALA.,    DISTRICT               609
                                  22. BILOXI HARBOR, MISS.

  Location.-Located on the Mississippi Sound in the southeastern
part of the State of Mississippi. It is 32 miles by water from Pas-
cagoula Harbor, Miss., on the east, and 14 miles from Gulfport Har-
bor, Miss., on the west. (See U. S. Coast and Geodetic Survey Chart
     1267.)
No.Previous
             projects.-Adopted by River and Harbor Acts of August
2, 1882, and July 5, 1884. For further details see page 1846 of Annual
Report for 1915, page 863 of Annual Report for 1929, and page 744
of Annual Report for 1938.
   Existing project.-This provides for a channel west of Deer Island
10 feet deep and 150 feet wide from the 10-foot contour in Missis-
sippi Sound to the south water front of the city of Biloxi, and thence
north of Deer Island to deep water in Back Bay of Biloxi and for a
relocated channel 10 feet deep, 150 feet wide, and 4,600 feet long in
front of East Beach, for discontinuing maintenance of the abandoned
portion of the channel, and for maintenance of the Coast Guard chan-
nel to a depth of 6 feet and a width of 300 feet. Under ordinary con-
ditions, the mean tidal range is about 13/4 feet.
   The estimate of cost for new work, revised in 1938, was $58,350, exclu-
sive of amounts expended on previous projects but including $5,000
contributed by local interests. The latest (1938) approved estimate
for annual cost of maintenance is $18,500.
   The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                                     Documents   1

July 3,1930    Present project dimensions_.. ---_-_- _          .   -.   H. Doc. No. 754,69th Cong., 2d sess.
June 20,1938   Relocation of channel_  .---------------------            H. Doc. No. 639, 75th Cong., 3d sess.


1Contain latest   published maps.

   Recommended modifications of project.-Under date of April 5,
1939, the Chief of Engineers recommended modification of the existing
project for Biloxi Harbor, Miss., so as to provide an entrance channel
6 feet deep and 50 feet wide into Old Fort Bayou, at an estimated
first cost of $4,000, with annual maintenance of $1,200, in addition to
that now required, subject to certain conditions of local cooperation
 (H. Doc. 258, 76th Cong., 1st sess.)
   Under date of May 25, 1939, the Chief of Engineers recommended
further modification of existing project for Biloxi Harbor, Miss.,
so as to provide an entrance channel 8 feet deep and 100 feet wide
through Cranes Neck into Bayou Bernard, at an estimated first cost
of $6,000, with annual maintenance of $2,000, in addition to that now
required and previously recommended, subject to certain conditions
of local cooperation (H. Doc. 326, 76th Cong., 1st sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-Consistof a number of light timber wharves
at Biloxi owned by private parties but available to the public. These
are considered adequate for the existing commerce.
        616634---45---pt. 1, vol. 1-39
610               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                             1944

   Operations and results during fiscal year.-None. The cost for
miscellaneous investigations was $554.84 charged to maintenance. The
expenditures were $552.66.
   Conditionat end of fiscal year.-The existing project was completed
in 1940. The controlling depth at the end of the fiscal year was 9.5
feet. Included in the total cost of maintenance is an item of $997.24
used for dredging in Ott Bayou, Miss., during the fiscal year 1938,
under section 3 of the River and Harbor Act of July 3, 1930, and an
item of $2,222.66 for dredging in this bayou during the fiscal year 1941,
under section 3 of the River and Harbor Act of October 17, 1940.
   The total costs and expenditures for the existing project to June
30, 1944, were as follows:

                                                                                                       Costs
                                                                                                                                              Expenditures
                                                                              New work           Maintenance               Total


Regular funds.......----------------------..                           .       $49, 780.16            $141, 680. 77       $191, 460. 93          $192, 291. 50
Contributed funds...........---------------------                                5,000.00                 200. 00
                                                                                                        10,                   200. 00
                                                                                                                            15,                    15, 200.00
        Total...........................--------------------------..            54, 780.16             151,880.77          206, 660.93            207, 491.50



   Proposed operations.-The balance unexpended at the end of the
fiscal year including an allotment of $9,000 made during July 1944,
will be applied as follows:
Accounts payable June 30, 1944 ---------------------------------         $2. 18
Maintenance dredging, with a hydraulic pipe-line dredge, to restore
  project dimensions about 1 month during September and October
  1944       -------------------------------------------------      32, 618. 40
             Total --------------------------------------                                                                                      32, 620. 58
   The additional sum of $30,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging to restore project dimen-
sions, with a hydraulic pipe-line dredge, for about 1 month.
                                                              Cost and financial summary
Cost of new work to June 30, 1944           -$94,                                                                                                  162.43
Cost of maintenance to June 30, 1944_------                                                                                --                 227, 990. 30
             Total cost of permanent work to June 30, 1944-------                                                                         1 322, 152. 73

Gross total costs to June 30, 1944 -----------------------     322, 152. 73
Minus accounts payable June 30, 1944--------------------------        2. 18

     Net total expenditures_---------                                                                                  ----                1 322, 150. 55
Unexpended balance June 30, 1944_                                                     -          --              --__ __ --               -23,    620. 58

             Total amount appropriated to June 30, 1944                                                      -------------                1   345, 771. 13

    Fiscal year ending June 30                                         1940               1941                 1942              1943              1944

Cost of new work                 ....-----------               .        .--------------
                                                                                  $16,426.81            -------........                        ... ....
Cost of maintenance--- ---------.......-                         $28,040.00           11,128.50            $25,685.37        $15,326. 76             $554.84

       Total cost_ _ ..-.--.-----.                                 28, 040.00         27, 555. 31           25, 685. 37         15, 326.76             554.84
Total expended-....-                                               29, 963.96         27, 631. 28           25, 685. 37         15, 326. 76            552. 66

Allotted----.-_              .--..-------                          20, 000. 00        27, 939. 44           15, 000. 00         22, 020. 79    ....-........

   1 In addition, $5,000 for new work and $10,200 for maintenance expended from contributed funds.
               RIVERS AND          HARBORS-MOBILE                 ALA., DISTRICT          611
Balance unexpended July 1, 1943-_--             --------------------               $24, 173. 24
Gross amount expended --------------------------------------                            552. 66

      Balance unexpended June 30, 1944 ----------------------                       23, 620. 58
Outstanding liabilities June 30, 1944 ---------------------------                         2. 18
     Balance available June 30, 1944------------------------                        23, 618. 40
Amount allotted in July 1944-------------------------------                          9, 000. 00
        Amount available during fiscal year 1945--- -------------                   32, 618. 40

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance   _2------------.._30,                                 000. 00
2 Exclusive of available funds.

           23. GULFPORT HARBOR AND SHIP ISLAND PASS, MISS.

   Location.--Gulfport Harbor is located on Mississippi Sound in the
southeastern part of the State of Mississippi, about 44 and 90 miles
by water from Pascagoula Harbor, Miss., and Mobile Harbor, Ala.,
respectively, on the east, and 78 miles from New Orleans (via the
inside route through Lake Borgne, the Rigolets, Lake Pontchartrain,
and industrial canal) on the west. (See U. S. Coast and Geodetic
Survey Chart No. 1267.)
   Previous projects.-Adopted by the River and Harbor Acts of March
3, 1899 (H. Doc. No. 120, 55th Cong., 3d sess.), March 2, 1907, Feb-
ruary 27, 1911, and January 21, 1927. For further details see page
1846, Annual Report for 1915, page 857, Annual Report for 1929, and
page 747, Annual Report for 1938.
   Existing project.-This provides for a channel 27 feet deep and 300
feet wide across Ship Island Bar, a channel 26 feet deep and 220 feet
wide through Mississippi Sound, and a depth of 26 feet in the anchor-
age basin at Gulfport. Under ordinary conditions the mean tidal
range here is about 13/4 feet, and the extreme tidal range is about
3 feet.
   The estimate of cost for new work made in 1927 was $200,000, exclu-
sive of amounts expended on previous projects. The latest (1927)
approved estimate for annual cost of maintenance is $185,000.
   The existing project was adopted by the River and Harbor Act
approved July 3, 1930 (H. Doc. No. 692, 69th Cong., 2d sess.). The
latest published map of this locality is in the project document.
   Terminal facilities.-The modern rail-connected terminal facilities
at this port are considered adequate for existing commerce. (See Port
Series No. 19, revised 1934, Corps of Engineers.)
   Operations and results during fiscal year.-The U. S. hydraulic
pipe-line dredge Pascagoula, operating in the Mississippi Sound
Channel from September 1 to October 8 and 15 to 19, 1943, removed
909,296 cubic yards of material; the U. S. hydraulic pipe-line dredge
Blaclkwater,operating in this channel from January 23 to February 15,
1944, removed 401,375 cubic yards of material; and the U. S. hydraulic
pipe-line dredge Wahalak, operating from January 28 to February 18,
1944, removed 804,834 cubic yards of material, at a cost of $101,702.16.
The cost of miscellaneous investigations and surveys was $2,542.05.
The total cost was $104,244.21, charged to maintenance. The expendi-
tures were $104,251.71.
   Condition at end of fiscal year.-The existing project was completed
in 1934. The controlling depths at the end of the fiscal year were as
612       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                  1.944

follows: Ship Island Bar Channel, 27 feet, Mississippi Sound Channel,
26 feet; anchorage basin, 25.5 feet.
  The total cost and expenditures under the existing project to June 30,
1944, were as follows:

                                                                  Costs
                                                                                                           Expenditures
                                             New work          Maintenance                 Total

Regular funds........
               --------------------   $70, 427.77 $1,155, 585. 58                    $1,226,013 35           $1,245,355.05
                                       47, 883. 19 ...
Public Works funds-------------- --.......                                                47, 883. 19            47, 883.19
                        --------- 118, 310. 96
      Total------...........-----...--.....                     1, 155, 585. 58       1, 273, 896. 54         1, 293, 238. 24


   Proposed operations.-The balance unexpended at the end of the
fiscal year, including an allotment of $44,000 made during July 1944,
will be applied to maintenance dredging by contract to remove shoals
in the Gulfport Ship Channel and Anchorage Basin, about 11/2 months
during April and May 1945.
   The additional sum of $35,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging by contract to remove
shoals in the Gulfport Ship Channel about 1 month.
                                  Cost and financial summary
Cost of new work to June 30, 1944---- --                               --            ---               $387, 328. 88
Cost of maintenance to June 30, 1944_                                                    .----------- 3, 467, 878. 12
        Total cost of permanent work to June 30, 1944 ---------- 3, 855, 207. 00

Net total expenditures----------------------------------                                              3,855, 207. 00
Unexpended balance June 30, 1944----------------------------5,                                               913. 54
        Total amount appropriated to June 30, 1944------------                                       3, 861, 120. 54

  Fiscal year ending June 30--        1940              1941                 1942             1943                 1944


Cost ofnew work ........
Cost of maintenance          $121, 198. 30
                          -...........             $78,884.28         $101, 147.89          $63, 090.93
                                                                                                             .       .     21
                                                                                                                 $104, 244.21
Total expended--------------  122, 092. 75          78, 814.95         101,072.06            63, 113. 98          104, 251.71

Allotted........-------------------68, 286. 99     114,000.00               60, 000.00        4,334.09             31,500.00


Balance unexpended July 1, 1943_                       -                                                   $78, 665. 25
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943_- -      -----                                                                      46, 500. 00
      Amount to be accounted for_-                                                                         125, 165. 25
Deductions on account of revocation of allotment----------15,                                                   000.-00
       Net amount to be accounted for_--                                                                   110, 165. 25
Gross amount expended----------------------                                 $104, 624. 85
Less reimbursements collected------------------                                   373. 14
                                                                                                           104, 251. 71
         Balance unexpended June 30, 1944---------                           -----------                     5, 913. 54
Amount allotted in July 1944_                                                                               44, 000. 00
       Amount available during fiscal year 1945       -------                                               49, 913. 54
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1 _    ------ ____--                                                       35, 000. 00
1Exclusive of available funds.
                  RIVERS AND HIARBORS-MOBILE,                                              ALA., DISTRICT                           613
                           24. WOLF AND JORDAN RIVERS, MISS.

   Location.-This improvement, located in the southeastern part of
the State of Mississippi, consists of dredging channels 1.6 and 2 miles
long, at the mouths of Wolf and Jordan Rivers, respectively, tribu-
taries of St. Louis Bay. It is 24 miles by water from Gulfport, Miss.,
on the east, and 54 miles from New Orleans, La. (via the inside route
through Lake Borgne, Lake Pontchartrain, and the Industrial Canal),
on the west. (See U. S. Coast and Geodetic Survey Chart No. 1268.)
   Existing project.-This provides for dredging at the mouths of
these streams channels 7 feet deep at mean low water and 100 feet
wide, extending from the 6-foot contour in St. Louis Bay to the 7-foot
contour in each stream. The length of the dredged channel at the
mouth of Wolf River is about 1.6 miles and at the mouth of Jordan
River abouit 2 miles. Under ordinary conditions, the mean tidal
range here is about 13/4 feet, and the extreme tidal range is about 31/2
feet.
   The estimate of cost for new work, made in 1906, was $30,000. The
latest (1928) approved estimate for annual cost of maintenance is
$2,000.
   The existing project was adopted by the River and Harbor Act of
March 2, 1907 (H. Doc. No. 917, 59th Cong., 1st sess.). The latest
published map is in the project document.
   Terminal facilities.-There are no terminal facilities and none are
required, as the natural landings along these streams are considered
adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1908. The controlling depths at the end of the fiscal year were as
follows: Wolf River, 7 feet; Jordan River, 7 feet. The total cost
and expenditures were $89,775.89, of which $29,195.19 was for new
work and $60,580.70 for maintenance.
   Proposedoperations.-No funds are available and no operations are
contemplated during the fiscal year 1945.
   The sum of $16,000 can be profitably expended during the fiscal year
1946 for maintenance dredging to restore project dimensions with a
hydraulic pipe-line dredge for about one-half month.
                                       Cost and financial summary
Cost of new work to June 30, 1944---------------------------                                                                 $29,195.195.
                                                                                                                                       19
Cost of maintenance to June 30, 1944-------------------------                                                                 60, 580. 70
       Total cost of permanent work to June 30, 1944------- ------ 89, 775. 89
Net total expenditures------------------------------------89, 775. 89
Total amount appropriated to June 30, 1944---------------------89, 775. 89

   Fiscal year ending June 30                1940                  1941                   1942              1943                 1944


Cost of mnte nancek-------------------------- $9,787.22                                   ------    ----------------
Total expended---------------.................. ...-------------
                                                                  $9 787.22..
                                                         ..........

Allotted            ....                    $9, 405. 59
                                     ...-----------------------    -212.78.............            .......................


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance- ------------------------------ $16, 000. 00
614    REPORT OF CHIEF OF ENGINEERS,          U. S. ARMY,   1944

                    25. PEARL RIVER, MISS. AND LA.

   Location.-PearlRiver rises in the east central part of Mississippi
and flows southwest about 172 miles to Jackson, Miss., thence south-
west about 269 miles to the head of its delta, where it divides into West
Pearl and East Pearl Rivers. The former flows about 34 miles to the
Rigolets, a tidal pass connecting Lake Pontchartrain with Lake
Borgne, an arm of the Gulf of Mexico.
   Previous projects.-Adopted by the acts of June 14, 1880, and April
21, 1900. For further details see page 950 of Annual Report for 1922,
and page 750 of Annual Report for 1938.
   Existing project.-This provides for a channel suitable for 6-foot
navigation from the mouth of West Pearl River to Bogalusa, La., by
dredging, snagging, and cut-offs at sharp bends from the mouth of
West Pearl River to a point immediately above Holmes Bayou to secure
a depth of 7 feet at low water; the construction of a lateral canal 7
feet deep and 80 feet wide extending 20.1 miles from the mouth of
Holmes Bayou to Pools Bluff with three locks of adequate dimensions;
and for the improvement of Pearl River from Pools Bluff to the mouth
of Bogalusa Creek by dredging, snagging, and easing of bends, with
suitable dams or sills in the river channel1 just below Pools Bluff and
across Bogue Chitto to maintain the levels in the canal and river.
   The estimated cost of new work, revised in 1941, is $4,110,500. The
latest (1937) approved estimate of cost for annual maintenance is
$57,000.
   The existing project was adopted by the River and Harbor Act of
August 30, 1935, subject to the approval of the Board of Engineers.
This approval is contained in House Document No. 408, Seventy-fifth
Congress, second session, which document contains the latest pub-
lished map.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-A privately owned wharf which is used for
unloading logs is located at the Pearl River highway bridge near Pearl
River Station, La. No other facilities exist except natural landings
at various locations on the river. These facilities are considered ade-
quate for existing commerce.
   Operations and results during fiscal year.-None. The cost was
$55.19 for inspection of completed portion of project, charged to new
work. The expenditures were $62.31.
   Condition at end of fiscal year.-The existing project was about 39.3
percent completed. The controlling depth for all-year navigation at
the end of the fiscal year is 7 feet from mile 0 to the site of lock No. 1
 (approximately mile 30). A depth of 1.5 feet is available during the
low-water season, June to December, inclusive, each year, along the
natural channel between the mouth of Holmes Bayou and Bogalusa,
the present head of navigation for boat traffic. A minimum depth of
6 feet is usually available over this stretch of the river from January
first to June first each year; however, due to the presence of numerous
logs, stumps, and other obstructions, navigation at the present time is
impracticable. The work remaining to be done to complete the project
consists of construction of locks 1, 2, and 3, and the Bogue Chitto and
Pools Bluff sills, clearing the low-water pools of locks Nos. 1 and 2, and
dredging and snagging the channel of Pearl River between Pools Bluff
and Bogalusa.
                      RIVERS AND                  HARBORS-MOBILE,                           ALA., DISTRICT                           615
   The total cost and expenditures on the existing project to June 30,
1944, were $1,523,182.19, all new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, plus $3,000 allotted in July 1944, a total of $6,334.81, will be
applied as follows:
Inspection of completed portion of project ---------------------                                                           $1, 534. 81
Payments for acquisition of flowage easements------------------                                                             4, 800. 00
       Total_ ----------------------------------------------                                                                6,334. 81
    No operations are contemplated during the fiscal year 1946.
                           Cost and financial summary
Cost of new work to June 30, 1944_------------------------    $1, 667, 625. 50
Cost of maintenance to June 30, 1944------------------------      168, 171. 64
       Total cost of permanent work to June 30, 1944---------- 1, 835, 797. 14

Net total expenditures------------------------------_         1, 835, 797. 14
Unexpended balance June 30, 1944--------------------------         3, 334. 81
       Total amount appropriated to June 30, 1944--------- -- 1, 839, 131. 95

    Fiscal year ending Juie 30                       1940               1941                1942              1943              1944

Cost of new work ..--------------........... $657, 486. 76          $459,167. 65          $165, 241.91       $2, 454.81              $55.19
Cost of maintenance----....         -----------------------------------------------------------
Total expended            ......                    605, 217. 99
                                        ..----------------           490, 651. 09        209, 090. 20         4, 635. 64             62. 31
Allotted.----------------------
                e.                                297,017. 00      1, 812,000.00    -----------          -1,897,000.00--     ....-


Balance unexpended July 1, 1943-                                                                                           $3, 397. 12
Gross amount expended_--------------------------                                                         $63. 18
Less reimbursements collected------------------------                                                       . 87
                                                                                                                                62. 31
     Balance unexpended June 30, 1944---------------- -----                                                                 3, 334. 81
Amount allotted in July 1944-------------------------------                                                                 3, 000. 00
     Amount available during fiscal year 1945----------- ----                                                               6, 334. 81
Amount (estimated) required to be appropriated for completion
of existing project 1 ------------------------------------                                                           2, 584, 000. 00
  1Exclusive      of available funds.
     26. F4XAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)
  The cost of work during the fiscal year was $281,368.55, all charged
to maintenance. The expenditures were $259,392.53. The balance
unexpended at the end of the fiscal year, including an allotment of
$50,000 made in July 1944, will be applied as needed during the fiscal
year 1945 to payment of expenses incurred under this heading.
  The additional sum of $69,000 can be profitably expended during
the fiscal year 1946.
                            Cost and financial summary
Cost of new work to June 30, 1944-------------------------                                                              ---
Cost of maintenance to June 30, 1944                                                                                 $2, 935, 231.     81
      Total cost of permanent work to June 30, 1944----------                                                         2, 935, 231.     81
Plus accounts receivable June 30, 1944          -4,                                                                            624.    13
       Gross total costs to June 30, 1944------------- - -                                                            2, 939, 855.     94
Minus accounts payable June 30, 1944----------       ---                                                                    5, 972.    81
       Net total expenditures _ -   -                                                                                 2, 933, 883.     13
Unexpended balance June 30, 1944                                                                                            7, 679.    43
       Total amount appropriated to June 30, 1944                                                                     2, 941, 562.     56
616            REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,                  1944


     Fiscal year ending June 30                           1940                     1941           1942               1943              1944

Cost of new work                   --................            ..........................
Cost of maintenance--------$168,288.63                                         $78, 436.67     $303,017.80      $359, 306.01          231,368.55
Total expended....-.............                        184, 141. 39             74, 332. 96   297, 103. 39      344, 107. 08         259, 392. 53
Allotted-__- ..--..-...                                 150, 335. 93             66, 617. 91   350, 000. 00      350, 000. 00          90, 000.00


Balance unexpended July 1, 1943_ -$177,                                                                                                071. 96
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942 -    -     $10, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943----------    80, 000. 00
                                                                                                                                   90, 000. 00
       Amount to be accounted for -------------------                                                                            267, 071. 96
Gross amount expended_-     ------        -  _   259, 635. 79
Less reimbursements collected-------------------      243. 26
                                                                                                                                 259, 392. 53
      Balance unexpended June 30, 1944---------------7,                                                                                679. 43
Outstanding liabilities June 30, 1944__5,                                                                                              972. 81
      Balance available June 30, 1944------------------------                                                                       1, 706.      62
Accounts receivable June30, 1944                                                                                                    4, 624.      13
      Unobligated balance available June 30, 1944-------------                                                                      6, 330.      75
Amount allotted in July 1944-------------------------------                                                                        50, 000.      00
      Amount availableduring fiscal year 1945---------------                                                                       56, 330.      75
Amount that can be profitably expended in fiscal year ending
. June 30, 1946, for maintenance 1   -         -    -     --                                                                       69, 000. 00
  1Exclusive of available funds.

27. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                       SUBMITTED

                                                                              For last full    Cost and expenditures to             Estimated
                          Name of project                                     report see             June 30, 1944                  amount re-
                                                                             Annual Re-                                              quired to
                                                                              port for-        New work        Maintenance           complete


1. Ochlockonee (Ochlockney) River, Ga. and
     Fla.' 2
2. Oostenaula and Coosawattee Rivers, Ga. 1 2                  1900                             $5, 000.00---.-----------                $20,000
                                                                1907                             32, 656. 41 .......-.....                  5, 500
3. Upper Chipola River, Fla., from Marianna
     to its mouth'--      -I-------                      -      1941                             36, 781.12       $63,193. 43                  4, 200
4. Choctawhatchee River, Fla. and Ala.' _-- _ _..              1942                            171, 884. 50      258, 907. 27           (4)
5. Holmes River, Fla.' --     ________               ----      1931                              8, 562. 05     5 36, 652. 41          (4)
6. Escambia and Conecuh Rivers, Fla. and Ala.5.                1943                            118, 336. 26      109, 568. 38          (4)
7. Tombigbee River from Demopolis,              Ala.,     to
                                - -- -- -- -- -- -- -- -- - -
      Walkers Bridge, Miss.-                                    1937                            197, 650. 71       234, 330. 73         (4)
8. Cahaba River, Ala.' 2--------__        ----------           1894                             45, 000.00-_-                          (6)
9. Tallapoosa River, Ala.'       _------                       1893                             43, 971.92 ..              .           (7)
10. Pascagoula River, Miss.'-------------------.1941                                             15,000.00         126, 321.51          (8)
11. Noxubee River, Miss. ' 2 0_ _            ___1902                                             47, 527, 52         14, 472. 48        (4)
12. Leaf and Chickasahay Rivers, Miss.' 2---...                 1919                             23, 089. 94         42, 676. 26               1, 900
13. Bluff Creek Miss.' 2 ----------------------- 1893                                             1,000.00 --------------               (4)
14. Old Town dreek, Miss.' 2             _-_                _-  1887                              3, 000. 00 .......
                                                                                                                _.....                  -7,      000
1 Chittoo Bogue, La.'M o---__--.1909
                                __015.                                                           14, 912. 60         12, 929. 94              30,000
16. East Pearl River, Miss.'----- -------.                  --- 1933                             37,127. 93          34,144. 18         (4)
17. Pearl River, Miss., Edinburg to Jackson '._ _               1911                             31, 872.06          36, 990. 55              31, 600

   1 No commerce reported.
  s Abandonmnent recommended in H. Doc. No. 467, 69th Cong., 1st sess.
  a Includes $2,160.86expended for work on La Grange Bayou, Fla.

  4 Completed.
   V
   6Channel adequate for commerce.
    The records indicate that this project has not been completed; however, the sum of $5,000 in excess of the
estimated cost has been expended.
  ' The records indicate that this project has not been completed; however, the sum of $3,846.92 in excess of
the estimated cost has been expended.
  s Maintenance only.
    That portion of the Noxubee River in Noxubee County, in the State of Mississippi, was declared non-
navigable on Feb. 24, 1934, Act S. 2337, 73d Cong., 2d sess. (48 Stat. 356).
  50 Considered unworthy of further improvements.
                    RIVERS AND HARBORS                                MOBILE, ALA., DISTRICT                                     617
                28. PLANT ALLOTMENT, MOBILE, ALA., DISTRICT
                                              Cost and financial summary
Undistributed costs June 30, 1944_ ---                            _       _______-.---------$1, 340, 116. 41

Net total cost to June 30, 1944------------------                                                --                 1, 340, 116. 41
Plus accounts receivable June 30, 1944_ ------------                                                  _             -307, 685. 20
      Gross total costs to June 30, 1944 --------------------                                                       1, 647, 801. 61
Minus accounts payable June 30, 1944_-        --   --    ---                                                           170, 815. 79

     Net total expenditures ----------------------------- 1, 476, 985. 82
Unexpended balance June 30, 1944--------------------------  217, 814. 53
           Total amount appropriated to June 30, 1944_                            ------------                      1, 694, 800. 35

    Fiscal year ending June 30                    1940             1941             1942                     1943              1944

Total expended--------------..               -$294, 915.01       $37, 301.14 -$275, 011.70                $337, 804. 58       $42,405.65
Allotted         .---------------------         163,630.89      -40, 500.00      311,100.00                501, 089.85      -588,200.00


Balance unexpended July 1, 1943_ __-------------                                                                      $848, 420. 18
Deductions on account of revocation of allotment,                                         --                           588, 200. 00
      Net amount to be accounted for-----------------------                                                               260, 220. 18
Gross amount expended--------------------       $3, 289, 729. 76
  L Reimbursements collected   $3, 242, 237. 50
ess Receipts from sales- ,--.       5, 086. 61
                                                                                  3, 247, 324. 11
                                                                                                                           42, 405. 65
                                        --------------------- 217, 814. 53
      Balance unexpended June 30, 1944....
Outstanding liabilities June 30, 1944-------------------------_170, 815. 79
      Balance available June 30, 1944_-----.--.-_-__-__        -                                                           46, 998. 74
Accounts receivable June 30, 1944_-- ------- __-    -__ ..----                                                            307, 685. 20

           Unobligated balance available June 30, 1944                            ------------                            354, 683. 94

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                                       Date trans-Recommen-
             Locality                       Authorization act           mitted to     Document No.                          dation
                                                                        Congress

Alabama-Coosa branch of                   Rivers and Harbors..................
  Mobile River system,                      Committee resolu-
  Georgia and Alabama                       tion, Apr. 28, 1936.
  (final report).
Alabama-Coosa branch of                   Commerce Commit- ............
  Mobile River system, and                 tee resolution, Jan.
  tributaries thereof, for                 18, 1939.
  flood control, navigation,
  hydroelectric power, etc.
  (final report).
Apalachicola Bay, Fla-......              Rivers and Harbors..................
                                           Committee resolu-
                                           tion, Apr. 29, 1937.
Apalachicola River, Fla.,                 River and Harbor_.....                 ..-.........
  Inland Waterway to New                   Act, Mar. 3, 1925.
  Orleans, La., and Apala-
  chicola and Chattahoo-
  chee Rivers to Columbus,
  Ga.
Apalachicola River and trib-              Sec. 1 of River and...................................
  utaries, Georgia, Alabama,                Harbor Act, Jan.
  and Florida, for naviga-                  21, 1927.
  tion, flood control, power,
  and irrigation (308 report).
Biloxi Harbor, Miss.........              Rivers and Harbors.......              ....................
                                           Committee resolu-
                                           tion, Oct. 21, 1938.
618       REPORT OF CHIEF OF ENGINEERS,                           U.   S. ARMY,         1944

Status of all investigations for navigation called for by river and harbor acts and
                          committee resolutions-Continued

                                                        Date trans-Recommen-
         Locality               Authorization act        mitted to     Document No.            Redation
                                                         Congress

Biloxi Harbor, Miss., chan-    Rivers and Harbors
  nel from Back Bay to           Committee resolu-
  Ott Bayou.                     tion, Feb. 11, 1941.
Biloxi Harbor, Miss., chan-    Rivers and Harbors
  nel to deep water in Mis-      Committee resolu-
  sissippi Sound along east     tion, Feb. 11, 1941.
  side of Deer Island.
Chattahoochee River, Ga.,      River and Harbor
  and connecting water-         Act, July 3, 1930.
  ways.
Chipola River, Fla. and        Rivers and Harbors
  and Ala., for navigation,      Committee resolu-
  flood control, power, and      tion, Jan. 21, 1942.
  related purposes.
Choctawatchee Bay to Pen-      Rivers and Harbors
  sacola Bay, Fla., Intra-       Committee resolu-
  coastal Waterway.              tion, Oct. 5, 1940.
Chunky Creek, Chickasa-        River and Harbor         Apr. 21,1944    -_____________..      Unfavorable.
  whay River, and Pasca-         Act, June 20, 1938.
  goula River, Miss., im-
  provement for navigation,
  flood control, and power.
Coosa River, Ga. and Ala.      Rivers and Harbors
   (final report).               Committee resolu-
                                 tion, Apr. 1, 1936.
Hancock County, Miss.,         River and Harbor Aug. 5, 1943 ....   .      ............. Do.
beach erosion study.            Act, July 3, 1930;
                                 Act June 26, 1936.
Harrison County, Miss.,        Act of Congress, June Sept. 25,1944 I_---____.___.___. Favorable.
  beach erosion study.           26, 1936.
Ohio River to the Gulf of      Rivers and Harbors
  Mexico, 12-foot waterway       Committee resolu-
  via the Tennessee, Tom-        tion, Oct. 5, 1943.
  bigbee, and Mobile Riv-
  ers (report to be made by
  special board).
Pascagoula Harbor and          River and Harbor
  Horn Island Pass, Miss.       Act, Aug. 30, 1935.
Pearl River, Miss., to pro-    Rivers and Harbors
  vide 9-foot channel up to      Committee resolu-
  Jackson.                       tion, June 6, 1939.
Pensacola Harbor, Fla......    Rivers and Harbors; July 31,1943        (Confidential) .....       Do.
                                 Committee resolu,
                                 tion, June 10, 1941.
St. Marks River, Fla., to      Commerce Commit-
  New Orleans, La., Intra-      tee resolution, Apr.
  coastal Waterway.              2, 1940.
Tombigbee and Tennessee        Rivers and Harbors
  Rivers, waterway con-          Committee resolu-
necting (Warrior River          tion, Feb. 27, 1934.
  route)      (under special
  board).
Warrior and Tombigbee          Rivers and Harbors
  Rivers, Ala. and Miss.,        Committee resolu-
  construction of impound-       tion, Mar. 10, 1937.
  ing dam No. 1 on Sipsey
  Fork of Black Warrior
  River, for navigation,
flood control, water pow-
  er, irrigation, etc.


            29. ALLATOONA RESERVOIR, COOSA RIVER BASIN, GA.

   Location.--The site of the proposed Allatoona Dam is on the Eto-
wah River in Bartow County, Ga., approximately 48 miles upstream
from the city of Rome, Ga., about 5 miles due east of the town of Car-
tersville, Ga., and about 2,000 feet downstream from the mouth of
Allatoona Creek. The reservoir will extend up the Etowah River
about 32 miles.
   Existing project.-The existing project provides for the construc-
tion of a reservoir for flood control, regulation of stream flow for navi-
                 FLOOD CONTROL---MOBILE,     ALA.,   DISTRICT             619
gation, and the development of hydroelectric power. The concrete
gravity type dam will be built to an approximate height of 190 feet
above the river bottom, or from elevation 690 feet to 880 feet mean
sea level with a fixed crest at elevation 835, and will be equipped
with nine taintor gates, 40 feet wide and 25 feet high, and two regulat-
ing gates 20 feet wide by 25 feet high, providing an overflow section
having a discharge capacity of 300,000 cubic feet per second with
water surface at elevation 868.8. Two 48-inch diameter sluicing con-
duits with free discharge valves are to be included in the dam. This
dam will create a reservoir covering 20,300 acres with a gross capacity
of 722,000 acre feet at elevation of 860, the top of the taintor gates.
The estimated cost is $13,644,300, for construction, and $3,755,700 for
lands and damages, including highway, railroad and utilities reloca-
tion, a total of $17,400,000. The estimated cost for annual main-
tenance and operation is $50,000. This project was authorized by the
Flood Control Act of August 18, 1941 (Public 228, 77th Cong., 1st
sess.) as outlined in House Document No. 674, Seventy-sixth Congress,
third session.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Under contract, from
March 20 to June 30, 1944, the following work was performed on a
railroad underpass on the access road: Excavated 500 cubic yards of
material; placed 41,435 pounds of steel for reinforcing concrete;
poured 75 cubic yards of class A concrete and 790 cubic yards of class
B concrete, at a cost of $26,154.89. The cost for preliminary surveys
and work incidental to the design of dam, powerhouse, and appur-
tenances, was $231,013.48. The total cost was $257,168.37, charged
to new work. The expenditures were $244,823.12.
   Condition at the end of fiscal year.-Construction work on the dam
has not been started. The work required to complete the project con-
sists of completing design of the project; completing design of gen-
erators and turbines; comp]eting negotiations for the treatment and
relocations of public utilities to be affected by the construction of the
reservoir; completing underpass on access road under the Nashville,
Chattanooga & St. Louis Railway; acquiring lands required for the
project; clearing of reservoir; constructing dam complete with all
appurtenant parts; constructing powerhouse complete with installa-
tion of two 36,000-kilowatt units and one 2,000-kilowatt unit. The
total cost under the existing project was $857,095.25 for new work.
The expenditures were $844,786.12.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $220,533.88, will be applied as follows:
Accounts payable June 30, 1944-----------------------------$40, 534. 92
New work:
    Continuing preliminary surveys, design, and
      preparation of contract plans and specifica-
      tions for dam, powerhouse, and appurtenances_$145, 353. 85
    Completing underpass on access road under the
      Nashville, Chattanooga & St. Louis Ry-------- 33, 845. 11
    Removal and temporary relocation of telephone
      lines from site of access road underpass--------- - 800. 00
                                                                  179, 998. 96

        Total-----------------------------           ------------- 220, 533. 88
620          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                 1944

   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                   Cost and financial summary
Cost of new work to June 30, 1944-_--------_______-___                                                  $857, 095. 25
Cost of maintenance to June 30, 1944___---        .  .                                                 ..-    ...

      Total cost of permanent work to June 30, 1944----------...                                          857, 095. 25
Undistributed costs June 30, 1944_   -----------------   _-_28,                                                225. 79
      Net total cost to June 30, 1944__  _-----------                                                     885, 321. 04
Minus accounts payable June 30, 1944------------------------                                               40, 534. 92

      Net total expenditures------------_ -    _844,                                                           786. 12
Unexpended balance June 30, 1944_----------------------                                                   220, 533. 88
           Total amount appropriated to June 30, 1944                    ------------                   1, 065, 320. 00

    Fiscal year ending June 30         1940            1941               1942                  1943            1944

Cost of new work ......---------------- _______ --   ____--   __       $316, 951. 88        $282,975.00       $257, 168. 37
C ost of m aintenance..........- .. ------.-.--. ...---.-.....-    -          -                  . .. . ..--.... .
                                                                                         -.---.-..-

Total expended......--       .
                         ---------------------- ------------            272, 058.,01          327, 904.99      244, 823.12
Allotted       -----------------------------------------           12,170,000.00 -9,000,000.00 -2, 104,680.00


Balance unexpended July 1, 1943_   ----- __------                                                      $2, 570, 037. 00
Deductions on account of revocation of allotment_                      --------------                   2, 104, 680. 00

       Net amount to be accounted for_-_-_---                                                         465, 357. 00
Gross amount expended------ ____-----$244,                                             828. 97
Less reimbursements collected.                                                              85
                                                                                         5-------------------
                                                                                         5.
                                                                                                      244, 823. 12
      Balance unexpended June 30, 1944---------------------                                                 220, 533. 88
Outstanding liabilities June 30, 1944_        _----40,                                                           534. 92
           Balance available June 30, 1944-             ..--------------                                    179, 998. 96
Amount (estimated) required to be appropriated for completion
                                    _
of existing project 1__ ._  ____-                    _
                                                 -_______-  -16,                                            335, 000. 00
  1Exclusive of available funds.

                         30. PRATTVILLE, AUTAUGA CREEK, ALA.
  Location.-The project is located at Prattville, Alabama, on Au-
tauga Creek, about 6.5 miles above its junction with the Alabama
River 12 miles below Montgomery, Alabama.
   Existing project.-The existing project provides for raising the
levee which flanks the north end of the power dam owned by private
interests and extending the levee upstream to a total length of about
4,600 feet with a 10-foot crown and side slopes of 1 on 5 and 1 on 3;
aleration of the dam spillways so as to increase their capacity to
approximately 22,000 cubic feet per second at a water elevation of 189;
enlarging and paving the channel, and constructing flood walls on
both sides of the creek for about 800 feet below the dam, reconstruc-
tion of a street bridge and a United States Geological Survey gaging
station in this section; clearing, grubbing, and enlarging the channel
              FLOOD CONTROL-:-MOBILE,      ALA., DISTRICT          621
for about 3,400 feet below the end of the flood walls, and lengthening
the highway bridge in this section. This improvement will protect
the town of Prattville against the largest floods of past record. The
existing project was authorized by the Flood Control Act approved
August 18, 1941 (Public 228, 77th Con., 1st sess.) as outlined in House
Document No. 657, Seventy-sixth Congress, third session. The esti-
mated Federal cQst of the project, revised in 1944, is $650,000. The
estimated cost to local interests is $10,400.
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to bear the expense of clearing and grubbing
the channel, of removal of houses, and of alterations to the existing
power dam. Assurances of local cooperation were approved by the
Chief of Engineers July 7, 1942. Requirements have been fully com-
plied with.
   Operations and results during fiscal year.-The contractor, from
July 1, 1943, to January 31, 1944, performed the following work:
Excavated 1,090 cubic yards of material from the diversion ditch;
excavated 26,151 cubic yards of material for retaining walls from the
restricted area; removed 113,275 cubic yards of material from the
channel below the Selma highway; stripped 2,141 cubic yards from the
levee base; placed 37,370 cubic yards of levee embankment; poured
11,343.9 cubic yards of concrete in the retaining walls and channel
paving; poured 139.8 cubic yards class A concrete in bridge extension;
placed 97,411.3 pounds of reinforcing steel in channel paving toe
wall; placed 552 cubic yards of weep hole gravel; placed 952.3 cubic
yards of riprap; placed 43,117 square yards of sodding; placed 143
cubic yards of roadway surfacing; constructed railroad abutment;
constructed temporary railroad span; constructed storm sewer; in-
stalled one 36-inch automatic drainage valve and two 24-inch auto-
matic drainage gates; reconstructed Geological Survey gaging station;
drove 670 square feet of steel sheet piling; and drove 1,260 linear feet
of round timber piling, at a cost of $452,386.29. The cost of prelim-
inary work including surveys, designs, and plans and specifications
was $1,041.49. The total cost was $453,427.78, charged to new work.
The expenditures were $506,917.15.
   The project was turned over to local interests for maintenance on
February 7, 1944.
   On April 26,1944, a cloudburst occurred over Prattville and vicinity,
during which 3.6 inches of rain fell in Prattville between 7:05 p. m.
and 8:30 p. m. As a result thereof the Prattville flood-control project
operated under its first severe test and the general operation of the
project was very satisfactory. Some minor flooding did occur in the
city of Prattville due to the overtaxing of local drainage facilities;
however, the damage was relatively small. Local inhabitants were of
the opinion that the project prevented what would have been one of
the most disastrous floods in the history of the community.
   Condition at end of fiscal year.-The existing project was essentially
complete in 1944. The total cost was $641,963.01, charged to new work.
The expenditures were $641,305.49.
622         REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY, 1944

   Proposed operations.-The balance unexpended at the end of the
fiscal year, $18,418.53, including accounts receivable, will be applied
as follows:
Accounts payable     -------------------------------------------              $701. 54
Available for revocation ------------------------------------               11, 405. 75
New work:
    Complete preliminary work, including surveys, designs,
      and plans and specifications, for plug dam and'
      reconditioning drainage ditch, and proposed work
         ,of
           checking prototype against results of model
      studies for project-----------------------------             $800.00
    Construct, by contract, plug dam and recondition
       drainage ditch       ------------------------------       5, 511. 24
                                                                             6, 311. 24
               Total   --------------------------------------------                                       18, 418.~53
  No operations are contemplated for the fiscal year 1946, as the
project will be completed during the fiscal year 1945.
                                     Cost and financial summary
Cost of new work to June 30, 1944__                                                                     $641, 963. 01
Cost of maintenance to June 30, 1944_

S     Total cost of permanent work to June 30, 1944-                                                    641, 963. 01
Plus accounts receivable June 30, 1944__                                                                        44. 02

  S Gross total costs to June 30, 1944_-                                                                 642, 007. 03
Minus accounts payable June 30, 1944__                                                                        701. 54

      Net total expenditures_                                                                            641, 305. 49
Unexpended balance June 30, 1944__.                                                                       18, 374. 51

          Total amount appropriated to June 30, 1944-                                -                   659, 680. 00

   Fiscal year ending June 30            1940             1941          1942                 1943              1944

Cost of new work.._ ...........-.............................         $15,047.79   $173,487.44               $453, 427.78
Cost of m aintenance...............  . . . . . .. . . . . . . ..      . . . . . .. . .. . ...              .. .
Total expended_-.......................-_-...-.-.............          13,851.60         120,536.74           506,917.15
Allotted............--------------------------------------------530,000.00          -.....                    129, 680.00


Balance unexpended July 1, 1943-_ --------------------------                                            $395, 611. 66
Amount allotted from War Department Civil Ap-
  propriation Act approved May 23, 1941.. ----                  $100, 000. 00
Amount allotted from War Department Civil Ap-
  propriation Act approved Apr. 28, 1942 .          ....---------- 29, 680. 00
                                                                                                         129, 680. 00
       Amount to be accounted for---       ----------                                                    525, 291. 66
Gross amount expended_ ____---------$510,                                            665. 56
Less reimbursements collected --------------------                                3, 748. 41
                                                                                                         506, 917. 15
       Balance unexpended June 30, 1944___                        -   -------                             18, 374. 51
Outstanding liabilities June 30, 1944_-----                               -----                     -         701. 54
      Balance available June 30, 1944_-------                                                ---          17, 672. 97
Accounts receivable June 30, 1944_- -         -----------                                                      44. 02

          Unobligated balance available June 30, 1944                  ---------------                    17, 716. 99
                            FLOOD CONTROL-'MOBILE, ALA., DISTRICT                                                          623
31. SNAGGING AND CLEARING UNDER AUTHORITY OF SECTION 2 OF
  THE FLOOD CONTROL ACT APPROVED AUGUST 28, 1937, AS AMENDED

   The Flood Control Act approved August 28, 1937, as amended by
the Flood Control Acts approved August 11, 1939, and August 18,
1941, authorized the allotment of not to exceed $500,000 from the
flood-control appropriations for any one fiscal year for the removal
of accumulated snags and other debris from, and the clearing and
straightening of channels in navigable streams and tributaries thereof
when such work is advisable in the interest of flood control; pro-
vided that not more than $25,000 shall be allotted for this purpose
for any single tributary from the appropriations for any one fiscal
year.
   No work was performed during the fiscal year. The unexpended
balance at the end of the fiscal year, $25,000, is available for revocation.
                                                Cost and financial summary
Cost of new work to June 30, 1944-___-                             -----------                                  $204, 021. 99
Cost of maintenance to. June 30, 1944_
          Total cost of permanent work to June 30, 1944                               ------------                  204, 021. 99

Net total expenditures_ _----        ---------------                                                                204, 021. 99
Unexpended balance June 30, 1944---------------_                                     ------------                    25, 000. 00

          Total amount appropriated to June 30, 1944--------------                                                  229, 021. 99

   Fiscal year ending June 30                      1940          1941              1942                1943              1944

Cost of new work---------------                  $62, 371.19   $41, 748. 64      $30, 603. 45         $25,'377.13--....            .
C ost of m aintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .                        .. .
      Total expended------------............      61,993. 88    42, 960. 04       31, 544. 57         27, 908.80

Allotted_----------.-.....               -...   -76, 366. 18    45, 000. 00       48, 900. 00          8, 755. 81


Balance unexpended July 1, 1943__ -----   ___--------$25,                                                                000. 00
Balance unexpended June 30, 1944_--------------.-------------                                                        25, 000. 00

32. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES
                   FOR FLOOD CONTROL

   The cost of work during the year was $123,402.71. The expendi-
tures were $132,831.05. The balance unexpended at the end of the
fiscal year, $109,296.43, will be applied to payment of expenses in-
curred under this heading.
   The additional sum of $150,000 can be profitably expended during
the fiscal year 1946.
                                                Cost and financial summary
Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944_------                                                     ---             $747, 973. 59
      Total cost of permanent work to June 30, 1944------------                                                     747, 973. 59
Minus accounts payable June 30, 19443,----------------                                                              -3 672. 78
      Net total expenditures---------- ---- '                                       _744,                                300. 81
Unexpended balance June 30, 1944 ----------                                                                         109, 296. 43
          Total amount appropriated to June 30, 1944--                                                              853, 597. 24
624           REPORT OF CHIEF OF ENGINEERS,                                   U.     S. ARMY,            1944


     Fiscal year ending June 30            1940              1941                  1942           1943              1944

Cost of new work--------           -----     -----------        ------        ---------------             ----------
Cost of maintenance-----------        $223,603.06         $106, 016.46        $87,279.65      $106, 095.81        $123, 402.71

                           --
Total expended..e ............         223, 630.86         107, 218. 21        77,237. 87       109, 870. 64       132, 831.05
              ...
Allotted ---------------------         183, 20.00           72, 747.24         40, 000.00       255,000. 00    -------




Balance unexpended July 1, 1943-                     --          ----------                                $242, 127. 48
Gross amount expended-----_-------------                                                                    132, 831. 05

      Balance unexpended June 30, 1944----------------------109,                                                    296. 43
Outstanding liabilities June 30, 1944---------------------------                                                 3, 672. 78

             Balance available June 30, 1944_                                                                  105, 623. 65

Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance     -_ _ __-                                                                       150, 000. 00
1Exclusive of available funds.

33. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                            For last          Cost and expenditures to           Estimated
                                                           full report              June 30, 1944                amount re-
                    Name of project                         see An-
                                                           nual Re-                                              quired to
                                                           port for-          New work      Maintenance          complete

1.   Flomaton, Escambia River, Ala............   ___           1938             1$485.25 --------------              2 $149,000
2.
3.
     Brewton, Conecuh River, Ala.................
     Rome, Coosa River, Ga-_            .-..----
                                                               1938
                                                               1941
                                                                                 1 487.10   ---------------
                                                                             366, 213.49- ........
                                                                                                                      2 235, 000
                                                                                                                       (3)
4.
5.
     Tombigbee River, Miss. and Ala   --------------
     Collinsville, Ala ---------------------------
                                                               1941          134, 801.39 .-.-.                     -150,     000
                                                               1940            71,118. 51 ------------ _               (4)
6.   Pearl River, Miss. and La., at Jackson, Miss.             1937--     .......      ----------                       210,000

     1Cost of plans and designs.
     2No funds have been allotted and no work has been done on this project.
     8Completed.
     4 Completed with funds appropriated for the maintenance and improvement of river and harbor works.

Status of all investigations for flood control called for by flood-control acts and
                                committee resolutions

                                                                 Date trans-Recom-
              Locality             Authorization acts             mitted to     Document No.                    me   ion
                                                                  Congress                                      mendation

Alabama-Coosa branch of          Rivers and Harbors
    Mobile River system,            Committee resolu-
    Georgia and Alabama            tion, Apr. 28,1936.
     (final report).
Alabama-Coosa branch of          Commerce Commit-
    Mobile River system,           tee resolution, Jan.
    and tributaries thereof,        18, 1939.
    for flood control, naviga-
    t i o n , hydroelectric
    power, etc. (Final re-
    port).
Apalachicola River a n d         Sec. 1 of River and
     tributaries, Georgia, Ala-     Harbor Act, Jan.
    bama, and Florida, for          21, 1927.
    navigation, flood control,
     power, and irrigation (308
     report).
Buttahatchee River, Ala-         Flood Control Com-
     bama and Mississippi.          mittee resolution,
                                    February 9, 1939.
Buttahatchee River, Missis-      Rivers and Harbors
   sippi and Alabama.               Committee resolu-
                                    tion, 1 Feb., 1939.
Chipola River, Florida and       Rivers and Harbors
   Alabama, for navigation,         Committee resolu-
   flood control, power, and        tion, Jan. 21, 1942.
   related purposes.
               RIVERS AND HARBORS---NEW                        ORLEANS, LA.,                DISTRICT             625

Status of all investigations for flood control called for by flood-control 'acts and
                         committee resolutions-Continued

                                                             Date trans-                                  Recom-
            Locality               Authorization acts         mitted to          Document No.            mendationi'
                                                              Congress

Chunky Creek, Chickasa-           River and Harbor Act      Apr. 21, 1944.    .......                   I Unfavorable.
                                                                                            ......---------------
  wbay River, and Pasca-          June 20, 1938.
  goula River, Mississippi,
  improvement for naviga-
  tion, flood control, and
  power.
Coosa River and tributaries,      Flood Control Act,
  Georgia and Alabama.             June 22, 1936.
Coosa River, Georgia and          Rivers and Harbors
Alabama (final report.)            Committee resolu-
                                    tion, Apr. 1, 1936. .May 15,              ....-------
Leaf and Bowie Rivers and         Flood Control Act,        May   15, 1944-   --------------------         Do.
  tributaries, Mississippi.         Aug. 11, 1939.
Luxapalila River, Alabama         Flood Control Com-
  and Mississippi.                  mittee resolution,
                                    Feb. 9, 1939.
    Do.........----------------   Rivers and Harbors
                                    Committee resolu-
                                    tion, Feb. 1939.
Noxubee River, Alabama                do.... ............
  and Mississippi.
Pearl River, Mississippi...       Flood Control Act,
                                    June 22, 1936.
    Do..................          Flood Control Act,
                                    Aug. 18, 1943.
Sipsey River, Alabama and         Flood Control Com-
  Mississippi.                      mittee resolution,
                                    Feb. 9, 1939.
    Do..................          Rivers and Harbors
                                    Committee resolution,
                                    Feb. 2, 1939.
Sucarnoochee Creek, Ala-          Rivers and Harbors
  bama.                             Committee resolu-
                                    tion, Apr. 13,1939.
Tombigbee River and trib-         Flood Control Com-
utaries, Mississsippi and           mittee resolution,
Alabama.                           May 2, 1939.
Tombigbee River and tribu-        Commerce Commit-
taries, Mississippi.               tee resolution, May
                                    2, 1939.
Warrior and Tombigbee             Rivers and Harbors
Rivers, Alabama and Mis-           Committee resolu-
sissippi, construction of          tion, Mar. 10, 1937.
impounding dam No. 1 on
Sipsey Fork of Black War-
rior River, for navigation,
flood control, water power,
irrigation, etc.


IMPROVEMENT OF RIVERS AND HARBORS IN THE NEW
           ORLEANS, LA., DISTRICT
  This district comprises all of southern Louisiana except small east-
ern and western portions, and southwestern Mississippi embraced in
the drainage basins tributary to the Mississippi River and the Gulf of
Mexico east of the easterly watershed line of the Sabine River and
Lake and south of a line from a point near Kurthwood, La., to Boyce,
La., continuing along the south bank of the Red River to the Missis-
sippi River, thence along the west bank of that river to a point west
of Warrenton, Miss., crossing the river to that place and following
southerly along the east bank to the northerly watershed line of Bayou
Pierre, thence to the westerly watershed line of the Pearl River
Basin, following along that line to the north bank of the Rigolets,
thence south of Long Point and Middle Ground Shoal to the north-
erly tip of Chandeleur Islands in Mississippi Sound. It includes the
sections of the Intracoastal Waterway from Lake Borgne Light No.
41 to the Sabine River and the Passes of the Mississippi River. It
          616634-45-pt. 1, vol. 1-40
626     REPORT OF CHIEF OF ENGINEERS,                 U. S. ARMY,      1944

exercises jurisdiction over flood-control work on the Mississippi River
from Warrenton, Miss., to the Head of Passes, in the Atchafalaya
River Basin, and over channel maintenance dredging from Warren-
ton to Baton Rouge, La., under the supervision of the president,
Mississippi River Commission. (For report on these projects see
vol. 2 of this report.)
  District engineer: Col. George H. Hudson, Corps of Engineers.
   Division engineer: Brig. Gen. M. C. Tyler, U. S. Army.
                                     IMPROV EMENTS

              Navigation                              Navigation-Continued
                                       Page                                       Page
1. Gulf Intracoastal Waterway                16. The inland waterway from
      between Apalachee Bay,                        Franklin to the Mermen-
      Fla., and the Mexican Bor-                    tau River, La____             664
      der (New Orleans district) _     626    17. Petit Anse, Tigre, and Car-
2. Southwest Pass and South                        lin Bayous, La-       -       668
      Pass, Mississippi River,                18. Mermentau River, Bayou
      La------------------_            634          Nezpique, and Bayou des
3. Mississippi River between                       Cannes, La___                 670
      Baton Rouge and New                     19. Calcasieu River and Pass,
      Orleans, La_                     644          La -__                        672
4. Bayous LaLoutre, St. Malo,                20. Lake Charles Deep Water
      and Yscloskey, La ...            647          Channel, La_                  675
5. Bayou Dupre, La                    648    21. Removing the water hya-
6. Bayou Bonfouca, La ....            649          cinths, Louisiana-            677
7. Chefuncte River and Bogue                 22. Examinations, surveys, and
      Falia, La_____                   651          contingencies (general) ---   680
8. Grand Bayou Pass, La ...           652    23. Other navigation projects
9. Barataria Bay, La_                 653          for which no estimates are
10. Bayou Lafourche, La ...            654          submitted__                   681
11. Waterway from the Intra-                  24. Plant allotment__.-        -    681
      coastal Waterway to
      Bayou Dulac, La. (Bayous                           Flood control
      Grand Caillou and Le                 25. Homochitto River, Miss..   -.--    683
      Carpe, La.)           ..         657 26. Bayou des Glaises, La ......       685
12. Bayou Grossetete, La_              658 27. Bayou Teche and Vermilion
                                                 River, La_                       686
13. Bayou Teche, La .....              659 28. Mermantau River, La ..
                                                                                  689
14. Atchafalaya River, Morgan              29. Preliminary     examinations,
      City to Gulf of Mexico,                    surveys, and contingencies
      La_..-
15. Intracoastal Waterway (5
                               -       662       for flood control-
                                           30. Other flood-control projects
                                                                              -   690
      by 40) Mississippi River                   for which no estimates are
      to Bayou Teche, La_              663       submitted__..              .     691

1. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY,
    FLA., AND THE MEXICAN BORDER (NEW ORLEA\NS DISTRICT)

   Location.-The section of the Gulf Intracoastal Waterway within
the New Orleans district extends from Lake Borgne Light No. 41,
near the mouth of the Rigolets, to the Sabine River, La. and Tex.
   The section from Lake Borgne Light No. 41 to the Mississippi River
follows the Rigolets and Lake Pontchartrain to the lake end of the
State-owned Inner Harbor Navigation Canal, thence by way of this
canal to the Mississippi River, a distance of 40.5 miles. By Public
Law No. 675, Seventy-seventh Congress, approved July 23, 1942, the
project was modified to provide for a land cut through the marsh
from the Rigolets to a point on the Inner Harbor Navigation Canal
about 2.25 miles from the Mississippi River, eliminating passage
through Lake Pontchartrain and five drawbridges, a distance of 30.8
        RIVERS AND HARBORS-NEW           ORLEANS,   LA.,   DISTRICT   627
miles to the Missisippi River by this route. From the Inner Harbor
Navigation Canal to the entrance to Harvey lock, the route follows
the Mississippi River for a distance of 5.5 miles.
    The section from the Mississippi River to Atchafalaya River, La.,
leaves the Mississippi River through Harvey lock about 3.3 miles above
Canal Street and follows Harvey Canal No. 1 and Bayou Barataria
to Bayou Villars, a land cut south of Lake Salvador to Harvey Canal
No. 2, Harvey Canal No. 2 to Larose, La., and a land cut to Houma,
La., thence over a land cut south of Bayou Black to Bayou Cocodrie,
thence through Bayou Cocodrie and a land cut to Bayou Black;
thence through Bayou Black, Bayou Chene, and Bayou Boeuf to
the Atchafalaya River about 0.5 mile south of Morgan City, La.,
.a total distance of 95.5 miles.
    An alternate route from the Mississippi River at Plaquemine (113
miles above New Orleans), follows Bayou Plaquemine and lower
Grand River to and through a dredged cut in the East Atchafalaya
Basin protection levee, thence through the levee borrow pit to Berwick
Bay; and thence through Berwick Bay to Morgan City, La., a total
  distance of 56 miles.
    The section from the Atchafalaya River to Vermilion River, La.,
  begins at the western end of the Mississippi-Atchafalaya section and
  follows the Atchafalaya River about 2.5 miles, portions of Little Wax
  Bayou, Possum Bayou, cut-offs, a land cut passing through North
  Bend Plantation to Bayou Bartholomew; Bayou Bartholomew to
  Little Bay, a land cut skirting the north edge of Cote Blanche Island
  and the west edge of Weeks Island to Vermilion River, about 24 miles
  below Abbeville, La., a total distance of about 63.6 miles.
     The section from Vermilion River to Mermentau River, La., begins
  at the western end of the Atchafalaya-Vermilion section and follows
Vermilion River 1.3 miles, a part of the Schooner Bayou cut-off canal,
  and a land cut running in a general northwesterly direction to Mer-
  mentau River at a point about 0.5 miles above its entrance into Grand
  Lake and about 16 miles below the town of Lake Arthur, La., a total
  distance of about 42.7 miles. Vermilion lock has been constructed
  about 1.75 miles west of Vermilion River to prevent the ingress of
  salt water from Vermilion Bay. Data regarding the lock are given
  in the paragraph "Existing project."
    The section from Mermentau River to Calcasieu River, La., begins
  at the western end of the Vermilion-Mermentau section and follows
  the Mermentau River upstream for about 1.5 miles, a land cut run-
  ning in a west-southwesterly direction to Lake Misere, passing north
  of the lake and Bayou Misere, westerly to Sweet Lake, south and west
  of Sweet Lake, northwesterly to Bayou Tete Bois, Bayou Tete Bois,
  Black Bayou, and cut-offs to a point on Calcasieu River about 16.6
  miles below the city of Lake Charles, La., a total distance of about 37.1
  miles.
    The section from the Calcasieu River to Sabine River, La., and Tex.,
  begins at the western end of the Mermentau-Calcasieu section and
  follows the Calcasieu River upstream about 1.6 miles, a land cut run-
  ning in a southwesterly direction 2.8 miles, thence west 22 miles to
  Sabine River at a point about 3 miles below Orange, Tex., a total dis-
  tance of about 27.1 miles.
     (See U. S. Coast and Geodetic Survey Charts Nos. 1116, 1268, and
  1269; Corps of Engineers, Mississippi River Commission Alluvial
628     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                     1944

Valley maps, Rigolets, Chef Menteur, Spanish Fort, Baton Rouge,
Grossetete, Chicot Lake, White Castle, Foster, Napoleonville, Morgan
City, Belle Isle, Bayou Sale, Jeanerette, and Derouen quadrangles;
U. S. Geological Survey maps, New Orleans (east), Chalmette, Ber-
trandville, Lake Cataouatche (east), Barataria, Cut-off, Houma, Gib-
son, Abbeville (southeast), Abbeville (southwest), Schooner Bayou
 (southeast), Schooner Bayou (southwest), Schooner Bayou (north-
east), Schooner Bayou (northwest), Grand Lake East (northeast),
Grand Lake East (northwest), Latania Lake, Lake Misere, Boudreaux
Lake, Sweet Lake, Lake Charles, Moss Lake, Black Lake, Cameron
Farms, and Phoenix Lake quadrangles; and navigation maps of Intra-
coastal Waterway, Port Arthur, Tex., to New Orleans, La.)
    Previous projects.-Previous projects for the different sections ot
this improvement were adopted by the following river and harbor
acts: August 11, 1888; March 2, 1907; March 3, 1909; June 25, 1910;
February 27, 1911; July 25, 1-12; August 8, 1917; July 18, 1918; March
2,1919; and September 22,1922. For further details see pages 878-895
of Annual Report for 1924.
    Eisting project.-This provides for a waterway 12 feet deep and
125 feet wide at mean low Gulf except in the section between Lake
Borgne Light No. 41, and New Orleans, where a width of 150 feet is
provided. An alternate route, 9 feet deep and 100 feet wide, is also
provided for between the Mississippi River at Plaquemine and Mor-
gan City. The project also provides for the following: Widening at
bends; passing places; locks or guard locks; such railroad bridges
over artificial cuts as are necessary; purchase of a pipe-line dredge;
construction of a double-leaf bascule, four-lane highway bridge with
approaches at State Highway No. 61, Louisiana; construction of bulk-
heads or jetties at Lake Borgne and Chef Menteur, La., if found nec-
essary; and for annual payments to the Board of Commissioners of
the Port of New Orleans for use of a portion of the Inner Harbor
Navigation Canal. The length of the waterway within the New Or-
leans district is 373.1 miles via the northerly or Plaquemine route and
299.4 miles via the southerly or Harvey Canal route.
    Under ordinary conditions the mean range of tide is about 10 inches
and the extreme range 14 inches. A severe storm may cause a high
tide of from 6 to 9 feet.
    The estimate of cost for new work, revised in 1943, exclusive of
amounts expended on previous projects, is $15,000,000. The latest
  (1943) approved estimate for annual cost of maintenance is $700,000,
including operation and care of locks and dams and costs pertaining to
use of necessary State-owned facilities in connection with the Inner
Harbor Navigation Canal.
                                   Harvey lock
Mlies from New Orleans, La. (Canal St.)------- 3.3.
Miles from Mississippi River__---- -----               0.13.
Width of chamber----------------------75                   feet.
Length available for full width --------------- 425 feet.
Lift------------------------------------0                 to 19.6 feet.
Depth on miter sill at low water-------------- 12 feet.
Character of foundation_------                  --     Timber piles.
Kind of dam-----------------None.
Type of construction---- ------                        Reinforced concrete.
Opened to navigation 1934 and completed 1935.
Cost (including approaches) .             -$1,775,132.24.
             RIVERS AND HARBORS---NEW                            ORLEANS,      LA.,   DISTRICT         629
                                                Plaquemine lock

Miles from New Orleans, La. (Canal St.) _ _...                          113.
Miles from Mississippi River-------.--------0.10.
Width of chamber_-------------_----__55                                    feet.
Length available for full width ---------------                         260 feet.
Lift------------------------------------0                                 to 28 feet.
Depth on miter sill at low water --------------                         10 feet.
Character of foundation --------------------                            Timber piles.
Kind of dam----                       ..---   __      ____------None.
Type of construction_-                      ---------                   Concrete.
Completed and opened to navigation                    ----------        1909.
Cost_             -           -           -       -       -        -.   $1,302,006.38.

                                                 Vermilion lock

Miles from Abbeville, La_         -------------------                   26.
Miles from Vermilion River_----                    --                   1.75.
Width between abutments_-----                      --                   56 feet.
Length available for full width---------------                          1,182 feet.
Lift_------------                                                       0 to 5 feet, either direction.
Depth on gate at mean low Gulf level---------                           12 feet.
Character of foundation_              ---------                         Timber piles.
Kind of dam_---------------------                     --                Reinforced-concrete spillway
                                                                          dam, vertical cast-steel gates,
                                                                           timber-pile foundations.
Type of construction-----------------------                             Reinforced concrete.
Opened to navigation 1933 and completed 1934.
Cost -----------------------------------                                $330,765.27.
  The existing project was authorized by the following river and
harbor acts:

     Acts                                Work authorized                                 Documents


Mar. 3,1925      Construction of waterway from New Orleans, La., to              H. Doc. No. 238, 68th Cong.,
                  Galveston Bay, Tex.                                             1st sess. (Contains latest
                                                                                  published map.)
Jan. 21,1927     Extension of waterway to Corpus Christi, Tex ..........            Do.
July 3, 1930     A channel 100 feet wide and 9 feet deep from Lake Pont-         H. Doc. No. 341, 71st Cong.,
                  chartrain to Mississippi Sound.                                 2d sess.
June 26,19341    Operation and care of locks and dams provided for with
                  funds from War Department appropriations for rivers and
                  harbors.
July 23,1942     Enlargement of waterway from 100 feet wide and 9 feet deep Public Law 675, 77th Cong.,
                  to 125 feet wide and 12 feet deep, from Apalachee Bay,         and report of the Chief of
                  Fla., to Corpus Christi, Tex., and its extension to the vicin- Engineers, April 27, 1942.
                  ity of the Mexican border, except between Mobile Bay,          (Report not printed.)
                  Ala., and New Orleans, La., where the width shall be 150
                  feet; and for rental of Inner Harbor Navigation Canal
                  facilities.


  1 Permanent Appropriations Repeal Act.
  NoTE.-The latest published map is printed in H. Doc. No. 230, 76th Cong., 1st sess.

  Recommend'ed modifcations of project.--In Senate Document No.
188, Seventy-eighth Congress, second session, it is recommended that
the existing project be modified to provide an alternate waterway
connection with the Mississippi River in the vicinity of Algiers, La.,
at an estimated cost to the United States of $8,000,000 for construc-
tion and $120,000 annually for maintenance and operation in addition
630    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,            1944

to the amount now required, subject to certain requirements of local
cooperation.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-The terminals at New Orleans which are most
generally used by Intracoastal Waterway traffic are those controlled
by the State of Louisiana on the Inner Harbor Navigation Canal.
Since April 1, 1944, the portion from the Mississippi River to its
intersection with the New Orleans-Rigolets section of the Gulf Intra-
coastal Waterway has been undei lease to the United States and is
now operated by the United States toll-free, 24 hours per day. Except
for the terminal facilities at New Orleans, facilities are in general
confined to privately owned piers, wharves, or oil docks. At Morgan
City on the Atchafalaya River there are two large and three small
wharves open to all without charge. The facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year-New worl.-New work
by leased plant and contract dredges was performed as follows:
1,325,006 cubic yards of material were removed in the section from
light No. 41 in Lake Borgne to the Mississippi River (via a portion
of Inner Harbor Navigation Canalf), New Orleans, La., for enlarge-
ment to new project dimensions, at a cost of $85,556.35; 21,275,338 cubic
yards were removed in the Mississippi-Atchafalaya section for en-
largement to new project dimensions, at a cost of $2,029,719.45; 3,227,-
861 cubic yards of material were removed from the Atchafalaya-Ver-
milion section for enlargement to new project dimensions, at a cost
of $498,451.47; 5,033,930 cubic yards of material were removed from
the Vermilion-Mermentau section for enlargement to new project
dimensions, at a cost of $820,021.39; and 2,321,491 cubic yards were
removed in the Mermentau-Calcasieu section for enlargement to proj-
ect dimensions, at a cost of $241,797.17. Retaining dikes were con-
structed in the Mississippi-Atchafalaya section at a cost of $8,982.68.
    Utilities crossing the relocated portion of the waterway between
Larose and Bourg, La., in the Mississippi-Atchafalaya section, were
altered by reimbursement agreements at a cost of $13,606.47, and in
the Lake Borgne-Mississippi section at a cost of $2,471.96.
    New work by Government plant and hired labor consisted of: Pre-
liminary surveys and mapping; procurement of local cooperation in
obtaining rights-of-way; removing 556,152 cubic yards of material
for enlargement to new project dimensions; constructing a road bed
across the abandoned channel of the Intracoastal Waterway near
Bourg. La., clearing and snagging operations; and constructing a
movable highway bridge across the Intracoastal Waterway at Larose,
La., all in the Mississippi-Atchafalaya section, at a cost of $331,460.12.
Condition survey of the Inner Harbor Navigation Canal, lock and
bridges from 3,000 feet north of Florida Avenue to the Mississippi
River, New Orleans, La., at a cost of $2,507.11; removing 777,831 cubic
yards from the Vermilion-Mermentau section at a cost of $116,247.30;
removing an island, 38,217 cubic yards, from the Mermentau-Calcasieu
section at a cost of $7,637.55; excavating temporary ferry slips at a
cost of $18,525.52; and marking rights-of-way at a cost of $8,534.39.
   Maintenance.-Dredgingby leased plant consisted of the removal
of 39,791 cubic yards of shoal material from the river approach to
Harvey lock in the Mississippi-Atchafalaya section at a cost of $7,-
440.83; and 14,648 cubic yards of shoal material from the river ap-
        RIVERS AND HARBORS-NEW          ORLEANS,   LA., DISTRICT   -631


proach to Plaquemine lock in the Plaquemine-Morgan City Alternate
route at a cost of $13,291.23.
   Maintenance dredging by Government plant and hired labor was
performed as follows: 50,132 cubic yards of shoal material were re-
moved from the forebay of Harvey lock, Louisiana, at a cost of $8,-
227.46; river deposits were removed from the low gate recesses at
each end of Harvey lock chamber, Louisiana, at a cost of $646.56;
and 66,280 cubic yards of shoal material were removed from the fore-
bay of the Inner Harbor Navigation Canal, Louisiana, at a cost of
$12,183.57. Periodic inspection of the waterway and removal of ob-
structions, as required, were accomplished during the year at a cost
of $11,256.13. Engineering studies and surveys were made at a cost
of $707.36. Inspecting and repairing automatic tide gages during
the fiscal year cost $247.64.
   Rental payment to the Board of Commissioners, Port of New Or-
leans, La., for use of Inner Harbor Navigation Canal facilities for
period April 1 to June 30, 1944, including overhead, was $66,000,
maintenance.
   Harvey, Plaquemine, and Vermilion locks were operated throughout
the fiscal year. Inner Harbor Navigation Canal lock and bridge were
operated by the United States Government from April 1 through
June 30, 1944.
   The locks, grounds, and structures were maintained in good condi-
tion, and all necessary and routine work thereon performed by,hired
labor at a cost of $211,574.77 (operating and care).
   The cost of operating the Paris Road pontoon bridge and the Flor-
ida Avenue Bridge to the end of the fiscal year was $23,350.18 (oper-
ating and care).
   The total costs were $4,542,209.75, of which $4,187,284.02 was for
new work, $120,000.78 for maintenance, and $234,924.95 for opera-
tion and care of locks and bridges. The total expenditures were
$4,691,963.18. Included in total costs of new work for fiscal year is the
amount of $1,762.09, Government costs on construction of dikes at
Micheaud, La., and construction of temporary highway bridge at
Paris Avenue, New Orleans, La., completed during fiscal year 1943
and not previously reported.
   Condition at end of fiscal year.-The existing project before modi-
fication by Public Law No. 675, Seventy-seventh Congress, approved
July 23, 1942, was completed in 1936. Dredging to modified project
dimensions was completed in 1944. The existing project, as modified,
is 93 percent conmplete.
   Harvey lock was completed in 1935; the reservation comprises 3.3
acres. Plaquemine lock was completed in 1909; its reservation com-
prises 19 acres. Vermilion lock was completed in 1934; the ground
on which it is constructed is possessed by the United States under an
easement deed to a strip of land 300 feet wide along the Intracoastal
Waterway. Dredging of the canal was completed in 1934. Inner
Harbor Navigation Canal facilities were leased by the United States
from the Board of Commissioners of the Port of New Orleans, effec-
tive April 1, 1944.
   The controlling depths and widths at mean low Gulf level on June
30, 1944, were as follows: New Orleans-Rigolets section, 10.5 feet by
150 feet. (Shoaling has occurred in the Lake Borgne area between
mile 35.7 and mile 36.4 east of Harvey lock in vicinity of Lake Borgne
632      REPORT OF CHIEF OF ENGINEERS' U. S. ARMY,                         1944

Light No. 41. The remainder of the section has a controlling depth
of 12 feet); Mississippi-Atchafalaya section, 12 feet by 125 feet;
Atchafalaya-Vermilion section, 12 feet by 125 feet; Vermilion-Mer-
mentau section, 12 feet by 125 feet; Mermentau-Calcasieu section, 12
feet by 125 feet.; Calcasieu-Sabine section, 30 feet over a bottom width
of approximately 100 feet, and 12 feet over a bottom width of 125 feet.
   Work required to complete the existing project, as modified, con-
sists of constructing a permanent bridge at Paris Road, New Orleans,
La., and bulkheads and jetties at Chef Menteur and Rigolets in the
New Orleans-Rigolets section; and completion of alterations to utility
crossings in the Mississippi-Atchafalaya section.
   The total costs under the existing project to the end of the fiscal
year (all funds) have been $16,627,362.14, of which $13,501,271.35 was
for new work (including $353,541.19 Public Works funds), $1,712,-
853.83 (including $5,762.38, costs, not previously reported, trans-
ferred to this district with that part of the project formerly under
the Mobile district) for maintenance, and $1,413,236.96 (excluding
$521,484.91, costs for works of improvement under provisions of the
permanent indefinite appropriation for such purpose) for operation
and care of locks and bridges. The total expenditures have been
$16,448.760.64. In addition the sum of $521,484.91 was expended be-
tween January 1, 1927, and June 30, 1935, on the operating and care
of works of improvement under the provisions of the permanent
indefinite appropriation for such purpose.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $510,639.87, plus an allotment of $755,000 made during
July 1944, will be applied as follows:
Accounts payable June 30, 1944__---.               -------------              $174, 821. 22
New work:
    By contract:
         Highway relocation at Bourg and Larose,
           July 1, 1944, to May 31, 1945- -$86,                       000. 00
         Temporary oil, gas, telephone, and power
           lines over Bourg-Larose Cut-off, July 1,
           1944, to Nov. 30, 1944_-- -            ------          65, 000. 00
              Total new work_--         __-------..--------151,                    000. 00
Maintenance:
    By contract:
         Reconstruction of fenders at Harvey lock
           from July 1, 1944, to Dec. 31, 1944-..... $67, 000. 00
    By hired labor:
         Maintenance dredging, from Sept. 1, 1944,
           to May 31, 1945-___        ---------                  229,000.00
    Operation     and     maintenance         of
      Plaquemine lock:
         Operation_        --------              $62,000.00
         Ordinary      maintenance         and
           repair_--------------------              10, 000. 00
                                                                  72, 000. 00
    Operation and maintenance         of Har-
      vey lock:
         Operation----------                        67, 000. 00
         Ordinary      maintenance         and
           repair_- -           -----               10, 000. 00
                                                                  77, 000. 00
    Operation and maintenance         of  Ver-
      milion lock:
         Operation.--.- ----                        40, 000. 00
         Ordinary maintenance              and
           repair_- ----------                       8, 000. 00
                                                                48, 000. 00
          RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                         633
Maintenance-Continued.
   Operation and maintenance of Inner
      Harbor Navigation Canal lock, and
      2 bridges:
        Rental payments-                 $264, 000. 00
        Operation, lock and bridges --    127, 000. 00
        Ordinary     maintenance     and
      S    repair_-   -                     7, 000. 00
                                                                     $398, 000. 00
     Operation and maintenance of Paris
      Road Bridge:
         Operation -------------------                 21, 000. 00
         Ordinary         maintenance  and
            repair----------------                      2000.00
                                                        2,
     Errgineering, supervision, and contingencies              -- 23, 000. 00
                                                                  25, 818. 65
              Total maintenance -----------------------------                          $939, 818. 65
             Total new work and maintenance -----------------                         1, 265, 639. 87
  The additional sum of $750,000 can be profitably expended during
the fiscal year 1946 as follows:
Hired labor:
    Maintenance dredging during the period August 1945 to May 1946 $140, 000
    Engineering surveys, supervision, and contingencies.-------------                 10, 000
    Operation and maintenance of Plaquemine lock:
         Operation ----------------------------------                       $62,000
         Ordinary maintenance and repair----------------                     10, 000
                                                           lock:000                   72, 000
    Operation and maintenance             of   Harvey
         Operation_       -------------------------------                    67, 000
         Ordinary maintenance and repair----------------                     10, 000
                                                                                      77, 000
    Operation and maintenance of Vermilion lock:
         Operation- ---------------------------------                        40, 000
         Ordinary maintenance and repair_                 -----------------   8, 000
                                                                                      48, 000
    Operation and maintenance of Inner Harbor Navigation
       Canal lock and 2 bridges:
         Rental payments ----------------------------                       246, 000
         Operation ----------------------------------                       127, 000
         Ordinary maintenance and repair.               ---------------       7, 000
                                                                                     380, 000
    Operation and maintenance of Paris Road Bridge:
         Operation ----------------------------------                        21, 000
         Ordinary maintenance and repair-----------------                     2, 000
                                                                                      23, 000

             Total maintenance ---------------------------------                            750, 000

                                 Cost and financial summary
Cost of new work to June 30, 1944 ----------------------                       1   $17, 548, 702. 20
Cost of maintenance to June 30, 1944---------------------                          2 4, 650, 782. 05

      Total cost of permanent work to June 30, 1944 _---                             22, 199, 484. 25
Undistributed costs June 30, 1944_ -   ------------                                        1, 982. 10
      Net total cost to June 30, 1944---------------------                           22, 201, 466. 35
Minus accounts payable June 30, 1944 ---------------------                               174, 821. 22
                           --------------------------
      Net total expenditures_                                                  1 2   22, 026, 645. 13
Unexpended balance June 30. 1944-...     -     -510,                                          639. 87
        Total amount appropriated to June 30, 1944                   -         1 2 22, 537, 285. 00
1 In addition $273,266.97 expended from contributed funds for new work.
s Includes $1,070,432.58 from Permanent Indefinite Appropriation.
634         REPORT OF CHIEF OF ENGINEERS,                                    U.       S. ARMY,                1944


   Fiscal year ending June 30                  1940          1941                 1942                 1943              1944

Cost of new work _.......            _.._.... .....                        __..
                                                                          ...       -... --   .   $2,087,173.16      $4,187, 284.02
Cost of maintenance ---------            $196,067.12      $177, 360.64      $608, 938. 59           308, 609. 58        354, 925. 73
      Total cost   ---------------         196, 067. 12    177, 360.64       608, 938. 59         2, 395, 782. 74     4, 542, 209. 75

Total expended.----------------190,969.15                  181, 640. 73      585, 071.86          2,110, 031.37       4, 691,963.18
Allotted-.---.-----------.----242,000.00                   210,000. 00       670, 924. 67         3,161,181.07        3, 714, 265. 27


Balance unexpended July 1, 1943_- -     --.---------                                                          $1, 488, 337. 78
Amount allotted from War Department Civil
  Appropriation Act approved May 23, 1941---                  $7. 20
Amount allotted from War Department Civil
  Appropriation Act approved June 2, 1943-..            300, 000. 00
Amount allotted from War Department Civil
  Appropriation Act approved June 24, 1940---                258. 07
Amount allotted from Second Deficiency Appro-
  priation Act 1943, approved July 12, 1943_--       3, 414, 000. 00
                                                                                                               3, 714, 265. 27
      Amount to be accounted for -------------------------                                                     5, 202, 603. 05
Gross amount expended---- ------------                                                                         4, 691, 963. 18
       Balance unexpended June 30, 1944-.... ------                                                                 510, 639. 87
Outstanding liabilities June 30, 1944          $76, 077. 90
Amount covered by uncompleted contracts------ 99, 353. 85
                                                                                                                    175, 431. 75
     Balance available June 30, 1944---------                                                                       335, 208. 12
Amount allotted in July 1944_______                                                                                 755, 000. 00
          Amount available during fiscal year 1945-----------                                                  1, 090, 208. 12
Amount (estimated) required to be appropriated for completion
of existing project 3    _-     .       -   -     -     -                                                     1, 000, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 3_                                                                                   750, 000.00
  8Exclusive of available funds.

     2. SOUTHWEST PASS AND SOUTH PASS, MISSISSIPPI RIVER, LA.

  Location.-Southwest Pass is the westermnost of the mouths of the
Mississippi .River. It flows in a generally southwesterly direction.
The entrance from the Gulf of Mexico is 115 miles from New Orleans,
La.; 160 miles from Mobile, Ala., on the east; and 330 miles from Gal-
veston, Tex., on the west. South Pass is the central one of the three
main mouths. It flows in a generally southeasterly direction. The
entrance from the Gulf of Mexico is 108.8 miles from New Orleans,
La.; 141 miles from Mobile, Ala., on the east; and 349 miles from
Galveston, Tex., on the west. (See U. S. Coast and Geodetic Survey
Chart No. 1272 and U. S. Geological Survey maps Cubits Gap, Pas
a Loutre (west) Southwest Pass, South Pass, Burrwood, and Mud
Pan Bayou quadrangles.)
  Previous projects.- (a) Southwest Pass.-Authorized by River and
Harbor Acts of July 4, 1836, March 3, 1837, August 30, 1852, July 8,
1856, March 2, 1867, and March 3, 1873. For further details see
page 1847, Annual Report for 1915, and page 767, Annual Report for
1938.
   (b) South Pass.-None.
             RIVERS AND HARBORS-NEW                         ORLEANS, LA., DISTRICT                     635
   Existing project- (a) Southwest Pass.-This provides for a chan-
nel through Southwest Pass 1,000 feet wide and 35 feet deep. The
general plan of improvement provides for contracting the pass to a
uniform cross section with approximately 1,420-foot surface width by
means of jetties, spur dikes, and bulkheads; for channel improvement
by dredging and retaining the dredged material between the dikes,
bulkheads, and jetties; for dredging a channel through the outer bar
inclining to the left of the jetty axis; for the construction of small
revetted openings through the narrow portions of the banks of the
pass for purpose of strengthening these banks; for closure of minor
outlets not required for maintenance of the banks; for the construc-
tion of sills to prevent the enlargement of The Jump and Cubits Gap;
for dredging to elevation minus 55 feet in the river at Head of Passes
as far up as Cubits Gap, a distance of 3.5 miles; for repairs to sill
across Pas a Loutre and bank revetment at Head of Passes; for con-
struction of dikes with a view to reducing the width of the river above
Head of Passes; for the construction of a submerged deflecting dike
above the Head of Passes; and for other minor work. The plane of
reference is mean low water. The east jetty is approximately 4.8
miles in length and the west jetty 3.8 miles. The jetties are composed
of a substructure of brush mattresses, originally built to about the
elevation of mean low water, surmounted with a superstructure of
concrete and large riprap. Spur dikes are composed of cribwork of
round piling filled with willows and stone, or with a curtain of round
piles along the upstream face.
   The estimate of cost for new work, revised in 1941, is $18,000,000,
exclusive of amounts expended on previous projects. The latest (1928)
approved estimate for annual cost of maintenance is $415,000 for a
channel width of 500 feet and $680,000 for a width of 1,000 feet.
   The existing project for Southwest Pass was authorized by the
following river and harbor acts:

               Acts                            Work authorized                            Documents


June 13, 1902-------------------For a navigable channel of 35-foot depth,       H. Doc. No. 329, 56th Cong.,
                                     the details of the work subject to modi-    1st sess., and Annual Re-
                                     fication at the discretion of the Secre-    port, 1900, p. 2287.
                                     tary of War.
May 28, 1908-....------------....--- Dredging shoals between Head of Passes     Specified in act.
                                     and Cubits Gap.
Mar. 3, 1909-----------------Provision made for increasing the plant                Do.
                                     by the addition of a large dredge.
Authority of Secretary of War,     Further contraction of the lower mile of     Interim report of board on
  Oct. 31, 1934.                     the jetty channel to a width of 1,420       revised plan for navigation
                                     feet by means of dikes, and removal of      structures, Cubits Gap to
                                     the sill across the head of South Pass.     the mouths of the Passes,
                                                                                  Oct. 20, 1934.
Authority of Secretary of War,     Spur dikes at the head of Southwest Pass     Second interim report of
Sept. 20, 1935.                     and the construction of new dikes and        board on revised plan for
                                    extension of existing dikes on the east      navigation structures, Cu-
                                    bank of the Mississippi River at Pilot-      bits Gap to the mouths of
                                     town, La.                                    the Passes, July 12, 1935.
636       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                    1944


             Acts                             Work authorized                          Documents

Authority of Secretary of War,    Additional spur dikes at the head of        Final report of board on re-
July 22, 1936.                     Southwest Pass and construction of          vised plan for navigation
                                    new dikes and extension of existing         structures, Cubits Gap to
                                   dikes in the lower jetty channel, South-      the mouths of the Passes,
                                   west Pass.                                     Dec. 20, 1935.
Authority of Secretary of War,    Dredging in Mississippi River between       Interim report of board of
June 30, 1938.                     Cubits Gap and Head of Passes to bot-       officers appointed to deter-
                                   tom elevation of -55 feet and construc-      mine what work may be
                                   tion of bank control structures and          advisable to complete the
                                   channel correction dredging in South-        existing project for South-
                                   west Pass below mile 10.                     west Pass, Mississippi
                                                                                River *     *   * dated June
                                                                                10, 1938.


  For latest published map see H. Doc. No. 215, 76th Cong., 1st sess.

   (b) South Pass.-The existing project authorized James B. Eads
and associates to construct permanent and sufficient jetties and auxil-
iary works necessary to secure and maintain for a period of 20 years
through the pass a channel 26 feet in depth and not less than 200 feet
wide at the bottom and having through it a central depth of 30 feet,
without regard to width; at the termination of the maintenance period
the channel to be maintained by the United States; construction and
maintenance of sill and submerged deflecting dikes across head of
South Pass and maintenance of sill across Pas a Loutre, removal of
west dike, and construction of submerged and spur dikes at Head of
Passes; for dredging a channel 35 feet deep, no width specified,
through the shoals in the river between Cubits Gap and Head of Passes
31/2 miles; and for a seaward extension of the west jetty at mouth of
pass; removal of false point at the head of South Pass to elevation
minus 45 feet and revetting new bank line. The east jetty foundation
is 12,070 feet long. Inner east jetty is 11,170 feet long. The west
jetty is 7,820 feet long. Inner west jetty is 790 feet long. The jetties
are composed of a substructure of brush mattresses surmounted by a
superstructure of concrete. Auxiliary works are spur dikes and inner
jetties, which are composed of a cribwork of round piling filled with
willows and stone.
   The plane of reference is mean low water. Variation of water sur-
face is 16 inches at the mouths and 10 inches at the heads of the passes,
due to tides. The extreme range of tide at the mouths of the passes is
28 inches.
   The amount paid James B. Eads and associates was $8,000,000, be-
ing the total cost of new work. The latest (1928) approved estimate
for annual cost of maintenance is $150,000.
             RIVERS AND HARBORS-NEW                                 ORLEANS, LA.,             DISTRICT                  637
   The existing project for South Pass was authorized by the following
river and harbor acts:

                Acts                                   Work authorized                                Documents


Mar. 3, 1875........-----------------..             Authorized James B. Eads and asso-
June 19, 1878_------------------
                     ..                              ciates to create and maintain a wide Specified in acts.
Mar. 3, 1879.................-----------------.       and deep channel.
June 6, 1900 1 _.------For                              maintenance by the United States           Do.
                                                     and the appropriation of not exceeding
                                                     $100,000 annually for that purpose.
May 28, 1908.-----------------For dredging in the river ............----------------               Do.
                                                    Removal of west dike and construction Report by Board of Engineer
                                                     of spur dikes and bank revetment at        officers (Annual Report
                                                     Head of Passes.                            1916, pp. 2420-2426).
Authority of Secretary of War, Removal of the sill across the head of Interim report of board op re-
  Oct. 31, 1934.                                      South Pass.                               vised plans for navigation
                                                                                                structures, Cubits Gap to
                                                                                                the mouths of the Passes,
                                                                                                Oct. 20, 1934.
June 26, 1934-----------------..................... For continuing maintenance operations Permanent Appropriations
                                                     with funds from regular annual War         Repeal Act.
                                                     Department appropriations.
Authority of Secretary of War, Improvement at the head of South Pass Interim report of board of offi-
  June 30, 1938.                                     by removal of the false point at this      cers appointed to deter-
                                                     locality to a bottom elevation of at least mine what work may be
                                                     minus 45 feet, including revetment of      advisable to complete the
                                                     the new bank line.                         existing project for South-
                                                                                                west Pass, Mississippi
                                                                                             River       *   *    *, dated June
                                                                                             10, 1938.


  1 Emergency Act.
  For latest published map see H. Doc. No. 215, 76th Cong., 1st sess.

    Prior to the fiscal year 1936, the projects Southwest Pass, Missis-
sippi River, La., and South Pass Channel, Mississippi River, La.
(Maintenance), were reported upon as separate projects.
  Recommended modifications of project.-Under date of February
25, 1939, the Chief of Engineers recommended that the existing proj-
ects for Mississippi River, Baton Rouge to New Orleans, and for
Southwest Pass and South Pass, Mississippi River, be modified and
combined, and a project covering the Mississippi River from New
Orleans to the Head of Passes be added thereto, to provide a single
project, Mississippi River, Baton Rouge to the Gulf of Mexico, with
channel dimensions as follows:

                                                                                                  Depth
                                                                                                (mean low            Width
                                                                                                  Gulf)

                                                                                                      Feet             Feet
Baton Rouge to New Orleans----.....---                      ---------------------------------------          35              500
Port limits of New Orleans ------------------------------------------------                                  35           1, 500
New Orleans to Head of Passes---------------------------------------------                                   40           1, 000
Southw est Pass---
                 ................................................                                            40              800
Southwest Pass Bar Channel -_----------------------------------------------                                  40              600
South Pass---    -----------------------------------------------------                                       30              450
South Pass Bar Channel----------                                                                             30              600
638    REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,          1944

    The estimated cost for new work is $4,200,000, and $250,000 annu-
ally for maintenance, all in addition to amounts now authorized for
existing projects (H. Doc. No. 215, 76th Cong., 1st sess.).
    Terminal facilities.-Some 100 piers, wharves, or docks serve the
port of New Orleans. Practically all wharves on the east or left
bank parallel the river bank forming nearly a continuous covered
quay about 10 miles long.
    Public wharves controlled by the Board of Commissioners of the
Port of New Orleans (the dock board) cover 62 percent of the improved
water front. The board also controls the terminal facilities on the
Inner Harbor Navigation Canal (the Industrial Canal) which connects
the Mississippi River with Lake Pontchartrain and turning basin
 (1,000 by 1,000 feet). Since April 1, 1944, the portion of the Inner
Harbor Navigation Canal from the Mississippi River to its intersec-
tion with the New Orleans-Rigolets section of the Gulf Intracoastal
Waterway, exclusive of terminal facilities, but inclusive of the lock
and the bridges at St. Claude Avenue ana at Florida Avenue, has been
under lease to the United States and is now operated by the United
States on a toll-free basis, 24 hours per day. From the turning basin
to the river the canal has a controlling depth of 30 feet. A quay
wharf of reinforced concrete, 265 feet wide by 2,400 feet long owned
by the dock board is located on the west bank of the canal.
   All public port facilities are served by paved roadways (generally
city streets) and by the Public Belt Railroad, municipally owned and
operated, which connects with all 12 trunk lines entering New Orleans.
   The existing terminal facilities include a ship-side grain elevator,
general cargo and cotton wharves, fruit landings, bunkering facilities,
terminal warehouses, railroad terminals, marine railways, and dry-
docks. They are considered adequate for present commerce. (For
further details see Port Series No. 5, Port of New Orleans, Corps of
Engineers, revised 1938.)
   Oparations and results duwring fiscal year.-(a) Southwest Pass.-
No new work was performed.
   Maintenance work consisted of the dredging of 1,901,948 cubic yards
of material in the bar and jetty channels, mile 16.2 to 19.3, by con-
tract, and 895,004 cubic yards of material by the U. S. hopper dredge
Benyaurd; also 418,736 cubic yards of material from the Head of
Passes (entrance to Southwest Pass) by contract, and 474,420 cubic
yards of material by the U. S. hopper dredge Benyaurd; repair and
maintenance by hired labor of permeable pile dikes, bulkheads, jetties,
outlets and revetments, routine channel surveys and miscellaneous hy-
draulic investigations, examinations and observations. Repairs to
dike No. 3 at Pilottown were completed as well as construction of per-
meable pile dikes in Outlet at mile 8.7 and Outlet E-1. Installation of
four automatic tide gages at Head Southwest Pass, Head Cubits Gap,
Venice Gage, and at Main Pass was completed. Raising of concrete
cap on outer end west jetty still remains about 20 percent complete.
No work was done on resetting concrete cap and filling excess voids on
the east jetty. Repairs to West Headland Dike remain partially corn-
          RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                             639

plete. Burrwood reservation shore plant and facilities were main-
tained.
   Costs were as follows:
Maintenance by contract: Dredging------------------------           $108, 327. 11
Maintenance by hired labor:
    Dredging-------------------------------- -----                   245, 600. 84
    Maintenance and repair of dikes, bulkheads, jetties, and other
      structures                                                           470. 71
                                                                        2,----------------------------
    Maintenance and repair'of outlets and revetments-             .    23, 956. 77
    Raising concrete cap on outer end west jetty---_-------- -               None
    Resetting concrete cap and filling excess voids with salvage
      stone, east jetty --------------------------------------               None
    Examination and surveys of channels and structures- -........      29, 137. 45
    Hydraulic surveys and investigations.----------------------        19, 737. 85
       Total maintenance ----------------------------------                  429, 230. 73
   (b) South Pass.-Maintenance work was performed during the
fiscal year which consisted of the dredging of 274,649 cubic yards of
material from the South Pass Bar Channel by the U. S. hopper dredge
Benyaurd; of the repair and maintenance, by United States plant and
hired labor, of outlets, revetments, and banks of South Pass; and of
routine channel and hydraulic surveys. Port Eads reservation was
maintained.
   Costs were as follows:
Maintenance by contract ------------------------------------                       None
Maintenance by hired labor:
    Dredging -----------        _-----    -------     --------               $24, 443.   33
    Maintenance and repair of dikes, revetments, and banks .. __-              2, 391.   81
    Examination and surveys of channels and structures - -      -              5, 141.   90
    Hydraulic surveys and investigations------      ---- - - --                3, 483.   15
       Total maintenance ----------------------------                         35, 460. 19
   Total costs for the combined project (Southwest Pass and South
Pass) were $464,690.92 which were all for maintenance; total expen-
ditures were $285,315.68.
   (c) Hydraulic surveys, investigations, and studies, begun during the
fiscal year 1938, continued through 1944. Data obtained included
complete hydrographic surveys of Southwest Pass and South Pass and
the river below Wilder Flats as required; continuous water-level
records at controlling poihts throughout the passes; discharge mea-
surements in each of the three main passes, and gagings of minor out,
lets; soundings by supersonic depth finder of four longitudinal ranges;
analyses of the materials at the bottom from samples obtained; and
construction and operation of a model at the United States Waterways
Experiment Station for testing new work plans and studies for reduc-
tion of maintenance. Periddic surveys were made of South and South-
west Passes, of both Bar Channels, at the Head of the Passes, at Pas a
Loutre, and at Cubits Gap.
640          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                            1944

   Average discharges at each of the three main passes in percentages
of the total discharge of the river at the Head of Passes during the
flood cycles are as follows:

                      1935     1936     1937     1938   1   19391     1940   1   1941 2    1942      1943    1944

Southwest Pass....    39.96    37.91    39.52     38.57      36.62     36.31      38.03    37.20     38.37    38.15
South Pass.--------   17.31    18.07    17.63     17.99      18.80     17.29      16.66    17.04     17.28    17.39
Pas a Loutre-.....    42.73    44.02    42.85     43.44      44. 58    46.40      45.31    45.76     44.35    44.46
      Total-....      100.00   100.00   100.00   100.00     100.00    100.00     100.00   100.00    100.00   100.00

  1Discharge   determined simultaneously for all 3 passes.
  s Data based on 4 discharge observations during flood stages, which lasted only 1 month during the fiscal
year 1941.


   Condition at end of fiscald year.-(a) Southwest Pass.-The existing
project is substantially completed. The jetties were completed to
present length in 1921. East jetty is 25,400 feet long. The concrete
cap needs resetting and excess voids filled with salvage stone. The
upstream portion is protected by a sand beach so that maintenance is
necessary on only about 10,150 feet on the outer end. West jetty is
19,960 feet long. The concrete cap is in good condition but low portion
needs to be raised. The upper end is protected by accretion formed
since its construction, and maintenance is required on only the outer
14,650 feet. Longitudinal inner bulkheads of creosoted-timber piling
were completed in 1923 to lengths of 22,822 feet and 15,080 feet on the
east and west sides, respectively, of the lower jetty channel. During
the fiscal years 1939 and 1940, the east jetty was restored to effective
grade and cross section over a total length of 4,570 feet after recent
major deterioration due to settlement and to storm action. However,
in May 1942, an explosion, attributed to enemy action, occurred at east
jetty, damaging about 100 feet of concrete jetty and displacing sections
of the concrete cap approximately 5 feet riverward.
   During the period 1908-23 mattresses were added to the sill at the
head of Pas a Loutre, mattress sills were placed across Cubits Gap
and The Jump, 11 outlet bayous in the pass were closed, the mattress
sill across Southwest Pass was removed, 53 spur dikes were constructed
in the lower 9 miles of the pass, and 5 spur dikes and a submerged
deflecting dike were built at the Head of the Passes. During the fiscal
years 1935 to 1940, 26 new spur dikes were constructed and 19 existing
dikes were extended to contract the pass to a uniform width of 1,420
feet from mile 10.15 below Head of Passes to mile 20.09 at the Gulf of
Mexico. In the fiscal years 1936 and 1937, 3 new spur dikes and exten-
sions to 3 existing dikes were constructed on the left (east) bank of
the river near Pilottown at Head of Passes, and 8 short spur dikes
were constructed along the east side of the pass adjacent to the West
Headland Dike which separates Southwest and South Passes. During
the fiscal year 1944, 3 spur dikes were damaged, Nos. 13.94 R, 16.62 L,
and No. 7 near Pilottown, and these will.be repaired during the present
low-water period.
   All structures are in good condition with exception of dikes between
bulkheads and jetties, which are no longer needed; and certain of the
spur dikes which have served the purposes intended and have become
buried in the accretions they were designed to produce; and the dikes,
jetties, and bulkheads which require periodic renewal of unserviceable
           RIVERS AND HARBORS                 NEW ORLEANS, LA., DISTRICT                         641
piling, and repair and maintenance due to settlement; and the three
dikes mentioned above.
  During the fiscal years 1941 to 1944, dredging of 20,675,560 cubic
yards of material from a 48- by 400-foot channel to correct alignment
between miles 9.25 and 20.2 was performed by contract, and 45,834.55
tons of stone were placed in repairing and stabilizing the east and
west jetties of Southwest Pass and the inner east jetty of South Pass.
Channel conditions on June 30, 1944, were as follows:

                                                                     35-foot channel

                                                         chnnlcentral
                                                      Length  of                             Minimum
                                                       channel    Minimum     Average         depth
                                                                      width    width


                                                          Miles      Feet       Feet           Feet
                                      -----------------
Entrance channel into head of the pass_                       1.0       520            765            35
Through pass from head to sea end of jetties .--.  .-        20. 2      500            800            37
Through bar channel at mouth of pass------------------        1.0       530            745            35



   Through the pass a 35-foot channel with an average width of 800
feet and a least width generally of not less than 400 feet was main-
tained during the year. Maintenance dredging was in progress at
the end of the fiscal year in the jettied channel and also on the bar
channel. -
    (b) South Pass.--Improvement begun by James B. Eads in 1875
comprised east and west jetties at the mouth, with lengths of 12,070
and 7,820 feet, respectively; 36 spur dikes between the jetties; 2 mat-
tress sills and various dikes at the Head of Passes; and dredging the
channel. These works were completed on July 8, 1879, when the 20-
year period of maintenance by contract was begun. Two side outlets
were closed and spur dikes were built at 2 locations in South Pass.
Inner east and west jetties, with lengths of 11,170 and 4,710 feet, re-
spectively, were completed in 1886. The Eads contract ended Jan-
uary 28, 1901.
   Since the latter date the pass has been maintained by the United
States. The work done includes a shoreward extension of 872 linear
feet to inner east jetty; placing a mattress sill across the head of South
Pass, which was removed in 1935; an upstream extension 1,300 feet
long, of the headland dike between South and Southwest Passes;
sinking of 232,742 square yards of mattress for bank-protection pur-
poses at the Head of Passes; construction of spur dikes along the left
bank above the Head of Passes; and placing of submerged deflecting
dike across the head of Pas a Loutre.
   The inner east jetty was repaired and capped with concrete to
elevation plus 6.0 mean Gulf level in 1939 for a distance of 5,440 feet
from its outer end, and the east jetty outer longitudinal dike was
placed in good condition by repairing it for a distance of 4,300 linear
feet from its outer end in the fiscal year 1940. The inner west jetty
was also placed in good condition in 1940 by repairing 2,700 feet from
its outer end. During the fiscal year 1941 work on the inner east jetty
consisted of placing 1,139.85 tons of stone at the outer end of the jetty.
   A stable channel in excess of project dimensions was available
throughout the length of South Pass during the fiscal year with the
exception of the bar channel where maintenance dredging was per-
       616634---45-pt. 1, vol. 1-41
642           REPORT OF CHIEF OF ENGINEERS,                                      U. S. ARMY,              1944

formed by the U. S. hopper dredge Benyaurd. Repairs and main-
tenance of outlets, revetments, and banks and routine channel and
hydraulic surveys and observations were made.                                               Controlling channel
conditions on June 30, 1944, were 30 feet deep over a width of 250 feet
on the bar channel at the Gulf entrance to the pass.
  The total cost and expenditures under the existing combined project
for Southwest Pass and South Pass June 30, 1944, were as follows:

                                                                  Costs
                   Item                                                                         Total          Expenditures
                                                  New work             Maintenance

Southwest Pass-_                    _------------$16,   179, 762. 06   $13, 266, 895. 91   $29, 446, 657. 97       797,
                                                                                                                $29,     61
                                                                                                                      262.
South Pass_ ____________..-         ..---         8, 765, 000. 00        6, 130, 715. 69    14, 895, 715. 69     14, 861, 682. 08

      Total    -----------------------           24, 944, 762. 06       19, 397, 611.60     44, 342, 373. 66     44, 658, 944. 69



   Proposed operations.-The balance unexpended at the end of the
fiscal year, $196,633.75, plus an allotment of $375,000 made during
July 1944, will be applied as follows:
Accounts payable June 30, 1944_-----------------------------                                                   $92, 646. 39
Maintenance:
    By contract:
         Maintenance dredging in Southwest Pass
          between Head of Passes and lower jetty
          channel, July 1, 1944, to May 31, 1945_- - $165, 000. 00
    By hired labor:
        Maintenance dredging by U. S. hopper
          dredge Benyaurd in bar and lower jetty
          channel Southwest Pass, bar channel,
          South Pass, and entrance channels at Head
          of Passes as required from July 1, 1944, to
          June 30, 1945_------------------------                  150, 000. 00
        Repairs and maintenance of bulkheads,
          dikes, and other structures in Southwest
          Pass, July 1, 1944, to June 30, 1945               - --  25, 000. 00
        Raising concrete cap on west jetty, South-
          west Pass, Sept. 1, 1944, to Mar. 31,
          1945-------------------------------25,000.00
        Repair and maintenance of east jetty South-
          west Pass, July 1, 1944, to June 30, 1945_               15, 000. 00
        Repair and maintenance of outlets and revet-
          ments, Southwest Pass, July 1, 1944, to
          June30,1945         ___       __ _ -          -__        15,000.00
        Repair and maintenance of outlets and revet-
          ments South Pass, July 1, 1944, to June
          30, 1945-----------------------------10,000. 00
        Routine channel surveys and miscellaneous
          examinations during fiscal year July 1,
          1944, to June 30, 1945---_ --------------                25,000. 00
        Hydraulic studies, observations, and hydro-
          graphic surveys during fiscal year July 1,
          1944, to June 30, 1945 -----------------                 30, 000. 00
        Maintenance and repair to Burrwood Reser-
          vation July 1, 1944, to June 30, 1945....                18, 987. 36

                   Total maintenance -----------------------------                                             478, 987. 36
                   Total for project -------------------------------                                           571, 633. 75
              RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                                              643
   The additional sum of $450,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
       By contract:
           Maintenance dredging in Southwest Pass between Head of
              Passes and lower jetty channel, as required between July
              1, 1945, and June 30, 1946 _$100,                                                                                           000
       By hired labor:
           Maintenance dredging by U. S. hopper dredge Benyaurd at
             Southwest Pass bar and lower jetty channel, South Pass
             bar and Head of Passes, as required between Aug. 31, 1945,
             and June 30, 1946_------------------------------------                                                              180, 000
           Repair and maintenance of banks of passes, jetties, dikes,
             outlets, revetments, and other structures, as required be-
             tween July 1, 1945, and June 30, 1946            -100,
           Examinations, hydrographic and channel surveys, observa-
                                                                                  --                                                      000

             tions, studies, etc., during the fiscal year July 1, 1945, to
             June 30, 1946----------------------------------------                                                                50, 000
           Additions, betterments, and repairs to Burrwood Reserva-
             tion and shore plant during fiscal year July 1, 1945, and
             June 30, 1946----------------------------------------                                                                20, 000
                     Total maintenance___---                            -----------                                              450, 000

                                              Cost and financial summary
Cost of new work to June 30, 1944_1111111                 111$26,                                                 674, 750. 59
Cosy of maintenance to June 30, 1944_-------                     -                                       1 19, 397, 611. 60
       Total cost of permanent work to June 30, 1944---------                                               46, 072, 362.                      19
Undistributed costs June 30, 1944_ __-----------409,                                                                .217.                      42
       Net total cost to June 30, 1944_-------               ---                                            46, 481, 579.                      61
Minus accounts payble June 30, 1944---          ---------                                                        92, 646.                      39
       Net total expenditures ---------------------------                                               1   46, 388, 933.                      22
Unexpended balance June 30, 1944 --------------------------                                                     196, 633.                      75
      Total amount appropriated to June 30, 1944                                       --------         1   46, 585, 566.                      97

   Fiscal year ending June 30                     1940               1941              1942          1943                         1944


Cost of new work_ .         -
                           .........          $845,132. 85     $i, 003, 442. 74   $98, 974. 65    $353, 536. 41    -         -                  _
Cost of maintenance-     ....        .....     704, 863. 67        630, 133. 93   300,170. 70      221, 277. 49              $464, 690. 92

      Total cost   --------------            1, 549, 996. 52    1, 633, 576. 67   399, 145. 35     574, 813. 90                  464, 690. 92

Total expended ---------------               1, 453, 085. 99    1, 666, 255. 92   623, 967. 43     590, 772. 37                  285, 315. 68

Allotted___    .___---------                 1, 429, 586. 36    1,151, 600. 00    916, 728. 21 I-343, 800. 00...


Balance unexpended July 1, 1943__                                                                             $481, 949. 43
Gross amount expended _____--------$385,                                                     127. 21
Less reimbursements collected ------------------                                         99, 811. 53
                                                                                                                  285, 315. 68
       Balance unexpended June 30, 1944                                                   _ _ _ __                196, 633. 75
Outstanding liabilities June 30, 1944------------                                          $562. 22
Amount covered by uncompleted contracts ------                                         135, 080. 52
                                                                                                                  1~ .              9    .74
                                                                                                                       60,        97X.     /




     Balance available June 30, 1944--    ------        _60,                                                           991. 01
Amount allotted in July 1944-------------------------------                                                       375, 000. 00
     Amount available during fiscal year 1945--------------                                                       435, 991. 01

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2______                                                                           450, 000. 00
  1 Includes $3,379,675.65 from Permanent Indefinite Appropriation.
  2 Exclusive of available funds
644          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                1944

                    3. MISSISSIPPI RIVER BETWEEN BATON ROUGE
                                AND NEW ORLEANS, LA..
  Location.-The Mississippi River between Baton Rouge and New
Orleans flows in a general southeasterly direction through the south-
eastern portion of the State of Louisiana. Other data are as follows:

                                                                                   Maximum        Minimum           Average

Width.....--------------------------------------- feet..                                 4, 700       1,500                 2,900
Discharge                     ..-------------------------------.. second-feet...    1, 557. 000     135.000    _.          .....
Fall of water surface (approximate)------------------                     feet__          27. 0          .5     ...         ..
Mean velocity (approximate)-------------_ feet per second..                                 9.0          .5-        --..


   (See Corps of Engineers, Mississippi River Commission Alluvial
Valley maps, Baton Rouge, White Castle, Donaldsonville, Mount Airy,
and Bonnet Carre quadrangles, and United States Geological Survey
maps, Lagan, Hahnville, Luling, New Orleans (west), New Orleans
(east), Chalmette, Bertrandville, and Belle Chasse quadrangles.)
   Previous projects.-Authorized by the River and Harbor Acts of
June 3, 1896, and January 21, 1927. For further details see page 724
of Annual Report for 1937 and page 775 of Annual Report for 1938.
   Existing project.-This provides within the limits of the port of
New Orleans where that authority has jurisdiction over both banks
of the river, a channel depth of 35 feet and maximum width of 1,500
feet, measured from a line generally 100 feet from the face of the
left-bank wharves, but not closer than 100 feet to wharves on the
right bank; and from the port of New Orleans to a line one-half mile
below the Louisiana Highway Commission bridge at Baton Rouge, a
distance of 132 miles, a channel depth of 35 feet and width of 500 feet.
   The estimate of cost for new work, made in 1938, was $200,000. The
latest (1938) approved estimate of cost for annual maintenance is
$89,000.
   The existing project was adopted by the River and Harbor Act
approved June 20, 1938 (H. Doc. No. 597, 75th Cong., 3d sess.), to
provide for the present project dimensions. The latest published map
is contained in House document No. 215, Seventy-sixth Congress, first
session.
   Recommended modifications of project.-See page 637 for recom-
mendation of the Chief of Engineers that a single project be provided
for Mississippi River, Baton Rouge to the Gulf of Mexico.
   Terminal facilities.-Modern terminal facilities were installed by
the city of Baton Rouge in 1926. A reinforced concrete dock for
deep-sea vessels, 308 feet in length, has a covered-shed area of approxi-
mately 20,000 square feet and is equipped with a 12-ton locomotive
crane. Attached to the downstream end of the main wharf is a float-
ing Wharf boat 231 by 401/2 feet, of 2,000-ton capacity. The facilities
are served by a transfer boat and municipal terminal, having a capacity
of 40 cars per day.
   Private terminals for handling oil and other products are located
at points on both sides of the river between New Orleans and Baton
Rouge.
         RIVERS AND HARBORS-NEW               ORLEANS, LA., DISTRICT            645

   The facilities are considered adequate for the existing commerce.
For further details see Transportation Series Report No. 2, 1929, and
Report No. 4, 1936, pertaining to Mississippi River.
   Operations and results duArinq fiscal year.-Dredging of 597,884
cubic yards of material for maintenance of the channel to project di-
mensions within the harbor at New Orleans was accomplished by leased
plant. Signal lights for control of river traffic in the vicinity of Algiers
Point in the port of New Orleans were operated when necessary during
the high-water period from March 13 to June 5, 1944. Surveys to
determine the condition of the channel were made at Granada and Red
Eye Crossings and in New Orleans Harbor. The total costs for the
year were $52,687.76, all for maintenance; total expenditures were
$54,074.20.
   Condition at end of fiscal year.-The existing project was completed
in 1940. Channel of full project dimensions was dredged at Red Eye
Crossing after the 1939 flood period. Channel was also dredged to
project dimensions within New Orleans Harbor from the upstream
end of the Bulk Commodity plant wharf to the lower end of Toulouse
Street wharf. Minor deficiencies in project dimensions at the lower
end of Dumaine Street wharf and Governor Nicholls Street wharf were
not corrected because of the presence of revetment mattresses at these
points. Existing depths opposite these locations are adequate for
present and anticipated future commerce. A natural channel of proj-
ect dimensions or greater was available throughout the remainder of
the project except within New Orleans Harbor where maintenance
dredging was required to provide project dimensions.
   The normal width of channel between 35-foot contours within the
limits of the port of New Orleans varies from approximately 1,600
feet to approximately 2,400 feet. Maximum depths are approximately
110 feet. The depth of this portion of the channel varies considerably
due to deposits and scouring during high stages of the river, and shoals
develop frequently at various points during falling and intermediate
stages. Dredging is required to maintain deep water to the wharves
along the banks of the river.
   The total costs under the existing project to the end of the fiscal
year have been $547,347.77, of which $184,320.99 was for new work and
$363,026.78 for maintenance; total expenditures, $547,560.22.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $121,481.34, including accounts receivable, plus an allot-
ment of $90,000 made during July 1944, will be applied as follows:
Maintenance:
    By contract:
        Dredging in New Orleans Harbor to remove flood deposits
           in critical locations as required between July 1, 1944, and
           June 30, 1945_           ---------------------------------   $160, 000. 00
    By hired labor:
        Dredging at Red Eye and Granada Crossings by United
           States pump barge, July 1, 1944, to June 30, 1945 --           40, 000. 00
        Surveys in New Orleans Harbor, Red Eye and Granada
           Crossings, July 1, 1944, to June 30, 1945-                 -    3,481. 34
        Operation of signal lights for river traffic control in New
           Orleans Harbor during flood stages, Feb. 1, to June 30,
           1945_ -------------------------------------------               8,000.00

              Total maintenance- .211,                                        481. 34
646                 REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

   The additional sum of $100,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
          By contract:
              Dredging in New Orleans Harbor to remove flood deposits in
                 critical locations as required on falling river stages
          By hired labor:
                                                                            $60, 000                   --------
              Dredging by United States pump barge at Red Eye Crossing
                 as required on falling river stages_         -              30, 000
              Operation of traffic lights in New Orleans Harbor as required
                 during high river stages                               -      6, 000
              Surveys at Red Eye and Granada Crossings and in New
                 Orleans Harbor during fiscal year                            4, 000       -----
                                  Total maintenance--------------------------------100, 000

                                             Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                                                      $184, 320. 99
Cost of maintenance to June 30, 1944----------------- --                                                           532, 081. 88
       Total cost of permanent work to June 30, 1944-
Plus accounts receivable June 30, 1944---
                                                                                                              -       716, 402. 87
                                                                                                                           212. 45

                Gross total costs to June 30, 1944----------------716,                                                     615. 32
Net total expenditures---- -------- _ ______                                                                          716, 615. 32
Unexpended balance June 30, 1944---------------------                                                                 121,268.89
                Total amount appropriated to June 30, 1944                                                            837, 884. 21

      Fiscal year ending June 30                1940             1941                    1942             1943             1944

Cost of new work....-------------            $184, 320. 99   .. ------         .......     --..    .......-                 .
Cost of maintenance -------------              23, 977. 07     $67, 668. 36       $34, 607. 38      $111, 764. 08         $52, 687. 76
          Total -------------------           208, 298. 06      67, 668. 36        34, 607. 38        111, 764. 08         52, 687. 76
Total expended-----.---------                 182, 896. 98      90, 715. 33        34, 065. 84        111, 142. 78         54, 074. 20
Allotted.......................                89, 000. 00      33, 684. 00       140, 000. 00          95, 000. 00


Balance unexpended July 1, 1943----- ----------------------                                                       $175, 343. 09
Gross amount expended ____------------------------------------54,                                                       074. 20
     Balance unex.pended June 30, 1944-                                 - ---                      ___                121, 268. 89
Amount covered by uncompleted contracts                             -----------------                                  29, 560. 00
      Balance available June 30, 1944-------------------------                                                         91, 708. 89
Accounts receivable June 30, 1944_---------                ----                                                            212. 45
     Unobligated balance available June 30, 1944                                   --------------                      91, 921. 34
Amount allotted in July 1944 --------------------------------                                                          90, 000. 00
              Amount available during fiscal year 1945                        ------------------                      181, 921. 34
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance ' --------------------------------                                                         100, 000. 00
  1 Exclusive of available funds.
        RIVERS AND HARBORS-NEW          ORLEANS, LA., DISTRICT      647
      4. BAYOUS LA LOUTRE, ST. MALO, AND YSCLOSKEY, LA.

    Location.-From their common head at the small settlement of
Yscloskey, Bayou La Loutre flows southeasterly for 29.4 miles to Eloi
Bay, and Bayou Yscloskey northeasterly for 2.2 miles to Lake Borgne.
Bayou St. Malo leaves Bayou La Loutre at mile 19.4, flowing north-
westerly 6.5 miles to Lake Borgne. (See U. S. Coast and Geodetic
Survey Charts Nos. 1270 and 1271, and U. S. Geological Survey maps,
Shell Beach, Lake Eloi, Lake Eugenie, and Morgan Harbor quad-
rangles.)
    Existing project.-This provides for a channel 5 feet deep and 40
feet wide from deep water in Lake Borgne to the shore line at the
mouth of Bayou Yscloskey; a channel 6 feet deep and 40 feet wide
from deep water in Lake Borgne through Bayous St. Malo, La Loutre,
and Eloi to deep water in Lake Eloi; and the removal of snags and
other obstructions from Bayou La Loutre between Hopedale and
Bayou St. Malo, the total length of the improvements being 30.0 miles.
The normal tidal variation.is about 1 foot. Hurricane tides, 6 feet
above normal, have been reported.
    The estimated cost of new work made in 1937 is $48,000. The latest
  (1937) approved estimate for annual cost of maintenance is $8,400.
    The existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. No. 275, 75th Cong., 1st sess.). The latest
published map is in the project document.
    Recommended modifications of projects.-Under date of June 20,
1941, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for a channel 5 feet deep and 30 feet wide
in Bayou La Loutre between Hopedale and Bayou St. Malo, at an
estimated first cost of $35,000, with $800 annually for maintenance, in
addition to the amount now required, subject to certain conditions of
local cooperation. (S. Doc. No. 116, 77th Cong., 1st sess.)
    Local cooperation.-Fullycomplied with.
    Terminal facilities.-None.
    Operations and results during fiscal year.-None. The cost was
$67.66 and expenditure $3,334.92, applied to settlement of accounts of
preceding fiscal year.
    Condition at end of fiscal year.-The existing project was completed
in 1940. On June 30, 1944, controlling depth at mean low Gulf level
was 5 feet from deep water in Lake Borgne through Bayous St. Malo
and La Loutre to deep water in Lake Eloi. Controlling depth in
Lake Borgne at the mouth of Bayou Yscloskey was 5 feet. Depths
over the bars at the mouths of the bayous are subject to rapid shoaling,
but navigation is possible throughout their length.
    Total costs and expenditures under the existing project have been
$53,151.43, of which $43,619.54 was for new work and $9,531.89 for
maintenance.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, $29.34, will be applied to reconnaissance of the bayous
during July 1944.
    The additional sum of'$9,000 can be profitably expended during the
fiscal year 1946 on maintenance dredging and the removal of snags
and overhanging trees by hired labor and Government plant, in No-
vember or December 1945.
648              REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY,                   1944

                                        Cost and financial summary

Cost of new work to June 30, 1944___-- --------                                                               $43, 619. 54
Cost of maintenance to June 30, 1944_--------                                                ---                9, 531. 89

             Total cost of permanent work to June 30, 1944------------                                          53, 151. 43

Net total expenditures_ _________-                                    -         -        -                      53, 151. 43
Unexpended balance June 30, 1944_---------                                                         ---               29. 34

             Total amount appropriated to June 30, 1944 --------------                                          53, 180. 77


     Fiscal year ending June 30                 1940           1941          1942                1943                    1944

Cost of new work...........------------       $38, 972.41-------------
Cost of maintenance.o-------                  ----             $407. 23       $601.33        $8, 455. 67                    $67.66

Total expended...............--------------    38, 761.90        701.78        600. 41           5,189. 33                3, 334.92

Allotted -------------------                   11, 585.00      2, 841.77   -7,746   00           8, 500.00............


Balance unexpended July 1, 1943-                                                             -                   $3, 364. 26
Gross amount expended_    _------------------3,                                                                      334. 92
                                             -----------------------
             Balance unexpended June 30, 1944___                                                                          29. 34

Amount that can be profitably expended in fiscal year ending
    June 30, 1946, for maintenance 1                          -----------------------------                        9, 000. 00
    1Exclusive of available funds.

                                              5. BAYOU DUPRE, LA.

   Location.-Bayou Dupre has its head in the marshes 3 miles east of
the Mississippi River levee and extends east and north to its mouth
in Lake Borgne. The Lake Borgne Canal leaves the east bank of the
Mississippi River through a lock at Violet, La., and joins Bayou Dupre
3.6 miles above its mouth. (See U. S. Coast and Geodetic Survey
Chart No. 1269 and U. S. Geological Survey maps Chalmette and
Martello Castle quadrangles.)
  Existing project.--This provides for a channel 6 feet deep from the
highway bridge at Violet, La., to deep water in Lake Borgne with
widths of 80 feet in the canal and bayou and 100 feet in the lake, and a
turning basin 100 feet wide and 200 feet long at Violet, La.; the length
of the improvement being 7.3 miles. The mean range of tide in Lake
Borgne is 1.5 feet, with occasional variations, due to winds, of 2 feet;
hurricane tides of 6 feet have been reported.
   The privately owned lock at Violet has a usable length of 261 feet, a
width of 40 feet, and a depth of 6 feet over the sills. The cost of this
lock and the Lake Borgne Canal is not known.
   The estimated cost of new work made in 1937 was $52,000. The
latest (1937) approved estimate for cost of maintenance is $5,000
annually for the first 3 years and $3,500 annually thereafter.
   The existing project was adopted by the River and Harbor Act of
August 26, 1937 (H. Doc. No. 321, 75th Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-Fullycomplied with.
   Terminalfacilities.-There is a private wharf at Violet, La., used by
the shrimp and oyster cannery, and a switch track to the Louisiana
Southern Railway. An additional area for a public terminal is set
                RIVERS AND HARBORS-NEW                                             ORLEANS,             LA., DISTRICT                      649
aside under the provisions of local cooperation. These facilities are
considered adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1939. On June 30, 1944, there was a channel with a mini-
mum width of 70 feet and controlling depths as follows: From the
bridge at Violet, La., to the turning basin, 3.5 feet; turning basin to
the mouth of the bayou, 6 feet; over the bar at the mouth of the bayou
at Lake Borgne, 4.5 feet. The bayou is navigable throughout its
length. Right-of-way monuments were established on Lake Borgne
Canal by United States plant and hired labor during 1942.
   The total costs and expenditures under the existing project have
been $39,887.75, of which $38,915 was for new work and $972.75 for
maintenance.
  Proposed operations.-No funds are available and no operations
are proposed during the fiscal year 1945.-
  The sum of $5,000 can be profitably expended during the fiscal year
1946 on maintenance dredging at entrance to the bayou and in the
turning basin by hired labor and Government plant during November
and December 1945.
                                                Cost and financial summary

Cost of new work to June 30, 1944__                                                                                           $38, 915. 00
Cost of maintenance to June 30, 1944_--                                                 ----------                                 972. 75

       Total cost of permanent work to June 30, 1944------------                                                                39, 887. 75
Net total expenditures_ __-----------------                                                                                     39, 887. 75
Total amount appropriated to June 30, 1944                                                                                      39, 887. 75


    Fiscal year ending June 30                       1940                   1941               1942               1943                1944

cost of new work....----------------         $10.30 ........
                                                          -.- -                                ..
                                                                                             ...                                     ...........
Cost of maintenance .........-------------------------   $425. 99                              $269. 34            $277. 42..
Total expended....-------------------54. 57                                   425. 99            269.34             277. 42     --     - -
Allotted----------------.......................-----6, 085. 00                439.55         -4,352.580           -114.00             ._     -..

Amount that can be profitably expended in fiscal year ending June

    30, 1946, for maintenance_-                                  ----.---                            __-----$5,                       000. 00

                                               6. BAYOU BONFOUCA, LA.

  Location.-This stream rises about 5 miles north of Slidell, La., and
empties into Lake Pontchartrain 5 miles west-southwest of that town.
(See U. S. Coast and Geodetic Survey Chart No. 1268 and Corps of
Engineers, Mississippi River Commission Alluvial Valley maps, Sli-
dell and Chef Menteur quadrangles.)
  Existing project.-This provides for dredging a channel 10 feet deep
at mean low water and 60 feet wide on the bottom from Slidell to deep
water in Lake Pontchartrain, a distance of about 9 miles. The aver-
age range of water level, due to tide, is 0.8 foot.
  The estimate of cost for new work, made in 1924, was $22,000, of
which $5,500 was contributed by local interests. The latest (1924)
approved estimate for annual cost of maintenance is $1,200.
650              REPORT OF CHIEF OF ENGINEERS,                                          U. S. ARMY,                 1944

   The existing project was adopted by the River and Harbor Act ap-
proved January 21, 1927 (H. Doc. No. 474, 68th Cong., 2d sess.). The
latest published map is in the project document.
   Local cooperation.-Fully complied with.
   Terminal facilities.-All terminal facilities are at Slidell and con-
sist of three loading slips and three wharves, with tram-track connec-
tions and skids for loading timber. There are also marine ways and
a graving dock. All terminal facilities are privately owned and con-
sidered adequate for present commerce.
   Operations and results during fiscal year.--Maintenance dredging
by leased plant of 129,001 cubic yards of shoal material from entrance
to Bayou Bonfouca was accomplished at a cost and expenditure of
$13,416, all for maintenance.
   Conditionat end of fiscal year.-The existing project was completed
in 1931. The controlling depths on June 30, 1944, were 10 feet through
the bayou to upper end of the improvement, and 10 feet, mean low
Gulf, over the bar at the mouth of the bayou. The channel is in good
condition. The head of navigation is at the town of Slidell, La., 73/4
miles above the mouth of the bayou.
   The total costs and expenditures under the existing project have
been $50,465.13, of which $30,997.27 was for new work and $19,467.86
for inaintenance. In addition, $5,500 was expended from contributed
funds for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $3,584, will be applied to removal of snags and obstructions
at such time as required.
   No additional funds can be profitably expended during the fiscal
year 1946.
                                                     Cost and financial summary
Cost of new work to June 30, 1944____ __                                                ___            __            1 $30, 997. 27
Cost of maintenance to June-30, 1944_    -                                         --------------                       19, 467. 86
             Total cost of pernianent work to June 30, 1944------------50, 465. 13

Net total expenditures __-   ---- _ ___--__ _          _________                                                         1 50, 465. 13
Unexpended balance June 30, 1944_ -        ---------------      _                                                          3, 584. 00
             Total amount appropriated to June 30, 1944------------
                                                            _       --                                                   1 54, 049. 13

     Fiscal year ending June 30                          1940          1941               1942              1943                 1944

C ost of new w ork -- - - - - - -. - - - - - -. . - - - - - - . - - - - - - . . . - - - - . .                               ..   .    ..   .
Cost of maintenance -------------------------         $140.11        $454.93        $267.31                                          $13,416
               .......
Total expended ------------------------------                            140. 11             446. 06          276. 18                 13, 416

Allotted ...................-------------------------.          $500   9, 640.11        -9, 155. 00         -122.   76                17,000



Amount allotted                   from War Department Civil Appropriation Act
approved June                    11, 1938 _$2,487.20
Amount allotted                   from War Department Civil Appropriation Act
approved June                    24, 1940-----------------------------                                                   14, 512. 80
      Amount to be accounted for ----------------------------                                                             17,000. 00
Gross amount expended                                                                                                     13, 416. 00
             Balance unexpended June 30, 1944                                 ---------------                               3, 584. 00
   1In addition $5,500 expended from contributed funds for new work.
              RIVERS AND HARBORS-NEW                       ORLEANS,          LA.,   DISTRICT       651
                    7. CHEFUNOTE RIVER AND BOGUE FALIA, LA.

  Location.-The Chefuncte River rises in the upper portions of
Tangipahoa and Washington Parishes, La., and flows southerly into
Lake Pontchartrain, opposite New Orleans. (See U. S. Coast and
Geodetic Survey Chart No. 1269 and Corps of Engineers, Mississippi
River Commission Alluvial Valley map, Covington quadrangle.)
  Previous projects.--Authorized by the River and Harbor Act of
June 10, 1872. For further details of previous projects see page 731,
Annual Report for 1913, and page 783, Annual Report for 1938.
  Existing project.-This provides for a channel 8 feet deep at mean
Gulf level from that depth in Lake Pontchartrain via Chefuncte River
and Bogue Falia to Washington Street, Covington, La. The total
length of improvement is 14 miles. Under ordinary conditions the
mean range of tide at the mouth is about 10 inches, and near Coving-
ton about 3 inches, and the extreme range about 14 inches and 5
inches, respectively. The variation of water surface in the upper
Chefuncte River and Bogue Falia, due to floods, is about 8 feet; that
in the lower Chefuncte River at Lake Pontchartrain, due to winds, is
about 3 feet.
  The estimate of cost for new work, revised in 1927, was $8,460, ex-
clusive of amounts expended on previous projects. The latest (1928)
approved estimate for annual cost of maintenance is $2,000.
  The existing project was authorized by the following river and
harbor acts:

       Acts                     Work authorized                                     Documents


Mar. 3,1881      Dredging of bar at mouth of Chefuncte River in     H. Ex. Doe. No. 54, 46th Cong., 2d
                  Lake Pontchartrain and dredging and removal        sess., and Annual Report, 1880, p.
                  of obstructions in Chefuncte River and Bogue       1181.
                  Falia to Covington, La. Width and depth not
                  specified.
July    3,1930   For a definitely stated project with the present   Rivers and Harbors Committee
                  project dimensions.                                 Doc. No. 2, 70th Cong., 1st sess.


For latest published map see Annual Report for 1916, p. 2437.


  Terminal facilities.-There are no terminal facilities on the Bogue
Falia. On the lower Chefuncte, wharves used in connection with the
boat yards have been constructed at Houltonville and Madisonville,
and these, in addition to minor wharves constructed by owners of
pleasure boats, are adequate for navigation needs. On both water-
ways additional sites are available if needed.
  Operationsand results duing fiscal year.-None.
  Condition at end of fiscal year.-Due to maintenance work under the
previous project, the work required by the project adopted in 1930 was
completed in 1929. The obstructions in the Chefuncte               and
Bogue Falia were originally removed in 1886, and the channel through
                                                                                          -River
the bar was originally dredged in 1903. The controlling depths on
June 30, 1944, were 9 feet, mean low Gulf, over the bar at the mouth
of the Chefuncte River, 15 feet in the river and in the Bogue Falia to
mile 13, and 2 feet from mile 13 to Washington Street, Covington, La.
The channel to mile 13 is in good condition, and from mile 13 toWash-
652                  REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

ington Street, Covington, La., is in poor condition and is nonnavigable
above this point.
   The total costs and expenditures under the existing project have
been $67,765.22, of which $19,342.24 was for new work and $48,422.98
for maintenance.
   Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
   The sum of $5,000 can be profitably expended during the fiscal year
1946, on maintenance dredging of the bar channel in Lake Pontchar-
train by contract during July and August 1945.
                                                              Cost and financial summary
Cost of new work to June 30, 1944_      _                                                   _$24,                                563. 24
Cost of maintenance to June 30, 1944_--------                                                                ---             48, 422. 98
      Total cost of permanent work to June 30, 1944------------    72, 986. 22
Net total expenditures----       ------------                   -72, 986.22
Total amount appropriated to June 30, 1944_    -------             72, 986. 22


      Fiscal year ending June 30                                1940           1941             1942          1943                 1944

Cost of new work_
Cost of maintenance
                  -----------------                                             $474. 13       $8,595.81 -         $395.45-----------
Total expended..............---------------------...             -421.                03        8,644. 26          400.10-------

Allotted-------------------------.........................             $500   18, 300. 00     -9, 212.94      -121.67        ..


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance--
                           _        -------------                                                                            $5, 000.00

                                                             8. GRAND BAYOU PASS, LA.

   Location.-GrandBayou Pass is on the coast of Louisiana, 16 miles
east of Barataria Pass and 30 miles northwest of the entrance to
Southwest Pass of the Mississippi River. (See U. S. Coast and
Geodetic Survey Chart No. 1273 and U. S. Geological Survey map,
Empire quadrangle.)
   Existing project.-This provides for a channel 6 feet deep and 60
feet wide through the entrance bar in the Gulf of Mexico by dredging.
The mean range of tide is 16 inches with an extreme range of 40
inches; hurricane tides of 6 feet have been reported.
   The estimate o'f cost of new work, made in 1938, was $25,000. The
latest (1938) approved estimate for annual cost of maintenance is
$15,000.
   The existing project was adopted by the River and Harbor Act
approved June 20, 1938 (S. Doc. No. 166, 75th Cong., 3d sess.). The
latest published map is in the project document.
   Terminal facilities.-None.
   Operations and results during fiscal year.-None.
   Conditionat end of fiscal year.-The existing project was completed
in 1939. The controlling depth over the bar on June 30, 1944, was 2.5
feet at mean low Gulf level. The pass is navigable throughout its
length. Maintenance dredging over the bar at the mouth of the pass
is required.
              RIVERS AND HARBORS-NEW                                   ORLEANS, LA.,           DISTRICT                653
  The total costs and expenditures have been $8,674.84, of which
$7,676.34 was for new work and $998.50 for maintenance.
  Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
   The sum of $10,000 can be profitably expended for maintenance
dredging under contract of the bar channel during November and
December 1945.
                                               Cost and financial summary
Cost of new work to June 30, 1944__    .   -     -.              $7, 676. 34
Cost of maintenance to June 30, 1944----------------------------     998. 50
      Total cost of permanent work to June 30, 1944                                                                 674. 84
                                                                                                                 8--------------,
Net total expenditures -------------------------------                                                           8, 674. 84
Total amount appropriated to June 30, 1944---------------------                                                  8,674. 84


    Fiscal year ending June 30                   1940           1941            1942             1943               1944

Cost of new work...         ...---------------...$7, 676.34-
Cost of maintenance -------------
                      .....                     __--$451.18                      $410.16          $137.16-

Total expended............------------------     7, 620. 30       472. 42         444. 79          137.33    .
Allotted      -----------------------
               .                                 4, 333.31     10, 000. 00   -21, 733. 78   --------------          -$258. 07



Balance unexpended July 1, 1943 ------------------------------           $258. 07
Deductions on account of revocation of allotment------------------        258. 07
Amount that can be profitably expended in fiscal year ending June 30,
  1946, for maintenance ------------------------------------          10, 000. 00

                                               9. BARATARIA BAY, LA.

   Location.-This waterway is in Jefferson Parish, La., and extends
about 37 miles in a generally southerly direction from the junction
of Bayou Villars and Big Barataria Bayou, through Big Barataria
Bayou, Bayou Dupont, a canal (Dupre Cut) through the marsh, Bayou
Cutler, Bayou St. Denis, and Barataria Bay to the east end of Bayou
Rigaud, at Grand Isle, and connects with the Gulf of Mexico through
Barataria Pass. (See U. S. Coast and Geodetic Survey Charts num-
bered 1116 and 1273 and U. S. Geological Survey maps, Barataria, Bay
Dogris, Wilkinson Bay, and Barataria Pass quadrangles.)
   Existing project.-This provides for dredging a channel 5 feet deep
at mean low Gulf level and 50 feet wide on the bottom from the junc-
tion of Bayou Villars and Big Barataria Bayou to Grand Isle, a dis-
tance of about 37 miles. The Secretary of War is authorized, in his
discretion, to change the location of the route and increase the dimen-
sions of the channel if the estimated cost of the improvement to the
United States is not increased thereby. Under ordinary conditions
the mean range of tide is 12 inches at the mouth and zero at the head,
and the extreme range 24 inches and 12 inches, respectively. The
variation of water surface near the mouth, due to hurricanes, has been
as high as 6 feet.
   The estimated cost of new work for a canal 5 by 40 feet along route
No. 6, revised in 1924, was $87,500. The latest (1928) approved esti-
mate for annual cost of maintenance is $5,000.
654             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

  The existing project was adopted by the River and Harbor Act of
March 2, 1919 (H. Doc. No. 200, 65th Cong., 1st sess.). The only
published map is in that document.
  Local cooperation.-Fullycomplied with.
  Terminal facilities.-Two public wharves, one at Lafitte and one at
Grand Isle, are available to all boats without charge. About 7 miles
below Lafitte there is an extensive oil terminal for transferring the
production of the Lafitte field to barges. The facilities are considered
adequate for existing commerce.
  Operationsand results during fiscal year.-None.
  Condition at end of fiscal year.-The existing project was completed
in 1925. The controlling depths at mean low Gulf on June 30, 1944,
were: 4 feet Barataria Bay and Bayou St. Denis; 6 feet in Bayou
Cutler, 4 feet in Dupre Cut, and 10 feet in Big Bayou Barataria
between Bayou Dupont and the Intracoastal Waterway. The bayous
are in good condition and are navigable throughout their lengths.
  The total costs and expenditures under the existing project to the
end of the fiscal year have been $107,337.94, of which $73,037.11 was
for new work and $34,300.83 was for maintenance.
  Proposed operations.-An allotment of $28,000, made during July
1944, will be applied to maintenance dredging under contract in Bara-
taria Bay, Bayou St. Denis, and Dupre Cut in the period between
September 1 and December 31, 1944.
  No additional funds can be profitably expended during the fiscal
year 1946.
                                                         Cost and finanoial summary

Cost of new work to June 30, 1944__                                                                                      $73, 037. 11
Cost of maintenance to June 30, 1944--                                                -__--------34,                          300. 83

       Total cost of permanent work to June 30, 1944-
Net total expenditures_-._      --      ------ _
                                                                                                              -          107, 337. 94
                                                                                                                         107, 337.94
Total amount appropriated to June 30, 1944                                            -------------------                107, 337. 94


     Fiscal year ending June 30                            1940                1941             1942        1943             1944

Cost of new work----
Cost of maintenance _._.                         __-__    _       ...            $61.94          $438.31     $408. 58          ---
        Total expended............                            ___--_--   --       61.94           422. 24     424. 65

Allotted-------------.........................            $1,000. 00          25, 061. 94    -24, 955. 00   -198.   11         _




Amount allotted in July 1944 -------------------------------                                                             $28, 000. 00
Amount available during fiscal year 1945                                       ---------------------                      28, 000. 00

                                                  10. BAYOU LAFOURCHE, LA.

   Location.-Prior to 1902 Bayou Lafourche was an outlet of the Mis-
sissippi River, its head being at Donaldsonville, La., 80 miles above
New Orleans. It flows in a general southerly direction to the Gulf of
Mexico, a distance of 107 miles. (See U. S. Coast and Geodetic Sur-
vey Charts Nos. 1116 and 1274; Corps of Engineers, Mississippi River
Commission Alluvial Valley maps, Donaldsonville, White Castle, and
Napoleonville quadrangles; and U. S. Geological Survey maps, Made-
wood, Labadieville, Lafourche, Lac des Allemands, Gibson, Houma,
       RIVERS AND    HARBORS-NEW       ORLEANS,   LA.,   DISTRICT   655
Cut Off, Lake Felicity, Mink Bayou, Leeville, and Belle Pass quad-
rangles.)
   Previous projects.-Authorized by River and Harbor Acts of June
18, 1878, and August 11, 1888. For further details, see page 850 of
Annual Report for 1915, page 833 of Annual Report for 1925, and page
791 of Annual Report for 1938.
   Existing project. This provides for the permanent closure of the
head of the bayou, without a lock; for a channel 6 feet deep and 60
feet wide from Napoleonville to the Intracoastal Waterway at Lock-
port; and a channel, of same dimensions from the Intracoastal Water-
way at Larose to the Gulf of Mexico via Belle Pass; the closure of
Pass Fourchon and for a jettied entrance at the mouth of Belle Pass.
The total length of improvement is about 79.25 miles. Under ordi-
nary conditions the mean range of tide is about 3 inches at the head
and 10 inches at the mouth of the bayou. Tropical hurricanes have
been known to cause a variation of 10 feet at-the mouth and severe
rains and overflow have caused a variation of 3 to 10 feet at the head.
   The estimate of cost for new work, revised in 1941, is $691,000. The
latest (1941) approved estimate of cost for annual maintenance is
$20,000.
   The existing project was adopted by the River and Harbor Act of
August 30, 1935 (H. Doc. No. 45, 73d Cong., 1st sess.). The latest
published map is in the project document.
   Local cooperation.-Fullycomplied with.
   Terminal facilities.-There are numerous private warehouses and
wharvesand stiff-leg derricks for handling cane along the bayou. At
Thibodaux there is a dock with freight transfer, and warehouses.
At Lockport the Barker Barge Line has a large wharf with covered
shed, and the Southern Pacific Railroad maintains a large wharf with
covered shed. At GioIen Meadow each of the sea-food canneries has
docking facilities suitable for its needs. Four oil companies have
docks at Leeville for transferring the production of the Leeville oil
fields to barges. The terminal facilities are considered adequate for
existing commerce.
   Operations and results during fiscal year.-Obstructions were re-
moved from the waterway, as required, by United States plant and
hired labor, at a cost of $27.50 for maintenance. Engineering studies,
including surveys, drafting, and related work were made at a cost of
$3,491.87, for maintenance. Total costs were $3,519.37, all for mainte-
nance. The total expenditures were $3,522.06.
   Conditionat end of fiscal year.--The existing project was 38 percent
complete. The dredging between Larose, La., and the Gulf of Mexico
was completed in 1939. The breakwaters at the mouth of Belle Pass
were completed in 1939, but were subsequently damaged by storm
action, which required the placement of additional stone. Additional
stone was placed adjacent to'both sides of the steel sheet pile break-
waters in 1940, and in the repair and extensions of the breakwaters in
1941. The controlling depths on June 30, 1944, referred to mean low
Gulf were as follows: 2.5 feet through the jetties; 5 feet through Belle
Pass; 6 feet from the junction of Belle Pass and Pass Fourchon to
Larose, La.; 9 feet from Larose to Lockport; 5.5 feet from Lockport to
Raceland, La., and 4 feet from Raceland to Napoleonville, La. The
channel width varies from 30 feet in the upper reaches, which are in
656        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

bad condition, to 180 feet at the mouth. Work remaining to be done
under the existing project consists of strengthening the breakwaters
and dredging the project channel between Lockport and Napoleonville,
La. The head of navigation is at Napoleonville.
   The total costs and expenditures under the existing project to the
end of the fiscal year have been $310,512.67, of which $271,088.65 was
for new work and $39,424.02 for maintenance.
 . Proposed oe'rations.---The balance unexpended at the end of the.
fiscal year, $27,052.30, plus an allotment of $10,000 made during July
1944, will be applied as follows:
Maintenance:
    By contract:
        Dredging in Belle Pass Channel November 1944 to March
           1945_ ------------------------------------------                                                       $15,000.00
    By hired labor:
        Repairs to jetties at Belle Pass Entrance Channel, Novem-
          ber 1944 to March 1945 ---------------------------                                                         20, 000. 00
        Stream patrol and removal of obstructions during fiscal
          year_-------------------------------------------                                                            2,052.30

             Total maintenance-_ _     --------------------    37, 052. 30
  The additional sum of $15,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging by contract in the Larose
to Gulf of Mexico section in April 1946.
                                         Cost and'finanoia summary

Cost of new work to June 30, 1944___    ---        _    _$524,                                                           024. 13
Cost of maintenance to June 30, 1944 --------------------------                                                      54, 869. 40
        Total cost of permanent work to June 30, 1944------------                                                 578, 893. 53

Net total expenditures_ __------------------578,                                                                         893. 53
Unexpended balance June 30, 1944__--             ---------                                                           27, 052. 30
        Total amount appropriated to June 30, 1944                                  --------------                605, 945. 83


   Fiscal year ending June 30                 1940              1941                1942            1943                      1944

Cost of new work .    .......--------------- $63, 571, 62     $21, 840. 22   ..      . .     ...    .       ..   .        .    ..
Cost of maintenance   ...       ......----------..
                                           --------------..    20,004. 82         $15, 571.15           $328. 68              $3,519.37
      Total cost.----------------           63, 571.62         41, 845.04          15, 571.15            328.68                3,519.37

             ----------------
Total expended....                          97, 294. 90        42, 108. 52         15, 221. 73      1,142. 46                  3, 522. 06
Allotted_ ----------------------            19, 720. 83        36, 200. 00        -3, 355. 86      15, 000. 00        -        -



Balance unexpended July 1, 1943                                    _$30,                                                 574. 36
Gross amount expended-_ _--------                                                  ------                             3, 522. 06
     Balance unexpended June 30, 1944--------                                      ---------------                   27, 052. 30
Amount allotted in July 1944_----------                                                      ----                    10, 000. 00
        Amount available during fiscal year 1945 ------------------                                                  37, 052. 30

Amount (estimated) required _to be appropriated for completion of
  existing project      1                         -----------------                                               420, 000. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance 1 --    -.-------                                                                       15, 000. 00
I Exclusive of available funds.
               RIVERS AND HARBORS-NEW                                 ORLEANS, LA.,         DISTRICT                      657
11. WATERWAY FROM THE INTRACOASTAL WATERWAY TO BAYOU
      DULAC, LA. (BAYOUS GRAND CAILLOU AND LECARPE, LA.)
   Location.-Bayou LeCarpe is a tidal stream which rises about 1.5
miles southeast of Houma in Terrebonne Parish and flows southerly
into Bayou Pelton, thence into Bayou Grand Caillou, which flows
southwesterly into Caillou Bay, a total distance of about 40 miles.
(See U. S. Coast and Geodetic Survey Chart No. 1116 and U. S.
Geological Survey maps Houma, Dulac, and Dog Lake quadrangles.)
   Existing project.-This provides for a waterway 5 feet deep and
40 feet wide from the intracoastal waterway at Houma through Bayou
LeCarpe, Bayou Pelton, and Bayou Grand Caillou to Bayou Dulac,
about 16.3 miles. The normal fluctuation due to tides is 3 to 10 inches,
but winds may rise or lower the water level 1 to 3 feet.
   The estimate of cost of new work, revised in 1935, was $56,250.
The latest (1935) approved estimate for annual cost of maintenance
is $3,000.
   The existing project was adopted by the River and Harbor Act
approved August 30, 1935 (H. Doc. No. 206, 72d Cong., 1st sess.). The
project document contains the latest published map.
   Local cooperation.-Fully complied with.
   Terminal facilities.-There are several private wharves and a num-
ber of stiff-leg derricks for handling cane along the banks of the
waterway, which are considered adequate for existing commerce.
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1938. The controlling depths at mean low Gulf level on June 30,
1944, were: 4 feet from the mouth of Bayou Grand Caillou to Dulac,
La.; 4 feet from Dulac via Bayous Pelton and LeCarpe to the Intra-
coastal Waterway. The head of navigation of Bayou Grand Caillou
is at Ashland, and of Bayou LeCarpe at the Intracoastal Waterway.
   The total costs and expenditures under the existing project to the
end of the fiscal year have been $51,823.25, of which $51,279.83 was for
new work, and $543.42 for maintenance.
   Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
   The sum of $10,000 can be profitably expended during the fiscal year
1946 on maintenance dredging under contract and for the removal of
obstructions by hired labor and Government plant during January
and February 1946.
                                     Cost and financial summary
Cost of new work to June 30, 1944_ _-----------$51,                                                                 279. 83
Cost of maintenance to June 30, 1944 _--_-543.                                                                           42

       Total cost of permanent work to June 30, 1944__                                                        51, 823. 25
Net total expenditures_                                                                                       51, 823. 25
Total amount appropriated to June 30, 1944                                                                    51, 823. 25

    Fiscal year ending June 30          1940                  1941             1942             1943                1944


Cost of new work .------------------------
Cost of maintenance_-.............   -----------------
                                                         --   -----       --.
                                                                           .     .    . .
                                                                                $407.69
                                                                                            .     .
                                                                                                  $72.73
                                                                                                        .     .   ..--------------

Total expended.....-------------------------------------------462. 45                                 80.97          --

Allotted.............----. -..-----------                     $10, 000.    -9, 455. 00            -1. 58 ...        _...

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance_ -__--------_--_-_---_----$10,                                                      000. 00
          616634-45--pt. 1, vol. 1-42
658      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                     1944

                         12. BAYOU GROSSETETE, LA.
  . 4Location.-This bayou rises in Pointe Coupee Parish, La., and ex-
tends in a generally southeastern direction, entering Bayou Plaque-
mine 8 miles below Plaquemine lock. (See Corps of Engineers,
Mississippi River Commission Alluvial Valley maps, New Roads,
Fordoche, Osca Bayou, and Grossetete quadrangles.)
    Existing project.-This provides for improving the stream for a
distance of 29 miles from its mouth to a point 5 miles above Marin-
gouin, La., by removing snags and trees and by dredging a channel
60 feet wide on bottom and 5 feet deep at mean low water. Mean
low water is 2 feet above mean low Gulf level. Under ordinary
conditions the mean range of tide is about 3 inches at the mouth and
nothing at the head, and the extreme range about 6 inches at the
mouth. The variation of water surface due to flood conditions may
be from 2 to 8 feet.
     The estimate of cost for new work, revised in 1932, is $130,000.
The latest (1912) approved estimate for annual cost of maintenance
is $500.
     The existing project was adopted by the River and Harbor Act
of July 25, 1912 (H. Doc. No. 348, 62d Cong., 2d sess:). The latest
published map is printed oppositepage 2540 of the Annual Report
for 1917.
     Terminal faeilities.-There are no wharves on the bayou. The
banks are firm and high. The steamboats and launches operating on
the stream unload their cargoes at any desired point, carrying the
freight by hand into the stores, which are generally on the bank of
the bayou. The facilities are considered adequate for the existing
commerce.
     Operationsand results duringfiscal year.-None.
    Condition at end of fiscal year.-The existing project was 15.8 per-
cent complete. A channel 5 feet deep at mean low water, and 60 feet
wide on the bottom was completed in 1914 to mile 10.3, and from that
point to the head of the project a 5- by 40-foot channel was dredged in
1916. To complete the project that portion of the stream above mile
10.3 is to be dredged 20 feet wider. The controlling depths, at mean
low water, on June 30, 1944, were as follows: 5 feet from mile 0 to niile
20, 3 feet from mile 20 to mile 26, and 2 feet from mile 26 to mile 29.
Channel conditions are good between miles 0 and 26, and poor between
miles 26 and 29. The head of navigation is at mile 29.
    The total costs and expenditures under the existing project, to the
end of the fiscal year, were $96,169.26, of which $29,392.49 was for new
work and $66,776.77 for maintenance.
   Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
    The sum of $10,000 can be profitably expended during the fiscal year
1946, on maintenance dredging under contract and the removal of
obstructions by hired labor and Government plant during July and
August 1945.
                          Cost and financial summary
Cost of new work to June 30, 1944__                  .-        -$29,          392. 49
Cost of maintenance to June 30, 1944                                      66, 776. 77
      Total cost of permanent work to June 30, 1944-----                  96, 169. 26
Net total expenditures_ ---              --                               96, 169. 26
Total amount appropriated to June 30, 1944- ----------------              96, 169. 26
             RIVERS AND            HARBORS-NEW                             ORLEANS, LA., DISTRICT                  659

   Fiscal year ending June 30                  1940                 1941            1942        1943           1944

Cost of new work......
Cost of maintenance--.     --
                     ......-               -------             __    __----516.            51   4,453.91    ....

Total expended....--------      ----------------------------                          500. 39   4,470.03-
Allotted--        .          .---.
                        ..--------------------.-..
                                               _                    $10, 000      -9, 424. 35   4, 394. 77 ..............



Amount (estimated) required to be appropriated for completion of
existing project __   ___--                           -      -                                        $100, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance--_____-------------10,                                                              000. 00

                                          13. BAYOU TECHE, LA.

   Location.-Bayou Teche has its source in Bayou Courtableau, in St.
Landry Parish, and flows in a southeasterly direction, a distance of
125 miles, to where it joins the lower Atchafalaya River, about 101/2
miles above Morgan City, La. (See U. S. Coast and Geodetic Survey
Chart No. 1116 and Corps of Engineers, Mississippi River Commis-
sion Alluvial Valley maps, Palmetto, Opelousas, Carencro, Arnaud-
ville, St. Martinville, Loreauville, Derouen, Jeanerette, Foster, and
Belle Isle quadrangles.)
   Previous projects.-Authorized by River and Harbor Acts of July
11, 1870, and September 19, 1890. For further details, see page 1851,
Annual Report for 1915, and page 798, Annual Report for 1938.
   Existing project.-This provides for a channel 8 feet deep and 80
feet wide on the bottom from the mouth of the stream to New Iberia,
La., 54.5 miles, thence 6 feet deep and 60 feet wide on the bottom to
Keystone lock, 18 miles, and thence 6 feet deep and 50 feet wide on
the bottom to Arnaudville, La., 34 miles, to be secured by dredging,
removing snags and overhanging trees, and construction of a lock and
dam and regulating works. The plane of reference is mean low Gulf
level.
                                        Keystone lock
Distance from New Iberia -----------------------------                  18 miles.
Distance from Intracoastal Waterway-------------------- 82.5 miles.
Width of chamber_ -----------------------------------                   36 feet.
Length available for full width-------------------------                160 feet.
Lift   ---------------------------------------------- 8 feet.
Depth on miter sill at mean Gulf level ---------------------                 Do.
Character of foundation_---------                            ----       Timber piles.
Kind of dam----         --- __         ___-----------Timber,                      rock-fill.
Type of construction_       ----------------                      _----Concrete.
Year completed ----------------------------------------- 1913.
Cost--------------------------------------------------- $257,720.48.
   Installation of movable crest gates on Keystone dam is provided for
in the flood-control project for Bayou Teche.
   Under ordinary conditions the mean range of tide is about 10 inches
at the mouth, 4 inches just below the lock, and zero above the lock, the
extreme range of tide being about 12 inches, 6 inches, and zero, respec-
tively. The variation of the water surface above Keystone lock due
to freshets is from 2 to 7 feet, while just below the lock it has been as
high as 12 or 15 feet and near the mouth about 4 or 5 feet.
   The estimate of cost for new work, revised in 1928, is $850,000, exclu-
sive of amount expended on previous projects. The latest (1936)
660         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                   1944

approved estimate for annual cost of maintenance from mouth to
Arnaudville is $12,000, including $6,000 for operating and care of the
lock and dam.
  The existing project was authorized by the following river and
harbor acts:

     Acts                       Work authorized                                  Documents


Sept. 19, 1890   Improvement of the stream from its mouth to St.    Annual Report 1889, p. 1532.
                   Martinville by removing obstructions and
                  dredging.
Mar. 2,1907      Construction of lock and dam and the extension     H. Doe. No. 527, 59th Cong., 1st sess.
                   of the improvement to Arnau dville, La.
Mar. 2,1919      Increase of channel dimensions from mouth to       H. Doc. No. 1329, 62d Cong., 3d sess.
                  Keystone lock.
June 26,19341    Operation and care of lock and dam provided for
                  with funds from War Department appropria-
                  tions for rivers and harbors.


  1Permanent Appropriation Repeal Act.
  For latest published map see H. Doc. No. 288, 66th Cong., 1st sess.

    Local cooperation.-Fullycomplied with.
    Terminal facilities.-Small, privately owned wharves are available
at all the towns along the bayou; public landing is permitted with-
out charge. There are privately owned terminals for transferring
crude oil to barges near the towns of Charenton, Jeanerette, Olivier,
and St. Martinville. The facilities are considered adequate for exist-
ing commerce.
    Operations and results during fiscal year.-Keystone lock was oper-
ated throughout the year and the lock, dam, structures, and grounds
were maintained and necessary and routine work thereon was per-
formed at a cost of $11,409.34 (operating and. care). The total ex-
penditures were $11,540.44.
    Condition at end of fiscal year.-The existing project was about 84
percent complete. Keystone lock and dam were completed in 1913.
The dredging and snagging done in 1916 completed that part of the
existing project for the 6- by 50-foot channel from Arnaudville to
Keystone lock. The contract dredging done in 1918-20 completed that
part of the previous project for a 6- by 50-foot channel from Key-
stone lock to mile 39.7 above the mouth. The 8- by 80-foot channel
from New Iberia to the mouth is 98 percent complete. From the
mouth to mile 5.8 a channel 8 by 80 feet, or greater, already existed,
and a new channel has been excavated, 8 by 80 feet from this point
to mile 50.06, about 3.65 miles below New Iberia, and 8 by 60 feet
from this point to New Iberia. The work required to complete the
existing project is the widening of the channel to a bottom width of
80 feet from mile 50.06 to New Iberia, and to a bottom width of 60
feet from New Iberia to Keystone lock. The lock is in fair condition,
and Keystone dam is in good condition. Work in connection with
repairs to Keystone lock will be continued at a future date.
   The controlling depths at mean Gulf level on June 30, 1944, were:
Mouth to Baldwin, 8 feet; Baldwin to New Iberia, 7.5 feet; New Iberia
to Breaux Bridge, 5 feet. Controlling depth at mean low water above
              RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                              661
Keystone lock to Arnaudville was 5 feet.                                      The head of navigation is
at Arnaudville, La.
     The total costs under the existing project to the end of the fiscal
year have been $1,138,839.42, of which $708,625.40 was for new work,
 $287,586.44 for maintenance, and $142,627.58 for operation and care
of the lock and dam.                        The total expenditures have been $1,229,878.92,
including $91,389.25 expended between July 1, 1913, and June 30, 1935,
on the operation and care of the works of improvement under the
provisions of the permanent indefinite appropriation for such pur-
poses.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, $24,891.12, including accounts receivable, plus an allot-
ment of $12,000 made during July 1944, will be applied as follows:
Accounts payable June 30, 1944 -------------------------------                 $393. 28
Maintenance:
    By contract:
        Dredging between Baldwin and New Iberia, Janurary to
           March 1945 ------------------------------------                   20,000.00
    By hired labor:
        Investigations and removal of snags and other obstructions
           during fiscal year, as required_ ------------------------ 2,797.84
        Operation and maintenance of Keystone lock:
             Operation---------------------------               $12, 200.00
             Ordinary maintenance and repair-..-            _-.   1, 500. 00
                                                                             13, 700. 00

                         Total maintenance_---------------------------                                         36, 891. 12
  The additional sum of $16,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    By hired labor:
        Removal of obstructions during fiscal year, as required- ------                                           $2, 000
        Operation and maintenance of Keystone lock:
             Operation_ -------------------------------        $12, 500
             Ordinary maintenance and repair---------- ---        1, 500
                                                                                                                  14, 000

                        Totalbmaintenance ------------------------------                                          16, 000

                          Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                                               $754, 329. 83
Cost of maintenance to June 30, 1944------------------------                                                521, 603. 27
       Total cost of permanent work to June 30, 1944-- -------                                           1, 275, 933. 10
Plus accounts receivable June 30, 1944------ -----------------                                                    43. 53

      Gross total costs to June 30,1944--------- ------------ 1, 275, 976. 63
Minus accounts payable June 30, 1944---_------------- ------          393. 28
      Net total expenditures_-----------------------------                                               1, 275, 583. 35
Unexpended balance June 30, 1944----------------                                         -----   _           24, 847. 59

          Total amount appropriated to June 30, 1944------------                                         1, 300, 430. 94

    Fiscal year ending June 30                 1940             1941             1942             1943            1944


Cost of new work ......."...        ......
Cost of maintenance..........----------
                                                      ...
                                              $8, 355.80
                                                            ................
                                                             $20,617.34
                                                                                         . ..............--
                                                                               $50, 631.58      $13, 450. 07
                                                                                                                -.......   .
                                                                                                                 $11, 409.34
Total expended........-..--                    7, 662. 73      16, 521.47       54, 953.43       13, 480. 50      11,540. 44
Allotted.--...................... -          -8, 620. 36      77, 500. 00      -11,   471. 41    36, 000. 00
662      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                   1944

Balance unexpended July 1, 1943-- -         ----------                 $36, 388. 03
Gross amount expended_-------                                        -11,
                                                              .-------        540. 44
       Balance unexpended June 30, 1944---------------------              24, 847. 59
Outstanding liabilities June 30, 1944 ---------------------                   427. 80
       Balance available June 30, 1944_--           --------             24, 419. 79
Accounts receivable June 30, 1944_---------                      ---           43. 53
       Unobligated balance available June 30, 1944   ------------         24, 463. 32
Amount allotted in July 1944 -------------------------------              12, 000. 00
      Amount available during fiscal year 1945---------------            36, 463. 32
Amount (estimated) required to be appropriated for completion
  of existing project   1-----------------                               100, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946 for maintenance 1-      _- -                --            16, 000. 00
1Exclusive of available funds.

14. ATCHAFALAYA RIVER, MORGAN CITY TO THE GULF OF MEXICO, LA.
    Location.-The Atchafalaya River is an outlet of the Mississippi
  as well as of the Red River. It begins at Old River on the northern
boundary of Pointe Coupee Parish and flows generally south a distance
of about 170 miles and empties into Atchafalaya Bay, an inlet of the
Gulf of Mexico. The section under improvement is from the 20-foot
contour in Atchafalaya Bay, 4 miles beyond the mouth of the Atcha-
falaya River, to the 20-foot contour in the Gulf of Mexico, a distance
of about 1534 miles. (See U. S. Coast and Geodetic Survey Chart
No. 1276, Corps of Engineers, Mississippi River Commission Alluvial
Valley map, Point au Fer quadrangle, and navigation maps of Intra-
coastal Waterway and Atchafalaya River System.)
    Existing project.-This provides for a channel 20 feet deep and
200 feet wide, extending from the 20-foot contour in Atchafalaya Bay
4 miles beyond the mouth of the Atchafalaya River to the 20-foot
contour in the Gulf of Mexico, the total length of channel being 1513/4
miles. The project depth refers to mean low water. Under ordminary
conditions the mean range of tide is about 10 inches, the extreme
range of tide about 14 inches. During the hurricane of August 1915
there was a rise of tide of about 10 feet. The estifiated cost of new
work, made in 1910, was $500,000. The latest (1916) approved esti-
mate for annual cost of maintenance is $120,000.
    The existing project was adopted by the River and Harbor Act of
June 25, 1910 (H. Doc. No. 669, 61st Cong., 2d sess.). The latest
published map accompanies House Document No. 410, Fifty-sixth
Congress, first session.
    Terminal facilities.-At Morgan City there are several small pri-
vate wharves and two large and three small public wharves open to the
use of all without charge. There are no warehouses needed, as the
business section is on the river front and all freight is transferred
directly from boats to stores. The terminals are considered adequate
for the existing commerce.
    Operations and results during fiscal year.-None.
    Condition at end of fiscal year.-The existing project was completed
in 1914. The controlling depth at mean low Gulf on June 30, 1944,
was 7 feet; the minimum width 160 feet. The river is navigable
throughout the limits of the project.
    The total costs and expenditures under the existing project to the
end of the fiscal year have been $677,494.84, of which $501,963.23 was
for new work, and $175,531.61 for maintenance.
              RIVERS AND HARBORS-NEW                                      ORLEANS,               LA., DISTRICT                    663
  Proposed operations.--No funds are available. No operations are
proposed during the fiscal year 1945.
  The sum of $20,000 can be profitably expended during the fiscal year
1946 on maintenance dredging, by contract, of a 10- by 100-foot chan-
nel from Eugene Island to the 10-foot contour in the Gulf of Mexico
and for investigation and survey of the waterway by hired labor
during May and June 1946.
                                                  Cost and financial summary
Cost of new work to June 30, 1944----------------------------                                                         $501, 963. 23
Cost of maintenance to June 30, 1944---------------------                                                              175, 531. 61
           Total cost of permanent work to June 30, 1944-- ---------                                                   677, 494. 84
Net total expenditures -                          - _- --                      -    -       -       -   -     -        677, 494. 84
Total amount appropriated to June 30, 1944---- ----------                                                              677, 494. 84

    Fiscal year ending June 30                       1940          1941                   1942              1943            1944

Cost of new work...
Cost of maintenance         ....-----------
                                       .      -     $3, 262. 89     $157.77               $331.50            $216.49
Total expended-----------------                     20,164. 96       210. 33               308.79            239.20        ----

              __
Allotted -- - _--1,
               -    -----                              959. 37    25,177.85        -25,    373.00            -79.01


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance------------------------------------                                                         $20, 000. 00

   15. INTRACOASTAL                           WATERWAY, MISSISSIPPI RIVER TO BAYOU
                                                   TECHE, LA.

   Location.-This waterway extends in a westerly direction from the
Mississippi River, at or near Harvey, La., to Bayou Teche, La., above
Morgan City. This route follows the Harvey Canal No. 1, and
Bayou Barataria from the Mississippi River to Lake Salvador; thence
across Lake Salvador; thence through Harvey Canal No. 2 to Bayou
Lafourche and up this bayou to Lockport; thence through the Com-
pany Canal to Bayou Terrebonne and up this bayou to the vicinity of
Houma; thence through a land cut to Bayou Black; thence along
Bayou Black, Bayou Chene, and Bayou Boeuf to Morgan City; thence
up the Atchafalaya River to the mouth of Bayou Teche, a total dis-
tance of 115 miles. (See U. S. Coast ayd Geodetic Survey Chart No.
1116; U. S. Geological Survey maps, New Orleans, Bertrandville, Lake
Cataouatche East, Barataria, Cut-Off, Houma, and Gibson quadran-
gles; Corps of Engineers, Mississippi River Commission Alluvial
Valley maps, Morgan City and Belle Isle quadrangles; and navigation
maps of Intracoastal Waterway and Atchafalaya River System.)
   Existing project.-This provides for a waterway from the Missis-
sippi River to Bayou Teche having a depth of 5 feet below mean low
Gulf level and a bottom width of 40 feet, with appropriate side slopes.
This project has been largely superseded by the Gulf Intracoastal
Waterway (New Orleans district). Under ordinary conditions the
mean range of tide is about 10 inches, and the extreme range about
14 inches. A severe storm may cause a high tide of from 6 to 9 feet.
   The estimate of cost for new work revised in 1922 is $875,000. The
latest (1919) approved estimate for annual cost of maintenance is
$20,000. The existing project was adopted by the River and Harbor
664         REPORT OF CHIEF OF ENGINEERS,                       U. S. ARMY,           1944

Act of March 2, 1919 (H. Doc. No. 610, 63d Cong., 2d sess.). The
latest published map is printed opposite page 2401 of the Annual
Report for 1920.
   Local cooperation.-Fully complied with.
   Terminal facilities.-On Bayou Terrebonne, at Houma, there are
several small privately owned wharves. On the Atchafalaya River at
Morgan City there are two large and three small wharves open to all
without charge; there are several private wharves. The facilities are
considered adequate for existing commerce.
   Operationsand results during fiscal year.-None.
   Conditionat end of fiscal year.-This project has not been completed
and has been superseded for most of its lengths by the present 12- by
125-foot Gulf Intracoastal Waterway which coincides with or parallels
it. Only those sections of the project which are used for navigation are
being maintained. The total costs and expenditures have been $5,866.64,
all for maintenance.
   All costs and expenditures incurred prior to July 1 1939, are re-
ported under previous projects of the Gulf IntracoastalWaterway be-
tween Apalachee Bay, Fla., and the Mexican Border (New Orleans
district).
   Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
   The sum of $1,000 can be profitably expended during the fiscal year
1946, on the removal of snags and obstructions by hired labor and
Government plant at such times as required.
                                 Cost and financial summary
Cost of new work to June 30, 1944------------------------------------
Cost of maintenance to June 30, 1944-------------------------- $5, 866. 64
      Total cost of permanent work to June 30, 1944------------                              5, 866. 64
Net total expenditures --------------------------------------                                5, 866.64
Total amount appropriated to June 30, 1944--- -----------------                              5, 866. 64

   Fiscal year ending June 30        1940          1941          1942          1943            1944


Cost of new work---
Cost of maintenance-------------$1,344.96         $2, 661. 60      $49.64     $1,810. 44
Total expended.-----------------     1,318. 10       112.62      2,625.48      1,810.44
Allotted   -----------------------   6,996. 46   -1, 644.00      1, 203. 74    -689. 56      .....



Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance -------------------------------                                 $1, 000. 00

16. THE INLAND WATERWAY FROM FRANKLIN TO THE MERMENTAU
                        RIVER, LA.

   Location.-This canal extends from Hanson lock on Bayou Teche
through Hanson Canal and Bayou Portage to the Intracoastal Water-
way, along the Intracoastal Waterway to its intersection with the
Schooner Bayou cut-off, along this cut-off to Schooner Bayou, thence
through Schooner Bayou and a land cut to White Lake, through
White, Turtle, Alligator, Collicon Lakes and connecting canals to
Grand Lake, and through Grand Lake to the Mermentau River at
its northern entrance into the lake. The total length of the water-
           RIVERS AND HARBORS-NEW             ORLEANS, LA., DISTRICT         665
way is 53.6 miles. (See U. S. Coast and Geodetic Survey Chart No.
1116; Corps of Engineers,. Mississippi River Commission Alluvial
Valley maps, Foster, Bayou Sale, Jeanerette, and Derouen quad-
rangles; U. S. Geological Survey maps, Abbeville (southeast), Abbe-
ville (southwest), Redfish Point, Schooner Bayou (southeast), Pecan
Island (northeast), Pecan Island (northwest), Constance Bayou
 (northeast), Grand Lake East (southeast), Grand Lake East (south-
west), and Latania Lake quadrangles; and navigation maps of Intra-
coastal Waterway and Atchafalaya River System.)
   Existing project.-This project provides for a waterway from Bayou
Teche at or near Franklin, La., to the Mermentau River, having a
depth of 5 feet below mean low Gulf and a bottom width of 40 feet,
with appropriate side slopes; also the purchase of the Hanson Canal
and the construction of a lock and dam in Schooner Bayou. This
project, reported in the Annual Report for 1924 under the headings,
Intracoastal Waterway, Franklin to Mermentau, La., and Intracoastal
Waterway from Vermilion River to Schooner Bayou, La., has largely
been superseded by the project "Gulf Intracoastal Waterway (New
Orleans district)." Under ordinary conditions the mean range of
tides is about 10 inches and the extreme range about 14 inches. A
severe storm may cause a high tide of from 6 to 9 feet.
   The estimate of cost for new work, revised in 1920, was $722,000.
The latest (1936) approved estimate for annual cost of maintenance is
$32,000, including $12,000 for operation and care of the locks. The
estimate of cost for the Schooner Bayou cut-off, made in 1913, was
$37,500 for new work and $1,800 for annual maintenance.
   Data regarding the locks are as follows:
                                    Hanson lock
Miles from Franklin, La__                      1.5.
Miles from Bayou Teche_                        0.
Width of chamber                               26.5 feet.
Length available for full width-               937 feet.
Lift __ _ - _ _                                0 to 5 feet.
Depth on miter sill at low water_              5 feet.
Character of foundation_                       Timber piles.
Kind of dam-                                   None.
Type of construction__                         Concrete buttresses, wooden miter-
                                                  ing gates, earth-lock chamber.
Completed 1907. Operated by the United
  States since 1923.
Cost_------------------               - $65,000, including 4.1 miles of canal.

                                 Schooner Bayou lock
Miles from Abbeville, La_                      32.
Miles from Vermilion River-            -       9.
Width  of chamber_                             36 feet.
Length available for full width-               300 feet.
Lift     -                                     0 to 3 feet.
Depth on miter sill at low water_              8 feet.
Character of foundation_                       Timber piles.
Kind of dam_                                   Timber.
Type of construction_---------                 Concrete buttresses, wooden gates
                                                  turning on horizontal hinges at
                                                  bottom, earth-lock chamber.
Lock completed and opened to navigation
  1913; dam completed 1914.
Cost---- -----------------------               $40,018.10 for lock and $0500 for
                                                 dam.
666         REPORT OF CHIEF OF ENGINEERS,                                    U. S. ARMY,          1944

  The existing project was authorized by the following river and
harbor acts:

              Acts                               Work authorized                              Documents 1


Mar. 2,1907-----------------
                  .                 The general project------------------_         H.    Doc. No. 640, 59th Cong.,
                                                                                        2d sess.
Mar. 3, 1909, and Feb. 27, 1911_- Authorized the Secretary of War to make
                                   such changes in location of channel as
                                   might be desirable.
               ----------------- Authorized the purchase of the so-called
July 25, 1912 .......
                                     Hanson Canal between Bayou Teche
                                     and Cote Blanche Bay, at a cost not to
                                     exceed $65,000.
           ----------------
Mar. 2, 1919_                       Construction of the Schooner Bayou             H.      Doc.    No.    1336,   62d
                                      cut-off.                                          Cong., 3d sess.
June 26, 1934 (Permanent Ap-        Inclusion of operation and care of locks
propriations Repeal Act).            in project provided for with funds from
                                      War Department appropriations for
                                      rivers and harbors.


I Contain latest published maps.

   Local cooperation.-Fully complied with.
   Terminal facilities.-This improvement comprises a system of arti-
ficial canals and natural waterways passing through an isolated marsh
section of the State, and there are no existing facilities for handling
freight along the route.
   Operations and results during fiscal year.-Hanson and Schooner
Bayou locks were operated, as required, throughout the fiscal year;
the locks, structures, and grounds were maintained in good condition,
and all necessary and routine maintenance work thereon performed at
a cost of $7,310.15, for operating and care. The total expenditures
were $7,347.03.
   Condition at end of fiscal year.-The existing project is completed.
The Hanson Canal and lock were acquired on October 16, 1923; the
lockmaster's house was completed in 1924; the United States property
on which the lock is situated is a strip of land 300 feet wide between
parallel lines running from Bayou Teche to Bayou Portage, and con-
taining 148 acres. Dredging from Vermilion Bay to the Mermentau
River was completed in 1912. The lock and dam at Schooner Bayou
lock were completed in 1913 and 1914, respectively, and the lockmas-
ter's house in 1917. The United States reservation at Schooner Bayou
lock comprises 2 acres. The controlling depth on June 30, 1944, was
3 feet. The channel is navigable throughout its length.
   The total costs to the end of the fiscal year under the existing proj-
ect have been $527,255.45, of which $249,051.81 was for new work,
$118,514.61 for maintenance, and $159,689.03 for operation and care
of locks. The total expenditures have been $692,326.21, including the
sum of $165,298.55 expended under the provisions of the permanent
indefinite appropriation for such purposes.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $2,788.63, including accounts receivable, plus an allotment
of $10,000 made during July 1944, will be applied as follows:
        *
           RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                   667
Accounts payable June 30, 1944-------------------------------$239. 19
Maintenance:
    Hired labor:
         Removal of obstructions and examination of the waterway as
              required_                               ----------                              _      3, 349.44
           Operation and maintenance of Schooner Bayou
            lock:
               Operation_    -                             $5, 600. 00
               Ordinary maintenance and repair -----------     900. 00
                                                                                                    6, 500. 00
           Operation and maintenance of Hanson lock:
                 Operaticn_                   -----------                          2,500. 00
                 Ordinary maintenance and repair -----------                         200. 00
                                                                                                    2, 700. 00
                                     ---------------------
                    Total maintenance__                                                       _    12, 788. 63
   The additional sum of $11,500 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Hired labor:
        Removal of obstructions and examination of the waterway as
           required--   ----------------------------------------                                       $1,000
        Operation and maintenance of Schooner Bayou lock:
             Operation                -------------              $6, 000
             Ordinary maintenance and repair-                     1,500
                                                                                                         7, 500
           Operation and maintenance of Hanson lock:
                        -----------------------------
               Operation_                                                                   2,500
               Ordinary maintenance and repair------------ ---                                500
                                                                                                         3, 000
                    Total maintenance             ------------------------------                       11, 500

                                   Cost aud financial summary
Cost of new work to June 30, 1944___                                                          $249, 051.81
Cost of maintenance to June 30, 1944------------------                                         443, 502. 19
       Total cost of permanent work to June 30, 1944-      -    692, 554. 00
Plus accounts receivable June 30, 1944-------------------------       11. 40
      Gross total costs to June 30, 1944---- ----------------- 692, 565. 40
Minus accounts payable June 30, 1944-------------------------       239. 19
      Net total expenditures_ -_                -------                                           692, 326. 21
Unexpended balance June 30, 1944----------------------------                                       2777.
                                                                                                    2,      23
        Total amount appropriated to June 30, 1944--------                                        695, 103. 44


   Fiscal year ending June 30        1940               1941        1942             1943              1944

Cost of new work ...                                                                $7 3.4...
Cost of maintenance----------
                     .........-- $18, 948. 69        $15, 619. 78   $16, 766. 70    $7,237 41          $7, 310. 15
Total expended-----------------     18, 186. 43        16,376. 54    16, 698. 35     7, 504. 97        7, 347. 03
Allotted.-----------------------    16, 500. 00        20, 500.00   -2, 497. 53     10,000. 00


Balance unexpended July 1, 1943 ----------------------------                                      $10, 124. 26
Gross amount expended -------------------------------------                                         7, 347.03
      Balance unexpended June 30, 1944 .-                                                           2, 777. 23
Outstanding liabilities June 30, 1944-                                                                 300. 00
        Balance available June 30, 1944-                                                            2, 477. 23
668         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

Accounts receivable June 30, 1944 ------------------------------                                  $11.40

     Unobligated balance available June 30, 1944---------------2, 488. 63
Amount allotted in July 1944_                                 -10, 000. 00
         Amount available during fiscal year 1945------------------12, 488. 63

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance     -  _ _____      -_____                                         11, 500. 00
  1 Exclusive of available funds.

                17. PETIT ANSE, TIGRE, AND CARLIN BAYOUS, LA.
   Location.-Bayou Tigre is a tributary of Bayou Carlin; Bayou
Carlin is a tributary of Bayou Petit Anse. Bayou Petit Anse has its
source in Iberia Parish about 5 miles northwest of New Iberia. It
flows in a southwesterly direction for about 15 miles to its intersec-
tion with the Intracoastal Waterway, thence for a distance of about
3 miles to Vermilion Bay. Bayou Tigre has its source in Vermilion
Parish about 6 miles northeast of Abbeville and flows in a southerly
direction for about 7 miles to its junction with Bayou Carlin. Bayou
Carlin has its source in Lake Peigneur in Iberia Parish and flows in
a southerly direction about 7.5 miles to its confluence with Bayou Petit
Anse at a point about 2.3 miles above the Intracoastal Waterway.
 (See U. S. Coast and Geodetic Survey Chart No. 1116, and Corps of
Engineers, Mississippi River Commission Alluvial Valley maps, De-
rouen quadrangle, and U. S. Geological Survey map, Abbeville, N. E.,
quadrangle.)
   Existing project.-This provides for dredging a channel in Bayou
Petit Anse 9feet deep and 80 feet wide from the Intracoastal Water-
way to the north end of Avery Island; a channel 5 feet deep and 40
feet wide from the Intracoastal Waterway via the McIlhenny Canal
to deep water in Vermilion Bay; and a channel 5 feet deep over a bot-
tom width of 40 feet in Bayou Carlin from Bayou Petit Anse to Lake
Peigneur. The total length of the improvements is 16.1 miles. Under
ordinary conditions the mean range of tide is about 10 inches.
   The estimated cost of new work, revised in 1937, was $58,500. The
latest (1940) approved estimate for annual cost of maintenance is
$6,500.
   The existing project was authorized, by the following river and
harbor acts:

     Acts                           Work authorized                               Documents


Aug. 30,1935 1 A channel in Bayou Petit Anse 60 feet wide and 9      H. Doc. No. 225, 72d Cong., 1st sess.
                 feet deep from the Intracoastal Waterway to a
                 point 3.2 miles upstream, thence 40 feet wide and
                 5 feet deep to highway bridge at head of Avery
                 island; and a channel in Bayou Carlin 40 feet
                 wide and 5 feet deep from Bayou Petit Anse to
                 Lake Peigneur.
Aug. 26, 1937   A channel in Bayou Petit Anse 9 feet deep and 80     Rivers and Harbors Committee Doc.
                 feet wide from the Intracoastal Waterway to           No. 40, 75th Cong., 1st sess. (Con-
                 the north end of Avery Island and a channel 5         tains latest published map.)
                  feet deep and 40 feet wide from4te Intracoastal             ,
                  Waterway to Vermilion Bay by way of the
                  McIlhenny Canal.


  1 Included in the Public Works Administration program Sept. 6, 1933.
       RIVERS AND HARBORS-NEW          ORLEANS, LA., DISTRICT       669
   Recommended modification of project.-In House Document No.
594, Seventy-eigth Congress, second session, it is recommended that
the existing project be modified to provide for a channel 9 feet deep
and 80 feet wide in Bayou Carlin from Bayou Petit Anse to Lake
Peigneur at an estimated first cost of $160,000, with $1,000 annually
for maintenance in addition to the amount now required, subject to
certain conditions of local cooperation.
   Local cooperation.-The work included in the Public Works pro-
gram and adopted by the River and Harbor Act of August 30, 1935, is
subject to the condition that local interests furnish all rights-of-way
and suitable areas for disposal of dredged material, and shall con-
struct a suitable public terminal at the head of Avery Island and
reconstruct all highway and railroad bridges to provide suitable clear-
ance, all without cost to the United States. These requirements, ex-
cepting the construction of a public terminal, have been complied
with. Under the provisions of the River and Harbor Act of August
26, 1937, local interests are required to furnish free of cost to the
United States, rights-of-way of not less than 200 feet along the
McIlhenny Canal and suitable spoil-disposal areas for new work and
subsequent maintenance as required.
   The necessary rights-of-way and spoil areas have been furnished by
local interests and accepted by the Chief of Engineers September 1,
1938.
   Under a permit issued March 24, 1937, the Texas Pipe Line Co. en-
larged the 5- by 40-foot channel in Bayou Petit Anse above mile 3.2 to
a depth of 9 feet and a width of 80 feet at an estimated cost of $30,000.
    Terminal facilities.-There is an extensive oil terminal at the head
of the improvement on Bayou Petit Anse and several private docks
and cane hoists. (Terminal facilities are further described in H. Doc.
No. 225, 72d Cong., 1st sess.) These facilities are considered adequate
for existing commerce.
    Operationsand results during fiscal year.-None.
    Conditionat end of fiscal year.-The existing project was completed
in 1939. The controlling depths at mean low Gulf level on June 30,
1944, were as follows: In Bayou Petit Anse from the Intracoastal
Waterway to Avery Island, 8 feet; in Bayou Carlin to Lake Peigneur,
5 feet; in channel from Intracoastal Waterway to Vermilion Bay via
McIlhenny Canal, 3 feet. The channel is in good condition. The
head of navigation on Bayou Petit Anse is the highway bridge north
of Avery Island; and on Bayou Carlin, Lake Peigneur.
    The total costs and expenditures under the existing project to the
end of the fiscal year have been $91,810.12, of which $57,490.29 was for
new work, including $47,858.13, Public Works funds; and $34,319.83
from regular funds for maintenance.
    Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
    The sum of $2,500 can be profitably expended during the fiscal year
1946 on removal of obstructions by hired labor and Government plant
at such times during the year as required.
670            REPORT OF CHIEF OF ENGINEERS,                                       U.   S.     ARMY,      1944

                                               Cost and financial summary
Cost of new work to June 30, 1944_---------------------------                                               $57, 490. 29
Cost of maintenance to June 30, 1944-------------------                                                      34, 319. 83
      Total cost of permanent work to June 30, 1944-                                             -91,            810. 12
Net total expenditures ___________------                                                       -_____        91, 810. 12
Total amount appropriated to June 30, 1944---- ---------                                                     91, 810. 12

    Fiscal year ending June 30                    1940               1941           1942           1943          1944


C ost of new work....-                      .-        - --.                           . ..
                                                                   - - - --.- - - - --..    . . . .. . . . . .
Cost of maintenance....                     --------------...
                                    ..---------...                $20, 908.57 --- -----    --------------
Total expended............--------------.           ...--------------20, 908. 57
Allotted- -------.---------------.-------                          21, 000. 00      -$91.    73.


Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance_ ---------------------------------                                                $2, 500. 00

       18. MERMENTAU RIVER, BAYOU NEZPIQUE, AND BAYOU DES
                            CANNES, LA.

    Location.-Mermentau River is formed by the junction of Bayous
des Cannes and                2.25 miles above Mermentau, La., and
                                  -Nezpique,

flowing in a southwesterly direction empties into the Gulf of Mexico.
    Bayou Nezpique rises in Evangeline Parish, flows in a southerly
direction, and empties into the Mermentau River.
    Bayou des Cannes rises in Evangeline Parish, flows in a south-
southwesterly direction, and empties into the Mermentau River. (See
U. S. Coast and Geodetic Survey Charts Nos. 1116 and 19278, and
U. S. Geological Survey maps, Evangeline, Hathaway, Mermentau,
Jennings, Lake Arthur, Gueydan, Thornwell, Latania Lake, Catfish
Lake, Grand Cheniere, and Bayou Labauve quadrangles.)
    Existing project.-The project provides for the removal of obstruc-
tions to navigation to secure the natural channel throughout the
entire Mermentau River, a distance of 71.5 miles, and through Bayou
Nezpique from its mouth to 25-miles above, and Bayou des Cannes
from its mouth to Evangeline Bridge (mile 8.5); for improving the
channel in Lower Mud Lake by constructing a brush dam to con-
centrate the action of the current and by dredging; and for remov-
ing a portion of the wrecked dam 7 miles above the mouth; and for
dredging a channel 9 feet deep over a bottom, width of 100 feet from
the Intracoastal Waterway to the junction of Bayous Nezpique and
des Cannes.
    Under ordinary conditions the mean range of tide on the Mer-
mentau River near the mouth is 10 inches and near the head about 3
inches, the extreme range being 14 inches and about 5 inches, respec-
tively. The variation of the water surface near the mouth may be as
much as 7 or 8 feet, due to hurricanes on the Gulf, and near the head
from 8 to 12 feet, due to freshets. On Bayou Nezpique, under ordi-
nary conditions, the range of tide is about 3 inches at the mouth and
nothing at the head. On Bayou des Cannes, under ordinary condi-
tions, the range of tide is about 3 inches at the mouth and nothing
at the head.
   The estimate of cost for new work, revised in 1935, was $53,615;
and that for the removal of the dam, made in 1916, $1,500. The
            RIVERS AND HARBORS-NEW                      ORLEANS,         LA., DISTRICT            671
latest (1935) approved estimate of cost for annual maintenance is
$2,200.
   The existing project was authorized by the following river and
harbor acts:

    Acts                      Work authorized                                 Documents


July 13,1892    General project _      _       _    _            Annual Report, 1891, p. 1862.
July 27,1916    Removal of portion of wrecked dam near mouth     H. Doc. No. 1232, 64th Cong., 1st sess.
                  of Mermentau River.
Mar. 2,1919     Improvement of Bayou Des Cannes     -- -         H. Doc. No. 1398, 65th Cong., 3d sess.
Aug. 30,19351   Channel in Mermentau River 9 feet deep plus 1     Rivers and Harbors Committee Doc.
                 foot overdepth from Intracoastal Waterway to     No. 36, 72d Cong., 1st sess. (Con-
                 the source at confluence of Bayous Nezpique       tains latest published map.)
                 and Des Cannes.


  1 Included in the Public Works Administration program Mar. 28, 1934.

   Local cooperation.-Fully complied with.
   Terminal facilities.-There are several small, privately owned
wharves at Grand Cheniere and a public terminal at the town of Lake
Arthur. At Mermentau, La:, the Southern Pacific Railroad owns a
wharf served by a spur track. Privately owned terminals for trans-
ferring crude oil to barges are at the following locations: One on
Lake Arthur near the town of Lake Arthur; one on the Mermentau
River near the, town of Mermentau; two on Bayou Nezpique near
Jennings; and four on Bayou des Cannes, one near Evangeline, one
at Mermentau, and two near Jennings. The facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Conditionat end of fiscal year.-The existing project, except for the
9- by 100-foot channel, was completed in 1917. The 9- by 100-foot
channel was completed in 1935. The controlling depths at mean low
Gulf level on June 30, 1944, were as follows: 2 feet across the bar at
mouth of the Mermentau River; 2 feet through Lower and Upper
Mud Lakes and Lower Grand Lake; 5 feet, Upper Grand Lake to the
Intracoastal Canal; 8 feet from the Intracoastal Canal to the junction
of Bayous Nezpique and des Cannes; Bayou Nezpique, 8 feet from its
mouth to mile 23; and 4.5 feet between mile 23 andmile 25; Bayou
des Cannes, 4 feet from its mouth to mile 8.5. The Mermentau River
is navigable throughout; Bayou Nezpique for a distance of 25 miles;
and Bayou des Cannes for a distance of 8.5 miles.
   The total costs and expenditures (regular funds) under the exist-
ing project have been $81,357.11, of which $27,580.35 was for new
work, and $53,776.76 was for maintenance.
   The total costs and expenditures (Public Works funds) under the
existing project have been $29,974.42, all for new work, The total costs
and expenditures, all funds, have been $111,331.53, of which $57,554.77
was for new work, and $53,776.76 for maintenance.
   Proposed operations.-No funds are available. No operations are
proposed during the fiscal year 1945.
   The sum of $2,000 ctn be profitably expended during the fiscal year
1946 on the removal of obstructions by hired labor and Government
plant at such times as required during the fiscal year.
672             REPORT OF CHIEF OF ENGINEERS,                               U. S. ARMY,             1944

                                              Cost and financial summary
                                 ---------------------------
Cost of new work to June 30, 1944_                                                                       $57, 454. 77
Cost of maintenance to June 30, 1944_   -  ------          ----                                           53, 776. 76

      Total cost of permanent work to June 30, 1944------------                                          111, 331. 53
Net total expenditures--
                      ____---------------111,                                                                 331. 53
Total amount appropriated to June 30, 1944_                          -------------------                 111, 331. 53


   Fiscal year ending June 30                   1940          1941            1942           1943                  1944

C ost of new w ork..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cost of maintenance           ........             .
                                                _$245.
                                               __.       .           00        $441. 28      $102.46      _

Total expended--_----------                                     176.88          509. 20        102.66_

           --
Allotted_-__             -               --         $500     13, 000. 00   -12, 710.00- --           -        --          $1.26



Balance unexpended July 1, 1943_--        ------------                                                              $1. 26
Deductions on account of revocation of allotment-----------------                                                    1. 26

Amount that can be profitably expended in fiscal year ending June 30,
1946, for maintenance---
                        __        -------------                       -2,                                          000. 00

                              19. CALOASIEU RIVER AND PASS, LA.

   Location.-Calcasieu River has its source in southwestern Louisi-
ana, and flows in a generally southerly direction to the Gulf of
Mexico. About 25 miles from the Gulf it debouches into Calcasieu
Lake, which lake is about 18 miles long. The connection between the
lake and the Gulf, about 7 miles long, is known as Calcasieu Pass.
 (See U. S. Coast and Geodetic Survey Charts Nos. 591 and 592; U. S.
Geological Survey maps, Edna, Thompson Bluff, Hecker, Moss Bluff,
Lake Charles, West Lake, Moss Lake, Hackberry, Sweet Lake,
Brown's Lake, Holly Beach, Grand Bayou, and Cameron quad-
rangles; and Corps of Engineers, Mississippi River Commission navi-
gation maps of Intracoastal Waterway and Atchafalaya River
System.)
   Previous projects.-The original project for this improvement was
adopted by the River and Harbor Act of June 10, 1872. Appropria-
tions were made by the River and Harbor Acts of March 3, 1881,
August 2, 1882, July 5, 1884, and August 11, 1888. The project was
modified by the River and Harbor Acts of September 19, 1890, July
13, 1892, and September 22, 1922. For further details, see Annual
Report for 1936, page 719, and Annual Report for 1938, page 819.
   Existing project.-This provides for a chainel 30 feet deep and 250
feet wide from the wharves of the Lake Charles Harbor and Terminal
District by way of Calcasieu River to the head of Choupique cut-off;
thence by a land-and-water cut along the west shore of Calcasieu
Lake; thence to and through Calcasieu Pass by a designated route to
the Gulf of Mexico, subject to such change in alinement as is ap-
proved by the Chief of Engineers; the reconstruction and extension
of the existing jetties initially to the seaward end of the east jetty,
and further extension to the 15-foot depth contour if found advisable
to reduce maintenance dredging costs; dredging, a channel 30 feet
deep and 250 feet wide between the jetties, and an approach channel
32 feet deep and 400 feet wide from the sea end of the jetties to a
depth of 32 feet in the Gulf of Mexico; also for the improvement of
            RIVERS AND        HARBORS-NEW              ORLEANS,           LA.,   DISTRICT         673
the river from Lake Charles to Phillips Bluff by removing logs, snags,
overhanging trees, and by dredging. Total length of improvement
is 94.7 miles. Under ordinary conditions, the mean range of tide is
10 inches at the mouth, diminishing to zero at Phillips Bluff, the ex-
treme range being 14 inches and zero, respectively.
   The estimate of cost for new work, including $3,400,000 for the
extension of the jetties to the 15-foot contour, revised in 1937, is
$9,260,000. The latest (1937) approved estimate for cost of main-
tenance is $250,000 annually for the first 3 years and $190,000 annu-
ally thereafter.
   The existing project was authorized by the following river and
harbor acts:

     Acts                     Work authorized                                    Documents


 _    . .... Modification of original project of 1872, dated
      -..                                                        H.     Ex. Doc. No. 46, 46th Cong., 3d
              May 12, 1881, provided for general improve-             sess.; and A. R. 1881, p. 1301.
                ment of the river from Phillips Bluff to the
                mouth by removing logs, snags, and overhang-
                ing trees, and by dredging.
Aug. 26,1937   Channel 30 feet deep and 250 feet wide from the   H. Doc. No. 299, 75th Cong., 1st sess.
                Lake Charles docks to the Gulf of Mexico.          (Contains latest published map.)


   Recommended modifications of project.-Under date of August
22, 1941, the Chief of Engineers recommended modification of the
existing project so as to provide for a channel 30 feet deep and 250
feet wide, suitably widened at bends, around Clooney Island, at an
estimated first cost of $55,000, with $3,000 annually for maintenance,
in addition to the amount now required, subject to certain conditions
of local cooperation (H. Doc. 465, 77th Cong., 1st sess.).
   Local cooperation.-Fully complied with.
   Under date of January 5, 1922, a permit was granted by the Assist-
ant Secretary of War to the police jury of Calcasieu Parish to enlarge
this river where necessary between Lake Charles and the eastern end
of the Calcasieu-Sabine section of the Intracoastal Waterway to a
depth of 30 feet over a bottom width of 125 feet.
   Terminal facilities.-Terminal facilities at the Port of Lake Charles
are owned by the Lake Charles Harbor and Terminal District and
operated by a board of commissioners. In addition to the municipally
owned terminals, there are several privately owned and operated
wharf structures located on the existing ship channel. (For further
details see Port Series No. 31, Corps of Engineers.)
   Operations and results during fiscal year.-Dredging of 4,003,366
cubic yards of material for maintenance of the channel to project di-
mensions was accomplished as follows: 1,822,060 cubic yards by the
United States dredge Benyaurd from seaward end of jetties to -32-
foot contour in the Gulf of Mexico; and 2,181,306 cubic yards from mile
12 to mile 29.8 above the mouth of Calcasieu Pass, by the U. S. dredge
Pullen at a cost of $227,337.06.
   The total costs for the year were $240,303.51, of which $12,966.45
was for delayed costs on new contract work completed during previous
fiscal years, and $227,337.06 for maintenance. Total expenditures were
$256,105.47.
        616(;34--45-pt. 1,vol. 1----3
674     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                        1944

   Condition at end of fiscal year.-Dredging in accordance with the
existing project was completed on April 25, 1941.
   The Calcasieu Pass jetties on the previous project were completed
in 1900. The east jetty is 8,620 feet long, of which 7,170 feet have been
built to approximately 6 feet above mean low Gulf level, and is gen-
erally above normal high tide. East jetty extends seaward from the
existing Gulf shore line a distance of 6,820 feet. West jetty is 8,050
feet long, of which 2,570 feet have been built to approximately 4 feet
above mean low Gulf level, and is generally above normal high tide.
West jetty extends seaward from the existing Gulf shore line a dis-
tance of 6,795 feet. The jetty extension to the 12-foot contour is
complete.
   The controlling depths at mean low Gulf on June 30, 1944, were as
follows: Over the bar at the mouth of Calcasieu Pass, 23 feet; through
the jetty channel, 32 feet; through Calcasieu Pass, 29 feet; through
Calcasieu Lake, 24 feet; from Calcasieu Lake to Lake Charles, 27 feet;
and from Lake Charles to Phillips Bluff, the head of navigation, 5 feet.
The jetties are in good condition. Shoaling has occurred in the bar
channel and in Calcasieu Lake from the head of Calcasieu Pass to mile
12 above the mouth of the pass, and dredging is contemplated to restore
project dimensions. Above Lake Charles the channel is in poor con-
dition.
   The project is now considered complete unless at a later date it is
found necessary to extend the jetties seaward to the 15-foot contour, as
provided in the project document.
   The total costs of the existing project to the end of the fiscal year have
been $4,936,170.84, of which $4,258,694.94 was for new work and $677,-
475.90 was for maintenance. The total expenditures have been
$4,936,106.84.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $6,393.11, including accounts receivable, plus an allotment
of $150,000 made during July 1944, will be applied as follows:
Accounts payable June 30, 1944             _-       _---------     ---
                                                                    _           $150. 31
Maintenance:
   Hired labor:
        Maintenance dredging by U. S. hopper dredge Benyaurd
          from the shore line to the minus 32-foot contour in the
          Gulf of Mexico, as required during the fiscal year _-..      70, 000. 00
        Maintenance dredging by U. S. pipe-line dredge Pullen
          between Lake Charles and the Gulf of Mexico, as re-
          quired during the fiscal year - -                       -81,     000. 00
        Surveys and observations between Lake Charles and the
          Gulf of Mexico ___                                  _5,          242.80
             Total maintenance -----------------------           _ _       156, 393. 11
  The additional sum of $180,000 can be profitably expended during
the fiscal year 1946 as follows:
Dredging by contract between Lake Charles and the Gulf of Mexico,
  as required during the fiscal year                       ---      $105, 000
Dredging by U. S. hopper dredge Benyaurd from the shore line to the
  minus 32-foot contour in the Gulf of Mexico---------------------    70, 000
Surveys and observations between Lake Charles and the minus 32-foot
  contour in the Gulf of Mexico ---------------------------------      5, 000
      Total maintenance- .     -....---------                                   180, 000
               RIVERS AND HARBORS-NEW                                 ORLEANS, LA., DISTRICT                              675
                                          Cost and financial summary
Cost of new work to June 30, 1944 _                               -____$4,                                   754, 608. 57
Cost of maintenance to June 30, 1944_------------------------                                                872, 326. 78
       Total cost of permanent work to June 30, 1944 _----                                              5, 626, 935. 35
Plus accounts receivable June 30, 1944 --            -_                                                       -86.   31

      Gross total costs to June 30, 1944-----------------                                               5, 627, 021. 66
Minus accounts payable June 30, 1944---       ----------                                                        150. 31

    Net total expenditures_ _____------------5,                                                              626,871.35
Unexpended balance June 30, 1944 _                                --------                                     6, 306. 80
             Total amount appropriated to June 30, 1944------------                                     5, 633, 178. 15

    Fiscal year ending June 30                1940             1941               1942           1943                1944

Cost of new work- ..-...         ..    $1, 493, 790.13      $923,149. 60       $793, 479.61       $271.43        $12, 966. 45
Cost of maintenance--- .---------------                      272, 366. 33        23, 629.19    154, 143.32       227, 337.06
       Total cost_--- -       - ---      1,493, 790.13     1,195, 515.93        817,108.80     154, 414.75       240, 303. 51
Total expended---------------            1, 373, 458. 35   1,139, 423, 63     1, 076, 065.13   183, 906.80       256,105.47
Allotted-_       -        ----------... ____876, 413. 64     137, 000.00        225, 000.00    179, 000.00---    -    -     -


Balance unexpended July 1, 1943-                                                                         $262, 412. 27
Gross amount expended---  -___---------_256,                                                                   105.47
       Balance unexpended June 30, 1944 --------------------                                                    6, 306. 80
Outstanding liabilities June 30, 1944-------------------------                                                     529. 61
      Balance available June 30, 1944--------------------                                                       5, 777. 19
Accounts receivable June 30, 1944---------------------------                                                        86. 31
     Unobligated balance available June 30, 1944-   -- ___                                                     5, 863. 50
Amount allotted in July 1944------------------------ ------                                                  150, 000. 00
             Amount available during fiscal year 1945                        ---------------                 155, 863. 50
Amount (estimated) required to be appropriated for completion
of existing project 1                                                                                  3, 400, 000. 00
Amount that can he profitably expended in fiscal year ending
June 30, 1946 for maintenance 1 -----           -------                                                     180, 000. 00
  1Exclusive of available funds.

                     20. LAKE CHARLES DEEP WATER CHANNEL, LA.
   Location.-The Lake Charles Deep Water Channel, 24.9 miles in
length, extends from the Calcasieu River to the Sabine River, follow-
ing the Calcasieu-Sabine section of the Intracoastal Waterway. The
channel has access to deep water through the Sabine River, Sabine-
Neches Canal, Port Arthur Canal, and Sabine Pass to the Gulf of
Mexico. (See U. S. Coast and Geodetic Survey Chart No. 592; U. S.
Geological Survey maps, Moss Lake, Black Lake, Cameron Farms,
and Phoenix Lake quadrangles; and Corps of Engineers, Mississippi
River Commission navigation maps of Intracoastal Waterway and
Atchafalaya River System.
   Existing project.-This provides for the maintenance of a channel
30 feet deep, with a bottom width of 125 feet, from Calcasieu River to
the Sabine River. Under ordinary conditions, the mean range of
tide is 2 to 3 inches; variations of 1 to 2 feet may be experienced due
to high water on the Sabine or Calcasieu River.
676           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                 1944

  The estimated cost of the work, made in 1931, is $50,000 for the first
initial maintenance and $30,000 annually thereafter.
   The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                Documents

Aug. 30, 19351    Maintenance of channel 30 feet by 125 feet from   H. Doc. No. 172, 72d Cong., 1st sess.
                    Lake Charles, La., to Sabine River.
Aug. 26,1937      Section of Calcasieu River from Intracoastal      H. Doc. No. 299, 75th Cong., 1st sess.
                    Waterway to Lake Charles dropped from exist-     (modifying project for Calcasieu
                    ing project.                                     River and Pass).

  I   Included in the P. W. A. program, Jan. 3, 1934.

   Local cooperation.-Fullycomplied with. Under a permit granted
January 5,1922, the police jury of Calcasieu Parish expended $2,630,350
in enlarging the Calcasieu-Sabine River section of the Intracoastal
Waterway to a depth of 30 feet over a bottom width of 125 feet.
   Terminal facilities.-(Seeproject for Calcasieu River and Pass.)
   Operations and results during fiscal year.-Engineering studies
were made at a cost of $130.59 for maintenance. The expenditures
were $125.94.
   Condition at end of fiscal year.-The channel was in good condition
throughout its entire length. Controlling depth on June 30, 1944,
was 30 feet in the center of the channel. Depths are somewhat less
on the edges of the channel, due to the lowering of the side slopes,
but the shoaling is not sufficient to interfere seriously with navigation.
The channel is navigable throughout. The total costs at the end of
the fiscal year were $239,128.71 and total expenditures were $239,124.06,
all for maintenance. Included in both total costs and expenditures
are Public Works funds in the amount of $79,577.63.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $71,499.30, plus an allotment of $35,000 made during July
1944, will be applied as follows:
Accounts payable June 30, 1944_ ---------               ---------.--------       $4. 65
Maintenance:
    Contract:
         Dredging to restore project dimensions in the channel from
           Calcasieu River to Sabine River as required during the
           fiscal year July 1, 1944, to June 30, 1945------------- 100, 000. 00
    Hired labor:
        Surveys and examinations during fiscal year, Julys 1, 1944,
           to June 30, 1945--_                ____-------------              6, 494. 65
              Total maintenance_     -----------------                     106, 499. 30
   The additional sum of $2,500 can be profitably expended during
the fiscal year 1946 for examination and survey of the channel.
                                     Cost and financial summary
Cost of new work to June 30, 1944_...................
Cost of maintenance to June 30, 1944-----------              ------ $239, 128. 71
         Total cost of permanent work to June 30, 1944         _        ---
                                                                      239, 128. 71
Minus accounts payable June 30, 1944--------------------------               4. 65
         Net total expenditures --                     -         -     239, 124. 06
Unexpended balance June 30, 1944_                                      71, 499. 30
       - Total amount appropriated to June 30, 1944_     -----         310, 623. 36
               RIVERS AND HARBORS-NEW                                   ORLEANS, LA., DISTRICT                  677


      Fiscal year ending June 30                1940             1941              1942         1943         1944

Cost of new work .  .....------------     - --
                                         I.                      .---
                                                                  --     -   ---
Cost of maintenance ..........                $89,085.28    ------       ----------------       $374.76        $130.59
Total expended_ .-...-----              -89,474.       10               .----------------------------
                                                                                                 374.76         125. 94




                                            _----.
Outstanding liabilities June 30, 1944------------                                   --___50.                        00

     Balance available June 30, 1944--- ----                                       __71,                     449. 30
Amount allotted in July 1944_               _----35,
                                   ------------                                                              000. 00

            Amount available during fiscal year 1945-----------------106,                                    449. 30

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance1______________         ___________                                              2, 500. 00
  I   Exclusive of available funds.

                21. REMOVING THE WATER HYACINTH                                            (LOUISIANA)

  Location.-Lakes and streams tributary to the Gulf coast.
   Existing project. This project provides for the extermination or
removal of plants from the navigable waters of the States of Florida,
Alabama, Mississippi, Louisiana, and Texas, so far as they are or may
become an obstruction to navigation, by any mechanical, chemical, or-
other means whatsoever; for the construction and operation of boats
equipped with suitable machinery for such removal; and for the con-
struction and operation of booms to prevent the drifting of plants from
one stream to another. The latest (1942) approved estimate for annual
cost of maintenance is $200,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                             Work authorized                                        Documents


Mar. 3,1899    Made appropriations for the States of Florida and H. Doc. No. 91, 55th Cong., 3d sess.
                 Louisiana and provided for the extermination
                 or removal of plants, the building of boats, and
                 the establishment of booms.
June 13,1902 Authorized the use of mechanical, chemical, or
                 other means whatsoever.
Mar. 3, 1905 Made the appropriation available forthe State
                 of Texas.
               In making appropriations for Florida, provided
           Dthat       no chemical process injurious to cattle
    Mar.
      2,1907     shall be used.
July 25,1912 Made the appropriation available for the State
                 of Mississippi and also made available for use
                 in that State the operating plant pertaining to
                 the work in Louisiana.
July 27, 1916 Made the appropriation available for the State
                 of Alabama.
678   REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944
  Terminal facilities.-The terminal facilities of the various streams
from which hyacinths were removed are described in the reports for
the improvement of these streams.
   Operations and results during fiscal year.-The mechanical hy-
acinth destruction plant Kenny destroyed a total of 3,123,201 square
yards of hycinths and alligator grass in Bayous Black, Big Bull,
Boeuf, Chevreuil, Copassaw, Cross, Grand, Lacassine, Lafourche, Oak,
Penchant, Point, and Possum and Upper Grand River and the Intra-
coastal Waterway. A total of 10,247,259 square yards of hyacinths
and alligator grass was removed by conveyors from Bayous Black,
Chevreuil, Copassaw, Folse, Grand Caillou, Lacombe, l'Eau Bleu,
Lafourche, Penchant, Segnette and Terrebonne and the Intracoastal
Waterway and its feeder areas. No hand removal work was under-
taken.
   At the start of the fiscal year only one medium conveyor was in
operation due to the necessity of conserving limited funds. When
it became apparent that the work could not be maintained in a satis-
factory manner on this basis, the mechanical destruction plant Kenny
and a second medium conveyor were put into operation. The third
medium conveyor was placed in operation in May. Additional funds
were secured to finance operation of all available plants. Continu-
ous efforts were.made throughout the year to devise new methods
of handling the work to increase the efficiency of existing plant and
reduce manpower requirements. Full advantage was taken of all
mechanical equipment and whenever possible the number of men re-
quired to operate a plant was reduced as machines were developed
to handle that phase of the work formerly done by hand. Difficulties
in securing replacement parts resulted in some delays in the over-all
schedule of operations.
   An inspection of booms and barricades along the Intracoastal Wa-
terway showed that several had been damaged and some destroyed
by collision of barges and through dredging operations. No effort
was made to replace the damaged structures at this time because of
lack of sufficient funds for this work.
   The total costs were $119,898.49 and the total expenditures were
$118,976.54, all for maintenance.
   Condition at end of fiscal year.-From 1900 to 1902 a boat with
suitable machinery for removing and crushing the hyacinth was op-
erated. From that time until 1936 the hyacinths were controlled
by spraying with a solution of arsenic and soda, hand removal, and
booms. The use of arsenic and soda has been abandoned and removal
by hand reduced to a minimum. Present methods of control are
by means of a crushing plant, power-operated conveyors, and booms.
Excellent results are being obtained.
   The total costs to June 30, 1944, were $1,773,877.24, and the total
expenditures were $1,775,252.57, all for maintenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $43,198.96, plus an allotment of $150,000 made in July
1944, or a total of $193,198.96, will be applied as follows:
                 RIVERS AND HARBORS-NEW ORLEANS, LA., DISTRICT                                                                    679
Accounts payable June 30, 1944-------                      -    - $384. 70
Maintenance work with hired labor and Government plant, July 1,
  1944, to June 30, 1945:
    Exclusion by structures-----------------_   -----    ____      4, 900.00
    Mechanical destruction---- --.                    --  ___     77,000.00
    Removalby conveyors ------------------------------           106, 900.00
    Experimental work                                                 000.00
                                                                   3,----------------------------
    Investigations, surveys_                                 -     1, 014. 26
            Totalmaintenance_____                                                                                         193,198. 96
  The additional sum of $218,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance work with hired labor and Government plant, July 1,
1945, to June 30, 1946:
    Exclusion by structures_-----------                        ----       $15, 000
    Mechanical destruction_            -  --         ---------             90, 000
    Removal by conveyors----             -------------                    106, 000
    Experimental work_-------------                                 -----   5,000
    Investigations, surveys_------------                          ----      2,000

            Total             -----------------------------------------------                                                218,000
                                                Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                                         ---             $1,773,877.24
       Total cost of permanent work to June 30, 1944 _----                                                          1, 773, 877. 24
Plus accounts receivable June 30, 1944---    ---------                                                                   1, 760. 03
      Gross total costs to June 30, 1944                           --------------------                             1, 775, 637. 27
Minus accounts payable June 30, 1944---                                          ----------                                 384. 70
      Net total expenditures_---------                                                        ---                   1, 775, 252. 57
Unexpended balance June 30, 1944_--                                       ----------                                    41,438.93
            Total amount appropriated to June 30, 1944                                 ------------                 1, 816, 691. 50

     Fiscal year ending June 30                    1940            1941                1942                  1943              1944


Cost of new work ..-----------
                     .--..-- ----
Cost of maintenance---                          $119, 339.14    $177,845. 91      $155, 002. 76           $115, 530. 36      $119, 898.49

Total expended           ....----------------    113, 080. 55     85, 604. 14      153, 683. 93            122, 711. 15       118, 976. 54

Allotted -.-.--------------..---                 231, 000.00     162, 529. 30      100, 360. 00             63,000.00         80, 000.00


Balance unexpended July 1, 1943----------------------------                                                               $80,415.47
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943- ----         ------------                                                                         80,000. 00
      Amount to be accounted for_--------              ---                                                                160, 415. 47
Gross amount expended -----------------------------------                                                                 118, 976. 54
      Balance unexpended June 30, 1944---------------------                                                                41, 438. 93
Outstanding liabilities June 30, 1944---  -----------                                                                          475. 00
      Balance available June 30, 1944_ -------------         -40,    963. 93
Accounts receivable June 30, 1944---------------------------      1, 760. 03
            Unobligated balance available June 30, 1944------------_                                                       42, 723. 96
680            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                               1944

Amount allotted in July 1944_- ----                                __----------$150,                                                        000. 00

            Amount available during fiscal year 1945                            ---------------                                  192, 723. 96

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1 ___   -     -                                                                            -__   218, 000. 00
  1Exclusive of available funds.

    22. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                                                                   (GENERAL)

  The cost of work during the fiscal year amounted to $60,478.51; the
expenditures were $60,344.74. The balance unexpended June 30, 1944,
$19,793.97, plus an allotment of $75,000 made during July 1944, will
be applied as needed during the fiscal year 1945 in payment of expenses
incurred under this heading.
  The additional sum of $75,000 can be profitably expended during
the fiscal year 1946.
                                                  Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_-                                  --------                                       $1, 480, 911. 64
      Total cost of permanent work to June 30, 1944----------1, 480, 911. 64
Minus accounts payable June 30, 1944_----         ------          1, 580.44
      Net total expenditures ------------------------------  1, 479, 331. 20
Unexpended balance June 30, 1944 ---------------------------     19, 793. 97
             Total amount appropriated to June 30, 1944------------                                                        1, 499, 125. 17


     Fiscal year ending June 30                     1940            1941               1942                     1943                        1944

Cost of new work--.-              ----             --      . - . -- .          .
                                                                        - . --..       .       .     .      .          .         .      .          .
Cost of maintenance-...            ....    _ _.   $82, 818.82    $127, 911.00       $137,150.41          -$65,997.00                   $60, 478. 51

Total expended--------------................--.    73, 661.92     134, 850.99        134,029.60             69, 870. 25                     60,344. 74
Allotted-----..            ....           .._,-92,000.00           97, 500.00         52,059.23            140, 000.00 _


Balance unexpended July 1, 1943__--                                     ---------                                                $80, 138. 71
Gross amount expended_------------                                                                 ----                           60, 344. 74

      Balance unexpended June 30, 1944---------------------                                                                          19, 793. 97
Outstanding liabilities June 30, 1944-------------------------                                                                        5, 124. 75
      Balance available June 30, 1944 -----------------------                                                                        14, 669. 22
Arhount allotted in July 1944_---  -    -----------                                                                                  75, 000. 00

             Amount available during fiscal year 1945--                                    -----                                     89, 669. 22

Amount that can be profitably expended in fiscal year ending -
                                                               June
                                                                  -                                                    -
                            1
                                    _________-   -  -   -
30, 1946, for maintenance      _                                                                                                    75, 000. 00
   1Exclusive available funds.
                 RIVERS AND HARBORS-NEW                                        ORLEANS, LA., DISTRICT                                   681
23. OTHER                 NAVIGATION                  PROJECTS FOR WHICH                                     NO ESTIMATES
                                                     ARE SUBMITTED

                                                                           For last       Cost and expenditures to      Estimated
                                                                         full report            June 30, 1944            amount
                          Name of project                                see Annu-                                     required to
                                                                             Report
                                                                         al for-          New work          Maintenance complete

1.   Bayou Pierre, Miss.1 s__ _                ___                 -______ 1888               $5,000.00- ....                     -(3)(.)---
2.   Bayou Lacombe, La-.....---.--.-----...----. 1942                                           4,715.91         $793.70             (4)
3.   Tangipahoa River, La---------....                                      -   1942          11,500.00        11,082.20             (t)
4.   Pass Manchac, La --------------------------- 1942                                          1,374.10        9,838.68             (4)
5.   Tickfaw, Natalbany, Ponchatoula, and Blood
        Rivers, La_ _ -------------------------------1942                                       8,115. 49       25,044.86             (4)
6.   Amite River and Bayou Manchac, La-----------............                   1942          28,233.68        62, 734.09            (4)
7.   Big Pigeon and Little Pigeon Bayous, La. ___                           -   1936 -37,                          669. 20           (3)
8.   Bayou Terrebonne, La ----------------------- 1942                                       120, 088.71      142, 474.02            (4)
9.   L itt le C aillou B ay ou , L a . . -... . . . . . . . . . . . . . . . . . 1942          77, 761.0 4      26, 634 . 79          (4)
10.   Bayou Vermilion, La. ------------------------ 1942                                       34, 900.00      200,168.83             (4)
11.   Waterway from White Lake to Pecan Island, La.._                            1942          10, 903.83           108.17           4$9,000
12.   Bayou Queue de Tortue, La.' ------------------ 1924                                      33, 355.18        4,276.10            (3)
13.   Bayou Plaquemine Brule, La ------------------ 1942                                       32, 759. 90      28, 864.70           (4)
14.   Vinton Waterway, La_ ..-...                 ----.----                      1937-----------------......-                        0 14, 000

  I Channels adequate for commerce.
  2   No commerce reported.
  3 Completed.
  4 No contruction work undertaken during fiscal year 1944, or proposed for fiscal years 1945 or 1946. Chan-
nels adequate for existing commerce.
  5 See also flood-control project for Vermilion River, La.
  6 Due to decline of traffic, local interests are no longer sufficiently interested to provide rights-of-way and
dumping privileges.

                 24. PLANT ALLOTMENT, NEW ORLEANS DISTRICT
                                                 Cost and financial summary

Undistributed costs June 30, 1944_------------------------                                                             $1, 095, 950. 65
Minus accounts payable June 30, 1944-       -- --------                                                                    206, 816. 02

     Net total expenditures_  _-  - -----------                                                                           889, 134. 63
Unexpended balance June 30, 1944_ --         ---                                               --         ---             484, 962. 13

            Total amount appropriated to June 30, 1944------------1,                                                      374, 096. 76


      Fiscal year ending June 30                    1940                1941               1942                 1943               1944

Total expended ..................                $25, 323. 54       $382, 347.42        $19, 121.00 1-$193, 451.11             -- $211,980.09
Allotted-....-..--.-...                      j     31, 299. 48   j-32,600.00          -301, 194. 47                             -80, 000. 00


Balance unexpended July 1, 1943_ ---      --   --
                                             ______           -__ $352, 982. 04
Deductions on account of revocation of allotment8-------------       0, 000. 00

      Net amount to be accounted for-----------------------272,                                                                    982. 04
Gross amount expended --------------..        ---          $790, 275. 15
Less:
        Reimbursements collected....                             $983, 945. 15
        Receipts from sales-                           -             18, 310. 09
                                                                                          1, 002, 255. 24
                                                                                                                        -- 211, 980. 09

      Balance unexpended June 30, 1944.....---------------------                                                          484, 962. 13
Outstanding liabilities June 30, 1944---_ _-_-.----52,      195. 92
Amount covered by uncompleted contracts....            155, 000. 00
                                                                                                                          207, 195. 92
            Balance available June 30, 1944_----                                          -__
                                                                                          ___         ___ -_              277, 766. 21
682        REPORT OF CHIEF OF ENGINEERS,                           U.          S. ARMY,             1944

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                              SDate trans-                     Document     Recom-
              Locality                  Authorization act       mitted to                         No.      mendation
                                                                Congress

Atchafalaya River and Atchafalaya        Rivers and Harbors
Bay Ship Channel, La.                     Committee reso-
                                           lution, Apr. 4,
                                           1938.
Boeuf, Rapides, Cocodrie and Courta- Commerce            Com-
bleau Bayous, La., for navigation,        mittee resolution,
flood control, and irrigation.            Feb. 8, 1939.
Calcasieu River, La., for navigation, Commerce           Com- ...............
flood control, and irrigation.            mittee resolution,
                                           Feb. 8,1939; Flood
                                           Control Commit-
                                           tee     resolution,
                                           Jan. 26,       1939;
                                           Rivers and Har-
                                           bors Committee
                                           resolution,     Jan.
                                           24, 1939.
Courtableau Bayou, La., for naviga- Rivers and Harbors ...........---
  tion, flood control, and irrigation.     Committee reso-
                                           lution, Jan. 24,
                                           1939.
     Do---------_.._.           .     .  Flood Control Com- ...............
                                           mittee resolution,
                                           Jan. 26, 1939.
Grand Caillou and Le Carpe Bayous, Rivers and Harbors ---- - - - - -
  La.                                      Committee reso-
                                           lution, Apr. 4, .....         d........-
                                           1938.
Lake Charles Deep Water Channel, Commerce                 Com- ---............
  Ship Channel, and Calcasieu River        mittee resolution,
  and Pass, La.                            Apr. 17, 1944.
Mermentau River, La., and its tribu- Commerce             Com-----     -   -   -    -      -

  taries, for navigation and drainage.     mittee resolution,
                                           Mar. 5, 1943.
Mississippi River at and below New Commerce               Com-
  Orleans, La., decrease in salinity.'     mittee resolution,
        1                                  Apr. 25, 1940.
     Do. .---._ .....                    Rivers and Harbors
                                           Committee reso-
                                           lution, Apr. 25,
                                           1940.
Mississippi River at or near New Commerce                 Com- Apr. 22, 1944 S. 188, 78th Favorable.
                                                              Apr.         22,     1944

  Orleans, La., to Corpus Christi,         mittee resolution,                             Cong., 2d
  Tex., Intracoastal Waterway, alter-      Feb. 12, 1944.                                 sess.
  nate connection with Mississippi                                                  ..............
  River in the vicinity of Algiers, La.
Mississippi River between Cairo, Ill., Flood Control com- Mar. 20, 1944 H. 509, 78th
                                                              Mar.         20,     1944             Do.
  and Baton Rouge, La., for 12-foot        mittee resolution,                             Cong., 2d
  channel (for navigation and flood        Mar. 8, 1943.                                  sess.
  control) .1                                                                        ----- do .....
     D o.'    ._._._
          _._._       ._.    _.........
                                     . . Commerce         Com- ----.   do-         -.---            Do.
                                           mittee resolution,
                                           Mar. 9, 1943.
Mississippi River, emergency outlet Commerce              Com-
  to Gulf of Mexico, 40-foot ship          mittee resolution,
  channel from the Industrial Canal,       Apr. 19, 1943.
  New Orleans, La., eastward to the
  Rigolets and thence to Chandeleur
  Islands.
     Do--------
         ..................... .         Rivers and Harbors
                                           Committee reso-
                                         lution   May    5,
                                         1943.
Mobile, Ala., to New Orleans, La.,      Commerce      Com-
Intracoastal Waterway, with re-         mittee resolution,
spect to improvement of the Violet      Aug. 16, 1944.
  Canal route.
Morgan City to Plaquemine, La.,         Commerce       Com-
section of the Louisiana-Texas          mittee resolution,
  Intracoastal Waterway.                  May 18, 1943.                    H. 594, 78th
Petit Anse, Tigre, and Carlin Bayous,   Commerce       Com- May 11, 1944     Cong., 2d     Do.
  La., additional improvements for       mittee resolution,
navigation and drainage.                Mar. 5, 1943.                       sess.
Petit Anse, Carlin, and Tigre Bayous,   Rivers and Harbors .....do ....... .       .....   Do.   5..do
  La., 9-foot channel- from Gulf of       Committee reso-
  Mexico to Erath and Jefferson Is-      lution May 4,
land.                                    1939.
Petit Anse, Carlin, and Tigre Bayous,   Commerce       Com- ..             ....do- ....    Do.
                                                                              d...do........
  La.                                    mittee resolution,
                                          Aug. 30, 1940.
  1 Field report being prepared by the Mississippi River Commission.
                FLOOD CONTROL-NEW                  ORLEANS,        LA.,     DISTRICT               683
Status of all investigations for navigation called for by river and harbor acts and
                          committee resolutions-Continued

                                                             Date trans-     Document        Recom-
               Locality                 Authorization act     mitted to        No.          mendation
                                                              Congress

Queue de Tortue Bayou, La., for navi-   Commerce     Com-----------..-..--.........-
gation and drainage.                    mittee resolution,
                                          Dec. 19, 1940.
Tigre Bayou to the town of Erath, La    Rivers and Harbors   May 11, 1944    H. 594, 78th   Favorable.
                                          Committee reso-                      Cong., 2d
                                         lution, Apr. 4,                       sess.
                                          1938.



                             25. HOMOCHITTO RIVER, MISS.

    Location.-The project is located along the Homochitto River in
Adams and Wilkinson Counties, Miss. (See Corps of Engineers,
Mississippi River Commission Alluvial Valley maps, Artonish, Wood-
ville, and Kingston quadrangles.)
    Existing project.-The plan of improvement provides for the con-
struction of a number of cut-offs, aggregating approximately 5.8
miles in length, which will reduce the length of the river from Rosetta,
Miss., to its mouth from 37.7 to 30.6 miles; construction of small earth
dams at points where the new cut-offs leave and reenter the existing
channel; clearing and snagging operations along both banks from
mile 1 to mile 35; and blasting along sides and bottom of the channel
where its development is retarded by stumps or hard nonerodible clay
strata.
    The project will result in clearing the river bed and banks of ob-
structions, shortening the channel and producing a more uniform
slope, thereby resulting in faster run-off of floodwaters in the basin,
minimizing the damages to crops and highways and making practi-
cable more general use of farm and timber lands which have been
hitherto subject to frequent extended inundation.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936, and modified by the Flood Control Acts
approved June 28, 1938, and August 18, 1941. The estimated cost of
new work, revised in 1941, is $200,000. The.latest (1943) approved
estimate for annual Federal cost of maintenance is $15,000.
   Local cooperation.-See page 7 for requirements.
   Operations and results during fiscal year.-New work.--Acquisition
of rights-of-way was continued and is now practically complete; costs
for the fiscal year were $74.47.
   Maintenance.-Clearing,snagging, and blasting of the channel and
banks were performed by hired labor at a cost of $8,250.28. Engineer-
ing studies and surveys were made at a cost of $146.59.
   The total costs for the fiscal year were $8,471.34, of which $74.47
was for new work and $8,396.87 was for maintenance. The total ex-
penditures were $6,537.51.
   Condition at end of fiscal year.-The construction of cut-offs be-
tween mile 4 and mile 35 above the mouth of the channel has been
completed. In addition 28.5 miles of clearing and snagging have
been completed between mile 2 and mile 35. The project is approxi-
mately 84 percent complete. Additional channel improvements and
the completion of acquisition of rights-of-way are needed to complete
684          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                        1944

the project. Maintenance, consisting of clearing, snagging, and blast-
ing, has been performed by hired labor between mile 3 and mile 32.
    The total costs to June 30, 1944, have been $191,321.18, of which
 $131 214.31 for new work and $41,396.87 for maintenance were from
regular funds and $18,710 for new work from Emergency Relief funds.
Total expenditures to June 30, 1944, have been $189,380.85, of which
 $170,670.85 was from regular funds and $18,710 from Emergency
Relief funds.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, $8,632.46, including accounts receivable, plus an allotment
of $21,000, made during July 1944, will be applied as follows:
SAccounts payable June 30, 1944 -------------------------------          $1, 953. 64
New work:
     Completion of acqiuisition of rights-of-way                                  --------------------
                                                                              75. 69
     Advance planning      --------------------------------------         6, 000. 00
Maintenance:
     By hired labor:
          Clearing the channel and removing snags and drift jams,
            July 1, 1944, to June 30, 1945 __-...    _____.----20,           603. 13
         Surveys and mapping_---------_           __ _.--        .------  1, 000. 00

                  Total          ------------------------------------------                                          29, 632. 46

    The additional sum of $15,000 can be profitably expended during the
fiscal year 1946 on maintenance of the waterway.
                                              Cost and financial summary
Cost of new work to June 30, 1944_ _______________________                                                   1$149, 924. 31
Cost of maintenance to June 30, 1944_    __----_  ____--__-- -                                                      41, 396. 87
        Total cost of permanent work to June 30, 1944                                     -----------           1191, 321. 18
Plus accounts receivable June 30, 1944.-------------------------                                                            13. 31
       Gross total costs to June 30, 1944-----------------------191,    334. 49
Minus accounts payable June 30, 1944-------------------------       1, 953. 64

       Net total expenditures__--..-                -------.-                                        __
                                                                                                   ___         1189, 380. 85
Unexpended balance June 30, 1944_----------------------                                                              8, 619. 15
            Total amount appropriated to June 30, 1944--------------                                                198, 000. 00


    Fiscal year ending June 30                    1940                 1941            1942            1943              1944

Cost of new work---       ------------          $65, 821.61        $32, 504.37          $88.76       $1, 435.10               $74.47
Cost of maintenance..-.....................                  .       13,817.63        4,182.37       15,000.00              8,396.87

      Total cost--.--------------                65, 821.61           46, 322.00       4, 271.13      16, 435.10             8,471.34
      Total expended-...----------........       58, 530.11           52, 977.94       4,889. 55      16, 445. 74            6, 537. 51
Allotted                                            ......--------------18,000. 00
                             ...........-------------------                           15, 000.00      15,000. 00         .


Balance unexpended July 1, 1943----------------------------                                                        $15, 156. 66
Gross amount expended -------------------------------------                                                          6, 537. 51
       Balance unexpended June 30, 1944----------------------                                                         8, 619. 15
Outstanding liabilities June 30, 1944_------------------------1,                                                        953. 64
            Balance available June 30, 1944----------..                                                   .           6, 665. 51
  &Includes $18,710 Emergency Relief funds.
                  FLOOD CONTROL-NEW ORLEANS,                                   LA., DISTRICT                    685
Accounts receivable June 30, 1944----------------------------                                                $13. 31

     Unobligated balance available June 30, 1944                            --------------                 6, 678. 82
Amount allotted in July 1944_
                            --------------------------------                                              21, 000. 00

Amount available during fiscal year 1945                     ---------------------                        27, 678. 82

Amount (estimated)     required to be appropriated for completion of
                  2- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
existing project                                                                                         50, 000. 00
Amount that can be profitably expended                   in fiscal year ending June
                                   2- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -   -
30, 1946, for maintenance                                                                                15, 000. 00
s Exclusive of available funds.

                                    26. BAYOU DES GLAISES, LA.

   Location.-The diversion channel commences at Bayou des Glaises,
near Moreauville, La., and runs in a southeasterly direction for a dis-
tance of approximately 6.1 miles, connecting with the landslide borrow
pits of the West Atchafalaya Basin protection levee at a point approx-
imately 31/4 miles south of Hamburg, La., all in Avoyelles Parish.
 (See Corps of Engineers, Mississippi River Commission Alluvial
Valley maps, Voorhies and Odenburg quadrangles.)
   Emisting project.-The plan of improvement provides for a diver-
sion channel between Bayou des Glaises, at Moreauville, and the bor-
row pit of the West Atchafalaya Basin protection levee, a distance
of approximately 6.1 miles. Bottom width for the first 2 miles is 60
feet and for the balance of the channel 100 feet, with an average
depth of 18 feet. The project also provides for the construction across
the channel of one timber, steel, and concrete highway trestle; one
timber road trestle; and one creosoted timber railroad trestle, and
the readjustment of utilities. This project will result in reduced flood
damages and will improve sanitary and living conditions by providing
needed drainage for an area of approximately 541 square miles. The
channel will relieve backwater conditions in Bayou des Glaises re-
sultant from closure of the Bordelonville floodgate during floods.
The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936. The estimated cost of new work, revised in
1940, is $147,200 for construction and $50,000 for lands and damages.
The project is adjacent to the Mississippi River Commission levee
system, Mansura to Hamburg, and the West Atchafalaya protection
levee; for further details see annual report, Mississippi River Com-
mission, for 1940.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The diversion channel is complete.
The length is 6.09 miles. Total costs to June 30, 1944, have been $183,-
760.87, all for new work, of which $162,923 was from regular funds and
$20,837.87 from Emergency Relief funds. The expenditures have been
$180,576.42, of which $159,738.55 vWas from regular funds and $20,837.87
from Emergency Relief funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $16,661.45, will be applied to payment for rights-of-way as
new work.
   No additional funds can be profitably expended during the fiscal
year 1946, as the project will be completed with the available funds.
686         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

                                       Cost and financial summary
Cost of new work to June 30, 1944__                                                                           $183, 760. 87
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944                                  -----------               183, 760. 87
Minus accounts payable June 30, 1944_--------                                                       ---          3, 184. 45
      Net total expenditures ------------------------------                                                    180, 576. 42
Unexpended balance June 30, 1944---------------------------                                                     16, 661. 45
         Total amount appropriated to June 30, 1944-------------                                               197, 237. 87


   Fiscal year ending June 30             1940            1941                   1942                1943                   1944

Cost of m aintenance....   - - - -   -- - - - - -     -- - - - - -      - - - - - - -         -- - - - -       . .          . ..

Total expended.----------------          32, 690.31         724.12                    32 29           305.22     ........
Allotted----......--------------------.....-----             ------------............-..            .......     ..............


Balance unexpended July 1, 1943__--                      ---------                                             $16, 661.45
Balance unexpended June 30, 1944_------,----__                                                                 . 16, 661. 45
Outstanding liabilities June 30, 1944_--------                                                ---                16, 643. 13
        Balance available June 30, 1944_--                                 ---------                                          18. 32
I Includes $20,837.87 Emergency Relief funds.

                  27. BAYOU TECHE AND VERMILION RIVER, LA.

  Location.-Bayou Teche has its source in Bayou Courtableau, in St.
Landry Parish, and flows in a southeasterly direction a distance of 125
miles to its conflitence with the lower Atchafalaya River, about 101/2
miles above Morgan City, La. Vermilion River, also called Bayou
Vermilion, is formed by the junction of Bayous Fusilier and Bour-
beau, west of Arnaudville, La., and flows in a southwesterly direction
to the western end of Vermilion Bay, a distance of 72 miles. Bayou
Teche is connected with the Vermilion River by Bayou Fusilier at
Arnaudville; and by Ruth Canal, an artificial, privately owned, non-
navigable waterway, constructed for diversion of water from Bayou
Teche to Vermilion River for rice irrigation. (See U. S. Coast and
MississippiSurvey
Geodetic             Charts Nos. 1116 and 1277; Corps of Engineers,
             River Commission Alluvial Valley maps, and U. S. Geo-
logical Survey maps.)
  Existing project.-This provides for increasing the pool elevation
in Bayou Teche above Keystone lock by 3 feet, by means of the
installation of movable crest gates on Keystone Dam; the excavation
of a channel with a bottom width of 35 feet at elevations varying
from -2 feet to -3 feet from the head of Bayou Teche at Bayou
Courtableau to a point approximately 11 miles downstream; the exca-
vation of a navigable channel 8 feet deep and 80 feet wide from the
8-foot contour in Vermilion Bay to the Intracoastal Waterway at its
junction with the Vermilion River; the excavation of a channel in
the Vermilion River, 9 feet deep by 100 feet wide, from the Intra-
coastal Waterway to Lafayette, La. (Pinhook Bridge); and the exca-
vation of a nonnavigable channel from Lafayette to the junction of
Bayous Bourbeau and Fusilier of adequate capacity to carry flood
          FLOOD CONTROL--NEW        ORLEANS,   LA.,   DISTRICT       687
flows of the upper Vermilion Basin. The plane of reference is mean
low Gulf level. See also individual report of navigation project for
Bayou Teche, La.
    The estimated Federal cost of new work, revised in 1944, is $2,185,-
000. The estimated local cost of new work is $94,000.
    The latest approved estimate of Federal cost of annual maintenance
is $4,000, in addition to the maintenance cost authorized for the works
constructed under authorizations for the improvement of rivers and
harbors.
    The existing project was authorized by the Flood Control Act of
August 18, 1941. (See S. Doc. No. 93, 77th Cong., 1st sess., which
also contains the latest published map.)
    Local cooperation.--See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to give assurances satisfactory to the Secretary
of War that they can and will prosecute all work required for con-
struction, operation, and maintenance of improvements in Ruth Canal;
that they will maintain and operate all bridges, pipe-line crossings,
and other utilities included in or affected by the improvements; and
that they will operate the control structure in Ruth Canal in accord-
ance with regulations prescribed by the Secretary of War.
    Assurances that conditions of local cooperation specified above
will be fully complied with have been given by losal interests and have
been accepted by the Secretary of War as satisfactory. Local inter-
ests are actively engaged in fulfilling provisions of these assurances.
    Operations and results during fiscal year.-New work by       dontract
consisted of removal of 956,526 cubic yards of material in dredging
the 8- by 80-foot new channel from approximate 7-foot contour in
Vermilion Bay to Gulf Intracoastal Waterway at a cost of $104,-
  117.31. New work by United States plant and hired labor was per-
  formed as follows: Preliminary surveys and mapping for 8- by 80-foot
navigation channel from Vermilion Bay to Vermilion River at Gulf
Intracoastal Waterway; and excavation of 283,846 cubic yards from
Vermilion River, La., to provide a navigation channel of 9 by 100 feet
  from mile 11 to mile 19, above the mouth of the river, at a cost of
 $128,354.72.
    The total costs for the year were $232,472.03, all for new work.
  Total expenditures were $198,788.62.
     Condition at end of fiscal year.-The 8- by 80-foot new .channel
  from approximate 7-foot contour in Vermilion Bay to Intracoastal
  Waterway was completed by contract in 1944. Dredging' to provide
  a 9- by 100-foot channel in Vermilion River between mile 11 and mile
  28.4, above the mouth of the river, was in progress by United States
  plant and hired labor forces. The project is about 14 percent com-
  plete. Work remaining consists of additional dredging in Vermilion
  River to provide a 9- by 100-foot channel from Gulf Intracoastal
  Waterway to Lafayette, La.; dredging a nonnavigable channel in Ver-
  milion River from Lafayette, La., to the junction of Bayous Bourbeau
  and Fusilier; dredging in Bayou Teche to provide a nonnavigable
  channel of 30 feet bottom width from Bayou Courtableau to a point
  approximately 13 miles downstream thereof; and constructing mov-
  able crest gates on Keystone Dam to raise the pool level in Bayou
  Teche above that point.
688       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                              1944

   The controlling depths at mean low Gulf on June 30, 1944, were
as- follows: Entrance to new channel from Vermilion Bay to Gulf
Intracoastal Waterway, 6 feet; through the new channel, 8 feet;
Vermilion River from Gulf Intracoastal Waterway to Abbeville,
La., 9 feet; Abbeville, La., to Lafayette, La. (Pinhook Bridge), the
head of navigation, 4 feet.
   The total costs under the existing project to the end of the fiscal
year have been $233,658.13, all for new work. The total expenditures
have been $199,053.46.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $1,217,946.54, will be applied as follows:
Accounts payable_____       ..--- ---------------------------                      $34, 604. 67
New work:
    By contract:
        Dredging from Abbeville, La., to Lafayette, La., from
          July 1, 1944, to June 30, 1945_ _-_               _____-----1, 180, 841. 87
    By hired labor:
        Construction of movable crest on Keystone Dam
           (flashboards) -------------------------------------                          2, 500. 00

             Total new work ----------------------------- 1, 217, 946. 54
  The additional sum of $768,000 can be profitably expended during
this fiscal year to complete the project, as follows:
New work:-
   Vermilion River:
       By contract:
           . Dredging from Lafayette, La., to Ruth Cana, September
               to November 1944__--                   ----------                $310, 900
             Dredging from Ruth Canal to mile 67.5, December 1944
               to January 1945_-_                           ----------           114, 000
             Clearing and snagging from mile 67.5 to the earthfill in
               Bayou Fuselier during February 1945                                  6, 000
             Construction of earthfill in Bayou Fuselier during March
               1945_-------------------------------------------                    2, 500
             Bridge modifications, February to March 1945              .----------36, 000
   Bayou Teche:
       By contract:
             Dredging from Port Barre to below Arnaudville, La., May
               to June 1945_ ----------------------------------                  280, 000
             Clearing during June 1945_- -                  -----           __
                                                                           ----    6, 600
             Bridge modifications, Upper Bayou Teche, during June
               1945 ------------------------------------------                    12,000

                                                                                         768, 000
  The additional sum of $4,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging and miscellaneous re-
pairs.
                             Cost and financial summary
Cost of new work to June 30, 1944_           _________--------$233,                       658. 13
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-----------                     233, 658. 13
Minus accounts payable June 30, 1944---    ---------                                34, 604. 67

                             -
      Net total expenditures_--      -------------                                  199, 053. 46
Unexpended balance June 30, 1944_-------                              ---        1, 217, 946. 54

       Total amount appropriated to June 30, 1944-                               1, 417, 000. 00
                 FLOOD CONTROL--NEW                     ORLEANS,           LA., DISTRICT                     689

   Fiscal year ending June 30           1940            1941             1942             1943            1944

                 .......-
Cost of new work---------          ---------------------------- $1,186.10                               $232,472.03
Cost of maintenance....-----------------------------------   ----------------------
Total expended------------------..................-----------------------                   264.84       198,788. 62
Allotted ..                                    .   ..         ..                           27,000.00
                                                         "-------------.---------------------------.   1,390,000. 00



Balance unexpended July 1, 1943_          _---------------     $26, 735. 16
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942___------------   _------------     1, 390, 000. 00

      Amount to be accounted for_ _             .--.-----------                                   1, 416, 735. 16
Gross amount expended_--      -----------------                                                      198, 788. 62
       Balance unexpended June 30, 1944-------------------                                       1, 217, 946. 54
Outstanding liabilities June 30, 1944_- ------ _--_49,                                                   006. 53
          Balance available June 30, 1944               -----.------------                       1, 168, 940. 01

Amount (estimated) required to be appropriated for completion
of existing project 1 _ __ -- __-         _       _-    ___
                                                         --                                        $768, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1       .  --------------                                                   4, 000. 00
  I Exclusive of available funds.
                                    28. MERMENTAU RIVER, LA.

   Location.-Mermentau River is formed by the junction of Bayous
des Cannes and Nezpique, 2.25 miles above Mermentau, La., and flow-
ing in a southwesterly direction, empties into the Gulf of Mexico.
   Bayou Nezpique rises in Evangeline Parish, flows in a southerly
direction, and empties into the Mermentau River.
   Bayou des Cannes rises in Evangeline Parish, flows in a south-
southwesterly direction, and empties into the Mermentau River.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1116 and 1278,
and U. S. Geological Survey maps.)
   Existing project.-The plan of improvement provides for enlarge-
ment of the channel of the lower Mermentau River to a depth of 15
feet below mean low Gulf level, over a bottom width of 170 feet
from mile 15 at upper Mud Lake to the Gulf of Mexico in order to
eliminate flood damages in the marsh area, and construction of a lock
and control spillway at Catfish Point, mile 24, to prevent salt-water
intrusion. See also individual report of navigation project for
Mermentau River, Bayou Nezpique, and Bayou des Cannes, La.
   The estimate of Federal cost for new work is $1,343,000. The ap-
proved estimate of Federal cost of annual maintenance is $18,000.
   The existing project was authorized by the Flood Control Act of
August 18, 1941. (See S. Doc."No. 94, 77th Cong., 1st sess., which
also contains the latest published map.)
   Local cooperation.-See page 7 for requirements. The cost of
maintenance and operation of the Federal project will be borne by
the United States. Local agencies have been unable to agree as to
details of the improvement. None of the conditions of local coop-
eration have been complied with.
   Operations and results during fiscal year.-Surveys were com-
menced in July 1943, and preparation of plans and specifications was
         616634--45-pt. 1, vol. 1-44
690         REPORT OF CHIEF OF ENGINEERS,                                                  U. S. ARMY,                   1944

commenced in September 1943. Work was suspended, pending sub-
mission of a review report, requested by resolution of the Committee
on Commerce, United States Senate, adopted March 5,1943.
   The total costs were $19,553.23, all for new work. Total expendi-
tures were $19,360.54.
   Condition at end of fiscal year.-No construction has been accom-
plished. Surveys and preparation of detailed plans and specifica-
tions are deferred, pending submission of a review report.
   The total costs to June 30, 1944, have been $19,553.23, all for new
work. The expenditures have been $19,360.54.
   Proposed operations.-No operations are proposed pending con-
gressional action on the report authorized by the resolution of the
Committee on Commerce of the United States Senate, adopted March
5, 1943.
                                          Cost and financial summary
Cost of new work to June 30, 1944_ ___$19,                                                                                          553. 23
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944                                               -----------                   19, 553. 23
Minus accounts payable June 30, 1944_--------                                                                            ---        192. 69
      Net total expenditures     ---------------------------                                                                    19, 360. 54
Unexpended balance June 30, 1944___    _   -----          ___                                                                  973, 639. 46
          Total amount appropriated to June 30, 1944-_                                                    _       _            993, 000. 00

   Fiscal year ending June 30                  1940                   1941                     1942               1943              1944

Cost of new work-------------..............------..........                       ----------------------------
                                                                                      ...........-------------                     $19, 553. 23
Cost of maintenance.-
Total expended-----            ---------------------------------------------------------                                            19,360.54
Allotted---------------------------------------------------------$23,                                                    000       970, 000. 00


Balance unexpended July 1, 1943__     -----------                                                                              $23, 000. 00
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942_------                 -_- ------                                                                      970, 000. 00
      Amount to be accounted for---       ----------                                                                           993, 000. 00
Gross amount expended_ ------------------------------------                                                                     19, 360. 54
      Balance unexpended June 30, 1944----------------------                                                                   973, 639. 46
Outstanding liabilities June 30, 1944_--------          ---                                                                     14, 952. 64
          Balance available June 30, 1944- -                                    ---------                                      958, 686. 82
Amount (estimated) required to be appropriated for completion of
   existing project 1_                    -                      -_                        -          -       -                350, 000. 00
  1 Exclusive of available funds.
29. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENOIES FOR
                       FLOOD CONTROL
   The cost of work during the fiscal year amounted to $687.30; the
expenditures were $680.75. The balance unexpended June 30, 1944,
$21,660.96, including accounts receivable, plus an allotment of $20,000
made during July 1944, will be applied as needed during the fiscal
year 1945 in payment of expenses incurred under this heading.
   The additional sum of $15,000 can be profitably expended during the
fiscal year 1946.
                  FLOOD CONTROL---NEW                               ORLEANS, LA.,                       DISTRICT                         691
                                        Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944 ---------------------------                                                             $76, 646. 78
       Total cost of permanent work to June 30, 1944--------------                                                              76, 646. 78
Plus accounts receivable June 30, 1944_--------                 ---                                                                   1. 19

      Gross total costs to June 30, 1944 ------------------                                                                     76, 647. 97
Minus accounts payable June 30, 1944-_-----             --------                                                                      7. 74

      Net total expenditures--- --.------------                                                                                 76, 640. 23
Unexpended balance June 30, 1944--      ------------     __                                                                     21, 659. 77
          Total amount appropriated to June 30, 1944                                      ---------------                       98, 300. 00


   Fiscal year ending June 30                1940                    1941                  1942                 1943                   1944

C ost of new work....-          .- - --.                      .-    ----.               - --.-.-..      ..     . . . . . .         .     .     ..
Cost of maintenance------------  $53, 319. 86                       $9, 250. 52           $4, 503.88           $1, 159. 48               $687.30

Total expended    -----------------
                     ..                     51, 824.89              11, 029. 44            4, 503. 88           1, 159. 48                   680. 75
Allotted_ _______-------------..            14, 250. 00            -3,000. 00          -10,150. 00             43, 500. 00        -20, 000.00



Balance unexpended July 1, 1943_---------          ----      $42, 340. 52
Amount allotted from War Department Civil Appropriation Act
  approved June 28, 1939_ -----------------                 -10, 000.00
      Am6unt to be accounted for_----           - --      _____                                                                 52, 340. 52
Deductions on account of revocation of allotment-----------------                                                               30, 000. 00

      Net amount to be accounted for_---                                                       - --                  ___        22, 340. 52
Gross amount expended_---- --------------                                                                                           680. 75

      Balance unexpended June 30, 1944_----                                                         -   ____                    21, 659. 77
Outstanding liabilities June 30, 1944_---------                                                                ---               7,000. 00

      Balance available June 80, 1944 ---------------------------                                                               14, 659. 77
Accounts receivable June 30, 1944                                                                                                     1. 19

     Unobligated balance available June 30, 1944---------                                                                       14, 660. 96
Amount allotted in July 1944 ----------------------------                                                        ___            20, 000. 00

          Amount available during fiscal year 1945 ------------                                                                 34, 660. 96

Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance                1-            -            -          -                                    -_____   15, 000. 00
  1Exclusive of available funds.

30. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                                 For last   Cost and expenditures to                             Estimated
                                                               full report        June 30, 1944                                  amount re-
                    Name of project                            see Annual -      __                                               quired to
                                                                    Report                                                        complete
                                                                      for-             New work              Maintenance

Buffalo River, Miss --------------------------                         1940           ..........----------------------------           I $40, 000


  1No work has      been done because of the lack of sufficient funds.
692        REPORT OF CHIEF OF ENGINEERS,                          U.   S. ARMY,                1944

Status of all investigations for flood control called for by flood-control acts and com-
                                     mittee resolutions

                                                              Date trans.
                                                              Date trans-     Document           Recommenda-
             Locality                 Authorization act        mitted to          ment           Recomenda-
                                                               Congress                              t

Boeuf, Rapides, Cocodrie and Commerce Committ-
  Courtableau Bayous, La., for           tee resolution, Feb.
  navigation, flood control, and irri-   8, 1939.
  gation.
Calcasieu River, La., for naviga.- Commerce Commit-
  tion, flood control and irrigation.    tee resolution, Feb.
                                         8, 1939; Flood Con-
                                         trol Committee res-
                                         olution, Jan. 26,
                                         1939; Rivers and
                                         Harbors Commit-
                                         tee resolution, Jan.
                                         24, 1939.
Courtableau Bayou, La., for navi. Rivers and Harbors
  gation, flood control and, irriga-     Committee resolu-
  tion.                                  tion, Jan. 24, 1939.
     Do.........................       Flood Control Com-
                                         mittee resolution,
                                         Jan. 26, 1939.
La Fourche Bayou, Ark. and La., Commerce Commit-
  for flood control and drainage.'       tee resolution, Apr.
                                         29, 1944.
Mermentau River, La., and its Commerce Commit-                           ..............
  tributaries for navigation and         tee resolution, Mar.
  drainage.                              5, 1943.
Mississippi River, alluvial valley, Flood Control Com- Feb. 12,1944 -..----------- Unfavorable.
  damages from backwater from            mittee resolution,
  Atchafalaya Basin and Wax Lake         June 6, 1939.
  Outlet.
Mississippi River between Cairo, Flood Control Com- Mar. 20,1944 H. 509, 78th Favorable.
  Ill., and Baton Rouge, La., for        mittee resolution,                   Cong., 2d
  12-foot channel (for navigation        Mar. 8, 1943.                         sess.
  and flood control).1
     D o.'.   .- - - - - - - - - .                            do........ .....----
                                       Commerce Commit- ...-----                    do....... Do.
                                         tee resolution, Mar.
                                         9, 1943.                              ..   --.-----



Mississippi (lower) River, protec- Flood Control Com-
  tion by levees, east bank from         mittee resolution,
  Vicksburg south to the Big Black       Apr. 26, 1944.                  --------------
  River.'
Pontchartrain Lake, La., from the Flood Control Act,
  Orleans-Jefferson" Parish line         Aug. 18, 1941.
  westward and northward to the                                          --------------
  vicinity of Frenier.
Queue de Tortue Bayou, La., for Commerce Commit-
  navigation and drainage.               tee resolution, Dec.
                                         19, 1940.
Rapides, Boeuf, Cocodrie Bayous Flood Control Act,                                      . . . . . . -..--
and watersheds thereof, from their      June 28, 1938.
  source in Rapides Parish to their
  outlet in St. Landry Parish, La.
Serpent Bayou, La., for flood con- Flood Control Com-
  trol and drainage.                     mittee resolution,
                                         Feb. 2, 1944.

  I Field report being prepared by the Mississippi River Commission.


     IMPROVEMENT OF RIVERS AND HARBORS IN THE
             VICKSBURG, MISS., DISTRICT
   This district comprises a very small portion of southwestern Ten-
nessee, northwestern Mississippi, southern Arkansas, a portion of
northeastern Texas, and northern Louisiana embraced in the drainage
basins of the eastern tributaries of the Mississippi River south of
Nonconnah Creek to Big Black River, inclusive, and of the western
tributaries south of the Arkansas River to the south bank of the Red
         RIVERS AND     HARBORS--VICKSBURG,           MISS., DISTRICT         693
River. It includes the drainage basin of the Red River from Fulton,
Ark., inclusive, to its mouth, excluisive of that portion south of the
river below Boyce, La.
   District engineer: Lt. Col. R. W. Sauer, Corps of Engineers.
   Division engineer; Brig. Gen. Max C. Tyler, U. S. Army.
                                   IMPROVEMENTS

              Navigation                          Flood control-Continued
                                    Page                                      Page
1. Red River below Fulton,                 10. Little Missouri River Basin,
     Ark _                           693          Ark -     -    --            710
2. Cypress Bayou and water-                11. Wallace Lake Reservoir, La_     713
     way between Jefferson,                12. Bayou Pierre, La ......         714
     Tex., and Shreveport, La-       695   13. Bayou Bodcau Reservoir,
3. Ouachita and Black Rivers,                     La_-                         716
     Ark. and La_                    698   14. Bayou Bodcau, Red Chute,
4. Removing snags and wrecks                     and Loggy Bayou, La ....     717
     from the Mississippi River            15. Natchitoches Parish, La ---    719
     below the mouth of Mis-               16. Pineville, Red River, La ---   720
     souri River and from the              17. Aloha-Rigolette area, Grant
     Old and Atchafalaya Riv-                    and Rapides Parishes, La_    721
     ers_   -    -   -    -
5. Examinations, surveys, and
                                     703   18. Saline Point, La--_   --       723
     contingencies (general)---      705
                                           19. Big Black River, Miss ....
                                           20. Emergency flood-control
                                                                              724
6. Other navigation projects for
     which no estimates are                      work_--                      725
      submitted_                     707   21. Preliminary examinations,
7. Plant allotment_-       -        707         surveys, and contingencies
                                                  for flood control-.......   726
             Flood control                 22. Other flood-control projects
8. Calion Ouachita River, Ark_      709         for which no estimates are
9. Black Bayou Reservoir, La.__     709         submitted------------         728

                   1. RED RIVER BELOW FULTON, ARK.

   Location.-Red River rises in the arid regions of eastern New
Mexico, flows in a general easterly and southeasterly direction for
1,300 miles, and enters the Mississippi River at Red River Landing,
La. (See U. S. Geological Survey State maps and Mississippi River
Commission Alluvial Valley quadrangle maps.)
   Previous projects.-Authorized by River and Harbor Acts of May
23, 1828, June 10, 1872, June 18, 1878, March 3, 1879, August 2, 1882,
July 5, 1884, August 11, 1888, and September 19, 1890. For further
details, see page 1868 of Annual Report for 1915 and page 895 of
Annual Report for 1938.
   Emisting project.-This provides for continuing improvement of
Red River from Fulton, Ark., to the Atchafalaya River, La., 455.6
miles by systematic clearing of the banks, snagging, dredging shoals,
building levees (either alone or in cooperation with riparian States),
closing outlets, revetting caving banks, and preventing injurious cut-
offs. The lower end of the section included in the project is 7.6 miles
above the nfouth of the river. No proposed channel dimensions were
given.
   Floods ordinarily cause fluctuations of stage between high and low
water of from 30 to 45 feet. Unusuial floods occasionally increase this
range about 10 feet.
694    REPORT OF CHIEF OF ENGINEERS,             U.   S.   ARMY,   1944

   The work being continuous, no estimate for completion was made.
The latest (1941) approved estimate for annual cost of maintenance
is $27,000.
   The existing project was adopted by the River and Harbor Act of
July 13, 1892 (Annual Reports for 1890, p. 1829, and for 1891, p.
1957). (For latest published maps see H. Doc. No. 378, 74th Cong.,
2d sess.)
   Terminal facilities.-None.
   Operations and results during fiscal year.-Duringthe period from
August 15 to 30, 1943, the dredge Todd removed 78,283 cubic yards of
material at King's Bayou, 34.6 miles above the mouth. This work is
classed as maintenance and was done with hired labor at a cost and
expenditure of $14,507.03.
   Condition at end of fiscal year.-The work under the existing project
being continuous, and no estimate being made, the date or percentage
of completion cannot be stated. Maintenance in recent years provides
navigation to Shreveport, La., at medium and high stages. The head
of navigation is the Arkansas-Oklahoma State line, to which point
boats may occasionally run during high water if snags, overhanging
trees, or similar obstructions do not interfere. From January to July
the prevailing stage is 6 feet and over, and minimum depths are about
4 feet to Fulton, Ark., 5 feet to Shreveport, La., and 6 feet to Alex-
andria, La. During the remainder of the year stages near zero may
be expected, with minimum depths less than 1 foot from Fulton to
Shreveport, 1 to 2 feet from Shreveport to Alexandria, 4 feet from
Alexandria to mouth of Black River, and 6.5 feet thence to the mouth.
The controlling depth at the end of the fiscal year was 38.1 feet to
the mouth of Black River and about 7 feet from there to Fulton, Ark.
   Total costs and expenditures under the existing project to June 30,
1944, were $409,928.91 for new work and $1,690,555.33 for maintenance,
a total of $2,100,484.24.
   Proposed operations.-The sum of $34,000 allotted during August
1944, plus the unexpended balance of $492.97, will be applied to one
month's dredging and snagging, on the Red River below the mouth
of the Black in order to maintain project depth.
   The additional sum of $17,000 can be profitably expended during
the fiscal year 1946, using Government plant and hired labor, on
maintenance, dredging, mouth of Black River to mouth of Red River
with U. S. pipe-line dredge Todd, two-thirds month (September 1945).
                         Cost and financial summary
Cost of new work to June 30, 1944-                                 $1, 963, 806. 41
Cost of maintenance to June 30, 1944---------------- ------         1, 690, 555. 33
      Total cost of permanent work to June 30, 1944---------- 3, 654, 361. 74
Net total expenditures-----------------------------------   3, 654, 361. 74
Unexpended balance June 30, 1944---------------------------         492. 97
      Total amount appropriated to June 30, 1944--- -------         3, 654, 854. 71
                      RIVERS AND HARBORS-VICKSBURG,                                               MISS.,       DISTRICT                  695

     Fiscal year ending June 30                                1940             1941             1942            1943                 1944

                                            .
Cost of new work .---------------------------. --..                                                     ....      ..    .       ..   ..-
                     ..
Cost of maintenance------ ----- -.... $38, 623.05                             $14,967. 74      $13,888. 49     $14,443. 77           $14, 507. 03

Total expended ....                   ......-----------------... 38, 623.05    15, 127. 56      13, 728.67      14,443. 77            14, 507.03

Allotted----------------------.........................    -37, 500.00         15,800.00        12, 500.00      15,000.00...........


Balance unexpended July 1, 1943----- -----------------------                                                                    $15, 000. 00
Gross amount expended--_------------- ----        $15, 507. 03
Less reimbursements collected----- --------------   1, 000. 00
                                                                                                                                 14, 507. 03

     Balance unexpended June 30, 1944_-------      -    -                                                                   -        492. 97
Amount allotted in August 1944-----------------------------                                                                      34, 000. 00

               Amount available during fiscal year 1945                                      ----------                          34, 492. 97

Amount that can be profitably expended          in fiscal year ending
                                1- - - - - - - - - - - - - - - - - - - - - - - - - - -
June 30, 1946, for maintenance                                                                                                  17, 000. 00
   1Exclusive of available funds.

2. CYPRESS BAYOU AND WATERWAY BETWEEN JEFFERSON, TEX., AND
                      SHREVEPORT, LA.

  Location.-This bayou rises in northeast Texas and flows in a south-
easterly direction to Caddo Lake, through this lake to Big Willow
Pass, and through Big and Little Willow Passes, Soda Lake, Twelve
Mile Bayou, the new diversion canal, and Cross Bayou to the Red
River at Shreveport, La., a distance of about 132 miles. (See U. S.
Geological Survey State maps.)
   Cypress Bayou proper ends where it enters Caddo Lake, but the
name is frequently applied to the whole waterway above described.
  Existing project.-This provides for dredging and straightening
the channel, removing obstructions, and clearing the banks for 66 miles
from the Red River at Shreveport, La., to Jefferson, Tex., and for the
construction of a dam without a lock at the foot of Caddo Lake.
                                                                      CADDO LAKE DAM

        Location: At foot of Caddo Lake, La., and Tex., about 23 miles above mouth
     of Jefferson-Shreveport Waterway.
        Below Mooringsport, La.: 2 miles.
        Length: 3,400 feet.
        Type: Fixed, on pile foundation.
        Date of completion: December 21, 1914.
        Cost : $100,553.47.
  Below the dam the fluctuations of the water level depend chiefly
upon backwater from the Red River, the maximum being about 10
feet. At the dam the fluctuations are from zero to 14 feet above the
crest of the spillway, and at Jefferson the maximum is 27.5 feet.
  The estimate of cost for new work was $20,000 for open-channel
work (Annual Report, 1872) and $100,000 for the dam (1907). The
696        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                       1944

latest (1933) approved estimate for annual cost of maintenance is
$1,700.
   The existing project was authorized by the following.,river and
harbor acts:

    Acts                        Work authorized                                     Documents


June 10, 1872   Open channel work.......------------------------Annual         Report 1872, p. 572.
June 25,1910    Construction of the dam............---------------------H. Doc. No. 220, 60th Cong., 1st sess.



  The latest published map is in House Document No. 378,. Seventy-
fourth Congress, second session.
  Terminal facilities.-There is one publicly owned brick warehouse
50 by 150 feet, at Jefferson, Tex. The following terminal facilities
are located at Mooringsport, La.:
      One privately owned covered dock, 60 by 60 feet, open to all small boats.
      One privately owned pipe rack, not decked.
      One privately owned boat ways.
   The warehouse at Jefferson has not been used for several years, since
no commerce has moved in that vicinity. The wharves, docks, and
warehouses at Mooringsport are all owned by oil companies. There
are no terminal facilities at Shreveport. The existing terminal facili-
ties are considered adequate for present commerce.
   Operations and results during fiscal year.-The work consisted of
caring for dam and making major repairs to dam, which entailed plac-
ing a total fill of 11,787 cubic yards of material along the upstream
side of the dam and 2,994 cubic yards of material in earth blanket on
the downstream side of the dam by contract, and with hired labor plac-
ing 333 cubic yards of riprap and 120 cubic yards of earth fill; sealing
2,438 linear feet of cracks and breaks; placing 98 cubic yards of sand
and gravel fill, and 4,780 cubic feet of grout. The repair work was
suspended on November 30, 1943, pending favorable weather condi-
tions and lake stages. Work on the spillway section of the dam, by
hired labor, remains to be completed. The work is classed as mainte-
nance and was done at a cost of $30,045.69 and expenditure of $29,-
414.24.
   Condition at end of fiscal year.-The dam at the foot of Caddo Lake
was completed in 1914, completing the project. Its construction and
maintenance insure a 4-foot navigable depth at low water from that
point to Jefferson, the head of navigation, but cuts off all possible
navigation to Shreveport except for such light draft boats as may pass
over the dam at high stages. Below the dam navigation is largely
dependent upon backwater from the Red River. A stage of from 15
to 24 feet on the Red River gage at Shreveport, depending on the run-
off from Cypress Bayou drainage area, is necessary to provide a 4-foot
depth up to the dam. Such stages are short in duration and irregular
in occurrence. The controlling depth between the dam and Jefferson,
Tex., was about 4 feet at the end of the year.
               RIVERS AND HARBORS                                      VICKSBURG, MISS., DISTRICT                                    697

                                                                                   United States        Contributed             Total
                                                                                      funds               funds
Cost of new work----------------------------------$202,817.48----------------$202,817.48
Cost of maintenance---------------------------------283, 057.99                                              $50,000           333, 057.99
      Total cost-.........-.---.------.-.-....-.- .                           -.       485, 875.47               50,000        535, 875.47
Total expended--.........---        ..------.-....-.-........                          485, 419.02               50,000        535, 419.02



   Proposed operations.-The balance unexpended, $45,293.50, plus an
allotment of $2,400, made during July 1944, a total of $47,693.50, will
be applied to ordinary maintenance of dam by hired labor together
with major repairs to dam, as follows:
Accounts payable June 30, 1944-- ----------             _-_____-$456.                                                                      45
Maintenance:
    Salary of dam tender-_____---------                  $2, 100. 00
    Repairs to Caddo Lake Dam___- -------                    300. 00
    Plans and Design, Caddo Lake Dam                         487.05
    Completion of repair of cracks and breaks in dam by
          hired labor -_ -                                 ---                                          44, 350. 00
                                                                                                                             47, 237. 05
       Total for all work ----------------------------------- 47, 693. 50
   The additional sum of $3,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
   Salary of dam tender -------------------------------------                                                                    $2, 100
   Repairs to dam___
                   --------------------------------------------                                                                      900

          Total for all work                 ---------------------------------------                                              3, 000

                                               Cost and financial summary
Cost of new work to June 30, 1944__-- ---------                                                                       $202, 817. 48
Cost of maintenance to June 30, 1944_-   ----------                                                                    283, 057. 99
      Total cost of permament work to June 30, 1944----------                                                               485, 875. 47
Minus accounts payable June 30, 1944_--------      --      -                                                                     456. 45

                           ___
      Net total expenditures--     ----------                -                                                              485, 419. 02
Unexpended balance June 30, 1944 ---------------------------                                                                 45, 293. 50
          Total amount appropriated to June 30, 1944                                      --------------                    530, 712. 52


   Fiscal year ending June 30                        1940                 1941             1942              1943                1944

Cost of new work-        -   -       -         -.-               ...    ...       --..
                                                                              -..... ... -        ...   ...- .      .....       ........
                      .......
Cost of maintenance -------------                  $1,719.16            $1,440.05         $1,881. 67       $6, 508.45           $30, 045. 69

Total expended----------.--.-..                    -1,480. 25             1,779.03         1,895.35         6, 440. 21           29, 614.24
Allotted-------- --------- _--
                           -                                                71.00.00
                                                                          1,700.00         4,500.00         4, 650.00            72,000.00
698       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                  1944

Balance unexpended July 1, 1943____                                      $2, 907. 74
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941 ------------- $40, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 2, 1943 ---------------32, 000. 00
                                                                         72, 000. 00
       Amount to be accounted for_                                       74, 907. 74
Gross amount expended_-------                  ---     $36,803.91
Less reimbursements collected                            7----------------------
                                                          . 189. 67
                                                                           29, 614. 24
     Balance unexpended June 30, 1944_------                   ---       45, 293. 50
Amount allotted in July 1944_----------                     ----          2, 400. 00

        Amount available during fiscal year 1945------------------       47, 693. 50

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1_        -_____--         -     -     -         3, 000. 00
1 Exclusive of available funds.


               3. OUACHITA AND BLACK RIVERS, ARK. AND LA.

   Location.-Ouachita River rises in Polk County, Ark., and flows
about 600 miles in a general southeasterly and southerly direction
through Arkansas and Louisiana. It is joined by Tensas and Little
Rivers at Trinity, La. (Jonesville, La.), below which place it is called
Black River, and enters Red River 35.5 miles above its mouth. (See
U. S. Geological Survey State maps and Mississippi River Commission
Alluvial Valley quadrangle maps.)
   Previous projects.-The project was adopted by the River and Har-
bor Acts of March 3, 1871, June 10, 1872, August 14, 1876, and July 5,
1884. A separate project for work in the Ouachita River between
Camden and Arkadelphia was adopted by the River and Harbor Act
of August 11, 1888. For further details, see page 1869 of the Annual
Report for 1915, and page 900 of the Annual Report for 1938.
   Existing project.-This provides for a navigable depth of 61/2 feet
at low water from the mouth of Black River, La., to Camden, Ark., a
distance of 351 miles, by the construction of six locks and dams, with
necessary dredging, and for removal of logs, wrecks, and overhanging
trees, etc., between mouth of Black River and Arkadelphia, Ark., 417
miles, and for a channel 7 feet deep and of suitable width from the
improved channel of the Ouachita River above dam No. 6 to the vicin-
ity of the railroad bridge over Lake St. Mary, thence a canal of the
same depth and 70 feet in width along the south side of the railroad
embankment to high ground near Felsenthal, a distance of 3,600 feet,
with a suitable turning basin near the inner end.
   The location and description of the locks and dams which are
included in the project are contained in the table following:
                                                                   Locks and dams, Ouachita River, Ark. and La.

                                                              Great-
                                                                 estDet         Depth
                                       Dis-     Above Width avail-                on                                                                                      Year    Year
No.             Location              tance
                                       from     mouth
                                                 of   of lock   able    Lift at miter     Character of                                                                   opened     of
           No.   Location              fr              ham- length       low    sill at          t                      Kind of dam        Type of construction            to     com-      Cost
                                      nearest
                                       town
                                                Black
                                                River
                                                        ber
                                                              for
                                                                 for
                                                                  gull water normal
                                                              width
                                                                  full
                                                              widthber           poolgain
                                                                                 olgation
                                                                                                                                                                          navi-    ple-
                                                                                                                                                                                  tn
                                                                                                                                                                                  tion
                                                              of lock           level

                                      Miles     Miles    Feet     Feet       Feet     Feet                                                                                                                 id
      2   Harrisonburg, La-......       0.1      73. 3      55      268       14.4      6.9    Piling in clay ..        Movable ...      Concrete Poiree needle dam;      1918    1921    $470,394.69
                                                                                                                                            steel mitering lock gates.
      3   Riverton, La...----------      2.0     134.0      55         268    14.8      6. 5 Piling in sand ...- ....      do---...---... _ do--- -            -          1919    1920      681,072.84
      4   Monroe, La ...__ _____         4.0     178.1      55         268     8. 9     6. 5 .    do-    .. .   ...        do ....        . __do-------...                1915    1915    1 641, 630. 23
      5   Sterlington Reach, La.          .6     208.3      55         268     6.9      6.6 Piling in clay    -......      do ...        Concrete Chanoine wicket
                                                                                                                                            dam; steel mitering gates.
                                                                                                                                                                          1924    1926      901, 096. 17
                                                                                                                                                                                                           4 .
      6
      8
          Near Felsenthal, Ark.__
          Near Calion, Ark       .
                                         3.3
                                        10. 5
                                                238.7
                                                297.5
                                                            55
                                                            55
                                                                       268
                                                                       268
                                                                               9.7
                                                                              13. 5
                                                                                        7.6
                                                                                        6. 5
                                                                                               Piling in sapd ..-...
                                                                                               Piling in clay ...-...
                                                                                                                           do ...... - _do _----
                                                                                                                           do ....-.....
                                                                                                                                   -
                                                                                                                                                             ..---
                                                                                                                                              do_ ------ __---1912
                                                                                                                                                                          1913    1923
                                                                                                                                                                                  1926    3
                                                                                                                                                                                          2 914,844.67
                                                                                                                                                                                            915, 445. 96
                                                                                                                                                                                                           zi
  1  Dam failed Aug 10, 1917, and was rebuilt under permanent indefinite appropriation                    3 Includes actual cost of original structure to June 30, 1919 ($592,922 43), and the cost of
for operating and care of canals. Type of dam now is concrete Poiree needle pass and                   modifications to permit elimination of locks and dams 7 and 9 ($322,523.53).
Chanoine wicket weir.
   2 Includes cost of original structure to June 30, 1919 ($559,539.34), and the cost of modi-
fications to permit elimination of lock and dam 7 ($355,305.33).
700        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

   Floods ordinarily cause fluctuations of stage from 25 to 45 feet
between high and low water. Extreme floods occasionally increase
this range about 10 feet.
   The latest revised estimate of cost of the system of locks and dams,
made in October 1920, as modified by the actual cost of Nos. 2, 3, 4,
and 6, since completed, was $4,576,838.52. The estimate of cost for
construction of the canal to Felsenthal, made in 1936, is $36,000. The
latest (1941) approved estimate for annual cost of maintaining the
improvement by removing obstructions to navigation between Cam-
den, Ark., and the mouth of Black River, La., is $130,500. No estimate
for maintenance above Camden has been approved. The latest (1936)
approved estimate of annual cost of maintaining the canal to Felsen-
thal is $2,000. The estimate of annual cost of operation and care,
revised in 1941, is $136,500.S
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                        Documents


Mar. 3,1871     Open-channel work from Arkadelphia to the            H. Ex. Doc. No. 60, pt. 4, 41st Cong.,
                 mouth.                                                3d sess., Annual Report, 1876, p. 336.
July 5,1884     Extension of open-channel work into Black River      Annual Report, 1883, p. 1155.
June 13,1902    Construction of locks and dams Nos. 4 and 6          Specified in act.
                 (canalization work based on report contained in
                 H. Doc. No. 448, 57th Cong., 1st sess.; Annual
                 Report 1902, p. 1435).
Mar. 2,1907     Construction of locks and dams Nos. 2 and 8;             Do.
                 elimination from the plan of lock and danl No.1.
June 25,1910    Obtaining sites for locks and dams Nos. 3 and 7__        Do.
July 25,1912    Construction of locks and dams Nos. 3 and 7.....         Do.
Aug. 8,1917     Construction of lock and dam No. 5 --------------        Do.
Mar. 2,1919     Modification of locks and dams Nos. 6 and 8 by       Rivers and Harbors Committee Doc.
                  raising their pool levels, which with dredging       No. 7, 65th Cong., 2d sess.
                  obviates the necessity for constructing locks
                  and dams Nos. 7 and 9.
Aug. 26, 1937   For the 7-foot channel and construction of a canal   Senate committee print, 75th Cong.,
                                                                                   1
                  3,600 feet long to Felsenthal, Ark.                  1st sess.
June 26,19342   Operating and care of locks and dams provided
                 for with funds from War Department appro-
                 priations for rivers and harbors.


  1 This document and Annual Report for 1913, p. 2336, contain the latest published maps.
  2 Permanent Appropriations Repeal Act.


   Recommended modifications of project.-Under date of August 16,
1938, the Chief of Engineers recommended modification of the exist-
ing project to eliminate the requirement that local interests provide a
highway at an elevation above that of the 1932 high water from the
main State highway system to the canal terminal near Felsenthal
 (H. Doc. No. 104, 76th Cong., 1st sess.).
   Local cooperation.-Local interests contributed $5,000 during the
fiscal year 1929, which was expended in connection with United States
funds in prevention of cut-off near Camden, Ark. The River and
Harbor Act of August 26, 1937, authorized construction of the canal
to Felsenthal, Ark., subject to the condition that local interests furnish,
free of cost to the United States, necessary rights-of-way and suititble
spoil-disposal areas for new work and for subsequent maintenance as
         RIVERS AND     HARBORS--VICKSBURG,         MISS.,   DISTRICT      701
required, release the United States from all claims for damages attrib-
utable to the work of improvement, and agree to construct a suitable
warehouse at the canal terminal and to provide a highway at an eleva-
tion above that of the 1932 high water, from the main highway system
to the canal terminal. Local cooperation is not yet assured.
    Terminal facilities.-At Monroe, La., there is one private electric
crane and one private warehouse. At West Monroe there are two
private warehouses with conveyors. At Camden, Ark., there are three
private warehouses. At Champagnolle Landing there is a private
dock for the loading of gasoline into barges. These existing facilities
are considered adequate for present commerce.
    Operations and results during fiscal year.-During periods from
July 10, 1943, to October 12, 1943, the dredge Todd removed 1,138,383
cubic yards of material from the channel at various points from the
mouth of Black River, mile 0.0, to lock and dam No. 3, mile 133.7.
    The United 'States towboat Capt. Eric Bergland, and derrick boat
3701 removed 18 obstructions from the navigable channel and cleared
debris from two slip-ins in pool 6.
    The six locks and dams were operated and maintained in a satisfac-
tory condition throughout the year.
    The work is classed as maintenance and was done by hired labor.
The costs for the year were $120,660.19 for channel maintenance and
$122,880.42 for operating and care of locks and dams, a total of
 $243,540.61 for maintenance. The total expenditures were $241,654.21.
    Condition at end of fiscal year,-The six locks and dams embraced
in the existing project for slackwater improvement of the Ouachita
River were completed in 1924 and provide navigation to Camden, Ark.
  (See table under existing project.)
    Construction of the canal to Felsenthal, authorized in 1937, has not
been started. The head of navigation is Arkadelphia, Ark., to which
point boats may occasionally run during high water if snags, over-
   anging trees, or similar obstructions do not interfere. From January
to June the gage at Monroe generally exceeds pool stage (13.3 feet),
caused by the river above, and minimum depths exceeding 7 feet are
usual between the mouth of Black River and Camden, Ark., a distance
of 350.8 miles. At intervals during this period the reading of the
Camden gage exceeds 15 feet, and minimum depths of 7 feet may be
expected between Camden and Arkadelphia. During the remainder
of the year the pools furnished by the six dams, with moderate dredg-
ing in Black and Ouachita Rivers, provide depths of 6.5 feet between
the mouth of Black River and Camden, Ark., and depths of only a few
inches may be expected between Camden and Arkadelphia, Ark.
    The controlling depth at the end of the fiscal year was 47.7 feet to
lock and dam No. 2, and 6.5 feet from there to Camden, Ark.
Cost of new work under existing project to June 30, 1944------ $4, 574, 551. 31
Cost of maintenance_---------                  ---              3, 957, 532. 10

      Total cost.                          _8,                       532, 083. 41
Total expended               .----------.--------             -   8, 530, 989. 30
  In addition, the sum of $2,940,952.07 was expended between Jan-
uary 25, 1913, and June 30, 1936, on operating and care of the works
of improvement under the provisions of the permanent indefinite
appropriation for such purposes.
702       REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,         1944

   For operations in connection with levees and levee walls under the
Mississippi River Commission, see report of the Mississippi River
Commission.
  Proposed operations.-The balance unexpended, $51,204.21, plus
accounts receivable at the end of the fiscal year $4,897.63, plus an
allotment of $210,000 made during July 1944, a total of $266,101.84,
will be applied to maintenance using Government plant and hired
labor as follows:
Accounts payable June 30, 1944- _                    _------                               $4, 797. 82
Maintenance:
    Dredging with U. S. pipe-line dredge Todd, 3/
      months (July August, September, 1944,
      June 1945) at $30,000       --------------- $110, 000. 00
    Snagging with U. S. towboat Capt.-Eric Bergland
      and U. S. derrickboat 3701, 2 months (August
      and September 1944) at $4,000 -------------     8, 000. 00
      Total        ---------------------                             118, 000. 00
Operating and care of locks and dams:
    Operations ---        -$110,                          500. 00
    Ordinary repairs-        -30,                         700. 00
    Improvement and reconstruction-                         0. 00
      Emergencies          ---------                    2, 104. 02
                                                                     143, 304. 02
                                                                                          261, 304. 02

        Total for all work----         -   ----------                        __           266, 101. 84
  The additional sum of $300,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredging with U. S. pipe-line dredge Todd, 4% months (July,
      August, November, 1945, and May and June 1946)---_---                                 $140, 000
    Snagging with U. S. towboat Capt. Eric Bergland and U. S.
      derrickboat 3701 3 months (July, August and September 1945)                              10, 000
      Total -----------------------------------------------                                  150, 000
Operating and care of locks and dams:
    Operations-------------------------- ---------                            $110, 500
    Ordinary repairs --------------------------------                           19,000
    Improvement and reconstruction ------------------                           20, 000
    Emergencies ------------------------------------                                500
                                                                                             150, 000

        Total for all work_--------------------                              ____--300,           000

                             Cost and financial summary
Cost of new work to June 30, 1944_-------                                   ---    $5, 248, 618. 94
Cost of maintenance to June 30, 1944_"--                  --------                  6, 898, 484. 17

       Total cost of permanent work to June 30, 1944---------                       12, 147, 103. 11
Undistributed costs June 30, 1944-----------_                                           -1,'193. 92

       Net total cost to June 30, 1944----------------------                        12, 145, 909. 19
Plus accounts receivable June 30, 1944 -----------------------                            4, 897. 63

      Gross total costs to June 30, 1944          --------------------              12, 150, 806. 82
Minus accounts payable June 30, 1944-----------------------                               4, 797. 82
     Net total expenditures_---------                                ---            12, 146, 009. 00
Unexpended balance June 30, 1944-                                                        51, 204. 21
        Total amount appropriated to June 30, 1944- -                 ---           12, 197, 213. 21
                  RIVERS AND                  HARBORS-VICKSBURG,                        MISS., DISTRICT                       703

   Fiscal year ending June 30                       1940            1941               1942            1943                1944

Cost of new work . . . . . . . . . . . . . . . ..                 . . . . . ..   .     . .. . .
Cost of maintenance             ...-----------   $260, 526. 72   $245,362. 16    $257, 541. 20     $252,036.45           $243, 540.61

Total expended         ........---------------- 265, 085.67       275, 033. 72       253,133. 51    253, 120.65           241, 654. 21
Allotted-......           -.........   ....       246, 000.00     267,000. 00        168, 400.00    281,688.66             40, 000. 00


Balance unexpended July 1, 1943_   ----------------------             $252, 858. 42
Amount allotted from W. D. Civil Appropriation Act approved
  June 2, 1943_---                                                       40, 000. 00
                                                          .----------------

       Amount to be accounted for--------------------                                                             292, 858. 42
Gross amount expended--      --------           $387, 156. 80
Less reimbursements collected -----------------  145, 502. 59
                                                                                                                  241, 654. 21
      Balance unexpended June 30, 1944_                                                 -----------               '51,  204. 21
Outstanding liabilities June 30, 1944_--------                                                     -          -      2, 847. 22
      Balance available June 30, 1944 -----------------------                                                       48, 356. 99
Accounts receivable June 30, 1944_---------                  -                                                -4,       897. 63
     Unobligated balance available June 30, 1944                                      ------------                 53, 254. 62
Amount allotted in July 1944_---     -----------                                                                  210, 000.00
          Amount available during fiscal year 1945 ----------------                                               263, 254. 62

Amount (estimated) required to be appropriated for completion
of existing project 1         -----------------                                                                    36, 000. 00

Amount that can be profitably expended in fiscal year ending
                                1
June 30, 1946, for maintenance ----------            _--300,                                                              000. 00
  1Exclusive      of available funds.

4. REMOVING SNAGS AND WRECKS FROM THE MISSISSIPPI RIVER
   BELOW THE MOUTH OF MISSOURI RIVER AND FROM OLD AND
  ATCHAFALAYA RIVERS

   Location.-The stretch of the Mississippi River under jurisdiction
of the Vicksburg Engineer District extends from the mouth of Ar-
kansas River to Vicksburg, Miss. (See Mississippi River Commission
maps, Alluvial Valley of the Mississippi River.) The work in the
New Orleans district on the Mississippi River from Vicksburg to the
Passes and 8 miles of Old River and 30 miles of Atchafalaya River
is handled by that district in connection with flood control, Missis-
sippi River and tributaries.
   Previous projects.-For the removal of these obstructions general
appropriations were made at regular intervals as early as 1824. For
further details, see page 1880, Annual Report for 1915.
   Existing project.-This is a continuation of the plan adopted in
1879, and provides for the removal and destruction of snags, wrecks,
drift heaps, and other obstructions to navigation in the Mississippi
River from the mouth of Arkansas River to Vicksburg, Miss.; also
for the felling of large trees on or near caving banks, thereby de-
creasing the number of snags to be destroyed thereafter. The work
is done by District's steel hull snagboat, C. H. West, built in 1934;
704         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                       1944

and other plant; all fitted with necessary equipment and appliances
and operated by Government employees.
  The existing project was authorized by the following river and
harbor acts:

     Acts                       Work authorized                        Documents


...-.......     Annual appropriations or allotments made 1879
                 to 1886, inclusive, except in 1883 and 1885.
Aug. 11, 18881 Annual expenditure of $100,000 made available
                 each year.
Mar. 3, 1909 Atchafalaya and Old Rivers from their junction-
                 with the Mississippi and Red Rivers to Mel-
                 ville, La., included in the project.
Mar. 2, 1919 Appropriation of $50;000 additional to cover in-
                 creased costs due to war conditions.
June 30, 1922 2
Mar. 2, 1923 2 Allotments of $25,000, $20,000, $17,500, and $13,000,
June 7, 1924 2 respectively, to cover increased costs.
Apr. 15, 1926 2
June 26, 1934 3 Maintenance provided for with funds appropri-
                 ated for the preservation and maintenance of
                 rivers and harbors, since June 30, 1935.

  1 Sec. 7.
    War Department Appropriation Act.
  2Permanent Appropriations Repeal Act.

   Terminal facilities.-At Greenville, Miss., there is a municipal con-
crete wharf and a municipal floating wharf. At Vicksburg, Miss.,
there is a paved municipal wharf 375 feet in length with inclined
ramp exits through sea wall. In addition, at Vicksburg below mouth
of Yazoo Canal there are a Federal barge line transfer terminal with
railroad connections and a private floating dock for the munloading of
petroleum products from barges.
   In addition, pipe lines from bulk plants to barge landings for
handling petroleum products, and log slips are located on the reach
south of the mouth of Arkansas River. Further details are contained
in the following reports: Transportation Series Report No. 2, 1929,
Transportation in the Mississippi and Ohio Valleys; Transportation
Series Report No. 4, 1936, Transportation Lines on the Mississippi
River System.
  The present facilities are considered adequate for existing com-
merce.
   Operations and results during fiscal year.-The U. S. snagboat
Chas. H. West made 27 complete trips between Rosedale, Miss., near
mouth of Arkansas River, and Racetrack Towhead, near Warrenton,
Miss., removing 291 snags from the channel. The work is classed as
maintenance and was done by hired labor at a cost and expenditure
of $22,500.
  Condition at end of fiscal year.---The project being one of contin-
uous maintenance of channel, no estimate of completion and total
cost can be made. Each freshet brings down new obstructions, and
constant changes in location of channel uncover old obstructions.
                  RIVERS AND HARBORS--VICKSBURG,                                     MISS.,     DISTRICT                      705
This work is of great benefit to commerce and navigation of the
river, and disasters caused by vessels striking channel obstructions
seldom occur.
  Operations provided a channel reasonably free from obstructions
at the end of the fiscal year, and there is sufficient plant available to
take care of future work. Total cost and expenditures of the existing
project in that stretch of the river under the jurisdiction of the
Vicksburg district to June 30, 1944, was $222,500 for maintenance.
  Proposed operations.-An allotment of $22,500 made during July
1944 will be applied to removing obstructions to navigation from the
mouth of Arkansas River to Warrenton, Miss., using U. S. snagboat
Chas. H. West, 41/2 months (August 15 to December 15, 1944) at
$5,000 per month.
  The additional sum of $25,000 can be profitably expended during
the fiscal year 1946, to be applied to removing obstructions to navi-
gation from the mouth of Arkansas River to Warrenton, Miss.,
using U. S. snagboat Chas. H. West.
                                                 Cost and financial summary

Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944_--------                                                    ---                     $222, 500

       Total cost of permanent work to June 30, 1944--------------                                                        222, 500
Net total expenditures-__________--------------222,                                                                            500
Total amount appropriated to June 30, 1944_------            ---                                                          222, 500


    Fiscal year ending June 30                       1940         1941              1942         1943                      1944

Cost of new work..           ...            . .-
                                    ...-----------      . . . . .--..
Cost of maintenance .              - _-....
                                       _..            $25,000 $25,$25,000            $25, 000     $25, 000                   $22,500

Total expended------------------                       25,000      25, 000            25,000           25,000                 22, 500

Allotted- ------------------....                       25, 000     25, 000            25, 000          22, 500       .


Balance unexpended July 1, 1943_---------                                                        ----                     $22, 500
Gross amount expended-_______------------$42,                                                          900
Less reimbursements collected_--------------------------                                           20, 400
                                                                                                                           22, 500

Amount allotted in July 1944--------------_                                                                      -         22, 500
Amount available during fiscal year 1945_-- -                                    ---------                                 22, 500

Amount that can be profitably expended in fiscal year ending June 30,
    1946, for maintenance 1_-
                           --                               ---    ____-     _       ___-________-          -              25, 000
  I Exclusive of available funds.

       5. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

  The cost of work during the fiscal year was $6,030.60. The expendi-
tures were $6,240.26. The balance unexpended June 30, 1944, $9,243.69,
plus an allotment of $18,000 made during July 1944, a total of




           616634-45-pt. 1, vol. 1-                     45
706           REPORT OF CHIEF OF ENGINEERS,                                       U. S. ARMY,                    1944

$27,243.69, will be applied as needed during the fiscal year 1945 to pay-
ment of expenses incurred under this heading. The additional sum of
$32,500 can be profitably expended during the fiscal year 1946.
                                             Cost and financial summary

Cost of new work to June 30, 1944_                                                              _
Cost of maintenance to June 30, 1944_-                                 --------                                   $353, 470. 31

       Total cost of permanent work to June 30, 1944                                  ------------                    353, 470. 31
Plus accounts receivable June 30, 1944---      ----------                                                                  111. 68

           Gross total costs to June 30, 1944_------                                                ---               353, 581. 99

Net total expenditures_------------                                                          ----                     353, 581. 99
Unexpended balance June 30, 1944_                           -                             .-------------                9, 243. 69

           Total amount appropriated to June 30, 1944                             --------------                      362, 825. 68


    Fiscal year ending June 30                 1940             1941               1942                   1943             1944

C ostofnew work .-                              - - --.-    - - - --.--      . . .. . . . .
                                                                          --..                                          .. .. .
Cost of maintenance .........------------.   $26,318.15     $56, 277.82 $19,141.75 $22, 557.34                            $6, 030.60

Total expended--------------                  26, 377. 39   55, 882. 20           20, 340.51         22, 755. 15            6, 240. 26

Allotted.........---------------------        37, 000. 00   45, 000. 00            5, 700. 00        32, 000. 00...............



Balance unexpended July 1, 1943_---    ---------            -                                                         $15, 483. 95
Gross amount expended --------------------------- $13, 282. 30
Less reimbursements collected---------------------- 7, 042. 04
                                                                                                                        6, 240. 26

       Balance unexpended June 30, 1944--                                                                               9,243. 69
Outstanding liabilities June 30, 1944-----------                                                                  -     2,095. 86
      Balance available June 30, 1944_--------                                                        -           -     7, 147.83
Accounts receivable June 30, 1944_---------                                                          ----                  111. 68
     Unobligated balance available June 30, 1944----------------7, 259. 51
Amount allotted in July 1944.___.-__  -   ----------            18, 000. 00
           Amount available during fiscal year 1945                         -----------------                          25, 259. 51

Amount that can be profitably expended in fiscal year ending June
   30, 1946, for maintenance                  1------------....--------.........                                       32, 500. 00
  1
      Exclusive of available funds.
                   RIVERS AND HARBORS--VICKSBURG,                                                 MISS., DISTRICT                              707
6. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                       SUBMITTED

                                                                             For last   Cost and expenditures to Estimated
                                                                           full report        June 30, 1944      amount re-
                         Name of project                                   seeReport
                                                                               Annual                             quired to
                                                                                       Reportquired                      to
                                                                               for-     New work Maintenance complete


1. Little Missouri River, Ark .-------------------- 1873                                        $19, 991.94----------------(1)
2. Bayou Dorcheat, Loggy Bayou, and Lake
       Bisteneau, La ----------------------------.                              1887               5, 000. 00     .- --             ---       (1)
3. Bayou Pierre, La---__-           -- ------                                  1887               8, 600.00 ---       -------                (1)
4. Little River, La.2----- _                 -------                           1890               2, 500. 00 ----------                      (1)
5. Rondeway and Vidal Bayous, La_                     -----                    1892               2,000.00--------------                     (1)
6. Cane River, La -_._------------------------                                 1910               2, 500.00          $1, 999. 50             (1)
7. Little Tallahatchie River, M iss.___ .- ... .                               1913              19, 000.00 ._- -__ _ _- -                   (1)
8. Sulphur River, Ark. and Tex.2 .........                        --.__..      1919              45, 988.99---         ---- __-(1)
                                  - ..
9 . B e ar C r eek , M is s - . .. - -...- ..-   -
                                                 ...  -..   ...   .             19 2 0             3 , 34 6 . 6 2      2 , 0 8 6 . 16         (1)
10. Tehula Lake, Miss__ --                                                      1921
                                                                         .--------                19, 384. 89         26, 585. 08             (1)
11. Bayou Bartholomew, La. and Ark.3 4.........                                 1931              45, 873. 53         42, 857.25              (1)
12. Saline River, Ark.2- 4                                                      1931              26, 900. 00         12, 791.67              (1)
13. Steele and Washington        3  - - Bayous
                                          -     - - and  - - Lake
                                                                -             -
       Washington, Miss. 4                                                      ]
                                                                                1931            19, 049.81               8,000. 00             $40, 000
14. Yalobusha River, Miss.25               __             _           _         1937             7,000. 00              15. 936. 38            (1)
15. Tallahatchie and Coldwater Rivers, Miss...                                  1939            43, 481.48             173, 066.02             (1)
16. Big Black River, Miss.'- 7_-                  -__ _              -          1895            15, 000.00-----                --.-            (1)
17. Bayous D'Arbonne and Corney, La.7 .........                                 1941            19, 000. 00             37,803. 88             (1)
18. Tensas River and Bayou Macon, La_ --------                                  1942            38, 366. 57             35, 352. 16          (8) (0)
19. Boeuf River, La ----------------------------
                                       ........           .......               1942            30, 000. 00            103, 736. 88         (8) (10)
20. Yazoo River, Miss_ --------------------                                     1942           359, 660. 70            480, 605.04           (1) (s)
21. Big Sunflower River, Miss               --------------------                1942           560, 026. 65            459, 327. 90         (8) (10)
22. Mouth of the Yazoo River, Miss_ -----------                                 1942        1, 179, 210.87             123, 271.05          (1) (8)

  1 Completed.
  2 Abandonment recommended in H. Doc. No. 467, 69th Cong., 1st sess.
  3 Abandonment recommended in H. Doc. No. 1692, 64th Cong., 2d sess., and H. Doc. No. 467, 69th
Cong., 1stsess.
  4 Channels adequate for existing commerce. Abandonment recommended in H. Doc. No. 1694, 64th
Cong., 2d sess., and H. Doc. No. 467, 69th Cong., 1st sess.
  5See report of Mississippi River Commission for operations in connection with the Yahoo Basin flood-
control project including channel clearing and rectification and New Grenada Reservoir on Yalobusha
River.
  8 See report of the Mississippi River Commission for opelations in connection with the Yazoo Basin flood-
control project, including Sardis Dam and Reservoir on Little Talahatchie River, Arkabutla Dam, and
Reservoir on Coldwater River, and channel clearing on Tallahatchie and Little Tallahatchie Rivers.
  7 No commerce reported.
  8 No funds available and no work proposed for fiscal years 1944 and 1945.
  9 Local cooperation required.
  10 Curtailment recommended in H. Doc. No. 467, 69th Cong., 1st sess.


              7. PLANT ALLOTMENT, VICKSBURG, MISS., DISTRICT

                                                  Cost and financial summary
Undistributed costs June 30, 1944 -------------------------- $264, 531. 60
Plus accounts receivable June 30, 1944_-  - ----------          7, 724. 78
      Gross total costs to June 30, 1944_    - ------                                                     _272,                           256. 38
Minus accounts payable June 30, 1944_ -------        __---                                                         -         -        13, 343. 11
      Net total expenditures_     _-----------------------258,                                                                         913. 27
Unexpended balance June 30, 1944_--     __----------.---                                                                          114, 207. 52
             Total amount appropriated to June 30, 1944--------------373, 120. 79


      Fiscal year ending June 30                      1940                 1941                  1942               1943                   1944


Total expended:-.................--                $54,198.68         -$16, 944.62       -$71,     681.73     -$16, 306. 57               $12, 975. 89

Allotted_---        -------------------              15,000.00 --------             -----------------------------                          72,000.00
708         REPORT OF CHIEF OF ENGINEERS,                               U.   S. ARMY,             1944

Balance unexpended July 1, 1943    -                                                                $199,183.41
Deductions on account of revocation of allotment_                                                     72, 000. 00

       Net amount to be accounted for-    -------------------                                        127, 183. 41
Gross amount expended_------------------------      $400, 931. 04
Less reimbursements collected--------------------    387, 955. 15
                                                                                                         12, 975. 89

      Balance unexpended June 30, 1944___--------                                                    114, 207. 52
Outstanding liabilities June 30, 1944_--------                                        ---              9, 200. 84

      Balance available June 30, 1944_-------                                               ---      105, 006. 68
Accounts receivable June 30, 1944____                                                                  7, 724. 78

         Unobligated balance available June 30, 1944                     --------------              112, 731. 46

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                                   Date trans-      Document          Recommen-
              Locality                   Authorization act          mitted to         No.               dation
                                                                    Congress

Jefferson-Shreveport     Waterway,      River and Harbor
  Tex. and La., enlarging existing        Act, Aug. 30, 1935.
  project and establishing reser-
  voirs on Cypress River above
  Jefferson.'
Jefferson-Shreveport     Waterway,      River and Harbor ........
  Tex. and La., thence via Red            Act, Aug. 26, 1937.
  River to Mississippi River, includ-
  ing Reservoirs in Cypress and
  Black Cypress Rivers.'
Jefferson-Shreveport     Waterway,      River and Harbor         -----------
  La. and Tex., thence via Red            Act, June 20, 1938.
   River to Mississippi River, sur-
  vey for navigation, flood control,
  power and irrigation, including
  water-supply reservoirs in Cy-
  press and Black Cypress Rivers.'
Mississippi River between Cairo,        Flood Control Com-         Mar. 20, 1944   H. 509, 78th      Favorable.
  Ill., and Baton Rouge, La., for         mittee resolution,                         Cong., 2d
   12-foot channel (navigation and        Mar. 8, 1943.                              sess.
  flood control).'
     D o.. . .- .- . .           .--    Commerce Commit- ..... do.......           - -.-
                                                                                       -     -do......     Do.
                                         tee resolution, Mar.
                                         9, 1943.
Ouachita River System, La. and          Commerce Commit-
Ark., and connecting waterways,         tee resolution, Feb.
singly or together, for navigation,     8, 1939; Flood Con-
flood control and irrigation.           trol Committee res-
                                          olution, Jan. 26,
                                          1939; Rivers and
                                          Harbors Commit-
                                         tee resolution, Jan.
                                          24, 1939.
Red River, La., Ark., Okla., and        Rivers and Harbors
Tex., for navigation, flood con-         Committee resolu-
trol, water power and irrigation         tion, Feb. 25, 1938.
  (report being prepared by the
lower Mississippi Valley Divi-
sion).
Red River, La., Ark., Okla., and        Commerce Commit-
  Tex., and connecting waterways,        tee resolution, Feb.
singly or together, for navigation       8, 1939; Flood Con-
flood control and irrigation.'           trol Committee res-
                                          olution, Jan. 26,
                                          1939; Rivers and
                                          Harbors Commit-
                                          tee resolution, Jan.
                                          24, 1939.
Sulphur River, Tex. and Ark., im-       River and Harbor
provement for navigation, flood          Act, June 20, 1938.
control, and water power.'
Yazoo River, Miss ...............       Rivers and Harbors         Mar. 27,1944 _U---------------    Unfavorable.
                                          Committee resolu-
                                          tfion, May 29,1940.
  1 Combine with report on Red River, La., Ark., Okla., and Tex., for navigation, flood control, power,
and irrigation, requested by resolution of the Committee on Rivers and Harbors, House of Representatives,
adopted Feb. 25, 1938, which is being prepared by the lower Mississippi Valley Division.
  2 Field report was made by the Mississippi River Commission.
            FLOOD CONTROL-      VICKSBURG,    MISS., DISTRICT         709
                  8. CALION, OUACHITA RIVER, ARK.

   Location.-The work covered by this project is on the west bank of
the Ouachita River near Calion, a small town in Union County, Ark.,
about 307 miles above the mouth of Black River and 13 miles northeast
of El Dorado, Ark. (See U. S. Geological Survey map, scale
1: 500,000.)
   Existing project.-The plan of improvement provides for the pro-
tection of the town of Calion, Ark., by the construction of an earth
loop levee, 1.36 miles in length, extending around the town and tying
to the existing embankment of the Chicago, Rock Island & Pacific
Railroad at each end, together with a floodgate and small pumping
plant to take care of interior drainage, at an estimated cost of $50,000
for construction and $5,200 for lands and damages. The existing
project was authorized by the Flood Control Act approved August
18, 1941. (See H. Doc. 427, 76th Cong., 1st sess., which also contains
the latest published map.)
   Local cooperation.-See page 7 for requirements. Local interests
have signified their approval of the project.
   Operationsand results during fscal year.-None.
   Condition at end of fiscal year.-Work has not been started.
   Proposed operations.-The sum of $8,000 allotted in July 1944 will
be applied to completion of surveys, soil investigations, and plans and
specifications.
   No additional funds can be profitably expended during the fiscal year
1946 in view of the existing Federal policies on wartime construction.
                   9. BLACK BAYOU RESERVOIR, LA.

   Location.-The work covered by this project is on Black Bayou in
Caddo Parish, La., 40 miles above the mouth of Twelve Mile Bayou,
and about 25 miles northwest of Shreveport, La.
   Existing project.-The plan of improvement provides for the con-
struction of an earth fill dam 1,350 feet long at the top, rising 24.8 feet
above the stream bed, with a reservoir providing for the controlled
sforage of 26,000 acre-feet, of which 7,500 acre-feet will be utilized as
a conservation pool. The outlet works are located over the present
channel of Black Bayou 260 feet from the right end of the dam, and
an uncontrolled tilting gate spillway 400 feet wide extends from a
point 260 feet from the right end of the dam. The reservoir will con-
trol 220 square miles or about 52 percent of the entire drainage area
of Black Bayou and provides flood storage for the protection of the
population and lands below. The existing project was authorized by
the Flood Control Act approved June 22, 1936. The revised estimate
of cost for construction is $289,000.
   Local cooperation.-See page 7 for requirements. Assurances that
local interests would assume all land and damage costs were received
by the Department in June 1939.
   Operations and results during fiscal year.-None.
   Conditionat end of fiscal year.-Work has not been started.
   Proposed operations.--The unexpended balance at the end of the
fiscal year, $20,000, will be applied to the initiation of detailed plans
and specifications.
710                REPORT OF CHIEF OF ENGINEERS,                                                           U. S. ARMY, 1944

   No additional funds can be profitably expended during the fiscal
year 1946 in view of the existing Federal policies on wartime construc-
tion.
                                                         Cost and financial summary
Cost of new work to June 30, 1944_                                                           __                                       .
Cost of maintenance to June 30, 1944_                                                             .
Unexpended balance June 30, 1944 ------------------------------
                                    .                                                                                                                      $20, 000
               Total amount appropriated to June 30, 1944                                                   -----------------                                20, 000


     Fiscal year ending June 30                               1940                    1941                    1942                    1943                    1944

Cost of new work---------------...........------------....-------------.............---............                                      ....------------.-------------.............
Cost    maintenance-...--.
Tot ofexpaien   e      .................................                                    ............................................
Total expended ......... ......
Allotted.....-----------------                              --------------                          -------------------- $20, 000                          ......------------


Balance unexpended July 1, 1943                                       ---------                   ----------------------                                   $20, 000

Balance unexpended June 30, 1944_                                                   - _-.----.--------20,.000
Amount (estimated) required to be appropriated for completion of exist-
ing project 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 269, 000
   1 Exclusive of available funds.

                                  10. LITTLE MISSOURI RIVER BASIN, ARK.

   Location.-The Little Missouri River rises in the southeastern cor-
ner of Polk County, Ark., on the southern slope of the Missouri Moun-
tains and flows in a southeasterly direction a distance of 147 miles
in a tortuous course to enter the Ouachita River 27.6 miles above
Camden, Ark.
   Terre Noire Creek rises in the Athens Plateau, midway between
Arkadelphia and Amity in Clark County, and flows in a general
southeasterly direction a distance of about 45 miles to enter Little
Missouri River on the left bank 2 miles above the mouth of the parent
stream.
   Ozan Creek, formed by the junction of North Fork, Middle Fork,
and South Fork near Blevins, in Hempstead County, flows in a general
northeasterly direction a distance of about 25 miles to join Little
Missouri River on the right bank at mile 73.2 above the mouth.
   Existing project.-The Flood Control Act approved August 18,T941,
approved the plan for the Narrows Reservoir for flood control and
other purposes on the Little Missouri River, Arkansas, and for local
flood protection on the main river below Murfreesboro, Ark., and on
the Terre Noire and Ozan Creeks, as set forth in House Document
No. 837, Seventy-sixth Congress, third session, and authorized
$3,000,000 for the initiation and partial accomplishment of the project.
   The plan of improvement provides for the construction of the Nar-
rows Reservoir on the Little Missouri River above Murfreesboro, Ark.,
with a gross storage capacity of 410,000 acre-feet and a power plant at
                  FLOOD       CONTROL--VICKSBURG,                   MISS.,        DISTRICT                      711
the dam site with an initial installation of hydroelectric generating
facilities having a capacity of 15,000 kilowatts and with provisions
for future enlargement of those facilities; channel clearing and snag-
ging of the Little Missouri River and the excavation of 11 cut-offs
between the mouth and mile 70; on Terre Noire Creek snagging of
the channel between the Missouri Pacific Railroad crossing and the
mouth, the enlargement of 0.9 mile of silted creek channel, the repair
of levee crevasses in the side levees, and the construction of required
drainage ditches; and clearing, snagging, and enlargement of the
channel of Ozan Creek between the lower end of the existing drainage
ditches to the mouth.
   The following is a list of the individual projects considered in the
approved plan:

                                                                                      Estimated cost
              Location                      Type of protection                        Etme          cs
                                                                         Federal          Local             Total

Narrows Reservoir near Murfrees-
  boro, Ark.
                                       Reservoir and power plant...__   $6,470,000 -.--            :-..--   $6, 470,000
Little Missouri River, Murfrees-       Channel improvement-......          230, 000          $10, 000          240,000
  boro, Ark., to the mouth.
Terre Noire Creek, Ark      .....---------- Channel improvement and        110,000            10,000           120,000
                                        repairs to levees.
Ozan Creek, Ark ....----------------   Channel improvement .....            28,000             5,000            33, 000


   Local cooperation.-See page 7 for requirements. On Ozan and
Terre Noire Creeks, drainage districts empowered to act for local
interests have signified their willingness to cooperate.
   Operationsand results during fiscal year.-The work of design and
preparation of contract drawings and specifications for Narrows Dam
and hydroelectric power plant were carried on during the year, and
foundation explorations were made.
   Office studies were carried on for the projects for Ozan Creek, Terre
Noire Creek, and Little Missouri River below Murfreesboro, Ark., in
connection with the preparation of detailed plans.           Surveys and
borings in this connection were completed.
   Costs during the fiscal year were $76,613.38 and expenditures were
$65,434.10 for new work.
   Condition at end of fiscal year.-Narrows Reservoir: Surveys and
mapping of the reservoir area are complete; appraisals of the value
of cinnabar mines and mineral rights in the reservoir area are com-
plete; preparation of plans and specifications and foundation explo-
rations are in progress.
  STerre Noire Creek: Surveys, mapping, and soil investigations are
complete. Plans are being prepared.
   Ozan Creek and Little Missouri River below Murfreesboro: Sur-
veys, mapping, and soil investigations are complete. Plans are being
prepared.
   Total costs to June 30, 1944, were $137,595.74, and total expenditures
were $129,828.45.
712          REPORT OF, CHIEF OF ENGINEERS, U. S. ARMY, 1944

   Proposed operations.-The balance unexpended at the end of the
fiscal year, $209,221.55, plus $11,000 allotted in July 1944, a total of
$220,221.55, will be applied as follows:
Accounts payable June 30, 1944_ ----------------                                                             $7, 767. 24
New work:
    Narrows Reservoir-Completion of final designs,
      and construction plans_ _---------$196,                                                482. 99
    Initiation and completion of plans and
       designs for-
         Ozan Creek_ __-------                 $2, 076. 15
         Terre Noire Creek--------4,                460. 19
         Little Missouri River below Mur-
            freesboro, Ark_ _-----               9, 434. 98
                                                                                          15, 971. 32
                                                                                                            212, 454. 31

                    Total for all work_                     _ __--- _---------                              220, 221. 55
   No additional funds can be profitably expended during the fiscal
year 1946 in view of the existing Federal policies on wartime con-
struction.
                                       Cost and financial summary
Cost of new work to June 30, 1944_ -----------                                                          $137, 595. 74
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 3Q, 1944-..                                            ..--- 137, 595. 74
Undistributed costs June 30, 1944___           --------                                                   --   0. 05
      Net total cost to June 30, 1944                                                                        37, 595. 69
                                                                                                            1-------------------------
Minus accounts payable June 30, 1944_--                                ---------                               7, 767. 24

      Net total expenditures--
                            __      ------------                                                            129, 828&45
Unexpended balance June 30, 1944---           ----------                                                    209, 221. 55
          Total amount appropriated to June 30, 1944-------------                                           339, 050. 00

    Fiscal year ending June 30             1940               1941           1942              1943               1944

Cost of new work        ......    .    .          -   -------------
                                                         .--.- .....       $10, 860. 04      $50,122.32          $76, 613. 38
                    .......-......-
Cost of maintenance---                                  .         ---------------------------------------
Total expended ...-..........         __     _        ------------           8, 574. 05       55, 820. 30         65, 434. 10
Allotted........--------------------------------------------100,00000                        185, 000 00          54,050.00


Balance unexpended July 1, 1943_--------           ---                                                  $220, 605. 65
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942_-----------                ----                                                      54, 050. 00

       Amount to be accounted for ---------------------------                                               274, 655. 65
Gross amount expended_-------                   ---  $69, 714. 87
Less reimbursements collected ---------------------    4, 280. 77
                                                                                                             65, 434. 10
      Balance unexpended June 30, 1944----------------------                                                209, 221. 55
Outstanding liabilities June 30, 1944-------------- $12, 643. 72
Amount covered by uncompleted contracts --------    103, 532. 72
                                                                                                            116, 176. 44
          Balance available June 30, 1944_ ------.----                                                       93, 045. 11
                FLOOD CONTROL--VICKSBURG,                  MISS., DISTRICT          713
Amount allotted in July 1944-_ -----------------------------                 $11, 000. 00

        Amount available during fiscal year 1945          ---------------    104, 045. 11
Amount (estimated) required to be appropriated for completion
of existing project 1       ----------------                 6, 487, 950. 00
1Exclusive of available funds.

                        11. WALLACE LAKE RESERVOIR, LA.

   Location.-The work covered by this project is in Red River Basin,
on Cypress Bayou, Caddo and De Soto Parishes, La., 66 miles above
the mouth of Bayou Pierre and about 14 miles southeast of Shreve-
port, La. (See U. S. Geological Survey State Map, scale 1: 500,000.)
   Existing project.-The plan of improvement provides for the con-
struction of an earth-fill dam 4,940 feet long at the top, including 644
feet of spillway and outlet works, rising 48 feet above the stream bed,
with a reservoir providing for storage of 96,200 acre feet, including a
conservation pool of 7,600 acre feet. The outlet works and uncon-
trolled spillway are centered about 1,250 feet north of the south abut-
ment. The reservoir will control 260 square miles, or about 20 per-
cent of the total drainage area of Bayou Pierre, Cypress Bayou, and
tributaries combined, and will afford complete protection against
floods for an area of about 90,000 acres of valley below the dam. The
existing project was authorized by the Flood Control Act approved
June 22, 1936 (H. Doc. No. 378, 74th Cong., 2d sess.). The estimate
of cost, revised in 1941, is $1,070,000 for construction and $24,000 for
preparation of land titles.
   The latest published map is in House Document No. 378, Seventy-
fourth Congress, second session.
   Local cooperation.-See page 7 for requirements. Local interests
have agreed to furnish necessary lands and flowage rights at a nom-
inal cost to the United States.
   Operations and results during fiscal year.-No construction work
was done in accordance with existing Federal policies on wartime
construction. The completed portions of the dam were cared for
during the year. The work of design, drawings, and specifications
was carried on in preparation for resumption of construction work
when conditions permit. Costs during the fiscal year were $3,381.30
for new work and expenditures were $3,309.55.
   Condition at end of fiscal year.-The main portion of the dam, work
on which was started August 2, 1942, was completed during the fiscal
year 1943 with the exception of the closure section and reinforcing
of the railroad embankment. Gravel and riprap stone have been
stockpiled for use in making the closure at such time as the work can
be resumed. Acquisition of rights-of-way for the reservoir is about
50 percent complete. Work was suspended on January 9, 1943, in ac-
cordance with existing Federal policies on wartime construction. The
entire project is about 94 percent complete.
   Total costs to June 30, 1944, were $950,618.95 for new work. Ex-
penditures were $950,524.79.
714         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

   Proposed operations.-The balance unexpended at the end of the
fiscal year, $13,475.21, will be applied as follows:
Accounts payable June 30, 1944 ----------     __--------.-----$94.                                                           16
New work:
    Stream gaging, office studies, and plans and speci-
      fications_   --------------------------------- $12, 881.05
    Preservation of uncompleted dam------------------              500. 00
                                                                                                                  13, 381. 05
         Total for all work_-- .                 ---------------------                                            13, 475. 21
  Additional funds in the amount of $180,000 can be profitably ex-
pended during the fiscal year 1946 to complete the project.
                                      Cost and financial summary
Cost of new work to June 30, 1944                                     _   _..._$950,                                  618. 95
Cost of maintenance to June 30, 1944_._
      Total cost of permanent work to June 30, 1944------------950, 618. 95
Minus accounts payable June 30, 1944_---------               ---     94. 16
      Net total expenditures -------------------------------
                                _                                                                                950, 524. 79
Unexpended balance June 30, 1944_ ----------------                                                                13, 475. 21
         Total amount appropriated to June 30, 1944                          --------------                      964, 000. 00


   Fiscal year ending June A0             1940                 1941           1942                1943                1944

Cost of new work................       $21,749. 79       $21,140. 63       $503, 210.93        $366, 510. 50          $3, 381. 30
Cost of maintenance ...
Total expended.------------              24, 505.96        22, 076.68       466, 931. 16        402, 594.   52         3, 309. 55
Allotted........--------------------------------         182,000.00         400, 000.00        -130,000.00-----..


Balance unexpended July 1, 1943 ----------------------------                                                     $16, 784. 76
Gross amount expended -------------------------- $3, 966. 88
Less reimbursements collected--- --------               657. 33
                                                                                                                   3, 309. 55
      3alance unexpended June 30, 1944_-                                                            ..-------- 13, 475. 21
Outstanding liabilities June 30, 1944_---------                                                   ---              403. 20
         Balance available June 30, 1944_-------                                                  ---             13, 072. 01
Amount (estimated) required to be appropriated for completion
Sof existing project 1-                         __-
                                                 -        --                     -         -            -        180, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work 1-------------                                                                      180, 000. 00
  1Exclusive of available funds.

                                      12. BAYOU PIERRE, LA.

  Location.-The work covered by this project is in Red River Basin
below Shreveport, La., along the channel of Bayou Pierre from Bayou
Wincey to the mouth at Grand Ecore, La. (See U. S. Geological
Survey State map, scale 1: 5001000.)
  Existing project.-The plan of improvement provides for the widen-
ing of the channel at intervals from Bayou Wincey, mile 30 to mouth
                    FLOOD CONTROL--VICKSBURG,                                     MISS.,          DISTRICT                       715

at Grand Ecore, La., consisting of 12.9 miles of channel widening
and 29.7 miles of snagging. The project will reduce flood damage and
improve sanitary and living conditions over a wide area. The exist-
ing project was authorized by the Flood Control Act of June 22, 1936
 (H. Doc. No. 378, 74th Cong., 2d sess.). The estimate of cost for
construction is $300,000. The estimated annual cost of maintenance is
$13,500. The latest published map is in House Document No. 378,
Seventy-fourth Congress, second session.
   Local cooperation.-See page 7 for requirements. The require-
ments have been fulfilled.
   Operations and results during fiscal year--Maintenance.--Work on
the collection of hydraulic data was continued by hired labor. Main-
tenance work was begun on October 16, 1943, and 76 acres were cleared
and 18.7 miles of channel were snagged, between miles 10 and 29.7.
Work was suspended February 5, 1944, pending favorable water stages.
   Costs and expenditures during the fiscal year were $19,950.50 for
maintenance.
   Condition at:end~of fiscal year.-New work under the existing project
has beei completed. Maintenance work, consisting of channel clear-
ing and snagging, has been accomplished as needed to assure effective
operation of the project. Collection of hydraulic data was in progress.
 ' The costs and expenditures to June 30, 1944, were $261,000 from
regular funds and $38,529.13 from Emergency Relief funds, a total
of $299,529.13 for new work; the costs and expenditures from regular
funds for maintenance were $24,414.80.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $17,585.20, will be applied to maintenance, channel clear-
ing, and snagging with rented tractors, 2 months (July and August
1944).
   The additional sum of $13,500 can be profitably expended during the
fiscal year 1946, to be applied to maintenance, channel clearing and
snagging.
                                            Cost and financial summary
Cost of new work to June 30, 1944----------------------       1$299, 529. 13
Cost of maintenance to June 30, 1944-------------------------    24, 414. 80
          Total cost of permanent work to June 30, 1944-----------                                               1   323, 943. 93

Net total expenditures-----  ------------------------------ 1 323, 943. 93
Unexpended balance June 30, 1944---------------------------17, 585. 20
          Total amount appropriated to June 30, 1944                                  ------------- 1 341, 529. 13

    Fiscal year ending June 30                    1940              1941              1942               1943                 1944

Cost of new work-------------....                                           ..-----------------
                                                                                 -----------------------------------....

Cost of maintenance        ....----------.........--------------   $3, 587.35          $526. 09           $350.86           $19, 950. 50
Total expended---------. --------               $1, 509. 20         3,587. 35           662.08              214.87           19,950.50

A llotted.----------------------15
       n..3.1           E.......                    00( . 00       13, 500.00 -_-- --- -- - - - - - - 13, 500.       ;00I


  ' Includes $38,529.13 Emergency Relief funds.
716        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,              1944

Balance unexpended July 1, 1943     ---           --
                                                   -$37,                   535. 70
Gross amount expended--- --------                  $22, 227. 23
Less reimbursements collected--- ------------------ 2, 276. 73
                                                                        19, 950. 50

        Balance unexpended June 30, 1944   ----------------------_17,      585. 20
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2--         _             _ _           13, 500. 00
2 Exclusive of available funds.

                         13. BAYOU BODCAU RESERVOIR, LA.

   Location.-The work covered by this project is in Red River Basin
on Bayou Bodcau in Bossier Parish, La., 72 miles above the mouth of
Loggy Bayou and 35 miles northeast of Shreveport, La. (See U. S.
Geological Survey State map, scale 1: 500,000.)
   Existing project.-The plan of improvement provides for the con-
struction of an earth-fill dam rising 76 feet above the stream bed with
a reservoir providing for a controlled storage capacity of 297,900 acre-
feet. The outlet works are located in the south abutment, and an un-
controlled spillway is located on the north abutment. The reservoir
will control 656 square miles, or 53 percent of the entire drainage area
of Bayou Bodcau. The construction of a floodway for the diversion
of Bayou Bodcau and Cypress Bayou to improve flood protection was
authorized by the Flood Control Act approved June 22, 1936. This
authorization was modified by the Flood Control Act approved June
28, 1938, which authorized the construction of a reservoir and other
flood-control works, in lieu of the construction of a floodway for the
diversion of Bayou Bodcau and Cypress Bayou., La., to improve flood
protection, and further modified by the War Department Civil Appro-
priation Act approved June 28, 1939, which provided that the reservoir
and other flood-control works on Bayou Bodcau and Cypress Bayou,
La., authorized by the Flood Control Act approved June 28, 1938, shall
be constructed in accordance with the revised plans and cost estimates
in the Office, Chief of Engineers. The revised estimate of cost is
$2,752,000 for construction and $180,000 for lands and damages.
   The latest published map is in House Document No. 378, Seventy-
fourth Congress, second session.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Specifications and con-
tract drawings for the dam were reviewed and revised.
   Cost of new work during the fiscal year was $7,910.78, with expend-
itures of $5,658.36.
   Condition at end of fiscal year.-Completion of specifications, and
contract drawings await final revision of the Board of Consulting
Engineers and the Chief of Engineers. Foundation borings, soil
analysis, land appraisals, preparation of tract maps for the damsite
area, and model study of the intake have been completed. Total costs
to June 30, 1944, were $189,264.82, and expenditures were $189,034.32
for new work.
   Proposed operations.-The balance unexpended, $9,965.68, plus an
allotment of $2,000 made in July 1944, a total of $11,965.68, will be
                           FLOOD CONTROL---VICKSBURG,                                 MISS.,        DISTRICT                       717
applied to completion of construction plans and specifications, and
studies in connection with malaria control.
   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                       Cost and financial summary
Cost of new worlekto June 30, 1944_--
                                  ....                                    ---------                                    $189, 264. 82
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-----------                                                          189, 264. 82
Minus accounts payable June 30, 1944_ - - ---------                                                                          230. 50
                            _ _------
      Net total expenditures--     *---                                                                                 189, 034. 32
Unexpended balance June 30, 1944 ----------------------------                                                             9, 965. 68
             Total amount appropriated to June 30, 1944---------                                                        199, 000. 00


     Fiscal year ending June30               1940                 1941                  1942                1943               1944

Cost of new work ...............         $87,164. 91            $63,807. 46            $1,093. 21         $2,941.91           $7, 210. 78
Cost of maintenance---
                    .----              .-        ..        ..        ..         ..       ..         ..------------------------------------------
                -----------------
Total expended ...   .                      84, 702.88          66, 177. 12             1,501.23           4,007. 25            5,658.36

Allotted ...............                 .......---------------..-740,000. 00
                                   ..----------------



Balance unexpended July 1, 1943                                                                                         $15, 624. 04
Gross amount expended--- ---------                  $5, 948. 11
                             ----------------------
Less reimbursements collected_                          289. 75
                                                                                                                           5, 658. 36

      Balance unexpended June 30, 1944                                                                                        965. 68
                                                                                                                           9,---------------9
Outstanding liabilities June 30, 1944_--------                                                               ---              445. 00

     Balance available June 30, 1944_----                                                           -___                   9, 520. 68
Amount allotted in July 1944_------------                                                                          -       2, 000. 00

             Amount available during fiscal year 1945----------                                                          11, 520. 68

Amount (estimated) required to be appropriated for completion
  of existing project 1_-       -  - _ ______
                                        -     --              2, 731, 000. 00
1Exclusive of available funds.

             14. BAYOU BODCAU, RED CHUTE, AND LOGGY BAYOU, LA.

  Location.-The work covered by this project is in Red River Basin,
below the site of the proposed Bayou Bodcau Reservoir, on Bayou
Bodcau, the lower portion of Bayou Bodcau known locally as Red
Chute, and Loggy Bayou, in Bossier, Bienville, and Red River Par-
ishes, La. (See U. S. Geological Survey State Map, scale 1: 500,000.)
   Existing project. The plan of improvement provides for continu-
ous clearing and snagging on Bayou Bodcau and Red Chute between
miles 14.1 and 57.0 except for bendways at cut-off locations, where
snagging only will be done, the construction of three channel cut-offs
having a total length of 1.36 miles, and enlargement of 1.9 miles of
the channel of Loggy Bayou between mile 3.9 and mile 6.4.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941, which modified the project for the Bayou
718            REPORT OF CHIEF OF ENGINEERS,                                                  U. S. ARMY,              1 944

Bodcau Reservoir, La., authorized by the act of June 22, 1936, as
modified by the acts of June 28, 1938, and June 28, 1939, to provide for
the channel improvements described above.
   The estimated cost is $198,000 for construction.
   Local cooperation.-Seepage 7 for requirements.
   Operations and results during fiscal year.-Surveys, borings, and
mapping were completed and preparation of specifications and draw-
ings for channel improvenent was initiated.
   Costs during the fiscal year were $6,336.82 and expenditures were
$6,306.10 for new work.
   Condition at end of fiscal year.-The specifications and drawings
for the channel improvement are 50 percent complete. Surveys, bor-
ings, and mapping are complete. The total costs to June 30, 1944,
were $6,336.82, and the expenditures were $6,306.10 for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $3,193.90, will be applied as follows:
Accounts payable June 30, 1944_-                                                                                                  $30. 72
New work: Completion of detailed plans and specifications for channel
improvement                                                                                                                    , 163. 18
                                                                                                                               3-----------------------------
            Totalforall work-------------------------------------3,                                                               193. 90
   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                                         Cost           finanoiarl summary
                                                                     and&
Cost of new work to June 30, 1944-_-------------                                                                              $6, 336. 82
Cost of maintenance to June 30, 1944__
      Total cost of permanent work to June 30, 1944-------------6, 336. 82
Minus accounts payable June 30, 1944- ---------         -----       30. 72
      Net total expenditures_ _____                                                  ___----------6,                              306. 10
Unexpended balance June 30, 1944_   _                                                     -----------------                    3, 193. 90
            Total amount appropriated to June 30,                                        1944 ---------------                  9, 500. 00

      Fiscal year ending June 30                                1940          1941             1942             1943              1944


Cost of new work-------------.--------------------------------------------------------$6,336.82
Cost of maintenance-----------------------------      ------------------         -----------------
Total expended----------..........------........                ------------------------------------------ -----                   6,306.10
Allotted-         ---------------------------------------------------------                                         $6, 000        3,500.00


Balance unexpended July 1, 1943---             ----------                                                                     $6, 000. 00
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942_--.    _.----------------        --                                                                   3, 500. 00
       Amount to be accounted for-----------------------------                                                                 9, 500. 00
Gross amount expended_- -----          __ -----        $6, 368. 82
Less reimbursements collected__ .--.  ---------             62. 72
                                                                                                                               6, 306. 10

            Balance unexpended June 30, 1944___----.--                                                 ----------              3, 193. 90

Amount (estimated) required to be appropriated for completion of
existing project '---------------------------------------.---- 188, 500. 00
  1   Exclusive of available funds.
                 FLOOD CONTROL-VICKSBURG,                  MISS.,    DISTRICT                   719
                            15. NATCHITOCHES PARISH, LA.

   Location.-The work covered by this project is on the west side of
Red River in Natchitoches Parish, La. (See U. S. Geological Survey
State map, scale 1: 500.000.)
   Existing project.-The plan of improvement provides for the con-
struction of levees on west side of Red River, from about mile 203 to
the existing levee at about mile 178; enlargement of the existing levee
about 5.2 miles in length, and extension of same about 11.1 miles to
Cane River, about 0.8 mile above its mouth; construction of an earth-
fill dam in Cane River and floodgate; and the construction of drain-
age ditches to give protection to approximately 135,000 acres of land
in the Cane Island area from'Red River overflow. The existing proj-
ectwas authorized by the Flood Control Act approved June 22, 1936
 (H. Doc. No. 378, 74th Cong., 2d sess.). The estimate of cost revised
in 1941 is $1,069,100 for construction and $88,100 for lands and
damages.
   The latest published map is in House Document No. 378, Seventy-
fourth Congress, second session.
   Local cooperation.-See page 7 for requirements. Requirements
have been fulfilled as needed.
   Operations and results during fiscal year.-None. Expenditures
were -$50.
   Condition at end of fiscal year.-By hired labor 2,150,500 cubic
yards of material have been placed in 26.6 miles of levee, and under
contract 1,668,363 cubic yards have been placed in 9.6 miles of levee,
totaling 3,818,863 cubic yards in 36.2 miles of levee. By hired labor
388,509 cubic yards of material have been removed in excavating 5.1
miles of diversion channels. Design of Cane River floodgate has been
completed and construction plans have been completed. Restoration
of rain and wave washed levees has been completed. All new work on
this project has been completed with the exception of Cane River dam
and floodgate, which has been indefinitely deferred.
   The cost of new work under the existing project to June 30, 1944,
was $742,764.33, $670,022.37 from regular funds and $72,741.96 from
Emergency Relief funds. Total expenditures were $742,764.33.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $26,312.15, will be applied to repair and preservation of the
completed work and office studies, plans, and specifications.
   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                   Cost and financial summary
Cost of new work to June 30, 1944-__    --             -----------                  1 $742, 764. 33
Cost of maintenance to June 30, 1944_--                   ------------------
        Total cost of permanent work to June 30, 1944          -----------           1   742, 764. 33

Net total expenditures---- -----------                                         _     1 742, 764. 33
Unexpended balance June 30, 1944_ _________            -        -       -       -         26, 312. 15

        Total amount appropriated to June 30, 1944 ------------                      1 769, 076. 48
I Includes $72,741.96 Emergency Relief funds.
720          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                     1944


   Fiscal year ending June 30                  1940           1941             1942                1943                 1944


Cost of new work..------------............
C ost of maintenance
                                            $276, 737.37
                                   . . . .- I ___- - __..
                                                              $7, 846.91
                                                     - -_ -__.......
                                                            - -..... _. _ --
                                                                  - --     -----
                                                                           _ _ ---
                                                                               $10,847.45         $8, 361.19
                                                                                             - - --.....
                                                                                                                .....

Total expended .....----------------       291, 059.70        7, 925. 73      11,509.87            7, 748.77              -$50.00
Allotted                      -.    -. .   .     ...-      --------.
                                                          -27,065.48         137,100.00       -300,000.00       -.


Balance unexpended July 1, 1943                                                                                $26, 262. 15

Net amount to be accounted for_____-         ----                                            __                 26, 262. 15
Gross amount expended_                  ------- -_                                          $190. 32
Less reimbursements collected___ -   --------                                                240. 32
                                                                                                                     - 50. 00
           Balance unexpended June 30, 1944 ----------------------                                              26, 312. 15

Amount (estimated)   required to be  appropriated for completion of
existing project 2-   - - - -   - -   - -     - - - - - -   - - -
                                            __                                                                 300, 000.00
2 Exclusive of available funds.

                                   16. PINEVILLE, RED RIVER, LA.

   Location.-The work covered by this project lies on the left bank of
Red River in Rapides Parish between the crossing of the Louisiana &
Arkansas Railroad at mile 122 and the crossing of the Missouri Pacific
Railroad at mile 124. (See Mississippi River Commission maps, Allu-
vial Valley of the Mississippi River, scale 1: 250,000, and quadrangle
maps, scale 1: 62,500.)
   Existing project.-The plan of improvement provides for the en-
largement of 0.8 mile of levee on the Pineville city front, the enlarge-
ment of 1,500 feet of the Louisiana & Arkansas bridge approach fill,
the construction of 0.6 mile of new levee, and the construction of one
floodgate. It also provides for the enlargement of 0.5 mile of existing
levee in the Rocky Bayou Loop.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941, which modified the project for Grant Parish
below Colfax, La., as authorized by the Flood Control Act approved
June 28, 1938, to provide for construction of the above-described
works.
  The estimate of cost is $159,100 for construction and $10,900 for
lands and damages.
  Local cooperation.-See page 7 for requirements.
   Operations and results during fiscal year.-Office studies in prepa-
ration of plans have been carried on. Surveys and borings in connec-
tion with these plans were completed.
   Cost of new work during the fiscal year was $6,792.91. Expendi-
tures were $6,548.03.
   Condition at end of fiscal year.-Preparation of plans is under way.
Surveys and borings are complete. Total cost of new work to June 30,
1944, was $6,792.91, and expenditures were $6,548.03.
   Proposed operations.--The unexpended balance, $7,451.97, plus an
allotment of $9,000 in July 1944 will be applied as follows:
Accounts payable June 30, 1944_                                                                                   $285. 01
New work: Completion of detailed plans and specifications--------                                               16, 166. 96
           Total for all work-- ------------------------                          _-_-.----16,                          451. 97
                     FLOOD CONTROL---ICKSBURG,                                  MISS., DISTRICT                       721

   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                             Cost and financial summary
Cost of new work to June 30, 1944____-$6,                                                                          792. 91
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-  _  -                                                    6, 792. 91
Undistributed costs June 30, 1944-----------------------------                                                    40. 13

      Net total cost to June 30, 1944__                                                                       6, 833. 04
Minus accounts payable June 30, 1944_                                                                            285. 01

      Net total expenditures_____                                                                             6, 548. 03
Unexpended balance June 30 1944--------------------7,                                                            451. 97
          Total amount appropriated to June 30 1944--------14,                                                     000. 00


    Fiscal year ending June 30                 1940                1941          1942            1943              1944


Cost of new work--.--.......................--------------.....-----------------------------------------           $6, 792. 91
Cost of maintenance ..
Total expended----
               .....---------------------------------------------------------                                       6, 548. 03
Allotted .------------.-------------.---------------------------                                    $9,000          5,000. 00


Balance unexpended July 1, 1943                        -                                                     $9,   000. 00
Amount allotted from War Department Civil Appropriation Act
approved Apr. 28, 1942      -----------------------------                                                    5000. 00
       Amount to be accounted for_                                                                    -14,         000. 00
Gross amount expended.                                         -           -       -        $6, 654. 22
Less reimbursements collected__  -                             -------                          106. 19
                                                                                                              6, 548. 03
      Balance unexpended June 30, 1944_                                                                       7 451. 97
Outstanding liabilities June 30, 1944 ----------------------------                                               42. 97
     Balance available June 30, 1944 -------------------------                                                7, 409. 00
Amount allotted in July 1944 -------------------------                                                        9000.00
                                                                                                              9,
          Amount available during fiscal year 1945                          ----------                       16, 409. 00
Amount (estimated) required to be appropriated for completion of
   existing project 1_                   -                 -              -_-           -         ___136,
                                                                                                       -_          100. 00
  1Exclusive    of available funds.

   17. ALOHA-RIGOLETTE AREA, GRANT AND RAPIDES PARISHES, LA.

  Location.- The work covered by this project lies on the left bank of
Red River in Grant and Rapides Parishes, between miles 125 and 171
above the mouth. (See U. S. Geological Survey State map, scale
1: 500,000.)
   Existing project.-The plan of improvement provides for the en-
largement of the authorized levee along the Red River between miles-
171 and 151 above the mouth; extension of the levee along the Red
River from the north bank of Bayou Darrow to the hills on the south
side of Bayou Rigolette, mile 125 above the mouth; construction of a
drainage ditch, two floodgates, and the provision of sump storage areas
at the mouth of Bayou Darrow, mile 141, and at the mouth of Bayou
          616634---45---pt. 1, vol. 1                 46
 722              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                     1944

Rigolette, mile 125; improvement of Bayou Rigolette from the vicinity
of United States Highway No. 71 to the mouth by clearing and snag-
ging of the old channel; and construction of an embankment at the
head of Bayou Darrow, to isolate the Bayou Darrow and Bayou Rigo-
lette drainage areas.
    The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941, which modified the project for Grant Parish
below Colfax, La., as authorized by the Flood Control Act approved
June 28,1938, to provide for construction of the above described works.
    The estimate of cost is $914,500 for construction and $21,500 for
lands and damages.
    Local cooperation.-Seepage 7 for requirements.
    Operations and results during fiscal year.-Office studies were car-
ried on in preparation of plans. Surveys and preliminary borings
were completed. No construction work was done.
    Cost of new work during the fiscal year was $12,192.94 and expendi-
tures were $11,908.98.
    Condition at end of fiscal yeuar.-Construction work has not been
started. Office studies in preparation of plans are in progress. Sur-
veys and preliminary borings are complete. Total cost of new work
to June 30, 1944, was $12,192.94 and expenditures were $11,908.98.
    Proposed operations.-The unexpended balance at the end of the
fiscal year, $28,541.02, will be applied as follows:
Accounts payable June 30, 1944                         _$283.                                                                                 96
New work: Completion of detailed plans-----------------------                                                                      28, 257. 06
               Total for all work--------                                                 --- _--------28,                             541. 02
    No additional funds can be profitably expended during the fiscal
year 1946 in view of the existing Federal policies on wartime con-'
struction.
                                                        Cost and financial summary

Cost of new work to June 30, 1944_                                                                 _$12,                               146. 78
Cost of maintenance to June 30, 1944_
       Total cost of permanent work to June 30, 1944-------------                                                                   12, 146. 78
Undistributed costs June 30, 1944_- -   -----------                                                                                     46. 16

       Net total cost to June 30, 1944_-------                                                                     ---              12, 192. 94
Minus accounts payable June 30, 1944_--                                                        ----------                              283. 96
        Net total expenditures__--- _-----------11,908.                                                                                      98
  Unexpended balance June 30, 1944_---------                                                                             ---        28, 541. 02
               Total amount appropriated to June 30, 1944                                             ---------------               40, 450. 00


       Fiscal year ending June 30                             1940                 1941                1942              1943           1944

  Cost ofnew work-----... ..       ..__ ... . ...--------------
                                                        ....                                        .....      ..-------------
                                                                                                                        ...--------------
                                                                                                                   .--------------.
                                                                                                                       ....           $12,146.78
  Cost of m aintenance ...... . . .-. . . . . .- . . . . . .                                       . . . . . . . . . - - -- -.. . . . .
Total expended             ----------------------------------..................                ----------------------------            11, 908.98

. Alloted-------------------------..........................---------------------------------                             $45,000      -4,550.00
                  FLOOD CONTROL--.VICKSBURG, MISS., DISTRICT                                        723
-3alanceunexpended July 1, 1943_ ___-         .----.-------       $45, 000. 00
Deductions on account of revocation of allotment ----------------   4, 550. 00

       Net amount to be accounted for__-           -------                       _    40, 450. 00
Gross amount expended_- .       ---------                              $12, 121. 78
Less reimbursements collected___ -        --------                            212. 80
                                                                          -11,            908. 98

       Balance unexpended June 30, 1944_                -----..----                         28, 541. 02
'Outstanding liabilities June 30, 1944_--             -------                    _---            23. 04

         Balance available June 30, 1944_ ------                ___----_____-               28, 517. 98

Amount (estimated) required to be appropriated for completion of
   existing project 1                                                                      874, 050. 00
                                                                                        _-----------------
  1Exclusive of available funds.

                                     18. SALINE POINT, LA.

   Location.-The work covered by this project is in the vicinity of
Saline Point on Red River, about 60 miles above the mouth and 8
miles northeast of Marksville, La. (See Mississippi River Commis-
sion maps, Alluvial Valley of the Mississippi River, scale 1:250,000
and quadrangle maps, scale 1: 62,500.)
   Existing project.-The plan of improvement provides for the exca-
vation of cut-off channels in Avoyelles and Catahoula Parishes. It
consists of cut-off excavation at Double Eddy, from approximately
mile 54.2 above the mouth of Red River to mile 56.5, with a pilot
channel 1,075 feet long, and cut-off channel across Saline Point ap-
proximately 5,400 feet long, from approximately mile 55.4 to mile
65.3 and levee set-back at the west end of the channel. The existing
project was authorized by the Flood Control Act approved June 22,
1936 (HI. Doc. No. 378, 74th Cong., 2d sess.). The estimate of cost
is $114,000 for construction and $21,000 for land and damages. The
latest published map is in House Document No. 378, eventy-fourth
Congress, second session.
   Local cooperation.-Fullycomplied with.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The project is complete with the
exception of reimbursing local interests for the acquisition of right-
of-way.
   Costs and expenditures under the existing project to June 30, 1944,
were $94,788.28, all for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $35,211.72, will be applied to reimbursement of local inter-
ests for acquisition of right-of-way, completing the project.
                                   Cost and financial summary
Cost of new work to June 30, 1944--- ...              ---.       --------                 $94, 788. 28
Cost of maintenance to June 30, 1944__
         Total cost of permanent work to June 30, 1944 -------------                         4, 788. 28

Net total expenditures_  - ---                ..-----                       -_____94,           788. 28
Unexpended balance June 30, 1944_ -----------------                                         35, 211. 72
         Total amount appropriated to June 30, 1944-                  ---                  130, 000. 00
724         REPORT OF CHIEF OF ENGINEERS,                           U.   S. ARMY,          1944


   Fiscal year ending June 30        1940               1941         1942           1943             1944

Cost of new work--------------     $28,732. 68        $38;207. 71   $9, 292 21         $2.35
Cost of maintenance .....            - .----------.....    ..-------
                                                 ... -------------------------       ---
Total expended----------------      14,509.80          52,588.04     9,205.14          25.52
Allotted ...... _ ...........       ---     -    --     5, 000. 00 -------------------------------


Balance unexpended July 1, 1943 ----------------------------                                   $35, 211. 72
Outstanding liabilities June 30, 1944---- -----------------------                               21, 000.00

         Balance available June 30, 1944---------------- ---------                               14, 211. 72

                                 19. BIG BLACK RIVER, MISS.

   Location.-The work covered by this project is on Big Black River,
Miss., which flows into the Mississippi River about. 25 miles below
Vicksburg, Miss. (See U. S. Geological Survey State Map, scale
1: 500,000.)
   Existing project.-The plan of improvement provides for improve-
ment of the flood channel by means of channel clearing and suitable
cut-offs from a point between Choctaw and Webster Counties, Miss.,
to the mouth, 325.6 miles. The project will lessen the frequency and
duration of floods on 180,000 acres of bottom lands. The existing
project was authorized by the Flood Control Act approved June 22,
1936. The estimate of cost is $850,000 for construction and $60,000
for lands and damages. The estimate of cost of maintenance is
$60,000 for the fiscal year 1944, $50,000 annually for the fiscal years
1945 and 1946, and $35,000 annually thereafter.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operation and results during fiscal year.-Maintenance work was
commenced in November 1943. Sixty-six miles of channel were
cleared and refuse over a stretch of 63 miles was piled and burned
between miles 2.5 and 65.5. Snagging was done over 14 miles of
channel. The work was suspended on February 10, 1944, due to high
river stages and was resumed in June 1944. Cost of maintenance
during the fiscal year was $33,865.07, with expenditures of $26,928.27.
   Conditionat end of fiscal year.-The project has been completed and
is being maintained.
   Cost of new work to June 30, 1944, was $910,162.39, with expendi-
tures of $909,676.74. Cost of maintenance to June 30, 1944, was
$141,166.56, with expenditures of $133,525.59.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $39,297.67, plus an allotment of $40,000 in July 1944, a total
of $79,297.67, will be applied as follows:
Accounts payable June 30, 1944------------------------------     $8, 126. 62
Maintenance: Channel clearing and snagging with Gov-
   ernment plant (tractors) approximately six months--   495. 57            -$67,
Hydraulic data and inspections----------------------- 3, 500. 00
R ight-of-way --------------------------------------     175. 48
                                                                 71, 171. 05
         Total for all work                                                                    .. 79, 297. 67
                  FLOOD CONTROL-VICKSBURG,                         MISS., DISTRICT                        725

  The additional sum of $50,000 can be profitably expended during
the fiscal year 1946 on maintenance, clearing, and snagging with
Government plant (tractors) approximately 5 months.
                                    Cost and financial summary
Cost of new work to June 30, 1944_ _ _- _---
                                          -----                                             $910, 162. 39
Cost of maintenance to June 30, 1944_ ------------------------                               141, 166. 56

      Total cost of permanent work to June 30, 1944.                                      1, 051, 328. 95
Minus accounts payable June 30, 1944 _----------------------8,                                    126. 62

      Net total expenditures ----------------------------- 1,043, 202. 33
Unexpended balanceJune 30, 1944--------------------------     39, 297. 67

          Total amount appropriated to June 30, 1944------------1, 082, 500. 00

    Fiscal year ending June 30          1940          1941           1942          1943               1944

Cost of new work .......            $324, 474. 26
                                 -.....              $45,369.87       $192. 31        $24. 52    .
Cost of maintenance -------------
                               ___29,129.                    51     28, 963.19    49, 208. 79        $33, 865.07

                 ----------------
      Total cost _                    324, 474. 26   74, 499. 38    29,155. 50    49, 233. 31         33, 865.07

             ................. 344, 194. 94
Total expended----------------                       75, 102. 32    28, 925. 00   48, 106. 93         26, 928. 27

Allotted_ ----    __-----------        35, 000. 00   32, 500.00     45, 000.00    60,000.00


Balance unexpended July 1, 1943                                                                 $66, 225. 94
Gross amount expended-_     ---------             $29, 591. 89
Less reimbursements collected--------------------   2, 663. 62
                                                                                                 26, 928. 27

      Balance unexpended June 30, 1944----------------------                                     39, 297. 67
Outstanding liabilities June 30, 1944--------------------------                                   1, 527. 61
     Balance available June 30, 1944_--    --------                                             37, 770. 06
Amount allotted in July 1944_-------------_                                                     40     -00-
          Amount available during fiscal year 1945----------------                               77, 770. 06

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1                             _-----------50,                              000. 00
  1Exclusive of available funds.

                       20. EMERGENCY FLOOD CONTROL WORK

   Because of the heavy demands for emergency repair work on flood-
control structures damaged or destroyed by the disastrous floods which
occurred in the spring of 1943 and again in the spring of 1944, Con-
gress, in the act approved July 12,1943, Public No. 138, Seventy-eighth
Congress, and in the act approved May 29, 1944, Public No. 318, Sev-
enty-eighth Congress, authorized the amounts of $10,000,000 and $12,-
000,000, respectively, to be appropriated as emergency funds to be
expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See p. 9 for details.)
   The sum of $1,000,000 was allotted in July 1943 for emergency flood-
control work in the Vicksburg district, pursuant to the act of July 12,
1943, but was reduced by revocation to $500,000. During the fiscal
year, emergency repairs were performed by the construction of levee
726               REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                              1944

setbacks along the south bank of the Arkansas River at Kimbrough,.
Pine Bluff, and Richland Bend. During the period, 1,076,373 cubic
yards of earthwork were placed at a cost of $343,476.70. Expenditures
were $342,939.10.
   The balance unexpended, $157,060.90, plus an allotment of $232,000
made in July 1944, less a revocation of $156,523.53, a total of $232,-
537.37, will be applied to emergency flood-control work during fiscal
year 1945 as follows :
Accounts payable June 30, 1944_            _    _ __$537.                                                                                               60
Emergency repair work-Red River and tributaries-_ $165, 000. 00
Emergency repair work-Yazoo River                   66, 999. 77               --------------
                                                                                                                                           231, 999. 77

               Total for all work                         .________---.-------------------232,                                                   537. 37"

                                                         Cost and financial summary
Cost of new work to June 30, 1944_--
Cost of maintenance to June 30, 1944- ----------                                                                                          $343, 476. 70
      Total cost of permanent work to June 30, 1944        .
Minus accounts payable June 30, 1944-------------------------
                                                              343, 476. 70'
                                                                - 537. 60
                                                                                                                      -----
      Net total expenditures__       __________________________ 342, 939. 10'
Unexpended balance June 30, 1944- ___--.----------         -    157, 060. 90
               Total amount appropriated to June 30, 1944_                                                     --------------              500, 000. 00

     Fiscal year ending June 30                                1940                  1941                       1942              1943           1944

Cost of new work --.....                .                      ...        .            .....
Cost of maintenance-------------.............----------...........            .-------.......................-------------.   --------------. $343,476.70
Total expended-------------------                                     ------------------------------------------                                342,939. 10
Allotted-----------...                    -------------- ------------------------------------------
                                     ..........                                                                                                 500, 000. 00


Amount allotted from Second Deficiency Appropriation Act
approved July 12, 1943___--    ----------             __$1,
Deductions on account of revocation of allotment--------------
                                                                                                                                           000, 000.
                                                                                                                                           500, 000. 00'
                                                                                                                                                        00'
       Net amount to be accounted for___     ....                                                                                          500, 000. 00
Gross amount expended_-       -----------                                                                         $887, 118. 37
Less reimbursements collected ------------------
                               ....                                                                                544, 179. 27
                                                                                                                                           342, 939. 10
      Balance unexpended June 30, 1944-                                                            ......                                  157, 060. 90
Outstanding liabilities June 30, 1944_.-                                                                       - - -                              81. 93
       Balance available June 30, 1944_._                                                                                                  156, 978. 97
Amount allotted in July 1944_ .---------                                                                          $232, 000. 00
                               -----------------
Less revocation in October 1944_                                                                                   156, 523. 53
                                                                                                                                            75, 476. 47
              Amount available during fiscal year 1945_                                               ---------------                      232, 455. 44

21. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES FOR
                       FLOOD CONTROL

   The cost of the work during the fiscal year was $57,994.21, with ex-
  enditures of $56,868.95. The balance unexpended at the end of the
fiscal year, $34,784.63, plus accounts receivable, $37.60, and an allot-
                   FLOOD CONTROL-VICKSBURG,                              MISS., DISTRICT                              727

ment of $90,000 in July 1944, a total of $124,822.23, will be applied as
needed during the fiscal year 1945 to payment of expenses incurred
under this heading.
   The additional sum of $76,500 can be profitably expended during the
fiscal year 1946.
                                          Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                              ---                $511, 594. 21
       Total cost of permanent work to June 30, 1944             511, 594. 21  ------------
Plus accounts receivable June 30, 1944 --------------------------      37. 60
      Gross total costs to June 30, 1944---------------------- 511, 631. 81
Minus accounts payable June 30, 1944-------------------------    1, 316. 44
      Net total expenditures--
                           _      ------------                                                                510, 315. 37
Unexpended balance June 30, 1944---------------------------                                                    34, 784. 63
           Total amount appropriated to June 30, 1944                      --------------                     545, 100. 00

   Fiscal year ending June 30                1940            1941           1942                 1943              1944

Cost of new work _
Cost of maintenance .......-----------.   $109, 179. 94    $28,105. 70    $81, 455. 83         $35, 059. 24       $57, 994. 21
Total expended ....---------------         115, 244. 36     28, 018.87     79, 616. 98          35, 901. 26        56, 868. 95
Allotted   ---------.....
             ....              -...         26, 500.00       3,000.00      99,100.00            48,000.00          56, 500. 00


Balance unexpended July 1, 1943     ---------------------------- $35, 153. 58
Amount allotted from War Department Civil Appro-
  priation Act approved June 28, 1939 ------------ $12, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940------------      6, 987. 03
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941--------------     7,      97                        7512.
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942                     --------------
                                                      30, 000. 00
                                                                  56, 500. 00
       Amount to be accounted for_--------             ---                                                    91, 653. 58
Gross amount expended_-------                ---    63, 963. 37
Less reimbursements collected --------------------- 7, 094. 42
                                                                                                               56, 868. 95
      Balance unexpended June 30, 1944_ ---------------                                                        34, 784. 63
Outstanding liabilities June 30, 1944--_ -------                                   _ __ __ _            -       6, 262. 47
      Balance available June 30, 1944----------------------                                                    28, 522. 16
Accounts receivable June 30, 1944_ .-----------------------                                                         37. 60
    Unobligated balance available June 30, 1944                          ---------------                       28, 559. 76
Amount allotted in July 1944-_---------_-_---------------                                                      90, 000. 00
           Amount available during fiscal year 1945 -----------------                                         118, 559. 76

.Amount that can be profitably _ expended in fiscal year ending June
   30, 1946, for maintenance                1_   _ __ __________________--
                                                                       -                   -        -          76, 500. 00
   SExclusive of available funds.
728             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

22. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                      ARE SUBMITTED

                                                                    For last      Cost and expenditures to                 Estimated
                                                                  full report           June 30, 1944                      amount re-
                       NaRe of project                            see Annual                                                     o
                                                                    Report                                                  quired to
                                                                      for-         New work          Maintenance            complete


1.   Colfax, Grant Parish, La......-------------1938                                $70, 348. 04-      .---------             (1)
2.   Red River Parish, La_ _ ------------------                        1939         149, 435.04-       ___-
                                                                                                          -     -     --      (2)
3.                  ---------------------------
     Jonesville, La ......                                             1940                                                    $368, 200
4.   Hempstead County Levee District No. 1, Ark__                      1941          88, 005. 78      --      -                2)
                                                                                                                              (--
5.   Columbia, La.....................-----------------------------.   1941         204, 739. 73    --------------            (2)
6.   Grant Parish below Colfax, La _---_.--------                      1941          38, 808.89-----.         -    -          (2)
7.   Blakely Mountain Reservoir, Ark ...... _____                      1941     ----------------------------
                                                                                 .    ....                                    (4)
8.                                      .
     Snagging and clearing -----------------------                     1943         297, 319. 63 --      - --   --            (5)

  I Completed under provisions of sec. 7 of the Flood Control Act approved May 15, 1928, as amended by
see. 9-6f the Flood Control Act approved June 15, 1936, and included in report of the Mississippi River
Commission.
  2 Completed.
  8 Awaiting local cooperation.
  4 Modified project recommendations contained in H. Doc. No. 647, 78th Cong., 2d sess.
  6 Work accomplished under authority of sec. 2 of the Flood Control Act approved Aug.      28, 1937, as
amended. Work suspended during war.

Status oJ all investigations for flood control called for by flood-control acts and com-
                                    mittee resolutions

                                                                        Date trans-N
               Locality                    Authorization act             mitted to          Document No.               Recommenda-
                                                                         Congress                                          tion

Bartholomew Bayou, Ash-                 Flood Control Act, I----------                 ----------------
ley and other counties, Ar-              June 28, 1938.
  kansas.
Black River, Catahoula and              Flood     Control Act,
  Concordia Parishes, La.                 Aug.    11, 1939.
Boeuf River, in Catahoula,              Flood     Control Act,
  Franklin, Caldwell, Rich-               Aug.    28, 1937.
  land, West Carroll, and
  Morehouse Parishes, La.
Boeuf and Tensas Rivers                 Commerce Commit-
  and Bayou Macon, Ark.                  tee resolution, May
  and La., for flood control             5, 1944.
  and drainage in Cypress
  drainage system of Desha,
  Chicot, and Lincoln Coun-
  ties, Ark., and outlets to
  Boeuf River, Chicot Coun-
  ty, Ark.
Bogue Phalia, Miss.........             Flood Control Com-
                                          mittee resolution,
                                          Apr. 23, 1942.
Caddo Lake Dam and Jef-                 Flood Control Act,
  ferson-Shreveport water-                June 22, 1936.
  way, Louisiana and Texas,
  on Red River.'
Jefferson -Shreveport water-             River and Harbor Act,
  way, Texas and Louisiana,               Aug. 30, 1935.
  enlarging existing project
  and establishing reservoir
  on Cypress River above
  Jefferson.i
Jefferson - Shreveport water-            River and Harbor Act,I
  way, Texas and Louisiana,                Aug. 26, 1937.
  thence via Red River to
   Mississippi River, includ-
  ing reservoirs in Cypress
  and Black Cypress Rivers.i
Jefferson - Shreveport water-            River and Harbor Act,
  way, Louisiana and Texas,               June 20, 1938.
   thence via Red River to
   Mississippi River, survey
   for navigation, flood con-
   trol, power and irrigation,
   including water - supply
   reservoirs in Cypress and
   Black Cypress Rivers.'
     See footnotes at end of            table.
                  FLOOD CONTROL---VICKSBURG,                                     MISS.,                  DISTRICT                                     729

Status oj all investigations for flood control called for by flood-control acts and com-
                             mittee resolutions-Continued

                                                              Date trans-                                                                    Recommenda-
            Locality               Authorization act           mitted to                         Document No.                                    tion
                                                               Congress

Little Missouri River, Ark..     Flood     Control Act,   - - - - - -   - - - - - - - - -

                                   June   22, 1936.
Macon Bayou in Franklin,         Flood     Control Act,   - - - - - - - -   - - - - - - -

Madisbn, Richland, East           Aug.   28, 1937.
Carroll, and West Carroll
Parishes, La.
Mississippi River between        Flood Control Com-        Mar. 20,1944                       H. 509, 78th Cong.,                            Favorable.
Cairo, Ill., and Baton            mittee resolution,                                           2d sess.
Rouge, La., for 12-foot           Mar. 8, 1943.
channel (navigation
                 2
                      and
flood control).
    Do.2.              ......    Commerce committee ....     -- ----- do
                                                       do ...-                                                          _.---------             Do.
                                   resolution, Mar. 9,
                                   1943.
Mississippi (lower) River,       Flood Control Com-
protection by levees, east        mittee resolution,
bank from Vicksburg south         Apr. 26, 1944.
to the Big Black River.'
Ouachita River and tribu-        Flood Control Com-
taries, Arkansas and Lou-         mittee resolution,
  isiana.                          Feb. 10, 1938.
Ouachita River and tribu-        Flood Control Act,
taries, La.                       Aug. 28, 1937.
Ouachita River Ark.,Blake-       Flood Control Com-
ly Dam, for food control,         mittee resolution,
power, etc. (final report).       May 11, 1938.
Ouachita River and tribu-        Flood Control Com-        May 30,1944                        H. 647, 78th Cong.,                               Do.
taries, construction of           mittee resolution,                                          2d sess.
Blakely Mountain Dam.             May 12, 1941.
Ouachita River near Calion,      Flood Control Act,       ...............
Ark.                              June 28, 1938.                                           -------------------.
Ouachita River and tribu-        Flood Control Com-
taries, Arkansas and Lou-         mittee resolution,
isiana, for flood protection      Apr. 13, 1938.
at Jonesville, La.
Ouachita River system,           Commerce Committee
Louisiana and Arkansas,          resolution, Feb. 8,
for navigation, flood con-       1939; Flood Control
trol and irrigation.             Committee resolu-
                                  tion, Jan. 26, 1939;
                                  Rivers and Harbors
                                  Committee resolu-
                                  tion, Jan. 24, 1939.
Ouachita River and tribu-        Commerce Committee        Feb. 3, 1944                       S. 151, 78th Cong.,                               Do.
  taries,   Arkansas and          resolution, Feb. 20,                                          2d sess.
  Louisiana, for flood control    1942.
  on Boeuf and Tensas Riv-
  ers and Bayou Macon,
  Arkansas and Louisiana.
Pierre Bayou, La., for flood     Commerce Committee       ---------------                   --------------------
  control at Shreveport, La.,      resolution, Oct. 28,
  and vicinity.                    1941.
Pierre Bayou, La., for flood     Flood Control Com-       ---------------                   --------------------
  control at Shreveport, La.,      mittee resolution,     ---------------                   - - - - - - - - - -   - - - - - -    - -   - -

  and vicinity.                    Nov. 12, 1941.
Pierre Bayou, La., for flood     Flood Control Com-       ---------------                   --------------------

  control in the vicinity of       mittee resolution,
  Shreveport, La.                  Nov. 24, 1942.
Red River, Ark.'........         Flood Control Act,       ---------------                   --------------------

                                   June 22, 1936.
    D o.'- - -.   -- - .. .      Flood Control Act,       ---------------                   - - - - - - - - -   - - -    - - - - - - - -

                                   May 6, 1936.
Red River, La., Ark., Okla.,     Commerce Committee       ---------------                   - - - - - - - - -   - - - - - - - - - - -

and Tex., and connecting          resolution, Feb. 8,
waterways, singly or to-          1939; Flood Control
gether, for navigation,           Committee Resolu-
flood control and irriga-         tion, Jan. 26, 1939;
tion.]                            Rivers and Harbors
                                   Committee resolu-
                                   tion, Jan. 24, 1939.
Red River, La., Ark., Okla.      Rivers and Harbors
" and Tex., for navigation,        Committee resolu-
  flood control, water power       tion, Feb. 25, 1938.
  and irrigation (report
  being prepared by the
  Lower Mississippi Valley
  Division).
    See footnotes at end of table.
730          REPORT OF CHIEF OF ENGINEERS,                           U.    S. ARMY,         1944

Status of all investigations for flood control called for by flood-control acts and com-
                            mittee resolutions-Continued

                                                          Date trans-         Document           Recommenda-
            Locality                 Authorization: act    mitted to            No.                  tion
                                                           Congress

Red River, La., east bank of,       Flood Control Act,-
  from hill line at south bank       June 28, 1938.
  of Loggy Bayou, thence
  along south bank of Loggy
  Bayou, and along east
  bank of Red River to
  Coushatta Bayou, Red
  River Parish.'
Red River in vicinity of            Flood Control Act,    May 27, 1944    H. 627, 78th Cong.,    Favoable.
  Shreveport, La., with view          Aug. 18, 1941.                        2d sess.
  to determining the advisa-
  bility of providing bank
  protection works.
                               -FloodAug. Control
Saline River, Ark--------........               Act, ..................
                                      28, 1937.
Sulphur River, Ark.l'-.....   Flood Control Act,--------                  --------------------
                                June 22, 1936.
    Do.'-.----------------Flood Control Act, .------
                                Aug. 28, 1937.
Sulphur River, Tex.'--_-_-_.-Flood Control Act,_
                                June 22, 1936.
    Do..'-------------.---.Flood Control Act,-
                                June 28, 1938.
Sulphur River, Tex. and River and Harbors .......
   Ark., improvement for        Act, June 20, 1938.
  navigation, flood control
   and water power.'
Yazoo River (lower tribu- Flood Control Conm- Mar. 25,1944 H. 516,78th Cong.,                     Do.
  taries), Miss.'               mittee resolution,                      .           2d sess.
                                Jan. 28, 1944.

   1Combine with report on Red River, La., Ark., Okla., and Tex., for navigation, flood control, power, and
irrigation, requested by resolution of the Committee on Rivers and Harbors, House of Representatives,
adopted Feb. 25, 1938, which is being prepared by the Lower Mississippi Valley Division.
  2 Field report was made by the Mississippi River Commission.


IMPROVEMENT OF RIVERS AND HARBORS                                                                IN THE
          MEMPHIS, TENN., DISTRICT
   This district comprises a portion of southeastern Missouri, the
western portions of Kentucky and Tennessee, a small portion of north-
ern Mississippi, and northeastern Arkansas embraced in the drainage
basins of the eastern tributaries of the Mississippi River south of the
Ohio River basin to Nonconnah Creek, inclusive, and those of the
western tributaries south of the Little River Diversion Channel and
Commerce, Mo., to the Arkansas River, inclusive, with the exceptions
of the drainage basins of the Arkansas and its tributaries above mile
120, 3 miles above Pine Bluff, Ark., and of the White River and its
tributaries above Peach Orchard Bluff, mile 168.7.
   District engineer: Col. Jarvis J. Bain, Corps of Engineers, to Sep-
tember 30, 1943; Col. Garner W. Miller, Corps of Engineers, since
that date.
   Division engineer: Brig. Gen. Max C. Tyler, U. S. Army.
            RIVERS AND HARBORS-MEMPHIS,                  TENN., DISTRICT            731
                                      IMPROVEMENTS

                Navigation                           Flood control-Continued
                                       Page                                         Page
1. White River, Ark. (below                   9. Augusta to Clarendon, White
      Peach Orchard Bluff)     ----     732         River, Ark------------_         744
2. Wolf River (Memphis Har-                  10. De Valls Bluff, White River,
      bor), Tenn_-----                  733         Ark-----------------_           745
3. Removing snags and wrecks                 11. Snagging and clearing under
     from the Mississippi River                     authority of section 2 of
      below the mouth of the                        the Flood Control Act ap-
      Missouri River, and from                      proved August 28, 1937, as
     the Old and Atchafalaya                        amended-_------------           746
      Rivers_---------------            736   12. .Emergency      flood-control
                                                    work under authority of
      0
4. Examinations, surveys, and
      contingencies (general)   ---
5. Other navigation projects for
                                        738         the Flood Control Act ap-
                                                    proved August 18, 1941__-       747
     which no estimates are                   13. Emergency flood-control
     submitted_                         739         work under authority of
f Plant allotment-        -            739         public laws Nos. 138 and
                                                    318, Seventy-eighth Con-
                                                    gress----------------           749
               Flood control                                     examinations,
                                              14. Preliminary
                                                    surveys, and contingencies
7.   Memphis, Wolf River, and                      for flood control    .-------   750
       Nonconnah Creek, Tenn _          740   15. Other flood-control projects
8.   North Little Rock to Gillett,                 for which no estimates
       Ark. (below Plum Bayou)-         742         are submitted----------         751

          1. WHITE RIVER, ARK. (BELOW PEACH ORCHARD BLUFF)

   Location.-This river rises in northwestern Arkansas and flows 690
miles, first north into Missouri, then southeasterly through Arkansas
to the Mississippi River, 33 miles above Arkansas City, Ark. (See
Mississippi River Commission alluvial valley maps, scale 1: 62,500 and
scale 1:500,000, for river from mouth to vicinity of Newport, Ark.,
and U. S. Geological Survey State map, scale 1: 500,000.)
   The White River enters the Memphis district at the foot of Peach
Orchard Bluff, Ark., and flows 169 miles in a southeasterly direction
to the Mississippi River, 4 miles north of Rosedale, Miss.
   Previous projects.-Adopted by the River and Harbor Acts of
March 3, 1871, June 23, 1874, August 14, 1876, June 14, 1880, July 5,
1884, and March 3, 1899.
   For further details see page 1874, Annual Report for 1915, and page
938, Annual Report for 1938.
   Existing project.-This provides for channel maintenance between
the mouth of the river and Batesville, 301 miles, by snagging and
dredging and by contraction works. The stream has an ordinary
freshet fluctuation of 15 feet throughout the portion covered by the
project, and an extreme stage fluctuation of 60 feet at the mouth, and
of 36 feet at Clarendon. No estimate of cost has been given, and
since 1899 the work has been prosecuted under annual estimates for
maintenance by snagging and dredging. The latest (1934) approved
estimate for annual cost of maintenance below Peach Orchard Bluff
is $125,000.
732         REPORT OF CHIEF OF ENGINEERS, U.                                          S. ARMY,        1944

  The existing project was authorized by the following river and
harbor act:

     Act                          Work authorized                                              Documents


July 13, 1892    Open-channel work      ...............------------------------   Annual Report, 1893, p. 2112.



   Terminal facilities.-Railway spur tracks are available for transfer
of freights between car and boat at Clarendon. There is a log slip for
use of the owners only at Clarendon. In 1932, a cotton, rice, and gen-
eral-merchandise terminal was built at De Valls Bluff. Present facili-
ties are considered adequate for existing commerce.
   Operations and results during fiscal year.--All operations during
the fiscal year of 1944 were for maintenance by hired labor with Gov-
ernment plant. In snagging operations during the fiscal year 1944, the
snag boats Arkansas II and Tom Stallings operated over the river be-
tween the mouth and Peach Orchard Bluff, Ark., removing 1,421 snags
and breaking 3 drifts. A dredging survey was made between the head
of Sibley Chute and the mouth of White River.
   The cost of maintenance during the year was $53,280.03 for snagging
operations, and the total Expenditures were $53,283.81. The cost and
expenditures for the dredging survey were $258.28.
   Condition at end of fiscal year.-The project being for maintenance,
completion is not contemplated. Though dredging was needed during
the fiscal year of 1944, none was accomplished as no dredge was avail-
able. Snagging operations have materially improved the condition of
the channel from the mouth as far as Peach Orchard Bluff (169 miles).
   This river is generally spoken of as navigable within the limits of
this district (mouth to Peach Orchard Bluff) by boats of 3-foot draft
at any time. Under ordinary conditions boats of n-foot draft may be
taken to Peach Orchard Bluff from the first of February to the last of
June, and from the middle of November to the end of December. Dur-
ing the fiscal year ending June 30, 1944, depths were available on the
White River which would permit navigation of vessels of 3-foot draft
between the mouth and Peach Orchard Bluff (169 miles), with the
exception of a shoal, approximately 2;000 feet long, in the mouth of
White River where depths of from 11/ to 3 feet existed during the
period August 1, 1943 to January 3, 1944, and from January 18 to
February 4, 1944.
   The total costs under the existing project to June 30, 1944, were $1,-
115,756 for maintenance. The total expenditures were $1,115,759.50.
   Proposed operations.-The balance unexpended, including accounts
receivable, plus an allotment of $70,000 made during July 1944 will be
applied as follows:
Snagging operations by Government plant and hired labor, between
  the mouth and Peach Orchard Bluff, Ark., about 5 months' work
                                    ------------------------ $38, 919. 09
  during the period July to November_
Dredging operations by leased plant between the mouth of White
  River and Clarendon, Ark., appoximately 3 months' work-----.-60, 000. 00

           Total- -------------------------------------------                                               98, 919. 09
              RIVERS AND HARBORS--MEMPHIS,                           TENN., DISTRICT                      733
  The additional sum of $100,000 can be profitably expended during
the fiscal year 1946 for snagging operations by Government plant and
hired labor between the mouth of White River and Peach Orchard
Bluff, Ark., and dredging operations by Government plant and hired
labor or leased plant between the mouth of White River and Clarendon,
Ark.
                                     Cost and financial summary
Cost of new work to June 30, 1944----------------- ---------.                                    $25, 000. 00
Cost of maintenance to June 30, 1944_---------                                                 1,115, 756. 00
         Total cost of permanent work to June 30, 1944---------- 1, 140, 756. 00
Plus   accounts receivable June 30, 1944 ------------------------          3. 50

         Gross total costs to June 30, 1944--------------------                                1,140, 759. 50

Net total expenditures_-__---------- __                                            _           1,140, 759. 50
Unexpendable balance June 30, 1944_--------                                        ---            28, 915. 59
         Total amount appropriated to June 30, 1944------------                                1, 169, 675. 09

   Fiscal year ending June 30           1940         1941             1942              1943            1944

Cost of new work .. . . . . . . .. . . . . . . .. . . .. . .
Cost of maintenance------------ $109,918.14     $79, 026.76  $63, 811.02 -- $52,888.09-                $53, 538.31
Total expended ....---------------   $116,458.84    78, 975. 28      59, 435. 04       57, 315.83       53, 542.09
Allotted---------------------81,000.00             101, 500.00       70,000.00         12,646.18


Balance unexpended July 1, 1943      __      ___________                                            82, 457. 68
Gross amount expended_--       -----        ---   $69, 983. 37
Less reimbursements collected-------------------- 16, 441. 28
                                                                                                    53, 542. 09

      Balance unekpended June 30, 1944 ----------------------                                       28, 915. 59
                                _
Accounts receivable June 30, 1944--      -----------                                                      3. 50

     Unobligated balance available June 30, 1944-------------                                       28, 919. 09
Amount alloted in July 1944_ ____-------------70,                                                       000. 00
          Amount available during fiscal year 1945                -----------------                 98, 919. 09

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1     ------------                                                  100, 000. 00
  I Exclusive of available funds.

                      2. WOLF RIVER (MEMPHIS HARBOR), TENN.

   Location.-Wolf River rises in Benton County, Miss., and flows gen-
erally northwesterly about 100 miles, through Shelby County, Tenn.,
emptying into the Mississippi River within the corporate limits of
the city of Memphis, Tenn. (See Mississippi River Commission
alluvial valley maps, scale 1: 62,500, and scale 1: 500,000.)
   Previows projects.-The River and Harbor Act of August 18, 1894,
authorized dredging at the mouth of Wolf River as an item in the
improvement of Memphis Harbor, the work being carried out under
the supervision of the Mississippi River Commission.
   Existing project.-This provides for a channel 9 feet deep at low
water (71/2 feet below zero on the Memphis gage) from its mouth to
North Second Street Road with bottom widths of 250 feet from the
mouth to Keel Avenue and 200 feet from Keel Avenue to North Sec-
734     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,           1944

ond Street Road, and thence 125 feet wide and 7.5 feet below zero of
the Memphis Beale Street gage from North Second Street Road to
Hindman Ferry Road.
    The estimate of cost for new work, revised in 1935, is $1,185,000.
The latest (1935) approved estimate of cost for annual maintenance
is $104,000.
    The work of improvement under the existing project up to Second
Street Bridge was authorized September 6, 1933,'by the Public Works
Administration, and the existing project was adopted by the River
and Harbor Act approved August 30, 1935 (Rivers and Harbors Com-
mittee Docs. No. 26, 72d Cong., 1st sess., and No. 45, 74th Cong., 1st
sess.). Sketch maps are printed in the project documents.
    Local cooperation.-The work under the existing project is subject
to the condition that local interests shall furnish, free of cost to the
United States, all rights-of-way required for channel enlargement
and straightening, and suitable areas with retaining levees where
needed for disposal of dredged material during initial construction
and future maintenance as and when needed, and shall furnish as-
surance satisfactory to the Secretary of War saving the United States
free from'damages resulting from the work. The work is also subject
to the provision that no work shall be undertaken on any section of
the channel through or above any bridge until such bridge has been
altered in a manner satisfactory to the Secretary of War, without
cost to the United States. The conditions as pertaining to the improve-
ment up to Second Street Bridge have been complied with. Condi-
tions above that point have not been complied with.
    Terminal facilities.-There are 36 terminals, including 1 small
marine ways available for public use, operating in the port of Mem-
phis, 12 being located on the Mississippi River front, 5 on Tennessee
Chute and 19 on Wolf River. Of the 36 terminals, 4, including a grain
elevator, are publicly owned, 2 are operated by contract with trans-
portation companies and 3 are operated by common carriers; the
balance are privately owned and operated. Present facilities are con-
sidered adequate for existing commerce.
    Operations and results during fiscal year.-Maintenance dredging
during the fiscal year of 1944 was conducted with Government plant
and hired labor and with leased plant. U. S. dredge Jadwin and
leased dredge Robert H. moved a total of 319,482 cubic yards of ma-
terial in maintaining a channel of project dimensions.
    The total costs for the year were $50,882.04, and the total expendi-
tures were $50,200.64.
    Condition at end of fiscal year.-The existing project was about
50 percent complete. At the end of the fiscal year there was a channel
of project width and more than 9 feet in depth from the mouth to
900 feet above Hall Street. From this point to beyond Second Street
Road, there were depths of from 1 to 2 feet during the low-water
season. The work remaining to be done to complete the project is
extending the channel from North Second Street to Hindman Ferry
Road, as authorized by the River and Harbor Act of 1935.
   Exclusive of maintenance dredging done during the fiscal year 1936
with Mississippi River funds which were indJuded in the annual report
of the Mississippi River Commission for that year under the
caption "Dredges and dredging," the total costs June 30, 1944, were
$939,294.61, of which $586,500 was from Public Works funds for new
             RIVERS AND                    HARBORS-MEMPHIS,                        TENN.,        DISTRICT                 735
work, and $952,794.61 was from regular funds for maintenance. The
total expenditures were $938,613.21. To cover the cost of retaining
levees required of local interest, there have also been costs and expend-
itures charged to contributed funds amounting to $17,500.
   Proposed operations.-Thebalance unexpended, plus an allotment
of $67,000 made during July 1944, will be applied as follows:
Accounts payable June 30, 1944 ---------------------------------   $681. 40
Maintenance: Dredging by leased plant in Wolf River beween its
mouth to a point approximately 3,000 feet below 2d Street Road,
about 4 months' dredging operations_ -----------------          79, 091. 29

         Total     ---------------------------------------------                                                    79, 772. 69
   An additional sum of $80,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging by Government plant and
hired labor or leased plant, from the mouth of Wolf River to a point
approximately 3,000 feet below Second Street Road, about 3 months'
dredging operations.
                                                Cost and financial summary

Cost of new work to June 30, 1944____ __________-----1                                                          $586,500. 00
Cost of maintenance to June 30, 1944_--   ------------                                                          352,794. 61
      Total cost of permanent work to June 30, 1944-----------                                                  939, 294. 61
Minus accounts payable June 30, 1944_-       -----        -----                                                      681. 40
      Net total expenditures---     ------------                                                              1 938, 613. 21
Unexpended balance June 30, 1944_--       ----------                                                                12, 772. 69
         Total amount appropriated to June 30, 1944_                                                          1-------------
                                                                                                               951, 385. 90

   Fiscal year ending June 30                        1940         1941             1942               1943             1944

Cost of new work    --------.                   ------..        ------.        ------...               ----. .......
Cost of maintenance--------------                     $881.29   $31, 285. 11   $50, 995. 44       $53, 761.87                 04
                                                                                                                       $50,882.
Total expended     __-----------------            20, 040.83     31, 286. 43     51,073.22         53, 761.87          50,200.64
A llotted -----------------------                   5,000.00     40, 000. 00     40, 000.00        55, 700.00       $ ,.      .   33--

Balance unexpended July 1, 1943-                                                                              $62, 973. 33
Gross amount expended ------------------------                                             $50, 526. 83
Less reimbursements collected---------------------                                              326. 19
                                                                                                                50, 200. 64
      Balance unexpended June 30, 1944---------------- ------                                                       12, 772. 69
Outstanding liabilities June 30, 1944---------------------------                                                        681. 40
     Balance available June 30, 1944_-------                                                      -          -12,       091. 29
Amount allotted in July 1944_---     -----------                                                                    67, 000. 00,

         Amount available during fiscal year 1945----------------                                                   79, 091. 29
Amount (estimated) required to be appropriated for completion of
   existing project        2-----------------                                                                   598,500. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for ,maintenance 2--    -      -    -                                                                80, 000. 00
1In addition, $17,500 contributed funds expended for new work.
2 Exclusive of available funds.
736           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                        1944

3. REMOVING SNAGS AND WRECKS FROM THE MISSISSIPPI RIVER
    BELOW THE MOUTH OF MISSOURI RIVER AND FROM OLD AND
    ATCHAFALAYA RIVERS
  Reports on work done under this title were formerly submitted by
the St. Louis engineer district. Beginning June 30, 1940, reports are
submitted by districts receiving allotments for work under the project.
  Looation.-The Mississippi River from its confluence with the Ohio
River to the mouth of the Arkansas River
  Previous projects.-Generalappropriations were made at irregular
intervals as early as 1824. For further details, see page 1880, Annual
Report for 1915.
   Existing project.-This is a continuation of the plan adopted in
1879 and provides for the removal and destruction of snags, wrecks,
drift heaps, and other obstructions to navigation in the Mississippi
River between the mouth of the Ohio River and the mouth of the
Arkansas River; also for the felling of large trees on or near caving
banks, thereby decreasing the number of snags to be destroyed there-
after. The work is done by the district's steel-hull snag boat, Arkan-
sas II, built in 1940.
   The existing project was authorized by the following river and
harbor acts:

      Acts                         Work authorized                        Documents


              _Annual
               .-     appropriations or allotments made 1879
                    to 1886, inclusive, except in 1883 and 1885.
Aug. 11,18881.__   Annual expenditure of $100,000nade available
                    each year.
Mar. 3, 1909   -   Atchafalaya and Old Rivers from their junction
                    with the Mississippi and Red Rivers to Mel-
                    ville, La., included in the project.
Mar. 2, 1919   --- Appropriation of $50,000 additional to cover in-
                    creased costs due to war conditions.
June 30, 1922 2_

Mar. 2, 1923 2___ Allotments of $25,000, $20,000; $17,500, and $13,000,
June 7, 1924 2     respectively, to cover increased costs.
Apr. 15, 1926 2__
June 26, 1934 3.. Maintenance provided for with funds appropri-
                    ated for the preservation and maintenance of
                    rivers and harbors, since June 30, 1935.


  1 Sec. 7.
  2 War Department Appropriation Act.
  3 Permanent Appropriations Repeal Act.


   Terminal facilities.-Exclusive of terminal facilities at Memphis,
Tenn., and Helena, Ark., there are several privately owned and oper-
ated barge-to-bank sand and gravel plants, pipe lines from bulk plants
to barge landings for handling petroleum products, and log slips.
   At Helena, Ark., there is a river and rail terminal operated by the
Federal Barge Line that is available for public use. For facilities
on port of Memphis, see report on Wolf River (Memphis Harbor,
Tenn.). The present facilities are considered adequate for existing
commerce.
             RIVERS AND            HARBORS-MEMPHIS,                     TENN.,       DISTRICT              737

   Operations and results during fiscal year.-All operations during the
fiscal year of 1944 were for maintenance by hired labor with Govern-
ment plant and consisted of removal of snags from the channel between
Cairo, Ill. (mile 966), and the mouth of the Arkansas River (mile 575)
with snag boat Arkansas II. The result of these operations was the
removal from the channel of 568 snags.
   The costs were $21,446.17, and expenditures were $20,985.86 for
maintenance.
   Condition at end of fiscal year.-The project being one of continuous
maintenance of channel, no estimate of completion and total cost can
be made. Each freshet brings down new obstructions, and changes in
location of channel, which are constantly going on, uncover old obstruc-
tions. Operations provided a channel reasonably free from snags at
the end of the fiscal year, and there is sufficient plant to take care of
future work.
   The total costs under the existing project to June 30, 1944, for
maintenance were $264,673.91. The total expenditures were $264,-
213.60.
   Proposed operations.-The balance unexpended, plus an allotment
of $35,000 made during July 1944, will be applied as follows:
                                     -
Accounts payable June 30, 1944_ -------                      ______-----$460. 31
Maintenance: Removal of snags and wrecks as required from the
  Mississippi River between the mouth of the Ohio River and the
  mouth of the Arkansas River ------------------------------             35, 526. 09

        Total-------------------                         -------------------------- 35, 986. 40
  The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 for maintenance in removing snags and wrecks
from the Mississippi River from the mouth of the Ohio River to the
mouth of the Arkansas River.
                                      Cost and financial summary
Cost of new work to June 30, 1944___
Cost of maintenance to June 30, 1944 -----------------------                                      $264, 673.91

      Total cost of permanent work to June 30, 1944----                                            264, 673. 91
Minus accounts payable June 30, 1944_--------                                           ---             460.31
      Net total expenditures ------------------------------                                        264, 213. 60
Unexpended balance June 30, 1944_---------------------                                                  986. 40
         Total amount appropriated to June 30, 1944- -------------                                 265, 200. 00


   Fiscal year ending June 30             1940            1941          1942            1943            1944

Cost of new work .-----------..
                     . . . . . .. . . . . . ... . . . .. . . .. .
Cost of maintenance.....     ...--------- $58, 254.56   $38,463.96     $21,430.98    $22,655.74        $21,446.17

Total expended     ------------- 65,168.62               38, 463. 96   19, 364. 35    24, 722.37        20, 985. 86

Allotted.....----------------------      60,000.00       47,000.00     45,000.00     -15,000.00      ........




        616634--45-pt. 1, vol. 1-----47
738             REPORT OF CHIEF OF ENGINEERS,                                       U. S. ARMY,               1944

Balance unexpended July 1, 1943 ----------------------------                                                       $21, 972. 26
Gross amount expended-------------------------               $21, 026. 11
Less reimbursements collected -----------------------              40. 25
                                                                                                                    20, 985. 86

      Balance unexpended June 30, 1944-------------- - -                                                               986. 40
Outstanding liabilities June 30, 1944---------------------------                                                       460. 31

     Balance available June 30, 1944-------------------------                                                           526. 09
Amount allotted in July 1944 --------------------------------                                                       35, 000. 00

             Amount available during fiscal year 1945------------                                      ----         35, 526. 09

Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1        --------------                                                                 40, 000. 00
1Exclusive of available funds.

      4. EXAMINATIONS,                             SURVEYS, AND CONTINGENCIES                              (GENERAL)

  The cost of work during the year amounted to $3,182.75; the expendi-
tures were $3,768.95. The balance unexpended on June 30, 1944,
$13,618.66, plus the sum of $10,000 allotted in July 1944 will be applied
as needed during the fiscal year 1945 to payment of expenses to be
incurred under this heading. An additional sum of $10,000 can be
profitably expended during the fiscal year 1946.
                                                   Cost and financial summary
Cost of new work to June 30, 1944_-
Cost of maintenance to June 30, 1944 ------------------------                                                  $203, 321. 18
       Total cost of permanent work to June 30, 1944------------                                                   203, 321. 18
Plus accounts receivable June 30, 1944------------------ ------                                                          17. 94

      Gross total costs to June 30, 1944---- -----------------                                                     203, 339. 12
Minus accounts payable June 30, 1944--------------------                                                                 65. 75
      Net total expenditures ------------------------- ____  203, 273. 37
Unexpended balance June 30, 1944----------------------------  13, 61& 66
             Total amount appropriated to June 30, 1944--------                                                    216, 892. 03

     Fiscal year ending June 30                       1940             1941           1942            1943              1944

Cost ofnew work..-                                           -    -- - - - - -      $-
                                                                                    - - - - --     .- - - - - - .. . . -1 - -
Cost of maintenance -------------                    $17,132.95      $22, 962. 39   $13, 342.62      $9, 676. 12        $3,182.75
Total expended----------------..................     16,411.89        23, 062. 11    14, 198. 47      9, 246. 15         3, 768. 95
Allotted-----------------------                      13,000.00        16,000.00 --------------       20,800.00


Balance unexpended July 1, 1943 ----------------------------                                                       $17, 387 61
Gross amount expended ---     ----------              $5, 371. 97
Less reimbursements collected--------------             1, 603. 02
                                                                                                                     3, 768. 95

      Balance unexpended June 30, 1944 -----------------------                                                      13, 618. 66
Outstanding liabilities June 30, 1944------------------ - -                                                             262. 52
      Balance available June 30, 1944 -------------------------                                                     13, 356. 14
Accounts receivable June 30, 1944 -----------------------------                                                        -- 17. 94
             Unobligated balance available June 30, 1944-                                     _       --            13, 374. 08
               RIVERS AND HARBORS--MEMPHIS, TENN., DISTRICT                                                                   739
Amount allotted in July 1944.                     ------------------------------                                      $10, 000. 00
          Amount available during fiscal year 1945_-----                                                 ---           23, 374. 08
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1         --------------                                                                    10, 000. 00
  1Exclusive of available funds.

5. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                     " SUBMITTED

                                                              For last full          Cost and expenditures to           Estimated
                                                              report see                    June 30, 1944               amount re-
                    Name of project                            Annual            -                                       quired to
                                                                 Reportco
                                                                   for-              New York         Maintenance        complete

1. Arkansas River, Ark., and Okla. (below Pine
      Bluff, Ark.) - -1943                                                           $380, 966. 95 $2, 913, 897.66          (1)
2. St. Francis and L'Anguille Rivers and Black-
    fish Bayou, Ark_-------------------------- 1943                                    92, 000. 34     300, 449.43          (1)
3. Obion River, Tenn.2 -1911                       - -            97                   28, 716. 775 ..                      (1)
4. Forked
     Fork Deer
            _....... River Tenn.,  including South
                             ..   . ...   ..----------------------------------
                                                                 1912                  25,000.00         12,818.50          (1)


  1 Existing project is for maintenance only.
  2 Recommended for abandonment in H. Doc. No. 467, 69th Cong., 1st sess.
  a Completed.

             6. PLANT ALLOTMENT, MEMPHIS, TENN., DISTRICT
                                            Cost and finanotal sumnary
Undistributed costs June 30, 1944_      _------------_          $152, 257. 52
Plus accounts receivable June 30, 1944 ------------------------    11, 931. 67
      Gross total costs to June 30, 1944_ - -------         164, 189. 19
Minus accounts payable June 30, 1944_------------------------6, 121. 13
     Net total expenditures ---------------------------                                              __158,                06&8. 06
Unexpended balance June 30, 1944---------------------115,                                                                  355. 76
           Total amount appropriated to June 30, 1944--------------273,                                                    423. 82

    Fiscal year ending June 30                  1940              1941                   1942             1943             1944

Total expended-----.-.---------$164,117. 86                  -$19, 853. 54           -$16, 052. 64     -$29, 011.53     -$27, 537.27
Allotted-.--------------------20, 000. 00 ........----------------------

Balance unexpended July 1, 1943_----------------------------$87,
                                                                          818. 49
Gross amount expended ------------------------         $156, 885. 10
Less:
     Reimbursements collected ----     . $184, 154. 37
     Receipts from sales--------------         268. 00
                                                        184, 422. 37
                                                                     -27, 537. 27
      Balance unexpended June 30, 1944---------------------115,                                                            355. 76
Outstanding liabilities June 30, 1944---------------------------6,                                                         127. 95
      Balance available June 30, 1944-----------------------_109, 227. 81
Accounts receivable June 30, 1944_ .----.       _-__11,--         931. 67
       Unobligated balance available June 30, 1944- - ------------                                                    121, 159. 48
740          REPORT OF CHIEF OF ENGINEERS,                          1i. S.   ARMY,       19 4 4

Status of all investigations for navigation, called for by river and harbor acts and
                                              committee resolutions

                                                          Date trans-
            Locality                Authorization act      mitted to     Document No.         Recommenda-
                                                           Congress                               tioni

Mississippi River between         Flood Control Com-     Mar. 20,1944   H. 509, 78th Cong.,   Favorable.
Cairo, Ill., and Baton             mittee resolution,                   2d sess.
Rouge, La., for 12-foot            Mar. 8,1943.
channel (navigation and
flood control).'
Mississippi River between         Commerce Commit- _____do .__....__..do ........... Do.
Cairo, Ill., and Baton            tee resolution, Mar.
Rouge,     La.,    for 12-foot    9, 1943.
channel (navigation and
flood control).'

1 Report   was made by the Mississippi River Commission.

       7. MEMPHIS, WOLF RIVER, AND NONCONNAH CREEK, TENN.

  Location.-The work covered by this project lies within and adja-
cent to the city of Memphis in Shelby County, Tenn., on the left
bank of Wolf River and the right bank of Nonconnah Creek from the
confluence of these streams with the Mississippi River upstream for
approximate distances of 10 and 4 miles, respectively. (See U. S.
Geological Survey map of Tennessee, scale 1: 500,000, and Mississippi
River Commission alluvial valley maps, scale 1: 62,500 and 1: 500,000.)
   Existing project.-The plan of improvement provides for the con-
struction of a system of levees, flood walls, and bank protection, con-
sisting of the following features: About 22,200 feet of earth levee and
two concrete railroad floodgates along the right bank of Nonconnah
Creek, extending from high ground near Tennessee Chute south of
Riverside Park to high ground at Bodley Avenue east of Prospect
Street; about 14,200 feet of concrete flood wall and 32,050 feet of earth
levee along the left bank of Wolf River, extending from downtown
Memphis to high ground near Douglass Park; construction of six new
pumping stations and eight storage reservoirs with appurtenant works
for the disposal of. interior drainage; the construction of a culvert
under North Bellevue Boulevard near Cypress Creek for the enlarge-
ment of the Cypress Creek Reservoir. The project will provide pro-
tection, with 3 feet freeboard, for the city of Memphis and adjacent
areas against a Mississippi River flood of 54.5 feet stage, or 4.1 feet
higher than the maximum flood of record, which occurred in February
1937. The project was adopted by the Flood Control Act approved
August 28, 1937, and so modified by the War Department Civil
Appropriation Act approved June 28, 1939, that the cost of providing
pumping stations and outlet works for interior drainage shall be
borne by the United States. The estimated cost of construction is
$9,000,000.
   Local cooperation.-See page 7 for requirements. General assur-
ances given by the city of Memphis and Shelby County, Tenn., were
approved by the Secretary of War on August 2, 1938. The rights-
of-way for flood-protection works along Nonconnah Creek were
accepted on March 29, 1939. The rights-of-way for the section 4
levee, Cypress Creek pumping station and Cypress Creek Reservoir
were accepted on August 27, 1940; and for section 2, Wolf River
             FLOOD CONTROL-'MEMPHIS, TENN., DISTRICT                          741
levee, and section 3, Wolf River flood wall, were accepted December
4, 1941.
   Operations and results during fiscal year.-Planning and design
were continued during the year for sections of the project not under
construction.
   The electrical installations at Nonconnah pumping station were
completed. Rain-wash repairs on section 8 levee were completed by
hired labor. All work in connection with section 8 levee, Nonconnah
Creek pumping station and reservoir was completed during the year,
and these features of the project were turned over to local interests
for maintenance and operation.
   The electrical installations at the Cypress Creek pumping station
were completed. By contract 136,465 cubic yards of earth blanket were
placed on the hydraulic levee in section 4. During the year small
hired labor forces made rain-wash repairs on section 4 levee and
accomplished a part of the repairs to the outlet channel of the Cypress
Creek pumping station.
   The costs for the year were $211,863.52, and the expenditures were
$234,151.75, all new work.
   Condition at end of fiscal year.-Plans and specifications were com-
pleted and approved for section 2 levee and section 3 floodwall. Pre-
liminary plans were started for section 5 floodwall. Section 6 levee
plans were completed. Section 7 levee, reservoirs, and pipe-line plans
were approximately 57 percent complete. Plans being prepared by
contract for remaining pumping stations are approximately 17 percent
complete.
   Section 8 levee Nonconnah pumping station and reservoir were
completed and were turned over to local interests for maintenance
and operation on March 15, 1944.
   Section-4 levee, including earth blanket placed on hydraulic section,
was complete, except for minor rain-wash repairs.
   The Cypress Creek pumping station was complete, except for altera-
tions to trash racks, minor adjustments to one pump motor, and repairs
to the outlet channel.
   New construction on this project is being deferred in accordance
with the present Federal policy limiting construction during the war.
   The total costs to June 30, 1944, were $3,767,630.15, and the total
expenditures were $3,750,985.94, all for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
$204,714.06, and accounts receivable, $90.72, plus the sum of $23,000
allotted in July 1944, a total of $227,804.78, will be applied as follows:
Accounts' payable June 30, 1944_     --    _-------          ____-     $16, 486. 32
New work:
    Completion of levee repairs to section 4 _--       $1,   500. 00
    Completion and security of Cypress Creek pump-
      ing station_-           _ _---    -        -____ 18,   500.00
    Completion of detailed plans ana design and speci-
      fications for remaining items ---------------- 191,    318. 46
                                                                       211, 318. 46

        Total for all work_ ---------------------------------          227, 804. 78
  No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime
construction.
742              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

                                                   Cost and financial summary
Cost of new work to June 30, 1944-_-- --- - --               .     $3,                                                  767, 630. 15
Cost of maintenance to June 30, 1944_
       Total cost of permanent
Undistributed costs June 30, 1944
                                                         Wo6rk
                                      to June 30, 1944- ---. -----
                                      -----------
                                                                    3,                                                  767, 630. 15
                                                                                                                          -248.& 61
       Net total cost to June 30, 1944-----------------------3,                                                         767, 381. 54
Plus accounts receivable June 30, 1944----------------------- -                                                               90. 72
       Gross total costs to June 30, 1944--------------- ----- 3,                                                       767, 472. 26
Minus accounts payable June 30, 1944 -----------------------                                                             16, 486. 32
      Net total expenditures ------------------------------                                                        3, 750, 985. 94
Unexpended balance June 30, 1944 --------------------------                                                           204, 714. 06
      Total amount appropriated to June 30, 1944 ------------                                                      3, 955, 700. 00


     Fiscal year ending June 30                       1940             1941               1942              1943             1944

Cost of new work -------------                     $677, 322.21   $1, 131, 646.23 $1, 099,416. X4        $515, 958.41      $211, 863.52
                  ............----.......
Cost of maintenance-------------                                    ......--------------..---------------------------..----------
Total expended----------------..................    671,507.37     1,082, 218. 77   1, 313, 280.52        327, 835.62       234,151.75
Allotted ----------------------................     750,000.00      897,000.00        275,000.00         -1,874, 600 ------------



Balance unexpended July 1, 1943__.-.-                                                                                  $438, 865. 81
Gross amount expended_    - --------                                                      $239, 254. 88
Less reimbursements collected-----------------                                               5, 103. 13
                                                                                                                        234, 151. 75

      Balance unexpended June 30, 1944_                                                                                 204, 714. 06
Outstanding liabilities June 30, 1944 -----------                                            $2, 18&8. 84
Amount covered by uncompleted contracts .       ..                                           39, 493. 50
                                                                                                                         41, 682. 34
      Balance available June 30, 1944_-------                                                              ---          163, 031.   72
Accounits receivable June 30, 1944_---------                                                                     ---          90.   72
      Unobligated balance available June 30, 1944                                      ------------                     163, 122.   44
Amount allotted in July 1944_----------                                                                  ----            23, 000.   00
              Amount available during fiscal year 1945                              ---          -----                  186, 122. 44

Amount (estimated) required to be appropriated for completion
  of existing project 1--------  -----------------------------                                                     5, 021, 300. 00
1Exclusive of available funds.

     8. NORTH LITTLE ROCK TO GILLETT, ARK. (BELOW PLUM BAYOU)

   Location.-The work covered by this project is on the left .bank of
the Arkansas River, between Sherrill and Gillett, Ark. (See Mis-
sissippi River Commission alluvial valley maps, scale 1: 62,500 and
scale 1: 500.000.)
   Existing,project.-The plan of improvement provides for the con-
struction of approximately 47.5 miles of new levee and enlargement
of existing levees along the north bank of the Arkansas River between
Sherrill and Gillett, Ark., to provide protection from the floodwaters
of the Arkansas River and backwaters of the Mississippi- River-for
agricultural lands and communities lying north of the Arkansas
River. This improvement comprises the lower portion of the more
comprehensive project of flood control, extending from North Little
Rock to Gillett. The work involves the handling of approximately
                    FLOOD CONTROL---MEMPHIS,                           TENN., DISTRICT                       743

5,925,000 cubic yards of earthwork and the construction of approxi-
mately 19 drainage structures through the levee. The project grade
of the levee is 3 feet below that of the opposite levee on the south
bank of the Arkansas River, which protects the entire Tensas Basin.
This project will greatly reduce the frequency of inundations of lands
on the north bank of the Arkansas River. The existing project was
authorized by the Flood Control Act approved June 22, 1936. The
estimated cost of construction, as authorized, for the whole project
from North Little Rock to Gillett, was $2,424,400, of which $1,404,400
was the amount estimated for the construction below Plum Bayou
 (Sherrill to Gillett). The estimated cost of construction, revised in
1940, is $1,021,100.
   Local cooperation.-See page 7 for requirements. Full require-
ments of local cooperation have been fulfilled down to Bayou Meto.
Below Bayou Meto the Farelly Lake levee district has provided pre-
liminary assurances but no rights-of-way.
   Operationsand results during fisoal year.-None.
   Condition at end of fiscal year.-At the end of the fiscal year, the
project was 91 percent complete. The work remaining to complete
the project is the completion of the levees below Bayou Meto. The
costs, all new work, to June 30, 1944, were $874,462.22, of which $834,-
372.76 was from regular funds, and $40.089.46 was from Emergency
Relief funds. The expenditures were $875,079.93.
   Proposed operations.-None for 1945.
   No additional funds can be expended during fiscal year 1946 in view
of the existing Federal policies on wartime construction.
                                       Cost and financial summary
Cost of new work to June 30, 1944_              ------ -_          1 $874, 462.                                   22
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944                         -----------
                                                                     1 874, 462.                                  22
Plus accounts receivable June 30, 1944_-------                 ---          617.                                  71
       Gross total costs to June 30, 1944_-    ----        -----       875, 079.                                  93
Net total expenditures _____--------________-             --         1875, 079.                                   93
Total amount appropriated to June 30, 1944 ------------------ 1875, 079.                                          93


   Fisealyear ending June 30               1940            1941            1942            1943            1944

Cost of new work ...-..-------------. $409,070.
                                              40    $2, 771.51            $1,829.35      $28,981.20 .------------
Cost of m aintenance--.... . .-------------- --------..
                                                 . . . . .                 .. .        . . .     .-  --   --
                                                                                                       . . .

Total expended----------------          425, 666 87        2,845. 64       1,829.35       29, 598. 91

Allotted__---------------------125, 000.00             -171,000.00        25, 000.00                          ----
                                                                                                             -$9.53


Balance unexpended July 1, 1943 _    __--       -__---------                                                $9. 53
Deductions on account of revocation of allotment-- --                                                        9. 53
Balance unexpended June 30, 1944..
Accounts receivable June 30, 1944_ - - _-----------617.                                                         71
Unobligated balance available June 30, 1944---         --------                                            617. 71

Amount (estimated)     required to be appropriated for completion of
                  2- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -        146, 000
existing project
  1Includes $40,089.46 Emergency Relief funds.
  2 Exclusive of available funds.;
744      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                             1944

           9. AUGUSTA TO CLARENDON, WHITE RIVER, ARK.

   Location.-The works covered by this project are principally on
the left (east) bank of the White River, between the towns of Augusta
and Clarendon, in Arkansas. A small part of these works, however,
is located at the town of Georgetown, on the right (west) bank of
the White Rivers for the purpose of providing local flood protection
at that point. (See Mississippi River Commission alluvial valley
maps, scale 1: 62,500 and scale 1: 500,000.)
   Existing project.-The plan of improvement provides for the con-
struction of approximately 40.3 miles of new levee and enlargement
of existing levees along the east bank of the White River between
Gregory Point and Clarendon, Ark., to provide protection from the
flood waters of the White River for agricultural lands and communi-
ties lying in Woodruff, Prairie, and Monroe Counties, east of that
stream. It also provides for the construction of a local protection
levee at Georgetown, on the west bank of White River, and the con-
struction of a pumping plant at that point, and drainage outlet
structures both at Georgetown and in the east bank levee. The esti-
mated cost of construction of the project is $2,800,000, of which amount
$36,500 is for the work at Georgetown. The estimated cost of lands
and damages is $710,000. The existing project was authorized by the
Flood Control Act approved August 18, 1941 (H. Doc. 98, 76th Cong.,
1st sess.).
   Local cooperation.-See page 7 for requirements. Local interests
state that they expect to be able fully to meet all the stipulated
requirements of local cooperation.
   Operations and results during fiscal year.-Surveys were made and
office studies were initiated.
   The costs for the year were $62,615.38, and the expenditures were
$62 107.57; all new work.
   Condition at end of fiscal year.-Surveys were approximately 90
percent complete, and planning was under way.
   The total costs to June 30, 1944, were $62,615.38 and the total ex-
penditures were $62,107.57, all for new work.
   Proposed operations.-The balance unexpended June .30, 1944,
$3,178.21, plus the sum of $43,000 allotted in July 1944, a total of
$46,178.21, will be applied as follows:
Accounts payable June 30, 1944               ___$507.                                         81
Completion of surveys and completion of advance planning, including
  detailed plans and specifications for new work_-----------------                 45, 670. 40
       Total for all work___---      ------------                                  46, 178. 21
   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                            Cost and financial summary
Cost of new work to June 30, 1944        _$62,                                        615. 38
Cost of maintenance to June 30, 1944_               _____                      -
       Total cost of permanent work to June 30, 1944        -----------            62, 615.   38
Minus accounts payable June 30, 1944_     -    ----                   ------           507.   81
       Net total expenditures _      -           -             -62,                    107.   57
Unexpended balance June 30, 1944                                                    3, 178.   21
       Total amount appropriated to June 30, 1944-                         .       65, 285.   78
                     FLOOD CONTROL---MEMPHIS,                             TENN., DISTRICT                          745

  Fiscal year ending June 30                 1940             1941             1942              1943          1944

                          --------------..............------------....--------------
Cost of new work..---...................                                             .........------------- $62,615.38
Cost of maintenance---....-------------------                   ----------------------------------------
Total expended------                   -------------------------------------------------------                 62, 107. 57
Allotted--------------------------......................-------------------------------$36,000                 29,285.78


Balance unexpended July 1, 1943 -$36,                                                                          000.00
Amount dllotted from War Department Civil Ap-
  propriation Act approved May 23, 1941-------- $33, 981. 38
Amount allotted from War Department Civil Ap-
propriation Act approved Apr. 28, 1942.---------- 2, 304. 40
                                                                                                           36, 285. 78

      Amount to be accounted for_ ________------72,                                                            285. 78
Deductions on account of revocation of allotment---------                                                    7,000. 00

       Net amount to be accounted for-----------------                                                     65, 285. 78
Gross amount expended_----------------------- $62, 461. 26
Less reimbursements collected--   --------            353. 69
                                                                                                           62, 107. 57

      Balance unexpended June 30, 1944---------------------                                                  3, 178. 21
Outstanding liabilities June 30, 1944-------------------------                                                  507. 81

     Balance available June 30, 1944_                                                                       2, 670. 40
Amount allotted in July 1944_ ____                                -----                                    43, 000. 00

          Amount available during fiscal year 1945---------------                                          45, 670. 40

Amount (estimated) required to be appropriated for completion of
existing project 1           ----------------                                                          2, 691, 700. 00
  1 Exclusive of available funds.

                        10. DE VALLS BLUFF, WHITE RIVER, ARK.
   Location.-The works covered by this project are on the right (west)
bank of the White River, at the town of De Valls Bluff, in Arkansas.
 (See Mississippi River Commission Alluvial Valley maps, scale
1: 62,500 and scale 1: 500,000.)
   Existing project.-The plan of improvement provides for the rais-
ing and extension of the present small front levee at De Valls Bluff,
with its grade equivalent to 37.8 on the De Valls Bluff gage or at 191
feet above mean Gulf level. Between high-ground points this levee
would be about 660 feet in length along the De Valls Bluff front, and
would insure a freeboard of 3 feet over the experienced 1927 flow line
 (the greatest of record at this locality) and a grade 3 feet higher
than the project levee grade on the opposite bank. The work involves
the handling of approximately 10,000 cubic yards of earthwork, the
construction of a railroad floodgate structure and three drainage out-
let structures through the levee, and the construction of a pumping
plant at an estimated construction cost of $47,500 and $160 for lands
and damages. The existing project was authorized by the Flood Con-
trol Act approved August 18, 1941 (H. Doc. 98, 76th Cong., 1st sess.).
   Local cooperation.-See page 7 for requirements. Local interests
have stated that they will fully meet all the stipulated requirements
of local cooperation.
   Operations and results during fiscal year.-Surveys were made and
work was accompliched on the preparation of plans.
   The costs for the year were $3,214.62 and expenditures were $2,264.96.
746           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                 1944

   Conditionat end of fiscal year.-Preparation of plans and specifica-
tions was in progress.
   The total costs to June 30,1944, were $3,214.62 and the total expendi-
tures were $2,264.96, all for new work.
   Proposed operations.-The balance unexpended June 30, 1944, $4,-
735.04, plus the sum of $1,000 allotted in July 1944, a total of $5,735.04,
will be applied as follows:
Accounts payable June 30, 1944      -------------------------                                                                        $949. 66
Continue work on surveys and plans- - _-    ---------                                                                               4, 785. 38
            Total for all work_ ___----------------5,735.                                                                                       04
   No additional funds can be profitably expended during the fiscal
year 1946, in view of the existing Federal policies on wartime con-
struction.
                                            Cost and financial summary
Cost of new work to June 30, 1944____--                                         ------                                  -$3,             214. 62
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944--------------                                                                   3, 214. 62
Minus accounts payable June 30, 1944----------------------------                                                                         949. 66

      Net total expenditures---- ----------                                                                                  -2,      264. 96
Unexpended balance June 30, 1944-----------                                                                    ---                 4, 735. 04
            Total amount appropriated to June 30, 1944----------------                                                              7, 000. 00

      Fiscal year ending June 30                 1940              1941                  1942                    1943                    1944

Cost of new work-------------------....        ..        --------------...-------------- --------------
                                                                                                ..                                       $3,214.62
Cost of maintenance ......                  ------.-.              - - --.          - --..  . .       .   ..     . .    ..         . .     . . .
Total expended----------------------..................    -----------------------------------------                                      2,264.96
Allotted--------------------------------------------                                 ------------------------                            7,000.00


Amount allotted from War Department Civil Appropriation Act ap-
  proved Apr. 28, 1942_ ___-------------------------------------$7,000.00
Gross amount expended---                  ----------                          $2, 386. 34
Less reimbursements collected_-------                                     ---     121. 38
                                                                                                                                   2, 264. 96
      Balance unexpended June 30, 1944__-------____                                                                                4, 735. 04
Outstanding liabilities June 30, 1944_---------                                                                 ---                   949. 66
     Balance available June 30, 1944------------                                                                                   3, 785. 38
Amount allotted in July 1944_----------                                                                    ----                    1, 000. 00
           Amount available during fiscal year 1945 ------------                                                                   4785.
                                                                                                                                   4,    38
Amount (estimated)      required to be appropriated for completion of
existing project 1- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - _ 39, 500. 00
  1   Exclusive of available funds.
11. SNAGGING AND CLEARING UNDER AUTHORITY OF SECTION 2 OF
  THE FLOOD CONTROL ACT APPROVED AUGUST 28, 1937, AS AMENDED

  The Flood Control Act approved August 28, 1937, as amended by
the Flood Control Acts approved August 11, 1939, and August 18,
1941, authorized the allotment of not to exceed $500,000 from the flood
control appropriations for any one fiscal year for the removal of accu-
                               FLOOD CONTROL--- MEMPHIS, TENN., DISTRICT                                                                          747
"mulated snags and other debris from, and the clearing and straight-
ening of channels in navigable streams and tributaries thereof when
such work is advisable in the interest of flood control; provided that
not more than $25,000 shall be allotted for this purpose for any single
tributary from the appropriations for any one fiscal year.
   Channel clearance work in the Memphis district, consisting of the
removal of snags, drift, and other debris by hired labor with Govern-
ment plant was done on two streams as follows: Hatchie River (and
its tributaries) over a distance of 148.25 miles; Obion River (and its
tributaries) over a distance of 192.78 miles, which includes 1.53 miles
excavated by Government-owned dragline on the South Fork of
Forked Deer River (a tributary of the Obion). The above work was
accomplished during the fiscal years 1938 to 1942, inclusive. There
was no cost during the fiscal year. The expenditures were $3.81.
   Work was suspended December 1942, in view of the existing Federal
policies on wartime construction.
   The total costs to June 30, 1944, were $280,626.31, of which $240,-
626.31 was from regular funds and $40,000 from Emergency Relief
funds. Total expenditures were $280,626.31.
                                                      Cost and financial summary
Cost of new work to June 30, 1944----_ 1--------------                                                                            1 $280, 626. 31
Cost of maintenance to June 30, 1944_-------. ----.                                                                 _          -----
       Total cost of permanent work to June 30, 1944-           1280, 626. 31
Net total expenditures_--      --    __-------               -1 280, 626. 31
Total amount appropriated to June 30, 1944_------------------ 1 280, 626. 31

      Fiscal year ending June 30                        1940              1941                      1942                   1943               1944


Cost of new work_
                    ............
Cost of maintenance----
                                   ....   ___   ...   $47, 711.34     $38, 308. 31              $25, 225.87
                                                                    .......------------------------------------------.
                                                                                                                         $33, 245.99--       --
Total expended.--------_-_------46, 494. 61                             37, 651.16                24,544.93               36, 019. 71                $3.81

Allotted._...............-......                       49,431.17        45,000. 00                42,000.00               13,000. 00         -5,285.    78



Balance unexpended July 1, 1943_-----------_                                                                                            $5, 289. 59
DedUctions on account of revocation of allotment------                                                         ---------                 5, 285. 78

      Net amount to be accounted for__--                                                      --------                                           3. 81
Gross amount expended_-------------                                                                   -                  ---             -       3. 81
   1 Includes $40,000 Emergency Relief funds.

12. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
         FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work, or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood. Pursuant to this act, $25,000 was allotted to the Memphis dis-
trict in June 1943 and $108,350 during fiscal year 1944.
   The following emergency work was accomplished during the fiscal
year: Strengthening Tennemo-Booth's Point roadway embankment,
involving placement of 190,375 cubic yards of earth at a cost of
$64,386.11; protection of Tennemo-Booth's Point roadway embank-
ment, $21,081.81; protection of Spur Dike levee station 5/5 +00, Tip-
748             REPORT OF CHIEF OF ENGINEERS, U.                                                        S. ARMY,                      1944

tonville-Obion River levee at a cost of $2,768.43; and emergency flood
protection on Memphis, Wolf River, and Nonconnah Creek, Tenn.,
project, at a cost of $1,504.66; a total cost of $89,741.01. Expendi-
tures were $73,819.50. In addition, expenditures were made in the
amount of $25,000 for costs incurred during the floods of May and
June 1943. The balance unexpended on June 30, 1944, amounting to
$34,530.50 will be applied as needed during fiscal year 1945 to the
payment of expenses to be incurred under this heading.
  In addition to the above, funds were allotted under the provisions
of section 9 of the Flood Control Act approved June 15, 1936, for
emergency flood-control work in the Memphis district. For further
information, see Mississippi River Commission report, emergency work
on tributaries of Mississippi River.
                                                 Cost and' financiat summary
Cost of new work to June 30, 1944_
Cost of maintenance to June 30, 1944------------------ -----                                                                           $114,741.01
             Total cost of permanent work to June 30, 1944------------                                                                    114, 741. 01
Net total cost to June 30, 1944------------------------__                                                                                 114, 741. 01
Plus accounts receivable June 30, 1944----------- -------------                                                                             4, 355. 10
      Gross total costs to June 30, 1944 ----------------                                                                                 119, 096. 11
Minus accounts payable June 30, 1944-------------------------                                                                              20, 276. 61
      Net total expenditures ------------------------------                                                                                98, 819. 50
Unexpended balanbe June 30, 1944---------------------                                                                                      34, 530.50
            Total amount appropriated to June 30, 1944-- ------------                                                                     133, 350. 00

     Fiscal year ending June 30                       1940                  1941                     1942                      1943                   1944

Cost of new work-...           . . .     . . . . .      . . . . .        . . . . .    ..        . . . .       . ..       . .     . . . . .           . . . . .
Cost of maintenance -------...........--------------.....--------------..-------------                                           $43.25      $114, 697.76
Total expended ------------
                 ....                                   --------------               --------               --------------                           98. 819. 50
Allotted..................-------------.........--.....-----------------       ...--.----..----------------                  25.000.00               108, 350.00


Balance unexpended July 1, 1943_                              _$25,                                                                                   000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941 ------------- $10, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942               20, 000. 00          --------------
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940               78, 350. 00          --------------                                                   10V., VV.
                                                                                                                                                .50. 00
                                                                                                                                                  . v.


       Net amount to be accounted for_                                        ---------                                                   133, 350. 00
Gross amount expended _- _- --                                                                   -          $100, 042. 08
Less reimbursements collected_ _---------                                                                      1, 222. 58
                                                                                                                                           98, 819. 50

      Balance unexpended June 30, 1944___-    -   ------------                                                                             34, 530. 50
Outstanding liabilities June 30, 1944-$20,                   459. 85
Amount covered by uncompleted contracts ----------- 13, 045. 00
                                                                                                                                           33. 504. 85
                                                                                                                                             v   ,    vv     .   vv




      Balance available June 30, 1944-------------------------                                                                               1,025. 65
Accounts receivable June 30, 1944                                                                                                               355, 10
                                                                                                                                           4,4-------------------------

             Unobligated balance available June 30, 1944_--------------                                                                      5, 380. 75
            FLOOD CONTROL---r MEMPHIS, TENN., DISTRICT                  749
13. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF PUB-
      LIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods which
occurred in the spring of 1943 and again in the spring of 1944, Con-
gress, in the act approved July 12, 1943, Public No. 138, Seventy-eighth
Congress, and in the act approved May 29, 1944, Public No. 318, Sev-
enty-eighth Congress, authorized the amounts of $10,000,000 and $12,-
000,000, respectively, to be appropriated as emergency funds to be
expended under the direction of the Secretary of War and the super-
vision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See p. 9 for details.)
Pursuant to the act of July 12, 1943, the sum of $400,000 was allotted
for emergency flood-control work in the Memphis district during fiscal
year 1944.
   Pursuant to the act approved July 12, 1943, emergency work was
accomplished as follows: Emergency repairs to the Tiptonville-Obion
River levee involving placement of 170,483 cubic yards of earth work,
3,847 cubic yards of stone riprap, and three pipe culverts, at a cost of
$97,486.72; emergency flood protection along Mississippi River in
April and May 1944 at a cost of $9,092.21; emergency repairs along
the Arkansas River, North Little Rock to Gillett (below Plum Bayou),
"involving placement of 364,463 cubic yards of earth work and one
culvert at a cost of $115,627.62; and emergency work along the White
River in Woodruff, Monroe, and Prairie Counties consisting of 165,913
cubic yards of earth work and repairs and reconditioning of weak
sections at a cost of $137,525.78. The total costs were $359,732.33,
and the expenditures were $392,976.01 for emergency flood-control
work. The balance unexpended on June 30, 1944, amounting to
$7,023.99, will be applied as needed during the fiscal year 1945 to the
payment of expenses incurred under this heading.
   In addition, funds in the amount of $250,000, allotted to the Mem-
phis district for emergency repairs pursuant to the act approved May
29, 1944, will be applied during the fiscal year 1945 to emergency repair
work necessitated by the floods which occurred in the spring of 1944.
                         Cost and financial summary
Cost of new work to June 30, 1944-__--.----_---   ----..---------
Cost of maintenance to June 30, 1944- ----------------------- $359, 732. 33
       Total cost of permanent work to June 30, 1944------------359, 732. 83
Plus accounts receivable June 30, 1944------------------------38, 443. 44
      Gross total costs to June 30, 1944----------------------398, 175. 77
Minus accounts payable June 30, 1944-------------------------5,    199. 76
      Net total expenditures -------------------------------     392, 976. 01
Unexpended balance June 30, 1944----------------------------7,        023. 99
      Total amount appropriated to June 30, 1944 -------------- 400, 000. 00
750        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                  1944


   Fiscal year ending June 30                    1940              1941                 1942                   1943                1944

Cost of new work.............       .....                    . .... . .............--------------
Cost of maintenance------------- --------------              ------------- ---- --------------------                          $359,732.33
Total expended------                  -------------------------------------                            --------------             392, 976.01
Allotted-------------------------                            ----------       --------------------------------                    400,000.00


Amount allotted from Second Deficiency Appropriation Act ap-
proved July 12, 1943--------------------------------------$900, 000. 00
Deductions on account of revocation of allotment --------------- 500, 000. 00

       Net amount to be accounted for ------------------------                                                              400 000. 00
Gross amount expended_------------------           $735, 468. 99
Less reimbursements collected --------------------  342, 492. 98
                                                                                                                            392, 976. 01

      Balance unexpended June 30, 1944-----------------------                                                                 7,023. 99
Outstanding liabilities June 30, 1944_ ------------------ ____                                                                5,762. 75
      Balance available June 30, 1944----             -------
Accounts receivable June 30, 1944--- ------------------------
                                                                                                       -     ____             1  261. 24
                                                                                                                             38, 443. 44
     Unobligated balance available June 30, 1944 --------------- 39, 704. 68
Amount allotted in July 1944 --     ------------------------     250, 000. 00

         Amount available during fiscal year 1945-----------------289, 704. 68

14. PRELIMINARY                   EXAMINATIONS, SURVEYS,                                        AND CONTINGENCIES
                                      FOR FLOOD CONTROL

  The cost of work during the fiscal year was $16,137.89. The ex-
penditures were $15,890.70. The unexpended balance on June 30,
1944, $19,109.30, and accounts receivable, $8.68 plus an allotment of
$90,000 made in July 1944, a total of $109,117.98, will be applied as
needed during the fiscal year 1945 to payment of expenses to be
incurred under this heading. The additional sum of $50,000 can be
profitably expended during the fiscal year 1946.
                                               Cost and financial summary
Cost of new work to June 30, 1944_
Cost of maintenance to June 30, 1944_---------------                                                                        $47, 528. 42
       Total cost of permanent work to June 30, 1944                                                  ---------              47, 528. 42
Plus accounts receivable June 30, 1944- --------------                                                      -------                8. 68
      Gross total costs to June 30, 1944-___   ------        ---                                                             47, 537. 10
Minus accounts payable June 30, 1944_        ---------------                                                                     255. 87
         Net total expenditures --                                                                -47,                             281. 23
Unexpended balance June 30, 1944___-                               ----                                      --
                                                                                                            ____             19, 109. 30
         Total amount appropriated to June 30, 1944--------------                                                            66, 390. 53


    Fiscal year ending June 30                    1940              1941                 1942                  1943                1944

C ost of n ew work ....
                      ........ .                     .   ---

Cost of maintenance     ........------------    $29,688.06           $204.42                -           -     --- -----            i- 137.89
                                                                                                                                  $1(,

Total expended    ................ 30, 398. 23                            558. 40                                                  15, 890. 70

Allotted ........            ......
                       ---.......                 3, 500. 00--------                -- $12, 109. 47              $15, 000          20, 000. 00
                        FLOOD CONTROIr---MEMPHIS,                                         TENN., DISTRICT                                  751
Balance unexpended July 1, 1943-      --        ----------                                                                  $15, 000. 00
Amount allotted from War Department Civil Appropriation Act
   approved Apr. 28, 1942__ ---         ------------                                                                          20, 000.00
        Amount to be accounted for_- __ - ----------                                                                          35, 000. 00
Gross amount expended-     -- ---------                    $16, 347. 61
Less reimbursements collected ---------------------             456. 91
                                                                                                                              15, 890. 70
       Balance unexpended June 30, 1944_-                                             --------                                19, 109. 30
Outstanding liabilities June 30, 1944                        ---------------                                 $56. 34
Amount covered by uncompleted contracts                                      ---------                    9, 158. 03
                                                                      9, 214. 37
      Balance available June 30, 1944_          - ------     --  --  9, 894. 93
Accounts receivable June 30, 1944_-----------------------------            8. 68
      Unobligated balance available June 30, 1944 --------------     9, 903. 61
Amount alloted in July 1944 -------------------------------         90; 000. 00
     Amount available during fiscal year 1945 -----------------     99, 903. 61
Amount that can" be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1------------------------------
                                          _                         50, 000. 00
  1Exclusive of available funds.
           15. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO
                       ESTIMATES ARE SUBMITTED
                                                                   For last full Expenditures to June 30,                      Estimated
                                                                   report see              1944                                 amount
                     Name of project                                 Annual                                                    required to
                                                                     Report                                                     complete
                                                                      for-                New work             Maintenance

1. Clarendon to Laconia Circle, White River
     Basin, Ark -      ----        --    ..   --------                  1937     ----------------------------                    $8,960,000
2. Big Creek and L'Anguille River, White River
    Basin, Arkto _.1937                                                                                                                86, 400
3. Tiptonville       Obion River, Tenn                   .------------- 1941              $608, 434. 27--__-_---_                    (1)
  I Completed.

   Status of all investigations for flood control, called for by flood-control acts and
                                  committee resolutions
                                                                             Date trans-
            Locality                     Authorization Act                    mitted to           Document No.               Recommenda-
                                                                              Congress                                           tion

L'Anguille River, Ark.1       --        Flood Control Com-n
                                          mittee resolution,
                                          Sept. 18, 1944.
Little River, Mo. and Ark.,             Flood Control Comn...- ......                                ......          ..
  for flood control, particu-             mittee resolution,
  larly Big Lake area and                 Feb. 23, 1944.
  Elk Chute drainage dis-
  trict, Missouri.
Meto Bayou, Ark___                 -..Flood      Control     Act,.........                         .........
                              Aug. 28, 1937.
Mississippi    River  below Flood Control Comn- _............................
Cape Girardeau, Mo., and     mittee resolution,
Obion and Forked Deer        Apr. 26, 1944.
Rivers and tributaries,
Tennessee, for flood con-
trol and drainage in Dyer,
Lauderdale, Lake, Obion,
Gibson, and Crockett
Counties, Tenn.'
Mississippi River between Flood Control Comn- Mar. 20,1944 H. 509, 78th Cong.,                                            FaVorable.
Cairo, Ill., and Baton       mittee resolution,                              2d sess.
Rouge, La., for 12-foot      Mar. 8, 1943.
channel (navigation and
flood control).'
    Do.'-----------------Commerce        Commit-- .... do............ do ..........                                            Do.
                             tee resolution, Mar.
                                         9, 1943.
Mississippi (lower) River,          Flood Control Comn- _...                    .......               .......
flood protection for the             mittee resolution,
St. Johns levee       district,         Nov. 16, 1943.
Missouri.

I Field   report being made by the Mississippi River Commission.
752      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                   1944

    IMPROVEMENT OF.RIVERS AND HARBORS IN THE
            GALVESTON, TEX., DISTRICT
   This district comprises all of Texas south of the Red River drainage
basin exclusive of the drainage basin of the Rio Grande and its tribu-
taries above and including the Pecos River, and exclusive of that part
of the Trinity River Basin above and including the Bedias Creek
Basin; that portion of western Louisiana in the Sabine River and
Lake drainage system, exclusive of the Louisiana section of the Gulf
Intracoastal Waterway and tributary waterways; and the portion of
easternNew Mexico embraced in the drainage basins of the Brazos and
Colorado Rivers. It includes the Intracoastal Waterway in Texas
from theSabine River to Brownsville.
   District engineer: Col. W. G. Saville, Corps of Engineers, to October
31, 1943; Lt. Col. Frank H. Newman, Jr., Corps of- Engineers, from
November 1 to 7, 1943 (acting); and Lt. Col. J. H. Anderson, Corps
of Engineers, since that date."
   Division engineer: Col. R. R. Neyland, Corps of Engineers, to June
8, 1944; CoL F. J. Wilson, Corps of Engineers, acting division engi-
neer, June 9 through 14, 1944. Brig. Gen. E. H. Marks, United States
Army, division engineer, since that date.
                                    IMPROVEMENTS

               Navigation                           Navigation-Continued
                                      Page                                      rage
1. Sabine-Neches Waterway,               20. Other navigation projects
       Tex---------------             752       for which no estimates are
2. Gulf Intracoastal Waterway                  submitted__                      809
      between Apalachee Bay,              21. Plant allotment-----               809
      Fla., and the Mexican                              Flood control
      border (Galveston district)._   758
3. Galveston Harbor, Tex_            769 22. Buffalo  Bayou,   Tex .    ....    811
4. Galveston Channel, Tex ....       772 23. Whitney Reservoir, Brazos
5. Channel from Galveston Har-                  River, Tex__                    816
      bor to Texas City, Tex -        774 24. Eagle Lake to Matagorda,
6. Channel to Port Bolivar,                     Colorado River, Tex ..          817
      Tex--                           777 25. Columbus, Colorado River,
7. Houston Ship Channel, Tex.        779       Tex--                            819
8. Double Bayou, Tex .....           783 26. La Grange, Colorado River,
9. Anahuac Channel, Tex .            785       Tex_                             820
10. Trinity River, Tex ....           786 27. Brady, Brady Creek, Tex     --     821
11. Cedar Bayou, Tex .......          788 28. Pecan Bayou, Tex _...              823
12. Clear Creek, Tex_                 790 29. North Concho River, Tex__          825
13. Dickinson Bayou, Tex. .           791 30. Emergency         flood-control
14. Freeport Harbor, Tex ...          792       work under authority of
15. Channel from Pass Cavallo                   the Flood Control Act
      to Port Lavaca, Tex    --
16. Port Aransas-Corpus Christi
                                      796       approved August 18, 1941_
                                          31. Emergency      flood    control
                                                                                 827

      Waterway, Tex__                 797       work under authority of
17. Corpus Christi, Tex., Chan-                 Public Law No. 138, Sev-
      niel to and including a                   enty-Eighth Congress ---        828
      turning basin at Navy               32. Preliminary     examinations,
      seaplane    base,     Encinal             surveys, and contingencies
      Peninsula _     ..              802        for flood control ... _...      829
18. Brazos Island  Harbor,   Tex _-   804 33. Other flood - control projects
19. Examinations, surveys, and                  for which no estimates are
      contingencies (general) ---     808       submitted-......._-..           830
                   1. SABINE-NECHES WATERWAY, TEX.

  Location.-This is a consolidation of the old improvements of
"Harbor at Sabine Pass and Port Arthur Canal" and "Sabine-Neches
               RIVERS AND HARBORS-GALVESTON,                                        TEX., DISTRICT                          753
Canal, including Sabine River to Orange and Neches River to Beau-
mont, Tex." Sabine Pass is on the Gulf of Mexico, approximately 58
miles east of Galveston and 280 miles west of Southwest Pass, Missis-
sippi River. It connects Sabine Lake with the Gulf of Mexico. The
Port Arthur Canal extends from near the upper end of Sabine Pass
to the Port Arthur docks at the mouth of Taylors Bayou, a distance
of 7 miles. Near its upper end the Sabine-Neches Canal joins and
extends to the month of the Neches and Sabine Rivers. The water-
way next extends up the Neches River to Beaumont and up the Sabine
River to Orange. (See U. S. Coast and Geodetic Survey Charts Nos.
517 and 533.)
   Previous projects.-The original project for improvement of Sabine
Pass was adopted by River and Harbor Act of March 3, 1875, and
subsequent projects and modifications by River and Harbor Acts of
August 2, 1882, June 3, 1896, June 13, 1902, and June 19, 1906. The
Port Arthur Canal was conveyed to the United States free of cost in
1906, and the River and Harbor Act of July 25, 1912, incorporated
it in the project. The Sabine and Neches Rivers were first improved
under the River and Harbor Acts of June 18, 1878, and March 3, 1899,
and the Sabine-Neches Canal was first improved under the River and
Harbor Acts of March 3, 1905, and March 2, 1907. The project was
enlarged by the River and Harbor Acts of February 27, 1911, July
25, 1912, March 2, 1919, and September 22, 1922.
   For further details, see page 1863 of Annual Report for 1915 for
the Sabine and Neches Rivers, Sabine Pass, and Port Arthur Canal,
and page 985 of the report for 1916 for Sabine-Neches Canal. (See
also pp. 1100 and 1105 of Annual Report for 1921 and p. 874 of
Annual Report for 1926.)
   Existing project.-The existing project dimensions provided for in
the various channels and basins comprising the waterways are shown
in the following tabulation:
                                                                                        Adopted project dimensions


             Section of Sabine-Neches Waterway, Tex.                                                                   Depth in
                                                                                                                        feet be-
                                                                                     Bottom width in feet              low mean
                                                                                                                       low Gulf
                                                                                                                          level

Sabine Pass outer bar----------------------------------------                     800     ... ...-------------------              36
Sabine Pass jetty channel ............-------------------------------             500 at inner end, increasing              (1)
                                                                                    to 800 at outer end.
Sabine Pass                                            ...-----------------------------------------
                                                                                  500 -----------------------          --         34
Sabine Pass anchorage basin.....-----------------------------                   800 by 3,000 long, exclusive                      34
                                                                                  of channel.
Port Arthur Canal_          -----------------------------------                 400--------------------------                     34
Port Arthur:
    East turning basin                                           420 by 1,800 long------------......
                              ....................................---------------------------------  34
    West turning basin ..-----..-----------------                               325 by 1,700 long----------                  - 34
Channel from Port Arthur west turning basin to Taylors Bayou 250---_----------------------                                        34
turning basin.
Taylors Bayou turning basin    ---------------------------- 150 to 1,000 by 2,900 long .                                          34
Sabine-Neches Canal:
    Port Arthur Canal to mouth of Neches River----------.....---.... --         350 --------------------------                    34
    Mouth of Neches River to mouth of Sabine River......---------. 125 --------------------------                                 30
Neches R iver, mouth to lower end of Smiths Bluff cut-off .--                   350 -------------------------                     34
Neches River, lower end of Smiths Bluff cut-off to Beaumont                     300 --------------------------                    34
turning basin, including cut-offs.
Beaumont turning basin....  --------------------------------                    500 by 1,500 long-            ---.                34
Beaumont turning-basin extension---------------.---------350 by 2,000 long------------                                 -          34
Sabine River, mouth to cut-off near Orange-----------------     125 -------------------------                                     30
Sabine River to Orange municipal wharf----.---------------
                                             ------------------
                                                                200 by 3,000 long
                                                                150 --------------------------
                                                                                                     -----------                  30
Sabine River cut-offtohighway bridge-- -                                                                                          25

  134 at inner end.    increasing to 36 at outer end.

         616634---45---pt. 1, vol. 1-             48
754         REPORT OF CHIEF OF ENGINEERS, U.                                S. ARMY,         1944

   The project also provides for two stone jetties at the Sabine Pass
entrance from the Gulf of Mexico, the western jetty to be 21,860 feet
long and the eastern jetty to be 25,270 feet long. The project further
provides for the removal of the guard lock in the Sabine-Neches
Canal and the construction of suitable permanent protective works
along the Sabine Lake frontage owned by the city of Port Arthur to
prevent dredged material from entering Sabine Lake and to prevent
the erosion of the material deposited.
  The mean tidal variation at the entrance is about 11/2 feet, at Port
Arthur about 1 foot, and at Orange and Beaumont about five-tenths
foot. The effect of the wind is often greater than that of the tide.
  The estimate of cost for new work, revised in 1944, exclusive of
amounts expended on provious projects, is $11,428,000, made up as
follows: $8,072,500 for dredging work, of which $385,500 has been
contributed in cash and useful work performed; $2,755,500 for jetty
work; and not to exceed $600,000 for the construction of suitable
permanent protective work in Sabine Lake along Port Arthur. The
latest (1938) approved estimate for annual cost of maintenance
dredging is $740,000.
  The existing project was authorized by the following river and
harbor acts:

     Acts                        Work authorized                                      Documents


July 25,1912     Existing project dimensions of jetties, a 26-foot      H. Doc. No. 773, 61st Cong., 2d sess.
                  channel through Sabine Pass, Port Arthur
                  Canal, and Port Arthur turning basin: a new
                   turning basin at Port Arthur 26 feet deep, 600
                   feet wide, and 1,700 feet long; a 25-foot depth in
                   Sabine-Neches Canal, Neches River to Beau-
                   mont and Sabine River to Orange, including
                   cut-offs and widening of the channels as recom-
                   mended by the Chief of Engineers and approved
                   by the Secretary of War, and purchase of a new
                   dredge.
Sept. 22, 1922   Deepening the channels to 30 feet from the Gulf to     H. Doc. No. 975, 66th Cong., 3d sess.
               Beaumont, with increased widths and an an-
               chorage basin in Sabine Pass 32 feet deep over an
               area of about 2,000 by 1,000 feet.
    Do....... Deepening the Port Arthur turning basin and               S. Doe. No. 152, 67th Cong., 2d sess.
               connecting channels thereto to 30 feet. For
               taking over and deepening Taylors Bayou turn-
               ing basin and connecting channel to 30 feet. For
               a 30-feet depth in the channel from the mouth
                  of Neches River to cut-off in Sabine River near
                   Orange.
Mar. 3, 1925     Removal of guard lock in Sabine-Neches Canal --        H. Doc. No. 234, 68th Cong., 1st sess.
Jan. 21, 1927    Increased widths of channels as follows: Sabine        H. Doe. No. 287, 69th Cong., 1st seas.
                   Pass jetty channel and Sabine Pass to 300 feet;
                   Port Arthur Canal to 200 feet; Sabine-Neches
                  Canal, from Port Arthur Canal to mouth of
                  Neches River, to 150 feet.    For dredging 2
                  passing places In Sabine-Neches Canal, easing
                  of bends, removal and reconstructing Port
                  Arthur field office, extending Beaumont turning
                  basin upstream 200 feet above the new city
                  wharves, and for an anchorage basin in Sabine
                  Pass, 4,500 feet long, 800 feet wide, and 30 feet
                  deep.
                RIVERS AND HARBORS-GALVESTON,                        TEX., DISTRICT                 755

     Acts                      Work authorized                                   Documents


Aug.30, 19351 A depth of 32 feet in the channels from the Gulf     Rivers and Harbors Committee Doe.
                to the Beaumont.turning basin, including all        No. 27, 72d Cong., 1st sess.
                turning basins at Port Arthur.
    Do....... Deepening the channels to 34 feet with increased     Rivers and Harbors Committee Doc.
                widths from the Gulf to the Beaumont turning        No. 12, 74th Cong., 1st seas.
                basin, including all turning basins at Port
                Arthur.
    Do-...... Construction of suitable permanent protective        Specified in act.
                works along the Sabine Lake frontage owned
                by the city of Port Arthur.
Aug. 26,1937  Taking over and maintaining channel from Sabine      Rivers and Harbors      Committee Doc.
                River to Orange municipal wharf.                     No. 3, 75th Cong.,    1st ses.
    Do....... Dredging 500 feet from the eastern end of Harbor     Rivers and Harbors      Committee Doe.
                Island and for abandonment of the channel            No. 20, 75th Cong.,   1st sess.
                south and west of Harbor Island.
June 20, 1938 Increased widths of channels from the Gulf to the    H. Doc. No. 581, 75th Cong., 3d sess.
                 Beaumont turning basin and channel connect-
                ing Port Arthur west turning basin and Taylors
                Bayou turning basin; deepening the Beaumont
                turning basin and Beaumont turning basin
                extension to 34 feet; and for dredging a new
                cut-off from Smiths Bluff cut-off to McFaddin
                Bend.
'Oct. 17,1940 Abandonment of the Orange turning basin;             S. Doc. No. 14, 77th Cong., 1st sess.
                 dredge a channel 25 feet deep, 150 feet wide,       (Contains the latest published map.)
                suitably widened on bends, to the highway
                 bridge and dredge a cut-off channel opposite
                 Orange 25 feet deep and 200 feet wide, approxi-
                 mately 2,400 feet long.


  1 Previously authorized Sept. 6, 1933, by Public Works Administration.

   The project is subject to the condition that no dredging shall be
<lone by the United States within 50 feet of existing pierheads or
established pierhead lines.
   Recommended modifications of project.-The following modifica-
tions were recommended by the Chief of Engineers under the dates
shown: March 21, 1940-Extension of the Beaumont turning basin
upstream 300 feet, thus forming a turning basin 350 by 2,300 feet, at
an estimated first cost of $10,000 in addition to that now required to
complete the existing project, with no increase in the annual cost of
maintenance; provided that no dredging shall be done by the United
States closer than 50 feet to existing pierheads or established pierhead
lines; subject to certain conditions of local cooperation (H. Doc. No.
685,  76th Cong., 3d sess.).
   November 20, 1940-Widening the Port Arthur west turning basin
to 600 feet for a distance of 900 feet from the east end, suitably flared
at the entrance, thence tapering a distance of 800 to 325 feet at the
west end at a depth of 34 feet, at an estimated first cost of $18,000, in
addition to that now required to complete the existing project, with no
increase in the present approved estimated annual cost of maintenance;
provided that no dredging shall be done by the United States closer
than 50 feet to existing pierheads or established pierhead lines; subject
to certain conditions of local cooperation (S. Doc. No. 60, 77th Cong.,
1st sess.).
756     REPORT OF CHIEF OF ENGINEERS,          U. S. ARMY,    1944

   July 16, 1941-For a channel 30 feet deep and 200 feet wide from the
Beaumont turning basin to the vicinity of the Pennsylvania Ship-
yards, no dredging to be undertaken within 50 feet of existing pier-
heads or established pierhead lines, at an estimated first cost of $27,000,
with no increase in the approved estimate of annual cost of mainte-
nance; subject to certain conditions of local cooperation (S. Doc. No.
158, 77th Cong., 2d sess.).
   Local cooperation.-Thecooperation required by the River and Har-
bor Act of June 20, 1938, provides that local interests shall furnish
free of cost to the United States rights-of-way and spoil-disposal areas
for initial work and for subsequent maintenance a-s may be required,
and release the United States from any claims for damages resulting
from the proposed dredging or disposal of excavated material. All
requirements under prior acts have been fully complied with. The
local cooperation yet to be met consists of furnishing rights-of-way,
and releases from damage liability along the channel from Port Ar-
thur west turning basin to Taylors Bayou turning basin. Local in-
terests have been unable to obtain all rights-of-way for widening the
channel to project dimensions from the Port Arthur west turning basin
to Taylors Bayou turning basin.
   Terminal facilities.-Modern terminal facilities adequate for pres-
ent commerce exist. (See pp. 839 and 840, Annual Report for 1938,
and Port Series No. 14, Corps of Engineers.)
   Operations and results during fiscal year-New work-A contract
for dredging the Sabine-Neches Canal (Port Arthur Canal to mouth
of Neches River) was completed from July 1 to December 3, 1943, by
removing 5,572,084 cubic yards of material over a channel length of
35,336 feet at a cost of $602,581.51.
   Maintenance.-Miscellaneous survey work was done, and the Port
Arthur field office was maintained. Miscellaneous surveys and inspec-
tions were made at a cost of $10,585.55.
   A contract for dredging the upper end of-Sabine Pass channel, Port
Arthur Canal and Taylors Bayou turning basin was continued from
November 3, 1943, to May 2, 1944, removing 5,568,956 cubic yards of
material over a channel length of 39,199 feet at a cost of $439,474.51.
The U. S. hopper dredge Manhattandredged the Sabine Pass outer bar
channel and outer portion of Sabine Pass jetty channel from March
16 to June 15, 1944, removing 2,414,618 cubic yards of material (bin
measurement) from a channel length of 33,000 feet at a cost of $103,-
701.31. A levee was constructed by United States plant and hired
labor around a spoil-disposal area from October 23 to December 20,
1943, at a cost of $4,269.30.
   The total cost for all work for the year was $1,160,612.18, of which
$602,581.51 was for new work and $558,030.67 for maintenance. The
total expenditures were $1,290,305.12.
   Condition at end of fiscal year.-The Sabine Pass jetties are com-
pleted to full project dimensions. The existing project for dredging
was about 99 percent completed. The work remaining to be done con-
sists of widening the channel connecting Port Arthur west turning
basin with Taylors Bayou turning basin from 200 to 250 feet, for which
local interests are unable to furnish the required rights of way.
   The controlling depths below mean low; tide in the various channels
               RIVERS AND HARBORS-GALVESTON,                                              TEX.,        DISTRICT                 757
and basins were as follows: Sabine Pass outer bar channel, 38 feet;
Sabine Pass jetty channel, 37 feet; Sabine Pass channel, 36 feet; Sabine
Pass anchorage basin, 30 feet; Port Arthur Canal, 39 feet; Port Arthur
east and west turning basins, 33 feet; channel connecting Port Arthur
west turning basin with Taylors Bayou turning basin, 36 feet; Taylors
Bayou turning basin, 33 feet; Sabine-Neches Canal, from head of Port
Arthur Canal to mouth of Neches River, 34 feet; Neches River, mouth
to Beaumont turning basin, including cut-offs and the Beaumont turn-
ing basin, 34 feet; Beaumont turning basin extension, 31 feet; Sabine-
Neches Canal, mouth of Neches River to mouth of Sabine River, 29
feet; Sabine River, mouth to cut-off near Orange, Tex., 30 feet; Sabine
River to Orange municipal wharf, 26 feet; Sabine River, cut-off to
Highway Bridge at Orange, Tex., 25 feet.
  The total cost of the existing project to June 30, 1944, was as follows:

                                                                             New work             Maintenance             Total

Regular funds                   ...................---------------------------------- $9,680,808.13 $7, 573, 944. 25   $17,254,752.38
Public Works funds         ------------------------------                              1, 363,652.47 --------            1, 363, 652.47
     Total United States funds ....      --------------------              11, 044, 460. 60    7, 573, 944.25           18, 618, 404.85
                                           __
Contributed funds (existing project)---.......             ..--.-              353, 500.00. ___---------353,                     500.00
      Total all funds ___-----------------.........                        11, 397, 960. 60        7, 573, 944.25       18, 971, 904.85



   The total expenditures were $18,597,608.15 of which $17,233,955.68
was from regular funds, including $1,965.49 for Mississippi River
flood-relief work and $1,363,652.47 from Public Works funds. In
addition $353,500 was expended from contributed funds for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $701,066.43, including an allotment of $540,000
made during July 1944, will be applied as follows:
Accounts payable June 30, 1944_           __------..-----        .- $21, 906. 09
Maintenance:
    Complete an existing contract for dredging the upper end of
      Sabine Pass Channel, Port Arthur Canal, and Taylors Bayou
      turning basin (July to September 1944)                                   -----------------
                                                                     30, 806. 43
    Dredge inland channels where necessary by contract (July 1944
      to June 1945) --------------------------------------          538, 353.91
    Dredge Sabine Pass outer bar and jetty channels with United
      States seagoing hopper dredge (April, May, and June 1945)_    105, 000. 00
    Construct levee around spoil-disposal area with United States
      plant (October, November, and December 1944) ---------           5, 000. 00
                 ----------------------------------------
             Total_                                                                                                    701, 066.43
  The additional sum of $700,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredge inland channels where necessary by contract (July 1945
      to June 1946)---     --   ----------------------            $595,000
    Dredge Sabine Pass outer bar and jetty channels with United
      States seagoing hopper dredge (April, May, and June 1946)    105, 000

             Total-------------                            -----------------------------                                   700, 000
758             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

                                           Cost and financial summary

Cost of new work to June 30, 1944                                                            -         1   $16, 225, 292. 11
Cost of maintenance to June 30, 1944_                          -_-     _           .----------               9, 953, 621. 03.
      Total cost of permanent work to June 30, 1944- -                                       ---.           26, 178, 913. 14
Undistributed costs June 30, 1944--------------------1,                                                              109. 39'

      Net total cost to June 30, 1944__                  -                                                   26, 180, 022. 53
Minus accounts payable June 30, 1944---------------------                                                         21, 906. 09
      Net total expenditures_ -2-        -                                                                 126, 158, 116. 44
Unexpended balance June 30, 1944------------------------                                                           161, 066. 43:
             Total amount appropriated to June 30, 1944---------1 26, 319, 182. 87

     Fiscal year ending June 30             X1940              1941             1942                  1943               1944


Cost of new work ...-------------          $348, 656. 45    $321, 377.23     $686, 743. 21        $735, 456. 22       $602, 581.51t
Cost of maintenance ........----      -.    331, 132.74      496, 281.62      120, 327.66          264, 763.69         558,030.6T

        Total cost-................         679, 789. 19     817, 658. 85     807, 070. 87       1,000, 219. 91      1,160, 612.18

Total expended ..................            64, 626. 88     778, 273. 95     787, 705. 21          938, 072.15      1, 290,305.12

Allotted------..........---819,                  500.00    1,023,000.00     1, 543,015.73           190, 000. 00     -122,   024. 83


Balance unexpended July 1, 1943--------------------------                                                    $1, 573, 396. 38
Deductions on account of revocation of allotment----                                --------                       122, 024. 83:

       Net amount to be accounted for                                                                          , 451, 371. 55.
                                                                                                              1---------------------
Gross amount expended_                                                                                        1, 290, 305.' 12
       Balance unexpended June 30, 1944----------------------161, 066. 43
Outstanding liabilities June 30, 1944_------------ $2, 663. 90
Amount covered by uncompleted contracts ---        50, 049. 17
                                                               52, 713. 07
     Balance available June 30, 1944_-- -------                                                                    108, 353. 36
Amount allotted in July 1944-  _540,                                                                                    000. 00
             Amount available during fiscal year 1945-------------                                                 648, 353. 36

Amount (estimated) required to be appropriated for comple-
tion of existing project-------------                   --                                                   -30,       000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2 ____..________                                                                   700, 000. 00
   I In addition, $931,006.78 was expended from contributed funds for new work.
   2Exclusive of available funds
2. GULF INTRACOASTAL WATERWAY BETWEEN APALACHEE BAY, FLA.,
        AND THE MEXICAN BORDER (GALVESTON DISTRICT)

   Location.-This section of the Gulf Intracoastal Waterway extends
,from a point on the Sabine River about 3 miles below Orange, Tex.,:
to Brownsville, Tex., a distance of about 424 miles; with a flood-
discharge channel, about 7 miles in length, in the Colorado River,
extending from Matagorda, Tex., to the Gulf of Mexico; a tributary
channel in the San Bernard River, extending from the Intracoastal
Waterway crossing to the State highway bridge some 30 miles above
the crossing; a tributary channel, in the Colorado River, extending
from the Intracoastal Waterway upstream a distance of 17 miles; a
tributary channel about 14 miles in length extending from the Intra-
coastal Waterway to Palacios, Tex.; a tributary channel about 2 miles
         RIVERS AND    HARBORS--GALVESTON,      TEX., DISTRICT       759
in length, extending from the Intracoastal Waterway to Rockport,
Tex.; and a tributary channel about 6 miles in length extending
from the Intracoastal Waterway near Port Aransas, Tex., to the town
of Aransas Pass, Tex. (See U. S. Coast and Geodetic Survey Charts
Nos. 1116, 1117, 592, 533, 1279, 1280, 12824 1283, 1284, 1285, 1286, 1287,
and 1288.)
   Previous projects--Sabine River-Galveston Bay section.-None.
   (1) West Galveston Bay and Brazos River Canal, Tew., River and
Harbor Acts of July 13, 1892, July 8, 1896, and June 13, 1902, the
latter providing for the purchase of the Galveston and Brazos River
Canal, and the act of March 2, 1907.
   (2) Channel between Brazos River and MatagordaBay, Tew., River
and Harbor Acts of June 25, 1910, and March 2, 1919. The act of
July 25, 1912, provided for the construction of highway bridges at
points where the waterway intersected existing county roads.
   (3) Channel from Pass Cavallo to Aransas Pass, Texw., River and
Harbor Acts of March 2, 1907, and July 25, 1912.
   For further details see pages 941, 944, and 947 of Annual Report for
1926, and page 845 of Annual Report for 1938.
   Existing project.-The existing project provides for a channel 12
feet deep at mean low water over a bottom width of 125 feet, with
such passing places,. widening at bends, locks or guard locks, and
railway bridges over artificial cuts as are necessary from the Sabine
River to Brownsville, Tex.; for the purchase or construction of a
20-inch pipe-line dredge; for the maintenance of a suitable flood dis-
charge channel in the Colorado River from Matagorda, Tex., to the
Gulf of Mexico; for a tributary channel 9 feet deep and 100 feet wide
in the San Bernard River, extending from the main channel to the
State highway bridge some 31 miles above the mouth of the stream;
for a tributary channel in the Colorado River 9 feet deep and 100
feet wide, extending from the main channel upstream a distance of
17 miles, with a turning basin of the same depth, 400 feet wide and
500 feet long at the head of the improvement; for a tributary channel
9 feet deep and 100 feet wide from Palacios, Tex., through Trespalacios
and Matagorda Bays to the main channel; for a tributary channel
9 feet deep and 200 feet wide from the main channel to the harbor at
Rockport, Tex., and improvement of that harbor to a depth of 9
feet; for a tributary channel 6 feet deep and 100 feet wide from the
main channel near Port Aransas, Tex., to the town of Aransas Pass,
Tex., ending in a basin of the same depth, 300 feet wide and 700 feet
long; and for operating and care of the waterway. From the Sabine
River (3 miles below Orange, Tex.) to the Port Arthur Canal, from
Port Bolivar to the west end of Galveston Channel, from Port Aransas
to Corpus Christi and from Port Isabel to Brownsville, Tex., the water-
way coincides with deep water channels improved and maintained
under other projects.
   The mean tidal variation is 0.5 foot at Orange, 1 foot at Port
Arthur, 1 foot in Galveston Bay, 1.8 feet at Freeport, 1 foot in
Matagorda Bay, 1 foot at Corpus Christi, 1.5 feet at Port Isabel, and
1 foot at Brownsville. The extreme ranges of tide under ordinary
conditions are 1 foot at Orange, 1.5 feet at Port Arthur, 2.3 feet in
Galveston Bay, 2.5 feet at Freeport, 1.5 feet in Matagorda Bay, 1.5
feet at Corpus Christi, 2 feet at Port Isabel, and 1.5 feet at Browns-
ville. The height of tides is dependent largely on the wind. Strong
760         REPORT OF CHIEF OF ENGINEERS,. U. S. ARMY,                                     1944

north winds have depressed the water as much as 2 feet below mean
low tide.
   The 9-foot tributary channel in the Colorado River is subject to
the provision that no dredging shall be done by the United States
within 50 feet of any wharf or structure excepting the highway bridge
which crosses the river at mile 8.3.
   The 9-foot tributary channel from Palacios, Tex., through Tres-
pjalacios and Matagorda Bays is subject to the provision that no dredg-
ing shall be done by the United States within 50 feet of any wharf or
structure.
   The estimate of cost of new work revised in 1943 is $19,164,000,
exclusive of amounts expended on previous projects. The latest
(1943) approved estimate for annual cost of maintenance is $1,034,000,
including $104,000 for operating and care of structures.
   The existing project was authorized by the following river and
harbor acts:

     Acts                       Work authorized                                    Documents


Mar. 3,1925     Channel 9 feet deep and 100 feet wide, from Sabine    H. Doc. No. 238, 68th Cong., 1st sess.
                 River to Galveston Bay, and for a 20-inch pipe-
                 line dredge.
Jan. 21,1927    Channel 9 feet deep and 100 feet wide, from Gal-          Do.
               veston Bay to Corpus Christi.
Aug. 26,1937 Maintenance of a flood-discharge channel in the          Senate committee print, 75th Cong.,
               Colorado River.                                          1st. sess.
June 20,1938 Channel 9 feet deep and 100 feet wide in San Ber-        H. Doc. No. 640, 75th Cong., 3d sess.
               nard River, Tex.
    Do-...... Channel in the Colorado River, 9 feet deep and          H. Doc. No. 642, 75th Cong., 3d sess.
               100 feet wide, with a turning basin.
     Do-...... Channel 9 feet deep and 100 feet wide from             H. Doc. No. 564, 75th Cong., 3d sess.
                  Palacios through Trespalacios and Matagorda
                  Bays.
     Do-...... Channel 9 feet deep and 200 feet wide from the         H. Doc. No. 641, 75th Cong., 3d sess.
                  main channel to the harbor at Rockport, and
               improvement of that harbor to a depth of 9 feet.
    Do-...... Channel 6 feet deep and 100 feet wide from the          H. Doc. No. 643, 75th Cong., 3d sess.
               main channel to Aransas Pass, Tex.
July 23,1942 Enlargement of waterway from Sabine River to             Public Law 675, 77th Cong.
               Corpus Christi and its extension to Browns-
               ville, Tex., so as to provide a depth of 12 feet and
                 width of 125 feet throughout.


  H. Doc. No. 230, 76th Cong., 1st seas., H: Doc. No. 402, 77th Cong., 1st sess., and the project documents
contain the latest published maps.

   Operating and care of the waterway was included in the project
July 1, 1935, under the provisions of the Permanent Appropriations
Repeal Act approved June 26, 1934.
   Recommended modifications of project.-The following modifica-
tions of the existing project for the Gulf Intracoastal Waterway were
recommended by the Chief of Engineers on the dates shown-
   July 5, 1939. To provide a branch channel 6 feet deep and 60 feet
wide, from a point on the waterway near Port O'Connor, Tex., into
Barroom Bay, Tex., at an estimated first cost of $6,300, with annual
maintenance of $1,000, in addition to that now required, subject to
         RIVERS AND HARBORS-GALVESTON,          TEX., DISTRICT       761
certain conditions of local cooperation (H. Doc. No. 428, 76th Cong.,
1st sess.).
   June 19, 1941. To provide a channel 9 feet deep and 100 feet wide
from the Intracostal Waterway at Port Aransas, Tex., extending
approximately 6.1 miles to a turning basin of the same depth and
300 feet wide by 700 feet long at Aransas Pass, Tex., at an estimated
first cost of $48,000, with no increase in the approved annual cost of
maintenance, subject to certain conditions of local cooperation (H.
Doc. No. 383, 77th Cong., 1st sess.).
   September 15, 1941. To provide a branch channel 9 feet deep and
100 feet wide from the Intracostal Waterway to the vicinity of
Harlingen via Arroyo Colorado with turning basin 9 feet deep, 400
feet wide and 500 feet long at the upper end, all at an estimated first
cost of $600,000, with $52,000 annually for maintenance in addition to
that now required, subject to certain conditions of local cooperation
(H. Doc. No. 402, 77th Cong., 1st sess.).
   Local cooperation.-The main channel from the Sabine River to
Brownsville, Tex., was authorized subject to the provisions that local
interests defray the cost of constructing or remodeling all highway
bridges, together with their subsequent maintenance and operation,
and furnish, without cost to the United States, all rights-of-way and
necessary spoil-disposal areas; that work on the Sabine River-Gal-
veston Bay section not be commenced prior to the receiving by the
Secretary of War of satisfactory assurances relative to the availabil-
ity, by the date of its completion, of adequate vessels, terminals, and
auxiliary equipment for the economical handling of at least 400,000
tons annually; that the general carrier service required for the New
Orleans-Sabine River section be extended to terminals on Galveston
Bay, and at Houston; and that work on the Galveston Bay-Corpus
Christi section not be commenced prior to the receiving by the Secre-
tary of War of satisfactory assurances relative to the availability, by
the date of its completion, of adequate vessels, terminals, and auxiliary
equipment for the. economical handling of at least 300,000 tons
annually.
   Local interests have complied with all of the above requirements
except those pertaining to the Corpus Christi-Brownsville section,
none of which has been complied with.
   The tributary channel in the San Bernard River was authorized
subject to the provisions that work not be undertaken without assur-
ance of extension of the Intracoastal Waterway to the river, and that
local interests furnish, free of cost to the United States, all lands,
easements, rights-of-way, and spoil-disposal areas for initial work
and for subsequent maintenance, hold and save the United States
free from any damages resulting from the improvement, and agree
to provide suitable terminal facilities, including turning basins,
wharves, etc., and to maintain an adequate portion thereof open to
the general public on equal terms to all (H. Doc. No. 640, 75th Cong.,
3d sess.).
   The tributary channel in the Colorado River was authorized sub-
ject to the provisions that local interests provide, without cost to the
United States, all lands, easements, rights-of-way, and spoil-disposal
areas for initial work and for subsequent maintenance, give assurances
satisfactory to the Secretary of War relative to the provision of nec-
essary terminal and transfer facilities, including a highway connec-
762     REPORT OF CHIEF OF ENGINEERS, U.         S. ARMY,   1944

tion, and hold and save the United States free from any damage
resulting from the execution and maintenance of the improvement
 (H. Doc. No. 642, 75th Cong., 3d sess.).
   The tributary channel to Palacios, Tex., was authorized subject to
the provisions that local interests provide and maintain a suitable har-
bor basin and furnish, free of cost to the United States, all rights-of-
way and suitable spoil-disposal areas for initial work and for subse-
quent maintenance (H. Doc. No. 564, 75th Cong., 3d sess.).
   The tributary channel to Rockport, Tex., was authorized subject
to the provisions that local interests furnish, free of cost to the United
States, necessary rights-of-way and suitable spoil-disposal areas for
initial work and for subsequent maintenance, and hold and save the
United States free from any damages resulting from the improvement
 (H. Doc. No. 641, 75th Cong., 3d sess.).
   The tributary channel to Aransas Pass, Tex., was authorized sub-
ject to the provisions that local interests furnish free of cost to the
United States, necessary rights-of-way and spoil-disposal areas for
initial work and for subsequent maintenance, and hold and save the
United States free from any damages resulting from the execution
and maintenance of the improvement (H. Doc. No. 643, 75th Cong.,
3d sess.).
   Local interests have complied with all of the above requirements
except those pertaining to the tributary channel in the Colorado
River, none of which has been complied with.
   Terminal facilities.-There are terminal facilities at Orange, Port
Arthur, Galveston, Freeport, Port Aransas, Corpus Christi, Port
Isabel, and Brownsville where this waterway coincides with channels
improved under other projects! (See Port Series, Nos. 6 and 14,
Corps of Engineers and report on Brazos Island Harbor, Tex.)
There are privately owned piers and wharves at Palacios, Rockport,
and Aransas Pass, and a municipal pier at Palacios and Aransas Pass.
The facilities are adequate for existing commerce.
   Operationsand results during fiscal year-New work.-Preliminary
surveys chargeable to dredging a tributary channeJ in the San Bernard
River were made at a cost of $17.04. Preliminary surveys chargeable
to dredging the proposed extension of the waterway from Corpus
Christi to Port Isabel, Tex., were made at a cost of $3,438.34. During
the period July 1 to September 15, 1943, the work of constructing two
floodgate structures at the Brazos River crossing, by contract was
completed and final payments amounting to $374,826.89 were made.
From July 1, 1943, to June 30, 1944, under a contract for constructing
two floodgate structures at the Colorado River crossing, 119,090 cubic
yards of material were excavated, 170,172 cubic yards of material were
placed in fills, 6,556 cubic yards of material were placed in an access
road, 159,531 linear feet of timber piles were driven, 225,845 board
feet of timber were used in framing, 25,819 cubic yards of concrete
were poured, 2,271,482 pounds of structural steel were erected, 96,821
pounds of reinforcing steel were placed, and miscellaneous work was
performed at a total cost of $1,857,103.65. From August 26, 1943, to
February 15, 1944, under a contract for constructing residences and
an office-warehouse at the Brazos River crossing, seven residences for
                   RIVERS AND HIARBORS-GALVESTON,                              TEX., DISTRICT                      763

operating personnel of the floodgates and one office-warehouse were
constructed and miscellaneous work was performed at a total cost of
$96,224.30. A total of 39,537,878 cubic yards of material was removed
from a total length of channel of 1,015,890 feet at a cost of
$3,419,724.38, as follows:

                                                                                      Cubic         Linear
Government plant                          Location                   Period          yards re-      feet of     Cost
    or contract                                                                       moved        channel
                                                                                                   dredged


Contract----------.........       Port Arthur to Port Bolivar, Aug. 14 to Dec. 13,   2,026, 589     83, 800 $211, 724.15
                                    Tex.                        1943.
     Do.                               do ....
                              ..--------------..               Aug. 23 to Dec. 25,   2, 046,081     89, 750   219, 962.62
                                                         1943.
                         S do_.
     Do---------.............            . ..   .-     Sept. 28, 1943, to
                                                 - - -- - .                          1,233,907      53, 477   166, 604.18
                                                         Jan. 2, 1944.
                          Brazos River crossing ....
      Do .....---------....                            Jury 1 to Aug. 13,              926,436       5, 659    82, 223.64
                                                         1943.
      Do_.........        San Bernard River_.......    Aug. 4 to Nov. 5,             1,000,987      51, 442   179,055.77
                                                         1943.
      Do ........... Galveston         causeway    to  Dec. 14, 1943, to Apr.        2, 411,164     35, 700   229, 449.21
                            Greens Lake.                 29, 1944.
      Do------
            .......---...Galveston Channel to Gal- Mar. 24 to June 1,                1,151, 459     18,900    108, 780.66
                            veston causeway.             1944.
      Do ........... Greens Lake to Halls Lake- Jan. 12 to Mar. 23,                  1,066,946      30,600    112, 450.55
                                                         1944.
      Do----------        Halls Lake to Bastrop Bayou Mar. 20 to June 30,            1, 797,266     45,900    129, 210.77
      Do.............                                    1944.
    * Do.............     Bastrop Bayou to Drum Bay Sept. 13, 1943, to Jan.          1, 876,496     46,050    256, 986.44
                           and Cedar Lakes to Caney      15, 1944.
                            Creek.
                          Drum Bay to Cedar Lakes___ Dec. 11, 1943, to May           3, 481,116     88, 783   240, 888.62
      Do.............
      Do ...... .......
                                                         28, 1944.
                         Bastrop Bayou to Drum Jan. 16 to Mar. 25,                     957,006      24,800     74, 959.68
                            Bay and Cedar Lakes to       1944.
                            Caney Creek.
U.                                                       ---
     S. pipe-ling dredge Vicinity of Cedar Lakes ....- Jan. 2-15, 1944......            41,439       1,900     14, 717. 46
   Omega.
Contract........... Caney Creek to Gulf, Tex ... Dec. 21,1943, to May                3, 321,258     79, 949   215, 707. 96
                                                         26, 1944.
      Do............. Gulf, Tex., to Oyster Lake -- Dec. 1, 1943, to June            2, 866,582     74,005    197, 862.94
                                                         30, 1944.
U.      S. pipe-line      Oyster Lake to Palacios      Nov. 1, 1943, to Feb.           426, 524      9, 920    87, 878.19
   dredge Sam Hous-         Point.                       8, 1944.
   ton.
U.S. pipe-line dredge .-...  do ......      -..        Apr. 4 to May 12,               170,805       3, 975    36, 676.23
   Omega.                                                1944.
Contract-..........       Port O'Connor, Tex., to San Jan. 20 to May 25,             2, 364, 555    59, 900   185, 757.97
                           Antonio Bay.                  1944.
      Do............. In San Antonio Bay ....          Feb. 3 to Apr. 23,            3,089, 510     45,000    174, 537.23
                                                         1944.
      Do ..........      In San Antonio and Aransas    Mar. 14 to June 30,           1, 409,609     19,900     85, 749.35
                            Bays.                        1944.
      Do------------      San Antonio Bay to Port      Jan. 21 to June 30,           2,631,519      76,500    181,427.06
                           Aransas.                      1944.
      Do............. In Matagorda Bay-.......... May, 19 to June 30,                2, 182,023     37,210    120, 505.01
                                                         1944.
      Do............. Cedar Lake Bayou to Caney May 1 to June 26,                      987,992      30,800     92,100.01
                            Creek.                       1944.
T. S. pipe-line           Colorado River Crossing...   June 21-30, 1944.....            70,609       1,970     14, 508.68
   dredges Sam
   Houston and
   Omega.




  Maintenance.--The U. S. derrick boat No. 8 removed and disposed
of obstructions in the channel and on the right-of-way between Gal-
veston and Oyster Lake, Tex., at a cost of $1,978.30. Miscellaneous
surveys not chargeable to subsequent dredging operations were made
at a cost of $33,619.59. Work of reestablishing reference lines and
erecting signs along the waterway between Port Arthur and Port
764                REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                              1944

Aransas, Tex., was performed at a cost of $7,885.91. A total of 3,956,-
886 cubic yards of material was removed from a total length of channel
of   "191,696
           feet at a cost of $623,064.24, as follows:

                                                                                                         Linear
Government plant                             Location                     Period             yards re- channelet
                                                                                                             of       Cost
    or contract                                                                                moved channeld
                                                                                                        dredged

Contract --------                  Port O'Connor, Tex., to San      Aug. 1 to Dec. 10,         680,742    26, 780   $86,117.35
                                     Antonio Bay.                     1943.
      Do.............              Big Boggy Bayou to Colorado      Sept. 21, 1943 to Jan.     770, 738   54, 000    92, 026.71
                                     River.                           2, 1944.
      Do--------.............      Colorado River crossing......    Mar. 31 to Apr. 16,         45, 925    3, 460    11, 262.85
                                                                      1944.
      Do-.............         Tributary channel to Aransas         Jan. 18 to June 17,        378, 840   26, 309    44, 504.80
                                 Pass, Tex.                           1944.
      Do-----------.............Flood-discharge channel in          Jane 17-30, 1944 ....      439, 987    9,400     35, 720.29
                                     Colorado River.
U.      S.       pipe-line         Vicinity of Palacios Point.-     July 1 to)Oct. 1, 1943_    522, 849   22, 510   80, 233.53
   dredge Sam Hous-
   ton.
      Do.............              Colorado River to Palacios       Oct. 2-31, 1943-.......     79,004     7, 900    24, 498.58
                                     Point.
      Do.............              Colorado River crossing-_ ....   Feb. 9 to Mar. 9,1944_      58, 354    6, 400    26, 367. 67
      Do.............              Brazos River crossing-.......    Mar. 10 to May 9,          215, 120    9, 033    51,917.83
                                                                      1944.
U.   S.      pipe-line             Vicinity of Halls Lake ......-   Aug. 16 to Sept. 30,       127, 669   11, 000    38, 718.74
  dredge Omega.                                                       1943.
    Do-----------.............     Vicinity of Greens Bayou...      Oct. 1 to Nov. 11,         176, 055    5, 040   38, 226. 22
                                                                      1943.
      Do-----......------Brazos River floodgates ...-               June 13-20, 1944 .         218, 960    5, 654   37, 47t. 24
      Do-----------.............   Flood-discharge channel in       Dec. 12, 1943, to Jan.     242, 643    4, 210   55, 993. 43
                                     Colorado River.                 2, 1944.



   Operating and care.-The Mud Bayou railway bridge near High
Island, Tex., was operated and maintained by hired labor at a cost
of $16,911.16. Log booms at the Colorado River crossing were oper-
ated by hired labor at a cost of $668.16. Costs in the amount of
$6,976.91 were incurred in connection with the operation of a tem-
porary removable dam at the Brazos River crossing. Floodgates at
the Brazos River crossing were operated and maintained by hired
labor at a cost of $32,222.05.
   The total cost of all work during the fiscal year was $6,474,660.92, of
which $5,751,334.60 was for new work, $666,548.04 for maintenance,
and $56,778.28 for operating and care. The total expenditures were
$6,245,658.53.
   Condition at end of fiscal year.-The existing project was about
63 percent completed. The dredging of the main channel to a depth
of 9 feet over a width of 100 feet from the Sabine River to Corpus
Christi, Tex., was completed. The dredging of the tributary channels
to Palacios, Rockport, and Aransas Pass, Tex., was completed. The
dredging of the tributary channel in the San Bernard River was com-
pleted from the main channel to a point 26 miles upstream. Con-
struction of a railway bridge near High Island, Tex., and of two
floodgate structures at the Brazos River crossing was completed. Con-
struction of two floodgate structures at the Colorado River crossing
was about 99 percent completed. The enlargement of the main chan-
nel to a depth of 12 feet over a width of 125 feet was completed from
the Sabine River to Galveston, Tex., and about 82 percent completed
from Galveston to Corpus Christi, Tex. The work remaining to be
done consists of completing the dredging of the tributary channel in
the San Bernard River, dredging the tributary channel in the Colo-
rado River, completing the floodgates and appurtenant structures
         RIVERS AND HARBORS-GALVESTON,           TEX., DISTRICT      765
at the Colorado River crossing, completing the enlargement of the
waterway to a depth of 12 feet over a width of 125 feet from the
Sabine River to Corpus Christi, Tex., and dredging the waterway
from Corpus Christi to Port Isabel, Tex.
   The controlling depths at mean low water were 12 feet from the
Sabine -River to Galveston, Tex., 10 feet from Galveston to Freeport
Harbor; 81/2 feet from Freeport Harbor to the Colorado River; 8
feet from the Colorado River to Port O'Connor, Tex.; 9 feet from
Port O'Connor to Corpus Christi, Tex.; 0 feet in the lower 1 -mile
reach and 12 feet in the upper reach of the flood-discharge channel
in the Colorado River; 9 feet in the lower 26-mile reach and 3
feet in the upper reach of the tributary channel in the San Bernard
River; 6 feet in the lower 8-mile reach and about 1 foot in the upper
reach of the tributary channel in the Colorado River; 31/ feet in
the vicinity of the harbor basin and 6 feet in the remainder of the
tributary channel to Palacios, Tex.; 8 feet in the tributary channel
to Rockport, Tex.; and 6 feet in the tributary channel to Aransas
Pass, Tex.
   The total cost of the existing project to June 30, 1944, was $15,660,-
751.34, of which $11,659,959.57 regular funds and $466,476.58 Public
Works funds, a total of $12,126,436.15, was for new work, $3,223,390.56
for maintenance, and $310,924.63 for operating and care from regular
funds. The total expenditures were $15,135,092.33, of which $14,668,-
615.75 was from regular funds and $466,476.58 from Public Works
funds. In addition, $33,172.98 was expended between July 1, 1934,
and June 30, 1935, for operating and care of the works of improve-
ment under the provision of the permanent indefinite appropriation
for such purposes.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $4;373,926.54, including allotments amount-
ing to $2,317,000 made during July 1944, will be applied as follows:
Accounts payable June 30, 1944-----------------------------$525, 659. 01
New work:
    Complete preliminary surveys for dredging be-
      tween Corpus Christi and Port Isabel, Tex.
      (July to September 1944)----------------- $7, 500. 00
    Complete enlargement of waterway in vicinity
      of Oyster Lake, by United States pipe-line
                                  ------------
      dredge (July and August 1944)                      15, 000. 00
    Complete enlargement of waterway between
      Gulf, Tex., and Oyster Lake, under existing
      contract -(July and August 1944)                   38, 500. 00
    Complete enlargement of waterway between
      San Antonio Bay and Port Aransas, Tex.,
      under existing contract (July and August
      1944)---------------------------            ------ 41,400.00
    Complete enlargement of waterway in San
      Antonio and Aransas Bays, under existing
      contract (July and August 1944)- --------- 112, 000. 00
    Complete enlargement of waterway between
      Halls Lake and Bastrop Bayou, under exist-
      ing contract (July 1944) ------------------        50, 400. 00
    Complete enlargement of waterway between
      Oyster Lake and Port O'Connor, Tex., under
      existing contract (July and August 1944). _ 148, 200. 00
    Complete elargpiment of waterway at Colo-
      rado River crossing, by United States pipe-
      line dredges (July and August 1944)- -----         72, 000. 00
766     REPORT OF CHIEF OF ENGINEERS,                U. S. ARMY,         1944

New work-Continued.
    Construct office, warehouse, and dwellings at

                                         _-------$80,
      Colorado River floodgates, by contract
      (September 1944 to March 1945)
    Complete construction of 2 floodgate structures
                                                             000. 00
     at Colorado River crossing, under existing
     contract (July 1944) ---------------------         118, 988.&46
    Dredge waterway from Flour Bluff, near Corpus
      Christi, Tex., southward a distance of about
      15 miles, by contract (November 1944 to
     April 1945) ----------------------------           810, 000.00
   Dredge waterway from Port Isabel, Tex.,
     northward a distance of about 20 miles, by
     contract (November 1944 to June 1945)       --
   Construct power line between 2 floodgate struc-
                                                        810, 000. 00
     tures at Colorado River crossing, under exist-
     ing contract (August and September 1944)_            22, 000. 00
   Construct 2 oil storage houses and water well
     at Colorado River floodgates, by contract
      (October 1944)------------ -------------             8, 000. 00
    Dredge trench across Colorado River for lower-
     ing power cable in connection with construc-
     tion of Colorado River floodgates, by United
      States pipe-line dredge (September 1944)__          8, 000. 00
    Balance remaining ------------------------          600, 000. 00
      Total for new work------------------------------                  $2, 941, 988. 46
Maintenance:
    Complete dredging of flood-discharge channel
      in Colorado River from Matagorda, .Tex.,
      downstream a distance of 5 miles, under ex-
      isting contract (July 1944) ----------             $57, 400. 00
   Complete removal of snags from waterway be-
      tween Galveston, Tex., and Oyster Lake, by
      United States derrick boat (July to Septem-
     ber 1944)------------------------------               8, 400.00
   Dredge shoal reach of tributary channel to
     Palacios, Tex., by United States pipe-line
     dredge (September and October 1944)        ..------ 50, 000. 00
   Drive mooring piles at passing place near Port
     Arthur, Tex., by contract (November 1944)_            7, 200. 00
   Drive mooring piles at passing place near Oyster
     Lake and at Port O'Connor, Tex., by con-
     tract (December 1944 and January 1945)__             14, 400. 00
   Drive mooring piles at Brazos River crossing,
     by United States derrick boat (September
     and October 1944)-------------------                 23, 400. 00
   Drive mooring piles at Colorado River cross-
     ing, by United States derrick boat (Novem-
     ber and December 1944)----- --------                 23, 400. 00
   Dredge shoal reaches of waterway between
     Port Arthur and Port Bolivar, Tex., by
     contract (February and March 1945)         .------- 75, 000. 00
   Dredge shoal reaches of waterway between
     Galveston, Tex., and Freeport Harbor, by
     United States pipe-line dredge (November
     and December 1944)---------------------             40, 000. 00
   Dredge shoal reaches of waterway between
     Freeport Harbor and Oyster Lake, by
     United States pipe-line dredge (November
     1944 to February 1945)   ---------------           120, 000. 00
   Dredge shoal reaches of waterway between
     Oyster Lake and San Antonio Bay, by
     United States pipe-line dredge (January to
     March 1945)--------------------------              100, 000. 00
   Dredge shoal reaches of waterway between
     San Antonio Bay and Port Aransas, Tex.,
     by contract (March and April 1945) ......          150, 000. 00
           RIVERS AND HARBORS           GALVESTON,      TEX., DISTRICT            767
Maintenance-Continued.
    Dredge lower 12-mile reach of flood-discharge
      channel in Colorado River, by contract
      (August and September 1944)                       $53, 000. 00
    Reestablish reference line and erect signs along
      waterway between Port Arthur and Port
      Aransas, Tex. (July 1944 to June 1945)__           25, 069. 16
        Total for ordinary maintenance-_        .-           .-           $747, 269. 16
Maintenance (operating and care):
    Mud Bayou Bridge:
        Operation (July 1944 to June 1945)    ------  $16, 200. 00
        Ordinary maintenance and repairs (July
           1944 to June 1945)_-      -----           -3, 600.00
        Improvement and reconstruction (July
           1944 to Jine 1945) -------------------       5, 000.00
    Brazos River floodgates:
        Operation (July 1944 to June 1945)     .------ 24, 000. 00
        Ordinary maintenance and repairs (July
           1944 to June 1945) ------------------        9, 000.00
        Improvement and reconstruction (July
          1944 to June 1945) ------------------        60, 000.00
    Colorado River floodgates:
        Operation (July 1944 to June 1945)
        Ordinary maintenance and repairs (July
                                              -------  24, 000. 00
          1944 to June 1945)_-       -----           -9, 000. 00
        Improvement and reconstruction (July
          1944 to June 1945)_-       -----           -8, 209. 91
              Total for operating and care --------------------            159, 009. 91

              Total for all work---------------------------            4, 373, 926. 54
  The additional sum of $2,424,000 can be profitably expended during
the fiscal year 1946, as follows:
New work:
   Dredge reach of waterway between Corpus Christi
      and Port Isabel, Tex., by contract (July 1945 to
      June 1946) ----------------------------------------             $1,620,000
Maintenance:
    Dredge where necessary between Port Arthur and
      Port Bolivar, Tex., by contract (August to October
      1945) -------------------------------------           $100, 000
   Dredge where necessary between Galveston, Tex.,
      and Freeport Harbor, by contract (January and
      February 1946)-                   -------------------- 80, 000
    Dredge where necessary between Freeport Harbor.
      and Oyster Lake by United States pipeline dredge
      (September 1945 to February 1946) -------------- 160, 000
    Dredge where necessary between Oyster Lake and
      San Antonio Bay, by contract (September to De-
      cember 1945) -------------------------------           150, 000
   Dredge where necessary between San Antonio Bay
      and Port Aransas, Tex., by contract (September
      1945 to January 1946) ------------------------- 210, 000
        Total for ordinary maintenance---------------------                   700, 000
Maintenance (operating and care):
    Mud Bayou Bridge:
        Operation (July 1945 to June 1946)                    $16, 400
                                                     .------------
        Ordinary maintenance and repairs (July 1945
          to June 1946) --                                       3,600
        Improvement and reconstruction (July 1945 to
          June 1946) -------------------------------             5, 000
768        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                       1944

Maintenance (operating and care)-Continued.
   Brazos River floodgates:
        Operation (July 1945 to June 1946) ------------ $24, 000
        Ordinary maintenance and repairs (July 1945 to
          June 1946) ---------------                     1Q, 000
        Improvement and reconstruction (July 1945 to
          June 1946) --------------------------------     5, 500
    Colorado River floodgates:
        Operation (July 1945 to June 1946)
        Ordinary maintenance and repairs (July 1945 to
                                                             000    -24,
          June 1946)-----                        -       10, 000
        Improvement and reconstruction (July 1945 to
          June 1946) --------------------------------     5, 500
               Total for operating and care---                            ---------                              $104, 000

               Total for all work_----------                                                    ----            2, 424, 000

                                     Cost and financial summary
Cost of new work to June 30, 1944__-- -------                                                          $12, 660, 597. 85
Cost of maintenance to June 30, 1944-------------------                                                  4, 987, 952. 07

       Total cost of permanent work to June 30, 1944         17, 648, 549. 92
                                 ---------------------------
Undistributed costs June 30, 1944_                               288, 834. 58

      Net total cost to June 30, 1944__- -------                                                          17, 359, 715. 34
Minus accounts payable June 30, 1944----------------------                                                    236, 824. 43

      Net total expenditures_ __----------__                                                              17, 122, 890. 91
Unexpended balance June 30, 1944          .2,                                                                 056, 926. 54

         Total amount appropriated to June 30, 1944-----------                                            19, 179, 817. 45 .

   Fiscal year ending June 30              1940              1941                1942              1943             1944

Cost of new work___        _         $1, 072, 745.73      $689, 998. 40      $471, 640. 23 $1, 893,094.89       $5, 751,,4.   60
Cost of maintenance--..... .             186, 255. 31      146, 657.03        965,990. 35      804, 312.41          723, 326. 32

      Total cost       ......----------- 1, 259,001.04     836, 655. 43     1, 437, 630. 58   2, 697, 407. 30    6, 474, 660.92

Total expended --------------        1, 32.'058. 79        845, 919.26      1, 467, 837.45    2, 447, 596.98     6, 245, 658. 53

Allotted-....------.-.-------           367, 000.00      1,369, 000.00      1, 785,455.80     3, 970, 675. 00    4, 310,000.00


Balance unexpended July 1, 1943_ -     ---    -----------                                                 $3, 992, 585. 07
Amount allotted from ,War Department Civil
Appropriation Act approved April 28, 1942_ -   $629, 000. 00
Amount allotted from Second Deficiency Appro-
priation act approved July 12, 1943 -   -..   3, 681, 000. 00
                                                                                                           4, 310, 000. 00

        Amount to be accounted for-------------------------                                                8, 302, 585. 07
Gross amount expended--------             --    6, 247, 943. 02
Less:
      Reimbursements collected      $2, 247. 50
      Receipts from sales.      -----------
                                         36. 99
                                                     2, 284. 49
                                                                                                           6, 245, 658. 53

         Balance unexpended June 30, 1944 ....                                          ....---------------2, 56, 926. 54
             RIVERS      AND HARBORS-GALVESTON,                       TEX., DISTRICT                 769
Outstanding liabilities June 30, 1944                -----------     $14, 143. 19
Amount covered by uncompleted contracts                        .   1, 117, 245. 99
                                                                                     $1, 131, 389. 18
     Balance available June 30, 1944 ---------------------                               925, 537. 36
Amount allotted in July 1944_-----------------------------                            2, 317, 000. 00
        Amount available during fiscal year 1945-----------                           3, 242, 537. 36

Amount (estimated) required to be appropriated for comple-
  tion pfexisting      project     1 ____------------4,                                 096, 000.00

Amount that can be profitably expended in fiscal year ending
June 30, 1946:
     For new work 1_--------------                                     ----           1, 620, 000. 00
   SFor maintenance                                                                      04,         00
                                                                                        8--------------------------------
                                                                                              000.




        Total 1-----------------------------------------                              2,424, 000. 00
I Exclusive of available funds.

                               3. GALVESTON HARBOR, TEX.

   Location.-The entrance to this harbor is situated on the Gulf of
Mexico, on the northern portion of the Coast of Texas, 328 miles west
of Southwest Pass of the Mississippi River and 278 miles northeast
from the mouth of the Rio Grande. (See U. S. Coast and Geodetic
Survey Chart No. 520.)
   Previous projects.-Adopted by River and Harbor Acts approved
June 23, 1874, June 14, 1880, and August 5, 1886. For further details
see page 1854, Annual Report for 1915,'and page 851, Annual Report
for 1938.
   Existing project.-This provides for two rubblestone jetties extend-
ing from Galveston Island (on the south) and Bolivar Peninsula (on
the north) into the Gulf of Mexico (the south jetty being 35,900 feet
long and the north jetty 25,907 feet long), and for a channel 800 feet
wide and 36 feet deep from deep water in the Gulf to a point between
the jetties 2 miles west of the seaward end of the north jetty, thence
800 feet wide and 34 feet deep to Bolivar Roads. The project also
provides for the maintenance by the United States of existing chan-
nels channelward of the harbor lines, 12 feet deep and 100 feet wide,
to the highway-ferry landings on Galveston Island and Bolivar Pen-
insula, for the construction_ of 13 groins to protect the sea wall
along the Gulf shore from about Twelfth to Sixty-first Street, Gal-
veston, Tex.
    Under ordinary conditions the mean tidal range is 2 feet on tlhe
outer bar and 1.64 feet on the inner bar. The extreme ranges are
2.76 and 2.27 feet, respectively. The height of the tides is dependent
largely on the wind, and during strong "northers" in the winter season
the water surface may be depressed 2 feet below mean low tide.
    The estimated cost of new work, revised in 1938, was $2,872,000.
exclusive of amounts expended under previous projects.
    The latest (1935) approved estimate of cost of annual maintenance
is $187,500, of which $7,500 is for channels leading to ferry landings.



        616634--45-pt. 1, vol. 1                49
770           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                      1944

The existing project was authorized by the following river and
harbor acts:

   SActs                           Work authorized                                     Documents


Aug.     5, 1886   Construction of 2 rubblestone jetties   ------        H. Doc. No. 85, 49th Cong., 1st sess.,
                                                                           and Annual Report 1886, p. 1311.
Mar. 2,1907        Extension of the jetties to present project length    H.1)oc. No. 340, 59th QQp,, 2d sess.,
                    and construction and operation of a dredge.           and Rivers and Harbors Committee
                                                                           Doc. No. 11, 59th Cong., 2d sess.
July 18,1918       Deepening channel to 35 feet with 800-foot width      H. Doc. No. 758, 65th Cong., 2d sess.
                     for experimental period of 2 years.
Jan.    21, 1927   Maintenance of channels 800 feet wide, 35 feet        H. Doc. No. 307, 69th Cong., 1st sess.
                     deep on outer bar and 34 feet on inner bar.
Aug. 30,19351    Maintenance of channels 12 feet deep, 100 feet          Rivers and Harbors Committee Doc.
                  wide leading to State highway ferry landings.            No. 31, 72d Cong., 1st sess.
       Do .....- Construction of 13 groins along Gulf shore from         H. Doc. No. 400, 73d Cong., 2d sess.
                     12th to 61st Sts. in the city of Galveston, at a
                     limit of cost of $234,000 (10 groins were con-
                     structed under this limitation).
Apr. 4,1938    2   Completion of the project for construction of 13          Do.
                    groins.
Aug. 30,1935       Deepening channel to 36 feet from the Gulf to a       Rivers and Harbors Committee Doc.
                     point 2 miles west of seaward end of north jetty.     No. 57, 74th Cong., 1st sess. (Con-
                                                                           tains latest published map.)


  1Previously      authorized Sept. 6, 1933, by Public Works Administration.
  2 Public, No. 463, 75th Cong.



  Terminal facilities.-There are no terminals on Galveston Harbor,
but it is the entrance channel leading to extensive terminal facilities
located on Galveston Channel, Texas City Channel, and Houston Ship
Channel. (See Port Series No. 6, pt. I, Corps of Engineers.)
   Operationsand results during fiscal year--Maintenance.-U.S. sea-
going hopper dredge Galveston, from July 1 to 26, 1943, removed
163,014 cubic yards of material from the inner bar channel and 274,748
cubic yards from the outer bar channel (bin measurement), at a cost
of $31,327.12. This dredging was terminated by the sinking of the
U. S. hopper dredge Galveston, during the hurricane of July 27, 1943.
The U. S. hopper dredge Manhattan from January I to March 15,
1944, dredged 405,495 cubic yards of material from the inner bar chan-
nel and 45,813 cubic yards from the outer bar channel (bin measure-
ment), at a cost of $90,825.59. Minor repairs to the shore end of the
north jetty were made from June 26 to 30,1944, placing 180 tons of core
stone, at a cost of $3,133.98. There were additional costs of $7,581.40
for miscellaneous surveys and inspections. The cost for all work
during the fiscal year was $132,868.09, all for maintenance. The total
expenditures were $135,224.54.
SCondition at end of fiscal year.-The existing project was completed
in 1939. The jetties were completed in 1910. The 35-foot channel
was completed in 1922. The 36-foot depth in the outer channel was
completed in 1938. The groin's along the Gulf side of the Galveston
sea wall were completed in 1939. The tidal scour, assisted by dredg-
ing, had previously formed a channel between the jetties 32.5 feet deep
at mean low tide, and 1,450 feet wide between the 30-foot contours.
              RIVERS AND              HARBORS-GALVESTON,                       TEX., DISTRICT                             771
   The controlling depths below mean low tide were about 34 feet in
the inner-bar channel, 35 feet in the outer-bar channel, and 13.5 feet
in the highway ferry channel.
   The total cost of the existing project to June 30, 1944, was $6,910,-
267.34, of which $2,867,886.03 was for new work, and $4,042,381.31
for maintenance including $13,121.45 from Public Works funds. The
total expenditures were $6,910,365.53 including $13,121.45 Public
Works funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $120,582.08, including accounts receivable
and an allotment of $120,000 made during July 1944, will be applied
as follows:
Maintenance:
      Dredge inner and outer bar channels with the U. S. seagoing
        hopper dredge Manhattan (August, October, and November
        1944) .------- -----------------------------------                                                    $117,716.06
      Complete minor repairs to shore end of North Jetty (July 1944)                                             2, 866. 02

             Total ----------------                 --------------------------                                    120, 582.08
  The total additional sum of $150,000 can be profitably expended
during the fiscal year 1946 for maintenance dredging on the inner and
outer bar channels with an available seagoing hopper dredge (Sep-
tember, November, and December 1945).
                                       Cost and financial summary
Cost of new work to June 30, 1944-----------------------                                                $11, 289, 882. 60
Cost of maintenance to June 30, 1944                                                                       4, 128, 508. 03
       Total cost of permanent work to June 30, 1944 -                                   --.                15, 418, 390. 63
Plus accouahts receivable June 30, 1944      ------                                                                   98. 19
         Gross total costs to June 30, 1944                                                                 15, 418, 488. 82
Net total expenditures --                                                                                   15, 418, 488. 82
Unexpended balance June 30, 1944_----------------- ------                                                            483. 89
         Total amount appropriated to June 30, 1944                                                         15, 418, 972. 71

   Fiscal year ending June 30            1940          1941                  1942                    1943              1944

Cost of new work-
Cost of maintenance -$105,                325. 52   $207, 025.48          $299, 181.26         $159, 622.89          $132,868.09
Total expended         ...        -     96, 343.
                                             9 89    210,889.06            264,104. 40             199, 285. 74       135, 224.54
Allotted -     - -       ---             1,500.00     86,000.00             90,000.00              200,000.00-
             Balan

Balan(ce unexpended July 1, 1943__                                                                            $135, 708. 43
Gross amount expended -_                                 _-
                                                          -           -             -          -            -135,     224. 54

       Balance unexpended June 30, 1944                                                                                483. 89
Accou nts receivable June 30, 1944_ -                         -----                      -----                          98. 19

      Unobligated balance available June 30, 1944                                       --                            582. 08
Amouint allotted in July 1944_ _120,                                                                                  000. 00
         Amount available during fiscal year 1945_                                             _                  120, 582. 08
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 1                ---      --                                                          150, 000
IExclusive of available funds.
772        REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                        1944

                               4. GALVESTON CHANNEL, TEX.

   Location.-This channel extends from a point in Galveston Har-
bor between Bolivar Peninsula and Fort Point across the former
inner bar to and along the wharf front of Galveston, and has a length
of about 5 miles and a width of 1,200 feet. (See U. S. Coast and
Geodetic Survey Chart No. 520.)
   Existing project.-This provides for a channel 34 feet deep at mean
low tide and 1,200 feet wide from Bolivar Roads (outer end of the
old inner bar near Fort Point) to Forty-third Street, thence to Fifty-
first Street with a width of 1,200 feet and 32 feet deep, in the city of
Galveston, and for its extension, when the interests of navigation and
commerce require it, with a width of 1,000 feet and depth of 32 feet
at mean low tide, to Fifty-seventh Street in the city of Galveston,
and for an extension of the sea wall, which lies along the Gulf front
of Galveston, from its angle at Sixth Street and Broadway to the south
jetty, with protection at its junction with the south jetty, this exten-
sion of the sea wall being for the purpose of protecting the outer end
of the channel from the effects of hurricanes.
   Under ordinary conditions the mean tidal range is about 1.1 feet
and the extreme range about 1.6 feet. The height of tide is dependent
largely on the wind, and during strong north winds in the winter
season the water surface may be depressed 2 feet below mean low tide.
   The estimated cost of new work on the channel, revised in 1942, is
$3,100,000, and of the sea-wall extension, revised in 1922, $2,986,000.
The latest (1935) approved estimate for annual cost of maintenance
of the channel is $260,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                     Documents



June 13,1902    A channel 1,200 feet wide and 30 feet deep from        H. Doc. No. 264, 56th Cong., 2d sess,
                 outer end of the inner bar to 51st St.
Mar. 3,1905     Purchase or construction of a hydraulic pipe line
                  dredge.
Mar. 2,1907     Extension of the channel from 51st St. to 56th St.,    H. Doc. No. 768, 59th Cong., 2d sess.
                 with depth of 30 feet and width of 700 feet.
June 25,1910    Conditional extension of the channel with a width      H. Doc. No. 328, 61st Cong., 2d sess.
                 of 1,000 feet and depth of 30 feet between 51st and
                 57th Sts.
July 27,1916    Extension of the sea wall from angle at 6th St. and    H. Doc. No. 1390, 62d Cong., 3d sess.
                  Broadway to a point abreast of the nearest bat-
                  tery at Fort San Jacinto.
Sept. 22,1922   Further extension of the sea wall to junction with     H. Doc, No. 693, 66th Cong., 2d sess.
                 south jetty and protection of this junction and
                 for repairing the sea wall in front of the Fort
                 Crockett Reservation.
Jan. 21, 1927   Deepening the channel to 32 feet -     - --            H. Doc. No. 307, 69th Cong., 1st sess.
Aug. 30,1935    Deepening the channel to 34 feet from Bolivar Road     Rivers and Harbors Committee Doc.
                 to 43d St.                                             No. 61, 74th Cong., 1st sess. (Con-
                                                                         tains latest published map.)



  Local cooperation.-Fully complied with.
   Terminal facilities.-The terminal facilities at Galveston are
located almost entirely on the south side of the channel. The prin-
                    RIVERS AND                         HARBORS-GALVESTON,                  TEX., DISTRICT                     773
cipal wharves are owned by the city of Galveston and extend from
Tenth Street to Forty-first Street, occupying a total channel frontage
of 12,400 feet with a berthing capacity of 31,152 linear feet. Immedi-
ately west of the above wharves there are three privately owned piers
and two slips having a berthing capacity for seven average-size ships.
Two privately owned oil docks having a berthing space of 7,580 linear
feet are located at the foot of Fourth and Fifth Streets, respectively.
A privately owned railroad ferry landing is located at the foot of
Ninth Street, and a highway ferry landing owned by the State of
Texas is located near the outer end of the channel on Fort San Jacinto
Military Reservation. A privately owned floating drydock and ma-
rine railway are located on Pelican Spit opposite Twenty-fourth
Street. The terminal facilities at Galveston are considered adequate
for existing commerce. (For further details see Port Series No. 6,
pt. I, Corps of Engineers.)
   Operations and results during fis cal year-Maintenance.-Thechan-
nel -was dredged between stations -0+500 and 1+472 by contract
from July 1 to 16, 1943, removing 456,417 cubic yards of material from
a channel length of 1,972 feet at a cost of $36,783.06. A small force
was employed occasionally on maintenance of sea-wall extension, rear
slope, and brick pavement at a cost of $797.76. There were additional
costs of $10,227.21 for miscellaneous surveys and inspections. The
total cost for the fiscal year was $47,808.03 all for maintenance. The
total expenditures were $150,312.67.
   Condition at end of fiscal year.-At the end of the fiscal year the
channel dredging was about 65 percent completed and the entire proj-
ect was about 88 percent completed. The sea-wall extension, with fill
and paving, was completed in 1926. The channel was completed to a
depth of 34 feet from the outer end of the old inner bar at Fort Point
Light to Forty-third Street in the fiscal year 1938. The work remain-
ing to be done to complete the project is the dredging of the channel
to a depth of 32 feet from Forty-third Street to Fifty-seventh Street
with 1,200 feet width from Forty-third Street to Fify-first Street and
1,000 feet width from Fifty-first Street to Fifty-seventh Street, the
work on this last-named section being contingent on the development
of the water-front facilities on the Chicago, Rock Island & Gulf Rail-
way and adjacent properties.
   The controlling depth in the channel was 30 feet at mean low tide
over a least bottom width of 925 feet.
   The total cost of the existing project to June 30, 1944, was as
follows:

                                                                              New Work           Maintenance            Total

United States funds:
    Channel ...-----------------------------------                            $1, 670, 874.19    $4, 225,112.18      .$5, 895, 986. 37
     Sea wall- .....................................                           2, 289, 213.54        148, 312.11       2, 437, 525.65
      Total United States funds.---------------------3,                          960, 087. 73      4, 373, 424. 29    8, 333, 512.02
Contributed funds_............----...................                            710, 274. 77 ................           710, 274. 77
       Total_-...........----------                      - ................    4, 670, 362. 50    4, 373, 424. 29      9,043, 786. 79


The total expenditures were $8,333,512.02. In addition, $710,274.77
was expended from contributed funds for sea-wall construction.
Proposed operation.-The balance unexpended at the end of the
774       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                    1944

fiscal, year, amounting to $357,083.49, including an allotment of $190,-
000 made during July 1944, will be applied as follows:
Maintenance:
    Dredge the channel by contract (September 1944 to March
      1945)     -------------------------------------------- $352, 083. 49
    Maintenance of sea-wall extension slopes and pavement (July
      1944 to June 1945) --------------------------------       , 5, 000. 00

           Total     -------------------------------------------                                             357,083.49
  The additional sum of $200,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance:
    Dredge a portion of the channel by contract (February to June
      1946)    ------------------------------------------          $195,000
    Maintenance of sea-wall extension slope and pavement----------    5, 000
        Total_ -----------------------------------------------                                                    200, 000

                                    Cost and financial summary
Cost of new work to June 30, 1944_ _                               ---------                           $3, 960, 087. 73
Cost of maintenance to June 30, 1944_------                                             ---             4, 373, 424. 29
        Total cost of permanent work to June                       80, 1944      ---------              8, 333, 512. 02
Net total expenditures  _    _   --     --      --       -                                              8,333, 512. 02
Unexpended balance June 30, 1944--------------------------                                                167, 083. 49
        Total amount appropriated to June 30, 1944                        ----------- 1 8, 500, 595. 51
   Fiscal year ending June 30           1940             1941                  1942             1943               1944

Cost of new work--------------------------------------------------------
Cost of maintenance-----------$169, 879. 70 $12, 701. 39. $31, 452. 30 $353, 342. 05                              $47, 808.03
Total expended   ----------------     177, 717.39        8, 293. 53       36, 390. 90         250. 535. 08        150, 312. 67
A llotted. ----------------------      12, 500.00      265,000.00         20, 000.00          278, 500.00     .



Balance unexpended July 1, 1943 ---------------------------                                              $317, 396. 16
Gross amount expended -----------------------------------                                                 150, 312. 67
     Balance unexpended June 30, 1944--------------------                                                    167, 083. 49
Amount allotted in July 1944_---------            ----                                                       190, 000. 00
        Amount available during fiscal year 1945                      --------------                         357, 083. 49
Amount (estimated) required  to be appropriated for completion
of existing project 2- - - - - - - - - - -             _                                               1, 430, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 2--------------.                                                              200 000. 00
1 In addition, $710,274.77 was expended from contributed funds for new work.
2Exclusive of available   funds.

    5. CHANNEL FROM GALVESTON HARBOR TO TEXAS CITY, TEX.

  Location.-Texas City is on the mainland of Texas on the west side
of Galveston Bay, about 10 miles northwest of the city of Galveston.
(See U. S. Coast and Geodetic Survey Charts Nos. 520 and 1282.)
  Previow projects.-Adopted by River and Harbor Act approved
March 3, 1899, and enlarged by River and Harbor Act approved June
25, 1910 (H. Doc. No. 328, 61st Cong., 2d sess.). For further details
                   RIVERS        AND HARBORS-GALVESTON,                      TEX., DISTRICT                775
see page 1856, Annual Report for 1915, and page 858, Annual Report
for 1938.
   Existing project.-This provides for a channel 34 feet deep at mean
low tide and 300 feet wide on bottom from deep water in Galveston
Harbor to the harbor at Texas City, a distance of about 61/2 miles,
with a pile dike on its north side 28,200 feet long covered with clay
and other material dredged from the channel, with a harbor 800 feet
wide on bottom and 34 feet deep at mean low tide extending approxi-
mately 4,250 feet to the southward of the south property line of the
Monsanto Chemical Co., and for the construction of a rubble-mound
dike a short distance south of the existing pile dike and extending
between stations -1+600 (the shore) and 26+000, a distance of
27,600 feet. Under ordinary conditions the -mean tidal range is about
114 feet and the extreme range is about 1 feet. The height of tide
is dependent largely on the wind, and during strong "northers" in
the winter season the water surface may be depressed 2 feet below
mean low tide.
   The estimate of cost for new work, revised in 1938, is $2,429,000,
exclusive of amounts expended on previous projects but inclusive of
$28,740.68 contributed by local interests. The latest (1937) approved
estimate of cost of annual maintenance of the channel and dike is
$144,500.
   The existing project was authorized by the following river and
harbor acts:

       Acts                         Work authorized                                    Documents


Mar.     4,1913     A channel 300 feet wide and 30 feet deep and con-     H. Doe. No. 1390, 62d Cong., 3d sess.
                     struction of a pile dike 28,200 feet long north of
                      channel.
July     3, 1930    For a harbor 800 feet wide and 30 feet deep at        H. Doc. No. 107, 71st Cong., 1st sess
                     Texas City, and the construction of a rubble
                     mound dike.
Aug. 30,19351       Extension of rubble mound dike to the shore line-     Rivers and Harbors Committee Doe
                                                                           No. 4, 73d Cong., 1st sess.
       Do..   __    Deepening the channel and harbor to 32 feet---        Rivers and Harbors Committee Doc.
                                                                            No. 46, 73d Cong., 2d sess.
       Do ...       Deepening the channel and harbor to 34 feet---        Rivers and Harbors Committee Doe.
                                                                           No. 62, 74th Cong., 1 st sess.
Aug. 26,1937        An extension to the harbor, 1,000 feet southward,     Rivers and Harbors Committee Doc
                     800 feet wide and 34 feet deep, provided that no      No. 47, 75th Cong., 1st sess. (Cou-
                      dredging be done by the United States within          tains latest published map.)
                      75 feet of any pierhead line or structure.

  1   Previously authorized Sept. 6, 1933, by Public Works Administration.


  Local cooperation.-Underthe provisions of the River and Harbor
Act of August 26, 1937, local interests are required to furnish free of
cost to the United States necessary rights-of-way and suitable spoil-
disposal areas for new work and for subsequent maintenance as re-
quired and release the United States from claims for damages attrib-
utable to the work of improvement and furnish assurance satisfactory
to the Secretary of War that they will construct a common-carrier
oil terminal substantially as proposed. None of these conditions has
been complied with. All prior requirements have been fully complied
with.
776          REPORT        OF CHIEF OF ENGINEERS,                           U.    S.     ARMY,         1944

  Terminal facilities.-Modern terminal facilities privately owned,
are located on the mainland at the inner end of this channel and are
considered adequate for existing commerce. (See Port Series No. 6,
pt. 3, revised 1935, Corps of Engineers.) A seatrain terminal, pri-
vately owned, was completed in 1940.
  Operations and results during fiscal year-Maintenance.-The
channel was dredged under contract from May 17 to June 30, 1944,
659,222 cubic yards of material being removed between stations 2 + 800
and 12+ 800, a channel length of 10,000 feet, at a cost of $52,8'35.76.
There were additional costs amounting to $5,342.99. The total cost for
the fiscal year was $58,178.75, all for maintenance. The total expendi-
tures were $14,463.36.
  Condition at end of fiscal year.-The existing project was 95 percent
completed. The work remaining to be done is the extension of the
Texas City, Tex., harbor 1,000 feet southward, as authorized by the
River and Harbor Act of August 26, 1937. The channel and the
harbor basin, except the authorized extension referred to above, were
completed in 1936. The pile dike was completed in 1915; the rubble-
mound dike in 1934. The controlling depth in the channel was 33.5
feet, and in the completed portion of the basin was 32.5 feet at mean
low tide. The total cost of the existing project to June 30, 1944, was
as follows:

                                                                   New work             Maintenance            Total

Regular funds ...----------------------------------.               $2,151,680. 52     $3, 503, 599. 88       $5,655, 280.40
Public Works funds....--------------------------------                                    _
                                                                      136, 295. 78 --------     --              136, 295. 78
     Total United States funds ---------------------                2, 287, 976. 30        3, 503, 599.88     5, 791, 576. 18
Contributed funds............ .                -................        28, 740. 68    .-----.----------          28, 740. 68
     Total all funds ------------------------------                 2,316, 716. 98        3, 503, 599. 88     5, 820, 316. 86



  The total expenditures were $5,747,860.79, of which $5,611,565.01 was
from regular funds and $136,295.78 from Public Works funds. In
addition $28,740.68 was expended from contributed funds for new
work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year amounting to $210,731.26, including an allotment of $25,000
made during July 1944, will be applied as follows:
Accounts payable June 30, 1944--------------------------- ---    $6,184.11
Maintenance:
    Complete an existing contract for dredging the channel and
      turning basin (July to September 1944)--- --------------- 204, 547. 15
             Total      -------------------------------------------                                         210, 731. 26
  The additional sum of $140,000 can be profitably expended during
the fiscal year 1946 for maintenance dredging by contract (September
to December 1945).
  No funds have been requested for new work for the fiscal year 1946
because it is not expected that local interests will furnish the required
cooperation by that time.
                  RIVERS AND HARBORS                            GALVESTON, TEX., DISTRICT                                       777
                                                Cost and~ finanoiaf summary
Cost of new work to June 30, 1944______________--------                                                       1 $2, 654, 798. 78
Cost of maintenance to June 30, 1944----------------------                                                       3, 698, 683. 09
       Total cost of permanent work to June 30, 1944                                                                6, 353, 481. 87
Undistributed costsJune 30, 1944                                                                                     -37,   531. 28
                                                                                                                     -----------------------

      Net total cost to June 30, 1944                                                                               6, 315, 950. 59
Minus accounts payable June 30, 1944 .                                  ------                                           6, 184. 11
      Net total expenditures    ------------------------                                                        16, 309, 766. 48
Unexpended balance June 30, 1944 -----------------------                                                                185, 731. 26
            Total amount appropriated to June 30, 1944--------                                                  1   6, 495, 497. 74


     Fiscal year ending June 30                    1940           1941                   1942               1943             1944

Cost of new work
Cost of maintenance-----------$150, 952. 29                     $57, 057. 62      $153,113. 80            $49,119. 40       $58, 178. 75
Total expended...............----------------    131, 057. 42    81, 208. 37           112, 837.05         88, 989.94        14, 463. 36
Allotted----.------------------                   75,000.00     205, 000. 00            20,000.00         100,000.00        100. 000.00



Balance unexpended July 1, 1943-                                                                                     $100, 194. 62
Amount allotted from War Department Ciivil Aporopriation Act
  approved June 2, 1943                                             -   ------------------
                                                                                                                        100, 000. 00
      Amount to be accounted for_                                         -       --            --                      200, 194. 62
Gross amount expended    -_                                                                                              14, 463. 36
     Balance unexpended June 30, 1944                                                                                   185, 731. 26
Amount covered by uncompleted contracts_                                                                                158, 924. 36
     Balance available June 30, 1944__                                                                                   26, 806. 90
Amount allotted in July 1944_ __-_                                            _           _                              25, 000. 00
            Amount available during fiscal year 1945                                                 --                  51, 806. 90
Amount (estimated) required to be appropriated for completion
    of existing project 2                  __                                                                              112, 000
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 2- _ _ __       -
                                                                                                                           140, 000
  1 In addition, $28.740.68 was expended from contributed funds for new work.
  2 Exclusive of available funds.


                                  6. CHANNEL TO PORT BOLIVAR, TEX.

   Location.-Port Bolivar is at the end of Bolivar Peninsula and 4
miles north of the city of Galveston. The channel connects the port
with the channel in Galveston Harbor. (See U. S. Coast and Geodetic
Survey Chart No. 520.)
   Previous projects.-Adopted by the River and Harbor Act of March
2, 1907. For further details see page 1856, Annual Report for 1915,
and page 860, Annual Report for 1938.
   Existing project.-This provides for a channel 30 feet deep at mean
low tide and 200 feet wide on bottom, beginning at deep water in
Galveston Harbor and extending to a turning basin 1,600 feet long,
with an average width of about 750 feet and 30 feet deep at mean low
tide in front of the wharves. Under ordinary conditions the mean
778          REPORT OF CHIEF OF ENGINEERS,                            U. S. ARMY,         1944

tidal range is about 1.7 feet and the extreme range about 2.3 feet. The
height of tides is dependent largely on the wind, and during strong
"northers" in the winter season the water surface may be depressed
2 feet below mean low tide.
   The estimated cost of new work, revised in 1928, is $187,000, exclu-
sive of amount expended on previous projects. The latest (1928) ap-
proved estimate for annual cost of maintenance of the channel and
turning basin is $20,000, which provides for a depth of 20 feet in the
channel and 20 feet in the turning basin, 500 feet square and an area
150 feet wide and 700 feet long in front of the highway ferry landing,
these dimensions being sufficient to accommodate existing commerce.
   The existing project was authorized by the following river and
harbor acts:

       Act                       Work authorized                                   Documents


June 25,1910     Excavation of a channel 30 feet deep and 200 feet    H. Doc. No. 328, 61st Cong., 2d sess.
                   wide, with turning basin 14 000 feet square.
Mar.    2,1919   Increase length of turning basin to 1,600 feet and   H. Doc. No. 1122 65ttrQo~n., 2dsess.
                   decrease width to about 750 feet.


I Contains the latest published map.

   Recommended modifications of project.-Under date of June 24,
1926, the Chief of Engineers recommended that the project be cur-
tailed by providing for a channel depth of 20 feet, 200 feet wide, with
a turning basin of the same depth 500 feet square (H. Doc. No. 467,
69th Cong., 1st sess.).
   Terminal facilities.-The terminals consist of two privately owned
piers, one 400 feet wide by 1,200 feet long, and the other 210 feet wide
by 1,200 feet long, and a highway ferry landing owned by the State
of Texas at the south end of the turning basin. The facilities are
considered adequate for the existing commerce.
   Operations and results during fiscal year-Maintenance.-Miscel-
laneous surveys were made at a cost of $805.97. The total cost for the
fiscal _year was $805.97, all for maintenance. The total expenditures
were $832.44.
   Condition at end of fiscal year.-The existing project was about
                                                                       90
percent completed. The channel, 200 feet wide, and turning basin
1,000 feet square, were completed in 1912. To complete the project the
turning basin must be enlarged to project dimensions. Constant shoal-
ming occurs, and projct dimensions have not been maintained, as lesser
dimensions are sufficient to accommodate existing commerce.
   The controlling depts at mean low tide were 20 feet in the channel, 10
feet over the area being maintained in the turning basin at the entrance
to slip No. 3, and 13.5 feet in front of new ferry landing.
   The total cost and expenditures under the existing project to June
30, 1944, were $631,873.38, of which $85,213.85 was for new work and
$546,659.53
   Proposedfor   maintenance.
              operations.-The balance unexpended at the end of the
fiscal year, amounting to $21,882.10, will be applied to maintenance
dredging of a portion of the turning basin by contract (April and
May 1945).
                 RIVERS AND HARBORS-GALVESTON,                                        TEX., DISTRICT                     779
   The additional sum of $10,000 can be profitably expended in the
fiscal year 1946 for maintenance dredging in a portion of the turning
basin by contract (May 1946).
                                              Cost and finanoial summary
Cost of new work to June 30, 1944_                                                                           $133, 924. 60
Cost of maintenance to June 30, 1944--------------------                                        -----         592, 760. 28
                                                         ------------
            Total cost of permanent work to June 30, 1944__                                                      726, 684. 88
Net total expenditures_                      ------------------------------------                                726, 684. 88
Unexpended balance June 30, 1944                                  --------                                        21, 882. 10

            Total amount appropriated to June 30, 1944---------------                                            748, 566. 98


   Fiscal year ending June 30                    1940            1941               1942          1943                1944

Cost of new work--
Cost of maintenance              -             $11, 702. 90      $583. 57      $19, 055.33       $7, 945.53             $805.97
Total expended ..-..                            11, 682. 90        603. 43         18,978. 75     7, 995.   78           832.44
Allotted-    -   -   -   -   -       -   -      17, 500. 00     13, 500.00         20,000.00    -7, 500.00 ..........


Balance unexpended July 1, 1943_---                                  -----------                                 $22, 714. 54
Gross amount expended_-------------                                                             -----                 832.44

            Balance unexpended June 30, 1944-----------------------                                               21, 882. 10

Amount (estimated) required to be appropriated for completion of
existing project 1_                                                                                                 102, 000
Amount that can be profitably expended in fiscal year ending June
   30, 1946 for maintenance 1                                 ___________________10,000
  1 Exclusive of available funds.


                                     7. HOUSTON SHIP CHANNEL, TEX.

   Location.-The channel connects Galveston Harbor, at a point op-
posite Port Bolivar, with the city of Houston, Tex,, extending 50
miles in a northwesterly direction across Galveston Bay through the
San Jacinto River and Buffalo Bayou to a turning basin at the head
of Long Reach with a light-draft channel 7 miles long from the turn-
ing basin to Main Street, Houston. (See U. S. Coast and Geodetic
Survey Charts Nos. 1282 and 532.)
   Previous projeets.-Authorized by River and Harbor Act of June
10, 1872, modified in 1877, and by River and Harbor Acts of March
3, 1879; March 3, 1899; February 20, 1900; March 3, 1905; and March
4, 1913. For further details see page 1856 of the Annual Report for
1915 and page 862 of the Annual Report for 1938.
   Eisting project.-This provides for a channel 34 feet deep at mean
low tide from deep water in Galveston Bay to and including the
Houston turning basin, with a width of 400 feet through Galveston
Bay, 300 feet in the cut through Morgan Point, 300 feet thence to a
point 5,000 feet above Baytown, thence 250 feet to Norsworthy, and
200 feet thence to the turning basin (about 1,000 feet wide) with
suitable widening of the bends at Lynchburg, Norsworthy, Man-
chester and Harrisburg. The project also provides for suitable wid-
ening of the channel in front of the wharf at Manchester, for certain
780           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                      1944

cut-offs and easing of sharp bends, for the construction of a dike 26,000
feet long to protect the channel in upper Galveston Bay, and for a
light-draft extension of the channel, 10 feet deep at mean low water
and 60 feet wide, without easing the bends, through Buffalo Bayou
from the turning basin to the mouth of White Oak Bayou in Houston,
Tex.
   The mean tidal range under ordinary conditions is about 1.3 feet
in the lower part of Galveston Bay, 0.6 foot in the upper bay, and
less than 0.5 foot in the San Jacinto River and Buffalo Bayou. The
extreme ranges under ordinary conditions are about 1.6 feet, 1.3 feet,
and 1 foot, respectively. Freshets sometimes cause rises of over 12
feet in Buffalo Bayou. The height of the tides, however, is dependent
largely on the wind, and during strong "northers" in the winter season
the water surface may be depressed 2 feet below mean low tide.
   The estimate of cost for new work, revised in 1942, is $10,535,535,
exclusive of amounts expended on previous projects, but inclusive of
$1,365,000 contributed by local interests. The latest (1935) approved
estimate for annual cost of maintenance is $800,000.
   The existing project was authorized by the following river and
harbor acts:

       Acts                      Work iuthorized                                        Documents


Mar. 5, 1905                          of sharp bends and construc-
                  Easing or cutting off                              Rivers and Harbors Committee Doc.
                   tion of a pile dike.                                   No. 35, 61st Cong., 2d sess.
Mar. 2, 1919      A channel 30 feet deep, widening bend at Man-      H. Doc. No. 1632, 65th Cong., 3d sess.
                   chester, and existing project dimensions of the
                   turning basin.
Mar. 3,1925       A light-draft extension of the channel to the      H. Doc. No. 93, 67th Cong., 1st sess.
                   Irouth of White Oak Bayou.
July    3, 1930   Widening the channel, through Morgan Point         H.     Doc. No. 13, 71st Cong., 1st sess.
                   and to a point 4,000 feet above Baytown and
                   widening certain bends.
Aug. 30, 19351    Deepening to 32 feet in the main channel and       Rivers and Harbors Committee Doc.
                   turning basin, and for a 400-foot width through     No. 28, 72d Cong., 1st sess.
                   Galveston Bay.
Aug. 30,1935      Existing project dimensions of the main channel_   Rivers and Harbors Committee Doe.
                                                                      No. 58, 74th Cong., 1st sess.      (Con-
                                                                      tains latest published map.)


  1 Previously authorized Sept. 6, 1933, by Public Works Administration.


  Recommended modifications of project.--Under date of March 4,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for a branch channel 10 feet deep and 60
feet wide in the old channel of Buffalo Bayou behind Brady Island
at an estimated cost of $21,300 for new work and $3,000 annually for
maintenance, provided that no dredging be done by the United States
within 15 feet of any wharf or structure; subject to certain conditions
of local cooperation (H. Doc. No. 226, 76th Cong., 1st sess.).
  Under date of April 18, 1939, the Chief of Engineers recommended
further modification of the existing project so as to provide a channel
34 feet deep from the entrance at Bolivar Roads to and including the
turning basin at Houston and two intermediate turning basins, one
at mouth of Hunting Bayou and one at lower end of Brady Island, the
channel widths to be as follows: 400 feet from Bolivar Roads to a
         RIVERS AND    HARBORS---GALVESTON,     TEX., DISTRICT       781

point 5,000 feet above Baytown, 350 feet thence to mouth of Boggy
Bayou, 300 feet thence to lower end of Fidelity Island, 250 feet thence
to the turning basin at the port of Houston at a total estimated cost
of $3,675,000 for new work, in addition to the cost of completing the
existing project, and an increase in cost of annual maintenance of
$60,000; subject to certain conditions of local cooperation (H. Doc.
No. 256, 76th Cong., 1st sess.)
   Further modification of the existing project was recommended by
the Chief of Engineers August 21, 1943, in a report requested by Rivers
and Harbors Committee resolution adopted April 24, 1941, and trans-
mitted to Congress by the Secretary of War February 5, 1944.
   Local cooperation.-The work authorized by the River and Harbor
Act of August 30, 1935, is subject to the provisions that local interests
shall furnish, free of cost to the United States, necessary rights-of-
way for the widening of the channel and suitable areas for the dis-
posal of dredged material during the initial construction and for
future maintenance as and when needed, and release the United States
from all claims for damages to private or municipal property due to
the improvement and its maintenance.
   Cooperation required by the above act has been complied with ex-
cept that suitable areas for spoil disposal for future maintenance are
to be furnished as and when needed.
    'erminial facilities.-The city of Houston and the Harris County
Houston Shin Channel navigation district have constructed modern
terminals which supplement privately owned wharves. The existing
facilities are considered adequate for existing commerce. (See Port
Series No. 6, pt. 9, Corps of Engineers.)
   Operations and results during fiscal year-Maintenance.-TheU. S.
pipe-line dredge Raynmond dredged in bayou section from August 17
to October 15, 1943, between stations 124+00 and 188+00 removing
477,485 cubic yards of material at a cost of $62,340.68; and from Octo-
ber 16 to November 20, 1943, between stations 69+500 and 66+000 in
the bay section, removing 211,720 cubic yards of material at a cost of
$38,821.66. U. S. derrick barge No. 8 from November 22 to December
10; December 22 to 31, 1943, and from January 1 to 22, 1944, removed
504 objects from the channel between Brays Bayou and Morgan Point
at a cost of $8,121.79. The channel in the bay section was dredged
under contract from February 1 to June 30, 1944, between stations
43 +000 and 70+400, removing 3,630,033 cubic yards of material at a
cost of $185,935.87. The total length of channel dredged was 94,900
feet. There were additional costs of $14,822.67 for miscellaneous sur-
veys and inspections; $14,384.70 for surveys to repair channel refer-
ence lines; $2,477.43 for preparing dumping grounds; and $165.16 for
preliminary surveys, plans, and specifications for dredging in lower
bay section by dredge Manhattan. The total cost for the fiscal year
was $327,069.96, all for maintenance. The total expenditures were
$269,980.83.
   Condition at the end of fiscal year.-The existing project was about
96 percent completed. The channel from Bolivar Roads to and in-
cluding the turning basin has been dredged to project dimensions.
   To complete the existing project would require dredging the light
draft extension of the channel above the turning basin and the con-
struction of a dike 26,000 feet long to protect the completed channel
in upper Galveston Bay.
  782             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY, 1944

    A side or tributary channel 10 to 12 feet deep and 3,700 feet long has
  been dredged from the ship channel to the mouth of Goose Creek.
    The controlling depths at mean low tide along the center line of the
  channel were as follows: Through Galveston Bay, 32.5 feet; therice to
  Vinces Bayou 33.8 feet; thence to turning basin 30.5 feet; in the turn-
  ing basin 31.5 feet; thence to Houston, 7 feet. The controlling depth
- inthe channel to mouth of Goose Creek was about 6 feet.
    The total cost of the existing project to June 30, 1944, was as follows:

                                                                                             New work          Maintenance           Total


  Regular funds.................----------------------------------                           $7, 319,603.01    $9, 612, 579. 98   $16, 932, 182. 99
  Public Works funds         .          ......------------------------------                  2 612, 931. 98                        2, 612, 931.98
         Total........................................------------------------------------   9,932,534.99       9, 612, 579.98     19, 545,114.97



    The total expenditures were $19,487,021.30 of which $16,874,089.32
  was from regular funds and $2,612,931.98 from Public Works funds.
  In addition $1,365,000 was expended from contributed funds for new
  work.
     Proposed operations.-The balance unexpended at the end of the
  fiscal year amounting to $878,970.72, including an allotment of $525,-
  000 made during July 1944, will be applied as follows:
  Accounts payable June 30, 1944-----------------------------$16, 940. 65
  Maintenance:
      Complete an existing contract for dredging a portion of the
        channel (July 1944) -------------------------------              48, 199. 90
      Dredge a portion of the channel under a pending contract (Au-
        gust 1944 to January 1945) ---                                  235, 000. 00
      Remove shoaling in the channel by contract (January to June
        1945)---------------------------------------332,                     000. 00
      Remove shoaling in the channel with United States pipe-line
        dredge (January to June 1945)                                   210, 000. 00
      Remove trees and stumps from the channel by United States
        plant and hired labor as needed during the fiscal year 1945-      8, 000. 00
      Remove shoaling in the light-draft extension of the channel with
        United States plant and hired labor as needed during the fiscal
        year 1945                                                        20,000.00
      Building levees and preparing dumping grounds by United States
        plant and hired labor (July 1944 to June 1945)----------          8, 830. 17

                   Total -------------------------------------------                                                              878, 970. 72
    The additional sum of $565,000 can be profitably expended during
  the fiscal year 1946, as follows:
  Maintenance:
      Remove shoaling in the channel by contract (January to June
        1946)                                                          $165,000
      Remove shoaling in the channel by United States pipe-line dredge
        (July 1945 to June 1946)                                        384, 000
      Remove trees and stumps from the channel by United States plant
        and hired labor as needed during the fiscal year 1946 -  ---      8, 000
      Building levees and preparing dumping grounds (July 1945 to
        June 1946)                         --                             8,000

                   Total           ---------------------------------------------                                                      565, 000
                 RIVERS AND HARBORS-GALVESTON,                                                 TEX., DISTRICT                              783
                                                  Cost and financial summary
Cost of new work to June 30, 1944_--------------------------                                                           $14, 037, 691. 86
Cost of maintenance to June 30, 1944--     ------        _                                                              10, 825, 722. 38
      Total cost of permanent work to June 30, 1944-..---                                                              1 24, 863, 414. 24
Undistributed costs June 30, 1944_-    ------                                                                               -- 41, 153. 02

      Net total cost to June 30, 1944___- ---        _     24, 822, 261. 22
Minus accounts payable June 30, 1944----------------------      16, 940. 65

      Net total expenditures ---------------------------                                                               1   24, 805, 320. 57
Unexpended balance June 30, 1944_-__    - _--------                                                                            353, 970. 72
           Total amount appropriated to June 30, 1944                                        ----------                125, 159, 291. 29

    Fiscal year ending June 30                       1940            1941                    1942                 1943                  1944

Cost of new work --------------                   $501, 099. 39   $333, 671.15     .......             ........                ....        ...
Cost of maintenance--- .-- ------
                                _                  354, 671.42     308, 259. 26       $376,114.15             $726,130.29             $327, 069.96

       Total cost-- --------------                 855, 770.81     641, 930.41          376,114. 15            726, 130.29             327, 069.96

Total expended------...      -------...   --...    845, 616. 91    738, 039. 36         386, 220. 53           721, 766. 90            269, 980.83

Allotted          ...     ..---------------------- 844, 500.00     159, 000.00          433, 000.00            663,000.00             -25, 000.00



Balance unexpended July 1, 1943      _         -                                               -          -                  $648, 951. 55
Deductions on account of revocation of allotment_                                                                              25, 000. 00

       Net amount to be accounted for          ---                                                             -              623, 951. 55
Gross amount expended -----------------------------                                                                           269, 980. 83
       Balance unexpended June 30, 1944                               --------------------                                    353, 970. 72
Outstanding liabilities June 30, 1944--------------                                            $7, 591. 49
Amount covered by uncompleted contracts ---                                                    57, 549. 06
                                                                                                                               65, 140. 55

     Balance available June 30, 1944_--                                           --------                                    288, 830. 17
Amount allotted in July 1944_---------                                                              ----                      525, 000. 00

           Amount available during fiscal year 1945--------------                                                             813, 830. 17

Amount (estimated) required to be apporpriated for completion
of existing project 2--  _ '               -- -603,                                                                                    000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2-             -     - -                                                           -          565, 000. 00
  1In addition, expenditures fr om contributed funds were $1,209,178,78 for new work and.$200,000 for main:
tenance on previous projeots and $1,365,000 for new work on existing project.
  2 Exclusive    of available funds.

                                                  8. DOUBLE BAYOU, TEX.

  Location,.-This bayou enters upper Galveston Bay on the east side,
about 30 miles north of Galveston and about 81/4 miles south of Ana-
huac. (See U. S. Coast and Geodetic Survey Chart No. 1282.)
   Ewisting project.-The existing project provides for a channel 6
feet deep at mean low tide and 100 feet wide through the bar at the
mouth of Double Bayou. Under ordinary conditions the mean tidal
range is about 0.7 foot and the extreme range is about 0.9 foot. The
height of tides is dependent largely on the wind, and, during strong
"northers" in the winter season, the water surface may be depressed
11/2 feet below mean low tide.
784           REPORT OF CHIEF OF ENGINEERS,                                           U. S. ARMY,                         1944

   The estimate of cost for new work revised in 1928 was $12,500. The
latest (1928) approved estimate for annual cost of maintenance is
$10,000.
   The existing project was authorized by the River and Harbor Act
approved March 3, 1899 (H. Doc. No. 387, 55th Cong., 2d sess.). The
latest published map is contained in the project document.
   Terminal facilities.-The terminal facilities on this waterway are
confined to small wharves for local use and an oil dock. They are
considered adequate for the present commerce.
   Operationsand results during fiscal year.-None.
   Conditionat end of fiscal year.-The existing project was completed
in 1941. The controlling depth was 4.5 feet at mean low tide. The
total cost and expenditures on the existing project to June 30, 1944,
were $128,556.55, of which $10,309.75 was for new work and $118,246.80
for maintenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year amounting to $40,000, including an allotment of $15,000
made during July 1944, will be applied as follows:
Maintenance:
     Dredge the channel under an existing contract (July and August
       1944)------$25,                                                   0000
     Remove shoaling from the channel by contract (June 1945)-.  .-. 15, 000
               Total       ----------------------------------------------                                                                    40,000
   The additional sum of $15,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging by contract (May 1946).
                                                 Cost and financial summary
Cost of new work to June 30, 1944___--   ___--------$10,                                                                                 309. 75
Cost of maintenance to June 30, 1944---     ---------                                                                               118, 246. 80
       Total cost of permanent work to June 30, 1944------------                                                                    128, 556. 55
Net total expenditures    -------------------------------                                                                           128, 556. 55
Unexpended balance June 30, 1944---.----------                                                                                       25, 000.00
       Total amount appropriated to June 30, 1944--------------                                                                     153, 556. 55

    Fiscal year ending June 30                      1940               1941                1942            1943                              1944


Cost of new w ork ..------.....---             ----------------------------           $3, 356.55               -   -      --.       . .. . . . .
Cost of maintenance_.-........_...--- .---                      ----
                                                           ..--..-        -.....       6,073.33-       -   -       -      -     -    -   -       -    -       -

       Total cost-.--                ---------      --------- - ---------              9,429.88-                                             -            -

                 ...........----------------------------
Total expended------------                                                             9,429.88
Allotted0    .. ... .       ..----.--      -        ----------          $15, 000     -5,     570. 12   -            ---                              $25,000


Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943---- -------------                                                                                            25,000.00
Balance unexpended June 30, 1944---    .....          --------                                                                       25, 000. 00
Amount covered by uncompleted contracts                                   ---------------------                                      20, 780. 00
    Balance available June 30, 1944-_ ---------------          -  ----                                                                4, 220. 00
Amount allotted in July 1944_ -           -----------            __                                                                  15, 000. 00
      Amount available during fiscal year 1945                                     -----------------                                 19, 220. 00
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1----------------------                                                                                  15, 000. 00
  1Exclusive    of available funds.
           RIVERS AND HARBORS-GALVESTON,               TEX., DISTRICT      785

                              9. ANAHUAC CHANNEL, TEX.

   Location.-The town of Anahuac is on the northeast side of upper
Galveston or Trinity Bay, opposite the mouth of the Trinity River,
38 miles north of Galveston and 25 miles northeast of Seabrook.
 (See U. S. Coast and Geodetic Survey Chart No. 1282.)
   Existing project.-There is no definite project for this channel.
The River and Harbor Act approved March 3, 1905, contained an item
for "Improving West Galveston Bay Channel, Double Bayou, and
mouths of adjacent streams, including Trinity River, Anahuac Chan-
nel, and Cedar Bayou," but at the time of the appropriation no recom-
mendation of definite channel dimensions had been made to Congress.
A channel 6 feet deep at mean low tide and 80 feet wide was dredged
in 1905 from Galveston Bay to the wharves at Anahuac, a distance of
16,000 feet. Under ordinary conditions the mean tidal range is about
0.7 foot and the extreme range is about 0.9 foot. The height of tide
is dependent largely on the wind, and during strong "northers" in the
winter season the water surface may be depressed 11/2 feet below mean
low tide.
   The latest (1928) approved estimate for annual cost of maintenance
is $12,500. The latest published map is contained in House Document
No. 440, Fifty-sixth Congress, first session.
   Terminal facilities.-The terminal facilities are at Anahuac and
consist of several small privately owned wharves and slips for local
use. They are considered adequate for existing commerce.
   Operations and results during fiscal year--Maintenance.-Prelimi-
nary surveys were made for dredging the channel under contract, at
a cost of $890.59. Miscellaneous surveys were made at a cost of $3,-
589.30. The total cost for the fiscal year was $4,479.89, all for main-
tenance. The total expenditures were $4,302.57.
   Conditionat end of fiscal year.-The existing project was completed
in 1911. The controlling depth was 3 feet at mean low tide.
   The total cost to June 30, 1944, was $363,121.56 of which $5,975.10
was for the new work and $357,146.46 for maintenance. The total
expenditures were $362,943.02.
   Proposed operations.-The balance unexpended at the end of the
fiscal year amounting to $30,910.78, including an allotment of $15,000
made during July 1944, will be applied as follows:
Accounts payable June 30, 1944 -------------------------------        $175. 98
Maintenance:
    Removal of shoaling from the channel by contract (October and
      November 1944)--------------------------------                22, 734. 80
    Removal of logs and snags from the channel by United States
      plant and hired labor as needed during the fiscal year 1945 _  8, 000. 00.

         Total-------------------------------------                  30,910.78
   The additional sum of $25,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Dredge a portion of the channel by contract (August and September
      1945) -------------------        --------------------           $20,000
    Removal of logs and snags from the channel by United States plant
      and hired labor as needed during the fiscal year 1946_ _   -      5, 00(-
        Total -         ----.--.--------.-----------------------        25, 000.
      616634-45-pt. 1, vol. 1            50
786          REPORT OF CHIEF OF ENGINEERS,                                       U. S.* ARMY,                 1944

                          Cost and financial summary
Cost of new work to June 30, 1944                                                                                      $5, 975. 10
Cost of maintenance to June 30, 1944_---          - --                                          ____                  357, 146. 46

      Total cost of permanent work to June 30, 1944-                                                 -                363, 121. 56
Undistributed costs June 30, 1944_--     ----------                                                                    -- -2. 56

      Net total cost to June 30, 1944 ------------------------- 363, 119. 00
Minus accounts payable June 30, 1944---------------------            175. 98

      Net total expenditures_--------                                                --           ___                 362, 943. 02
Unexpended balance June 30, 1944_---                                              - --          _____                  15, 910. 78
          Total amount appropriated to June 30, 1944---------                                                         378, 853. 80


   Fiscal year ending June 30                1940               1941               1942               1943                   1944

Cost of new work ...           - ---   --------          ---
Cost of maintenance --     . - ...        $19,082. 57      $17, 646.62           $32, 341.40        $24, 153.85              $4, 479.89

Total expended           - -                19, 477.12         17, 152. 72        32, 634. 02        24,113. 90               4, 302. 57

Allotted-.......---------------------      25,000.00           10,000.00          18, 837.04         20,000.00          --          -




Balance unexpended July 1, 1943 _                                                                    --               $20, 213. 35
Gross amount expended-- _____-----------__                                                                              4, 302. 57
      Balance unexpended June 30, 1944----------------                                                                 15, 910. 78
Outstanding liabilities June 30, 1944 _ ----                                                    _-                -        175. 98
     Balance available June 30, 1944_-      ----           -____                                                       15, 734. 80
Amount allotted in July 1944__________            _     ___                                                            15, 000.00
     Amount available during fiscal year 1945 ------------                                                             30, 734. 80

Amount that can be profitably expended in fiscal year ending June 30,
   1946, for maintenance 1 ___________                              -        -            -     -            --              25, 000
  I Exclusive of available funds.


                                       10. TRINITY RIVER, TEX.

  Location.-This river rises in north-central Texas and flows south-
easterly about 760 miles, discharging into Galveston Bay, 37 miles
northeasterly from Galveston.
  Previous projects.-The project outlined in House Document No.
409, Fifty-sixth Congress, first session, was adopted in part by the
River and Harbor Acts of June 13, 1902, March 3, 1905, March 2, 1907,
June 25, 1910, July 25, 1912, March 4, 1913, and July 27, 1916, each
of which acts authorized the construction of certain-named locks and
dams. The provisions of all of these acts for this improvement, so
far as they related to lock and dam construction, were repealed by the
River and Harbor Act of September 22, 1922. For further details see
page 1113 of Annual Report for 1921, and page 986 of Annual Report
for 1932.
  Existing project.-This provides for a channel 6 feet deep. and of
navigable width from the mouth to Liberty, 41.4 miles above the mouth.
At low water tidal influence extends about 50 miles above the mouth,
the mean tidal range at the mouth being about one-half foot. The
          RIVERS AND HARBORS--GALVESTON,       TEX., DISTRICT      787

ordinary variation between high and low water at Liberty is 14 feet,
extreme 26.3 feet.
   The estimate of cost, made in 1920, exclusive of amounts expended
on previous projects, was $72,000 for new work and $20,000 annually
for maintenance.
   The River and Harbor Act of September 22, 1922, having directed
the abandonment of the improvement of the Trinity River from Lib-
erty to Dallas (H. Doc. No. 989, 66th Cong., 3d sess.), the improve-
ment of the remainder, from Liberty to the mouth, continues as pro-
vided for by the River and Harbor Act of July 25, 1912. The latest
published map is in House Document No. 409, Fifty-sixth Congress,
first session.
   Recommended modifications of project.-Under date of September 4,
1941, the Chief of Engineers recommended approval of a comprehen-
sive plani of improvement as outlined in the district engineer's report
and construction at this time of Benbrook, Little Elm, and Grapevine
Reservoirs, the modification of Garza Dam, and the improvement of
levees and floodways at Fort Worth and Dallas, for flood protection
and water conservation in the Trinity River Basin, and provision of
a navigable channel from Houston Ship Channel to Liberty, with a
project depth of 9 feet, 200 feet wide in Galveston Bay and 150 feet
wide in the river section, and with a turning basin at Liberty, Tex.;
at an estimated Federal cost of $15,000,000 for construction and
 $155,000 annually for maintenance and operation; subject to certain
conditions of local cooperation (House Doc. No. 403, 77th Cong., 1st
sess.).
   Under date of February 19, 1944, the Chief of Engineers recom-
mended further modification of the existing project for Trinity River
to the extent ofmodifying the comprehensive plan of improvement
outlined in House Document No. 403, Seventy-seventh Congress, first
session, to provide for the construction at this time of Lavon Reservoir
on East Fork of Trinity River, Tex., with capacity of 272,000 acre-
feet for flood control, at an estimated cost of $3,733,000, and $12,000
annually for operation and maintenance (H. Doc. No. 533, 78th Cong.,
2d sess.).
   Local cooperation.-Fully complied with.
   Terminal facilities.-The only wharves on this river are all in the
first 20 miles above the mouth. They are four in number and range
from 10 to 20 feet in length. All are privately owned, and usage is
free at all except one. One has a ihand derrick; the other three have
no freight-handling facilities. They have no physical connection with
any railroad. They are adequate for the existing commerce, and there
is ample room for future enlargement.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1925. The ruling depth at low water was 6 feet between the mouth
and mile 29 and 2 feet thence to Liberty. The total cost and expendi- .
tures under the existing project to June 30, 1944, were $264,946, of
which $112,255.72 was for new work and $152,690.28 was for main-
tenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $11,961.81, will be applied to removal of logs
and snags from the channel as needed during the fiscal year 1945.
   No additional funds will be required in the fiscal year 1946.
788         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                             1944

                                     Cost antd financial summary
Cost of new work to June 30, 1944_--                       -----                 -_--1            $2, 002, 661.37
Cost of maintenance to June 30, 1944_ -                     -----------                             2 696, 352. 59

         Total cost of permanent work to June 30, 1944---------                                    2, 699, 013. 96

Net total expenditures_-----                                   -----                  -         12-2, 699, 013. 96
Unexpended balance June 30, 1944_--------                                                 ---          11,961. 81
         Total amount appropriated to June 30, 1944                                               2 2, 710, 975. 77
                                                                                                1----------

   Fiscal year ending June 30            1940          1941               1942             1943            1944


Cost of new work--
Cost of maintenance------------.      $20, 504.22    $70, 507. 55   _________         ______------



Total expended .............     .      20,412. 24    70, 599. 53
Allotted-__-------.----.----..       --- 5,000.00     26, 933. 58          $19, 000       -$17, 960
                                                                                 _.

Balance unexpended July 1, 1943                                                                        11, 961. 81
                                                                                                      $--------------------
Balance unexpended June 30, 1944                                                                       11, 961.81
  1In addition, $66,000 was expended from contributed funds for new work.
  2 Includes $252,659.92 from permanent indefinite appropriation, 1884-1909.

                                     11. CEDAR BAYOU, TEX.
   Location.-This bayou is about 30 miles long. It flows to the south
and empties into the northwest corner of upper Galveston Bay, about
11/2 miles below the mouth of San Jacinto River and about 281/2 miles
north of Galveston, Tex. (See U. S. Coast and Geodetic Survey Chart
No. 1282.)
   Previous projects.-Adopted by the River and Harbor Acts of Sep-
tember 19, 1890, and July 13, 1892. For further details see page 869,
Annual Report for 1938.
   Ecxisting project.-This provides for a channel 10 feet deep at mean
low tide and 100 feet wide from the Houston Ship Channel to a point
on the bayou, 11 miles above the mouth. The project also includes the
jetties at the mouth of the bayou provided for under the previous
project. Under ordinary conditions the mean tidal range is about 0.6
foot and the extreme range 1.3 feet. The height of tides is dependent
largely on the wind, and during strong "northers" in the winter season
the water surface may be depressed 2 feet below mean low tide.
   The estimate of cost for new work made in 1930, exclusive of
amounts expended on previous projects, is $50,000, of which $25,000 is
to be contributed by local interests. The latest (1930) approved esti-
mate for annual cost of maintenance is $20,000.
   The existing project was adopted by the River and Harbor Act of
July 3, 1930 (S. Doc. No. 107, 71st Cong., 2d sess.). The latest pub-
lished map is in this document.
   Local cooperation.-The River and Harbor Act, approved July 3,
1930, provides that local interests shall contribute 50 percent of the
estimated first cost of the improvement, but not to exceed $25,000, and
shall furnish, without cost to the United States, all necessary ease-
ments, rights-of-way, and dumping grounds.
   These conditions have not been completely met, but local interests
have complied with all the necessary requirements to complete the
channel to the first bend in Cedar Bayou above the mouth.
   Terminal facilities.-The terminal facilities consist of a few small
                RIVERS AND HARBORS--GALVESTON,                                    TEX., DISTRICT                                   789
wharves, privately owned, for local use located at various places along
Cedar Bayou. an oil-loading wharf owned by the Atlantic Pipe Line
Co. located one-half mile above the mouth of the bayou, and on an oil-
loading wharf owned by the Sinclair-Prairie Oil Co. located 11 miles
above the mouth of the bayou. The present facilities are considered
adequate for existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was about 50
percent completed. The channel has been completed to project di-
mensions from the Houston Ship Channel to the first bend in Cedar
Bayou above the mouth. Two brush and stone jetties have been con-
structed at the mouth of Cedar Bayou. To complete the project the
bayou must be dredged to project dimensions from the first bend above
the mouth to a point 11 miles above the mouth. The controlling
depths at mean low tide were 4 feet from the Houston Ship Channel to
the first bend in Cedar Bayou above the mouth and 7.5 feet thence to
a point in the bayou 11 miles above the mouth. The total cost of the
existing project to June 30, 1944, was $169,284, of which $25,151.13
was for new work (consisting of $12,575.56 United States funds and
$12,575.57 contributed funds) and $144,132.87 for maintenance. The
total expenditures were $169,284, of which $156,708.43 were United
States funds and $12,575.57 contributed funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $47,500, including an allotment of $22,500
made during July 1944, will be applied to maintenance dredging of a
portion of the channel by contract (February to April 1945).
   No additional funds will be required in the fiscal year 1946.
                                        Cost and financial summary
Cost of new work to June 30, 1944 -----------------------------                                               1 $51, 662. 71
Cost of maintenance to June 30, 1944 ------------------------                                                       213, 917. 00

            Total cost of permanent work to Juie 30, 1944_                             -265,                              579. 71

Net total expenditures _--_--                                                                                 1 265 579. 71
Unexpended balance June 30, 1944_ _ ________-__25,                                                                  000. 00
            Total amount appropriated to June 30, 1944_                       --------                        1     290, 579. 71

   Fiscal year ending June 30                1940           1941                1942               1943                   1944


Cost of new work                                -                        -          -              --                          -
Cost of maintenance         - -   -       $24, 548. 81 .      $35. 87     $26, 129. 80      ----              ---      - ---


Total expended.........                       4, 530.69
                              ..-----------------.
                                     .                         53.99          26, 129. 80
Allotted.      ------------------------------              22,000.00     -11,     285.52                25, 000


Balance unexpended July 1, 1943_ __________$25,                                                                           000. 00

Balance unexpended June 30, 1944-----                                   ___                   _          _           25, 000. 00
Amount allotted in July 1944 _                                                                                       22, 500. 00

            Amount available during fiscal year 1945_----------                                                      47, 500. 00
Amount (estimated) required to be appropriated for, completion
of existing project 2 3  -                                                                                          12, 500. 00
  i In addition, $12,575.57 was expended from contributed funds for new work.
  2In addition, $12,424 to be contributed by local interests.
  * Exclusive of available funds.
790        REPORT       OF CHIEF          OF ENGINEERS,              U.    S. ARMY,        1944

                                     12. CLEAR CREEK, TEX.
   Location.-ClearCreek has its source about 13 miles south of Hous-
ton, Tex., and flows southeast for a distance of about 25 miles, empty-
ing into the west side of upper Galveston Bay at a point 24 miles
northwest of Galveston, Tex. (See U. S. Coast and Geodetic Survey
Chart No. 1282.)
   Existing project.-This provides for a channel 6 feet deep at mean
low tide and 60 feet wide from deep water in Galveston Bay to the
bridges 1 mile above the mouth of Clear Creek. Under ordinary
conditions the mean tidal range is about 0.6 foot and the extreme
range 1.3 feet. The height of tides is dependent largely on the wind
and during strong "northers" in the winter season the water surface
may be depressed 2 feet below mean low tide. The original estimate
of cost for new work, made in 1900, was $10,000.
   The latest (1935) approved estimate for annual cost of mainte-
nance is $6,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                        Work authorized                                     Documents



June 13,1902   A channel 4 feet deep and 50 feet wide- ....-   ...   H. Doc. No. 449, 56th Cong., 1st sess.
Aug. 30,1935   Enlargement of the channel to depth of 6 feet and     H. Doc. No. 264, 73d Cong., 2d sess.
                 width of 60 feet.                                        (Contains latest published map.)



   Recommended modifications of project.--Under date of July 11,
1941, the Chief of Engineers recommended modification of the exist-
ing project so as to provide for a channel 7 feet deep and 75 feet
wide from deep water in Galveston Bay to a new entrance to Clear
Creek, and a channel 7 feet deep and 60 feet wide in Clear Creek
and Clear Lake to the county highway bridge at League City at an
estimated cost of $30,000 for new work with $4,000 annually for main-
tenan;e in addition to that now required; subject to certain condi-
tions of local cooperation (H. Doc. No. 319, 77th Cong., 1st sess.).
   Terminal facilities.-The terminal facilities consist of small, pri-
vately owned wharves for local use located at the town of Seabrook,
at the mouth of the creek, and at various points along the length of
the waterway. They are considered adequate for existing commerce.
   Operationsand results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1936. The controlling depth at mean low tide was 5.5 feet. The
total cost and expenditure to June 30, 1944, was $95,444.67 of which
$14,290.95 was for new work and $81,153.72 for maintenance.
   Proposed operations.-No funds are available and no work is ex-
pected to be needed during the fiscal year 1945.
   The sum of $15,000 can be profitably expended during the fiscal year
1946 for maintenance dredging by contract (November and December"
1945).
                 RIVERS AND HARBORS-GALVESTON,                                      TEX., DISTRICT                        791
                                                 Cost and financial summary
Cost of new work to June 30, 1944_                                                                      $14, 290. 95
Cost of maintenance to June 30, 1944                                                                       1, 153. 72
                                                                                                         8-------------------------

       Total cost of permanent work to June 30, 1944-    -95,                                                   444. 67
Net total expenditures ------------------------------                                                       95, 444. 67
Total amount- appropriated to June 30, 1944---- ---------                                                   95, 444. 67

    Fiscal year ending June 30                     1940            1941         1942           1943                  1944


Cost of new work----------------
Cost of maintenance ------.                         $447. 33        -     _   $11, 552. 67   -.--------
                                                                                                 -          -----



Total expended..............------------------.     447. 33    -               11, 552.67
Allotted ......           ...   ... ..    ....            -                   - -               .-- -   -           - -     -

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance-------------------------------                                               $15,        000.000.
                                                                                                                      00

                                         13. DICKINSON              BAYOU,      TEX.

   Location.-This bayou enters Galveston Bay on the west side about
20 miles northwest of Galveston. (See U. S. Coast and Geodetic
Survey Chart No. 1282.)
   Existing project.-This provides for a channel 6 feet deep and 60
feet wide at mean low tide along the present route from the natural
6-foot depth in Galveston Bay through Dickinson Bay and Dickinson
Bayou to the Galveston, Houston & Henderson Railroad bridge at
Dickinson. Under ordinary conditions the mean tidal range is about
0.9 foot and the extreme range about 1.6 feet. The height of tides is
dependent largely on the wind, and during strong north winds in the
winter season the water surface may be depressed 21/2 feet below mean
low tide.
   The estimated cost for new work, revised in 1938, was $42,000. The
latest (1938) approved estimate for annual cost of maintenance is
$12,500.
   Authority for the original dimensions (4 feet by 50 feet) of this
channel is explained in the Annual Report for 1931, page 1093. The
River and Harbor Act approved June 20, 1938, authorized the present
project dimensions (H. Doc. No. 568, 75th Cong., 3d sess.). The latest
published map is in this document.
   Local cooperation.-The work authorized by the River and Harbor
Act approved June 20, 1938, is subject to the provisions that local
interests shall furnish, without cost to the United States, all lands,
easements, and rights-of-way and spoil-disposal areas for the initial
work and for subsequent maintenance as required. These conditions
have not been complied with since no rights-of-way and spoil-disposal
areas were needed for initial construction.
   Terminal facilities.-The terminal facilities consist of small pri-
vately owned wharves for local use. They are considered adequate
for the existing commerce.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-The existing project was completed
in 1940. The controlling depth was 5.5 feet at mean low tide.
792         REPORT OF CHIEF OF ENGINEERS,                                U. S. ARMY,                  1944

  The total cost and expenditure to June 30, 1944, was $90,096.20 of
which $33,942.37 was for new work and $56,153.83 for maintenance.
  Proposed operations.-No fuinds are available and no work is ex-
pected to be needed during the fiscal year 1945.
  The sum of $20,000 can be profitably expended during the fiscal
year 1946 for maintenance dredging by contract (September and
October 1945).
                                     Cost of financial summary
Cost of new work to June 30, 1944--                       -__---------                                  $33, 942. 37
Cost of maintenance to June 30, 1944_                     ------                          -      --      56, 153. 83

       Total cost of permanent work to June 30, 1944-
Net total expenditures -------------------------------
                                                                                      _         -        90, 096. 20
                                                                                                         90, 096. 20
Total amount appropriated to June 30, 1944                     -------------                             90, 096. 20


   Fiscal year ending June 30          1940             1941             1942                  1943          1944

Cost of new work ...---------    ----- $24, 881. 98    $2, 773. 11    ...- $60                -----       _.--...
Cost of maintenance--------------------------------$600------------------..
                          -
Total expended...............         24, 531. 86      12, 123. 23              600   -

Allotted--------------- ----.--.              ---.-   -- 4, 255."09      -11,000--.-------------..
Amount that can be profitably expended in fiscal year
                                                      ending June
   30, 1946, for maintenance -------------------------------------                                      $20, 000. 00

                            S   14. FREEPORT HARBOR, TEX.

   Location.-This harbor is formed by the improvement of the Brazos
River, Tex., from the mouth to Freeport, about 6 miles above. (See
U. S. Coast and Geodetic Survey Chart No. 525.)
   The mouth of the Brazos River is about 47 miles southwest of
Galveston Harbor entrance and about 137 miles northeast of Aransas
Pass (Port Aransas).
   Previous projects.-Authorized by River and Harbor Act of June
14, 1880. For further details see page 1860 of Annual Report for 1915,
and page 872 of Annual Report for 1938.
   Ensting project.-This provides for a channel 32 feet deep from
deep water in the Gulf of Mexico to a point about one-half mile
below the Stauffer chemical plant with two turning basins, one 700
by 700 feet at Brazosport and one 600 by 600 feet at the upper end of
the channel, the channel to have a width of 300 feet seaward of the
jettied entrance, 200 feet from jettied entrance to the Brazosport turn-
ing basin, widened at the bend, and averaging 375 feet, thence to the
upper turning basin; the widths in the approaches to the turning basins
to converge within a distance of 800 feet from the width of the turning
basin to the width of the channel; and provides also for the extension
of the channel with a depth of 30 feet and a width of 200 feet to and
including the turning basin near the Stauffer chemical plant at Free-
port at a cost of $18,000 when required in the interests of commerce and
navigation. The work to be accomplished as may be found desirable,
by dredging, by jetties at the mouth of the harbor, and by a diversion
dam in the Brazos River, a diversion channel, and necessary auxiliary
works in general accordance with plan No. 6, as proposed by the dis-
trict engineer, together with a lock in the diversion dam, approxi-
                         RIVERS AND HARBORS-GALVESTON,                            TEX., DISTRICT                793
mately 200 feet long, 55 feet wide and 121/2 feet deep over the miter
sills. The River and Harbor Act of July 3, 1930, modified the act of
March 3, 1925, so as to provide that when local interests shall have
furnished assurances satisfactory to the Secretary of War that they
will maintain the diversion channel, the United States shall assume
the cost of maintenance of the navigable channel, estimated at $75,000
annually, including care and operation of the lock, if provided (Rivers
and Harbors Committee Doc. No. 18, 70th Cong., 1st sess.).
   Under ordinary conditions the mean tidal range is about 1.8 feet
and the extreme range about 21/2 feet. Freshets in the river, except
under extreme conditions, do not cause a greater variation in the water
surface than the tidal action.
   The estimated cost of new work, revised in 1935, is $2,504,000, includ-
ing $1,334,500 to be provided by local interests.
   The latest (1935) approved estimate of cost of annual maintenance
is $115,000 for 2 years after completion of the project and $100,000
thereafter.
   The existing project was authorized by the following river and
harbor acts:

       Acts                               Work authorized                                    Documents


Mar. 3,1899               Dredging and such other work as may be deemed        Specified in act.
                           most effective in the judgment of the Secretary
                           of War in improving and developing the harbor;
                           for taking over the jetties and other privately
                           built works at the mouth of the river.
Mar.       2,1907         Examination authorized. The work was subse-          H. Doc. No. 1087, 60th Cong., 2d sess.
                           quently confined to maintenance of the jetties.
Feb. 27, 1911             Repairs to jetties and dredging        _ __          Specified in act.
Mar. 4, 1913              Construction of a seagoing hopper dredge, one-           Do.
                           half the cost to be charged to this improvement
                           and one-half to Aransas Pass.
Aug.       8,1917         Purchase of one     15 inch pipe-line   dredge and   H. Doc. No. 1469, 63d Cong., 3d sess.
                           equipment, its operation for an experimental

                                   3
                           period of 3 years, the operation of the seagoing
                           dredge
                           jetties.
                                      time for 3 years, and repairs to the

Mar. 3,1925               Diversion dam, diversion channel, and necessary      Rivers and Harbors Committee Doc.
                           auxiliary works.                               .     No. 10, 68th Cong., 2d sess.
July       3,1930         Maintenance of the diversion channel at the ex-      Rivers and Harbors Committee Doc.
                           pense of local interests.                             No. 18, 70th Cong., 1st sess.
Aug. 30,1935 1 Dredging the channels and turning basins to                     Rivers and Harbors Committee Doc.
                           greater depths. (Project completed to within          No. 15, 72d Cong., 1st sess.
                           36 mile of the upper limit of the channel with
                           Public Works Administration funds and con-
                           tributed funds.)
Do---------...........    Maintenance of the present project dimensions        Rivers and Harbors Committee Does.
                           of the channels and turning basins at Federal         Nos. 15, 72d Cong., 1st sess., and
                           expense.                                              29,2 73d Cong., 2d sess.


   1 Included in Public Works Administration program, Sept. 6, 1933.
   2Contains latest published          maps.

  Local cooperation. All required local cooperation has been fully
complied with, except the 50-percent contribution toward the cost of
the extension of the channel to Freeport, which has not beenrequested.
  Ter'minal facilities.-The terminal facilities are located at the town
of Freeport at the upper end of this improvement and at a point about
794             REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,                 1944

a mile above the inner ends of the jetties. The facilities at Freeport
consist of a small wharf, privately owned, and one free public wharf
owned by the municipality of Freeport. The facilities just inside the
mouth of the river consist of one sulfur-loading dock, about 250 feet
long,-and one oil dock. The existing facilities are considered adequate
for the commerce that exists.
   Operationsand results during fiscal year-Maintenance.-The U. S.
seagoing hopper dredge Manhattan redredged the sea bar and jetty
channels from September 115 to October 31, 1943, removing 831,141
cubic yards (bin measurement) from a channel length of 9,000 feet at
a cost of $58,409.57.
   Under a contract the portion of the waterway from just above the
Brazosport turning basin to and including the upper turning basin
was redredged from October 20 to November 21, 1943; 722,371 cubic
yards of material were removed from a channel length of 8,100 feet at
a cost of $70,095.75. The U. S. seagoing hopper dredge Manhattan
redredged the sea bar and jetty channels from June 16 to 30, 1944,
removing 369,302 cubic yards (bin measurement) from a channel
length of 9,000 feet at a cost of $16,048.33.
   There were additional costs of $1,171.01 for miscellaneous surveys
and inspections, and $7.91 for purchase of a small tract of land and
minor improvements.
   The total cost of all work during the year was $145,732.57 all for
maintenance. The total expenditures were $147,499.31.
   Condition at end of fiscal year.-The existing project was about 85
percent completed. The work remaining to be done consists of dredg-
ing the extension of the channel to and including a turning basin near
the Stauffer Chemical Plant at Freeport and constructing a lock in the
diversion dam in the Brazos River.
   The controlling depths at mean low tide in the various channels and
turning basins were as follows: From deep water in the Gulf of Mex-
ico to the jettied entrance 31.2 feet; thence to the Brazosport turning
basin 29.7 feet; and the Brazosport turning basin 28 feet; in the chan-
nel above the Brazosport turning basin to and including the upper
turning basin, 33 feet; and in the remainder of the channel including
the turning basin at the Stauffer Chemical Plant, 17.5 feet.
   The total cost of the existing project to June 30, 1944, was as follows:

                                                             New work              Maintenance            Total

Regular funds_--          ---------------                   $1, 101,061.89        $2, 381,094. 77      $3, 482, 156.66
Public Works funds-------------                                 116, 574. 74--------------                 116, 574. 74
      Total United States funds_ .   ---------               1, 217, 636. 63         2, 381, 094. 77     3, 598, 731.40
Contributed funds (includes $225,000 contributed under
see. 4, River and Harbor Act of Mar. 4, 1915) ...-.....        758, 302. 79 ................              758, 302. 79

       Total all funds--.................................    1, 975, 939.42          2, 381, 094. 77     4, 357, 034.19



   The total expenditures were $3,600,695.41 of which $3,484,120.67                                             was
from regular funds and $116,574.74 from Public Works funds.                                                      In
addition $758,302.79 was expended from contributed funds.
   Proposed operations.-The balance unexpended at the end of                                                    the
fiscal year amointing to $134,697.28, including accounts receivable                                             and
             RIVERS AND HARBORS-GALVESTON,                                      TEX., DISTRICT                          795
an allotment of $85,000 made during July 1944, will be applied as
follows :
Maintenance:
     Dredge the sea bar and jetty channels with the U. S. seagoing
       hopper dredge Manhattan (July 1 to 31, 1944) -----------     -                                        $40, 000. 00
     Dredge the Brazosport turning basin and channel to and in-
       cluding the turning basin at the U. S. Coast Guard station
       by contract (Aug. 15 to Oct. 30, 1944)--------------     ____                                          94, 697. 28
           Total_ -------------------------------------------                                                134, 697.28
   The additional sum of $80,000 can be profitably expended during the
fiscal year 1946 for maintenance dredging of the sea bar and jetty
channels with an available United States seagoing hopper dredge
during July and August 1945.
                                    Cost and financial summary

Cost of new work to June 30, 1944_                                                                 1 $1, 364, 735. 06
Cost of maintenance to June 30, 1944                                                                  2, 381, 094. 77
      Total cost of permanent work to June 30, 1944_                                                    3, 745, 829. 83
Undistributed costs June 30, 1944----                                                                             -1.    50
       Net total cost to June 30, 1944__                                                                3, 745, 828. 33
Plus accounts receivable June 30, 1944                          --                                             1, 965. 51

         Gross total costs to June 30, 1944                                                             3, 747, 793. 84
Net total expenditures _ _______                                                                       13, 747, 793. 84
Unexpended balance June 30, 1944                      -_                                                      47,731.77

         Total amount appropriated to June 30, 1944                                                    1 3, 795, 525. 61

   Fiscal year ending June 30          1940                1941              1942              .1943              1944


C o sto f ne w w o rk                                  .-..............
                                                      _-
                                                      -=.             ...            . .. .. .. .. .. ..........         ....
Cost of maintenance .......          $56,
                                        698.73        $129,  85
                                                          326.             $86, 808. 17        $9, 409. 03      $145, 732. 57
Total expended--
               .56,                      827. 78        120, 998. 22        95, 228. 37         9, 656. 69       147, 499. 31

Allotted ...........    .......       46, 000. 00      165, 000. 00         72, 500. 00        90, 000 00


Balance unexpended July 1, 1943                 _-                     -         -         -             $195, 231. 08
Gross amount expended_-----                                --                                              147, 499. 31

      Balance:unexpended June 30, 1944---- --                                                                 47, 731. 77
Accounts receivable June 30, 1944_                                                                             1, 965. 51
     Unobligated balance available June 30, 1944-----------                                                   49, 697. 28
Amount allotted in July 1944_                        -85,                                                         000. 00
         Amount available during fiscal year 1945----------134,                                                   697. 28
Amount (estimated) required to be appropriated for completion
  of existing project                          ----                                        -                   9 000. 00
                                                                                                               9,--.---------
Amount that can be profitably expended in fiscal year ending
June 30, 1946; for maintenance 2_ __---_----------_                                                          80, 000. 00
1In addition, $758,302.79 was expended from contributed funds for new work.
2 Exclusive of available funds.
796        1EPORT OF CHIEF              OF ENGINEERS,              U.    S. ARMY,        1944

       15. CHANNEL FROM PASS CAVALLO TO PORT LAVACA, TEX.

   Location.-The bar at Pass Cavallo is 125 miles southwest of Gal-
veston entrance and 54 miles north of Aransas Pass. Port Lavaca lies
26 miles to the northwest of the pass, across Matagorda and Lavaca
Bays. (See U. S. Coast and Geodetic Survey Chart No. 1117.)
   Eaisting project.-This provides for a depth of 9 feet and a width
of 100 feet from Lynns Bayou at Port Lavaca, Tex., to deep water in
Matagorda Bay near Port O'Connor, Tex., a distance of about 11
miles. Under ordinary conditions the mean tidal range is- about
1 foot and the extreme range about 2 feet. The height of tide is
dependent largely on the wind, and during strong "northers" in the
winter season the water surface may be depressed 2 feet below mean
low tide.
   The estimate of cost for new work, revised in 1937, was $138,874.
The latest (1937) approved estimate of cost for annual maintenance
is $15,000.
   The existing project was authorized by the following river and
harbor acts:

    Acts                       Work authorized                                     Documents


June 25,1910    Channel to Port Lavaca, Tex., 7 feet deep and 80    H Doc. No. 1082, 60th Cong., 2d sess,
                 feet bottom width.
Aug. 30, 1935   Extension of 7-foot channel to the shore line of    Rivers and Harbors Committee Doc.
                 Lavaca Bay at the mouth of Lynns Bayou.              No. 28, 74th Cong., 1st sess.
Aug. 26, 1937   Deepen and widen channel to present project         Rivers and Harbors Committee Doc.
                 dimensions.                                          No. 37, 75th Cong., 1st sess. (Con-
                                                                        tains latest published map.)


  Recommended modification of project.-Under date of May 25,
1939, the Chief of Engineers recommended modification of the exist-
ing project so as to provide a channel 100 feet wide and 6 feet deep
from Port Lavaca by way of Lavaca Bay and Lavaca River to about
mile 3 on the Navidad River, a total distance of 20 miles, at an
estimated first cost of $85,000, with annual maintenance of $10,000, in
addition to that now required; subject to certain conditions of local
cooperation (H. Doc. No. 314, 76th Cong., 1st sess.).
   Further modification of the existing project was recommended by
the Chief of Engineers December 10, 1943, in a report requested by
Rivers and Harbors Committee resolution adopted January 21, 1942,
and transmitted to Congress by the Secretary of War February 11,
1944.
  Local cooperation.-Fully complied with.
   Terminal facilities.-The terminal facilities consist of several pri-
vately owned piers and two privately owned slips at Port Lavaca,
and a municipally owned wharf, turning basin, and refrigerated sea-
food processing and packing plant at the mouth of Lynns Bayou.
The municipally owned facilities are open to the general public and
are adequate for existing commerce.
   Operations and results during fiscal yea.-From July 1 to 7, 1943,
119,898 cubic yards of material were removed from a reach of the
waterway 10,491 feet in length between Lynns Bayou and Gallinipper
               RIVERS AND HARBORS-GALVESTON,                                      TEX., DISTRICT                              797
Reef, by contract, at a cost of $12,906.07. Miscellaneous surveys were
made at a cost of $309.06. The total cost of work during the fiscal
year was $13,215.13, all for maintenance. The total expenditures were
$42,607.17.
   Condition at end of fiscal year.-The existing project was completed
in 1939. The controlling depth at mean low water was 71/2 feet.
   The total cost and expenditures to June 30; 1944, were $218,608.24,
of which $111,494.49 was for new work and $107,113.75 was for main-
tenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $58,296.75, including an allotment of $57,500
made during July 1944, will be applied to performing maintenance
dredging where necessary during October and November 1944.
   The additional sum of $15,000 can be profitably expended in the fiscal
year 1946 for maintenance dredging where necessary, by contract,
about October 1945.
                                    Cost and financial summary
Cost of new work to June 30, 1944__                       111111111                                             $111, 494. 49
Cost of maintenance to June 30, 1944_-                                           - --         _____107,               113. 75
          Total cost of permanent work to June 30, 1944-                                         -               218, 608.&24

Net total expenditures-                                                           _                  _-          218, 608. 24
Unexpended balance June 30, 1944                                    --------------------                              796. 75

          Total amount appropriated to June 30, 1944                        --------                             219, 404. 99

   Fiscal year ending June 30         1940               1941                1942                    1943                  1944

Cost of new w ork .-                    - --.-.-          - --..-     .-.. --.      .   . .    . . .        .   . .   .     . .   .
Cost of maintenance .......          $1,624. 41        $45, 060. 15         $1, 177. 51        $36,190. 31                $13, 215.13

Total expended------------------      2, 830. 16        45, 003. 10          1,088.32            6, 945. 82                42, 607. 17

Allotted...----------------------    12, 500. 00        17, 500.00           1, 500. 00         35, 000. 00



Balance unexpended July 1, 1943_ _                 -            -            -            -            -         $43, z03. 92
Gross amount expended_------------                                                            ----                42, 607. 17

     Balance unexpended June 30, 1944-----------------------                                                          796. 75
Amount allotted in July 1944---  -----          -     ____                                                        57, 500. 00

         Amount available during fiscal year 1945                     -----------------                           58, 296. 75

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 1--------------15,                                                                               000. 00
  I Exclusive of available funds.

            16. PORT ARANSAS-CORPUS CHRISTI WATERWAY, TEX.

  Location.-This is a consolidation of the old improvements of
Port Aransas, Tex., and the channel from Aransas Pass to Corpus
Christi, Tex. Aransas Pass is on the southern portion of the coast,
of Texas, 180 miles southwest of Galveston and 132 miles north of
the mouth of the Rio Grande. Aransas Pass connects Corpus Christi
Bay and Aransas Bay with the Gulf of Mexico. The waterway ex-
tends from deep water in the Gulf through the Aransas Pass jettied
entrance, thence westerly 204 miles to and including a turning basin
798            REPORT OF CHIEF OF ENGINEERS,                                       U.      S. ARMY,                 1944

at Corpus Christi, thence westerly 13/4 miles through the Industrial
Canal to and including the turning basin at Avery Point, thence
westerly 41/4 miles to and including a turning basin near Tule Lake.
 (See U. S. Coast and Geodetic Survey Charts Nos. 1285 and 1286.)
   Previous projects.-The original project for improvement of
Aransas Pass (Port Aransas) was authorized by the River and Har-
bor Act of March 3, 1879. The improvement was taken over by the
Aransas Pass Harbor Co. on June 30, 1890, under authority of the
act of May 12, 1890. This company relinquished its rights to the
United States on March 27, 1899. The channel from Aransas Pass
to Corpus Christi was first improved under the River and Harbor
Acts of March 2, 1907, and June 25, 1910.
   For further details see page 1861 of Annual Report for 1915 and
page 877 of Annual Report for 1938.
   Existing project.-The modified project dimensions provided for
in the various channels and basins comprising this waterway are shown
in the following tabulation:

                                                                              Adopted project dimensions

Section of the Port Aransas-Corpus Christi                                                                                     Depthin
               Waterway, Tex.                                                                                                  feet below
                                                                         Bottom width in feet                                  mean low
                                                                                                                               Gulf level


Aransas Pass outer bar -------------------              700---------------------------------------                                          37
Aransas Pass jetty channel     -----------------        600 from inner end to opposite station 90,
                                                           north jetty, thence increasing to 700 at
                                                                                                                                      (1)
                                                           outer end of jetty.
Inner basin at iarbor Island ---------------            650 by 3,0        long     ----------------------------
                                                                                     _        .....                                         30
Inner basinat Clines Point to west end Humble           400 at east an4d ecreasing to 300 at west end_                                      35
  Oil & Refining Co., basin.
Channel to town of Port Aransas_ .........              10....----------------------------------------                                      12
Channel from Port Aransas to Corpus Christi             200-----------------------------------------                                        32
turning basin.
Corpus Christi turning basin-------... --------         1,000 by 5,500 long (includes approach to                                           32
                                                           turning basin).
Industrial Canal   ------------------------             150----------------------------------------                                         32
Turning basin at Avery Point__-.............. --        800 by 1,200 long _------------------------32
Channel to vicinity of Tule Lake- .........             150...............................----------------------------------------.         32
Turning basin near Tule Lake .........-------------..   900 by 1,000 long ----------------------------                                      32

  1   35 feet from inner end to opposite station 90, north jetty, increasing to 37 feet at outer end of jetty.

    The project also provides for two rubblestone jetties at Aransas
Pass entrance, extending into the Gulf from St. Joseph and Mustang
Islands, the project lengths of which are 11,190 and 8,650 feet, re-
spectively. The project further provides for a stone dike on St.
Joseph Island about 19,100 feet long connecting with the north jetty
and extending up this island to prevent a channel being cut around
th jetty.
   Under ordinary conditions the mean tidal range at Aransas Pass
is about 1.1 feet and the extreme range about 2 feet, and at Corpus
Christi the mean range about 1 foot and the extreme about 11/2 feet.
The heights of tides are dependent largely on the strength and direc-
tion of winds, and during strong north winds in the winter season
the water surface may be depressed as much as 3 feet below mean low
Gulf level.
   The estimated cost for new work, revised in 1941, exclusive of
amounts expended on previous projects is $11,000,000. The latest
 (1938) approyed estimate for annual cost of maintenance is $624,000.
                 RIVERS AND HARBORS-GALVESTON,                            TEX., DISTRICT                 799
  The existing project was adopted by the following river and harbor
acts:

      Acts                       Work authorized                                     Documents



Mar.    3,1899  Acquisition of the old curved portion of the north     Specified in act.
                 jetty previously constructed by private parties.
June 13, 1902   Completion of north jetty in accordance with the           Do.
Mar. 3, 190.5    plaas of its ,builder .
Mar. 2, 1907 Connection of old curved jetty to St. Joseph Is-          Rivers and Harbors Committee Doc.
                  land, and construction of south jetty.                 No. 5, 59th Cong., 2d sess.
Feb. 27,1911 Dredging roadstead in Harbor Island Basin to              H. Doc. No. 1094, 61st Cong., 3d sess,
                  depth of 20 feet and construction of 10,000 linear
                  feet of the stone dike on St. Joseph Island.
Mar. 4,1913     Deepening of channel between jetties and the Har-      H. Doc. No. 1125, 62d Cong., 3d sess.
                  bor Island Basin to depth of 25 feet, extension of
                 jetties seaward, extension of dike on St. Joseph
                  Island 9,100 feet, and dredging the approach
                  channel 12 feet deep to town of Port Aransas.
Sept. 22, 1922 Dredging channel from Aransas Pass to Corpus            H. Doc. No. 321, 67th Cong., 2d sess.
                  Christi, 25 feet deep, 200 feet bottom width.
                                                                                                                t
July 3, 1930    Deepening entrance channel from Gulf of Mexico         H. Doc. No. 214, 70th Cong., 1st sess.
                  to Harbor Island and provision of an inner basin
                  at Harbor Island of reduced area but greater
                 depth.
    Do -.--     Aransas Pass to Corpus Christi Channel with            Rivers and Harbors Committee Doc.
                  depth of 30 feet.                                      No. 9, 71st Cong., 1st sess.
Aug. 30, 1935 2 Enlarging all channels from the Gulf to the west-      Rivers and Harbors Committee Doc.
                 ern end of basin dredged by Humble Oil & Re-           Nos. 35, 72d Cong., 1st sess.,' and 40,
                                                                                            1
                 fining Co. at its docks on Harbor Island, with         73d Cong., 2d sess.
                  PublicWorks Administration funds.
    Do .... Maintenance of channel and maneuvering basin               H. Doc. No. 130, 72d Cong., 1st sess.
                 between breakwater and western shore line of
                  Corpus Christi Bay.
    Do ..... Maintenance to 30 feet depth, except on strips
                 lying 50 feet channelward of any established
                                                                       Rivers and  -Iarbors Committee Doc.
                                                                        No. 13, 74th Cong., 1st sess.
                                                                                                      1

                 pierhead lines or within 50 feet of the foot of any
                 wharf or structure of the approach channel,
                 turning basin at Corpus Christi, Industrial
                  Canal and turning basin at Avery Point.
Aug. 30, 1935 Maintenance and deepening to 32 feet of the chan-        Rivers and Harbors Committee Doc.
                 nel from deep water at Port Aransas to and in-         No. 63, 74th Cong., 1st sess.'
                 cluding the turning basin at Corpus Christi.
June 20,1938 Extend the main turning basin at Corpus Christi           H. Doc. No. 574, 75th Cong., 3d sess.'
                 westward 2,500 feet at its present width and
                 depth, deepen the existing Industrial Canal and
                 turning basin to 32 feet and for the extension of
                 this canal at a depth of 32 feet and general width
                 of lE0 feet, westward along Nueces Bay shore to
                 a turning basin 32 seet deep, 900 feet wide, and
                 1,000 .feet long near Tule Lake.


  1 Contain the latest published maps.
  2 Included in Public Works Administration program Sept. 6, 1933, and Feb. 16, 1935.


  Recomimended modification of project.--Under date of March 30.
1944, the Chief of Engineers recommended modification of the existing
project, so as to provide for a depth of 34 feet in all the project
channels and basins from Port Aransas to and including the Tule
Lake turning basin, for a channel 250 feet wide between Port Aransas
and the breakwater at Corpus Christi; for a width of 200 feet in the
800    REPORT OF CHIEF OF ENGINEERS,        TJ. S. ARMY,   1944

Industrial Canal and in the channel between the Avery Point and
Tule Lake turning basins and for widening the Avery Point turning
basin to 1,000 feet, at an estimated cost of $830,000 for new work
and $25,000 annually for maintenance in addition to the amounts now
required; subject to certain conditions of local cooperation (H. Doc.
No. 544, 78th Cong., 2nd sess.).
   Local.cooperation.-Underprovisions of the River and Harbor Act
of June 20, 1938, local interests are required to furnish, free of cost
to the United States, necessary lands, rights-of-way, and spoil-disposal
areas for initial work and for subsequent maintenance as may be
required, and release the United States from all claims for damages
attributable to the work of improvement; and provided further,
that deepening of the existing Industrial Canal with its turning basin
and construction of the proposed extension thereto and new turning
basin near Tule Lake shall not be undertaken until and unless the
Nueces County navigation district furnishes assurances satisfactory
to the Secretary of War that bona fide arrangements have been made
with various industries so as to guarantee additional tonnage sufficient
to warrant the construction and maintenance of the extension of the
Industrial Canal to any point up to and including the proposed
turning, basin near Tule Lake. All prior requirements fully com-
plied with.
   Terminal facilities.-Terminal facilities located on Harbor Island
at the head of Aransas Pass, Ingleside, Corpus Christi, and Avery
Point are considered adequate for existing commerce. (See Port
Series, No. 6, pt. 3, Corps of Engineers.)
   Operationsand results during fiscal year.-Maintenance.-The U. S.
seagoing hopper dredge Manhattan redredged the sea bar and jetty
channel from November 1 to December 31, 1943, removing 613,733
cubic yards (bin measurement) from a channel length of 9,000 feet
at a cost of $91,175.64.
   Under a contract the maneuvering basin and the channel easterly
thereof to station 1000+00 were redredged from June 14 to 30, 1944;
639,339 cubic yards of material were removed from a channel length
of 9,600 feet at a cost of $48,136.36.
   There were additional costs of $11,572.91 for miscellaneous surveys
and inspections.
   The total cost of all work during the year was $150,884.91, all for
maintenance. The total expenditures were $112,318.90.
   Condition at end of fiscal year.-The existing project was about 47
percent completed. The two jetties have been built to partial project
lengths, the north jetty being 9,240 feet long and the south jetty
7,385 feet long. A stone dike connecting with the north jetty has
been constructed on St. Joseph Island, its total length being 20,991
feet; this part of the project was completed in 1916. The channel
between the jetties from the Harbor Island Basin to the Gulf has
been dredged to 35 feet at mean low tide inside and 37 feet deep at
the Gulf end. Harbor Island Basin has been deepened to 30 feet
at mean low tide over an area 650 feet wide and about 1,000 feet
long at the lower end adjacent to the dock.
   The approach channel from Harbor Island Basin to the town of
Port Aransas was completed in 1914. The channel to Corpus Christi,
                RIVERS AND HARBORS-GALVESTON,                                                    TEX., DISTRICT                        801
including a turning basin approximately 1,000 feet wide and 5,500 feet
long, and the approach channel were completed in 1940. The indus-
trial canal arid turning basin at Avery Point have been dredged to
30.feet.
   The work required to complete the existing project consists of
extension of the jetties estimated to cost $5,000,000; enlargement of
the Harbor Island Basin at an estimated cost of $120,000 deepening
the Industrial Canal and turning basin at Avery Point, and dredging
the channel from Avery Point turning basin to and including a turning
basin near Tule Lake estimated to cost $742,000. These items of work
are not required at the present time.
   The controlling depths along the center line of various sections of
the channels and turning basins were as follows:
                                                                                                                               Depth in feet
                                                                                                                                below mean
                                                                                                                                  low tide
Deep water in the Gulf of Mexico to station 90 on North Jetty------- --                                                                38. 5
Station 90 on North Jetty to Clines Point--------------------------                                                                    29. 7
Clines Point to westward end of Humble Basin--------------- - -                                                                        32. 4
Inner Basin at Harbor Island -             -           -30.                                                                                7
Channel to Port Aransas------------------------- ---------------                                                                       14. 1
Channel, Port Aransas to Corpus Christi turning basin---- -----------                                                                  28. 8
Turning basin at Corpus Christi ----------------------------------                                                                     33. 8
Industrial canal-----       --------------                         ----                                                                33. 8
Turning basin at Avery Point ------------------------------------                                                                      34.2
  The total cost of the existing project to June 30, 1944, was as
follows:

                                                                                     New work              Maintenance           Total


Regular funds                                                            . $4, 811,471.32
                                     ....----------------------------------..                              $6, 972, 788. 01   $11, 784, 259. 33
                          -
Public Works funds-...............                   .......                         -...324, 287.14   -                          324, 287.14
     Total United States funds .-....-.               ......              ....       5,135, 758. 46         6, 972, 788. 01    12,108, 546. 47
Contributed funds-.. -.......... _._ --..               .       ......-          _-____-_______-               152, 555. 09       152, 555. 09

       Total all funds_- ........            -.-.-.................                  5,135, 758. 46         7,125, 343. 10     12, 261, 101. 56



   The total expenditures were $12,069,076.02, of which $11,744,788.88
was from regular funds and $324,287.14 from Public Works funds.
In addition $152,555.09 was expended from contributed funds for
maintenance.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $418,987.73, including an allotment of $50,000
made during July 1944, will be applied as follows:
Accounts payable June 30, 1944------------------------------$9,                                                                    663. 00
Maintenance:
    Complete existing contract for dredging the channel between
      station 1096+00 and station 640-+00 and between station
      43+00 and station 4+00 (July 1 to Aug. 30, 1944) ......      170,                                                            238. 61
    Dredge sea bar and jetty channels with an available United
      States seagoing hopper dredge (December 1944 and January
      1945) --                                                      80,                                                            000. 00
    Dredge the channel eastward of station 640+00 to Port Aransas,
      by contract (April and May 1945) ---------------------- 159,                                                                 086. 12

              Total          -----------------------------------------                                                        418, 987. 73


          616634-45-pt. 1, vol. 1-                  51
802          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                            1944

   The additional sum of $251,000 can be profitably expended during
fiscal year 1946 as follows:
Dredge the sea bar and jetty channels with an available United States
seagoing hopper dredge (January, February, and March, 1946)...       $105, 00                                                     -
Dredge the inside channels and basins where necessary, by contract
  (April, May, and June, 1946) --------------------------------        146, 000

           Total        -----------------------------------------------                                                                    251,000

                                                   Cost and financial summary
Cost of new work to June 30, 1944_--------                                                            ---                        $6, 508, 292. 89
Cost of maintenance to June 30, 1944_------                                                                 ---                  1 7, 035, 239. 87

      Total cost of permanent work to June 30, 1944---------                                                                     13, 543, 532. 76
Undistributed costs June 30, 1944                                                                                                   -29, 807. 45

      Net total cost to June 30, 1944_------           ---                                                                       13, 513, 725. 31
Minus accounts payable June 30, 1944-----------------------                                                                            9, 663. 00

      Net total expenditures ---------------------------                                                                     1   13, 504, 062. 31
Unexpended balance June 30, 1944_--------                ---                                                                         368, 987. 73

           Total amount appropriated to June 30, 1944                                                                        1 13, 873, 050. 04

    Fiscal year ending June 30                           1940         1941                     1942                   1943                    1944

Cost of new work       _______-            .       $228,408. 95     $11, 529.05    .........                       .......               ......
Cost of maintenance- ..          ___           .    284, 298. 49    241, 730. 89      $147, 289. 91               $495, 002.06            $150,884. 91

       Total cost   ---------------                 512, 707. 44    253, 259. 94         147, 289. 91             495, 002.06              150,:884. 91

Total expended-----.........     ____...            443, 399. 49    357,153. 57          102, 236. 14              538, 745.35              112, 318. 90

Allotted                       .---------------------
                                           300,200.00               450, 000.00         172, 724. 12               105, 000.00-



Balance unexpended July 1, 1943 ---------------------------                                                                         $481,306. 63
Gross amount expended_---          -----------                                                                                    -112, 318. 90
      Balance unexpended June 30, 1944_                                                                                                368, 987. 73
Outstanding liabilities June 30, 1944-- -----       $20. 48
Amount covered by uncompleted contracts------- 137, 296. 48
                                                                                                                                       137, 316. 96
     Balance available June 30, 1944_
                                                                                                                                       231, 670. 77
Amount allotted in July 1944_                                                                                                           50, 000. 00
           Amount available during fiscal year 1945-                                                                                   281, 670. 77
Amount (estimated) required to be appropriated for completion
                                   _
   of existing project           2-                  -          -    _         -                                                   5, 862, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for maintenance 2-       -     -     --     -                                                                           251,000. 00
  1In addition, $152,555.09 was expended from contributed funds for maintenance.
  2Exclusive of available funds.

17. CORPUS CHRISTI, TEX.-CHANNEL TO AND INCLUDING A TURNING
       BASIN AT NAVY SEAPLANE BASE, ENCINAL PENINSULA

   Location.-This improvement is an extension to-the Port Aransas-
Corpus Christi waterway, Texas. The channel                  in a south-                                etends
westerly direction from the Port Aransas-Corpus Christi waterway
opposite McGloins Bluff, to the western shore of Corpus Christi Bay
at Encinal Peninsula, a distance of 8.7 miles, including a turning basin
             RIVERS AND HARBORS-GALVESTON,                                        TEX., DISTRICT                803
'2,000 feet square. For the entrance from the Gulf and channel to the
turn-off point see "Location" under the Port Aransas-Corpus Christi
waterway, Texas.
    Existing project.-This provides for a channel 30 feet deep and
200 feet wide and for a turning basin at the southwest end, 30 feet
deep and 2,000 feet square.
    Under ordinary conditions the mean tidal range at Encinal Penin-
sula is about 1 foot, and the extreme about 11/2 feet. The height of
tides is dependent largely on the strength and direction of winds.
Durig strong-north winds in the winter seasop the water surface may
be depressed as much as 3 feet below mean iowi   Gulf level.
    The estimate of cost for new work, made in 1940, was $1,500,000.
The approved (1940) estimate of annual cost of maintenance is
 $300,000.
    The existing project was authorized by the River and Harbor Act
of October 17, 1940, and in accordance with the report on file in the
Office, Chief of Engineers.
    Terminal facilities.-Those constructed, and to be constructed are
owned by the United States Navy and will not be open to the public.
    Operationsand results duringfiscal year.-No maintenance dredging
was done. This waterway was used during the year by shallow draft
vessels only. There were costs of $3,129.47 for miscellaneous surveys
and inspections, and $909.55 for preliminary surveys for plans and
specifications. The total cost for the year was $4,039.02, for main-
tenance. The total expenditures were $4,254.80.
    Condition at end of fiscal year.-The existing project was completed
December 10, 1941.
    The controlling depth at mean low tide along the center line of the
channel: was 24.8 feet and in the turning basin25 feet.
    The total cost and expenditures on the existing project to June 30,
1944, were $1,205,067.45, of which $1,194,344.69 was for new work and
 $10,722.76 was for maintenance.
    Proposed operations.-Theallotment of $200,000 made during July
1944 will be applied to maintenance dredging of the channel and
turning basin by contract, if required by Navy vessels.
    The additional sum of $100,000 can be profitably expended during
the fiscal year 1946 in redredging the channel and turning basin where
necessary, by contract (January through June, 1946.)
                                        Cost and financial summary

Cost of new work to June 30, 1944---------- ----------         $1, 194, 344. 69
Cost of maintenance to June 30, 1944--------------------------      10, 722. 76
       Total cost of permanent work to June 30, 1944 ----------                                      1, 205, 067. 45
Net total expenditures -                 ----                                                        1, 205, 067, 45
Total amount appropriated to June 30, 1944----11      -       -                                      1',205;O67. 45

   Fiscal year ending June 30                1940             1941              1942          1943           1944

Cost of new work               I..        -     $550, 585. 30 $643,759. 39
Cost of maintenance----
                     ...--......--
                                ----------------------------------------                     $6,683.74       $4,039.02
Total expended   ...---------..........
                                ------------                173, 881. 79   1, 020, 462. 81    6,468.05        4,254.80

Allotted             ...---------------------..
                                            --    --- -   1, 500,000. 00   -105, 356. 42     10,000. 00   -199, 576. 13
804        REPORT OF CHIEF OF ENGINEERS,               U.   S.   ARMY,   1944

Balance unexpended July 1, 1943-------- -------------------               $203, 830. 93
Deductions on account of revocation of allotment-   --  _199,                   576. 13

      Net ainount to be accounted for-----------------------                    4, 254. 80
Gross amount expended-------------------------------                            4, 254. 80
Balance unexpended June 30, 1944___
Amount allotted in July 1944_-     -     -----------                       200, 000. 00
Amount available during fiscal year 1945   ---------------------           200, 000. 00
Amount 'that can be profitably expended in fiscal year ending
June 30, 1946: For maintenance 1-           -     -    _100,                     000.00
I Exclusive of available funds


                          18. BRAZOS ISLAND HARBOR, TEX.

   Location.-At the extreme south end of the coast of Texas, about 7
miles north of the mouth of the Rio Grande, and about 125 miles south
of Port Aransas. The harbor is at the inner end of Brazos Santiago
Pass, which lies between Brazos and Padre Islands, and is the natural
outlet from the Laguna Madre to the Gulf of Mexico. (See U. S. Coast
and Geodetic Survey Chart No. 1288.)
   Previous projects.-Authorized by River and Harbor Acts of June
18, 1878, March 3, 1881, and March 2, 1919. For further details see
page 1017, Annual Report for 1932 and page 882, Annual Report for
1938.
   Exsting project.-This provides for a channel 31 feet deep and
300 feet wide through Brazos Santiago Pass; for a channel 28 feet
deep and 100 feet wide from the pass to a point on the westerly side
of Long Island; for a channel 28 feet deep and 100 feet wide from
the end of Brazos Santiago Pass-Long Island Channel to and in-
cluding a turning basin 600 feet wide by 700 feet long at Point Isabel;
for a channel 28 feet deep and 100 feet wide from the end of Brazos
Santiago Pass-Long Island Channel to and including a turning basin
1,300 feet long and 1,000 feet wide in the vicinity of Brownsville and
for the easement of bends and curves. The project also provides for
two jetties at the Brazos Santiago Pass entrance. The project further
provides that all inside channels and turning basins may be widened
with the approval of the Chief of Engineers provided local interests
bear the entire cost. Under ordinary conditions the mean tidal range
is about 11/2 feet and the extreme range about 2 feet. The height of
the tides is dependent, to some extent, on the wind, and during strong
"northers" in the winter season the water surface in the southern end
of the Laguna Madre may be raised 4 feet or more above the mean low
tide in the Gulf.
    The estimate of cost for new work, revised in 1938, was $5,185,000,
inclusive of $2,425,000 contributed by local interests, but exclusive
of amounts expended on previous projects. The latest (1937) ap-
proved estimate of annual cost of maintenance is $150,000.
                 RIVERS AND HARBORS-GALVESTON,                            TEX., DISTRICT                805
  The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                   Documents


July    3,1930    Jetty channel, all inside channels and turning        Rivers and Harbors Committee Doc.
                   basins, and 2 rubble mound jetties.                   No. 16, 71st Cong., 2d sess.
May 24,1934       Local cooperation requirements modified to pro-       Rivers and Harbors Committee Doe.
  (P. W. A.)       vide for the contribution of sufficient funds to      No. 10, 72d Cong., 1st sess.
Aug. 30, 1935      cover the entire cost of the original dredging of
                    all inside channels and turning basins.
Aug. 26, 1937    Deepening the jetty channel to 31 feet and all inner   Rivers and Harbors Committee Doc.
                   channels and the Brownsville and Point Isabel          No. 32, 75th Cong., 1st sess. (Con-
                    turning basins to 28 feet, provided no dredging      tains latest published map.)
                    will be done at public expense within 50 feet of
                    any established pierhead line, wharf, or other
                    structure.



  Recommended modifications of project.-Under date of May 25,
1939, the Chief of Engineers recommended modification of the exist-
ing project, so as to provide for the enlargement of the turning basin
at Port Isabel, Texas, to 1,300 feet in length and 1,000 feet in width,
with a flared entrance, at an estimated first cost of $127,500, with an-
nual maintenance of $5,000 in addition to that now required, subject
to certain conditions of local cooperation (H. Doc. No. 335, 76th
Cong., 1st sess.).
   Under date of May 6, 1941, the Chief of Engineers recommended
further modification of the existing project to provide for deepening
the channel through Brazos Santiago Pass to 35 feet from deep water
in the Gulf of Mexico to station 0+000; deepening and widening the
bay channel to 33 by 200 feet from station 0+000 to station 15+525;
deepening the Brownsville Channel to 32 feet from station 15+525
to station 82+ 890; deepening the Port Isabel Channel and turning
basin to 32 feet; extending the north side of the Brownsville turning
basin 5,140 feet to the east and deepening the, basin to 32 feet; and
dredging the shallow-draft channel from the railroad bridge around
the south part of Port Isabel, to the shore line of Laguna Madre and
the shallow-draft channel connecting with the Port isabel turning
basin to provide a depth of 6 feet and a width of 60 feet; at an esti-
mated first cost of $635,000 with $22,000 annually for maintenance in
addition to that now required; subject to certain conditions of local
cooperation (H. Doc. No. 347, 77th Cong., 1st sess.).
   Local cooperation.-Fullycomplied with.
   Terirnal facilities.-On the westerly side of the turning basin at
Point Isabel there is a steel-sheet pile wharf about 550 feet long, pro-
vided with a sheet-metal transit shed 100 feet wide and 350 feet long
and a precooling plant of approximately 24 cars capacity each 8 hours.
Westward, about 70 feet back of the warehouse on the dock, is a
sheet-metal warehouse 100 feet wide and 200 feet long. Along the
north side of the turning basin, distinctly separate from other struc-
tures, is an oil dock 300 feet long equipped for receiving and loading
oil cargoes. All the facilities above mentioned are owned by the Port
Isabel, San Benito navigation district. An oil refinery and storage
806     REPORT OF CHIEF OF ENGINEERS,            U. S. ARMY,     1944

tanks, served by pipe line, all privately owned, are located near the
Point Isabel turning basin. This refinery has a maximum daily ca-
pacity of 7,500 barrels of refined products and a tank storage capacity
of 360,000 barrels. The entire terminal system has railroad and high-
way connections and is open to all on equal terms. All docks and
wharves are equipped with facilities for bunkering ships and servicing
with fresh water and electric current.
   Thet Brownsville navigation district has constructed along the
north side of the Brownsville turning basin 3 concrete wharves, each
approximately 400 feet long, provided with sheet-metal-covered tran-
sit sheds, each approximately 80 feet wide and 400 feet long. Along
the west side of the turning basin is a concrete wharf about 400 feet
long provided with a sheet-metal-covered transit shed enclosing a
precooling plant of 100 cars daily capacity. To the north of the
general cargo terminal is a high-density cotton compress, privately
owned, with storage sheds for about 25,000 bales of cotton. All docks
and wharves are equipped with facilities for servicing ships with
fresh water and electric current. There are no bunkering facilities
at this terminal. To the eastward of the general cargo terminal is a
creosoted-pile oil dock owned by the Brownsville navigation district
for unloading refined-oil cargoes into nearby privately owned storage
tanks of approximately 15,000 barrels capacity. This terminal has
railroad and highway connections and is open to all on equal terns.
   The terminals, as provided at Point Isabel and Brownsville, are
sufficient for existing and prospective commerce.
   Operations and results duvring fiscal year-Maintenance.-TheU. S.
seagoing hopper dredge Hoffman redredged the sea bar and jetty
channel, and the inside channel across the Laguna Madre from July 1
to September 15, 1943, removing 408,771 cubic yards (bin measure-
ment) from a channel length of 20,000 feet at a cost of $72,163.21.
   The U. S. pipe-line dredge Welatka redredged a portion of the chan-
nel across Laguna Madre, from June 20 to 30, 1944, removing 47,332
cubic yards of materials from a channel length of 577 feet at a cost of
$46,634.63.
   There were additional costs of $10,906.77 for miscellaneous surveys
and inspections.
   The total cost of all work during the year was $129,704.61, all for
maintenance. The total expenditures were $116,934.76.
   Condition at end of flcal year.-The existing project was completed
in 1940. The 25-foot project channels and jetties were completed in
1936. The sea bar and jetty channels and the channel from inside the
pass to a point opposite Long Island, and thence to the turning basins
at Point Isabel and Brownsville were deepened to the new project
dimensions in 1940.
  The controlling depths along the centerline of the various channels
and turning basins were as follows:
                                                                        Depth infeet
                                                                         below mean
                                                                          lbw tide
Deep water in the Gulf of Mexico to jettied entrance------------------   32
Jetty channel to inside the Pass_    -        -    -    -    -     -     31. 9
Channel inside the Pass to Long Island.                                  26. 0
Channel from Long Island to Point Isabel turning basin                    27. 9
Point Isabel turning basin-                                              29. 5
Channel from Long Island to Brownsville turning basin-                   26
Brownsville turning basin     -                                        .30. 4
                 RIVERS            AND        HARBORS-GALVESTON,                         TEX.,        DISTRICT                  807

   The total cost of the existing project to June 30, 1944, was as
follows:

                                                                             New work           Maintenance               Total


Regular funds...--------....--.................--------------------------     $710,071. 15        $1, 199, 518.46  $1, 909, 589. 61
Public Works funds_ ------------------------------                           2, 848, 560. 03   ....             --..2, 848, 560. 03
     Total United States funds...---------------------                       3, 558, 631. 18       1, 199, 518.46        4, 758, 149. 64
Contributed funds      __
                   --------------------------------                          1, 683, 257. 70                             1, 683, 257. 70

       Total all funds-----------------------------.__                       5, 241,888.88         1,199, 518. 46        6, 441, 407. 34


   The total expenditures were $4,747,778.20 of which $1,899,218.17
was from regular funds and $2,848,560.03 from Public Works funds.
In addition $1,683,257.70 was expended from contributed funds for
new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $250,471.98, including an allotment of
$125,000 made during July 1944, will be applied as follows:
Accounts payable June 30, 1944                                                                                              371. 44
                                                                                                                      $-------------$10,
Maintenance:
    Dredge the inside channels and basin west of station 2 +000
      where necessary with the U. S. pipe-line dredge Welatka
      (July 1 to Dec. 30, 1944)-  -                      -160,                                                              100. 54
    Dredge sea bar and jetty channels with the U. S. seagoing hop-
      per dredge Manhattan (February and March 1945)--.        .                                                       80, 000. 00

               Total                   ---------------------------------------                                        250,471.98
   The additional sum of $85,000 can be profitably expended during
fiscal year 1946 to dredge the sea bar and jetty channel, and the channel
across the Laguna Madre with an available seagoing hopper dredge
during April and May 1946.
                                                 Cost and financial summary
Cost of new work to June 30, 1944_ _                                                                        1 $4, 234, 486. 48
Cost of maintenance to June 30, 1944_                                       -1,                                   199, 518. 46
      Total cost of permanent work to June 30, 1944                                        -----                 5, 434, 004. 94
Minus accounts payable June 30, 1944----------------------                                                           10, 371. 44
      Net total expenditures-  - ------                                                                       1 5, 423, 633. 50
Unexpended balance June 30, 1944--                                     -125,                                            471. 98
           Total amount appropriated to June 30, 1944                                -----------                 5, 549, 105. 48

    Fiscal year ending June 30                           1940        1941              1942              1943               1944

Cost of new work                      $554, 092.93
                                .--------------
Cost of maintenance ---------.-         53, 400.06                $162, 263.19      $69,530.82        $100, 089. 54       $129, 704.61
       Total cost- --- ------------                607, 492.99     162, 263.19       69, 530.82        100, 089.54         129, 704.61
Total expended ....----------------                624, 304.45     178, 835. 94      69, 029. 66       103, 268.26         116, 934.76
Allotted ----------------------                     150, 000.00     32,156.19        76, 077.99        150,000.00           80, 000.00

  1 In addition, $1,806,619.37 was expended from contributed funds for new work.
808              REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                   1944

Balance unexpended July 1, 1943----------            ---                                                                         $162, 406. 74
Amount allotted from War Department Civil Appropriation Act
  approved April 28, 1942                                                                                                            0, 000. 00
                                                                                                                                    8-----------------------------
      Amount to be accounted for_------                                                             -_242,                              406. 74
Gross amount expended_---        -------------                                                                                     116, 934. 76
      Balance unexpended June 30, 1944_                                                                    --_                     125, 471. 98
Outstanding liabilities June 30, 1944_--                                               ---------                                    10, 371. 44
     Balance available June 30,1944_--                                                --------                                     115, 100. 54
Amount allotted in July 1944_---------                                                     -          --              -            125, 000, 00

             Amount available during fiscal year 1945                                  --------------                              240, 100. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2    -     ----------                                                                                   85, 000
  2 Exclusive of available funds.


      19. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

   The cost of work during the year amounted to $33,173.46 and the
expenditures were $32,808.36. The balance unexpended at the end
of the fiscal year, amounting to $190,222.82, including an allotment
of $91,500 made in July 1944, will be applied as needed in payment
of expenses incurred under this heading during the fiscal year 1945.
The additional sum of $125,000 can be profitably expended during the
fiscal year 1946.
                                                      Cost and financial summary
Cost of new work to June 30, 1944---
Cost of maintenance to June 30, 1944                                  ----------------------                                 $1, 610, 263. 12
      Total cost of permanent work to June 30, 1944_                                                                             1, 610, 263. 12
Minus accounts payable June 30, 1944--    -------                                                                         --             266. 10
      Net total expenditures-------------_                                                                                       1, 609, 997. 02
Unexpended balance June 30, 1944---        ------                                                      -         -           -       98, 722. 82
             Total amount appropriated to June 30, 1944                                     ------------                         1, 708, 719. 84

     Fiscal year ending June 30                          1940            1941                1942                     1943               1944

Cost of new work ...
Cost of maintenance-- .--------. $109, 917. 85                        $113, 078.99         $71, 384. 87          $75, 210. 51         1 $33, 173.46
              ----------------
Total expended....                                     150, 122. 51    106, 538. 03        105, 044. 88              45, 155.40        132, 808. 36
Allotted................--------------.------......    186, 900.00     140, 000.00 ---------------                   63, 050. 00        -6, 962. 58


Balance unexpended July 1, 1943 ---------------------------                                                                       $138, 493. 76
Deductions on account of transfer to Denison, Tex., district- ___                                                                    6, 962. 58
        Net amount to be accounted for_-------                                                               ---                   131, 531. 18
Gross amount expended_                                                                             $39, 770. 94
Less transfer to Denison district-----------------                                                   6, 962. 58
                                                                                                                                   1 32, 808. 36
              Balance unexpended June 30, 1944---------------------                                                                 98, 722. 82
  I Includes $6,962.58 credit for costs and expenditures transferred to Denison, Tex., district in this fiscal
year.
                 RIVERS AND                     HARBORS-GALVESTON,                            TEX.,      DISTRICT                    809

Outstanding liabilities June 30, 1944_                               -           -        ---------                         $266. 10
     Balance available June 30, 1944_-    --    -   -__98,                                                                    456. 72
Amount allotted in July 1944-------------------------                                                                     91, 500.00
            Amount available during fiscal year 1945----------------                                                     189, 956. 72
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2- - - - -   - - - - -   - -                                                       -
                                                                                                                            125, 000
     2 Exclusive of available funds.


20. OTHER              NAVIGATION                      PROJECTS FOR WHICH NO ESTIMATES
                                                      ARE SUBMITTED

                                                                     For last        Cost and expenditures to
                                                                   full report,            June 30, 1944                  Estimated
                     Name of project                               see Annual                                             amount re-
                                                                     Report                                                quiredr to
                                                                       for-          New work           Maintenance        complete

1. Johnsons Bayou, La.'                       ____                        1933         $2, 261.35         $54,042.26           (2)
2. Mouth of Trinity River, Tex.'                ----------------          1928         79, 540.44          10, 870. 95         (2)
3. Chocolate Bayou, Tex. 1 3 .....................                        1922          6, 512.12          33, 248. 17               $8, 500
4. Bastrop Bayou, Tex.1 ........................                          1931          9.920. 22          27, 129. 21               10.000
5. Brazos River, Tex., from Velasco to old Wash-
     ington 1   - -                -                                      1924        216, 989. 48        223, 010. 52         (2)
6. Guadaloupe River to Victoria, Tex.1 4. ....                            1922        172, 547. 28        106, 100. 36         (2)
7. East Bay Bayou (Hanna Reef), Tex.'1 5 .-..                             1922          2,476.02               847.80            7, 500
8. Oyster Creek, Tex.5...    -      --      -                             1922          6,942.24            7,556.73           (2)


     1 Channel adequate for commerce.
  2 Completed.
  3 Under date of May 25, 1939, the Chief of Engineers recommended modification of the existing project;
H. Doc. No. 337, 76th Cong., 1st sess.
  4 Under date of Feb. 24, 1939, the Chief of Engineers recommended modification of the existing project;
IH. Doe. No. 247, 76th Cong., 1st sess.
   SNo commerce reported.


             21. PLANT ALLOTMENT, GALVESTON, TEX., DISTRICT

                                                 Cost and financial summary
Undistributed costs June 30, 1944 ______-----------$2,                                                                   309, 215. 37
Plus accounts receivable June 30, 1944 - -                                                    ----                       127, 805. 20
      Gross total costs to June 30, 1944----------------                                                           2,437, 020. 57
Minus accounts payable June 30, 1944 __149,                                                                               519. 10
      Net total expenditures- --  -------           _                                                              2,287, 501. 47
Unexpended balance June 30, 1944-------------------------                                                            951, 776. 07
            Total amount appropriated to June 30, 1944--------                                                     3,239, 277. 54

       Fiscal year ending June 30                     1940               1941             1942              1943              1944

Total expended ....                ..         -$76,
                                            .--         796. 63    $246, 274. 53 -$158,       382. 99    $177, 009. 73      $185, 223.40
Allotted--.......    ..-   .----        ...--     148, 000. 00      126,000.00 -      .--..              300, 673.04         582, 359.38



Balance unexpended July 1, 1943                                                                                        $554, 640. 15
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941 ---------------------------------                                                                582, 359. 38
       Amount to be accounted for_                                 -------                      ---                1, 136, 999. 53
Gross amount expended-    - -------                                                  $4, 203, 906. 67
810        REPORT OF CHIEF OF ENGINEERS,                              U. S. ARMY,            1944

Less:
     Reimbursements collected              $4, 018, 648. 21
      Receipts from sales ..                         35. 00
                                                                   $4, 018, 683. 21
                                                                                                 $185, 223. 46
     Balance unexpended June 30, 1944-                                                            951, 776. 07
Amount covered by uncompleted contracts                                                           566, 317. 27
      Balance available June 30, 1944                                                             385, 458. 80
Accounts receivable June 30, 1944_----------                                                      127, 805. 20
         Unobligated balance available June 30, 1944-                                             513, 264. 00

Status of all investigations for navigation called for by river and harbor acts and
                                committee resolutions

                                                           Date trans-Recommen-
          Locality                Authorization act         mitted to     Document No.             Reommen-
                                                            Congress                                 dation

Aliens Creek, tributary of      River and Harbor Act,     _
  Brazos River, Austin            Aug. 26, 1937.
  County, Tex., for naviga-
  tion and flood control.
Aransas Pass-Corpus Chris-      Rivers and Harbors        Apr. 17,1944     H. 544, 78th Cong.     Favorable.
  ti Channel, Tex.                Committee resolu-                          2d sess.
                                  tion, Dec. 10, 1943.
Aransas Pass, Tex., alternate   Rivers and Harbors
  routes in this vicinity, to     Committee resolu-
  Intracoastal Waterway           tion, May 5, 1944.
  from Mississippi River at
  or near New Orleans, La.,
  to Corpus Christi, Tex.
Brazos Island Harbor, Tex.,     Rivers and Harbors Nov. 22, 1943             _________________    Unfavorable.
  improvement at and near         Committee resolu-
  Port Isabel.         .         tion, Feb. 11, 1941.
Brazos River, Tex., compre-     River and Harbor Act,
  hensive survey for naviga-     Aug. 26, 1937.
  tion, flood control and
  other water uses.
Brazos River, Tex., to pro-     Rivers and Harbors
  vide navigable channel          Committee resolu-
   from Richmond to the In-       tion, Sept. 22, 1944.
   tracoastal Waterway.
Colorado River, Tex., for       Commerce Commit-
  navigation and flood con-       tee resolution, Aug.
   trol.                          4, 1936.
Colorado River and tribu-       River and Harbor Act,
   taries, Texas, improve-        Aug. 26, 1937.
   ment for navigation and
   flood control.
Guadalupe River, Tex., im-      Rivers and Harbors
   provement for navigation,      Committee resolu-
   flood control, power and       tion, Apr. 8. 1938.
   irrigation (final report).
Houston Ship Channel, Tex       Rivers and Harbors        Feb.   5, 1944   (Restricted)      .- I Favorable.
                                  Committee resolu-
                                  tion, Apr. 24, 1941.
Jones Creek and vicinity,       Rivers and Harbors
  Texas, for navigation,          Committee resolu-
  flood control, and other        tion, Sept. 5, 1944.
  purposes (review of Free-
  port Harbor and Brazos
  River, Tex.).
Louisiana-Texas Intracoast-     Commerce Commit-
  al Waterway, for side chan-    tee resolution June
  nel and turning basin in       17, 1944.
  Red Fish Bay, Tex.
Mill Creek, a tributary of      River and Harbor Act,
Brazos River in Austin           Aug. 26, 1937.
County, Tex., for naviga-
tion and flood control.
Mill Creek, Austin County,      Rivers and Harbors
Tex., for flood control and      Committee resolu-       -- - - - - -- - - - - - -- - - - - -
navigation.                      tion, Aug. 16, 1944.
Oyster Creek, Tex., to pro-     Rivers and Harbors
vide navigation channel          Committee resolu-
from Sugar Land to Intra-        tion, Sept. 22, 1944.
coastal Waterway.
                   FLOOD CONTROI-GALVESTON,                           TEX.,      DISTRICT                    811
Stat us of all investigations for navigation called for by river and harbor acts and
                           committee resolutions-Continued

                                                            Date trans-                               Recommen-
           Locality                Authorization act         mitted to        Document No.              dation
                                                             Congress

Palacios, Tex., and Camp          Rivers and Harbors-
  John A. Hulen, channel to         Committee resolu-
the Intracoastal Water-            tion, Sept. 13, 1944.
way.
Pass Cavallo, Tex      .--------- Rivers and Harbors        Feb. 12,1944   ...-----------------...   Unfavorable.
                                    Committee resolu
                                    tion, May 24, 1939.
Pass Cavallo to Port Lavaca, Rivers and Harbors             Feb. 11,1944    (Restricted)-......      Favorable.
  Tex., Channel.                    Committee resolu-
                                    tion, Jan. 21, 1942.
Sabine-Neches Waterway,           Rivers and Harbors        Aug. 14,1943 -----------------           Unfavorable.
  Tex., removal of Harbor           Committee resolu-
  Island in Sabine River.           tion, Sept. 12, 1941.
Sabine-Neches     Waterway,      Rivers and Harbors         ..................
  Tex., from Orange, Beau-        Committee resolu-
  mont, and Port Arthur,          tion, Oct. 15, 1943.
  Tex., to the Gulf of Mexi-
  co.
San Antonio River, Tex.,         River and Harbor Act,        -
  improvement for naviga-          June 20, 1938.
  tiqn, flood co ztrol, power,
  and preventtoio of e0rosion.
Trinity River and tribu-         Rivers and Harbors         ..................
taries, Texas, to change          Committee resolu-
course of proposed channel       tion, Feb. 16, 1944.
  below Anahuac nearer to
  eastern shore of Trinity
  Bay.



                                  22. BUFFALO BAYOU, TEX.

   Location.-This project covers the improvement for flood control of
Buffalo Bayou and tributaries upstream from the Houston Ship Chan-
nel turning basin at Houston, .Tex. The streams and watershed in-
volved are located in and immediately northwest of Houston, Tex.
   Existing project.-This provides for the improvement of Buffalo
Bayou and its tributaries above the turning basin (Houston) of the
Houston Ship Channel to provide for the control of floods, the pro-
tection of the city of Houston from flood 4damages,,and the prevention
of the deposit of silt in the turning basin of theHouston Ship Channel
by means of detention reservoirs, enlargement and rectifications of
channels, the construction of control works, and any diversions which
may be found advisable. The authorized cost of Federal participation
for construction is limited to $9,000,000. The total estimated cost of
the project is $31,995,400. Of this sum the Federal cost is estimated
at $9,000,000 for construction and $9,751,700 for lands and damages.
The estimated cost to local interests is $13,243,700.
   The existing project was authorized by the River and Harbor Act
approved June 20, 1938 (H. Doc. No. 456, 75th Cong., 2d sess.) and
the Flood Control Act approved August 11, 1939.
   Local cooperation.-See page 7 for requirements. The require-
ments are being complied with. The offer of the Harris County flood-
control district to advance the sum of $2,500,000 to the Department
for prosecution of the Buffalo Bayou project was accepted by the
Secretary of War on December 18, 1940.
   Operations and results during fiscal year---New work.-The opera-
tions during the fiscal year consisted of the continuation of the acqui-
sition of lands, preparation of leases,. engineering studies and design,
preparation of plans and specifications, and curative work required
812    REPORT OF CHIEF OF ENGINEERS,         U.   S. ARMY,   1944

in connection with the acquisition of land. Construction of Barker
Dam was carried on during the year.
   The cost during the fiscal year was $1,150,306.56, all for new work of
which $839,282.53 were from funds advanced by local interests and
$311,024.03 were from regular funds. The expenditures were
$1,094,881.31, including $833,411.74 from funds advanced by local in-
terests and $261,469.57 from regular funds.
   Condition at end of fiscal year.-Topographic surveys have been
completed on Barker Reservoir, Addicks Reservoir, and Buffalo Bayou
channel rectification and are 75 percent complete on White Oak Reser-
voir, 30 percent on relocation of Burlington-Rock Island Railroad, and
80 percent on Brickhouse Gully bypass channel. Due to newly de-
veloped oil fields a realignment of the North Canal was necessary and
the additional realignment and topographic surveys are 90 percent
complete.
   Land surveys were completed on Barker Reservoir, Buffalo Bayou
channel rectification and are 85 percent complete on Addicks Reser-
voir, 50 percent complete on White Oak Reservoir and 90 percent com-
plete on the North Canal.
   Land appraisals were completed on Barker Reservoir, Buffalo
Bayou channel rectification and are in progress on Addicks and White
Oak Reservoirs.
   Condemnation proceedings of lands for the Barker Reservoir, Ad-
dicks Reservoir, Buffalo Bayou channel rectification and North Canal
have been initiated and hearings to determine values are in progress.
Soil explorations and tests for the entire project are about 87 percent
complete. The work of designing and preparing contract drawings
and specifications for construction has been completed for Addicks
Dam and Buffalo Bayou channel rectification, and is in progress for
White Oak Dam, Brickhouse Gully bypass channel, and relocation of
Burlington-Rock Island Railroad. Preliminary studies for the North
Canal are in progress. The construction of Barker Dam and appur-
tenant outlet works, channel rectification and drainage ditches is 70
percent complete. No work has been done on the second stage of the
development, which includes the construction of the South Canal and
its appurtenant interception dam and rectification work. To com-
plete the project, surveys, explorations, and detailed design must be
completed, the construction of the Barker Dam must be continued to
completion, and the construction of the remaining units of the author-
ized project must be accomplished.
   The total costs to the end of the fiscal year were $3,195,811.38, of
which $326,027.61 were from Federal funds for rivers and harbors;
$1,962,898.75 from funds advanced by local interests, and $906,885.02
from Federal flood-control funds. Total expenditures were $3,042,-
820.36, including $326,027.61 from Federal funds for rivers and har-
bors, $1,861,361.11 from funds advanced by local interests, and $855,-
431.64 from Federal flood-control funds.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $2,321,007.25, including $1,682,368.36 of Fed-
eral flood-control funds, and $638,638.89 of funds advanced by local
                  FLOOD CONTROL--GALVESTON,                                   TEX., DISTRICT                      813
interests, plus an allotment of $10,000 in July 1944 will be applied as
follows:
Accounts payable June 30, 1944 .........-..........                                                       $69, 201. 90
New work:
    Designing and preparing plans and specifications for the
      construction of Brickhouse Gully bypass (July 1944) ...                                              20, 000. 00
    Designing and preparing plans and specifications for con-
      struction of White Oak Dam (July to Oct. 1, 1944)-
    Engineering investigations, surveys, design, and partial
                                                                                               -           40, 000. 00

      preparation of plans and specifications for constructioi of
      North Canal (July 1944 to 30 June 1945)           __-                                               100, 000. 00.
    Completing the construction of Barker Dam, appurtenant out-
      let works and riprap paving by contract (July to Oct. 31,
      1944)--------------------------                                                                     650, 000. 00(
    Acquiring lands, easements, and rights-of-way, including
      reconstruction and relocation costs, for Barker Reservoir
      (July 1944 to June 30, 1945)-----_                                                                  600, 000. 00
    Acquiring lands for Buffalo Bayou channel rectification from
      Barker Dam outlet works to South Canal (July 1944 to
      June 30, 1945) -- -Vn           --                                                                  196, 000. 00
    Partially acquiring lands, easements, and rights-of-way for
      Addicks Reservoir (July 1944 to June 30, 1945)                                                      250, 000. 00
    Partially acquiring lands, easements, and rights-of-way for
      White Oak Reservoir (July 1944 to June 30, 1945) ...                                                265, 805. 35
    Partially acquiring lands, easements, and rights-of-way for
      North Canal (July 1944 to June 30, 1945)                               ------------                  50, 000. 00
    Partially acquiring lands for Brickhouse Gully bypass
      channel (July 1944 to June 30, 1945)                                                                 15, 000. 00
    Partially acquiring lands for Relpeation of Burlington-Rock
      Island R. R. (July 1944 to June 30, 1945)             -25,                                               000. 00
        Total, new work----                         --------                              _            2, 321, 007. 25
Maintenance of Barker Dam----                              -----------                                     10, 000. 00

        Total       ------------------------------------------                                         2, 331, 007. 25
  The additional sum of $625,000 can be profitably expended during
the fiscal year 1946, as follows:
New work
    Preparation of plans and specifications on other units of the
      project (July 1, 1945, to June 30, 1946)___-                                                          $170, 000
    Acquisition of lands, easements and rights-of-way (July 1, 1945,
        to June 30, 1946)                                                -       -            ---            430, 000

      Total for new work                    ----------                                                       600, 000
Maintenance           -                -             ---------                                                 25,000

        Total     -----------------------------------------------                                            625, 000

                                     Cost and financial summary
                                           UNITED STATES           FUNDS

Cost of new work to June 30, 1944__               -------------                      ------         1 $1, 232, 912. 63
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944
Undistributed costs June 30, 1944_--------
                                                                                 -- -                11, 232, 912. 63
                                                                                                        - 37, 927. 62
      Net total cost to June 30, 1944__- -------                                                      1, 194, 985. 01
Minus accounts payable June 30, 1944----------------------                                                13, 525. 76
      Net total expenditures                                                         --              1 1, 181, 459. 25
Unexpended balance June 30, 1944                                 ----------                           1, 682, 368 36
        Total amount appropriated to June 30, 1944--_-- _                                            1 2, 863,. 827. 61
1 Includes $326,027.61 rivers and harbors funds.
814                REPORT OF CHIEF OF ENGINEERS,' U.                                                                S. ARMY,              1944


      Fiscal year ending June 30                                   1940                  1941                  1942                1943                   1944

Cost of new work- .....
                   _                         --                $326,027.61         $269, 515.89            $223,802.19          $102, 542.91         $311, 024.03
C ost of m aintenance ..                      - - -       --    - - - - -.    .    - -    - - - -        .- . . . . . .. . .               ..- -      ----.
Total expended-------........----...-----.....                 324, 314.84          262, 989. 54            212, 575.42          120, 109. 88         231, 469. 57

Allotted---------------------.........................          140, 000.00         900,000. 00           1, 386, 027.61                    -        -62, 200.00


Balance unexpended July 1, 1943_ __ -          --                                                                                         $2, 006, 037. 93
Deductions on account of revocation of allotment-                                                                                              62, 200. 00

       Net amount to be accounted for                                                                                                      1, 943, 837. 93
Gross amount expended_                                                                                       $267, 818. 74L
Less receipts from sales_                                                                                       6, 349. 17
                                                                                                                                                 261, 469. 57

      Balance unexpended June 30, 1944___-_                   _                                                            -               1, 682, 368. 36
Outstanding liabilities June 30, 1944 ---     $1, 574, 767. 21
Amount covered by uncompleted contracts     .     13w, 328. 96
                                                                                                                                           1, 713, 096. 17
     Balance available June 30, 1944_     -   --                                                               --          --                   -- 30, 727. 81
Amount allotted in July 1944_ _ -------------                                                                                                      10, 000. 00

Amount available during fiscal year 1945                                                                                                        -20,    727. 81
                                                                                                                                                ----------------

Amount (estimated) required to be appropriated for comple-
tion of existing project 2     --------------                                                                                            15, 887, 872. 39

Amount that can be profitably expended in fiscal year ending
June 30. 1946: 2- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
   For new work                                                                                                                                  600, 000. 00
          For maintenance                         2----                                                                                             5, 000. 00
                                                                                                                                                   2-------------

               Total        2-------------------                                                                                                $625, 000. 00
   I Exclusive of available funds.
                                                                      ADVANCED FUNDS

Cost of new work to June 30, 1944------------------------$1, 962, 898. 75
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944- --------                                                                              1, 962, 898. 75
Undistributed costs June 30, 1944------_ ----------------                                                                                    -45, 861. 50

      Net total cost to June 30, 1944-----------------------                                                                               1, 917, 037. 25
Minus accounts payable June 30, 1944---------------------                                                                                      55, 676. 14

      Net total expenditures-----------------------------                                                                                  1, 861, 361. 11
Unexpended balance June 30, 1944--------------------------                                                                                    638, 638. 89

                Total amount appropriated to June 30, 1944-_------ ---                                                                     2, 500, 000. 00


      Fiscal year ending June 30                                   1940                  1941                  1942                1943                   1944

                          -
Cost of new work ....-...........---------------                                   $37, 331.37            $438, 799.18         $647, 485.67          $839, 282. 53
Cost of maintenance -........                              .....          ......                    .-                                                -

Total expended                      ---............-------------- -       -          33, 379. 43            393, 569. 59         601, 000. 35          833, 411. 74

Allotted.....---------------------------------                                       97, 715.00           2, 402, 285.00    -
                 FLOOD CONTROL---GALVESTON,                                 TEX.,      DISTRICT                        815
Balance unexpended July 1, 1943__ -- --------                                                          $1, 472, 050. 63
Gross amount expended_----- ---   -----        $833, 562. 26
Less reimbursements collected---------------------150. 52
                                                                                                              833 411 74

      Balance unexpended June 30, 1944___                                                                     638, 638. 89
Outstanding liabilities June 30, 1944 ------------                               $1, 243. 48
Amount covered by uncompleted contracts ---                                     616, 049. 92
                                                                                                              617, 293. 40
        Balance available June 30, 1944____._                                                                  21, 345. 49

   CONSOLIDATED         COST AND FINANCIAL SUMMARY                            FOR BUFFALO              BAYOU, TEX.

Cost of new work to June 30, 1944 -----------------------                                          1    $3, 195, 811. 38
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944
Undistributed costs June 30, 1944 ---      ------------------
                                                                                  -            -       1 3, 195, 811. 38
                                                                                                          -83,      789. 12
      Net total cost to June 30, 1944----------------------3,                                                 112, 022. 26
Minus accounts payable June 30, 1944----------------------                                                     69, 201. 90
      Net total expenditures_---------------------------    3, 042, 820. 36
Unexpended balance June 30, 1944-------------------------2,    321, 007. 25
        Total amount appropriated to June 30, 1944-----------                                          1 5, 363, 827. 61

   Fiscal year ending June 30                1940             1941             1942              1943               1944


Cost of new work -_-     _-      _      $326, 027. 61      $306, 847. 26    $662, 601. 37   $750, 028. 58      $1, 150, 306. 56
Cost of maintenance--
Total expended ...                          324, 314. 84
                     ..........----------------.            296, 368.97      606, 145.01       721, 110. 23      1,094, 881.31

Allotted.----------------------           140, 000.00       997, 715.00    3, 788, 312. 61--                      -62, 200.00


Balance unexpended July 1, 1943_       __                                              _                $3, 478, 088. 56
Deductions on account of revocation of allotment-.                                                           62, 200. 00
       Net amount to be accounted for                                                                    3, 415, 888. 56
Gross amount expended -------------------          $1, 101, 381. 00
Less:
     Reimbursements collected-----        $150. 52
     Receipts from sales ----------- 6,349. 17
                                                         6, 499. 69
                                                                                                         1, 094, 881. 31
       Balance unexpended June 30, 1944_------__-                                                        2, 321, 007. 25
Outstanding liabilities June 30, 1944---------- 1, 576, 010. 69
Amount covered by uncompleted contracts.... -      754, 378. 88
                                                                                                         2, 330, 389.      57
      Balance available June 30, 1944------                                                                 -9, 382.       32
Amount allotted in July 1944__--                                                                              10, 000.     00
      Amount available during fiscal year 1945-----------                                                         617.     68
Amount (estimated) required to be appropriated for completion
of existing project 2_- - _-                  _- _- - - -- - - - --                                    15, 887,872. 39
Amount that can be profitably expended in fiscal year ending
June 30, 1946:
    For new work 2--                                                                                          600, 000. 00
    For maintenance 2 --               ---- - _ - - - -    - - - - - -                                         25, 000. 00
      Total 2--------------------------------------------                                                     625, 000. 00
1Includes $326,027.61 rivers and     harbors funds.
2 Exclusive of available funds.
816        REPORT OF CHIEF OF ENGINEERS, U.                             S. ARMY,    1944

                23. WHITNEY RESERVOIR, BRAZOS RIVER, TEX.

    Location.-The site of the Whitney Dam is on the Brazos River,
Tex., about 442 miles above the mouth of the river, 5.5 miles southwest
of Whitney, Tex., and about 38 miles upstream from the city of Waco,
Tex. (See U. S. Geological Survey sheets: Waco, Cleburne, and
Grandbury, scale 1: 125,000, and Whitney, Blum, and Morgan, scale
1: 02,500.)
    Existing project.-The plan of improvement provides for a concrete
dam about 1,870 feet long at the top, including a 1,200-foot spillway
section, and an earth embankment about 1,490 feet long. The top of
the dam will be about 116 feet.above the river bed. The reservoir will
have a gross storage capacity of 721,000 acre-feet, including 491,000
acre-feet of flood-control storage, 129,000 acre-feet of power storage,
and 101,000 acre-feet of dead storage. A powerhouse will be located
immediately downstream from the nonoverflow section of the dam.
T
   he capacity of the initial installation of hydroelectric generating
facilities will be 30,000 kilowatts. The project will afford substantial
flood protection for the city of Waco, Tex., and the lower Brazos
River Valley and will provide for generation of hydroelectric power,
and for other beneficial water uses.
    The cost of the project, estimated in 1939, is $8,166,000 for con-
struction and $1,984,000 for land and damages, including railway
relocations, a total of $10,150,000.
    The estimated cost of annual maintenance, made in 1939, is $70,000
for maintenance and operation, including the power plant.
    The Flood Control Act, approved August 18, 1941, approved the
existing project in accordance with the recommendation of the Chief
of Engineers in House Document No. 390, Seventy-sixth Congress,
first session, which contains the latest published maps, and authorized
$5,000,000 for the initiation and partial accomplishment of the project.
    Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results diring the fiscal year.-Primary control
surveys for the reservoir were accomplished by the United States
Coast and Geodetic Survey under a cooperative agreement. Final
topographic surveys and subsurface investigation of the dam site were
partially completed.
    The costs during the fiscal year were $17,540.29 and the expenditures
$15,061.50 all for new work.
    Condition at the end of the fiscal year.-Primary control surveys
have been completed. Final topographic surveys and subsurface in-
vestigation of the dam site were approximately 50 percent complete.
Total costs were $47,188.45 and the expenditures $44,709.66 under the
existing project to June 30, 1944, all for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $130,290.34, plus an allotment of $100,000 made during
July 1944, a total of $230,290.34, will be applied as follows:
Accounts payable June 30, 1944_                        -----             ----         $2, 478. 79
Preparation of detailed plans_ ...----....                     ------           -    227, 811. 55
        Total.----------------------------------230,                                       290. 34 .
   The additional sum of $100,000 can be profitably expended during
fiscal year 1946 for completion of plans.
                     FLOOD CONTROL---GALVESTON,                             TEX., DISTRICT                             817
                                        Cost and financial summary
Cost of new work to June 30, 1944__-- --------                                                                 $47, 188. 45
Cost of maintenance to June 30, 1944 ...-                                                                                .

      Total cost of permanent work to June 30, 1944-                                                            47, 188. 45
Minus accounts payable June 30, 1944_----                                                  -__                   2,478. 79
      Net total expenditures --                                                                                 44, 709. 66&
Unexpended balance June 30, 1944 _130,                                                                              290. 34
           Total amount appropriated to June 30, 1944-------------                                             175, 000. 00


   Fiscal year ending June 30              1940              1941              1942               1943              1944

Cost of new work          ........            ..        ..           -... . $28, 802.41
                                                                    ..                            $845. 75         $17, 540. 29,
Cost of m aintenance -     -   --....
                                . -   . .      .    .    .     .-    .- .     -. -- ..--
                                                                                     -

Total expended..-------.......-------   ---------            - -       --             --         29, 648. 16        15,061. 5
Allotted       .                                        --------------
                      ...... ...------------------------------               100,000.00          75, 000. 00


Balance unexpended July 1, 1943_ -------------------                                                         $145, 351. 84
Gross amount expended_ ----------------                                                    -____                15, 061. 50-
      Balance unexpended June 30, 1944_--                                    ----           ___                130, 290. 34
Outstanding liabilities June 30, 1944_-----------------                                                          2, 478. 79
     Balance available June 30, 1944_ --- _-----___                                                            127, 811. 55
Amount allotted in July 1944_ --------------------                                                             100, 000. 00
           Amount available during fiscal year 1945----------------                                            227, 811. 55
Amount (estimated) required to be appropriated for completion
of existing project 1-  ----------------------------                                                    9, 875, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work 1_ _                  -___- -100,                                                      000. C0
1Exclusive of available funds.

        24. EAGLE LAKE TO MATAGORDA, COLORADA RIVER, TEX.

   Location.-Along the Colorado River, Tex., between the town of-
Matagorda and the town of Eagle Lake extending from 6.5 to 115
miles above the mouth of the river. (See U. S. Geological Survey
base map, Texas, scale 1: 500,000.)
   Ewisting project.-The plan of improvement provides for a system
of parallel levees along the river, with the following features: About
82.2 miles of earth levee along the left bank of the river from     6.5                                          nmile
to mile 115 above the mouth; about 53.9 miles of earth levee along the
right bank from mile 15 to mile 87; suitable drainage structures and
appurtenant works; a cut-off channel 14,100 feet long at the town of
Wharton between mile 63 and mile 70.5; channel improvement near
Glen Flora between mile 75.6 and mile 77; construction of a new high-
way and a new railroad bridge across the cut-off at Wharton; and
alterations of two highway and two railroad bridges across the flood-
way. The project will provide protection to about 421,000 acres of
agricultural land and eight towns against major floods reasonably to
be contemplated.
   The Federal cost of the project, estimated in 1939, is $6,150,000.
The local cost including bridge alterations isestimated at $672,000.
           616634-45-pt. 1, vol. 1-52
818          REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,             1944

    The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 312, 76th Cong., 1st sess., which
contains the latest published maps).
    Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation, as provided by law, local
interests are required to bear the expense of necessary bridge altera-
tions and to maintain and operate the two new bridges across the
cut-off at Wharton.
    Operations and results during fiscal year---New work.-Operations
during the fiscal year consisted of control and topographic surveys
and office studies for the preparation of detailed plans.
    The costs during the fiscal year were $62,259.40 and the expenditures
$57,126.47, all for new work.
    Conditions at end of fiscal year.-Approximately 25 percent of the
.control and topographic surveys have been completed for the prepara-
tion of detailed plans. The total costs were $62,259.40 and the ex-
penditures $57,126.47 under the existing project to June 30, 1944.
    Proposed operations.-The balance unexpended at the end of the
fiscal year, $5,873.53, plus an allotment of $150,000 made during July
1944, a total of $155,873.53, will be applied as follows:
Accounts payable June 30, 1944              -----------                                                                   $5, 132. 93
Partial preparation of the detailed plans---------------- -150,                                                               740. 60

          Total ----------------------------------------                                                                 155, 873. 53

   The additional sum of $68,000 can be profitably expended during the
fiscal year 1946 for the preparation of detailed plans.
                                           Cost and financial summary
Cost of new work to June 30, 1944----------------------                                                                  $62, 259. 40
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-                                                      -               62, 259. 40
Minus accounts payable June 30, 1944- ------------------                                                                   5, 132. 93

      Net total expenditures --------------------------                                                                   57, 126. 47
Unexpended balance June 30, 1944---------------------------                                                                5, 873. 53
          Total amount appropriated to June 30, 1944-- ----------                                                        63, 000. 00


    Fiscal year ending June 30                    1940                  1941                  1942            1943            1944

Cost of new work..----            --------------------------------------------------------                                   $62, 259. 40
Cost of maintenance-----           --              .        .-.           .     -----------
                                                                                 .                ----
                                                                                      ..---------------
Total expended ----------------            ------------------                                -------                          57,126.47

Allotted..---       ------------------------------------------------------                                     $50,000        13,000.00


Balance unexpended July 1, 1943----------------------------                                                              $50, 000.00
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942---------------------------                                                                       13, 000. 00
       Amount to be accounted for---------------------63,                                                                     000. 00
Gross amount expended ------------------------------------                                                                57, 126.47
          Balance unexpended June 30, 1944- -----------------                                                               5, 873. 53
                 FLOOD       CONTROL-GALVESTON,               TEX., DISTRICT                        819
Outstanding liabilities June 30, 1944 --------------------------                              $5, 132. 93

        Balance available June 30, 1944_ _ ____ _                       -                -        740. 60
Amount allotted in July 1944_            - ____    _150,        --                               000. 00

        Amount available during fiscal year 1945                              - -            150, 740. 60

Amount (estimated) required to be appropriated for completion of
existing project 1              ---                  -5,                                    937, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work 1 _       .- _         _________                                 68, 000. 00
I Exclusive of available funds.

                     25. COLUMBUS, COLORADO RIVER, TEX.

   Location.-On the right bank of the Colorado River, about 135 miles
above the mouth, at the city of Columbus in Colorado County, Tex.
(See U. S. Geological Survey base map, Texas, scale 1: 500,000.)
   Existing project.-The plan of improvement provides for an earth
levee about 28,500 feet long, around the city of Columbus, with suit-
able drainage structures and bank protection where necessary. The
improvements will protect the city of Columbus against major floods
reasonably to be contemplated.
   The cost of the improvement, estimated in 1939, is $250,000 for
construction and $18,000 for land and damages.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. No. 312, 76th Cong., 1st sess.,
which contains the latest published maps).
   Local cooperation.-See page 7 for requirements.
   Operation and results during fiscal year.-Operations during the
fiscal year consisted of topographic surveys, subsurface investigations,
and office studies necessary for the preparation of detailedplans.
   The costs during the fiscal year were $14,377.17 and the expenditures
were $14,312.51 all for new work.
   Condition at end of fiscal year.-Topographic surveys and subsur-
face investigations have been completed for the preparation of detailed
plans. The total costs were $14,377.17 and the expenditures $14,312.51
under the existing project to June 30, 1944.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $9,387.49, plus an allotment of $14,000 made during July
1944, a total of $23,387.49, will be applied as follows:
Accounts payable June 30, 1944- .                                  $64. 66
Completion of detailed plans and specifications-_             ----                   _        23, 322. 83
        Total        -----------------------          ---------------------                   23, 387.49
   No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                   Cost and financial summary
Cost of new work to June 30, 1944 -----------------------                                    $14, 377. 17
Cost of maintenance to June 30, 1944-
      Total cost of permanent work to June 30, 1944-                                     -    14, 377. 17
Minus accounts payable June 30, 1944                                                               64. 66

        Net total expenditures-----               _--- -           -           _____          14, 312. 51
Uniexpended balance June 30, 1944 ------------------                          _      ___       9, 387.49
        Total amount appropriated to June 30, 1944                            _23,               700. 00
820            REPORT OF CHIEF OF ENGINEERS,                                           U.     S.       ARMY,          1944


    Fiscal year ending June 30                    1940                1941                1942                 1943            1944

Cost of new work ............----------------.----------------------.......--------------...........--------------...         $14,377.17
Cost of maintenance .....................                                         ....................
       Total expended---....--.....-- ------------------------......-------------- .......--------------.                      14,1312.51
Allotted.............-------------------------------------------..............--------------..                  $15,000         8, 700.00


Balance unexpended July 1, 1943_                                                                                          $15,000.00
Amount allotted from War Department Civil Appiopriation                                                             Act
approved Apr. 28, 1942-----------------------------                                                                         8, 700. 00
       Amount to be accounted for_------                                                         ---           __         23, 700.00
Gross amount expended_-------                                                      -      -             -____             14, 312. 51
      Balance unexpended June 30, 1944_---                                                              ____                 9, 387. 49
Outstanding liabilities June 30, 1944_  11111111111                                                                             634. 66
     Balance available June 30, 1944------                                                                ____              8, 752, 83
Amount allotted in July 1944 --------------------------                                                                    14, 000.00
            Amount available during fiscal year 1945                              ------------------                      22, 752. 83
Amount (estimated) required to be appropriated for completion of
  existing project 1- - - - - - - __- -     - - - - -  - -    -
                                                                 212, 300. 00
1 Exclusive of available funds.

                             26. LA GRANGE, COLORADO RIVER, TEX.

   Location.-On the left bank of the Colorado River, Tex., between
mile 173.6 and mile 176.6 above the mouth, at the city of La Grange,
in Fayette County, Tex. (See U. S. Geological Survey base map,
Texas, scale 1: 500,000.)
   Existing project.-The plan of improvement provides for about
13,500 feet of earth levee, with suitable drainage structures, extending
from high ground on the upper side of the town, around low-lying
portions of the town along the river, to high ground on the lower side
of the town. The improvements will protect the city of La Grange
against major floods reasonably to be expected.
   The cost of the project, estimated in 1939, is $100,000 for construc-
tion and $15,000 for land and damages, a total of $115,000.
   The existing project was authorized by the Flood Control Act
approved August 18, 1941 (H. Doc. 312, 76th Cong., 1st sess., which
includes the latest published maps).
   Local cooperation.-See page 7 for requirements.
   Operations and results during fiscal year.-Operations during the
fiscal year consisted of topographic surveys, subsurface investigations,
and office studies necessary for the preparation of detailed plans.
   The cost and expenditures during the fiscal year were $8,385.06, all
for new work.
   Condition at end of fiscal year.-Topographic survey and subsurface
investigations have been completed for preparation of the detailed
plans. The total cost and expenditures under the existing project to
June 30,1944, were $8,585.06.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $7,414.94, plus an allotment of $7,000 made during July
                   FLOOD CONTROL---GALVESTON,                                                      TEX.,           DISTRICT                         821

1944, a total of $14,414.94, will be used for the completion of the de-
tailed plans and specifications.
  No additional funds can be expended during the fiscal year 1946 in
view of the existing Federal policies on wartime construction.
                                               Cost and financial summary
Cost of new work to June 30, 1944 ---------------------------                                                                            $8, 585. 06
Cost of maintenance to June 30, 1944
         Total cost of permanent work to June 30, 1944-------                                                                             8, 585. 06
Net total expenditures_------              -   -      -_____                                                                              8, 585. 06
Unexpended balance June 30, 1944----------------------------                                                                              7,414. 94
         Total amount appropriated to June 30, 1944--------                                                                              16, 000. 00

   Fiscal year ending June 30                         1940                          1941                1942                 1943             1944

Cost of new work            -.. ..                         ------------.......--.           .                  ...... ---..-..               $8, 585.06
C ost of m aintenance -       - - -
                              --           .        .--- - -              .    ..-- - .          . . . .       ..- - ..    . . . . . .     -... .
Total expended .....      . . . . . ..              . . . . .......           . . ...              ..   . ..   .               . .
                                                                                                                          .....-.              8, 585.06
Allotted ....----
                - - -
               ---               ..   ..       ..     . . . ..        .        . -      .                                     $14,000          2,000.00


Balance unexpended July 1, 1943--- -      ---------                                                                                     $14, 000. 00
Amount allotted from War Department Civil Appropriation                                                                          Act
  approved May 23, 1941        ---------------------------                                                                                2000.00
                                                                                                                                          2,
       Amount to be accounted for ------------------------                                                                               16, 000.00
Gross amount expended_------------                                                                                                        8, 585. 06
     Balance unexpended June 30, 1944                                                              -7414.
                                                                                                -------------                             7,      94
Amount allotted in July 1944_--------                                                                              -        ___           7, 000. 00
         Amount available during fiscal year 1945 ------------                                                                           14, 414. 94
Amount (estimated) required to be appropriated for completion of
existing project 1            ------------------                                                                                        77, 000. 00
  1 Exclusive of available funds.


                                27. BRADY, BRADY CREEK, TEX.

   Location.-On Brady Creek, between 28.6 and 30.4 miles above
the mouth, in the city of Brady, McCulloch County, Tex. (See U. S.
Geological Survey sheet Brady, Tex., scale 1:125,000.)
   Existing project.-The plan of improvement provides for an im-
proved floodway for Brady Creek and levees and floodwalls in the
city of Brady consisting of the following features: Approximately
9,700 feet of channel enlargement, 6,935 feet of earth levee, 345 feet
of concrete floodwall, alteration of two highway bridges and one
railroad bridge, and the necessary drainage structures. The proj-
ect provides for the protection of the city of Brady from floods with
a peak discharge 2.4 times as great as that of the maximum flood of
record which occurred in July 1938.
   The Federal cost of the improvement, estimated in 1939, is $825,000
for construction. The local cost for lands and 'damages, including
bridge replacements and alterations, is $348,000.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941 (H. Doc. No. 441, 76th Cong., 1st sess., which
contains the latest published maps).
822          REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,                   1944

   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law,
local interests are required to bear the expense of the necessary bridge
alterations.
   Operationsandreslts during fiscal year.-Operations during the
fiscal year consisted of topographic surveys, subsurface investigations,
and office studies necessary for the preparation of detailed plans.
   The costs during the fiscal year were $24,340.73 and the expenditures
$20,840.11 all for new work.
   Condition at end of fiscal year.-Topographic surveys and subsur-
face investigations have been completed for the preparation of detailed
plans. The total costs were $24,340.73 and the expenditures $20,-
840.11, under the existing project to June 30, 1944.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, $4,159.89, plus an allotment of $10,000 made during July
1944, a total of $14,159.89, will be applied as follows:
Accounts payable June 30, 1944------------------------------                                                                    $3, 500. 62
Preparation of detailed plans and specifications------------- ----                                                              10, 659. 27
           Total ---------------------------------------                                                                        14, 159. 89
   The additional sum of $15,000 can be profitably expended during
fiscal year 1946 for completion of plans.
                                               Cost and financial summary
Cost of new work to June 30, 1944---------------------------                                                                   $24, 340. 73
Cost of maintenance to June 30, 1944-              -

      Total cost of permanent work to June 30, 1944                                                     - - --                  24, 340. 73
Minus accounts payable June 30, 1944-                                                                                            3, 500. 62
      Net total expenditures -----------------------------                                                                      20, 840. 11
Unexpended balance June 30, 1944_---           ----                                                                              4, 159.89
           Total amount appropriated to June 30, 1944                                                 -25,                               000. 00

   Fiscal year ending June 30                       1940                    1941              '1942                 1943                 1944

Cost of new work---------                           ------------------------------------                                             $24, 340. 73
Cost of maintenance--------------                              ----

Total expended-------------------20,840.                                                                                                        11
Allotted     -------------------------------------....................
                                      .                                              --------------------           $25, 000      ----


Balance unexpended July 1, 1943                                                                             -         -        $25, 000. 00
Gross amount expended----------------------------                                                                               20, 840. 11

      Balance unexpended June 30, 1944                                                  --        -4,                                159. 89
Outstanding liabilities June 30, 1944                                                             - -   -       -                 3, 500. 62
           Balance available June 30, 1944--------------------------                                                                659. 27
Amount allotted in July 1944_                                         ------------                                              10, 000. 00
           Amount available during fiscal year 1945 -10,                                                                                 659. 27
Amount (estimated) required to be appropriated for completion of
  existig project _               _ __                           _                                                                  790,000
Amount that can be profitably expended in fiscal year ending June
                                -              -              -
  30, 1946, for new work 1 _         _                   _                                                                      15, 000. 00
1Exclusive of available funds.
                        FLOOD CONTROL-GALVESTON,                                  TEX., DISTRICT                        823
                                           28. PECAN BAYOU, TEX.

   Location.-These improvements are located on Pecan Bayou and
its tributary, Hords Creek, in the State of Texas. Definite locations
of the individual items are given in the following paragraph. (See
U. S. Geological Stirvey sheets, Brownwood, Coleman, and Ballinger,
scale 1:125,000, and Grosvenor and Zephyr, scale 1: 62,500.)
   Existing project.-The Flood Control Act approved August 18,
1941, authorized the plan of improvement for flood control and other
purposes on Pecan Bayou and tributaries as set forth in House Docu-
ment No. 370, Seventy-sixth Congress, first session, and authorized
$1,400,000 for initiation and partial accomplishment of the project,
including $460,000 for the Hords Creek Reservoir. The plan of im-
provement provides for the enlargement of the existing Lake Brown-
wood Reservoir and for the construction of the Hords Creek Reser-
voir. The following tabulation gives descriptive data on these
reservoirs.
                                               Dams and Reservoirs

Name __.--
      --                                                 _                  Lake Brownwood                   Hords Creek

Nearest city__             -    -      -  -                            Brownwood, Tex _....               Coleman, Tex.
Distance above mouth (miles)----------------                           57.1 on Pecan Bayou        -       27.8 on Hords Creek.
Height of dam ____                                                     135 feet ....-                     74 feet.
Type of dam_--        ---------              _-                        Earth fill ..   _-                 Earth fill.
Reservoir capacity --------------------------...                       768,000 acre-feet -.- ..       .   21,200 acre-feet.

Estimated cost:
    Construction .......................              _...........                       $1, 678, 000                 $522, 000
    Lands and damages .                                       ._822,                              000                   38,000

      Total ....               .......      ...------------------------------------------.1 2, 500, 000                560,000

  1 Estimated first cost of enlarging Lake Brownwood Dam and Reservoir.                           The estimated investment
in existing Lake Brownwood Dam and Reservoir is $1,500, 000.

   The Hords Creek Reservoir will afford substantial flood protection
to the city of Coleman, Tex., and to other extensive areas in the Hords
Creek Valley, and will provide municipal water supply for the city
of Coleman.
   The Lake Brownwood Reservoir will afford substantial flood pro-
tection in the valleys of Pecan Bayou and the lower Colorado River,
including the city of Brownwood, Tex., and will also provide addi-
tional conservation storage.
   Local cooperation.-Thisproject was adopted subject to the follow-
ing conditions: (a) That local interests contribute the sum of $100,000
toward the first cost of the Hords Creek Reservoir; and (b) that the
local agency owning and controlling Lake Brownwood permit the
United States to utilize, without cost, the existing dam, reservoir, and
appurtenant works, and any of its lands needed for the construction
and operation of the enlarged dam and spillway, and maintain and
operate the enlarged reservoir upon completion in accordance with
regulations prescribed by the Secretary of War.
   Operations and results during the fiscal year.-Operations during
the fiscal year consisted of control and topographic surveys, subsur-
face investigations, and office studies necessary for the preparation
of detailed plans. The primary control surveys were accomplished
by the United States Coast and Geodetic Survey under a cooperative
agreement.
824            REPORT OF CHIEF OF ENGINEERS,                                                   U. S. ARMY,              1944

   The cost during the fiscal year was $48,627.08, of which $27,014.87
were on Hords Creek Reservoir and $21,612.21 on Lake Brownwood
all for new work.
   The expenditures were $34,003.21, of which $26,005.93 were on
Hords Creek Reservoir and $7,997.28 on Lake Brownwood.
   Conditions at end of fiscal year.-Control and topographic surveys
for the Hords Creek Reservoir have been completed and subsurface
investigations were approximately 50 percent complete. Control
surveys have been completed on Lake Brownwood and the topographic
surveys and subsurface investigations were approximately 10 percent
complete. The total costs were $48,627.08 and the expenditures $31,-
003.21 under the existing project to June 30, 1944.
   Proposed operations.-The balance unexpended at the end of the
fiscal year $19,396.79 and an allotment of $95,000 made during July
1944, amounting to $114,396.79, will be applied as follows:
Accounts payable June 30, 1944                           -----------                                                            $14, 623. 87
Hords Creek Reservoir: Preparation of detailed plans and specifica-
  tions   ----------------------------------------------                                                                         30, 185. 13
Lake Brownwood Reservoir: Partial preparation of detailed plans
  and specifications ---------------------------------------                                                                     69, 587. 79

            Total_             -------------------------------------                                                            114, 396. 79
  The additional sum of $120,000 can be profitably expended during
the fiscal year 1946 for the completion of plans and specifications for
Lake Brownwood and Hords Creek Reservoirs.
                                                   Cost and financial summary
Cost of new work to June 30, 1944                                                                                               $48, 627.08
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-
Minus accounts payable June 30, 1944------------------ ------
                                                                                                               -                 48, 627. 08
                                                                                                                                 14, 623. 87

      Net total expenditures  -------------------------                                                                          34, 003. 21
Unexpended balance June 30, 1944---------------------                                                                            19, 396. 79
            Total amount appropriated to June 30, 1944--------                                                                   53, 400. 00

    Fiscal year ending June 30                          1940                   1941               1942           1913                1944

Cost of new work ....------------------         -----------------------------------------                                           $48, 627.08
Cost of maintenance..----------      ---------------------------------------------------

Total expended ............----------------          ..------..      ..    .     ....--------------      ---------                   34, 003.21
Allotted              _.
               ---------------------------------------------------------                                             $40, 000        13,400.00


Balance unexpended July 1, 1943 ----------------------------                                                                    $40, 000. 00
Amount allotted from War Department Civil Appropriation Act
approved April 28, 1942-----------------------------------                                                                      13, 400. 00
      Amount to be accounted for- -------------------------                                                                      53, 400. 00
Gross amount expended_------------------------------------                                                                       34, 003. 21
      Balance unexpended June 30, 1944----- -----------------                                                                    19, 396. 79
Outstanding liabilities June 30, 1944---- --------------------                                                                   14, 741. 17
            Balance available June 30, 1944_                                                                                      4, 655. 62
                    FLOOD CONTROIr--GALVESTON,                         TEX., DISTRICT                       825
Amount allotted in July 1944_ -----                                   ------------                 $95,000.00

          Amount available during fiscal year 1945                                                  99, 655. 62

Amount (estimated)     required       to be appropriated                for completion of
                               - - - -- - - -      - -- - - - -- - - - -- - - - -- - - -- - -
existing project 1- - - - - -                                                                      2, 811, 600. 00
Amount that can be profitably           expended- - - - - in
                                                           - - fiscal
                                                                - - - - -year
                                                                          - - - endingJune
                                                                                - - - - - - - - - -
30, 1946, for new work I
                                - - - - - - - -                                                        120, 000.00
  1 Exclusive of available funds.

                              29. NORTH CONCHO RIVER, TEX.

   Location.-These improvements are located on the North Conicho
River, a tributary of the Concho River, in the vicinity of the city of
San Angelo, Tex. Definite locations of the individual items are given
in the following paragraphs. (See U. S. Geological Survey base map,
Texas, scale 1: 500,000, and sheet Wall, scale 1: 62,500.)
   Existing project.-The Flood Control Act approved August 18,
1941, authorized the plan of improvement for flood control on the
North Concho River, Tex., as set forth in House Document No. 315,
Seventy-sixth Congress, first session, and authorized $2,000,000 for the
initiation and partial accomplishment of the project. The plan of
improvement provides for the construction of the San Angelo Reser-
voir on the North Concho River upstream from San Angelo and for
the construction of a floodway, levees, and floodwalls in the city of
San Angelo.
   The San Angelo Reservoir will be located about 6.7 miles above the
mouth of the North Concho River, near the town of San Angelo, Tex.
The dam will be of the earth-filled type with a gate-controlled concrete
spillway located in the channel. An emergency overflow spillway will
be located in a draw to the south of the dam. The maximum height
of the dam will be 90 feet above the valley floor. The upstream slope,
when the height of the dam exceeds 30 feet, is to be protected by rip-
rap 18 inches thick laid on a 6-inch gravel blanket, and a rock drain is
provided at the toe of the dam. The reservoir will have a gross storage
capacity of 364,900 acre-feet. The estimated cost of construction is
$5,489,000 and of lands and damages is $542,000.
   The local protection works in the city of San Angelo provide for
constructing levees and floodwalls along vulnerable sections of the
city, filling in low-lying areas adjacent to the river, removing existing
channel obstructions, altering existing bridges, and improving the
carrying capacity of the channel over a reach from mile 0.9 to 3.5.
Enlargement of the channed will be accomplished by excavating
1,057,000 cubic yards of material which, in turn, will be used to fill in
the low-lying areas along the south bank of the river in order to reclaim
these areas. Five highway bridges which restrict the waterway open-
ing will be reconstructed. Three low-water dams, two of which are
located adjacent to bridges and present serious obstruction to the free
discharge of the river, will be removed. The levees and floodwalls will
consist of about 9,270 feet of earthen embankment and 2,000 feet of
reinforced concrete wall. Two pumping stations and appurtenant
drainage structures, to handle interior drainage, will be constructed.
The estimated cost of construction is $769,000, and of lands and dam-
ages is $600,000.
   The reservoir will provide substantial flood protection in the valleys
of the lower Concho and Colorado Rivers, and, supplemented by the
826           REPORT OF CHIEF OF ENGINEERS,                                     U.         S. ARMY,                       1944

local protection works at San Angelo, it will afford protection to that
city from floods with a discharge one and one-half times as great as
that of the maximum flood of record, which occurred in September
1936.
   Local cooperation.-See page 7 for requirements.
   Section 2 of the Flood Control Act approved June 28, 1938, applies
to the San Angelo Reservoir.
   In addition to the usual requirements for local cooperation as pro-
vided by law, local interests are required to bear the expense of the
necessary alterations of bridges for the local protection works at San
Angelo.
   Operations and results during the fiscal year.-Operations during
the fiscal year consisted of control and topographic surveys, subsurface
investigations, and office studies necessary for the preparation of de-
tailed plans. The primary control surveys were accomplished by the
United States Coast and Geodetic Survey under a cooperative agree-
ment.
   The costs during the fiscal year were $74,071.45 and the expenditures
$77,790.97, all for new work.
   Condition at end of fiscal year.-Control and topographic surveys
have been completed and subsurface investigations were approxi-
mately 30 percent complete for the preparation of detailed plans.
The total costs were $74,071.45 and the expenditures $77,790.97 under
the existing project to June 30, 1944.
   Proposed operations.-The balance unexpended at the end of the
fiscal year and an allotment of $55,000 made during July 1944, amount-
ing to $67,309.03, will be applied as follows:
Accounts payable June 30, 1944------------------------------                                                               --     $506. 57
Partial preparation of the detailed plans-----------------                                                                      66, 802. 46
           Total- -------------------------------------                                                                         67, 309. 03

   The additional sum of $167,000 can be profitably expended in the
fiscal year 1946 for completion of the detailed plans and specifications
and land surveys.
                                      Cost and financial summary
Cost of new work to June 30, 1944------------------------------                                                                $74, 071. 45
Cost of maintenance to June 30, 1944-
      Total cost of permanent work to June 30, 1944-
Undistributed costs June 30, 1944---
                                                                                                      _        -                74, 071.   45
                                                                                                                                    226. 09
                                                                                                                                 4,-------------------4
      Net total cost to June 30, 1944------------------                                                                         78, 297. 54
Minus accounts payable June 30, 1944--------------------------                                                                      506. 57
      Net total expenditures -------------------------                                                                          77, 790.97
Unexpended balance June 30, 1944       ---------------------                                                                    12, 309. 03
            Total amount appropriated to June 30, 1944--------                                                                  90, 100. 00

    Fiscal year ending June 30            1940                      1941                 1942                      1943             1944

                .............
Cost of new work--------------            ----.....------------
                                                        - -                                                                        $74,071.45
Cost of maintenance-..............                 ....           . . . . ...   ..        . . .....                . . . .
Total expended ................                                                                                                     77, 790. 97
Allotted----------------......................--........                             .          ..        -.        $65, 000        25, 100. 00
                      FLOOD CONTROIr-GALVESTON,                                  TEX., DISTRICT                                                     827
Balance unexpended July 1, 1943--- -      --------         -$65,    000. 00
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942__---      ------            ____       25, 100. 00
      Amount to be accounted for_------                                                          ---            __                      90, 100. 00
Gross amount expended---- ----------                                                                             _                      77, 790. 97
      Balance unexpended June 30, 1944-....                                          -           -              _ ___12,                      309. 03
Outstanding liabilities June 30, 1944_---------                                                                     ---                       989. 57
     Balance available June 30, 1944--       ----                                                        _11,                               319. 46
Amount allotted in July 1944----       -----------                                                                                      55, 000. 00

             Amount available during fiscal year 1945                       ----------                                                  66, 319. 46

Amount (estimated) required to be appropriated for completion of
existing project 1         -      -----------                                                                                          6, 654, 900
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 1                                . -167,                                                                                     000
  1Exclusive of available funds.

30. EMERGENCY FLOOD CONTROL WORK UNDER AUTHORITY OF THE
         FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,00
for any one fiscal year to be expended in rescue work or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood.
   The sum of $6,620 was allotted during the fiscal year to the Gal-
veston district for emergency repairs to levees of the Kaufman County
Levee Improvement District No. 10 on the East Fork of the Trinity
River. Operation consisted of repairing breached sections of the
levee. The costs during the fiscal year were $2,699.65 and the ex-
penditures $1,648.80. The unexpended balance at the end of the fiscal
year, amounting to $4,971.20, will be applied to the completion of
emergency repairs to the levees of Kaufman County Levee Improve-
ment District No. 10.
                                          Cost and financial summary
Cost of new work to June 30, 1944                        --            -             -               -          -               -               -

Cost of maintenance to June 30, 1944_------                                                                      -                      $2, 699. 65
      Total cost of permanent work to June 30, 1944                                                                                      2, 699. 65
Undistribetted costs June 30, 1944-- ------------                                                                                           942..75
      Net total cost to June 30, 1944_-----          -__                                                                                 1, 756. 90
Minus accounts payable June 30, 1944-------------------------                                                                               108. 10
      Net total expenditures--------_                                                                                                    1, 648. 80
Unexpended balance June 30, 1944_--                                   ----------                                                         4, 971.20
             Total amount appropriated to June 30, 1944--------------                                                                    6, 620. 00

    Fiscal year ending June 30                  1940           1941                      1942                   1943                          1944


C ost of new w ork- - - - - - - - -- - - - - - - - - - - - - - -- - - - - - - -- - - - -. . .                                                 .. . . .
Cost of m aintenance - - - - - -      . . . . . . . . ..... ... ,    . . .
                                                                    ...      .. . . . . ...                                                    $2,699.65
Total expended .      .        .     .      .           . .       .    .   .1,   -       --.--                              -       -     -         648.80
A llotted.        -             -......
                          ...................     ....... .........         ......                               .        ......               6,620.00
828        REPORT OF CHIEF OF ENGINEERS,                                            U. S. ARMY,               1944

Amount allotted from War Department Civil Appropriation                                                   Act
  approved June 24, 1940   --------------------                                                                      $6, 620.00
Gross amount expended                                                                                                  , 648. 80
                                                                                                                      1----------------------------

     Balance unexpended June 30, 1944-------------------------4, 971. 20
Amount covered by uncompleted contracts----1,                    967. 08

         Unobligated balance available June 30, 1944                                               -           3      3, 004. 12

31. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY                                                                              OF
     PUBLIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods
which occurred in the spring of 1943 and again in the spring of
1944, Congress, in the act approved July 12, 1943, Public No. 138,
Seventy-eighth Congress, and in the act approved May 29, 1944, Pub-
lic No. 318, Seventy-eighth Congress, authorized the amounts of
$10,000,000 and $12,00,000, respectively, to be appropriated as emer-
gency funds to be expended under the direction of the Secretary of
War and the supervision of the Chief of Engineers for the repair.
restoration, and strengthening of levees and other flood-control works
which had been threatened or destroyed by the recent floods. (See
p. 9 for details.)
   The sum of $19,000 was allotted during the fiscal year to the Gal-
veston district for emergency repairs to levees of the Rockwall County
Levee Improvement District No. 1 on the East Fbrk of the Trinity
River, pursuant to the act of July 12, 1943. Operations consisted
of repairing breached sections of the levee. The costs during the
fiscal year were $5,948.66 and the expenditures $1,385.21. The un-
expended balance at the end of the fiscal year amounting to $17,614.79
will be applied to the completion of emergency repairs to the levees
of Rockwall County Levee Improvement District No. 1.
   In addition, funds in the amount of $100,000 were allotted to the
Galveston district in July 1944, for emergency repairs, pursuant to
the act approved May 29, 1944. Emergency repair work will be
accomplished during fiscal year 1945 with these funds.
                          Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944 --------------------------                                                      $5, 948. 66
       Total cost of permanent work to June 30, 1944---------- ---                                                    5, 948. 66
Undistributed costs June 30, 1944 -------------------------     --                                                    4, 563. 45
       SNet total cost to June 30, 1944---------------------                                                          1, 385. 21
Net total expenditures-------------                                                                                   1, 385. 21
Unexpended balance June 30, 1944                          - --------                              __                 17, 614. 79
         Total amount appropriated to June 30, 1944------------                                                      19, 000. 00

   Fiscal year ending June 30               1940                  1941                 1942            1943              1944
Cost of new work_,....                  -        _---
                                             -....--                                         --    --- --      ---        '__. .
Cost of maintenance..........       ..-------------- -------------------------------------                               $5, 948.66
Total expended     .      .                                                                                                 38. 21
                                                                                                                          1-----------------.-.--.-1,
Allotted-........................           ..... ....i.............. .................                        .          19000.00
                  FLOOD            CONTROL-GALVESTON,                           TEX., DISTRICT                              829
Amount allotted from Second Deficiency Appropriation Act 1943,
   July 12, 1943 -                                        --------------                                           $19, 000. 00
      Gross amount expended_-----         --                                                                         1.385. 21
      Balance unexpended June 30, 1944                                           --------------                     17, 614. 79
Amount covered by uncompleted contracts---- -------------                                                           17, 614. 79
Balance available June 30, 1944-
Amount allotted in July 1944                     ---                       --                       __             100, 000. 00
Amount available during fiscal year 1945 ____                                                                      100, 000. 00

32. PRELIMINARY                    EXAMINATIONS, SURVEYS, AND CONTINGENCIES
                                      FOR FLOOD CONTROL

  The cost of the work during the year amounted to $76,903.49 and
the expenditures were $75,408.49. The balance unexpended at the
end of the fiscal year, including accounts receivable, and an allot-
ment of $95,000 made in July 1944, amounting to $195,521.85, will
be applied as needed during the fiscal year 1945 to payment of ex-
penses incurred under this heading. The additional sum of $125,000
can be profitably expended during the fiscal year 1946.
                                      Cost and financial summary
Cost of new work to June 30, 1944-                                 -            --
Cost of maintenance to June 30, 1944 _-                                                                     $1, 158, 296. 09
       Total cost of permanent work to June 30, 1944_                                                        1, 158, 296. 09
Undistributed costs June 30, 1944        -                                                                  -.-      6, 165. 13
       Net total cost to June 30, 1944 -                                                              --1,152, 130. 96
Plus accounts receivable June 30, 1944-                                                                                 949. 61
       Gross total costs to June 30, 1944                                                                    1, 153, 080. 57
Minus accounts payable June 30, 1944-                                                                                348. 10
       Net total expenditures                                                                                1, 152, 732 47
Unexpended balance Jie      30, 1944                                                                             9, 572. 24
       Total amount appropriated to June 30, 1944_                                                    -      1,252, 304. 71

    Fiscal year ending June 30           1940             1941                       1942            1943               1944

Cost of new work.........-
Cost of maintenance -------           $358, 620. 12    $149, 229. 36            $131, 842. 95      $72, 182. 58        $76, 903. 49
Total expended      _         --       355, 095. 88     160, 540. 65             130, 735. 47       73, 475. 85         75, 408. 49

Allotted                               298. 10-0.00     140, 000. 0-0                              173, 000.00        -14, 295. 29


Balance unexpended July 1, 1943     -  --                                                                         $189, 276, 02
Deductions on account of:
    Revocation of Allotmenit-                                                        $3, 369. 78
    Transfer of expenditures to Denison District-                                    10, 925. 51
                                                                      14, 295. 29
       Net amount to be accounted for                                     980. 73
                                                                    1----------------74,
Gross amount expended_                                         -     75, 408. 49
       Balance unexpended June 30, 1944 ---                          99, 572. 24
Outstanding liabilities June 30, 1944                                  6, 639. 23
       Balnce available June 30, 1944--                -_92,              933. 01
Accounts receivable June 30, 1944_                                     -949.     61
       Unobligated balance available June 30, 1944                        882. 62           -93,
Amount allotted in July 1944-------------------------------          95,000.00
       Amount available during fiscal year 1945- ---     -   -   -18_     882. 62
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1        -----------               125, 000. 00
  1 Exclusive of available funds.
830        REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY,                                                                  1944

33.    OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                       ARE SUBMITTED

                                                      For last     Cost and expenditures to                                                                   Estimated
                                                     full report        June 30, 1944                                                                        amount re
                 Name of project                     see Annual                                                                                               quired to
                                                       Report                                                                                                 quired to
                                                         for-      New work                                   Maintenance                                      Complete

1. Snagging and clearing l(I)
                          under authority of sec.       1943        $25, 702.86                           -to
     2 of the Flood Control Act approved Aug. 28,
     1937, eahitneded.
  1 Completed.

Status of all investigations for flood control called for by flood-control acts and com-
                                    mittee resolutions

                                                         Date trans-                                                                                        Recommenda-
          Locality               Authorization act        mitted to                 Document No.                                                                tion
                                                          Congress

Allens Creek, tributary of      River and Harbor Act,
  Brazos River, Austin           Aug. 26, 1937.
  County Tex., for naviga-
  tion and flood control.
Brazos River, Tex., compre-     River and Harbor Act,
  hensive survey for naviga-     Aug. 26, 1937.
  tion, flood control, and
  other water uses.
Brazos River and, tributar-     Flood Control Act,
  ies, Texas.                     Aug. 28, 1937.
Colorado (lower) River,         Flood Control Act,      --------------
  Tex.                            June 22 1936.
Colorado River and tribu-       River and Harbor Act,                                                                             =
  taries, Texas, improve-         Aug. 26, 1937.
  menit or navigation and
  flood erit I.
Colorado River, Tex., im-       Commerce Committee
  provement for navigation        resolution, Aug. 4,
  and flood control.              1936.
Colorado River, Tex., above     Flood Control Act,
  county line between Coke        June 22, 1936.
  and Runnels Counties.
Guadalupe River, Tex., im-      Rivers and Harbors
  provement for navigation,       Committee resolu-
  flood control, power and        tion, Apr. 8,1938.
  irrigation (final report).
Jones Creek And vicinity,       Rivers and Harbors
  Texas, for navigation,          Committee resolu-
  flood control, and other        tion, Sept. 5,1944.
  purposes (review of Free-
  port Harbor and Brazos
  River, Tex).
Leon River, Tex .........       Flood Control Act,
                                  June 22, 1936.
Mill Creek, a tributary of      River and Harbor Act,
Brazos River in Austin           Aug. 26, 1937.
County Tex., for naviga-
tion and flood control.
Mill Creek, Austin County,      Rivers and Harbors
Tex., for flood control and'     Committee resolu-
navigation.                      tion, Aug. 16,1944.
Neches River and tributar-      Flood Control Act,                       --------------------

ig:Texas.                        June 22, 1936.
Edi s River 'and tributar'     Flood Gontrol Act,                       --------------------

ies, Texas and Louisiana.        May 15, 1936.
Nueces River and tributar-      Flood Control Act,                       - - - - -            - - - - - - - - - - - - - - -


ies, Texas.                      June 4, 1936.
    Do......................    Flood Control Act,                       -- -   -   -   -     -   -   -   -   -   -   -   -   -   -   -   -   -   ---


                                  June 22, 1936.
Sabine River and tributar-      Flood Control Act, Apr. 5, 1944          - - - - - -              - - - - - - - - - - - - - -                               Unfavorable.
  ies, Texas and Louisiana.       May 15, 1936.
Sabine River, Tex ........      Flood Control Act,     ...do........     - - - -            - - - - - - - - - - - - - - - -
                                                                                                                                                               Do.
                                  June 22 1936.
San Antonio River, Tex.,        River and Harbor Act, --..-----.....-    - - - - -            - - - - - - - - - - - - ---                               -


  improvement for naviga-         June 20, 1938.
  tion, flood control, power
and prevention of erosion.
                   RIVERS AND HARBORS-DENISON,                             TEX., DISTRICT                  831
Status of all investigations for flood control called for by flood-control acts and com-
                              mittee resolutions-Continued
                                                             Date trans-                          Recommenda-
              Locality             Authorization act         mitted to       Document No.             tion
                                                              Congress

San Jacinto River and tribu-     Flood   Control Act, _........              ... ......
     taries   in   Montgomery,     Aug. 28, 1937.
     Walker, San Jacinto,
     Grimes, 'Wailer, Liberty,
     and amrs CotiesTex.
Santa Isabel Creek, north-       Flood Control       Act,   Apr. 21, 1944-_-..........      .     U-nfavorable.
  west of Laredo, Webb             June 28, 1938.
  County, Tex.
Trinity River and tributar-      Flood Control Comn-        Mar. 27,1944    H. 533, 78th Cong.,   Favorable.
  ies, Texas (construction of     mittee    resolution,                      2d sess.
  Lavon Dam and Reser-            July 2, 1943.
     voir for flood control).


IMPROVEMENT                       OF RIVERS AND HARBORS                                           IN    THE
                                 DENISON, TEX., DISTRICT

  This district includes the Red River and tributaries above Fulton,
Ark., and that part of the Trinity River Basin above and including
the Bedias Creek Basin. Within these drainage areas lie a portion of
western Arkansas, the northern portion of the Stae of Texas, except-
ing the major portion of the Panhandle, and the southern portion
of the State of Oklahoma.
  District engineer: Col. William W. Wanamaker, Corps of Engi-
neers, to January 17, 1944, and Maj. Emlen J. Wanless, Corps of
Engineers, since that date.
  Division engineer: Col. Robert R. Neyland, Corps of Engineers, to
June 9, 1944- Col. Francis J. Wilson, Corps of Engineers, to June 15,
1944, and Brig. Gen. Edwin H. Marks, United States Army, since that
date.
                                               IMPROVEMENTS

                         Navigation                                Flood Control-Continued
                                                    Page                                                   Page
1. Examinations, surveys, and                               5. Emergency flood-control
     contingencies (general) ----                    832         work under authority of
2. Other navigation projects for                                 Public Laws Nos. 138 and
     which no estimates are sub-
     mitted                                                      318, Seventy-eighth Con-
                                                     832
                                                                 gress-_                                    838
             Flood control                                  6. Preliminary examinations,
3. Denison Reservoir, Red River,                                 surveys, and contingencies
     Tex. pnd Okla                                   833         for flood control-    --                   839
4. Emergency' flood-control
     work under authority of the                            7. Other flood-control projects
     Flood Control Act approved                                  for which no estimates are
     August 18, 1941 -                               838         submitted-- -                              840
832             REPORT OF CHIEF OF ENGINEERS,                                     U. S. ARMY,                     1944

        1. EXAMINATIONS, SURVEYS, AND CONTINGENCES (GENERAL)

  The cost of work during the year was -$43,770.32; the expenditures
were $8,464.58. The balance unexpended at the end of the fiscal year,
$55,971.14, will be applied as needed during the fiscal year 1945 to
payment of expense incurred under this heading. No additional
funds will be required for the fiscal year ending June 30, 1946.
                                               Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944                               ------------------------ $518,                              336. 69
      Total cost of permanent work to June 30, 1944  -
Minus accounts payable June 30, 1944 ---------------------------
                                                                518, 336. 69
                                                                     68& 27
                                                                                                              -
      Net total expenditures -----------------   --- ___- -  517, 648. 42
Unexpended balance June 30, 1944----------------------------55, 971. 14

            Total amount appropriated to June 30, 1944--- - -                                              - --          573, 619. 56


    Fiscal year ending June 30                    1940             1941             1942                   1943                1944

Cost of new work_
Cost of maintenance-            -...
                                   '            $47, 520. 78    $24, 850.47      $13, 165. 41               -$0.02         -$43,   770.32

Total expended........------------.....--        60, 449.48      22, 254.44       13, 117. 21'               495. 47           8,464.58

Allotted...................----------------------. 11, 000.00    13, 000.00 -      -    -        -     -     -       -     -   6, 962. 58



Balance unexpended July 1, 1943----------------------------$57, 473. 14
Amount allotted by transfer from Galveston district           6,962. 58             ---------
      Amount to be accounted for---------------------------                                                              64, 435. 72
Gross amount expended_-------------                      - -                                                              8,464. 58
      Balance unexpended June 30, 1944---- ------         -----                                                          55, 971. 14
Outstanding liabilities June 30, 1944--------------------    -                                                            1,000. 00
           Balance available June 30, 1944------ - - - - -                              -      - - -- - -                54, 971. 14

2. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                       SUBMITTED

                                                                 For last       Cost and expenditures to                  Estimated
                                                                full report            June 30, 1944
                     Name of project                            see Annual                                                amountre-
                                                                 Report                                                    quired to
                                                                   for-         New work         Maintenance               complete

Red River from Fulton, Ark., to mouth of                              1924      $378, 573.82         $182,157.05         Maintenance
Washita River, Okla.,                                                                                                    only.

  1Curtailment of project is recommended in H. Doc. No. 947, 64th Cong., 1st sess.
                           FLOOD CONTROL---DENISON,                                       TEX.,          DISTRICT                  833
Status of all investigations for navigation called for by river and harbor acts and
                                 committee resolutions

                                                                         Date trans-Recommen-
              Locality                     Authorization act              mitted to     Document No.                          datiRecomn-
                                                                        SCongress

Red River, La., Ark., Okla.,             Rivers and Harbors---
and Tex., for navigation,                 Committee Resolu-
flood control, water power,              tion, Feb. 25, 1938.
and    irrigation    (report
being prepared by the
Lower Mississippi Valley
  Division).
R ed R iv er , L a., A rk ., O k la .,   C o m m e r c e C om m i t -   ... . . . . .. . . . . .. . . . . .
  and Tex., and connecting                 tee resolution, Feb.
  waterways, singly or to-                 8, 1939; Flood Con-
  gether, for navigation,                  trol Committee Res-
flood control and irriga-                 olution Jan. 26, 1939;
  tion.                                    Rivers and Harbors
                                           Committee resolu-
                                           tion, Jan. 24, 1939.
Red River, La., Ark., Okla,              Rivers and Harbors              -............................
and Tex., extension of                    Committee resolu-
navigable channel from                    tion, Apr. 27, 1944.
  Fulton, Ark., upstream to
Denison, Tex.1
Trinity River and tribu-                 Rivers and Harbors- ....-           -              ....         ....   ....   ....      ...
taries, Texas., for naviga-               Committee resolu-
tion and flood control.                   tion, Mar. 31, 1944.
Wichita River, Tex., navi-               Rivers and Harbors_
gation,    flood    control,              Committee resolu-
power, irrigation, or water              tion, May 9, 1944.
  conservation.

  I Combine with report on Red Rive, La., Ark., Okla., and Tex., for navigation, flood control, power,
and irrigation, requested by resolution of the Committee on Rivers and Harbors, House of Representa-
tives, adopted Feb. 25, 1938, which is being prepared by the Lower Mississippi Valley Division.

          -    3. DENISON RESERVOIR, RED RIVER, TEX. AND OKLA.

   Location.-Denison Reservoir is located on Red River, 751 miles
above the mouth of the river and 5 miles northwest of Denison, Tex.
 (See U. S. Geological Survey Maps for Denison, Tex., and Tisho-
mingo, Okla., quadrangles; scale 1: 125,000.)
   Existing project.-The plan of improvement provides for the con-
struction of a roll-filled dam 15,200 feet long, rising 165 feet above the
stream bed with a reservoir providing 2,745,000 acre-feet of flood-
control storage, 2,060,000 acre-feet of power storage, and 1,020,000
acre-feet for accumulation of silt. The outlet works consisting of a
gate-control house and eight conduits, each 20 feet in diameter, and
the powerhouse, are located on the right abutment. A chute type
spillway located in a saddle on the right bank will discharge through
a creek to a point 1 mile below the dam. The plan of improvement
also provides for the diversion of the Washita River and the con-
struction of levees to protect the Cumberland oil field from inundation.
   The project provides for flood protection to lands in Te:as, Okla-
homa, Arkansas, and Louisiana, for the generation of power, improve-
ment of navigation, regulation of the flow of the Red River, and for
other beneficial uses. The existing project was authorized by the
Flood Control Act approved June 28, 1938, and amended by section 4,
Public No. 868, Seventy-sixth Congress, third session, approved Octo-
ber 17, 1940. (See H. Doc. No. 541, 75th Cong., 3d sess., which con-
tains the latest published maps.) The estimated cost of the project is


          616634-45--pt. 1, vol. 1-- 53
834    REPORTOF CHIEF OF ENGINEERS,           U. S.   ARMY,   1944

$31,750,000 for construction and $23,500,000 for lands, damages, and
relocations.
   Local cooperation.--Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results dwring flfcal year.-Work under continuing
contract for construction of main dam embankment and excavation for
the spillway was completed. A total of 845,788 cubic yards of common
and rock excavation was accomplished and a total of 1,545,044 yards of
random pervious and impervious fill was placed. Construction of the
spillway was completed and 26,950 cubie yards of concrete and 52,585
yards of riprap were placed. Construction of the powerhouse was
completed and installation of powerhouse equipment was substan-
tially completed. Clearing of 13,181 acres of land in the reservoir area
by hired labor, contract, and prisoner-of-war labor was accomplished.
Relocations of the St. Louis-San Francisco Railway, Missouri-Kansas-
Texas Railroad, U. S. Highway No. 70 except bridge superstructure
and west approach from Kingston, Okla., State Highway No. 99 and
necessary utility lines were completed. Powerhouse generator, tur-
bine, governor, crane, penstocks, and miscellaneous powerhouse equip-
ment were fabricated and installed. Construction of the Cumberland
levees for diverting the Washita River was completed involving a total
of 7,224,025 cubic yards of common and unclassified excavation, 1,063,-
000 cubic yards of random pervious and impervious fill, and a total of
141,960 yards of riprap.
    Filling of the Denison Reservoir began on October 31, 1943. The
storage and elevation on midnight, October 31, 1943, were 7,800 acre-
feet and 526.4 feet mean sea level, respectively. On and subsequent to
January 12, 1944, and through the remainder of the fiscal year the
releases through the flood-control conduits varied from about 12 to 230
cubic feet per second except on June 30, 1944, when the flood-control
gates were tested during a 30-minute interval of opening and closing.
The instantaneous release on the above date was 11,000 cubic feet per
second. On and subsequent to March 30, 1944, the power releases
varied from 30 cubic feet per second (house unit) to 5,700 cubic feet
per second (main unit). The releases from the main unit were used
primarily for testing purposes and these releases were exceptionally
small except during the period June 20 to 23, 1944, when a maximum
of 5,700 cubic feet per second was released. The reservoir storage and
elevation on midnight, June 30, 1944, were 1,441,000 acre-feet and 593.9
feet, mean sea level, respectively. Throughout the period that the res-
ervoir has been in operation the flood stage, 25 feet, at the control point
 (Index, Arkansas, 261 river miles below the dam) was approached only
once. The maximum stage at the control point was 21.85 feet on May
4, 1944. The average daily release from the dam during May 1 to 10,
1944, was 50 cubic feet per second. The maximum reservoir inflow dur-
ing the same period was 15,000 cubic feet per second. It is estimated
that the effect of the reservoir operation resulted in a reduction in
stage of 1 foot at the control point. There were other periods dur-
ing the fiscal year that greater reductions resulted at the control point,
but in each instance the natural stage was considerably below the flood
stage. Costs during the fiscal year were $15711,165 57 for new work.
The expenditures were $16,044,707.17. All expenditures were from
regular funds.
               FLOOD CONTROIr-DENISON,                      TEX., DISTRICT                      835
   Condition at end of f#scal year.-Construction of outlet works, main
dam embankment, spillway, and powerhouse is complete. Installation
of one generator, one turbine, one governor, and miscellaneous power-
house equipment for the initial installation has been completed. Relo-
cations of the St. Louis-San Francisco Railway and the Missouri-Kan-
sas-Texas Railroad are complete. Relocation of Highway No. 70 is
complete except for bridge superstructure and west approach from
Kingston, Okla. Construction of State Highway No. 99 and construc-
tion of the Washita River diversion and levees are complete. Fabrica-
tion of powerhouse equipment is complete. Construction of switchyard
and transmission line from powerhouse to Denison-Payne station of
Texas Power & Light Co. is complete. Construction of switchyard and
transmission line to tie line of the Oklahoma Gas & Electric Co. is
approximately 50 percent complete. Construction of access road was
started and is approximately 22 percent complete. The entire project
is 92 percent complete. The total cost of existing project to the end of
the fiscal year, all for new work, was $51,160,511.64, all from regular
funds. Total expenditures were $50,834,830.53, all from regular funds.
The work remaining to be done consists of completing the work now in
progress, installation of additional powerhouse equipment, completing
superstructure and west approach from Kingston, Okla., for U. S.
Highway No. 70, access road and bridges, public facilities at dam
site and quarters for operating personnel.
   Proposed operations.-The balance unexpended on June 30, 1944,
including accounts receivable, of $3,312,945.01 plus allotments totalling
$450,000 in July and September 1944 will be applied as follows:
Accounts payable__
                 ------------------------------------------                             $282, 371.94
New work:
    Engineering and administration: Engineering, surveys, in-
      vestigations and office studies, including completion draw-
      ings and reports (by hired labor) July 1, 1944, to June 30,
      1945 __          __-                                  _ - -                        170, 000. 00
    Land acquisition: Acquisition of land for reservoir area, in-
      cluding cost of acquisition (by hired labor) July 1, 1944, to
      June 30,1945             _---__      -                  -     --     -    -        600, 000. 00
    Clearing: Complete clearing of the reservoir area to elevation
      620 feet mean sea level July 1, 1944, to January 1, 1945, as
      follows:
           Contract-- ___  -----------               $235, 000. 00
           Hired labor   ---                            _                80, 000. 00
           Prisoners of war_-           -----           ---              55, 000. 00
                                                                                        370, 000. 00
    Dam structure:
       Embankment protection, including sodding
         of upstream and downstream slopes and
         riprap on upstream slope (by hired labor)
         July 1, 1944, to Nov. 30, 1944----------                        95, 000. 00
       Sodding of earth pad over spillway slab and
         banks of channel cut (by hired labor)
         July 1, 1944, to Nov. 30, 1944         _____                    28, 000. 00
       Completion of access road through Govern-
         ment reservation to dam site structures
         (by contract) July 1, 1944, to Oct. 31,
           1944_   ___ - _        _        -            --           151,000.00
        Improvements to control area, lighting,
          fencing and clean-up (by hired labor)
           July 1, 1944, to June 30, 1945                   _ _--    217, 800. 00

             Total dam structure                                                    _   4
                                                                                        491,      00
                                                                                             800 00
                                                                                             800.
836       REPORT OF CHIEF OF ENGINEERS,                 U. S. ARMY,            1944

New work-Continued.
   Power facilities:
       Complete acquisition of miscellaneous mi-
         nor power equipment, exclusive of equip-
         ment for second power unit deferred to
         post war (by hired labor) July 1, 1944,
         to June 30, 1945--------------------      $200,000.00
       Complete construction of power lines from
         dam site to Texas Power & Light Co.,
         Payne substation at Sherman, Texas &
         Oklahoma Gas and Electric Co., line at
         Cartwright, Oklahoma (by contract)
         July 1, 1944, to Nov. 1, 1944-__      --    27, 000. 00
       Equipment installation and wiring of power-
         house (by contract) July 1, 1944, to June
         30, 1945 ----------------------------       16, 400. 00

               Total power facilities-----------             -                  $243, 400. 00
      Relocations:
          Completion of contract agreement with
            State of Oklahoma for the relocation of
            roads and highways (by contract) July 1,
            1944, to Apr. 30, 1945_---___-----$149,500.00
          Erection of Washita River bridge super-
            structure on Federal Highway No. 70 (by
            contract) July 1, 1944, to Feb. 28, 1945 __ 550, 900. 00
          Construction of west approach to Federal
            Highway No. 70 bridge (by contract)
            July 1, 1944, to Feb. 28, 1945-------         310, 000. 00
          Completion of contract agreement with
            M. K. & T. R. R. Co. for relocation of
            their lines (by contract) July 1, 1944, to
            Nov. 30, 1944 -                 _-   _-___     31,900.00
          Completion of contract agreement with St.
            L. & S. F. R. R. Co., for relocation of their
            lines (by contract) July 1, 1944, to Aug.
            31, 1944 ---------------------------          210, 000. 00
          Completion of contract agreement with the
            Oklahoma Gas & Electric Co., for reloca-
            tion of their power lines (by contract)
            July 1, 1944, to Feb. 28, 1945_         ---    18, 000. 00
          Completion of contract agreement with
            Southwestern Bell Telephone Co., for re-
            location of their lines (by contract) July
            1, 1944, to Sept. 30, 1944-----          --     7,000.00
          Complete corrective relocation of the water
            and sewer lines of the city of Tishomingo
            and water lines of Murray College at
            Tishomingo, Okla. (by contract) July 1,
            1944, to Sept. 30, 1944_----               --  58, 000. 00

                Total relocations_                                             1, 335, 300. 00
      Miscellaneous work:
          Completion of water line to dam site (by
             hired labor) July 1, 1944, to Sept. 30,
             1944 -------------------------------                $1,000.00
          Administration of recreational facilities (by.
             hired labor) July 1, 1944, to June 30,
             1945------------ -------------------                31,000. 00
          Hydraulic studies, including stream gaging             38, 073. 07

             Total miscellaneous work-     - -------------                        70, 073. 07

          Total new work_----        -----           ----       3, 562, 945. 01
Maintenance: Maintenance and operation of the completed project    200, 000. 00
        Total for all work- -----------
                              -                         ----- _----3,             762, 945. 01
                        FLOOD CONTROL---DENISON,                            TEX.,      DISTRICT                        837
  With this expenditure of funds it is estimated that the project
will be 100 percent complete with the exception of work deferred to
post war.
  The additional sum of $216,000 for maintenance and operation can
be profitably expended during fiscal year 1946.
                                       Cost and financial summary

Cost of new work to June 30, 1944                               _.                                 $51, 160, 511. 64
Cost of maintenance to June 30, 1944
      Totalcost of permanent work to June 30, 1944---------                                          51, 160, 511. 64
Undistributed costs June 30, 1944_----------                                                          -652, 763. 67

       Net total cost to June 30, 1944_- - -------           50, 507, 747. 97
Plus accounts receivable June 30, 1944----------------------     609, 454. 50
      Gross total costs to June 30, 1944                     ----------------                        51, 117, 202. 47
Minus accounts payable June 30, 1944_--                                 --------                         282, 371. 94

      Net total expenditures-------------------------                                                50, 834, 830. 53
Unexpended balance June 30, 1944_--     ---------                                                     2, 703, 490. 51

           Total amount appropriated to June 30, 1944                          -----------           53, 538, 321. 04


    Fiscal year ending June 30              1940             1941               1942             1943            1944

Cost of new work -------------         $2, 863, 331. 32 $7, 765, 790. 75 $5,390, 175. 84 $19, 297, 008. 71 $15, 711, 165. 57
Cost of maintenance ...-                                                         -         ---                     -

                  ---------------
Total expended ......                  2, 665, 118. 09    7, 438, 082. 26    5, 365, 578. 23 19, 158,883. 42 16,044, 707. 17
Allotted__.--.------.------.-..--7, 224, 947. 95         8, 500, 000. 00 10, 950, 000. 00 21, 000, 000. 00-.-..........



Balance unexpended July 1, 1943_-                          -------                          _      $18, 748, 197. 68
Gross amount expended_-----                                  --             $17, 513, 120. 02
Less:
        Reimbursements collected_ $1, 391, 285. 72
        Receipts from sales --- .      77, 127. 13
                                                                              1, 468, 412. 85
                                                                                                        16, 044, 707. 17
      Balance unexpended June 30, 1944-------------------                                               2, 703, 490. 51
Outstanding liabilities June 30, 1944---------   $976, 705. 74
Amount covered by uncompleted contracts__      1, 679, 973. 53
                                                                                                         2, 656, 679. 27
      Balance available June 30, 1944_---------------------                                                 46, 811. 24
Accounts receivable June 30, 1944---------------------609,                                                      454. 50
     Unobligated balance available June 30, 1944                               -----------                 656, 265. 74
Amount allotted in July and September 1944----------------                                                 450, 000. 00
           Amount available during fiscal year 1945                         ---------------              1, 106, 265. 74

Amount (estimated) required to be appropriated for completion
of existing project 1_-                                                                                 1, 460, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_                                                                         216, 000. 00
  1Exclusive     of available funds.
838             REPORT OF CHIEF OF ENGINEERS,                                                  U.        S.    ARMY,            1944

4. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
        FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work, or in the repair
or maintenance of any flood-control work threatened or destroyed
by flood. Pursuant to this act, $20,000 was allotted to the Denison
district in June 1943 for emergency repair work.
   These funds were expended for emergency repairs on the project
located in Garvin County, near Pauls Valley, Okla., approximately
167 river miles above the mouth of the Washita River. The necessary
restoration work was started on August 4, 1943, and the project com-
pleted October 13, 1943. Costs and expenditures during the fiscal
year were $20,000.
                                                Cost and financial summary
Cost of nev work to June 30, 1944__
Cost of maintenance to June 30, 1944_--------                                                                          ---              $20, 000
            Total cost of permanent work to June 30, 1944---------------                                                                20, 000
Net total expenditures                     -     -         _--                                                          -          -    20, 000
Total amount appropriated to June 30, 1944____-                                                               -20,                          000


    Fiscal year ending June 30                       1940                   1941                    1942                1943             1944

Cost of new work .-----------. .                      .     .     ..--------------- --------------------------------                      $20000
Cost of maintenance:          ----                                                                                                        $20,000
              ........
Total expended--------                  ---------------------------------------------------------                                           20,000
Allotted..---------------------------------------................
                                        .....                                      -------------------                       $20,000-


Balance unexpended July 1, 1943_---------                                                                            ----               $20, 000
Gross amount expended_- ___       ---------------                                                                                        20, 000

5. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF PUBLIC
       LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood
control structures damaged or destroyed by the disastrous floods
which occurred in the spring of 1943 and again in the spring of 1944,
Congress, in the act approved July 12, 1943, Public No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public No.
318, Seventy-eighth Congress, authorized the amounts of $10,000,000
and $12,000,000, respectively, to be appropriated as emergency funds
to be expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See p. 9 for details.)
Pursuant to the act of July 12, 1943, the sum of $70,594.43 was al-
lotted for emergency flood-control work in the Denison district dur-
ing fiscal year 1944.
   Pursuant to the act approved July 12, 1943, emergency repair work
at a cost of $19,250.43 was accomplished during the fiscal year to
levees on Rush Creek and along the Washita River at Pauls Valley,
Okla. Expenditures were $19,250.43. The balance unexpended at
the end of the fiscal year, $51,344, will be applied to restoration of
                     FLOOD CONTROL-DENISON,                      TEX., DISTRICT                                     839

levees in the Dallas County, Tex., Improvement District No. 2 and
Ellis County, Tex., Levee Improvement District No. 4, during fiscal
year 1945.
   In addition, funds in the amount of $600,000, allotted to the Den-
ison district in July 1944, pursuant to the act of May 29, 1944, will be
applied to emergency repair and restoration work during fiscal
year 1945.
                          Cost and financial summary
Cost of new work to June 30, 1944_ _"
Cost of maintenance to June 30, 1944_--------                                        ---                  $19, 250. 43
          Total cost of permanent work to June 30, 1944 ----                                 -              19, 250. 43

Net total expenditures_--- ----------                                                __               _     19, 250.43
Unexpended balance June 30, 1944_---------                                              ----                51, 344. 00
          Total amount appropriated to June 30, 1944---------                                               70, 594. 43

    Fiscal year ending June 30          1940            1941       1942                        1943              1944
Cost of new work...-
Cost of maintenance-                                                                                            $19,250.43
Total expended-             .                                                                     -19,250.43
Allotted .....-         -          --     .....    ...........              -
                                                                        ..------------ .....------.              70, 594. 43



Amount allotted from Second Deficiency Appropriation Act, 1943,
July 12, 1943_----     -------------------                     $70,594.43
Gross amount expended_- ____-----------                                                ____                 19, 250. 43
     Balance unexpended June 30, 1944__-          -     _____  51, 344. 00
Amount allotted in July 1944     -----------------------      600, 000. 00
           Amount available during fiscal year 1945------------                                            651, 344. 00

6. PRELIMINARY                  EXAMINATIONS, SURVEYS,                     AND              CONTINGENCIES
                                    FOR FLOOD CONTROL

  The cost of work during the year was $28,801.59; expenditures
were $41,178.61. The balance unexpended at the end of the fiscal
year, $6,632.67, plus accounts receivable, $10,699.80, and the sum of
$54,306 allotted in July and September 1944, a total of $71,638.47,
will be applied as needed during the fiscal year 1945 to payment of
expenses incurred under this heading.
                          Cost and financial summary
Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944_     _-_ ------                                                      $161, 035. 47
            Total cost of permanent work to June 30, 1944-                                                 161, 035. 47
Plus accounts receivable June 30, 1944__                         ----                                       10, 699. 80

      Gross total costs to June 30, 1944                                              ____                 171, 735. 27
Minus accounts payable June 30, 1944                                                                         2, 169. 24
            Net total expenditures--_-----------                                        ----               169, 566. 03
Unexpended balance June 30, 1944-                                                                              6, 632. 67

            Total amount appropriated to June 30, 1944                                                     176, 198. 70
840             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                      1944


     Fiscal year ending June 30                     1940                 1941                   1942                  1943                   1944

Cost of new work....-             ----.
Cost of maintenance.............$46, 617. 34                            $9, 017. 24           $22,234.87             17,461. 02             $28, 801. 59
Total expended........              .....          46, 361. 90           9, 048. 35            19, 832. 44           18, 589. 25             41, 178. 61
Allotted----------------------.........................--------------35,000.00                                       5,000.00                29,295.29


Balance unexpended July 1, 1943_----                                                                             -_--                $18, 515. 99
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941-                                                                     $3, 369. 78
Amount allotted from War Department Civil Appro-
  priation Act approved June 28, 1939                                                                     15, 000. 00
Transferred from Galveston district----------------                                                       10, 925. 51
                                                                                                                                      29, 295. 29
       Amount to be accounted for_---------           ----                                                                            47, 811. 28
Gross amount expended--- ------------------------------                                                                               41, 178. 61
       Balance unexpended June 30, 1944------------------------                                                                           6, 632. 67
Outstanding liabilities June 30, 1944_   -     - -       ___                                                                              2, 500. 00
      Balance available June 30, 1944_------_                                                                                             4, 132. 67
Accounts receivable June 30, 1944_---------                                                                     --                 -10,      699. 80
     Unobligated balance available June 30, 1944                                              --------------                          14, 832. 47
Amount allotted in July and September 1944-----------------                                                                           54, 306. 00
            Amount available during fiscal year 1945-------------                                                                     69, 138. 47
7. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                    ARE SUBMITTED

                                                                        For last            Cost and expenditures to                      Estimated
                                                                   full report                       June 30, 1944                        amount re-
                      Name of project                              see Annual                                            _                 quired to
                                                                     Report                                                                quired to
                                                                         for-               New work         Maintenance                   complete

Lugert-Altus Reservoir, North Fork of Red
  River, Okla_.--------------------...-.-----1942                                            $1,130,000       --------------                  (1)



  1 The    participation by the War Department in the financing of the Logert-Altus project has been com-
pleted.

Status of all investigations for flood control called for by flood-control acts and com-
                                    mittee resolutions

                                                                            Date trans-
              Locality                       Authorization act               mitted to                Document No.                   Recommenda-
                                                                             Congress                                                    tion

Altus Project, Okla......... Flood Control Com-
                               mittee resolution,
                                            Apr. 13, 1938.
Cossatot River, Ark-.........             Flood Control          Act,    ---------------                                       -

                                             June 22, 1936.
Cossatot River, Sevier Coun-                Flood Control Act,
  ty, Ark.
Eagletown Reservoir, Okla.
                                              May 6, 1936.
                                            Flood Control        Act,
                                                                         --------------- --------------------
                                                                          -------------
                                                                                                    --------------------




                                             June 22, 1936.
                     -Flood
Kiamichi River, Okla.......
                               June 28, 1938.
                                                   Control       Act,    ---------------
                                                                                         --------------------
Little River, Ark----------............
                             Flood Control Act, ---------------                                     --------------------
                               May 6, 1936.
    Do-.-----------------Flood      Control Act,
                               June 22, 1936.
                                                                         ----------------
                                                                                                I   --------------------
    See footnote at end of table.
             FLOOD       CONTROL-ALBUQUERQUE,                      N.    MEX.,    DISTRICT           841
Status of all investigations for flood control called for by flood-control acts and com-
                            mittee resolutions-Continued


                                                          Date trans-                        Recommenda-
           Locality                Authorization act       mitted to      Document No.           tion
                                                           Congress

Mangum-Salt Fork, Greer          Flood Control Act,
   County, Okla.'                  Aug. 11, 1939.
Pease River
          1   and tributaries,   Flood Control Act,
  Texas.                           June 22, 1936.
Purdy Reservoir on Rush          Flood Control Act,
   Creek, Okla.'                   Aug. 11, 1939.
Red River, La., Ark., Okla.,     Rivers and Harbors
  and Tex., for navigation,        Committee resolu-
  flood control, water power,      tion, Feb. 25, 1938.
  and irrigation (report be-
  ing prepared by the Lower
  Mississippi Valley Divi-
  sion).
Red River, La., Ark., Okla.,  Commerce Commit-
  and Tex., and connecting     tee resolution, Feb.
  waterways, singly or to-     8, 1939; Flood Con-
  gether,    for navigation,   trol Committee reso-
  flood 1 control and irriga-  lution, Jan. 26, 1939;
   tion.                        Rivers 4nd Harbors
                                Committee resolu-
                                tion, Jan. 24, 1939.
Salt Fork of Red River and1   Flood Control Act,
  tributaries, Oklahoma.       June 28, 1938.
Trinity River and tributar-   Rivers and Harbors
  ies, Texas, for navigation    Committee resolu-
  and flood control.           tion, Mar. 31, 1944.
Walnut Bayou, Little River    Flood Control Act,
   County, Ark.1               Aug. 28, 1937.
Walnut Creek, Love and        Flood Control Act,
   Carter Counties, Okla.       Aug. 18, 1941.            --
                                                          - --- --- --     --- --- --- ---
                                                                          ---
Washita River, Okla ....... Flood Control Act,
                               Aug. 28, 1937.
Washita River, Okla. (in- Commerce Commit-
  terim report on Red River    tee resolution, Feb.
   Survey).                    8, 1939; Flood Con-
                               trol Committee reso-
                               lution, Jan. 26, 1939;
                                Rivers and Harbors
                                Committeeresolu-
                               tion, Jan. 24, 1939.
Washita Valley, Okla .     -....
                              Flood Control Com-
                               mittee resolution,
                               Apr. 14, 1937.
Wichita River, Tex., navi- Rivers and Harbors
  gation,    flood   control,  Committee resolu-
  power, irrigation or water   tion, May 9, 1944.
  conservation.

  i Combine with report on Red River, La., Ark., Okla., and Tex., for navigation, flood control, power, and
irrigation, requested by resolution of the Committee on Rivers and Harbors, House of Representatives,
adopted Feb. 25, 1938, which is being prepared by the Lower Mississippi Valley Division.


      IMPROVEMENT OF RIVERS AND HARBORS IN THE
            ALBUQUERQUE, N. MEX., DISTRICT
   The district comprises the watershed of the South Canadian River
and tributaries entering the river west of the Texas-New Mexico State
line; the watershed of the Arkansas River and tributaries entering
the river west of and including Walnut Creek, Kans., the watershed
of the Rio Grande and tributaries entering the river west of and in-
cluding the Pecos River and its tributaries; and the watershed of the
Mimbres River and its tributaries in New Mexico.
   District engineer: Lt. Col. R. E. Cole, Corps of Engineers.
   Division engineer: Col. R. R. Neyland, Corps of Engineers, to June
8, 1944; Col. F. J. Wilson, Corps of Engineers, acting division engi-
neer, from June 9 to June 14, 1944; and Brig. Gen. E. H. Marks,
United States Army, division engineers, since that date.
842     REPORT OF CHIEF OF ENGINEERS,               U.   S. ARMY,   1944

                                  IMPiROVEMENTS

            Flood control                         Flood control-Continued
                                   Page                                       Page
1. Conchas Dam and Reservoir,           4. Emergency flood-control work
     South Canadian River, near             under authority of public
     Tucumcari, N. Mex-------       842     laws Nos. 138 and 318,
2. John Martin Reservoir, Ar-
     kansas River, Colo. (for-                 Seventy-eighth Congress___      848
     merly Caddoa Reservoir)--      845   5. Preliminary examinations, sur-
3. Emergency flood-control work
     under authority of the                   veys, and contingencies for
     Flood Control Act ap-
     proved August 18, 1941 --.     847
                                              flood control_-------------
                                            Plant allotment-------------
                                                                              849
                                                                              850

1. CONCHAS DAM AND RESERVOIR,              SOUTH CANADIAN RIVER, NEAR
                            TUCUMCARI,      N. MEX.


   Location.-The dam is located in San Miguel County, N. Mex., on
the South Canadian River approximately one-fourth mile down
stream of the confluence of the South Canadian and Conchas Rivers.
It is approximately 30 miles northwest of Tucumcari, N. Mex., and
744 miles upstream from the mouth of the South Canadian River.
The South Canadian River has a total length of approximately 906
miles, rises in the northeastern part of New Mexico, and flows south
and east to the Arkansas River in the vicinity of Webbers Falls, Okla.
 (See U. S. Geological Survey State map of New Mexico, scale 1:500,-
000, and U. S. Geological Survey topographic map, Tucumcari quad-
rangle; scale 1:125,000.)
   Exmisting project.-The existing project provided for the construc-
tion of a flood-control dam and reservoir which will also be used for
irrigation and water-supply purposes. The dam consists of a concrete
gravity main section 235 feet high and 1,250 feet long located in the
South Canadian River Canyon, together with earth dikes on each side
having an over-all length of about 4 miles. The main section contains
conduits located in its base capable of releasing water to maintain low-
water flow and for drainage of the reservoir, and an overflow spillway
300 feet in length. The earth dikes are of varying heights up to 100
feet and the north dike contains a concrete ogee type emergency spill-
way 3,000 feet long. The project involved about 836,000 cubic yards
of concrete, 3,600,000 cubic yards of fill, and 1,300,000 cubic yards of
excavation. The reservoir has a gross storage capacity of 600,000
acre-feet, consisting of 300,000 acre-feet for water conservation and
irrigation, 200,000 acre-feet for flood control, and 100,000 acre-feet
dead storage. The total cost was $15,451,908.56, including $2,279,-
325.70, the cost of initiating construction of the project under au-
thority of the Emergency Relief Appropriation Act of 1935. The
estimated annual cost of maintenance and operation is $50,000.
   The project is based on the report on the South Canadian River,
N. Mex., Tex., and Okla., dated June 1, 1931, made in compliance with
House Document No. 308, Sixty-ninth Congress, first session, and
approved by the President, July 29, 1935, under the provisions of the
Emergency Relief Appropriation Act of 1935, and adopted by Con-
        FLOOD    CONTROL-ALBUQUERQUE,         N.   MEX.,   DISTRICT       843

gress in the Flood Control Act of June 22, 1936 (H. Doc. No. 308, 74th
Cong., 1st sess.)
   Local cooperation.-See page 7.
   Operationsand results during fiscal year.-Miscellaneous minor re-
pairs were made and the structures were operated and maintained in
a serviceable condition throughout the year.
   The level of the reservoir has been maintained near the spillway
crest elevation 4,201.00 since June 30, 194a; it having reached a maxi-
mum elevation of 4.201.71 on May 30, 1944, and a minimum elevation
of 4,199.00 on August 16, 1943, due to temporary drawdown for test-
ing of outlet works. Total releases through June 30, 1944, for the
water year beginning October 1, 1943, were 91,466 acre-feet, of which
1,666 acre-feet were for irrigation, 1,987 acre-feet for power pro-
duction and 87,813 acre-feet for test of conduits, wave wash over the
service spillway and other losses. All irrigation release has been
to the local Bell Ranch project except 822 acre-feet released for testing
the canal of the as yet incomplete Tucumcari project, under develop-
ment by the Bureau of Reclamation.
   Ihe costs for the year were $44,966.22 for maintenance and -$4,-
305.85 for new work, making a total cost of $40,660.37. The ex-
penditures were $41,643.03.
   Condition at end of fiscal year.-The existing project was com-
pleted in 1940. The reservoir and appurtenances were in good con-
dition and in operation at the end of the fiscal year. The costs to
the end of the fiscal year, from regular funds, were $12,302,605.11 for
new work; $185,012.32 for maintenance and $110.57 undistributed.
The expenditures were $12,486,063.86.
   The costs and expenditures to the end of the fiscal year, Emergency
Relief funds, were $869,977.75 for new work.
   The total costs to the end of the fiscal year for all funds from
departmental appropriations were $13,172,582.86 for new work; $185,-
012.32 for maintenance and $110.57 undistributed. The total ex-
penditures were $13,356,041.61. In addition, the costs and expendi-
tures for work accomplished in initiating the project under the pro-
visions of the Emergecy Relief Appropriation Act of 1935 were $2,-
279,325.70.
  Proposed operations.-Operation of the reservoir will continue
as in the fiscal year 1944. The unexpended balance, amounting at the
end of the fiscal year to $25,420 and accounts receivable, $329.82, a
total of $25,749.82, plus additional funds in the amount of $40,000,
allotted in July 1944, will be applied as follows:
Accounts payable -----------------------------------------        $1, 993. 96
Operation-------------------------------------- --                30, 255. 86
Ordinary repairs_-----------------------------------               7, 150. 00
Improvement and reconstruction                                        050. 00
                                                                   6,----------------------6
Special studies and records - - - ---------------    -------      20, 300.00
      Total for all work_    ----------------------------         65, 749. 82
   The additional sum of $55,000 can be profitably expended during the
fiscal year 1946, for operation and maintenance.
844            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                          1944

                                                   Cost and financial summary
Cost of new work to June 30, 1944_ -_.---      .----   .---- $13, 172, 582. 86
Coss of maintenance to June 30,1944 ----------------------        185, 012, 32.
       Total cost of permanent work to June 30, 1944 -....                                                   1 13, 357, 595. 18
Undistributed costs June 30, 1944_     -    -     -     -                                             --                110. 57

       Net total cost to June 30, 1944----------------------13, 357, 705. 75
Plus accounts receivable June 30, 1944-                              329. 82

      Gross total costs to June 30, 1944_                                                                     13, 358, 035. 57
Minus accounts payable June 30, 1944                                                                                   993. 96
                                                                                                                    1---------------------,

      Net total expenditures_----------_                                                                     1 13, 356, 041. 61
Unexpended balance June 30, 1944_---------                                                           ---            25, 420. 00

          Total amount appropriated to June 30, 1944 ----------                                              113, 381, 461. 61

    Fiscal year ending June 30                        1940            1941             1942                1943                 1944

Cost of new work................                   $496,609.17     ....         ..    ...... .         $4, 359. 38            -$4, 305. 85
Cost of maintenance.............                     24, 332. 34     $27, 576. 93    $40, 515.39       47, 621.44               44,966. 22
      Total cost---------------.................    520, 941.51      27, 576. 93      40, 515. 39      51, 980. 82              40, 660. 37

Total expended.................                     783. 646.74      27, 472.04       39, 939.01       51, 079.99               41, 643.03

                             -466,182. 54
Allotted.........................                                  -95,352.62         54,000.00        75, 000.00              -9, 400.06


Balance unexpended July 1, 1943_                                                                                     $76, 463. 09
Amount allotted from War Department Civil Appropriation
  Act approved Apr. 28, 1942__.........                                                                               25, 599. 94
      Amount to be accounted for                                                                                     102, 063. 03
Deductions on account of revocation of allotment.....                                                                 35, 000. 00
       Net amount to be accounted for_                                                                                67, 063. 03
Gross amount expended_                    .---------- $57, 962. 79
Less:
     Reimbursements collected -------   $5, 804. 01
     Receipts from sales_ ---         - 10, 515. 75
                                                      16, 319. 76
                                                                                                                      41, 643. 03
       Balance unexpended June 30, 1944-                                           - - -                             S25, 420. 00
Outstanding liabilities June 30, 1944 ------------                                     $1, 993. 96
Amount covered by uncompleted contracts                                     -------     1, 047. 56
                                                                                                                         3 041 .            952
                                                                                                                         J,    V7      4I



          Balance available June 30, 1944-                              -                     .-----------            22, 378. 48
Accc)unts    receivable June 30, 1944_                                                                                    329. 82

      Unobligated balance available June 30, 1944-----------                                                          22, 708. 30
Amo )unt allotted in July 1944_ ___---40,                                                                                 000. 00
      Amount available during fiscal year 1945---------------                                                         62, 708. 30
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2__________- --          -55,                                                                  000. 00
  1 Includes $3,492,695.92 maintenance and improvement funds and $869,977.75 Emergency Relief funds,
but does not include $2,279,325.70, the cost of initiating the project under authority of the Emergency Relief
  2
Appropriation Act of 1935.
   Exclusive of available funds.
        FLOOD   CONTROIr--ALBUQUERQUE,       N.   MEX., DISTRICT     845

2. JOHN MARTIN RESERVOIR, ARKANSAS RIVER, COLO.              (FORMERLY
                    CADDOA RESERVOIR)

   Location.-JohnMartin Reservoir is located on the Arkansas River
1,155 miles upstream from its mouth, 295 miles downstream from its
source, and in Bent County, about 18 miles upstream from the city of
Lamar, Colo. (See U. S. Geological Survey maps for Lamar and Las
Animas (Colo.) quadrangles, scale 1: 125,000.)
   Existing project.-The existing project provides for construction
of a dam and reservoir for flood control and water conservation in
Colorado and Kansas. The dam will be a concrete and earth fill
structure approximately 130 feet high with an overflow gated spillway
1,174 feet long. The earth section extending to the abutments will
flank the concrete gravity section in the valley, and earth dikes on each
abutment in continuation of the earth section will extend to high
ground, making the over-all length of the structure approximately 2.6
miles. The reservoir, which is one unit of a comprehensive reservoir
plan for flood control in the Arkansas River Basin, will have a storage
capacity of 270,000 acre-feet for flood-control, and 385,000 acre-feet for
conservation.
   The estimated costs revised in 1943 are $11,413,000 for construction
and $3,387,000 for lands and damages.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936, under the title "Caddoa Reservoir, near
Lamar in Colorado." (See H. Doc. No. 308, 74th Cong., 1st sess.,
which contains the latest published maps.) The War Department
Civil Appropriation Act approved June 24, 1940, provided that frbm
and after the approval of that act, the Caddoa Reservoir project for
flood control and water conservation in Colorado and Kansas should
be known and designated on the public records as the John Martin
Reservoir project.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Land acquisition was
continued. Soil stabilization for the relocation of the Atchison,
Topeka & Santa Fe Railway by hired labor was completed.
   The partially completed dam (construction suspended March 29,
1943) was maintained and operated during the year on a limited stor-
age basis. Storage for irrigation up to elevation 3,815 (approximately
109,000 acre-feet) is permitted and the balance of the storage provided
by the unfinished structure (179,000 acre-feet) is reserved for flood
control. Storage operation of the reservoir for irrigation has been
maintained since March 11, 1943. The reservoir level has fluctuated
from stream bed level with no water in storage during the period
September 15, 1943, to December 9, 1943, to a maximum elevation of
3,817.62 on May 29 and 30, 1944, during a period when the reservoir
was being operated for flood storage. The reservoir was operated for
flood control from May 29 to June 22, 1944. On the latter date, the
pool had fallen to elevation 3,815.08, and irrigation operation was
resumed. Total releases through June 30, 1944, for the water year
beginning October 1, 1943, were 144,387 acre-feet, of which 45,102
acre-feet were for irrigation and 99,285 acre-feet were for flood control.
   The costs during the fiscal year were $413,933.02 for new work p
$67,272.21 for maintenance and $806.54 undistributed. The expendi-
tures were $635,121.78.
846      REPORT OF CHIEF OF ENGINEERS, U. S.                       ARMY,            1944

   Conditionat end of fiscal year.-Surveys and exploration in connec-
tion with construction of the project are complete. Land acquisition
is 97.2 percent complete. The construction for the relocation of the
Atchison, Topeka & Santa Fe Railway and salvage of the abapdoned
railroad are completed.
   Construction by continuing contract of the dam and appurtenant
works was commenced August 23, 1940, and suspended March 29, 1943.
A total of 560,000 cubic yards of concrete and 5,895,000 cubic yards
of embankment was placed. A total of 3,325,000 pounds of reinforcing
and structural steel, and a total of 2,507,000 pounds of steel sheet
piling were placed. Contractor's plant and equipment were dis-
mantled. The construction of the dam and appurtenant works is
85.1 percent complete. The earth-fill abutments are completed to
design height and the concrete structure is complete except for the
spillway bridge. Installation of steel crest gates is deferred until
after the present war emergency.
   The project as a whole is 87 percent complete.
   The total costs to the end of the fiscal year were $12,665,993.83 for
new work and $67,272.21 for maintenance. The total expenditures
were $12,732,272.44.
  Proposed operations.-Designand preparation of plans and specifi-
cations for completion of the dam, permanent operators' quarters and
facilities, Fort Lyons protective works and miscellaneous appurte-
nances will be completed during the fiscal year 1945. Operation of the
reservoir will continue as in the fiscal year 1944. The balance unex-
pended on June 30, 1944, $101,249.49, and accounts receivable, $1,072.84,
a total of $102,322.33, plus additional funds in the amount of $50,000
allotted in July 1944, will be applied as follows:
Accounts payable June 30, 1944------------------------------                            $2, 872. 98
Amount covered by uncompleted contracts---- ----------------                            57, 433. 20
Land acquisition, July 1, 1944, to June 30, 1945-----------                               1, 500. 00
Preparation of plans and specifications for completion-------                           12, 694. 90
Ordinary repairs--------------------------------          ----                            9, 100.00
Improvement and reconstruction------------------------------                             9, 521. 25
Operation       -----------------------------------------                               36, 000. 00
Special studies and records----------------------------                                 23, 200. 00
       Total   .------------------                                                     152, 322. 33

  The additional sum of $55,000 can be profitably expended during
the fiscal year 1946 for operation and maintenance.
                                     Cost and financial summary
Cost of new work to June 30, 1944_                                                $12, 665, 993. 83
C~ost of maintenance to June 30, 1944--------------------                               67, 272. 21
      Total cost of permanent work to June 30, 1944               --      -   -    12, 733, 266. 04
Undistributed costs June 30, 1944 -------------------------                                 806. 54
       Net total cost to June 30, 1944_
                                     ----------------------                        12, 734, 072. 58
Plus accounts receivable June 30, 1944-------------------                                1, 072. 84
      Gross total costs to June 30, 1944---------------                ----        12, 735, 145. 42
Minus accounts payable June 30, 1944 ----------------------                              2, 872. 98
     Net total expenditures _-12,                                                      732, 272. 44
Unexpended balance June 30, 1944_ -             _- -      --                           101, 249. 49
       Total amount appropriated to June 30, 1944-                            ,_- 12, 833, 521. 93
                  FLOOD CONTROL--ALBUQUERQUE,                                     N. MEX., DISTRICT                               847

    Fiscal year ending June 30                1940               1941                  1942                 1943              1944

Cost of new work__---------          $1, 314, 247. 33 $4, 460, 773. 77 $4, 444, 639. 72 $1, 863, 643. 57                    $413, 933. 02
                       .....
Cost of maintenance ----------                 --------------         -------------------------                               67,272.21

                     ------------
        Total cost.....   ....    1, 314, 247. 33          4, 460, 773. 77       4, 444, 639. 72       1, 863, 643. 57       481, 205. 23

             --------------
Total expended......                       969, 211.56     4, 261, 222. 45       4, 503, 806. 54       2,195, 894. 95        635,121.78
Allotted- ...............-..             3, 130, 000. 00   3,826, 187. 92        2, 800, 000.00- .............             -- 675, 765.99



Balance unexpended July 1, 1943                              _               -          -          -               $1, 412, 137. 26
Amount allotted from War Department Civil Aoppropriation Act
    approved Apr. 28, 1942_ ____-                                                 -            -_120,                         900. 00

      Amount to be accounted for_-----------------------                                                            1, 533, 037. 26
Deductions on account of revocation of allotment----------                                                             796, 665. 99
        Net amount to be accounted for_                                                                                  736, 371. 27
Gross amount expended ----------------------- $764, 206. 29
Less:
      Reimbursements collected .   .$126, 102. 86
     Receipts from sales-- -------       2, 981. 65
                                                    129, 084. 51
                                                                                                                         635, 121. 78
       Balance unexpended June 30, 1944-                                                                                 101, 249. 49
Outstanding liabilities June 30, 1944--- -----------                                    $2, 872. 98
Amount covered by uncompleted contracts                                      -        .57, 443. 20
                                                                                                                          60, 316. 18
      Balance available June 30, 1944                                                                                     40, 933. 31
Accounts receivable June 30, 1944_                                                                                         1, 072. 84
     Unobligated balance available June 30, 1944-                                                                         42, 006. 15
Amount allotted in July 1944-----------------                                                                             50, 000. 00
            Amount available during fiscal year 1945                                                                      92, 006. 15
Amount (estimated) required to be appropriated for completion
    of existing project 1        -   _          -- -_ _      -   -                                                  2, 062, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1_ _-__                     - --                                                         55, 000. 00
1Exclusive of available funds.

3. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
         FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work, or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood. Pursuant to this act, $15,000 was allotted to the Albuquerque
district during the fiscal year for emergency repairs in the Middle Rio
Grande Conservancy District.
   The Middle Rio Grande Conservancy District, a local agency,
authorized by and operating under the laws of the State of New
Mexico, has constructed levees in the Middle Rio Grande Valley, that
portion of the flood plain of the Rio Grande in New Mexico extend-
ing upstream about 164 miles from Elephant Butte Reservoir (river
mile 1,418) to the mouth of White Rock Canyon near the Pena
Blanca (river mile 1,582), in order to protect from inundation during
 848                REPORT OF CHIEF OF ENGINEERS,                                                            U.    S. ARMY,             1944

periods of high water the cities of Albuquerque, Belen, and Socorro,
and numerous villages and Indian pueblos, as well as agricultural
lands, in the flood plain.
   Repairs were initiated January 22,1944. The costs and expenditures
during the fiscal year were $15,000. The total costs and expenditures,
including work done during fiscal years 1942 and 1943, to the end of
the fiscal year were $49,147.41.
                                                           Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944                                                                   -      -$49,                            147. 41
       Total cost of permanent work to June 30, 1944                                                                          - -          49, 147. 41
Net total expenditures-    ..-...                                                                                                          49, 147. 41
Total amount appropriated to June 30, 1944           -                                                               -     - - -    -      49, 147. 41

      Fiscal year ending June 30                                1940                     1941                 1942             1943            1944

Cost of new work ....--------..-------.....-------------
Cost of maintenance.............-.-....                               --.-.-.- .............                $29, 946. 47      $4, 200.94         $15, 000

Total expended--...........--------------.--------------30,                                                       200.68       3,946. 73          15, 000

Allotted ------------------------...................------------------..............--..............   --    50, 000. 00    -15, 852. 59          15, 000


Balance unexpended July 1, 1943
Amount allotted from War Department Civil Appropriation Act ap-
  proved May 23, 1941 --                                        $15, 000. 00
Gross amount expended --------------------                       15, 000. 00

4. EMERGENCY FLOOD-CONTROL      WORK UNDER AUTHORITY OF
   PUBLIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS
   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods
which occurred in the spring of 1943 and again in the spring of 1944,
Congress, in the act approved July 12, 1943, Public No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public No. 318,
Seventy-eighth Congress, authorized the amounts of $10,000,000 and
$12,000,000, respectively, to be appropriated as emergency funds to be
expended under the direction of the Secretary of War and the super-
vision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had
been threatened or destroyed by the recent floods. (See p. 9 for
details.) Pursuant to the act of July 12, 1943, the sum of $440,000
was allotted for emergency flood-control work to the structures of
the Middle Rio Grande Conservancy District in the Albuquerque
district.
   Repairs to the levees and structures of the Middle Rio Grande
Conservancy District (for details see preceding statement on p. 847)
were initiated on January 22, 1944, and were continuing at the close
of the fiscal year. The costs during the fiscal year were $394,756.72,
and the expenditures were $351,677.78. The total costs to the end
of the fiscal year were $394,756.72, and the total expenditures were
$351,677.78. The balance unexpended on June 30, 1944, totaling $88,-
322.22, will be expended during fiscal year 1945 for obligations in-
curred under this heading.
            FLOOD CONTROL--ALBUQUERQUE,                                         N. MEX., DISTRICT              849

  Additional funds in the amount of $46,000 were allotted to the
Albuquerque district in July 1944 for emergency repairs pursuant to
the act of May 29, 1944. These funds will be applied for the emer-
gency repair of flood-control structures located in the Albuquerque
district which have been damaged by flood..
                                   Cost and financial summary
Cost of new work to June 30, 1944
                                                                 -
Cost of maintenance to June 30, 1944- - - - - - - - - - - - - - - - - - - - - --                    $394, 120. 78
       Total cost of permanent work to June 30, 1944---      - 394, 120. 78               ----
Undistributed costs June 30, 1944-----------------------------      635. 94

      Gross total costs to June 30, 1944_-------------------                                            394, 756. 72
Minus accounts payable June 30, 1944------------------------                                             43, 07&8. 94
      Net total expenditures- ---------------------------   351, 677. 78
Unexpended balance June 30, 1944---------------------------88, 322. 22
         Total amount approuriated to June 30, 1944- - - - - - - - - - - -                              440, 000. 00

   Fiscal year ending June 30          1940                  1941                 1942       1943            1944

C ostofnew w ork ..-                    - - --.- - - - --.--                            . .-..-..
                                                                                 .-.-.--..
                  -------------
Cost ofmaintenance------           ------------------------------------------            -- - - - - -       3410 78
                                                                                                           $394,i20. 7

Total expended-------------------------------------------------------------                                 351, 677.78
Allotted.-----------------------    - --------------                     -----------------------------      440,000.00


Balance unexpended July 1, 1943_
Amount allotted from Second Deficiency Appropriation Act approved
               ----------------------------------------- $440, 000.00
  July 12, 1943_
Gross amount expended_-----------          -------------- ____    351, 677. 78

      Balance unexpended June 30, 1944----------------------                                             88, 322. 22.
Outstanding liabilities June 30, 1944 ---------------
                                           _          $43, 078. 94
Amount covered by uncompleted contracts---------- 11, 265. 47
                                                                                                         54, 344. 41
     Unobligated balance available June 30, 1944- - - - - - - - - - - - -                                33, 977. 81
Amount allotted in July 1944_ -------------------------      ____                                        46, 000. 00

         Amount available during fiscal year 1945 -----------------                                      79, 977. 81

5. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES FOR
                      FLOOD CONTROL

   The cost of the work during the year was $215,236.17; the expendi-
tures were $208,072.76. The balance unexpended at the end of the
fiscal year, $56,252.42, plus accounts receivable, $3,500, and the sum of
$95,000 allotted in July 1944, amounting to a total of $154,752.42, will
be applied to accounts payable in the amount of $16,898.59 and as
needed during the fiscal year 1945 to the payment of expenses incurred
under this heading.
   The additional sum of $115,000 can be profitably expended during
the fiscal year ending June 30, 1946.



         616634--45-pt. 1, vol. 1-            54
850            REPORT OF CHIEF OF ENGINEERS,                                            U.       S. ARMY,                 1944

                                               Cost of financial summary
Cost of new work to June 30, 1944--------                                                                                 ----------
Cost of maintenance to June 30, 1944                         ..-----                                         ___               $397, 584. 54

      Total cost of permanent work to June 30, 1944                   584. 54
                                                                3------------397,
Plus accounts receivable June 30, 1944-------------------------    3, 500.00

      Gross total costs to June 30, 1944--  ----        ___                                                                     401,084. 54
Minus accounts payable June 30, 1944 -------------------                                                                         16, 898. 59

      Net total expenditures                                                                                                    384,185. 95
Unexpended balance June 30, 1944 ----------------------------                                                                    56, 252. 42
            Total amount appropriated to June 30, 1944_                                                                         440, 438. 37

     Fiscal year ending June 30                  1940               1941                 1942                      1943                 1944

C ost of new w ork ....        . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                            . . . .. . . .
Cost of maintenance------------.............   $31, 361.33     $7, 369. 79          $18, 274. 96              $89, 828. 64            $215, 236.17

Total expended..................                31, 361.33      7, 369. 79              14, 410. 29            69,183.17               208, 072. 76

Allotted-.-------------------..-24, 000. 00                  -15,       835. 30         26, 500. 00            96, 252. 59             225,166. 05


Balance unexpended July 1, 1943 .   ..     .. .....                                                                             $39, 159. 13
Amount allotted from War Department Civil Appropriation Act
  approved Apr. 28, 1942----      --------           -__                                                                        225, 166.05
       Amount to be accounted for                                   -              -_                                           264, 325. 18
Gross amount expended                                                                            $208,217. 13
Less reimbursements collected                                                                         144.37
                                                                                                                                208, 072. 76

      Balance unexpended June 30, 1944_                                                                      __                  56, 252. 42
Outstanding liabilities June 30, 1944                                                                $16,898.59
Amount covered by uncompleted contracts                                 ----------                     2, 934. 74
                                                                                                                               S19, 833. 33

      Balance available June 30, 1944                                    ---------------------                                   36,419.09
Accounts receivable June 30, 1944                                                                                          -       , 500. 00
                                                                                                                                  3----------------------
     Unobligated balance available June 30,1944---------39,919.                                                                           09
Amount allotted in July 1944- _  -   ------------                                                                                95, 000. 00

            Amount available during fiscal year 1945                              ------------                                  134, 919. 09
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenancel        -----------           -115,000.00
  1 Exclusive of available funds.


       6. PLANT ALLOTMENT, ALBUQUERQUE, N. MEX., DISTRICT
                                               Cost and financial summary
Undistributed costs June 30, 1944 _______-_                                                          _                    -- $102, 372. 54

Net total cost to June 30, 1944____________                                                                                -102,372.           54
Plus accounts receivable June 30, 1944________ ___                                                                               68, 392. 16
      Gross total costs to June 30, 1944                                                     -           -     -               -33, 980. 38
Minus accounts payable June 30, 1944__ -                                   ---                   -            __                 18, 877. 76
            Net total expenditures___                                                            _________                     -52,     858. 14
Unexpended balance June 30, 1944__                              -__                                                             214, 070.48
            Total amount appropriated to June 30, 1944                                  ----------                              161, 212. 34
             FLOOD       CONTROL---ALBUQUERQUE,                                 N.            MEX.,         DISTRICT                  851

   Fiscal year ending June 30                1940              1941                      1942                  1943               1944

Total expended--........-..---            $130, 964. 42 -$166. 914. 17 -$577, 903. 81                      $174, 633.35         $386, 362.07
Allotted.........................          361, 212.34   -100, 000.00 .              .           .     .                       -100,000.00


Balance iinexpended July 1, 1943 _    -       -     -      -                                                          -$700,      432. 55
Deductions on account of revocation of allotment----------                                                                   100, 000. 00

       Net amount to be accounted for__--     ------               __                                                        600, 432. 55
Gross amount expended_--       ---------                  $1, 397, 031. 37
Less:
     Reimbursements collected ..        $1, 010, 274. 30
     Receipts from sales----------                395. 00
                                                            1, 010, 669. 30
                                                                                                                             386, 362. 07

      Balance unexpended June 30, 1944 ....                                                                     _            214, 070. 48
Outstanding liabilities June 30, 1944_ - ---                                                     $18, 877. 76
Amount covered by uncompleted contracts .                                                         84, 901. 23
                                                                                                                             103, 778. 99

      Balance available June 30, 1944_---                                                     - --              ___          110, 291. 49
Accounts receivable June 30, 1944_ _____-                             -----                                _                  68, 392. 16
     Unobligated balance available June 30, 1944                                               ---                           178, 683. 65
Amount revoked in August 1944_---           - --                                                               ____           61, 212. 00

         Amount available during fiscal year 1945------------                                                                117, 471. 65

Status of all investigationsfor flood control called for by flood-control acts and committee
                                        resolutions


                                                                    Date trans-                                              Recommenda-
           Locality                    Authorization act            mitted to                   Document No.
                                                                                                                                 tion
                                                                     Congress
                            -    f                             1                          i                             1 -     - -

Alamogordo Dam and Res-              Sec. 7 of Flood Control
ervoir, Pecos River, N.               Act, Aug. 11, 1939.
  Mex., flood control, irriga-
  tion, and other uses.
Arkansas River and tribu-            Commerce Commit-
  taries, Colorado.                    tee resolution, Sept.
                                       30, 1942.
Arkansas River and tribu-            Flood .Control Com-
  taries (local flood protec-          mittee resolution,
  tion along the main stem,            July 2, 1943.
  above       Great    Bend,
  Kans.).
Arkansas River for flood Flood Control Com-
  control at and in the         mittee resolution,
  vicinity of Great Bend,       Jan. 21,1944.
  Kans.
Huerfano River, Colo., trib- Flood Control Act,
utary of Arkansas River.       June 22,1936.
Long's Canyon, Colo. (Las Flood Control Act,                       Jan. 24, 1944              H.  387,     78th              Favorable.
  Animas County, trib-          June 28,1938.                                                  Cong., 2d sess.
  utary      of     Purgatoire
  River).
Mimbres River and tribu- Flood Control Act,                        Aug.       6,1943                                         Unfavorable.
  taries, New Mexico.           Aug. 18, 1941.
Pecos River and tributaries, .Flood Control Act,
  Texas and New Mexico.         June 28,1938.
Purgatoire (Picket Wire) Flood Control Act,                        Jan. 24, 1944              H.   387,    78th              Favorable.
  River,      Colo.    (tribu-  June 22,1936.                                                   Cong., 2d sess.
  tary of Arkansas River).
Rio Grande and tributaries, Flood Control Act,
  New Mexico.                   Aug. 18,1941.
Rio Grande and tributaries, Commerce Commit-                       July 29,1943                S. 104, 78th Cong.,              Do.
flood control in vicinity of   tee resolution, July                                              1st sess.
  Creede, Colo.                 22, 1941.
Rio Grande and tributaries Commerce Commit-                        Apr. 17,1944               --------------------           Unfavorable.
  in vicinity of Alamosa,       tee resolution, Oct.
  Colo.                         28, 1941.
                                 I                             I                          I                              I
852     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                         1944

   IMPROVEMENT OF RIVERS AND HARBORS IN THE
                 LITTLE ROCK, ARK., DISTRICT
   This district comprises the northern and western portions of Arkan-
sas, a portion of southern Missouri, and a small portion of eastern
Oklahoma embraced in the drainage basins of the Arkansas River and
tributaries above and exclusive of Pine Bluff, Ark., and below the
mouth of Poteau River, near Fort Smith, Ark., and of the White
River and tributaries above Peach Orchard Bluff, Ark.
   District engineer: Col. Alexander M. Neilson, Corps of Engineers,
from June 9, 1944, to June 14, 1944.
   Acting district engineer: Lt. Col. George R. Schneider, Corps of
Engineers, November 29, 1943, to January 3, 1944.
   District engineer: Lt. Col. William A. Davis, Corps of Engineers,
since that date.
   Division engineer: Col. R. R. Neyland, Corps of Engineers, to June
8, 1944.
   Acting division engineer: Col. F. J. Wilson, Corps of Engineers,
from June 9, 1944, to June 14, 1944.
   Division engineer: Brig. Gen. E. H. Marks, United States Army,
since that date.
                                     IMPROVEMENTS

              Navigation                            Flood control-Continued
                                       Page                                         Page
1. White   River,   Ark.   (above            10. Norfork    Reservoir,    White
      Peach Orchard Bluff)   - --      852          River Basin, Ark .              869
2. Black River, Ark. and Mo           855    11. White River Basin, Little
3. Upper White River, Ark .           856          Rock district__                 871
4. Examinations, surveys, and                12. Emergency         flood-control
      contingencies (general) _--      860          work under authority of
5. Other navigation projects for                   the Flood Control Act
      which no estimates are sub-                   approved August 18, 194_        873
      mitted_                           860   13. Emergency        flood-control
                                                    work under authority of
             Flood control                          Public Laws Nos. 138 and
6. Blue Mountain Reservoir,                        318, Seventy-eighth Con-
      Arkansas   River     Basin,                   gress _--   ----                875
      Ark_ _           --               861   14. Preliminary     examinations,
7. Nimrod Reservoir, Arkansas                      surveys, and contingencies
      River Basin, Ark                  863         for flood control --            876
8. Arkansas River Basin, Little              15. Other flood-control projects
      Rock district      -              866         for which no estimates are
9. Clearwater Reservoir, White                     submitted_                      878
      River Basin, Mo __..              867   16. Plant allotment_.                 878
      1. WHITE RIVER, ARK. (ABOVE PEACH ORCHARD BLUFF)
  Location.-This river rises in northwestern Arkansas and flows 720
miles, first north into Missouri, then southeasterly through Arkansas
to the Mississippi River, 45 miles above Arkansas City, Ark. The
portion of the river within the limits of this district extends from
the headwaters downstream to Peach Orchard Bluff, Ark. (169 miles
above the mouth), at which point the river enters the Memphis En-
gineer district. (See Mississippi River Commission Alluvial Val-
ley maps, scale 1: 62,500 and scale 1: 500,000, for river from Peach
Orchard Bluff to vicinity of Newport, Ark., and U. S. Geological
SSurvey State map, scale 1: 500,000.)
  Previows projects.-Adopted by the River and Harbor Acts of
March 3, 1871, June 23, 1874, August 14, 1876, June 14, 1880, July 5,
1884, and March 3, 1899.
          RIVERS    AND HARBORS-LITTLE              ROCK, ARK.,     DISTRICT        853

   For further details see page 1874 of Annual Report for 1915, and
page 963 of Annual Report for 1938.
   Existing project.-This provides for channel maintenance between
the mouth of the river and Batesville, 301 miles, by snagging and
dredging and by contraction works. The stream has an ordinary
freshet fluctuation of 15 feet throughout the portion covered by the
project and an extreme stage fluctuation of 36 feet at Newport and
Batesville. No estimate of cost has been given, and since 1899 the
work has been prosecuted under annual estimates for maintenance by
snagging and dredging. The latest (1934) approved estimate for
annual cost of maintenance above Peach Orchard Bluff is $20,000.
   The existing project was authorized by the River and Harbor Act
of July 13, 1892, which made appropriation for completion of prior
project for improving the river from its mouth to Forsyth, Mo., and
provided that the additional sum appropriated should be expended
in the discretion of the Secretary of War. A project for the improve-
ment of the river above Batesville by locks and dams is reported under
the heading Upper White River, Ark.
    Terminal facilities.-Railway spur tracks are available for transfer
of freights between car and boat at Newport. There are log slips for
use of the owners only at Newport and Augusta. These terminal
facilities are considered adequate for existing commerce.
   Operations and results during fiscal year.-All operations were for
maintenance with Government plant and hired labor, and consisted of
dredging and snagging. The U. S. derrick boat No. 2001 removed
2,500 cubic yards of material from the channel at lower Grand Glaize,
mile 241, during the period October 10 to 16, 1943.
   The U. S. snag barge Harve Goodwin snagged 124.9 miles on the
White River during the periods February 9 to April 21 and June 15 to
30, 1944, between Peach Orchard Bluff, mile 169, and Newport, mile
258. During these operations 240 snags and 5 stumps were removed,
15 drifts were broken, and 25,444 trees were cut.
   The costs during the fiscal year were $104.19 for dredging and
$13,692.74, for snagging, a total of $13,796.93. The expenditures were
$11,172.04, all for maintenance.
   Condition at end of fiscal year.-The project being for maintenance,
completion is not contemplated. Snagging and dredging operations
have materially improved the channel from Peach Orchard Bluff to
the mouth of Black River and as a result a minimum navigable depth of
4 feet was maintained throughout the year. A minimum depth of 21/
feet existed from the mouth of Black River to lock No. 1.
    The total costs under the.existing project to June 30, 1944, are:
For maintenance:
    Snagging operations.                                       $451, 106. 07
     Dredging operations                        --------------  181,531. 20
       Total     -------------------------------------------                 $632, 637. 27
Specials:
     Augusta, for prevention of cut-off----------------             $314. 84
     Augusta Narrows, levee and revetment-
     Augusta Narrows, set-back levee----------
                                                   ------        50, 620. 16
                                                                  5, 407. 38
     Little Red River snagging:
          1914 ------------------------------------                  500.00
          1935-                                                      358. 80
          1940-                                                      886. 83
                                                                               58, 088. 01
            Total costs to June 30, 1944-                                     690, 725. 28
854         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

  The total expenditures were $1,029,100.39 (excluding $60,613.63 for
operating and care reported under Upper White River). In ad-
dition, $3,291.44 contributed funds were expended for maintenance
at Augusta Narrows.
  Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $6,873.82, will be applied to channel main-
tenance as follows:
Accounts payable, June 30, 1944                                     $4, 024. 89
Snagging operations between Jennings Landing (mile 219)and lock No.
  1 about 1 month with Government plant and hired labor during the
  month of July 1944                                   ____          2, 848. 93
          Total for all work                                                                                             6,873. 82
  The additional sum of $30,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance:
   Snagging operations between Peach Orchard Bluff and lock                                                     No. 1,
      about 4 months with Government plant and hired labor in                                                   period
      July 1945 to June 1946__      ----------                                                                   ___ _$12, 000
   Dredging operations between Peach Orchard Bluff and lock                                                     No. 1
      about 4 months with Government plant and hired labor in                                                   period
      July 1945 to June 1946__---     ------------                                                                     18, 000
             Total for all work -------------------------------------                                                      30, 000

                                            Cost and financial summary
Cost of new work to June 30, 1944                                                                                    $337, 801. 57
                                    -
Cost of maintenance to June 30, 1944___                                      ---------                                693, 923. 71
       Total cost of permanent work to June 30, 1944------------ 1, 031, 725. 28
Undistributed costs June 30, 1944_---------                   ----    1,400. 00
      Net total cost to June 30, 1944___------                                                       -            1, 033, 125. 28
Minus accounts payable June 30, 1944--         ----                                                   -___4,              024. 89
     Net total expenditures_ _   ------------                                                                     1,029, 100. 39
Unexpended balance June 30, 1944_-----                                                    -              -_6,            873. 82
          Total amount appropriated to June 30, 1944--------                                                      1, 035, 974. 21

    Fiscal year ending June 30                  1940             1941                  1942                1943            1944

Cost of new work .......
Cost of maintenance.-..........              $36, 387:36       $28, 993.67        $15, 283.43            $27, 860.65      $13, 796.93
Total expended....         ........--------------35, 588. 55    25, 490. 12           19, 180. 34         28, 266. 10      11,172. 04
Allotted.---..-...      ..........            41,000.00         26, 000. 00           25, 000.00    --------------         12, 000. 00


Balance unexpended July 1, 1943_                                        -----------                                     $6, 045. 86
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941 -------------- $2, 000. 00
Amount allotted from War Department Civil Appro-
priation Act approved Apr. 28, 1942               10, 000. 00 ---------
                                                                                                                        12, 000. 00

       Amount to be accounted for- _                                ------                              ___             18, 045. 86
Gross amount expended_--------                                           ---                  $11, 796. 35
Less receipts from sales-                                                                          624. 31
                                                                                                                        11, 172. 04

          Balance unexpended June 30, 1944--.                                     -                 -                    6, 873. 82
           RIVERS AND HARBORS-LITTLE ROCK, ARK., DISTRICT                  855

Outstanding liabilities June 30, 1944--- ------------- $4, 024. 89
Amount covered by uncompleted contracts------- ---         155. 00
                                                                     $4, 179. 89

        Balance available June 30, 1944---------------------          2693.
                                                                      2,    93
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1_-           _-     ---           _--   30, 000. 00
I Exclusive of available funds.

                             2. BLACK RIVER, ARK. AND MO.
   Location.-This river rises in Iron County, Mo., and flows in a
southerly direction 300 miles to White River, at Jacksonport, Ark.
 (See Mississippi River Commission Alluvial Valley Maps, scales
1: 62,500 and 1: 500,000; and U. S. Geological Survey State maps,
scale 1: 500,000.)
   Previous projects.-Adopted by the River and Harbor Act of
March 3, 1871. It is not practicable to state the amount expended
under the project; however, it is known to have been very small.
For further details see page 1877, Annual Report for 1915.
   Existing project.-Improvement of the river below Poplar Bluff,
Mo., 211 miles, by snagging operations, by deepening the water on
shoals by wing dams, and by concentrating the water into one main
channel by the closure of secondary channels.
   The stream has an ordinary freshet fluctuation of 10 feet at Poplar
Bluff, 4 feet near Corning, Ark., and 15 feet at the mouth. Its ex-
treme stage fluctuations are 19 feet at Poplar Bluff, 11 feet near
Corning, Ark., and 36 feet at the mouth. The original estimate was
$80,800, to be expended in two working seasons (Annual Report
for 1880, p. 1326). The River and Harbor Act of September 19,
1890, appropriated an amount to complete the estimate and author-
ized maintenance of the improvement. While dredging is not men-
tioned in the project, it is necessary as a means of maintenance and
has been authorized. The latest (1928) approved estimate for annual
cost of maintenance is $18,000.
   The existing project was adopted by the River and Harbor Acts
of June 14, 1880, and March 3, 1881. (Annual Report for 1880, p.
1325.) The approximate location and course of the navigable por-
tion of this stream are shown in sketch map printed in Annual Report
for 1911, opposite page 1877.
   Terminal facilities.-Privatelyowned log slips or chain conveyors
for the use of the owners are maintained at the several saw and stave
mills. The facilities are considered adequate for the existing com-
merce.
   Operations and results during fiscal year.-None. The expendi-
ture for the year was $891.58 for accounts payable from the previous
fiscal year.
   Condition at end of fiscal year.-The project being for maintenance,
completion is not contemplated. Maintenance operations were sus-
pended for the duration of the present war emergency.
   Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $1,291.72, will be applied to accounts
payable and maintenance contingencies.
   No work is contemplated during the fiscal year 1946.
856         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

                                          Cost and financial summary
Cost of new work to June 30, 1944                                                                                     $80, 000. 00
Cost of maintenance to June 30, 1944_-------                                                       ---                577, 280. 47
      Total cost of permanent work to June 30, 1944------------                                                       657, 280. 47
Undistributed costs June 30, 1944_---------              ----                                                           3, 333, 09
      Net total cost to June 30, 1944_-_                                      --------                                660, 613. 56
Plus accounts receivable June 30, 1944---                                      ----------                                  404. 28

      Gross total costs to June 30, 1944--                                   --------                                 661, 017. 84
Minus accounts payable June 30, 1944_--------                                                                   ---          4. 14

      Net total expenditures _______------                                                        -_____              661, 013.70
UJnexpended balance June 30, 1944_-                                -         --------                                      887. 44

          Total amount appropriated to June 30, 1944                               --------                           661, 901. 14

    Fiscal year ending June 30                 1940             1941                1942                 1943               1944
Cost of new wor ......                                                                                      2         .   .......... .
Cost of maintenance............             $12, 278. 92      $13, 736. 63         $9, 597. 68            $727. 26
Total expended               -.......... -...... 11,293. 11    12, 560.35          13, 043.02            1, 395 .60         .    $891. 58
Allotted.......-----------------------         5,000.00        13, 500.00          10, 000. 00    --------------          -12, 000.00


Balance unexpended July 1, 1943 ----------------------------     $13, 779. 02
Deductions on account of revocation of allotment----------------12, 000. 00

       Net amount to be accounted for__-                               --                   -     _____                   1, 779.02
Gross amount expended_--------                                              ---                  $6, 967. 21
Less receipts from sales--------.                                      -----                      6,075. 63
                                                                                                                                891. 58


      Balance unexpended June 30, 1944_-------                                                              ---             887. 44
Outstanding liabilities June 30, 1944_---------                                                             ---               4. 14

      Balance available June 30, 1944_--                                     ----------                                     883. 30
Accounts receivable June 30, 1944___                                                                                        404. 28

          Unobligated balance available June 30, 1944                              ---------------                        1, 287. 58

                                   3. UPPER WHITE RIVER, ARK.

  Location.-These works are on the White River, Ark., lock and
dam No. 1 being 1 mile below Batesville, Ark., and Nos. 2 and 3 being
7.8 and 19.7 miles, respectively, above that city. (See Mississippi
River Commission Alluvial Valley map, scale 1:500,000, and U. S.
Geological Survey map, scale 1: 500,000.)
  Previous projects.-See previous projects for White River, page
1874, Annual Report for 1915.
    Existing project.-This provides for the construction of 10 fixed
dams with concrete locks to give 4-foot navigation the year around.
The River and Harbor Act of March 2, 1907, after providing for the
completion of the third lock and dam, abandoned further construc-
tion work, its language fixing the appropriation carried therein as
the final one. The stream is nontidal, with an ordinary freshet fluc-
tuation of 16 to 18 feet, and with an extreme stage fluctuation of 38
feet just below lock No. 1 and of 51 feet at Calico Rock, 39 miles above
lock No. 3.
               RIVERS AND HARBORS                                    LITTLE ROCK,                       ARK.,              DISTRICT            857

   The estimated cost for the 10 locks and dams originally projected
was $1,600,000. The estimate of annual cost of operation and care
of the 3 locks and dams, made in 1936, is $42,500.
  The existing project was adopted by the following river and harbor
acts:

       Acts                            Work authorized                                                                     Documents



Mar.     3,1899    Existing project adopted__-------------------- H. Doc. No. 78, 54th Cong., 2d sess.,
                                                                                                    Annual Report, 1897, p. 1992.
Mar. 2, 1907       Abandonment of further new work on the project                                H. Doc. No. 150, 59th Cong., 1st sess.
June 26, 19341     Operating and care of locks and dams provided
                     for with funds from War Department appro
                     priations for rivers and harbors.


  1Permanent Appropriations Repeal Act.

  The locations, dimensions, etc., of the three completed locks and
dams are as follows:

                                                   Lock No. 1                              Lock No. 2                             Lock No. 3


Location-..-.          -f----Batesville-----------.............                   Earnharts-----------.............         Walls Ferry.
Distance from mouth of river_              300.6 miles                                          ...........
                                                                   ......----------. 309.4 miles----------                  321.3 miles.
Dimensions of locks:
    Length available.........----------.   147 feet.. _-____.---147                   feet..........-------------....       147 feet.
    Width available ......-----------      36 feet-....-......                    36 feet--------------.................    36 feet.
    Depth on lower sill at mean            4.3 feet....        ........                ..........
      low water (open river).
     Depth on lower sill at nor-           .....................                                    -
                                                                                  6.5 feet--................ 4.7 feet.
       mal pool.
     Depth on upper sill at nor-           7.1 feet__-.              ....---      5.3 feet...........-------------....      5.2 feet.
       mal pool.
    Lift at mean low water and             15.6 feet.......................
      normal pool.
   Lift at normal pools..-----------               -------------               _12.8  feet.........------------..           14.5 feet.
   Foundations..............     --        Bedrock-----......---------            Bedrock...........------------..          Bedrock.
Dams:
              ----------------- Fixed.............--------------.. Fixed --------------
    Kind of.....                                                                                                            Fixed.
    Type of construction-..... Timber crib filled Timber crib filled                                                        Timber crib filled with
                                  with stone.                        with stone,                                              stone.
    Length-----------------     660.5 feet.------------658 feet-------------                                                750.7 feet.
Date opened to navigation- ..    1904-....      .---.-.-                          1905 ........---------------              1908.
Date of completion ----------- 1904___ -----------                                1905_---------------                      1908.
Cost of construction ----------- $278,587.56.........----------...                $297,627.94.........----------..          $236,981.31.


  All dams are with concrete caps.
  The approximate location of these locks and dams is shown on
district map (sketch) printed in Annual Report for 1911, opposite
page 1877.
   Terminal facilities.-Log slips, derricks, and conveyors exist at the
several woodworking establishments, all for the individual use of the
owners. The terminal facilities are considered adequate for the pres-
ent commerce.
   Operations and re8u~lts during fiscal year.-All work was for main-
tenance with Government plant and hired labor at locks and dams
Nos. 1, 2, "and 3. Work during the year consisted of operation of the
locks and routine maintenance of appurtenant river structures, build-
ings, and grounds.
   The U. S. derrick boat No. 2001, during the period July 1 to 31, 1943,
removed 850 cubic yards of material from lock pits and approaches
at lock No. 1.
858       REPORT OF CHIEF OF ENGINEERS,                            U.       S.   ARMY,        1944


   The U. S. snag barge Harve Goodwin, during the period August 4
to 14, 1943, removed 153 snags and 7 stumps from the channel above
locks Nos. 1 and 2, and cut 70 overhanging trees.
   The costs during the fiscal year were $21,929.74, and the expenditures
were $21,355.47, all for maintenance.
   Condition at end of fiscal year.-The new work accomplished to the
end of the fiscal year is the construction of three locks and dams men-
tioned under paragraph "Existing project." The project, as amended,
is complete. These works, by aid of dredging, give all-year slack water
navigation for 4-foot draft from 1 mile below Batesville to Guion,
which is 33 miles upstream therefrom.
   The total costs to the end of the fiscal year were:
For new work (construction of locks and dams) -------   _---- -                                    $813, 196. 81
For maintenance (operation and care) (includes $60,613.63 not
  covered by cost and financial summary for White River, Ark.) _-_                                         310, 631. 71

        Total cost to June 30, 1944_----------------------                                        1, 123, 828. 52
  The total expenditures to the end of the fiscal year were:
For new work (construction of locks and dams)-- ----                                   -          $813, 196. 81
For maintenance (operation and care)---- ---------------------                                     337, 958. 39
        Total expenditures to June 30, 1944----_            -----------                           1, 151, 155. 20
  In addition, the sum of $1,187,282.59 was expended between January
16, 1904, and June 30, 1935, on the operations and care of the works of
improvement under the provisions of the permanent indefinite appro-
priation for such purposes.
  Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $16,423.70, plus an allotment of $25,000
made during July 1944 will be applied to operation and maintenance
of the three locks and dams during the fiscal year 1945 under approxi-
mate distribution as follows:
Accounts payable__---------------------------------------        $1, 681.65
Maintenance of channel: Dredging and snagging pools, approaches,
  and landings, about 2 months with Government plant and hired
  labor in period July 1944 to June 1945 ---------------------     6, 000. 00
Maintenance (operating and care):
     Operations---------------------------- ---------            16, 000. 00
     Ordinary repairs------------------------------ ---          17, 742. 05
        Total for all work--------------------------                                                        41, 423. 70
  The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 as follows:
Maintenance of channel: Dredging and snagging pools and approaches
about 312 months with Government plant and hired labor in period
  July 1945 to June 1946                           ----------                                          -      $12, 000
Maintenance (operating and care):
      Operations     ---                                 -------                           $15, 000
      Ordinary repairs -    ---                                                              9, 000
      Improvement and reconstruction                            --                 --        4, 000

        Subtotal           ----------------------------------                                --                 28, 000
        Total for all work                                              -          -              --           40,000
              RIVERS AND HARBORS-LITTLE ROCK, ARK., DISTRICT                                                           859
                                     Cost and financial summary
Cost of new work to June 30, 1944                                                                         $813, 196. 81
Cost of maintenance to June 30, 1944_----                                                -__           1 1, 497, 914. 30
       Total cost of permanent work to June 30, 1944                                    __              2, 311, 111. 11
Undistributed costs June 30, 1944_ __                                                                       14, 848. 25
       Net total cost to June 30, 1944_                                                                 2, 325, 959. 36
Plus accounts receivable June 30, 1944_                                                  __2,                   160. 08

      Gross total costs to June 30, 1944-----------------                                               2, 328, 119. 44
Minus accounts payable June 30, 1944                                                                         1, 681. 65

      Net total expenditures                                                                            2, 326, 437. 79
Unexpended balance June 30, 1944_                                                                           14, 263. 62
            Total amount appropriated to June 30, 1944------------                                      2, 340, 701. 41

   Fiscal year ending June 30            1940            1941               1942                1943              1944

C ost of n ew w ork -- - - - - - - . - - - - - - .   -- - - - - - -- - - - - -.           - .. - - - - . . .. . . . .
Cost of maintenance                    $46, 999.61     $30, 301.37   $30, 341.01             $35, 687. 26    $21, 929. 74
Total expended             -50,            808. 02      28, 797. 26        46, 875. 52       28, 329. 34          21, 355. 47

Allotted_                               34, 000.00      45, 000. 00        39, 000.00          20, 000. 00      -12,   000.00


Balance unexpended July 1, 1943_---------                ---                                                 $47, 619. 09
Deductions on account of revocation of allotment----------                                                    12, 000. 00

       Net amount to be accounted for_                                                                        35, 619. 09
Gross amount expended_--      --------                                        $48, 879. 30
Less receipts from sales-              ---- -_                        __       27, 523. 83
                                                                                                              21, 355. 47
      Balance unexpended June 30, 1944 ..                                                                     14, 263. 62
Outstanding liabilities June 30, 1944 --------------                            $1, 681. 65
Amount covered by uncompleted contracts                     ----------              685. 86
                                                                                                               2, 367. 51
      Balance available June 30, 1944_                                                                        11,896. 11
Accounts receivable June 30, 1944_                                                                             2, 160. 08
     Unobligated balance available June 30, 1944                                                              14, 056. 19
Amount allotted in July 1944 _ _.. *                                                                          25, 000. 00
            Amount available during fiscal year 1945-------------                                             39, 056. 19
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 2_-                                                                          40, 000. 00
1Includes $60,613.63 allotted during fiscal years 1937 and 1938 to White River for                    operatiohs on both
White and Upper White River projects.
  $ Exclusive of available funds.
860           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                              1944

        4. EXAMINATIONS, SURVEYS,                       AND CONTINGENCIES                       (GENERAL)

   The cost of work during the year was $28,727.76, and the expendi-
tures were $30,448.63.
   The balance unexpended June 30, 1944, $26,871.19, plus an allot-
ment of $5,000 made in July 1944, will be applied as needed during the
fiscal year 1945 to payment of expenses to be incurred under this
heading. The additional sum of $5,000 can be profitably expended
during the fiscal year ending June 30, 1946.
                                       Cost and financial summary
Cost of new work to June 30, 1944_
Cost of maintenance to June 30, 1944                                                                  $986, 996. 46
            Total cost of permanent work to June 30, 1944----                                              986, 996. 46
Minus accounts payable June 30, 1944--- -----------                                                             490. 13

Unexpended balance June 30, 1944 ____                                                                       26, 871. 19

            Total amount appropriated to June 30, 1944------------1, 013, 377. 52

      Fiscal year ending June 30          1940             1941              1942             1943              1944

Cost of new work -- - - - - - --          -- - . -. . - - -    --..
Cost of maintenance                    $151, 443. 59    $214, 750. 62   $173, 983.38       $115, 184.57        $28, 727. 76

Total expended----------------152, 803. 00               310, 064. 97       73, 992. 83     117, 348. 67         30, 448. 63
Allotted-     --------------------      255, 000. 00     388, 000. 00   -----                 4, 000. 00 ........


Balance unexpended July 1, 1943__--                            ---------                                   $57, 319. 82
Gross amount expended_-------                                         ---        $65, 536. 30
Less receipts from sales_-------                                      ---         35, 087. 67
                                                                                                            30, 448. 63

      Balance unexpended June 30, 1944_-       -   --     ___                                               26, 871. 19
Outstanding liabilities June 30, 1944                  -----------------
                                                      $490. 13
Amount covered by uncompleted contracts------------- 64. 92
                                                                                                                    555. 05

     Balance available June 30, 1944--   ---        -    ___                                                26, 316. 14
                            ---------------------------------
Amount allotted in July 1944_                                                                                5, 000. 00
            Amount available during fiscal year 1945-----------                                             31, 316. 14

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance- 1 ---            - ."    ___                                                 5, 000. 00
     I Exclusive of available funds.

5.     OTHER            NAVIGATION          PROJECTS FOR WHICH                               NO      ESTIMATES
                                           ARE SUBMITTED
                                                          For last      Cost and expenditures to
                                                           full re-           June 30, 1944                  Estimated
                    Name of project                       port
                                                          Annualsee                                          amount   re-
                                                                                                              quired to
                                                           Report       New work          Maintenance         complete


1. Arkansas River, Ark. and Okla. (above Pine
        Bluff, Ark.)_                                        1938       $614, 254. 98      $482, 168.29             (1)
2. Current River, Ark. and Mo_                               1937           17, 000. 00     119, 962. 53            (2)

     I Channels adequate for existing local commerce.Completion not contemplated.
      Existing commerce does not warrant additional expenditures.
                    FLOOD             CONTROI-LITTLE                      ROCK, ARK.,                  DISTRICT            861
Status of all investigations for navigation called for by river and harbor acts and
                                 committee resolutions

                                                                      Date trans-                                    Recommenda-
           Locality                     Authorization act             mitted to                  Document No.            tion
                                                                          Congress

Arkansas River, Ark. and               River   and    Harbor---               -----....                ......
  Okla. (under Division                 Act, Aug. 30, 1935.
  Board).
Arkansas River and tribu-              Rivers and    Harbors         . ------                    - -     ------
  taries, Arkansas, hydro-              Committee      resolu-
electric potentialities (un-           tion, Jan. 24, 1939.
der Division Board).
White River, Ark---------.-.           River   and    Harbor
                                        Act, Aug. 30, 1935.
White R iver, A rk. and M o.,          R ivers and H arbors      -    -   -   -   -   -   --   . . . . . . . . . .
  improvement for naviga-               Committee resolu-
  tion, flood control, and              tion, Jan. 24, 1939.
irrigation.
    Do ..........------------------    Commerce Commit--
                                        tee resolution, Feb.
                                        8, 1939.



     6. BLUE MOUNTAIN RESERVOIR, ARKANSAS RIVER BASIN, ARK.

   Location.-The site of the Blue Mountain Dam is located in Yell
County, Ark., on the Petit Jean River about 76 miles above its con-
fluence with the Arkansas River, and about 12 miles south of Paris,
Logan County, Ark. Blue Mountain Reservoir will extend westward
from the dam into Logan County. (See U. S. Geological Survey map
for Magazine, Ark., quadrangle, scale 1:125,000.)
   Existing project.-The plan of improvement provides for the con-
struction of an earth fill dam about 2,800 feet long at the top and about
115 feet in height above the stream bed. Outlet works will consist of
a gate-controlled, concrete-lined tunnel through the right abutment,
Sand discharges will be directed back into the Petit Jean River about
3,000 feet below the dam. -An uncontrolled saddle spillway will be
located on the left abutment about 1,200 feet downstream from the
dam axis. The reservoir, which is one unit of a comprehensive plan
for flood control and other purposes in the Arkansas River Basin, will
control approximately 46 percent of the total drainage area of the
Petit Jean River. It will provide storage capacity of about 233,000
acre-feet for flood control, and a permanent pool of about 25,000 acre-
feet for recreational purposes and as a wildlife refuge. The existing
project was authorized by the Flood Control Act approved June 28,
1938. The estimated cost of the project, revised in 1941, is $3,117,000
for construction and $583,000 for lands and damages.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies..
   Operations and results during fiscal year.-Operations having been
suspended for the duration of the present war emergency, no con-
struction work was accomplished. Land acquisition by hired labor
was practically completed. Preparation of new plans and specifica-
tions for the relocation of cemeteries and the revision of plans and
specifications for excavation of spillway and construction of embank-
ment were well advanced. Preparation of plans and specifications for
the reservoir clearing was completed. Maintenance and care of the
project in its present condition was continued throughout the year.
   The costs during the fiscal year were $164,476.94 and the expendi-
tures were $224,907.77, all for new work.
 862            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                     1944

   Condition at end of fiscal year.-Construction of the spillway and
embankment was 69 percent complete when construction was sus-
pended on November 6, 1942. The outlet works and initial clearing
of the reservoir were complete. The project as a whole is 69 percent
complete. One hundred and ninety tracts of land, or 93 percent of
the total required, have been purchased.
   The total costs to the end of The fiscal year were $2,700,098.83, and
the expenditures were $2,700,226.54, all for new work.
   Proposed operations.-The balance unexpended June 30, 1944. in-
cluding accounts receivable, $37,444.70, plus an allotment of $30,-
000, in July 1944, will be applied to new work during the fiscal year
1945 as follows:
Accounts payable June 30, 1944_--- ------------                          $1, 232. 26
New work:
     Lands, damages, and relocation of cemeteries by contract and
       hired labor, July 1944 to June 1945                                25, 000. 00
     Prepare contract plans and specifications with hired labor, July
       1944 to June 1945                                                  11, 212. 44
     Care and preservation of the project in its present condition, July
       1944 to June 1945-_----  --      ----    _------              -30,     000. 00
                Total for all work_                 ---                _--__                           __          67, 444. 70
   No additional funds can be expended for construction during the
fiscal year 1946 in view of the existing Federal policies on wartime
construction.
                                             Cost and financial summary
Cost of new work to June 30, 1944___                                                                         $2, 700, 098. 83
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944_                                                          2, 700, 098. 83
Undistributed costs June 30, 1944                                                                                     104. 02
       Net total cost to June 30, 1944 -                                                                      2, 700, 202. 85
Plus accounts receivable June 30, 1944                                                                             1, 255. 95
             Gross total costs to June 30, 1944                        --                                     2, 701, 458. 80
Minus accounts payable June 30, 1944                                                                               1, 232. 26
      Net total expenditures -                                                                                2, 700, 226. 54
Unexpended balance June 30, 1944 ___                                                                              36, 188. 75
            Total amount appropriated to June 30, 1944__                                                      2, 736, 415. 29


    Fiscal year ending June 30                    1940              1941             1942             1943                1944

Cost of new work ...       ..   $190,742.43     $565, 627. 08 $1, 428,169. 13 $330, 544.50                              $164, 476. 94
C ost ofm aintenance -- - - - -. -- - - - - . . . .. . ..- . . . .- --..- - - -.. . .                              -      .
                                                                                                                          - ----.
                                                                                                                               .
Total expended ...........----------------   218, 393. 79        465, 095. 92   1, 363, 683. 22    410, 452. 57          224, 907. 77
Allotted.--------------.........
            _10,000.                                      00   1,963, 397. 97     330, 000. 00    -250, 000. 00        -246, 982. 68
                                                                                                               $58I7.2

Balance unexpended July 1, 1943______________                                                                  $508, 079. 20
Deductions on account of revocation of allotment                                   -                            246, 982. 68
            Net amount to be accounted for_                                                                       261, 096. 52
Gross amount expended                        --                                        $228, 973. 1 5
               FLOOD CONTROL-LITTLE              ROCK,    ARK.,     DISTRICT         863
Less reimbursements collected_ __-_       __             _     $4, 065. 38
                                                                             $224, 907. 77

      Balance unexpended June 30, 1944_                                        36, 188. 75
Outstanding liabilities June 30, 1944 ........                 $1, 232. 26
Amount covered by uncompleted contracts                         1, 112. 15
                                                                                2, 344. 41I
      Balance available June 30, 1944_                                         33, 844. 34
Accounts receivable June 30, 1944      __                                       1, 255. 95
     Unobligated balance available June 30, 1944             ---               35, 100. 29
Amount allotted in July 1944 _ . . . __._.
                                      ._____.
                                         . ..  . ..            ..              30, 000. 00

        Amount available during fiscal year 1945             -65,                  100. 29

Amount (estimated) required to be appropriated for completion
of existing project 1_____                               __                     933, 600
1 Exclusive of available funds.

          7. NIMROD RESERVOIR, ARKANSAS RIVER BASIN, ARK.

   Location.-The site of the Nimrod Dam is located in Perry County,
Ark., on the Fourche La Fave River, 62.6 miles above its confluence
with the Arkansas River, and about 19 miles southeast of Danville,
Yell County, Ark. (See U. S. Geological Survey map for Hot
Springs, Ark., quadrangle, scale 1: 125,000.) Nimrod Reservoir ex-
tends westward from the dam into Yell County.
   Existing project.-The plan of improvement provides for the con-
struction of a concrete gravity type dam 986 feet long at the top and
about 97 feet in maximum height. It consists of a spillway section 198
feet long located above the present river channel, and two nonoverflow
sections contiguous thereto and extending into the abutments. Seven
gate-controlled conduits for regulating and discharging flood flows
are located through the base of the spillway section. In addition, two
smaller valve-controlled conduits are provided through the spillway
section for regulating low flows. Penstocks and provisions for future
spillway gates have been installed to provide for future power genera-
tion. The reservoir, which is one unit of a comprehensive plan for
flood control and other purposes in the Arkansas River Basin, controls
approximately 60 percent of the entire drainage area of the Fourche La
Fave River. It provides storage capacity of about 307,000 acre-feet
for flood control, and a permanent pool of about 29,000 acre-feet
for recreational purposes and as a wildlife refuge. The existing proj-
ect was authorized by the Flood Control Act approved June 28, 1938.
The estimated cost of the project, revised in 1941, is $2,580,000 for
construction and $920,000 for lands and damages.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Acquisition of land by
hired labor was completed on July 1, 1943. Erection of a barbed wire
fence, cattle guard, and gates by hired labor was completed on Sep-
tember 1, 1943.
   Operation of Nimrod Dam for flood control was governed prin-
cipally by stages on the Fourche La Fave River at Aplin, Ark.,
13.7 miles downstream from Nimrod Dam and 3.5 miles downstream
from the mouth of the South Fourche La Fave River (drainage area
864           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                       1944

242 square miles), which is the only large tributary downstream from
the dam. Inasmuch as the area between the dam and the Aplin gage
comprises 64 percent of the total uncontrolled area of the Fourche La
Fave River Basin, the stage at Aplin provides a good index of the
run-off from the entire area downstream from the dam. The results
of flood-control operation for the rises during the year which exceeded
or would have exceeded flood stage at Aplin without Nimrod Dam are
shown in the following table. The flood stage of 28 feet at Aplin
represents the channel capacity in the reach from the dam to about
Perryville, Ark. (mile 22). Downstream from Perryville the channel
capacity is dependent upon stages of the Arkansas River.

                                       Nimrod Reservoir                                  Aplin, Ark.


                                      Outflow
                                    coincident Maximum                                   Estimated
  Date of peak                      with peak    pol eleva Flood con-         Experi-    crest stage Estimated
                         Peak        flow from   tipooleleva-n
                                                          f    trol storage Exer-         without    reduction
                        inflow     uncontrolled tion 1(feet used (acre- enced crest Nimrod            in stage
                                    area (cubic above mean         feet)    stage (feet) Dam (feet)     (feet)
                                      feet per   sea level)
                                      second)

Feb.   9, 1944......     10, 900              0      347.27       23,400         17.7          29.8        12.1
Feb.             __
       18, 1944-...      15, 700          1, 300     349. 90      39, 000        20.7          31.3        10.6
Feb.   29, 1944....      15, 600          2,000      350.13       40,400         20.0          31.0        11.0
Mar.   17, 1944....      13, 200          1, 300     354.53       72, 400        19. 5         30. 5       11.0
Apr.   11, 1944-.....    11, 400          2,000      348.68       31,400         15.9          29.4        13.5
Apr.   23, 1944-.....    16,600                0     349.92       39, 100        33. 4         35.6         2.2
May    2, 1944-......    21,000                0     356. 12      85, 700        20. 6         32.9        12.3

1Conservation pool elevation 342.

   The flood of April 23, 1944, which originated almost entirely on the
South Fourche La Fave River Basin, resulted in a stage only 1.7 feet
below the maximum experienced stage at Aplin, in spite of the fact
that all flow from the area above the dam was retained until the river
had receded well below flood stage at Aplin. Under conditions with-
out Nimrod Dam this flood would have exceeded the maximum ex-
perienced stage by 0.7 foot. The flood of May 2, 1914, was the largest
during the fiscal year on the area upstream from the dam and was coin-
cident with high stages on the Arkansas River, which caused back-
water flooding on the Fourche La Fave River downstream from Perry-
ville. The operation of the reservoir effected a substantial reduction
in thecrest stage in the backwater area. The flood of May 2 was the
only flood coincident with stages above flood stage on the Arkansas
River downstream from the mouth of the Fourche La Fave River, and
a slight reduction in stage on the Arkansas River was effected by the
reservoir.
   During low-flow periods the dam was usually operated to main-
tain the conservation pool at elevation 342. However, from July
through September 1943 the reservoir was operated for mosquito con-
trol by means of a gradual draw-down of the pool from elevation 344
to elevation 342. During June 1944, a mosquito-control operation,
consisting of a weekly fluctuation of the pool, superimposed on a
gradual draw-down, was performed.
   The costs during the fiscal year were $6,516.48 for new work and
$34,131.66 for maintenance. The expenditures were $5,352.18 for new
work and $36,821.02 for maintenance.
                    FLOOD CONTROL---LITTLE                               ROCK,         ARK., DISTRICT                          865




  Condition at end of fiscal year.-All new work has been completed
with the exception of landscaping and installation of hydrological
equipment. Two hundred and sixty-six tracts of land, the total re-
quired, have been purchased. The project is now in an operating and
care status.
  The total costs to the end of the fiscal year were $3,274,419.84 for new
work and $60,364.73 for maintenance. The total expenditures were
$3,284,148.96 for new work and $60,801.39 for maintenance.
  Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $20,152.30, plus an allotment of $25,000
in July 1944, will be applied during the fiscal year 1945 as follows:
Accounts payable June 30, 1944                ------------------------------     $1, 682. 21
New work:
    Landscaping by contract during the period July 1944
      to June 1945            ---------------------------           $10,000.00
    Installation of hydrological equipment by hired
      labor_ -------------------------------------                    7, 720. 09
      Subtotal    -------------------------------------------                                                           17, 720. 09
Maintenance (operating and care):
    Operation----------------------------------                                                     $10, 000.00
    Ordinary repairs ---------------------------
    Improvement and reconstruction--- -------------
                                                                                                      5000.00
                                                                                                      5,
                                                                                                      5, 750. 00
    Emergencies ----------------------------------                                                    5000.00
                                                                                                      5,
              Subtotal_         -25,                                                                                        750. 00

           Total for all work                    -----------------------------------                                    45, 152. 30
   The additional sum of $37,000 can be profitably expended during the
fiscal year 1946 for maintenance.

                                                Cost and financial summary
Cost of new work to June 30, 1944------------------ ------                                                         $3, 274, 419. 84
Cost of maintenance to June 30, 1944 ------------------------                                                           60, 364. 73
       Total cost of permanent work to June 30, 1944-------                                                         3, 334, 784. 57
Undistributed costs June 30, 1944 _-                                                                                    11, 039. 29
       Net total cost to June 30, 1944                                                                              3, 345, 823. 86
Plus accounts receivable June 30, 1944                                                               -808.                       70
      Gross total costs to June 30, 1944                                                              -    -        3, 346, 632. 56
Minus accounts payable June 30, 1944 -                                       -           -1,                                682. 21
     Net total expenditures_ ------------------------                                                               3, 344, 950. 35
Unexpended balance June 30, 1944_. -19,                                                                                     343. 60
          Total amount appropriated to June 30, 1944--------                                                        3, 364, 293. 95


   Fiscal y ear ending June 30                      1940              1941              1942                1943            1944

Cost of new work----- ---------       .      $289, 338. 50 $1, 723, 348.49         $866, 920. 75      $319,134.36           $6, 516.48
                     ........-.-------------------------------
Cost of maintenance--------                                                                    -.       26,233.07           34,131.66
       Total cost      ........------------       289, 338:50    1, 723, 348. 49    866. 920. 75          345, 367.43       40, 648.14
Total expended----------------                    266. 606. 79   1, 632, 660.02     974,683.10            366, 646.90       42,173. 20
        .........-------.......----..
Allotted--------                              - 1,900, 000.00      800,000.00          64, 000.00          29,300.00     -195, 006. 05


          616634---45-pt. 1, vol. 1                        55
866       REPORT        OF CHIEF OF ENGINEERS,                 U.    S. ARMY,              1944

Balance unexpended July 1, 1943_                                                            $256, 522. 85
Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941        -                                                                  2, 633. 07
      Amount to be accounted for            -                                                259, 155. 92
Deductions on account of revocation of allotment                         - -           -     197, 639. 12
       Net amount to be accounted for --                                                      61, 516. 80
Gross amount expended ....                                          $65, 755. 98
Less reimbursements collected --                                     23, 582. 78
                                                                                              42, 173. 20
                                                                     ---- --
      Balance unexpended June 30, 1944_                                                       19, 343. 60
Outstanding liabilities June 30, 1944 -                               1, 682. 21
Amount covered by uncompleted contracts ..                            4. 922. 63
                                                                    __                            6, 604. 84

      Balance available June 30, 1944                                                         12, 738. 76
Accounts receivable June 30, 1944_                                                                808. 70

     Unobligated balance available June 30, 1944.                                             13, 547. 46
Amount allotted in July 1944 -      -                                                         25, 000. 00

        Amount available during fiscal year 1945                                              38, 547. 46
Amount that can be profitably expended in fiscal year
ending June 30, 1946, for maintenance 1                                       -----          37, 000. 00
1 Exclusive of available funds.

            8. ARKANSAS RIVER BASIN, LITTLE ROCK DISTRICT
   Location.-These improvements are located on tributaries of the
Arkansas River and are in the State of Arkansas. More definite
locations of the individual items are given in the following paragraph.
  Existing project. The Flood Control Act approved June 28, 1938,
approved the general comprehensive plan for flood control and other
purposes in the Arkansas River Basin, as set forth in Flood Control
Committee Document No. 1, Seventy-fifth Congress, first session, with
such modifications thereof as in the discretion of the Secretary of
WVtr and the Chief of Engineers may be advisable, and authorized
the sum of $21,000,000 for reservoirs, for the initiation and partial
accomplishment of the plan, the reservoirs to be selected and approved
by the Chief of Engineers, subject to the provision that the author-
ization shall include the Canton Reservoir on the North Canadian
River in Oklahoma, as set forth in House Document No. 569, Sev-
enty-fifth Congress, third session. The Flood Control Act approved
August 18, 1941, modified the general comprehensive plan to include
the reservoirs in the Grand (Neosho) River Basin in Oklahoma and
Missouri, and in the Verdigris River Basin in Kansas, in accordance
with the recommendations of the Chief of Engineers in House Docu-
ments Nos. 107 and 440 of the Seventy-sixth Congress, first session,
and, in addition to previous authorizations, the latter act authorized
to be appropriated the sum of $29,000,000 for the prosecution of the
comprehensive plan. The reservoirs within the Little Rock District
included in the comprehensive plan are listed below:
      Reservoir                                     Location                                      Total est-
                                                                                                  mated  cost

Blue Mountain.....      On Petit Jean River (mile 76 above the mouth) near Blue Mountain,          $3, 700, 000
                          Ark.
Nimrod__----------On Fourche La Fave River (mile 60 above the mouth) near Nimrod,                   3,500,000
                           Ark.
          FLOOD. CONTROL-LITTLE ROCK, ARK.,       DISTRICT         867

   Blue Mountain and Nimrod Reservoirs have been selected and
approved for construction by the Chief of Engineers in accordance
with the above authorization, and individual reports on the two reser-
voirs have been given in the preceding pages. All operations pre-
viously reported under the heading "Arkansas River Basin, Little
Rock District" for those two projects are now contained in the in-
dividual reports, and previous costs and expenditures have also been
transferred to those reports.
     9. CLEARWATER     RESERVOIR, WHITE RIVER BASIN,         MO.

   Location.-Clearwater Dam is located in Wayne and Reynolds
Counties, Mo., on the Black River, 257 miles above its confluence with
the White Riveir, 6 miles southwest of Piedmont, Mo., and 32 miles
northwest of Poplar Bluff, Mo. (See U. S. Geological Survey map
for Piedmont, Mo., quadrangle, scale 1: 62,500.) From the dam, the
reservoir will extend northward and westward in Reynolds County.
   Existing project.-The plan of improvement provides for an earth-
fill dam about 4,225 feet long at the top and about 143 feet in height
above the flood plain. Outlet works consisting of a gate-controlled,
concrete-lined tunnel will be located in the right abutment and will
discharge into the river below the dam. An uncontrolled, concrete-
type ogee spillway will be located on the right abutment with over-
flow discharging into Webb Creek and thence reentering the river
about 1 mile downstream from the dam. The reservoir, which is one
unit of a comprehensive plan for flood control and other purposes in
the White River Basin, will control the run-off from an area of ap-
proximately 898 square miles. It will provide storage capacity of
about 391,000 acre-feet for flood control, and a permanent pool of
about 22,000 acre,-feet for recreational purposes and as a wildlife
refuge. The existing project was authorized by the Flood Control
Act approved June 28, 1938. The estimated cost of the project, as
revised in 1941, is $7,509,000 for construction and $991,000 for lands
and damages.
   Local cooperation.-Section 2 of the Flood Control Act, approved
June 28, 1938, applies.
    Operations and results during fiscal year.-Operations having been
suspended for the duration of the present war emergency, no construc-
tion work was accomplished. Land acquision by hired labor was prac-
tically completed. Preparation of revised plans and specifications
for excavation of spillway, construction of embankment, and reloca-
tion of cemeteries was underway. Preparation of plans and specifica-
tions for the reservoir clearing was completed. Care and preserva-
tion of the project in its present condition were continued through
the year.
    The costs during the fiscal year were $176,087.66 and the expendi-
tures were $177,444.28, all for new work.
    Condition at end'of fiscal year.-Construction of the spillway and
embankment was 55 percent complete on August 7, 1942, when opera-
tions were suspended. Construction of the outlet works and initial
clearing of the reservoir are complete. The project as a whole is
55 percent complete. One hundred and fifty-nine tracts of land, or 96
percent of the total required, have been purchased.
868             REPORT OF CHIE'                        OF ENGINEERS,                      U. S. ARMY,               1944

   The total costs to the end of the fiscal year were $4,008,497.27, and
the expenditures were $4,000,571.95, all for new work.
  Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $105,844.76, plus an allotment of $27,000,
in July 1944, will be applied to new work during the fiscal year 1945, as
follows:
Accounts payable June 30, 1944_---------                                  ----       $1, 911. 57
New work:
    Lands, damages, and relocations by                  contract and hired   labor,
      July 1944 to June 1945__ -------------------------                             60, 000. 00
   Prepare contract plans and specifications with hired labor, July
      1944 to June 1945 _------------------------------------43,                         933. 19
    Care and preservation of the project in its present condition,
      July 1944 to June 1945_----------                                    --       -27, 000. 00
                                  ---------------------------------
                 Total for all work_                                                                                       132, 844. 76
  No additional funds can be expended for construction during fiscal
year 1946 in view of existing Federal policies on wartime construction.
                                              Cost and financial summary
Cost of new work to June 30, 1944 ------------------------                                                          $4, 008, 497. 27
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944---------- 4, 008, 497. 27
Undistributed costs June 30, 1944  --------------------------- -7, 170. 30
       Net total cost to June 30, 1944__-                                    --------                                4, 001, 326. 97
Plus accounts receivable June 30, 1944--                                      ----                        -__1,              156.55
      Gross total costs to June 30, 1944                              ---------------------                          4, 002, 483. 52
Minus accounts payable June 30, 1944-------------------                                                                   1, 911. 57
                           ------------------------------
      Net total expenditures_                                                                                        4, 000, 571. 95
Unexpended balance June 30, 1944_--     ----------                                                                      104, 688. 21
            Total amount appropriated to June 30, 1944                                    ------------               4, 105, 260. 16


     Fiscal year ending June 30                      1940             1941                  1942             1943                  1944

Cost of new>work---------.......-----.....      $450,515.14 $1,025,522.47           $1,679,848. 13          $602,103.82          $176,087.66
Cost of maintenance                                                                      - --.....--- ---.-.. .    .-       ..
Total expended................----------------465,      364. 95      951, 752. 44       1, 585, 909. 89     751, 101. 45          177, 444. 28
Allotted. __        ----------------.-..
                                2,000,000.00 1, 789, 060. 16                            1,970,000.00 -2, 450. 000.00


Balance unexpended July 1, 1943----------                         ---                                                $282, 132. 49
Gross amount expended_
                             -----------------
Less reimbursements collected__
                                               ___-------$178,1, 785. 75
                                                                 341. 47
                                                                                                                           177, 444. 28

      Balance unexpended June 30, 1944---------------------                                                                104, 688. 21
Outstanding liabilities June 30, 1944            1, 911. 57       --------
Amount covered by uncompleted contracts          6, 149. 59
                                                                                                                             8, 061. 16

    Balance available June 30, 1944__-.-  -------                                                             -.            96, 627. 05
Accounts receivable June 30, 1944 ----------------------------                                                               1, 156. 55
             Unobligated balance available June 30, 1944-                                          -         .- -           97, 783. 60
                                                                                                                                                 v
                FLOOD CONTROIr--LITTLE ROCK, ARK.,              DISTRICT          869
Amount allotted in 'July 1944_-------------------------------              $27, 000. 00

        Amount available during fiscal year 1945---------------            124, 783. 60

Amount (estimated) required to be appropriated for completion
of existing project 1----------------                       _ 4, 394, 700. 00
I Exclusive of available funds.


           10. NORFORK RESERVOIR, WHITE RIVER BASIN, ARK.
   Location.--The site of the Norfork Dam is located on the North
Fork River about 4.8 miles above its confluence with the White River,
near Norfork, Baxter County, Ark. (See U. S. Geological Survey
map for Mountain Home, Ark., quadrangle, scale 1: 125,000.) Nor-
fork Reservoir will extend northward from the dam across Baxter
County, Ark., into the southern part of Ozark County, Mo.
   Ewisting project.-The plan of improvement provides for construe-
tion of a     -concrete
                    gravity-type dam about 2,624 feet long at the top
and about 220 feet in maximum height. It will consist of a spillway
section 568 feet long located above the existing river channel and two
nonoverflow sections contiguous thereto and extending into the abut-
ments. Gate-controlled conduits through the base of the spillway
section will provide for regulating and discharging flood flows. Pen-
stocks and provisions for power generation include an initial installa-
tion of 2 generating units having a capacity of 35,000 kilowatts each,
but only one generating unit will be installed at this time. The reser-
voir, which is one unit of a comprehensive plan for flood control and
other purposes in the White River Basin, will control practically the
entire drainage area of the North Fork River. It will have a storage
capacity of about 732,000 acre-feet for flood control and will provide
storage of about 1,251,000 acre-feet for generation of power and
stream-flow regulation. The existing project was authorized by the
Flood Control Act approved June 28, 1938, as amended by the Flood
Control Act approved August 18, 1941. The estimated cost of the
project, revised in 1941, is 24,400,000 for construction and $3,100,000
for lands and damages.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Construction of the
project by continuing contract was continued throughout the year.
Work performed included the following: Rock excavation (all
classes), 13,138 cubic yards; concrete, 465,589 cubic yards; and rein-
forcing steel, 841,400 pounds. Land acquisition by hired labor was
completed except for one tract of land. Under separate contracts, the
following work was accomplished: Clearing of the reservoir area
was completed on September 30, 1943, a total of 24,392 acres being
cleared; relocation of roads and cemeteries was completed on March
24, 1944; fabrication of penstock gates was completed and final de-
livery to the project was made on December 7, 1943. Construction
of the powerhouse was practically completed. Work performed on
the powerhouse included the following: Rock excavation (all classes),
40,782 cubic yards; concrete, 18,230 cubic yards; and reinforcing steel,
86,033 pounds. Installation of one 13,800-volt, 35,000-kilowatt gene-
rating unit, with all accessories, was completed on June 18, 1944.
Final closure of the dam for storage of water in the reservoir was
made June 18, 1943. No releases were made until May 1, 1944, when
870      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                     1944

operation of the house service unit was started. Operational testing
of the main power unit was begun on May 8, and trial run power pro-
duction started on June 18. At the end of the trial run period on
June 29, 1944, in order to alleviate a serious power emergency in the
Southwestern Industrial Area, the unit was placed in limted com-
mercial operation. All power developed by the unit was delivered
to the Southwestern Power Administration, an agency of the Depart-
men of the Interior, for distribution. A total of 28,000 acre-feet
of -water was released from the dam during the period May 1 to
June 30, with a maximum release of about 3,400 cubic feet per second
on June 21. The reservoir filled to a maximum elevation of 529.0
on June 17, 1944, corresponding to 814,000 acre-feet of storage, and
was at elevation 528.6, corresponding to 807,000 acre-feet of storage,
at the end of the fiscal year. Only minor rises occurred on the North
Fork and upper White Rivers during the fiscal year, and storage of
floodwaters in the reservoir had only negligible effects on flood reduc-
tions downstream.
   The costs during the fiscal year were $6,001,195.22, and the expendi-
tures were $6,560,210.84, all for new work.
   Condition at end of fiscal year.-Construction of the dam is 97
percent complete. Four hundred and fifty-five tracts of land, or
practically all of the land required, have been purchased. Installa-
tions for power generation include four penstocks in the dam, two of
which enter the existing powerhouse, which is designed for future
expansion riverward to provide for the maximum installation of four
generating units. The powerhouse contains one 35,000-kilowatt gen-
erating unit, with provision made for the installation of the second
unit, manufacture and installation of which have been deferred.
   The total costs to the end of t~he fiscal year were $22,330,323.74,
and the expenditures were $21,542,833.90, all for new work.
   Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $3,145,399.01, plus an allotment of $60,000
in July 1944, will be applied during the fiscal year 1945 as follows:
Accounts payable June 30, 1944----------------------------              $819, 410. 34
New work:
    Complete construction of dam and powerhouse
      by continuing contract, July 1944 to
      November 1944 _                               $2, 195, 000. 00
    Preparation of contract plans and specifica-
      tions by hired labor,' July 1944 to June 1945      90, 988. 67
    Lands, damages, and relocations by hired
      labor, July 1944 to June 1945------------          40, 000. 00
        Subtotal    -------------------------------------- 2, 325, 988. 67
Maintenance (operating and care):
    Operations------------------------------     $50, 000. 00
    Ordinary repairs              ---------        2, 500.00
    Improvement and reconstruction-------- --      2, 500. 00
   Emergencies------------------------- ---        5, 000.00
       Subtotal_----        ------------------                            60, 000. 00
       Total for all work---------------------------------             3, 205, 399. 01
   The amount of $136,000 can be expended for maintenance during
fiscal year 1946.
                      FLOOD CONTROL-LITTLE ROCK, ARK., DISTRICT                                                                     871
                                                     Cost and financial summary
Cost of new work to June 30, 1944_                                                                -_             $22, 330, 323. 74
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944 _---                                                            22, 330, 323. 74
Undistributed costs June 30, 1944_--------------------------                                                              6, 740. 38
       Net total cost to June 30, 1944- -                    22, 337, 064. 12
Plus accounts receivable June 30, 1944----------------------      25, 180. 12

      Gross total costs to June 30, 1944----------------                                                            22, 362, 244. 24
Minus accounts payable June 30, 1944_                                                                                   819, 410. 34

      Net total expenditures---: ___21,                     542, 833. 90
Unexpended balance June 30, 1944-------------------------3, 120, 218. 89

            Total amount appropriated to June 30, 1944--------                                                      24, 663, 052. 79

   Fiscal year ending June 30                            1940             1941             1942              1943               1944

Cost of new work                      --              $261, 744. 36 $1, 456, 389. 47 $5, 322, 366. 55 $9, 253, 272. 41 $6,001, 195. 22
C ost of m aintenance ..      . . . . .             . . . . . . . .. . . . . .- .           -- - - - . . .      -.-- - -. . . . .
Total expended                                 --      266, 923.26   1,035, 272. 54   4, 918, 187. 46   8, 732, 325. 79     6, 560, 210. 84
Allotted-    -   -    -   -   -   -        -        1,449, 850. 00   3, 300, 000.00 15, 900, 000. 00    6, 415, 000.00      2, 836, 297. 21


Balance unexpended July 1, 1943_                                                                                $12, 516, 726. 94
Deductions on account of revocation of allotment----------                                                ---     2,836, 297. 21

       Net amount to be accounted for__                                                                             9, 680, 429. 73
Gross amount expended-                                                                                              6, 560, 210. 84
      Balance unexpended June 30, 1944-------------------                                                           3, 120, 218. 89
Outstanding liabilities June 30, 1944-----------  $819, 410. 34
Amount covered by uncompleted contracts          2, 163, 468. 67
                                                                                                                    2, 982, 879. 01
      Balance available June 30, 1944 ----------------------                                                              137, 339. 88
Accounts receivable June 30, 1944_--      ----------                                                                       25, 180. 12

     Unobligated balance available June 30, 1944 -----------                                                              162, 520. 00
Amount allotted in July 1944_------                                                                                        60, 000. 00

            Amount available during fiscal year 1945_-                                                                    222, 520. 00
Amount (estimated) required to be appropriated for completion
  of existing project 1 -----------------------------------                                                         2, 844, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1---------------------------                                                             136, 000. 00
1Exclusive of available funds.

                     11. WHITE RIVER BASIN, LITTLE ROCK DISTRICT

  Location.-These improvements are located on tributaries of the
White River and are in the States of Arkansas and Missouri. More
definite locations of the individual items are given in the following
paragraph.
  Existing project.-The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood controland other
purposes in the White River Basin, as set forth in Flood Control
Committee Document No. 1, Seventy-fifth Congress, first session, with
such modifications thereof as in the descretion of the Secretary of
872         REPORT OF CHIEF OF ENGINEERS,                         U. S. ARMY,         1944


War and the Chief of Engineers may be advisable, and authorized
the sum of $25,000,000 for reservoirs, for the initiation and partial
accomplishment of the plan, the reservoirs to be selected and approved
by the Chief of Engineers. The Flood Control Act approved August
18, 1941, authorized to be appropriated the sum of $24,000,000, in addi-
tion to previous authorizations, for the prosecution of the comprehen-
sive plan approved in the Act of June 28, 1938, for the White River
Basin in Missouri and Arkansas, including the projects for flood
control and other purposes recommended by the Chief of Engineers
in House Document No. 917, Seventy-sixth Congress, third session,
and the modifications in the Norfork Reservoir project recommended
by the Chief of Engineers in House Document No. 290, Seventy-
seventh Congress, first session. The reservoirs included in the com-
prehensive plan are listed below:

                                                                                                Total
   Reservoir                                       Location                                   estimated
                                                                                                 cost

Clearwater .... On Black River (mile 257above the mouth) near Clearwater, Mo ..                $8, 500,000
Water Valley....    On Eleven Point River (mile 13 above the mouth) near Water Valley, Ark
Bell Foley ...-.
Norfork 1 __-_On
                    On Strawberry River (mile 24 above the mouth) near Bell Foley, Ark  --    7,600,000
                                                                                              5, 363, 000
                       North Fork River (mile 4.8 above the mouth) near Norfork, Ark .... 27, 500, 000
Lone Rock-.....     On Buffalo River (mile 3.6 above the mouth) near Lone Rock, Ark_: _.     11, 422, 000
Greers Ferry ...-   On Little Red River (mile 77 above the mouth) near Greers Ferry, Ark___   7,179,000
Bull Shoals ....    On White River (mile 420 above the mouth) near Amos, Ark---      _ __ _. 47,000, 000
                                                                                     37, 000,000
Table Rock..... On White River (mile 528 above the mouth) near Branson, Mo----------...........

  1See individual report for details of project.

   Local cooperation.-Section2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.--Reservoir mapping,
stream gaging, field surveys, foundation explorations, compilation of
land ownership data and studies in connection with the development
of the general comprehensive plan were continued with hired labor
throughout the year.
   The costs during the fiscal year were $224,827.96 and the expendi-
tures were $204,543.19, all for new work.
   Condition at end of fiscal year.-Surveys, studies, and detailed
plans were well advanced for development of the general comprehen-
sive plan for flood control and other purposes in the White River
Basin. The construction progress of projects selected for construc-
tion under the authorization is given in individual reports.
   The total costs to the end of the fiscal year were $1,035,529.08, and
the total expenditures were $1,027,833.35, all for new work.
   Proposed operations.-The balance unexpended June 30, 1944, in-
cluding accounts receivable, $577,429.80, plus an allotment of $250,-
000, in July 1944, will be applied to accounts payable, in the amount of
$10,972.75, and to the continuation of foundation investigations, field
surveys, and the preparation of detailed plans and specifications dur-
ing the fiscal year 1945.
  SThe additional sum of $700,000 can be profitably expended during
the fiscal year 1946 to continue the development of the comprehen-
sive plan for flood control in the White River Basin.
                      FLOOD CONTROI,-LITTLE ROCK, ARK.,                                                   DISTRICT                        873
                                            Cost and financial summary
    Cost of new work to June 30, 1944_------------------------                                                           1,035, 529. 08
    Cost of maintenance to June 30, 1944 _                                                                                                -
          Total cost of permanent work to June 30, 1944-                                                                 1, 035, 529. 08
    Undistributed costs June 30, 1944 ---------------------------                                                             2, 719. 92
           Net total cost to June 30, 1944                                                                               1, 038, 249. 00
    Plus accounts receivable June 30, 1944                                                                                       557. 10
          Gross total costs to June 30, 1944--------------------1,038, 806. 10
-   Minus accounts payable June 30, 1944------------------------    10, 972. 75
          Net total expenditures _-  -                                                                                  1,027, 833. 35
    Unexpended balance June 30, 1944                                                                                      576 872. 70
               Total amount appropriated to June 30, 1944------------1,                                                      604, 706. 05

       Fiscal year ending June 30                1940                    1941                1942                1943                 1944

    Cost of new work-_- ------              $234, 203.12            $160, 373.13       $212, 960.84        $174, 001.05          $224, 827. 96
    Cost of m aintenance .- - - - - .-- - -             - .. . . . . . . . ..                  - --..
                                                                                               --  . .     .     . .     . . .   .     . .
    Total expended                              230, 935. 20
                            ........----------------                  161,885. 58          217, 377. 61        184, 957.13           204, 543. 19
    Allotted   ----------------------         554, 025.00- --                          625, 000. 00            250,000.00            141,006.05


    Balance unexpended July 1, 1943               ----------                                                             $640, 409. 84
    Amount allotted from War Department Civil
      Appropriation Act approved May 23, 1941--           $107, 006. 05
    Amount allotted from War Department Civil
      Appropriation Act approved Apr. 28, 1942 ....-         34, 000. 00
                                                                                                                             141, 006. 05
           Amount to be accounted for--------------------------                                                              781, 415. 89
    Gross amount expended_------                 ---   211, 548. 24
    Less receipts from sales -------------------------   7, 005. 05
                                                                                                                             204, 543. 19
          Balance unexpended June 30, 1944 ---------------------                                                             576, 872. 70
    Outstanding liabilities June 30, 1944--------------  10, 972. 75
    Amount covered by uncompleted contracts             329, 100. 44            --------
                                                                                                                             340, 073. 19
          Balance available June 30, 1944 -----------------------                                                            236, 799. 51
    Accounts receivable June 30, 1944 ----------------------------                                                                557. 10
         Uno bligated balance available June 30, 1944
    Amount allotted in July 1944_---
                                                                                            ------------                   237, 356. 61
                                          ---------                                                                     -250, 000. 00
               Amount available during fiscal year 1945                              ---------------                         487, 356. 61
    Amount that can be profitably expended in fiscal year ending
       June 30, 1946 for new work                  1           --------------                                                700, 000. 00
      1Exclusive of available funds.

    12. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
             FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

       The Flood Control Act approved August 18, 1941, authorized the
    allotment from flood-control appropriations of not to exceed $1,000,000
    for any one fiscal year to be expended in rescue work, or in the repair
    or maintenance of any flood-control work threatened or destroyed by
874       REPORT OF, CHIEF OF ENGINEERS, U.                                       S. ARMY,           1944

flood. Pursuant to this act, funds in the amount of $14,062.85 were
allotted to the Little Rock district in June 1943, and the amount of
$20,000 was allotted during the fiscal year 1944 for emergency repair
work.
   Emergency repair operations were accomplished during the fiscal
year, the principal operation consisting of the protection of ex-
isting structures in the vicinity of North Little Rock, Ark. The
Arkansas State Highway Commission contributed funds in the
amount of $55,500 toward this work. The costs during the fiscal
year were $33,833.79 and expenditures were $32,108.41.
   In addition to the above, funds were allotted under the provisions
of section 9 of the Flood Control Act approved June 15, 1936. for
emergency flood-control work in the Little Rock district. For fur-
ther information, see Mississippi River Commission report, emergency
work on tributaries of the Mississippi River.
                                  Cost and financial summary
                                    UNITED       STATES FUNDS
Cost of new work to June 30, 1944___
Cost of maintenance to June 30, 1944-------------------------                                          $33, 833. 79
      Total cost of permanent work to June 30, 1944-------------                                            33, 833. 79
Minus accounts payable June 30, 1944_-     --------                                                          1,725. 38

      Net total expenditures --------------------------------                                               32, 108.41
Unexpended balance June 30, 1944 -----------------------------                                               1, 954. 44
        Total amount appropriated to June 30, 1944---------------34,                                           062. 85

   Fiscal year ending June 30        1940              1941                   1942            1943             1944

Cost of new work----------------            ---------------------------------------------
Cost of maintenance-----------------        -----------------------------------------                          $33,833.79
                           ---    -------------- ---------------------------
Total expended----------------.................-.                                                              32, 108.41
                   ........------------
Allotted...-----------------------...........           --------------
                                     ...........------...                                   $14, 062. 85       20,000.00


Balance unexpended July 1, 1943_----------              ----                                                14, 062. 85
Amount allotted from War Department Civil Appropriation Act ap-
  proved June 11, 1938---------------_                       -                                              20, 000. 00
       Amount to be accounted for---------------------                                                      34, 062. 85
Gross amount expended --------------------------      $36, 971. 36
Less receipts from sales---------.      -_-----4,          862. 95
                                                                                                            32, 108. 41
      Balance unexpended June 30, 1944----------------                                                       1,954. 44
Outstanding liabilities June 30, 1944----------------------------                                            1, 645. 90
        Unobligated balance available June 30, 1944                          ---------------                    308. 54
                                       CONTRIBUTED FUNDS

Cost of new work to June 30, 1944_
Cost of maintenance to June 30, 1944_-------                                                ---            $55, 004. 91
      Total cost of permanent work to June 30, 1944-------------                                            55, 004. 91
Minus accounts payable June 30, 1944---------             ---                                               17, 109. 18
      Net total expenditures ------------------------------                                                 37, 895. 73
Unexpended balance June 30, 1944                                                                            17, 604. 27
         Total amount coitributed to June 30, 1944-                                                         55, 500. 00
                   FLOOD        CONTROI,-LITTLE                     ROCK,        ARK.,      DISTRICT              875

   Fiscal year ending June 30                  1940             1941                1942           1943        1944

Cost of new work .----------------------------------------------------------------------
Cost of maintenance------------
                   ...........-----........................-----------------------------------------          $55,004. 91

Total expended-------------------------........................-------------------------------------           37, 895. 73

Contributed---------------------.....................-.........-----------------------------------------.      55, 500.00


Amount contributed under authorizing act approved July 19, 1937_ $55, 500. 00
Gross amount expended--_ -----------------------       $38, 701. 97
Less receipts from sales .----------------------------      806. 24
                                                                    37, 895. 73
      Balance unexpended June 30, 1944--      ....                              -           _____           17, 604. 27
Outstanding liabilities June 30, 1944----------------_                                 -$17,     188. 66
Amount covered by uncompleted contracts                             -----------                  191. 46
                                                                                                            17, 380. 12

           Unobligated balance available June 30, 1944--- ------------                                         224. 15

13. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF
    PUBLIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods
which occurred in the spring of 1943 and again in the spring of 1944,
Congress, in the act approved July 12, 1943, Public No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public No.
318, Seventy-eighth Congress, authorized the amounts of $10,000,000
and $12,000,000, respectively, to be appropriated as emergency funds
to be expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See p. 9 for details.)
As a result of the disastrous floods of May-June 1943 on the White
and Arkansas Rivers and the consequent heavy demands for emer-
gency repair work on flood-control structures, funds in the amount
of $750,000 were allotted to the Little Rock district for emergency
repairs pursuant to the act approved July 12, 1943.
   During the period August 1943 to June 1944, 1,898,484 cubic yards
of earth embankment were constructed by contract in 14 levee districts,
and 358,610 cubic yards of earth embankment were constructed with
Government plant and hired labor in 12 levee districts. Numerous
drainage structures were constructed or repaired by contract and
hired labor. All work was completed at the end of the fiscal year
with the exception of rain-wash repairs to levees to be performed with
Government plant and hired labor. The costs during the fiscal year
were $727,635.03, and the expenditures were $725,193.28, all for new
work.
   The balance unexpended June 30, 1944 (including accounts receiv-
able), $24,862.04, plus an allotment of $151,000 in July 1944 for emer-
gency repairs pursuant to the act of May 29, 1944, will be applied
during the fiscal year 1945 to the payment of outstanding liabilities
and other expenses to be incurred under this heading.
  In addition, funds were allotted under the provisions of section 9
of the Flood Control Act approved June 15, 1936, for emergency flood-
876         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                 1944

control work in the Little Rock district. For further information,
see Mississippi River Commission report, emergency work on tribu-
taries of the Mississippi River.
                                     Cost and financial summary
Cost of new work to June 30, 1944-
Cost of maintenance to June 30, 1944_                                                                     $727,635. 03
       Total cost of permanent work to June 30, 1944-
Undistributed costs June 30, 1944
                                                                                          -                727, 635. 03
                                                                                                                   203. 23

       Net total cost to June 30, 1944__                                                                   727, 838. 26
Plus accounts receivable June 30, 1944_                                                                          55. 32

      Gross total costs to June 30, 1944_                                                                  727, 893. 58
Minus accounts payable June 30, 1944                                                                         2, 700. 30
      Net total expenditures______                                                                         725, 193. 28
Unexpended balance June 30, 1944__                                                                          24, 806. 72
         Total amount appropriated to June 30, 1944                                                        750, 000. 00

   Fiscal year ending June 30            1940            1941            1942                1943                   1944


Cost of
Cost      new work.
          mnenancek----------------------
Cost ofof maintenance
                    .......               --------------
                            ___................ ..       -------------- ------------
                                                         . ..... ........     ...                                $727,635.03--
                                                                                                                 $727, 63503
Total, expended..-.-.-- ......-.- ..---
         Total epended----------------------                                                                      725, 193.28
                                             --------------        --------------         ---------
                                                                                                      _____..
                                                                                                                  75132
Allotted.-----......-........--------------.---------------------------                                            750,000.00


Amount allotted from Second Deficiency Appropriation Act ap-
  proved July 12, 1943 -----------------------------------               $750, 000. 00
Gross amount expended--- --------                          $759, 002. 14
Less receipts from sales-------..----.                       33, 808. 86
                                                                          725, 193. 28
       Balance unexpended June 30, 1944 ----------------------                                                  24, 806. 72
Outstanding liabilities June 30, 1944_---- --         2, 700. 30
Amount covered by uncompleted contracts                       ---------
                                                     13, 925. 79
                                                                                                                16, 626. 09

      Balance available June 30, 1944_-     -----        -----                                                   8, 180. 63
Accounts receivable June 30, 1944 -----------------------------.                                                     55. 32
     Unobligated balance available June 30, 1944 --------------                                               8, 235. 95
Amount allotted in July 1944--
                           __       ------------                                                            151, 000. 00
          Amount available during fiscal year 1945-----------------                                         159, 235. 95

14. PRELIMINARY                EXAMINATIONS, SURVEYS,                               AND    CONTINGENCIES
                                  FOR FLOOD CONTROL

   The costs during the fiscal year were $381,010.25 and the expendi-
tures were $400,271.79. The balance unexpended June 30, 1944, in-
cluding accounts receivable, $50,390.49, plus an allotment of $90,000,
will be applied as needed during the fiscal year 1945 to payment of
expenses to be incurred under this heading.
  The additional sum of $150,000 can be profitably expended during
the fiscal year 1946.
                     FLOOD CONTROL---LITTLE                     ROCK, ARK., DISTRICT                                   877
                                    Cost and financial summary
Cost of new work to June 30, 1944   ---------------------------------
Cost of maintenance to June 30, 1944----------------------                                               $1,.529, 702. 92
      Total cost of permanent work to June 30, 1944----------                                             1, 529, 702. 92
Undistributed costs June 30, 1944------- -------------------                                                       62. 66

       Net total cost to June 30, 1944 ---------------------- 1,529, 765. 58
Plus accounts receivable June 30, 1944----- -----------------     1, 691. 29

      Gross total costs to June 30, 1944                    --------------------
                                                             1, 531, 456. 87
Minus accounts payable June 30, 1944 -----------------------      1, 227. 53

      Net total expenditures---------------------- ---                                                    1,530, 229. 34
Unexpended balance June 30, 1944_--------              ---                                                   48, 699. 20

            Total amount appropriated to June 30, 1944--- --------                                        1, 578, 928. 54


    Fiscal year ending June 30               1940           1941             1942                 1943              1944

C ost of new w ork .-                .-         - --.       - --.-..          ---
                                                                  . . . . . . . . . . ..--                          -----
Cost of maintenance -----------           $265, 898. 53   $485,572.13 $259, 028.21 $9,003.10                      $381, 010. 25

Total expended        ----------------     256, 854. 61   386, 310. 65     362, 834.46           18, 500. 06       400, 271.79

Allotted ----------------------            319, 000.00    400,000.00      -10,000.00         200, 000.00           200,000.00



Balance unexpended July 1, 1943 _--                                                                        $248, 970. 99
Amount allotted from War Department Civil Appropriation Act
  approved April 28, 1942 __               __200,                                                                   000. 00
       Amount to be accounted for--   ------                                             _448,                      970. 99
Gross amount expended _          --          -                                $407, 155. 95
Less reimbursements collected-----------------                                   6, 884. 16
                                                                                                 -             400, 271. 79
      Balance unexpended June 30, 1944----------------                                                          48,699. 20
Outstanding liabilities June 30, 1944- -----           __1,                                                        227, 53
      Balance available June 30, 1944--                            ----                  __47,                     471. 67
Accounts receivable June 30, 1944_-----"--                                               -__                     1,691. 29
     Unobligated balance available June 30, 1944                            ------------                        49, 162. 96
Amount allotted in July 1944_- --------                                                -__                      90, 000.00
            Amount available during fiscal year 1945                     ----------                            139, 162. 96
Amount that can be profitably expended in fiscal year ending
June 30 1946, for maintenance_-    ------            -__                                                      150, 000.00
878              REPORT OF                  CHIEF OF ENGINEERS,                                        U.          S.       ARMY,                  1944


15. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                                      For last full                 Cost and expenditures to                                 Estimated
                                                                       report see                         June 30, 1944                                      amount re-
                        Name of project                                 Annual                                                                                qud t
                                                                        Report                                                                               quired to
                                                                         for-                      New work                     Maintenance                   complete


1.   West of Mrrilton, Ark.1--------------------                              1937        ------------------------                                           $603,000.00
2.   Clarksville, Art.1                                                       1937                                                                             70, 000. 00
3.   Little Rock, Arkansas River, Ark.2                                       1939                   $2, 304. 89- ..........--                                132, 195.11
4.   North Little Rock, Arkansas River, Ark .                                 1943                 501, 639. 08--------------                                    (3) (6)
5.   Near Dardanelle, Arkansas River, Ark. ....                               1939                         475. 89_ _------                                      113, 774.11
6.   East Poplar Bluff and Poplar Bluff, Mo.2 _                               1937-              -
                                                                                             - ........................                                           546, 800.00
7.   Little Black River, in Butler and Ripley
        Counties, Mo., and in Clay and Randolph
        Counties Ark.2---------------              ____--                      1937        ---         _____-----------                                           754, 900.00
8.   Big Bottom, Ark. .......             ............-----------------       1937                    --                                                         128, 700.00
9.   Faulkner County, Arkansas River, Ark ..                                  1941                     99, 510. 65 -(3)
10.   From North Little Rock to Gillett, Ark.
        (above Plum Bayou)_                                                    1941                    840, 914. 32- .-------                                       (3)
11.   Black River, Poplar Bluff, Mo., to Knobel,
        Ark --                                                                 1941                    445, 584.54 -- ___--                                4 1,   196, 390.00
12.   Skaggs Ferry, Black River, East of Pocahon-
        tas, Ark                                                               1941                     81, 023. 32-----.                          -----            (3)
13.   Newport, White River, Ark-----------------                               1941                    314, 276. 28 -----                                    -(3)
14.   Village Creek, White River, and Mayberry
        Districts, Ark_                                                        1941                    532, 310. 17                                                 (2)
15.   Crawford County levee district, Arkansas
        River, Ark                                                             1941-             - .....                -            ..........
                                                                                                                                 --.....                          284, 000. 00
16.   Little Rock to Pine Bluff, Arkansas River,
        Ark ......................                                             1941        ----------------------------                                           641,000.00
17.   Snagging and clearing under authority of sec.
        2 of the Flood Control Act approved Aug.
        28, 1937, as amended__------------                   _----1941                                      2, 823. 73----------------(3)

  1Awaiting local cooperation.
  SConditions of local cooperation not likely to be fulfilled.
  3 Completed.
  4 For Missouri portion (Arkansas portion completed).
  5 Conditions of local cooperation not likely to be fulfilled for the Missouri portion.
  8 Balance unexpended $13,360.92.


           16. PLANT ALLOTMENT, LITTLE ROCK, ARK., DISTRICT
                                                  Cost and financial summary
Undistributed costs June 30, 1944__                                        -           -          --               -        -                     -- $127, 485. 94
Net total cost to June 30, 1944_  ---    ----       ---                                                                                            -- 127, 485. 94
Plus accounts receivable June 30, 1944-----------------------                                                                                         225, 779. 36
      Gross total costs to June 30, 1944---------------------                                                                                           98, 293. 42
Minus accounts payable June 30, 1944__       ------      _                                                                                             122, 945. 39
      Net total expenditures-_ -------                                                                                                               -24, 651. 97
Unexpended balance June 30, 1944-      --                                       ------                                           _                    231, 651. 97
             Total amount appropriated to June 30, 1944------------                                                                                   207, 000. 00


      Fiscal year ending June 30                     1940                  1941                             1942                       1943                       1944


Total expended.. ...                          _      _        _-                 --                $202, 325. 56            -$366,834. 53                           $139, 857

Allotted ...                          ---                                                          307,000.00                   --          -                      -100,000



Balance unexpended July 1, 1943__            ----------                                                                                             $471, 508. 97
Deductions on account of revocation of allotment                                                                                                     100, 000. 00

       Net amount to be accounted for                                                                                                                 371, 508. 97
Gross amount expended                                                                                   2, 190. 902. 22
                  FLOOD          CONTROL-LITTLE                       ROCK, ARK.,                        DISTRICT                   879
Less:
     Reimbursements
       collected-_ -       -       -                 $2, 045, 961. 05
     Receipts from sales ---------                         5, 084. 17
                                                                              -$2,       051, 045. 22
                                                                                                                          $139, 857. 00

      Balance unexpended June 30, 1944---------------------                                                                231, 651. 97
Outstanding liabilities June 30, 1944                     -----------
                                                          $122, 945. 39
Amount covered by uncompleted contracts                      18, 477. 00
                                                                                                                           141, 422. 39

      Balance available June 30, 1944 ------------------------                                                              90, 229. 58
Accounts receivable June 30, 1944_--
                                   ---------                 -                                                             225, 779. 36

          Unobligated balance available June 30,1944                             ------------                              316, 008. 94

Status of all investigations for flood control called for by flood control acts and corn:m
                                    mittee resolutions

                                                                    Date trans-                                             Recommen.
           Locality                     Authorization act           mitted to                 Document No.                    dation
                                                                     Congress

Arkansas River and tribu-          Flood Control Com-               Feb. 17, 1944         H. 447, 78th Cong.,              Favorable.
  taries (local flood protec-        mittee resolution,                                     2d sess.
  tion along the main stem,          July 2, 1943.
  from Pine Bluff, Ark., to
  Great Bend, Kans.).
Arkansas River and tribu-          Rivers and Harbors
  taries, Ark., hydroelectric        Committee resolu-
  potentialities (under Di-          tion, Jan. 24, 1939.
  vision Board).
Arkansas River, Ark., Con-         Flood Control Com-               Oct. 18, 1943         H. 341, 78th Cong.,                 Do.
  way County levee dis-              mittee resolution,                                    1stsess.
  tricts Nos. 1 and 8.               May 14, 1941.
Arkansas River, Ark., Con-         Flood Control Com-                  do ..... --- do .......--
                                                                    ....                                                      Do.
  way County levee dis-              mittee resolution,
  tricts Nos. 2 and 6.               Nov. 12, 1941.
Arkansas River and tribu-          Flood Control Com-              Feb. 17,1944           H. 447, 78th Cong.,                 Do.
  taries, flood control in Cy-       mittee resolution,                                    2d sess.
  press drainage district,           Apr. 23, 1942.
  Perry and Conway Coun-
  ties, Ark.
Big Piney Creek, Johnson           Flood Control Com-
  County, Ark.                       mittee resolution,
                                     June 21, 1944.
Black River, Mo. and Ark-          Flood Control Act,
                                     June 28, 1938.
Fourche Bayou, Ark ......          Flood Control Com-              Feb. 17,1944           H. 447, 78th Cong.,                 Do.
                                     mittee resolution,                                    2d sess.
                                     Nov. 19, 1940.
Galla Creek, Pope County,          Flood Control Com-                                    _        ..........----
Ark.                                mittee resolution,
                                     June 21, 1944.
Illinois Bayou, Pope Coun-         ..    do --.. . . ..   . . .
   ty, Ark.
Little Red River, Ark, con-        Flood Control Com-
   struction of multiple-pur-       mittee resolution,                                   . .. . . ... . . . . .    -- -
   pose reservoir in the vicini-    Apr. 5, 1940.
   ty of Greers Ferry, Ark.
Palarm Creek in Pulaski            Flood Control Com-                                    .................--



   and Faulkner Counties,           mittee resolution,
   Ark.                             June 21, 1944.
Point Remove Creek, Ark-           Flood Control Act,
                                    June 22, 1936.
                                                                  ---------------            ....................
White River, Ark. and Mo.,
improvement for naviga-
                                   Rivers and Harbors
                                     Committee resolu-
                                                                  ---------------
tion, flood control, and           tion, Jan. 24, 1939.                                 ....................
irrigation.
    Do .---------------....        Commerce Committee              -----------       -

                                    resolution, Feb. 8,                                  ....................
                                        1939.
White River, Mo. and Ark.,
flood control on west bank
                                   Flood Control Com-
                                     mittee resolution,
                                                                  ---------------
                                                                  ----------------
between Augusta and                 Mar. 20, 1944.
Clarendon, Ark., and up-
stream from Augusta.
880     REPORT OF CHIEF OF ENGINEERS,                  U. S. ARMY,     1944

IMPROVEMENT            OF RIVERS AND HARBORS                              IN THE
                      TULSA, OKLA., DISTRICT
  This district comprises southern Kansas, small portions of south-
western Missouri and western Arkansas, northern Oklahoma, the
northern portion of the Texas Panhandle, and small portions of north-
eastern New Mexico and southeastern Colorado, embraced in the
drainage basin of the Arkansas River and tributaries above the mouth
of the Poteau River, inclusive, and below the mouth of Walnut Creek,
near Great Bend, Kans., exclusive of that portion of the watershed
of the South Canadian River and its tributaries west of the Texas-
New Mexico State line.
  District engineer: Col. F. J. Wilson, Corps of Engineers.
  Division engineer: Col. R. R. Neyland, Corps of Engineers, to June
$, 1944. Col. F. J. Wilson, Corps of Engineers, division engineer
from that date to June 14, 1944. Brig. Gen. E. H. Marks, United
States Army, division engineer since that date.
                                    IMPROVEMENTS

              Navigation                            Flood control-Continued
                                      Page                                         Page
1. Examinations, surveys, and               10. Tulsa and West Tulsa, Ar-
     contingencies (general)---       880          kansas Rivei, Okla .....        894
2. Other navigation projects for            11. Markham Ferry Reservoir,
     which no estimates are                        Arkansas    River     Basin,
     submitted_                       881          Okla- --      _- - - - - -      897
                                             12. Fort Gibson Reservoir, Ar-
                                                   kansas River Basin, Okla __     898
             Flood control                   13. Arkansas River Basin, Tulsa
                                                   District_                       900°
3. Hutchinson, Arkansas River,              14. Emergency        flood-conti ol
      Kans_      .                    882          work under authority of
4. Wichita and Valley Center,                     the Flood Coritrol Act ap-
      Arkansas River, Kans '_-__      883          proved August 18, 1941___       9034
5. Fort Supply Reservoir, North             15. Emergency flood-control
      Canadian River, Okla ---        885          work under authority of
6. Canton Reservoir, Arkansas                     Public Laws Nos. 138 and
      River Basin, Okla ...           887          318, Seventy-eighth Con-
                                                   gress                           904
7. Cherokee, Salt Fork of Ar-               16. Preliminary    examinations,
      kansas River, Okla ....         889          surveys, and contingencies
8. Great Salt Plains Reservoir,                   for flood control__      _      905
      Salt Fork of Arkansas                  17. Other flood-control projects
      River, Okla__                   891          for which no estimates are
9. Hulah    Reservoir,    Caney                   submitted_                      907
      River, Okla_                    893    18. Plant allotment_-_                907

   1. EXAMINATIONS, SURVEYS, AND CONTINGENCIES                       (GENERAL)

   The cost of work during the year was $3,767.17; the expenditures
were $5,170.71. The balance unexpended including accounts receiv-
able at the end of the fiscal year, $2,641.51, plus the sum of $3,200
allotted in July 1944, a total of $5,841.51, will be applied as needed
during the fiscal year 1945 to payment of expenses to be incurred
under this heading. The additional sum of $3,500 can be profitably
expended during the fiscal year ending June 30, 1946.
                         RIVERS AND HARBORS----TULSA,                                    OKLA., DISTRICT                               881

                                                    Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_------                                                              ---            $135, 626.42
      Total cost of permanent work to June 30, 1944-
Undistributed costs June 30, 1944 -----------------------------
                                                                135, 626. 42
                                                                     855. 00
                                                                                                          --
       Net total cost to June 30, 1944__----------                                                                          136, 481. 42
Plus accounts receivable June 30, 1944_--                                                ---------                               800. 00

      Gross total costs to June 30, 1944-- --------           137, 281. 42:
Minus accounts payable June 30, 1944-------------------------      839. 09

      Net total expenditures -------------------------------                                                                136, 442. 33
Unexpended balance June 30, 1944                   -1,                                                                           841. 51
              Total amount appropriated to June 30, 1944                                   --------              -          138, 283. 84


     Fiscal year ending June 30                          1940            1941               1942               1943              1944

Cost of new work .--------------.                           -   --.-.    - --. . .       -. .  .     -
                                                                                                     ..-. .. . .              .. .
Cost of maintenance ----                        -      $11,252. 75      $9,051.72         $4,095. 46      $675. 48              $3, 767. 17

Total expended. -----------------                       11,082. 49       8,616.16          4, 575. 00             214. 13        5,170. 71

Allotted.................----------------------..      20, 000.00        4,500.00                              7;000.00      ........



Balance unexpended July 1, 1943_-                                          _----------$7,                                        012. 22
Gross amount expended_ ____----------$5,                                                                  183. 94
Less reimbursements collected___---------                                                                  13. 23
                                                                                                                              5, 170. 71
      Balance unexpended June 30, 1944_--                                                                ____                 1,841. 51
Outstanding liabilities June 30, 1944                                -----------------                   $839. 09
Amount covered by uncompleted contracts                                     -----------                   583. 75
                                                                                                                              1, 422. 84
      Balance available June 30, 1944------------------                                                    ------               418.67
Accounts receivable June 30, 1944_---------                                                                    ----             800. 00
     Unobligated balance available June 30, 1944 --------                                                                     1218.
                                                                                                                              1,    67
Amount allotted in July 1944----------------------                                                                            3, 200. 00

             Amount available during fiscal year 1945 ----------                                                             4418.
                                                                                                                             4,         67
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1_-_.        -------------------                                                                  3, 500. 00
   IExclusive of available funds.

2. OTHER NAVIGATION PROJECTS FOR WHICH NO ESTIMATES ARE
                        SUBMITTED

                                                                        For last     Cost and expenditures to
                                                                        full re-           June 30, 1944                     Estimated
                         Name of project                                port see                                             amount re-
                                       N                                Annual                                                quired to
                                                                        Report
                                                                         for-        New work
                                                                                     -                   Maintenance          complete


Arkansas River, Okla., above Fort Smith, Ark.'_                           1938           $23, 290.00       $80,758.06            (1)


  1 Channels adequate for existing local commerce.                      Completion is not contemplated.




            616634--45-pt. 1, vol. 1                        56
882          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                   1944

Status of allinvestigations for navigation called for by river and harbor acts and
                               committee resolutions

                                                          Date trans-
            Locality               Authorization act       mitted to     Document No.          Recomen-
                                                           Congress                              dation

Arkansas River, Ark. and          River and Harbor Act, ..........................................
  Okla.     (under     Division    Aug. 30, 1935.
  Board).
Arkansas River and tribu-         Commerce Committee...        ...      .-
                                                                         _   ..   .._   ....         ..   ..
taries. Oklahoma, hydro           resolution, Oct. 12,
electric potentialities (un-      1938.
der Division Board).



                       3. HUTCHINSON, ARKANSAS RIVER, KANS.
   Location.-The work covered by this project is located on the Ar-
kansas River and Cow Creek, a tributary of the Arkansas River,
in the immediate vicinity of Hutchinson, Kans. (See U. S. Geological
Survey maps for Lyons and Hutchinson (Kans.) quadrangles, scale
1: 125,000.)
   Existing project.-The plan of improvement provides for the
construction of a floodway varying from 2,100 to 3,700 feet in width,
beginning at a point about 10 miles north and 7 miles west of Hutch-
inson, and extending for a distance of about 17 miles along the
base of hills, which lie to the north of Hutchinson, thence turning
directly south and extending for a distance of about 6 miles, enter-
ing the Arkansas River about 7 miles downstream from Hutchinson
and about 1 mile downstream from the mouth of Cow Creek. Along
with the construction of the floodway, about 2 miles of levees are
provided for along the Arkansas River about 8 miles upstream from
Hutchinson to prevent floodwaters on the Arkansas River from pass-
ing to the lowlands of the Cow Creek Valley. The project provides
for the complete protection to approximately 92 percent of the area
in the flood plain, including the area in the city of Hutchinson.
   The estimated cost is $1,050,000 for construction.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See H. Doc. No. 308, 74th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation.-See page 7 for requirements. To date these
conditions have not been met, either in whole or in part; however,
local interests have recently indicated an urgent desire for expediting
the construction of flood protection to the city of Hutchinson and
have asserted their willingness to cooperate in a modification of the
existing project.
   Operations and results during fiscal year.-Engineering studies and
preparation of detailed plans were initiated.
   The cost during the fiscal year was $13,320.25; the expenditures
were $2,342.34, all for new work.
   Condition at end of fiscal year.-Preparation of detailed plans
was in progress.
   The total cost to the end of the fiscal year was $13,320.25, and
the expenditures were $2,342.34.
                     FLOOD CONTROL--TULSA,                               OKLA., DISTRICT                                     883
  Proposed operations.-The balance unexpended June 30, 1944,
$57,657.66, will be applied as follows:
Accounts payable June 30, 1944 -----------------------------      $10; 977. 91
New work: Preparation of detailed plans and other engineering
  studies, by hired labor, July 1944 to June 1945--- ------------  46, 679. 75

           Total_   ---------------------------------------------                                                   57, 657. 66
  The additional sum of $60,000 can be profitably expended during
the fiscal year 1946 for the preparation of construction plans and
specifications.
                                     Cost and financial summary
Cost of new work to June 30, 1944-_                                                                              $13, 320. 25
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944-                                                         -       13, 320. 25
Minus accounts payable June 30, 1944-----------------                                                                10, 977. 91
      Net total expenditures--------------------------------                                                         2, 342. 34
Unexpended balance June 30, 1944--------------------                                                                57, 657. 66
           Total amount appropriated to June 30, 1944-- ------                                                      60, 000. 00

   Fiscal year ending June 30            1940                 1941                   1942              1943               1944

Cost of new work-- ----      ------...        .       . .
                                             --------------             .. ,..                    -.   ...               $13, 320. 25
Cost of m aintenance ..   . . . . . --. . . . . .      . . . . . .        .               . ..-
                                                                                     - . -..                   .
                                                                                                        . . . -..
Total expended-------------------                              --------                                                    2,342. 34
Allotted        --------------------------         --------------------------------------                           --   60,000.00


Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941-------------------------------- -- $60, 000. 00
Gross amount expended -------------------------------------  2, 342. 34
       Balance unexpended June 30, 1944---------------                                                              57, 657. 66
Outstanding liabilities June 30, 1944--- ------------ $10, 977. 91
Amount covered by uncompleted contracts--- --------         84. 16
                                                                                                                    11, 062. 07

           Balance available June 30, 1944------------------------                                                  46, 595. 59
Amount (estimated) required to be appropriated for completion of
   existing project 1---         -----------------------------------------                                       990, 000. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946. for new work 1                  -------------------------------------                                  60. 000. 00
  1 Exclusive of available funds.


      4. WICHITA AND VALLEY CENTER, ARKANSAS RIVER, KANS.

  Location.-The work covered by this project is located on the
Arkansas River, and Little Arkansas River and Chisholm Creek, trib-
utaries of the Arkansas River, in the immediate vicinity of Wichita
and Valley Center, Kans. (See U. S. Geological Survey map for
Wichita, (Kans.) quadrangle, scale 1: 125,000.)
  Existing project. - The plan of improvement provides for the
construction of a floodway varying from 2,300 to 2,600 feet in width,
beginning at a point about 2 miles northwest of Valley Center and
running south for a distance of about 3 miles, intercepting the Arkan-
sas River, thence turning southeasterly along Big Slough, for a dis-
884          REPORT OF CHIEF OF ENGINEERS,                                          U.        S. ARMY,              1944

tance of about 25 miles, and entering the Arkansas River about 6 miles
downstream from Wichita. Along with the construction of the flood-
way, about 63 miles of levees are provided with an average height
of 7 feet and a crown width of 8 feet. The plan of improvement also
provides for the construction of about 1.5 miles of diversion channels
for purpose of diverting Chisholm Creek into Little Arkansas River
at a point about 1 mile north of Wichta. About 5 miles of channel
rectification along Chisholm Creek are also provided. The project
provides for protection of people, city property, and environs.
   The estimated cost is $2,603,100 for construction.
   The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936. (See H. Doc. No. 308, 74th Cong., 1st, sess.,
which contains the latest published maps.)
   Local cooperation.-See page 7 for requirements. To date these
conditions have not been met, either in whole or part; however, local
interests have recently indicated an urgent desire for expediting the
construction of flood protection to the city of Wichita and have
asserted their willingness to cooperate in a modification of the ex-
isting project.
   Operationsand results during fiscal year. Engineering studies and
preparation of detailed plans were initiated.
  The cost during the fiscal year was $1,217.76; the expenditures were
$1,111.77, all for new work.
   Conditionat end of fiscal year.-Preparation of detailed plans was
in progress.
  The total cost to the end of the fiscal year was $1,217.76 and the ex-
penditures were $1,111.77.
  Proposed operations.-The balance unexpended June 30, 1944,
$43,888.23, plus $15,000 allotted in September 1944 will be applied as
follows:
Accounts payable June 30, 1944_     ---------------                      $105. 99
New work: Preparation of detailed plans and other engineering studies,
  by hired labor, July 1944 to June 1945 -------       ----     ___ -58,782.24

           Total -------------------                                -------------------------                           58, $88& 23
   The additional sum of $100,000 can be profitably expended during
the fiscal year 1946 for the continuance of engineering studies and
plans.
                                            Cost and financial summary
Cost of new work to June 30, 1944_-__                                              _-----$1,                                 217. 76
Cost of maintenance to June 30, 1944

      Total cost of permanent work to June 30, 1944_                                                                       1, 217. 76
Minus accounts payable June 30, 1944 ------------------------                                                                 105. 99.
      Net total expenditures_--- ------------                                                                            1, 111. 77
Unexpended balance June 30, 1944-----_                                             _                                    43, 888. 23

           Total amount appropriated to June 30, 1944-------------                                                      45, 000. 00

   Fiscal year ending June 30                    1940               1941                   1942           - 1943             1944

Cost of new work .. ..                                                                                                       $1, 217. 76
Cost of maintenance ..
Total expended-   ..      . - .     .   .    .      .   .   .   .      .   .   .       .      .   .   .   .   .1,111.77

Allotted    __           ........                                                                                  ,.        45, 000. 00
                    FLOOD CONTROL-TULSA,             OKLA., DISTRICT               885

Amount allotted from War Department Civil Appropriation Act
  approved May 23, 1941------------------------------ -----   $45,000.00
Oross amount expended_--
                       ___-------------                     -   1, 111.77

      Balance unexpended June 30, 1944-----------------                     43, 888. 23
Outstanding liabilities June 30, 1944--------------------------                 105. 99

     Balance availa ble June 30, 1944--------------------                   43, 782. 24
Amount allotted in September 1944- -----            -------
                                                          __                15, 000. 00

        Amount available during fiscal year 1945     -----------------      58, 782. 24

Amount (estimated) required to be appropriated for completion of
  existing project 1               ---------------                       2, 543, 100. 00
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for new work 1------------___                                  100, 000. 00
1 Exclusive of available funds.


    5. FOR't SUPPLY RESERVOIR, NORTH CANADIAN RIVER, OKLA.

   Location.-Fort Supply Reservoir is located on Wolf Creek, a
tributary of the North Canadian River, about 12 miles northwest of
Woodward, Woodward County, Okla. (See Sectional Aeronautical
Chart, Wichita sheet, scale 1: 5001000.)
   Existing project.-The plan of improvement provides for flood
control in a portion of the North Canadian River Basin, in the
Arkansas River watershed in Oklahoma, by the construction of an
earth-fill dam 11,325 feet long at the top, rising 81.5 feet above the
stream bed, with a reservoir providing for the storage of 102,000
acre-feet for flood control and 16,000 acre-feet for a permanent pool
for recreation and preservation of wildlife. The outlet works, con-
sisting of an egg-shaped conduit with an area approximately equiva-
lent to a circular section 17.7 feet in diameter, controlled by three
71/2- by 16-foot vertical-lift gates, and a stilling basin, are located in
the left abutment. A concrete chute-type spillway, approximately
800 feet long and 540 feet wide, controlled by a concrete weir at the
upstream end and terminating in a stilling basin, provides for the
passage of flood flows around the left end of the dam into the river
valley below. The reservoir will control practically the entire drain-
age area of Wolf Creek and is operated as a unit of the coordinated
reservoir system for flood control in the Arkansas River Basin.
   The estimated costs, revised in 1944, are $7,233,000 for construction,
and $217,000 for lands and damages, a total of $7,450,000.
   The existing project was authorized by the Flood Control Act
approved June 22, 1936. (See H. Doc. No. 308, 74th Cong., 1st sess.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.--Additional landscap-
ing, riprapping and minor clean-up work was continued by hired
labor. Miscellaneous ordinary repairs were made and the structures
were operated and maintained in a serviceable condition throughout
the year. During the periods October 26-November 14, 1943, and
February 6-March 3, 1944, releases were made for the purpose of
replenishing the Oklahoma City, Okla., water supply. The maximum
discharges were 1,100 cubic feet per second and 210 cubic feet per sec-
ond, respectively, and the volumes of water released during the two
periods were 6,590 acre-feet and 5,690 acre-feet, respectively. During
886       REPORT OF CHIEF OF ENGINEERS,                       U. S. ARMY,         1944

the period April 24-29, 1944, approximately 26,000 acre-feet of storage
were utilized, raising the pool elevation to 2,005.8 feet and resulting
in reductions of flood heights of 1 foot and 0.5 foot at Woodward and
Canton, Okla., respectively.
   The cost during the fiscal year was $27,913.63 for new work and
$41,980.98 for maintenance; the expenditures were $34,670.35 for new
work and $40,708.56 for maintenance.
   Condition at end of fiscal year.-The project as a whole is essen-
tially complete and is in operation. The work remaining to complete
the project consists of minor clean-up work around the permanent
buildings, landscaping, and riprapping of dam, and demobilization
and demolition of construction camp.
   The total cost for new work to the end of the fiscal year was $7,352,-
397.69, of which $7,265,359.98 was from regular funds and $87,037.71
from Emergency Relief funds. The total cost for maintenance to the
end of the fiscal year was $59,740.13 from regular funds. The expen-
ditures for new work were $7,264,365 regular funds and $87,037.71
Emergency Relief funds, a total of $7,351,402.71; the expenditures
for maintenance were $58,845.21, all from regular funds.
   Proposed operations.-The balance unexpended on June 30, 1944,
$93,752.08, and accounts receivable, $848.61, plus the sum of $20,000
allotted in July 1944, a total of $114,600.69, will be applied as follows:
Accounts payable June 30, 1944_ _____------------------------------$2,                     795. 89
New work:
    Engineering studies in connection with construc-
      tion and reservoir operations studies, by hired
      labor      ---------------------------                           $10,000.00
    Completion of landscaping, riprapping, demobiliza-
      tion and demolition of construction camp, minor
      clean-up work, and contingencies, by hired labor- 81, 545. 90
        Total, new work__--------------_                                                91, 545. 90
Maintenance by hired labor:
    Operation of completed project--- -------------                    $10, 000. 00
    Ordinary repairs_----                - -             ____            10, 258. 90
        Total, maintenance_--            -------                 ---       ____         20, 258. 90
        Total for all work--------------------------------                             114, 600. 69
  With the expenditures of funds shown above for new work, the
project will be completed. The additional sum of $30,000 can be
profitably expended during the fiscal year 1946 as follows:
Maintenance by hired labor:
   Operation of completed project ----------------------------                            $15, 000
   Ordinary repairs ------------------------------------------                              15, 000
        Total for all work ---------------------------------------                         30,000
                                Cost and financial summary
Cost of new work to June 30, 1944_                 -  -_    1 $7, 352, 397. 69
Cost of maintenance to June 30, 1944-----------------------        59, 740. 13
      Total cost of permanent work to June 30, 1944
Undistributed costs June 30, 1944_
                                 --------------------------
                                                                -          -      1 7, 412, 137. 82
                                                                                             57. 38
       Net total cost to June 30, 1944-                                            7, 412, 195. 20
Plus accounts receivable June 30, 1944-.                _--     -_-848.                         61
        Gross total costs to June 30, 1944             __-----_-7,                     413, 043. 81
                          FLOOD CONTROL-TULSA,                              OKLA.,       DISTRICT                       887
Minus accounts payable June 30, 1944_-                           ____-         -------                           $2, 795. 89

      Net total expenditures__---------           ---     -17, 410, 247. 92
Unexpended balance June 30, 1944-------------------------       93, 752.08
            Total amount appropriated to June 30, 1944-----------                                         1 7, 504, 000. 00


      Fiscal year ending June 30             1940              1941               1942             1943              1944

                    -- -
Cost of new work_ __--                 $1, 742, 291.75 $1, 602, 272. 55 $2,054, 697. 26         $181, 280. 54       $27, 913.63
Cost of maintenance _.........                   ..........             ..   .....      _         17, 759.15         41,980.98

         Total cost--------------       1, 742, 291. 75   1, 602, 272. 55    2,054, 697.26       199, 039. 69        69, 894.61

Total expended ...---------------
                      ..          1, 748, 355. 58         1, 384, 795. 57    2, 295, 985. 33     195, 493.82         75, 378. 91

Allotted_        .----- _-_-     ---    2, 663, 000.00    1, 509, 975.00        70, 500.00        30, 000. 00     -235,000.00



Balance unexpended July 1, 1943_ ____----------$404,                                                                 130. 99
Deductions on account of revocation of allotment------                                   ----                   235, 000. 00
       Net amount to be accounted for_                                                                          169, 130. 99
Gross amount expended--- --------               $84, 691.38
Less reimbursements collected------------------   9, 312. 47
                                                                                                                 75, 378. 91
      Balance unexpended June 30, 1944-                                                                          93, 752. 08
Outstanding liabilities June 30, 1944 ------------                                $2, 795. 89
Amount covered by uncompleted contracts                                               722. 95
                                                                                                                  3, 518. 84
      Balance available June 30, 1944                                                                            90, 233. 24
Accounts receivable June 30, 1944_                                                                                   848. 61
     Unobligated balance available June 30, 1944_                                                                91, 081. 85
Amount allotted in July 1944_                                                                                    20, 000. 00
            Amount available during fiscal year 1945_                                                           111, 081. 85
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2_                                                                               30, 000. 00
  I    Includes $87,037. 71 Emergency Relief funds.
      SExclusive of available funds.

            6. CANTON RESERVOIR,                      ARKANSAS RIVER BASIN, OKLA.

   Location.-Canton Reservoir is located on the North Canadian
River about 393 miles above its mouth and about 3 miles north of
Canton, Blaine County, Okla. (See Sectional Aeronautical Chart,
Wichita sheet, scale 1: 500,000.)
   Existing projeet.-The plan of improvement provides for flood
control in a portion of the North Canadian River Basin, in the
Arkansas River watershed in Oklahoma, by construction of an earth-
fill dam 15,100 feet long at the top, rising 68 feet above the valley
floor, with a reservoir providing for the storage of 240,000 acre-feet
for flood control and 150,000 acre-feet for conservation of water and
siltation reserve. Of the conservation storage, 40,000 acre-feet is
allocated as a reserve for the abatement of pollution downstream
from the project. The outlet works will consist of three 7- by 12-foot
gated sluices through the spillway weir. A concrete spillway, con-
trolled by sixteen 40- by 25-foot gates on the weir crest, will pro-
vide for the passage of flood flows around the right end of the dam
888     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,               1944

into the river valley below. The reservoir will be operated as a unit
of the coordinated reservoir system for flood control in the Arkansas
River Basin.
   The estimated costs, revised in 1940, are $13,220,000 for construction
and $650,000 for lands, damages, and relocations, a total of $13,870,000.
   The existing project was authorized by the Flood Control Act
approved June 28, 1938. (See H. Doc. No. 569, 75th Cong., 3d sess.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Preparation of plans
and specifications for construction of spillway and completion of em-
bankment was continued. Acquistion of lands and rights-of-way in
the reservoir area, limited to specific curtailmenit requirements, was
continued. Partially completed features were maintained in a serv-
iceable condition throughout the year.
   The cost during the fiscal year was $22,044.77; the expenditures were
$21,908.22, all for new work.
   Condition at end of fiscal year.-The project as a whole is 24 per-
cent complete. A major portion of the embankment is complete and
excavation for the spillway is essentially complete. All construc-
tion accomplished has been placed in a standby status until after the
existing war emergency. The work remaining to complete the project
consists of completion of embankment, acquisition of lands and rights-
of-way in the reservoir area, relocation of highways and utilities, con-
struction of operator's quarters, clearing of reservoir area, and land-
scaping.
   The total cost to the end of the fiscal year was $2,357,205.68; the
expenditures were $2,356,297.93, all for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
$197,677.07, and accounts receivable $7.50, plus the sum of $5,000
allotted in July 1944, a total of $202,684.57, will be applied as follows:
Accounts payable June 30, 1944          ------------               $2, 186. 79
New work:
   Engineering, design, and studies by hired labor, July 1944 to
     June 1945 .....-                                               8,000.00
   Land acquisition and relocations, by hired labor, July to Sep-
     tember 1944-_                                           -    187, 497. 78
   Repair and preservation of suspended project by hired labor,
     July 1944 to June 1945-                                        5, 000. 00

        Total for all work---------------------------------        202, 684. 57
  No additional funds can be expended for construction during fiscal
year 1946 in view of existing Federal policies on wartime construction.
                          Cost and financial summary
Cost of new work to June 30, 1944                         -     $2, 357, 205. 68
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944----------   2, 357, 205. 68
Undistributed costs June 30, 1944 ---------------------------        1, 271. 54
       Net total cost to June 30 1944----------------------- 2, 358, 477. 22
Plus accounts receivable June 30, 1944------------------------- ---    7. 50
      Gross total costs to June 30, 1944 -2,                       358, 484. 72
                                FLOOD               CONTROL--TULSA,              OKLA.,         DISTRICT                     889
Minus accounts payable June 30, 1944------------------------                                                          $2, 186. 79

       Net total expenditures ----------------------------- 2, 356, 297. 93
Jnexpended balance June 30, 1944--------------------------    197, 677. 07
              Total amount appropriated to June 30, 1944-----_--- ---                                          2, 553, 975. 00


     Fiscal year ending June 30                         1940             1941            1942           1943             1944

Cost of new work..........---------------..           $115, 728. 49   $516, 752. 77    $973, 542. 00  $591, 133. 87   $22, 044. 77
Cost of maintenance....--------- ..                   . ..       . ..   ..            -.... ..    . . . . ..        . . . .
Total expended-----------------..................      108, 96. 54     521,920.60     1,075,506. 18    600, 756. 98      21, 908. 22
Allotted---------------------.........................1,400,000.001,   009, 975.00    2,800,000.00 -2, 800, 000.00-300,000.00


Balance unexpended July 1, 1943                                                                                 $519, 585. 29
Deductions on account of revocation of allotment--- ---------                                                    300, 000. 00

              Net amount to be accounted for----                                                                  219, 585. 29
Gross amount expended ---------------------- $132, 135. 11
Less reimbursements collected------------------                                            110, 226. 89
                                                                                                                      21, 908. 22
      Balance unexpended June 30, 1944---------------------197, 677. 07
Outstanding liabilities June 30, 1944-------------$2, 186. 79
Amount covered by uncompleted contracts-          145, 617. 23
                                                                                                                  147, 804. 02
      Balance ayailable June 30, 1944-----------------49,                                                                873. 05
Accounts receivable June 30, 1944_-                                                                                        7. 50

     Unobligated balance available June 30, 1944------------                                                          49, 880. 55
Amount allotted in July 1944-------------------------------                                                            5, 000. 00
              Amount available during fiscal year 1945--54,                                                              880. 55
Amount (estimated) required to be appropriated for completion
of existing project 1 -_---------------                      11, 316, 025. 00
   a Exclusive of available funds.

                7. CHEROKEE, SALT FORK OF ARKANSAS RIVER, OKLA.

   Location.-The work covered by this project is located on Cotton-
wood Canyon, a tributary of the Salt Fork of the Arkansas River, in
the immediate vicinity of Cherokee, Okla. (See Sectional Aeronauti-
cal Chart, Wichita Sheet, scale 1: 500,000.)
   Ewisting project.-The plan of improvement provides for levees and
other work in connection with a floodway which will divert flows of
Cottonwood.Canyon away from Cherokee. The south wing levee will
begin on the right bank of Cottonwood Canyon, at mile 7, above its
mouth, and will extend to mile 4, where it will approach the shorter
north wing levee and the floodway will begin. The floodway, 3.6 miles
in length, and varying from 165 to 290 feet in width, will carry flood
flows east to the Great Salt Plains. The total length of levees pro-
posed is 11.1 miles, with a grade elevation for the south levee varying
from 6 feet to 1 foot above the height of the confined flow of the maxi-
mum flood of record on Cottonwood Canyon. The grade elevation of
the north levee, through its entire length, is 1 foot above the height of
this flood. The project provides for the protection of approximately
4,650 acres of rural and urban areas.
890           REPORT OF CHIEF OF ENGINEERS,                                        U.   S. ARMY,          1944


   The estimated Federal cost, approved in 1939, is $800,000. The
total cost for lands and damages is $60,000.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941. (See H. Doc. No. 480, 76th Cong., 2d sess.,
which contains the latest published maps.)
   Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, local
interests are required to bear the expense of necessary changes to the
county road, including abridge across the diversion channel, and of
required relocation of telephone and power lines. To date these con-
ditions have not been met, either in whole or in part, but at a public
hearing held at Cherokee, Okla., and subsequent thereto, local interests
have asserted their willingness to meet all these conditions.
   Operations and results during fiscal year.                     studies                  -Engineering
and preparation of detailed plans were initiated.
   The' cost during the fiscal year was $1,193.05; the expenditures were
$1,130.50, all for new work.
   Condition at end of fiscal year.-Engineering studies and prepara-
tion of detailed plans were initiated.
   The total cost to the end of the fiscal year was $1,193.05; the ex-
penditures were $1,130.50, all for new work.
   Proposed operations.-The balance unexpended June 30,*1944, $33,-
869.50, will be applied as follows:
Accounts payable June 30, 1944 ------------------------------     $62. 55
New work: Preparation of detailed plans and other engineering
  studies, by hired labor, July 1944 to June 1945--- -------  33, 806. 95

                             ------------------------------------
           Total for all work_                                                                                  33, 869. 50
  The additional sum of $40,000 can be profitably expended during
the fiscal year 1946 for the preparation of construction plans and
specifications.
                                              Cost and financial summary
Cost of new work to June 30, 1944__-                                                                            $1, 193. 05
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944----- --------                                                1, 193. 05
Minus accounts payable June 30, 1944---------------------------                                                      62. 55
      Nettotal expenditures---------------------------------  1, 130. 50
Unexpended balance June 30, 1944----------------------------33, 869. 50
           Total amount appropriated to June 30, 1944------ --------                                            35, 000. 00

    Fiscal year ending June 30                     1940                 1941        1942          1943.            1944

Cost of new work----------------------------------------------------------------                                   $1,193.05
Costofm aintenance --- - - - - - - -                   -- - - - - - - - - - - - - - - - -        . . . . . .... . . .
                                                                                               .-..
Total expended-                                               -1,130.                                                     50
                      .....--------------------------------------
Allotted-------------------....................                                                    $35, 000-

Balance unexpended July 1, 1943                     -----------                                                $35, 000. 00
Gross amount expended -------------------------------------                                                      1, 130. 50
Balance unexpended June 30, 1944-                                                                               33, 869. 50
                   FLOOD CONTROL-TULSA,      OKLA.,   DISTRICT             891
Outstanding liabilities June 30, 1944 ----------------------------
                                         _      _$62.                        55

       Balance available June 30, 1944----------------- --------     33, 806. 95

Amount (estimated) required to be appropriated for completion
of existing project 1-----------------------------------
                                                        _____     765, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 1           ___                       ___  40, 000. 00
1Exclusive of available funds.
   8. GREAT SALT PLAINS RESERVOIR, SALT FORK OF ARKANSAS
                         RIVER, OKLA.

    Location.-Great Salt Plains Reservoir is located on the Salt Fork
of the Arkansas River 93.5 miles above its mouth, and about 12 miles
east of Cherokee, Alfalfa County, Okla. (See Sectional Aeronautical
Chart, Wichita sheet, scale 1: 500)000.)
   Existing project.-The plan of improvement provides for flood con-
trol in the Salt Fork Valley in the Arkansas River watershed in
Oklahoma, by construction of an earth-fill dam 5,700 feet long, rising
68.5 feet above the valley floor, with a reservoir providing for the
storage of 259,000 acre-feet for flood control and 58,000 acre-feet for
siltation, recreation, and preservation of wildlife. A concrete cas-
cade-type spillway approximately 800 feet long and 338 feet wide,
containing three gravity-type concrete weirs, provides for the passage
of flood-flows around the right end of the dam into the river valley
below. The outlet works consist of four ungated 10- by 12-foot con-
duits through the center section of the upper weir. The reservoir is
operated as a unit of the coordinated reservoir system for flood con-
trol in the Arkansas River Basin.
   The estimated costs, revised in 1942, are $4,059,000 for construction
and $426,000 for ands and damages, a total of $4,485,000.
    The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936. (See H. Doc. No. 308, 74th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year.-The continuing contract
for installation of a protective flood lighting system was completed
during the fiscal year. Minor landscaping and riprapping were per-
formed by hired labor. Continuing contract for relocation of rail-
road lines was let. Miscellaneous ordinary repairs were made and
the structures were operated and maintained in a serviceable condi-
tion throughout the year. During the period March 12-May 12, 1944,
approximately 51,000 acre-feet of storage were utilized, raising the
pool elevation to 1,128.9 feet and resulting in reductions of flood
heights of 3.8 feet immediately below the dam and 2.2 feet at Tonkawa,
Okla.
    The cost during the fiscal year was $9,468.12 for new work and
$44,641.83 for maintenance; the expenditures were $8,338.52 for new
work and $44,578.40 for maintenance.
    Condition at end of fiscal year.-The project as a whole is essen-
tially complete and is in operation. The work remaining to complete
the project consists of relocation of railroad lines and minor land-
scaping and riprapping of dam.
892          REPORT OF CHIEF OF ENGINEERS,                              U. S. ARMY,                       1944

   The total cost for new work to the end of the fiscal year was $4,-
303,695.76, of which $4,278,952.17 was from regular funds and $24,-
743.59 from Emergency Relief funds. The cost for maintenance to
the end of the fiscal year was $82,312.24 from regular funds. The
expenditures for new work were $4,277,868.23 regular funds and
$24,743.59, Emergency Relief funds, a total of $4,302,611.82; the
expenditures for maintenance were $82,170.52, all from regular funds.
   Proposed operations.-The balance unexpended June 30, 1944,
$185,717.66, and accounts receivable $746.08, plus the sum of $20,000
allotted in July 1944, a total of $206,463.74, will be applied as follows:
Accounts payable June 30, 1944 _     ___________       _______                                               $1, 971. 74
New work:
   Engineering studies in connection with construction
     and reservoir operation studies, by hired labor     $6, 014. 70
   Relocation of railroad lines by present continuing
     contract__             __158,                           255. 10
   Completion of landscaping and rip-rapping, by
     hired labor __                                      17, 790. 52

        Total for new work .                                                                          -     182, 060. 32
Maintenance by hired labor:
   Operation of completed project-                                                 $10, 000. 00
   Ordinary repairs_                                                                12, 431. 68

         Total maintenance           -_                                                -_      _      _      22,431.68

         Total for all work_                                                       -           ,            206, 463. 74
  With the expenditure of funds shown in the above amount for new
work, the project will be completed. The additional sum of $30,000
can be profitably expended during the fiscal year 1946 as follows:
Maintenance by hired labor:
    Operation of completed project_---         ----                     -- ----               --           ---.. $15, 000
    Ordinary repairs_-__ _____________.--_________                                                 ..             15, 000
         Tota for aallwork--_             _                                                                      30,000

                                     Cost and financial summary
Cost of new work to June 30, 1944 ------------------------ $4, 303, 695. 76
Cost of maintenance to June 30, 1944-----------------------     82, 312. 24
       Total cost of permanent work to June 30, 1944                         ---------                14,   386, 008. 00
Plus accounts receivable June 30, 1944----------------------746.                                                      08
      Gross total costs to June 30, 1944                 --------------------                             4, 386, 754. 08
Minus accounts payable June 30, 1944-----------------------                                                    1, 971. 74
      Net total expenditures_ ______-----------1                                                          4,384, 782. 34
Unexpended balance June 30, 1944_--------                                              ---                  185, 717. 66
         Total amount appropriated to June 30, 1944                     -----------                       4, 570, 500. 00

   Fiscal year ending June 30             1940            1941            1942                 1943              1944

Cost of new work___-.-              $1,483, 219. 91 $1, 716,216. 26   $121, 028. 29          $90, 440.14         $9, 468.12
Cost of maintenance _      _ _     _ ___
                                  .........      -___
                                                _.     -_     __         11, 220. 29          26, 450.12         44,641.83
      Total cost --------------
                   .                1, 483, 219.91   1, 716, 216.26    132, 248.58           116, 890.26         54, 109.95
Total expended .--------------..............
                               1, 352, 567.01 1, 742, 359. 22          278, 070.17           112, 610.18         52, 916. 92
Allotted -    .--------------------
                                1,200,000.00            67,300.00     -70,000.00              30,000.00


  I Includes $24,743.59 Emergency Relief funds.
                      FLOOD CONTROL-TULSA,     OKLA.,   DISTRICT            893
Balance unexpended July 1, 1943---------------------------          $238, 634. 58
Gross amount expended-------------------_      -- $56, 077. 13
Less reimbursements collected---- ------------      3, 160. 21
                                                                      52, 916. 92

       Balance unexpended June 30, 1944---------------      -----    185, 717. 66
Outstanding liabilities June 30, 1944------------- $1, 971. 74
Amount covered by uncompleted contracts- ------ 149, 60&8. 32
                                                                     151, 580. 06

      Balance available June 30, 1944-----------------------          34, 137. 60
Accounts receivable June 30, 1944--------------------------               746. 08
     Unobligated balance available June 30, 1944-- --------           34, 883. 68
Amount allotted in July 1944------------------------------            20, 000. 00

          Amount available during fiscal year 1945--- ----------      54, 883. 68

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 2------------                         30, 000. 00
S   Exclusive of available funds.


                      9. HULAH RESERVOIR, CANEY RIVER, OKLA.

   Location.-Hulah Reservoir is located on Caney River 78 miles above
its confluence with the Verdigris River and is about 15 miles northwest
of Bartlesville, near Hulah, Osage County, Okla. (See U. S. Geo-
logical Survey Maps for Pawhuska and Sedan (Okla.) quadrangles,
scale 1: 125,000.)
   Existing project.-The plan of improvement provides for flood con-
trol in the Caney River Valley in the Verdigris River Basin, Arkansas
River watershed, by construction of an earth-fill dam 5,500 feet long
and rising 72 feet above the valley floor, with a reservoir providing for
the storage of 280,000 acre-feet for flood control and 15,000 acre-feet
for siltation, recreation, and preservation of wildlife. A concrete un-
controlled spillway will provide for the passage of flood flows through
a saddle in the right abutment of the dam. The outlet works will con-
sist of three 7- by 12-foot gated sluices through the spillway. The
reservoir will be operated as a unit of the coordinated reservoir system
for flood control in the Arkansas River Basin.
   The estimated costs, revised in 1940, are $7,165,000 for construc-
tion and $1,675,000 for lands, damages, and relocations, a total of
$8,840,000.
   The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936. (See H. Doc. 308, 74th Cong., 1st sess.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Operations during the
fiscal year consisted of continuation of studies relative to value of min-
eral deposits within the reservoir area and preliminary steps toward
land acquisition by hired labor.
   The cost of new work during the fiscal year was $14,258.82; the
expenditures were $15,165.10, all for new work.
   Condition at end of fiscal year.-Preparation of construction plans
and specifications is complete except for minor revisions. The work
remaining to be done to complete the project consists of minor revi-
sions to construction plans and specifications, acquisition of lands,
894             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                1944

relocation of highways and utilities, and construction of the dam and{
appurtenant works.
    The total cost to the end of the fiscal year was $229,148.97; the
expenditures were $228,977.85, all for new work.
    Proposed operations.&-Thebalance unexpended June 30, 1914, $14,-
161.44 will be applied as follows:
Accounts p.ayable June 30, 1944           ---                   $171. 12               -
New work: Engineering, design, .and studies by hired labor, July 1944
   to June 1945--- ----------------------------------          --      13, 990. 32
            Total for all work------------------------------------14,                                                    161. 44
   No additional funds can be expended during the fiscal year 1946
in view of the existing Federal policies on wartime construction.
                                               Cost and financial summary
/Costof new work to June 30, 1944                             $229,                                                      148. 97
Cost of maintenance to June 30, 1944------------------
       Total cost of permanent work to June 30, 1944-----_- -  229,                                                      148.     97
Minus accounts payable June 30, 1944------------------------                                                             171.     12
       Net total expenditures-------------------------------228,                                                         977.     85
Unexpended balance June 30, 1944-------------------------       14,                                                      161.     44
       Total amount appropriated to June 30, 1944---------     243,                                                      139.     29

    Fiscal year ending June 30                    1940           1941           1942              1943                   1944

Cost of new work--------                         $57, 322. 47   $74, 474. 94  $20,807. 85    $23, 506. 20            $14, 258.82
C ost of m ain tenance....           . . . . . . . . . . . . . . . . . . . . . . . .. . .   . . . . .        . . . ...     . ..
Total expended ...........----------------       58, 546. 75    72, 719, 38   20, 184. 23     25, 141.43                 15, 165. 10
Allotted     ---------------------              400, 000.00     14, 240. 00                   -          -        -210,000.       00


Balance unexpended July 1. 1943------------------------------                                                $239,       326.     54
Deductions on account of revocation of allotment---------- ----                                               210,       000.     00
      Net amount to be accounted for------------------                                                         29,       326.     54
Gross amount expended ------------------------------------                                                     15,       165.     10
      Balance unexpended June 30, 1944__                                                                       14,       161.     44
Outstanding liabilities June 30, 1944--- -------------     $171. 12
Amount covered by uncompleted contracts-- ---------         312. 50
                                                                                                                    483. 62
     Balance available June 30, 1944------                ---                                                   13, 677. 82
Amount (estimated) required to be appropriated for completion of
   existing project 1-----------------                                                                   8, 596, 860. 71
  1Exclusive of available funds.

                10. TULSA AND WEST TULSA, ARKANSAS RIVER, OKLA.

  Location.-The work covered by this project is located on the Ar-
kansas River at Tulsa and West Tulsa, Okla. (See U. S. Coast and
Geodetic Survey maps, Hominy, Okla., and Claremore, Okla., quad-
rangles, scale 1: 125,000.)
  Existing project.-The plan of improvement provides for raising
the existing left bank levee, connecting the discontinuous portions of
the levee and constructing a leveed floodway up Black Boy Creek
with levees and diversion ditches eastward and westward thereof,
and raising the existing right bank levee to the proposed grade and
constructing the necessary appurtenances thereto. The left bank levee
              FLOOD CONTROL-TULSA,        OKLA.,   DISTRICT          895

begins at mile 531.3 above the month of the Arkansas River and ends
at mile 524.0. The right bank levee begins at mile 526.7 and ends
at mile 521.3. The project provides for the protection of 5,020 acres
of highly developed industrial, urban, and agricultural land, with
grade elevation allowing a 1-foot freeboard above the flow of the
maximum probable flood.
   The estimated cost revised in 1943, is $2,700,000 for construction.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941. (See H. Doc. No. 157, 77th Cong., 1st sess.,.
which contains the latest published maps.)
  Local cooperation.-See page 7 for requirements. In addition to
the usual requirements for local cooperation as provided by law, the
State of Oklahoma is required by appropriate legislation to assure
that the construction of bridges or other works which might adversely
affect the flood-carrying capacity of the channel at the locality will
not be permitted. Assurances of local cooperation were approved by
the Secretary of War on August 12, 1943, and necessary lands and
rights-of-way have been furnished aS required for construction.
   Operations and results during fiscal year.-Preparation of con-
struction plans and specifications was continued. Contracts for all
features of the project were awarded and construction operations
under each contract were initiated.
   Construction of levee from Sand Springs to Black Boy Creek was
essentially completed during the fiscal year by the accomplishment
of the following work by contracts: Placement of 506,186 cubic yards
of fill material and 7,675 cubic yards of riprap; construction of 260
linear feet of flood wall; completion of drainage system; completion
of seeding and sodding; and substantial completion of three pumping
plants.
   Construction of the Black Boy floodway structure was well advanced
by the accomplishment of the following work by contracts: Excava-
tion of 9,535 cubic yards of material; placement of 3,375 cubic yards of
concrete and 524,000 pounds of reinforcement steel; placement of
17,100 cubic yards of earth fill; and removal and relocation of
highways, railroads, and other utilities.
   Construction of levee from Black Boy Creek to Tulsa was well
advanced by the accomplishment of the following work by contracts:
Placement of 295,500 cubic yards of fill material, excavation of 15,100
cubic yards of material; placement of 1,005 cubic yards of concrete
and 190,300 pounds of reinforcement steel; and commencement of
installation of two pumping plants.
   A total of 56,000 cubic yards of fill material, 325 cubic yards of con-
crete, and 52,000 pounds of reinforcement steel was placed by contract
in the construction of the levee at West Tulsa.
   The cost during the fiscal year was $1,292,616.69; the expenditures
were $1,125,554.21 all for new work.
   Condition at end of the fiscal year.-The project as a whole is 62
percent complete. Levee from Sand Springs to Black Boy Creek is
essentially complete. Black Boy Creek floodway structure is 65 percent
complete. Levee from Black Boy Creek to Tulsa is 58 percent complete,
and levee at West Tulsa is 10 percent complete. The work remaining
to complete the project consists of the following: Placing of about
816,000 cubic yards of earthwork, 7,700 cubic yards of riprap, and
896           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                1944

3,650 cubic yards of concrete; construction of six stop-log structures;
completion of seven pumping plants; and construction of miscellaneous
drainage structures and other minor features. The total cost to the
end of the fiscal year was $1,358,051.40; the expenditures were
$1,192,396.84, all for new work.
   Proposed opeirations.--The balance unexpended June 30, 1944,
$1,507,603.16, will be applied as follows:
Accounts payable June 30, 1944_                                 _ $165,                                                           654. 56
New work:
    Engineering studies in connection with construction, by hired
      labor, July to November 1944                                   10,                                                          944. 77
    Completion of levee and appurtenances from Sand Springs to
      Blackboy Creek, by contracts, July to August 1944-
    Completion of Blackboy Creek floodway structure, by con-
                                                                     87,                                             -            212. 88

      tract, July to September 1944_ -       -_                      95,                                                          725. 78
    Completion of levee and appurtenances from Blackboy Creek to
      Tulsa, by contracts, July to September 1944 -           ___392,                                                             851. 17
    Completion of levee and appurtenances at West Tulsa, by
      continuing contract, July to November 1944 -- -----           658,                                                          159. 79
    Completion of bank protection, seeding and sodding, and
      contingencies, by contract, July to November 1944              97,                                    ------                054.'21
         Total for all work-                                      1,507,                                                          603. 16
  With the expenditure of these funds the project will be completed
and placed in operation.
                                               Cost and financial summary
Cost of new work to June 30, 1944___                                                                                   $1, 358, 051. 40
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944-                                                                   1, 358,   051.   40
Minus accounts payable June 30, 1944                                                                                       165,   654.   56
       Net total expenditures-                                                                                          1, 192,   396.   84
Unexpended balance June 30, 1944-                                                                                       1, 507,   603.   16
       Total amount appropriated to June 30, 1944-                                                                      2, 700,   000.   00

    Fiscal year ending June 30                         1940                     1941            1942            1943              1944

Cost of new work_----- ......--------............ ----                              $5, 202.79                $60, 231.92    $1, 292, 616.69
Cost of maintenance-----      -----------------------------------------------------                                                -
Total expended---------......             .-           -----............           .   .       5, 202. 79     61, 639. 84     1, 125, 554.21
Allotted-------                      .
                                  ---................---   .             ......-..-.
                                                                              -                5, 202. 79     538,000.00      2,156, 797. 21


Balance unexpended July 1, 1943__________________                                                                        $476, 360. 16
Amount allotted from War Department Civil
  Appropriation Act approved June 24, 1940
Amount allotted from War Department Civil
                                             $200, 000. 00                             ----
  Appropriation Act approved May 23, 1941_     600, 500. 00
Amount allotted from War Department Civil
  Appropriation Act approved Apr. 28, 1942     356, 297. 21
Amount allotted from Third Supplemental Na-
  tional Defense Act, 1942, Dec. 17, 1941   1, 000, 000. 00                        ------                               2, 156, 797. 21
       Amount to be accounted for___                                                                                    2, 633, 157. 37
Gross amount expended-_     -------                                                           $1, 125, 963. 77
Less reimbursements collected_                                 ------                         -   -- 409. 56
                                                                                                                        1, 125, 554. 21
      Balance unexpended June 30, 1944----------------                                                                  1, 507, 603. 16
Outstanding liabilities June 30, 1944 ----------- $165, 654. 56
Amount covered by uncompleted contracts----- 1, 115, 885. 97
                                                                                                                        1, 281, 540. 53
           Balance available June 30, 1944---------.                                               -_                       226, 062. 63
                 FLOOD CONTROI--TULSA,                  OKLA.,   DISTRICT          897
11. MARKHAM FERRY RESERVOIR, ARKANSAS                            RIVER BASIN, OKLA.

   Location.-Markham Ferry Reservoir is located on the Grand
 (Neosho) River, 46.7 miles above its mouth, and 2.5 miles north and
west of Locust Grove, Mayes County, Okla. (See U. S. Geological
Survey maps for Pryor and Vinita (Okla.) quadrangles, scale
1:125,000.)
   Existing project.-The plan of improvement provides for combined
flood control and hydroelectric power in this portion of the Grand
 (Neosho) River Basin, in the Arkansas River watershed in Oklahoma,
by construction of a concrete gravity type dam and earth-fill embank-
ment structure 10,600 feet in total length along the crest, rising 90
feet above the stream bed, with a reservoir providing for the storage
of 233,000 acre-feet for flood control and 187,000 acre-feet for power
storage. The project will include a powerhouse structure housing the
hydroelectric generating equipment, a gate-controlled spillway, and
two nonoverflow abutment sections. A concrete gravity nonoverflow
section will form the left abutment of the structure and the right abut-
ment will be an earth-fill embankment. The powerhouse structure
will be located on the left bank with the spillway structure extending
across the existing river channel. The entire dam structure will be
topped by a roadway. The reservoir will be operated as a unit of the
three-reservoir system for dual-purpose flood control and hydroelectric
power on the lower Grand (Neosho) River, and as one unit in the
comprehensive plan for flood control of the Arkansas River Basin.
   The estimated cost, revised in 1943, is $14,645,000 for construc-
tion and $4,650,000 for lands, damages, and relocations, a total of
$19,295,000.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941. (See H. Doc. No. 107, 76th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Preparation of con-
struction plans and specifications and other engineering studies were
continued.
   The cost during the fiscal year was $31,177.89; the expenditures were
$29,554.24, all for new work.
   Condition at end of fiscal year.-The preparation of construction
plans and specifications was 20 percent complete.
   The total cost to the end of the fiscal year was $135,805.93; the ex-
penditures were $134,142.81, all for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
$181,313.92, plus the sum of $100,000 allotted in July 1944, a total of
$281,313.92, will be applied as follows:
Accounts payable June 30, 1944-----------------------------                  $1, 663. 12
New work: Preparation of construction plans and specifications
  and other engineering studies, by hired labor, June to Decem-
  ber 1944_ ---------------------------------------------                   279,650.80
      Total for all work_----------------------------------                 281, 313. 92
  The amount of $100,000 can be expended during fiscal year 1946 for
the completion of plans and specifications.
      616634--45-pt. 1, vol. 1-57
898          REPORT OF CHIEF OF ENGINEERS,                               U. S. ARMY,             1944

                                          Cost and financial summary

Cost of new work to June 30, 1944--------------------------                                        $135, 805. 93
Cost of maintenance to June 30, 1944
      Total cost of permanent work to June 30, 1944------------                                        135, 805. 93
Minus accounts payable June 30, 1944_------             -__                                              1,663. 12

      Net total expenditures_ -------------                                             ____           134, 142. 81
Unexpended balance June 30, 1944_---------                                              -__            181, 313. 92

           Total amount appropriated to June 30, 1944                     ----------                   315, 456. 73


   Fiscal year ending June 30                 1940           1941          1942           1943                1944

Cost of new work__ ...-...._...
                              -__ _       -_
                                      _.........       -_ $98, 510. 94                   $6,117.10    $31,177. 89
C ostofm aintenance . - - - - -- - - - - - .- - - - .- . -- - - .--                     . . . . . .. . .. . .
Total expended-----_ _........... _-                    - _ -_-     -    96, 931. 31      7, 657. 26          29, 554. 24
Allotted    .   ..----------------..   --------------   --------------   115, 456. 73           00
                                                                                         200,000.         _     ....


Balance unexpended July 1,1943_--------                                           ---             $210, 868. 16
Gross amount expended_ ____---------__29,                                                               554. 24
      Balance unexpended June 30, 1944 ----------------                                                181, 313. 92
Outstanding liabilities June 30, 1944 -------------- $1, 663. 12
Amount covered by uncompleted contracts                   32. 16  ---------
                                                                                                         1, 695. 28

     Balance available June 30, 1944_-------                                            ---            179, 618. 64
Amount allotted in July 1944 ________----------                                                        100, 000. 00
           Amount available during fiscal year 1945----------------                                    279, 618. 64

Amount (estimated) required to be appropriated for completion
   of existing project 1     _--_-                 ---__-     18, 879, 543. 27
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for new work 1        ------------                100, 000. 00
1 Exclusive of available funds.

     12. FORT GIBSON RESERVOIR, ARKANSAS RIVER BASIN, OKLA.
   Location.-FortGibson Reservoir is located on the Grand (Neosho)
River, 7.7 miles above its mouth,-and about 5 miles north and east
of Fort Gibson, Muskogee County, Okla. (See U. S. Geological
Survey maps for Muskogee and Pryor (Okla.) quadrangles, scale
1: 125,000.)
   Existing project.-The plan of improvement provides for com-
bined flood control and hydroelectric power development in the por-
tion of the Grand (Neosho) River Basin, in the Arkansas River
watershed in Oklahoma, by construction of a concrete gravity-type
dam 2,900 feet long at the top, rising 110 feet above the stream bed,
with a reservoir providing for the storage of 922,000 acre-feet for
flood control and 365,000 acre-feet for power storage. The project
will include a powerhouse structure housing the hydroelectric generat-
ing equipment, a gate-controlled spillway, and two nonoverflow abut-
ment sections. The powerhouse structure will be located on the left
bank of the existing river channel with the spillway structure ex-
tending across the river channel and a major portion of the right
bank flood plain. The entire dam structure will be topped by a road-
way. The reservoir will be operated as a unit of the three-reservoir
                FLOOD CONTROL---TULSA,           OKLA.,   DISTRICT                  899

system for dual-purpose flood control and hydroelectric power on the
lower Grand (Neosho) River, and as one unit in the comprehensive
plan for flood control of the Arkansas River Basin.
   The estimated costs, revised in 1942, are $16,250,000 for construc-
tion and $5,185,000 for lands and damages, a total of $21,435,000.
   The existing project was authorized by the Flood Control Act ap-
proved August 18, 1941. (See H. Doc. No. 107, 76th Cong., 1st sess.,
which contains the latest published maps.)
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during.fiscal year.-Acquisition of lands and
rights-of-way in the reservoir area, limited to specific curtailment re-
quirements, was continued. Preparation of construction plans and
specifications was continued. Existing Government buildings and
access roads were repaired and kept in a serviceable condition.
   The cost during the fiscal year was $711,705.07; the expenditures
were $717,996.76, all for new work.
   Condition at end of fiscal year.-Preparation of construction plans
and specifications is substantially complete. Land acquisitions are
approximately 40 percent complete. Government buildings and access
roads to the dam site are complete. The work remaining to be done to
complete the project consists of the completion of construction plans
and specifications, completion of land acquisitions, relocation of high-
ways, railroads, and utilities, and construction of the dam and ap-
purtenant works.
   The total cost of the project to the end of the fiscal year was
 $1,830,585.25; the expenditures were $1,836,784.99, all for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
 $488,215.01, and accounts receivable $9,908.66, plus the sum of $103,000
allotted in July and August 1944, a total of $601,123.67, will be
applied as follows:
Accounts payable, June 30, 1944 -----------------------------                 $3, 708. 92
New work:
    Engineering, design, and studies, by hired labor, July 1944 to
      May 1945 -----------------------------------------                      82, 963. 10
    Land acquisitions and relocations, by hired labor, July to
      December 1944                     -------------------------------      511, 451. 65
    Repairs and preservation of suspended project by hired labor,
      July 1944 to June 1945------------------------                            3,000. 00
          Total for all work---------------------------                      601, 123. 67
   No further construction operations are proposed for the duration
of the existing war emergency.
                             Cost and financial summary
Cost of new work to June 30, 19441111111_1                   $1, 830, 585. 25
Cost of maintenance to June 30, 1944------------------------      --------
      Total cost of permanent work to June 30, 1944 ---------             $1, 830, 585. 25
Plus accounts receivable June 30, 1944----------------- ------                  9, 908. 66
      Gross total costs to June 30, 1944------------- ---                  1,840, 493. 91
Minus accounts payable June 30, 1944 -------------------------                 3, 708. 92
      Net total expenditures-------------------------                      1,836, 784. 99
                               --------------------------
Unexpended balance June 30, 1944_                                            488, 215. 01
       Total amount appropriated to June 30, 1944-                         2, 325, 000. 00)
900         REPORT OF CHIEF OF ENGINEERS, U.                                     S. ARMY,                   1944

   Fiscal year ending June 30                1940              1941          1942                   1943              1944

Cost of new work---------------....                                       $388, 633.41        $730, 246.77          $711, 705.07
Cost of m aintenance....-   - - - - - - - - - - -           -
                                                           --          .--
                                                                      .-- - - -      -   .-   - -         . . . .. . . . .

Total expended-..................   .-.......... 368, 827.38
                               --.............                                                  749, 960.85          717,996.76
Allotted...----------------       --------------------------             8,425,000.00 -6,000,000.00                -100,000.00

Balance unexpended July 1, 1943-------------------------- $1, 306, 211. 77
      Deductions on account of revocation of allotment--------- 100, 000. 00

Net amount to be accounted for------------- --------------                                                   1, 206, 211. 77
Gross amount expended----------------------       $718, 30L 52
Less reimbursements collected---- ---------------          304. 76
                                                                                                                717 09 676

       Balance unexpended June 30, 1944__                                                                       488, 215. 01
Outstanding liabilities June 30, 1944-------------                                3, 708. 92
Amount covered by uncompleted contracts-------                                  338, 643. 50
                                                                                                                342, 352. 42
     Balance available June 30, 1944_-------                                                        ---         145, 862. 59
Accounts receivable June 30, 1944_                                                                          -     9, 908. 66

     Unobligated balance available June 30, 1944------------                                                    155, 771. 25
Amount allotted in July and August 1944--------------------                                                     103, 000. 00
         Amount available during fiscal year 1945---------------                                                258, 771. 25

Amount (estimated) required to be appropriated for completion
of existing project 1_ ____________     -    -           -__ _19, 007, 000. 00
1Exclusive of available funds..

                  13. ARKANSAS RIVER BASIN, TULSA DISTRICT

   Location.-These improvements are located on tributaries of the
Arkansas River and are in the States of Kansas and Oklahoma. More
definite locations of the individual items are given in the following
paragraph.
   Existing project.-The Flood Control Act approved June 28, 1938,
approved the general comprehensive plan for flood-control and other
purposes in the Arkansas River Basin, as set forth in Flood Control
Committee Document No. 1 (75th Cong., 1st sess.), with such modi-
fications thereof as in the discretion of the Secretary of War and the
Chief of Engineers may be advisable, and authorized the sum of
$21,000,000 for reservoirs, for the initiation and partial accomplish-
ment of the plan, the reservoirs to be selected and approved by the
Chief of Engineers, subject to the provision that the authorization
shall include the Canton Reservoir on the North Canadian River in
Oklahoma, as set forth in House Document No. 569 (75th Cong.,
3d sess.). The Flood Control Act approved August 18, 1941, modi-
fied the general comprehensive plan for the Arkansas River Basin
to include the reservoirs in the Grand (Neosho) River Basin in Okla-
homa and Missouri and in the Verdigris River Basin in Kansas, in
accordance with the recommendations of the Chief of Engineers in
House Documents Nos. 107 and 440 (76th Cong., 1st sess.), and in
addition to previous amounts authorized to be appropriated the sum
of $29,000,000 for the prosecution of the comprehensive plan. The
reservoirs included in the comprehensive plan within the limits of the
Tulsa district are listed below:
                                                                                                                                                                                    Estimated cost

           Reservoir     Reservoir            River
                                              River
                                                                   Distance
                                                                    mouth
                                                                    above             Naettw
                                                                                      Nearest   town                dam andheight
                                                                                                                   Maximum  type of                capacity
                                                                                                                                                   Reservoir     delo-Cntu-
                                                                                                                                                                  Power
                                                                                                                                                                 develop-
                                                                                                                                                                   ment
                                                                                                                                                                   mouthdy
                                                                                                                                                                                         amns
                                                                                                                                                                                           d
                                                                                                                                                                           Construc- damages,              Total
                                                                                                                                                                             tion       and relo-
                                                                                                                                                                                         cations

                                                                       Miles                                                                       Acre-feet     Kilowatts
Canton 1-_         -
Mannford. ---------------
                         - -          North Canadian-----    ......---
                                      Cimarron ---------------
                                                                         393
                                                                          20
                                                                                Canton, Okla .---------...... 68 feet-earth-fill ...
                                                                                Mannford, Okla--...           120 feet-earth-fill         _....
                                                                                                                                                      390, 000
                                                                                                                                                      600,000
                                                                                                                                                                    (2)
                                                                                                                                                                    (2)
                                                                                                                                                                           $13, 220, 000
                                                                                                                                                                             6,100,000
                                                                                                                                                                                            $650, 000
                                                                                                                                                                                           1,800, 000
                                                                                                                                                                                                         $13, 870,000
                                                                                                                                                                                                            7, 900,000    O
                                                                                                                                                                                                                          0
Toronto__-----------------            Verdigris ---------------- 271            Toronto, Kans --.....         85 feet-earth-fill .......              195, 000      (2)      4, 815, 000   3, 287,000       8,102,000     0
Fall River ....                       Fall River .-------------- 54
                           ....---------------                                  Fall River. Kans-....         94 feet-earth-fill--------........      263, 000      (2)      8, 335, 000   1,130, 000       9. 465, 000
Oologah._ ---                     .-- Verdigris
                                          ri         --..
                                                      -      -- -87             Oologah, Okla ....---------   100 feet-earth-fill ......              815, 000
                                                                                                                                                      650, 000
                                                                                                                                                                    (3)      4, 745, 000
                                                                                                                                                                             8,090, 000
                                                                                                                                                                                           3, 600, 000
                                                                                                                                                                                           1, 700,000
                                                                                                                                                                                                            8, 345.000
                                                                                                                                                                                                            9, 790. 000
                                                                                                                                                                                                                          0
Tenkiller Ferry --                 -. Illinois_ ....      ------          13    Vian, Okla                    160 feet-earth-fill ..--                              (3)
                                                                                                                                                                                                                          z
Wister---
        _.....-_.....                 Poteau------------------            61    Wister, Okla-.....            83 feet-earth-fill .--------.....       430, 000      (2)      4, 765,000    1, 710, 000      6, 475,000
Neodesha ---.....             .... Verdigris---------------- 223                Neodesha, Kans:-....... 35 feet-earth-fill--........                   90, 000      (2)      3, 785. 000   1,372, 000       5, 157, 000   HV
Elk City (Table Mound) --             Elk_ ------                    - -   9    Independence,   Kans    ...   55 feet-earth-fill....-------           250,000       (2)      6, 836,000    2, 479, 000      9. 315,000    0T
                                                                                                                                                                                                                          CI
Markham Ferry 1-.-...-....            Grand (Neosho) ---------            46    Locust Grove, Okla ..         90 feet-concrete earth-.                420, 000     40, 000 14, 645, 000    4, 650, 000     19, 295, 000
Fort Gibson i-                        _ do      ..-------------------
                                            .-----                        7.7   Ft. Gibson, Okla ......- 110 feet-concrete gray-                   1, 287, 000     45, 000 16, 250,000     5, 185, 000    21, 435,000
                                                                                                                ity.

    1For details    of this project, see individual report.
    8
    2 None.
      Includes provision for future power installation.                                                                                                                                                                   00
902         REPORT OF CHIEF OF ENGINEERS,                                U.       S. ARMY,                1944

   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-Operations during the
fiscal year consisted of the preparation of preliminary plans and esti-
mates, foundation investigations, engineering studies and surveys in
connection with the general comprehensive plan by hired labor.
   The cost during the fiscal year was $97,982.37; the expenditures were
$92,708.97, all for new work.
   Conditions at end of fiscal year.-Surveys, studies, and detailed plans
were well advanced at the end of the fiscal year for development of
the general comprehensive plan for flood control and other purposes.
   The total cost to the end of the fiscal year was $528,238.93; the
expenditures were $523,114.63, all for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
$414,385.37, plus the amount of $330,000 allotted in July 1944,
will be applied as needed during fiscal year 1945 to payment
of expenses incurred for engineering studies, surveys, detailed plans,
and construction plans and specifications in connection with the gen-
eral comprehensive plan for flood control in the Arkansas River Basin.
   The additional sum of $340,000 can be profitably expended during
the fiscal year 1946 for continuation of the development of the com-
prehensive plan for flood control and other purposes in the Arkansas
River Basin.
                                    Cost and financial summary
Cost of new work to June 30, 1944_                               --                                        $528, 238. 93
Cost of maintenance to June 30, 1944
       Total cost of permanent work to June 30, 1944------------ 528, 238. 93
Plus accounts receivable June 30, 1944-------------------------    4, 386. 37

      Gross total costs to June 30, 1944----------------- ---- 532, 625. 30
Minus accounts payable June 30, 1944-------------------------    9, 510. 67
      Net total expenditures-------------------------                                                        523, 114. 63
Unexpended balance June 30, 1944---------------------                                                        414, 385. 37
           Total amount appropriated to June 30, 1944--------                                                937, 500. 00


   Fiscal year ending June 30           1940            1941                   1942               1943                   1944

Cost of new work      . _ ....
                     _--            $271,011.50      $101,271.14       $11,841. 36                $11,502.46            $97,982.37
Cost of m aintenance               . . . . . . . . . . ...     . . . . . . . . .. . .             . . .    . .   ..-.      . .
               ....
Total expended----------------       279, 729. 51      89, 969. 61        14,117. 60               12, 020. 70          92, 708. 97

Allotted   ---------------------     317,125. 00    -240, 000. 00        -5,     000. 00          450, 000.00           25, 000.00



Balance unexpended July 1, 1943 ---------------------------                                                $482, 094. 34
Amount allotted frc:m War Department Civil Appro-
  priation Act approved June 24, 1940--- ---------                                    $10, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941-- -----------                                     25, 000. 00
                                                                                           135,                         000. 00
      Amount to be accounted for---------------------------                                                  517, 094. 34
Deductions on account of revocations of allotment---------------                                              10, 000. 00
           Net amount to be accounted for-.                           ..------------                         507, 094. 34
                    FLOOD          CONTROL-TULSA,              OKLA.,         DISTRICT              903

Gross amount expended_                            ------- -_                  $93, 159. 52
Less reimbursements collected------_                                     -         450. 55
                                                                                             $92, 708. 97

      Balance unexpended June 30, 1944_                                                      414, 385. 37
Outstanding liabilities June 30, 1944           ---------------                $9, 510: 67
Amount covered by uncompleted contracts---------                               30, 051. 97
                                                                                              39, 562. 64

      Balance available June 30, 1944_--                        --------                     374, 822. 73
Accounts receivable June 30, 1944_---------                                          ---       4, 386. 37
     Unobligated balance available June 30, 1944                     --------------          379, 209. 10
Amount allotted in July 1944__------------_
                                _--330,                                                           000. 00

        Amount available during fiscal year 1945                ----------------             709, 209. 10

Amount that can be profitably expended in fiscal year ending June
  30, 1946, for new work            1     ______--------            -------                  340, 000. 00
1 Exclusive of available funds.


14. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
         FLOOD CONTROL ACT APPROVED AUGUST 18, 1941

   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work, or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood. Pursuant to this act, the amount of $50,000 was allotted to
the Tulsa district in June 1943 for emergency repairs and rescue work.
   Actual operations began in the latter part of fiscal year 1943 and
consisted of placing approximately 50,000 cubic yards of fill material
to repair levees damaged by the spring flood of 1943. Operations
performed under this allotment are complete. The cost during the
fiscal year was $47,037.05; the expenditures were $45,943.49, all for
repairs and rescue work. The balance unexpended on June 30, 1944,
amounting to $4,056.51, will be applied to outstanding liabilities.
   In addition to the above, funds were allotted under the provisions
of section 9 of the Flood Control Act approved June 15, 1936, for
emergency flood-control work in the Tulsa district. For further in-
formation, see Mississippi River Commission report, emergency work
on tributaries of Mississippi River.
                                        Cost and financial summary
Cost of new work to June 30, 1944___
Cost of maintenance to June 30, 1944_-------                                       ---       $47, 037. 05
      Total cost of permanent work to June 30, 1944------------- 47, 037. 05
Minus accounts payable June 30, 1944_-              -    _____       093. 56                   1,
      Net total expenditures_----------                                           ----        45, 943. 49
Unexpended balance June 30, 1944-____   _-----                                     ----        4, 056. 51

        Total amount appropriated to June 30, 1944                    -------------           50, 000. 00
904              REPORT OF CHIEF OF ENGINEERS,                                        U. S. ARMY,                   1944


     Fiscal year ending June 30                       1940             1941               1942             1943              1944

Cost of new work ...       ..       ..                  ..   -         ..     .       .    ...        - -       .
Cost of maintenance__           ...-------------.--.......                                              .----...
                                                                  .... ---------------------------------------              $47, 037.05
Total expended.......------------------...
                                      __ --...-                  ----------------------------             .     ..
                                                                                                     --------------          45, 943.49
Allotted------------....    --           --..   ---------------------------------------                     $50, 000


Balance unexpended July 1, 1943__--   -----------             $50, 000. 00
Gross amount expended -------------------------- $45, 963. 08
Less reimbursements collected-----------------------   19. 59
                                                               45, 943. 49

      Balance unexpended June 30, 1944___-------                                                            -              4, 056. 51
Outstanding liabilities June 30, 1944                            --------------                    $1, 093. 56
Amount covered by uncompleted contracts                                     ------------             1, 868. 77
                                                                                                                           2, 962. 33

              Balance available June 30, 1944_--------                                                    ---              1, 094. 18

     15. EMERGENCY FLOOD CONTROL WORK UNDER AUTHORITY OF
        PUBLIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods which
occurred in the spring of 1943 and again in the spring of 1944, Con-
gress, in the act approved July 12, 1943, Public No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public No.
318, Seventy-eighth Congress, authorized the amounts of $10,000,000
and $12,000,000, respectively, to be appropriated as emergency funds
to be expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See p. 9 for details.)
Pursuant to the act approved July 12, 1943, the amount of $205,000
was allotted in fiscal year 1944 for emergency repair work on flood-
control structures damaged or destroyed by the spring floods of 1943
in the Tulsa district.
   Actual operations began in the early part of fiscal year 1944 and
consisted mainly of placing approximately 200,000 cubic yards of fill
material for repair, restoration, and strengthening of levees threat-
ened or destroyed by the spring floods of 1943. Operations performed
under this allotment are substantially complete as a whole. The cost
during the fiscal year was $154,734.70; the expenditures were
$141,184.45, all for repairs and restoration.
   The balance unexpended on June 30, 1944, amounting to $63,815.55,
will be applied to the payment of expenses incurred under this head-
ing. The amount of $305,000 was allotted in July 1944 for emergency
flood-control work in the Tulsa district pursuant to the act approved
May 29, 1944.
                         FLOOD CONTROL---TULSA,                            OKLA.,           DISTRICT                                   905
                                         Cost and financial summary
Cost of new work to June 30, 1944--
Cost of maintenance to June.30, 1944_ --------                                                              -         $154, 734.70
       Total cost of permanent work to June 30, 1944------------   154, 734. 70
Plus accounts receivable June 30, 1944_ --     ---     ---     ---       78. 64
      Gross total costs to June 30, 1944- - --------                                                                    154, 813. 34
Minus accounts payable June 30, 1944 ------------------------                                                            13, 628. 89
     Net total expenditures ___-- ------------                                                                          141, 184. 45
Unexpended balance June 30, 1944_-      - ----------                                                                     63, 815. 55
          Total amount appropriated to June 30, 1944--------------                                                     205, 000. 00


   Fiscal year ending June 30                1940                   1941            1942                    1943                1944

Cost of new work.................-             .       . ..............                            ......             ............
Cost of maintenance--           .....--------------.....----------------------------                 -------------            $154, 734. 70
Total expended.....---------------           ------------------            ----------------------------                         141, 184.45

Allotted- ---                                ----------------------------------------------                                     205, 000.00


Amount allotted from Second Deficiency Appropriation Act ap-
  proved July 12, 1943___                                        $205,000. 00
Gross amount expended_    -------             ---  $141, 888. 75
Less reimbursements collected---------------------       704. 30
                                                                                                                       141. 184. 45
       Balance unexpended June 30, 1944 ..           _______                                                              63, 815. 55
Outstanding liabilities June 30, 1944---------------- 13, 628. 89
Amount covered by uncompleted contracts---------      27. 605. 24
                                                                                                                          41, 234. 13


      Balance available June 30, 1944_-------                                                               ---           22, 581. 42
Accounts receivable June 30, 1944_---------                                                                    ----            78. 64
     Unobligated balance available June 30, 1944--------------                                                          22, 660. 06
Amount allotted in July 1944_---------                ----                                                             305, 000. 00
          Amount available during fiscal year 1945 ----------------                                                    327, 660. 06

16. PRELIMINARY                      EXAMINATIONS, SURVEYS,                                AND CONTINGENCIES
                                         FOR FLOOD CONTROL

   The cost of work during the fiscal year was $190,654.85; the expendi-
tures were $196,589.64. The balance unexpended on June 30, 1944,
$42,874.43, and accounts receivable, $3,032.21, plus the sum of $100,000
allotted in July 1944, a total of $145,906.64, will be applied as needed
during fiscal year 1945 to payments of expenses to be incurred under
this heading.
   The additional sum of $160,000 can be profitably expended during
the fiscal year 1946.
906          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                            1944

                                          Cost and financial summary
Cost of new work to June 30, 1944____--
                                                                                                      ---
                                                                                                                  -----------
                                                                                                                    $738,829.82
Cost of maintenance to June 30, 1944_-------
       Total cost of permanent work to June 30, 1944------------                                                        738, 829. 82
Undistributed costs June 30, 1944__--     ----------                                                                         829. 31

       Net total cost to June 30, 1944_-------            ---   739, 659. 13
Plus accounts receivable June 30, 1944-------------------------   3,032.21

      Gross total costs to June 30, 1944_------        ---    742, 691. 34
Minus accounts payable June 30, 1944-------------------------      752. 75

      Net total expenditures_   -------------------                                                                     741, 938. 59
Unexpended balance June 30, 1944----------------------------                                                             42, 874. 43

           Total amount appropriated to June 30, 1944                               --------------                      784, 813. 02


    Fiscal year ending June 30               1940              1941                  1942                  1943                  1944

Cost of new work .-----------.---                                                            ...
                                                                                            ---...    .     .     .     ...       .   .   .
Cost of maintenance .......-----------.   $268,775. 85       $81,295. 74        $30, 449.69           $12, 608.39              $190, 654. 85

Total expended      ----------------
                       . ...               269, 526. 11       82, 544. 50           28, 426. 60            9, 038. 72            196, 589. 64
Allotted    ---------------------          158, 000.00    ------------              10, 000. 00           96,000-0.0             107, 500.00


Balance unexpended July 1, 1943-__                               $131,964.07
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941-----------   $40,000.00
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942 --
Amount allotted from War Department Civil Appro-
                                                      583. 80            -41,
  priation Act approved June 2, 1943 _..          23, 916. 20
Amount allotted from War Department Civil Appro-
  priation Act approved June 11, 1938              2,---------2000.00
                                                                  107, 500. 00

       Amount to be accounted for---------------------                                                                   239, 464.07
Gross amount expended--- --------                   $198,700.20
Less reimbursements collected_-    --------            2, 110. 56
                                                                                                                         196, 589. 64
      Balance unexpended June 30, 1944----------------                                                                        42, 874. 43
Outstanding liabilities June 30, 1944                     ---------------
                                                     $752. 75
Amount covered by uncompleted contracts                284. 85    ----------
                                                                                                                               1, 037. 60
      Balance available June 30, 1944_--                                        -           --       ____                     41, 836. 83
Accounts receivable June 30, 1944-------____                                                                                   3, 032. 21
     Unobligated balance available June 30, 1944--------                                                                  44, 869. 04
Amount allotted in July 1944_---------                 ----                                                              100, 000. 00
           Amount available during fiscal year, 1945-----                                -----                           144, 869. 04
Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1_--  --- ____-_____-                                                                    160, 000. 00
   1Exclusive of available funds.
                               FLOOD CONTROL--TULSA,                                       OKLA., DISTRICT                                               907
            17. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO
                        ESTIMATES ARE SUBMITTED

                                                                           For last full               Expenditures to                        Estimated
                                       project
                                      Name
                                      Name  of
                                       project
                                            of                              report see                  June 30, 1944                         amount re-
                                                                           Annual Re-                                                          quired to
                                                                           port for _           New work            Maintenance                complete


            ARKANSAS RIVER, MAIN STEM AND
                  MINOR TRIBUTARIES
1. Kaw, Okla.2.---................................                              1937           ...........-------------..---------------..         $32, 500
2. Near Fort Gibson in Muskogee County,                                         1937-        ..............       -----                             33,600
      Okla.2                                     -- -- -- -- -- - -
3. Big Slough to Belle  - - - - - - - Kans.2
                   3 - - Plaine,       - - - - - -............
                                                   - - -- -- -- -- -             1937 -----------------------------                               1,650,200
4. Augusta, Kans. 3-.                                     - - - - - -- -                 ..............------......------------
                                                                                 1938------------                                                  (4)
5. Winfield, Kans. __                _.      _._.. .                            1937   -------------- --------------                              (4)
6. Optima Reservoir, North Canadian River,                                      1938-    ......---.--              .--------.                    6, 700,000
      Okla.
                    GRAND (NEOSHO) RIVER

7.   Pensacola Reservoir, Okla_----. .---.-.-.--                             1942           $42,386. 55 --------------                           (s)
8.   Florence, Kans.2 -------                                                1937     ..........................                                    17, 000
9.   Cottonwood Falls,   - - -Kans......
                               - -- --     - - ---...........
                                                 - -- -- - - - - -- -- -      1937                                        --------------...
                                                                                          ..................--------------...                          7, 200
10.   Emporia, Kans.                                          2- - -- -- - -  1937   ----------------------------                                    22,700
11.   Neosho Rapids, Lyon County, Kans. ......                                1937     ........................                                      38, 900
12.   Lyon County, Kans.2......................                                        ..............---............
                                                                              1937-----------                                                       237, 100
13.   Hartford, Kans.2-----..................---------------------            1937      ..........-------------..........------------                43, 200
14.   Burlington, Kans.2--           ----------------------                  1937    ----------------------------                                    27,000
15.   Leroy, Kans.2-------- -------------------- 2 -                         1937                .....
                                                                                       ----------------------------                                    9, 600
16.   Neosho Falls, Woodson County, Kans. .....                               1937--        ...-...                       .-----.----.-              32, 400
17.   Humboldt, Kans.2  2        -
                                    ---------------------
                                    -   -    -          -       -   --       11937
                                                                               937   -----------------------------
                                                                                        - - -- --- -- - -- - -- -- - -- -- -- --              -      19,
                                                                                                                                                     2 8 , 300
                                                                                                                                                           600
18.   Chetopa, Kans.                                                   -                                     .
19.   Cherokee County, Kans.'_------------------1937 --                                                               __---         _____           234, 000
20.   Iola, Kans...------------------------------.................            1939              20,989.80-------      .............                (4)
                          VERDIGRIS RIVER
21. Verdigris
            2 River from mouth to Madison,                                             ..............---...---......-----------
                                                                                 1938------------                                                  (4)
      Kans.
22. West of Fredonia, Wilson County, Kans.2_....
                                           2                                     1937            ...                         ..
                                                                                                                  ...-------------- ....            189, 900
23. West of Benedict, Wilson County, Kans. ...                                   1937--       ._.........._ ___               .    .....            195, 000
24. West of2 Elk City, Montgomery County,                                        1937--         ..-.      ---..........-.....                        81,400
      Kans.
25. Caney Creek, Washington County, Okla.,                                       1937        ...........    ...........
                                                                                          ------------------------------                            157,600
     and Chautauqua and Montgomery Coun-
     ties, Kans.2

              SALT FORK OF ARKANSAS RIVER

26. Blackwell, Okla.2                                         _--------------------------1937--------------.--------------                               50,000

  1In 1937 the projects were reported by the Memphis district; in 1938 and 1939 by the Little Rock district.
  2 Awaiting local cooperation.
  3 Project completed by Kansas Works Progress Administration.
  4 Complete.
  6 Transferred to Federal Works Agency in February 1943.

  6 Some work on this project was done. by Wilson County (Kans.) Civil Works Administration in 1933
and 1934.

                   18. PLANT ALLOTMENT,                                         TULSA, OKLA., DISTRICT
                                                      Cost and financial summary
Undistributed costs June 30, 1944_                                        -         --------                                  --      $448, 148. 10
Net total cost to June 30, 1944__ --    ---------                                                                               --         448, 148. 10
Plus accounts receivable June 30, 1944_ ------                                                                      ---                    155, 837. 98
Gross total costs to June 30, 1944-----------_                                                                                       - 292, 310. 12
Minus accounts payable June 30, 1944                                          ---------------------                                  --- 68, 933. 29
Net total expenditures ---------------------------------                                                                           --- 361, 243. 41
Unexpended balance June 30, 1944_-----       --- __ -----                                                                              546, 243. 41
Total amount appropriated to June 30, 1944 ------------------                                                                              185, 000. 00
908         REPORT OF CHIEF OF ENGINEERS, U.                               S. ARMY,           1944


   Fiscal year ending June 30            1940

Total expended ....----------------    $2, 929.19
Allotted...---------------------185, 000.00


Balance unexpended July 1, 1943__--- ------.---                                     _          $620, 866. 53
Gross amount expended--                         -$1,                       712, 132. 16
Less reimbursements collected-----------------1,                           637, 509. 04
                                                                                                 74, 623. 12
      Balance unexpended June 30, 1944                    --------------------                  546, 243. 41
Outstanding liabilities June 30, 1944------------                          $68, 933. 29
Amount covered by uncompleted contracts                                    127, 005. 14
                                                                                                195, 938. 43
      Balance available June 30, 1944_-                                      __           -     350, 304. 98
Accounts receivable June 30, 1944_---------                                         ---         155, 837. 98
     Unobligated balance available June 30, 1944                         ------------           506, 142. 96
Amount revoked in August 1944 ----------------------------                                      270, 392. 96
         Amount available during fiscal year 1945                 ---------------               235, 750. 00

   Status of all investigations for flood control called for by flood control acts and
                                  committee resolutions

                                                           Date trans-                          Recommenda-
           Locality               Authorization act         mitted to       Document No.        Recommenda
                                                            Congress

Arkansas River and tribu-        Flood Control Com-       Feb. 17, 1944    H. 447, 78th Cong., I Favorable.
  taries (local flood protec-      mittee resolution,                       2d sess.           I
  tion along main stem, from       July 2, 1943.
  Pine Bluff, Ark., to Great
  Bend, Kans.).
Arkansas River and tribu-        Commerce Commit-
  taries, Okla., hydroelec-       tee resolution, Oct.
  tric potentialities (under      12, 1938.
  Division Board).
Arkansas River for flood         Flood Control Com-
  control at and in the vicin-     mittee resolution,
  ity of Hutchinson, Kans.         Jan. 21, 1944.
Arkansas River and tribu-        Flood Control Com-
  taries from Hutchinson,          mittee resolution,
  Kans., to the Kansas-Ok-         June 21, 1944.
  lahoma State line.
Arkansas River and tribu-        Flood Control Com-
  taries, flood control on         mittee resolution,
  Lightning, Labette, and          Apr. 13, 1938.
  Flat Rock Creek, Kans.
Arkansas River and tribu-        Flood Control Com-
  taries; and the Walnut           mittee resolution,
  River and its tributaries,       May 5, 1944.           -- -- -- -- --
  Kansas, for flood control
  at and in the vicinity of
  Arkansas City, Cowley
  County, Kans.
Beaver River, Okla.........      Flood Control Act,
                                   Aug. 28, 1937.
Canadian River and its trib-     Commerce Commit-
  utaries, Texas and Okla-         tee resolution, June
  homa.                            5, 1944.
Cimarron     (Dry) River,        Flood Control Act,
  Union County, N. Mex.            June 22, 1936.
Cimarron River, Okla. and        Flood Control Act,
  Kans.                            Aug. 28, 1937.
Deep Fork, Okla., for flood      Flood Control Com-
  control.                         mittee resolution,
                                   Feb. 23, 1944.
Dirty Creek, Muskogee            Flood Control Act,
County, Okla.                     Aug. 11, 1939.
Dogy and Clear Creeks,           Flood Control Act,
tributaries of Arkansas           Aug. 18, 1941.
River, Okla.
Eufaula Reservoir, Okla.,
on South Canadian River.
                                 Flood Control Act,
                                   June 22, 1936.         I----
                         FLOOD CONTROI---TULSA,               OKLA.,       DISTRICT                    909
  Status of all investigations for flood control called for by flood control acts and
                         committee resolutions-Continued

                                                         Date trans-                            Recommenda-
          Locality               Authorization act        mitted to        Document No.             tion
                                                          Congress

Grand (Neosho) River and       Flood Control Act,
  tributaries,   Oklahoma,       Aug. 28, 1937.
  Kansas, Missouri, and
  Arkansas.
Grand (Neosho) River,          Flood Control Act,
  Morris County, Kans.           June 22, 1936.
Kenton Reservoir, Cimar-
  ron River, Okla.
                               Flood Control Act,
                                 June 22, 1936.
                                                        ---------------I------------------
Little River Watershed,        Commerce Commit-
  Okla., tributary of the        tee resolution, Jan.
  Arkansas River.                15, 1944.
Little River Watershed,        Flood Control Com-
  Okla., for flood control       mittee resolution,
  and allied purposes.           Feb. 23, 1944.
Mannford Reservoir, Cim-       Flood Control Act,
  arron River, Okla. (under      June 22, 1936.
  Division Board).
North Canadian. River,         Flood Control Act,       -- - -- - - --    -- - - -- - -- - -
  Okla. and Tex.                 Aug. 28, 1937.
Oologah Reservoir, Verdi-      Flood Control Act,
  gris River, Okla.              June 22, 1936.
Polecat     Creek,     Creek   Flood Control Com-                        --------------------
  County, Okla., tributary       mittee resolution,
  of Arkansas River.             July 23, 1941.
Polecat     Creek,     Creek   Flood Control Act,       --------------- --------------------
  County, Okla.                  Aug. 18, 1941.
Poteau River, Ark-.......      Flood Control Act,       --------------- --------------------
                                 June 22, 1936.
   Do......          _         Flood Control Act,       ------------------------------------
                                Aug. 28, 1937.
Poteau River, Le Flore         Flood Control Com-                        --------------------
  County, Okla. (under          mittee resolution,
  Division Board).               Feb. 10, 1938.
Salt Creek of Arkansas         Flood Control Act,
  River and tributaries,        Aug. 18, 1941.
  Osage County, Okla.
South Canadian        River,   Flood   Control Act,
  Okla.                         Aug. 28, 1937.
South Canadian        River,   Flood Control Com-
  N. Mex., Tex., and Okla.,      mittee resolution,
  for construction of a dam      Jan.21, 1944.
  at or in the vicinity of
  Sanford, Tex.
Tenkiller Ferry Reservoir      Flood Control Act,
  on Illinois River, Okla.       June 22, 1936.
Verdigris River, Kans. and     Flood Control Com-
  Okla.                          mittee resolution,
                                 Apr. 23, 1942.
Wister Reservoir on Poteau     Flood Control Act,
River, Okla. (under Divi-       June 22, 1936.
sion Board).

   IMPROVEMENT OF RIVERS AND HARBORS IN THE
          ST. LOUIS, IVMISSOURI, DISTRICT
   This district comprises those portions of southwestern Illinois and
eastern Missouri embraced in the drainage basin of the Mississippi
River and its western tributaries, exclusive of the Missouri River,
between the mouth of the Ohio River and mile 300 above the same,
and of its eastern tributaries to Hamburg Bay at mile 261 on the left
bank, exclusive of the tributary basin of the Illinois Waterway up:
stream of the new La Grange Lock and Dam at mile 80.15 above the
confluence of the Illinois and Mississippi Rivers. The district also
includes the drainage basin in Missouri tributary to the Little River
Diversion Channel. Report on Mississippi River between the Mis-
souri River and mile 300 is included in the report on Mississippi River
between Missouri River and Minneapolis, Minn. Report on that por-
tion of the Illinois River downstream of the new La Grange Lock
910      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                          1944

and Dam is included in report on Illinois Waterway, Ill., contained
in the report of the district engineer, Chicago, Ill.
  District engineer: Col. Lawrence B. Feagin, Corps of Engineers.
  Division engineer: Col. Malcolm Elliott, Corps of Engineers.
                                        IMPROVEMENTS

                Navigation                               Flood control-Continued
                                          Page                                          Page
1. Mississippi River between                    12. Columbia drainage and levee
       the Ohio and Missouri                           district No. 3, Illinois _ _-     925
       Rivers_____________                 910   13. Wilson and Wenkel and
2. Mississippi River between                          Prairie du Pont drainage
       the Missouri River and                          and levee districts, Illinois_    927
       Minneapolis, Minn. (St.                   14. East St. Louis and vicinity,
       Louis district)                     939         Illinois _                        928
3. Illinois Waterway, Ill. (St.                 15. Wood River drainage and
       Louis district)                   1371          levee district, Illinois ..       930
4. Examinations, surveys,      and              16. Meredosia Lake and Willow
       contingencies (general)  ---        917         Creek drainage and levee
                                                       districts, Illinois River,
5. Other navigation projects for
       which no estimates are                          Ill----                           931
       submitted                           918   17. Seahorn drainage and levee
                                                       district, Illinois_               932
6. Plant allotment                        918                                  River
                                                 18. Upper      Mississippi
                                                       Basin, St. Louis district. -      933
               Flood control                     19. Emergency flood-control
7. East Cape Girardeau and                            work under authority of
                                                       the Flood Control Act
      Clear Creek drainage dis-
                                           919         approved August 18, 1941_         935
      trict, Illinois_
                                                 20. Emergency flood-control
8. Clear Creek drainage and                           work under authority of
      levee district, Illinois .....       920         Public Laws Nos. 138 and
9. Preston drainage and levee                         318, Seventy-eighth Con-
      district, Illinois .....             922         gress      . .     .-- -    -     936
10. Perry County drainage and                    21. Preliminary      examinations,
      levee districts Nos. 1, 2,                       surveys, and contingencies
      and 3, Missouri .........            923         for flood control-                937
11. Harrisonville and Ivy Land-                  22. Other flood-control projects
      ing drainage and levee                           for which no estimates are
      district No. 2, Illinois - .- -      924         submitted                         938

  1. MISSISSIPPI RIVER BETWEEN THE OHIO AND MISSOURI RIVERS

   Location.-The Mississippi River rises above Lake Itasca, Minn.,
and, from that lake, flows in a southerly direction about 2,450 miles
and empties into the Gulf of Mexico. The portion included in this
report embraces the 195-mile section known as the middle Mississippi,
between the tributary Ohio and Missouri Rivers, about 1,081 to 1,276
miles from the Gulf.
   Previous projects.-The original project for the improvement of
the Mississippi River between the Ohio and Missouri Rivers was
recommended by a Board of Engineers in a report, dated April 13,
1872, and concurred in by the Chief of Engineers. For further details
:see page 1879 of the Annual Report for 1915 and page 1014 of the
Annual Report for 1938.
   Existing project.-This provides for obtaining and maintaining a
minimum channel depth of not less than 9 feet, a minimum width of
not less than 300 feet at low water, with additional width in bends
               RIVERS     AND HARBORS-ST.                  LOUIS, MISSOURI,             DISTRICT         911
from the mouth of the Ohio River (about 1,081 miles from the Gulf)
to the northern boundary of the city of St. Louis, 191 miles; thence
200 feet wide, with additional width in bends to the mouth of the Mis-
souri River, 4 miles; all to be obtained by regulating works and dredg-
ing: First, by regulating works, for closing sloughs and secondary
channels, and narrowing the river; by building new banks where
the natural width is excessive and protecting new and old banks from
erosion where necessary to secure permanency. Second, by dredging
or other temporary expedients to maintain channels of project
dimensions.
  The estimated cost of new work, revised in 1934, is $43,000,000, with
$1,300,000 for annual maintenance.
  The existing project was authorized by the following river and
harbor acts:

       Acts                        Work authorized                                   Documents


         .......   Project for regulating works adopted in 1881.        Annual Report, 1881, p. 1536.
                     (To obtain a minimum depth of 8 feet.)
June     3, 1896
June 13, 1902      Dredging introduced as part of the project ...
Mar. 2, 1907
Mar. 3, 1905 1     These acts practically abrogated that part of the
Mar. 2,19071        project for the middle Mississippi which pro-
                    posed regulating works.
June 25, 1910      Regulating works restored to the project and ap-     H. Doc. No. 50, 61st Cong., 1st sess.,
                    propriations begun with a view to the comple-         and H. Doc. No. 168, 58th Cong.,
                     tion of the improvement between the Ohio and         2d sess.
                     Missouri Rivers within 12 years at an esti-
                     mated cost of $21,000,000, exclusive of amounts
                     previously expended.
Jan. 21, 1927      For a depth of 9 feet and width of 300 feet from     Rivers and Harbors Committee Doc.
                     the Ohio River to the northern boundary of the      No. 9, 69th Cong., 2d sess.
                     city of St. Louis, with the estimated cost of
                    maintenance increased to $900,000 annually.
July    3, 1930    Project between the northern boundary of the         Rivers and Harbors Committee Doc.
                     city of St. Louis and Grafton (mouth of Illinois    No. 12, 70th Cong., 1st sess.
                     River) modified to provide for a channel 9 feet
                    deep and generally 200 feet wide with addi-
                     tional width around bends, at an estimated
                     cost of $1,500,000, with $125,000 annually for
                    maintenance.


  SAlso joint resolution, June 29, 1906.


   See House Document No. 669 (76th Cong., 3d sess.) for report of
Chief of Engineers dated February 27, 1940, containing a general
plan for improvement of the Mississippi River between Coon Rapids
Dam and the mouth of the Ohio River for purposes of navigation,
power development, the control of floods, and the needs of irrigation.
   Recommended modifications of project.-Under date of March 15,
1939, the Chief of Engineers recommended modifications of the exist-
ing project to approve a comprehensive plan for development of the
Mississippi River at Chain of Rocks so as to provide for construc-
tion of a lateral canal at an estimated first cost to the United States
of approximately $10,290,000, with annual maintenance and operation

          616634-45-pt. 1, vol. 1-            58
912       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                         1944

cost of $70,000, subject to such modification as the Chief of Engineers
may find necessary when the project is undertaken; and to authorize
the relocation of the river channel and reclamation of the area in
Sawyer Benad for airport, park, recreational, and similar purposes at
a cost to local interests of approximately $17,555,000; provided that
any modification of the present river channel required by the civic
development be deferred until completion of the lateral canal in the
interest of navigation and that the river diversion work connected
with such civic development be under the supervision of the Chief
of Engineers in order to insure that the interests of interstate and
foreign commerce be properly protected; and further provided that
local interests hold and save the United States free from any claims
for damages that might be incurred due to the construction, mainte-
nance, or operation of such civic development or any part thereof
 (H. Doc. No. 231, 76th Cong., 1st sess.).
   Terminal facilities.-The water terminal and transfer facilities of
the district are fully described as of December 31, 1918, in House
Document No. 652, Sixty-sixth Congress, second session, pages 1211-
1239. Additional data for water termiinal and transportation facili-
ties are also contained in Transportation Series No. 2, 1929, Trans-
portation in the Mississippi and Ohio Valleys, and as of 1941, in
volume 1 of the four-volume report of the Board of Engineers for
Rivers and Harbors, entitled "Survey of Terminals and Landings on
the Inland Waterways of the United States."
   Operations and results during fiscal year.-Extensive construction
work was carried on throughout the first half of the fiscal year, but
during the last half of the year, practically no construction work was
done because of high river stages. A stage of 39.1 feet (9.1 feet above
flood stage) was recorded on the St. Louis (Market Street) gage on
April 30. Regulating works were maintained and project dimensions
of channels were secured by dredging. The district's standard speci-
fications for construction work were used. Location, quantities, and
costs of open river regulating works follow:

                                                                        Miles                         Dikes (hurdles)
                                                                       above
               Class of work and locality                            mouth of
                                                                        Ohio                             Linear
                                                                        River         Number               feet         Cost

New work by contract:
   Missouri Sister Island-Thompson Towhead-Brooks
    Point --------------             -      --      -18                             ------------....     ---------      $33,387.32
   Cairo Protection-Thompson Towhead-Schenimann.__                           5-58                  5        1,810        88, 414. 47
   Seventy Six-Liberty....--------------------------------                     99                  1          165        15, 863. 99
      Total--------   -----...       .--------------------------------------...                   6         1,975       137,665.78
Maintenance by United States plant and hired labor. --------------------------                              8,970    1 235, 040.04

1Includes cost of screening 9,920 linear feet of dikes with mattress lumber.
           RIVERS         AND HARBORS                          ST. LOUIS,         MISSOURI,               DISTRICT                 913

                                                                    Bank protection (revetment)
                                    Miles
         work and locality
                    of     maboveClass
                           mouth of
                                 of                                  Linear
                                                                      feet      Squaresfeet)
                                                                                         (100 square bank
                                                                                                      Toe piles
                                                                                                           pro-                  Cost
Class ofwork and locality
                                     Ohiero Number bank                                                     tection
                                         Riverprotec-                                                           linear
                                                                     tion       Mattress        Paving            feet

New work by contract:
   Cape Girardeau......      .     49.5                         1   ....           _                178- . - ...               $20,195. 75
   Cape Girardeau-Giboney
     Island-Willard...     ..   48-67                           2        810          807           295                         38, 259.80
   Wilkinson ----------...         90. 5                        1      2, 000      1, 800           667                         76, 062. 15
       Do-   - - - -        - -    91. 5                        1      1, 260      1, 260           254                         51,442. 73
   Ste. Genevieve, Ill......      125                           2      2,035       2,035          1,085         ..              93,613.99

      Total-------_               __--     --        --        7       6,105       5,902          2,479           -            279,574.42

New work by United States
  plant and hired labor:
    Cape Girardeau-----                   49. 5                 1         860         861           453   ---------
                                                                                                            ..                  35, 550. 2&
    Ste. Genevieve, Mo .                 123. 5                 1      1, 700      1, 020   -                                   35, 233. 11
      Total     .     .     ..------------------
                              __       __2                            2,560        1,881            453     .              _   70,783.39

Maintenance by United States
plant and hired labor__-.. -                    -
                                                .-        .....       3, 456       1, 164         4,539           9, 955       243, 701. 11


   New work.-Two revetments, totaling 2,560 feet in length, consisting
of 1,881 squares of mattress and 453 squares of paving were built by
hired labor with Government plant, at a cost of $70,783.39. A total of
66,969 cubic yards of material was handled by a United States hydrau-
lic dredge in preparing one locality for new regulating works at a cost
of $10,904.99, and an additional cost of $230.06 was incurred in connec-
tion with the purchase of land for regulating works. Six dikes, total-
ing 1,975 feet in length, were built under contract at a cost of $137,-
665.78. Seven revetments, totaling 6,105 feet in length, consisting of
5,902 squares of mattress and 2,479 squares of paving, were built under
contract at a cost of $279,574.42. In addition to completed work there
was under construction, by contract, two dikes to total about 2,380
linear feet. The total cost of new work was $499,208.64, from regular
funds.
   Maintenance.-Dikes and revetments were repaired at a cost of $478,-
741.15. The required 9-foot channel was maintained, except for the
short periods needed to move a dredge to the shoal, by four United
States hydraulic dredges. During the year 73 shoals developed, of
which 71 were dredged once, and 2 were dredged twice. There were
6,810,051 cubic yards of sand and gravel removed by these dredges
from the channel through 73 bars; 32,639 cubic yards of material were
removed in outside-the-channel dredging at a cost of $4,496.62. The
channels had a combined length of 26 miles, an average width of 345
feet, and an average gain in depth of 5.4 feet. The total cost of main-
tenance dredging was $531,092.86.
   Hydrographic surveys were made covering approximately 200 miles
of river, costing $68,372.26. Other miscellaneous costs were: Snag-
ging, $1.598.03; aids to navigation, $47,258.23; cooperative stream gag-
ing, $7,010.97; gages, $21,684.56; safeguarding structures, $51,894.91;
and removing grounded vessels, $4,815.39, all charged to maintenance.
The total cost of all maintenance was $1,212,468.36. The expenditures
were $1,215,608.81 from regular funds.
         616634-45-pt. 1, vol. 1-                         58
914         REPORT OF CHIEF OF ENGINEERS,                                        U. S. ARMY,             1944

      Condition at end of fiscal year.--Open river regulating works are
about 86 percent completed. The quantities required to complete the
project are estimated at 70 dikes, 58,000 linear feet; and 30 revetments,
110,000 linear feet. Dikes and revetments are now in good repair and
the channel has been greatly improved by the work that has been done.
Dredging is required at low stages to remove temporary shoals and
maintain the required channel depths.
   In recent years, the project dimensions of channels have generally
been maintained throughout the navigation season. The navigation
season formerly extended from the middle of February to the middle
of December, the river being generally closed by ice the remainder of
the year. However, in recent years navigation has continued through-
out the winter, except when the river is actually blocked by running
ice or gorges. The river is generally above the 10-foot stage, St. Louis
gage for 6 months of the year, latter part of February to latter part of
August, during which time project channel depths generally prevail
without dredging. The mean stage of the river for the fiscal year 1943
was 14.90 feet, St. Louis gage. The mean stage of the river for the
fiscal year 1944 was 12.13 feet.
   The following table gives condition of the channel during the fiscal
year 1944:
                                                                      Channel affording 1.
                                     tiofee-   9         m          Lessthan 9Con-
                  Sectione                     9 feet or more       Les ethan 9 7 feet or less         6 feet or less       trol-
                                      tion                                                                                  ling
                                                                                                                            depth

                                               Length   Pi-     Length                Length Pei- Length


Ohio River to Commercial           Miles       Miles    Days        Miles      Days   Miles    Days    Miles        Days    Feet
  Point---------...                 32.7        31.9     363          0.8         2       0      0         0           0      8
Commercial Point to Com-
  merce---------------------6.7                   5.5     363         1.2         2        0       0          0         0      8
Commerce to Grays Point-..           6.6          5.7     363            .9       2        0       0          0         0      8
Grays Point to Grand Tower          33. 7        32.9     362           .8        3        0       0          0         0      8
Grand Tower to Fort Gage-           36.3         35.9     364            .4       1        0       0          0         0      8A
Fort Gage to Little Rock .           9.5          9.5     365         0           0        0       0          0         0      9
Little Rock to River des
  Peres .........-........
                     -              46.5         45.3     364         1.2         1        0       0          0         0      8
River des Peres to Merchants
  Bridge-.-.         ---.  _--      11.2         11.2     365         0           0        0       0          0         0    11
Merchants Bridge to north-
  ern bdundary city of St.
  Louis 2-------.........      - .   8.0          8.0     365         0           0        0       0          0         0      9
Northern boundary to mouth
  of Missouri River .......          3.8          3.8     365         0           0        0       0          0         0      9

  I Project width is 300 feet from Ohio River to northern boundary of St. Louis and 200 feet from that point
to Missouri River, with additional width in bends throughout.
  2 This is known as the "Chain of Rocks Reach."


  The costs and expenditures under the existing project to June 30,
1944, have been as follows:
                                                                              Costs
               Kind of funds                                                                                      Expenditures
                                                  New work             Maintenance             Total

Regular .-------------------------              $32, 396, 384. 82 $26, 636, 620.94        $59, 033,005. 76        $59,019,696.72
Public Works- __.....--------           -         3, 462, 154. 46----             -         3, 462, 154. 46         3, 462, 154. 46
Emergency Relief .......                             996, 747. 95----------------              996, 747. 95            996, 747. 95
       Total--...............-.......... -       36, 855. 287. 23      26, 636, 620. 94    63, 491,908. 17         63, 478, 599. 13
       RIVERS AND HARBORS-ST. LOUIS, MISSOURI,                          DISTRICT        915
   Proposed operation.- The unexpended balance at the end of the
fiscal year plus $2,000,000 allotted since June 30, 1944, will be applied
as follows:
Accounts payable, June 30, 1944----------------------------$13,309.04
New work:
    By contract (completion of existing contract),
      July 1 to Aug. 25, 1944:
        Piling dikes: Cairo protection-Thompson
           Towhead-Schenimann----------------_       $86,000.00
    By contract, July 1, 1944, to June 30, 1945:
        Piling dikes:
             Hurricane Field-Thompson Towhead_       104, 000. 00
             Kaskaskia Island-Ste Genevieve, Ill     155, 000. 00
              Fish Bend-Pulltight----------------    345, 000. 00
         Bank protection:
             Price Landing-Goose Island ----------   100, 000. 00
              Seventy Six-----------------------     100, 000. 00
    By hired labor with United States plant, July 1,
      1944, to June 30, 1945:
        Piling dikes:
              Devils Island- --------------------     54,000.00
              Chesley Island                          26, 000. 00
        Solid dikes:
             Boston Bar------------------------ 33, 000. 00
             Goose Island_     ------------------     50,000. 00
        Bank protection:
            .Giboney Island----------------           33,000.00
                Total for new work------------------------         1,086,000. 00
Maintenance:
    By hired labor with United States plant, July 1,
      1944, to June 30, 1945:
        Dikes and bank protection--- ----------      $404,000.00
        Project channel dredging --------------       567,000.00
        Snagging -----------------------------         73,000.00
        Rock removal at Beaver Dam               ------------
                                                       34, 000. 00
        Surveys, gages, and studies---------- ----     99, 000. 00
        Aids to navigation-----------------            50, 000. 00
        Cooperative stream gaging--- -----------       15, 000. 00
           Total maintenance -----------------------------                    1, 242, 000. 00
           Unallocated balance--- ---------------------------                         952. 60
           Total for all work -----------------------------             __ 2,342,261. 64
  The sum of $2,000,000 can be profitably expended during the fiscal
year 1946, as follows:
New work:
   By contract, July 1, 1945, to June 30, 1946:
       Dikes ---------------------------------                  $280,000
       Bank protection--------------------------                 470, 000
   By hired labor:
       Dikes ----------------------------------                  100,000
       Bank protection--------------------------                 150, 000
          Total for new work ------------------------------                     $1,000,000
    By hired labor with United States plant:
        Dikes and bank protection------------ ----              $265,   000
       SProject channel dredging---- --------------              550,   000
        Snagging                                                  30,   000
        Surveys, gages, and studies------------ ----              90,   000
        Aids to navigation -------------------------              50,   000
        Cooperative stream gaging-                                15,   000

           Totalmaintenance-                                                     1,000,000

           Total for all work_                                      -            2, 000,000
916            REPORT OF CHIEF OF ENGINEERS,                                             U. S. ARMY,                   1944

  It is expected that, with the proposed expenditures, the project will
be about 91 percent complete.
                                                   Cost and financial summary
Cost of new work to June 30, 1944_--_ _                                         ----               ---            $38, 271, 906. 89
Cost of maintenance to June 30, 1944__                              ---------------------                         131, 897, 225. 77
      Total cost of permanent work to June 30, 1944
Minus accounts payable June 30, 1944------------
                                                                                               -           -
                                                                                                         _13,
                                                                                                                       70, 169, 132. 66
                                                                                                                                309. 04

      Net total expenditures_ ____----------_             1 70, 155, 823. 62
Unexpended balance June 30, 1944-------------------------       342, 261. 64

            Total amount appropriated to June 30, 1944                                             --             1    70, 498, 085. 26

    Fiscal year ending June 30                         1940              1941               1942                1943                   1944


Cost of new work................                    $686, 655. 23   $990, 722. 54       $558, 732. 47      $980, 530. 26            $499, 208 (r4
Cost of maintenance-----------.............        1,092, 307. 96    725,050. 95         891,127. 93        673, 499. 97           1, 212, 468 36
       Total cost--------------.................   1,778, 963.19    1, 715, 773.49     1, 449, 860.40     1,654, 030. 23           1, 711, 677.00

Total expended-----.-.-.-...--2, 017, 684.96                        1, 568, 360. 93    1, 594, 454.40     1, 982, 642.26           1, 215, 608. 81
Allotted...........--------------------2,009,040. 00                1, 750, 000.00     2, 034, 400.00     1,574,000.00             -450,000.00


Balance unexpended July 1, 1943_--------                ---                                                            $2, 007, 870. 45
Deductions on account of revocation of allotment---------                                                                  450, 000. 00
       Net amount to be accounted for__                                                                                 1, 557, 870. 45
Gross amount expended.                                                                 $1, 734, 620. 41
Less reimbursements collected----------------                                              519, 011. 60
                                                                                                                        1, 215, 608. 81

      Balance unexpended June 30, 1944:-                                                                                    342, 261. 64
Outstanding liabilities June 30, 1944                                                        $6, 127. 72
Amount covered by uncompleted contracts                                                     121, 319. 17
                                                                                                                            127, 446
                                                                                                                            "-iv
                                                                                                                                     .9
                                                                                                                                 .... V~


     Balance available June 30, 1944                                     ----------------                                  214, 814. 75
Amount allotted since June 30, 1944-                                                                                    2, 000, 000. 00
           Amount available for fiscal year 1945--                                                                     2, 214, 814. 75
Amount (estimated) required to be appropriated for completion
of existing project 2                                                                                                  5, 000, 000. 00
Amount that can be profitably expended in fiscal year ending
     June 30, 1946:
   For new work 2 ---                      -   ----                         -                                          1,   000, 000. 00
   For maintenance 2-                     -1,                                                                               000, 000. 00
                       2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
           Total                                                                                                       2, 000, 000. 00

  1 Includes $5,260,604.83 from permanent indefinite appropriation covering snagging operations of which
$280,572.72 pertained to Vicksburg and Memphis districts.
  2 Exclusive of available funds.


  2. MISSISSIPPI RIVER BETWEEN MOUTH OF MISSOURI RIVER AND
             MINNEAPOLIS, MINN. (ST. LOUIS DISTRICT)

See report, "Mississippi River between the Missouri River and
Minneapolis, Minn.," page 939.
            RIVERS AND HARBORS-ST. LOUIS,                                             MISSOURI, DISTRICT                                 917
           3. ILLINOIS WATERWAY, ILLINOIS (ST. LOUIS DISTRICT)

    See report, "Illinois Waterway, Illinois," page 1371.
     4. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

   The cost of the work during the year was $19,717.60, and the expendi-
tures were $20,161.96. The balance unexpended, $9,386.58, plus
$274,000 allotted since June 30, 1944, will be applied as needed during
the fiscal year 1945 to payment of expenses incurred under this heading.
The additional sum of $96,000 can be profitably expended during the
fiscal year ending June 30, 1946.
                                                   Cost and financial summary
Cost of new work to June 30, 1944--------------                                                                                    -

Cost of maintenance to June 30, 1944-                                       -     -                   -
                                                                                                      -_          __-$477, 603. 27
      Total cost of permanent work to June 30, 1944------------                                                              477, 603. 27
Minus accounts payable June 30, 1944-                                                                                          1, 666. 44
      Net total expenditures -------------------------------                                                                 475, 936. 83
Unexpended balance June 30, 1944                                                                                                  386. 58
                                                                                                                               9,-----------------------9
           Total amount appropriated to June 30, 1944--------                                                                485, 323. 41


   Fiscal year ending June 30                         1940           1941               1942                    1943               1944

Cost of new work ---------
                     .
Cost of maintenance------ -.---. --
                                       --                 .
                                                   - -. - --.
                                                    $47, 138. 39
                                                                   -. - - - -. -. - - - -.
                                                                   $28, 661.28
                                                                                         .
                                                                                      $34, 042. 03
                                                                                                      .         -..
                                                                                                           $37, 442.14
                                                                                                                       . . .. .     . . .
                                                                                                                                  $19, 717. 60

Total expended     ...........-----------------.     45, 112. 42    24, 365. 15        35, 189. 84             34, 712. 40         20, 161.96

Allotted   ----------------------
               ........                              25, 000. 00    15, 000. 00        17, 500. 00             51, 600. 00             5, 000. 00



Balance unexpended July 1, 1943_    --     ---------                                                                         $24, 548. 54
Amount allotted from War Department Civil Appro-
priation Act approved June 28, 1939                                                              $2, 302. 99
Amount allotted from War Department Civil appro-
priation Act approved June 24, 1940--                                                               2, 697. 01
                                                                                                                                5, 000. 00

       Amount to be accounted for_                                                                        -                   29, 548. 54
Gross amount expended                                                                            $20, 732. 05
Less reimbursements collected__                                                                       570. 09
                                                                                                                              20, 161. 96
       Balance unexpended June 30, 1944------                                                             __                    9, 386. 58
Outstanding liabilities June, 30, 1944--.....                                          --             ___                       1, 666. 44
     Balance available June 30, 1944_----                                                    -            __                   7, 720:14
Amount allotted in July 1944_ .----------------------------                                                                  274, 000. 00

           Amount available during fiscal year 1945                                         -------                          281, 720. 14

Amount that can be profitably expended in fiscal year
  ending June 30, 1946, for maintenance 1---------------------                                                                96, 000. 00
1Exclusive of available funds.
918           REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                               1944

5. OTHER              NAVIGATION                PROJECTS FOR WHICH                                       NO           ESTIMATES
                                             SARE  SUBMITTED

                                                   For last      Cost and expenditures to
                                                 full report          June 30, 1944                              Estimated amount
               Name of project                   see Annual                                                     required to complete
                                                   Report
                                                     for-        New work                 Maintenance

                        1
Cuivre River, Mo. 2 .______________                   1883         $12 000.00 ---.-.---                        Inactive.
Kaskaskia River, 11.2 3-----------------              1896           10;460. 80 -                 -            Completed; inactive.

  1 River declared nonnavigable by act of Mar. 23, 1900.-
  2No commerce reported.
  3 By authority of the Chief of Engineers, dated Dec. 12, 1895, this work was dropped from the duties in
charge of the St. Louis, Mo. district (A. R., C. of E., 1896, p. 1761).


                  6. PLANT ALLOTMENT, ST. LOUIS, MO., DISTRICT

                                             Cost and financial summary
Undistributed costs June 30, 1944-------------------------$2,                                                                504, 236. 10

Net total cost to June 30, 1944_ _-                                                                                    2, 504, 236. 10
Plus accounts receivable June 30, 1944_-------                                                           ---              442, 516. 25

      Gross total costs to June 30, 1944---------------------2,                                                              946, 752. 35
Minus accounts payable June 30,1944-----------------------                                                                   227, 498. 67

      Net total expenditures_                                                                             -            2, 719, 253. 68
Unexpended balance June 30, 1944_                                                                                     -416,    116. 37

           Total amout appropriated to June 30, 1944------------3,                                                           135, 370. 05


    Fiscal year ending June 30                 1940             1941                      1942                 1943               1944


Total expended__-..             _--_-$193,       995. 36       $7, 178. 41        -$45,     228. 17   -$273,       659. 21      $159, 820. 34

Allotted__-------------------                150, 000.00               - -   --      10,000.00            11,129,40                7,500.00


Balance unexpended July 1, 1943            -----------                                                                   $568, 436. 71
Amount allotted from War Department Civil Appropriation
  Act approved June 28, 1939_------------_                                                                            -100,       000. 00
      Amount to be accounted for_--------               ---                                                                  668, 436. 71
Deductions on account of revocation of allotment--------------                                                                92, 500. 00

       Net amount to be accounted for__       -   --------                                                                   575, 936. 71
Gross amount expended--      --------                 $4, 558, 762. 23
Less:
     Reimbursements collected-     $4, 362, 477. 90
     Receipts from sales ..    .        36, 463. 99
                                                        4, 398, 941. 89
                                                                                                                             159, 820. 34
      Balance unexpended June 30, 1944___-    -------                                                                        416, 116. 37
Outstanding liabilities June 30, 1944-------------------------                                                               415, 221. 60
      Balance available June 30, 1944_--                                              --------                                    894. 77
Accounts receivable June 30, 1944--------_                                                  -                  -             442, 516. 25

           Unobligated balance available June 30, 1944 ------------                                                          443, 411. 02
                   FLOOD      CONTROL-ST.             LOUIS,     MISSOURI,               DISTRICT                      919
Status of all investigations for navigation called for by river and harbor acts and
                                conimittee resolutions

                   Locality           Authorization        Datetrans-               Document                  Recommen-
                                          act               mittongressd
                                                                   to                 No.                       dation
                         LocalityCongress

Illinois River, Illinois Water-    Rivers and Hartbors -
   way, and the Mississippi          Committee resolu-
  River below Grafton, Ill.,        tion, Mar. 16, 1943.
  for 12-foot channel.
Mississippi River between          Flood Control Com-      Mar. 20,1944        H. 509,78th Cong.,             Favorable.
Cairo, Ill., and Baton              mittee resolution,                            2d sess.
  Rouge,    La.,   for   12-foot    Mar. 8, 1943.
  channel for navigation and
  flood control.
     Do__------------------        Commerce Committee        .do-------........---..do........-------------      Do.
                                    resolution, Mar. 9,
                                     1943.
Mississippi River between          Rivers and Harbors-------           --------------------
mouth of the Illinois River         Committee resolu-
and Minneapolis Minn.,              tion, Sept. 21, 1943.
for 12-foot channel with
suitable widths.
Mississippi River between          Rivers and Harbors-
Ohio River and Alton, Ill.          Committee resolu-
                                    tion, Feb. 28, 1938.



           7. EAST CAPE GIRARDEAU AND CLEAR CREEK DRAINAGE
                                              DISTRICT, ILL.

   Location.-This project is in the north end of Alexander County,
Ill., on the left bank of the Mississippi River between river miles 46
and 57 above Ohio River, and includes the bottom lands between the
river on the west and south, Clear Creek on the north, and the Illinois
Central Railroad on the east.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by the reconstruction of approximately 10.2 miles
of river-front levee and 0.8 mile of back levee and the construction
of one gravity drainage structure and one stop-log structure. The
project does not in itself afford complete protection to this district;
but in combination with and upon completion of authorized work
in the North Alexander and Miller Pond drainage and levee districts
and the Clear Creek and Preston drainage and levee districts, protec-
tion will have been provided this and the              districts named        "other
against a flood of about 50-year frequency. The construction cost,
revised in 1944, is $819,000. The project was authorized by the Flood
Control Act approved June 22, 1936.
   Local cooperation.-Partiallycomplied with.
   Operations and results during fiscal year.-Constructing and en-
larging levees was carried on by contract at a cost of $2,894.90, and
153,750 cubic yards were placed by contract and 843,103 cubic yards
by hired labor at costs of $73,892.11 and $132,942.80, respectively, to
repair damage to levees, caused by the May-June 1943 flood. The
total costs were $209,729.81 from regular funds for new work. The
expenditures were $213,729.81.
   Condition at end of fiscal year.--Studies made during the year have
indicated the necessity for raising the levee grades along this reach
of the Mississippi River to provide the degree of protection contem-
plated for this project as authorized. Work under the existing project
is considered to be 60 percent complete. The total costs and expendi-
920        REPORT OF CHIEF OF ENGINEERS,                              U. S. ARMY,             1944

tures to June 30, 1944, were $502,046.72-from regular funds for new
work.
  Proposed operations.-None. The unexpended balance at the end
of the fiscal year, $1,468.25, will be applied to preparation of plans.
                                   Cost and financial summary
Cost of new work to June 30, 1944-                                                             $502, 046. 72
Cost of maintenance to June 30, 1944

        Total cost of permanent work to June 30, 1944-------                                           502, 046. 72
Net total expenditures-                                                -502,                               046. 72
Unexpended balance June 30, 1944_-----------                                                       -     1,468. 25
        Total amount appropriated to June 30, 1944---------- ---                                    503, 514. 97

   Fiscal year ending June 30         1940            1941               1942          1943                 1944

Cost of new work .............$18, 484. 91         $165, 293. 89      $97, 362 17    $11,175.94           $209, 729.81
Cost of maintenance-----
Total expended-----------------      17, 164. 62    149,804. 83       102, 324. 86    19, 022. 60          213, 729. 81
Allotted----------------------25,000.00             310,000.00     ---------------   39, 485. 03           208, 000.00


Balance unexpended July 1, 1943 _____                                                                   $7, 198. 06
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940------------ $108, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941---------      100, 000. 00
                                                                                                    208, 000. 00
      Amount to be accounted for_---------------------------                                        215, 198.06
Gross amount expended ------------------------------                                                213, 729. 81

         Balance unexpended June 30, 1944.                                                                  468. 25
                                                                                                         1,---------------1
Amount (estimated) required to be appropriated for completion                             of
                  ----------------------------------
existing project 1                                                                       _            316, 000. 00
  1Exclusive of available funds.

          8. CLEAR CREEK DRAINAGE AND LEVEE DISTRICT, ILL.
   Location.-This project is in Union and Alexander Counties, Ill.,
on the left bank of Mississippi River and between river miles 57 and 66
above Ohio River and, except for some lowlands and islands along the
river, includes practically all the bottoms between the river and the
bluffs and between Ware, Ill., on the north and McClure, Ill., on the
south.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by reconstructing approximately 10.8 miles of
river-front levee and 10.3 miles of back levee and the construction of
seven gravity drainage structures. The project, when completed, will
not in itself afford complete protection to this district; but in combi-
nation with and upon completion of authorized work in the East Cape
Girardeau and Clear Creek drainage district, the North Alexander
and Miller Pond drainage and levee districts, and the Preston drainage
and levee district, protection will have been provided this and the other
districts named against a flood of about 50-year frequency. The esti-
mated construction cost, revised in 1944, is $2,538,000. The project
was authorized by the Flood Control Act of June 22, 1936.
              FLOOD CONTROL-ST. LOUIS, MISSOURI, DISTRICT                                                        921
   Local cooperation.---Partiallycomplied with.
   Operations and results during fiscal year.-A total of 45,339 cubic
yards of material was placed by contract at a cost of $22,720.29 to repair
damage to completed levees, caused by the May-June 1943 flood. Total
costs and expenditures were $22,720.29 from regular funds for new
work.
   Condition at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach of
the Mississippi River to provide the degree of protection contemplated
for this project as authorized. Work under the existing project is
about 20 percent complete. Construction on this project has been sus-
pended until after the war. The total costs and expenditures to June
30, 1944, were $473,747.68 from regular funds for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year plus $2,000 allotted in July 1944 will be applied as follows:
New work:
   Repair and preservation of levees by hired labor-------------$2, 000. 00
   Preparation of plans and specifications for river-front levees by
     hired labor_ _____----15,                                           469. 77
        Total for all work______                                     17, 469. 77
   The amount of $900,000 can be expended in fiscal year 1945 for con-
struction and the additional sum of $874,000 can be expended in fiscal
year 1946 for continuing the raising and enlarging of these levees.
                           Cost and financial summary
Cost of new work to June 30, 1944                         -.-                                       $473, 747. 68
Cost of maintenance to June 30, 1944-       -       -_-                                                          _

       Total cost of permanent work to June 30, 1944----------                                          473, 747. 68
Net total expenditures ------------------------------------                                             473, 747. 68
Unexpended balance June 30, 1944_ -15,                                                                       469.77
       Total amount appropritaed to June 30, 1944-    -----                                             489, 217. 45
   Fiscal year ending June 30         1940           1941            1942                  1943              1944


Cost of new work                   $19, 921. 12   $204, 343. 25   $182, 665.63           $14, 379. 73       $22, 720. 29
Cost of maintenance                                                         ----

Total expended------------------22,     751. 10    170, 550.83     196, 881.45            34, 516. 84        22, 720. 29
Allotted-----------------------140, 000. 00       -35,000. 00      238, 017.45          -30, 000.00        -186,800. 00

Balance unexpended July 1, 1943---------------------------                                          $224, 990. 06
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940 ----------------------------------                                               70, 000. 00
      Amount to be accounted for --------------------------                                             294, 990. 06
Deductions on account of revocation of allotment-                                                       256, 800. 00
       Net amount to be accounted for_-------                                             ---            38, 190. 06
Gross amount expended_    _ __----------22,
                              -             --                                                               720. 29
     Balance unexpended June 30, 1944--------------------                                                 15, 469. 77
Amount allotted in July, 1944_----------               --                                           -2,       000. 00
        Balance available for fiscal year 1945_                                    .--------             17, 469. 77
Amount (estimated) required to be appropriated for completion of
  existing project 1 ___--                                                                        2, 047, 000. 00
Amount that can be profitably expended in fiscal year ending
June 30, 1946 for new work ' .-       -      -      -     -                                            874, 000. 00
1 Exclusive of available funds.
922         REPORT OF CHIEF OF ENGINEERS,                                  U.      S. ARMY,       1944

            9. PRESTON DRAINAGE AND LEVEE DISTRICT, ILLINOIS

   Location.-This project is in Union County, Ill., on the left bank
of Mississippi River between river'miles 65 and 76 above Ohio River,
and includes practically all the bottom lands between Mississippi River
on the west, Big Muddy River on the north, the bluffs and the Illinois
Central Railroad on the east and Clear Creek drainage and levee
district on the south.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by reconstruction of 10.2 miles of river-front levee
and 5.7 miles of flank levee. The project, when completed, will not in
itself afford complete protection to this district; but in combination
with and upon completion of authorized work in the East Cape
Girardeau and Clear Creek drainage district, the North Alexander and
Miller Pond drainage and levee districts, and the Clear Creek drainage
and levee district, protection will have been provided to this and the
other districts named against a flood of about 50-year frequency. The
construction cost, revised in 1944, is $1,210,000. The project was au-
thorized by the Flood Control Act approved June 22, 1936.
   Local cooperation.-See page 7. Cooperation for the authorized
project was approved on April 6, 1937. Assurances of local coopera-
tion approved by county court of Union County, Ill., have not been
furnished.
   Operations and results during fiscal year.-None. The total expen-
ditures were $357.93 from regular funds for new work.
   Condition at end of fiscal year.-No construction work has been
started. Studies made during the year have indicated the necessity for
raising the levee grades along this reach of the Mississippi River to
provide the degree of protection contemplated for this project as au-
thorized. The total costs and expenditures to June 30, 1944, were
$8,557.02 from regular funds for new work.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $21,442.98, will be applied to preparation of
construction plans and specifications by hired labor.
   The sum of $1,180,000 can be expended for construction during fiscal
year 1945.
                                      Cost and financial summary
Cost of new work to June 30, 1944----------------------------                                           $8, 557. 02
Cost of maintenance to June 30, 1944
          Total cost.of permanent work to June 30, 1944-------_                                          8, 557. 02
Net total expenditures --------------------------------------                                            8, 557. 02
      Unexpended balance June 30, 1944--------------- -21,                                                  442. 98
          Total amount appropriated to June 30, 1944--- -----------                                     30, 000. 00


    Fiscal year ending June 30             1940               1941              1942       1943             1944

Cost of new work ...-------    ------------------------------------------                 $8, 557.02-       ...
Cost ofmaintenance ..---------   ------------------------------------------------------                     -      ---

Total expended     ............                                                           8,   199.09        $357.93
Allotted------------------..            ------.-------------------------                  30,000. 00
              FLOOD       CONTROL-ST.              LOUIS,       MISSOURI, DISTRICT          923
Balance unexpended July 1, 1943_
                               -------------------------------                       $21,800.91
      Gross amount expended ---------------------------------                            357. 93

        Balance unexpended June 30, 1944-----------------------                       21, 442. 98
Amount (estimated) required to be appropriated for completion of
existing project 1-------------------------------------------   1,180,000.00
1 Exclusive of available funds.


10. PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS NOS. 1, 2, AND 3,
                          MISSOURI

   Location.-This project is in Perry County, Mo., on the right bank
of the Mississippi River between river miles. 94 and 111 above the
Ohio River, and includes that portion of the bottoms between the
river and the bluffs and between Red Rock Landing, Mo., and Kas-
kaskia Island, but does not include Horse Island, Crain Island, Belle
of Memphis Towhead, or Puckett Island.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by reconstruction of 20.3 miles of river-front levee
and 14.4 miles of back levee, and the construction of nine gravity
drainage structures and 900 linear feet of concrete floodwall. The
project, when completed, will afford protection to the district against
a flood of about 50-year frequency. The construction cost, revised in
1944, is $3,561,000. The project was authorized by the Flood Control
Act approved June 22, 1936.
   Local cooperation.-See page 7. Assurances of local cooperation
for the project were approved by the Secretary of War as follows:
District No. 1, December 30, 1936; district No. 2, March 16, 1937;
district No. 3, September 29, 1936. Right-of-way data for the back
levees were approved December 14, 1937, and June 3, 1938. Collection
of right-of-way data for the river-front levees will be undertaken as
needed.
   Operations and results during fiscal year.-Topographic surveys
incident to the preparation of plans and specifications were carried on
by hired labor at a cost of $7,597.10, and 85,840 cubic yards of material
were placed by contract at a cost of $41,281.68 to repair damage to
levees, caused by the May-June 1943 flood. Total costs and expendi-
tures were $48,878.78 from regular funds for new work.
   Condition at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach
of the Mississippi River to provide the degree of protection contem-
plated for this project as authorized. Work under the existing project
is about 17 percent complete. The total costs and expenditures to June
30, 1944, where $542,620.93 from regular funds for new work and
$38,275.34 from Emergency Relief funds, all for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, plus $3,000 allotted in July 1944, will be applied as follows:
New work:
   Repair and preservation of completed levees by hired labor ---                    $3, 000. 00
   Preparation of plans and specifications for uncompleted levees
                  -----------------------------------______
     by hired labor_                                                                 21 379. 07

           Total for all work -------------------------------------                  24, 379. 07
924            REPORT OF CHIEF OF ENGINEERS,                                     U. S. ARMY,               1944

  The additional sum of $900,000 can be profitably expended during
the fiscal year 1945 for construction and the amount of $995,000 can
be expended during fiscal year 1946 for the continuation of the raising
and enlarging of these levees.
                                       Cost and financial summary
Cost of new work to June 30, 1944                                     _1                                           $580, 896. 27
Cost of maintenance to June 30, 1944_

           Total cost of permanent work to June 30, 1944-----------                                                   580, 896. 27
Net total expenditures----      -------------                                                                  1 580, 896. 27
Unexpended balance June 30, 1944_---------                                                      -          -           21, 379. 07
           Total amount appropriated to June 30, 1944-------------                                             1      602, 275. 34


    Fiscal year eiding June 30            1940                     1941               1942          1943                    1944

Cost of new work -------------         $169, 024.69     --------------------------------------                             $48, 878.78
Cost of m aintenance -- - - - - -- - - - - - .                . . . - ..-        --    -- - -   ----           - .-    -    -       --
                                                                                                                                   --

Total expended-..............-     .    193, 017. 61                                                                        48, 878. 78
Allotted--- ------------------.-          7, 724. 66              -$15,    000                        $21,000               43, 000.00



Balance unexpended July 1, 1943-----------------------------                                                          $27, 257. 85
Amount allotted from War Department Civil
  Appropriation Act approved June 11, 1938 ......-   $19, 000. 00
Amount allotted from War Department Civil
  Appropriation Act approved June 24, 1940            24, 000. 00
                                                                                                                       43, 000. 00
      Amount to be accounted for_---------------------------                                                           70, 257. 85
Gross amount expended_------------                   ----                                                              48, 878. 78
     Balance unexpended June 30, 1944-----------------------                                                           21, 379. 07
Amount allotted in July 1944_----------              ----                                                               3, 000. 00
           Amount available for fiscal year 1945-------------------                                                    24, 379. 07
Amount (estimated) required to be appropriated for completion
   of existing project 2_----                    --------------                                                2, 956, 000. 00
Amount that can be profitably expended in fiscal year ending June
   30, 1946, for new work 2_ _             ____ _ _ _ _ _ _ _..-___                              __    _              995, 000. 00
  1Includes $38,275.34 Emergency Relief funds.
  2 Exclusive of available funds.


      11. HARRISONVILLE AND IVY LANDING DRAINAGE AND LEVEE
                       DISTRICT NO. 2, ILLINOIS

   Location.-This project, in Monroe County, Ill., lies on the left bank
of the Mississippi River between river miles 141 and 161 above the
Ohio River, and is bounded by Fountain Creek and the Mississippi
River on the north and west, and on the east by the bluffs to Valmeyer,
Ill., and by Moredock and Ivy Landing drainage district No. 2 from
Valmeyer south.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by the reconstruction of about 12 miles of river-
front levee, 5.5 miles of flank levee, the construction of 4 miles of new
levee, a diversion channel for Fountain Creek, and the combining and
replacing of gravity drainage structures. The project, when com-
                     FLOOD CONTROL-ST.                         LOUIS, MISSOURI, DISTRICT                               925
pleted will not in itself afford complete protection to this district; but
upon completion of the upper portion of authorized work in the Fort
Chartres and Ivy Landing project, protection will have been provided
for those areas against a flood of about 50-year frequency. The esti-
mated construction cost, revised in 1944, is $2,215,500. The project was
authorized by the Flood Control Act approved June 22, 1936.
   Local cooperation.-See page 7. Assurance of local cooperation,
approved by the county court of Monroe County, Ill., has been fur-
nished for initial phases of the project.
   Operations and results during the fiscal year.-No work was done
on the project.
   Condition at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach
of the Mississippi River to provide the degree of protection contem-
plated for this project as authorized. No construction work has been
started. The total costs and expenditures to June 30, 1944, were
$37,016.59 from regular funds for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, amounting to $38,483.41, will be applied to the preparation
of construction plans and specifications by hired labor.
   The sum of $1,000,000 can be expended during fiscal year 1945 for
construction and the additional amount of $1,140,000 can be expended
during fiscal year 1946 for the continuation of the raising and enlarging
of these levees.
                                            Cost and financial summary
Cost of new work to June 30, 1944 ---------------------------                                                   $37, 016. 59
Cost of maintenance to June 30, 1944
            Total cost of permanent work to June 30, 1944-----------                                             37, 016. 59

Net total expenditures------------------------ -------                                                           37, 016. 59
Unexpended balance June 30, 1944_--    -------                                                 _--               38, 483. 41
            Total amount appropriated to June 30, 1944-------------                                              75, 500. 00

    Fisca   3year    ending June 30              1940             1941            1942           1943               1944

Cost of new work                         $13, 592. 36
                    ..---------------.......                     $1,076. 22      $1, 329. 38::
                                                                                            :. ...      .....            ..
                                                                                                                    .. _..    .
Cost of maintenance -..--.
Total expended- ....         .........          13, 714. 15       1,190. 6(1     1, 329. 38                             __

Allotted      ....         ..........----------------------
                                                  87, 500.00   -600,000.00----    ---------     -$25, 000.


Balance unexpended July 1, 1943----------------------------                                                     $38, 483. 41
Balance unexpended June 30, 1944__--      ---------                                                              38, 483. 41
Amount (estimated) required to be appropriated for completion
  of existing project 1-------------------2,-----------------                                             2     140, 000. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for new work '----- ------         __- -------                                           1, 140, 000. 00
1Exclusive of available funds.

      12. COLUMBIA DRAINAGE AND LEVEE DISTRICT NO. 3, ILLINOIS

  Location.-This project, in Monroe County, Ill., lies on the left
bank of Mississippi River between river miles 157 and 167 above Ohio
River, and embraces most of the bottoms between the river and the
926       REPORT OF CHIEF OF ENGINEERS,                  U. S. ARMY,      1944

bluffs and between Fountain Creek on the south and Columbia Creek
on the north.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by the reconstruction of about 10.6 miles of river-
front levee and 9.0 miles of flank levee, and th6 construction of 8
gravity drainage structures. The project, when completed, will
afford protection to this district against a flood of about 50-year fre-
quency. The construction cost, estimated in 1944, is $1,501,000. The
project was authorized by the Flood Control Act approved June 22,
1936.
   Local cooperation.-Fullycomplied with.
   Operations and results during fiscal year.-A total of 182,973 cubic
yards of material was placed by contract at a cost of $68,245.11 for
placing project in a safe condition upon termination of contract for
item 3, and a total of 46,411 cubic yards of material was placed by
contract at a cost of $26,921.19 to repair damage to completed levees,
caused by the May-June 1943 flood. Costs of $1,806.09 and $64.13
were incurred by hired labor for clearing at Fountain Creek and for
partial preparation of construction plans and specifications for un-
completed levees, respectively. The total costs were $97,036.52 from
regular funds for new work. The total expenditures were $113,592.45.
   Conditionat end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach of
the Mississippi River to provide the degree of protection contemplated
for this project as authorized. Work under the existing project was
considered to be 35 percent complete until the May-June 1943 flood
caused considerable damage to the completed levee, necessitaging
emergency repairs to the levee at an estimated cost of $16,842.25. This
repair work has not yet been accomplished. The total costs and ex-
penditures to June 30, 1944, were $515,807.38 from regular funds for
new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year plus $3,000 allotted in July 1944, will be applied as follows:
New work:
   Repair and preservation of completed levees by hired labor -    $3, 000. 00
   By contract and hired labor, emergency repair of levees damaged
     by May-June 1943 flood_                                    _  16, 842. 25
   Preparation of construction plans and specifications for uncom-
     pleted levees by hired labor_---     ------------              2, 350. 37
        Total for all work ---------------------------------- 22, 192. 62
  The sum of $420,000 can be expended during fiscal year 1945 for
construction.
                           Cost and financial summary
-Costof new work to June 30, 1944      -------------------------           $515, 807. 38
Cost of maintenance to June 30, 1944
        Total cost of permanent work to June 30, 1944-       -        _     515, 807. 38
                    __
Net total expenditures---      ----------                        __         515, 807. 38
Unexpended balance June 30, 1944_--         ----------                       19, 192. 62
        Total amoun appropriated to June 30, 1944           --              535, 000. 0
                 FLOOD       CONTROL-ST.                  LOUIS,        MISSOURI,          DISTRICT                    927

   Fiscal year ending June 30                1940              1941           1942               1943              1944


Cost of new work___-                        $7, 878. 12       $4, 514. 04   $81, 284. 97   $128, 439. 14         $97, 036.52
Cost of maintenance          ------------             -
Total expended           _                  20, 431. 48        3, 467. 17    72, 863. 88       121, 552.46       113, 592. 45
Allotted-_ _ _                          180, 000. 00      -                     -    -     -      -            -191,   000. 00



Balance unexpended July 1, 1943 -                           $323, 785. 07
Amount allotoed from War Department Civil Appropriation Act
approved June 28, 1939_        --          -        -         8, 000. 00

      Amount to be accounted for_                                                                            331, 785. 07
Deductions on account of revocation of allotment__                                                           199, 000. 00
       Neu amount to be accounted for_                                                                       132, 785. 07
Gross amount expended                                                                                        113, 592. 45
     Balance unexpended June 30, 1944-                                                                        19, 192. 62
Amount covered by uncompleted contracts                                                                        89,842. 25
     Balance available June 30, 1944                                                                          10, 350. 37
Amount allooted in July 1944_                                                                                  3, 000. 00
          Amount available for fiscal year 1945                                                               13, 350. 37

Amount (estimated) required to be appropriated for completion of
existing project 1                                                                                          963, 000. 00
  1 Exclusive of available funds.


13. WILSON AND WENKEL AND PRAIRIE DU PONT DRAINAGE AND
                                  LEVEE DISTRICTS, ILLINOIS

   Location.-This project lies in Monroe and St. Clair Counties, Ill.,
on the left bank of Mississippi River between river miles 168 and 175
above Ohio River, and includes the bottoms between the river and the
bluffs and extends from about opposite the lower end of Jefferson
Barracks, Mo., north to Prairie du Pont Creek. The district is now
known as the Prairie du Pont drainage and levee district.
   Existing project.-This provides for raising and enlarging the ex-
isting levee system by the reconstruction of about 8.7 miles of river-
front levee and 4.5 miles of flank levee, and the construction of 8
gravity drainage structures and two floodgate structures and the ex-
tension of four proposed gravity drainage structures under proposed
embankment of Illinois State Highway No. 132. The project, when
completed, will afford protection to this district against the maximum
flood of record (1844) confined. The construction cost, revised in
1944, is $1,344,000. The project was authorized by the Flood Control
Act approved June 22, 1936.
   Local cooperation.-See page 7. Assurance of local cooperation,
approved by the county court of St. Clair County, Ill., was approved
by the Secretary of War November 14, 1939. Right-of-way data for
3.6 miles of upper-flank levee of the project were approved April 26,
1940. Right-of-way data for the remainder of the project are being
prepared.
   Operations and results during fiscal year.-None.
928         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                          1944

   Condition at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach of
the Mississippi River to provide the degree of protection contemplated
for this project as authorized. The existing project is about 23 percent
complete. The total costs and expenditures to June 30, 1944, were
$277,334.47 from regular funds for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, plus $2,000 allotted in July 1944, will be applied as follows:
New work:
   Repair and preservation of completed levees by hired labor      $2, 000. 00             --
   Preparation of construction plans and specifications for uncom-
    pleted levees by hired labor_---------                 ---     32, 665. 53

       Total for all work___--------------------------------- 34, 665. 53
  The amount of $831,000 can be profitably expended for construction
during fiscal year 1945.
                                      Cost and financial summary
Cost of new work to June 30, 1944_--------                                        ---           $277. 334.47
Cost of maintenance to June 30, 1944___
         Total cost of permanent work to June 30, 1944-----------                                 277, 334. 47

Net total expenditures_                                                                           277, 334. 47
Unexpended balance June 30, 1944                                                                   32,665. 53

         Total amount appropriated to June 30, 1944--------------                                 310, 000. 00

   Fiscal year ending June 30           1940           1941          1942               1943              1944

Cost of new work .....       --....   $47, 528.82   $202, 702.24    $3,011.29           $277.29
Cost ofmaintenance.--------------
Total expended-....   .---...--        41, 917.52    208, 470.80     3,634.61            337.62       -     --


                               70, 000. 00
Allotted.........................                    218, 000. 00   20, 000. 00    -230, 000. 00-.               -



Balance unexpended July 1, 1943_ _------___                            __.----$32,                        665. 53

Balance unexpended June 30, 1944----------------------------32, 665. 53
Amount allotted in July 1944-_ -------------------------      2, 000. 00

         Amount available for fiscal year 1945 -------------------                                   34, 665. 53

Amount (estimated) required to be appropriated for completion
of existing project 1----------------------_-_---1,                                              032, 000. 00
  1Exclusive of available funds.

                   14. EAST ST. LOUIS AND VICINITY, ILLINOIS

   Location.-This project is in St. Clair and Madison Counties, Ill.,
on left bank of Mississippi River between river miles 175 and 195
above Ohio River and, with the exception of Chouteau, Nameoki, anti
Venice, and Chouteau Island levee and drainage districts, and some
islands and low-lying lands along the river bank, includes all that
part of the alluvial valley between the river and the bluffs and between
Cahokia Diversion Channel on the north and the village of Prairie du
Pont on the south and is known as the East Side levee and sanitary
district.
             FLOOD      CONTROL-ST. LOUIS,                MISSOURI,        DISTRICT           929
   Existing project.-This provides for raising and enlarging the exist-
ing levee system by the reconstruction of about 20.6 miles of river-front
levee, 4.1 miles of upper flank levee, and 6.9 miles of lower flank levee,
and construction of 3 stop-log gates, 11 gravity drainage structures,
and 600 linear feet of levee wall. Of the 20.6 miles of river-front
levee, about 2 miles of levee were constructed as part of the Granite
City Engineer Depot, and, as a consequence, reconstructing the river-
front levee for this distance need not be done. Approximately 10
miles of river-front levee, included in the above 20.6 miles, also may
not need to be reconstructed if the project "Chain of Rocks Reach"
recommended in House Document No. 231, Seventy-sixth Congress,
first session, is authorized and constructed. The project, when com-
pleted, will afford protection to the district against the maximum flood
of record (1844) confined. The construction cost, revised in 1944, is
 $2,993,300. The project was authorized by the Flood Control Act
approved June 22, 1936.
    Local cooperation.-Seepage 7. Assurance of local cooperation for
the entire project was approved by the Secretary of War March 24,
1937. Right-of-way data for the lank levees were approved Novem-
ber 27, 1937, and August 7, 1940. Additional right-of-way data for
future work are being prepared.
    Operations and results during fiscal year.-No work was done on
this project.
    Condition at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach of
the Mississippi River to provide the degree of protection contemplated
for this project as authorized. Work under the existing project was
considered to be about 17 percent complete until the May-June 1943
flood caused considerable damage to the levee, necessitating emergency
repairs to the levee at an estimated cost of $25,000. The total costs
and expenditures to June 30, 1944, were $448,036.13, $445,136.13 from
regular funds and $2,900 from Emergency Relief funds for new work.
    Proposed operations.-The unexpended balance at the end of the
fiscal year, plus $2,000 allotted in July 1944, will be applied as follows:
New work:
   Repair and preservation of completed levees by hired labor --- $2, 000. 00
   By contract and hired labor, emergency repair to levees damaged
     by May-June 1943 flood------------------------------          25, 000. 00
   Preparation of construction plans and specifications for uncom-
     pleted levees by hired labor     ---------------------------29, 263. 87
           Total for all work----------------------------------56,                          263. 87
  The amount of $999,000 can be profitably expended for construction
during fiscal year 1945 and the additional sum of $1,000,000 can be
expended during fiscal year 1946.
                                  Cost and financial summary
Cost of new work to June 30, 1944 ------------------------                         1 $448, 036. 13
Cost of maintenance to June 30, 1944_____._
        Total cost of permanent work to June 30, 1944                -----------    1   448, 036. 13
Net total expenditures_ -----------------------------------                         1 448, 036. 13
Unexpended balance June 30, 1944          --------------                                 54, 263. 87
         Total amount appropriated to June 30, 1944                   _-            1 502, 300. 00
  I Includes $2,900 Emergency Relief funds
        616634-45--pt. 1, vol. 1-        59
930            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                     1944


      Fiscal year ending June 30                   1940           1941           1942                 1943             1944

Cost of new work ..--------------............    $37, 676. 09   $82, 626. 92   $43, 383. 89            $903. 27-
Cost of maintenance ......-                                              .                    -        --..

Total expended....----------------                56, 257. 90    80, 464. 42    50, 995. 06           1, 349. 60

Allotted_-         ---...........
                               ..-       -      -45,000.00      447, 000.00     23,100.00         -680,700.00            $25, 000


Balance unexpended July 1, 1943 ----------------------------    $29, 263. 87
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940---------------_                     -25,    000. 00

           Amount to be accounted for_---------                                                       ---           54, 263. 87

Balance unexpended June 30, 1944_---------                                                           ---            54, 263. 87
Amount allotted in July 1944_-------------                                                                      -    2, 000. 00

             Amount available during fiscal year 1945----------------                                               56, 263. 87
Amount (estimated) required to be appropriated for completion
of existing project 2-           -   -     -      -    -     -     2, 489, 000. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 2.      -    ---                     -___1,    000, 000. 00
  2   Exclusive of available funds.


         15. WOOD RIVER DRAINAGE AND LEVEE DISTRICT, ILLINOIS

   Location.-The project lies in Madison County, Ill., on the left bank
of the Mississfppi River between river miles 196 and 203, and includes
the bottoms between the river and the bluffs and extends from the
southern city limits of Hartford, Ill., to Alton, Ill. The small indus-
trial cities of Hartford, Wood River, and East Alton lie within the
district.
   Existing project.-Thisprovides for raising and enlarging about 5.5
miles of the existing levee system along Wood River and constructing
approximately 11.3 miles of new levee to provide protection from the
Mississippi River, and the construction of 1 stop-log structure, 20
gravity drainage structures, 3 pump houses, 1 spillway dam in Wood
River, and sewer repairs and alterations. The project when completed
will afford protection to this district against the maximum flood of
record (1844) confined. The construction cost, revised in 1944, is
$2,580,000. The project was selected and approved by the Chief of
Engineers for construction under the general authorization for the
upper Mississippi River Basin contained in the Flood Control Act
approved June 28, 1938.
   Local cooperation.-Seepage 7. Assurance of local cooperation has
not yet been furnished, but the local district officials are proceeding
with the reorganization of the district in order to furnish formal assur-
ance of local cooperation., Detailed right-of-way data have not been
furnished.
   Operations and results during fiscal year.-None. The total
expenditures were $144.31 from regular funds for new work.
   Conditions at end of fiscal year.-Studies made during the year have
indicated the necessity for raising the levee grades along this reach of
the Mississippi River to provide the degree of protection contemplated
for this project as authorized. No construction work has been started.
                    FLOOD CONTROL-ST.                      LOUIS,     MISSOURI,          DISTRICT                 931

The total costs and expenditures to June 30,1944, were $47,599.01 from
regular funds for new work.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, amounting to $37,400.99, will be applied to preparation
of construction plans and specifications by hired labor.
   The amount of $1,000,000 can be profitably expended for construc-
tion during fiscal year 1945 and the additional sum of $1,495,000 can be
expended during fiscal year 1946.
                                             Cost and financial summary
Cost of new work to June 30, 1944_-_                                  ---------                          $47,599.01
Cost of maintenance to June 30, 1944.--
           Total cost of permanent work to June 30, 1944__----                                            47, 599. 01

Net total expenditures -------------------------------------                                              47, 599. 01
Unexpended balance June 30, 1944                        ----------                                        37, 400. 99
                                                     -------------
           Total amount appropriated to June 30, 1944_                                                    85, 000. 00

    Fiscal year ending June 30                 1940           1941            1942          1943                1944


                           .
Cost of new work--------------------------                  $12, 651.46      $6,910.63    $28, 036.92-_-_---------
Cost of maintenance....
Total expended        ----------------------------           12, 376.81       7,154.91     27, 922.98            $144. 31

Allotted ------------------------
            _                                   $25, 000    350, 000.00   -310,000.00      20, 000. 00     _-


Balance unexpended July 1, 1943-----------------------------                                             $37, 545. 30
Gross amount expended -------------------------------------                                                   144. 31

                                                       .....
           Balance unexpended June 30, 1944 ----------------------                                        37, 400. 99
Amount (estimated) 1required to be appropriated for completion
of existing project' -----------------------------------               2, 495, 000. 00
Amount that can be profitable expended in fiscal year ending
June 30, 1946, for new work 1                  _       _------------1,    495, 000. 00
  1Exclusive of available funds.

16. MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE AND LEVEE
                DISTRICTS, ILLINOIS RIVER, ILL.

   Location.-This project is in Morgan aid Cass Counties, Ill., on the
left or east bank of Illinois River, between miles 73 and 78.8, above
its mouth and north of the village of Meredosia, Ill.
   Existing project.---This provides for the reconstruction of about 1.4
miles of river-front levee and 1.1 miles of flank levee along Indian
Creek, and the construction of about 4 miles of new river-front levee
and 4.3 miles of new flank levee along Willow Creek, involving the
construction of 11 gravity drains, extension of 1 gravity drain at the
pumping station, and removal by local interests of an existing power
line from the levee right-of-way. Additional flood protection will be
provided for approximately 4,200 acres of highly productive farm
land and improvements and their attendant population. The esti-
mated construction cost, revised in 1940, is $300,000; lands and dam-
ages, and alterations by local interests, $24,425. The existing project
was selected for construction by the Chief of Engineers in accordance
with the general authorization for the upper Mississippi River Basin
contained in the Flood Control Act approved June 28, 1938, and is
932         REPORT OF CHIEF OF ENGINEERS,                                        U.    S. ARMY,                  1944

described in House Document No. 182, Seventy-second Congress, first
session.
  Local cooperation.-Fullycomplied with.
   Operations and results during fiscal year.--A total of 5,868 cubic
yards of material was placed by contract at a cost of $9,985.21 to repair
damage to completed levees, caused by the May-June 1943 flood. The
total costs and expenditures were $9,985.21 from regular funds for
new work.
   Condition at end of fiscal year.-Work under the existing project is
complete. The total costs and expenditures from regular funds to
June 30, 1944, were $249,737.84.
  Proposed operations.-None. The unexpended balance at the end
of the fiscal year, $2,595.38, is available for revocation.
   The project is completed.
                                       Cost and financial summary
Cost of new work to June 30, 1944---------------------------                                                      $249, 737. 84
Cost of maintenance to June 30, 1944_
         Total cost of permanent work to June 30, 1944                                -----------                    249, 737. 84

Net total expenditures ------------------------------                                                                249, 737. 84
Unexpended balance June 30, 1944-----------------_  ---------                                                          2, 595. 38
         Total amount appropriated to June 30, 1944---- --------                                                     252, 333. 22

   Fiscal year ending June 30               1940                  1941             1942                   1943            1944


Cost of new work---------------     $4, 077. 91                 $3, 500. 29     $144, 651. 48       $85, 724. 30         $9, 985. 21
Cost of maintenance.....    .......                              .......      ..           .....        ........
Total expended-----------------..3,956. 85                        2, 524.08     130, 399. 52        101, 124. 28          9,985. 21
Allotted..------------       -----------------------------------------                             -47,     366.78       11, 000. 00


Balance unexpended July 1, 1943-                          --                                                          $1, 580. 59
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940 ----------------------------------                                                           11, 000. 00
       Amount to be accounted for---------------------------                                                          12, 580. 59
Gross #mount expended-------------------------------------                                                             9, 985. 21
         Balance unexpended Jun                    30, 1944----------------------                                      2, 595. 38

        17. SEAHORN DRAINAGE AND LEVEE DISTRICT, ILLINOIS
  Location.-This project, in Fulton County, Ill., lies on the right
bank of the Illinois River between river miles 111 and 115 above the
mouth, and is bounded by Kerton Creek, Otter Creek, and the bluffs.
  Existing project.-This provides for raising and enlarging the
existing levee system by the reconstruction of about 1.3 miles of levee,
and involves the placing of about 200,000 cubic yards of earthwork
and construction of one drainage structure. The project, when com-
pleted, will afford protection to the district against a flood equivalent
to that of 1904 (the maximum discharge of record) confined. The
construction cost, estimated in 1936, is $32,000, and the estimated cost
of lands and damages is $2,000. The project was authorized by the
Flood Control Act, approved June 22, 1936.
               FLOOD      CONTROL--ST.              LOUIS,    MISSOURI,     DISTRICT            933
  Local cooperation.-Fullycompiled with.
  Operations and results during fscal year.-None.
  Condition at end of fiscal year.-The existing project is practically
complete. The work required to complete the project is the repair of a
concrete box culvert. The total costs and expenditures to June 30,
1944, were $25,839.56 from regular funds and $5,200 from Emergency
Relief funds for new work.
  Proposed operations.-The unexpended balance of $960.44 will be
applied to the repair of the concrete discharge box by contract July 1,
1944, to June 30, 1945.
  With the proposed expenditures the project will be completed.
                                    Cost and financial summary
Cost of new work to June 30, 194411111111                                   1          1 $31, 039. 56
Cost of maintenance to June 30, 1944
           Total cost of permanent work to June 30, 1944-----------                      31, 039. 56

Net total expenditures ------------------------------------                             1 31, 039. 56
Unexpended balance June 30, 1944 -                          ------------                      960. 44
           Total amount appropriated to June 30, 1944------- ------                      32, 000. 00

   Fiscal year ending June 30          1940           1941           1942       1943         1944

Cost of new work___                   $3, 739. 80      $141.84
Cost of maintenance ...
Total expended ...                     4, 753. 99       141. 84
Allotted     -----------------------


Balance unexpended July 1, 1943 __              ------------                                $960. 44
Balance unexpended June 30, 1944 ------------------------------                              960. 44
  1 Includes $5,200 Emergency Relief funds,

       18. UPPER MISSISSIPPI RIVER BASIN, ST. LOUIS DISTRICT

   Location.-The Mississippi River Basin above the Ohio River, ex-
clusive of the Missouri River Basin, in the St. Louis district.
   Existing project.-The Flood Control Act of June 28,1938, approved
the general comprehensive plan for flood control and other purposes in
the upper Mississippi River Basin described in the Flood Control Com-
mittee Document No. 1, Seventy-fifth Congress, first session, with such
modifications thereof as in the discretion of the Secretary of War and
the Chief of Engineers may be advisable, and authorized $6,600,000
for reservoirs and $2,700,000 for local flood-protection works on the
upper Mississippi and Illinois Rivers; the reservoirs and local protec-
tion projects to be selected and approved by the Chief of Engineers.
The act specifically provides that the authorization shall include the
enlargement and extension of a system of levees located on the south
side of the Sangamon River east of Chandlerville, Ill., as set forth in
House Document No. 604, Seventy-fifth Congress, third session. The
following individual projects located in the St. Louis district were
considered in the comprehensive plan:
934          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                           1944

                                                            Reservoirs
                                                                                                      Sae                 Total esti-

                          Name                                        Tributary basin                 State               mated cost


Meramec..................................-------------------------------- Meramec.....-------- Missouri----------          $12, 440,000
Big River...................................
                -----------------------------------. . do-..---------..........--. -do.-------              -----            6,647,000
                   ----------------------------------
Carlyle...........................                 .....             Kaskaskia ...-..          Illinois ..------------      10, 805, 000
Joanna--..--------------------------------
          .....                 .              -------------
                                           Salt__                                              Missouri-....--------         4,918,000.


                        Estimated construction cost of levees
Mississippi River:
      Wood River levee project, Illinois 1 2_    _____         -$2,                                                         580, 000
      Stringtown-Fort Chartres and Ivy Landing, Illinois 2                                                               1, 124, 000
      Kaskaskia Island levee project, Illinois 2    ---------                                                            1, 168, 000
      Grand Tower levee project, Illinois 2      -----------                                                                880, 000
      Miller Pond levee project, Illinois 2-           -      -     --                                                      106, 000
Illinois River: Meredosia Lake and Willow Creek levee project,
   Illinois 1                            ----------------------                                                            300, 000
Kaskaskia River, Ill.: Levees between New Athens and Carlyle,
  Illinois, in conjunction with Carlyle Reservoir-----------------                                                       2, 624, 000
   SSee individual report for details of project.
  2 Estimate revised in 1944. Studies made during the year have indicated the necessity for raising the
levee grade along this reach of the Mississippi River to provide the degree of protection contemplated for this
project as authorized.

   Local cooperation.-Seepage 7 for requirements.
   Operations and results during fiscal year.-The costs for general
studies for the development of the comprehensive basin plan were
$46,613.19 and the expenditures were $43,573.01.
   Conditionat end of fiscal year.-The construction progress of proj-
ects selected for construction under this authorization is given in
individual reports. The total cost for general studies for the develop-
ment of the comprehensive basin plan was $47,762.49 from regular
funds for new work, and total expenditures were $44,712.26.
   Proposed operations.-The balance unexpended at the end of the
fiscal year, amounting to $56,085.11, plus $75,000 allotted in July 1944,
will be applied to continuing surveys and preparation of detailed plans
for the development of the comprehensive plan for flood control in
the upper Mississippi River Basin.
   The sum of $400,000 can be profitably expended during fiscal year
1946 for continuation of the preparation of plans for proj ect units.
                                        Cost and financial summary
Cost of new work to June 30, 1944__- ---------------                                                                   $47, 762. 49
Cost of maintenance to June 30, 1944.

      Total cost of permanent work to June 30, 1944-------------47, 762. 49
Minus accounts payable June 30, 1944.-    ---    ----    _---3,     050. 23
      Net total expenditures_  -                                  .---------------                                       44, 712. 26
Unexpended balance June 30, 1944_                                    --------.-------                                    56, 085. 11
          Total amount appropriated to June 30, 1944                                    --------------                 100, 797. 37

    Fiscal year ending June 30                  1940                  1941              1942              1943               1944

Cost of new work-......---.-.--                  $142.05               $271.85    --------------            $80.08          $46,613.19
Cost of maintenance....
Total expended..........-....             ---     170. 10                80. 00           191.85              70. 03         43, 573. 01
Allotted...-------.---.---.             -22,      500. 00           30, 000. 00     -22, 500. 00         70, 000.00
                     FLOOD CONTROL-ST. LOUIS, MISSOURI, DISTRICT                                                                          935
Balance unexpended July 1, 1943_ _----------------------------$99,                                                              658.&12
Gross amount expended_ ___________----       ----------                                                                     43, 573. 01

      Balance unexpended June 30, 1944                                                                                      56, 085. 11
Outstanding liabilities June 30, 1944_--                                      ----------                                     3, 050. 23
     Balance available June 30, 1944------------------------                                                                53, 034. 88
Amount allotted in July 1944_ __--------------75,                                                                               000. 00

            Amount available for fiscal year 1945_-----                                                --                128, 034. 88

Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work 1-_---------------                                                                               400, 000. 00
   1Exclusive of available funds.

19. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF THE
         FLOOD CONTROL ACT APPROVED AUGUST 18, 1941
   The Flood Control Act approved August 18, 1941, authorized the
allotment from flood-control appropriations of not to exceed $1,000,000
for any one fiscal year to be expended in rescue work, or in the repair
or maintenance of any flood-control work threatened or destroyed by
flood. Pursuant to this act, the amount of $400,560 was allotted in
fiscal year 1943 for emergency repair and rescue work in the St. Louis
district, and the additional amount of $2,000 was allotted for this work
in fiscal year 1944.
   The operations undertaken during the fiscal year, pursuant to this
authorization, consisted of reinforcing levees to prevent breaches, re-
pairing breached and eroded levees, and conducting rescue and evacu-
ation activities during the April-May 1944 highwater. The costs
during the year were $202,558.20, and the expenditures were $260,-
516.60. The total costs and expenditures to June 30, 1944, were
$310,648.52.
   The balance unexpended on June 30, 1944, $91,911.48, will be applied
to the completion of uncompleted contracts and to other costs to be
incurred under this heading.
                                              Cost and financial summary
Cost of new work to June 30, 1944..
Cost of maintenance to June 30, 1944---                                       --------                                $310, 648. 52
            Total cost of permanent work to June 30, 1944-                                             -                 310, 648. 52

Net total expenditures ------------------------------                                                                    310, 648. 52
Unexpended balance June 30, 1944      ------------    ---                                               ____              91, 911.48
            Total amount appropriated to June 30, 1944--------                                                           402, 560. 00

    Fiscal year ending June 30                     1940               1941                 1942             1943                       1944

Cost of new work ................ .............. ..............                   ..................               .................
Cost of maintenance.............             ......-....     ..............       ..............       $108, 090.32              202, 558. 20

Total expended_--------..................          ------
                                            ___----------------                                          50,131.92               260, 516.60
                                          -------------------------.------------.
Allotted.--....-------------................._.                                                         400, 560.00                    2,000.00


Balance unexpended July 1 1943_                       .-.---- $350, 428. 08
Amount allotted from War Department Civil Appropriation Act
  approved June 24, 1940- -    -  --      -     -102,               000. 00
            Amount to be accounted for-                                 --                    -452,                                428. 08
936         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                      1944

Deductions on account of revocation of allotment--------------                                               $100, 000. 00
      Net amount to be accounted for------------------------                                                    352, 428. 08
Gross amount expended----       -------------                                                                   260, 516. 60
     Balance unexpended June 30, 1944____-       ------                                                          91, 911.48
Amount covered by uncompleted contracts ---------------------                                                    71,400. 00
         Balance available June 30, 1944_ - -                            ---------                               20, 511. 4§
20. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY                                                                             OF
     PUBLIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency-repair work to flood-
control structures damaged or destroyed by the disastrous floods which
occurred in the spring of 1943 and again in the spring of 1944, Con-
gress, in the act approved July 12, 1943, Public No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public
No. 318, Seventy-eighth Congress, authorized the amounts of $10,000,-
000 and $12,000,000, respectively, to be appropriated as emergency
funds to be expended under the direction of the Secretary of War
and the supervision of the Chief of Engineers for the repair, restora-
tion, and strengthening of levees and other flood-control works which
had been threatened or destroyed by the recent floods. (See p. 9 for
details.) Pursuant to the act of July 12, 1943, the amount of $2,175,-
000 was allotted to the St. Louis district during fiscal year 1944 for
emergency flood-control work.
   Emergency flood-control work along the Mississippi, Illinois, and
Kaskaskia Rivers was accomplished during fiscal year 1944 at a cost
of $2,050,231.22. Expenditures were $2,025,035.71.
   The balance unexpended on June 30,1944, $149,964.29, will be applied
to accounts payable, $25,195.51, and to emergency repair of levees
damaged by the May-June 1943 flood along the Mississippi, Illinois,
and Kaskaskia Rivers. In addition, the amount of $4,646,500, allotted
in July, August, and September 1944, for emergency flood-control
work, pursuant to the act approved May 29, 1944, will be appltied during
fiscal year 1944 to the repair of levees damaged by the May June 1944
flood in levee districts located along the Mississippi, Illinois, and
Kaskaskia Rivers.
                                         Cost and financial summary
Cost of new work to June 30, 1944__
Cost of maintenance to June 30, 1944----------------------                                                 $2, 050, 231. 22
      Total cost of permanent work to June 30, 1944 -2,                                                         050, 231. 22
Minus accounts payable June 30, 1944--- ------                                                         -         25, 195. 51
      Net total expenditures_-----------------------------                                                  2, 025, 035. 71
Unexpended balance June 30, 1944-       -    -     ---  -_
                                                         __                                                    149, 964. 29
          Total amount appropriated to June 30, 1944------------                                            2, 175, 000. 00

   Fiscal year ending June 30                1940                 1941               1942         1943                1944


Cost of new work---
Cost of maintenance------------- ---------------------------                -------------- -------------- $2,050,231.22
Total expended-------------------------------------------------2,                                                   025,035. 71
Allotted ......... .              -...........
                                     ..I-   -           I1.-.--            I-.-..           I--    -        -     2, 175, 000. 00
                   FLOOD CONTROL-ST.                     LOUIS, MISSOURI,                 DISTRICT                937
Amount allotted from Second Deficiency Appropriation Act
                        -------------------------------
approved July 12, 1943___                               $2, 175, 000. 00

Net amount to be accounted for-___-----__                                                             2,175, 000. 00
Gross amount expended_-----------------------------                                                   2,025, 035. 71

      Balance unexpended June 30, 1944 ---------------------                                              149, 964. 29
Outstanding liabilities June 30, 1944- ------------   $806. 10
Amount covered by uncompleted contracts------- 117, 045. 28
                                                                                                          117, 851. 38
Unobligated balance available June 30, 1944--------------------     32, 112. 91
Amount allotted in July, August, and September 1944- --------   4, 646, 500. 00

           Amount available during fiscal year 1945-- -------------                                   4, 678, 612. 91

21. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES FOR
                       FLOOD CONTROL
  The cost of work done during the year amounted to $142,595.46
and the expenditures were $132,230.69. The balance unexpended, $57,-
420.31, plus $29,500 allotted in July 1944, will be applied as needed
during the fiscal year 1945 to payment of expenses incurred under this
heading. The additional sum of $40,000 can be profitably expended
during the fiscal year 1946.
                           Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_-----------------------                                           $278, 4b5. 33
       Total cost of permanent work to June 30, 1944                             -----------            278, 485. 33
Minus accounts payable June 30, 1944-------------------------                                            10, 605. 64
       Net total expenditures-------------------------                                                  267, 879. 69
Unexpended balance June 30, 1944 ---------------------------                                             57, 420. 31
       Total amount appropriated to June 30, 1944---------- ---                                         325, 300. 00

     Fiscal year ending June 30             1940            1941             1942            1943              1944


Co s t of n ew wo rk - - - - - .-    . .-    . . . . . .. ..             . .. . . .           -   -
Cost of maintenance---- ....------   -   $6,196. 43   $24, 999. 06         $82, 536. 21    $15, 658 17      $142, 595. 46
Total expended ------------------           2, 629. 31     26, 365. 79      82, 31i. 23     17, 839. 67      132, 230. 69
         -----------------------
Alotted ....      .                      35,000. 00        96, 000. 00 --------------      118, 800. 00       69,000. 00


Balance unexpended July 1, 1943------- --------------------                                            $120, 651. 00
Amount allotted from War Department Civil Appro-
priation Act approved May 23, 1941--------                                          54, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942- -----------                                    15, 000. 00
                                                                                                           69, 000. 00
      Amount to be accounted for--------------------------                                                189, 651. 00
Gross amount expended -----------------------------------                                                 132, 230. 69
       Balance unexpended June 30, 1944 ----------------------                                             57, 420. 31
Outstanding liabilities June 30, 1944--------------------------                                            10, 605. 64

     Balance available June 30, 1944---- ---                                         _                     46, 814. 67
Amount allotted in July 1944 -------------------------------                                               29, 500. 00

            Amount available for fiscal year 1945---- ----------------                                     76, 314. 67

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1    ---------------------------------                                          40, 000. 00
   I Exclusive of available funds.
938          REPORT OF CHIEF OF ENGINEERS,                                              U.      S. ARMY,               1944

22. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED

                                                                For last           Cost and expenditures to                   Estimated
                                                               full report               June 30, 1944
                    Name of project                           see Annual                                                      a unred
                                                                 Report                                                        quired to
                                                                  for-             New work                    Maintenance     complete


1. North Alexander drainage and levee district,
      Illinois - - - -_                                       1942           $295, 482. 55       ....          .                 1 $172,000
2. Miller Pond drainage and levee district,
      Illinois-.- -                                      --   1941              34, 251 78 --------------                          1 71,000
8. ])eGognia and Fountain Bluff levee and
      drainage district, Illinois 2                           1939              17,000.00     .........                          2,543,000
4. Kaskaskia Island drainage and levee district,
      Illinois.--1-----------------------------1943                           294, 925. 68 -        .....                         1873, 000
5. Ste. Genevieve levee district No. 1, Missouri 3           1941                   199. 49              - -                    1, 056, 000
6. Fort Chartres and Ivy Landing drainage
      district No. 5, Illinois 2- --------
7. Chouteau, Nameoki, and Venice drainage
                                                              1941                   521.43                -                     1,124, 000
      and levee district, Illinois 4..     ...              _ 1938         .. . . . . . .. ...                .132,                     000
8. St. Louis County drainage and levee district,
      Missouri 4-.    .  .............                        1938       ----------------------------                              259. 000
9. Wiedmer chemicals drainage -and levee dis-
      trict, Missouri 5--         ...          ..--.---       1938
                                                              198....... -76,                                                           500
10. Riverland levee district, Missouri 6                      1938 --------------------------                                       73, 000
11. McGee Creek levee and drainage district,
      Illinois River, Ill.2--- ----            -      ------  1940------------------                                               135, 000

  1 Revised in 1944. Studies made during the year have indicated the necessity for raising the levee grades
along this reach of the Mississippi River to provide the degree of protection contemplated for this project
as authorized.
  2 Work under the project has been deferred pending fulfillment of the required local cooperation.
  8Work deferred pending a review of H. Doc. No. 669, 76th Cong., 3d sess.; modification recommended
Jan. 2, 1942, in H. Doc. No. 727, 77th Cong., 2d sess.
  4 May be modified by project for "Chain of Rocks Reach," recommended to Congress in H. Doc. No. 231,
76th Cong., 1st sess.
  b Action deferred pending further study.

  6 Low-lying lands in this district have been acquired under authorizations contained in the River and
Harbor Act approved Aug. 26, 1937. Action regarding protection for the remaining areas in the district
deferred pending further study.

  Status of all snvestigatsons for flood control callcd for by flood control acts and
                                  commzttee resolutions

                                                                        Date trans-                                          Recommen-
            Locality                    Authorization act                mitted to                Document No.                 dati
                                                                                                                             Remmon
                                                                         Congress

Illinois River and tribu-            Fleod Control         Act,    ..     -----------
   taries,   including both           Aug. 11, 1939.
     creeks    having    name
   "Crow," Gimlet Creek,
   and Ten Mile Creek, Ill.
    (comprehensive Illinois
   River survey report being
   made by the Upper Mis-
   sissippi Valley Division).
Kaskaskia River, Ill .-.             Flood Control Act,--------..........
                                       June 28, 1938.
Mississippi (Lower) River,           Flood Control Com-_.................
flood protection for Cape             mittee    resolution,
  Girardeau, Mo.                       Nov. 16, 1943.
Mississippi River between            Flood Control Conm------------------------------
  Coon Rapids Dam and the              mittee    resolution,
mouth of the Ohio River               June 21, 1944.
for flood protection in
Illinois between the pro-
posed new outlet of Cache
  River near Cache, Ill.,
and Miller City, Ill.
Mississippi River, flood pro-        Flood Control Comn--_---------                                .--- ---------
tection between mouth of              mittee    resolution,
  Kaskaskia River and Fort             Sept. 18, 1944.
  Chartres and Ivy Land-
ing drainage and levee
district, particularly at
Prairie du Rocher, Ran-
dolph County, Ill.
Mississippi River, flood con-        Flood Control Com-----                 .- -             . .............
troi above mouth of Mis-              mittee    resslution,
souri River.                          Sept. 18, 1944.
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS            939
MISSISSIPPI RIVER BETWEEN THE MISSOURI RIVER
             AND MINNEAPOLIS, MINN.
   The section of the river covered in this report is divided into three
reaches, under the supervision and direction of district engineers at
St. Louis, Mo., Rock Island, Ill., and St. Paul, Minn.
   The section in the St. Louis district extends from the mouth of
the Missouri River to mile 300 above the Ohio River, a distance of
about 105 miles; the Rock Island district extends from mile 300 to
mile 614, a distance of about 314 miles; and the St. Paul district
extends from mile 614 to the Minneapolis, St. Paul, and Sault Ste.
Marie Railway bridge, Minneapolis, a distance of about 244 miles.
   District engineers: At St. Paul, Minn., Col. Lynn C. Barnes, Corps
of Engineers; at Rock Island, Ill., Lt. Col. John H. Peil, Corps of
Engineers; at St. Louis, Mo., Col. Lawrence B. Feagin, Corps of
Engineers.
   Division engineer: Col. Malcolm Elliott, Corps of Engineers.
  Location.-The Mississippi River rises in the northern part of
Minnesota, flows about 2,450 miles in a southerly direction, and
empties into the Gulf of Mexico. The portion included in this report
extends from the mouth of the Missouri River to the Minneapolis,
St. Paul, and Sault Ste. Marie Railway bridge, Minneapolis, a dis-
tance of about 663 miles.
  Previous projects.---Adopted by the River and Harbor Acts of
June 10, 1872, June 18, 1878, August 18, 1894, February 9, 1905,
March 3, 1905, March 2, 1907, June 25, 1910, September 22, 1922,
March 3, 1925, January 21, 1927, and July 3, 1930.
   For further details see pages 1879, 1880, and 1887*of the Annual
Report for 1915, pages 1106, 1107, and 1108 of the Annual Report
for 1932, and page 1047 of the Annual Report for 1938.
   Existing project.-This project provides for a channel of 9-foot
depth and of adequate width between the mouth of the Missouri
River (1,276 miles from the Gulf) and the Minneapolis, St. Paul, and
Sault Ste. Marie Railway bridge at Minneapolis, by the construction
of a system of locks and dams, supplemented by dredging. The
project also provides for a further improvement at St. Paul to pro-
vide a basin 9 feet deep, varying in width from 400 to 1,100 feet
and extending downstream from the Robert Street Bridge for a
distance of 2.7 miles, and at Minneapolis to provide adequate ter,
minal facilities.
   The estimate of cost for new work, revised in 1939, is $170,000,000,
which includes $8,259,000 for work upstream from the lower North-
ern Pacific Railway bridge at Minneapolis, but is exclusive of amounts
expended on previous projects. The latest approved estimate for
maintenance and operating costs is $1,805,000 annually, including
$795,000 for operating and care of locks and dams.
940           REPORT OF CHIEF OF ENGINEERS,                                         U.    S. ARMY,             1944


    The existing project was authorized by the following river and
harbor acts:

                  Acts                                       Work authorized                                  Documents


Sept. 22, 1922...................                  Dredging channels to landing places on
                                                     the main river and subsidiary sloughs
                                                     for the river above the mouth of the
                                                     Missouri River.
July 3, 1930----------------...................... Project adopted and to be prosecuted in        H. Doc. No. 290, 71st Cong.,
                                                     accordance with the plan for a compre-        2d sess.
                                                     hensive project to secure a channel of
                                                    9-foot depth; amount authorized to be
                                                     appropriated limited to $7,500,000, in
                                                     addition to amounts authorized under
                                                    the then existing projects.
Feb. 24, 1932 (Public Res. No.                     Chief of Engineers granted discretionary
  10, 72d Cong., 1st sess.).                        authority to make such modification in
                                                    plan as may be advisable.
Aug. 30, 1935 (included in the Missouri River established as the lower                            H. Doe. No. 137, 72d Cong.,
  Public Works Administra-                          limits of the project; authorizes further      1st sess., and Rivers and
  tion and Emergency Relief                         improvement of the harbor at St. Paul,         Harbors Committee Doe.
  Administration programs).                          Minn.; authorizes appropriation of the        No. 44, 74th Cong., 1st
                                                    entire sum required for completion of             sess.
                                                    the project.
Aug. 26, 1937 ----           ---.            . - Project modified in accordance with rec-         Rivers and Harbors Com-
                                                    ommendation of the district engineer,           mittee Doe. No. 34, 75th
                                                    Rock Island, Ill., providing for rectifica-     Cong., 1st sess.
                                                    tion of damages that may be caused to
                                                    drainage and levee districts bordering
                                                    the Mississippi River by seepage and
                                                    backwater as a result of the navigation
                                                    improvement. The estimated cost is
                                                    $2,515,566, including $624,6'5 for ac-
                                                    quiring low-lying lands in 7 districts,
                                                    $125,000 for continuing a study of the
                                                    districts for 5 years, $247,290 for annual
                                                    rectification of damages during the
                                                    period of study, $150,000 contingent
                                                    construction by the United States, and
                                                    $1,368,631 for estimated capitalized in-
                                                    creased drainage costs.
     Do.... .. .. . . . . . . Extension of the 9-foot channel above St.                           H. Doc. No. 137, 72d Qpng.
                                                    Anthony Falls (subject to such changes         1st sess.
                                                                                                  1
                                                    as may be found advisable by the Chief
                                                    of Engineers and the final approval of
                                                    the plan by the Board of Engineers for
                                                    Rivers and Harbors, as necessary to
                                                    provide adquate terminal facilities for
                                                    Minneapolis, Minn.). Final approval
                                                    of a plan, incorporating certain changes
                                                    found advisable by the Chief of Engi-
                                                    neers, was given by the Board of Engi-
                                                    neers for Rivers and Harbors Feb. 8,
                                                    1938. Modification of the requirements
                                                    for brAdge clearances was approved by
                                                    the Board of Engineers Oct. 28, 1940,
                                                    and by the Chief of Engineers Nov. 27,
                                                    1940. (S. Doe. No. 54, 77th Cong., 1st
                                             sess.)
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS                                         941

                     Acts                             Work authorizcd                Documents

June 26, 1934 (Permanent Ap-            Operating snag boats, and operation and
  propriations Repeal Act).              care of locks and dams provided for
                                         with funds from War Department ap-
                                         propriations for rivers and harbors.
June   11,    1938    (War   Depart-    This appropriation act contained the pro-
ment        Civil    Appropriation       vision that no part of the appropriation
  Act, Public,        No. 591,   75th     shall be expended for any work upon or
  Cong.).                                 incident to the project to extend the
                                          channel of the Mississippi River above
                                          St. Anthony Falls.



    The Chief of Engineers, under date of December 28, 1938, reported
without recommendation that the best determination practicable of
the exact damages that may be caused at Cochrane, Wis., by seepage
and backwater resulting from the creation of pool No. 5 on the Mis-
sissippi River, is $33,000 (H. Doc. No. 137, 76th Cong., 1st sess.)
    See House Document No. 669 (76th Cong., 3d sess.) for report of
Chief of Engineers dated February 27, 1940, containing a general
plan for improvement of the Mississippi River between Coon Rapids
Dam and the mouth of the Ohio River for purposes of navigation,
power development, the control of floods, and the needs of irrigation.
    The latest map and profile published showing this section of the
river have been inserted between pages 20 and 21 of House Document
No. 137, Seventy-second Congress, first session. A map of the section,
Minneapolis to Lake Pepin, is published in House Document No. 583,
Sixty-ninth Congress, second session. The latest published ,maps of
the locality at Moline are in House Document No. 397, Fifty-eighth
Congress, second session, and House Document No. 263, Sixty-ninth
Congress, first session. A map showing location of drainage districts
 (Bellevue, Iowa, to Missouri River) is published in Rivers and Har-
bors Committee Document No. 34, Seventy-fifth Congress, first
session.
   Pertinent data for existing and proposed locks and dams, etc., are
given in the following table:
                                         Locatin                                                                       Loc
                                   Location                                                                            Lock
                                                            i-      L-----------




                                                                          Dimensions                                 Depth on                                                                           Per-             Estimated
                                                                                                                     miter sill                                                                         cent-           cost of each
                                                                                                                                                                                                         age   Year
                                                                                                                                                                                                                       lock and dam           h
                                                                           ----       ,---          ----     I--            I

                                                                                                                                                                               Character of dam         com- opened including    work         0
                      Miles                                             Great-                                                                                                   foundation            pleted,to navi- in pool and
                      above      Distance from nearest                                                                                            Character of founda-
                                                                          est
                                                                 Width length                                                                            tion                                          locks gation flowage     dama-
                       Ohio              town                                                                                                                                                           and
                      River                                        of   avail-
                                                                 cham- able for                Lift 1 Upper                 1Lower 1                                                                   dams                 ges
                                                                  ber    full
                                                                        width
                                         -         I                                         1--            'I------
                                                                                                              1--               I            I                            I                                                                   M
                                                                  Feet         Feet                Feet            Feet             Feet
St. Anthony Falls      853.9   In city of Minneapolis,               56          400                49. 7           15.7              12. 5 Some limestone, main- Limestone.....---------                ()              4$4, 628,000.00
  upper lock.                    Minn.                                                                                                        ly sandstone. No                                                                                0
                                                                                                                                              piles.
St. Anthony Falls 853.3           do....................
                               ....                   56                           400         626.4                15.5            6 10.1  Sandstone. No piles.. Sandstone-----------                        0           53,631,000.00
  lower lock and dam.
Lock and dam No. 1_. 847.6     6.2 miles above Omaha                 56            400         635.9               613.5             10.1        Rock and piles in gra-       Piles in gravel.......      100     1917   891,000,539.26
                                  R. R. bridge, St. Paul,            56            400              35. 9           712.5             7.6         vel.
                                  Minn.
Lockand dam No. 2.__ 815.2     1.3 miles above Hastings,            110            500              12.2            16.0             15.1        Piles in sand, silt, and Piles in sand, silt,            100     1930    12   5,215,000.00
                                  Minn.                           10 110          1o600             12. 2           22. 2            13.0          clay.                    and clay.                    11 73
Lock and dam No. 3_. 796. 9    6.1 miles above Red                  110            600               8.0            17.0             14.0        .....do ... ......    .. Piles in sand .-.....           100     1938     5, 834,000.00          t


                                  Wing, Minn.
Lock and dam No. 4__ 752. 8    Alma, Wis-----------                 110            600               7.0           17.0              13.0        Piles in sand and gra-
                                                                                                                                                                      Piles in sand and                   100     1935     5, 091, 000.00
                                                                                                                                                   vel.                 gravel.
Lock and dam No. 5__ 738.1     Minneiska, Minn ....                 110            600               9.0            18.0             12.0            do . ........... Piles in sand ...-
                                                                                                                                                    -..                                                   100     1935     5, 302, 000.00
Lock and dam No. 728. 5        3 miles above Winona,                110            600               5.5            18. 0            12.5        Piles in sand--_-_   .--do---      -                     100lO   1936     4,775,  000.00
5A.                             Minn.
Lock and dam No. 6.__ 714. 3   Trempealeau, Wis ....                110            600               6.5            17. 0            12. 5       Piles in sand, gravel,       Piles in sand and           100     1936     4,743, 000. 00
                                                                                                                                                   and silt.                    clay.
Lock and dam No. 7.._ 702. 5   Dresbach, Minn- ......               110            600               8.0            18.0             12.0        Piles in sand and gra-       Piles in sand .....-        100     1937     5,810,000.00
                                                                                                                                                   vel.
Lock and dam No. 8__ 679.2     Genoa, Wis                           110            600             11.0             22.0             14.0        Piles in sand, gravel,       Piles in sand and           100     1937     6, 280, 000.00
                                                                                                                                                   and broken rock.             gravel.
Lock and dam No. 9_. 647. 9    3.3 miles below Lynxville,           110            600              9.0             16.0             13.0        Piles in sand .......        Piles in sand ....-         100     1938     6, 776,000. 00
                                  Wis.
Lock and dam No. 10. 615.1     Guttenberg, Iowa .......             110            600              8.0             15.0             12.0        ....do . .. -        -    ...do ....   ....             100      1936     4, 928, 000. 00
Lock and dam No. 11_ 583.0     3.7 miles above Dubuque,             110            600             11.0             18. 5            12.5        Piles in sand, gravel,       do -......
                                                                                                                                                                           ....              ....        100      1937     6, 977, 000.00
                                  Iowa.                                                                                                            and silt.
Lock and dam No. 12_ 556. 7    Bellevue, Iowa........               110            600              9.0             17. 0            13.0        Piles in sand and gra- Piles in sand and                100      1938     5, 365, 000. 00
                                                                                                                                                   vel.                     gravel.
Lock and dam No. 13_ 522. 5    4.3 miles above Clinton,             110            600             11.0             19. 0           13.0         Piles in sand, clay, and ----do .        -              100      1938     7,694,000.00
                                  Iowa.                                                                                                            gravel.
Lock and dam No. 14. 493.3     3.7 miles below Le Claire,           110            600             11.0             20.5            13. 5        Rock ..............      Rock .............             100      1939     5, 342,000. 00
                                  Iowa.
                                                                                               11.0        17.6       10.9       _do..........------      ----------------------           100         1922          (13)
Le Claire Lock (Can- 493.1           3.9 miles below Le Claire,             80       320
  al).                                  Iowa.                                                           1424.0        11.0   -- - do    - d a- ---     Rock --------------                 100          1934       7, 757, 000.00
                                     Foot of Arsenal Island,               110       600       16.0
Lock and dam No. 15_ 482.9                                                 110                 16.0     1417.0        11.0                                                                                                    UP
                                        Rock Island, Ill.                            360                                                                                                               1937        6, 202, 00. 00
                                                                           110       600        9.0        17.0        12.0 Piles in sand and gra-     Piles in sand and           100                                         0
Lock and dam No. 16         457.2   1.8 miles above Muscatine,                                                                  vel.                     gravel.
                                        Iowa.                                                              16.0        13.0 ... do         .-----------Piles in sand .--            100                 1939       5,549,000.000
Lock and dam No. 17         437.1    4.2 miles above New Bos-              110        600       8.0
                                         ton, Ill.                                                                                                   _ Piles                        100                 1937
                                      6.5 miles above Burling-             110        600       9.8       16.5         13.7 Piles in sand ---                  in sand and                                         6,151,000.00
Lock and dam No. 18         410.5                                                                                                                          gravel.
                                         ton, Iowa.                                                                                                                                                             (17) 5, 747,000.00
                                                                                    358*       38. 2       14.0          9.2 Rock ......------------   Rock .------------ (18)100                       1913
Lock and dam No. 19         364.2     Keokuk, Iowa--..     -_-...           110 (15)600}
                                                                                                           15.0        12.0 ....- do----------         Rock and piles in            100                 1936       5, 507,000.00
Lock and dam No. 20         343.2     0.9 mile above Canton,              (1110     600        10.0                                                      sand and gravel.
                                         Mo.                                                                                                                    in sand and          100                1938       5, 738, 000.00
                                      2.1 miles below Quincy,               110     600         10. 5      16.5        12.0 Piles in sand and Piles       gravel.
Lock and dam No. 21         324.9                                                                                                gravel.
                                         Ill.                                                                          13.8 Rock-----------------      Rock------------  .. -- 100                       1938      5,037,000.00
Lock and dam No. 22         301.2     1.5 miles below Saver-                110       600       10.2        18.0                                                                                                                  0
                                         ton, Mo.                                                                                                      Piles in sand -.-...          100                 1940      6,411,000.00
                                                                            110       600       15.0        19.0        12.0 Rock; piles in sand-...                                                               8, 272, 000.00
Lock and dam No. 24         273.4     Clarksville, Mo_--                              600       15.0        19.0        12.0 Piles in sand and Piles in sand and                     100                 1939
Lock and dam No. 25         241.4     Cap Au Gris, Mo -----                 110                                                  gravel.                  gravel.
                                                                            110       600 (18)22.0      (14) 32.0   (19)12.0   Piles in sand ---       Piles in sand ---   -         100                 1938      13, 295,000.00
                                           --
Lock and dam No. 26 202.9 Alton, Ill-...........- -                         110                                     (19)12.0 -. -do ------------
                                                                                      360 (18)22.0          16.0                                            do----------      -------------
                                                                                                                                                                                                                              26
                                                                                                                                                                                                                  165,060, 539.---------------
  (Henry T. Rainey
   dam.)                                                                                                                                                                                                          165,060,    26
                                                                                                                                                                                                                           539.
                                -
     Total locks and-_ ..........---------                                                                           --- - _ - - - - - -- - - - - -                                    ....      ..   .......

       dams.                                                          i                                                                                   i



                                                                             ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT
                                                                                                        .      .                                                                                                 298, 780.7
                                                                                                                     . .841.3------------------------------------------------------------------------------------------------
St. Paul Harbor improvements-----------192-.                                                                                                                                                                       9,81
Minneapolis turning basin - - --------         -- -       -
Regulating works between Lock and dam No. 26 (Henry T. Rainey Dam) and the Missouri                                River   --------------------                  -------------     -                          2        0545,315.2
                                                                                                                                                                                                             2-1-----
                                                                                                                                                                                                                , 175, 523.62
Rectification of damages to drainage and levee districts ----------------------------------------------------------                     .     . .                                                               1,175,523.6
                                                                                                                                                   ..-------------------------------------.------------------------------------------------------------
M iscellaneous . . . . . . . . .                    . . . . .                    .     .     .     .       .     .    .  .  .     .

       Total additional features--------------
                                                                            ------------------------------------------------------------------------------------------------------                              21170,000,000.00      0
       Total existing project .......-----------
                                                                                                                                                                                                                                      00
  1 Lifts and depths on miter sills, based on completion of all locks and dams.                                       13Existing Le Claire Canal lock is used as auxiliary to lock No. 14; previous project
  2 Total estimated flowage damages, including clearing, surveys, and Government costs                              costs, $540,000.
$24,  000, 000. dam, owned by Northern States Power Co., is complete. Construction of                                 14Depth over upper poiree sill. Depth over upper miter sills is 27 feet at locks No. 15;
  SExisting                                                                                                         and 34 feet at main lock No. 26.
                                                                                                                      15 Proposed main lock.
lock has not been started.                                                                                            16 Not including proposed main lock.
  a Includes upper approach dredging. (Federal cost only.)
     Includes upper and lower approach dredging. (Federal cost only.)                                                 17In addition, cost of $640,868, for first lock, was reported by the Mississippi River
  6 Based on pool elevation of 723.1 in pool No. 1 which is crest of dam. Pool No. 1 is nor-                        Power Co., transferred to Government free in lieu of improvements destroyed (A. R.
mally maintained at elevation 725.1 by flashboards.                                                                1928, pp. 1118-1119). Present estimate includes $3,283,000 for main lock.
  7 Old upper guard sill.                                                                                             18 Lift above possible future pool. Lift at extreme low water about 28.2 feet.
                                                                                                                      19 Based on possible future pool.
  8 In addition $1,948,772.95 was expended from previous projects, and $1,349,557.78 from
operating and care appropriation for reconstruction of first of twin locks.                                           20Includes $40,000 contributed funds.
     Actual cost.                                                                                                     21In addition, $620,000 was expended from the allotment for examinations, surveys, and
  10Landward lock.                                                                                                  contingencies, covering the original 9-foot survey, and a total of $613,551.44 has been
  11 Foundation and masonry for landward lock. (100 percent completed.)                                             expended by the Works Progress Administration for miscellaneous clearing and espla-
  12Includes landward lock and appurtenant works. In addition, $1,965,316.22 was                                    nade work in the Rock Island district.
expended from previous projects.
944    REPORT OF CHIEF OF ENGINEERS, U.          S. ARMY,   1944

   Recommended modifications of project.-The following modifica-
tions of the existing project for Mississippi River, Missouri River-
Minneapolis, were recommended by the Chief of Engineers under the
dates shown.
   (a) July 26, 1938. To provide at Red Wing, Minn., a basin 5 feet
below the minimum controlled pool level approximately 450 feet wide
and 800 feet long, at an estimated first cost of $11,500, with annual
maintenance of $300, in addition to the amounts now required, subject
to certain conditions of local cooperation (H. Doc. No. 103, 76th
Cong., 1st sess.).
    (b) December 19, 1939. To provide for enlargement of the flood
capacity of the main channel between Smith Avenue Bridge and State
Street in the city of St. Paul; for the dredging of a small-boat harbor
at the lower end of Harriet Island; and for the placing of excavated
material in such manner as to provide necessary fill for a roadway
along the left bank of the river between Market Street and Lambert
Landing, at an estimated first cost of $130,000, with no increase in
annual maintenance; subject to certain conditions of local cooperation
 (H. Doc. No. 517, 76th Cong., 3d sess.).
    (c) April 2, 1941. The provision of a basin at Winona, Minn., by
dredging to a depth of 9 feet an area along the right bank of the
Mississippi River between Chatfield and Carimona Streets, and by
dredging to a depth of 5 feet and protecting with a breakwater an
area between Carimona and Hamilton Streets, at an estimated first
cost of $17,000 with annual maintenance at $600, subject to certain
conditions of local cooperation (H. Doc. No. 263, 77th Cong., 1st sess.).
    (d) July 16, 1941. That the Secretary of War be granted discre-
tionary authority to permit the future modification of the existing
lock and dam improvement No. 2, near Hastings, Minn., for develop-
ment of hydroelectric power in accordance with the provisions- of the
Federal Water Power Act, at no cost to the United States (H. Doc.
No. 432, 77th Cong., 1st sess.).
    (e) January 13, 1944. That requirements of local cooperation
for extension of the 9-foot channel above St. Anthony Falls, as given
in paragraph on local cooperation below, be revised to require local
interests to make a cash contribution of $1,100,000 to the first cost
of improvement as a whole; that responsible local agencies furnish
assurances satisfactory to the Secretary of War that they will: make
the necessary alterations to highway bridges and publicly owned util-
ities, furnish free of cost to the United States all lands, easements, and
rights-of-way necessary for the channel and lock and dam construc-
tion, and furnish at their own expense suitable spoil-disposal areas
for the new work and for subsequent maintenance when and as re-
quired (H. Doc. No. 449, 78th Cong., 2d sess.).
    Local cooperation.-The authorized plan for the extension above
St. Anthony Falls provides that local interests shall give assurances
satisfactory to the Secretary of War that they will bear the cost of
necessary bridge modifications and adjustments to utility structures
estimated at $1,774,000, and furnish free of cost to the United States
all lands needed for the improvement and suitable spoil-disposal areas
for new work and for subsequent maintenance as required. These
conditions were complied with by resolution adopted by the city
council of the city of Minneapolis, and approved by the Secretary of
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS           945
War under date of May 5, 1939. All prior requirements fully
complied with.
  Terminal facilities.-A complete list of terminals available to the
public on the Mississippi River between the mouth of the Ohio River
and Minneapolis, Minn., as of January 1, 1940, can be obtained from
the division engineer, Upper Mississippi Valley Division, St. Louis,
Mo.
               OPERATIONS AND RESULTS DURING FISCAL YEAR

   St. Paul district-New work-Miscellaneous.-At lock and dam
No. 2, clean-up of approach dredging operations and painting of
sheet piling cut-off wall were completed, and design in connection
with gates and machinery, guide walls, esplanade and approach dredg-
ing for landward lock, lock and dam No. 2 and guard and guide walls,
locks and dams 3 to 10, and other miscellaneous items were carried
on all by hired labor.
   Land and flowage acquisition.-Fieldand office work were carried
on by hired labor and flowage easements were acquired in pool No. 2
on 5.7 acres of land.
   Cost of work by classes.-Incidental work, lock and dam construc-
tion, $39.84; land acquisition, including flowage surveys, etc., $7,819;
design, engineering, etc., landward lock, lock and dam No. 2, $50,-
931.71; design, engineering, etc. (general), $7,158.96. Cost by hired
labor $65,949.51.
   Maintenance.-Channeldredging was performed at 42 localities by
Government plant and hired labor, resulting in removal of 1,884,702
cubic yards of material at a cost of $256,628.17, including $33,482.50
for surveys. Aids to navigation and gages were maintained and
stream gaging, removal of snags, shore protection and dike repairs
were carried on at a cost of $25,922.43.
    Operatingand care.-The locks and dams were operated as required,
necessary repairs were made thereto and to appurtenant structures,
and protective measures were installed as required, all at a cost of
$516,202.84.
   Rock Island district-New woork-Miscellaneous.-Design and
studies in connection with the proposed main lock, drydock, bridge
alterations, and rock excavation at lock and dam No. 19, guard and
guide walls, mooring facilities and modification of electrical systems,
at various locks and dams, and channel alignment, upper approach
to lock and dam No. 21, were continued by hired labor.
   Land and flowage acquisition.-Fieldand office work were carried
on by hired labor and 4,126 acres of land in fee ancd flowage easements
on 647 acres were acquired in pools 11, 13, 14, 18, 22, and 24.
    Cost of work by classes.-Incidental work, lock and dam construc-
tion, minus $31,871.79 (reimbursement by Chicago district for prorata
share of cost of derrick boat Hercules); land acquisition, including
flowage surveys, railroad damages, etc., $22,650.41; rectification of
damages to drainage and levee districts, $152,991.19; miscellaneous
work in pool areas, $12,293.39; design, etc., proposed main lock No. 19,
$80,509.33; design, engineering, etc. (general), $35,473.12. Cost by
contract, minus $27,135.14; by hired labor $299,180.79.
 * Maintenance.-Channeldredging was performed at 29 localities by
Government plant and hired labor resulting in removal of 1,676,584
      616634---45--pt. 1, vol. 1-60
946             REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                1944

cubic yards of material at a cost of $176,970.81 including $18,046.19
for surveys.
   A total of 31,124 cubic yards of material was removed from pool No.
20 by contract at a cost of $8,029.02.
   Under a contract for construction of shore protection immediately
downstream from lock and dam No. 14, a total of 14,212 cubic yards
of embankment, 5,382.9 cubic yards of shore protection, and 935 square
yards of road surfacing, were placed. Cost of preliminary and inci-
dental work, $675.20; contract cost, $25,100.70.
  Investigations and reports on damage claims resulting from opera-
tion of locks and dams, were made at a cost of $3,237.99.
   Maintenance of navigation aids, bar surveys, etc., were carried on
at a cost of $4,522.19.
   Operatingand care.-The locks and dams were operated as required
and necessary repairs were made thereto and to appurtenant structures
at a cost of $599,096.25.
  St. Louis district-New work-Miscellaneous.-Revision of draw-
ings, locks and dams Nos. 24, 25, and 26; studies relative to rectification
of damages; and work on miscellaneous minor items were carried on
by hired labor.
  Land and flowage acquisition.-Field and office work were carried
on by hired labor and 35 acres of land in fee and flowage easements
on 667 acres were acquired in pool No. 26.
   Cost of work by classes.-Land acquisition, including flowage sur-
vays, legal expense, etc., $8,631.77; rectification of damages to drainage
and levee districts, $153.91; design, engineering, etc. (general),
$11,055.70.
  Maintenamce.-Channel dredging was performed at various lo-
calities by Government plant and hired labor resulting in the removal
of 1,090,700 cubic yards from 18 bars at a cost of $113,348.88 including
$6,522.22 for surveys.
  Aids to navigation and gages were maintained at a cost of $32,137.86.
   Operatingand care.-The locks and dams were operated as required
and necessary repairs were made thereto and to appurtenant structures
at a cost of $228,714.72.
  The costs and expenditures during the fiscal year were as follows:

                                                             St. Paul       Rock Island      St. Louis           Total
                                                             district         district        district

Costs:
     New work _.-------------------
                 _                                           $65, 949. 51    $272, 045. 65    $19, 841.38        $357, 836. 54
     Maintenance.                    .
                            _______ -..           _.....     282, 550. 60     218, 535. 91    145, 486. 74         646, 573. 25
     Operating and care..      -----------------
                                      .      .               516, 202.84      599, 096. 25    228, 714. 72      1, 344, 013.81

       Total costs ............             ---------        864, 702. 95   1,089, 677.81     394, 042. 84      2, 348, 423.60

Expenditures......................------------------------   863,160. 56    1,117, 849. 31    560, 629. 59      2, 541, 639.46



                                      CONDITION AT END OF FISCAL YEAR


   The 9-foot project as a whole, excluding extension of the project
above St. Anthony Falls, Minn., was about 92 percent complete.
The entire project was about 87.5 percent completed.
  St. Paul district-Work completed.-Locks and dams Nos. 1 to 10,
inclusive (except the landward lock at No. 2 where construction has
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS                                                                                947

been suspended and appurtenant works at various sites); improve-
ment of harbors at St. Paul and Minneapolis; miscellaneous channel
dredging and realignment; channel markers; and clearing pool areas
have been completed. For information pertaining to locks and dams,
see table under paragraph "Existing preject."
   Status of land and flowage acquisition.-Approximately 50,654 acres
of land in fee and flowage easements on approximately 14,312 acres
have been acquired. Disposition of claims cases in connection with
sites, encroachment areas, and damages, in pools Nos. 3, 4, 5A, 6, and
9, is pending. Completion of land and flowage acquisition is ex-
pected in fiscal year 1945.
   Work remaining to complete the portion of the project in the St.
Paul district consisted of the following: Extension above St. Anthony
Falls; completion of landward lock and appurtenant works at No. 2;
guard and guide walls at Nos. 3 to 10, inclusive; foot-bridge and ac-
cess road at No. 7; modification of electrical systems and construction
of stage recorder houses at various sites; and disposition of claims
cases.
  The condition of the channel on June 30, 1944, was such that con-
trolling depths of 9 feet at low water and widths suitable for long-
haul common carrier service were being maintained in all pools.
  The total costs and expenditures under the existing project (St.
Paul district) to June 30, 1944, exclusive of $40,000 contributed funds
expended for new work, were as follows:

                                                       Regular funds           Public Works            Emergency                   Total
                                                                                    funds              Relief funds


Costs:
   New work.----.               --.            ._-- $20, 255, 452. 69 $24, 210,070. 55             $9,071, 214.10               $53, 536, 737.34
   Maintenance_-------__                              4,867,121.41 ......----------------------------                       -     4,867,121.41
   Operating and care..............--------------1 4,201, 107.71 ......-------------...................----------------..         4,201, 107.71

         Total costs_............-...-.-.                29, 323, 681.81        24, 210, 070. 55        9, 071, 214.10           62,604, 966.46
Expenditures             ---...........--------          29, 314, 907.91        24, 210, 070. 55        9,071, 214.10           62, 596,192.56

1Includes $762,195.71 expended between 1930 and 1936 on the operating and care of the works of improve.
ment under the provisions of the permanent indefinite appropriation for such purposes.

   The above costs and expenditures for new work, regular funds,
include $159,358.93 transferred from the Rock Island district covering
pro rata share of cost of derrick boat Hercules.
   Rock Island distrct-Work completed.-Locks and dams Nos. 11
to 22, inclusive (except proposed main lock at No. 19, and appurtenant
works at various localities); alterations to Eagle Point bridge; rock
excavation in pools Nos. 15 and 16; diversion of Henderson River;
clearing in most pools; removal of old lateral dam along LeClaire
Canal, mile 496.5; addition to pump house and installation of machin-
ery in the Union Township drainage district; seepage ditch and
remedial works in Des Moines County drainage district No. 7, Iowa;
remedial works in Sny Island levee district; and extensions to upper
river walls at locks Nos. 11, 16, 18, 20, and 22, have been completed.
For information pertaining to locks and dams, see table under para-
graph "Existing project."
   Status of land and flowage acquisition.-Approximately 107,234
acres of land in fee and flowage easements on approximately 11,078
acres have been acquired. The distribution of funds paid into reg-
948           REPORT OF CHIEF OF ENGINEERS,                                     U. S. ARMY,               1944

istry of the court on 83 tracts of land was all that remained at the
close of the fiscal year.
    Work remaining to complete the portion of the project in the
Rock Island district consisted of the following: Main lock and ap-
purtenant works at No. 19; guard and/or guide walls at Nos. 11, 15,
16, 17, 18, 20, 21, and 22; mooring facilities at Nos. 12, 15, 16, 17, 18,
20, and 22; removal of lateral dam in pool No. 14, mile 493.5; dredg-
ing for project depth and alignment in pools Nos. 17, 18, 20, and 21;
clearing in pools Nos. 12, 13, 14, 17, 18, 19, 21, and 22; modification
of electrical systems at all sites except No. 19; rectification of dam-
ages to drainage and levee districts; land and flowage acquisition;
and miscellaneous minor items.
   The condition of the channel on June 30, 1944, was such that con-
trolling depths of 9 feet at low water and suitable widths for long-
haul common carrier service were being maintained in all pools.
   The total costs and expenditures under the existing project (Rock
Island district) to June 30, 1944, were as follows:

                                                    Regular          Public Works          Emergency              Total
                                                      funds                funds           Relief funds


Costs:
    New work- ..........-....         ..... $39, 018,051.15       $17, 403, 322. 39       $11,338,864. 90     $67, 760, 238. 44
    Maintenance- .----------.----            1 5, 527, 012. 80 -----------------                                5, 527, 012. 8(}
    Operating and care-.       ... ..    -_-_2 4, 346, 000. 58 -_                _ _.--   . __4,                   346, 000. 58

                      -------------------
         Total costs___                           48, 891, 064. 53     17, 403, 322. 39    11, 338, 864. 90    77, 633, 251. 82'

Expenditures. _------------------46,                  332, 826. 31     17, 403, 322. 39    11, 338, 864. 90    75, 075, 013. 60

   1Includes cost of removing obstructions from Rock River, $4,500, and Galena River and connecting
sloughs, $1,000, under authority of sec. 3, River and Harbor Act of July 3, 1930.
  2 Includes $305,411.54 expended betweaen 1930 and 1936 on the operating and care of the works of improve
ment under the provisions of the permanent indefinite appropriation for such purposes.

   The above costs and expenditures for new work, regular funds,
exclude $207,166.61 transferred to the St. Paul and St. Louis districts
covering their prorata shares of cost of derrick boat Hercules.
   St. Louis district--Work completed.-Locks and dams Nos. 24, 25,
and 26 (Henry T. Rainey Dam) and dikes and revetments have been
completed. For information pertaining to locks and dams, see table
under paragraph "Existing project."
   Status of land and flowage acquisition.-Approximately 32,285
acres of land in fee and flowage easements on approximately 5,164
acres have been acquired.
   Work remaining to complete the portion of the project in the St.
Louis district consisted of the following: Emergency bulkheads and
derrick and storage barge at No. 26; clearing in pool No. 26; and
rectification of damages to drainage and levee districts and land and
flowage acquisition in pools Nos. 25 and 26.
   The condition of the channel on June 30, 1944, was such that con-
trolling depths of 9 feet at low water and generally suitable widths
for long-haul common-carrier service were being maintained in all
pools.
 MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS                                                                 949
  The total costs and expenditures under the existing project (St.
Louis district) to June 30, 1944, were as follows:

                                                 Regular funds         Public Works       Emergency               Total
                                                                          funds           Relief funds

Costs:
   New work .......    _ _ __                    $14, 696, 455. 71 $10, 282, 566. 31 $2, 440, 265. 65 $27, 419, 287. 67
   Maintenance -..      ---------                  3, 931, 505. 51 ------------- ---------------- 3, 931, 505. 51
   Operating and care_                              1, 331, 903. 81   -         - -- -1,                   331, 903. 81

       Total costs                                19, 959, 865. 03     10, 282, 566. 31    2, 440, 265. 65     32, 682, 696. 99
Expenditures                   ---                20, 112, 432. 94     10, 282, 566. 31    2, 440, 265. 65     32, 835, 264. 90



  The above costs and expenditures for new work, regular funds,
include $47,807.68 transferred from the Rock Island district covering
prorata share of cost of derrick boat Hercules.
   The total costs and expenditures under the existing project, for
the three districts, to June 30, 1944, exclusive of $40,000 contributed
funds expended for new work, were as follows:

                                                 Regular funds        Public Works        Emergency              Total
                                                                         funds            Relief funds

Costs:
   New work--------- -------               -     $73, 969, 959. 55 $51, 895, 959. 25 $22,850, 344. 65 $148, 716, 263. 45
   Maintenance                                     14, 325, 639. 72--                                   14, 325, 639. 72
    Operating and care__
                      --------------              1 9, 879, 012. 10 -----------------------------        9, 879, 012. 10

      Total costs        _
                     -------------------          98, 174, 611. 37     51, 895, 959. 25   22, 850, 344. 65    172, 920, 915. 27
Expenditures------ ----------------               95, 760, 167. 16     51, 895, 959. 25   22, 850, 344. 65    170, 506, 471.06

  1Includes $1,157,637.25 extended between 1930 and 1936 on the operating and care of the works of
improvement under the provisions of the permanent indefinite appropriation for such purposes.


   In addition, the sum of $1,579,507.38 was expended between 1888
and 1936 for operating snag boats, Upper Mississippi River and
tributaries, under the provisions of the permanent indefinite appro-
priation for such purposes.

                                               PROPOSED       OPERATIONS

   The balance unexpended at the end of the fiscal year, plus $1,830,500
allotted since June 30, 1944, and $200,000 advanced to "Plant" allot-
ment, will be applied as follows:
Accounts payable, June 30, 1944_                          -             --
                                                                     _______-- --          --        -$138,         843.46
New work:
   Lock and dam No. 2 (Hastings) (hired labor):
   Design, gates and machinery, guide walls, esplanade, and
       approach dredging for landward lock------------------                                                    9, 500. 00
   Lock and dam No. 3 (Red Wing) (hired labor):
       Acquisition of land and flowage rights      $33, 900. 00                --
        Design, guard and guide walls--------- ---   5, 400. 00
                                                                                                              39, 300. 00
                                                                                                              39,300.00
   Lock and dam No.   4  (Alma) (hired labor):
             Acquisition of land and flowage rights------- 34, 800. 00
             Design, guard and guide walls-                 2, 000. 00
                                                                                                              36, 800. 00
      Lock and dam No. 5 (Minneiska ) (hired labor):
          Design, guard and guide walls_                                                                        5, 400. 00
950      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                       1944

New work-Continued.
   Lock and dam No. 5A (Winona) (hired labor):
       Acquisition of land and flowage rights .-  $14, 300. 00
       Design, guard and guide walls-------------   6, 000. 00
                                                                           $20, 300. 00
      Lock and dam No. 6 (Trempealeau) (hired labor):
          Acquisition of land and flowage rights------      5, 500. 00
          Defending suit of contractor---------------       3, 000. 00
          Design, guard and guide walls_-------------       3, 500. 00
                                                                            12, 000. 00
      Lock and dam No. 7 (Dresbach) (hired labor):
          Design, guard and guide walls, footbridge, and access
            road _ ..             .        ._              .                    4, 500. 00
      Lock and dam No. 8 (Genoa) (hired labor):
          Design, guard and guide walls__                                       4, 600. 00
      Lock and dam No. 9 (Lynxville) (hired labor):
          Acquisition of land and flowage rights------ 63, 300. 00
          Defending suit of contractor --------------   3, 000. 00
          Design, guide aud guard walls ------------    4, 900. 00
                                                                            71, 200. 00
      Lock and dam No. 10 (Guttenberg) (hired labor):
          Design, guard and guide walls, and remedial dike .                    5, 100. 00
      Lock and dam No. 11 (Dubuque) (hired labor):
          Acquisition of land and flowage rights------ 10, 500. 00
          Design, guide wall, and modification of elec-
            trical system --------------------------     4, 400. 00
                                                                            14, 900. 00
      Lock and dam No. 12 (Bellevue) (hired labor):
          Design, mooring facilities, and modification of electrical
                     _..._
            system.....                    ...........                          3, 600. 00
      Lock and dam No. 13 (Clinton) (hired labor):
          Acquisition of land and flowage rights------ 11, 000. 00
          Design, modification of electrical system- -    1, 400. 00
                                                                            12, 400. 00
      Lock and dam No. 14 (LeClaire) (hired labor):
          Acquisition of land and flowage rights .------ 8, 400. 00
          Design, modification of electrical system -..   1, 400. 00
                                                                                9, 800. 00
      Lock and dam No. 15 (Rock Island) (hired labor):
          Design, guard wall, mooring facilities, and modification of
            electrical system------_______   __                             11, 400. 00
      Lock and dam No. 16 (Muscatine) (hired labor):
          Aqquisition of land and flowage rights-..        4, 000. 00
          Design, guide wall, mooring facilities, and
            modification of electrical system-     _      12, 400. 00
                                                                            16, 400. 00
      Lock and dam No. 17 (New Boston) (hired labor):
         SDesign, guide wall, mooring facilities, and modification of
            electrical system---___-----                                    10, 500. 00
      Lock and dam No. 18 (Burlington) (hired labor):
          Design, guide wall, mooring facilities, and modification of
            electrical system                                               10, 700. 00
      Lock and daze No. 19 (Keokuk) (hired labor):
          Design, main lock, drydock, and bridge alterations ..            140, 000. 00
      Lock and dam No. 20 (Canton) (hired labor):
          Design, guide wall, mooring facilities, and modification of
            electrical system                                                   9, 200. 00
      Lock and dam No. 21 (Quincy) (hired labor):
          Design, guide wall, and modification of electrical system._       10, 500. 00
      Lock and dam No. 22 (Saverton) (hired labor):
          Acquisition of land and flowage rights- ---       1, 000. 00
          Design, guide wall, mooring facilities, and
            modification of electrical system--- -----     12, 400. 00
                                                                            13, 400. 00
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AlD MINNEAPOLIS                                     951

New work-Continued.
   Lock and dam No. 24 (Clarksville) (Rock Island
     district) (hired labor):
       Acquisition of land and flowage rights------$2, 000. 00
       Rectification of damages (levee districts):
          Land payments-----------------------1,       200. 00
                                                                                     $3, 200. 00
    Lock and dam No. 25 (Cap au Gris) (hired labor):
        Rectification of damages (levee districts)--               50, 000. 00
        Acquisition of land and flowage rights-                     6, 000. 00
                                                                                     56, 000. 00
    Lock and dam No. 26 (Henry T. Rainey Dam)
      (Alton) (hired labor):
        Design, emergency bulkheads, and derrick
           and storage barge--     ------             -5,     000. 00
        Rectification of damages (levee districts)- -106,     000. 00
        Acquisition of land and flowage rights -.         23, 000. 00
                                                                                   134, 000. 00
    General:
        Rock Island district:
             Rectification of damages (levee districts)
               (hired labor):
                 Studies to determine damages              -       30, 000. 00
                 Annuity payments for damages --                   35, 000. 00
                                                                                       An nn n
                                                                                       ,,elVV.   VV

                       Total new work-------------------------729, 700. 00
Maintenance (July 1944 to June 1945):
    Channel maintenance dredging--------------------------706,                           500.    00
    Maintenance of existing regulating works--30,                                        000.    00
    Surveys, gages, studies, and aids to navigati6n- -      141,                         500.    00
    Snagging---------------------------------------------     7,                         500.    00
      Total maintenance----------------------------------885,                            500.    00
Maintenance (operating and care) (July 1944 to June 1945):
    Operations  ----------------------------------------     1, 248, 000. 00
    Ordinary repairs--------------------------------------174,       000. 00
    Improvement and reconstruction-------------------------112, 000. 00
       Total operating and care---------------------------                       1, 534, 000. 00
Unallocated balance----------------------------------------                           4, 115. 01
       Total available funds------------------------------                       3, 292, 1758. 47
  The sum of $3,582,000 can be profitably expended during the fiscal
year 1946 as follows:
New work:
   Lock and dam No. 2 (Hastings):
       Design, landward lock_                                                            $-------------------------
                                                                                          8, 000
   General:
       Rectification of damages (levee districts):
            Studies to determine damages------_     -----       $30, 000
            Annuity payments for damages-----   .--      ---     35, 000
            Payment of capital costs--- -----------          1, 339, 000
                                                                                     1, 404, 000
                  Total new work_ ------------------------------                     1, 412, 000
Maintenance:
    Channel maintenance dredging -----------------------------                         526, 000
    Maintenance of existing regulating works----- ----------------                      30, 000
    Surveys, gages, studies, and aids to nav igation------------ ---                   146, 000
    Snagging -----------------------------------------------                             8, 000

       Total maintenance_------------------------------------                          710, 000
952          REPORT OF CHIEF OF ENGINEERS,                             U. S. ARMY,                      1944

Maintenance (operating and care):
   Operations------------------------------------------$1,208, 000
   Ordinary repairs---------------------------------------137,    000
   Improvement and reconstruction----------------------------115, 000
           Total operating and care------------------------------1,                                              460, 000
           Total for all work------------------------------------3,                                              582. 000
  It is expected that the proposed expenditures will bring the project
as a whole to about 88.8 percent completion.
                                     Cost and financial summary
Cost of new work to June 30, 1944__
                                 ---------------------    1 $197, 728, 909. 26
Cost of maintenance to June 30, 1944---------------------     32, 677, 249. 13
      Total cost of permanent work to June 30, 1944-------                                          230, 406, 158. 39
Undistributed costs June 30, 1944------------------------                                                207, 395. 66
      Net total cost to June 30, 1944_
                                     --------------------                                           230, 613, 554. 05
Minus accounts payable June 30, 1944------------------                                                   138, 843. 46
      Net total expenditures   _--------------------------2 230, 474, 710. 59
Unexpended balance June 30, 1944-----------------------       1,261, 658. 47
           Total amount appropriated to June 30, 1944-                                 -1        2231, 736, 369. 06
      Fiscal year ending June 30        1940           1941               1942                   1943              1944

Cost of new work__---------   $5, 320, 981, 26 $3,800, 330. 21 $3, 034, 135. 94         $1, 213, 322. 20         $357, 836. 54
Cost of maintenance .. __ ____ 1,993, 263.95    1, 770, 898. 00 1, 885, 097.63           2, 272, 330. 09        1, 990, 587. 06
        Totalcost-------------- 7, 314, 245. 21
                 ................                  5, 571, 228. 21   4, 919, 233. 57        3, 485, 652. 29     2, 348, 423.60
Total expended --------------................
                          7, 453.869.94 5, 030, 360. 46 5, 974, 688. 87                     3, 424,179. 89      2, 541, 639. 46
Allotted----..---.---.--......-4, 073, 552. 32     5, 339, 775.00    2, 019, 300.00           223, 700.00       -608, 721. 79



Balance unexpended July 1, 1943-------------------------                                                $4, 412, 019. 72
Amount allotted from War Department Civil Appropriation
  Act approved June 2,1943                                                                                      0, 350. 00
                                                                                                               9-----------------------------
      Amount to be accounted for-----------------------                                                  4, 502, 369. 72
Deductions on account of revocation of allotment-----------                                                 699, 071. 79

Net amount to be accounted for--------------------------                                                 3, 803, 297. 93
Gross amount expended -                        $2, 594,192.89
Less:
     Reimbursements collected     $17, 014. 81
     Receipts from sales --------  35, 538. 62
                                                    52, 553. 43
                                                                                  --                     2, 541, 639. 46
      Balance unexpended June 30, 1944------------- ----                                                 1,261, 658. 47
Outstanding liabilities June 30, 1944 --------- $664, 798. 50
Amount covered by uncompleted contracts-           2, 496. 05
                                                                                                              667, 294. 55
     Balance available June 30, 1944--------------- -----                                                   594, 363. 92
Amount allotted in July 1944_-----------------------------                                               1, 830, 500. 00
            Amount available during fiscal year 1945---- -------                                         2, 424, 863. 92
  I Exclusive of $40,000 expended from contributed funds.
  2 Includes $5,863,584.26 from permanent indefinite appropriation of which $4,284,076.88 was for operating
and care of locks and dams and $1,579,507.38 for operating snag and dredge boats.
          RIVERS AND HARBORS-ROCK ISLAND, ILL., DISTRICT                                     953
Amount (estimated) required to be appropriated for com-
pletion of existing project 3- -    -               -_$20,                           514, 000. 00

Amount that can be profitably expended in fiscal year ending
June 30, 1946: 3 -       -  - - - - -   -     - - -    -    -
   For new work __ _                                                               1, 412, 000. 00
   For maintenance ----------------------------------
                    3_                                    _                        2, 170, 000. 00

       Total 3 .              "            --                      -    _ .
                                                                        __--       3, 582, 000. 00
8Exclusive   of available funds.

IMPROVEMENT OF RIVERS AND HARBORS IN THE ROCK
            ISLAND, ILL., DISTRICT
   This district comprises portions of western Illinois, southwestern
Wisconsin, southern and southwestern Minnesota, eastern and central
Iowa, and northeastern Missouri, embraced in the drainage basin of
the Mississippi River and its eastern and western tributaries between
mile 300 (above the mouth of the Ohio River) and mile 614, and of
its eastern tributaries only, between Hamburg Bay, at mile 261, and
mile 300. This district also includes the Illinois and Mississippi Canal
and the drainage basin of Bureau Creek, Ill.
   That section of the Mississippi River between mile 300 and mile
614 is included in the report on Mississippi River between Missouri
River and Minneapolis, Minn.
   District engineer: Lt. Col. John H. Peil, Corps of Engineers.
   Division engineer: Col. Malcolm Elliott, Corps of Engineers.
                                                IMPROVEMENTS

                  Navigation                                   Flood Control-Continued
                                                  Page                                       Page
1. Mississippi River between                          7. Union Township drainage
     the Missouri River and                                 district, Missouri __......._     963
     Minneapolis, Minn. (Rock                          8. Coralville Reservoir, Iowa___       964
       Island district)           -   --          939 9. Upper Mississippi River Ba-
2. Illinois and Mississippi.Canal                          sin, Rock Island district__       965
        Ill.                                      953 10. Emergency flood - control
3. Mill Creek and South Slough                             work under authority of
       at Milan, Ill_
4. Examinations, surveys, and
                                  -               958       Public Laws Nos. 138 and
                                                            318, Seventy-eighth Con-
        contingencies (general) ..                959       gress_                            966
5. Plant allotment____                           961 11. Preliminary     examinations,
                                                            surveys, and contingencies
              Flood Control                                 for flood control .........       967
                                                      12. Other flood-control projects
6. Gieen Bay levee and drain-                              for which no estimates are
      age district No. 2, Iowa -                  962       submitted          -              968
1. MISSISSIPPI RIVER BETWEEN THE MISSOURI RIVER AND MINNE-
              APOLIS, MINN. (ROCK ISLAND DISTRICT)

  For report on this improvement see page 939.
                    2. ILLINOIS AND MISSISSIPPI CANAL, ILL.

  Location.-This canal connects the Illinois and Mississippi Rivers,
proceeding from a point on the Illinois River about 12 miles from
La Salle across the State of Illinois to the Mississippi River at the
mouth of Rock River.
954           REPORT OF CHIEF OF ENGINEERS,                           U. S. ARMY,         1944

  Existing project.-This provides for the construction of a canal
from the Illinois River, near Bureau Junction, running westerly via
the Bureau Creek Valley to Rock River, near Colona, thence in the
bed of Rock River to the rapids near Milan, Ill., and thence to the
Mississippi River at the mouth of Rock River, at Rock Island, the
length of the main line being 75 miles. The feeder, 29.3 miles in
length, extends from Rock Falls on Rock River to the summit level
of the canal, about 28 miles from the Illinois River.
  There are 32 locks in the main canal, described in the following
tabulation. There is also a lock and controlling works at the head
of the feeder at Rock Falls, and a lock in Rock River at Rock Falls
connecting the pool of the Government dam with the power company's
dam below. This lock has dimensions similar to those in the main
canal and cost $75,000.
  The estimate of cost for new work, revised in 1902, was $8,911,551.12.
The estimated cost of operation and maintenance, made in 1936, is
$176,000 annually.
   The existing project was authorized by the following river and
harbor acts:

       Acts                       Work authorized                                   Documents


Sept. 19, 1890    Existing project adopted..---------------------H.      Ex. Doc. Nos. 316 and 429, 51st
                                                                        Cong., 1st sess., Annual Report, 1890
                                                                        p. 263.
                  Estimate of cost for new work revised to $8,911,-   H. Doe. No. 297, 57th Cong., 1st sess.
                    551.12.
June 26,19341 Operation and care of the works of improvement
               provided for with funds from War Department
               appropriations for rivers and harbors.
July     3,1930   For payment of $8,450.75 to the Mud Creek spe-      H. Doc. No. 108, 70th Cong., 1st sess.
                    cial drainage district for work accomplished by
                    the said district.
    Do_-.....     Secretary of War authorized to expend from funds    Specified in act.
                    appropriated and available for maintenance
                    and improvement of existing river and harbor
                    works the sum of $25,235 as a contribution to-
                    ward the relocation and reconstruction of the
                    highway bridge across the Illinois and Missis-
                    sippi Canal at Wyanet, Bureau County, Ill.,
                    known as Bridge No. 10.


  1Permanent      Appropriation Repeal Act.

  The latest published map is shown on page 2013 of Annual Report
for 1908.
                                                                     Table showing features of the Illinois and Mississippi Canal
                                                                                                             LOCKS

                                                             Location                                                   Locks
                                                                     T        so       i
                                                                                                           Dimensions             Depth on miter

             Name                       Distance
                                         from         Distance from nearest town or
                                                                                                                                       sill
                                                                                                                                                                 Character of foundation to
                                                                                                                                                                                          Year opened              Total cost
                                                                                                                                                                                                                                   H
                                                                                                                                                                                            navigation
                                        Missis-        mouth of navigable tribu-                       Greatest
                                         sippi         tary                                             length
                                                                                              Width of available
                                         River                                                                          Lift      Upper            Lower
                                                                                              chamber for full                                                                                                                     C
                                                                                                        width
                            -       I            -I                                          I-
                                                                                                                -                 -            I             I         -   _______ __     -_                                       w
                                         Miles                                                    Feet        Feet      Feet          Feet          Feet
Lock    No. 1...............             S74.87       Illinois River, 2,000 feet west.....            35      143.08       9.0          8.17           7.0       Sand and clay ..   --    .. Oct. 24, 1907           $41,305.03
Lock    No. 2......----....                73. 91     At Bureau Junction- .----                       35      143.08       9.0          8.17           7.0       Sand, clgy, and gravel__     - -do ....              42,099. 69
Lock    No. 3...............               73. 29     1/ mile west of Bureau Junction                 35      143.08       9.0          8.17           7.0. Quicksand and gravel__                                    39,172.01
Lock    No. 4___.._-_                      71.75      22 miles west of Bureau Junc-                   35      143.08       9.0          8.17           7.0 Sand and gravel .... .              _-do     .. .          39,357.10
                                                        tion.
Lock No. 5____--                .          70.63      3j miles west of Bureau Junc-                  35       143.08       8.0          8.17           7.0                                                            39,509.45    (1
                                                        tion.
Lock No. 6...............                  68. 75     5 miles west of Bureau Junction -_             35       143.08      10.0          8.17           7.0       Sand,     hardpan, and            do   ...           41,927.72
                                                                                                                                                                  gravel.
Lock No. 7_-_---_                          68.00 3 miles east of Tiskilwa _- - --                    35       143.08       8.0          8.17           7.0       Loam and sand ........        __do .       _         35,635.09
Lock N o. 8 _.. -.....-.-..                67. 02 2 miles east of Tiskilwa---- --                    35       149. 75      8.0          8.17           7.0          - d o ............  .... .....do      .. .        36,274.37
Lock No. 9--          - ..                 66. 80 1% miles east of Tiskilwa ---                      35       149.75       8.0          8.17           7.0       Clay --....-      ----           do    .-..          32,134.93
Lock No. 10--.           .                 64.98 At Tiskilwa --------------                          35       149.75       9.0          8.17           7.0       Sand and gravel          . ...    do                 36,113.71
Lock No. 11_ ---           _ -             64.13 1 mile west of Tiskilwa _- -_--                     35       149.75       9.0          8.17           7.0       ---do         ---------------     do         .-      36,710.05
Lock No. 12 ___.....                       63. 56 13 miles west of Tiskilwa ----.                    35       149.75       8.0          8.17           7.0         _do -     .    .------------ .do     -.            33,827.14
                                                                                                                                                                                                                                   C
Lock No. 13_-                              62.83 3 miles west of Tiskilwa --- -                      35       149.75      10. 0         8.17           7.0       Loam and clay-----------  do.                        32,294.88
Lock No. 14.........                       62. 02 3 miles east of Wyanet .-..                        35       149.75      10. 0         8.17           7.0       Sand and gravel----------do -                        31,524.90
Lock No. 15 ........                       61.42 2% miles east of Wyanet - --                        35       149.75      10. 0         8.17           7.0          do       ---       ... do -                       29, 974.01
Lock No. 16 _-----                         61.23 2 miles east of Wyanet ..----...                    35       149.75                    8.17               Loam, clay, and sand.---
                                                                                                                                                                                                                                   H
                                                                                                                          11.0                         8.0                                         do ..              34,08919
Lock No. 17 ........                       60. 98 1% miles east of Wyanet .. -                       35       149.75      10. 0         8.17           7.0 Sand and gravel-           .-..        .do ...             32,576.27
Lock No. 18.........                       59. 90 1 mile east of Wyanet.......                       35       149.75       9.0          8.17           7.0 Clay and gravel .----------- do ...                        35,372.69
Lock No. 19....- ,.                        59.12 At Wyanet         ------------                      35       149.75      10. 0         8.17           7.0-Sand and gravel ---------.              do ..              34, 239.36
Lock No. 20.........                       58. 09 1 mile west of Wyanet -----                        35       149.75      11.0          8.17           7.0 Loam, clay, and sand           ..-      do ..              36,838.76
Lock No. 21..........                      57. 83 1% miles west of Wyanet ...                        35       149.75      11.0          8.17           8.0  __ do ------------------               do ..              38, 026.88
Guard lock.........                        29. 20 29 miles north main-line canal       1             35       149.00     (2)            8.30           6.5 Lim estone:...............
                                                                                                                                                             . .
                                                                                                                                                               .do .........
                                                                                                                                                                                              .... do ..
                                                                                                                                                                                                   d o . ...
                                                                                                                                                                                                          .
                                                                                                                                                                                                                      32,678.57
Rock River lock 3.......                   29. 20 At Rock Falls, Ill.1                               35       143.08     (2)            8.47           6.6                                                            75, 605.01
Lock No. 22.........                       46.32 13 miles west of Wyanet ----                        35       143.08       9.0          8.17           7.0 Clay - --------------.----- do ...                         42,458.63
Lock No. 23.........                       37. 12 10 miles east of Geneseo -.. --                    35       143.08      11.0          8.17           7.0   ...do   .------                   -. do ..               41,777.95
Lock No. 24........______                  27. 05 At Geneseo-                                        35       143.08      11.0          8.17           7.0 Clay and gravel...----------do ..                          47, 059.15
Lock No. 25..............                  21.56 5% miles west of Geneseo......                      35       143.08       8.0          8.17           7.0 Sand...-----------------..-do ....                         40,492.10
     See footnotes at end of table.
                                                     Table showing features of the Illinois and Mississippi Canal-Continued
                                                                                                                        LOCKS-Continued

                                                         Location                                                                                         Locks
                                                                                                        I                                           -                  T


                                                                                                                           Dimensions                                          Depth on miter                                                                                                 0
                                                                                                                                                                                     sill                                                                                                     0
                                    Distance                                                                              sI                f            u         i                                           Character of foundation                    Year opened    Total cost
             Name                    from          Distance from nearest town or                                                                                                                                                                         to navigation
                                     Missis-        mouth of navigable tribu-                                         Greatest                                                                                                                                                                0
                                     sippi          tary                                                               length
                                                                                                             Width of available
                                     River                                                                   chamber for full                               Lift              Upper           Lower
                                                                                                                        width
                                                                                                 _      --        ---     I-         ----       I       -----               ------       -----            I-         --   -      -     -         I


                                       Miles                                                                    Feet                 Feet                   Feet                Feet             Feet
Lock No.     26_       _______          20. 46     5 miles east of Colona .. _.                                     35               143.08                    9.0                8.17             7.0      Sand. .......        .....                    Oct. 24,1907   $40, 428. 75         0
Lock No.     27__...._                  18.13      2% miles east of Colona ......                                   35               143.08                    8.0                8.17             7.0      Gravel.............---                       ....do.,......
                                                                                                                                                                                                                                                               do.......  39, 090. 66
                                                   At Colona_..                                                     35               143.08                    8.0                8.17             7.0      Rock....................                     .....            30, 808. 53
Lock No.     28_____..                  15.70
Lock No.     29.... ........            13. 37     2% miles west of Colona .                                        35               143.08                   11.0                8.17             7.0     ..... do.........                             ....do-....... 37, 262.65
Lock No.     30........                  4.62      1% miles east of Milan-.......                                   35               149.00                    0                  7.00             7.0      Rock, etc., hardpan.....                     ....do.......    71,-588.00
                                                                                                                                                                                                                                                         ..... do.......
Lock No.     31.___..                    2.02      1 miles west of Milan ......                                     35               145.42                    6.0                7.17             7.0      Clay and gravel-......                       ..... do.......  38, 711.44         0
Lock No.     32.._...                      . 15    32 miles west of Milan.......                                    35               143.08                   12. 0               8.00             7.O         ... do.........       .......                              85, 468. 31

       Total cost of locks__      I----------I                       ----------            -                 --------          ---          ----
                                                                                                                                             ---                       ,--            -----       -             --                         ---       -        .---       1,382,432.98
                                                                                       ADDITIONAL FEATURES ENTERING INTO COST OF PROJECT
Sterling Dam and dams at Milan, Ill...............................................................-----------------------------------------------------------...'-----------------------------------------.........................  $128, 857.97       0
Bridges---------------------_                                                                                             -------------------------------------------------------------------------- 1,1,513,82                       513, 823. 25------------------------
C uvers . .. . .. . .. . .. . .. . .. . ..-----------------------------------------------------------------------------------
Culverts--------------                           .....            . .. . .410,...                        . .                                                                             -----------------------------------------     410,1919
                                                                                                                                                                                                                                        6 198. 19
Houses--     ---------        -  -.-.---------------------------------------------------------------------------------------------------------------------------                                                                       76.974. 69
Surveys, flowage, and right-of-way....................                                                                                                                                                                                     656. 61
                                                                                                                                                                                                                                      7--------------------------------------
Excavations, embankments, clearing, fences, etc...--.....-------------------------------------------------------------------------------------------                                                                                2,956,451.61
Rock River pool-Dredging, removing snags and stumps, etc.........................                            ----------------------------------------------------------------------------------
Contribution to Mud Creek special drainage district-Dredging..........................................-----------------------------------------...----------------------------------------........................................
                                                                                                                                                                                                                                                                           152,43................
                                                                                                                                                                                                                                      152, 439. 58---------------------------
                                                                                                                                                                                                                                        8, 450.75
Contributions to State of Illinois-Relocation and reconstruction of highway bridge at Wyanet, Ill ---.-------------------------------------------------------                                                                          25, 235. 00
Miscellaneous------------------...........................----------------------------------------------------------------------------------------------------.............                                                           223, 622. 78
       Total additional features..........                                        ....................................
                                                                                  .....................................                                                                                                                                                               43---------------------------
                                                                                                                                                                                                                                                                         6, 222, 710. 43
       Total cost of project----------................                                         .-----------------------------                                          --             --------        -          --------------------------------- 7,605, 143. 41
    1Feeder     section.
    2Variable.
    3 Rock River lock is on Rock River at Rock Falls, Ill. It is located in the south end of the Sterling Dam and about 600 feet below the guard lock of the Illinois and Mississippi
Canal (feeder section).
    NOTE.-There are no dams except at the guard lock and lock 30. At the former locality there is a fixed dam across the Rock River, with a movable crest constructed of wood,
concrete, and steel; at lock 30 there are crib dams across the north and south channels of Rock River. The north dam has a 60-foot opening and has been superseded by a concrete
power dam a short distance below; the south dam adjoining lock 30 has been reinforced with concrete laid in the water,
         RIVERS AND          HARBORS-ROCK ISLAND,               ILL., DISTRICT      957
  Local cooperation.-Fullycomplied with.
  Terminal facilities.-None.
  Operations and results during fiscal year.-The work done during
the fiscal year consisted of repairs to bridges, buildings, telephone lines,
roadways, and fences; cleaning out culverts, aqueducts, and seep
ditches; maintenance dredging in the canal by contract and by hired
labor; repair of canal banks, and cutting and burning of brush and
weeds along the canal right-of-way. The costs during the fiscal year
were $191,044.96, for operating and care. The expenditures were
$182,631.83.
   Condition at end of fiscal year.-The existing project was completed
in 1918. All locks, dams, aqueducts, buildings, and other appurte-
nances are in fair condition. The project depth of the channel is 7 feet.
The bottom width of the canal is 52 feet and width at the water surface
is 80 feet, except at aqueducts where the width is 40 feet, and at locks,
35 feet.
   The total cost to June 30, 1944, from regular funds was $9,024,647.44,
of which $7,580,143.41 was for construction and $1,444,504.03 was for
operation and care. The expenditures were $9,001,429.91. The costs
and expenditures from Emergency Relief funds for removal of snags
and stumps in Rock River pool were $25,000, all new work. In addi-
tion, the sum of $4,143,282.27 was expended between April 1895 and
June 30, 1936, on the operating and care of the works of improvement
under the provisions of the permanent indefinite appropriation for
such purposes.
   Proposed operations.-The unexpended balance at the end of the
fiscal year, $27,113.47, plus an allotment of $180,000 received in July
1944, $207,113.47, will be applied as follows:
Accounts payable, June 30, 1944----------------------------                 $23, 191. 53
Maintenance (operating and care):
    Operations ------------------------------    $60, 000. 00
    Ordinary repairs---------------------------   78, 000. 00
    Improvements and reconstruction ------------- 45, 921. 94
                                                                             183, 921. 94

       Total---_   -----.------------------------------------               207, 113. 47
  The additional sum of $173,000 can be profitably expended for
operating and care of the canal during the fiscal year 1946, as follows:
Operations    ------------------------------------------------  $60,000
Ordinary repairs --------------------------------------------- 60, 000
Improvements and reconstruction -------------------------------  53, 000
       Total -----------------------------------------------------               173, 000
                             Cost and financial summary
Cost of new work to June 30, 1944_-------------------------$7,              605, 143. 41
Cost of maintenance to June 30, 1944_--------------_-------5,               587, 786. 30
       Total cost of permanent work to June 30, 1944 --------- 13, 192, 929. 71
Undistributed costs June 30, 1944--.-----------------------         -           -26.00
        Net total cost to June 30, 1944-___ _-----------_                 13, 192, 903. 71
Plus accounts receivable June 30, 1944___
       Gross total costs to June 30, 1944------ --------                  13, 192, 903. 71
Minus accounts payable June 30, 1944----------------23,                           191. 53
      Net total expenditures------- ------- ----------                    13, 169, 712. 18
                                          -
Unexpended balance June 30, 1944- ......-.... -       -                       27, 113. 47
        Total amount appropriated to June 30, 1944-----------13, 196, 825. 65
958         REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                           1944


   Fiscal year ending June 30           1940            1941            1942             1943                1944

Cost of new work .......
Cost of maintenance ___-_-..____     $190, 311. 57   $176, 272. 18   $173, 738. 23   $191, 113. 17         $191,044. 96
Total expended.   ----------------    181, 929. 91    178, 047. 08    177, 150. 73    194, 491.17           182, 631.83
Allotted------
         ..         _ ___ _ -__       175, 000. 00    186, 000. 00    162, 850.00     197, 400.00            15,800.00


Balance unexpended July 1, 1943----------------------------                                      $193, 945. 30
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943-----------------------------------                                            30, 000. 00

      Amount to be accounted for-- ------       -------                                              223, 945. 30
Deductions on account of revocation of allotment.--------------                                       14, 200. 00
       Net amount to be accounted for-----------------------209,                                             745. 30
Gross amount expended_------                  ---         $183, 476. 54
Less reimbursements collected -------------------                844. 71
                                                                                                     18,     631. 83

       Balance unexpended June 30, 1944---------------------                                          27, 113. 47"
Outstanding liabilities June 30, 1944------------- $21, 173. 79
Amount covered by uncompleted contracts--------      5, 000. 00
                                                                                                      26, 173. 79
     Balance available June 30, 1944_                                        --- _939.                          68
Amount allotted in July 1944                                                                               000. 00
                                                                                                     1------80,

         Amount available during fiscal year 1945---------------                                     180, 939. 68

Amount that can be profitably expended in fiscal year ending
June 30, 1946, for maintenance 1-         -     -    -     -                                        173, 000. 00
1 Exclusive of available funds.

              3. MILL CREEK AND SOUTH SLOUGH AT MILAN, ILL.

   Location.-Mill Creek empties into South Slough about 1 mile
east of the town of Milan, Ill., and 6.5 miles above the mouth of South
Slough, which empties into the Mississippi River.
   Previous projects.-Adopted by the River and Harbor Act of Jan-
uary 21, 1927. (For further details see p. 1132, Annual Report for
1932, and p. 1081, Annual Report for 1938.)
   Existing project.-This provides for floodgates in the walls of the
canal, or other devices for carrying the floodwaters of Mill Creek
across the canal right-of-way into Rock River; for the construction
of a levee on the east bank of Mill Creek extending from the Chicago,
Rock Island & Pacific Railroad to the canal embankment; for the
construction of a levee on the west bank of Mill Creek and its exten-
sion in a westerly direction to a connection with Water Street at the
point E, shown on map of project document; and for the removal
of obstructions in Mill Creek and South Slough, at an estimated
cost of $87,500 for new work and $2,000 annually for maintenance.
   The existing project was adopted by the River and Harbor Act
approved July 3, 1930 (Rivers and Harbors Committee Doc. No. 19,
71st Cong., 2d sess.). The latest published map is in the project
document.
   Terminal facilities.-None.
   Operations and results during fiscal year.-The work done during
the fiscal year consisted of cutting brush and willows on banks of
           RIVERS AND HARBORS                       ROCK ISLAND,            ILL., DISTRICT           959
Mill Creek and South Slough; removal of debris at Mill Creek spill-
way, and operating spillway gates. The cost of the work was $1,483.69
for maintenance. The expenditures were $1,406.02.
   Condition at end of fiscal year.-The existing project was completed
in 1932. At the end of the fiscal year the project was in good condi-
tion. The total cost under the existing project to June 30, 1944, was
$84,573.14, of which $63,633.58 was for new work and $20,939.56 was
for maintenance. The expenditures were $84,167.98.
   Proposed operations.-The unexpended balance at the end, of the
fiscal year $465.60, plus $2,000 received in July 1944, $2,465.60, will
be applied to payment of accounts payable, $362.16, and minor dredg-
ing and snagging to maintain channel, $2,103.44.
   The additional sum of $2,000 can be profitably expended during the
fiscal year 1946 for maintenance operations.
                                     Cost and financial summary
Cost of new work to June 30, 1944    --------------------------                               $63, 718.82
Cost of maintenance to June 30, 1944------------------                                         20, 939. 56
       Total cost of permanent work to June 30, 1944                        -----------        84, 658. 38
Undistributed costs June 30, 1944_ -----------                                                      43. 00
      Net total cost to June 30, 1944                                                          84, 615. 38
Minus accounts payable June 30, 1944_--------                                      ---             362. 16
      Net total expenditures --------------------------------                                  84, 253. 22
Unexpended balance June 30, 1944------------------------------                                     465. 60
        Total amount appropriated to June 30, 1944---------------                              84, 718. 82

   Fiscal year ending June 30          1940            1941          1942          1943           1944

Cost of new work
Cost ofmaintenance-----     _ _ _.
                                 -    $3, 500. 83     $1, 208. 31   $2, 349. 44   $1,984.08       $1,483.69

                -
Total expended .____-...... .  3,565. 83               1, 208 31     2, 349. 44   1,656. 59        1, 406. 0
Allotted-....._ ...............2,000.00                2,000.00      2,000.00_------- - ----       1,000.00


Balance unexpended July 1, 1943 ------------------------                                          871. 62
Amount allotted from War Department Appropriation Act approved
July 14, 1932_ -------------------------------------------                                     1, 000. 00
       Amount to be accounted for_----_---_____                                                 1,871.62
Gross amount expended----------                                                                   406. 02
                                                                                                1-,
      Balance unexpended June 30, 1944 -------------                                              465. 60
Outstanding liabilities June 30, 1944 ..-----------------------                                   465. 60

Amount allotted in July 1944--- -     ------------               2, 000. 00
Amount available during fiscal year 1945------------------------2, 000. 00
Amoun6 that can be piofitably expended in fiscal year ending June
30, 1946, for maintenance 1___      -     --                   _-2,                               000. 00
1 Exclusive of available funds.

   4. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)
  The cost of work during the fiscal year amounted to $53,918.61;
the expenditures were $54,527.66. The balance unexpended June 30,
1944, $11,276.01, plus an allotment of $166,000 received in July 1944,
$177,276.01, will be applied as needed during the fiscal year 1945
 960            REPORT OF CHIEF OF ENGINEERS,                                                            U. S. ARMY,                1944

to payment of expenses incurred under this heading. The additional
sum of $240,600 can be profitably expended during the fiscal year
ending June 30, 1946.
                                                         Cost and financial summary
Cost of new work to June 30, 1944
Cost of maintenance to June 30, 1944_                                             -          --------                                  $674, 896. 84

       Total cost of permanent work to June 30, 1944_---       -                                                                         674, 896. 84
Undistributed costs June 30, 1944 ------------------------------                                                                              28. 00
       Net total cost to June 30, 1944_-------                                                                              ---          674, 924. 84
Minus accounts payable June 30, 1944_--------                                                                               ---           3, 255. 44
       Net total expenditures_--- -----------                                                                                            671, 669. 40
Unexpended balance June 30, 1944_--    ----------                                                                                        11, 276. 01
            Total amount appropriated to June 30, 1944--------------                                                                     682, 945. 41


     Fiscal year ending June 30                             1940                       1941               1942               1943                 1944

C os t of n ew w ork . .--
                         - - - - - - - --            -. -. - - - -       .   --    - - -          ------------
                                                                                                  .-.    . . . . . .                .    .    . ..--
Cost of maintenance-                  _ _ _ _....        $47, 556. 09            $22, 767.66        $27, 651.94         $40, 776. 12           $53,918.61

TI'otal expended     ...............----------------.     48,650. 97              23, 069. 25           28,062.04          38, 362.28            54, 527. 66
Allotted-........................                         42, 000.00              15,000. 00 -------------                 55, 500.00            43, 000.00



Balance unexpended July 1, 1943-------------- _$22,                                                                                              803. 67
Amount allotted from War Department Appropriation
   Act approved July 14, 1932_------               ---                                                                 $78. 76
Amount allotted from War Department Civil Appro-
   priation Act approved July 19, 1937                                        --------------                           433. 42
Amount allotted from War Department Civil Appro-
   priation Act approved June 2, 1943                                        ---------------                     10, 000. 00
Amount allotted from War Department Civil Appro-
   priation Act approved June 11, 1938--------------                                                                 3, 167. 57
Amount allotted from War Department Civil Appro-
   priation Act approved June 28, 1939                                        --------------                     16, 040. 89
Amount allotted from War Department Civil Appro-
   priation Act approved June 24, 1940--------------                                                             13, 279. 36
                                                                                                                                             43, 000. 00

        Amount to be accounted for ----------------------------                                                                              65, 803. 67
Gross amount expended--- ---------                   $55, 009. 71
Less reimbursements collected-----------------------      482. 05
                                                                                                                        -                    54, 527. 66

        Balance unexpended June 30, 1944_------                ---                                                                           11, 276. 01
. Outstanding liabilities June 30, 1944---------------------------                                                                            4, 898. 17

      Balance available June 30, 1944_--------                                                                               ---              6, 377. 84
Amount allotted in July 1944--
                             ____------------166,                                                                                                000. 00

            Amount available during fiscal year 1945                                             -----------------                       172, 377. 84

Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1 -------    _____------                                                                                     240, 600. 00
   1Exclusive of available funds.
                RIVERS AND HARBORS---ROCK                                 ISLAND, ILL., DISTRICT                           961
               5. PLANT ALLOTMENT, ROCK ISLAND, ILL., DISTRICT
                                             Cost and financial summary
Undistributed costs June 30, 1944.                          ------------------------                           $1, 669. 841. 23

Net total cost to June 30, 1944 ----------------------------   1, 669, 841. 23
Plus accounts receivable June 30, 1944 -----------------------    146, 104. 90
      Gross total costs to June 30, 1944 -------------------                                                    1, 815, 946. 13
Minus accounts payable June 30, 1944 ---------------------                                                          76, 120. 62

      Net total expenditures      ------------------------                                                      1, 739, 825. 51
Unexpended balance June 30, 1944_                                                                                  155, 311.01
            Total amount appropriated to June 30, 1944                                                     1, 895, 136. 52
                                                                                                      .------------


     Fiscal year ending June 30                     1940           1941             1942                1943            1944

Total expended- .                .---------- -$2,     575. 63 -$102, 301.98   $250, 651.47       -$18,584.94        -$252, 763.45
Allotted__--_____--------.-__-           _        25, 000. 00   -47,953.77        223, 000. 00       -11,129.40      -154,000.00



Balance unexpended July 1, 1943..       -------------           $56, 547. 56
Deductions on account of revocation of allotment--------------154, 000. 00
Net amount to be accounted for__                                                                                    97, 452. 44
                                                                                                                  ---------------
Gross amount expended_                              $1, 708, 129. 82
Less:
     Reimbursements collected.     $1, 946, 881. 90
     Receipts from sales ---------      14, 011. 37
                                                      1, 960, 893. 27
                                                                                                                -- 252, 763. 45
      Balance-unexpended June 30, 1944                                                                            155, 311. 01
Outstanding liabilities June 3, 1944_ --------                                                   ---              222, 847. 22
      Balance available June 30, 1944_ -                                                         _                 ----- 536. 21
                                                                                                                  -67,
Accounts receivable June 30, 1944_-   - ----------                                                                 146, 104. 90

            Unobligated balance available June 30, 1944------------                                                 78, 568. 69

 _Status of all investigations for navigation called for by river and harbor acts and
             "                    committee resolutions

                                                                     Date trans-Recon
              Locality                    Authorization act           mitted to     Document No.                  Reommenda-
                                                                       Congress                                         tion


Des Moines River, Iowa,                 River and Harbor Act,       May 31, 1944        H. 651, 78th Cong.,        Favorable.
construction of dam at or               June 20, 1938.                                   2d sess.
   near Madrid, for naviga-
   tion and flood control.
Illinois and Misslssippi                Rivers and Harbors ........                 _.....
   Canal, Ill.      -                     Committee resolu-
                                          tion, Sept. 21, 1943.
Mississippi River between               Rivers and Harbors ............
mouth of the Illinois River              Committee resolu-
and Minneapolis, Minn.,                  tion, Sept. 21, 1943.
for 12-foot channel with
suitable widths.
Mississippi River between               Commerce Committee ...........
-Missouri Riverand Minn-                 resolution, Sept. 22,
  eapolis. Minn. (damages                 1944.
  caused at Clinton. Iowa,
  by creatiol of pool No. 14
  on Mississippi River).

           6166354-45-pt. 1, vol. 1                    61
962          RIEPORT OF CHIEF OF ENGINEERS,                          U. S. ARMY,                1944

       6. GREEN BAY LEVEE AND DRAINAGE DISTRICT NO. 2, IOWA

   Location.-The work covered by this project is on the right banks
of the Skunk River and Mississippi River, Lee County, approxi-.
mately 387-496 miles above the mouth of the Ohio River.
   Ili   isting project.---The plan of improvement provides for the recon-
structioni of a system of levees consisting of the following features:
About 8.9 miles of main river levee, 7.3 miles of levee along Skunk
River, .17 miles of levee along Lost Creek involving the placing of
200,000 cubic yards of earthwork; excavation of.four cut-off channels
for Skunk River and construction of four earth dams across the
present channel of Skunk River, involving the removal of 242,900
cubic yards of earth and placing of 48,550 cubic yards of earth, respec-
tively... The project will provide protection for 13,337acres of farm
land. The existing project was authorized by the Flood Control Act
approved June 22, 1936. The estimated cost of new work, revised in
1941, is$139,500 for construction. The estimated cost of lands and
damages is $1,400 for lands and $1,200 for damages.
   Local cooperation.-See page 7 for requirements. Assurances were
approved by the Secretary of War on June 11, 1940. Rights-of-way
for the Skunk River section were approved on June 7, 1940. Rights-
of-way for the Mississippi River section have not: been received.
   Operations and results during fiscal year.-Minor work in connec-
tion with the preparation of designs and plans for the Mississippi
River section was performed. The costs during the fiscal year were
$151.59 for new work. The expenditures were 224.33.
    Condition at end of fiscal year.-Construction work on the Skunk
River section has been completed. Construction work on the Missis-
sippi River section has not been started. The costs and expenditures
to June 30,1944, were $88,561.11 for new work.
   Proposed operations.-Of the balance unexpended at the end of
the fiscal year, $28,238.89, the sum of $1,600 will be applied to the
preparation of plans and specifications for the improvement of the
Mississippi River section. The balance is available for revocation.
    No additional funds can be profitably expended during the fiscal
year 1946 in view of the existing Federal policies on wartime con-
struction.
                                      Cost and financial summary
Cost                             ---------------------------
     of new work to June 30, 1944_                                                                   $88, 561. 11
Cost of maintenance to June 30, 1944 ....
            Total cost of permanent work to June 30, 1944-------------                                88, 561. 11
                     _
Net total expenditures--       -----------------                                                      88, 561. 11
Unexpended balance June 30, 1944-                                                      ..-.           28, 238. 89
            Total amount appropriated to June 30, 1944--------------                                 116, 80000O


   Fiscal year ending June 30             1940            1941        1942               1943                1944

Cost of new work._............          $1, 675.46     $61, 414.84   $4;036.16     '   $17, 358.93               $151.59
Cost of maintenance.................                                                             ................
Total expended..................          1, 261.79     454,
                                                          799. 59     9, 728, 76        18, 671.05                  224.33
Allotted.       .............-------------...-----------
                                              ............---.
                                          ......         -32,500.    49,300.00
                 FLOOD      CONTROL---ROCK        ISLAND, ILL., DISTRICT                    963
Balance unexpended July 1, 1943 ----------------------------                        $28, 463. 22
Gross amount expended_--------------------------------------                             224. 33
      Balance unexpended June 30, 1944_                                              28j. 238,. 89
Outstanding liabilities June 30, 1944___168.                                                    65

         Balance available June 30, 1944_                        ...........-----    28, 070. 24

Amount (estimated) required to be appropriated for completion of
existing project 1          ------------------                                      22, 700. 00
  1 Exclusive of available funds.


            7. UNION TOWNSHIP DRAINAGE DISTRICT, MISSOURI

   Location.-The work covered by this project is on the west bank
of the Mississippi River in Lewis County, Mo., opposite and upstream
from Quincy, Ill., 331 to 335 miles above the mouth of the Ohio
River.
   Existing project.-The plan of improvement provides for the im-
provement of 3.2 miles of river-front levee and 5.9 miles of cross
levees, including the placing of 250,000 cubic yards of earthwork, to
provide protection against a recurrence of the maximum flood of
record to 5,037 acres of farm land. The existing project was se-
lected and approved by the Chief of Engineers for construction under
the general authorization for the upper Mississippi River Basin con-
tained in the Flood Control Act approved June 28, 1938. The esti-
mated cost of new work revised in 1943 is $99,600 for construction.
The estimated cost of lands and damages is $2,300.
   Local cooperation.-Seepage 7 for requirements.      Assurances and
rights-of-way for all sections except a portion of the Durgans Creek
levee were approved by the Acting Secretary of War on September
8, 1941.
   Operations and results during fiscal year.-The work done during
the fiscal year consisted of minor work in connection with pireparation
of plans. The costs and expenditures during the year were $50.43
for new work.
   Condition at end of fiscal year.-Construction work on the Oyster
Creek and Mississippi River sections has been completed; work on the
Durgans Creek section has not been started. The total cost and ex-
penditures to June 30, 1944, were $50,281.47 for new work.
   Proposed operations.-The balance unexpended on June 30, 1944,
amounting to $2,339.17, will be applied to work in connection with de-
signs and tests and to the preparation of contract plans and specifica-
tions by hired labor during the fiscal year 1945..
   No additional funds can be profitably expended during the fiscal
year 1946 in view of the existing Federal policies on wartime
construction.
                                    Cost and financial summary
Cost of new work to June 30, 1944 ..                                 __             $50, 281. 47
Cost of maintenance to June 30, 1944_ _.              ..                             .    .

         Tctal cost of permanent work to June 30, 1944.......-------------           50, 281. 47

Net total expenditures-  -   -            .--------------.--..                       50, 281. 47
Unexpended balance June 30, 1944,-.-------.--------. .-....                           2, 339. 17

         Total amount appropriated to June 30, 1944------.--....-.-52, 620. 64
964            REPORT OF CHIEF OF ENGINEERS,                                                     U. S.         ARMY,     1944


    Fiscal year ending June 30                   1940                    1941                       1942          1943             1944

Cost of new work---------------.    .           $4, 971.05                 $640.43             $ 43,848.07         $ 21. 49           $50.43
Cost of maintenance-------------............-                  .......
                                                        ---------------------------------------------------

Total expended....-----------------.             4,908.78                    697.54               43, 710.26           164.46             50.43
Allotted-----------------------.--------------                         12, 070.64              -20, 400.00        2,200.00...........


Balance unexpended July 1, 1943-----------------------------_ $2, 389. 60
Gross amount expended ---------------------------------------      50. 43

      Balance unexpended June 30, 1944-----------------------                                                                    2, 339. 17
Outstanding liabilities June 30, 1944 ----------------------------                                                                   75. 00

            Balance available Jurs 30, 1944--------------------------                                                            2, 264. 17

Amount (estimated) required to be appropriated for completion of                                                                47, 000. 00
existing project. 1
  I Exclusive of available funds.


                                    8. CORALVILLE RESERVOIR, IOWA

   Location.-The work covered by the project is on the Iowa River
in Johnson County, Iowa, approximately 83.5 miles above the mouth
of the waterway which empties into the Mississippi River about 433
miles above the mouth of the Ohio River.
   Existing project.-The plan of improvement provides for the con-
struction of an earth-fill dam, 1,400 feet long at the top, rising ap-
proximately 95 feet above the stream bed, with a reservoir providing
for a controlled storage of 400,000 acre-feet. The outlet works are
located adjacent to the left abutment and the uncontrolled spillway
is located on the right abutment with discharge from spillway en-
tering the river about 900 feet downstream from the toe of the dam.
The reservoir will accomplish almost complete control of floods and
will minimize flood damages on the Iowa River from the dam to the
mouth of the Cedar River. It will provide a large degree of protec-
tion for lands along the Iowa River below the mouth of the Cedar
River, and significant reductions of Mississippi River flows at Keo-
kuk, Iowa, and reduction in flows at Cairo, Ill. The existing project
was selected and approved by the Chief of Engineers under the gen-
eral authorization contained in the Flood Control Act approved
June 28, 1938. The estimated cost of new work, revised in 1940, is
 $4,217,000 for construction and $1,790,000 for lands and damages.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operations and results during fiscal year.-The work done during
the fiscal year consisted of studies and investigations in connection
with the consideration of alternate dam sites. The costs during
the year were $12,760.20, for new work. The expenditures were
$10 319.13.
    (ondition at end of fiscal year.-Construction work has not been
started. The costs to June 30, 1944, were $229,093.74 for new work.
The expendituires were $226,457.44.
   Proposed operations.-The balance unexpended on June 30, 1944,
amounting to $65,190.78 will be applied to accounts payable, June 30,
                   FLOOD CONTROL--ROCK                             ISLAND,        ILL.,             DISTRICT                    965
1944, $2,362.30, and to surveys, hydraulic studies, and preparation of
contract plans and specifications, by hired labor, $62,828.48.
  Additional funds in the amount of $50,000 can be profitably ex-
pended during the fiscal year 1946 on investigations and plans.
                                                Cost and financial summary
Cost of new work to June 30, 1944_ _-                                     -            .     -.                   $229, 093. 74
Cost of maintenance to June 30, 1944.------                                                                 ---
      Total cost vf permanent work to June 30, 1944-----------                                                       229, 093. 74
Undistributed costs June 30, 1944                                                                                         274. 00
                                                                                                                       ------------------------------

      Net total cost to June 30, 1944- -     -228,                                                                         819. 74
Minus accounts payable June 30, 1944_-------                                                          ---               2, 362. 30
      Net total expenditures__-
                             .         ---------...                                                                  226, 457. 44
Unexpended balance June 30, 1944_ -------------                                                                       65, 190. 78
          Total amount appropriated to June 30, 1944-------------                                                    291, 648. 22

    Fiscal year ending June 30                     1940           1941                1942              1943                 1944

Cost of new work ..........          .          $146, 163. 65   $28, 998. 51    $17, 150.07            $3, 441.17           $12, 760. 20
Cost of maintenance .-                                                                          -
Total expended.....      ......---------------. $145, 715. 39    34, 347. 24      18. 574. 53           3, 837. 69           10, 319. 13
Allotted---
         .............                     --------------
                                         ....    ....     -180,000.      00    -24, 451.78             72, 500.00


Balance unexpended July 1, 1943__-----                                                 ---- -               -        $75, 509. 91
Gross amount expended--- -      ----------------                                                                      10, 319. 13
       Balance unexpended June 30, 1944----------------------65, 190. 78
Outstanding liabilities June 30, 1944 ---------------------    2, 600. 00
          Balance available June 30, 1944_-                              ----------                                    62, 590. 78
Amount (estimated) required to be appropriated for completion of
existing project 1_-----_ _          -----                _-__                                                 5, 715, 351. 78
Amount that can be profitably expended in fiscal year ending June
30, 1946, for new work                      -     - _-- -                                                        -_-_50,    000. 00
  I Exclusive of available funds.


      9. UPPER MISSISSIPPI RIVER BASIN, ROCK ISLAND DISTRICT

   Location.-The Mississippi River Basin above the Ohio River, ex-
clusive of the Missouri River Basin, in the Rock Island district.
   Existing project.-The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control and other
purposes in the upper Mississippi River Basin described in Flood
Control Committee Document No. 1, Seventy-fifth Congress, first ses-
sion, with such modifications thereof as in the discretion of the Sec-
retary of War and the Chief of Engineers may be advisable, and
authorized $6,600,000 for reservoirs and $2,700,000 for local flood-
protection works on the upper Mississippi and Illinois Rivers; the
reservoirs and local protection projects to be selected and approved
by the Chief of Engineers. The act specifically provides that the
authorization shall include the enlargement and extension of a system
of levees located on the south side of the Sangamon River east of
Chandlerville, Ill., as set forth in House Document No. 604, Seventy-
fifth Congress, third session. The following individual projects lo-
966         REPORT OF CHIEF OF ENGINEERS,                              U.. S. ARMY,              1944

cated in the Rock Island district were considered in the comprehen-
sive plan:
                                                RESERVOIRS

                                                                                                           Total
             Name                           Tributary basin                        State                 estimated
                                                                                                        Federal cost

Central City-..._- ..... ____
                          _                     ------------
                                    Wapsipinicon_                     Iowa .....--------------------     $2, 290,000
Coralville 1------                  Iowa-          -   -       -
                                                              ....
                                                           ........       do--      -                      6,007, 000
Rochester_ .... ......--------------------.      do        ------------------
                                                             ....             . do -------------------- 3, 952,000
Howell ..................-------------------- Des Moines----_        _ .....
                                                                        -       do-------------------   13, 544,000


                                                       LEVEE

                             .................. Missouri_-
Union Township drainage dis---------------------------                                  --..--               $99, 600
trict.1

  1See individual report for details of project.

   Local cooperation. See page 7 for requirements.
   Operations and results during fiscal year.-None other than those
shown on individual reports for Coralville Reservoir and the Union
Township drainage district projects.
   Condition at end of fiscal year.-The status of planning of Coral-
ville Reservoir and the construction progress of the Union Township
drainage district project, which have been selected for construction
under this authorization, are given in individual reports.
   Proposed operations.-No operations are proposed in the fiscal
years 1945 and 1946 other than those shown in the individual reports.
10. EMERGENCY FLOOD-CONTROL WORK UNDER AUTHORITY OF PUB-
      LIC LAWS NOS. 138 AND 318, SEVENTY-EIGHTH CONGRESS

   Because of the heavy demands for emergency repair work to flood-
control structures damaged or destroyed by the disastrous floods
which occurred in the spring of 1943 and again in the spring of 1944,
Congress, in the act approved July 12, 1943, Public, No. 138, Seventy-
eighth Congress, and in the act approved May 29, 1944, Public, No.
318, Seventy-eighth Congress, authorized the amounts of $10,000,000
and $12,000,000, respectively, to be appropriated as emergency funds
to be expended under the direction of the Secretary of War and the
supervision of the Chief of Engineers for the repair, restoration, and
strengthening of levees and other flood-control works which had been
threatened or destroyed by the recent floods. (See. p. 9 for details.)
Pursuant to the act of July 12, 1943, $1,285.80 was allotted to the
Rock Island district during the fiscal year for emergency flood-control
work.
   Emergency repairs consisting of the filling of 13 small crevasses
in east levee and 4 small crevasses in west levee of the Six Mile Drain-
age and Levee District, Pike County, Ill., located within, but not a
part of, the Sny Island Levee District, were accomplished at a cost
of $1,285.80. Expenditures were $1,285.80.
   Pursuant to the act of May 29, 1944, an allotment of $350,000,
made in July 1944, will be applied during fiscal year 1945 to emer-
gency levee repair work and for flood fighting and rescue work neces-
sitated by the spring floods of 1944.
                             FLOOD CONTROL--ROCK                                     ISLAND, ILL., DISTRICT                                      967
                                                        Cost and financial summary
Cost of new work to June 30, 1944______---.--------                                                                                        ----    ..-
Cost of maintenance to June 30, 1944-_-----                                                                      -----                    $1, 285. 80

       Total cost of permanent work to June 30, 1944-------------                                                                          1, 285. 80
Net total expenditures_--      --  __-----------                                                                                           1, 285.80
Total amount appropriated to June 30, 1944                                                                                                    285. 80
                                                                                                                                           1,---------------------

      Fiscalyearunding June 30                               1940                  1941                 1942                1943              1944

C ost of new work .. .                     . _. . . . ,.             .   .    . . . ..              . . . .-..              . . . .         . . . .
        Costfnewor------------------------ -------------- -------------- ------------
Cost of maintenance----------------   ------------------------------------------      $1, 285.80
Total expended--------------------------...............                         -------------------------------------                          1,285.80
Allotted.............-----------------..    ---        ----..........           -------------.--                                -    -         1,285. 80


Balance unexpended July 1, 1943                                                                                                          ---------
Amount allotted from Second Deficiency Appropriation Act July
  12, 1943 ---------------------------------------------                                                                                  $1,500.00
Deductions on account of revocation of allotment--------------                                                                               214. 20

      Net amount to be accounted for-----------------------                                                                                1, 285.   80
Gross amount expended- _________--------------1,                                                                                              285.   80
Amount allotted in July 1944_ ___350,                                                                                                         000.   00
Amount available during fiscal year 1945 ---------------------                                                                           350, 000.   00
11. PRELIMINARY                             EXAMINATIONS, SURVEYS,                                              AND       CONTINGENCIES
                                                 FOR FLOOD CONTROL
   The costs for work during the fiscal year amounted to $49,752.07.
The expenditures were $46,484.51. The balance unexpended June 30,
1944, $4,587.46, plus an allotment of $91,000 received in July 1944,
 $95,587.46, will be applied as needed during the fiscal year 1945 to
the payment of expenses incurred under this heading. The additional
sum of $40,000 can be profitably expended during the fiscal year ending
June 30, 1946.
                                                         Cost and financial summary
Cost of new work to June 30, 1944_-----------                                                                                        ------
Cost of maintenance to June 30, 1944--- ---------                                                                                   $656, 185. 00
       Total cost of permanent work to June 30, 1944                                                                                     656, 185. 00
Minus accounts payable June 30, 1944_--      ---------                                                                                    4, 587. 46

      Net total expenditures_---------                                                                              ----                 651, 597. 54
Unexpended balance June 30, 1944__---                                                              -------                               - 4, 587. 46
                Total amount appropriated to June 30, 1944--------------                                                                 656, 185. 00

       Fiscal year ending June 30                             1940                  1941                1942                1943              1944

C ost of new work .. . . . . . . . . . .                        . . . . . . . . . . .              . . . . . . . . .
                                                                                                   -.                         . . . . . . . . . . .
Cost of maintenance.............                       $195, 133. 59          $181, 988. 70       $113, 498. 72         $38, 362 06         $49, 752. 07

Total expended------
              ..........--                 -....           186, 897. 33          186, 524.32        120,210.73             38, 778. 82        46,484. 51

Allotted_ .               --
                        .......---.--.-            -       249,150.00             75, 600.00- _ -            -     - -73,     035.00          12,000.00


Balance unexpended July 1, 1943          -- _   ---------                                                                                39, 071. 97
Amount allotted from War Department Civil Appropriation Act
   approved Apr. 28, 1942_                                 -                                                                               12, 000. 00
                Amount to be accounted for                                   .........-                                                   51, 071. 97
968         REPORT OF CHIEF OF ENGINEERS,                                    U.   S. ARMY,            1944

Gross amount expended_ __ ____                       ____----------------                                 $46, 484. 51

      Balance unexpended June 30, 1944-.... -                                 -------                          4, 587. 46
Outstanding liabilities June 30, 1944--------                                 --      ---       __-            4, 587. 46

Amount allotted in July 1944 --------------------------------                                              91, 000. 00
Amount available during fiscal year 1945_   ------       -    - -                                          91, 000. 00
Amount that can be profitably expended in fiscal year ending June
  30, 1946, for maintenance 1 __   ---- _ _        -----   --     --._                                     40, 000. 00
1 Exclusive of available funds.
12. OTHER FLOOD-CONTROL PROJECTS FOR WHICH NO ESTIMATES
                     ARE SUBMITTED


                                                         For last full      Costs and expenditures to          Estimated
                  Name of project                         report see                                             amount
                                                           Annual.                                             required to
                                                         Report for-        New work        Maintenance         complete

1. Green Island levee and drainage district No. 1,
      Iowa 1 _..                                          1938     _...........................                     $68, 000
2. Carroll County levee and drainage district
      No. 1, Illinois 1                                   1938 - -        -          - -.            -     -     -13,      200
4. Keithsburg
3. Henderson drainage        district, Illinois 1....... 1938     .......................                              11,000
                   County drainage district No. 3,
      Illinois 2--   ----------------------------
                           ....                         . 1939 ----------------------------                          13,600
5. Gregory drainage district, Missouri...-----------     1940              $77, 100 --------------
                                                                                            .                      (3)
6. Fabius River drainage district, Missouri,
7. South Quincy drainage and levee district,
                                                   -      1941                60, 500 --------------               (3)
      Illinois_ -------------------------------           1940
                                                          1---                61, 200 ----------                   (3)
8. South River drainage district, Missouri .             1941                55, 300-....---------                (3)
9. Sny Island levee district, Illinois--         ------- 1942                61, 400 ---------------              (3)
10. Janesville and Indian Ford Dams, Wis. .....           1938- --------------------------                           29, 000
11. Freeport on Pecatonica River, Ill------------ 1941-             .-----------                  .-------          463, 000
12. Penny Slough, Rock River, Ill_----------- 1940                            85,800------                         (3)

I Work under the project has been deferred pending further study.
2 Work under the project has been deferred pending fulfillment of the required local cooperation.
3 Completed.

     Status of all investigations for flood control called for by flood control acts and
                                 committee resolutions

                                                                 Date trans-                               Recommen-
           Locality                  Authorization act            mitted to         Document No.             dation
                                                                  Congress

Apple River, Jo Daviess           Flood Control Comn---.----------       ...-...--
County, Ill.                       mittee resolution,
                                    Jan. 21, 1944.
Bureau Creek, Ill-------
                 .......--.       Commerce Committee
                                    resolution, Jan. 9,
                                    1942.
Des Moines River, Iowa,           River and Harbor Act, May 31, 1944 H. 651, 78th Cong.,            Favorable.
construction of dam at or          June 20, 1938.                    2d seas.
near Madrid for naviga-
tion and flood control.
Henderson River, Ill........ Flood Control Act,_....-.-.---                      ----..
                                                                                      .. ..  .
                                    June 28, 1938.
McCraney, Hadley, Kaiser,---do-----                 -----------------------------------
Six Mile, and Bay-Creeks
and their tributaries, Pike
County, Ill.
Mississippi River for flood Commerce Committee
  control at East Moline and        resolution, Jan. 15,
  Campbell's Island, Ill. .         1944.
Mississippi River, flood con- Flood Control Com---------                                    .--------------------
  trol above mouth of Mis-          mittee resolution,
  souri River.                      Sept. 18, 1944.
Rock River, Ill ...       ..-----------
                                 Flood Control Act,-            .---..---...                 --
                                    June 28, 1938.
Rock River, Ill. and Wis.... Flood Control Com-------------------------.....                    -.
                                    mittee resolution,
                                    Apr. 13, 1938
    Do.....------.--..            Commerce               eo ..
                                                    itt.e----            ..-.--------....-......
                                    resolutionM . ',
                                    1938.
Salt River, Mo.__.......... Flood Control Act,-                 .
                                    June 22, 1936.
                RIVERS AND                HARBORS----ST.                 PAUL,        MINN.,         DISTRICT               969
      IMPROVEMENT OF RIVERS AND HARBORS IN THE
               ST. PAUL, MINN., DISTRICT
  This district comprises western Wisconsin, a small western portion
of the upper peninsula of Michigan, the major portion of Minnesota,
northern and eastern North Dakota, and small portions of northeast-
ern South Dakota and northern and northeastern Iowa embraced in
the drainage basins of the Mississippi River and tributaries from its
source to mile 614 above the mouth of the Ohio River, of the Red River
of the North and tributaries, and of those streams north of the Mis-
souri River Basin in North Dakota. That section of Mississippi
River above mile 614 is included in the report on Mississippi River
between Missouri River and Minneapolis, Minn.
  District engineer; Col. Lynn C. Barnes, Corps of Engineers.
  Division engineer: Col. Malcolm Elliott, Corps of Engineers.
                                                        IMPROVEMENTS

                         Navigation                                                          Flood control
                                                             Page                                                            Page
1. Mississippi River, between                                    8. Dry Run, Iowa_                                          979
       the Missouri River and                                     9. Lake Traverse and Bois de
       Minneapolis, Minn. (St.                                         Sioux River, S. Dak., and
       Paul district)_                                       939       Minn_      --     -    --                              981
2. Reservoirs at headwaters of                                  10. Lac Qui Parle Reservoir,
       Mississippi River ....                                969       Minnesota River, Minn --                               984
3. St. Croix River, Wis., and                                   11. Upper Mississippi River
       Minn                                                  973       Basin, St. Paul district _                             987
4. Minnesota River, Minn ..                                 974 12. Preliminary     examinations,
5. Examinations surveys, and                                          surveys, and contingencies
       contingencies (general)                   ---         976       for flood control ....                                 987
6. Other navigation projects
       for which no estimates are
       submitted-                                             977
7. Plant allotment-                                          978

       1. MISSISSIPPI RIVER, BETWEEN THE MISSOURI RIVER AND
                MINNEAPOLIS, MINN. (ST. PAUL DISTRICT)

    For report on this improvement see page 939.
            2. RESERVOIRS AT HEADWATERS OF MISSISSIPPI RIVER
  Location.-Reservoirs are located on the Mississippi River and sev-
eral of its tributaries, in Itasca, Beltrami, Hubbard, Aitkin, Cass, and
Crow Wing Counties, Minn., as follows:
                                                             Outlet                                                Area
        Name of reservoir                                                                  Watershed
                                                     River                  PaulSt.
                                                                          Above                         Original      Reservoir
                                                                                                         lake

                                                                                            Square      Square            Square
                                                                                Miles        miles       miles            miles
Winnibigoshish----------
                 ......... ---              Mississippi------------............      408        1,442         117             179.4
Leech Lake...--------........-------- Leech ............-----------------..          410        1,163         173             250.9
Pokegama_                                   Mississippi-----------
                             __-----------------            ...........              344          660          24              35.0
Sandy, Lake ----------------
               .                            Sandy -----------------                  267          421           8              16.6
Pine River----------------Pine..........------------------                           199          562          18              23.7
Gull Lake-----------------Gull...............----------------..                      168          287          20              20.5


  Previous project.-Adopted by the River and Harbor Act of June
14, 1880. .For further details see page 1888 of the Annual Report for
1915, and page 1098 of the Annual Report for 1938.
970          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                      1944

   E'xsting project.-This provides for the reconstruction of the five
original reservoir dams, viz, Winnibigoshish, Leech Lake, Pokegama,
Sandy Lake, and Pine River, and the construction of Gull Lake
Reservoir.
   The estimated cost revised in 1928, exclusive of amount expended on
previous projects, was $895,000. The estimated cost of operation and
maintenance of the reservoirs, made in 1936, is $25,000 annually. The
above dams are of solid concrete construction, Pokegama being built
on bedrock and the others on pile foundations. The Sandy Lake Dam
includes a lock 160 feet long, 30 feet wide, with a maximum lift of
9.5 feet and a depth of 2.5 feet on the lower sill at low water. The
abandonment of the ditches to connect Long Lake to Round Lake and
Round Lake to Gull Lake was recommended in House Document No.
413, Sixty-fourth Congress, first session, and was ordered by Congress
in the River and Harbor Act of July 27, 1916.
   The existing project was authorized by the following river and
harbor acts:

    Acts                                  Work authorized                                    Documents


Mar. 3, 1899     For reconstruction of 4 of the 5 original dams, and surveys to
                   determine the extent of lands overflowed by the reservoirs.
Mar. 2, 1907     Reconstuction of Sandy Lake Dam and the construction of Gull
                   Lake Reservoir.
June 25,1910     Construction of an equalizing canal between Winnibigoshish and        H. Doc. No. 363, 61st
                  Leech Lake Reservoirs (no work was done and this part of the          Cong., 2d sess.
                  project was abandoned in the act of Mar. 4, 1915).
June26,19341     Operation and maintenance provided for with funds from War
                  Department appropriations for rivers and harbors.


  I Permanent Appropriations Repeal Act.

    For maps see pages 1973 and 1978, Annual Report for 1911.
           Lower operating limits authorized by regulations approved Feb. 4, 1936

                Reservoir                    Minimum                      Reservoir                 Minimum
                                               stage                                                  stage

                                                  Feet                                                 Feet
Winnibigoshish------------------------               6.00   Sandy Lake---------------------------...7.00
Leech Lake---------------------------                1.00   Pine Lake ...----------------------------.      9.00
Pokegama...........----------------------------      6.00   Gull Lake-----------... -----------------       5.00


  Local cooperation.-Fully complied with.
  Terminal facilities.-None.
  Operations and results dwring fiscal year.-The reservoirs were
operated as required and the necessary repairs made to the appurte-
nant structures. Major repair items consisted of: Repairing the gage
well and temporary repairs to the dike at Sandy Lake Dam, and
repair of the pavement on the dike at Winnibigoshish Dam.
  Following one of the heaviest inflows for many years, closely ap-
proximating the record for the-first 6 months of the calendar year,
the reservoirs were all high at the end of the fiscal year. Heavier
than normal discharges were made from the Winnibigoshish, Leech,
and Pokegama Reservoirs from July 1943 to March 1944, in order to
                RIVERS AND                 HARBORS-ST.                                 PAUL,                MINN.,                   DISTRICT                        971

dissipate stored water. Additional heavy discharges were made from
Sandy, Pine River, and Gull Reservoirs from December 24, 1943, to
January 20, 1944, during which time about 161,000 acre-feet were re-
leased from this reservoir system to assist in providing sufficient
depth in the "Chain of Rocks Reach" of the Mississippi River channel
near St. Louis, Mo. Released waters were also of material benefit
to water power plants along the Mississippi River which utilize a total
head of about 307 feet, including Keokuk Dam. The operation .of
these reservoirs resulted in a reduction of about 2 feet in the peak
flood-stage at Aitkin, Minn., in May and a reduction of about 0.6 foot
in June. This operation raised the Sandy Lake Reservoir to a maxi-
mum stage of 14.26, 3.26 feet above normal maximum operating
limit. Pokegama Reservoir reached a peak stage of about 12.3 feet,
0.3 foot above normal maximum operating limit. During the year
there was a net inflow of about 1,305,000 acre-feet into the reservoirs
and about 1,416,000 acre-feet discharged.
                                  Mean monthly stages for the fiscal year 1

                                                                 1943                                                                     1944
           Reservoir                 -             -----        --------                                -     -----                          -          - ----
                                  July Aug. Sept.                      Oct. Nov. Dec.                       Jan.          Feb. Mar. Apr. May June

                                   Feet        Feet Feet Feet Feet Feet Feet Feet Feet Feet Feet                                                                      Feet
Winnibigoshish .----             12. 45      12. 5312. 07 11.35 10.69 10.06  9. 34 8.50 8. 14 8.42 9. 29                                                             10.66
Leech Lake                       3.48         3.31  2.92 2.45 2.22 2.02 1.72 1.44 1.38         1.55  2.12                                                             3.01
Pokegama_---                 -9.83            9.12  9.02 8.56 8.80 7.74 7.86 7.32 7.49 7.10 8.80                                                                     11.55
Sandy Lake                      10.24        10.12 10.16 10.11 10.28 9. 64 7. 25 5.72 5. 33 6. 94 10. 21                                                             12. 74
Pine River    -                 13.88        13.34 13.36 13.32 13.46 13. 18 11.86 10.53 10.14 10.55 12.20                                                            14.60
Gull Lake------_---              6.34             6.29    6.35        6.40          6.66        6.36       5.37          4.79        4.24       4.41      5.83        6.45

   1 The mean monthly stage is the average of the stages on the 1st, 10th, 20th and last day of the month.


    The total costs for the year were $20,636.35 for operating and care.
  The total expenditures were $20,591.65.
     Condition at end of flscal year.-The existing project was com-
  pleted in 1937. The 5 dams originally built of timber have been re-
  constructed of concrete. A concrete dam has been constructed at
  Gull Lake. Three dikes at Winnibigoshish, 4 at Pokegama, 2 at Sandy
  Lake, and 16 at Pine River have been constructed. Flowage rights
  have been acquired on all lands affected by the construction, mainte-
. nance, and operation of the reservoirs.

                                           Capacity at                     Previous projects                       Existing projects
             Reservoir                       maximum                             -          --                              -                              Total cost
                                           stagefeet)
                                                   (cubic            ComCoin
                                                                     pleted                  Cost             pleted                    Cost



Winnibigoshish .......---------- 42,163, 000,000                      1884              $214, 000.00          1900                   $173, 470.00           $387, 470. 00
Leech Lake.--------------- 32,379, 000, 000                           1884               171,805.00           1902                     84,380. 00            256, 185. 00
Pokegama ----------------         5, 260, 000, 000                    1884                85,000. 00          1904                    126, 030. 00           211,030. 00
Sandy Lake_   ---------------     3, 158, 000, 000                    1895               114, 000.00          1909                    117, 020.00            231, 020.00
Pine River_ ---------------- 7, 733, 000, 000                         1886                97, 000. 00         1907                    133, 320. 00           230, 320.00
Gull Lake-----------------3,085,000,000---                                                                   1913
                                                                                                        .--------------- 86,826.00                                86,826.00
Surveys and flowage rights              .---...                             _..................160,939.49                                                       160,939.49
       Total, new work---  .-      ----------------                                         681, 805. 00 _...                          881, 985. 49        1, 563, 790. 49
Total operating and care--------............                                               100, 857.10_ .--                     -     173,153. 70            274, 010. 80
Permanent       indefinite   ap-
   propriation for operating
   and care, Feb. 1, 1895, to
   ena of fiscal year 1936 ..             -    .            .         ....            ..--..------...                                  967, 197. 08              967, 197. 08
        Total-.-------------93, 778, 000, 000                                                786.. 62.10              -              2, 022, 336. 27       2, 804, 998. 37
972            REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                             1944

   All reservoirs and appurtenances were in good condition and in
operation at the end of the fiscal year.
  The total costs under the existing project to June 30, 1944, were
$1,055,139.19, being $881,985.49 for new work and $173,153.70 for oper-
ating and care. The total expenditures were $1,055,038.10. In addi-
tion, the sum of $967,197.08 was expended between February 1, 1895,
and June 30, 1936, on the operating and care of the works of improve-
ment uinder the provisions of the permanent indefinite appropriation
for such purposes.
  Proposed operations.-The unexpended balance June 30, 1944, $1,-
622.72, plus an allotment of $24,000 made in July 1944, a total of
$25,622.72, will be applied as follows:
Accounts payable, June 30, 1944-------------------------------    $101.09
Maintenance (operating and care):
    Operation------------------------- -------------           21, 400.00
    Ordinary repairs -_-                                        2,000. 00
    Improvement and reconstruction-                             2,000. 00
Unallocated balance ------------------------------------------     121.63

           Total-----------------------------------                                              ---                        25, 622. 72
  The additional sum of $20,000 can be profitably expended during
the fiscal year 1946, as follows:
Maintenance (operating and care):
   Operation    ---------------------------------------------                                                                  $19,000
    Ordinary repairs ------------------------------------------                                                                  1,000
           Total         ------------------------------------------------                                                       20,000

                                                Cost and financial summary
Cost of new work to June 30, 1944                                                                                    $1, 563, 790. 49
Cost of maintenance to June 30, 1944_------                                                            ---            1, 241, 207. 88
      Total cost of permanent work to June 30, 1944---------- 2, 804, 998. 37
Minus accounts payable June 30, 1944_-------                 ---      101. 09
      Net total expenditures---         -----------                                                                      2, 804, 897. 28
Unexpended balance June 30, 1944-----------                                                                          -        1, 622.72
            Total amount appropriated to June 30, 1944------------                                                       2, 806, 520. 00

    Fiscal year ending June 30                     1940                  1941             1942                1943              1944

C ost of new w ork -- - - - - -- . . . ---            --       --   -    -   -   --.-   -. --..
                                                                                            . . . . . . . . . . .. . . .
Cost of maintenance .........------------. $17, 650. 44             $20, 223.68         $17, 850. 23 $16, 475.13  $20, 636. 35
Total expended...............----------------     18, 663.69            19, 992. 44        112.30
                                                                                         18,                 16, 473. 09        20, 591.65
Allotted-----------------------                  26, 000. 00            11, 500. 00     21, 000. 00          16,000.00         -1, 450. 00


Balance unexpended July 1, 1943_--       ----------                                                                        $23, 664. 37
Deductions on account of revocation of allotment---------                                                                    1,450. 00

       Net amount to be accounted for_----           --   __                                                                22, 214. 37
Gross amount expended ----------------------- $21,430. 50
Less:
      Reimbursements collected              $833. 85-----------
      Receipts from sales -----------------    5. 00
                                                        838. 85
                                                                                                                             20, 591. 65
            Balance unexpended June 30, 1944-- -------------                                                                  1, 622. 72
                RIVERS AND          HARBORS-ST.           PAUL, MINN., DISTRICT                      973
Outstanding liabilities June 30, 1944---------------------------$369. 89
     Balance available June 30, 1944_ -      __--------                                         1, 252. 83
Amount allotted in July 1944     --------------------------
                                                        ...                                    24, 000. 00

           Amount available during fiscal year 1945----------------                            25, 252. 83

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1         --------------                                            20, 000. 00
  1 Exclusive of available funds.


                          3. ST. OROIX RIVER, WIS. AND MINN.

   Location.-The source of the river is in northwestern Wisconsin. It
is about 164 miles long and for its greater part forms the boundary
between Wisconsin and Minnesota. It flows southwesterly and then
southerly into the Mississippi River at Prescott, Wis., 41.5 miles below
the Northern Pacific Railroad bridge, Minneapolis, Minn. The por-
tion included in this improvement extends from the mouth of Taylors
Falls, a distance of 52.3 miles. (See U. S. Geological Survey map of
Minnesota, scale 1: 500,000, for general location.)
   Existing project.-This provides for the maintenance of a channel
9 feet in depth and of suitable width from the mouth to Stillwater
 (24 miles) in connection with the improvement of the upper Missis-
sippi River to afford a depth of 9 feet, and a channel '3 feet deep at
mean low water, between Stillwater and Taylors Falls (28 miles);
also the improvement of the harbor and water front at Stillwater.
   The estimate of cost of new work, revised in 1927, was $150,400.
   The latest (1941) approved estimate for annual cost of maintenance
for that portion of the project between the mouth and Stillwater is
$10,000. The latest authorization (1939) for maintenance work on
the stretch between Stillwater and Taylors Falls is limited to an
expenditure of not to exceed $5,000 per year.
   The existing project was authorized by the following river and
harbor acts:

    Acts                         Work authorized                                  Docuinents


June 18, 1878    Dredging, etc., for a 3-foot channel between the    H. Ex. Doc. No. 75, pt. 6, 43d Cong.,
                  mouth and Taylors Falls.                            2d sess.; Annual Report 1875, p. 372.
June 3,1896      Harbor and water front at Stillwater .-----
Jan. 21, 1927    A 6-foot channel to Stillwater__       - - --
                                                       _ __          H. Doc. No. 378, 69th Cong., 1st sess.
Aug. 30, 1935    The 9-foot channel from the mouth to Stillwater__   H. Doc. No. 184, 72d Cong., 1st sess.



   The latest published map is in House Document No. 1008, Sixty-
fourth Congress, first session.
   Terminal facilities.-At Stillwater there is a concrete-paved levee,
550 feet long and 40 feet wide, sloping from the top of the river bank
to the water. There is also a piling and timber trestle wharf on the
right bank, of which 276 feet is dock and 96 feet approach. At other
points along the river landings are made on the banks. The facilities
are considered adequate for existing commerce.
  Operations and results during fiscal year.-None.
  Condition at end of fiscal year.-All new work was completed in
1930. The extension to provide a 9-foot channel from the mouth to
974       REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                                                                   1944

Stillwater was completed on August 12, 1938, when full pool at dam
No. 3 of the Mississippi River canalization project was acquired. The
maximum draft that could be carried June 30, 1944, between Still-
water and Taylors Falls was about 2.5 feet; below Stillwater, 9 feet.
The total costs to June 30, 1944 were $245,700.89, being $150,409.50
for new work and $95,291.39 for maintenance. The total expenditures
were $245,700.89.
  Proposed operations.-The balance unexpended will be applied as
follows:
Maintenance:
    Dredging channel between Stillwater and mouth by Government
      plant and hired labor (October 1944)--------------------   $24, 000.00
   Preliminary surveys for dredging by hired labor--------------      462. 33

        Total maintenance---                               ---        _____---------24,                                                        462. 33
   The additional sum of $5,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance:
    Preliminary channel dredging surveys by hired labor---------------  $500
    Dredging channel between Stillwater and mouth by Government
    Splant and hired labor (July 1945) ---------------------------     4, 500
           Total maintenance-- ------------------------                                                                                          5, 000

                                              Cost and financial summary
Cost of new work to June 30, 1944                                                                                                      $150, 409. 50
Cost of maintenance to June 30, 1944_------                                                               ---                            95, 291.39

        Total cost of peimanent work to June 30, 1944------------                                                                          245, 700. 89

Net total expenditures_ __------------                                                                         -                  -        245, 700. 89
Unexpended balance June 30, 1944_                                     -        ------------                                                 24, 462. 33
        Total amount appropriated to June 30, 1944--------------                                                                           270, 163. 22

  Fiscal year ending June 30                      1940                    1941                1942                       1943                   1944

Cost of new work         -_           -        ..- -             -        --                         -   ---            '---------------------------
Cost of m aintenance     _-.-----.-           --_$1,120.47            $9, 935.76               $902.
                                                                                                -    50            --                  -
Total expended_.   ...                ... I            '     82
                                                            "1,066.       9, 989.41             902. 50        -              -

Allotted--------------------------------.-5,000.00                                        13,000.00


Balance unexpended July 1, 1943                                                                                                            $24, 462. 33
Balance unexpended June 30, 1944_----------                                                                             ---                 24, 462. 33

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance' --------------------------                                                                                       5, 000. 0l
  1 Exclusive of available funds.

                                       4. MINNESOTA RIVER, MINN.

   Location.-This river has its source in South Dakota, about 35
miles from Browns Valley, Minn. It is about 400 miles in length, its
general direction of flow being easterly, and it empties into the Missis-
sippi River at St. Paul, Minn. For general location, see United States
Geological Survey map of Minnesota.
   Previous projects.-The original project was adopted by the River
and Harbor Act of March 2, 1867, and modified by the River and Har-
         RIVERS AND HARBORS-ST.         PAUL,   MINN., DISTRICT       975
bor Acts of August 11, 1888, and July 13, 1892. For further details
see page 1890 of Annual Report for 1915, and page 1105 of Annual Re-
port for 1938.
    Existing project.-This provides for open-channel improvement
from the Mississippi River to Shakopee (25.6 miles). The-object to be
accomplished by this improvement is to obtain a channel with 4 feet
of water from the Mississippi River to Shakopee, which will accom-
modate vessels of 3-foot draft.
    The estimate of cost for new work, made in 1892, was $10,000, ex-
clusive of amounts expended on previous projects. The latest (1941)
approved estimate for annual cost of maintenance is $2,500. The ex-
isting project was adopted by the River and Harbor Act of July 13,
1892 (p. 2209 of the Annual Report for 1891). The latest published
map will be found on page 1574 of the Annual Report for 1888.
    Local cooperation.-None required under the existing project.
    Local interests on March 27, 1942, requested that the section of the
channel between the mouth and Savage, Minn., be dredged to a depth
of 9 feet, and the Secretary of War under authority contained in sec-
tion 4 of the River and Harbor Act approved March 4, 1915, authorized
acceptance of a total of $139,670.91 as local contribution to defray
costs of dredging in excess of the authorized 4-foot project depth.
   Terminal facilities.-At Port Cargill, mile 13.7, Cargill, Inc., owns
and operates a launching ways, a dock 650 feet in length with ware-
house adjacent, with additional mooring space 1,300 feet in length.
    Operationsand results during fiscal year.-Contractdredging from
the mouth to mile 13.7 (near Savage, Minn.) was completed, approxi-
mately 3,993 cubic yards of material having been removed. Costs for
the year were minus $12,754.62, United States funds for mainten-
ance, and $13,919.04, contributed funds for new work, a net total of
 $1,161.42. The total expenditures were $14,804.59, including $13,-
919.04 contributed funds.
    Conditionat end of fiscal year.-The existing project was completed
in 1931. Additional channel dredging (see "Local cooperation"),
completed in July 1943, provides: A channel with minimum depth of
9 feet and a width of 100 feet from the mouth to Port Cargill, mile
13.7, except that the 9-foot depth is restricted to a width of 74 feet at
the Chicago, Milwaukee, St. Paul & Pacific Railroad bridge, mile 1.7;
and a launching basin at Port Cargill, near Savage, Minn., with depths
up to 20 feet. Navigation was practicable from Port Cargill, mile 13.7,
to Shakopee for drafts not in excess of 3 feet. The total costs and ex-
penditures under the existing project to June 30, 1944, were $71,431.20,
being $12,730.69 for new work and $58,700.51 for maintenance. In ad-
dition, the cost and expenditure from contributed funds was $139,-
670.91 for new work dredging to a depth of 9 feet, under the provisions
of section 4 of the River and Harbor Act of March 4, 1915.
   Proposed operations.-The balance unexpended June 30, 1944
$335.79, plus an allotment of $10,000 made in July 1944, a total of $10,-
335.79, will be applied to removal of snags from the mouth to mile
13.9, near Savage, with Government plant and hired labor.
   The additional sum of $1,000 can be profitably expended for main-
tenance during the fiscal year 1946 for the removal of snags from the
mouth to Shakopee.
976           REPORT OF CHIEF OF ENGINEERS,                                             U. S. ARMY,               1944

                                                         Cost and financial summary
Cost of new work to June 30, 1944_          -----------                                                            1$130, 273. 48
Cost of maintenance to June 30, 1944_--------                                                            ---            58, 700. 51

           Total cost of permanent work to June 30, 1944                                                               188, 973. 99

Net total expenditures_-  _____--                                             _
                                                                          --------                                  1188, 973. 99
                                 _
Unexpended balance June 30, 1944--                                           -----------                                  335. 79
           Total amount appropriated to June 30, 1944                                       ---------               1 189, 309. 78


   Fiscal year ending June 30                              1940          1941               1942           1943             1944

Cost of new work........
Cost of maintenance----___             ..-                $5,914. 18      $128.02          $2, 197. 16   $35, 679.47     -$12,754. 62

                                  5, 914.18
Total expended ...............-----------------. 128. 02                                    2,197. 16     22, 039.30           885. 55

Allotted   ................-----------------------....     1, 000.00     2,500.00          10, 000.00     12,000.00


Balance unexpended July 1, 1943_                                                                                        $1, 221. 34
Gross amount expended--     -------                                                 - ---            $3, 167. 63
Less reimbursements collected                                          -----------                    2282. 08
                                                                                                      2,
                                                                                                                            885. 55
     Balance unexpended June 30, 1944-....      ------                                                                      335. 79
Amount allotted in July 1944--------------------------------10,                                                             000. 00
           Amount available during fiscal year 1945------------------10,                                                    335. 79
Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance--        __----------_-             _-                                                       -1,000.00
  1SExclusive
    In addition, $139,670.91
               of available
                                        contributed and expended for new work.
                                      funds.

     5. EXAMINATIONS, SURVEYS, AND CONTINGENCIES (GENERAL)

  The cost of the work during the year was $59,866.45 and the ex-
penditures were $55,612.83. The unexpended balance, on June 30,
1944, including accounts receivable, $7,729.94, plus an allotment of
$152,000 made in July 1944, a total of $159,729.94, will be applied as
needed during the fiscal year 1945 to payment of expenses incurred
under this heading.
  The additional sum of $122,600 can be profitably expended during
the fiscal year 1946.
                                                         Cost and financial summary
Cost of new work to June 30, 1944____
Cost of maintenance to June 30 1944_                                     _            _---1                         $923, 514. 83
      Total cost of permanent work to June 30, 1944-----------923, 514. 83
Undistributed costs June 30,1944----------------------------     2, 098. 32

        Net total cost to June 30, 1944- -                                      ---------                              925, 613. 15
Plus accounts receivable June 30, 1944_----                                                ----------                   3, 650. 68
       Gross total costs to June 30, 1944----------------------                                                        929, 263. 83
Minus accounts payable June 30, 1944_---      --  -------------                                                         7,634. 03
       Net total expenditures   - ------------------------.                                                         1 921, 629. 80
Unexpended balance June 30, 1944--------------------------                                                               4, 079. 26
          Total amount appropriated to June 30, 1944 ------------- 1 925, 709. 06
   1Includes $14,341.31 from permanent indefinite appropriation for "Gaging waters of the Mississippi
River and its tributaries."
                RIVERS AND HARBORS-ST.                                       PAUL, MINN.,                   DISTRICT                -977

      Fiscal year ending June 30                            1940          1941             1942                   1943            1944


Cost of new work .............................................
Cost of maintenance ------------ $86,505. 16 $97, 202. 03 $67, 961.94 $36, 551. 72 $59,866.45

Total expended.-----------------                           93, 943.49    94,202.87        71,530. 26            35,431.90         55,612.83

Allotted          ..............----------------------..   93,000.00     78,000.00        31,000. 00            62,000.00          4,000. 00



Balance unexpended July 1, 1943_                                                                                             $55, 692. 09
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943-      -
                           -....-----------                                                                                   14,000.00

      Amount to be accounted for_                               69, 692. 09
Deductions on account of revocation of allotment---------------10, 000. 00
       Net amount to be accounted for-__                                                   --                                 59, 692. 09
Gross amount expended-          .--                                                   _         $76, 212. 55
Less:
         Reimbursements collected --------- $20, 567. 22
         Receipts from sales_ ------              32. 50
                                                                                                  20, 599. 72
                                                                                                                              55, 612. 83

      Balance unexpended June 30, 1944--------------------- -                                                                  4, 079. 26
Outstanding liabilities June 30, 1944_---------        ---                                                                     9, 426. 36

      Balance available June 30, 1944-----------------                                                                       -5, 347. 10
Accounts receivable June 30, 1944_ ---------------                                                                ----          3, 650. 68

     Unobligated balance available June 30, 1944----------1,696.                                                                       42
Amount allotted in July 1944___                                                                                              152, 000. 00
            Amount available during fiscal year 1945----------------150, 303. 58

Amount that can be profitably expended in fiscal year ending June
30, 1946 for maintenance 2__                                   .                                                            122, 600. 00
  2   Exclusive of available funds.

6.     OTHER          NAVIGATION                             PROJECTS FOR WHICH NO                                       ESTIMATES
                                                            ARE SUBMITTED

                                                                          For last    Cost and expenditures to                 Estimated
                                                                        full report         June 30, 1944                       amount
                     Name of project                                    see Annual                                            requirede to
                                                                          Reportcre
                                                                            for-      New work          Maintenance            complete


1. Mississippi and Leech Rivers, Minn.1 .._-                    --         1929       $277, 615.12             $40, 251.01    Completed.
2. Red River of the North, Minn., and N. Dak.1 2                           1921        293, 343.60              76, 209.40
3. Mississippi River between Brainerd and                                  1925         47, 793. 81              3,890. 79
     Grand Rapids Minn.3               1
4. Lake Traverse, Minn., and S. Dak. 4         .                           1921               91.83    -----
5. Red Lake and Red Lake River, Minn.'. _ _ .                              1923            9,070.00     .......
6. Wisconsin River, Wis.' 6-_ ____1888
7. Black River, Wis_- _______________...-------                            1942           67, 584.96----------------$4,400.


  1 No commerce reported.
  2 Abandonment recommended in 1915 (H. Doc. No. 1666, 63d Cong., 3d sess.) and June 24, 1926 (H. Doc.
No. 467, 69th Cong., 1st sess.)
  3 Abandonment recommended June 24, 1926 (H. Doc. No. 467, 69th Cong., 1st sess.)
  4 Abandonment recommended in 1915 (H. Doc. No. 439, 64th Cong., 1st sess.) and June 24, 1926 (H. Doc.
No. 467, 69th Cong., 1st sess.).
  5 Originally included in project "Fox and Wisconsin Rivers, Wis." Abandonment of improvement of
Wisconsin River by channel contraction works recommended in 1886-87 (H. Ex. Doc. No. 65, 49th Cong.,
2d sess.)'.
  6 Expenditures included under project "Fox and Wisconsin Rivers, Wis." No break-down available.

           616634-45--pt. 1, vol. 1                             62
978          REPORT OF CHIEF OF ENGINEERS,                                             U. S. ARMY,                      1944

       7. PLANT ALLOTMENT, ST. PAUL, MINNESOTA, DISTRICT
                                                Cost and financial summary
Undistributed costs June 30, 1944_--. ----                                 _-------$1,                                    195, 923. 59

Net total cost to June 30, 1944----------------------------1,                                                             195, 923. 59
Plus accounts receivable June 30, 1944-- ------------     ---                                                              32, 270. 05
      Gross total costs to June 30, 1944---------------------                                                           1, 228, 193. 64
Minus accounts payable June 30, 1944-- ---------------                                                                      60, 301. 43
      Net total expenditures_                                                                                           1, 167, 892. 21
Unexpended balance June 30, 1944 --------------------------                                                                233, 206. 53
           Total amount appropriated to June 30, 1944------------                                                       1, 401,098. 74


   Fiscal year ending June 30                        1940           1941                  1942                1943                 1944


             ................
Total expended--------------                   -$75, 795. 35    $63, 881.87            $86, 433. 71      -$59, 401.22          -$127, 244. 25

Allotted   ........---------------------         112, 500.00       66, 691.40          49, 450.00 --                -     --     130,350.00



Balance unexpended July 1, 1943_---------------------------                                                              $236, 312. 28
Amount allotted from War Department Civil Appropriation Act
  approved June 2, 1943_- --------------------------                                                                            4, 000.00
      Amount to be accounted for_-     -----------                                                                  -     240, 312. 28
Deductions on account of revocation of allotment                                   --------------                         134, 350. 00

      Net amount to be accounted for-----------------                                                                     105, 962. 28
Gross amount expended -       ---       _     -$1,    204, 224. 27
Less Reimbursements collected__ $1, 320. 265. 49
  esSReceipts from sales_--       -  11, 203.03
                                           --      1, 331, 468. 52
                                                                                                                        -127,     244. 25

      Balance unexpended June 30, 1944----------------------233, 206. 53
Outstanding liabilities Junie 30, 1944_ ----------------      87, 124. 22

     Balance available June 30, 1944.---- -------------                                                                   146, 082. 31
Accounts receivable June 30, 1944_ ----------------                                                      __                32, 270. 05

           Unobligated balance available June 30, 1944-------------178,                                                            352. 36

Status of all investigations for navigation called for by river and harbor acts and
                                 committee resolutions

                                                                      Date trans-Recommend
           Locality                        .Authorization Act          mitted to     Document No.                         Recommenda-
                                                                       Congress

Lake City Harbor, Minn___                  Rivers and Harbors_
                                             Committee resolu-
                                            July 18, 1939.
Mississippi River, improve-                Rivers and Harbors ..
ment in Lake Pepin.                         Committee resolu-
                                            tion, Dec. 19, 1938.
Mississippi River-Missouri                 Commerce Committee_ ._.                ..   _-.       .....         ..
River to Minneapolis,                      resolution, Aug. 30,
improvement of harbor at                    1938.
Lansing, Iowa, for small
craft.
Mississippi River at McGre-                Commerce Committee__............
  gor, Iowa, improvement of                 resolution, Feb. 19,
harbor for small craft.                     1938.
Mississippi River at Min-                  Rivers and Harbors        Feb.       5, 1944      H. 449,78th Cong.,           Favorable.
neapolis, Minn., to modify                  Committee resolu-                                2d sess.
existing project.                           tion Apr. 24, 1941.
                  FLOOD CONTROL-ST.                       PAUL,   MINN., DISTRICT                979
Status of all investigations for navigation called for by river and harbor acts and


          Locality
                          committee resolutions---Continued

                                  Authorization Act
                                                            Date trans-
                                                             mitted to    Docunient No.
                                                                                          Ia
                                                                                          Recommenda.
                                                                                              tion
                                                             Congress


Mississippi River at Wa-         Rivers and Harbors
basha, Minn.                     Committee resolu-
                                  tion, Apr. 30, 1940.
Mississippi River between        Rivers and Harbors
Missouri River and Min-           Committee resolu-
neapolis, damage by seep-        tion, June 6, 1939.
age and backwater in
Minnesota and Wisconsin
 (pools Nos. 5-A, 7, 8, 9, 10,
  and 11).
Mississippi River between        Rivers and Harbors
Missouri River and Min-           Committee resolu-
neapolis, damage by seep-         tion, Mar. 16, 1939.
age and backwater from
pools Nos. 3, 4, 5, and 6,
Wisconsin; and from open-
ing gates at Red Wing,
Minn.; and Alma, Foun-
tain City, and Trem-
pealeau, Wis.
Mississippi River between        Rivers and Harbors
Missouri River and Min-           Committee resolu-
neapolis, damage by seep-         tion, Mar. 1, 1939.
age and backwater in
  Minnesota (pools Nos. 3,
4, 5, 7, and 8).
Mississippi River between        Rivers and Harbors
  Missouri River and Min-          Committee resolu-
  neapolis, damage by seep-        tion, Mar. 10, 1939.
  age and backwater in the
  State of Iowa (pools Nos. 9,
  10, and 11).
Mississippi River between        Rivers and Harbors
  Missouri River and Min-          Committee resolu-
  neapolis, damage by seep-        tion, Apr. 4, 1939.
  age and backwater in State
  of Minnesota (pools Nos.
  5-A and 6).
Mississippi River between        Rivers and Harbors
  mouth of the Illinois River      Committee resolu-
  and Minneapolis, Minn.,          tion, Sept. 21, 1943.
  for 12-foot channel with
  suitable widths.
Missouri River diversion         Commerce Committee
  project (under      Special      resolution, June 22,
  Board).                          1937.



                                         8. DRY RUN, IOWA

    Location.-In northeastern Iowa, on Dry Run, a tributary of the
upper Iowa River at Decorah, Iowa. (See U. S. Geological Survey
map, Decorah quadrangle, Iowa.)
    Existing project.--The Flood Control Act approved June 22, 1936,
authorized a flood-retention reservoir and channel enlargement down-
stream for the protection of the city of Decorah. The Flood Control
Act approved August 18, 1941, Public, No. 228, Seventy-seventh Con-
gress, first session, modified the project to provide for diversion of
Dry Run into the upper Iowa River, a levee system along the upper
Iowa River in Decorah for protection of adjacent property against
augmented high-water flow, raising a section of railroad tracks and
State Highway No. 9, and necessary alterations to bridges and pro-
tection to existing structures in the vicinity. The diversion is to be
accomplished by a dam across Dry Run at a point about 1 mile south-
west of Decorah and a diversion channel 3,200 feet in length from
that point through high ground to the upper Iowa River on the
north. The project will provide complete protection to residential,
980           REPORT OF CHIEF OF ENGINEERS,                                       U. S. ARMY,              1944

industrial, and commercial areas totaling about 260 acres within the
city limits of Decorah against the nmximum probable flood on Dry
Run and the upper Iowva River. Floods creatiig serious damages
have occurred about once every 11 years. The estimated Federal cost
is $460,000, and the cost to local interests for lands and damages is
$22,000.
   Local cooperation.-See page 7 for requirements.
   Operations and results during fiscal year.-Design, including pre-
liminary surveys and exploration, was intermittently carried on by
hired labor as other work more directly essential to the war effort
permitted. The costs for the year were $15,602.55 for new work and
the expenditures were $13,618.41.
   Conditionat end of fiscal year.-Design;including preliminary sur-
veys and explorations, is approximately 74 percent complete. No
construction has been started. The total costs under the existing
project to June 30, 1944, were $48,165.60 for new work, and expendi-
tures were $45,980.39.
   Proposed operations.-The balance unexpended, $19,019.61, will be
applied to new work, completing design of the proposed improve-
ments with hired labor by June 1, 1945.
   No operations are proposed for fiscal year 1946 in view of existing
Federal policies on wartime construction.
                                            Cost and financial summary
Cost of new work to June 30, 1944                                                                                $48, 165. 60
Cost of maintenance to June 30, 1944_
      Total cost of permanent work to June 30, 1944--                                                             48, 165. 60
Minus accounts payable, June 30, 1944_'-    ----                                                   ___             2, 185. 21
          Net total expenditures                                    --                         _   ____45,            980. 39
Unexpended balance, June 30, 1944                              -----------------                                  19, 019. 61
           Total amount appropriated to June 30, 1944---------------                                              65, 000. 00

    Fiscal year ending June 30                    1940              1941           1942             1943              1944

Cost of new work-- --------- -                  $21,975. 14       $2, 244. 64        $95. 55       $3, 247. 72       $15, 602. 55
Cost ofmaintenance....----------------------                                              ------
Total expended        ....                        21,911. 46
                                .......----------------             2, 265. 50       138. 37        3,046. 65         13, 618. 41

Allotted------.............---------------379,000.00           -354,000.00        35,000.00


Balance unexpended, July 1, 1943- ---------------------    $32, 638. 02
Gross amount expended ------------------------------------ 13, 618. 41
      Balance unexpended, June 30, 1944---------------_                                                    -      19, 019. 61
Outstanding liabilities, June 30, 1944-----------                                                                  2,207. 91

          Balance available, June 30, 1944_                              -   --       ---          _____          16, 811. 70
Amount (estimated) required to be appropriated for completion of
   existing project 1-            _         -            ---------------------                                      395, 000
  1Exclusive    of available funds.
           FLOOD CONTROL-ST. PAUL,        MINN.,   DISTRICT        981
9. LAKE TRAVERSE AND BOIS DE SIOUX RIVER, S. DAK. AND MINN.

   Location.-The works covered by this project lie along Lake Trav-
erse and Bois de Sioux River between the upper end of Lake
Traverse at Browns Valley, Minn., and the mouth of Bois de Sioux
River at Breckenridge, Minn. The lake drains through the river to
the Red River of the North, and the two waters form a portion of
the boundary between the State of Minnesota and the States of North
and South Dakota. For general location see United States Geolog-
ical Survey map of Minnesota.
   Existing project.-The plan of improvement provides for use of
Lake Traverse as a flood-control and water-conservation reservoir
and for channel improvement in the river below the lake. It includes
construction of a dam near White Rock, S. Dak., at the north end
of Lake Traverse, a structure at the Reservation Highway crossing
for control of the upper section of the reservoir, levees, and embank-
ments necessary near Browns Valley, Minn., and channel improve-
ment of approximately 24 miles of the Bois de Sioux River from the
outlet of Lake Traverse northward toward Breckenridge, Minn. The*
dam near White Rock, S. Dak., consists of a movable-gate control sec-
tion between two sections of rolled fill embankment with a total length
of approximately 14,400 feet from high ground on the Minnesota
side to high ground on the South Dakota side, and supplemented by
channel improvement of the Bois de Sioux River downstream and
an embankment approximately 5,000 feet long at the south end of
Lake Traverse for the protection of*Browns Valley, Minn., consti-
tutes the flood-control feature of the project. The structure at Res-
ervation Highway crossing consists of a stone-paved dike spillway
with superimposed stop log spans with total length of approximately
113 feet between steel sheet pile abutment walls behind which com-
pacted fill connects with the existing highway, and is operated to
maintain the water level in the upper section of the lake. The project
with reservoir capacity for flood control of 126,000 acre-feet, affords
protection to about 42,000 acres of agricultural land from floods up
to those which may be expected to occur once in 30 years and should
restore Lake Traverse to its former natural condition as a habitat for
an abundance of wildlife and fish.
   The latest approved estimate of cost (1937) is $1,474,000, of which
$1,115,200 is for construction and $358,800 for land and damages.
The latest (1944) approved estimate of annual cost of maintenance
is $9,000.
    The existing project was authorized by the Flood Control Act ap-
proved June 22, 1936.
    Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
    Operations and results during fiscal year.-The only new work car-
ried on was land acquisition and miscellaneous design, accomplished
with hired labor. Easements on approximately 740 acres of land
were acquired. In addition, declarations of taking were filed on the
remaining 36.20 acres of land being acquired in fee title and on 365.42
acres of land on which easements are required. Costs for the year
for acquisition of land and flowage rights were $23,394.10; for design,
 $807.16.
982     REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,           1944

    The White Rock Dam and the reservation control structure were
operated as required, and the necessary repairs made thereto and to
appurtenant works at a cost of $24,329.61. Major repair items con-
sisted of remedial work on the esplanade at White Rock Dam and
permanent repairs to-the reservation dike. The project operation
during the fiscal year was normal, floodwaters being retained until
they could be released at rates so as not to exceed a 4-foot stage on
the United States Weather Bureau gage at Wahpeton, N. Dak., a
critical point located about 30 miles downstream from White Rock
SDam. From July 1 to August 15, 1943, about 20,000 acre-feet of flood
storage from the preceding spring were released, bringing the upper
and lower pools approximately to their conservation levels. From
the latter date until freeze-up, a small flow of from 5 to 10 second-
feet was released to maintain fish life in the channel below. During
the winter, there was no discharge from the reservoir. Inflow to
the reservoir from spring break-up was exceptionally light and was
being discharged when extremely heavy rains occurred June 2 and 3,
1944, at which time the discharge was discontinued until June 11,
1944, by which time the flood had receded downstream. Closure of
the White Rock Dam is estimated to have reduced the flood crest at
Wahpeton, N. Dak., and Breckenridge, Minn., one-half foot, from
8.5 to 8 feet, and to have averted the flooding of most of the agri-
cultural land along the Bois de Sioux channel, except near Wahpeton,
N. Dak. As a result of this operation, the volume of flood storage
increased to 40,000 acre-feet, which was being released at the close
of the fiscal year.
    Total costs for the year were $48,530.87, of which $24,201.26 was
for new work, and $24,329.61 for operating and care. The expendi-
tures were $50,559.29.
    Condition at end of fcal    year.-The existing project as a whole
was 80 percent complete. A contract for raising and reconstructing
State Highways Nos. 27 and 28 near Browns Valley Dike, on which
work has been suspended, is 90 percent complete. Work remaining
to be initiated to complete the project included: Necessary alterations
of bridges and raising of highways along Minnesota side of Lake
Traverse; construction of an esplanade and slope protection at White
Rock Dam.
    There are involved in the land and4lowage acquisition 1,278.48 acres
of land in fee title and approximately 5,910 acres of land on which
easements are required. Of these totals, fee title to 1,242.28 acres and
easements on 1,979.26 acres have been acquired. In addition, declara-
tions of taking have been filed on the remaining 36.20 acres of land
being acquired in fee title and on 365.42 acres of land on which ease-
ments are required.
    The White Rock Dam and the reservation control structure are in
operation and in good condition except for the slide gate controls for
the reservation control structure which were destroyed by ice move-
ments. The earth dams, dikes, channels, and appurtenances are in
fair condition.
                     FLOOD CONTROL-ST. PAUL, MINN., DISTRICT                                                                  983
  The total costs under the existing project to June 30, 1944, were
$1,178,256.25, being $1,142,766.02 for new work ard $35,490.23 for
operating and care. The expenditures were $1,176,107.48.
  Proposed operations.-The balance unexpended June 30, 1944,
$232,592.52, and accounts receivable at the end of the year, $85.88, plus
an allotment of $6,000 made in July 1944, a total of $238,678.40, will
be applied as follows:
Accounts payable June 30, 1944 --------------------------------- $2, 234. 65
New work:
   Hired labor:
       Design ---------------------------------          $9, 100. 00
       Acquisition of lands and flowage rights -------- 194, 300. 00
   Contract: Raising and reconstruction of Highways
     Nos. 27 and 28-----------------------------          6, 000.00                                                    ,

        Total new work ----------------------------------      209, 400.00
Maintenance (operating and care):
    Operation -----------------------------------    8, 000.00
    Ordinary repairs ------------------------------  1,000. 00
       Total operating and care -------------------------------                                                9000.
                                                                                                               9,     00
Unallocated balance ---------------------------------------                                                   18, 043.75
          Total all work -------------------------------------                                               238,678.40
   It is expected that the acquisition of lands and flowage rights will
be completed under the above proposed operations.
   The additional sum of $9,000 can be profitably expended during the
fiscal year 1946, as follows:
Maintenance (operating and care):
   Operation_ ----------------------------------------------                                                               $8, 000
   Ordinary repairs ------------------------------------------                                                              1,000
          Total operating and care ---------------------------------                                                        9,000

                                           Cost and financial summary
Cost of new work to June 30, 1944-          ..                                                         $1, 142, 766. 02
Cost of maintenance to June 30, 1944------------------------                                                35, 490. 23
       Total cost of permanent work to June 30, 1944 ----------. 1, 178, 256. 25
Plus accounts receivable June 30, 1944-----------------------             85. 88

      Gxoss total costs to June 30, 1944--- -----------------                                           1, 178, 342. 13
Minus accounts payable June 30, 1944----------- ------------                                                 2, 234. 65
      Net total expenditures-----------------------------                                               1, 176, 107. 48
Unexpended balance June 30, 1944 --------------------------                                                232, 592. 52
          Total amount appropriated to June 30, 1944 ------------                                       1, 408, 700. 00

    Fiscal year ending June 30                  1940             1941            1942           1943                       1944

                        -
Cost of new work .............              $335, 996. 26     $568, 770.36    $138, 961.03    $74, 837.11              $24, 201.26
                              -----
Cost of maintenance- ................ __       -- _ _-.. ..         _             1,940.51      9, 220.11               24, 329.61
       Total cost----------------            335, 996. 26      568, 770. 36    140, 901.54     84, 057. 22                 48, 530.87
Total expended    ----------------
                     .....                   280, 940. 72      577, 805. 44    187, 812.05     78, 989.98                  50, 559. 29
Allotted_        .--------------------     1, 475, 500.00        4, 000.00    -49,100.00     -21,700.00      .......
984      REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                              1944

Balance unexpended July 1, 1943_ -----         _____-------$283,                       151. 81
Gross amount expended_ _-------------____---$50,                 620. 30
Less rembursements collected--------------------                  61. 01
                                                                                   50, 559. 29

      Balance unexpended June 30, 1944_        -------------- _.                  232, 592. 52
Outstanding liabilities June 30, 1944 -------------------------                   174, 336. 51
      Balance available June 30, 1944_ --------------------.-                      58, 256. 01
Accounts receivable June 30, 1944_ - - _-----------                                     85. 88
     Unobligated balance available June 30, 1944_----                      --      58, 341. 89
Amount allotted in July 1944_  -----------------                                    6, 000. 00
       Amount available during fiscal year 1945      ---------------               64, 341. 89
Amount (estimated) required to be appropriated for completion
  of existing project 1_-- ___     ---------------                                111,800. 00
Amount that can be profitably expended in fiscal year ending
  June 30, 1946, for maintenance 1________ _ __-
                                              -           "___---9,
                                                           - --                        000. 00
1Exclusive of available funds.

       10. LAC QUI PARLE RESERVOIR, MINNESOTA RIVER, MINN.

  Location.-The works covered by this project lie along Marsh and
Lac qui Parle Lakes and the Minnesota River between the head of
Marsh Lake and Granite Falls, Minn. For general location see United
States Geological Survey map of Minnesota.
  Existing project.-Construction of the Lac qui Parle Reservoir was
initiated as a Works Progress Administration project sponsored by
the State of Minnesota, prior to its authorization as a Federal project
by the Flood Control Act approved June 22, 1936. The present plan
of improvement provides for completion and maintenance by the War
Department of the structures on Marsh and Lac qui Parle Lakes and
the Chippewa River diversion works, substantially completed by the
Work Projects Administration for use of Marsh and Lac qui Parle
Lakes as flood control and water conservation reservoirs, and for chan-
nel improvement of the Minnesota River below the lakes. The project
includes a main dam at the outlet of Lac qui Parle Lake, a structure
between Marsh Lake and Lake Lac qui Parle, for control of the Marsh
Lake Reservoir, a dam and diversion channel near Watson, Minn., for
diverting floodwaters of the Chippewa River into the Lac qui Parle
Reservoir, necessary alterations to highways, railroads, and bridges in
the vicinity, and improvement of the channel of the Minnesota River
at various locations between Lake Lac qui Parle and Granite Falls.
The Lac qui Parle Dam, which carries a highway across the Minne-
sota River, consists of a control structure of 12 bridge spans incor-
porating sluice gates and a fixed spillway weir, a 2,500-foot emergency
spillway, and sections of highway embankment connecting with high
ground on either side of the valley. The Marsh Lake Dam consists of
a 110-foot concrete spillway and two sections of dredged earth fill
4otaling approximately 8,500 feet in length. The Chippewa River
Flood Diversion Dam consists of a concrete fixed crest structure sup-
porting a highway bridge, and a section of earth fill through which is
provided a conduit for discharge of low water flow. The diversion
           FLOOD CONTROL--ST. PAUL, 1IIINN., DISTRICT              985
channel for passing floodwaters of the Chippewa River into the Lac
qui Parle Reservoir is 3,500 feet in length cut through a natural ridge
separating the river and an arm of the lake. A rolled earth fill dike
extending along the lower south side of the channel is an extension of
the diversion dam and serves also to protect the adjacent railroad
tracks from being flooded. Improvement of the Minnesota River be-
tween Lake Lac qui Parle and Granite Falls consists of rock removal
and cut-offs at various locations to provide for increasing the bank-full
capacity of the channel to about 4,000 second-feet. The project, with
reservoir capacity of about 94,500 acre-feet for flood control above
normal elevations of the two conservation pools, will provide protec-
tion for agricultural lands against summer floods estimated to have
a frequency of about once in 25 years and protection against spring
floods having a frequency of about once in 12 years. Storage of
58,500 acre-feet for conservation purposes provided below normal
elevations of conservation pools will result in improved lake levels for
recreation and game conservation in addition to providing for in-
creased low water flow downstream for agricultural interests and for
sewage disposal at Granite Falls.
   The estimated cost to the United States for completion of the
project, revised in 1943, is $299,500 for construction and $495,000 for
lands and damages. The estimated annual cost of maintenance is
$9,000.
   Local cooperation.-Section 2 of the Flood Control Act approved
June 28, 1938, applies.
   Operationsand results during fiscal year.-Negotiations and surveys
were carried on by hired labor toward completing agreements with the
Chicago, Milwaukee, St. Paul & Pacific Railroad and the State of
Minnesota relative to land acquisition and toward securing flowage
easements on all affected roads and highways. Costs for the year were
$12,011.49, being $8,322.85 for new work, acquisition of land and flow-
age rights, and $3,688.64 for maintenance. Expenditures were
$12,027.39.
   Condition at end of fiscal year.-The existing project as a whole was
41 percent complete. Contracts have been completed, all in the year
1942, as follows: Lac qui Parle Dam improvements; channel im-
provement of the Minnesota River; bituminous surfacing, Lac qui
Parle Dam spillway; Marsh Lake Dam improvements; Great North-
ern Railroad bridge alteration and grade raising; and stage recorder
houses. Work remaining to be initiated to complete the project in-
cludes: Raising or relocating Louisburg-Correll Highway; clearing
portions of the reservoir area; a short reach of channel excavation
below Marsh Lake Dam; and installation of cranes and bulkheads at
the Lac qui Parle Dam.
   Negotiations toward obtaining fee title or flowage easements on all
affected lands is nearing completion. The total costs under the exist-
ing project to June 30, 1944, were $330,069.18, being $323,618.42 for
new work and $6,450.76 for maintenance. The expenditures were
$329,976.89.
   Proposed operations.-Theunexpended balance June 30, 1944, $443,-
673.11,and.aceounts.receivable at the end of the year, $254.71, plus an
986          REPORT OF CHIEF OF ENGINEERS, U. S. ARMY,                                            1944

allotment of $8,000 made in July 1944, a total of $451,927.82, will be
applied as follows:
Aecountspayable Junei' 30, 1944--------------------------------                                              $347.00
New work:
    Hired labor:
         Design---------------------------------$1,500.00
         Railroad and highway damages ....------------      48,000.00
         Land acquisition-_--------------------_376,            800.00
    Contract: Raising or relocation of Louisburg-Cor-
      rell Highway -____-        __--___-      _____----- _ 12, 800. 00

      Total new work ------------------------------------       439, 100.00
Maintenance (operating and care):
    Operation_   ------------------------------      $7,500.00
    Ordinary repairs-..-..          ------------- --  1, 500.00
      Total operating and care -----------------------                                                   9,000. 00
Unallocated balance ----------------------------     ------ ------                                       3, 480. 82
          Total all work__-------------------------------------451,                                           927. 82
   It is expected that the acquisition of lands and flowage rights will
be completed under the above proposed operations.
   The additional sum of $9,000 can be profitably expended during
fiscal year 1946, as follows:
Maintenance (operating and care):
   Operation   ----------------------------------------------                                                 $8,500
   Ordinary repairs --------------------------------------------                                                 500
          Totaloperatingandcare                ----------------------------------                               9,000

                                          Cost and financial summary
Cost of new work to June 30, 1944 --------------------------                                       $323, 618. 42
Cost of maintenance to June 30, 1944_--------               ---                                       6, 450.76
       Total cost of permanent work to June 30, 1944-----------                                    $330, 069. 18
Plus accounts receivable June 30, 1944-_   _________                                                     254. 71
      Gross total costs-to June 30, 1944-                      --------------------                    330, 323. 89
Minus accounts payable June 30, 1944---                                 ---------                           347. 00
     Net total expenditures_--      -------------                                                      329, 976. 89
Unexpended balance June 30, 1944 ---------------------------                                           443, 673. 11
          Total amount appropriated to June 30, 1944--------------                                     773, 650. 00

    Fiscal year ending June 30              1940           1941              1942          1943               1944

Cost of new work--------------      $25, 599. 94          $6, 322. 71    $212, 898.14    $73, 070.40          $8, 322. 85
Cost of maintenance--.----
                    ......     ----.-----.----.-----                 _____-----2,             762.12           3, 688. 64

      Total cost----------------           25, 599. 94     6, 322. 71     212, 898. 14    75,832. 52          12, 011.49
Total expended....----------------         23,121.80       5, 652. 70     213, 724. 94    75, 450.06          12, 027. 39
Allotted.........----------------------    82, 350.00    209,000.00       453,600.00      28,700.00      -    13,000.00


Balance tnexpended July 1, 1943__
                               ---------------------------       $468, 700. 50
Deductions on account of revocation of allotment ---------------- 13, 000.00

          Net amount to be accounted for_-.--------------------455,                                           700. 50
                FLOOD CONTROL--ST.                    PAUL, MINN., DISTRICT                     987
Gross amount expended- -.--        --------------                   $12, 218. 73
Less reimbursements collected--------.-.-.-------                        191. 34
                                                                                     $12, 027. 39

      Balance unexpended June 30, 1944 ---------------------..
                                          ....                 443, 673. 11
Outstanding liabilities June 30, 1944------------------------- 360, 607. 00
      Balance available June 30, 1944 ------------------------                         83, 066. 11
Accounts receivable June 30, 1944-----------------------------                             254. 71
     Unobligated balance available June 30, 1944..                   ----              83, 320. 82
Amount allotted in July 1944 --------------------------------                           8, 000. 00
        Amount available during fiscal year 1945------------ ----                      91, 320. 82
Amount (estimated) required to be appropriated for completion of.
  existing project 1------                 --------                         ----       30, 800. 00
Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1         -------------- _ _                                    9, 000. 00
I Exclusive of available funds,


       11. UPPER MISSISSIPPI RIVER BASIN, ST. PAUL DISTRICT

  Location.-The Mississippi River Basin above the Ohio River, ex-
clusive of the Missouri River Basin, in the St. Paul district.
  Existing project.-The Flood Control Act of June 28, 1938, ap-
proved the general comprehensive plan for flood control and other
purposes lin the upper Mississippi River Basin described in Flood
Control Committee Document No. 1,' Seventy-fifth Congress, first
session, with such modifications thereof as in the discretion of the
Secretary of War and the Chief of Engineers may be advisable, and
authorized $6,600,000 for reservoirs and $2,700,000 for local flood-
protection works on the upper Mississippi and Illinois Rivers; the
reservoirs and local protection projects to be selected and approved
by the Chief of Engineers. The act specifically provides that the
authorization shall include the enlargement and extension of a sys-
tem of levees located on the south side of the Sangamon River east
of Chandlerville, Ill., as set forth in House Document No. 604, Sev-
enty-fifth Congress, third session. The following project located in
the St. Paul district is included in the comprehensive plan:

                                                                                           Total esti-
            Name                     Tributary basin                    State              mated cost

Black River Reservoir....---------Black_------_-__-___-      Wisconsin_.................    $6, 541,000



   Local cooperation.-See page 7 for requirements.
   Operations and results during fiscal year.-None.
   Condition at end of fiscal year.-No work has been undertaken.
   Proposed operations.--None.
988                REPORT OF CHIEF. OF ENGINEERS, U. S. ARMY,                                                                1944

12. PRELIMINARY EXAMINATIONS, SURVEYS, AND CONTINGENCIES FOR
                       FLOOD CONTROL
   The cost of work during the year was $91,637.98 and the expendi-
tures were $88,870.74. The balance unexpended on June 30, 1944,
including accounts receivable, $6,857.32, plus. an allotment of $60,000
made in July 1944, a total of $66,857.32, will be applied as needed
during the fiscal year 1945 to payment of ex-penses incurred under
this heading. The additional sum of $120,000 can be profitably ex-
pended during the fiscal year 1946.
                                                   Cost and financial summary
Cost of new work to June 30, 1944_-
Cost of maintenance to June 30, 1944_-------                                                                        ---       $584, 133. 07
       Total cost of permanent work to June 30, 1944------------ 584, 133. 07
Plus accounts receivable June 30, 1944-------------------------        66. 65
      Gross total costs to June 30, 1944--                                            --------                                    584, 199. 72
Minus accounts payable June 30, 1944                                                                                                6, 390. 39
      Net total expenditures_--     ------------                                                                                  577, 809. 33
Unexpended balance June 30, 1944 ----------------------------                                                                       6, 790. 67
              Total amount appropriated to June 30, 1944                                         -------------                    584, 600. 00


      Fiscal year ending June 30                         1940   ,          1941                  1942                 1943             1944

C ostofnew w ork...
                  - -                   - - - -    .--   - -    .- .--    - -     .-- .-    -       .--   -   -..     . . . . . . . . .. .
Cost of maintenance----------...........-.         $147,814.78 $115,194. 74                $119, 501.29             $45, 532.85      $91, 637.98

Total expended ---------------- 153, 553.92                              112,440.97         120,069.34               45, 303.89       88,870.74
Allotted---------------------........         ..     177,900.00           70,000.00             44, 000.00          104, 300.00       30,000.00


Balance unexpended July 1, 1943__           .---- -------                                                                         $65, 661. 41
Amount allotted from War Department Civil Appro-
  priation Act approved June 24, 1940--------------       $17, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved May 23, 1941_---             --      5, 000. 00
Amount allotted from War Department Civil Appro-
  priation Act approved Apr. 28, 1942 --------------         8, 000. 00
                                                                                                                                   30, 000. 00

      Amount to be accounted for_--------                                                                     ---                  95, 661. 41
Gross amount expended ------------------                                                                                           88, 870. 74
      Balance unexpended June 30, 1944 -----------------------                                                                      6, 790. 67
Outstanding liabilities June 30, 1944_--------           ---                                                                        6, 793. 32
      Balance available June 30, 1944_--------                                                                                         -- 2. 65
Accounts receivable June 30, 1944 -------------------------------                                                                        66. 65
     Unobligated balance available June 30, 1944---------------                                                                         64. 00
Amount allotted in July 1944__ _________        _------60,                                                                             000. 00

               Amount available during fiscal year 1945                                -----------------                           60, 064. 00

Amount that can be profitably expended in fiscal year ending June
30, 1946, for maintenance 1-     -     -      -                -__ 120, 000. 00

   1Exclusive of available funds.
                 FLOOD CONTROL--ST.                         PAUL,                     MINN.,                        DISTRICT                          989

Status of all investigations for flood control called for by flood control acts and
                                committerresolutions

                                                                   Date trans-
         Locality                   Authorization act               mitted to                                Document No.                   Recom     n
                                                                    Congress

Chippewa River and tribu- Commerce Committee
taries, Wisconsin.         Resolution, Oct. 28,
                                    1941.
Clearwater River, Minn    -....--
                             Flood Control               Act,    Oct.              25, 1943               H. 345, 78th Cong.,               Favorable.
                                    June 28, 1938.                                                          1st sess.
Crow River, South Fork, Flood Control Com-                      ...............
  Minn., for flood control    mittee    resoluttion,
  and drainage.               Sept. 18, 1944.
Forest River, N. Dak-....... Commerce Committee
                                 resolution, Dec. 1,
                                                                                                   __
                                 1938.
Goose River and tributaries,   Flood Control Act,
North Dakota.                   Aug. 11, 1939.
Hay Creek, Goodhue             Flood Control Act,                 May 26,1944                                                               Unfavorable.
County, Minn.                   June 28, 1938.
Kickapoo River, Wis.......     Flood Control Act,               ..............
                                 Aug. 28, 1937.
Little Minnesota River,        Commerce Committee               ...............
  diversion of waters into       resolution, Nov. 4,
  Lake Traverse, for flood       1940.
  control and water con-
  servation.
Minnesota River, Minn .... Flood Control              Act,
                                June 22, 1936.
Mississippi River, flood       Flood Control Com-
  control. above mouth of        mittee    resolution,
  Missouri River.                SeDt. 18, 19$.                                                         .....................
Mississippi River between°     Commerce Committee                ...      .       .    .   .   .    .
  Sandy Lake and Brainerd,      resolution, Aug. 8,                                                       --.- 345,-78th--ong.,
  Minn. (Aitkin County).         1944.
Missouri River diversion       Commerce Committee                                                             1stsess.------
  project (under Special         resolution, June 22,
  Board).                        1937.
Park River, N. Dak., tribu-    Commerce Commit-                   Apr. 26,1944                              8. 194, 78th Cong.,             Favorable.
  tary of Red River of the       tee resolution, Dec.                                                           2d sess.
  North.                         1, 1938.
Pembina River and tribu-       Flood Control Act,                 Apr. 26,1944                              H. 565, 78th Cong.,                 Do.
  taries, North Dakota.          June 28, 1938.                                                              2d sess.
Poplar River, Wis..........    Flood Control Com-
                                 mittee    resolution,
                                                    .
                                 Noew. 10, 194'3: ;
    Do ....--- - - -           Commerce Commit-
                                 tee resolution, Oct.
                                  1, 1943.
Red Lake River and tribu-      Flood Control Act,                 Oct.                25,1943               H.194,
                                                                                                            S.  345,78th
                                                                                                                193, 78th Cong.,
                                                                                                                     78th Cong.,
                                                                                                                          Cong.,                Do.
taries, Minnesota.              June 28, 1938.                                                                    sess.
                                                                                                               1stsess.
                                                                                                               2d
Red River of the North         Flood Control Act,
  Drainage Basin, Minn.,         Aug. 18, 1941.
  S. Dak., and N. Dak.
Root River, Fillmore,          Flood Control             Act,
  Mower, Olmsted, Win-          Aug. 28, 1937.                  ....... 22,1.                            ..............         .   .   .
  ona, and Houston Coun-
  ties, Minn.
Rosea River, Minn., trib-      Flood Control             Act,
  utary of Red River of the     June 22, 1936.
  North.
Sheyenne River, N. Dak.,       Commerce             Commit-        Apr. 22,1944                                                                 Do.
  tributary of Red Rierof       s   te   resolutioget:                                                          2d sess.
  the Ndrth.                    1, 1938.
Wisconsin River and tribu-     Commerce Commit-
  taries, Wisconsin.            tee resolution, Oct.
                                28, 1941.                        ..............-
Yellow Medicine Creek,        Food Control Com-
  Minn., for flood control      mittee resolution,
  and drainage, tributary       Sept. 18, 1944.
  of Minnesota River.
